United States Court of Appeals, Tenth Circuit
United States Court of Appeals, Tenth Circuit
2d 677
60 USLW 2204, 15 UCC Rep.Serv.2d 854
District Judge.*
BRETT, District Judge
4
This diversity action arises out of a series of six gas purchase contracts between
the sellers, Prenalta Corporation, twelve individuals,1 and The Spelpren
Company, who own working interests in various natural gas wells located in
Sweetwater County, Wyoming ("Prenalta"), and the buyer, Colorado Interstate
Gas Company ("CIG"), an interstate gas pipeline company. Prenalta brought
this action for declaratory relief against CIG concerning the price of
deregulated gas under Contracts 422 and 516, and for damages due to breach of
the "take-and-pay" clauses under Contracts 321, 323, 324, 327 ("300 Series
Contracts") and the "take-or-pay" clauses under Contracts 422 and 516. CIG
counterclaimed for declaratory judgment as to the price of deregulated gas
under Contracts 422 and 516 and for restitution of payments made to Prenalta in
excess of that required under Contracts 422 and 516. The parties agree that the
law of Wyoming applies to this dispute.
7 Is CIG entitled to a refund of money paid after January 1, 1985 in excess of the
(1)
escalated base price for deregulated gas under Contracts 422 and 516?
8 What is the proper measure of damages for breach of the take-or-pay clauses of
(2)
Contracts 422 and 516? and
9 What is the proper measure of damages for breach of the take-and-pay clauses of
(3)
the 300 Series Contracts?
10
Prenalta contends that as to (1) there are at least controverted issues of material
fact, and as to (2) and (3), the trial court erroneously determined the measure of
damages and erred in not permitting Prenalta to proceed with a trial on the
merits, whatever the proper measure of damages.
11
For the reasons set forth below, the summary judgment of the district court in
favor of CIG is vacated and the case is remanded for jury trial consistent with
this opinion.
BACKGROUND
12
The Prenalta parties are the owners of working interests in approximately thirty
gas-producing wells in Sweetwater County, Wyoming. CIG is an interstate gas
pipeline company engaged in the business of purchasing, gathering,
transporting and selling natural gas. From 1966 through 1973 Prenalta and CIG
entered into six long-term contracts for the sale and purchase of natural gas
produced from Prenalta's wells--the 300 Series Contracts and Contracts 422 and
516 ("subject contracts"). As of the filing of this appeal, CIG continued to
purchase natural gas from Prenalta under these contracts.
13
When the terms were negotiated and the subject contracts executed, the prices
to be paid for gas produced under the contracts were regulated by the federal
government--initially, the Federal Power Commission and later, the Federal
Energy Regulatory Commission (FERC). The prices for gas under the 300
Series Contracts continue to be regulated by FERC. However, pursuant to
Section 121 of the Natural Gas Policy Act of 1978 (NGPA), 15 U.S.C. 3331,
the price for gas sold from two of the wells under Contract 422 and from all of
the wells under Contract 516 was deregulated on January 1, 1985. The
regulatory environment within which these contracts were formed, therefore, is
pertinent to an adequate understanding of the contracts' purpose and effect.
14
At the time Prenalta and CIG entered into the subject contracts, the regulatory
price ceilings on natural gas sold in the interstate market had contributed to
conditions of decreased production and, ultimately in the early 1970s, natural
gas shortages. Mobil Oil Exploration & Prod. S.E., Inc. v. United Distribution
Co., --- U.S. ----, ----, 111 S.Ct. 615, 620, 112 L.Ed.2d 636 (1991) ("severe
shortages persisted in the interstate market because low ceiling prices for
interstate gas sales fell considerably below prices the same gas could command
in intrastate markets, which were as yet unregulated"); Pierce, Natural Gas
Regulation, Deregulation, and Contracts, 68 Va.L.Rev. 63, 67-68 (1982).
During this period of limited supply, long-term gas purchase contracts became
even more advantageous to the pipeline/purchaser. While the market and
supply security of long-term contracts continued to be valuable to both
Not only did regulatory price ceilings help create market conditions
advantageous to the execution of long-term gas purchase contracts, but they
also affected the negotiation of specific provisions of these contracts due to the
limitation of price as a bargaining term. In order to compete in a market of
limited supply, pipelines were forced to grant producers benefits other than
price. Because the present allocation of the risk of future events is endemic to
long-term contracts, producers negotiated price-substitute benefits which
shifted the risk of a decline in market demand for natural gas to the pipelines
through the contract inclusion of take-and-pay or take-or-pay clauses. See
generally Pierce, supra, at 77-82.
16
Under a take-and-pay clause, the pipeline is required annually to take and pay
for a minimum contract quantity of gas. A take-and-pay clause benefits the
producer by maximizing revenue through the steady depletion of gas reserves.
Johnson, Natural Gas Sales Contracts, 34 Inst. on Oil & Gas L. & Tax'n 83, 108
(1983). Under a take-or-pay clause, the pipeline is required annually to take
and pay for a minimum contract quantity of gas or pay for a specified quantity.
A take-or-pay clause differs from a take-and-pay clause in that it assures the
producer a constant cash flow rather than the actual purchase of the contract
quantity of gas over the term of the contract. Johnson, supra, at 110. In addition,
a take-or-pay clause adds some measure of flexibility in a long-term gas
purchase contract by allowing the pipeline to pay for a specified quantity in lieu
of taking the contract quantity without endangering its long-term source of
supply.2 4 H. Williams, Oil and Gas Law 724.5, at 665 (1990). Under both
provisions, however, the pipeline assumes the risk that a market for the contract
quantity of natural gas might fail during the contract term. The take-and-pay
provision in the 300 Series Contracts and the take-or-pay provision in Contracts
422 and 516 are typical of such clauses in the natural gas purchase contracts of
the early 1970s.
17
While regulation of natural gas prices encouraged the formation of these longterm take-and-pay and take-or-pay contracts, deregulation encouraged their
On June 22, 1983, CIG circulated an interoffice memo stating that a "
[m]anagement decision has been issued not to make any further payments for
take-or-pay claims." (P.Exh. 20). As a result of this decision, CIG sent a
negotiation team in September 1983 to discuss with Prenalta possible
modifications of existing contracts. On March 21, 1984, CIG submitted its first
of a series of written proposals for renegotiation of the contracts which
continued until the filing of this lawsuit.
19
On January 1, 1985 the price for gas from two of the wells under Contract 422
and from all of the wells under Contract 516 was deregulated. Prenalta and CIG
had anticipated possible deregulation of gas by the time they executed the last
of the subject contracts, Contract 516, in 1973, and had consequently contracted
pricing provision 5.1(d). The parties also incorporated this provision by
amendment to Contract 422 in 1973. Section 5.1(d) provides that in the event of
deregulation of the price of gas sold under the contract, Prenalta would have the
right to request a redetermination of the price during the first six months after
the date of deregulation and during the six-month period preceding each five
year anniversary of the date of deregulation. Upon such request, the parties
agreed to meet and determine a fair value of the gas.
20
22
CIG sent Prenalta two letters on March 8, 1985--one concerning Contract 516
wells and the other concerning two Contract 422 wells--explaining its position
on pricing since deregulation: "Since there is no longer a regulated price and
since the price for deregulated gas has not been redetermined as provided in
Article V of the referenced contract, CIG intends to pay the applicable contract
base price as of January 1, 1985." (Exhs. 1 & 2 to P.Exh. 1). The letters also
offered $2.80/MMBtu6 for deregulated gas if Prenalta would agree to modify
the contracts to reduce CIG's take obligations and to forgive any past take-orpay liability incurred by CIG.
23
In a letter dated June 24, 1985, Prenalta responded to the March 8, 1985 letters,
rejecting CIG's proposed modifications of Contracts 422 and 516 and asserting
its disappointment with CIG's "failure to address the problem of gas
deficiencies in takes that have occurred to date on all wells covered by our
contracts." (P.Exh. 8). Prenalta further stated that "[a]lthough we recognize our
unilateral right as seller to invoke the price redetermination procedure provided
in Article 5.1(d) of our contracts, in the spirit of cooperation and to avoid, if
possible, an adversary approach we hereby elect not to do so."7
24
Due to the confusion resulting from CIG's March 8, 1985 letters and Prenalta's
continued receipt of commercially reasonable prices for both Contract 422 and
516 gas, Jim Masterson of Prenalta telephoned CIG Vice-President Glenn
Bjustrom on June 12, 1985 and sent a follow-up letter on June 25, 1985 in an
effort to determine the price CIG had been paying for deregulated gas under
Contract 516. In these communications, Masterson listed the range of "apparent
prices received" from HPC from January 1984 through March 1985, and
requested a statement of the price paid for such gas. (P.Exh. 3). Although
Bjustrom knew on June 25, 1985 that Prenalta was being paid only $.46/Mcf
for Contract 516 gas,8 he sent a letter to Masterson on July 19, 1985 listing
"CIG's Btu and pricing history" of Contract 516 gas which ranged from $4.54 in
September 1984 to $3.17 in May 1985, and advising that CIG's "company
policy does not permit release of gas purchase statement data to parties other
than the payee, which in this case is HPC, Inc." (Exh. 2 to P.Exh. 2). The letter
concluded by stating that "[t]he ceiling price of NGPA Section 102 was
effective until 1-1-85, when $2.80/MMBtu price became effective."
25
On July 22, 1985, Masterson wrote CIG acknowledging receipt of the July 19
letter "concerning the prices paid by CIG for gas from September, 1984
through May, 1985." (P.Exh. 27). Masterson, noting the difference in the prices
paid by CIG and those received by Prenalta, stated that Prenalta would explore
this problem and the matter of monthly statements with HPC but objected to
CIG's refusal to submit the statements to Prenalta stating that "[o]ur contract
clearly provides that we are entitled to such a monthly statement, and
something will have to be done so that we can audit the price we are receiving
for our gas."9
26
The next letter Prenalta received from CIG concerning the price of Contract
516 gas was sent on December 23, 1985. In this letter CIG stated that "there has
been no applicable contract price as of January 1, 1985" since the price has not
been redetermined. (P.Exh. 9). The letter further stated that "CIG has paid and
will continue to pay, as the law requires, a commercially reasonable price
pending determination of a price for your deregulated gas," and proposed
"$2.15 per MMBtu as the price applicable to the deregulated gas sold under the
referenced Contract, as now written, effective January 1, 1986."
27
It was not until the January 10, 1986 meeting between representatives of
Prenalta and CIG that Prenalta discovered that CIG had been paying HPC only
$.46/Mcf for Contract 516 gas since January 1, 1985. Prenalta wrote CIG a
letter dated February 12, 1986 complaining that the information is "contrary to
the advice previously given to us in your letter dated July 19, 1985 when you
advised us that the price was approximately $3.17." (P.Exh. 4). The letter went
on to present Prenalta's position that the escalated base price under 5.1(a) and
(b) was not the applicable price for deregulated gas which had not been
redetermined. Prenalta cited CIG's December 23, 1985 letter which stated that
the applicable price was the "commercially reasonable price" of $2.40 in lieu of
29
30
Understand
that this increase in price was implemented by CIG as a good faith
expression of our willingness to reach a mutually agreeable settlement and is not
intended as our agreement with Prenalta's position that the base price specified in the
contract is not the applicable price for your deregulated gas.
31
(P.Exh. 10). To which Prenalta responded in their September 10, 1986 letter:
"We are, of course, pleased that CIG has made this increase in price as a good
faith expression of their willingness to reach a mutually agreeable settlement,
and we reiterate our desire to resolve the many issues facing us in a fair and
expeditious manner." (Exh. 6 to P.Exh. 1). Although CIG continued to pay a
commercially reasonable price for deregulated gas under Contract 422 and 516,
CIG persisted in its position that the escalated base price was the applicable
contract price in its subsequent correspondence with Prenalta.
32
33
36
Failing to renegotiate the terms of the contracts, CIG sent a final letter to
Prenalta on December 22, 1988 addressing the "two main issues, pricing and
take-or-pay." (Exh. 10 to P.Exh. 1). After taking exception to Prenalta's
estimates of CIG's "take" deficiencies, CIG claimed $713,000.00 in
overpayments to Prenalta since January 1, 1985 because the "price payable for
deregulated gas produced under Contract 422 (dated August 12, 1971) and
Contract 516 (dated June 1, 1973) was the base price as provided in Paragraph
5.1(a)," and CIG had only complied with Prenalta's demand "in a conciliatory
gesture to continue negotiations."
37
Unable to reach any negotiated modification of Contracts 422 and 516, Prenalta
brought suit against CIG in March 1989. On cross-motions for partial summary
judgment, CIG argued that the applicable price under Contracts 422 and 516
was the escalated base price of 5.1(a) and (b), while Prenalta argued that a
commercially reasonable price was the contract price in the absence of
redetermination. The district court agreed with CIG and found that the pricing
provisions in 5.1(a-d) in Contracts 422 and 516 were clear and unambiguous:
if Prenalta failed to exercise its right to price redetermination within six months
after deregulation pursuant to 5.1(d), then the price scale set forth in 5.1(a),
escalated at a rate in accordance with 5.1(b), determines the price to be paid
under the contracts.
38
CIG then moved for summary judgment on its counterclaim for a refund of the
difference between the amount paid Prenalta since January 1, 1985 and the
escalated contract base price. The district court granted CIG's motion and held
that CIG was entitled to a refund of the money paid in excess of the escalated
base price, in the amount of $124,826 under Contract 422 and $1,023,844 under
Contract 516.10 In so holding the district court reasoned that CIG's reservation
of rights under Wyo.Stat. 34.1-1-207(a) (1991)11 entitled CIG to a refund as a
matter of law and Prenalta had failed to establish any issue of material fact in
support of its arguments that CIG had waived its right to a repayment or was
equitably estopped from seeking repayment.
39
40
41
43
44
CIG counters that its conduct does not unequivocally manifest its intent to
relinquish a claim for repayment because pursuant to Wyo.Stat. 34.1-1-207(a)
(1991) it reserved its right to seek repayment. Section 34.1-1-207(a) states that
"[a] party who, with explicit reservation of rights, performs or promises
performance or assents to performance in a manner demanded or offered by the
other party does not thereby prejudice the rights reserved. Such words as
'without prejudice', 'under protest' or the like are sufficient." CIG argues that if
it "intended to make voluntary payments and abandon the base price issue,
there would have been no reason to state in the September 5, 1986 letter and
subsequent correspondence that CIG was not waiving its rights."
45
CIG, however, confuses the "right" reserved. In these letters, CIG reserved its
legal right to limit its payments to the contract price, the escalated base price
under 5.1(a) and (b); CIG did not reserve its "right" to a refund of money it
decided to pay to continue negotiations with Prenalta. In CIG's September 5,
1986 letter which followed its August 8, 1986 retroactive payment, CIG
emphasized that the increase in price was implemented "as a good faith
expression of our willingness to reach a mutually agreeable settlement and is
not intended as our agreement with Prenalta's position that the base price
specified in the contract is not the applicable price for your deregulated gas."
That the increase payment was made to foster negotiation was obviously
understood by Prenalta when Prenalta responded in its September 10, 1986
letter to CIG that it was "of course, pleased that CIG has made this increase in
price as a good faith expression of their willingness to reach a mutually
agreeable settlement." The excess payments made by CIG were, therefore,
extra-contractual and voluntary, and any right to their repayment would have
had to arise from an agreement between the parties. No such agreement exists
in the record on appeal. Prenalta's demand for the increase in price before it
would continue negotiating with CIG as set forth in its letters of February 12,
1986 and June 11, 1986 certainly does not evidence Prenalta's agreement to
refund the excess payments if negotiations failed. The record reflects the only
"right" CIG reserved was its position that the escalated base price was the
applicable price under the terms of Contract 516. 12
46
47
II.
48
Prenalta also appeals the district court's summary judgment ruling that Prenalta
is precluded from recovering damages for CIG's alleged breach of its take-andpay obligations under the 300 Series Contracts and its take-or-pay obligations
under Contracts 422 and 516 because Prenalta failed to plead the proper
measure of damages under Wyo.Stat. 34.1-2-708(b) (1991). In so ruling, the
district court reasoned that 1) the Wyoming Uniform Commercial Code (UCC)
applies to the subject contracts and provides the remedy for their breach; 2)
Prenalta seeks damages in the amount of the full contract price; 3) the seller's
remedy under the UCC which allows recovery of the full contract price,
Wyo.Stat. 34.1-2-709 (1991), is inapplicable to the facts of this case because
the goods (the natural gas) are not "identified to the contract"; 4) Prenalta's
remedy for breach of the subject contracts lies in 34.1-2-708(b) which
provides for lost profits; and 5) Prenalta has failed to plead a measure of
damages under which it would be entitled to any recovery. Therefore, although
it was uncontroverted that CIG had breached its take-and-pay and take-or-pay
obligations under the subject contracts, the trial court granted summary
judgment to CIG. Prenalta argues that it correctly stated the measure of
damages for breach of the subject contracts as the value of CIG's "shortfall";13
and even if such measure is incorrect, it should be permitted the opportunity to
offer evidence on the "lost profits" measure of damages which resulted from
CIG's breach.
A.
49
Contracts 422 and 516 are take-or-pay contracts. Prenalta alleges that under
Article IV of the contracts, CIG agrees to "take" during each contract year a
minimum of 1000 Mcf of gas per day for each 7.3 million Mcf of committed
reserves attributable to the contract wells--the "contract quantity" under 4.1(a)
of the contracts. If CIG fails to purchase the contract quantity for any year, then
the contract provides that CIG would have to "pay" for the contract quantity:
Upon payment of the "difference between the Contract Quantity and Buyer's
actual takes" (the "shortfall"), CIG is credited the gas paid for but not taken.
CIG can recoup this "Make-up Gas" over the succeeding five years.
52
Prenalta argues that 4.2 of Contracts 422 and 516 clearly provides the contract
remedy for breach, and that the measure of damages under the provision is the
value of the "quantity of gas which is equal to the difference between the
Contract Quantity and Buyer's actual takes" for each year CIG has been in
breach of the contracts.14 We agree.
53
Gas purchase contracts are contracts for the sale of goods and are governed by
Article 2 of the Uniform Commercial Code (UCC). Wyo.Stat. 34.1-2105(a), 34.1-2-107(a) (1991);15 American Exploration Co. v. Columbia Gas
Transmission Corp., 779 F.2d 310, 314 (6th Cir.1985); Northwest Cent.
Pipeline Corp. v. Mesa Petroleum Co., 723 F.Supp. 1410, 1413 (D.Colo.1989).
Although the UCC applies to gas purchase contracts, the parties can vary the
provisions of the UCC by agreement, pursuant to Wyo.Stat. 34.1-1-102(c)
(1991):
56
57
At the time Contracts 422 and 516 were executed, take-or-pay provisions in gas
purchase contracts were common in the natural gas industry. In return for the
producer's exclusive dedication of the gas from its wells to the pipeline over a
long term, take-or-pay clauses were drafted to assure the producer a continuous
cash flow and to shift the risk of market demand to the pipeline:
58
The purpose of the take-or-pay clause is to apportion the risks of natural gas
production and sales between the buyer and seller. The seller bears the risk of
production. To compensate seller for that risk, buyer agrees to take, or pay for
if not taken, a minimum quantity of gas. The buyer bears the risk of market
demand. The take-or-pay clause insures that if the demand for gas goes down,
seller will still receive the price for the Contract Quantity delivered each year.
59
Universal Resources, 813 F.2d at 80. It is accepted practice in the natural gas
industry that "[i]n the event of failure of Buyer to take the quantity of gas
specified in a 'take-or-pay' contract, Buyer is required to pay for the specified
quantity of gas." 4 H. Williams, Oil and Gas Law 724.5, at 665 (1990). The
express language of 4.2 and the industry-recognized purpose of take-or-pay
clauses compel the interpretation of the provision as Prenalta's remedy for
CIG's failure to take the contract quantity of gas under Contracts 422 and 516.
Any other interpretation would defeat the purpose of the take-or-pay clause: to
insure Prenalta annual payments for the contract quantity in return for Prenalta's
dedication of its gas and CIG's right to make-up any "take" deficiencies over a
five-year period.
60
CIG argues that 4.2 of the contracts provides for alternative performance
under the contracts and as such cannot be a remedy for breach of performance.
CIG further contends that if 4.2 is interpreted as a remedy, it is necessarily an
unenforceable liquidated damages or penalty provision.
61
Co. v. Sea Robin Pipeline Co., 493 So.2d 909, 915-16 (La.Ct.App.1986), writ
denied, 497 So.2d 310 (La.1986). Because one of the alternative performances
in a take-or-pay contract is the payment of money, courts have distinguished
the "pay" provision from a liquidated damages provision. Universal Resources,
813 F.2d at 80 n. 4; Sabine Corp. v. ONG Western, Inc., 725 F.Supp. 1157,
1184 (W.D.Okla.1989); Enron, 669 F.Supp. at 1041. This distinction is
particularly necessary because the payments made pursuant to the take-or-pay
provision, the "pay" alternative of Contracts 422 and 516, are not payments for
the sale of gas. Kaiser-Francis Oil Co. v. Producer's Gas Co., 870 F.2d 563, 570
(10th Cir.1989) (quoting ANR Pipeline Co. v. Wagner & Brown, 44 FERC p
61,057, 61,158 (1988) ("[T]he take-or-pay payment for gas is not intended to
be a payment for gas and is not a part of the price of gas until it is applied at the
time of sale.")); Diamond Shamrock Exploration Co. v. Hodel, 853 F.2d 1159,
1167-68 (5th Cir.1988). The difference between alternative performance and
liquidation of damages is lucidly explained in 1082 of Corbin on Contracts:
62
It is evident that some alternative contracts giving the power of choice between
the alternatives to the promisor can easily be confused with contracts that
provide for the payment of liquidated damages in case of breach, provided that
one of the alternatives is the payment of a sum of money.... If, upon a proper
interpretation of the contract, it is found that the parties have agreed that either
one of the two alternative performances is to be given by the promisor and
received by the promisee as the agreed exchange and equivalent for the return
performance rendered by the promisee, the contract is a true alternative
contract. This is true even though one of the alternative performances is the
payment of a liquidated sum of money; that fact does not make the contract one
for the rendering of a single performance with a provision for liquidated
damages in case of breach.16
63
Under the terms of Contracts 422 and 516, CIG could elect either to purchase
the contract quantity or to pay the value of the contract quantity (the "minimum
bill") in exchange for Prenalta's tender of the contract quantity of gas or any
make-up gas due CIG for past deficiencies. This is clearly an alternative
contract which allows CIG to perform either alternative, to "take" or "pay" for
the gas, in exchange for Prenalta's return performance, rather than a contract
which requires CIG to "take" the contract quantity of gas with a triggering
liquidated damages provision if CIG fails to do so.
64
Section 4.2 also sets the parameters of the alternative performances under the
Contracts 422 and 516. CIG can elect to purchase the contract quantity of gas
only within "any 1-year period, commencing with the 1st day of the month in
which initial delivery is made from each well." If CIG does not purchase the
contract quantity of gas within the 1-year period, CIG "shall pay Seller on or
before the 20th day of the 2nd month of the next following year for that
quantity of gas which is equal to the difference between the Contract Quantity
and Buyer's actual takes during such period." (emphasis added). This type of
alternative contract eliminates the availability of one alternative with the
passage of time. See Ply-Gem Indus., Inc. v. Green, 503 F.2d 1362, 1366 (2nd
Cir.1974). As stated in 1085 of Corbin on Contracts:
65
66
Section 4.2 limits CIG's "take" alternative to a period of one year, after which
CIG's obligation is sole: the payment of the minimum bill. Prenalta's damages
are therefore measured by CIG's obligation to pay--the value of which is the
contract price in effect at the time such deficiency occurred 18 multiplied by the
difference between the contract quantity and the actual quantity of gas
purchased for any year CIG was in breach of Contract 422 and/or Contract 516.
B.
67
The 300 Series Contracts are take-and-pay contracts. Under 4.1 of the 300
Series Contracts, CIG is required to take and pay for one thousand Mcf of gas
per day for each eight million Mcf committed reserves attributable to a contract
well during a delivery period (initially a five-year period, then subsequent
three-year periods). Failure to do so results in breach of the contracts. Unlike
the take-or-pay Contracts 422 and 516, the take-and-pay 300 Series contracts
do not contain a remedy provision:
68
69
70
As stated above, gas purchase contracts are contracts for the sale of goods
under title 34.1 of the Wyoming statutes (UCC), 34.1-2-105(a), 34.1-2107(a) (1991). In the absence of a contracted remedy, Prenalta's remedy for
CIG's breach of the take-and-pay 300 Series Contracts is provided by the
available seller's remedy or remedies under Wyo.Stat. 34.1-2-703 (1991).
71
The trial court's analysis concerning the measure of damages for breach of the
300 Series Contracts is correct. Section 34.1-1-106(a) of the Wyoming UCC
states that "[t]he remedies provided by this act shall be liberally administered to
the end that the aggrieved party may be put in as good a position as if the other
party had fully performed." While an action for the price pursuant to 34.1-2709(a)(ii) would effectively compensate Prenalta for CIG's breach, it is
inapplicable here, as the gas has not been produced and, therefore, is not
identified to the contract. Piney Woods Country Life School v. Shell Oil Co.,
726 F.2d 225, 234 (5th Cir.1984), cert. denied, 471 U.S. 1005, 105 S.Ct. 1868,
85 L.Ed.2d 161 (1985). The parties agree that 34.1-2-708(a), contrarily,
would not put Prenalta in as good a position as if CIG had performed because
the price under the contracts is less than the market price at the time and place
of tender. Prenalta's remedy, therefore, is provided by 34.1-2-708(b)19:
72the measure of damages provided in subsection (a) is inadequate to put the seller
If
in as good a position as performance would have done then the measure of damages
is the profit (including reasonable overhead) which the seller would have made from
full performance by the buyer, together with any incidental damages provided in this
article (section 34.1-2-710), due allowance for costs reasonably incurred and due
credit for payments or proceeds of resale.
73
III.
74
76
The Honorable Thomas R. Brett, United States District Judge for the Northern
District of Oklahoma, sitting by designation
"Mcf" is a thousand cubic feet--the standard unit for measuring the volume of
natural gas
Sometime after January 1986, HPC adjusted its payments to Prenalta to reflect
the actual price paid by CIG
degree Fahrenheit." H. Williams & C. Meyers, Oil and Gas Terms 99 (7th ed.
1987)
7
The time period for Prenalta's initial redetermination of price under Contracts
422 and 516 expired on June 30, 1985
10
11
We refer to the renumbered sections of title 34.1 of the Wyoming statutes, the
Uniform Commercial Code. In 1989 former articles 1 through 10 ( 34-21-101
through 34-21-1002) of chapter 21 of title 34 were renumbered as the present
title 34.1 ( 34.1-1-101 through 34.1-10-104), in accordance with Wyo.Stat.
28-8-105
The Official Comments to the Uniform Commercial Code were added to the
corresponding sections in 1991. Only 34.1-1-207 has been substantively
amended, effective July 1, 1991, by the addition of subsection (b) which reads:
"Subsection (a) does not apply to an accord and satisfaction."
12
13
The "shortfall" is the quantity of gas which is equal to the difference between
the contract quantity and buyer's actual takes
14
Prenalta does not claim repudiation of the contracts, but seeks damages for the
years CIG failed to purchase the contract quantity or to make take-or-pay
payments under 4.2 of Contracts 422 and 516. Although Prenalta alleges that
CIG has failed to make take-or-pay payments since 1983, it acknowledges that
its pre-1985 claims are barred by the four-year statute of limitation, Wyo.Stat.
34.1-2-725(a) (1991)
15
"Goods" means all things (including specially manufactured goods) which are
movable at the time of identification to the contract for sale other than the
money in which the price is to be paid, investment securities (article 8) and
things in action. "Goods" also includes the unborn young of animals and
growing crops and other identified things attached to realty as described in the
section of goods to be severed from realty (section 34.1-2-107)
Wyo.Stat. 34.1-2-105(a) (1991).
A contract for the sale of timber, minerals or the like or a structure or its
materials to be removed from realty is a contract for the sale of goods within
this article if they are to be severed by the seller but until severance a purported
present sale thereof which is not effective as a transfer of an interest in land is
effective only as a contract to sell.
Wyo.Stat. 34.1-2-107(a) (1991).
16
17
18
The price for deregulated gas under Contracts 422 and 516, from January 1,
1985 until it is redetermined pursuant to 5.1(d), is the escalated contract base
price as set forth in 5.1(a) and (b) of the contracts
19
It is not clear from the record whether free market competition exists for
Prenalta's natural gas or whether the production is limited by pipeline
accessibility and control