PM3.5 Planning Budgeting
PM3.5 Planning Budgeting
Budgeting
Initial Release
1.0
Date:
January 1997
Overview of Project
Budgeting
To develop the budget, the applicable cost factors associated with the project
tasks are identified. The development of costs for each task should be simple
and direct and consist of labor, material, and other direct costs. Cost of
performing a task is directly related to the personnel assigned to the task, the
duration of the task, and the cost of any non-labor items required by the task.
Budget estimates are obtained from the people responsible for managing the
work efforts. This provides the expertise required to make the estimate and
provides buy-in and accountability during the actual performance of the task.
These team members identify people or labor categories required to perform the
work and multiply the cost of the labor by the number of hours required to
complete the task, as discussed in scheduling. Determining how long the task
performance takes is the single most difficult part of deriving a cost estimate.
The Labor costs should factor in vacation time, sick leave, breaks, meetings ,
and other day-to-day activities. Not including these factors jeopardizes both
scheduling and cost estimates.
In calculating the cost of labor, be certain to burden the costs appropriately for
your organization. Burdened cost typically refers to the overhead and general
expenses associated with an employee. These costs are beyond strict salary
expenses (e.g., office space, benefits, etc.).
Non-labor charges include such items as material costs, reproduction, travel,
cost of capital (if leasing equipment), computer center charges, and equipment
costs.
PM Planning
Budgeting
Page 1
Labor and non-labor cost information is entered into a cost estimation system or
spreadsheet, depending upon the complexity of the project. Spreadsheets work
well for projects of small to medium scope. A sample of a budget using a
spreadsheet is shown below.
Activity Description
2.0
DESIGN
2.1
Analysis in Hours
Analysis in Dollars
Budget Actual
Est to
Est @
Variance
hours hours Complete Complete (+=More)
900
1,150
1,150
250
90,000 115,000
115,000
2.1.1
400
500
500
100
40,000
50,000
50,000
10,000
2.1.2
300
250
250
(50)
30,000
25,000
25,000
(5,000)
2.1.3
40,000
2.2
200
400
400
200
20,000
1,000
640
408
1,048
48
100,000 64,000
25,000
40,000
20,000
40,8000
104,800
4,800
2.2.1
600
600
608
60,000
60,000
800
60,800
800
2.2.2
400
40
400
440
40
40,000
4,000
40,000
44,000
4,000
430
430
430
43,000
43,000
43,000
430
430
43,000
43,000
43,000
1676
5,256
646
167,600
525,600
59,600
2.3
2.3.1
2.4
Document Design
430
10
160
4,820
3,620
466,000 358,000
For large systems, a project management tool is typically preferred for cost
estimation. A Project Estimate Summary worksheet, included at the end of this
section, is another appropriate model for costing and can be useful if completed
prior to entering information into a tool. Tasks included in this sample should
be tailored to specific project cases.
Costs are assigned to the lowest level WBS work package task. These costs are
then combined to determine a sub-task cost. In turn, these are combined to
determine the overall task cost, which can be summed to find the total project
cost.
PM Planning
Budgeting
Page 2
Document
Assumptions
Budget for those tasks where risks are inherent. There is no rule
of thumb for this multiplier; it depends on the degree of risk and
the overall importance of the task to the project.
Development of project budgets typically require more than one person. Rarely
does a single individual have the knowledge and understanding of all the factors
affecting every aspect of a project. A good process is to have the same people
that reviewed the activity list and schedule, review the budget.
Upon completion of a draft budget, interview the team and determine if the
work descriptions, schedule and associated budgets are complete and accurate.
Determine if there is a common understanding of what it costs to do the tasks.
Get independent estimates. Where there are significant differences, determine
the reasons and either redefine the work packages, schedule, and budgets or
review and reiterate the estimates.
PM Planning
Budgeting
Page 3
A large component of the budget is labor costs. Carefully determine that the
reviewer is providing an estimate of the calendar time required to perform the
task based on the actual labor hours needed. The total labor days per phase can
also be checked against the rule of thumb that suggests the following
distribution of development project effort and cost:
Form:
The project budget is included in the project management plan template as the
Estimate to Complete. The initial project budget is shown in the budgeted
columns and the actual expenditures are compared on a regular basis to the
plan.
PM Planning
Budgeting
Page 4
Form: PM 04
Project Estimate Summary Worksheet - Sample
Customer: ________________________________
Project: __________________________________
Date: _________________
Project Task
1.
Labor
Hour
Labor
Cost
Material
Cost
Travel
Cost
Other
Cost
Total per
Task
Project Design
1.1
Develop Functional
Specifications
1.2
1.3
1.4
1.5
2.
Project Development
2.1
Develop Components
2.2
Procure Hardware
2.3
Development Acceptance
test Package
2.4
Perform Unit/Integration
Test
3.
Install System
4.
Train Users
5.
6.
PM Planning
Budgeting
Page 5
Project Task
7.
8.
Archive Materials
9.
Project Management
9.1
Customer Progress
Meetings/Reports
9.2
Internal Status
Meetings/Reports
9.3
9.4
9.5
Configuration Management
9.6
Quality Assurance
Labor
Hour
Labor
Cost
Material
Cost
Travel
Cost
Other
Cost
Total per
Task
Other:
TOTAL (scheduled)
Comments: (List assumptions for costs as appropriate.)
PM Planning
Budgeting
Page 6