Public Transport Capacity Analysis Procedures
Public Transport Capacity Analysis Procedures
JACK REILLY
HERBERT LEVINSON
The Transport Research Support program is a joint World Bank/ DFID initiative
focusing on emerging issues in the transport sector. Its goal is to generate
knowledge in high priority areas of the transport sector and to disseminate to
practitioners and decision-makers in developing countries.
CONTENTS
ACKNOWLEDGEMENTS ......................................................................VIII
1
1.1
1.2
1.3
1.4
1.5
OBJECTIVES ...................................................................................................... 13
AUDIENCES ...................................................................................................... 13
APPLICATIONS .................................................................................................. 13
USING THE MANUAL ......................................................................................... 14
MANUAL ORGANIZATION ...................................................................................15
2
2.1
2.2
2.3
2.4
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14
3.15
3.16
3.17
3.1
3.2
3.3
3.4
3.5
INTRODUCTION ............................................................................. 11
INTRODUCTION ................................................................................................ 24
OPERATING EXPERIENCE ................................................................................... 24
BUS SERVICE DESIGN ELEMENTS AND FACTORS .................................................... 24
OVERVIEW OF PROCEDURES ................................................................................27
OPERATION AT BUS STOPS ................................................................................ 30
3.5.1Berth (Stop) Capacity Under Simple Conditions .........................................31
BUS BERTH CAPACITY IN MORE COMPLEX SERVICE CONFIGURATIONS .......................35
STOP DWELL TIMES AND PASSENGER BOARDING TIMES ......................................... 38
CLEARANCE TIME ............................................................................................. 41
CALCULATION PROCEDURE ................................................................................ 42
VEHICLE PLATOONING ...................................................................................... 43
VEHICLE CAPACITY ........................................................................................... 45
PASSENGER CAPACITY OF A BUS LINE ................................................................. 48
TRANSIT OPERATIONS AT INTERSECTIONS............................................................ 49
3.13.1Curb Lane Operation ............................................................................. 49
COMPUTING BUS FACILITY CAPACITY................................................................... 52
MEDIAN LANE OPERATION ................................................................................ 52
CAPACITY AND QUALITY REDUCTION DUE TO HEADWAY IRREGULARITY .....................53
3.16.1Capacity Reduction ................................................................................53
3.16.2Extended Wait Time Due to Headway Irregularity .................................. 54
3.16.3Travel Times and Fleet Requirements ..................................................... 55
TERMINAL CAPACITY ......................................................................................... 58
iii
4
4.1
4.2
4.3
4.4
4.5
4.6
INTRODUCTION ................................................................................................ 64
OPERATING EXPERIENCE ................................................................................... 64
DESIGN CONSIDERATIONS ................................................................................. 64
OVERVIEW OF PROCEDURES ............................................................................... 66
LINE CAPACITY................................................................................................. 68
4.5.1General Guidance ................................................................................... 68
4.5.2Running Way Capacity ........................................................................... 68
LINE PASSENGER CAPACITY ................................................................................75
4.6.1Passenger Capacity .................................................................................75
5
5.1
5.2
5.3
5.4
5.5
5.6
LIST OF TABLES
Table 2-1: Summary of Transit Vehicle and Passenger Capacity Estimate ............................................... 17
Table 2-2 Maximum and Schedule Capacity ........................................................................................... 20
Table 3-1: Hourly Passenger Volumes of High Capacity Bus Transit Systems in the Developing World ... 25
Table 3-2: Transit Design Elements and Their Effect on Capacity ........................................................... 26
Table 3-4: CAPACITY Assessment of Existing BRT Line ...........................................................................27
Table 3-5: Capacity Assessment of a Proposed BRT Line ........................................................................ 29
Table 3-6: Z-statistic Associated with Stop Failure Rates ....................................................................... 32
Table 3-7: Bus Berth Capacity (uninterrupted flow) for a Station with a Single Berth ...............................33
Table 3-8: Actual Effectiveness of Bus Berths ......................................................................................... 34
iv
vi
LIST OF FIGURES
Figure 3-1Incremental Capacity of a Second Bus Berth: ...........................................................................35
Figure 3-3: Plan View of Transmilenio Bus Station .................................................................................. 36
Figure 3-4: Speed vs. Frequency ............................................................................................................. 56
Figure 4-1: Boarding Time As a Function of Railcar Occupancy ................................................................70
Figure 4-2: Minimum Train Separation .................................................................................................... 71
Figure 4-3: Train Turnaround Schematic Diagram .................................................................................. 74
Figure 5-1" Interrelationship Among Station Elements ........................................................................... 79
Figure 5-2: Walking Speed Related to Pedestrian Density ...................................................................... 81
Figure 5-3: Pedestrian Flow Rate Related to Pedestrian Density ............................................................. 82
Figure 5-4: Rail Station Example............................................................................................................ 117
vii
ACKNOWLEDGEMENTS
The authors would like to acknowledge the contributions of a number of
people in the development of this manual. Particular among these were Sam
Zimmerman, consultant to the World Bank and Mr. Ajay Kumar, the World
Bank project manager. We also benefitted greatly from the insights of Dario
Hidalgo of EMBARQ. Further, we acknowledge the work of the staff of
Transmilenio, S.A. in Bogota, especially Sandra Angel and Constanza Garcia
for providing operating data for some of these analyses.
A number of analyses in this manual were prepared by students from
Rensselaer Polytechnic Institute. These include:
Case study Bogota
Case Study Medellin
Simulation modeling
Ivan Sanchez
Carlos Gonzalez-Calderon
Felipe Aros Vera
Brian Maleck
Michael Kukesh
Sarah Ritter
Platform evacuation
Kevin Watral
Sample problems
Caitlynn Coppinger
Vertical circulation
Robyn Marquis
Several procedures and tables in this report were adapted from the Transit
Capacity and Quality of Service Manual, published by the Transportation
Research Board, Washington, DC.
viii
1 I NTRODUCTION
Specific measures of the pattern of travel demand over the day (e.g.,
peaking characteristics) may vary in different countries.
1.1 O BJECTIVES
The objectives of this work are:
As such, the document and its procedures will be incorporated into the
curricula of the World Banks urban transport capacity building program and
serve as a resource for the capacity building efforts of the Banks partners.
1.2 A UDIENCES
It is expected that the primary audience for this document are public transport
planning and design practitioners, academics and researchers in developing
countries. Secondarily, it serves the same functions for academics and
researchers and to a certain extent, practitioners in the developed world.
1.3 A PPLICATIONS
This document is useful for both planning, design and systems analysis
purposes. The tables and procedures from this document can enable a
transportation system planner to scale each element of a rail or an enhanced
bus transportation system to the design passenger load for the system. In this
context, it is assumed that a transportation system of known required
13
The techniques for assessing bus rapid transit systems differ from those from a
rail system. Therefore, each is discussed separately.
The specific factors of the transit services that influence capacity included in
this work, irrespective of mode are:
14
1.
2.
3.
4.
5.
6.
7.
15
16
the maximum number of vehicles per transit unit (buses or rail cars),
The equations and guidelines shown in table 2.1 show how these factors can
be quantified. Further details are shown in subsequent sections.
T ABLE 2-1: S UMMARY OF T RANSIT V EHICLE AND P ASSENGER C APACITY E STIMATE
3600
headway
green
cycle
passengers
vehicle
vehicles
unit
(Eq. 2.1)
green
cycle
(dwell
time
dwell time
variance
clearance time)
(Eq.2.2)
operating margin
Source: H. Levinson
Use peak 15 minute passenger flow rather than peak hour flow rates
since ridership demand is not uniform over an entire peak period.
Fifteen minute flow rates can be obtained by direct measurement.
Commonly a peak hour factor is often used. This factor represents
the ratio of the hourly observed passenger volume to the peak 15
minute period time 4. It is a measure of the dispersion of riders about
the peak period.
The appropriate design volume for transit systems should be the peak
15 minutes since designing for the average over the peak hour will
result in operationally unstable service during peak intervals within
the peak period which have a disproportionate share of travel.
In some large urban areas, there is little variation in ridership over the
peak period. This suggests that the ridership is constrained by
capacity. Where possible, increased capacity should be provided.
18
2.2.1 T H E O R E T IC A L
VS .
P R AC T IC AL O PE R AT I NG C AP AC I T Y
F
Crush
capacity
E
Vehicle capacity
(veh./hr.)
Schedule
capacity
Peak
Scheduled
Capacity
Domain
D
E
Schedule
Maximum
capacity
capacity
Running way capacity (veh./hour)
The user is cautioned against designing a transit service in which the capacity
is just sufficient enough to meet expected peak passenger volumes. Transit
operations are characterized by various random events, many of which are not
in the direct control of operators particularly in bus operations. Operating at or
near capacity leaves the operator little margin to respond to such events
without substantial service disruption.
The purpose of measuring capacity is not just to provide a measure of system
capability to transport passengers but also to provide some insight into the
effect of service and physical design on customer service quality. When the
demand for a service exceeds its schedule design capacity, service quality
deteriorates either due to overcrowding on vehicles or at station platforms or
diminished ability of customers to board the next arriving transport vehicle
since it is already fully loaded, increased dwell times and hence decrease
revenue speeds. A more useful measure of service performance than capacity
from the customer perspective is the comfort level on vehicles which is usually
a function of the ratio of customers to vehicle capacity or available space per
passenger.
20
where passengers arrive randomly at stops, the customer waiting time when
arrivals between vehicles are uniform is one-half of the headway. However,
when this uniform interval is disrupted by factors such as intersection delay, or
variability in time spent at bus stops, the average waiting time is increased.
The time variability at stops and in the case of buses at intersections, also
results in variations in the travel times of customers already on the vehicle.
While some factors that introduce randomness are beyond the control of
transit operators, variation in time can be minimized through better service
design, scheduling practices and street operations management. Traffic signal
priority, exclusive bus lane enforcement, more efficient fare collection, better
station design and headway based scheduling are examples of such measures.
Poor reliability has consequences for both customers and operators. A service
with poor day-to-day requires riders to add buffer time to their planned
departure time to account for the probability of late arrivals of buses and trains
and variation in travel speeds. As such, a more reliable service, all other things
being equal has value to customers. Reliability also has an effect on in-vehicle
passenger comfort. Variation in the headway of scheduled vehicles results in
irregular loading patterns of vehicles and diminishes effective capacity. On
high frequency bus services, particularly where scheduled headway is nearly
the same as the traffic signal cycle length at critical intersections, there is a
tendency for buses to bunch and travel in platoons. Grade separated transit
generally has better reliability than transit vehicles subject to street traffic
interference.
While this does not diminish the theoretical capacity, it does reduce the
practical or effective capacity. This is because with headway intervals longer
than the scheduled headway, the number of customers arriving at a stop
between successive buses will exceed the design arrival rate for some of the
buses, resulting in overcrowding,
Conversely, vehicles arriving at intervals shorter than the design headway will
be underloaded. This load imbalancing deteriorates customer service quality
and operators add vehicles to compensate for this. Further, reliability has
another impact on operating costs. Schedule recovery time must be build
into vehicle and crew schedules so that delays do not accumulate over the
course of a peak period or day.
These result in the need for more vehicles to provide the same service
frequency and capacity. improvements in reliability also result in reductions in
schedule recovery time and hence on the number of vehicles/drivers and
mechanics required to carry a given number of people. For the purposes of
this report, procedures to improve reliability such as reduction of dwell time
variability, will be introduced not only so that reliability itself can be improved
but also as a means of improving comfort levels and reducing operating costs.
22
AND
C OST
23
3 B US S YSTEM C APACITY
3.1 I NTRODUCTION
Bus rapid transit (BRT) systems are increasing in importance and use in cities
throughout the developing world. They can be implemented quicker than rail
rapid transit and may cost substantially less even in total life cycle cost terms.
They can also serve as a precursor to future rail systems.
This chapter provides guidelines for estimating the capacity of BRT lines. It
overviews existing operational experience, describes the design and operating
factors that influence capacity, sets forth procedures for estimating bus
vehicles and passenger capacities and presents additional analyses related to
bus operations, service quality and capacity.
BRT, in contrast with rail rapid transit operates in a variety of environments. It
may run on segregated, fully grade separated running ways, e.g., in reserved
freeway lanes railroad rights of way, or in arterial street median busways or
single or dual curbside bus lanes. Sometimes, buses may have to operate in
mixed traffic environment. From a capacity perspective, operation through
traffic signal controlled environments is common.
T ABLE 3-1: H OURLY P ASSENGER V OLUMES OF H IGH C APACITY B US T RANSIT S YSTEMS IN THE D EVELOPING W ORLD
Region
City
Peak Volume
(pphpd)*
Asia
Ahmedabad
Beijing
Guanzhou
Hangzhou
Jakarta
Jinan
Seoul
3,000
4,100
25,000
6,600
4,000
3,600
6,700
Latin America
Belo Horizonte
Bogota
Curitiba
Mexico City
Porto Alegre
Sao Paulo
Quito
16,000
45,000
14,000
9,000
26,100
20,000
8,000
Africa
Lagos
*pphpd passengers per hour per direction
10,000
1.
2.
3.
Bus boarding area factors such as bus stop length and width, number
of berths, approach to assignment of multiple routes to boarding
berths, availability of passing lanes and platform height in relation to
floor height.
25
4.
5.
These elements are discussed separately and the effect of changes on service
quality and capacity is augmented with empirical tables. Essentially, the
capacity of a route in passengers per period per direction is a product of the
running way capacity (vehicles per hour per direction) and the vehicle capacity
(passengers per vehicle). Error! Reference source not found. illustrates how
the design decisions affect the components of system capacity.
Time at
Intersections
Time
Moving
Vehicle
Capacity
X
X
X
X
X
X
X
X
X
X
X
X
26
Passing capability
Pedestrian behavior
X
X
Other policies
Lane enforcement
Loading standard
Traffic law enforcement
Intersection characteristics
Traffic signal cycle times
and splits
Phases
Turn restrictions
Pedestrian flows and
behavior
X
X
X
X
X
X
illustrate procedures for assessing the capacity of existing and proposed BRT
lines respectively. These tables also show ways of increasing vehicle capacity.
T ABLE 3-3: CAPACITY A SSESSMENT OF E XISTING BRT L INE
28
The distribution of dwell times at the critical stop in a transit system can limit
the number of vehicles per hour that can pass through the station.
Accordingly, measures that reduce the dwell time or dwell time variation can
2
The critical stop is the one in which the mean plus two standard deviations of the dwell time is
maximum.
30
3.5.1 B E R T H (S T O P ) C AP AC IT Y U N DE R S IM P LE C O ND IT IO NS
3 .5 .1 .1 L O A D I N G B E R T H D Y N A M I C S A N D C A P A C I T Y
For this discussion, it is assumed that there is a single route serving the bus
stop so that passengers can select any arriving bus to travel to their
destination and further there is a single boarding location at the bus stop.
Given the variation in arrival rates of buses and the dwell (service) times of
buses, there is a possibility that an arriving bus will not be able to immediately
access the stop. If the arrival and service time distributions are know with any
precision, the probability of delay due to bus berths being occupied, referred
to as the failure rate, can be computed. Transit planners can reduce this rate
by reducing the mean or variability of the service time, increasing the headway
or reducing the headway variance. Alternatively, the number of bus berths can
be increased.
The operating margin (tm) is defined as:
tm = s Z = cv td Z
(Eq. 3.3)
Where,
tm = operating margin (sec)
s = standard deviation of dwell times
Z = the standard normal variable corresponding to a specific failure rate (onetailed test)
cv = coefficient of variation (standard deviation/mean) of dwell time; and
31
Acceptable Failure
Rate
1%
5%
10%
Z -statistic
2.326
1.645
1.282
There is a tradeoff between the failure rate and the berth capacity. A high
operating margin is required to assure that the failure rate is tolerable. One
method is to specify a failure rate and through actual observation of mean and
standard deviation of dwell time, estimate the capacity of the stop. At
reasonable failure rates, this value represents the practical sustainable
capacity. The maximum theoretical capacity will occur at a failure rate which
may be unacceptably high.
3 .5 .1 . 2 B E R T H C A P A C I T Y W I T H U N I N T E R R U P T E D F L O W
The capacity of a bus berth in vehicles per hour can be estimated by the
following equation:
B = 3600/(td + tm + tc)
(Eq. 3.1)
Where,
B = berth capacity in buses per hour
td = mean stop dwell time
tm = operating margin
tc = clearance time, (the time for stopped buses to clear the station, minimum
separation between buses, and time to re-enter the traffic stream
3 .5 .1 . 3 C A P A C I T Y F O R S T O P S N E A R S I G N A L I Z E D I N T E R S E C T I O N S
The maximum flow capacity at a bus stop near a signalized intersection in
vehicles per hour is:
Bl = 3600(g/C)/(td(g/C) + tm + tc)
(Eq. 3.2)
Where,
Bl = buses per berth per hour
g = green time at stop
32
Dwell Time
Mean (sec.)
10
20
30
40
50
60
70
80
90
Dwell Time
Coefficient of Variation
0.3
0.6
144
90
65
51
42
36
31
27
24
120
72
51
40
32
27
24
21
19
St. Jacques, K.R. and Levinson, H. S. TCRP Report 26, Operational Analysis of Bus Lanes on
Arterials, TRB, national Research Council, Washington, DC 1997.
33
buses to pass each other, then the efficiency of successive berths beyond the
first will be diminished. That is, doubling the number of berths will not double
the effective capacity. Simulation studies, augmented by empirical data found
the following relationships (Error! Reference source not found.) between the
number of berths and the capacity of the multi-berth stop.
Some cities, especially in South America, provide bypass lanes around stations
on median arterial busways. The service pattern should be analyzed. The
capacities should be computed for the busiest stop for each group of buses.
For example, if stop A can accommodate 80 buses per hour and stop B can
accommodate 100 buses per hour, the system capacity would be the sum
assuming that different buses serve each stop.
T ABLE 3-7: A CTUAL E FFECTIVENESS OF B US B ERTHS
On-Line Station
Off-Line Station
Number
Effectiveness of
Total Effectiveness of
Total
of Berths
Berth
Effectiveness* of
Berth
Effectiveness* of
all Berths
all Berths
1
1.0
1.00
1.00
1.00
2
.75
1.75
.85
1.85
3
.70
2.45
.80
2.65
4
.20
2.65
.65
3.25
5
.10
2.75
.50
3.75
*Ratio of the capacity of the number of berths to a single berth.
(Source: Research Results Digest 38, Operational Analysis of Bus lanes on Arterials, Transportation Research Board.
Using observed data from Barcelona, Spain, Estrada et al., (2011) determined
that the incremental capacity of a second loading berth was a function of the
standard deviation of dwell time and developed the chart below to assess this
value.
34
Example: A transit route at the critical stop has a mean dwell time of 30 seconds with a coefficient of
variation of 0.3. Compute the capacity of the system in vehicles per hour if 3 bus bays are provided. Note
that there are no passing lanes at the bus stop.
Capacity of single stop berth = 87
Effectiveness of first three berths (on-line) = 2.45
Capacity of 3 bus berths (on line) = 87 * 2.45 =213 buses per hour
35
In the figure berth 2 has a queuing space behind it in the boarding lane.
Boarding and discharging is not done in the queuing space. The queuing space
can be accessed from the bypass lane. The set of routes assigned to berth 1 is
distinct from the routes assigned to berth 2.
In order to present a set of tools to analyze this and other situations, a set of
simulation models was developed to determine the capacity of the following
four configurations:
Single loading berth no queuing space
Single loading berth queuing space for one bus
Dual loading berth no queuing space
Dual loading berth queuing space for one bus
Capacity was defined for several acceptable failure rates including (5%, 10%
and 25%) with the failure rate being defined as the probability that an arriving
bus will not be able to enter either a vacant berth or a queuing space. Other
variables in each of these assessments included mean service time with values
4
of 20, 20, 40, 50, 60 and 75 seconds . The final two input variables were service
time variability and arrival rate variability. To simplify the assessment, these
two variables were staged as either high or low. Definitions are shown in the
table below.
T ABLE 3-8: S ERVICE V ARIABILITY L EVELS
Input
Service time variability
Headway variability
Level
Low
High
Low
High
Definition
CV* = 0.4 times mean service time
CV = 0.8 time mean service time
CV = 0.4 times mean headway
CV = 0.8 time mean headway
The term service time is used in these calculations. Service time includes the dwell time (time the
bus is stopped) as well as the safe separation time between successive vehicles about 12 seconds.
36
This analysis resulted in the development of 8 tables two for each of the four
service domains described above and the presence or absence of a traffic
signal at the station. These are shown in tables 3-22 through 3-29. A summary
table appears in Error! Reference source not found. These tables require
relatively little data collection effort to estimate station capacity. On high
volume BRT services, mean service times can be obtained with about an hours
worth of observations. A similar length of time would enable a determination
of low or high values of service time and headway variability. These data are
for articulated (18m) buses. Non-articulated (13 m) buses are likely to increase
capacity slightly since the time for the bus to clear the station is about 5
seconds less. Conversely, a bi-articulated bus takes 7-8 seconds to clear the
station.
The determination of an acceptable failure rate is more complex. In cases
where some buses bypass certain stops, the inability of buses serving the stop
to access either the berth or the queuing area may result in blocking through
buses. In such cases a low failure rate of about 10% is suggested. In high
volume cases, a high failure rate may result in a queue which may not dissipate
for a long time, perhaps as much as several minutes. The photograph (Error!
Reference source not found.) below shows a long queue at a TM stop.
Fortunately, this dissipated within 2 minutes.
T ABLE 3-9: T RANSMILENIO S TATION (B OGOTA ) W ITH L ONG Q UEUE
37
T ABLE 3-10: B US B ERTH C APACITY ( UNINTERRUPTED FLOW ) FOR A S TATION WITH A S INGLE B ERTH
Berths
1
1
1
1
2
2
2
2
Queue
Space
Yes
Yes
No
No
Yes
Yes
No
No
Traffic
Signal*
Yes
No
Yes
No
Yes
No
Yes
No
30
60
60
35
45
80
80
60
80
40
45
50
30
40
55
65
50
65
50
35
40
25
30
40
50
40
50
60
25
25
20
20
40
45
30
35
75
25
25
15
15
35
35
25
30
Table entries are capacities in vehicles per hour with a failure rate of 10% with moderate service time
variation and moderate headway variation. In this table, dwell time includes time to enter the stop, and
time to depart the stop. This is about 15 seconds.
* If yes, green to cycle time ratio is 0.5
Situation
Boarding
Pre-payment*
Single ticket or token
Exact change
Swipe or dip card
Smart card
Observed
Range
Suggested
Default
2.2-2.8
3.4-3.6
3.6-4.3
4.2
3.0-3.7
2.5
3.5
4.0
4.2
3.5
38
Alighting
Front door
Rear door
2.6-3.7
1.4-2.7
3.3
2.1
* includes no fare, bus pass, free transfer, pay on exit and off-board payment rear door boarding.
Add 0.5 sec./pass to boarding times when standees are present.
Subtract 0.5 sec./pass from boarding times and 1.0 sec./pass. from front-door alighting times on low floor
buses.
Source: Transit Capacity and Quality of Service Manual
The stop dwell time is also influenced by customer discipline and operating
practices. With on-board driver-controlled fare collection, boarding customers
enter through the front door and ideally exit through the rear door. In practice,
however, several passengers exit through the front door. This delays boarding
passengers and sometimes extends dwell times. The critical door capacity
calculation must take this into account.
Off board or conductor-controlled fare collection allows for multiple door
boarding and alighting and can reduce stop dwell times.
The common method for estimating dwell time requires as an input the
expected value and distribution of number of boarding passengers at each
stop. This is captured in the following equation:
td = Pata + Pbtb + toc
(Eq. 3.4)
where:
td
Pa
ta
Pb
tb
toc
Example: At a busy bus stop with off-board fare collection, the design number of boardings is 12 and the
design number of alightings is 14. There are two single stream doors, and customers use each equally for
boardings and alighting. Assume door opening and closing time is 2 seconds. Compute the expected
dwell time for this stop.
td = Pata + Pbtb + toc
= (6 * 3.3) + (7 * 3.3)+ 2 = 45 seconds
39
Fernandez et al (2007) proposed a formulation for dwell times using data from
TranSantiago. Two models were calibrated one for BRT trunk buses and the
other for feeder buses. On the BRT buses passenger fares were collected
through contactless smart cards through the front door. The feeder fares were
collected through conventional fare technology.
For the BRT routes, the model was of the form:
td = 9.32 + max j=door((2.05 + .88d1)Bj + (3.32 1.93d2)Aj
where,
td
dwell time
d1
Bj
d2
Aj
Loosely interpreted, there is a 9.3 second time for door opening and closing.
For each boarding customer, the time is 2.05 seconds unless the boardings at
the stop exceed 40. Similarly the discharge rate is 3.32 seconds per customer
unless the discharge rate exceeds 15, in which case the rate reduces by 1.93
second per customer. For the feeder routes, the model was
td = 8.04 + max j=door((3.82 + .88d1)Bj + (3.32 1.93d2)Aj
where,
d1
d2
These models have reasonably good explanatory power with the R (the
proportion of variation in dwell times explained by the model) being 0.84 and
0.72 for the trunk and feeder buses respectively. Additional research in this
area is warranted, particularly in determining the effect of crowded buses on
dwell time.
Predictive models of dwell time which use boarding and alighting data have
limited utility in the planning and design of new services since travel demand
forecasting models do not explain boardings and alightings by individual trip.
Further, in high capacity bus rapid transit systems, the mean dwell time is
more a function of the physical design of station and vehicle elements such as
doorway width, fare collection scheme and the difference in height between
the bus floor and the boarding platform. Some limited data on dwell time of
the high capacity bus rapid transit service in Bogota, Colombia is shown in
40
Error! Reference source not found. below. The Transmilenio system has high
floor buses, level loading platforms at stations, off-board fare collection and
articulated buses with three loading doors each capable of accommodating
two parallel boarding streams. This mode of operation was designed
specifically to minimize mean dwell time.
T ABLE 3-12: S TOP D WELL T IME B OGOTA T RANSMILENIO
Stop
Time
Period
Calle 100
AM Peak
Calle 72
Mean
(sec.)
Coefficient of
Variation
24
Standard
Deviation
(sec.)
17
PM Peak
22
14
0.64
AM Peak
19
15
0.79
PM Peak
20
10
0.50
0.71
Source: Transmilenio, SA
41
Adjacent Lane
Volume
(veh/hr)
100
200
300
400
500
600
700
800
900
1000
Average
Re-entry
Delay
(sec)
1
2
3
4
5
6
8
10
12
15
(Eq. 3.5)
Where,
Bs
Bl
Nel
3,600
g/C
time)
tc
td
Z
= standard normal variable corresponding to a desired failure
rate (one-tailed test)
42
cv
Example: Compute the capacity of a bus stop with two in-line berths where the average dwell time is 40
seconds with a coefficient of variation of 0.3 and the g/C ratio is 0.5. Assume 500 cars per hour in the
adjacent lane and the tolerable failure rate is 5%.
Bs = NelBl =Nel (3600*(g/C))/(tc + td(g/C) +Zcvtd)
Nel =1.75
g/C = 0.5
tc = 5 seconds (from table x) plus 10 seconds equal 15 seconds
td = 40 seconds
cv = 0.3
Z = 1.645 (one-tailed z-statistic associated with 5% failure rate)
Bs = 1.75* ((3600 * .5)/(15 +(40 * 0.5)+ (1.645*0.3*40))=46 buses per hour
Bl
Nel
=
of two buses
3,600
g/C
=
green time ratio (ratio of effective green time to cycle time.
This equals 1.0 for unsignalized intersections)
tc
td
=
mean dwell time (sec.) (This is the dwell time associated with
the route with the highest number of passenger transactions in cases where
the platoon serves two routes.)
Z
= standard normal variable corresponding to desired failure rate (one
tail) ; and
cv
Example: Compare the capacity in vehicles per hour of a two berth bus stop with platooning and nonplatooing of arriving buses if the dwell time mean is 30 seconds and the standard deviation is 10 seconds.
Assume a 5% permitted failure rate, a non-signalized intersection and a 10 second clearance time.
Platooned arrival:
Note: cv = standard deviation/mean
Therefore, cvtd = standard deviation
Bs = NelBl = Nel 3,600(g/C)/(tc + td(g/C)+Zcvtd)
=(1.85 * 3600)/(20 + 30 (1) + (1.645 * 10)) = 100 buses per hour
Non platooned arrival (no passing):
Bs = NelBl = Nel 3,600(g/C)/(tc + td(g/C)+Zcvtd)
=(1.75 * 3600)/(20 + 30 (1) + (1.645 * 10)) = 95 buses per hour
44
Table 3.11 provides some typical values of bus capacity at a stop with multiple
berths. In the table the assumed failure rate is 5% and the clearance time is 10
seconds.
T ABLE 3-14: S TOP C APACITY FOR M ULTIPLE B ERTH S TOPS AT V ARIOUS D WELL T IME L EVELS
Bus Berths
Dwell
Time
(sec.)
Coefficient of
Variation of
Dwell Time
20
0.3
93
162
20
0.6
76
132
30
0.3
68
30
0.6
54
40
0.3
0.6
40
204
255
278
166
208
227
118
149
186
203
95
119
149
163
53
93
117
146
160
42
74
93
116
127
Manufacturer
Model
Floor
Height
Ashok Leyland
222
Volvo
Tata
Length
(m)
Seating
Capacity
Standing*
Capacity
High
10.9
50
20
Articulated bus
High
16
52
20
8700
Low
12
40
N/A
8700
Low
13.5
45
N/A
8700
Low
15
53
N/A
8700
High
12
53
N/A
8700
High
13.5
55
N/A
STAR ULF
Ultra
low
Low
12
27
35
12
44
35
STAR LF
* Manufacturers estimate
For planning purposes, the standee density standard would be the amount of
space each standee would be assigned to allow an acceptable level of
crowding across an average peak hour. For crush design purposes, the
density would correspond to the peak fifteen minutes. In either case, this is a
policy standard that reflects social norms and available resources. It also
reflects the type of service provided and the nature of the market. The longer
that people must stand (e.g., for on long distance CBD-oriented commuter
services), the more space generally assigned to each standing passenger
Typical standards for urban bus and rail services are shown in Error!
Reference source not found. below.
T ABLE 3-16: U RBAN B US AND R AIL L OADING S TANDARDS
Place of Application
Typical Number of
Standees per Square
Meter
EU
4-5
US, Canada
3-4
6-8
Asia
8-10
A generalized formula for the capacity of a bus given its geometry, door and
seating configuration and acceptable loading standard is as follows:
Vc = (L -1)*(W-0.2) (0.5DnWsDw) + (1- Sa/Ssp)N((L-1)-Dn(Dw+2Sh)
Ssp
Sw
Where,
Vc =
L =
W=
Dn =
Number of doorways
Ws=
Dw =
Sa =
longitudinal]
Ssp =
46
N=
Vehicle arrangement
Sb =
door) [0.2 m]
Error! Reference source not found. below shows typical capacities for a range
of bus types (single unit, articulated and bi-articulated) and loading standard.
In each case, the assumed number of doors is 2 for single unit, 3 for articulated
and 4 for bi-articulated buses. The first table is for transverse seating, while the
second is for longitudinal (peripheral) seating.
T ABLE 3-17: B US V EHICLE C APACITY
Transverse Seating
Bus type
single
articulated
bi-articulated
Doorways
Length (m)
Standees/sq. m.
4
5
6
7
8
2
13
3
20
4
25
80
87
94
101
109
126
137
148
158
169
160
174
188
203
217
Longitudinal Seating
Bus type
single
articulated
bi-articulated
Doorways
Length (m)
Standees/sq. m.
4
5
6
7
8
2
13
3
20
4
25
86
97
108
120
131
136
153
170
188
205
172
194
217
239
262
The passenger capacity of a bus depends on its seating configuration and the
allowable loading design standard. The use of low-floor buses complicates the
analysis since in low floor buses, vehicle wheel wells and internal stairs reduce
passenger capacity.
47
(Eq. 3.8)
Where,
C
Bl
Nel
3,600
g/C
time)
tc
td
Z
= standard normal variable corresponding to a desired failure
rate (one-tailed test)
cv
48
Example: Compute the line capacity of a bus line with three in-line berths at the critical stop where the
average dwell time is 200 seconds with a coefficient of variation of 0.3 and the critical g/C ratio is 0.6.
Assume a 10 second clearance time and the tolerable failure rate is 5%.
Bs = VNelBl =Nel (3600*(g/C))/(tc + td(g/C) +Zcvtd)
V = 80 passengers
Nel =2.45 (from table 3.x)
g/C = 0.5
tc = 10 seconds
td = 20 seconds
cv = 0.3
Z = 1.645 (one-tailed z-statistic associated with 5% failure rate)
C = 80* 2.45* ((3600 * .6)/(10 +(20 * 0.5)+ (1.645*0.3*20))=14,100 passengers per hour
3.13.1 C U R B L A N E O P E R AT IO N
Traffic conflicts at signalized intersections can impede bus movements when
the green per cycle time is limited and/or when right turns from or across the
bus lane conflict with through buses. The delay can constrain bus capacity
where right turn volume conflicts with heavy pedestrian movements. The
result is reduced capacity in the curb or interior bus lane.
3 .1 3 . 1. 1 S C R E E N I N G F O R R I G H T T U R N C O N F L I C T S
The impact of pedestrian-right turn conflicts on curb bus lane capacity may call
for restricting the right turns, or possibly grade separating the conflicting
pedestrian movement. A simple method to assess these effects is set forth in
TCRP Report 90 Bus Rapid Transit Implementation Guidelines. A more
detailed method is available in the Transit Capacity and Quality of Service
Manual at page 4-48.
49
The simplified method assumes each pedestrian channel takes a specified time
to cross the area in which there is a conflict with right turns; in effect, each
pedestrian delays each right turn by this time. The time lost can be estimated
by weighing the time per pedestrian by the number of pedestrians and right
turns per signal cycle. The green time which is lost due to pedestrian-right turn
conflicts can then be approximated by the following equation:
t = rpts/L
(Eq. 3.9)
Where,
t = green time to be gained per cycle,
r = right turns/cycle (peak 15 minutes)
p = conflicting pedestrians/ cycle (peak 15 minutes)
ts = time per pedestrian (e.g. 3 or 4 seconds), and
L = number of pedestrian channels in crosswalk (e.g., 1 to 4)
The lost time per cycle is deducted from the green time per cycle. If the
remaining effective green time is less than 25% of the cycle time, then the turn
conflicts will not impede operation of the curbside bus lane.
Estimated lost time per signal cycle by conflicting right turns and pedestrian
volumes is shown in Table 3.13.
T ABLE 3-18: L OST T IME P ER C YCLE D UE TO R IGHT T URN -P EDESTRIAN C ONFLICTS
1 Lane
2 Lanes
3 lanes
4 Lanes
4
8
12
16
20
24
12
24
36
48
60
72*
6
12
18
24
30
36
4
8
12
16
20
24
3
6
9
12
15
18
For a 60 second cycle, time loss should not exceed 25% of the cycle time or 15
seconds. In the table, the boldface values are not acceptable, and turns should
be prohibited.
50
Example: A curbside bus lane operates at an intersection where the green time per cycle is 50
seconds and the cycle time is 90 seconds. The number of pedestrian crossings per hour 200 and the
number of right turning cars is 120 per hour. Is there sufficient time to operate a curbside lane with
right turning vehicles in the bus lane?
The number of pedestrian crossing per cycle is 5(200/40). The number of right tuning vehicles per
cycle is 3 (120/40). The number of conflicts per cycle is 20. If there are 3 pedestrian lanes and the time
per pedestrian in one channel is 3 seconds then the time lost due to conflicts is 20 (5 * 4 *3/3). The
percentage loss per cycle is 20/90 or 22%. This is less than the 25% threshold, suggesting that the
right turn movement volume is compatible with the curbside bus lane.
3 .1 3 . 1. 2 A D J U S T M E N T F O R M I X E D T R A F F I C I N T H E R I G H T L A N E
The previous procedure provided guidance as to whether the volume of right
turn movements would affect capacity of the bus lane. The actual reduction in
capacity can be computed by applying a mixed traffic adjustment factor to the
estimated lane capacity.
Mixed Traffic Adjustment Factor
where,
fm = mixed traffic adjustment factor (from Error! Reference source
not found.)
fl = bus stop location factor (See table below)
v = curb lane volume (veh/h)
c = curb lane capacity (veh/h) (see table below)
The curb lane capacity is a function of the number of conflicting pedestrians
and the traffic signal g/c ratio and is shown in Error! Reference source not
found.
Type 1
Type 2
Type 3
Near side
0.9
Mid block
0.9
0.7
Far side
0.8
0.5
51
0.35
0.4
0.45
0.5
0.55
0.6
510
580
650
730
800
870
100
440
510
580
650
730
800
200
360
440
510
580
650
730
400
220
290
360
440
510
580
600
70
150
220
290
360
440
800
70
150
220
290
1000
70
150
where,
B = Bus facility capacity (bus/h)
Bl = Bus loading area capacity
Nel = number of effective loading areas
fm = mixed traffic adjustment factor
2.
3.
Buses are not permitted to cross the intersection when left turns or cross
traffic have green indications.
52
(Eq. 3.10)
Where,
fe
cvh
= coefficient of variation of headway (headway standard
deviation/mean headway)
The actual capacity of the route is the product of the vehicle capacity and the
effective frequency. While this is a good framework, there is limited data
available on the factors causing headway irregularity. Evidence indicates that
53
headway variability is low at terminals and increases along the route. The
appropriate method of determining actual system capacity is to review
headway coefficient of variation at the maximum load segment to determine
effective frequency.
Data from the BRT system in Jinan, China which has an exclusive median right
of way, suggest that the coefficient of variation in headway on BRT routes is
high as shown in Error! Reference source not found. below. High frequency
routes in Jinan are very susceptible to headway variation since some traffic
signal cycle times are on the order of 4 minutes, which exceeds the scheduled
headway.
T ABLE 3-21: BRT H EADWAY V ARIATION - J INAN , C HINA
Line number
Headway (min)
Headway cv
3
0.36
3.5
0.54
4.5
0.42
Example: The published frequency of a BRT route is 15 vehicles per hour and the loaded vehicle capacity
is 60. What is the effective capacity if the arrival rate of passengers is uniform and if the coefficient of
variation of headway is about 0.3?
fe
=
=
=
f/(1 + cvh)
15/(1.3)
11.5 vehicles per hour * 60 passengers/vehicle = 690 passengers
3.16.2 E XT E N D E D W A IT T IM E D UE
TO
H E A DW AY I R R E G UL AR IT Y
(Eq. 3.11)
where,
54
average headway
cvh
=
coefficient of variation of headway (headway standard
deviation/mean headway)
There is limited understanding of how the operating environment affects
headway variation. The evidence suggests that measures such as traffic signal
priority at intersections and management of passenger loading can assist in
5
this effort.
Just as in the case of capacity diminution, the headway variability causes
irregular gaps in service and more customers arrive at the stop during longer
gaps.
Example: Compute the average customer wait time at a stop if the headway is 4 minutes with no
variance? What is the average wait time if the headway coefficient of variation is 0.3?
Average waiting time with no variance = h/2 = 4/2 = 2 minutes
Average waiting time with headway coefficient of variation of 0.3 = (h/2)* (1 + cvh)= 2 * (1.3) = 2.6
minutes
3.16.3 T R AV E L T I M E S
AN D
F LE E T R E QU IR E M E NT S
Proper scheduled running times are essential for proper transit operation.
Running times that exceed what is required to maintain schedules result in
higher than necessary operating costs. Excessively tight (lower than optimal)
running times, on the other hand, result in late arrivals at timepoints. If there is
not sufficient schedule recovery time built into driver schedules, inadequate
times can also cause delays in terminal departures on subsequent trips, a key
factor in late arrivals on successive stops. This requires balancing the
requirements for operating efficiency and requirement for sufficient layover
time for schedule recovery and operator breaks.
The BRT running time between terminals will depend on both the length of the
trip and the speed of travel time. The speed or travel time rate depends on the
distance between stops, the time spent at each stop and the number of buses
operating during the design period.
Normally, when bus flows are less than about 50-70 percent of the maximum
line capacity, there is little reduction in operating speeds. Beyond that point,
5
For example, on loaded buses the flow rate of customers onto vehicles is very low. Rather than
wait until all customers are on board, a policy of loading only until the flow rate falls below some
minimum value will probably increase capacity due to reduction of dwell time and dwell time
variability, each of which also influence throughput capacity on a route.
55
however, there is a rapid drop in speeds to about half the free-flowing speed
when the ratio is 0.9 or more. An illustrative example for the Avenue Caracas
corridor in Bogota is shown in figure 3.3.
F IGURE 3-3: S PEED VS . F REQUENCY
30
25
20
15
10
0
0
20
40
60
80
100
120
140
The actual running time for each individual trip can be prepared based on
either observed or archival data. However, preparing schedules in which the
scheduled travel times varies very often throughout the day results in irregular
headways if the number of vehicles assigned is held constant or irregular fleet
assignment patterns if headways are held constant. In actual practice, the
number of time intervals must reflect a balance between accuracy in reflecting
significant predictable variation among trips and portraying a schedule which
is easy to understand by customers and avoids complicated vehicle and
staffing patterns.
The optimal half-cycle time, the scheduled time to travel between terminals
and time allowance prior to departure of the next trip, balances schedule
efficiency, operator layover and schedule recovery. Consider the extreme case
in which there is no variability in terminal to terminal time. In such case, a
sufficient time would be allowed at the end of the bus trip to allow for operator
break. Roughly 10% is allocated to this. On the other hand, for a trip with
considerable variability between days, the objective would be to provide
sufficient time to assure on-time departure on the next trip from the same
terminal. From a simple statistical test, the running time required to assure
56
160
that the probability that there is sufficient time for 90%, 95% or 99% of trips
departing on time can be computed. Specifically, a one-tailed normal test can
be used to make this estimate. The best half cycle time would be the larger of
(1) the times necessary for driver layover and (2) the time necessary for
punctual terminal departure on the subsequent trip. A value of 95% is
appropriate. In plain terms, sufficient time should be allowed to assure that the
probability that the next trip can depart on time is at least 95%.
Mathematically, the appropriate half cycle time is:
tc = max (tm*(1+rd)), tm * (1 + (cv * z)) (Eq. 3.12)
where,
tc = half cycle time
tm = mean terminal to terminal time
rd = driver recovery percent
cv = coefficient of variation of terminal to terminal time
Z = value of unit normal z statistic corresponding to desired probability of ontime departure for the subsequent trip. (Error! Reference source not found.)
T ABLE 3-22: Z- STATISTIC FOR O NE -T AILED T EST
Desired On-time
Probability for next
departure
99%
95%
90%
Z -statistic
2.330
1.645
1.280
Example: The average terminal to terminal time in the morning peak hour is 32 minutes, with a standard
deviation of 0.1 minutes. Compute the half cycle time required to assure both sufficient driver break time
(10%) and schedule recovery if the desired probability of on-time departure for the following trip is 95%.
What would the half cycle time be if the coefficient of variation is 0.3 and the desired on time departure
was 99%.
tm = 32 min.
rd = 10%
cv = 0.1
z95% = 1.645
z99% = 2.33
Running time for driver recovery = 1.1 * 32 = 35 minutes
Running time for on-time departure = 32 * (1+(.1 *1.645)) = 37 minutes
The greater of these is 37 minutes
The half cycle time if the desired on-time departure rate for the next trip is 99% is:
32 * (1 + (.1 * 2.33)) =39.5 minutes
57
Failure Rate
Headway CV
30
40%
40%
5%
48
10%
58
25%
68
40%
80%
19
33
60
80%
40%
44
49
58
80%
80%
17
37
55
40%
40%
43
46
54
40%
80%
23
30
49
80%
40%
32
41
46
80%
80%
17
27
40
40%
40%
33
35
45
40%
80%
18
22
41
80%
40%
25
28
37
80%
80%
15
19
33
40%
40%
25
30
37
40%
80%
15
20
37
80%
40%
23
26
33
80%
80%
13
22
28
40%
40%
18
25
29
40%
80%
13
18
28
80%
40%
20
22
28
40
50
60
75
58
80%
11
14
21
40
50
60
75
Failure Rate
Service Time
CV*
40%
Headway CV
40%
5%
58
10%
64
25%
83
40%
80%
33
47
66
80%
40%
45
55
68
80%
80%
31
38
56
40%
40%
44
47
57
40%
80%
23
35
54
80%
40%
35
42
52
80%
80%
24
30
44
40%
40%
35
44
50
40%
80%
20
29
43
80%
40%
28
30
41
80%
80%
15
19
37
40%
40%
27
33
40
40%
80%
16
26
37
80%
40%
25
27
33
80%
80%
13
22
31
40%
40%
25
26
32
40%
80%
15
18
28
80%
40%
22
23
28
80%
80%
11
19
26
40
Failure Rate
Service Time
CV*
40%
Headway CV
40%
5%
26
10%
37
25%
51
40%
80%
10
12
34
80%
40%
22
34
48
80%
80%
32
40%
40%
23
32
44
40%
80%
10
23
80%
40%
18
25
38
80%
80%
59
26
60
75
40%
40%
19
26
35
40%
80%
18
80%
40%
16
21
34
80%
80%
10
21
40%
40%
16
20
30
40%
80%
16
80%
40%
14
20
26
80%
80%
12
16
40%
40%
13
17
25
40%
80%
13
80%
40%
11
15
23
80%
80%
13
40
50
60
75
Failure Rate
Service Time
CV*
40%
Headway CV
40%
5%
29
10%
47
25%
68
40%
80%
10
12
33
80%
40%
27
40
60
80%
80%
40%
40%
26
37
53
40%
80%
10
30
80%
40%
21
27
50
80%
80%
40%
40%
22
30
41
40%
80%
22
80%
40%
19
25
35
80%
80%
40%
40%
18
23
39
40%
80%
16
80%
40%
14
21
32
80%
80%
40%
40%
13
18
29
40%
80%
13
80%
40%
11
16
24
80%
80%
60
40
50
60
75
Failure Rate
Service Time
CV*
40%
Headway CV
40%
5%
67
10%
75
25%
96
40%
80%
50
68
79
80%
40%
55
58
76
80%
80%
46
55
76
40%
40%
50
61
76
40%
80%
43
51
66
80%
40%
42
48
60
80%
80%
32
45
59
40%
40%
43
48
60
40%
80%
35
47
58
80%
40%
32
37
50
80%
80%
27
35
52
40%
40%
37
43
52
40%
80%
27
40
49
80%
40%
25
31
43
80%
80%
23
28
41
40%
40%
30
33
39
40%
80%
22
29
36
80%
40%
24
28
34
80%
80%
20
25
35
40
50
Failure Rate
Service Time
CV
40%
Headway CV
5%
74
40%
10%
90
25%
105
40%
80%
56
80
94
80%
40%
56
63
84
80%
80%
54
64
82
40%
40%
55
67
78
40%
80%
48
62
76
80%
40%
46
51
61
80%
80%
39
44
66
40%
40%
40%
48
80%
51
36
61
68
46
60
60
75
80%
40%
37
41
52
80%
80%
32
35
50
40%
40%
41
45
52
40%
80%
35
42
54
80%
40%
25
33
43
80%
80%
26
32
42
40%
40%
30
33
41
40%
80%
27
31
45
80%
40%
24
27
34
80%
80%
20
26
36
40
50
60
75
Failure Rate
Service Time
CV*
40%
Headway CV
40%
5%
50
10%
64
25%
85
40%
80%
28
45
73
80%
40%
44
55
74
80%
80%
21
36
65
40%
40%
46
50
68
40%
80%
20
41
62
80%
40%
32
42
53
80%
80%
18
30
52
40%
40%
35
41
55
40%
80%
15
29
51
80%
40%
30
37
47
80%
80%
16
25
45
40%
40%
31
37
49
40%
80%
15
28
42
80%
40%
24
27
40
80%
80%
13
24
32
40%
40%
25
30
38
40%
80%
13
23
36
80%
40%
20
23
31
80%
80%
13
19
31
62
40
50
60
75
Failure Rate
Service Time
CV*
40%
Headway CV
40%
5%
64
10%
79
25%
104
40%
80%
33
49
88
80%
40%
51
59
82
80%
80%
28
44
77
40%
40%
50
57
81
40%
80%
23
42
65
80%
40%
38
48
60
80%
80%
24
33
55
40%
40%
39
50
63
40%
80%
16
37
56
80%
40%
32
37
49
80%
80%
16
25
47
40%
40%
31
40
54
40%
80%
15
31
47
80%
40%
25
33
42
80%
80%
13
24
32
40%
40%
26
31
42
40%
80%
13
23
37
80%
40%
20
26
34
80%
80%
13
20
31
63
4 R AIL C APACITY
4.1 I NTRODUCTION
Rail rapid transit systems provide important public transportation service in
very large cities in developing countries. Trains operate along rights-of-way
that are completely separated from street traffic interference. They carry
large numbers of people safely and reliably. Train control signal systems
govern train operations and capacities.
This chapter provides guidance for computing the capacities of rail lines and
stations. It overviews existing operational experience, identifies the key
design and operating factors and sets forth procedures for estimating
capacities in terms of trains per track per hour, passengers per track per hour
and station platforms and access to them.
Region
City
Peak Volume
(pphpd) *
Asia
Bangkok
50,000
Chongqing (monorail)
17,000
Hong Kong
50,000
Manila
26,000
Buenos Aires
20,000
Mexico City
39,300
Santiago
36,000
Sao Paulo
60,000
Latin America
2.
3.
4.
5.
Transit analysts generally consider the critical station to be the one with the highest mean dwell
time plus two standard deviations of dwell time.
65
6.
66
x Cars
Hour
Train
Car
The precise values for this equation will vary among transit agencies.
4.5.2 R U N N IN G W AY C A PAC I T Y
The running way capacity in trains per track per hour depends on the
passenger dwell time at intersections, the variation in the dwell time (the
operating margin), and the safe separations between trains.
68
4.5 . 2. 1 C R I T I C A L S T A T I O N D W E L L T I M E
The major limitations on train capacity are usually the dwell time and safe
separation time between trains at the critical stop. While this is normally the
busiest stop, the distribution of actually observed dwell times has an effect on
determining the critical stop. The dwell time depends on the pattern of
passenger boardings and discharges and the number of through passengers on
the train. Trains with high levels of through passengers take more time to
board per passenger than those that are less congested. Dwell time is also
influenced by the electrical and mechanical characteristics of the train
including time for the system to recognize that the train is fully stopped prior
to door opening, opening and closing time of doors and time for safety checks
to assure that all doors are closed prior to train departure from the station.
This time is referred to as the function time.
Dwell time distributions on existing rail systems can be measured directly and
this data can be used in planning new systems. A more detailed approach on
determining the dwell time at the critical intersection is discussed below. This
treatment discusses passenger boarding and discharge time as well as function
time.
A formulation estimating dwell time attributable to Puong (2000) is shown
below:
-4
(R = 0.89)
Where,
SS = dwell time
Ad = alighting passengers per door
Bd = boarding passengers per door
TSd = through standees per door
(i.e. total through standees divided by the number of doors)
3
This formulation also includes a term (TSd Bd ) which accounts for delayed
boarding time associated with more crowded vehicles. Source: Puong (2000)
below illustrates the effect of vehicle crowding on boarding flow rates.
69
4.5 . 2. 2 O P E R A T I N G M A R G I N
An operating margin must be introduced in estimating station capacity. This is
a buffer time to allow for random variation in dwell time. An operating margin
allows for dwell time variability without disrupting scheduled operating.
The operating margin can be set at 25 to 30 seconds or can be based on two
standard deviations from the mean observed dwell time. The average dwell
times, based on North American experience, range from 30 to 50 seconds and
the coefficient of variation ranges from 0.25 to 0.70.
4.5 . 2. 3 M I N I M U M S E P A R A T I O N I N T E R V A L
In addition to the dwell time and operating margin, an additional separation
time between successive trains is required. This additional separation time is
the sum of two related factors.
70
the time required for a train to travel its own length and clear the station, and,
a safe separation time between trains that depends on characteristics of the
signal systems, platform length, train length and station.
The safe separation time depends on, among other things, characteristics of
the signal system, platform length, train length, and station approach speed.
Error! Reference source not found. shows safe separation time excluding
station dwell time and operating margin as a function of train length, and type
of signal system. Note that the separation distance increases with the train
length. Further, the figure shows that a three aspect fixed block signal system
has the highest safe separation distance, cab signaling is slightly less. The
moving block signal system with variable stopping distances has the lowest
separation. The Transit Capacity and Quality of Service Manual, part 5,
Chapter 7 contains a more detailed treatment of this topic.
F IGURE 4-2: M INIMUM T RAIN S EPARATION
4.5 . 2. 4 M I N I M U M H E A D W A Y R E L A T I O N S H I P
The minimum headway is obtained by summing the various headway
components. The basic equation is as follows:
h = td + tom + tcs (Eq. 4.2)
Where,
h
minimum headway
td
71
tom
operating margin
tcs
the number of trains per track per hour, the line capacity, is computed as
follows:
T = 3600/h
(Eq. 4.3)
Where,
T
Modern signal systems with 182 meter trains and a critical stop with modest
average dwell times (i.e. less than 30-40 seconds) can support between 24 and
30 trains per track per hour.
Modern systems with cab or moving block signals and single routes (no
branches or merges) can operate slightly more frequently. Transit managers
rarely schedule more than 30 tranis per hour despite the fact that the
theoretical capacity is higher.
Example: The critical station in a proposed rapid transit system has been identified and the number
of train boardings per hour is expected to be 5,000, and discharges of 2,000. The system will have 6
car trains each 20m long with three doors per car. The design frequency is expected to be about 30
train per hour. The busiest door will have 30% more transactions as the average door and trains are
expected to have 10 through passengers per door. Determine if the system can maintain 30 trains
per hour.
1. Compute peak flow through busiest doors:
5,000 passengers boarding per hour / 30 trains per hour / 6 cars per train / 3 doors per car = 9.3
passenger boardings per door .
2,000 passengers boarding per hour / 30 trains per hour / 6 cars per train / 3 doors per car = 3,7
passenger discharges per door .
2. Adjust upward for ratio of busiest door to average door:
9.3 * 1.3 = 12 boardings
3.7 * 1.3 = 5 discharges
Using the Puong formulation, the expected dwell time is:
SS =
12.22 + 2.27 * Bd + 1.82 Ad +6.2* 10-4 * TSd3Bd
= 12.22 + 2.27 * 12 +1.82 *5 +6.2 *10 -4 * 103 * 12
= 56 seconds
Operating margin = 25 seconds
Safe separation time = 42 seconds
The total is 123 seconds. It is likely that the 2 minute headway may be maintained.
The running way capacity in trains per track per hour depends on the
passenger dwell time at intersections, the likely variation in the dwell time (the
operating margin), the time for trains to clear stations and the safe separations
between trains.
72
Example: Compute the train capacity in trains per hour of a rail transit system where the governing
dwell time is 45 seconds, the operating margin is 13 seconds and the minimum train control
separation is 45 seconds.
Minimum headway: 45 sec + 13sec + 45 sec = 103 sec. This is about 35 trains per hour
4.5 . 2. 5 V A R I A T I O N I N L I N E C A P A C I T Y
Line capacity is influenced by several variables. These include type of signal
control, train consist length and operating speeds. The Transit Capacity and
Quality of Service Manual guide indicates the following ranges in train per
track per hour.
Fixed block 30 or less if long dwell times
Cab single controls 30-34
Moving block 35-40
Error! Reference source not found. shows the combined effects of station
dwell times, operating margins and signal control times on line capacity.
T ABLE 4-4: C OMPONENTS OF M INIMUM T RAIN S EPARATION T IME
Operating
Margin
(sec.)
Fixed
Block
Cab
Moving
Block
30
30
40
40
50
50
20
30
20
30
20
30
24
24
24
24
24
24
50
50
50
50
50
50
57
57
57
57
57
57
Maximum Frequency
(trains/hr.)
Fixed
Cab
Moving
Block
Block
49
43
43
38
38
35
36
33
33
30
30
28
34
31
31
28
28
26
4.5 . 2. 6 T U R N A R O U N D S
The basic end-of-line track configuration is illustrated in Error! Reference
source not found.. An entering train (presumably on the right track) goes to
the station platform on the right track unless it is occupied by another train. In
such cases, it must crossover to the other platform. The geometry and train
performance characteristics will determine a maximum layover duration per
train that can be accommodated for each value of scheduled headway. If the
layover time exceeds this maximum, then trains will be delayed and the
scheduled frequency will not be able to be maintained.
73
On train systems with short headways and long train length, this may require
drop-back crew scheduling in which the driver of the entering train is relieved
by a second driver. The first trainman then walks the length of the train and
drives the following scheduled train on that platform. This enables some driver
layover time, assures on-time departure for scheduled trips and maintains
service consistent with the system design.
F IGURE 4-3: T RAIN T URNAROUND S CHEMATIC D IAGRAM
Table 4.6 below illustrates the maximum layover for the simple configuration
using common values of geometry and train performance. The last row
illustrates the number of seconds that a driver requires to walk the length of
the train at a walking speed of 1.9 km/hr.
T ABLE 4-5: M AXIMUM T RAIN L AYOVER
Headway
Minutes
Seconds
150
200
250
120
186
182
179
240
423
419
416
300
529
525
522
360
644
640
637
80
106
134
74
4.5 . 2. 7 B R A N C H O R J U N C T I O N C A P A C I T Y
Branches and junction are rarely used in modern rail rapid transit design.
Analytical relationships are complex and train simulation models may be
appropriate. The US Transit Capacity and Quality of Service manual indicates
that flat, at grade junctions may support two minute headways but with
delays, grade separated relationships can sustain 150 to 180 second intervals
between trains.
5-6
9-10
As in the case of bus service, the scheduled loading standard should be applied
to the peak within the peak. If they are applied across the entire peak hour or
peak period, there will be some trains with extraordinarily high loading beyond
the standard.
4.6.1 P AS S E N G E R C AP AC IT Y
The previous discussion illustrated computational methods for train capacity in
trains per track per hour and the vehicle capacity in persons per train car. The
passenger capacity is computed as the product of the train capacity and
vehicle capacity adjusted by the peak hour factor:
P = TV(PHF) = 3,600 V(PHF)/ hgs
(Eq. 4.4)
Where,
T = track capacity in trains per hour
75
V = train capacity
PHF = peak hour factor
Example: A transit system operates 6 car trains which are 20 meters feet long per car. If the peak hour
factor is 0.9 and the maximum line capacity is 30 trains per hour what is the passenger capacity of the
line.
V = pass/car * cars/train = (20 *10) * 6 = 1200 pass/train
P = V * PHF * trains/hour = 1200 * .9 *30 = 32,400 passengers/hour/track
Vehicle capacity is highly dependent on trainset length and the seating
configuration. Error! Reference source not found.Error! Reference source
not found. below shows the maximum vehicle capacity per trainset for a
variety of rail transit lines throughout the developed world. The capacity is
based on an assumed loading standard (shown in the table in standing
passengers per square meter) and the number of seats .
T ABLE 4-6: T RAIN C APACITY
City
Train length
(m)
Cars
Seats
Total
Capacity
Loading
Standard
2
(p/m )
Bangkok
65
126
1,139
Guanzhou
59
142
675
Shanghai
140
288
1,860
Singapore
138
300
1,728
Shenzen
140
288
2,208
It is convenient to think about the capacity in the form of seats and standees
per meter of length. Planners must trade off seating capacity for standing
capacity. Higher seating density such as transverse 2 + 2 seating occupies
about 3.5 seats per meter of train length. Longitudinal or peripheral seating
occupies about 2.5 seats per meter of length. Using these estimates and
various loading conditions, the capacity of various train car lengths can be
computed.
A calculation similar to that offered for buses for an approximate capacity of
rail cars is as follows:
Vc = (L -1)*(W-0.2) + (1- Sa/Ssp)N((L-1)-DnDw)
Ssp
Sw
where
Vc =
L =
W=
Dn =
Number of doorways
Ws=
Dw =
Sa =
longitudinal]
Ssp =
N=
Vehicle arrangement
Error! Reference source not found. below shows the seating capacity per car
of a rail car with transverse seating for varying car lengths and number of
doors per side. As in the case for bus capacity, the design number of
passengers per unit of area is shown.
T ABLE 4-7: T RAIN C AR C APACITY
Passengers/
sq.m
4
5
6
7
8
20
3
202
264
327
389
452
25
4
234
306
378
450
522
There is little published data on this variability. It is reported that the rail transit operator in
Santiago de Chile has a system by which individual cars in a train consist are weighed upon
departure from busy stations as a means of monitoring passenger load volumes.
77
where,
V = train capacity
N = number of cars per train
Vc = capacity per car
DF = loading diversity factor
The loading diversity factor is the ratio of the number of customers on the
train with the most crowded car to the theoretical capacity of the train.
78
The transit station platform and its ancillary access facilities provide an
integrated system of pedestrian movement and accommodation. Error!
Reference source not found.shows how the various elements relate while
Error! Reference source not found. provides a more detailed description of
each element.
F IGURE 5-1" I NTERRELATIONSHIP A MONG S TATION E LEMENTS
Train arrival
Passengers
Platform
Pedestrians
Stairs
Escalators
Elevators
80
The flow rate, measured in pedestrians per hour is the product of speed and
density. Researchers commonly normalize the flow rate per unit width of the
facility (corridor, staircase etc.), it is probably more practical to think of flows
as flow rates per lane of width with each lane being about 0.75 meters.
Error! Reference source not found. shows how the pedestrians per meter per
minute decreases as the square meters of space per pedestrian.
81
LOS
Pedestrian
Space
2
(m /p)
Avg. Speed,
S (m/min)
v/c
>3.3
79
0-23
0.0-0.3
2.3-3.3
76
23-33
0.3-0.4
1.4-2.3
73
33-49
0.4-0.6
0.9-1.4
69
49-66
0.6-0.8
0.5-0.9
46
66-82
0.8-1.0
<0.5
<46
Variable
Variable
Access to and from the station should be sufficient to clear at least one train,
preferable two trains, before the second train arrives.
The platform dimensions should be sufficient to minimize passenger crowding.
The acceptable degree of overcrowding will vary among systems The following
station capacity procedures are keyed to the pedestrian densities (e.g.
passenger occupancies) shown in figure xxx.
The first step in determining the required platform capacity is to establish the
design quality of service. While US practice is to assign a letter designation (AF) to various densities of queuing area occupancy, having a design occupancy
in persons per square meter will suffice. This level should be adjusted to
account for factors such as more persons with large briefcases or handbags.
The design level of customers at any one time should be computed to obtain
the net required area for waiting. The platform capacity must include space for
passenger circulation and designers should recognize that the effective area is
diminished by other factors.
Passengers avoid platform edges. About 0.5 to 0.6 meters from the
edge of platform should be deducted from the queuing space. If
platform screens are used, occupancy to the edge of the platform can
be assumed.
There is some interaction between platform capacity and train headway. The
design headway should enable each customer to board the next arriving train
at all stations under normal operating conditions recognizing that the ability to
board passengers at a station in diminished by the number of through
passengers on arriving trains. Under normal conditions, the platform capacity
should be sufficient to hold the number of expected passenger arrivals
between the scheduled arrival of two successive trains.
The US practice is to design station platforms to be large enough to
accommodate the anticipated boardings during the peak 15 minutes under
extreme operating conditions. The design event for the purpose of platform
capacity is to assume that a single train is removed from the service schedule.
That is, for a narrow time interval, the effective train headway is twice the
published headway. Under these circumstances, there will be a larger than
normal number of persons waiting for the train. The design volume of
passengers waiting would be the expected arrival rate of passengers per
minute during the peak 15-minute interval times the scheduled headway times
83
2 to account for the train removed from the schedule. Note that emergency
egress requirements of arriving trains may require larger platform sizes.
The platform size for waiting passengers is determined by the design number
of waiting passengers divided by the design occupancy standard.
2.
84
Minimum
width
m
1.73
1.10
1 12
1.83
1.83
0.91
0.51
0.46
Capacity
Travel Speed
p/m/min
89
63
72
63
70
89
50 ppm
25 ppm
(m/min)
61.0
15.2
18.3
15.2
15.2
In addition to the main emergency exits, stations are required to have a second
emergency means of egress of at least 1.12 m in width. The second exit must
also be along a different route than the main exit.
To determine exit capacity of passengers for constricted exits which have a
capacity limitation such as doors and stairs, the capacity in persons per meter
per minute is multiplied by the width of the exit type. For example:
Minimum width
M
1.73
85
Effective width
M
1.07 at platform edge
1.22 at walls
1.73
1.22 at walls
Other types of emergency exits, such as doors, do not need effective widths
for design purposes, but any unusual features should be kept in mind when
calculating capacity on an existing facility.
When designing the flow of persons from the station to a safe distance, it is
important to consider the sequence of exit types, and any bottlenecking that
may consequently occur during escape. For example, if the path from the
platform to the street level consists of a doorway and then a staircase, the
total flow will be limited by the staircase. Thus, when calculating the design
flow, it does not matter that 81 ppm can pass through the door if the staircase
can only service 70 ppm.
Active escalators can be considered emergency exits with some restrictions. If
an escalator can operate in both directions, then it is considered an emergency
exit. If the escalator can only run in one direction, it is only an emergency exit
if running in the exit direction. If it is operating in the wrong direction, the
escalator must be capable of manual or automatic stopping to be considered
effective in evacuation. Note that a running escalator does not have any
additional emergency capacity than a stairway or a stopped escalator. Also,
when considering escalators as points of egress, one should design the facility
as if the most highly used escalator is out of order for maintenance.
An example of how the evacuation assessment is conducted in contained in an
appendix.
5.4.1 S T A IR W A Y S
Stairway capacity is usually measured in number of passengers per meter of
width per minute. However, since persons on stairways (and escalators)
normally walk in line, a more practical method of estimating capacity is to
assess the flow per lane with each lane being about 0.75 meters wide.
As in the case of pedestrian flows, the flow volume of a staircase depends on
average walking speed and the pedestrian density. Error! Reference source
not found. gives pedestrian flow rates (passengers/min) at low density, free
flow operation and at design flow where density is much higher.
86
Traffic Type
Young/Middle
Aged Men
Young/Middle
Aged Women
Elderly people,
family groups
Speed (m/s)
0.9
Flow (p/min)
27
Speed (m/s)
0.6
Flow (p/min)
60
0.7
21
0.6
60
0.5
15
0.4
40
5.4.2 E S C A LA T O R S
Escalators can transport passengers for level changes up to 200 feet. In most
rail transit systems, they are the primary means of changing level from the
ground to the station platform and crossovers. The theoretical and observed
capacity are shown the table below. The theoretical capacity assumes that
each stair is occupied by a traveler. The more likely case of lower density on
escalators results in a nominal observed capacity as illustrated in Error!
Reference source not found..
T ABLE 5-6: E SCALATOR C APACITY
Step Width
Speed
Maximum Capacity
Theoretical
Nominal Capacity
Observed
600 mm
.45 mps
.50 mps
.60 mps
.45 mps
Same as 600 mm
.50 mps
Same as 600 mm
.60 mps
Same as 600 mm
.45 mps
.50 mps
.60 mps
800 mm
1000 mm
5.4.3 E LE V AT O R C AP AC IT Y
Elevators are necessary to accommodate certain travelers who due to
disability, fear or personal preference do not use stairs or escalators. In some
deep tunnel transit systems, elevators are the primary means of access to
station platforms, with stairs used only for emergency evacuation. In such
cases, high capacity, high speed elevators must be deployed.
87
1200
1400
1600
1600 (alt.)
1800
1800 (alt.)
2000
2250
2700
Width
Depth
Area (m )
2100
2100
2100
2350
2100
2350
2350
2350
2350
1300
1450
1650
1450
1800
1650
1800
1950
2150
2.7
3.0
3.5
3.4
3.8
3.9
4.2
4.6
5.1
Observed
loading
(passengers)
10
12
16
16
18 or 19
18 or 19
20
22
25
The cycle time of elevators is determined by vertical travel distance and speed,
door opening speed and width. Larger elevators have heavier and wider doors
resulting in longer door opening times. Further, larger elevators have longer
stop dwell time to allow for passenger entries and discharges.
Error! Reference source not found. shows some typical value of throughput
capacity. Note that the capacity is not very sensitive to elevator speed since
most of the elevator cycle time is used for boarding and discharging
passengers.
T ABLE 5-8: E LEVATOR T HROUGHPUT C APACITY IN P ASSENGERS P ER H OUR P ER D IRECTION
Elevator Speed (m/sec)
Elevator Cab
Passenger
Capacity
10
Floor height
(m)
0.5
1.5
2.5
4.5
390
410
420
420
430
10
380
400
410
420
420
10
360
390
400
410
420
15
4.5
430
440
450
450
450
88
420
440
440
450
450
15
400
430
440
450
450
20
4.5
450
460
470
470
470
20
440
460
460
470
470
20
430
450
460
460
470
25
4.5
470
470
480
480
480
25
460
470
480
480
480
25
450
460
470
480
480
Portal Type
Gateway
Clear Opening
Swing Door
Flow (persons/minute)
60-110
60-110
40-60
Flow (persons/hour)
3600-6600
3600-6600
2400-3600
Some of this material may apply to off-board fare collection at BRT stations.
89
60-90
3600-5400
2535
90
15002100
BIBLIOGRAPHY
Bus Rapid Transit Planning Guide, Third Edition, Institute for Transportation
and Development Policy, New York, 2007
Chen, Feng, Wu, Qibing, Zhang, Huihui, Li, Sanbing, and Zhao, Liang
Relationship Analysis on Station Capacity and Passenger Flow: A
Case of Beijing Subway Line Journal of Transportation Systems
Engineering and Information Technology 9(2), April 2009
Cromwell, P.R., Cracknell, J. A. and Gardener, G., Design Guidelines for
Busway Transit, Overseas Road Note 23, 1993 Transport Research
Laboratory, Crowthorne, Berkshire, United Kingdom
Estrada, M., Ortigosa, J. and Robuste, F., Tandem Bus Stop Capacity, paper
submitted for publication, Annual Meeting, Transportation
Research Board, Washington, DC. January 2011.
Fernandez, R., del Campo, M. de A., and Swett, C., Data Collection and
Calibration of Passenger Service Time Models for the Transantiago
System, European Transport Conference, 2008
Fernendez, Rodrigo, Zegers, Pablo, Weber, Gustavo and Tyler, Nick Influence
of Platform Height, Door Width and Fare Collection on Bus Dwell
Time: Laboratory Evidence for Santiago, Chile, TRB 2010 Annual
Meeting
Gibson, Jaime Effects of a Downstream Signalized Junction on the Capacity
of a Multiple Berth Bus Stop
Harris, N.G., Anderson, R.J., An International Comparison of Urban Rail
Boarding and Alighting Rates, Rail and Rapid Transit Vol. 221 Part
F: J 2007
Highway Capacity Manual, Transportation Research Board, Washington
D.C., 2000
Huang, Zhaoyi and Wright, Craig The Experience of Developing Bus Rapid
Transit in China Mainland, TRB 2010 Annual Meeting
Jaiswal, Sumeet, Bunker, Jonathan M. and Ferreira, Luis, Relating bus dwell
st
time and platform crowding at a busway station. Proceedings 31
Australasian Transport Research Forum (ATRF), 239-249, Gold
Coast, Australia. 2008
91
92
St. Jaques, Kevin and Levinson, Herbert, Operational Analysis of Bus Lanes on
Arterials, TCRP Report 26, Transportation Research Board,
Washington D.C., 1997
Steer-Davies-Gleave, Estudio de Capacidad del Sistemo Transmilenio,
prpepared for Transmilenio, S.A., Bogota, 2007
Tann, Helen, Hinebaugh, Dennis Characteristics of Bus Rapid Transit for
Decision Making, 2009 Federal Transit Administration
Tan, Dandan, Wang, Wei, Lu Jian and Bian, Yang Research on Methods of
Assessing Pedestrian Level of Service for Sidewalk, Journal of
Transportation Systems Engineering and Information Technology
Volume 7, Issue 5, October 2007
Wang, Tiantian, Zhang, Ruhua, Zhu, Xianyuan, Wu, Xiangguo and Zhang,
Rufeng Rapid Bus Transit in Jinan, China: Applying Flexibility to
Transit System, TRB 2010 Annual Meeting
Zhou Xiang, Foong Kok Wai, Chin Hoong Chor Pedestrian speed-flow model
on escalators and staircases in Singapore MRT stations
Government of Gujarat, Ahmedabad Bus Rapid Transit System (ART), Bus
Technology, undated.
NFPA. (2000). Standard for Fixed Guideway Transit and Passenger Rail Systems.
National Fire Protection Assocation , Quincy, MA.
Schachenmayr, M. P. (1998). Application Guidelines for the Egress Element of
the Fire Protection Standard for Fixed Guideway Transit Systems.
Monograph 13, (Parsons, Brinckerhoff, Quade & Douglas), New
York.
Puong, A., Dwell Time Model and Analysis fir the MBTA Red Line, Internal
Memo, MIT, March, 2000.
93
94
ANALYSIS APPROACH
In this analysis, we determine if the offered headway (2 minutes) is sufficient
to accommodate the current ridership level at the accepted loading standard.
The next step is to determine the capacity of the bus stop at the critical
intersection. This will enable an assessment of capacity increasing strategies
such as increasing service frequency.
B =P/ (Pmax PHF)
Where,
P = design peak hour flow
B = number of buses per hour to accommodate the peak flow
2
1,800
Pmax
11
PHF
90
28
This assessment suggests that the 30 buses offered per hour is sufficient to
accommodate the demand at an acceptable loading level.
Step 1 Computer current capacity for a single berth stop
1.1 Compute operating margin
where,
tom = operating margin (s)
s = standard deviation of dwell times
Z = standard normal variable corresponding to a desired failure rate (See table
below).
95
Failure rate
1%
2.33
2.5%
1.96
5%
1.65
7.5%
1.44
10%
1.28
15%
1.04
20%
0.84
25%
0.68
30%
0.53
50%
0.6
tc
11
td
90
1.28
cv
0.09
tom = sZ
10
Bl(bus/h)
55
headway (sec)
60
Type 1
Type 2
Type 3
Near side
0.9
Mid block
0.9
0.7
Far side
0.8
0.5
0.35
0.4
0.45
0.5
0.55
0.6
510
580
650
730
800
870
100
440
510
580
650
730
800
200
360
440
510
580
650
730
400
220
290
360
440
510
580
600
70
150
220
290
360
440
800
70
150
220
290
1000
70
150
Calculation 2
fl
0.8
200
580
fm=1-fl(v/c)
0.724
97
where,
B = Bus Facility Capacity (bus/h)
Bl = Bus Loading Area Capacity
Nel = number of effective loading areas (See table below)
fm = mixed traffic adjustment factor
T ABLE 5-13: O N -L INE L OADING A REAS , R ANDOM A RRIVALS
Loading Area
Efficiency
100%
75%
1.75
70%
2.45
20%
2.65
10%
2.75
Calculation 3
Bl
55
Nel
fm
0.724
40
This suggests that the single berth facility is sufficient to accommodate the
design headway of 2 minutes or 30 buses per hour since the capacity is 40
buses per hour.
1.5 Estimate person capacity for a single berth stop
The person capacity is:
where,
P = person capacity (p/h)
Pmax = maximum schedule load per bus (p/bus) (See table below)
B = Bus facility capacity (bus/h)
PHF = Peak hour factor
98
Bus type
single
articulated
bi-articulated
Doorways
Length (m)
Standees/sq. m.
4
5
6
7
8
2
13
3
20
4
25
86
97
108
120
131
136
153
170
188
205
172
194
217
239
262
Calculation 4
Pmax
86
40
PHF
0.75
P (pass/hr)
2580
2,900
Pmax
86
PHF
.75
45
Note that in task 1.4, the capacity of the single berth stop was determined to
be 40. Introducing 45 buses per hour will require either an additional berth or
shorter stop dwell times or higher allowable failure rate.
Step 2.1 Assess the introduction of larger (articulated) buses
Using larger buses changes only Calculation 4. The current Pmax, (maximum
load per bus) is 86 at the prescribed loading density. If articulated buses are
introduced, Pmax will be 136. In this assessment, the same frequency of service
as is currently operated (30 buses per hour) is assumed.
Calculation 4
Pmax
136
30
PHF
0.75
P (pass/hr)
3,060
From this chart, the person capacity with the larger buses will be about 3,000
persons per hour. This increased capacity alone will accommodate the
expected ridership increase. In practice, if the increased demand were
somewhat less than 50%, the service frequency can be reduced to provide the
minimum amount of service to meet the demand at the prescribed loading
standard. In this case, the required number of buses per hour will be:
B = P/(Pmax PHF)
From the analysis in step 1.4, the number of buses per hour which can be
serviced by a single berth stop is approximately 40. The introduction of higher
capacity buses will not require a multiple berth stop.
Step 2.2 Assess the introduction of off-board fare collection
Off-board fare collection reduces the amount of time per person during the
boarding process and can improve the capacity of the stop by reducing stop
dwell time. Further, with off-board fare collection, boarding customers can
enter through the rear door, further reducing stop dwell time. More precise
data collection at the critical stop will be required to determine if dwell time
reduction due to rear door boarding is significant. The assessment will
determine the single berth capacity with a reduced dwell.
100
pre-pay
single ticket
exact
change
swipe card
smart card
front door
rear door
Observed
Range
Boarding
2.25-2.75
3.4-3.6
3.6-4.3
Suggested
Default (s/p)
2.5
3.5
4
4.2
3.0-3.7
Alighting
2.6-3.7
1.4-2.7
4.2
3.5
3.3
2.1
where,
td = average dwell time (s)
Pa = alighting passengers per bus through the busiest door (p)
ta = alighting passenger service time (s/p)
Pb = boarding passengers per bus through the busiest door (p)
tb = boarding passenger service time (s/p)
toc = door opening and closing time (s)
Original boarding
time
Pa
100%
Pa
100%
ta
100%
ta
100%
Pb
100%
Pb
100%
tb
100%
tb
63%
toc
100%
toc
100%
td
td
2.625
101
g/C
Calculation 1
Calculation 2
Calculation 3
Calculation 4
Adjustment Factor
Person Capacity
0.6
fl
tc
11.1
td
22
1.28
s
tom
7.9
10
Bl
63
fm
Bl
63
200
Nel
580
fm
0.724
0.724
45.6
Pmax
86
45
PHF
0.75
2,900
Bl
Calculation 3
Calculation 4
Bus Facility
Capacity
Person Capacity
55
Nel
1.75
fm
0.724
70
Pmax
86
70
PHF
0.75
4,500
102
Calculation 1
Calculation 2
Calculation 3
Calculation 4
Adjustment Factor
Bus Facility
Capacity
Bl
63
Person Capacity
fl
Pmax
86
tc
11.1
200
Nel
45
td
22
580
fm
.724
PHF
0.75
1.28
fm
0.724
45
7.9
3,800
tom
10
Bl
63
Step 2.5 Increase the Allowable Standing Density
If the critical bus stop with a single loading berth is constrained to 40 buses per
hour, then a calculation can be made of the maximum standing density to
accommodate the load.
Pmax =P/ (B PHF)
Calculation 1
P
2,900
40
PHF
.75
Pmax
97
From the table on bus sizes and densities, this indicates that the peak density
on board will be about 5 standing passengers per square meter.
103
where,
Tl =
3,600 =
tcs =
td =
tom =
tcs
60
td
30
tom
24
Tl (bus/h)
30
headway (sec)
120
The scheduled train frequency of 20 trains per hour is less than the line
capacity of 30 trains per hour.
1.3 Estimate person capacity
The person capacity is:
where,
P = person capacity (p/h)
Pmax = maximum schedule load per traincar (see table below)
C = consist length
T = Station capacity (trains/hour)
PHF = Peak hour factor
T ABLE 5-16: R AIL V EHICLE C APACITY
Passengers/
sq.m
4
5
6
7
8
20
3
146
157
167
177
188
105
25
4
172
186
200
214
228
Calculation 2
Pmax
167
30
PHF
0.75
30,000
The current maximum person capacity is 30,000 passengers per hour. This is
the maximum capacity if the trains were scheduled at the lines maximum
capacity of 30 trains per hour.
Step 2- Enumerate and Assess Alternatives
If the system is currently at its maximum capacity, a 40% increase in ridership
will require a design for at least 22,400 passengers per hour. Four alternatives
were reviewed to determine if they were feasible in increasing capacity. These
included:
1.
2.
3.
4.
200
20
PHF
0.75
24,000
From this chart, the person capacity at the current frequency of 20 trains per
hour is 24,000 passengers per hour. This increased capacity will be able to
accommodate the expected ridership increase to 22,400 passengers per hour.
106
167
20
10
PHF
0.75
25,000
From this chart, the person capacity is increased to 25,000 passengers per hour
at the current frequency and loading standard. This increased capacity will be
able to accommodate the expected ridership increase to 22,400.
Step 2.3 Assess increasing the acceptable loading standard
If the acceptable loading standard is increased to 8 customers per square
meter, the line person capacity is computed as follows.
Calculation 2
Pmax
188
20
PHF
0.75
22,560
This is just enough capacity to accommodate the target peak load of 22,400
passengers per hour. It should be noted that operating at a higher load
standard will likely increase the stop dwell time since the passenger flow rate
on and off trains is diminished due to crowding. Given that the computed line
capacity is about 20 trains per hour, in the instant case this is not problematic.
Step 2.4 Assess increasing the service frequency
The current scheduled headway necessary to meet the demand is about 180
seconds or 3 minutes (calculated in original calculation 1). This is a frequency
of 20 trains per hour. Increasing the frequency by 40% would require
scheduling about 28 trains per hour at the current acceptable load factor. From
previous calculations, this is determined to be feasible since the flow capacity
of the line is 30 trains per hour. The number of trains per hour to meet the
requirement is:
107
T = P/(Pmax C PHF )
where all terms have been defined previously
Calculation 2
P
22,400
Pmax
167
PHF
0.75
23
This suggests that scheduling 23 trains per hour will be able to accommodate
the passenger demand. This is less than the line capacity of 30 trains per hour.
108
1.
2.
3.
4.
5.
6.
Date
Stop
Observer
Location at stop
Train Departure
Time
Passenger Density
110
Passenger Density
Stop
Passenger Density
Passenger Density
111
Date
Station
Observer
Start time
End Time
Transaction
Duration
Transaction Type
Transaction
Duration
112
Transaction Type
Date
Station
Observer
Direction
Time (train
departure)
Time (train
stopped)
Time (train
departure)
113
observer for each door of a subway car. Generally, only the car determined to
be the busiest should be observed.
Collection method: The following are steps that may be used to collect field
data on passenger service times. An example of a data collection sheet is
shown in Figure C.6.
1.
From a position at the rail stop under study, record the identification
number and run number for each arriving vehicle.
2.
3.
4.
Count and record the number of passengers alighting and the number
of passengers boarding at the door.
5.
Record the time that the major passengers flows end. (Note: This is
somewhat subjective but essential to correlate flows per unit of time.
This time for stragglers to board or exit should not be included.)
6.
7.
8.
Record the time when the vehicle starts to move. (Note: Leave time
should exclude waiting where the train must wait for a traffic signal to
turn green.
9.
The passenger service time for each transit vehicle arrival is computed by
taking the difference between the time that the door opens and the time that
the main flow stops. The service time per passenger is computed by dividing
the number of passengers boarding (or alighting) by the total service time. A
chart showing the flow rate under varying levels of train occupancy after
departing from the station is desirable. This can be a staged variable in three
levels: all customers seated, standees at a rate of 0-2 passengers per square
meter and standees as a rate of greater than 2 passengers per square meter.
114
Date______
Time _______
Route _____
Arrival Time
Doors
Open
Main
Flow
Stops
Bus Number________
Doors
Closed
Train
Leaves
Ons
Offs
Passengers
Departing
On Board
115
Collection method:
A data collection effort at high capacity bus stops is proposed. For each
arriving bus the time from when the vehicle comes a complete stop and the
time that the vehicle begins movement to leave the stop is recorded. Note:
Leave time should exclude waiting where the bus must wait for a traffic signal
to turn green. A suggested form is shown as figure C-7.
T ABLE 5-23: B US H EADWAY AND D WELL T IME D ATA F ORM
Date
Stop
Observer
Direction
Time (bus
departure)
Time (bus
departure)
116
1.
2.
3.
4.
Count and record the number of passengers alighting and the number
of passengers boarding.
5.
Record the time that the major passengers flows end. (Note: This is
somewhat subjective but essential to correlate flows per unit of time.
This time for stragglers to board or exit should not be included.)
6.
7.
8.
Record the time when the vehicle starts to move. (Note: Leave time
should exclude waits at timepoints or at signalized intersections
where the vehicle must wait for a traffic signal to turn green.
9.
The passenger service time for each transit vehicle arrival is computed by
taking the difference between the time that the door opens and the time that
the main slow stops. The service time per passenger is computed by dividing
the number of passengers boarding (or alighting) by the total service time.
To determine passenger service times for use in evaluating the differences
between systems (such as single- and dual-stream doors, high- and low-floor
buses, or alternate fare collection systems), data collection should only at
high-volume stops. These stops are typically downtown or at major transfer
points. The data collection effort will require one or two persons, depending
on the number of passengers.
117
Exits = 2 staircases and one escalator one at each end of the station
(2.24 m wide)
dividing by the number of scheduled trains during the hour. This calculation
provides the number of customers on the next train during the peak 15
minutes under normal operation. The recommended practice is to increase
this number by two to account for a service interruption where a train is
eliminated from the headway. The maximum arriving passenger design load is
the maximum train capacity.
Arriving Passenger Design Load = (Arriving passengers per hour / (trains per
hour * PHF) ) *2
Arriving Passenger Design Load = (5,600/(12 * .8) ) * 2 = 1,166
Total Design Load
The total design load for platform evacuation is the sum of the design load of
awaiting passengers and arriving passengers. This is 640 + 1,166 = 1,806
passengers.
Test 1- Platform Evacuation Assessment
There are 2 staircases and 2 escalators at each end of the platform. The design
requirement is to assume that one of the escalators is out of service due to
maintenance requirements. Using capacity estimates in Error! Reference
source not found., the estimated egress capacity is illustrated in Error!
Reference source not found. below. This suggests that the evacuation rate
from the platform is 454 passengers per minute. It would take just under 4
minutes to evacuate the platform under these conditions. Therefore, the
design meets test 1 which requires platform evacuation in 4 minutes or less.
T ABLE 5-24 : F LOW R ATES OF M EANS OF E GRESS IN S AMPLE P ROBLEM
width
(m)
capacity per
unit width
Effectiveness
Flow
Effective Flow
(pass/min)
(pass/min)
189
75.6
189
75.6
189
76
189
0
454
(Pass/m/min)
Stair 1
Escalator 1
Stair 2
Escalator 2
Total
3
1.2
3
1.2
63
63
63
63
1
1
1
0
120
Walking Time
The station evacuation test requires that all occupants be able to evacuate to a
safe location within 6 minutes. The travel time to a safe location is the sum of
the travel time without any queuing delays plus to queuing delays caused by
restrictions on capacity at stairs and escalators, faregates and doors.
The normal travel time of the person leaving from a point on the platform
farthest from the street is computed. Error! Reference source not found.
below illustrates the computations.
T ABLE 5-25: T IME FROM P LATFORM TO E XIT
Distance (m)
Speed
(m/min)
Time (min)
40
61
0.66
15
0.60
20
61
0.33
concourse to stairs
30
61
0.49
15
0.60
platform to stairs
climb stairs
stairs to street
Total
108
2.68
The platform to stairs time assumes that an occupant is at the farthest possible
distance from a staircase or escalator. The maximum unimpeded time is about
2.7 minutes.
Waiting Time
A separate queuing assessment is made at each location where free flow is
restricted. The four restricted spaces are described in the table below.
The first part is computing the waiting time at the platform exit of the last
exiting passenger. This is the platform evacuation time (computed at 2.68
minutes) minus the walk time of the last passenger to the platform exit. (This
assumes that there will be queue at the platform exit even after walking to the
exit from the point farthest from the exit.
The next barrier is the fare exit barrier. The delay time for this barrier is the
concourse load divided by the fare barrier exit capacity. The design number of
exiting passengers is 1806. The exiting flow capacity of the faregates is 50
passengers per minute. (from table xx). With 8 exit faregates, the time to
evacuate all passengers is 1806/(8 * 50) = 4.5 minutes. The delay time
121
The waiting time at the fare barrier gate by the last exiting person is the fare
barrier flow time minus the platform clearance time of 2.34 minutes.
If the flow capacity of the exit faregates were higher than that of the platform
exit, then the delay time of the last passenger at the faregate would have been
0.
The next step is to assess the delay time at the stairs from the concourse to the
street level. At each of the two exits there is a staircase 3 meters wide. No
escalators are used. From the calculation of the exit capacity from the stairs
from the platform to the concourse, the maximum flow time at the base of the
exit stairway is:
The waiting time at the concourse exit by the last evacuating passenger is
g1
The total exit time is the sum of the unimpeded walk time plus the sum of the
delay time at the three points of restricted flow the stairs from the platform
to the concourse, the faregates and the stairs from the concourse to the street.
122
This egress system does not meet the NFPA standards. Remedies which could
be considered include:
Increasing the exit capacity through the faregates. This might be done
by adding an emergency bypass gate at the faregates. This would
increase flow and reduce additional delay time at the faregates.
123
Transport Division
Transport, Water and
Information and Communication
Technology Department
The World Bank
1818 H Street NW
Washington DC 20433
USA
www.worldbank.org/Transport