Chapter#03 Mcqs Project Management: Personality
Chapter#03 Mcqs Project Management: Personality
E) Management style
A good project management system provides for defining the interface between the
project team and the organization in all the following areas except
A) Authority
B) Allocation of resources
C) Development of project team members
D) Integration of the project into the organization
Mega Computers, Inc. has assigned a project manager for each of the five new-product
teams. The managers as well as the project team members work on the projects on a fulltime basis. The structure being used is ________ organization.
A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Project
Elizabeth is considering how to structure a project team that will not directly disrupt
ongoing operations. The project needs to be done quickly and a high level of motivation
will be needed in order to do that. For this situation, the ______ organization would be
the best choice.
A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Project
A project management system provides a framework for launching and implementing
project activities within a ______ organization.
A) Matrix
B) Balanced
C) Weak
D) Sponsor
E) Parent
In which of the following is the balance of authority strongly in favor of the functional
managers?
A) Weak matrix
B) Balanced matrix
C) Strong matrix
D) Strong
10
E) Project
From the list below, which is not a primary characteristic of organization culture?
A) Control
B) Team emphasis
C) History
D) Conflict tolerance
11
E) Risk tolerance
Who is responsible for determining how tasks will be done in a matrix project
management structure?
A) The functional manager
B) The project manager
C) Both are responsible
D) This is no pattern of who takes responsibility
12
structure?
A) Project
B) Balanced Matrix
C) Project Matrix
D) Functional Matrix
13
E) Functional
The Organizational Culture Diagnosis Worksheet classifies cultural characteristics into all
of the following except:
A) Physical characteristics
B) Public documents
C) Behavior
D) Folklore
14
E) Ethics
Which of the following is not one of the typical forms of a project management office?
A) Command center
B) Control tower
C) Resource pool
D) Weather station
E) All of these are typical forms of a project management office
15
The method used to collect information to use through all phases of the project
life cycle is called
Responsibility matrix
A)
Organization breakdown structure
B)
Work breakdown structure
C)
Priority matrix
D)
Work package
E)
B)
C)
D)
E)
The ability of 911 emergency systems to identify the caller's phone number and
location are considered to be a
Technical requirement
A)
Milestone
B)
Project limit
C)
Project exclusion
D)
Project deliverable
E)
"To construct a high-quality, custom home within five months at costs not to
exceed $150,000" is best classified as
A deliverable
A)
A milestone
B)
An objective
C)
A limit
D)
An exclusion
E)
Which of the following is not one of the basic classifications of project priorities?
Profit
A)
Cost
B)
Time
C)
Performance
D)
All of these are basic classifications
E)
If a project criterion indicates that the project must meet a specific date, that
criterion is classified as
Constrained
A)
B)
C)
D)
E)
Enhanced
Accepted
Limited
Fixed
The tool used to assist in making project trade-offs between schedule, budget,
and performance objectives is called a
Responsibility matrix
A)
Work breakdown structure
B)
Project priority matrix
C)
Work package
D)
Criterion matrix
E)
10
11
12
13
14
If a project is small or of narrow scope and does not require an elaborate system,
which of the following is a good choice?
Responsibility matrix
A)
B)
C)
D)
E)
15
Janet is forecasting how much money her department needs to support a new
project. She estimates that two people and $25,000 in expenses will cover her
needs. Because management typically insists on reducing forecasts by 20
percent, she increases her estimates to allow for that reduction. Which of the
following factors is illustrated in this situation?
Padding estimates
A)
Planning horizon
B)
Project structure
C)
People
D)
Organization culture
E)
Top-down estimates are most likely to occur during the ______ phase.
Concept
A)
Planning
B)
Execution
C)
Delivery
D)
All of these are equally likely
E)
Sean is forecasting the time and cost of developing a customized software
program by looking at the number of inputs, outputs, inquires, files, and
interfaces. Which of the following methods is he using?
Ratio
A)
B)
C)
D)
E)
Template
Apportion
Function point
Learning curve
Learning curves are more likely to apply in situations where most of the costs are
Materials
A)
Labor
B)
Overhead
C)
Evenly spread over materials, labor, and overhead
D)
All of these are equally likely situations for learning curves
E)
The approach that begins with a top-down estimate for the project and then
refines estimates as the project is implemented is known as ______ method.
Function point
A)
Template
B)
Learning curve
C)
Phase estimating
D)
Apportion
E)
The cost to prepare bottom-up estimates will typically run how much more than
the costs to prepare the top-down estimates?
About the same
A)
About twice as much
B)
About three times as much
C)
About four times as much
D)
About five times as much
E)
Project costs are typically viewed from all of the following except:
Scheduled
A)
Sunk
B)
Actual
C)
Committed
D)
All of these are correct
E)
10
Which of the following is not one of the recommended guidelines for developing
useful work package estimates?
Estimates should be made by those responsible for the work
A)
B)
C)
D)
E)
11
Reasons why estimating time and cost are important include all of the following
except:
To schedule work
A)
To determine how long the project should take and cost
B)
To develop cash flow needs
C)
To determine how well the project is progressing
D)
All of the above are valid reasons
E)
12
The bottom-up approach for estimating times and costs that uses costs from past
projects that were similar to the current project is known as:
Detailed WBS work package estimates
A)
Template method
B)
Function point method
C)
Time-phased cost estimates
D)
Phase estimating
E)
13
Which of the following top-down methods is used when projects closely follow
past projects in features and costs and result in costs being assigned by
percentages to major segments of the project?
Apportion
A)
Function point
B)
Phase estimating
C)
Learning curve
D)
Consensus
E)
14
15
Design flaws being revealed after the fact, extreme weather conditions, and
accidents occurring are examples of:
Hidden interaction costs
A)
Things going wrong on a project
B)
Normal conditions not applying
C)
Changes in project scope
D)
None of these are correct
E)
Which of the following is provided by a project network but not by the work
breakdown structure?
Dependencies
A)
Sequencing
B)
Interrelationships
C)
Both A and B are correct
D)
A, B, and C are all correct
E)
E)
Milestone
Which of the following is not one of the basic rules to follow when developing
project networks?
An activity cannot begin until all preceding activities have been
A)
completed
Each activity must have a unique identification number
B)
Conditional statements are allowed but looping statements are not
C)
allowed
An activity identification number must be larger that that of any
D)
preceding activities
Networks flow from left to right
E)
10
11
12
The amount of time an activity can be delayed and yet not delay the project is
termed
Total slack
A)
Free slack
B)
Critical float
C)
Float pad
D)
E)
Slip pad
13
14
15
INCORRECT