02 - Student Lesson 2 Pile Driving System
02 - Student Lesson 2 Pile Driving System
Lesson2ThePileDrivingSystem
Lesson 2
THE
PILE DRIVING
SYSTEM
2-1
Page 2-1
StudentManual
Lesson2ThePileDrivingSystem
Learning Outcomes
Identify Pile Installation Equipment and Tools
Identify various pile types
Use Pile Driving Equipment terminology
Interpret 455 specifications related to the pile
driving system
2-2
Page 2-2
StudentManual
Lesson2ThePileDrivingSystem
2-3
Page 2-3
StudentManual
Lesson2ThePileDrivingSystem
Pile Types
Concrete Piles
Pipe Piles
Steel H-Piles
Composite Piles
Hollow Core Cylinder Piles
Steel Sheet Piles
Timber Piles
2-4
Page 2-4
StudentManual
Lesson2ThePileDrivingSystem
Steel
- H-Pile Sections
- Pipe Sections
Timber
2-5
Page 2-5
StudentManual
Lesson2ThePileDrivingSystem
B. Piling
455-3 Description.
Furnish and install concrete, steel, or wood piling including
driving, jetting, preformed pile holes, cutting off, splicing,
dynamic load testing, and static load testing of piling.
455-4 Classification.
The Department classifies piling as follows:
(1) Treated timber piling.
(2) Prestressed concrete piling.
This course
(3) Steel piling.
(4) Test piling.
(5) Sheet piling.
(a) Concrete sheet piling.
(b) Steel sheet piling.
(6) Polymeric Piles (see Section 471 for requirements).
2-6
Page 2-6
StudentManual
Lesson2ThePileDrivingSystem
2-7
Page 2-7
StudentManual
Lesson2ThePileDrivingSystem
2-8
Page 2-8
StudentManual
Lesson2ThePileDrivingSystem
2-9
Page 2-9
StudentManual
Lesson2ThePileDrivingSystem
2-10
Page 2-10
StudentManual
Lesson2ThePileDrivingSystem
2-11
Page 2-11
StudentManual
Lesson2ThePileDrivingSystem
2-12
Page 2-12
StudentManual
Lesson2ThePileDrivingSystem
Cylinder Piles
Least common of the piles.
54 or 60 diameter
Manufactured for specific project
needs.
Used in corrosive environments.
Used when project is accessible
by large barges and cranes.
Very heavy, requires larger than
typical barges, cranes and
driving equipment.
2-13
Page 2-13
StudentManual
Lesson2ThePileDrivingSystem
2-14
Page 2-14
StudentManual
Lesson2ThePileDrivingSystem
Steel Piling
SIZE
TYPE
STEEL
H Pile
STRUCTURE
TYPE
DESCRIPTION/APPLICATION
H-piles and open end pipe piles are nondisplacement types, closed end pipe is
Bridges, building, another type of displacement pile. Not as
pipelines, towers, common as concrete piles in Florida. Usually
used where long pile over 125 are required
retaining earth
(rule-of-thumb) and where geotechnical
structures, &
information shows extremely variable
others
subsurface conditions or very long piles are
needed. The benefit to steel piles is the ease
of splice. Non displacement piles are also
sometimes used in areas where a large
number of piles are required in a small area
such as under a bascule bridge pier.
2-15
Page 2-15
StudentManual
Lesson2ThePileDrivingSystem
Page 2-16
StudentManual
Lesson2ThePileDrivingSystem
Page 2-17
StudentManual
Lesson2ThePileDrivingSystem
2-18
Page 2-18
StudentManual
Lesson2ThePileDrivingSystem
Composite Piles
2-19
Page 2-19
StudentManual
Lesson2ThePileDrivingSystem
Composite Piles
Used in very hard strata to obtain
penetration of the stinger and
provide tension and lateral
stability
Breakage can be a problem
The stinger will not help the rest
of the pile penetrate deeper
Concrete filled pipes increase
stiffness of pile
Shell or mandrel driven piles are
backfilled with concrete
2-20
Page 2-20
StudentManual
Lesson2ThePileDrivingSystem
455-6.1
Description:
Drive
timber
piles
constructed of round timber of the kind and
dimensions specified in the plans at the locations
and to the elevations shown in the plans, or as
directed by the Engineer.
2-21
Page 2-21
StudentManual
Lesson2ThePileDrivingSystem
Page 2-22
StudentManual
Lesson2ThePileDrivingSystem
Concrete or Steel
Utilized for retaining systems,
such as cofferdams & bulkheads
For retaining systems, steel sheet
piles are driven in the ground
using either impact or vibratory
hammers
2-23
Page 2-23
StudentManual
Lesson2ThePileDrivingSystem
Learning Outcome
Square prestressed concrete piles are considered
non-displacement piles.
True
False
Page 2-24
StudentManual
Lesson2ThePileDrivingSystem
Learning Outcome
Steel H piles are typically used when piles lengths are
expected to be over ___ feet.
A.50
B.75
C.100
D.125
Concrete piles must be cured ___ days prior to ____
and the concrete has achieved the 28-day compressive
strength.
A. 3
B. 7
C. 7
D. 3
driving
driving
shipping
shipping
2-25
Page 2-25
StudentManual
Lesson2ThePileDrivingSystem
2-26
Page 2-26
StudentManual
Lesson2ThePileDrivingSystem
Pile cushion
Pile
2-27
Page 2-27
StudentManual
Lesson2ThePileDrivingSystem
Hammers
Air/Steam
Diesel
Open end
Closed end
Hydraulic
Vibratory
2-28
Page 2-28
StudentManual
Lesson2ThePileDrivingSystem
2-29
Page 2-29
StudentManual
Lesson2ThePileDrivingSystem
Page 2-30
StudentManual
Lesson2ThePileDrivingSystem
In this slide we see an air/steam single acting hammer. This hammer has the
following advantages:
Same stroke each impact
Consistent operation rate
Low impact velocity
More efficient than diesel
Cleaner exhaust than diesel
This hammer has the following disadvantages:
Additional support
equipment required
Heaviest hammer
Not as dependable as diesel
Thick hammer cushion
stack required
Single acting air/steam hammers are essentially gravity, or drop hammers, for whic h
the hoist line has been replaced by a pressuri zed medium, being either steam or air.
While originally developed for steam power, most of these hammers today operate
on compressed air. To lift the ram weight with motive pressure, a simple
onecylinder steam engine principle is used. Durin g the upstroke cycle , the ram is
raised by externally produced air or steam pressure acting against a piston housed in
the hammer cylinder.
The piston, in turn, i s connected to the r am by a r od. During the downstroke cycle,
the ram falls by gravity (less friction) to im pact the striker plate and hammer cushion.
Just before impact, the pressure valve is activated and pressure again enters the
cylinder. These hammers must be equipped with at least two strokes, one full strok e
and another of lesser height called short stroke.
Version 1.0 -1/2015
Page 2-31
StudentManual
Lesson2ThePileDrivingSystem
Slide bar
cams
2-32
The stroke is controlled by the use of a device called slide bar shown in this
picture. The slide bar has cams that trip the valves at fix ed locations. The
maximum stroke of single acting air/ steam hammers generally ranges from 2
to 5 feet. Single acting air/steam hammers have the advantages of moderate
cost and relatively simple operation and maintenance. They are versatile for
many pile types, particularly large concrete and steel pipe piles.
Page 2-32
StudentManual
Lesson2ThePileDrivingSystem
455-5.2.1 Air/Steam
455-5.2.1 Air/steam: 455-5.2.1 Air/steam: Variable
energy air/steam hammers shall be capable of
providing at least two ram stroke lengths. The short
ram stroke length shall be approximately half of the
full stroke for hammers with strokes up to 4 feet and
no more than 2 feet for hammers with maximum
strokes lengths over 4 feet. Operate and maintain
air/steam hammers within the manufacturers
specified ranges. Use a plant and equipment for
steam and air hammers with sufficient capacity to
maintain, under working conditions, the hammer,
volume and pressure specified by the manufacturer.
2-33
Page 2-33
StudentManual
Lesson2ThePileDrivingSystem
455-5.2.1 Air/Steam
455-5.2.1 Air/steam: (Continued)
. Equip the plant and equipment with accurate
pressure gauges which are easily accessible to the
Engineer. The Engineer will not accept final bearing
on piles the Contractor drives with air/steam
hammers unless the Contractor operates the
hammers within 10% of the manufacturers rated
speed in blows per minute, unless otherwise
authorized by the Engineer.
2-34
Page 2-34
StudentManual
Lesson2ThePileDrivingSystem
Page 2-35
StudentManual
Lesson2ThePileDrivingSystem
455-5.2.2 Diesel
455-5.2.2 Diesel: Variable energy diesel hammers shall
have at least three fuel settings that will produce reduced
strokes. Operate and maintain diesel hammers within the
manufacturers specified ranges. Determine the rated
energy of diesel hammers using measured ram stroke
length multiplied by the weight of the ram for open end
hammers and by methods recommended by the
manufacturer for closed end hammers.
2-36
Page 2-36
StudentManual
Lesson2ThePileDrivingSystem
455-5.2.2 Diesel
2-37
Page 2-37
StudentManual
Lesson2ThePileDrivingSystem
Disadvantages
Lowest efficiency
Most difficult to spot
operation problems
2-38
Page 2-38
StudentManual
Lesson2ThePileDrivingSystem
2-39
Page 2-39
StudentManual
Lesson2ThePileDrivingSystem
LINK-BELT SPEEDER
25
23
21
19
17
t
Up
0f
o5
t
Up
15
t. H
e
os
0f
o8
t. H
to
Up
e
os
110
ft. H
ose
13
11
16,000
18,000
20,000
22,000
24,000
26,000
2-40
Page 2-40
StudentManual
Lesson2ThePileDrivingSystem
Hydraulic Hammer
Advantage
Controllable variable stroke
High efficiency blow
Low impact velocity
Light weight
Clean running, quiet
Disadvantage
Need hydraulic power
pack and hoses
Need dedicated person for
hydraulic controls
Repairability / high tech
Expertise in hammer
operation needed
2-41
Page 2-41
StudentManual
Lesson2ThePileDrivingSystem
455-5.2.3 Hydraulic
455-5.2.3 Hydraulic: Variable energy hydraulic hammers
shall have at least three hydraulic control settings that
provide for predictable energy or equivalent ram stroke.
The shortest stroke shall be a maximum of 2 feet for the
driving of concrete piles. The remaining strokes shall
include full stroke and approximately halfway between
minimum and maximum stroke.
Supply hammer instrumentation with electronic read out,
and control unit that allows the operator to read and adjust
the hammer energy or equivalent ram stroke. When
pressure measuring equipment is required to determine
hammer energy, calibrate the pressure measuring
equipment before use.
Page 2-42
2-42
StudentManual
Lesson2ThePileDrivingSystem
Vibratory Hammer
2-43
Page 2-43
StudentManual
Lesson2ThePileDrivingSystem
455-5.2.4 Vibratory
455-5.2.4 Vibratory: Vibratory hammers of sufficient
capacity (force and amplitude) may be used to drive
steel sheet piles and, with approval of the Engineer, to
drive steel bearing piles a sufficient distance to get the
impact hammer on the pile (to stick the pile). The
Engineer will determine the allowable depth of driving
using the vibratory hammer based on site conditions.
However, in all cases, use a power impact hammer for
the last 15 feet or more of the final driving of steel
bearing piles for bearing determinations after all piles in
the bent/pier have been driven with a vibratory hammer.
Do not use vibrating hammers to install concrete piles,
or to install support or reaction piles for a load test.
2-44
Page 2-44
StudentManual
Lesson2ThePileDrivingSystem
Learning Outcomes
Which of the following hammers is NOT to be used to drive
concrete piles?
A. Vibratory
B. Diesel
C. Hydraulic
D. Air/Steam
A bounce chamber pressure gauge is to be provided for which
of the following hammers?
A. Air/Steam
B. Open end diesel
C. Closed end diesel
D. Hydraulic
2-45
Page 2-45
StudentManual
Lesson2ThePileDrivingSystem
Learning Outcomes
A scale or jumpstick is to be provided for which hammer?
A. Closed end diesel
B. Open end diesel
C. Hydraulic
D. Not required on any hammer
A diesel hammer is to have a least ___ fuel settings that
produce reduced strokes.
A. 2
B. 3
C. 4
D. None required
2-46
Page 2-46
StudentManual
Lesson2ThePileDrivingSystem
Hammer
Ram & Anvil
Striker Plate
Hammer Cushion
(Cap Block)
Helmet
2-47
Page 2-47
StudentManual
Lesson2ThePileDrivingSystem
Hammer Cushions
Used on all impact
hammers except gravity
(drop) hammers.
Must be made of
durable
manufactured
(man-made) materials.
Wood, & asbestos not
allowed.
Striker plate must be
used
2-48
Page 2-48
StudentManual
Lesson2ThePileDrivingSystem
Wood
Asbestos
2-49
Page 2-49
StudentManual
Lesson2ThePileDrivingSystem
Page 2-50
StudentManual
Lesson2ThePileDrivingSystem
Page 2-51
StudentManual
Lesson2ThePileDrivingSystem
Pile Cushion
Hammer
Ram & Anvil
Striker Plate
Hammer Cushion
(Cap Block)
Helmet
Pile Cushion
Pile
2-52
Page 2-52
StudentManual
Lesson2ThePileDrivingSystem
Pile Cushion
Used with concrete piles.
Made of pine plywood or
oak lumber
Replaced if compressed
to more than one-half
original thickness.
Replaced if charred,starts
to burn, splintered, or per
the Engineers instruction.
2-53
Page 2-53
StudentManual
Lesson2ThePileDrivingSystem
2-54
Page 2-54
StudentManual
Lesson2ThePileDrivingSystem
2-55
Page 2-55
StudentManual
Lesson2ThePileDrivingSystem
Page 2-56
StudentManual
Lesson2ThePileDrivingSystem
2-57
Page 2-57
StudentManual
Lesson2ThePileDrivingSystem
2-58
Page 2-58
StudentManual
Lesson2ThePileDrivingSystem
2-59
Page 2-59
StudentManual
Lesson2ThePileDrivingSystem
Cranes
JIB GANTRY
JIB
JIB LINES
BOOM LINE
(PENNENTS)
MAIN LINE
BOOM STOPPERS
BOOM
WHIP LINE
YOKE
SPLICE
TOPPING LIFT
HEADACHE
BALL
BOOMGANTRY
CAB
COUNTER
WEIGHT
TURN TABLE
MAIN LOAD
BLOCK
OUTRIGGER
PADS
RADIUS
2-60
Page 2-60
StudentManual
Lesson2ThePileDrivingSystem
Leads
Leads
2-61
Page 2-61
StudentManual
Lesson2ThePileDrivingSystem
Swinging-Lead
CABLE
HAMMER
BOOM
MUST HAVE
TEMPLATE
LEAD
CRANE
PILE
2-62
Page 2-62
StudentManual
Lesson2ThePileDrivingSystem
Semi-fixed Lead
FIXED AT TOP
HAMMER
BOOM
MUST HAVE
TEMPLATE
LEAD
PILE
CRANE
2-63
Page 2-63
StudentManual
Lesson2ThePileDrivingSystem
Fixed Lead
FIXED AT TOP
HAMMER
BOOM
BRACE
TEMPLATE
NOT REQUIRED
LEAD
CRANE
PILE
2-64
Page 2-64
StudentManual
Lesson2ThePileDrivingSystem
Fixed Lead
2-65
Page 2-65
StudentManual
Lesson2ThePileDrivingSystem
455-5.4 Leads
2-66
Page 2-66
StudentManual
Lesson2ThePileDrivingSystem
2-67
Page 2-67
StudentManual
Lesson2ThePileDrivingSystem
Templates
Leads
(swinging)
Template
2-68
Page 2-68
StudentManual
Lesson2ThePileDrivingSystem
Templates
2-69
Page 2-69
StudentManual
Lesson2ThePileDrivingSystem
Templates
CL Plan
As-built CL
15
Pile in
incorrect
position
CL Plan
Template Elev. is 5 ft.
above Pile Cut-off Elev.
Pile in correct
position
2-70
Page 2-70
StudentManual
Lesson2ThePileDrivingSystem
455-5.6 Templates
2-71
Page 2-71
StudentManual
Lesson2ThePileDrivingSystem
455-5.6 Templates
455-5.6 Templates: (Continued)
Supply a stable reference close to the
pile, which is satisfactory in the opinion of the
Engineer, for determination of the pile
penetration. At the time of driving piles, furnish
the Engineer with elevations of the original
ground and template at each pile or pile group
location. Note the highest and lowest elevation
at each required location and the ground
elevation at all piles.
2-72
Page 2-72
StudentManual
Lesson2ThePileDrivingSystem
Acceptable Template?
2-73
Page 2-73
StudentManual
Lesson2ThePileDrivingSystem
2-74
Page 2-74
StudentManual
Lesson2ThePileDrivingSystem
2-75
Page 2-75
StudentManual
Lesson2ThePileDrivingSystem
Anvil
Drill Rod
Split-Barrel
Drive sampler
Seating Spoon6
Second Increment 6
Third Increment 6
SPT
Resistance
(N-value) is
total number of
blows to drive
sampler the 2nd
and 3rd 6 inch
increments
2-76
Page 2-76
StudentManual
Lesson2ThePileDrivingSystem
2-77
Page 2-77
StudentManual
Lesson2ThePileDrivingSystem
Jetting
2-78
Page 2-78
StudentManual
Lesson2ThePileDrivingSystem
Page 2-79
2-79
StudentManual
Lesson2ThePileDrivingSystem
Page 2-80
StudentManual
Lesson2ThePileDrivingSystem
2-81
Page 2-81
StudentManual
Lesson2ThePileDrivingSystem
Punches
Punch
Combination Jet/Punch
2-82
Page 2-82
StudentManual
Lesson2ThePileDrivingSystem
Drilling/Augering
2-83
Soil augers or drills is one of the tools frequently used to install piles. Predrilling is used to
perform the following:
-Install piles by preforming holes or predrilling through soils with obstructions, such as old
timbers, boulders, and riprap.
-Install piles through soil embankments.
-Drill a starter hole.
-To assist in the advancement of the piles through very dense materials that prevent the
piles to reach a minimum penetration.
-To reduce pile heave when displacement piles are driven at close spacings.
-To predrill holes in order to minimize vibrations
--Where jetting or punching are not allowed by the Contract documents.
Page 2-83
StudentManual
Lesson2ThePileDrivingSystem
Drilling/Augering
2-84
Page 2-84
StudentManual
Lesson2ThePileDrivingSystem
Followers
2-85
Page 2-85
StudentManual
Lesson2ThePileDrivingSystem
Followers
455-5.5 Followers: Use followers only for underwater
driving. Obtain the Engineers approval for the type of
follower, when used, and the method of connection to
the leads and pile. Use followers constructed of steel
with an adequate cross-section to withstand driving
stresses. When driving concrete piles, ensure that the
cross-sectional area of the follower is at least 18% of the
cross-sectional area of the pile. When driving steel piles,
ensure that the cross-sectional area of the follower is
greater than or equal to the cross-sectional area of the
pile. Provide a pile helmet at the lower end of the
follower sized according to the requirements of 4555.3.3.
2-86
Page 2-86
StudentManual
Lesson2ThePileDrivingSystem
Followers
455-5.5 Followers: (continued) .Use followers
constructed that maintain the alignment of the pile,
follower, and hammer and still allow the pile to be driven
within the allowable tolerances. Use followers designed
with guides adapted to the leads that maintain the
hammer, follower, and the piles in alignment.
Use information from driving full length piles described in
455-5.1.2 compared to driving piles with the follower
and/or dynamic load tests described in 455-5.13 to
evaluate the adequacy of the follower and to establish
the blow count criteria when using the follower.
2-87
Page 2-87
StudentManual
Lesson2ThePileDrivingSystem
Learning Outcome
Which of the following leads does not require the use of a
template?
A. Swinging
B. Semi-fixed
C. Fixed
D. None require the use of a template
2-88
Page 2-88
StudentManual
Lesson2ThePileDrivingSystem
Learning Outcome
When jetting & driving, the jets should be positioned approx.
___ ft. behind the pile tip.
A. 2
B. 3
C. 4
D. 5
Jetting in the embankment is permitted when ____.
A. Not permitted
B. Anytime
C. Embankment heights are less than 10 feet
D. Embankment heights less than 20 feet
2-89
Page 2-89
StudentManual
Lesson2ThePileDrivingSystem
Learning Outcomes
2-90
Page 2-90
StudentManual
Lesson2ThePileDrivingSystem
End of Lesson 1
ANY
QUESTIONS ?
1-91
Page 2-91