Att-2 Grounding & Lightning Protection - Tech - Specs.
Att-2 Grounding & Lightning Protection - Tech - Specs.
Protection
PROJECT NAME
TOTAL 34 PAGES
(Including Cover)
Purpose
For Information
DOCUMENT NO.
: KP-00B__-EE210-G6015
TITLE
OWNER
For Review
For Approval
For Construction
As-Built
09 April 2013
For Approval
H. Halvachi
S. Mikoleit
A. Zarali
H. zcan
17 February 2014
3rd Draft
H. Halvachi
S. Mikoleit
A. Zarali
H. zcan
20 January 2014
2nd Draft
H. Halvachi
A. Brutigam
A. Zarali
H. zcan
24 October 2013
1st Draft
H. Halvachi
A. Brutigam
---
---
Rev.
No.
DATE
DESCRIPTION
PREPARED
CHECKED
REVIEWED APPROVED
GAMA POWER SYSTEMS ENG &CONTRACTING,INC.
Owner
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
2 of 34
TABLE OF CONTENTS
1
2.1
General:
2.2
Implementing Specification:
2.3
2.4
General Abbreviations:
2.5
2.6
Basic Design:
2.7
GROUNDING SYSTEM:
3.1
Foundation Earth:
3.2
3.3
3.4
10
3.5
Grounding Connections:
10
11
4.1
General:
11
4.2
11
4.3
12
4.4
13
13
14
14
14
5.1
Equipotential Bonding:
15
5.2
15
SHIELDING OF BUILDINGS:
16
PERFORMANCE REQUIREMENT:
17
7.1
Interfaces:
17
7.2
17
17
17
17
18
18
18
18
7.3
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
3 of 34
18
19
19
7.3.7 Switchgear:
19
20
20
20
20
20
21
7.4.4 Fences:
21
21
21
Cable Ducts:
22
22
22
22
22
22
7.6
Materials:
23
23
8.1
23
8.2
24
SCOPE OF SUPPLY:
25
9.1
Foundation Earth:
25
9.2
25
9.3
26
9.4
27
9.5
28
10
DOCUMENTATION REQUIREMENTS:
28
10.1
General Requirements:
28
10.2
Documentation Requirements:
28
10.3
Documents to be Provided:
30
10.4
Project Control:
30
10.5
30
30
30
31
7.4
7.5
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
4 of 34
31
11
31
11.1
General Requirements:
31
12
RATING:
32
12.1
Load Cases:
32
13
APPENDIX:
33
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
5 of 34
List of Tables
Table 1: Lightning protection level
12
List of Figures
Figure 1: Location of the power plant
Figure 2: An example for the fixed grounding point
Figure 3: Lightning protection zone concept in accordance with IEC 62305-4
Figure 4: The expansion piece for the air termination
Figure 5: Internal lightning protection and equipotential bonding bar (EBB)
Figure 6: An example for equipotential bonding and an equipotential busbar
Figure 7: Arrangement of the foundation earth electrode
Figure 8: Earth termination system
Figure 9: An example for the external lightning protection
Figure 10: An example for the air termination system
Figure 11: Internal Grounding
6
10
12
13
14
15
25
26
27
27
28
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
6 of 34
Khabat is about 35 km away from Erbil and can be reached by car in about 35 minutes.
The present specification is applicable for the design and erection of grounding and lightning
protection systems for the 2 x 150 MW Khabat Power Plant Project.
General:
The grounding and lightning protection system shall be required for personal protection and
minimization of material damage. Thus, the apparent short-circuit and lightning currents must be
safely dissipated, and the exposure of people to voltages and the risk of over voltages for
electrical, instrumentation and control equipment must be limited to acceptable values.
The grounding system shall ensure protective and system grounding for the electrical power and
instrumentation and control installations as well as sufficient grounding for the lightning protection
systems.
A grounding system shall assure:
Doc. No
KP-00B__-EE210-G6015
Rev. No.
2.2
Page
7 of 34
Implementing Specification:
Grounding and lightning protection systems shall comply with the requirements specified in the
following sections. The effect of the lightning protection system must conform to lightning
protection class I according to standards for buildings with control rooms, instrumentation and
control computers, protective devices or central switchgear and to lightning protection class II for
other buildings such as turbine house, boiler house or administrative buildings.
The earthing of instrumentation and electronic circuits shall be done according to their
manufacturer requirements and IEEE 1050.
The Supplier shall point out any deviations from these specifications already at the tendering
stage.
2.3
IEC 62305-1
IEC 62305-2
IEC 62305-3
IEC 62305-4
IEC 60228
IEEE 80 - 2000
IEEE 998
IEEE 1050
BS 6739
BS 7430
NFPA 780
2.4
General Abbreviations:
2.5
2.6
LPZ
LPS
LPL
SPD
132 kV
15.75 kV
6 kV
230/400 VAC
220 VDC
24 VDC
Main
Generator voltage
MV switchgear (IT system)
Consumer voltage (TN-C system)
DC - UPS voltage for control system
DC - UPS voltage for control system
Basic Design:
All components of the grounding and lightning protection system shall be dimensioned and
7
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
8 of 34
2.7
The components and systems belonging to the grounding and lightning protection systems are
listed below.
Grounding system
External lightning protection
Internal lightning protection
Equipotential bonding
Lightning surge suppressors
Shielding of cables
3GROUNDING SYSTEM:
A safe grounding system has to carry electric currents into the earth under normal and fault
conditions without exceeding any operating and equipment limits or adversely affecting continuity
of service. It has also to assure that a person in the vicinity of grounded facilities is not exposed to
the danger of critical electric shock.
The method of grounding resistance calculations and safety limits for equipment and personnel
protection has to be based on the standard IEEE 80.
The parameters used for design and the detailed grounding calculations are shown and explained
in the specification KP-00B__-EE365-G6025, including ground fault potential rise, and step and
touch potential study.
A common grounding system shall be provided for the power plant. The following system
components are considered:
High-voltage protective grounding
Medium-voltage protective grounding
Low-voltage grounding
Functional grounding (error-free functioning of an electrical system and ensuring that there
is electromagnetic compatibility)
Lightning protective grounding
The grounding system shall consist of a foundation earth of each building, a ring earth electrode
around every building and an external mesh earth electrode.
3.1
Foundation Earth:
The foundation earth is a conductor that is installed with a connection to the reinforcing steel in the
concrete foundation and is used as an earth electrode. The foundation earth must be enclosed and
8
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
9 of 34
3.2
3.3
The external mesh earth electrode shall be established between the individual buildings at the
power plant site. The external mesh earth electrode offers a large surface to distribute the fault or
lightning currents.
All buildings and steel construction shall be connected to each other as well as to the grounding
system through the external mesh earth electrode.
The outlying electrical control cabinets and devices shall be connected to the grounding system by
means of external mesh earth electrode.
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
10 of 34
The external mesh earth electrode shall be connected to the ring earth electrodes by means of the
detachable connecting points every 20 m. A 120mm stranded copper conductor shall be used for
the external mesh earth electrode, and the mesh size across the entire power station grounds will
be about 20 m.
The conductor earth electrodes (ring and external mesh earth electrode) must be laid in
consolidated, flush subsoil. The backfill must be free of stones, rough gravel, rubbish or slag.
The conductor earth electrodes shall be of stranded high-conductivity copper to IEC 60228.
3.4
Any external cables shall be directly laid in the soil, PE tubing, duct blocks or precast ducts.
A grounding conductor shall be laid above buried cables for protection against direct lightning
strikes. Based on the distance between grounding conductor and cables, there shall be a resulting
protection angle of 90.
This grounding conductor has to be connected with the following components of the grounding
system:
External mesh grid (at intersection points)
Ring earth conductor (around building)
All grounding conductors, for example in cable ducts, have to be connected with each other.
The grounding conductor shall be of stranded high-conductivity copper to IEC 60228.
3.5
Grounding Connections:
The grounding connection points shall be provided to connect the grounding system to the process
and electrical components. The grounding connection shall be provided preferably as fixed
grounding points in the concrete and wall. Grounding lugs shall be used in the areas where no
fixed earthing terminals are mountable.
The grounding components shall be connected directly or via an equipotential bonding busbar to
the fixed grounding point or grounding lugs. The grounding components are the process and
10
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
11 of 34
4.1
General:
The external lightning protection has the task of capturing the lightning, conducting the lightning
current from the point of impact to the earth, and of spreading it throughout the earth without
generating any damage to protected equipment or people through thermal or mechanical effects
when a dangerous overvoltage occurs.
4.2
A lightning protection zone (LPZ) is a zone in which the electromagnetic environment is defined in
regard to lightning risk. The LPZ limit consists of the outer and inner zones.
The LPZ 0A and LPZ 0B are outer zones, which are located outside of the building. The inner
zones are located inside the building.
For this project, four LPZ are defined as follow:
LPZ 0A: Direct lightning strikes are possible; the entire lightning current or parts thereof may
occur, as well as the full electromagnetic field of lightning.
LPZ 0B: Protected against direct lightning strike; parts of the lightning current can occur, as
well as the full electromagnetic field of lightning.
LPZ 1: The lightning currents are limited by current sharing and possibly by surge protection
devices (SPD) at the zone boundaries. The electromagnetic field of the flash may be
attenuated by spatial shielding.
LPZ 2: The lightning currents are further limited by current sharing and possibly by surge
protection devices at the zone boundaries. The electromagnetic field of lightning is usually
further attenuated by shielding.
11
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
12 of 34
4.3
The lightning protection is divided into four levels. The levels appropriate different probabilities that
the peak value of lightning current is below a predetermined current strength.
The following table shows the definitions for the peak value of lightning current depending on the
lightning protection level:
Lightning protection level
II
III
IV
99%
98%
97%
97%
200kA
150kA
100kA
100kA
99%
97%
91%
84%
3kA
5kA
10kA
16kA
20m
30m
45m
60m
5x5 m
10x10 m
15x15 m
20x20 m
12
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
13 of 34
The lightning protection level affects only the dimensions and requirements of the external lightning
protection, particularly the air terminals and, to a limited extent, the requirements for surge
protection devices. The other parts of the lightning protection system are widely independent of the
lightning protection level.
It is also generally accepted that the buildings have different lightning protection levels even in a
cross-building LPZ.
4.4
The design of the air terminals is determined by the rolling sphere method. The radius of the rolling
spare shall be considered for air terminal design.
Aluminum (AlMgSi) shall be used for the air terminal rods. The length and number of air terminals
are dependent on building and roof structures.
13
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
14 of 34
5.1
Equipotential Bonding:
In the event of ground fault or lightning strike, effective equipotential bonding shall be provided
inside of buildings. The sufficiently low impedance connections among the equipment shall be
14
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
15 of 34
Equipotential bonding can be executed by several connected equipotential bonding bars on a level.
A copper ground bus shall be installed on the bottom level of every building. The ground bus can
be a closed or non-closed ring. The ground bus shall be connected to the external grounding
system via fixed grounding terminals.
All conductive plant components (extraneous conductive parts), which must have the same
potential and be connected with electrical equipment, shall be connected to the equipotential
bonding by the shortest route. These are mainly containers, parts of the building structure,
pipelines, ventilation ducts, stairs, railings, grids, cable support structures, switchgear, etc.
5.2
Lightning surge suppressors need only be installed in particular cases for buildings or components
subject to increased lightning hazards. Mainly, these are:
The lightning surge suppressors shall be installed directly at the entry into the building.
The cables leading to the lightning surge suppressors from outside must not be laid in parallel with
other indoor cables up to the lightning surge suppressor.
The lightning protection concept should be designed so as to avoid the need for lightning surge
suppressors wherever possible.
The cabinets and racks for the lightning surge suppressors shall be connected to the mesh earth
electrode or the building reinforcement by the shortest route via the ground stud.
15
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
16 of 34
6SHIELDING OF BUILDINGS:
Buildings with control rooms, instrumentation and control computers, protective devices or central
switchgear shall be shielded with one of the following measures:
1. Electrically interconnected reinforcement of reinforced concrete
2. Metal facades
3. Air terminals and down conductors installed at the outer surfaces with a maximum mesh
size of 5m x 5m
For the first measure, the reinforcement can be used as shielding according to IEC 61024-1-2 if the
reinforcement steel is weldable. In this case, the reinforcement bars shall be welded to each other
every 1 m.
Note: The steel qualities usually used for concrete reinforcement at the moment are suitable for
welding.
With regard to the second measure, the metal facade covers the building as shielding. The metal
facade shall be mounted electrically conductive. The facade shall be connected to the grounding
system.
For the third measure, the mesh earth electrode shall consist of round steel bars and has to be
installed under a minimum concrete cover of 5 cm.
The mesh sizes in the roof ceilings shall not exceed 5m x 5m. The mesh sizes in the foundation
plate shall not exceed 10m x 10m.
In concrete outer walls, the mesh size shall not exceed 5m x 5m. In concrete columns or precast
concrete columns of outer walls, low impedance connection possibilities should be provided at the
top and bottom.
All concrete-encased mesh earth electrodes shall be electrically connected to the equipotential
bonding of the electrical installation by means of detachable connecting elements.
The number of detachable connecting elements results from the mesh size for:
All connecting elements must be labelled and visible; where the size of a side of a building is
smaller than the interval, the corners of the building must be connected, e.g., facade sheet steel.
16
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
17 of 34
7PERFORMANCE REQUIREMENT:
7.1
Interfaces:
Connecting points of the external and internal lightning protection, and metal parts of the building
structure for equipotential bonding strips inside of buildings. All major equipment and tanks shall be
connected to the main ground grid in two places on opposite sides.
All metallic structures and equipment, such as motor frames, switchgear, unit substations, motor
control centers, panelboards, lighting cabinets, conduits, cable trays, crane rails, stairs, handrails
and tracks shall be permanently and effectively grounded.
It must be ensured that there is no electrically conducting connection directly or indirectly
between cathodically-protected equipment and other parts. These parts in particular include
structures made of reinforced concrete, grounding systems and all other buried metallic piping,
vessels, sheeting walls, etc.
Detailed information is included in the Cathodic Protection Specification KP-00B__-EE210-G6005.
7.2
17
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
18 of 34
Additionally, it shall be observed that flashovers into the cables shall not occur due to the vicinity to
the air terminals and down conductors. Such cables shall be laid in closed sheet-metal gutters,
cable tray, metal pipes or behind metal facades. The electrically connected sheet-metal gutters,
cable tray and metal pipes shall be connected to the mesh earth electrode at the ends.
7.3
7.3.2
Medium-Voltage Transformer:
The transformer tank of the step up transformer must be connected to the grounding system at
least twice.
The star point of the transformer must be connected to the grounding system via the surge
arrester. The cross section of grounding cable to the grounding system must be chosen according
to the sustained short-circuit current.
18
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
19 of 34
The individual cable trays of a cable route shall be conductively connected by means of the joint Hsupports.
At the ends and the building borders, cable routes/trays shall be connected to the foundation earth
electrode, the reinforcement, the steel structure, etc., by the shortest route.
Two stranded copper conductors for cable trays with power cables > 1 kV and one stranded
copper conductor for cable trays with power cables < 1 kV, each with 70 mm cross-section, shall
be installed in the corner of a tray rail. In the course of a cable route, only one ground wire
connection shall be carried.
For electrically conducting between the grounding conductor and the cable tray there shall be a
connection every 20 m between the two elements using an appropriate clamp.
7.3.7 Switchgear:
In addition to the protective conductor of the incoming feeder cable, the ground busbars shall be
connected to the grounding system at each end of the equipment.
The ground bus carried on the cable route shall be connected to the PE or PEN bar in the
incoming-feeder panel of every low-voltage switchgear.
The ground bus carried on the cable route shall be connected to the protective conductor bar of the
medium-voltage switchgear.
The switchgear shall be conductively connected to the base frame.
19
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
20 of 34
7.4
20
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
21 of 34
7.4.4 Fences:
When using bare metal fence, it must be earthed. This is to cater for the situation where a live
conductor (overhead line) has come into contact with the fence or to prevent the fence voltage
rising due to coupling with nearby live conductors.
The fence shall therefore be connected to the grounding system at intervals of about 15 m. The
individual fence fields within the power station grounds shall be connected among each other.
This shall be done by installing a 70 mm stranded copper conductor at a depth of 0.5 m along the
fence and connecting it to the fence posts. The earthing system shall be extended such that the
grounding conductor is 1 meter outside the fence. This ensures that touch voltage on the fence will
remain at a low level.
A conductive connection shall be installed from the fence posts to every framed fence element and
the doors. The parts of the power station border fence must also be connected to each other and in
intervals of about 50 m to the potential gradient control ring that follows the fence.
21
Doc. No
KP-00B__-EE210-G6015
Rev. No.
7.5
Page
22 of 34
Cable Ducts:
22
Doc. No
KP-00B__-EE210-G6015
Rev. No.
7.6
Page
23 of 34
Materials:
Stranded copper conductors with a cross section of 120 mm shall be used for grounding
electrodes and earthing conductors.
Stranded copper conductors with a cross section of 70 mm shall be used for protective conductors
and main equipotential bonding conductors. In particular cases (e.g., grounding of door frames),
fewer cross sections or less galvanized flat iron is admissible. The ground buses inside the
buildings shall consist of stranded copper conductors with a minimum cross section of 70 mm.
Stranded copper conductors shall be connected by means of clamps.
The equipotential bonding strips shall be made of flat copper, minimum 40 x 5 mm. The conductors
shall be connected by means of clamps. If a screw connection is necessary, then a wider bus must
be used.
The concrete-encased mesh earth electrode shall be made of smooth round steel bars, 10 mm
diameter.
As conductor material for the air terminals round aluminum (AlMgSi) with 10 mm diameter shall be
used; for down conductors 8 mm diameter shall be used.
8.1
KB-00+++-PS732-P0001
KB-00+++-PS732-P0003
KP-00+++-MQ732-G0008
Packing Guideline
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
24 of 34
For each point the Supplier shall indicate the internal procedure that is applicable. He shall also
indicate whether a report or protocol will be generated for each point, or whether other associated
documentation will be provided (quality certificates, reception reports, etc.).
The Buyer may select the points on this program which they or their representatives can witness.
During the inspection visits, the Buyer reserves the right to review applicable documentation that
has not been presented for his approval (reception procedures, manufacturing procedures, etc.).
In addition to the points mentioned in the appendices, the Inspection and Test Plan shall comprise
a minimum of the following sections, in which the following information shall be given:
a) Materials inspection
Main materials and components: Inspection upon receipt of materials to be used in manufacture,
with indication of those that will require quality certificates.
Auxiliary elements: Inspection of receipt of components with indication of those that will be required
with reception test protocols.
b) Inspection of manufacturing
List of the main as a minimum, the construction phases of the grounding and lightning protection
systems.
c) Examinations and tests
A list of all the tests indicated in this specification, with reference to each associated procedure that
specifies the acceptance criteria for the test in question.
d) Protection, cleaning, painting, labeling and delivery; final documentation
A statement of the monitoring or inspection of these activities setting out the procedures to be
applied and including a revision point for the final documentation dossier and an issue point for the
Delivery Note.
Inspection call will be used for inspection notifications with sequential numbering.
All of the required inspections and tests shall be made at the Suppliers / Subcontractors expense,
including the cost of all samples used.
8.2
The site tests of lightning protection systems/components shall be generally by visual inspection.
Visual inspection of the lightning systems shall take place in order to ensure that all components
are mechanically assembled and fixed properly and that there are no imperfections.
Electrical tests related to lightning systems, such resistance measurements and insulation /
shielding, shall also be carried. The test results shall be submitted immediately following the
completion of tests as computer printout or, alternatively, hand written.
Site test reports shall illustrate all test details as well as details of all applied testing equipment and
their calibration validity.
The field measurement of the constructed grounding system shall be done according to IEEE80.
The lightning protection system shall be inspected according to NFPA 780 Annex D.
9SCOPE OF SUPPLY:
The equipment for grounding and lightning protection shall include but not be limited to the
following:
24
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
25 of 34
All other materials which may be necessary, but which are not mentioned herein specifically, to
complete the grounding and lightning protection in all respects to the best engineering practices
shall be in the Sellers scope.
All materials, consumables, special tools and tackle, testing instruments and machines required for
execution of the work are also included in Sellers scope.
9.1
Foundation Earth:
Round steel bars, 10 mm diameter
Clamp connections
Fixed earthing terminal
9.2
25
Doc. No
KP-00B__-EE210-G6015
Rev. No.
9.3
Page
26
26 of 34
Doc. No
KP-00B__-EE210-G6015
Rev. No.
9.4
Page
27
27 of 34
Doc. No
KP-00B__-EE210-G6015
Rev. No.
9.5
Page
28 of 34
10DOCUMENTATION REQUIREMENTS:
10.1
General Requirements:
A technical documentation must be prepared for the systems, plants, components, operating
materials and spare parts, which guarantees the erection, commissioning, operation and
maintenance of the power unit.
This specification details the definitions regarding types of documents, document forms,
information mediums, identification, number, terms and conditions of handing over, registration and
administration of documents and data.
The scope of supply will be considered as unfulfilled if the listed documents were not submitted to
the Purchaser.
10.2
Documentation Requirements:
All documentation, manuals, drawings, etc., must be in English. The final version of the operation
and maintenance manual and training course documentation must be in English.
Drawings shall be made available in CAD format. In general, all documents will be provided in both
native and portable (PDF) format.
The document and drawing numbering systems of the Purchaser shall be used throughout the
28
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
29 of 34
project
The Supplier shall issue a document list containing all the documents that he will issue under the
contract. This list will be reviewed/commented by the Purchaser. The status of this document list
will continuously be updated by the Supplier and included in the monthly progress reports.
The size of the documents shall be in accordance with ISO A-series of Technical product
documentation. Sizes and layout of drawing sheets EN-ISO 5457. Drawings shall not exceed the
A0 size. All drawings shall remain legible when printed at A3 size for site use. Documents in
electronic format shall be provided in accordance with the following software:
Other electronic formats shall only be used following written approval of the Purchaser.
All documents issued by the Supplier (drawings, texts, etc.) must be developed according to the
project-specific formats and must include the project-specific cover or title box (to be provided
later).
The revision and/or approval by the Purchaser of the drawings or other documents issued by the
Supplier will not release the Supplier from his responsibility of complying with all the contract
requirements.
The documentation coding procedure of the Purchaser will be used for the revision process of the
documentation. After reviewing a drawing or another document, the Supplier will issue an upper
revision indicating the reason of the modification in the title box. Modifications with respect to the
previous revision shall be identified in the drawing or document with a revision cloud or mark.
Any changes to the documents must be controlled during the development of the project. Changes
may be originated from design modifications, non-conformities, as-built deviations, etc. All changes
approved by the Purchaser shall be incorporated in order to maintain all project documents
updated. The final edition of all documents in the as-built edition must be incorporated into a final
dossier.
The Supplier must not carry out any changes in drawings or other documents already approved
without the Purchasers written acceptance.
Revision to the documents will be made by the Purchaser / Architect Engineer in the first round,
and after the updated documents have no more comments, further revisions will be made by the
Owner / Owners Engineer.
The Supplier will answer and clarify any comment to the documentation until it is closed before
issuing an upper revision of each document.
The Purchaser will usually have a two-week period to return the document with comments to the
Supplier.
29
Doc. No
KP-00B__-EE210-G6015
Rev. No.
10.3
Page
30 of 34
Documents to be Provided:
The applicable technical must be submitted by the Supplier for Contractor information or approval
in accordance with the contract. These documents must include all information needed for project
interfaces, input data, contract follow-up and maintenance and operation.
The specific project document list will be provided by the Supplier during the contract.
The documentation marked as critical will be considered in payment milestones and/or may be
penalized according to purchasing conditions.
The Supplier shall also provide all the necessary documentation and project files that may be
required for the official legalization of equipment.
10.4
Project Control:
The Supplier shall submit monthly progress reports on the activities performed during the period.
The monthly progress report must be brief and concise. Any deviation from the project schedule
must be identified. An activities plan for the next period and a corrective and preventive actions
plan to avoid deviations and to eliminate pending items must be included in the report.
Meetings at the Suppliers facilities can be held to ascertain the project quality and progress.
Development of the design, material take-off, manufacture, procedures, tests, etc., will be analyzed
during these meetings.
10.5
The manuals shall be organized by sections, in accordance with the following contents:
10.5.1 Section I. General:
Title page.
Index of sections and reference to the content of the remaining sections.
Table of contents.
Description of how to use the manual and introduction.
General description and performance.
General philosophy of operation.
Operating conditions.
General description of the system equipment and controls.
Start-up, shutdown and emergency procedures.
Risk prevention measures.
Arrangement drawings.
General description.
Operating specifications.
Start-up instructions.
Operating instructions.
Shutdown instructions.
30
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
31 of 34
Conservation instructions.
Installation and commissioning instructions.
Design data and curves.
Control operating sequences.
The start-up, operating and shutdown instructions shall include, step by step, the procedures,
precautions and critical points to be observed, and they will differentiate between those considered
as preliminary, normal and post-maintenance.
Maintenance plan.
Search, diagnosis and repair of failures.
Disassembly instructions.
Maintenance instructions.
Arrangement, clearances and adjustment data.
Assembly instructions.
General Requirements:
The Supplier must maintain a quality assurance system according to ISO 9001/9002/9004 or an
equivalent quality management system which must be approved by MoE.
The Supplier shall prove that a quality management system according to ISO 9001/9002/9004 has
been introduced and is being applied by furnishing a certificate of an accredited certifier.
The Supplier must impose appropriate obligations on his subcontractors.
For the implementation of quality assurance primarily quality planning and inspection the
Supplier must draw up plans for quality assurance for the entire plant.
The Supplier must document the quality assurance measures taken. In particular, the following
must be observed:
CE labelling or presentation of declarations of conformity or manufacturers declarations
must be carried out according to legal requirements. The declarations of conformity or
manufacturers declarations must be handed over with the final documentation.
If no CE labelling is required by law, the Supplier must still hand over declarations of
conformity or manufacturers declarations for the respective equipment/systems with the
final documentation. Additionally, the documentation must include notes for the client
informing him of how to proceed when replacing spare parts or carrying out repair work in
31
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
32 of 34
12RATING:
12.1
Load Cases:
The ground buses shall be dimensioned according to the maximal thermal load in case of fault.
The tripping time of the superordinate protection system shall be taken into account with regard to
the thermal rating of the current discharging grounding components
32
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
13APPENDIX:
1) Typicals for grounding and lightning protection
KP-00B__-EE165-G6024
No.
Description
Typical 1
Typical 2
Typical 3
Typical 4
Typical 5
Typical 6
Typical 7
Typical 8
Typical 9
Typical 10
Typical 11
Typical 12
Typical 13
Typical 14
Typical 15
Typical 16
Typical 17
Typical 18
Typical 19
Lightning Protection
Typical 20
33
33 of 34
Doc. No
KP-00B__-EE210-G6015
Rev. No.
Page
34 of 34
End of Document
34