EE2401 Power System Operation and Control
EE2401 Power System Operation and Control
: EE2401
Power System Operation and Control
IV year
VII semester EEE 2008 Regulation
PREPARED BY,
M.ULAGAMMAI
AP(SG)/EEE
Two Marks:
1. What is Load curve?
Ans:The curve drawn between the variations of load on the power
station with reference to time is known as load curve. There are
three types namely Daily load curve, Monthly load curve and
annual load curve.
2. What is Daily load curve?
Ans:The curve drawn between the variations of load on the power
station with reference to the various time periods of a day is
called as Daily load curve.
3. What is connected load?
Ans:It is the sum of continuous rating of all the equipments
connected to the supply systems.
4. What is demand factor?
Ans:It is the ratio of maximum demand to connected load.
D.F = Maximum demand / Connected load
5. What is load factor?
Ans:The ratio of average load to the maximum demand for a given
period is called as Load factor
6. What is diversity factor?
Ans:The ratio of sum of individual maximum demand to the
maximum demand of the power station is called as Diversity
factor
7. What is capacity factor?
Ans:The ratio of actual energy produced to the maximum possible
energy that could have been produced during a given period.
8. What is plant use factor?
4500 KW
6 8 hr
3500 KW
8 12 hr -
7500 KW
12 14 hr
2000 KW
14 18 hr
8000 KW
18 20 hr
2500 KW
20 24 hr
5000 KW
Load Factor=
Unitsgenerated 1,25,000
=
=5208 KW
Time hrs
24
Average Load
5208
=
=65.1
maximumdemand 8000
Average demand
X 100
Ratedcapacity of plant
5208
X 100=43.4
12000
Hot reserve
The generators are conventionally able to be brought on-line is
less than 10 minutes, a slower contingent of reserves, or hot
reserve, can be kept available. The hot reserve is capacity
generally provided by thermal generation where the turboalternator is shut down but the boiler is left in a hot state.
Thus, some regions like New York and New England require
additional reserve that must be fully available within 30 minutes.
California ISO requires a replacement reserve to be fully
available within 60 minutes. This additional reserve
(replacement, secondary) is used to redispatch after
contingencies and to restore operating reserve requirements.
Cold reserve
Literally, reserve energy which is currently cold. Refers
specifically to energy produced by thermal generators which is
available but not currently operating, and derives from the fact
that an available, nonfunctional oven or steam boiler is colder
than one which is in operation.
3. Explain in detail about the power system operation.
Overview of system operation
Load forecasting
Load forecasting is simply defined as a systematic procedure for
quantitatively defining future loads. It is a methodology to be
performed as a part of the systems planning. For the addition of
*Intermediate
*Long term
techniques
Factors affecting load forecasting
The factors effecting load forecasting are
a) Geographic factors
b) Historical data
c) Population growth
d) Load density
e) Alternative energy sources
f) Community development plans
g) Industries plans
h) City plans
i) Land use
Forecasting techniques
Forecasting techniques may be divided into three broad classes
(i) Extrapolation technique
(ii) Correlation technique
(iii) Combination of both
Unit Commitment
The process of committing the generating units to be ON or OFF
is called unit commitment. This unit commitment deals with the
scheduling the ON/OFF status of the generating units. The
resultant schedule should minimise the production cost during
(iii) Feeders
The voltage control can be achieved by the following methods
a)
b)
c)
d)
By excitation control
Static VAR compensators
Tap changing transformers
Static shunt capacitors, shunt
reactors,
series
capacitors,
synchronous condensers.
TWO MARKS:
1. What is the major control loops used in large generators?
Ans : The major control loops used in large generators are
1. Automatic voltage regulator (AVR)
2. Automatic load frequency control (ALFC).
2. What is the use of secondary loop?
Ans : A slower secondary loop maintains the fine adjustment of the
frequency, and also by reset action maintains proper MW
interchange with other pool members. This loop is insensitive to
rapid load and frequency changes but focuses instead on drift like
changes which take place over periods of minutes.
3. What is the adv of AVR loop over ALFC?
Ans : AVR loop is much faster than the ALFC loop and therefore
there is a tendency, for the VR dynamics to settle down before
they can make themselves felt in the slower load frequency
control channel.
4. What is the diff. between large and small signal analysis?
Ans : Large signal analysis is used where voltage and power may
undergo sudden changes of magnitude that may approach 100
reasons.
All the AC motors should be given constant frequency supply so
as to maintain speed constant.
In continuous process industry, it affects the operation of the
process itself.
For synchronous operation of various units in the power system
network, it is necessary to maintain frequency constant.
16. What is damping factor?
Ans :
PART B
16 MARKS
1. What are the components of speed governor system? Derive
its transfer function with an aid of block diagram.
The speed governor is the main device for load frequency control. It
consists of the following components.
Speed Governor:
This is the mechanical speed sensitive device coupled directly to
and built directly on to prime movers to adjust the increased
speed. It senses the change in speed or frequency. For example
when the speed increase the flywheel move towards and point B
Modelling:
Pg
at a
Pc
X A =K Pc . ------- (1)
XA
-------------------------- (2)
K 1K 2
-------------------------- (3)
K 3K 4
linkage arms 3 and 4. The oil flows into the hydraulic motor and it
is proportional to X D of the pilot valve.
X D
X E =K 5
-------------------------------------- (4)
The constant
K5
X E ( s )=
K 5 X D
s
--------------------(6)
--------------------------------------- (7)
Eliminating X c ( s ) and X D ( s )
X E ( s )=
K 5
[ K 3 X c ( s )+ K 4 X E ( s ) ]
s
K
[ 1 F ( s )K 2 Pc (s)]+ K 4 X E ( s )
K 3
K
5
s
K 4 K 5 K 5
=
[ K 3 K 1 F ( s )K 3 K 2 Pc (s )]
s
s
X E ( s ) 1+
X E ( s )=
K5
K
K K 1 F ( s ) K 3 K 2 5 Pc ( s )
s 3
s
1+
K4 K5
s
On simplifying
[ K 3 K 2 Pc ( s ) K 3 K 1 F ( s ) ]
K4+
[ K 3 K 2 Pc ( s ) K 3 K 1 F ( s ) ]
K 4 1+
s
K4K5
K 3 K 2 Pc ( s )
s
K5
K 4 1+
K1
F ( s)
K2
s
K4K5
KG
1
P c ( s ) F ( s )
1+s T G
R
Where
K G= K 3
K2
1
T G=
R=K 2 / K 1
K4
K4 K5
KG
1+ s T G
Turbine Model:
General representation of turbine model is given by
GT ( s )=
KT
PG (s)
=
1+s T T X E ( s )
PG ( s ) =
KGKT
F ( s)
[ Pc ( s )
]
R
( 1+ s T G )( 1+ s T T )
KGKT
( 1+ s T G )( 1+ s T T )
[ Pc ( s ) ]
(i.e) F ( s ) = 0;
Case (i):
A step change of Pc ( s ) is made to find the steady state change in
the generator output.
Pc ( s ) =
Pc
s
PG ( s ) =
KGKT
[ Pc /s ]
( 1+ s T G )( 1+ s T T )
s PG ( s )= PG ( static )=
KGKT
( 1+ s T G )( 1+ s T T )
[ Pc ]
Assuming
Case (ii) :
K G K T =1
, PG ( static )=[ Pc ]
PG ( s )=
KGKT
F ( s )
]
R
( 1+ s T G )( 1+ s T T )
and T G T T 0K G K T =1
F ( s ) = F / s
PG ( s ) =
F
sR
s PG ( s )= PG ( static )=
F
F
t h erefore
RHz / MW
R
PG
1
F( s) G ( s ) P D ( s ) G p ( s ) = F (s)
R
F ( s ) 1+
F ( s) =
1
G ( s ) G p ( s ) = P D ( s ) G p ( s )
R
PD ( s ) G p ( s )
1+
1 ( ) ( )
G s Gp s
R
Static Analysis:
P D ( s )=
PD
s
s0
P D ( s ) G p ( s )
1+
1 ( ) ( )
G s Gp s
R
K p P D
1
1+ K p
R
Therefore
Kp
1
P D w h ere K p = Hz / puMW
1
D
1+ K p
R
( )
Fstatic=
P D P D
1/ D
P D=
=
1/ D
1
1+
D+
R
R
( )
Fstatic=
Where
=D+
1
puMw /Hz
R
Fstatic=
PD
Dynamic Analysis:
Letting TG = TT = 0 and KGKT =1;
F ( S)=
Kp
PD
(
)
(1+ s T p )
s
1+
Kp
1
R (1+s T p )
On simplifying
F ( S)=
PD K p R 1
R+ K p s
1
R+K p
s+
Tp R
Dynamic response:
To control the dynamic frequency changes with step load change,
an integral controller is added which activates the speed changer
by real power command signal Pc .
Pc ( s ) =
K I
F ( s)
s
PD
s
K I
1
F ( s ) F ( s ) P D ( s ) G p ( s )= F ( s )
s
R
F ( s ) 1+
( Ks + R1 ) (1+sK T ) ]= sP
I
Kp
(1+ s T p )
1
K s
R p
s = PD K p
F (s)
(1+s T p )+ K I K p +
(1+ s T p)+ K I K p +
s
t h erefore F ( s )=
F ( s) =
1
K s
R p
PD K p
P D K p
s T p +s 1+
1
K + KI K p
R p
PD K p /T p
[ (
s 2+ s
K K
1
1
+
Kp + I p
T p RT p
Tp
K K
1
1
+
Kp + I p
Tp RT p
Tp
Kp
R
2T p
1+
Kp
R
2T p
s+
K
1+ p
R
2T p
1+
Kp
R
2T p
1+
If KIKp/Tp>
Then,
Kp
1
KI >
(1+ )
4 K pT p
R
If KI> Kcritical, then the denominator roots are positive and real.
This is super critical case and the response is damped oscillatory.
If KI< Kcritical, it is sub critical case and the response contains
exponential terms
Static response:
(1+s T p )+ K I K p +
1
K s
R p
PD K p
F ( s )=
Fstatic=lim s F ( s )=0
s0
X h
X
=
=2 X =200 hh=
200 2
100
600X
h
=
400
2.5
( 100X )=4 X
X
230.76
=
=2.31
100
100
TWO MARKS:
1. What are the sources of reactive power? How it is
controlled?
Ans: The sources of reactive power are generators, capacitors, and
reactors.
These are controlled by field excitation.
Give some excitation system amplifier.
The excitation system amplifiers are,
a) Magnetic amplifier
b) Rotating amplifier
c) Modern electronic amplifier.
2. When is feedback stability compensation used?
Ans : High loop gain is needed for static accuracy but this causes
undesirable dynamic response, possibly instability. This
conflicting situation is resolved by adding feedback stabling
compensation to the AVR loop.
3. Give the characteristics of line compensators?
Ans : The characteristics of line compensators are,
a. Ferranti effect is minimized.
b. Under excited operation of synchronous generator is not
required.
4. What is known as bank of capacitors? How it is adjusted?
Ans : When a number of capacitors are connected in parallel to get
the desired capacitance, it is known as bank of capacitors. These
can be adjusted in steps by switching (mechanical).
5. What is the disadvantage of switched capacitors are
employed for compensation?
characteristics
16.How the TSCs are characterized?
Ans : TSCs are characterized by step wise control, no transients,
very low harmonics, low
losses, redundancy and flexibility.
17.Write the expression of effective reactance in series
compensation.
Ans :
XL = X - Xc
Where, XL = Line reactance
XC = Capacitor reactance
18.List the advantages of series compensation.
Ans : The advantages of series compensation are,
a. Series capacitors are inherently self-regulating and a control
system is not
required.
b. For voltage stability, series capacitors lower the critical
c. Series capacitors possess adequate time-overload capability.
d. For the same performance, series capacitors are often less costly
than SVCs and
losses are very low.
19. What is active compensation?
Ans :
PART B
16 MARKS
1. Draw the block diagram of Automatic voltage regulator and
derive its transfer function. Explain its static and dynamic
analysis.
Functions of AVR:
For an isolated generator, AVR is used to maintain the bus bar
voltage constant
To keep system voltage constant, so that the connected
equipments are satisfactory
To improve stability
To obtain suitable distribution of reactive power load between
machines working in parallel.
With sudden disturbances like load fluctuations, the AVR is
required to reduce magnitude and duration of load variations
AVR senses the terminal voltage and adjusts the excitation to
maintain constant terminal voltage and also maintains reactive
power control
One generator with AVR is used to maintain bus bar voltage while
the excitation of the rest are used to distribute properly VAR
among the generators
(ii) Amplifier:
This device is characterized by a gain factor KA and time constant
TA (TA< 100 ms)
Transfer function of amplifier =
KA
=V 2 (s)/V 1 (s)
(1+s T A )
(iii) Exciter:
It is basically an amplifier and its transfer function is :
KE
=V r (s)/ V 2( s)
(1+s T E )
(iv) Generator:
The transfer function of generator depends upon nominal operating
state of generator. Stator currents are neglected and direct axis
component id is negligible in magnitude and rotor voltage is
V r =r r i r + Lr
d ir
=r r i r + s i r Lr =i r (r r +s Lr )
dt
ir L s
2
Kr
Ls
V ( s)
=
w h ere K r =
T =L /r
V r ( s ) (1+ s T r )
2(r r ) r r r
d i st
di
V r=r i st + L st
dt
dt
V st ( s )
sM i st
s K st
M
L
=
=
w h ere K st = T st =
R
R
V r ( s ) (R +sL)i st (1+s T st )
Static Analysis:
The above block diagram can be reduced as
p
|V |
100 ref
G (s )
|V |=
G ( s)
e 0=|V ref |
[1
G( 0)
p
]|V ref |<
|V |
100 ref
1+G ( 0 )
Taking LCM,
1+G ( 0 )G ( 0 )
p
V ref |<
|
|V |
100 ref
1+ G ( 0 )
1
1
V ref|=
|
|V |
1+
k ref
1+G ( 0 )
Therefore
1
p
|V |< |V |
1+ k ref 100 ref
1
p
100
100
<
=K +1>
=K >
1
1+ k 100
p
p
Dynamic analysis:
From the closed loop model
1+G(s)
|V | G ( s )
=
|V ref |
1+G( s)
G (s )
|V ( t)|=L1
K
(1+s T A )(1+ s T E )(1+ s T r )
V P 1 V Q
.
=
.
=1
P V
Q V
Therefore :
dV =
dP
dQ
+
P Q
(
)
V
V
P
Q
V
V
( PV jQ )( R+ jX )
drop=Real
Therefore
drop=
PR+Q X
V
V =V 1V =
PR+QX
V
V
( 1V )V =PR+QX
V
( 1V V 2QX )/R
P=
V
( 1V V 2PR )/ X
Q=
Partially differentiating
V
( 12 V )/ R
P
=
V
V
( 12 V )/ X
Q
=
V
Therefore
V
V
( 12 V )/ X
dQ
( 12V )/ R+
dP
dQ dP
dV =
+
=
P Q
(
)
V
V
V
(12V )
R dP+ X dQ
dV =
V
( 12 V )=0 =RdP=XdQ
RdP+ XdQ
Therefore
( RX ) dP
dQ=
In general
Q
V
experimentally
Q
V
Q
V
drop
Q
V
on network configuration
(b)
Static series capacitors
(c)
Synchronous compensators
(ii) Tap changing Transformers
(iii) Booster transformers
(iv) Regulating transformers
(v) Static VAR compensators
(i) Injection of Reactive Power
Injection of reactive power is done to minimize the transmission
losses and to improve voltage profile
(a) Shunt Capacitors:
The function of shunt capacitor applied as single unit or group of
units is to supply lagging VAR to the system at the point where
they are connected
It has the same effect as an over excited synchronous condensers
or motors
It is the cheapest means of Q supply
It is mainly used for power factor correction at load terminals of
low voltage
When voltage falls, Q produced by shunt capacitor falls. When
voltage raises, capacitor output is large. The voltage control is
not smooth in shunt capacitors
It is applied at the load end of the circuit breaker because (i) it
increases the voltage level at the load (ii) reduces losses (iii)
Increases power factor of source generators (iv)Improves voltage
regulation and (v) Decreases KVA loading
(b) Series capacitors:
They are connected in series with the line and are used to reduce
inductive reactance between supply and load
One major drawback with series capacitor is the high over
voltage produced when short circuit current flows through it
They are used to compensate the effect of series X when a
capacitor with reactance Xc is connected. The reactance of line
can be achieved
When the line voltage varies beyond certain set value, the voltage
sensitive relay connected is actuated either to close raise
contacts or lower contacts. The driven motor rotates in
required direction to achieve tap changing. The motor stops
automatically after changing the tap as the unit switch provided
in the mechanism operates.
Thus the tap changing on load tap changer provides automatic
regulation of bus bar voltage.
Derivation of nominal ratio (ts) :
Ts&tr are fractions of nominal transformation ratios (i.e) tap
ratio/nominal ratio
For example a transformer a nominal ratio 6.6 kv to 33 kv, when
tapped to give 6.6 to 33 kv has a ts = 36/33 = 1.09
V1 and V2 are the nominal voltages at the end of the lines and the
actual voltage being ts V1 and tr V2.
ts tr =1 (i.e) voltage level remains in same order.
V s=t s V 1V r =t r V 2
t s V 1 =V s=V r + IZ=t r V 2+ IZ
w.k.t,
V =V 1V =
V =IZ =
PR+QX
V
PR+QX PR+QX
=
V
tr V 2
Therefore
t s V 1 =t r V 2 +
PR+ QX
tr V 2
Also ,
t s t r =1t r=
t s=t r
t s=
1
ts
V 2 PR+QX
+
V 1 t r V 1V 2
1 V 2 PR+QX
+
t
ts V 1
V 1V 2 s
V 2 PR+QX 2
+
t
V1 V1V2 s
Therefore,
t s2 [1
PR+QX V 2
]=
V 1V 2
V1
TWOMARKS
1. Define economic dispatch problem?
Ans: The objective of economic dispatch problem is to minimize the
operating cost of active power generation.
2. Define incremental cost?
Ans: The rate of change of fuel cost with active power generation is
called incremental cost. Write the load balance equation? Pg-pdpl=0.
3. Define base point?
Ans: The present operating point of the system is called base point.
4. Define participation factor?
Ans: The change in generation required to meet power demand is
called as participation factor.
5. Define hydrothermal scheduling problem?
Ans: The objective is to minimize the thermal generation cost with
the constraints of water availability.
6. Define Unit commitment?
Ans: Commitment of minimum generator to meet the required
demand.
7. Define spinning reserve?
Ans: It is the term to describe the total amount of generation
availability from all units synchronized on the system.
8. What is meant by scheduled reserve?
Ans: These include quick start diesel turbine units as well as most
hydro units and pumped storage hydro units that can be brought
online, synchronized and brought up to full capacity quickly.
9. What are the thermal unit constraint?
Ans: The problem involves the long range of water availability and
scheduling of reservoir water releases. For an interval of time
that depends on the reservoir capacities.
17. What are the optimization techniques for long range
hydro scheduling problem?
Ans: Dynamic programming composite hydraulic simulation
methods statistical production cost.
18. Define short range hydro scheduling problem?
Ans: It involves the hour by hour scheduling of all generators on a
system to achieve minimum production condition for the given
time period.
19. Define system blackout problem?
Ans: If any event occurs on a system that leaves it operating with
limits violated, the event may be followed by a series of further
actions that switch other equipment out of service. If the process
of cascading failures continues, the entire system of it may
completely collapse. This is referred as system blackout.
20. What is meant by cascading outages?
Ans: If one of the remaining lines is now too heavily loaded, it may
open due to relay action, thereby causing even more load on the
remaining lines. This type of process is often termed as cascading
outage.
PART B
16 MARKS
Pcost
[ ( k , I ) + Scost ( k 1, L ; K , I ) + F cost (k 1, L) ]
F cost ( k , I )=min
{ L}
Where
Pcost ( k , I )
Fcost ( k , I )
Min
Max
gen.
150
gen
600
Heat rate
Fuel
510+7.2P1+0.001
cost
1.1
2
42 P1
100
400
310+7852P2+0.00
1.0
2
194 P2
50
200
78+7.97P3+0.004
2
8 P3
1.2
Priority order:
Unit
Min
Max
FLAP
2
1
3
gen.
100
150
50
gen
400
600
200
9.48
9.79
11.188
Min
gen.
300
250
100
Max
gen
1200
1000
400
Min F T = Fi ( Pi )
i=1
N
L=F T +
= Pi (Pload + Ploss )
Where
i=1
Differentiating w.r.t
Pi
Pload P loss
L FT
=
+
+
1 =0
Pi P i
Pi
Pi
d Fi
Ploss
+
1 =0
d Pi
Pi
d Fi
Ploss
=
1
d Pi
Pi
Ploss
Pi
Where
[
[
d Fi
P
= 1 loss
d Pi
Pi
d Fi
P
=
1 loss
d Pi
Pi
=
]
]
d Fi
PF
d Pi
P
PF= 1 loss
Pi
Ploss= P m Bmn Pn
m
Solution Technique:
Consider a three unit system. Assume an incremental cost rate
Find the power outputs of each of the 3 units for this value of
At the end of first iteration if the error is negative the increase
by 10% and try another solution
Otherwise decrease by 10% and proceed
By keeping track of total demand (vs) incremental cost, the
desired operating point can be found
Stopping rule based on tolerance or maximum number of
iterations
'
Fi and
''
Fi
to
0 + .
d Fi
=F 'i
d Pi
d i
=F 'i'
d Pi
''
; i= PiF i ( Pi ) =
''
For N units: P1= / F 1 ( P 1)
P N = / F ''N ( P N )
P D=
i=1
1
F 'i '
Where,
P D=Pload + Ploss
Participation Factor:
N
Pi
1
= '' /( ' ' )
PD
Fi
i=1 F i
( )
Participation factor
1
''
Fi
P.f=
1
N
F1' '
i =1
i
Pnewi =P basei +
Pi
( PD PD
F2
500+27P2+0.1
P22
F3 =
900+16P3+0.07
P3
d F 1 d F2 d F 3
=
=
d P1 d P 2 d P 3
d F1
=21.5+ 0.05 P 1
d P1
d F2
=27+0.2 P 2
d P2
d F3
=16+0.14 P3
d P3
d F 1 d F2
=
=21.5+0.1 P 1=27+0.2 P2
d P1 d P2
Therefore :P 1=55+2 P 2
d F 2 d F3
=
=27+0.2 P2=16+ 0.14 P3
d P2 d P 3
Therefore :P 3=78.57+1.43 P2
P1+ P 2+ P3 =200
Therefore
P2=15 Mw
d F 1 d F3
=
=21.5+0.1 P 1=16+0.14 P3
d P1 d P 3
21.5+0.1(161P 3)=16+ 0.14 P3
Therefore
Therefore
P3=90 Mw
P1=16190=71 Mw
Fuel cost:
At
P1=71 Mw : F1=2578.5
Rs
hr
TWO MARKS:
1. What are the functions of control center?
Ans: System monitoring contingency analysis security constrained
optimal power flow.
2. What is the function of system monitoring?
Ans: System monitoring provides upto date information about the
power system.
3. Define scada system?
Ans: It stands for supervisory control and data acquisition system,
allows a few operators to monitor the generation and high
voltage transmission systems and to take action to correct
overloads.
4. What are the states of power system?
Ans: Normal state alert mode contingency mode emergency mode.
Define normal mode? The system is in secure even the
occurrence of all possible outages has been simulated the system
remain secure is called normal mode.
5. Define alert mode?
Ans: The occurrence of all possible outages the system does not
remain in the secure is called alert mode.
6. What are the distribution factors?
Ans: Line outage distribution factor, generation outage distribution
factor.
:
It is an integral part of the power system
:
It means committing a generating unit(i.e
State estimation :
It is the process of estimating the state of the power
generation. State estimation based on system monitoring data
produces the best estimate of latest power system condition.
SCADA
Configuration:
Computer receives data from RTOS via the
Normal state:
A. All the constraints are satisfied.
B. Reserve margin is high to meet the system well secured.
C. when the security level falls below certain level or when
disturbance increases, the system enters into Alert state
Alert state:
a. It is the state, all the constraints are satisfies.
b. Reserve margin is not sufficient to deal with the disturbances.
c. If the disturbance is present some of the inequality constraints
will not be sacrificed
d. But corrective actions taken in time may bring conditions
satisfied and bring back the system to normal state.
e. But if severe disturbance occurs then the system is pushed to
emergency state.
Emergency state:
a. In this state, system is totally insecure .inequality constraints are
violated.
Security monitoring :
The estimated quantities are compared against overload
3. Security assessment :
After state estimation, security assessments have to
be carried out. All the bus voltages and loadings are compared
with their respective limits. if any limit violation, system is
insecure and insecurity enhancement procedures have to be
carried out. If not, the system is said to be in secure mode. In
such case, security assessment studies are continued.
The various possible outages that may occur in the system are
simulated one at a time and their effects are studied. If the
system is secure for all possible outages, the system is in normal
mode and security enhancement procedures are not necessary. If
the system is insecure for at-least one outage, system is said to
be in alert mode and security enhancement procedures are
carried out to bring it to normal state.
4. Security Enhancement