Loss of Containment
Loss of Containment
Introduction ................................................................................................................................ 3
Part 1 - Management of process integrity .................................................................................. 5
Part 2 - Small bore tubing and piping systems......................................................................... 13
Part 3 - Information, instructions and training........................................................................... 21
Part 4 - Isolations and permits to work..................................................................................... 25
Part 5 - Process plant protection systems................................................................................ 31
Part 6 - Change control ............................................................................................................ 39
Part 7 - Maintenance and verification of process safety-critical elements................................ 45
Part 8 - Control of miscellaneous process hazards.................................................................. 51
Part 9 - FPSO specific systems ............................................................................................... 59
Part 10 - Process plant construction & commissioning ............................................................ 63
-1-
-2-
Introduction
Reducing Offshore Hydrocarbon Releases
This document, originally designed to give guidance to inspectors under the Key Programme 1
- Reducing offshore hydrocarbon releases initiative, indicates ten important elements relating
to the management of the integrity of the process containment envelope and provides advice
on topics for inspection within each of the elements. The maintenance of high standards of
operation in these areas should help to minimise the frequency of occurrence of offshore
hydrocarbon leaks.
Asset Integrity Programme
This programme, known as KP3 ran from 2004 to 2007. It focused on the effective
management and maintenance of safety critical elements. Inspectors using a template, which
covered a number of key topics, obtained an overall picture of industry performance. One
topic, relevant to loss of containment prevention, where performance was poor was Topic C
Maintenance of safety critical elements.
Offshore Hydrocarbon Releases
HSL was asked to identify the main causes of major and significant releases between 2001
and 2007 using the Hydrocarbon Releases Database. Information was obtained on systems,
equipment types, equipment causes, operational causes, procedural cause and operational
mode. The key issues and underlying causes relating to hydrocarbon releases are
summarised below.
Evidence suggests that piping systems, including flanges and valves collectively
continue to be a major source of Hydro Carbon Releases (HCRs), with piping being the
single largest contributor. Instruments (i.e. Small Bore Tubings (SBTs)) contribute the
second largest single source of HCRs. Gas Compression is the operating system
having the highest number of HCRs.
Non-compliance with procedure (i.e. human factors issue) is the most common
procedural cause where procedural failures are reported.
Reported experience of inspection and survey on SBT systems suggests that 26% of
fittings examined are found to contain faults, e.g. under-tightness, incorrect or
mismatched components, leaks, incorrect or poor installation, etc., and that this failure
rate has remained constant from 2001 to 2007.
-3-
Inspection Topics
Guidance Notes
Policy / Record of Arrangements
1.1.1
inherent safety
hierarchy of prevention, detection, control, mitigation
role of risk assessment and ALARP principles
maintaining up to date documentation
competence, and adequacy of resources
working within a safe operating envelope
control of changes that impact on process safety
maintenance / verification of safety critical systems
line management monitoring
independent management and technical audits
establishing basic causes of accidents / incidents
reviewing process safety performance
continuous improvement, with improvement plans
Principles of quality management e.g. ISO 9000.
Legal
Basis
An employer has a legal duty under s.2 (3) of HSWA to have a written policy statement
with respect to health and safety. This statement of his general policy should include the
organisation and arrangements for carrying out that policy, including those applicable to
process safety. MHSWR, Reg. 5 requires a record of arrangements for planning,
organisation, control, monitoring and review of preventive and protective measures. A
policy statement addressing process safety management will help define the management
requirements. Senior management should endorse the policy, which should be adequately
communicated; commitment to it should be visibly demonstrated.
1.2
1.2.1
Accountabilities etc.
Are responsibilities /
accountabilities for process
integrity adequately defined
and allocated (e.g. between
operational and technical
functions)?
1.2.2
Technical Support
-5-
Item
Legal
Basis
1.3
1.3.1
Inspection Topics
Guidance Notes
Legal
Basis
1.4
Training / Competence
1.4.1
-6-
Item
Inspection Topics
Guidance Notes
Process specific training should deal with:
1.4.2
1.4.3
Training responsibilities /
programme evaluation
Who is responsible for
developing / validating
training material, carrying out
training, reviewing needs?
-7-
Item
Inspection Topics
1.4.4
Competence
Legal
Basis
1.5
Guidance Notes
-8-
Item
Inspection Topics
Guidance Notes
performance of humans engaged on safety critical tasks
associated with those hazards. It includes as key
milestones identification of safety critical tasks, task
analysis and human error analysis (together with
consideration of performance influencing factors).
Investigation procedures should address both immediate
and underlying causes, including human factors. HSG65
Appendix 5 describes one approach that may be used as
a guide for analysing the immediate and underlying
causes of effects. There are several other methodologies
available in the industry.
Legal
Basis
MHSWR Reg 5 requires employers to make arrangements for the effective planning,
organisation, control, monitoring and review of the preventive and protective measures
defined in Reg 1 Paragraph 36 of the ACOP to the regulations indicates that monitoring
includes investigating the immediate and underlying causes of incidents, to ensure that
remedial action is taken, lessons are learnt and longer term objectives are introduced..
1.6
1.6.1
Arrangements
What monitoring
arrangements are in place
for key risk control
procedures?
-9-
Item
1.6.2
Inspection Topics
Allocation of
responsibilities
How have responsibilities
been allocated between
onshore and offshore staff?
1.6.3
Guidance Notes
Understanding of risk control systems is facilitated by, for
instance, the bow-tie diagram and barrier diagrams (e.g.
Reasons Swiss Cheese Model). Consideration should be
given to each risk control measure identified on the
diagram as a relevant measure in order to effectively
manage process integrity.
Organisations need to decide how to allocate
responsibilities for monitoring at different levels in the
management chain, and what level of detail is appropriate.
In general, managers should monitor the achievement of
objectives and compliance with standards for which their
subordinates are responsible. Managers and supervisors
responsible for direct implementation of standards should
monitor compliance in detail. Above this immediate level of
control, monitoring needs to be more selective, but provide
assurance that adequate first line monitoring is taking
place.
Directors and senior managers should be actively involved
in the control of business risks (corporate governance).
(HSG254 page 7 Step 1.3). Senior managers should
understand fully the business benefits of performance
measurement and clearly see how managing process
safety contributes to the success and sustainability of their
company. Performance indicators should be used to show
the status of the process safety management system.
Direct and tangible action should be taken to make
improvements where necessary based on the information
gained from performance indicators. (HSG254 page 14,
Step 3.4 & page 17, Step 4.4).
The indicators should be chosen to provide the
management team with the right scope and level of
information they need to be satisfied that process safety
risks are under control
The management should: actively participate in the
development of indicators and the setting of tolerances;
routinely see and act upon the information provided from
the process safety measurement system. (HSG254 page 7
Step 1.3). Both leading and lagging indicators should be
used to monitor specific process safety risks (HSG254
page 2 Figure1: Dual Assurance). Information from the
measurement system should have a clear and tangible
impact on the management of process safety risks.
- 10 -
Item
Inspection Topics
Guidance Notes
1.6.4
Content of monitoring
programmes
1.6.5
change control
isolation practices
control of locked valves
control of overrides on
process protection
systems
adequacy of local risk
assessments etc.?
Records
What records are kept, how
are the results reviewed, and
actions implemented?
Legal
Basis
1.7
1.7.1
Audit scope
How is process integrity
catered for in the audit
programme?
1.7.2
Audit description
- 11 -
Item
Inspection Topics
Guidance Notes
1.7.3
Audit implementation
1.7.4
1.7.5
Legal
Basis
MHSWR Reg. 5 require effective arrangements for monitoring and review of preventive
and protective measures.
- 12 -
Inspection Topic
Guidance Notes
Management Systems for Small Bore Tubing
2.1.1
Overview
2.1.2
2.1.3
Are responsibilities /
accountabilities adequately
defined for management of
small bore tubing?
Training and Competence
How is competence
established / assured?
Is there a register of
competent persons?
2.1.4
- 13 -
Item
Inspection Topic
Guidance Notes
2.1.5
Maintenance and
Operational Procedures
Does the DH have specific
maintenance and operational
procedures for small bore
tubing?
Have these been reviewed
against the IP / Oil and Gas
UK Guidelines?
2.1.6
Reinstatement Procedures
Do the maintenance and
operational procedures cover
reinstatement of small bore
tubing and fittings?
PUWER Regs 3,4,5,6,8 and 9 require employers, and duty holders (Reg. 3), to ensure:
Work equipment is constructed or adapted so as to be suitable for the purpose for which it is
provided (Reg. 4); work equipment is maintained in an efficient state, efficient working order,
and good repair (Reg. 5); where work equipment is of a type where safe operation is
critically dependent on it being properly installed, (or reinstalled) the equipment is inspected
before being put into service, and at suitable intervals (Reg. 6); people who use work
equipment have adequate health and safety information, and written instructions (Reg. 8);
all persons who use work equipment have received adequate training (Reg. 9).
PFEER Reg. 5 and 9, and MHSWR Reg. 5 are also relevant.
2.2
- 14 -
Item
Inspection Topic
Guidance Notes
2.2.1
Identification of Vibration
Problems
2.2.2
Assessment of Vibration
Does the DH have a structured
assessment methodology to
identify potential problem
areas?
Has the duty holder addressed
the issue of excitation
mechanism in the
methodology? (Stage 1)
What further analysis of the
vibration sensitive system has
been undertaken? (Stages 2
and 3)
- 15 -
Item
Inspection Topic
Guidance Notes
2.2.3
Legal
Basis
2.3
2.3.1
2.3.2
Integrity of supporting
arrangements
Are the supporting
arrangements in accordance
with specified arrangements?
(To be examined for selected
systems)
2.3.3
- 16 -
Item
Inspection Topic
Guidance Notes
2.3.4
Legal
Basis
2.4
2.4.1
Management of flexible
hoses
- 17 -
Item
Inspection Topic
Guidance Notes
2.4.2
2.4.3
2.4.4
Legal
Basis
- 18 -
Item
Inspection Topic
Guidance Notes
- 19 -
Inspection Topics
Guidance Notes
Design data / as built status
3.1.1
Document control
procedures
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
- 21 -
Item
Inspection Topics
Guidance Notes
on P&IDs.
3.1.8
Legal
Basis
3.2
3.2.1
Identification of Safe
Operating Limits
3.2.2
Legal
Basis
PUWER Reg. 8 requires employers to ensure that all persons who use work equipment
have adequate health and safety information and, where appropriate, written
instructions.
3.3
3.3.1
Legal
Basis
- 22 -
Item
3.4
Inspection Topics
Operating Procedures
Guidance Notes
3.4.1
Availability of procedures
3.4.2
Scope of procedures
Do the procedures address
each phase of operation?
(Select a section of plant and
examine the procedures in
detail)
3.4.3
Safety Information
3.4.4
Legal
Basis
3.5
3.5.1
- 23 -
Item
Inspection Topics
Guidance Notes
Legal
Basis
MHSWR, Reg. 5 requires arrangements for planning and control ... of preventive and
protective measures.
HSWA, s2(2)(c) requires the provision of such information ... as is necessary.
PFEER Reg. 9 requires duty holders to take appropriate measures with a view to
preventing fire and explosion....
3.6
Monitoring of Documentation
3.6.1
documentation relating to
as built status
definition of safe operating
limits
protection settings
operating procedures
handover arrangements
plant condition records,
and
control room records.
Legal
Basis
MHSW Regs 1999, Reg. 5 requires arrangements for planning and control and monitoring
of preventive and protective measures.
3.7
Training / Competence
3.7.1
3.7.2
Legal
Basis
- 24 -
Inspection Topics
Guidance Notes
Isolation Standards and Procedures
4.1.1
- 25 -
Item
Inspection Topics
Guidance Notes
Legal
Basis
4.2
4.2.1
Legal
Basis
4.3
4.3.1
Is a register used?
Is there a procedure for
checking long-term isolations?
Are there arrangements for
periodic review?
- 26 -
Item
Inspection Topics
Guidance Notes
Legal
Basis
4.4
4.4.1
Legal
Basis
4.5
4.5.1
- 27 -
Item
Inspection Topics
Guidance Notes
Legal
Basis
4.6
4.6.1
- 28 -
Item
Inspection Topics
Guidance Notes
Legal
basis
- 29 -
Inspection Topics
Guidance Notes
Instrumented protection and ESD systems
5.1.1
Safety Criticality
Are protective functions
identified as safety critical
elements?
5.1.2
Documentation
Is there documentation
available that identifies
protective functions as SCEs?
Is there further information on
e.g. performance standards,
cause and effects analysis, trip
settings, proof test procedures,
test intervals and test results?
- 31 -
Item
5.1.3
Inspection Topics
5.1.4
Testing
What arrangements are in
place for testing safety critical
instrumented protection
functions and are they being
followed?
Guidance Notes
including details of the requisite performance standards
may not always be available.
Where no independent mechanical protection (e.g.
pressure relief protection) is provided, an instrument
based protective trip function (e.g. a HIPS system) is an
alternative but requires particularly high integrity. Such
trips are not the preferred protective arrangement, and
need to be engineered with detailed attention to failureto-safety, fault tolerant multiple redundant architecture,
speed of response etc. Note that the use of pressure
switches rather than pressure transmitters is undesirable
on HIPS. The concept of Safety Integrity Levels (SILs) is
now commonly used for instrumented protective
functions, and has largely overtaken the concept of
HIPS.
Examples of such systems have been found where no
detailed response analysis had been carried out, and the
response characteristics were such that the required
performance standards could not be achieved.
All safety critical instrumented protective functions
should be tested at suitable intervals to ensure that their
performance standards continue to be met.
Higher integrity functions require a more stringent test
programme than lower integrity functions. HIPS systems
require regular proof testing, and monitoring of the
demand rate and performance in service.
Typically, testing may be broken down into separate
processes on the sensors, logic and final end elements.
Sensors may be tested quite easily with the logic
inhibited, so are usually tested at intervals of a few
months to 1 year. Testing the logic and end elements
may involve a real plant trip, and is often undertaken
less frequently, typically at two or three times that
interval.
It may be possible to take credit for real or spurious trip
demands, if all the appropriate data are gathered. In any
event, failures in service should be investigated. Trip
testing should check all redundant paths through the
function, including all of the solenoid valves controlling
ESD valves.
5.1.5
- 32 -
Item
Inspection Topics
Guidance Notes
purposes?
5.1.6
5.1.7
Legal
Basis
5.2
5.2.1
Inhibit requirements
Have requirements for the
application of inhibits been
adequately defined?
Do inhibits apply to only one
function, or groups of
functions?
5.2.2
Risk assessment
Are inhibits assessed before
being applied?
- 33 -
Item
Inspection Topics
Guidance Notes
5.2.3
Is there a comprehensive
record of all inhibits that have
been applied?
Are they removed when no
longer needed?
Are adequate monitoring
arrangements in place?
If there are two control
locations, is there a proper
protocol in place?
Legal
Basis
5.3
5.3.1
Application of
programmable systems
Legal
Basis
5.4
5.4.1
Design standard
5.3.2
5.3.3
- 34 -
Item
Inspection Topics
Guidance Notes
standard?
5.4.2
Legal
Basis
- 35 -
Item
5.5
Inspection Topics
Guidance Notes
Relief / blowdown / flare system integrity
5.5.1
5.5.2
- 36 -
Item
Inspection Topics
5.5.3
Legal
Basis
Guidance Notes
- 37 -
Inspection Topics
Change Control Procedure
Guidance Notes
6.1
Legal
Basis
6.2
Scope of Application
6.2.1
Hardware / software
modifications
Does the change control
procedure include:
- 39 -
Item
Inspection Topics
Guidance Notes
6.2.2
Temporary changes
Replacement equipment
Does the change control
procedure apply for
replacement of equipment?
6.2.4
Operating procedures
Does it apply for changes to
operating procedures or other
formal operating instructions?
6.2.5
Organisational changes
How are changes to
organisational structures
managed e.g. contractorisation,
downsizing, multi-skilling,
change in shift patterns?
Legal
Basis
6.3
6.3.1
Change initiation
6.3.2
Change approvals
Who approves change?
- 40 -
Item
6.3.3
Inspection Topics
Guidance Notes
safe limits.
Communication
6.4
6.4.1
Hazard Identification
What hazard identification tools
are used?
- 41 -
Item
Inspection Topics
Guidance Notes
6.4.2
Risk assessment
Legal
Basis
6.5
6.5.1
6.5.2
Legal
Basis
6.6
6.6.1
- 42 -
Item
Inspection Topics
Guidance Notes
6.6.2
SCR Reg. 14 require the revision of the contents of the SC as often as may be appropriate
and/or where revision will render the SC materially different.
SCR Regs. 20 & 21 review, revision, and continuing effect of verification scheme
PFEER Reg. 5(1) assessment to be performed and repeated as often as may be appropriate
PFEER Reg. 19(2) & (3) operation of a suitable written scheme of examination
6.7
6.7.1
Introduction to Operational
Risk Assessment
Is the duty holder using
Operational Risk Assessment
on the installation?
6.7.2
1.
Recognise the need
2.
Identify the Hazard
3.
Assess the Risk
4.
Analyze Risk Control Measures
5.
Make Control Decisions
6.
Implement Risk Control Measures
7.
Monitor and Review
Operational Risk Management There are many desired outputs from the ORA:
1)
a decision as to whether the offshore team is
suitably qualified to conduct the ORA in all of the
Is the duty holder getting the
circumstances, and if not to supplement the team;
desired outputs from the
2)
identification of cumulative effects which have a
Operational Risk Assessment?
bearing on the situation e.g. number of impaired barriers to
prevent or mitigate a major accident;
3)
identification of practicable interim additional barriers
to supplement those of the design;
4)
identification of suitable interim/special emergency
response arrangements;
Is the duty holder using a
suitable Operational Risk
Assessment Process?
6.7.3
- 43 -
Item
Inspection Topics
Guidance Notes
5)
an estimate of time scale for the barrier/barriers to
be restored;
6)
an assessment of the residual risk;
7)
according to the residual risk, consideration of the
level of authority required to proceed;
8)
a decision that the residual risk is tolerable or not for
the proposed timescale, and taking the appropriate action
i.e. continue production with the additional measures or shut
down all or part of the process plant;
9)
audit and review periodically to ensure no further
degraded situations have arisen, and that the time for
restoration of the barrier/barriers has not slipped.
6.7.4
- 44 -
Inspection Topics
Guidance Notes
Process safety critical elements (SCEs)
7.1.1
Identification of SCEs
Have industry guidelines on
identification of SCEs been
followed, and do they include
those referenced opposite?
7.1.2
Performance standards
Are performance standards
measurable / auditable?
Has an independent competent
person reviewed them?
7.1.3
7.1.4
- 45 -
Item
Inspection Topics
Guidance Notes
undertaken?
Legal
Basis
7.2
7.2.1
Corrosion policy
7.2.2
Organisation
7.2.3
7.2.4
Performance monitoring
- 46 -
Item
Inspection Topics
Guidance Notes
7.2.5
7.2.6
Legal
Basis
PFEER Reg. 9 requires duty holders to take appropriate measures for preventing the
uncontrolled release of flammable etc substances.
PUWER Reg. 5 requires the maintenance of work equipment in an efficient state.
MHSWR Reg. 5 requires arrangements for planning and control ... of preventive and
protective measures.
7.3
7.3.1
- 47 -
Item
Inspection Topics
Guidance Notes
Legal
Basis
7.4
7.4.1
Overview
7.4.2
Responsibilities
Are responsibilities /
accountabilities adequately
defined for management of
bolted pipe joints?
7.4.3
- 48 -
Item
Inspection Topics
7.4.4
Legal
Basis
Guidance Notes
7.5
7.5.1
Legal
Basis
- 49 -
8.5 Protection against air ingress and flammable mixtures in process plant
Flammable mixtures can form in piping, plant and equipment when air enters systems that
normally contain hydrocarbon, as a result of operational or maintenance activities. Correct
purging and operational procedures will ensure that the risks are minimised.
- 51 -
Inspection Topics
8.1
Guidance Notes
Note: Hydrogen Sulphide is a highly toxic gas, and adequate precautions have to be in place
to deal with toxic hazards. However, this inspection project focuses primarily on prevention of
loss of containment, not on dealing with the consequences.
8.1.1
8.1.2
8.1.3
Integrity monitoring
Is the integrity of the H2S & CO2
plant adequately maintained?
Was the plant designed, and is it
inspected, to ANSI M fluid
service code requirements?
- 52 -
Item
Inspection Topics
Guidance Notes
Legal
Basis
MHSWR Reg. 5 requires arrangements for planning and control ... of preventive and
protective measures.
PUWER Reg. 8 requires adequate health and safety information and, where appropriate,
written instructions.
PFEER Reg. 9 requires appropriate measures for preventing the uncontrolled release of
flammable etc substances.
8.2
Sand management
8.2.1
8.2.2
8.2.3
8.2.4
Sand monitoring
- 53 -
Item
Inspection Topics
Guidance Notes
8.2.5
Operating procedures
Legal
Basis
DCR Reg. 14 requires the well-operator to assess the well conditions, and any hazards
PFEER Reg. 9 requires duty holders to take appropriate measures for preventing the
uncontrolled release of flammable etc substances.
PUWER Reg. 5 requires the maintenance of work equipment in an efficient state.
8.3
Control of Hydrates
8.3.1
8.3.2
Procedures
Do procedures cover hydrate
hazards, and the arrangements for
prevention and control?
8.3.3
Provision of inhibitor
Are operators aware of the
requirement for inhibitor during all
operating modes?
Is hydrate inhibitor injection
provided at all necessary points
on the installation?
- 54 -
Item
Inspection Topics
Guidance Notes
Legal
Basis
MHSWR Reg. 5 requires arrangements for planning and control ... of preventive and
protective measures.
DCR Reg. 7 require the duty holder to ensure that the installation is not operated unless
appropriate limits within which it is to be operated have been recorded.
PUWER Reg. 8 requires employers to ensure that all persons who use work equipment have
available to them adequate health and safety information and, where appropriate, written
instructions.
8.4
Sampling arrangements
8.4.1
8.4.2
- 55 -
Item
Legal
Basis
Inspection Topics
Guidance Notes
8.5
8.5.1
8.5.2
Vessel purging
Are adequate purge rates
maintained at all times to prevent
air being drawn into process
vessels?
8.5.3
Maintenance purging
Do procedures cover the
precautions taken to minimise the
formation of flammable
atmospheres within systems
following maintenance or routine
operations?
How is the adequacy of purging
determined?
- 56 -
Item
8.5.4
Legal
Basis
Inspection Topics
Guidance Notes
8.6
8.6.1
Integrity of segregation
Seal pots and seal loops in the drain headers are used
to provide segregation between drain systems. Seal pots
and loop seals can either rely on a continuous or a
dedicated water supply, which should maintain all seals
liquid full. Routine plant inspections should include
checking that seals are intact and that no debris has
collected to block drains or gullies.
8.6.2
Other considerations
Has winterisation been
considered?
Have effects of modifications been
considered?
Legal
Basis
PFEER Reg. 9 requires duty holders to take appropriate measures for preventing the
uncontrolled release of flammable etc substances.
PUWER Reg. 5 requires the maintenance of work equipment in an efficient state.
- 57 -
Inspection Topics
Guidance Notes
Effects of Motion on Process Plant Systems
9.1.1
Operating Envelope
Is the operating envelope clearly
defined?
9.1.2
9.1.3
Procedures / Instructions
Are there instructions on action to
take when operating limits are
reached?
Are instructions adhered to? Have
inhibits / overrides been applied to
avoid tripping due to vessel
motion?
Legal
Basis
- 59 -
Item
9.2
Inspection Topics
Guidance Notes
Turret Arrangements / Swivel Joints & Seals, Leakage & Recovery
9.2.1
Design limits
Are the operating limits for the
system clearly specified?
Are recuperation facilities
designed to withstand maximum
foreseeable pressure?
9.2.2
Operations
Are there instructions on action to
take when the limits of vessel
rotation, or swivel seal leakage,
are reached?
Are swivel seals being regularly
flushed / greased to minimise
wear and reduce leakage?
Is there any evidence of leakage
of process fluids to atmosphere?
Legal
Basis
PUWER Reg. 4, work equipment has to be constructed or adapted as to be suitable for the
purpose for which it is used or provided.
PUWER Reg. 6, inspection.
PUWER Reg. 8, provision of information and instructions
SCR Reg. 12
PFEER Regs. 4, 5, 9 & 19
DCR Regs. 4-8
9.3
9.3.1
Inspection / Testing
Are inspection / testing
arrangements adequately in
place?
- 60 -
Item
Inspection Topics
Guidance Notes
Legal
Basis
9.4
9.4.1
Design
9.4.2
Operations
Are isolations controlled and
monitored using a locked open /
locked closed valve register?
Legal
Basis
9.5
9.5.1
Design
Are P&IDs adequate for process
requirements?
Are there any indications of
incompatibility between marine
and process systems?
9.5.2
Operations
Is there clear demarcation
between marine and process
systems?
- 61 -
Item
Inspection Topics
Guidance Notes
Legal
Basis
PUWER Reg. 4, work equipment has to be constructed or adapted as to be suitable for the
purpose for which it is used or provided.
9.6
HP Fuel Gas
9.6.1
Design
9.6.2
Operations / maintenance
Legal
Basis
9.7
Gas Compression
9.7.1
Design
Have any design problems been
noted for use of compressors in a
marine environment?
9.7.2
Legal
Basis
Operations
- 62 -
Inspection Topics
Management System
Guidance Notes
All personnel, including third parties, should have been
made aware of the overall aims of the project and how
health and safety aspects are integrated into the plan.
Legal
Basis
10.2
Post Design
10.2.1 HAZOP
Have HAZOP and / or other safety
studies (e.g. API RP 14C review of
HP / LP interfaces) been carried
out at the design stage?
- 63 -
Item
Inspection Topics
Guidance Notes
10.3
Pre-construction
Legal
Basis
- 64 -
Item
10.4
Inspection Topics
Construction
Guidance Notes
Problems have been experienced with incorrectly
assembled piping flange joints and small bore fittings.
The problems include the use of incorrect or
incompatible materials and fittings, incorrectly tensioned
bolts in flanged joints, over or under tightened
compression fittings and insufficient tubing / piping
length inserted into compression fittings.
To reduce the probability of leaking joints, there should
be systems in place for competence assurance of the
personnel carrying out and inspecting such work. The
system(s) may include the retraining / testing of
personnel.
Joints identified as safety critical should require bolts to
be torqued or tensioned to specified values and the work
to be witnessed by independent parties. These values
should be formally recorded and tagged as per the
latest industry guidelines.
10.5
Commissioning
10.5.1 Procedures
Have procedures been developed
and approved?
Is there a system for controlling
distribution, changes and status?
- 65 -
Item
Inspection Topics
Guidance Notes
The flushing process would normally be carried out
using a high volume flow of compatible fluid, i.e.
normally fresh water but special fluid or hydraulic oil for a
hydraulic system so as not to contaminate the system
with water. For some systems seawater may be used for
flushing but it should be inhibited as required. Some
systems, e.g. stainless steel, may require fresh water
flush, following seawater, to remove chlorides.
Following water flushing, the system is drained at low
points; residual water may be blown out of the system
using dry air. Where the system is to be left empty for
more than a few days, it should be blanketed with dry air
or nitrogen to prevent internal corrosion. For prolonged
periods in this state, the system may need to be treated
with corrosion inhibitor.
Pressure testing includes proof / strength testing, and
leak testing. Pressure testing can be carried out either
hydraulically or pneumatically. Wherever practicable
hydraulic testing should be employed to reduce the risks
to personnel. Guidance is available in Safety in
Pressure Testing, HSE Guidance Note GS4 (3rd ed.
1998).
Strength testing is carried out to prove the quality of
materials and the construction of the equipment / system
before it enters service. Test pressure is typically 1.25 1.5 x system design pressure. All temporary connections
must be adequately rated for the test. Relevant
standards are:
- 66 -
Item
Inspection Topics
Guidance Notes
10.5.6 Training
Legal
Basis
PUWER Reg. 6, requirement to inspect work equipment after it has been installed and put into
service for the first time, or after assembly at a new site or location. Requirement to keep
records of inspection.
PUWER Reg. 12, protection against specific hazards. Cleaning, flushing and pressure testing
contribute to the overall scheme of taking measures to prevent the unintended discharge of
fluids from the work equipment.
10.6
Post Commissioning
Legal
Basis
- 67 -
Part 10 Glossary
ACOP
DCR
DH
ESD
ESDV
FMEA
FPOSO
HAZID
HAZOP
HCR
HIPS
HSWA
ICP
LOPA
MAH
MHSWR
NUI
ORA
OSD
PFEER
PTW
PUWER
QRA
SBT
SC
SCE
SCR
SIL
SMS
SSIV
- 68 -