Fuse Quick Start Guide
Fuse Quick Start Guide
S1 // Projects Tab
Use the Get External Data toolbar to set up the Fuse workbook by linking to a single or multiple
schedules, cost estimates, or risk models. Import baseline schedules or project snapshots here as well.
S2 // Diagnostics Tab
Set up your analysis by selecting the grouping and time phases you want to see. Then, hit Fuse to run
the analysis.
Change the activity browser view or publish the results to a report.
Phase options
Grouping options
Fuse analysis
Reporting options
Metric Analysis
Ribbons
Ribbon Analyzer
Activity Browser
S5 // Dashboard Tab
Now that the Fuse workbook has been set up, view
the dashboard by selecting the dashboard tab to get
a high level overview of project status and quality.
Click on an image to view the driving activities or
additional information.
S2 // Logic Tab
Forensics Tab
Before using the forensics tab, you must load project snapshots to compare against one another. On
the projects tab, select the project you want to compare to. While the project is highlighted, use the
Get External Data toolbar to add a snapshot for comparison. Once you have loaded all of your
snapshots, click the forensics tab to view variances between them.
Use the toolbar at the top of the forensics tab to select attributes for Fuses variance analysis. Publish
this view to Excel for a project forensics report. Drag column headings to the top to group results or
select a column heading to sort results by.
Metrics Tab
2. Compare variances
3. Select field
4. Select function
5. Write in value or
select field
On the projects tab use the Get External Data toolbar to link to a single project or multiple projects.
2. Apply Uncertainty
Use the uncertainty sliders to apply duration or cost uncertainty to a single activity or groups of
activities. Move the slider left (more conservative) or right (more aggressive) at any hierarchical level.
The assignments automatically cascade down to any children.
Click the matrix icon to the right of the sliders to add a new risk event the event will be mapped
automatically to the selected activity or group of activities.
When youre satisfied with your risk and uncertainty loading, choose the drop down menu of the Run
Risk Analysis icon to choose which risk analysis/scenario you would like to run.
Choose the risk drivers report from the Right Panel menu to view schedule and cost risk drivers.
Using the Acumen Risk Contribution Factor, find out how much impact activities and risk events
have on any given milestone or group of activities.