Structure Design Manual 032016
Structure Design Manual 032016
MARCH 2016
Article 1.2: Article revised to define Illinois State Toll Highway Authority as
(Illinois Tollway). Tollway reference updated throughout manual.
Article 1.2: Article revised to clarify that IL-120 Loading shall include the IL-120
Design Truck and Design Lane Load as specified in AASHTO LRFD Article
3.6.1.2.4, and the IL-120 Design Truck Diagram shall be added to the plans.
Article 2.5: Article revised to clarify that Illinois Tollway Bond Rate, Anticipated
Illinois Tollway Revenue Increase and Anticipated Rate of Illinois Tollway
Construction Cost Inflation is only needed if the DSE is asked to calculate the
real discount rate.
Article 3.2: Article revised to clarify that a Level 3 Barrier Warrant Analysis shall
be performed prior to TS & L submittal in order to determine abutment types and
locations and span configuration, and culvert lengths.
Article 3.5: Article revised to clarify that SGRs shall be submitted with the 30%
design submittal.
Article 5.1: The updated Illinois Tollway Manuals and Base Sheets and AASHTO
Specifications have been referenced and Bridge Concrete Deck, Approach
Slabs, Transition Slabs and Parapet, Retaining Wall Moment Slab and Moment
Slab Barriers, and IDOT Prestressed Concrete Beam Design Stresses have
been updated. Material Specifications were removed for Box Culverts. Noise
abatement wall design wind load updated to match Article 23.2.2. Retaining Wall
Live Load Criteria (when a barrier is constructed integrally with top of wall) was
revised to clarify barrier shall be designed for transfer of impact loads to top of
wall.
Article 5.3: Paragraph received minor edits to reference Article 3.2 for Barrier
Warrant Analysis requirements.
Article 5.6: New Article 5.6 added to clarify the Dead Load to include in design.
Remaining articles revised.
Article 5.9: Article revised to clarify table to be used for all railroad bridges and
bridge structure over railroads. Minor edit to table to include operational
restrictions under specific railroad requirements.
Article 6.2: Structural Seal Requirements on the GP&E removed from this Article
and added to new Article 6.3.13.
Article 6.3.3: Article revised to clarify when to use the No Salvage note.
Article 6.3.4: Construction Specifications and IL-120 Design Truck Diagram were
added.
Article 6.3.13: New article added to require Structural Engineer (SE) seal on all
GP&E sheets.
Article 6.8: New article added to define the beam numbering sequence on
structures.
Article 6.9: New article added to define the minimum requirements for the
Preliminary (60%) Plan Submittal.
Article 7.1.2: Added note to designer to General Note 7 and updated General
Note 9.
Article 7.1.3: Clarified the application of General Notes 4 and 5. Added new
General Note 9 for deck pouring sequence.
Article 7.1.4: Added new General Note 10 for protective shielding. Added
General Note 26 regarding MSE wall settlement.
Article 7.2.2: Article revised to clarify erection plans for both Steel and PPC
beams and updated Notes 1, 2 and 3.
Article 7.3: Removed General Note 12 for culvert lap lengths and duplicate
General Note 10. Renumbered remaining General Notes.
Article 8.1: Allowable locations of stage lines revised. Figure 8.1.1 received minor
edits.
Article 9.1: Figure 9.1.1 was revised to clarify which dimensions are required for
all substructure units.
Article 10.3: Revised article to clarify Combination MSE and Intergal Abutments
are allowed on all structures.
Article 10.3: Minor revisions made to Figures 10.3.1, 10.3.4 and 10.3.6.
Article 10.3: Figures 10.3.2 and 10.3.5 revised to match updated Approach Slab
base sheet. Minor revisions also made.
Article 10.3: Figure 10.3.3 modified to show wingwall pile directly in center of
wingwall. Other minor revisions made.
Article 10.3: Figures 10.3.7, 10.3.8 and 10.3.9 were revised to clarify the limits of
removal and disposal of unsuitable material for structures, remove the
requirement for crossroad bridges only, provide consistency between figures,
include the abutment soil reinforcement, note and revise location of H
dimension, and clarify dimensions and payment of concrete seal. Figure 10.3.10
was renumbered to Figure 10.3.9.
Article 10.3: Figure 10.3.10 was revised to remove the use of bond breaker
membrane on front of panel and replaced with PJF. Figure 10.3.9 was
renumbered to Figure 10.3.10.
Article 10.7.1: Article revised to include an increased height of slope wall lip on
structures skewed 10 degrees or greater and clarify that details are now in Base
Sheet M-BRG-525.
Article 10.7.2: Article revised to include an increased height of slope wall lip on
structures skewed 10 degrees or greater and clarify that details are now in Base
Sheet M-BRG-525 and the latest IDOT Bridge Manual.
Article 10.7.3: Article revised to clarify that details are now in Base Sheet MBRG-525. Removed Figures 10.7.3.1 and 10.7.3.2.
Article 10.8: Article revised to allow the use of dog-ear style wing walls that are
parallel to the centerline of abutment for integral abutment bridges.
Article 10.9: Figure 10.9.1 was revised to reduce the required clearance between
anchor bolts and shear stirrups and transverse reinforcement from 4 to 2.
Article 11.3: Figure 11.3.1.8 title was changed from Integral Pier Detail to Grade
Separation Pier Detail (For use with integral abutment bridge).
Article 11.9: Figure 11.9.1 was revised to reduce the required clearance between
anchor bolts and shear stirrups and transverse reinforcement from 4 to 2.
Article 12.2: Article revised to consider the use of bottom lateral bracing.
Article 13.1: Article revised to reference IDOT All Bridge Designers Memorandum
15.2.
Article 13.2: Second paragraph from Article 13.2.3 moved to Article 13.2.
References to restrictions for debonding of prestressing strands have been
added.
Article 13.2.1: Final paragraph from Article 13.2.3 moved to Article 13.2.1.
Article 13.2.2: Table 13.2.2.1 renamed to Fig. 13.2.1 and revised to clarify
debonding assumptions made in calculations.
Article 13.2.3: Second paragraph moved to Article 13.2 and final paragraph
moved to Article 13.2.1.
Article 13.3: Clarified beam end details for IL-Beams. Removed Figures 13.3.2
and 13.3.3.
Article 13.5.1: Article revised to clarify reference to IDOT Base Sheets and
remove Figure 13.5.1.1.
Article 14.1: Revised floating (pot) bearing call out to High Load Multi-Rotational
bearings. Added paragraph to show detail of bearing for erection temperatures
on the plans.
Article 14.2: Revised floating (pot) bearing call out to High Load Multi-Rotational
bearings.
Article 15.1: Article revised to only include bridge deck and bridge parapet
concrete type and design stresses. Approach slab references were removed and
added to Article 19.1. Clarification added that overlays shall not be considered
structural for composite section properties. Design requirements revised to also
include IDOT ABD Memo 15.2.
Article 15.2: Future Lane Line callout removed from Figure 15.2.1.
Article 15.2: Article revised to clarify deck capacity after partial depth deck
removal and overlay placement.
Article 15.4: Figure 15.4.1 revised to show minimum laps that meet the
requirements of IDOT ABD Memo 15.4.
Article 15.5: Title revised. Jurisdictional requirements for barriers clarified. Article
adjusted to clarify that reinforcement requirements replace the requirements of
IDOT ABD Memo 14.1. Text and Figure 15.5.1.4 added to clarify location of 1/8
aluminum joints in parapet at piers and abutments. Figure 15.5.1.3 title changed
Article 15.5.2: Article revised to clarify which Standard the Single Face Barrier
can be used with fill.
Article 15.6: Figure 15.6.1 was revised to remove the word pressurized from the
note in the typical section. Location of longitudinal joint clarified.
Article 15.6: Article revised to clarify the open joint is not required if the deck is
staged and the total width of the staged pours is less than or equal to 120 feet.
Article 15.8: Article revised to meet slipforming conditions in IDOT ABD Memo
12.4.
Article 17.1: Article revised to clarify reference to approach slab base sheets and
added joint seals shall be one continuous piece for the full length of joint.
Article 19.1: Article revised to clarify bridge approach slab and transition
approach slab definitions, approach slab lengths for curved structures and when
transition approach shoulder slabs shall be utilized. In addition, article revised to
include concrete type and design stresses.
Article 19.2.1: Article revised to allow for consideration of precast approach slabs
for distances from back of abutment to centroid of stiffness of 130 feet or greater.
Article 19.4: Article revised to clarify that approach bent details shall be included
in the structural plans.
Article 21.1: Article revised to reference Article 3.2 for Barrier Warrant Analysis
requirements for culvert barrel length.
Article 21.2.4: Article revised to clarify Temporary Construction Works details for
culvert construction staging.
Article 22.3.1: Figures 22.3.1.4 and 22.3.1.5 revised to include shims as required.
Minor revisions made to dimensions in Figure 22.3.1.6.
Article 22.4.4: Article revised to clarify minimum requirements for the flat area in
front of retaining walls.
Article 22.5.1: Figure 22.5.1.1 revised to clarify dimensions for flat area in front of
wall. Limits of Structure Excavation and Porous Granular Backfill and location of
Bond Breaker clarified.
Article 22.6.1: Article revised to clarify the designer shall be responsible for the
analysis of settlement, bearing capacity and overall slope stability for MSE
retaining walls.
Article 22.14: Article revised to include concrete type and design stresses.
Minimum thickness of aggregate below moment slab on any type of wall is
specified and direction to show on the plans is given.
Article 22.14: Figure 22.14.2 was revised to change the PJF to PJF.
Article 22.15: Article added to include requirement for fence or railing on retaining
wall.
Article 23.2.2: Article revised to clarify dead load for bridge and retaining wall
noise abatement walls.
Article 23.3.1: Article revised to clarify that changes in noise abatement wall
heights shall be accomplished in increments no greater than 2 feet or no smaller
than 1 foot. Figures 23.3.1.2 and 23.3.1.3 revised to clarify the maximum and
minimum step requirements.
Article 23.3.3: Figure 23.3.3.1 revised to remove minimum distance from noise
abatement wall to edge of pavement. Figure 23.3.3.2 revised to clarify ground
mounted noise abatement wall dimensions.
Articles 24.4, 24.5, 24.6, 24.7, 24.9 and 24.10: Articles revised to clarify standard
drawings and base sheets to be used, allowable span lengths, allowable sign
types and barrier warrant requirements for all standard overhead sign structures.
Article 24.14: Added new article for Foundations for Overhead Sign Structures.
TABLE OF CONTENTS
SECTION 1.0
1.1
1.2
1.3
1.4
SECTION 2.0
2.1
2.2
2.3
2.4
2.5
SECTION 3.0
3.1
3.2
3.3
3.4
3.5
SECTION 4.0
4.1
4.2
4.3
SECTION 5.0
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.7.1
March 2016
Illinois Tollway
TABLE OF CONTENTS
5.7.2
5.7.3
5.7.4
5.8
5.9
SECTION 6.0
6.1
6.2
6.2.1
6.2.2
6.2.3
6.2.4
6.3
6.3.1
6.3.2
6.3.3
6.3.4
6.3.5
6.3.6
6.3.7
6.3.8
6.3.9
6.5
6.6
6.7
March 2016
ii
Illinois Tollway
TABLE OF CONTENTS
6.8
6.9
SECTION 7.0
7.1
7.1.1
7.1.2
7.1.3
7.1.4
7.2
7.2.1
7.2.2
7.2.3
Structural Assessment Reports for Contractors Means and Methods ..... 7-6
7.3
SECTION 8.0
8.1
8.2
8.3
8.4
SECTION 9.0
9.1
9.2
9.3
9.4
9.5
9.6
Cofferdams...................................................................................................... 9-2
9.7
9.8
March 2016
iii
Illinois Tollway
TABLE OF CONTENTS
March 2016
iv
Illinois Tollway
TABLE OF CONTENTS
March 2016
Illinois Tollway
TABLE OF CONTENTS
14.2.2 Low Profile Steel Rocker Bearings (Fixed Only) .................................... 14-2
14.2.3 High Load Multi-Rotational Bearings ...................................................... 14-2
SECTION 15.0 CONCRETE BRIDGE DECKS, PARAPETS AND BARRIERS ....... 15-1
15.1 New and Replacement Decks ....................................................................... 15-1
15.2 Existing Deck Widenings and Repairs .......................................................... 15-1
15.3 Cross Slopes ................................................................................................. 15-2
15.3.1 Tangent Sections ................................................................................... 15-2
15.3.1.1New, Replacement and Widened Decks ................................................ 15-2
15.3.1.2Overlays ................................................................................................. 15-2
March 2016
vi
Illinois Tollway
TABLE OF CONTENTS
March 2016
vii
Illinois Tollway
TABLE OF CONTENTS
March 2016
viii
Illinois Tollway
TABLE OF CONTENTS
March 2016
ix
Illinois Tollway
TABLE OF CONTENTS
March 2016
Illinois Tollway
TABLE OF CONTENTS
March 2016
xi
Illinois Tollway
INTRODUCTION
1.1
Reserved
1.2
The Illinois State Toll Highway Authority (Illinois Tollway) is transitioning from the
American Association of State Highway and Transportation Officials (AASHTO) 2002
Standard Specifications for Highway Bridges Division I Load Factor Design (LFD) and
Allowable Stress Design (ASD) to the latest edition of the AASHTO LRFD Bridge
Design Specifications for new bridge construction. It is anticipated that this process will
be ongoing over the next few years. As such, this Design Manual refers to both the
AASHTO Standard and AASHTO LRFD Specifications.
The design of all new and replacement structures after November of 2007 shall be in
accordance with the latest edition of the AASHTO LRFD Bridge Design Specifications
except as modified by the following Illinois Department of Transportation (IDOT)
Manuals: Bridge, Culvert, Drainage, Geotechnical and Sign Structures, or as amended
herein by the Illinois Tollway Structure Design Manual. The most current IDOT manuals
related to structural policy, documents and procedures are available on the Internet web
pages at the following site:
http://www.idot.illinois.gov/
Navigation to technical manuals begins with Doing Business then Procurements.
The AASHTO LRFD Bridge Design Specifications was not completely adopted by IDOT.
Several parts were modified or subjected to interpretation by IDOT. The following
examples are representative of some of the changes made by IDOT:
Portions of Live Load Distribution for bridges have been simplified and/or not
adopted (Section 3.3.1).
When to apply lateral stresses for steel beam design has been interpreted
(Section 3.3.5).
Moment Redistribution in LRFD and LFD is not allowed (Section 3.3.6).
Seismic design is according to LRFD with some interpretations, but the IDOT
Bridge Manual clarifies options in LRFD to use for Illinois (Sections 3.7, 3.10
and 3.15).
Vehicle collision design forces and the approach to design have been
interpreted by IDOT (Section 3.9.3.7 and ABD Memo 12.1). The 600 kip
force shall be applied to the top of the crashwall.
The phi factor to use for pile design has been interpreted (Section 3.10).
March 2016
1-1
Illinois Tollway
March 2016
1-2
Illinois Tollway
The maximum deflection resulting from the IL-120, HL-93 truck, or HL-93
Tandem alone, or
The deflection resulting from the design lane load plus the maximum
deflection resulting from 25 percent of the IL-120, HL-93 truck, or the HL93 Tandem.
Crossroad bridges over the Illinois Tollway shall meet the requirements shown above,
except checks for IL-120 live load are not required.
1.3
Illinois Tollway structures shall be designed to meet the minimum requirements for
AASHTO Seismic Performance Zone 1 (LRFD) or Category A (LFD) with a low
probability of being exceeded during the normal life expectancy for a bridge. Bridges
and their components that are designed to resist Zone 1 (Category A) forces and
constructed in accordance with the design details contained in the latest IDOT Bridge
Manual should not experience total collapse, but may sustain repairable damage due to
seismically induced ground shaking.
1.4
For a complete list of Illinois Tollway terms, definitions and acronyms including project
requirements, see the latest DSE Manual.
March 2016
1-3
Illinois Tollway
12K
24K
10'-0"
24K
20K
4'-0"
22'-0"
20K
4'-0"
20K
4'-0"
44'-0"
6'-0"
FIGURE 1.2.1
ILLINOIS TOLLWAY
SECTION 2.0
2.1
Structure condition reports shall be submitted during the master planning or preconceptual phase. Reports shall follow the guidelines of the latest IDOT Bridge
Condition Report Procedures and Practices. Existing structures to be abandoned and/or
removed or completely replaced shall not be inspected or require a condition report.
Only those structures which are to be rehabilitated, reconstructed or widened shall
require both in-depth inspections and condition reports.
In general, retaining walls shall not be inspected nor require a condition report, unless
the existing wall(s), or portions thereof, are to be incorporated into the proposed project.
In which case, an inspection shall be performed and a condition report prepared for
each wall or section to be utilized in conjunction with the project.
Before any element of a structure and/or its foundations can be considered for reuse in
replacing, reconstructing or rehabilitating an existing structure, it shall be evaluated and
analyzed in accordance with Section 2.2 of the IDOT Bridge Manual. The results of
these evaluations and analysis shall be summarized and included in the Structure
Condition Report for each structure where reuse is being considered. The backup data
and calculations for each summary shall not be submitted for review unless requested
by the Illinois Tollway.
2.3
Hydraulic Analysis
March 2016
2-1
Illinois Tollway
Scour Analysis
The report shall also include any recommendations to mitigate or prevent scour at each
structure.
2.5
Life Cycle Cost Analysis (LCCA) is required for all replacement versus rehabilitation
decisions. LCCA for bridge elements such as beams, piers, abutments, etc. (excluding
decks) shall be performed in accordance with procedures outlined in Publication No.
FHWA-SA-98-079, NCHRP Report 483 Bridge Life-Cycle Cost Analysis and the
following guidelines:
1.
No inflation, that is, constant dollars shall be used. Inflation is included in the real
discount rate calculation, provided.
2.
A real discount rate of 2.6% shall be used (from Equation 14, NCHRP 483). If the
DSE is asked to calculate this rate, the following shall be used as the equation
variables:
March 2016
2-2
Illinois Tollway
4.
The life of a new bridge element shall be 100 years, unless fatigue dictates a
shorter life.
5.
b.
6.
If the cost of repair is less than or equal to 10% of the cost of a new structural
element, then an LCCA is not necessary and replacement is not required.
7.
If the cost of repair is greater than or equal to 80% of the cost of a new structural
element, then an LCCA is not necessary and replacement shall be
recommended.
8.
9.
10.
11.
12.
The salvage value is the percentage of the design life of the most recent
rehabilitation remaining at the end of the analysis period multiplied by the cost of
this rehabilitation.
March 2016
2-3
Illinois Tollway
March 2016
Illinois Tollway
SECTION 3.0
3.1
General
The TS & L Plans form the basis for preparation of Construction Contract Plans. TS & L
plans shall be submitted with the 30% design submittal. TS & L Plans are required for
new or replacement structures, and all widenings and superstructure replacements.
Structures identified for rehabilitation and/or redecking shall not require TS & L Plans.
TS & L Plans for Illinois Tollway structures shall not require completion of a Structure
Report (BBS Form 153), a Preliminary Bridge Design and Hydraulic Report (BLR Form
10210) or a Project Development Outline. TS & L Plans for those structures that are
either fully or partially funded and/or maintained by IDOT shall follow all guidelines and
requirements of Section 2.0 of the latest IDOT Bridge Manual. Prior to submittal of any
TS & L Plans, the Plans shall be checked for compliance with Section 2.3.13 of the
latest IDOT Bridge Manual.
3.2
A Bridge Type Study is the process by which the most appropriate structure type for a
given location is determined. A Bridge Type Study considers the structure types feasible
for the site parameters or environmental commitments, provides the reasoning for
eliminating or developing particular alternatives, including cost estimates for all
alternatives considered, and finally explains the rationale for the selection of the
structure type chosen.
A Level 3 Barrier Warrant Analysis (including a Benefit/Cost Analysis) shall also be
performed according to the requirements of the latest Illinois Tollway Traffic Barrier
Guidelines in order to determine abutment type and location and span configuration for
all bridges over the Illinois Tollway. This procedure shall also be followed in determining
culvert lengths. All Barrier Warrant Analyses shall be submitted and reviewed by the
Illinois Tollway prior to submission of TS & L Plans.
The Bridge Type Study is a part of the planning process which justifies the TS & L Plan.
For major bridges or when requested by the Illinois Tollway, the Bridge Type Study shall
be submitted to the Illinois Tollway for review and acceptance before preparation of the
TS & L Plan can commence. Such a study would provide additional written treatments
concerning economic evaluations for the viable alternatives, span length versus pier
height studies for the approaches, pier type structural and aesthetic studies, main span
and the approach span structure type aesthetic studies, and architectural presentations
of the alternative systems presented in the study. The report shall also document
unusual design procedures, deviations from or variations of AASHTO Specifications to
be used, special materials or details proposed or tests anticipated.
Beam selection criteria shall be in accordance with the Illinois Department of
Transportation (IDOT) Bureau of Design and Environment (BDE) Manual and Sections
12 and 13. All Illinois Tollway bridges shall be designed in accordance with
March 2016
3-1
Illinois Tollway
Structure Report
Structure Reports are not required to construct, reconstruct, widen or extend Illinois
Tollway mainline or ramp structures. However, if the Illinois Tollway is planning on
constructing, reconstructing, widening or extending a structure that is jointly maintained
by the Illinois Tollway, IDOT or a local agency, the Designer is required to complete the
appropriate Structure Report as noted above and submit it with the TS & L Plan
package for IDOTs review and approval.
3.4
Hydraulic Information
TS & L Plans for all new structures and existing structures to be replaced,
reconstructed, widened or extended which span over or convey waterways shall require
a Waterway Information Table, a Design Scour Elevation Table, if required, and the
scour critical analysis coding as described in Article 2.4 of this Manual.
3.5
TS & L Plans for all new structures and existing structures to be replaced,
reconstructed, widened or extended shall require a subsurface soil investigation and
Structure Geotechnical Report (SGR) in accordance with IDOTs Bridge Manual
Sections 2.1.5.3, 2.3.4.3 and 2.3.6.3. The Designer along with the Geotechnical
Engineer shall develop a subsurface exploration program for each structure. The
subsurface exploration and analyses shall be in accordance with the latest IDOT and
Illinois Tollway Geotechnical Manuals. The data from the exploration program shall be
analyzed and the resulting foundation recommendations shall be documented in the
SGR in accordance with the All Geotechnical Manual Users (AGMU) Memo 05.2
issued September 26, 2005. SGRs shall be submitted with the 30% design submittal.
March 2016
3-2
Illinois Tollway
SECTION 4.0
4.1
Introduction
Context Sensitive Solutions (CSS) is an interdisciplinary process, embraced by the
Illinois Tollway that seeks effective, multimodal transportation results by working with
stakeholders to develop, build and maintain cost-effective transportation facilities which
are appropriate to and reflect the projects surroundings. When implementation of the
CSS process has been initiated for a particular project, the DSE is expected to
coordinate potential enhancements during the appropriate phase of planning and
design. When a formal CSS process is not implemented, the DSE shall consider context
of the site as an integral part of the functional and aesthetic design development.
4.2
Bridges
All bridges make an aesthetic impression on the surroundings and the DSE shall
consider and control the impact early in the design phase. The main aesthetic of a
bridge is primarily a product of the structural members themselves. The structure form
and shape, through the use of proper materials, dimensional relationships and
proportions shall be used to emphasize the lightness, slenderness and horizontal
continuity, allowing the bridge structure to produce the primary aesthetic on its own.
Supplemental details such as texture and color can be important but are ordinarily
considered secondary or complementary enhancements to the structural shape.
Ornamentation shall not be added or shall be kept to a minimum and used only with
special requirements for structures of significance.
Detailing and placement for appurtenances such as drain pipes, conduits, utilities,
fencing, rails, signage and lighting shall be coordinated for visual compatibility and
design consistency. Drain pipes and other conduit systems shall employ simple details
and be located as visually unobtrusive as possible.
The standard treatment for a bridge and its overpass and underpass area is the use of a
basic utilitarian highway bridge, essential erosion control and seeding in landscape
areas, and routine Illinois Tollway signage identifying the crossroad. Upgrade
treatments for a bridge and the overpass or underpass area where a response to the
significance of the crossroad, physical context, or community has been determined,
may include the addition and aesthetic enhancements of architectural elements,
landscape treatments and signage components. Throughout design, the DSE shall
orchestrate all primary aesthetic structural elements and details for efficiency and
economy to minimize cost and to achieve an attractive bridge.
March 2016
4-1
Illinois Tollway
Walls
Due to the potential size, quantity and location, walls including noise abatement walls
and retaining walls are often highly visible components within the Illinois Tollway
corridors. The vertical and horizontal alignment, material type, textures and color
become important elements of consideration. The primary wall aesthetic theme is to
create a natural appearance that blends with the surrounding environment. Walls shall
be designed as visual assets from the prospective views of motorists and adjoining
communities. The DSE shall develop all wall types together with surrounding structural
and non-structural elements to create a visual relationship to one another and provide a
harmonious aesthetic throughout the corridor.
March 2016
4-2
Illinois Tollway
SECTION 5.0
DESIGN CRITERIA
5.1
Structural Design Criteria
The following criteria shall be used for the design of structures on the Illinois Tollway.
The applicable information shall be shown on the contract plans as discussed in Article
6.3.4.
BRIDGES New or Replacement
2014 AASHTO LRFD Bridge Design
Specifications (except as modified by
IDOT and Illinois Tollway Structure
Design Manual)
Illinois Tollway Structure Design Manual
Illinois Department of Transportation
Design Specifications
Bridge Manual
Design Loads
th
Design Specifications
Design Loads
March 2016
th
th
HL-93
5-1
Illinois Tollway
Reinforced Concrete
Reinforcement
3,500 psi
60,000 psi
24,000 psi
60,000 psi
fc=Compressive Strength
(IDOT Bms.)
fc =Compressive Strength
(Illinois Tollway Bms.)
0.6 fci
Case (a): 0.60w fc ;
w = 1 for IDOT
members
Case (b): 0.45 fc
0.19fc (max)
0.24fc
0.40fc
Uncracked
<=0.095fc
0.153 in
0.217 in
270,000 psi
fy = yield strength
50 ksi (Typ.)
Prestressing Strands
Structural Steel
March 2016
5-2
Illinois Tollway
Other Bridges
BRIDGES
Seismic Design
Zone 1 (LRFD)
Category A (LFD)
Site-specific based on
existing soil type.
Review SGR for
additional information.
BOX CULVERTS
Design Specifications
March 2016
5-3
th
March 2016
Latest Edition
November 2, 2011
Rev. January 27, 2012
Service Load Design
Method for
modifications or
extensions of existing
foundations
Illinois Tollway
150 pcf
120 pcf
40 pcf
50 pcf
3,500 psi
fc = Compressive Strength
5,000 psi
fy = Yield Strength
60,000 psi
24,000 psi
fy = Yield Strength
65,000 psi
RETAINING WALLS
Design Specifications
th
150 pcf
120 pcf
Live load surcharge
equivalent to 2 feet of
earth.
Barrier shall be
designed to transfer
impact loads to top of
wall.
Impact Loads
Earth Pressure
March 2016
5-4
Illinois Tollway
3,500 psi
4,000 psi (Design)
4,000 psi (Design)
60,000 psi
24,000 psi
Soldier Piles
fy = Yield Strength
36,000 psi
Timber Lagging
1,000 psi
Design Specifications
th
Current Edition
March 2016
March 2016
Dead Load
Wind Loads
Seismic Loads
Deflection
Structure Mounted:
L/180
Ground Mounted: L/240
March 2016
5-5
Illinois Tollway
Design Specifications
Design Loads
March 2016
5-6
th
6 Edition
Latest
March 2016
March 2016
Self-weight
Per Loading
requirements on Illinois
Tollway Standard F
Drawings and Base
Sheets
Illinois Tollway
The following table lists the minimum vertical clearance requirements for all vehicular
bridges and railroad bridges over the Illinois Tollway. Early coordination with railroads
is required to ensure that these minimum vertical clearances are acceptable for railroad
bridges over the Illinois Tollway.
Bridge Over Illinois
Tollway
Illinois Tollway Single
Interstate Routes (1)
Illinois Tollway
Bridge Over
All Routes
Type of Work
New Bridge or
Reconstructing Bridge
Widening or
Rehabilitating
Existing Bridge
New Bridge or
Reconstructing Bridge
Vertical Clearance
Widening or
Rehabilitating
Existing Bridge
15'-5"** (desirable)
Type of Work
New Bridge or
Reconstructing Bridge
Widening or
Rehabilitating
Existing Bridge
16'-5"*
16'-0"
16'-5"* (desirable)
15'-5"** (minimum)
* 16-5" allows for an ultimate 16'-0" clearance after a 5" overlay is constructed.
**15'-5" allows for an ultimate 15'-0" clearance after a 5" overlay is constructed.
(1)
The following segments of the Illinois Tollway are considered Single Interstate
Routes (Military Defense Route):
Tri-State:
Tri-State:
Jane Addams Memorial:
Reagan Memorial:
Veterans Memorial:
March 2016
5-7
Illinois Tollway
In addition to the above, vertical clearances shall comply with requirements of the latest
IDOT Traffic Manual. If the clearance is less than 14-6, the clearance shall be posted
on a rectangular Low Clearance sign mounted to the structure over the highway. If the
clearance is less than 14-0, the clearance shall also be posted on a Low Clearance
sign in advance of the structure over the highway, as a supplement to the sign mounted
to the structure.
The following minimum vertical clearances shall be used for all other structures:
Structures over railroads 23'-0" between top of rail and low structure measured
at or within 9'-0" each side of center of outside tracks or as mandated by the
operating railroad. On widening structures, not less than the existing, unless
written approval is obtained from the railroad. Any clearance less than 21'-6"
shall require Interstate Commerce Commission approval.
Stream crossings 2'-0" measured between design high water and low structure,
or 1'-0" between any measured high water and low structure. Use whichever
criterion produces the highest low structure.
March 2016
5-8
Illinois Tollway
Edge of pavement to the nearest face of existing piers on the Illinois Tollway System
shall be 10'-0" minimum.
The horizontal clearance from the edge of traveled way to the closest face of shoulder
piers or abutments shall be established by a Barrier Warrant Analysis prepared by the
Design Section Engineer and reviewed by the Illinois Tollway. Refer to Article 3.2 for
additional guidance.
The preferred design for a bridge crossing over the Illinois Tollway is a two-span
continuous structure without shoulder piers and with slopewalls to provide an open
feel.
In the case of an abutment constructed on an embankment, the toe portion of the
slopewall shall be graded to a maximum slope of 1:4 (V:H) unless shielded by barrier or
guardrail. The limit (Grade Break Point) of 1:4 slope shall be determined by a Barrier
Warrant Analysis as previously described. The remainder of the slopewall shall be
graded to a maximum of 1:2 (V:H). The entire slopewall shall be paved. See Article
10.7.
5.4
Deck Width
For structures carrying mainline, the minimum bridge width shall match the approach or
departure roadway, including pavement lane widths, shoulder widths and gutters. The
bridge shoulder width shall equal the roadway shoulder width plus 1-0 for guardrail or
2-0 for F-Shape or single-slope barrier and shall be a minimum of 12-0. In cases
where the approach and departure gutters are different, the larger bridge shoulder
dimension shall be used.
For ramps and CD structures, the minimum bridge width shall match the approach or
departure roadway, including pavement lane widths, shoulder widths and gutters. The
bridge shoulder width shall equal the roadway shoulder width plus 1-0 for guardrail or
2-0 for F-Shape or single-slope barrier. The right shoulder shall be a minimum of 12-0
and the left shoulder shall be a minimum of 6-0 in the direction of traffic.
Increase shoulder widths on curved bridges, if necessary, to provide required stopping
sight distance.
5.5
The Illinois Tollway preference is to support all of the mainline and directional ramp
bridges on a minimum of six lines of beams or girders unless the ramp traffic can be
detoured for the duration of construction and/ or reconstruction.
5.6
Dead Loads
The deck dead loads used for interior beams shall include the calculated fillets expected
and the deck width center to center of the beam spacing. The deck dead loads used for
March 2016
5-9
Illinois Tollway
Field Survey
General
Prior to the beginning of the conceptual or TS & L designs, a field survey shall be
completed and shall include, but shall not be limited to, the items as outlined herein. A
stationing system shall be established and all topography within the site which is
relevant to the proposed work shall be collected utilizing one of the networks of
Continuously Operating Reference Stations (CORS) coordinated by the National
Geodetic Survey (NGS). Illinois Tollway CORS stations are located at the following
Maintenance and or Plaza facilities:
Station Name
ALSIP
GURNEE
SCHAUMBURG
BELVIDERE
ROCKFORD
NAPERVILLE
DEKALB
DIXON
BOLINGBROOK
Station I.D.
Number
TM01
TMO4
TMO5
TM06
TMO7
TM08
TM11
TM12
TP89
A permanent Benchmark for each structure shall be established and all elevations taken
for the structure shall be tied to this Benchmark.
5.7.2
On existing barriers and parapets that are proposed for modification, the joint locations
shall be field verified before designing the new longitudinal reinforcement bars.
5.7.3
Bearings
A condition survey shall be made of the existing bearings to verify the recommendations
March 2016
5-10
Illinois Tollway
On bridges that are to be widened, the following data shall be obtained or verified:
Elevations along the bottom of the beam adjacent to the widening and elevations
at the top of the deck at the same points.
Top of seat elevations at each abutment and pier adjacent to the proposed
widening.
5.8
Construction
General:
If the designers construction scenario requires a special method of work or restriction to
the way the Contractor builds the structure, it shall be defined in the contract
documents.
An example would be:
Precast Beams:
The pre-cast beams have been designed to accommodate loads arising from
normal hoisting, storage and transportation. Specifically:
-
The lifting apparatus used to pick the beams shall distribute loads evenly
between all the lifting points shown. Furthermore, load distributing slings and
pins with the same radius as that shown for lifting loops on the drawings shall
be used every time the beams are hoisted including movement in the precast
yard.
Beams shall be supported within a distance equal to 1 1/2 times the depth of
the beam from each end of the beam during storage and transportation.
March 2016
5-11
Illinois Tollway
Railroad Crossings
Right of entry, insurance and railroad safety training are required when inspecting and
working on railroads right of way.
The following information shall be provided on the drawings and within the contract
documents for railroad bridges and bridge structure over railroads:
Information
Comments
Design Specifications:
Used for design of all railroad bridges.
Grade Separation Manual (Railroad
Specific)
AREMA (Latest Release)
Illinois Tollway Structure Design
Manual
Loading:
Used for design of railroad bridges. AREMA and
Cooper E-80 or Railroad Specific
Railroad Specific Grade Separation Manuals shall be
used.
Horizontal
diagram
and
vertical
March 2016
5-12
Illinois Tollway
Comments
March 2016
5-13
Illinois Tollway
March 2016
Illinois Tollway
SECTION 6.0
6.1
PLAN PREPARATION
CADD Standards
Plan presentation shall be in accordance with the Illinois Tollway CADD Standards
Manual.
6.2
Each bridge, culvert and retaining wall shall consist of a set of sequentially numbered
plan sheets. Plan sheets shall be organized in such a manner as to facilitate
construction. Shown below are plan sheet lists for several types of structures.
6.2.1
Bridges
1. General Plan and Elevation
2. General Notes, Index of Sheets and Total Bill of Material
3. Construction Staging
4. Substructure Layout, Temporary Retention and Slope Paving Details
5. Limits and details of Temporary Soil Retention System
6. Pile Driving and/or Drilled Shaft Installation Records
7. Abutment Details
8. Pier Details
9. Framing Details
10. Bearing and Anchor Rod Details
11. Superstructure Elevations
12. Superstructure Details
13. Expansion Joint Details
14. Drainage Details
15. Approach Slab Details
16. Boring Logs
6.2.2
Culverts
1. General Plan and Elevation
2. General Notes, Index of Sheets and Total Bill of Material
3. Construction Staging (if required)
4. Foundation Layout and Details (if required)
5. Limits of Temporary Soil Retention Systems (if required)
6. Barrel Details
7. Head and Wing Wall Details
8. Approach Slab Details (if required)
9. Boring Logs
6.2.3
March 2016
6-1
Illinois Tollway
For Performance Based Retaining Walls, the DSE shall review Working Drawings to
ensure they are in accordance with the Plan Sheet requirements in Article 6.2.3.
6.3
6.3.1
The plan and elevation views for each bridge shall include at a minimum the following
information:
Skew angles
Stations and elevations at the centerline of each pier and back of and centerline
of bearing of each abutment
March 2016
6-2
Illinois Tollway
Type and depth of spans, i.e., 72-inch PPC I-beam or 48-inch Steel Plate Girder,
etc.
Location of fixed and expansion bearings, deck drainage, signing and lighting
Bottom of footing elevations and foundation type including pile or drilled shaft
size, length and capacity
Location of all existing and proposed utilities (overhead and buried) and storm
sewers in the vicinity of the bridge
Benchmark
Include location and description of the benchmark in the upper left-hand corner of the
General Plan and Elevation Sheet.
6.3.3
Structure Description
Structure Rehabilitation - Include a description of the existing structure and list of Major
Items of Work as well as the required maintenance of traffic (MOT).
Structure Widening - Include a description of the existing structure and required MOT.
Structure Replacement - Include a description of the existing and proposed structure as
well as the required MOT.
New Structure - Include a description of the proposed structure and MOT if required.
Salvage For the removal of existing structures, reconstruction and rehabilitation,
indicate if any items of the existing bridge will be removed and incorporated into a future
Illinois Tollway contract or for future Illinois Tollway use. If no portion of the structure will
be removed for reuse in a future contract, indicate No Salvage.
March 2016
6-3
Illinois Tollway
Design Criteria
Design criteria are listed in Article 5.1. The design criteria shown on the plans shall
include the following:
Design Specifications
Construction Specifications
o Illinois Department of Transportation Guide Bridge Special
Provisions (GBSPs)
o Illinois Tollway Supplemental Specifications to the Illinois
Department of Transportation Standard Specifications for Road and
Bridge Construction [Use latest edition]
o Illinois Department of Transportation Supplemental Specifications
and Recurring Special Provisions [Use latest edition]
o Illinois Department of Transportation Standard Specifications for
Road and Bridge Construction [Use latest edition]
Items indicated in [ ] and bold are notes to the designer to include the latest date and
edition for plan presentation.
Design Stresses
Seismic Criteria
6.3.5
Profile Sketches
Provide "Profile Grade" sketches for the structure, roadways, waterways and facilities
crossed by the bridge. Indicate location and limits of the bridge on the appropriate
Profile Grade Sketch. For examples of "Profile Grade" sketches, see Figures 6.3.6.1
and 6.3.6.2.
March 2016
6-4
Illinois Tollway
Superelevation Transitions
Location Map
Provide a "Location Map" containing the following information in the lower right hand
corner of the sheet. For an example of a "Location Map" see Figure 6.3.8.1.
North Arrow
Location of Structure(s)
Significant Landmarks
6.3.9
Highway Classification
For grade separations, provide the following information for the Route over and under
the proposed structure(s): Route Identification, Class, DHV (existing and future), ADT
(existing and future), ADTT (existing and future truck traffic) and Design Speed.
6.3.10 Railroad Information
For railroad crossings, provide the number, type and time of trains passing over/under
the proposed structure each day. In addition, all structures on or over railways shall be
located by the Railroad Mile Post (MP) number.
6.3.11 Waterway Information
For waterway crossings, provide a waterway information table in accordance with
Section I-302.02 of the latest IDOT Drainage Manual and the scour critical analysis
codings as described in Article 2.4 of this Manual. Refer to Figure 6.3.11.1 for an
example.
6.3.12 Structure Rating
The Inventory and Operating Rating for each new, reconstructed or widened structure
shall be calculated by the Designer for the HL-93 loading and shown on the General
Plan and Elevation Sheet. The load rating shall include future wearing surface.
March 2016
6-5
Illinois Tollway
A coded "Summary of Quantities" for individual Pay Items and a "Total Bill of Material"
shall be shown in the plans for each structure. The "Total Bill of Material" shall be
divided into Superstructure, Substructure, Total and Record Quantities and shall be
placed on the first or second sheet of the structure plans. Summary of Quantities shall
be provided for all Pay Items included in the structure contract on appropriate plan
sheets. The total of all of the individual Summary of Quantities shall equal the Total
shown in the Total Bill of Material.
6.5
Abbreviations
Provide a list of all abbreviations and their meanings which will be used on the
drawings. A list of some typical abbreviations is shown below.
P.G.L.
N.B.L.
S.B.L.
S.
ABUT
N.
ABUT
E.F.
F.F.
B.F.
6.6
I.F.
O.F.
P.J.F.
P.J.S.
NORTH ABUTMENT
BK/
INSIDE FACE
OUTSIDE FACE
PREFORMED JOINT FILLER
PREFORMED JOINT
SEALER
BACK OF
EACH FACE
FRONT FACE
BACK FACE
B/
T/
PROP.
EXIST.
BOTTOM OF
TOP OF
PROPOSED
EXISTING
Index of Sheets
Provide an Index of Sheets for each bridge. The index shall list all of the sheet numbers
and titles that are part of the bridge plans. The titles in the index shall exactly match the
individual sheet titles.
March 2016
6-6
Illinois Tollway
Separate Reinforcement Bar Schedules shall be prepared for each element of the
structure and shown along with bending diagrams of each bent bar on the appropriate
plan sheet. See Figure 6.7.1 for the Reinforcement Bar List format.
When detailing lengths of reinforcement bars, consideration shall be given to
transportation and handling and, where extremely long lengths are contemplated, to
availability and special orders. When the location of bar splices is arbitrary, as in the
case of the longitudinal reinforcement of deck slabs on beams and girders, the preferred
maximum lengths are as follows:
#6 bars and up ...... 36'-0"
#4 & #5 bars .......... 30'-0"
Bars shall be detailed to the closest inch of length and the weight of reinforcement bars
shown in the Bill of Material shall be to the nearest ten (10) pounds.
To provide uniformity on all structure plans, bar designations used shall be as follows:
a
b
c
d
e
g
h
m
n
p
s
t
u
v
w
x
In no case shall the same designation be used for reinforcement bars of a different size,
length and shape when they are employed in other elements of the structure.
6.8
Beam Numbering
All beam lines shall have a unique beam number. For complete replacement bridges,
beams and girders shall be numbered from left to right when looking in the direction of
increasing station. When new beams are added to an existing structure, the existing
beams shall not be renumbered. The new beams shall be numbered with a suffix
consecutively, such as Beam 1A, 1B, 8A, 8B, etc.
March 2016
6-7
Illinois Tollway
The Preliminary 60% plans form the basis of establishing final geometry and
dimensions of the structure. The objective of the Preliminary Design Phase (60%) is to
incorporate comments from the Conceptual Design Phase (30%), and to demonstrate
that the plans are being developed into the Pre-Final Design Phase (95%).
The following items shall be included in the 60% submittal:
Plan sheets, details and views shall be included to ensure the sheet index and layout of
sheets has been established per Illinois Tollway guidelines.
Appropriate Illinois Tollway Base Sheets shall be incorporated as plan details into
the Contract Plans (the Base Sheets may not be finalized).
March 2016
6-8
Illinois Tollway
51'-6"
27'-6" 27'-6"
51'-6"
"
"
TANGENT TO
6"
1 "
2086
~ TOLL HIGHWAY
STA.2086+72.44
2087
"
1'
-1 "
SKEW
1'
-0 "
7"
~ BRG.
~ PIER 1
~ PIER 2
~ BRG.
W. ABUT.
E. ABUT.
OFFSET SKETCH
MARCH, 2016
FIGURE 6.3.5.1
ILLINOIS TOLLWAY
EL. 651.
95
EL. 655.
66
EL. 652.
95
%
71
+2.
-3.
71
%
LVC = 200'
STRUCTURE LIMITS
MARCH, 2016
FIGURE 6.3.6.1
ILLINOIS TOLLWAY
EL. 652.
29
STA. 1625+00
C
ROAD OVER)
L (
STA. 1624+15.
37
EL. 652.
95
STA. 1623+00
-0.
33%
MARCH, 2016
FIGURE 6.3.6.2
ILLINOIS TOLLWAY
RANGE 12 E
3 RD PM
FOREST
PRESERVE
AD
RO
IET
JOL
21
TOWNSHIP 38 N.
20
WILLOW
SPRINGS ROAD
55
12
20
28
29
45
NW
C&
F
S&
T
A
294
PROPOSED STRUCTURE
LOCATION MAP
MARCH, 2016
FIGURE 6.3.8.1
ILLINOIS TOLLWAY
MARCH, 2016
FIGURE 6.3.11.1
ILLINOIS TOLLWAY
PIER
113D)
61)
111)
71)
113C)
113B)
CONDITION (
ITEM
113A)
113)
NBI CODING
E. ABUT
Q500
Q100
W. ABUT
MARCH, 2016
FIGURE 6.3.12.1
ILLINOIS TOLLWAY
No.
SIZE
LENGTH
d51(E)
28
#5
4'-3"
e50(E)
18
#5
13'-3"
h51(E)
#5
5'-5"
h52(E)
24
#5
3'-9"
h53(E)
24
#5
8'-6"
h61(E)
24
#5
2'-0"
h62(E)
34
#5
3'-8"
h51(E)
20
#6
7'-3"
h52(E)
54
#6
5'-4"
v51(E)
18
#5
4'-8"
v52(E)
18
#5
4'-6"
v53(E)
18
#5
2'-6"
s51(E)
18
#5
4'-0"
s52(E)
18
#5
1'-3"
s53(E)
18
#5
6'-11"
t51(E)
50
#6
5'-8"
t52(E)
24
#6
10'-5"
t53(E)
24
#6
2'-8"
SHAPE
BILL OF MATERIAL
PAY
ITEM
MARCH, 2016
RECORD
DESCRIPTION
UNIT
FIGURE 6.7.1
QUANTITY
QUANTITY
ILLINOIS TOLLWAY
March 2016
Illinois Tollway
SECTION 7.0
7.1
GENERAL NOTES
The following general plan notes, in addition to those from Section 3.1.3 of the latest
IDOT Bridge Manual, shall be included in the Contract Plans as applicable.
Items indicated in [ ] and bold are notes to the designer and shall be filled in or removed
in the plans as applicable.
7.1.1
Cast-In-Place Concrete
1. All exposed concrete edges shall have a " x 45 chamfer, except where shown
otherwise. Chamfer on vertical edges shall be continued a minimum of one foot
below finished ground level.
2. Cast counter weights at least 48 hours in advance of placing deck slab.
7.1.2
Reinforcement Bars
March 2016
7-1
Illinois Tollway
Structural Steel
1. All bearing and side retainer anchor rods shall be set before permanently bolting
diaphragms or cross frames over supports.
2. All side retainers shall be installed and bolted down prior to forming and pouring
the deck slab.
3. Web plates shall be furnished in available mill lengths and widths with a minimum
number of web splices. Location of splices shall be subject to the approval of the
Designer and shall be a minimum of 1-0 from stiffeners or flange splices.
4. Bearing stiffeners and ends of beams shall be perpendicular to flange. [For all
rolled beam bridges and plate girder bridges with grades of 3% or less and
skews of 20 degrees or less]
5. Bearing stiffeners at abutments shall be vertical and ends of beams shall be
vertical. Bearing stiffeners at piers shall be perpendicular to flange. [For plate
girder bridges with grades greater than 3% or skews greater than 20
degrees]
6. The calculated deflections of the primary beams under steel self-weight shall be
used to detail diaphragms, cross frames and lateral bracing connections, and to
erect structural steel such that the beams will be plumb within a tolerance of +/1/8 inch per vertical foot throughout.
7. Painting of new structural steel shall be accomplished in accordance with Section
506 of the Standard Specifications except field-applying intermediate or final
coats of paint on new steel shall not be allowed.
8. Load carrying components including tension flanges, webs and splice plates
designated NTR shall conform to the AASHTO Impact Testing Requirement,
Zone 2. [This note shall be included on sheets detailing structural steel
main members.]
9. The deck pouring sequence shown on the plans has been used to design the
required beam camber and to determine the Theoretical Grade Elevations
Adjusted for Dead Load Deflection used in the calculation of fillet heights, t.
Requests for changes to the plan pouring sequence shall be submitted in writing
(prior to ordering of steel, prior to the start of building forms for the deck
concrete) [Choose applicable phrase]. Modifications, either to the camber
diagrams or the Theoretical Grade Elevations Adjusted for Dead Load
Deflection, resulting from changes to the plan pouring sequence shall be the
responsibility of the Contractor. All required plans shall be submitted with the
request and shall be sealed by an Illinois Licensed Structural Engineer.
March 2016
7-2
Illinois Tollway
Construction
1. Plan dimensions and details relative to existing structure have been taken from
existing plans and are subject to nominal construction variations. It shall be the
Contractor's responsibility to verify such dimensions and details in the field and
make necessary approved adjustments prior to construction or ordering of
materials. Such variations shall not be cause for additional compensation for a
change in the scope of work; however, the Contractor shall be paid for the
quantity actually furnished at the unit price for the work.
2. Contractor shall not scale dimensions from the Contract Plans for construction
purposes. Scales shown are for information only.
3. No construction joints except those shown on the plans shall be allowed unless
approved by the Engineer.
4. The Contractor may request copies of existing construction plans that are
currently on file with the Illinois Tollway. The request shall be in writing with the
understanding that any reproduction cost will be at the Contractors expense at
no additional cost to the Illinois Tollway.
5. No concrete cutting shall be permitted until the cutting limits have been outlined
by the Contractor and approved by the Engineer.
6. It shall be the Contractor's responsibility to verify the location of all utilities prior to
starting construction. Contact J.U.L.I.E., 800-892-0123.
7. It shall be the Contractors responsibility to verify the location of all fiber optic
utilities prior to starting construction. The Contractor shall initiate the location
process for the fiber optic cable by completing a Request Illinois Tollway Utilities
Locate form filled in online at the Illinois Tollway website under Doing Business
at least four (4) business days prior to starting any underground operations,
excavations or digging of any type in the general area of the fiber optic cable.
8. The Contractor shall use care when excavating around existing foundations. Any
damage to the existing structure and/or supporting foundation shall be repaired
or replaced at the Contractor's expense at no additional cost to the Illinois
Tollway.
9. Existing reinforcement which is to be incorporated into the new construction shall
be blast cleaned to grey metal, straightened (without heating), and cut to fit. Cost
of which shall be included with Concrete Removal. [If used, add incidental
items to Special Provision 110.]
10. The protective shield system shall extend a minimum of 10 beyond the indicated
limits of repair shown in the plans or 5 beyond the actual limits of partial or full
depth repair as identified in the field, whichever is greater.
March 2016
7-3
Illinois Tollway
March 2016
7-4
Illinois Tollway
The following general plan notes may be included in the Contract Plans as applicable,
with appropriate modifications.
7.2.1
Demolition Plan
1. The Contractor shall submit a demolition plan to the Engineer for review and
acceptance, detailing the proposed methods of demolition and the amount,
location(s) and type(s) of equipment to be used. With the exception of removal of
single box culverts, for work adjacent to or over an active roadway, railroad or
navigable waterway, the demolition plan shall include an assessment of the
structures condition and an evaluation of the structures strength and stability
during demolition and shall be signed and sealed by an Illinois Licensed
Structural Engineer.
March 2016
7-5
Illinois Tollway
Erection Plan
[Include for both Steel and Precast Prestressed Concrete Beams]
1. A Structural Engineer, licensed in the State of Illinois, shall prepare and submit
Structure Assessment Reports (SARs) for the proposed work associated with
March 2016
7-6
Illinois Tollway
March 2016
7-7
Illinois Tollway
March 2016
7-8
Illinois Tollway
SECTION 8.0
8.1
CONSTRUCTION STAGING
General
The plans shall clearly identify and show all stages of construction, both superstructure
and substructure details, required to replace, widen or reconstruct each structure, while
simultaneously maintaining traffic in one or both directions. For an example of a
Construction Staging Plan, see Figure 8.1.1. Construction stage lines shall be shown
and located in all plan views and cross sections. The Designer shall verify that the
structure and adjacent roadway staging match. Stage lines shall be located along a lane
line wherever possible, and at a distance greater than of the beam spacing from the
centerline of any beam (within the middle half of the beam spacing). If stage lines
cannot be located along a lane line, they shall be located within the center third of the
lane. Pay items for structural removal shall be per bridge.
8.2
The Construction Staging Plans shall also show the location of all temporary concrete
barriers for each stage of construction where barriers are required. The temporary
concrete barrier shall be anchored to the existing deck slab when the distance from the
back of the barrier to the edge of the slab is less than 3-9. Drilling of anchors into new
deck slabs shall not be permitted and the 3-9 distance to the edge of the new slab
shall be provided.
8.3
A drawing or drawings shall be included in the bridge plans to define the limits of a
protective shield system when it is required. The quantity of protective shield system to
be installed shall be stated within the Plans. Removal of protective shield system shall
not be measured for payment. A special provision is required to cover the cost of
designing, furnishing, erecting, maintaining and removing temporary protective shields
at the locations and limits shown in plans. The Contractor is responsible for the
convenience and safety of the public during erection and construction of each element
of the structure in accordance with Article 107.09 of the latest Illinois Tollway
Supplemental Specifications.
A protective shield system shall be required under the superstructure or at the lower
level of the superstructure whenever equipment, falling objects or material may cause
damage to existing aerial wire lines, railroads, streets, highways, regulatory waterways,
vehicular or waterway traffic or injury to pedestrians, bicyclist or individuals traveling in
trains, vehicles or water craft.
The limits of the protective shield system for bridge projects limited to full and partial
depth deck patching shall be set considering the area of the deck to be improved. At a
minimum, protective shield shall extend 10 beyond the expected limits of partial or full
depth repair above traffic.
March 2016
8-1
Illinois Tollway
The lateral limits of the protective shield system are shown in the following table:
Construction or
Reconstruction
Case
1
New construction
Deck and superstructure
widening
Deck removal and
replacement
Deck replacement and
widening
2
3
4
5
8.4
Transverse Limits of
Protective Shield System
Outside of new parapet + 2' to outside of
new parapet + 2'
Existing fascia beam to outside of new
parapet + 2'
Outside of existing parapet + 5' to outside
of existing parapet + 5'
Outside of new parapet + 2' to outside of
new parapet + 2'
10 outside of expected repair limits above
traffic
Temporary Shoring
The staging plans shall also indicate the location of all temporary shoring including the
applied loads required to support portions of the new or existing structure during each
stage of construction. The Contractor is responsible for designing, detailing, erecting,
maintaining and removing the temporary shoring utilizing the information shown in the
proposed and/or existing plans for his or her particular method of construction.
March 2016
8-2
Illinois Tollway
27'-0"
2'
TEMPORARY CONCRETE
BARRIER (ANCHORED)
STAGE I TRAFFIC
STAGE I REMOVAL
1'
3'2'
24'-0"
2 LANES @ 11'-0"=22'
DENOTES REMOVALS
5'-0" 1'-0"
25'-0"
2' 4'
1'
STAGE II TRAFFIC
5'-0" 1'-0"
27'-0"
2'
TEMPORARY CONCRETE
BARRIER (UNANCHORED)
DENOTES REMOVALS
6'-0"
58'-0"
27'-0"
2'2'
27'-0"
5'-0" 1'-0"
FINAL
FIGURE 8.1.1
ILLINOIS TOLLWAY
March 2016
Illinois Tollway
SECTION 9.0
9.1
Substructure Layout
The basic geometry for the location of the substructure shall be clearly shown on the
plans. All elements of the substructure shall be referenced to the same single
longitudinal reference line. For an example of a substructure location plan on tangent
alignment, see Figure 9.1.1. For an example of a substructure layout on curved
alignment, see Figures 3.1.8-2 and 3.1.8-3 of the latest IDOT Bridge Manual.
9.2
Pile Numbering
On any structure, proposed to be supported on piling, a "Pile Driving Record" table shall
be included with the substructure layout or on a separate plan sheet. The "Pile
Location" and "Pile Number" column shall be completed during design leaving some
additional rows for field changes during construction. The pile numbering system will be
used to identify the individual pile and its location in the substructure and "Pile Driving
Record". For an example of the pile numbering system and driving record, see Figure
9.1.1 and Figure 9.2.1, respectively. This data is for record purposes and shall be filled
in by the Engineer during pile driving.
9.3
The location and limits of the Temporary Soil Retention System(s) (TSRS) shall be
shown and identified on the substructure location plan and/or separate plan sheets in
accordance with Section 3.13 of the latest IDOT Bridge Manual. The Designer shall
specify the use of TSRS wherever possible. Temporary sheet piling shall only be used
when site conditions and/or constraints preclude the use of TSRS or where cofferdams
are required to construct elements of the substructure underwater.
March 2016
9-1
Illinois Tollway
The location and limits of all temporary and permanent sheet piling shall be clearly
shown and identified on the substructure location plan and/or separate plan sheets in
accordance with Section 3.13.1 of the latest IDOT Bridge Manual. The cut off elevation
for any part that is to remain in place shall also be shown.
The inside face of the temporary sheeting shall be offset 2'-0" from the proposed
footing; while the inside face of any permanent sheeting shall be located along the edge
of the footing.
The following note shall be added to the plans if a stiff or dense soil layer is present
which may require jetting and/or a larger hammer to penetrate:
Hard driving may be encountered during the sheet piling installation.
The Contractor shall provide the appropriate driving equipment for the
soil conditions indicated on the boring logs.
9.6
Cofferdams
Cofferdams shall be used to construct all elements of the substructure which are
located in water. When shallow water is present; i.e., less than 2 feet, other methods of
dewatering that allow the Contractor maximum flexibility during construction may be
considered.
The location and limits of all cofferdams shall be clearly shown and identified on the
substructure location plan. The top and bottom elevations of the cofferdam shall also
be shown, as well as the cutoff elevation for any part that is to remain-in-place. The
inside face of the cofferdam shall be offset 1'-0" from the proposed footing. The
cofferdam and seal coat shall be designed in accordance with Section 3.13.3 of the
latest IDOT Bridge Manual.
The following note shall appear on the substructure location plan when cofferdams are
required:
The information shown for cofferdams is estimated.
It is the
Contractor's responsibility to provide a design and details for each
cofferdam, complete with calculations and drawings, signed and sealed
by an Illinois Licensed Structural Engineer, for the Engineers review and
acceptance before starting work.
March 2016
9-2
Illinois Tollway
The location and limits of structural sub drains behind abutments and wingwalls
including invert elevations, slopes, and outfalls shall be shown on the substructure
location plan.
March 2016
9-3
Illinois Tollway
BK. WEST
BK. WEST
MARCH, 2016
APPR. BENT
~ PIER
BK. EAST
ABUT.
BK. EAST
ABUT.
APPR. BENT
X'-X"
X'-X"
X'-X"
SKEW (TYP.)
A
10
11
13
12
12
11
11
10
& RDWY.
OR P.G.L.
4
2
~ BRIDGE
10
10
FOOT
I
NG
2' MI
N.
(
TYP.
)
FOOT
I
NG
LEGEND:
ILLINOIS TOLLWAY
*
*
FIGURE 9.
1.
1
10
13
12
14
13
11
11
14
15
14
12
12
15
13
16
15
17
16
13
14
14
15
15
16
A
16
16
H-PILES
TEMPORARY SOIL RETENTION
SYSTEM OR SHEET PILING
MARCH, 2016
FIGURE 9.
2.
1
ILLINOIS TOLLWAY
MARCH, 2016
FIGURE 9.
3.
1
ILLINOIS TOLLWAY
General
Design
The friction force caused by an expansion bearing sliding on its bearing plate or
deforming on the supporting substructure element shall be included in the design of the
substructure. These forces are determined by multiplying the coefficient of friction by the
total dead load reactions on the bearing. For steel on steel, a coefficient of 0.30 shall be
used and for teflon on teflon, a coefficient of 0.10 shall be used.
For elastomeric bearings, the force required to deform the elastomeric pad shall not be
less than 25 pounds per square inch of bearing area for Type I bearings or 0.04 times
the dead load reaction for Types II and III bearings.
An allowance for additional eccentricity shall be considered in all abutment designs. For
structures with total lengths of greater than 400 feet, each non-integral abutment shall
be designed with an allowance for additional eccentricity of 3 inches. An allowance for
additional eccentricity shall not reduce the required design capacity.
10.3
Abutment Types
Integral or semi-integral abutments shall be utilized whenever possible for new grade
separation structures and stream and railroad crossings. High wall abutments may be
considered where integral and semi-integral abutments are not feasible.
For bridges over the Illinois Tollway mainline, the preferred abutment type is open
abutment with slopewalls and no shielding.
Integral abutments shall be used with steel beams and girders, cast-in-place
concrete slabs, or precast, pre-tensioned concrete beams. Beams shall be
composite with the cast-in-place concrete deck. The superstructure shall be
designed and constructed as a continuous unit between abutments. New integral
abutments shall be designed and detailed in accordance with the IDOT ABD
Memorandum 12.3, "2012 Integral Abutment Bridge Policies and Details", dated
July 25, 2012. See Figures 10.3.1 through 10.3.3 and 10.3.9 for additional
details.
Semi-integral abutments shall be utilized where soil conditions require the use of
two or more rows of piles to support the proposed loadings. Regardless, the
superstructure shall be designed and constructed as a continuous unit between
March 2016
10-1
Illinois Tollway
Stub abutments with expansion joints shall be utilized where the existing soil
condition and proposed loading (reactions) would require two or more rows of
piles for support. They shall also be used when the proposed span length and/or
skew angles exceed the maximums specified for integral and semi integral
abutments. See Figure 10.3.6 for details.
Combinations of retaining walls and pile supported integral, semi integral and
stub abutments shall be utilized in lieu of highwall or vaulted abutments to reduce
span lengths and increase vertical clearance or eliminate the need for shoulder
piers and short end spans. See Figures 10.3.7 and 10.3.10 for details of a pile
supported stub abutment with MSE walls. See Figure 10.3.8 for details of a pile
supported semi-integral abutment with MSE walls. See Figure 10.3.9 for details
of a pile supported integral abutment with MSE walls. MSE walls shall not wrap
around under the approach slab barrier when integral or semi-integral abutments
are used.
Vaulted abutments, either sand filled or void, founded on spread footings or piles
shall not be utilized to support new or replacement structures unless specifically
authorized by the Illinois Tollway. Only existing structures which are to be
widened and are currently supported by vaulted abutments shall utilize the same
design to extend the existing abutments and construct new curtain walls.
10.4
Foundations
10.4.1 Piles
Piles for foundations shall be designed in accordance with the Section 3.10 of the latest
IDOT Bridge Manual.
March 2016
10-2
Illinois Tollway
In general, abutments shall be widened in kind, especially those which can be viewed
by the traveling public. At locations not exposed to the traveling public, such as
structures over railroads or streams, other types of designs may be considered. The
final selection shall be based on serviceability and economics.
Foundations for widened abutments widened to the outside shall be the same type as
the existing. However, construction procedures and type of construction shall be
considered when placing new foundations adjacent to existing so as not to reduce the
load carrying capacity or cause settlement of existing foundations. Existing soil borings
and new soil borings (if required) shall also be considered in the final selection.
Abutment widenings shall be designed to carry any longitudinal or transverse forces
March 2016
10-3
Illinois Tollway
Bridge Seats
The bridge seats shall be constructed in steps poured monolithically with the abutment.
The minimum step shall be inches. Metal shims shall be provided for each bearing if
step is less than inches. The elevation and height of each step shall be shown on the
plans. Steps shall be reinforced when one or more of the preceding steps are equal to
or exceed 4 inches; see Figure 10.6.1. In all cases, the bridge seats between the
bearings shall be sloped inch to drain. The bearing seat shall meet the minimum
support length requirements specified in the AASHTO Seismic Design Section for
Seismic Performance Zone 1 (LRFD) or Category A (LFD).
Concrete sealer shall be applied to the exposed surfaces of all backwalls, bridge seats
and bearing pedestals that are located under expansion or rotation joints between the
deck and backwall.
10.7
Slope Paving
March 2016
10-4
Illinois Tollway
Wing Walls
The traffic face of the shoulder parapet shall be carried the full length of each wing wall,
vaulted span or approach slab. The sloping curb portion of the barrier shall not be
battered to a vertical face or clipped at the leaving or entering end of the barrier. See
Standard Drawings C9, C10 and C11 for the required end treatment of a barrier or
parapet mounted on a wing wall, vaulted span or approach slab. Dog-ear style wing
walls that are parallel to the centerline of abutment may also be considered for
structures with integral abutments. See the latest IDOT integral abutment base sheets
for details.
10.9
Abutment Cap Reinforcement
A detail scaled drawing of the reinforcement and the holes drilled for the bearing anchor
rods shall be provided in the plans, see Figure 10.9.1. The detail drawing shall include
all reinforcement that may interfere with the drilling operation, the reinforcement spacing
and the clearances of the reinforcement to the edge of the cap and the future holes.
10.10 Concrete Shoulder Barrier Transition
A Concrete Shoulder Barrier Transition shall be used upstream of a high wall abutment,
even if the shoulder width is not transitioning.
March 2016
10-5
Illinois Tollway
SUPERSTRUCTURE
70' TRANSITION
MARCH, 2016
APPROACH SHOULDER
CONSTRUCTION
ABUTMENT
B
SLAB
EXPANSION JOINT
JOINT
APPROACH BENT
B
PARAPET
PLAN
SUPERSTRUCTURE
FIGURE 10.
3.
1
CONSTRUCTION JOINT
70' TRANSITION
APPROACH SLAB
EXPANSION JOINT
PARAPET
DECK
FASCIA
APPROACH SLAB
BEAM
ILLINOIS TOLLWAY
END DIAPHRAGM/
ADHESIVE
BACKWALL
APPROACH BENT
**
*INCREASE WHEN EXPANSION MOVEMENT
GREATER THAN 1".
ABUTMENT
WINGWALL
ELEVATION A-A
SUPERSTRUCTURE
70' TRANSITION
MARCH, 2016
APPROACH SHOULDER
SLAB
1'-0"
CONSTRUCTION JOINT
EXPANSION JOINT
1
1
GEOTECHNICAL
FABRIC FOR
4"} PERFORATED
FRENCH DRAINS
APPROACH BENT
DRAINAGE AGGREGATE
SECTION B-B
DIAPHRAGM/BACKWALL
DECK AND
PARAPET
FIGURE 10.
3.
2
GEOCOMPOSITE
WALL DRAIN
"x 1'-4" NEOPRENE SHEET (55
DUROMETER) ATTACHED FULL
HEIGHT AT EDGES TO THE END
DIAPHRAGM/BACKWALL AND
WINGWALL WITH A "x5" STEEL
PLATE AND " } ANCHOR BOLTS,
ABUTMENT
ILLINOIS TOLLWAY
WI
NGWALL
WING WALL
2" MIN. PREFORMED JOINT FILLER *
SECTION D-D
BE DESIGNED CONSIDERING
EFFECTIVE EXPANSION LENGTH
SECTION C-C
**
PARAPET
&
APPROACH SLAB
(TYP.)
WINGWALL
2"CL.
1'-2'' 1'-2''
2'-4''
NOTE:
PILE SPACING SHALL BE 4'-0" MIN. TO 8'-0" MAXIMUM
FIGURE 10.3.3
ILLINOIS TOLLWAY
SUPERSTRUCTURE
MARCH, 2016
30'-0"
70' TRANSITION
APPROACH SHOULDER
CONSTRUCTION
ABUTMENT
B
SLAB
EXPANSION JOINT
JOINT
APPROACH BENT
B
PARAPET
A
C
PLAN
30'-0"
SUPERSTRUCTURE
70' TRANSITION
FIGURE 10.
3.
4
APPROACH SLAB
EXPANSION JOINT
PARAPET
DECK
FASCIA
APPROACH SLAB
BEAM
2" MIN. PREFORMED JOINT
FILLER WITH SUITABLE
ILLINOIS TOLLWAY
**
~ BEARING
ABUTMENT
APPROACH BENT
ADHESIVE
WINGWALL
*
*ADHESIVE MUST BE COMPATIBLE WITH PREFORMED
ELEVATION A-A
SUPERSTRUCTURE
MARCH, 2016
30'-0"
70' TRANSITION
APPROACH SHOULDER
SLAB
1'-0"
CONSTRUCTION JOINT
EXPANSION JOINT
1
1
GEOCOMPOSITE
WALL DRAIN
GEOTECHNICAL
FABRIC FOR
4" } PERFORATED
FRENCH DRAINS
APPROACH BENT
DRAINAGE AGGREGATE
2'-0"
DIAPHRAGM/BACKWALL
ABUTMENT
ILLINOIS TOLLWAY
WI
NGWALL
NOTE 1
NOTE 2
NOTE 1
DECK AND
PARAPET
FIGURE 10.
3.
5
SECTION B-B
NOTES:
*
**
2. 2" MIN. PREFORMED
JOINT FILLER FULLY BONDED TO
*
ABUTMENT CAP WITH SUITABLE ADHESIVE.*
*
1. 2" MIN. PREFORMED JOINT FILLER WITH SUITABLE
ADHESIVE.
SECTION C-C
ABUTMENT SOIL
TO DRAIN (INCLUDED AS
REINFORCEMENT
ABUTMENT
MIN.
MIN.
**
BACK OF
C.I.P. COPING
1'
-0"
9"
PART OF COPING)
TOP OF EXPOSED
LIMITS OF
PANEL LINE
REINFORCED
SOIL MASS
3'-0"
"H"
PRECAST PANELS
MIN.
SOIL REINFORCEMENT
DRAINAGE AGGREGATE
EMBANKMENT
GEOTECHNICAL FABRIC
SELECT FILL
TOP OF FINISHED
MIN.
3'
-6"
GRADE
EXISTING
GROUND LINE
PILES
4" PERFORATED
1'-6"
2'
-0"
PIPE UNDERDRAIN
TOP OF LEVELING
PAD
LIMITS OF REMOVAL AND DISPOSAL
OF UNSUITABLE MATERIAL FOR
STRUCTURES (IF REQUIRED).
X'-X"
X'-X"
FIGURE 10.3.7
ILLINOIS TOLLWAY
MIN.
9"
PART OF COPING)
REINFORCEMENT
**
BACK OF
C.I.P. COPING
MIN.
1'
-0"
ABUTMENT
TOP OF EXPOSED
LIMITS OF
PANEL LINE
REINFORCED
SOIL MASS
3'-0"
"H"
PRECAST PANELS
MIN.
SOIL REINFORCEMENT
EMBANKMENT
DRAINAGE AGGREGATE
GEOTECHNICAL FABRIC
SELECT FILL
TOP OF FINISHED
MIN.
3'
-6"
GRADE
EXISTING
GROUND LINE
PILES
4" PERFORATED
1'-6"
2'
-0"
PIPE UNDERDRAIN
TOP OF LEVELING
PAD
LIMITS OF REMOVAL AND DISPOSAL
OF UNSUITABLE MATERIAL FOR
STRUCTURES (IF REQUIRED).
X'-X"
X'-X"
FIGURE 10.3.8
ILLINOIS TOLLWAY
COARSE AGGREGATE
BACKFILL AS REQUIRED
(INCLUDED AS PART OF
MIN.
BACK OF ABUTMENT
1'
-0"
9"
MIN.
COPING)
C.I.P. COPING
LIMITS OF
TOP OF EXPOSED
REINFORCED
PANEL LINE
SOIL MASS
PRECAST PANELS
3'-0"
"H"
MIN.
CORRUGATED STEEL PIPE
SOIL REINFORCEMENT
EMBANKMENT
**
LENGTH)
DRAINAGE AGGREGATE
SELECT FILL
GEOTECHNICAL FABRIC
2'
-0"
EXISTING
GROUND LINE
1'
-0"
MIN.
4" PERFORATED
PIPE UNDERDRAIN
MIN.
3'
-6"
1'-6"
PILE
TOP OF LEVELING
PAD
X'-X"
FIGURE 10.3.9
ILLINOIS TOLLWAY
1'
-3"
1 "
3'
-6"
1'-7"
2'
-7 "
2"
2
1: .)
AX
(M
"
1'
-0" (
MAX.
)
PJF
PRECAST
PANEL
SELECT FILL
*SOIL REINFORCEMENT
6"
1'-0"
FIGURE 10.3.10
ILLINOIS TOLLWAY
1 "
(
TYP.
)
2" CL.
2" CL.
(TYP.)
d
1'
-0"
(
MIN.
)
(
MIN.
)
1'
-0"
2"
(
TYP.
)
CHAMFER
"
2 "
3" Min.
2 "
BACKWALL
ELEVATION
NOTE 1:
EXTEND EXTERIOR h(E) BARS
FULL LENGTH OF ABUTMENT IF
REQUIRED FOR TEMPERATURE
AND SHRINKAGE
BACKWALL
BEAM SEAT
SLOPE BEAM SEAT
" BETWEEN
VARIES
BEARINGS.
LOW BEAM
" CHAMFER (TYP.)
SEAT
ABUTMENT/SEAT
TYPICAL SECTION
FIGURE 10.6.1
ILLINOIS TOLLWAY
SHOULDER
LINE
~ ROADWAY
1:4 (PREFERRED)
1:2.5 (MAXIMUM)
SHOULDER
LINE
1:4 (PREFERRED)
1:2.5 (MAXIMUM)
V:H
V:H
EMBANKMENT
EMBANKMENT
SLOPE
SLOPE
N
IO
T
I
NS
A
TR
E
OP
L
S
AREA IN FRONT OF
TR
AN
SI
SL
TI
OP
ON
E
ABUTMENT IS EITHER
CONCRETE PAVED
SLOPEWALL, RIP RAP OR
BITUMINOUS COATED
AGGREGATE SLOPEWALL
EMBANKMENT CONES
MARCH, 2016
FIGURE 10.7.5
ILLINOIS TOLLWAY
General
Piers shall be designed in accordance with the latest AASHTO Specifications and
Section 3.9 of the latest IDOT Bridge Manual, except as herein modified.
Multi-column pier shapes, as shown in Figure 11.3.1.1 (Except Single Column Hammerhead) and Figure 11.3.1.2, are the most commonly used pier types for grade separation
structures. The use of square or round columns is appropriate; however the standard
application of square columns is preferred whenever practical to provide system
consistency. A typical 3 offset between the face of column and the face of the pier cap,
and a 6 offset between the face of column and the face of the crash wall is desirable.
Piers under deck joints, in medians or within 12 feet of the outer edge of shoulder shall
have all exposed surface areas treated with a concrete sealer. For cases involving
structure widening, the existing concrete substructure shall be power washed and both
the new and existing surfaces treated with a concrete sealer.
11.2
Design
The friction force caused by an expansion bearing sliding on its bearing plates or
deforming on the supporting substructure element shall be included in the design of the
structure. These forces are determined by multiplying the coefficient of friction by the
total dead load reactions on the bearing. Coefficients of 0.30 for steel on steel and 0.10
for Teflon on Teflon shall be used.
For elastomeric bearings, the force required to deform the elastomeric pad shall not be
less than 25 pounds per square inch of bearing area for Type I bearings or 0.04 times
the dead load reaction for Types II and III bearings.
The fixed pier(s) design shall include the net frictional force from expansion bearings
on adjacent piers.
An allowance for additional eccentricity shall be considered in all pier designs. For
structures with total lengths of greater than 400 feet, each pier shall be designed with an
allowance for additional eccentricity of 3 inches. An allowance for additional eccentricity
shall not reduce the required design capacity.
The bearing seat shall meet the minimum support length requirements specified in the
AASHTO Seismic Design Section for Seismic Performance Zone 1 (LRFD) or Category
A (LFD).
11.3
Pier Types
11-1
Illinois Tollway
In general, existing piers shall be widened in-kind, especially those which can be viewed
by the traveling public, except Article 11.6 shall be followed. At locations not exposed to
the traveling public, such as structures over railroads or streams, other designs may be
considered. The final selection shall be based on serviceability and economy.
Pier widenings shall be designed to carry all forces which pass through the bearings.
All pier widenings shall be tied to the existing cap, column and footing areas with dowel
bars drilled into the existing concrete. Minimum depth embedment of dowels in existing
concrete shall be 12 inches for vertical bars and the development length for horizontal
bars. Maximum spacing shall be 18 inches.
Foundations for widened piers shall be the same type as the existing structure. Existing
soil borings and new soil borings (if required) shall also be considered. Construction
and installation procedures shall be considered when placing new foundations adjacent
to existing so as not to reduce the load carrying capacity or cause settlement of existing
foundations.
Special attention shall be given to the widening of existing piers that consist of 3-foot
March 2016
11-2
Illinois Tollway
An integral pier cap is a pier cap that is incorporated either entirely or largely within the
depth of the superstructure. The cap can be constructed of either concrete or steel.
For steel superstructures, the longitudinal beams are typically run continuous through
the cap. When the superstructure is constructed of prestressed concrete, a pier
segment may run continuous through the cap or the ends of beams may be cast into the
integral cap. When the beams are not continuous through the cap, a positive
connection is made between the cap and the beams with post-tensioning.
Integral pier caps may be utilized to: Improve vertical clearances, simplify framing,
eliminate bearings, improve aesthetics and reduce the mass of the structure which
reduces the seismic design forces.
The beams shall be supported on falsework while the caps are constructed. The top
surface of the cap is intentionally roughened. Stirrups are extended from the top surface
of the cap to provide a positive connection to the deck. After tensioning of cap tendons,
the falsework supporting the beams and cap are removed. The deck concrete is then
placed according to the deck pouring sequence shown in the plans.
A post-tensioning tendon shall be placed in each corner of the cap along with one or
more draped tendons. Strand tendons shall be used rather than bars for simplicity of
construction and to allow more flexibility in the tendon profile.
After placement and hardening of the cap concrete but before the deck is cast, tendons
shall be tensioned from one end according to a specified sequence. Tendons are then
grouted to provide corrosion protection and to provide bond between the strands and
the structure.
11.6
March 2016
11-3
Illinois Tollway
11.7
Pier Columns
If pier columns are over 20 feet high, a bonded construction joint or joints shall be
detailed at approximately mid-height or third points.
11.8
Foundations
March 2016
11-4
Illinois Tollway
A detail scaled drawing of the reinforcement and the holes drilled for the bearing anchor
rods at expansion bearings and anchor bolts at fixed piers shall be provided in the
plans, as shown in Figure 11.9.1. The detail drawing shall include all reinforcement that
may interfere with the drilling operation, the reinforcement spacing and the clearances
of the reinforcement to the edge of the cap and the future holes.
March 2016
11-5
Illinois Tollway
19' TO 32'
4'
-6"
3'-6"
32' TO 46'
4'
-6"
3'-6"
46' TO 62'
4'
-6"
3'-6"
FIGURE 11.3.1.1
ILLINOIS TOLLWAY
62' TO 76'
4'
-6"
MARCH, 2016
3'-6"
76' TO 95'
4'
-6"
3'-6"
ILLINOIS TOLLWAY
~ PIER
3" (TYP.)
6"
2'-6"
6"
MEDIAN SHOULDER
MIN.
LANE 1
TOP TO MATCH
5'
-0" MIN.
3'-6" MIN.
L.
G.
P.
4'
-0" MIN.
2"
SLOPE OF P.G.L.
END ELEVATION
MARCH, 2016
FIGURE 11.3.1.3
ILLINOIS TOLLWAY
~ PIER
6"
6 MAX.
:
1
END ELEVATION
* AS DETERMINED BY BARRIER WARRANT ANALYSIS
MARCH, 2016
FIGURE 11.3.1.4
ILLINOIS TOLLWAY
RESERVED
MARCH, 2016
FIGURE 11.3.1.5
ILLINOIS TOLLWAY
~ PIER
2'-6"
MIN.
1'-3"
3'-0" MINIMUM
5'-0" DESIRABLE
2"
3"
3'-0"
MIN.
5'
-0" MIN.
EDGE OF PAVEMENT
4'
-0" MIN.
2.0%
END ELEVATION
MARCH, 2016
FIGURE 11.3.1.6
ILLINOIS TOLLWAY
~ PIER
TO ABUT.
3'-0"
MIN.
10'-0" MIN.
EDGE OF
PAVEMENT
5'-0" MIN.
3'-6"
1:
2
MIN.
2%
6
:
1
4'
-0" MIN.
1
:
6
5'
-0" MIN.
2"
SIDEWALK
2% MAX
.
END ELEVATION
FIGURE 11.3.1.7
ILLINOIS TOLLWAY
~ PIER
2'-6"
MIN.
5'
-0" MIN.
2"
3'-6"
EMBEDMENT
2'
-6"
MINIMUM
4'
-0" MIN.
MIN.
END ELEVATION
FIGURE 11.3.1.8
ILLINOIS TOLLWAY
MARCH, 2016
END VI
EW
STREAM
2'
-6" M I
N.
MIN.
1'
-3" R
ELEVATI
ON
MIN.
FIGURE 11.3.2.1
2'
-6"
3" MIN.
ONLY WHEN
SEATS.
HYDROLOGICAL
DESIGN ENGINEER
ADDITIONAL WIDTH IS
* USE
CAP SECTI
ON
* OPTI
ONAL PI
ER
3" MIN.
VERIFIED BY
ELEVATION TO BE
4'-0"
CROSSI
NG FI
XED OR EXPANSI
ON PI
ER
BED
LINE
STREAM
FLOW
TOP PLAN
3'-0" MIN.
ILLINOIS TOLLWAY
~ PIER
3"
2-6"
3"
MIN.
~ TRACK
1'-3"
END ELEVATION
3' MIN.
(
V:
H)
4' MIN.
1:
2
3'-6"
RAILROAD OWNER
VERIFY WITH
6"
T/RAIL
*
*
CLEARANCE TABLE
X
X > 25'-0"
0"
6'-0"
X < 12'-0"
12'-0"
FIGURE 11.3.3.1
ILLINOIS TOLLWAY
6"
6"
6"
6"
PLAN
EXISTING
COLUMN
NOTE:
CROSS HATCHED AREAS
INDICATE CONCRETE REMOVAL.
ELEVATION
MARCH, 2016
FIGURE 11.4.1
ILLINOIS TOLLWAY
WALL WIDTH
1" SAW CUT (TYP.)
6"
6"
6"
6"
PLAN
NOTE:
CROSS HATCHED AREAS
INDICATE CONCRETE REMOVAL.
ELEVATION
FIGURE 11.4.2
ILLINOIS TOLLWAY
General
The design and detailing of steel superstructures shall be in accordance with the
appropriate AASHTO Specifications and the provisions of Section 3.3 of the IDOT
Bridge Manual except as herein modified.
12.2
Design
Structural steel shall be AASHTO M270 Grade 50 (ASTM A709) unless otherwise
noted. Grade 70 steel may be used in areas of high stress, if this will result in a more
economical solution.
All horizontally curved structures not considered essentially straight and/or structures
with skews greater than 45 deg. shall be designed and/or checked using threedimensional analysis. If either type of structure is to be constructed in stages, the
beams in each stage shall be checked using three-dimensional analysis for stability,
and bending, shear and torsion stresses. For these conditions, the Designer shall
consider using a closer spacing (15- 20) for cross frames or diaphragms and the use of
bottom lateral bracing.
Generally, all shop connections shall be welded. All field connections shall be made
with -inch diameter zinc-coated, high-strength bolts per AASHTO M164 (ASTM A325),
and shall be designed as friction type connections.
In order to minimize fillet heights on steel structures, the beam or plate girder slopes
shall be changed at the splices to conform to the general configuration of the bottom of
the formed deck slab.
Plate girders shall be cambered for dead load deflection and vertical curve geometry
except where the resulting camber would be less than one inch.
Welded plate girder flange transitions shall be limited to twice the thickness of the
thinner plate.
Top of beam or girder web elevations at the center line of each splice and/or bearing
shall be shown on the framing plan.
Fracture critical details shall be identified in the plans.
Load carrying components including tension flanges, webs and splice plates shall
be designated NTR on the plans and shall conform to the AASHTO Impact Testing
Requirement, Zone 2.
March 2016
12-1
Illinois Tollway
Intermediate vertical stiffeners shall be a minimum of 7/16 inch thick and shall be
welded to the web with a -inch minimum continuous fillet weld. The distance between
the end of the stiffeners and the near edge of the web-to-tension-flange fillet weld shall
be no more than six times or less than four times the web thickness.
For plate girders with web depths equal to or smaller than 54 inches, it is preferable not
to utilize intermediate stiffeners. For plate girders with web depths larger than 54
inches, the web thickness may be increased to a maximum inch to eliminate or limit
the vertical stiffeners to only one or two locations per span beyond those provided for
cross frame attachments. The minimum web thickness of a plate girder shall be 7/16
inch.
12.4
Bearing Stiffeners
Bearing stiffeners need not be welded to either flange of rolled beams or plate girders,
except as hereafter indicated. They shall be milled on the bearing end and have a tight
fit at the other end.
On all skewed plate girders, or rolled beams with skews 45 deg. and larger and on all
horizontally curved beams and plate girders, the bearing stiffeners shall be welded to
both flanges where these stiffeners are used as connecting plates for cross frames or
diaphragms. Welding to the flanges shall be done with fillet welds on both sides of
stiffeners. The length of the fillet weld at the mill to bear end shall be the width of the
stiffener minus 1 inch ( inch at each end). The length of the fillet weld at the other end
shall be the full width of stiffener. The bearing stiffener plates at the junction of the
flanges and the web shall be clipped 1 inch horizontally and a minimum of 1 inch
vertically for rolled beams, or four times the web thickness plus the size of web-to-flange
fillet weld for plate girders.
12.5
Superstructure Diaphragms
March 2016
12-2
Illinois Tollway
To provide ready information for any future analysis of a structure and to provide the
reviewing agencies with a basis for checking of the design, all detailed bridge plans
shall include, as a part of said plans, a Table of Moments and Shears. Refer to the
latest IDOT Bridge Manual Section 3.1.12 for suggested table layouts.
12.7
Painting of steel beams shall be performed in accordance with the applicable IDOT
GBSPs and All Bridge Designers (ABD) Memorandum 10.1. Desirable finish color is
Gray, Munsell No. 5B 7/1. If existing bridge structure contains finish colors that are
different than gray, then the Designer shall match this color as closely as possible. A
typical color on the Illinois Tollway system other than gray is interstate green with the
Munsell No. 7.5G 4/8. Shop Painting is used exclusively for new structural steel, field
painting of intermediate and finish coats is not allowed.
March 2016
12-3
Illinois Tollway
Weathering Steel
Weathering steel may be considered for Illinois Tollway structures over railroads and
waterways. Illinois Tollway approval is required during preliminary stages of design.
March 2016
12-4
Illinois Tollway
General
The design and detailing of PPC I-Beams and Bulb-T beams shall be in accordance
with the latest AASHTO LRFD Bridge Design Specification, Section 3.4 of the latest
IDOT Bridge Manual and IDOT All Bridge Designers Memorandum 15.2 except as
herein modified.
13.2
Design
Twenty-two PPC I-Beam and Bulb-T sections may be used on the Illinois Tollway
system. First is a standard 28-inch Illinois Tollway section. The next four are standard
36-inch, 42-inch, 48-inch and 54-inch IDOT I-Beams. The next two sections are 63-inch
and 72-inch IDOT Bulb-T beams. The next four sections are the 36-inch, 45-inch, 54inch and 72-inch Illinois Tollway Bulb-T beams. Refer to Illinois Tollway Base Sheets MBRG-509-520 for details. Finally, the eleven new IDOT IL-Beam shapes may also be
used on Illinois Tollway projects.
The prestressing strands used in PPC beam designs shall be either 0.5 or 0.6
diameter, low relaxation strands with areas of 0.153 or 0.217 square inches,
respectively.
In the design of continuous composite PPC structures, the superimposed dead load,
live load and impact stresses shall be computed on the basis of full continuity at the
interior supports.
Strand debonding may be considered to reduce the stresses developed at beam ends.
The locations of debonded strands shall adhere to the restrictions listed in IDOT All
Bridge Designers Memo 15.2, Manual for Fabrication of Precast Prestressed Products
2015 and Article 5.11.4.3 of the latest Interims to the AASHTO LRFD Bridge Design
Specifications.
The final compressive stress in the bottom flange of the PPC beams at piers for
continuous designs shall be calculated at the strand load transfer point (assumed to be
at the strand transfer length from the end of the beam) and the edge of bearing pad or
diaphragm.
Vertical stirrups are required at the ends of all prestressed beams to resist 6% of the
total initial prestressing force at 18 ksi located within a distance of of the beam depth
from the end of the beam. For 63-inch and 72-inch beams, the minimum stirrup
reinforcement shall be 5 pairs of #6 bars.
13.2.1 IDOT and 28 Illinois Tollway Beams
The 28-day concrete compressive strength for these prestressed beams shall be 6,000
psi and may be increased to a maximum of 7,000 psi. The higher strength, above 6,000
psi, shall be used only when economical. Concrete strengths at strand release shall be
March 2016
13-1
Illinois Tollway
Details
At all piers supporting continuous spans for beams other than IL-Beams, a minimum of
two #8 bars for I-Beams and three #8 bars for Bulb-T beams shall be added to the
bottom flange, projecting beyond the beam end in accordance with the details shown in
March 2016
13-2
Illinois Tollway
To provide ready information for any future analysis of a structure and to provide the
reviewing agencies with a basis for checking of the design, all detailed bridge plans
shall include a Table of Moments and Shears. See Section 3.1.12 of latest IDOT Bridge
Manual for an example of a moment and shear table for PPC I-Beams.
13.5
Superstructure Diaphragms
March 2016
13-3
Illinois Tollway
All handling, storage and transportation of PPC Beams shall be in accordance with the
latest version of Manual for Fabrication of Precast Prestressed Concrete Products,
Section 3.6 except as herein modified. All designers shall include these provisions in
the contract documents.
IDOT requires that all PPC I-Beams and Bulb T-Beams on continuous structures shall
be a minimum of 45 days old before they are permitted to be shipped to the job site.
This waiting period combined with a typical minimum timeframe of 15 days from delivery
to casting of the deck results in a period of 60 days minimum between casting of the
beam and placing of the concrete deck. In addition, G6 hook bars are provided at the
beam ends made continuous over piers using a cast-in-place concrete diaphragm.
These requirements are intended to mitigate the loss of contact between the bottom
flange of the beams and the diaphragm over the pier as well as other design and
construction problems caused by beam creep, shrinkage, shortening and camber.
The Illinois Tollway allows the Contractor to ship beams to the site on or after the 5th
calendar day after the beam is cast if the beam has attained the specified strength.
For I-beams and T-beams on multi-span, continuous structures (beams with G6 bars),
the casting of the deck and continuity diaphragm shall not occur prior to 60 calendar
days after casting of the youngest beam. At structures with beams exceeding 99 feet in
length and supported on bearing assemblies, the beams may be placed on bearings
upon delivery, but the bearings shall be reset after the 60 th calendar day after beam
casting. Repositioning of the beams on the bearings or resetting of bearings after the
60th calendar day shall be at the Contractors expense at no additional cost to the Illinois
Tollway.
13.7
Spliced Girders
13.7.1 Introduction
A Spliced Girder is precast prestressed or post-tensioned concrete, fabricated in several
March 2016
13-4
Illinois Tollway
March 2016
13-5
Illinois Tollway
March 2016
13-6
Illinois Tollway
36 Deep
Beam
45 Deep
Beam
54 Deep
Beam
72 Deep
Beam
4.5
104
123
139
169
5.0
101
119
135
165
5.5
98
117
132
162
6.0
96
114
129
158
6.5
94
111
126
155
7.0
93
110
124
152
7.5
91
107
121
148
8.0
87
103
119
146
8.5
85
101
116
143
9.0
84
99
114
141
The maximum spans provided in the table above were calculated based on the
following design parameters:
1. Live Loads consist of Design Truck IL-120, Design Truck HL-93, Design Lane and Design
Tandem loading, following requirements of Article 1.2 of this Manual.
2. Dead loads consist of self-weight of the Bulb-T beams, 2 thick fillet, 8 thick concrete deck,
50-psf future wearing surface and 200 plf of superimposed dead load to account for the 42
F-Shape concrete parapet shared by 3 beams.
3. Compressive strengths of 4,000 psi and 8,000 psi used for the bridge deck and BT-beam,
respectively. The BT-Beam concrete strength was assumed to be 6,800 psi at the release.
4. The strands have a 0.60-inch diameter and ultimate strength of 270 ksi. The maximum
numbers of straight and draped strands are 36, 40, 42 and 48 for the 36, 45, 54 and 72
deep BT-Beams, respectively.
5. For two-equal span bridges, the maximum span lengths presented in the table above may
increase by approximately 5% to 10% due to continuity at the center support.
6. Debonded strands meeting the requirements of AASHTO and IDOT have been used.
March 2016
Figure 13.2.1
Illinois Tollway
General
Bearings shall be designed and detailed in accordance with Section 3.7 of the latest
IDOT Bridge Manual except as amended herein. Only High Load Multi-Rotational
(HLMR), elastomeric, low profile steel rocker bearings (fixed) and rocker plates are
acceptable types. Sliding plate bearings shall not be used.
Elastomeric bearings are generally used with precast prestressed concrete (PPC) beam
and steel beam or girder spans having moderate load and movement requirements.
Elastomeric bearing assemblies are divided into three types according to the expansion
lengths which they will accommodate.
Low profile rocker bearings shall be used as fixed bearings to support PPC beams at
fixed piers or fixed abutments with joints. See IDOT Base Sheets PI-2F and PI-2FB for
details.
Only fabric or unreinforced elastomeric pads shall be used to support PPC beams at
integral abutments.
Low profile rocker bearings shall be used as fixed bearings in combination with
elastomeric types I, II and III expansion bearings to support steel spans. See Figure
3.7.1.2-1 in the latest IDOT Bridge Manual for details.
Rocker plates shall be used to support steel beams or girders at integral abutments.
See Figure 3.7.1.2-2 in the latest IDOT Bridge Manual for details.
Only HLMR bearings shall be used to support concrete (segmental or CIP box girders)
or steel structures on curved alignment. They may also be used for concrete or steel
structures on tangent alignments with high dead load reactions and skew angles and
expansion lengths greater than 40 and 450 ft., respectively.
On steel bridge widening projects where the new deck is structurally tied to the existing
and the extended substructure is discontinuous, the bearings for the new beams or
girders resting on the discontinuous portion of the substructure shall be of the HLMR
bearing type.
A detail showing the centerline of the bearing over the centerline on the substructure
unit and the orientation of the bearing for erection temperatures above and below 50
degrees Fahrenheit shall be provided on the plans.
14.2
Design
Elastomeric and low profile steel rocker bearings including anchor bolts and pintels shall
be designed and detailed in accordance with Section 3.7 of the latest IDOT Bridge
Manual. HLMR bearings shall be designed and detailed by the Designer in accordance
with Section 3.7.5 of the latest IDOT Bridge Manual. Inverted Pot Bearings shall not be
used.
March 2016
14-1
Illinois Tollway
March 2016
14-2
Illinois Tollway
March 2016
14-3
Illinois Tollway
March 2016
Illinois Tollway
Performance Mix Concrete, fc=4,000 psi min. shall be used for bridge decks and
diaphragms.
Cross Road Bridge deck thickness, deck geometry and material property will depend on
the Inter-Governmental Agreement (IGA). The above specified conditions shall be used
if ownership of the bridge deck is under Illinois Tollways jurisdiction.
15.2
For widenings, partial replacements or repairs of existing decks, the deck thickness
shall match the existing deck thickness. The top reinforcement bars in the new deck
portion shall be placed at the same level as the existing deck bars. The proposed deck
widenings shall be designed using the design specifications used for the existing deck
in accordance with Section 3.2 of the latest IDOT Bridge Manual. Full bar lap splice
shall be provided between the old and new reinforcement bars at the longitudinal
construction joint. When the length of the existing reinforcement projecting beyond the
construction joint is insufficient to develop a full lap splice, the mechanical splice detail
shown in Figure 15.2.1 shall be included in the plans.
When overlaying an existing bridge deck, scuppers shall be adjusted to match the new
top of overlay elevations.
March 2016
15-1
Illinois Tollway
Cross Slopes
The cross slopes of new, replacement and widened decks shall match that of the
approach roadway and/or shoulders. A Design Deviation is required for cross slopes not
matching the approach roadway and shoulders.
15.3.1.2
Overlays
For bridges on tangent sections, the cross slopes of the proposed bridge deck overlay,
shall match the existing cross slopes; however, the capacity of the existing beams or
girders shall be checked. For bridges carrying Illinois Tollway traffic that do not have
adequate capacity to carry the IL-120 Design Truck at Inventory Level and for other
bridges that do not have adequate capacity to carry the AASHTO Design Loading at
Operating Level, the following criteria shall be followed:
For longitudinal grades of 0.3% or less, the minimum cross slope required shall
be 1.5% for all lanes.
For longitudinal grades between 0.3% and 1%; a minimum cross slope of 1% for
each lane immediately adjacent to the crown line is acceptable, although not
desirable. A minimum cross slope of 1.5% is still required for all other lanes.
Maximum cross slope for traveled lanes shall be 2.5% and for shoulders shall be
4%.
These criteria apply only to bridge deck overlays and their purpose is to minimize the
overlay thickness, while providing a reasonably smooth surface with adequate ability to
drain for the safety as well as the comfort of the traveling public. The transition to these
cross slopes shall be completed on the roadway, transition slab and roadway shoulder,
not on the bridge deck or approach slab.
March 2016
15-2
Illinois Tollway
When a superelevated horizontal curve is located within the limits of a bridge and its
approach slabs, the bridge deck and approaches shall be sloped at a constant rate. The
approach slab and bridge deck shall be planar. The transition in the approach shoulder
break shall occur in the transition slab and roadway shoulders at no greater than a 0.5%
relative gradient.
15.3.2.2
For bridges on superelevated sections, the minimum cross slope required for deck
sections shall equal the original design superelevation rate unless the deck is to be
replaced.
The procedure for Preparing Profile Worksheets for Bridge Deck Overlays and
approach pavement profile transitions is detailed in Article 18.2 of this Manual. See
Article 15.3.1.2 for additional requirements for overlays.
15.4
Reinforcement Bars
The top and bottom longitudinal and transverse bars shall not be lapped at the same
locations in the deck, except at staged construction joints. Transverse bars shall be
lapped at the locations shown in Figure 15.4.1.
On PPC structures made continuous for live load and superimposed dead loads, the
additional longitudinal reinforcement bars over the piers shall be designed and checked
for fatigue in accordance with the latest AASHTO Specifications and IDOT Bridge
Manual. These are the only deck reinforcement bars that need to be checked for
fatigue. The additional longitudinal reinforcement shall be placed in the top and bottom
of the deck between the #5 bars over the piers for the full width of the superstructure
including portions of the deck under parapets, sidewalks, raised medians and median
barriers.
Two minimum bar lengths are required for these additional bars; the shorter bars shall
be 80% or less of the longer bar. This staggering of bars will help minimize transverse
cracking at bar terminations.
On bridge replacement projects for mainline bridges and flyover ramps under Illinois
Tollway jurisdiction that provide direct access to the Illinois Tollway, the use of stainless
steel reinforcement bars shall be considered. Specifications for stainless steel
reinforcement are available from the Illinois Tollway upon request. Stainless steel
reinforcement bars are limited in use to bridge deck, parapet walls and beam end
diaphragms. The rest of the structure shall use epoxy coated rebar. Stainless steel
reinforcement bars shall not be considered for the cross road bridge structures.
March 2016
15-3
Illinois Tollway
The 11 spacing of the #5 front face vertical reinforcement bars shall be reduced
to 7.
The Designer shall also verify the bridge slab and approach slab capacity at the junction
with the parapet and barrier wall.
Although these design details are governed by end impact, at parapet ends and joints,
these revisions apply to the full length of the 42 parapet and barrier wall. See Figure
15.5.1.3.
1/8 aluminum parapet joints required at piers, abutments and other locations specified
in the latest edition of the IDOT Bridge Manual shall be detailed according to Figure
15.5.1.4.
March 2016
15-4
Illinois Tollway
Longitudinal Joints
When the distance between the fascia girders exceeds 90 feet, the deck shall be split
with an open joint. The joint may be located in parapet sections or in a raised median.
Joints in a raised median curb shall be sealed using a 1-3/4 inch preformed joint seal.
The open joint is not required if the deck is staged and the total width of the staged
pours is less than or equal to 120 feet.
The Illinois Tollway prefers not to utilize open or sealed longitudinal joints unless they
are located along the center line of the main line between the median barriers on each
side of the joint. Details of a sealed joint are shown on Figure 15.6.1.
Longitudinal construction joints between the edges of shoulders shall not be used
unless they fall on a lane line and are located at a distance greater than of the beam
spacing from the centerline of any beam (within the middle half of the beam spacing).
15.7
The Designer shall identify the location and size of all embedded conduits, expansion
fittings and junction boxes on the structural drawings and reference the roadway
electrical drawings for details.
Shoulder and median mounted light pole details for the 42 F-Shape barrier are shown
in Figures 15.7.1 through 15.7.7.
15.8
Slipform Parapet
Slipforming may be used to construct the parapets shown in plans. Slipforming shall be
done in accordance with the latest IDOT Guide Bridge Special Provision #61,
Standard Base Sheet SFP 34, 42 and All Bridge Designers (ABD) Memoranda 12.4
for slipforming of Parapet Option. If one of the conditions from the ABD Memo 12.4
which would exclude slipforming is met, a note shall be added to the plans indicating
March 2016
15-5
Illinois Tollway
A deck pouring sequence shall be provided in the Contract plans for all new and
existing steel superstructures on curved alignment and those with continuous or simple
span lengths of 150 feet or greater. The same shall be provided for tangent steel
superstructures with a skew angle greater than 40 deg., regardless of the type of span
or length. In addition, the concrete for the bridge deck shall be placed parallel to the
skew when it is greater than 40 deg.
Special care shall be taken when construction staging reduces the width of the pour in
relation to span length and/or the number of beams or girders to three or less, in the
initial stage, the superstructure framing shall be checked for stability and out of plane
displacements and rotation.
Required pouring sequences shall consider the impacts to the project schedule and the
design project schedule shall include the time required to comply with the required
pouring sequences shown on the plans. Wherever possible the number of required
pours shall be minimized to allow the Contractor to complete deck pours in a minimum
time and avoid waiting 72 hours between pours. The numbering of the pouring
sequence sections shall be duplicated whenever possible rather than using separate
numbers for each segment. For example, all positive moment pours could be one (1)
and all negative pours could be two (2). Reasonable production rates in the bridge area
for deck pours shall be considered.
See Article 7.1.3 for the note to be included in the plans.
15.10
Closure Pour
On stage constructed bridges where the differential deflection between adjacent stages
is 2 or greater, and it is not feasible or economical to use a deeper or stiffer beam or
girder section, a closure pour shall be considered. Closure pours will be considered by
the Illinois Tollway on a case-by-case basis.
March 2016
15-6
Illinois Tollway
MECHANICAL SPLICERS
EXISTING BARS
MARCH, 2016
FIGURE 15.2.1
ILLINOIS TOLLWAY
MARCH, 2016
~ BRIDGE
1'-6''
"
NOTES:
3"
9"
5"
"
2'
-8"
1 "
7" 3" 1
9 "
FIGURE 15.
5.
1.
1
ILLINOIS TOLLWAY
4''
"
(MANDATORY)
1
1 " MIN.
1"
"
DRIP NOTCH
(FULL LENGTH)
NOTES:
1. PPC BEAM SHOWN,
STEEL BEAM SIMILAR
2. ALL FORM MATERIAL
SHALL BE REMOVED
FROM OPEN JOINT
~ BRIDGE
VARIES 9" MIN.2
VARIES 3"' MAX.2
5"
1'-6''
"
2'
-8"
"
VARIES 2
1 3" 7"
2'-10'' MAX.
3"
1 "
7"
2'-8'' MIN.
1"
4''
1 "
DIFFERENCE
MIN.
ELEVATION
1 THIS DIMENSION SHALL
INCREASE BY THE
"
THICKNESS OF THE
PROPOSED OVERLAY
3"
1'-6''
5"
HORIZONTAL TO
2'-8'' VERTICAL RATIO.
"
3"
1 "
7"
1 3" 7"
2'
-8"
2'
-8"
"
9"
VARIES
AT CONSTANT 3"
~ BRIDGE
ELEVATION
4''
"
1 "
1"
MIN.
DIFFERENCE
MARCH, 2016
FIGURE 15.5.1.2
ILLINOIS TOLLWAY
1" CL.
(MIN.)
F-SHAPE
PARAPET
#5 e1(E) (TYP.)
#5 d1(E) AT 7"
1 "
3'
-6"
#5 d(E) AT 7"
#8 e(E)
PARAPET REINFORCEMENT
MARCH, 2016
FIGURE 15.5.1.3
ILLINOIS TOLLWAY
2'-0"
10"
2" 8"
3"
NOTE:
COST OF ANCHOR BOLTS IS INCLUDED IN
~ LIGHT
POLE
CL.
1 "
1'
-3"
1"
15"} BOLT CIRCLE
10 "
2'
-6"
CL.
1'
-3"
2'
-3"
1'-4"
2'
-0"
PLAN
1'
-0"
& WASHER
GALVANIZED
GALVANIZED
7"
THREAD
*d(E)
*e(E)
4'
-5"
LEVELING NUT
& WASHER
2'
-0"
3'
-0"
1'-3"
BAR e (E)
BAR d (E)
MARCH, 2016
FIGURE 15.7.1
ILLINOIS TOLLWAY
1'-2"
(BY OTHERS)
VIBRATION WASHER (BY OTHERS)
3"
10"
" VIBRATION ISOLATION PAD (BY OTHERS)
7"
2"
STAINLESS
STEEL MESH
2
7-#6 e(
E) BARS
3-#6
d(E) BARS
8 "
2"
10"
SECTION A-A
1 SEE FIGURE 15.7.1 FOR DETAILS OF d(E) AND e(E) BARS
2
STAINLESS STEEL STANDARD GRADE WIRE CLOTH TYPE 304, 4 x 4 MESH , 0.047'' WIRE DIAMETER.
MARCH, 2016
FIGURE 15.7.2
ILLINOIS TOLLWAY
3'-0"
MEDIAN BARRIER
3" 5"
TOE OF NORTHBOUND
9"
CL. (
TYP.
)
9"
1 "
1 "
3"
MEDIAN BARRIER
TOE OF SOUTHBOUND
5"
1'
-3"
2'
-6"
10 "
1'
-3"
(TYP.)
A
8"
10"
1 "
3"
"
1. COST OF ANCHOR BOLTS IS
d(E)
CONCRETE SUPERSTRUCTURE
e(E)
1"
~ TOLL HIGHWAY
2. SEE FIGURES 15.7.5 AND
15.7.6 FOR SECTION A. SEE
TOP PLAN
MARCH, 2016
FIGURE 15.7.3
ILLINOIS TOLLWAY
8"
BOTT. OF SLAB
BOTT. OF SLAB
TOP &
1'
-3"
1 "
2'
-9 "
.)
"
P
2
Y
T
.(
L
C
TOP &
*(E) BARS
1-#5 b
1'
-3"
1 "
5-#6 a (
E) BARS
(
BY OTHERS)
11"
~ LIGHT POLE
7"
1'-6"
LAP WITH #5 a (
E) TRANSVERSE BARS
1'-6"
MEDIAN BARRIER
TOE OF NORTHBOUND
MEDIAN BARRIER
TOE OF SOUTHBOUND
(
TYP.
)
*(E) BARS
2-#5x2-0" b
3'-0"
NOTE:
SEE FIGURES 15.7.5
AND 15.7.6 FOR
SECTION A-A AND
8"
1"
VIEW B-B.
~ TOLL HIGHWAY
BOTTOM PLAN
(SHOWING ADDITIONAL REINF. IN DECK AT LIGHT POLE LOCATIONS)
MARCH, 2016
FIGURE 15.7.4
ILLINOIS TOLLWAY
STEEL MESH
2"
STAINLESS
7"
MARCH, 2016
(BY OTHERS)
1
SECTION A-A
ILLINOIS TOLLWAY
MARCH, 2016
3'-0"
1'-6"
1'-6"
1 SEE FIGURE 15.7.1 FOR DETAILS
9" 3"
5"
3" 9"
5"
#5e1(E)
#5d(E) @ 7"
#5d2 (E)
5"
1"
#8e(E)
#5e1 (E)
3"
#5d1(E) @ 7"
7" 3"
5 "
1 "
7"
FIGURE 15.
7.
6
2'
-8"
2'
-8"
#5e1(E)
(TYP.)
1 7-#6e2*(
E) BARS
#5b (E)
8"
4"
1"
ILLINOIS TOLLWAY
3"
SECTION A-A
NOTE:
(E) BARS SHALL BE (S) BARS
FOR BRIDGE DECKS USING
STAINLESS STEEL BARS.
1"
1"
1
MARCH, 2016
2'-9"
2'
-8"
2'
-8"
2'
-9 "
1 "
5"
10"
FIGURE 15.
7.
7
SOUTHBOUND GUTTER
#5d 1
(E) @ 7" O.C.
ELEVATION, TOE OF
3"
BARRIER
VIEW B-B
(SHOWING DIMENSIONS AND REINFORCING)
1
ILLINOIS TOLLWAY
Deck Drains
When floor drains are required, they shall be uniformly spaced along the gutter line on
one or both sides of the bridge deck as indicated in the drainage study. In no case shall
the discharge from floor drains be collected in a closed drainage system and piped
down and/or off the bridge. The free fall method of discharge shall be permitted except
over areas noted herein.
Floor drains may be angled if required to clear the beam or girder flange. Preference
shall be given first to the use of 6 inch diameter reinforced fiberglass pipe or aluminum
tube. If insufficient space exists between face-of-curb and the girder for a 6 inch
diameter drain, consideration shall be given to the use of the 4 x 12 tube. Reinforced
fiberglass pipe shall meet the requirements of Article 16.3.2. Aluminum shall be either
an extrusion or welded plates meeting the requirements of ASTM B221, Alloy 6061-T6
or ASTM B209, Alloy 6061-T6.
Floor drains shall be omitted from sections of the decks where the discharge would fall
on underlying roadways, bikeways, walkways, railroads, aggregate slope paving or
unprotected earthen embankments, and other developed or highly erodible areas.
Where free fall is not permitted scuppers and a closed drainage system as described
below is used. Floor drains shall be located a minimum of 1/2 of the drop height from
the face of any abutment or pier. The drop height is defined as the vertical distance
between the bottom of the drain pipe and the top of the surface below. Drains shall be
located a minimum of 4 clear of all diaphragms and on the upstream side of bridge
deck expansion joints. Drain pipes shall extend a minimum of 6 below the bottom of
adjacent superstructure members.
16.2
Drainage Scuppers
The IDOT DS11 or DS12 Drainage Scuppers may be used. Drainage from scuppers
may be collected in a closed drainage system and piped off the bridge or allowed to free
fall to the ground except in the areas noted herein.
Scupper frames and grates shall be grey cast iron meeting the requirements of
AASHTO M105, Class 35B. Stainless steel hold down bolts as specified in the Standard
Specifications Article 1006.29(d) shall be used to secure the grates to the frames.
Structural steel weldments of equal sections and of the same configuration may be used
in lieu of the grey cast iron frame. Fillet or full penetration welds shall be used for the
weldments. Structural steel weldments shall not be used in lieu of the cast iron grates.
Structural steel shall meet the requirements of AASHTO M270, Grade 50. Structural
March 2016
16-1
Illinois Tollway
Drain Pipe
Wherever freefall discharge is not feasible, the drainage shall be collected and piped to
the ground or lower roadway. Drain pipes shall not be placed on the traffic face of crash
walls. Scuppers shall be located directly above downspouts attached to the
substructure. Midspan locations that would result in complex, lengthy drain piping shall
be avoided wherever possible. Where horizontal (collection) piping is required,
horizontal runs shall be 8 inch in diameter. Vertical (downspouts) piping shall also be 8
inches in diameter. Figures 16.3.1 and 16.3.2 illustrate typical drainage system details.
Drainage piping and fittings shall be polyvinyl chloride (PVC), reinforced fiberglass or
galvanized steel. Cast iron pipe and fittings shall not be used. The following note shall
be added to the list of General Notes.
Drain pipe for Bridge Drainage System, including all piping, fittings, support
brackets, inserts, bolts, and splash blocks shown, shall be as specified in the
latest IDOT GBSP for Drainage System, except as modified herein. Drain pipe
may be Polyvinyl Chloride (PVC) Pipe, Reinforced Fiberglass pipe or Galvanized
Steel Pipe.
16.3.1 Polyvinyl Chloride Pipe
Polyvinyl Chloride (PVC) pipe and fittings shall be 8 diameter schedule 80 meeting the
requirements of ASTM D1785 (F441), D2464 and D2467, colored in accordance with
Article 16.5. These requirements shall be added as a note to the list of General Notes.
March 2016
16-2
Illinois Tollway
Pipe Supports
Pipe hangers shall be provided for all horizontal (collection) drain pipes at each fitting,
cleanout, or change in direction and at intermediate points not more than 5-0 on
centers. Collection pipe hangers shall have an allowable load capacity of not less than
500 lbs. and shall be designed so as not to apply excessive compressive stress to the
pipe. See Figures 16.4.1 and 16.4.2 for pipe hanger details. Steel straps, bars and
plates shall meet the requirements of AASHTO M270, Grade 36 or 50.
Pipe supports shall be provided for all vertical (downspout) drain pipes at points not
more than 12-0 on centers. See Figures 16.4.3 through 16.4.6 for drain pipe support
details. Structural steel shapes shall meet the requirement of AASHTO M270, Grade
36.
All pipe hangers, supports and hardware shall be hot-dipped galvanized after fabrication
in accordance with AASHTO M232 (ASTM A153) unless otherwise noted. All bolts,
nuts and washers shall be stainless steel. Stainless steel bolts, and washers shall to
the Standard Specifications Article 1006.29(d).
16.5
Painting
All exposed surfaces of floor drains, hangers, brackets and piping located on the
exterior side of painted fascia beams and/or visible to the motoring public shall be
painted or supplied in the appropriate color except stainless steel and galvanized shall
not be painted. The color of the final coat shall match that of the adjacent beam and/or
column, Munsell numbers 7.5G4/8 Interstate Green or 5B7/1 Gray. Final color shall be
submitted to the Engineer for approval.
16.5.1 Aluminum Tube
The exterior surfaces shall be cleaned and given a wash coat pretreatment in
accordance with SSPC - SP1 and SSPC - Paint 27. The pretreated surfaces shall be
painted with an adhesion bonding primer and top coat per the system recommended by
the pretreatment manufacturer for painting aluminum surfaces in an exterior
environment. These requirements shall be added as a note to the list of General Notes.
March 2016
16-3
Illinois Tollway
March 2016
16-4
Illinois Tollway
~ SCUPPER
~ SCUPPER
MARCH, 2016
2%
BRIDGE DECK
45 ELBOW
(TYP.)
2%
NEOPRENE
SLOPE
~ SCUPPER
SLOPE
GASKET
PIER
PIPE SUPPORT
45 Y-BRANCH
CLEAN OUT (TYP.)
(TYP.)
Y-BRANCH CLEAN OUT
PIPE HANGER
SUPPORT DRAIN
FIGURE 16.
3.
1
(SEE FIGURES
16.4.1 OR 16.4.2)
45 ELBOW
(TYP.)
8"} DRAIN PIPE
NOTES:
EMBED
(TYP.)
ILLINOIS TOLLWAY
END ELEVATION
FIXED PIERS
~ SCUPPER
~ SCUPPER
MARCH, 2016
NEOPRENE
GASKET
(TYP.)
BRIDGE DECK
2%
2%
SLOPE
SLOPE
~ SCUPPER
(TYP.)
CLEAN OUT PLUG
(TYP.)
PIPE HANGER
(SEE FIGURES
16.4.1 OR 16.4.2)
PIER
REDUCER AND
EXPANSION COLLAR
FIGURE 16.
3.
2
PIPE SUPPORT
NOTE:
ILLINOIS TOLLWAY
SPLASH BLOCK
(SEE FIGURE
16.4.5)
SUPERSTRUCTURE BETWEEN
THE PIER AND THE SCUPPER.
3. BOLT PATERN AND SIZE IN DRAIN
END ELEVATION
General
All bridge deck expansion and fixed (rotational) joints shall be sealed to prevent water
from penetrating to the bridge elements below the deck surface. Both expansion and
fixed (rotational) joints shall be designed and detailed in accordance with Section 3.6 of
the latest IDOT Bridge Manual except as herein amended. Integral and semi-integral
abutments shall be utilized wherever possible to eliminate the need for expansion joints
at these locations. See Section 10.0 of this Manual for parameters pertaining to the use
of these types of abutments.
Expansion and fixed joints installed on bridges with 10 degree skews or greater shall be
modified to intersect the barrier or curb line at 90 deg. This change in direction shall
occur 6 inches from the back face of curb or front face of parapet (see Base Sheets MBRG-500 and M-BRG-501).
Joint seals shall be one continuous piece for the full length of the joint. Splicing of the
gland is not allowed.
17.2
Only Strip Seals and Modular Joints shall be utilized to seal expansion or fixed (rotation)
joints in new or replacement decks. Unbonded Preformed Joint Seals, Neoprene,
Bituminous, Poured Silicone and steel Finger Plates shall not be used. Only Strip Seals
and Modular Expansion Joints currently on the latest IDOT Pre-Qualified products list
shall be considered for use by the Illinois Tollway.
17.2.1 Strip Seals
Strip Seals shall be used to seal the deck joints of all new or replacement structures
located on tangent alignments where the skew angle(s) are 60 deg. or less and the
expansion length is not greater than 250. They may also be used for structures on
curved alignment provided the skew angles(s) are 40 deg. or less and the expansion
length is equal to or less than 250, measured along the center or baseline. The Illinois
Tollway will consider the use of greater expansion lengths on a case-by-case basis. See
Base Sheets M-BRG-500, M-BRG-501 and M-BRG-502 for details.
17.2.2 Modular Joints
Modular Joints shall be used to seal expansion joints of structures on tangent or curved
alignment exceeding the strip seal limits specified above, provided skew angles are 60
deg. or less and the expansion length does not exceed 800 feet.
17.3
Structures that are to be widened on one or both sides shall utilize the same type of
joint that is currently installed in the existing deck, provided it is in good condition. If the
March 2016
17-1
Illinois Tollway
When a deck is only being repaired and/or resurfaced and isolated sections of the
existing joint are in poor condition, they shall be reconstructed or repaired in-kind,
provided the total length of repairs does not exceed 40% of the original length.
Regardless of the repair length, the existing seal or gland shall be completely replaced.
Whenever the total length of repairs will exceed 40% of the original, or the entire joint is
in poor condition, the existing joint shall be completely reconstructed and sealed with a
Strip Seal or a Bonded Preformed Joint Seal.
When reconstructing expansion joints on existing bridges with skews greater than 10
deg., the joints shall be modified so they intersect the face of the parapet or curb at 90
deg. This modification typically consists of removing a short section of the existing
parapet and relocating the parapet joint so that the modified expansion joint intersects it
at 90 deg.
17.5
Approach Slabs
Only Bonded Preformed Joint Seals which are fully adhered to both faces of the open
joint shall be utilized to construct the expansion joints between the approach and
transition slabs and the transition slab and roadway pavement as detailed in the Base
Sheets M-RDY-408 and M-RDY-409.
Joint armor is not required or allowed. See Base Sheets M-RDY-408 and M-RDY-409
and Figure 17.5.1 for details.
17.6
Fabrication
All structural steel for expansion joints shall be hot dipped galvanized after fabrication in
accordance with AASHTO M232 (ASTM A153).
March 2016
17-2
Illinois Tollway
March 2016
Illinois Tollway
New Bridges
A table showing top of deck slab elevations along the centerline of each longitudinal
beam or girder, stage construction joint, break in cross slope, and profile grade line shall
be included in the bridge plans for all structures with steel or concrete stringers. This
table is usually in the form of a computer output reduced in tabular form on individual
plan sheets. Examples of these sheets are shown in Figures 3.1.9-1 through 3.1.9-4 of
the latest IDOT Bridge Manual.
In addition, top of bridge approach slab, transition approach slab, and transition
approach shoulder slab elevations along each longitudinal profile grade line, break in
cross slope, stage construction joint, edge of pavement or shoulder shall also be
provided on separate individual plan sheet(s) after the deck elevation sheet(s).
Examples of which are shown in Figures 3.1.9-5 and 3.1.9-6 of the latest IDOT Bridge
Manual.
Where the stringer lies below a curb, sidewalk or median section, the elevations shall be
given for a theoretical top of slab, which would be the projection of the cross slope from
the roadway template to the centerline of stringer.
The increments for elevations along centerline of each web shall be 10 feet with any
odd increment not greater than 15 feet or less than 5 feet placed at the end of a span.
A new series of 10-foot increments shall begin in each respective span along the
structure. In all cases, the increments shall progress in the direction of the stationing on
the bridge for the full length of the structure. The theoretical top of slab elevations at
these increment points shall be adjusted for dead load deflection and tabulated in a
separate column, which will become the finished elevations for construction of the deck
slab.
Actual dead load deflection diagrams (due to weight of concrete deck and all
superimposed dead loads except future wearing surface) shall be shown on the top of
the slab elevations indicating deflection ordinates at the quarter points and midpoint of
all stringers of each span. However, if the variance in deflection between the exterior
and interior stringers is one-eighth inch or less, one dead load deflection diagram shall
be sufficient for all stringers. Dead load deflection diagrams shall be qualified with the
following note:
"The above deflections are not for use in the field if the Engineer is
working from the Theoretical Grade Elevations Adjusted for Dead Load
Deflection."
If the superstructure will be constructed in stages, any concentrated superimposed dead
loads (noise abatement walls, parapets, sidewalks and medians) applied during the
initial stage shall only be distributed to a maximum of three adjacent stringers erected in
that stage. These initial concentrated superimposed dead loads shall not be considered
in the deflection calculations for stringers erected in subsequent stages.
March 2016
18-1
Illinois Tollway
The procedure described below shall be used in the preparation of profile worksheets
for bridge deck overlays and approach pavement profile transitions.
Profiles shall be prepared for each edge of pavement and crown line. Where there is an
auxiliary lane on the deck, a profile for the edge of the auxiliary lane shall also be
prepared. The profiles shall have a longitudinal scale of at least 1 inch equals 50 feet,
and a vertical scale of at least 1 inch equals 1 foot, although a vertical scale of 1 inch
equals foot will facilitate reading elevations from the profiles.
Plot existing overlay surface elevations and existing concrete deck elevations at
20-foot centers on roadway and 10-foot centers on deck.
Using 1-1/4-inch minimum concrete cover over the existing concrete high points
and applying the cross slope criteria as defined in Article 15.3, fit smooth
curvilinear profiles following as close as possible the general direction and
configuration of the original profile grade. Where scuppers are involved, cross
sections shall be drawn to verify that the scuppers will not present a problem.
After the tentative profiles are sketched out, the cross slope shall be checked
again for compliance with the criteria. More than one trial and error run may be
required to achieve the best fit set of profiles for each individual deck. Profile
lines shall not follow theoretical grades and parabolic curves unless such grades
and curbs happen to give the best fit for a particular location.
The deck profiles shall be transitioned back to the existing or proposed approach
roadway elevation within 100 feet to 200 feet from each end of the bridge deck.
The transition shall be long enough and end at the most convenient point as to
provide a continuous smooth profile, without breaks, dips or bumps.
Upon review and acceptance by the Illinois Tollway, the profile worksheets shall
be finalized with all lines neatly drawn and identified. It is intended that these
worksheets will be used by the Engineer during construction.
The elevations for the overlay surface contour plans or screed elevations may be
scaled directly from the profiles developed from the field survey.
March 2016
18-2
Illinois Tollway
General
Bridge approach slabs and transition approach slabs shall be included with the plans for
each new and widened bridge. Mainline or ramp bridges carrying Illinois Tollway traffic
shall be provided with approach and transition slabs including shoulders at each
abutment. The bridge approach (30 ft.) and transition approach slabs (70 ft.) shall be
100 feet long as detailed in the latest Illinois Tollway Base Sheets M-RDY-408 and MRDY-409.
For curved structures, the joints between the bridge deck and bridge approach slab
(non-integral) and between the bridge approach slab and transition approach slab shall
be parallel to the bridge centerline of bearing. The 30 foot length shall be measured
along a line tangent at the centerline of bearing. The joint between the transition
approach slab and roadway pavement may be made radial to the roadway baseline.
Transition approach shoulder slabs shall be used on integral and semi-integral
structures when asphalt shoulders are adjacent to the concrete approach slab to
provide a full concrete bond for the bonded preformed joint seal. They are not required
on non-integral structures and if a moment slab or concrete shoulder is adjacent to the
approach slab.
Bridges carrying traffic other than that of the Illinois Tollway shall also be provided with
approach pavement at each end of the structure. The approach pavement shall be 30
feet long as detailed in the latest IDOT Base Sheets.
Existing approach slabs and shoulders shall be widened, where required, in kind. The
new expansion joints at the roadway end of the approach slab shall match the existing
joints unless they are in poor condition, in which case the existing joint shall be
reconstructed as part of the approach slab widening.
On bridge replacement or approach slab replacement projects for the mainline bridges
and flyover ramps under the Illinois Tollway jurisdiction that provide direct access to the
Illinois Tollway, concrete type shall be determined in accordance with the following
policy:
Performance Mix Concrete, fc=4,000 psi min. shall be used for cast-in-place
bridge approach slabs, transition approach slabs, and transition approach
shoulder slabs.
BS Concrete, fc=4,000 psi min. shall be used on all parapets and barriers.
SI Concrete, fc=3,500 psi min. shall be used in all substructure elements of the
bridge approach and transition approach slabs.
March 2016
19-1
Illinois Tollway
19-2
Illinois Tollway
All approach bents shall be supported by piles in accordance with Base Sheets M-RDY408 and M-RDY-409. The approach pile bent details shall be included in the structural
plans.
The piles shall be designed to support the longitudinally reinforced approach slab
similarly to a typical bridge structure. The installation of piles shall be divided into
furnishing, driving and test pile pay items. Concrete, reinforcement and piles in the
approach pile cap shall not be included in the cost of Bridge Approach Slab or
Transition Approach Slab.
March 2016
19-3
Illinois Tollway
March 2016
Illinois Tollway
March 2016
20-1
Illinois Tollway
General
Culverts shall be designed in accordance with the latest AASHTO LRFD Bridge Design
Specifications and IDOT Culvert Manual, except as herein modified.
Box culverts may be single or multi-cell box, three-sided box or three-sided arch
sections constructed of cast-in-place or precast concrete. Culverts are most commonly
used to carry water under roadways, but they are also used for pedestrian/bicycle
underpasses. The minimum size for a pedestrian/bicycle underpass is 10 feet high by
10 feet wide. Typical sections for the most frequently used box culverts are shown in
Figure 21.1.1.
For culverts over waterways, a type study shall be performed in accordance with the
Illinois Tollway Drainage Design Manual Article 8.1 to ensure that the type selected is in
accordance with United States Army Corps of Engineers permits.
Corrugated metal arch or box culverts are not permitted for new or replacement
structures.
Hydraulic and geometric requirements of the site shall determine the area and
maximum height of the culvert. Once the maximum height and required area are
determined, the selection of the type of culvert, its construction and number of cells is
determined by economics and site conditions. Barrel lengths are computed to the
nearest 6 inch.
The designer shall determine the end of the barrel based on a barrier warrant analysis
(see Article 3.2). For multi-cell culverts, the cell widths shall be kept equal.
Wingwalls shall be designed according to the IDOT Culvert Manual. Horizontal
Cantilever Wingwalls shall be used for wingwall lengths less than or equal to 14 feet. TType or L-Type Vertical Cantilever Wingwalls shall be used when the length of wingwall
is greater than 14 feet. Reinforced concrete aprons between the wingwalls and safety
end treatments shall be placed at both ends of the culvert. The barrel section of a
culvert used for a pedestrian/bicycle under pass shall be covered with a waterproof
membrane system, in accordance with Section 581 of the latest IDOT Standard
Specifications.
21.1.1 Cast-In-Place Concrete Culverts
All designs shall be in accordance with the latest version and interims of the AASHTO
LRFD Bridge Design Specifications. The Unit Weight of Backfill (s) shall be taken as
120 lbs/cu ft. The lateral earth pressure acting on the sidewalls shall be assumed as an
equivalent fluid pressure of 40 lbs/cu ft for the depth of the fill and 50 lbs/cu ft for the
height of the barrel. A surcharge of 2 feet shall be added to the fill, when live load is
considered in the design of the barrel. Refer to Figure 21.1.1.1 for illustration.
March 2016
21-1
Illinois Tollway
Minimum Dimension
Top Slab
6 inches
Bottom Slab
Side Walls
All reinforcement bars for cast-in-place concrete box culverts shall be epoxy coated.
21.1.2 Precast Concrete Culverts
Precast concrete culverts are used where labor and materials are not readily available,
and when the duplication and installation of identical precast culvert sections would be
more economical than cast-in-place construction. Precast concrete culverts are not
suitable in areas where the supporting soils are susceptible to excessive or differential
settlements, unless they are supported by a reinforced concrete slab or strip footing
founded on piles or if settlement can be reduced by providing subgrade improvement.
A minimum of 6 feet of the barrel shall be poured monolithically with horizontal
cantilever wingwalls.
21.2
Plan Preparation
Station and elevation at the centerline of the culvert, showing locations of the
joints, if any
Section thru barrel showing all concrete dimensions and reinforcement bar
details
March 2016
21-2
Illinois Tollway
General Notes
Index of Sheets
Bill of Material
The latest version and interims of the AASHTO LRFD Bridge Design
Specifications
IDOT All Bridge Designers (ABD) Memorandum 11.3 (Rev) dated November 2,
2011, (revised January 27, 2012)
The latest IDOT Standard Specifications for Road and Bridge Construction and
all subsequent Supplemental Specifications
March 2016
21-3
Illinois Tollway
March 2016
21-4
Illinois Tollway
LIVE LOAD
SURCHARGE=2' FILL
P
EQ. FLUID
EQ. FLUID
PR.=40 PCF.
1.75 F
PR.=40 PCF.
P1
EQ.
FLUID
PR.=
50 PCF.
T2
T1
T1
EQ. FLUID
CLEAR HEIGHT
CLEAR SPAN
PR.=50 PCF.
D
P2
P1
P1
P2
BOX CULVERT
USE WHEN NO LIVE
LOAD INCLUDED
IN DESIGN OF
BARREL
CROSS SECTION
MARCH, 2016
FIGURE 21.1.1.1
ILLINOIS TOLLWAY
Wall Types
Retaining wall structures are used to hold back soil or loose material where an abrupt
change in ground elevation occurs. There are several types of retaining wall structures.
Depending on the application, certain wall types are more advantageous than others.
The designer shall generalize the site as being either a fill wall location or a cut
wall location.
22.2
Cut Walls
Soldier Piles
Sheet Pile
Soil Nails
Tangent Drilled Shafts
For discussion of the retaining wall selection process, refer to Sections 2.3.5.5 and
2.3.12 in the IDOT Bridge Manual.
The Designer shall submit a feasibility study to the Illinois Tollway prior to preparation of
TS & L plans. The purpose of the feasibility study is to select the most cost effective
retaining system for advancement to the TS & L Phase. As part of the feasibility study,
the Designer shall investigate a no wall option. This may often require additional rightof-way, earth work and/or relocation of existing utilities and existing structures. If the no
wall option is not feasible, the Designer shall study a combination of slopes and wall
types to minimize the wall length and height, while remaining aesthetically acceptable
and cost effective.
The feasibility study shall include the following items:
March 2016
22-1
Illinois Tollway
Retaining Wall Criteria Design loads, allowable soil pressures, site constraints
and design requirements for the retaining wall.
Structural Alternates Description and cost estimate for each of the wall types
investigated including No Wall option.
22.3
Plan Preparation
March 2016
22-2
Illinois Tollway
EXAMPLE: TS38.40R,NB(R) for a retaining wall located along the Tri-State Tollway (I294) northbound at milepost 38.4 on a ramp
If two walls of the same type have identical starting mileposts, the inventory milepost of
one of the walls shall be shifted by one hundredth of a mile to create unique names.
22.4
Dead Loads
March 2016
22-3
Illinois Tollway
Live Loads
See Article 5.1.
Earth Pressure
See Article 5.1. The formula to compute lateral earth pressure is Coulomb's
equation for the resultant parallel to the backfill slope. The maximum angle
of internal friction for granular material shall be = 30 deg.
The formula to compute lateral earth pressure for sloping backfill assumes
the mass of earth behind the wall extending to the point of intersection of the
two planes (slope plane and failure plane of soil). In many cases the sloping
backfill ends at a certain height above the wall where a roadway is
intersected. The formula gives conservative results for this case. See Figure
22.4.2.1 for details
Wind Loads
A wind load on the parapet and/or noise abatement wall shall be applied to
the exposed surface area in any direction.
22-4
Illinois Tollway
22-5
Illinois Tollway
Shear Key.
The shear key shall be located in line with the front face of the stem except
under severe loading conditions. The width of the shear key shall be 1-0
minimum and the minimum depth is 1-0. The shear key shall be placed
against undisturbed material.
The total resistance to sliding is based on the soil strength in front of the
shear key and adhesion between the footing and soil behind the key.
Spread footings on rock. The width of the key shall be 1-0 minimum. Key the
footing a minimum depth of 6 into the rock.
Pile Footings.
The maximum slope to be used for determining the horizontal resistance of a
battered pile shall be 3 inches horizontal per foot vertical.
For the lateral resistance of battered or vertical piles, in addition to horizontal
component of battered piles, consult the structural geotechnical report.
22.6
Flexible retaining walls include; Mechanically Stabilized Earth (MSE), Precast Modular,
Soldier Pile, Sheet Pile, Soil Nail and Gabion.
The required design life for all elements of retaining wall structures is 75 years except
for walls in front of bridge abutments which require a design life of 100 years.
Provide full height expansion joints in the gutter and parapet every 90 feet. The
expansion joints shall be detailed as shown in Figures 22.12.1 and 22.14.1. Provide
partial height parapet joints in the upper portion of the parapet at 15 foot centers. These
partial height joints shall be -inch open joints.
Design loads for retaining walls with moment slabs shall include the provisions of the
AASHTO LRFD Bridge Design Specifications, Article 11.10.10.2 and Test Level 5 (TLMarch 2016
22-6
Illinois Tollway
Location
MSE walls shall be located a minimum of 10'-0" inside of the Illinois Tollway's Right of
Way. MSE walls are not allowed at water crossings or adjacent to water where hydraulic
draw down within the wall limits is possible.
22.6.1.2
The Contractor shall be provided with plans showing a line diagram envelope (Elevation
View) of the proposed wall location, grades, and dimensions. Specifications shall be
furnished covering the work requirements for design, construction plans, materials
procurement, and wall construction. The prequalified retaining wall supplier selected by
the Contractor shall submit a complete set of design calculations, detailed plans, and
explanatory notes for the designer's review and acceptance prior to ordering any
material. The design shall be in accordance with the latest AASHTO LRFD Bridge
Design Specifications and the special provisions.
The designer shall prepare plan sheets containing the following information:
March 2016
22-7
Illinois Tollway
Utility accommodations
Drainage requirements
22.7
Block retaining walls shall be designed in accordance with the applicable parts of
Section 3.11.1 of the IDOT Bridge Manual and the latest LRFD AASHTO Bridge Design
Specifications except as amended herein.
When specifying a proprietary block retaining wall, the special provisions shall state that
the wall shall be built according to the manufacturers specifications. The manufacturers
specifications generally need to be supplemented. Material specifications for backfill,
leveling pad, drainage systems, fill for hollow blocks, geotextile fabrics or any other
special requirements shall be clearly stated in the special provisions.
Modular block retaining walls shall be designed and sealed by the manufacturers
Illinois Licensed Structural Engineer. Soil reinforcement shall be either galvanized or
coated steel or polypropylene or polyester geogrids. In the absence of more accurate
data, design loads on the wall shall be based on a non-cohesive material with an angle
of internal friction of 34 deg. The minimum size of the concrete leveling pad shall be 6
inches deep by 12 inches wide. All steel components of a system shall be hot dipped
galvanized in accordance with the AASHTO M111 (ASTM A123).
March 2016
22-8
Illinois Tollway
Soldier pile walls shall be designed in accordance with Section 3.11.3 of the latest IDOT
Bridge Manual and the latest AASHTO LRFD Bridge Design Specifications except as
amended herein. Timber lagging is not permitted as a facing material for permanent
soldier pile walls.
22.9
Permanent sheet pile retaining walls shall be designed in accordance with Section
3.11.4 of the latest IDOT Bridge Manual.
22.10
Soil nailed and other specialized wall systems shall be designed in accordance with
Section 3.11.6 of the latest IDOT Bridge Manual.
22.11
Temporary soil retention systems, including temporary sheet piling, wire-faced MSE
walls, braced excavations and other temporary construction works shall be designed in
accordance with Section 3.13 of the latest IDOT Bridge Manual.
22.12
The need for and design of the snow storage area shall be according to the latest
version of the Illinois Tollway Roadway Design Criteria. When snow storage is required,
the retaining wall and parapet shall move away from the edge of shoulder to create a
place to store the snow in front of the parapet. If a noise abatement wall will be required
at the location, the parapet shall not move away from the edge of shoulder and snow
storage shall be accommodated between the parapet and the noise abatement wall.
Figure 22.12.1 shows the configuration of the parapet and noise abatement wall when a
moment slab is used.
22.13
Parapet Shape
The Illinois Tollway uses two parapet shapes for retaining walls within the clear zone
42 F-Shape and 42 single slope. Both types shall be designed to accommodate crash
Test Level 5 (TL-5). See the latest AASHTO LRFD Table A.13.2-1 for loading details.
F-Shape
The F-Shape shall be used on the front (traffic side) of the parapet whenever a moment
slab is used to counteract forces applied to the parapet. See Figure 22.14.2 for an
example using F-Shape.
March 2016
22-9
Illinois Tollway
A moment slab includes both the horizontal slab and the 42 F-Shape vertical parapet
that is attached to the slab. Design loads for strength that include flexure, shear and
torsion are applied in accordance with the AASHTO LRFD Bridge Design
Specifications, Section 13, Table A13.2, Test Level 5 (TL-5). Design loads for global
stability including sliding and overturning shall follow recommendations of NCHRP 663.
Prior to this change, walls and moment slabs were designed in accordance with
AASHTO Standard Specifications Load Factor Design (LFD) methodology.
A minimum 6 thick layer of CA-6 aggregate shall be placed beneath the moment slab
to develop friction. This layer is to be detailed on the plans.
Concrete for moment slabs under the Illinois Tollway jurisdiction shall be placed in
accordance with the following policy:
Performance Mix Concrete, fc=4,000 psi min. shall be used for moment slabs.
Structural Capacity The structural capacity of the parapet and concrete moment slab
shall be designed using dynamic TL-5 loads in accordance with Sections 5 and 13 of
the AASHTO LRFD Bridge Design Specifications.
Global Stability Sliding and overturning stability of the moment slab shall be based
on an Equivalent Static Load (ESL) applied to the top of the traffic parapet. For TL-5
parapet systems, the ESL shall be 23 kips.
Rigid Body Definition Moment slabs that have a minimum width of 4-0 measured
from the point of rotation to the heel of the slab and a minimum average depth of 10
are assumed to provide rigid body behavior up to a length of 60 for end parapet and
interior parapet impacts. Rigid body behavior may be increased from 60 to a maximum
of 120 if the torsional rigidity constant of the moment slab is proportionately increased
and the reinforcement bars are designed to resist combined shear, moment, and torsion
from impulse loads.
March 2016
22-10
Illinois Tollway
22-11
Illinois Tollway
Safety Fencing
For walls with exposed heights greater than 4 feet, either the top of wall shall be
extended 4 feet above the gutter line or railing and/or fencing shall be provided. See
Figure 22.5.1.1 for details.
March 2016
22-12
Illinois Tollway
OR FACING
CONSTRUCTION JOINT
STEM
RETAINING WALL
MANDATORY UNBONDED
LAP LENGTH
" CHAMFER
FRONT FACE
2" CL.
(TYP.)
2"
CEMENT NAILS FLAT HD. C.S. 1" LONG
AT 12" CTS. VERTICAL EACH FACE (COST
6"
OR FACING
STEM
RETAINING WALL
"
MARCH, 2016
FIGURE 22.3.1.1
ILLINOIS TOLLWAY
SUBDRAIN
GROUT
STEM
RETAINING WALL
NON-METALLIC
SLEEVE THROUGH
RETAINING WALL
MARCH, 2016
FIGURE 22.3.1.3
ILLINOIS TOLLWAY
2"
"
OR LINE POST
"
2 "
" STIFFENER `
" `
6" MIN.
SHIM AS REQUIRED
PROP. WALL
EXPANSION ANCHORS
2" 2"
7"
2" 2"
1" (TYP.)
1 " (
TYP.
)
ELEVATION
7"x7"x" BASE ` W/
4-"} HOLES FOR "}
7"
GALVANIZED EXPANSION
ANCHORS W/WASHERS
PLAN
AND NUTS
NOTES:
1. BASE PLATES, STIFFENERS AND EXPANSION ANCHORS FOR MOUNTING FENCE
ON RETAINING WALLS SHALL BE INCLUDED IN THE COST OF CHAIN LINK FENCE.
2. IF NECESSARY THE SIZE OF THE BASE PLATE AND LOCATION OF THE EXPANSION
ANCHORS MAY BE ADJUSTED TO MISS THE WALL REINFORCEMENT.
3. BASE PLATES AND STIFFENERS SHALL BE FABRICATED FROM MATERIAL MEETING THE
REQUIREMENTS OF AASHTO M270 GRADE 36.
4. BASE PLATES, STIFFENERS AND POSTS SHALL BE HOT DIPPED GALVANIZED AFTER
FABRICATION IN ACCORDANCE WITH AASHTO.
FIGURE 22.3.1.4
ILLINOIS TOLLWAY
3"
OR LINE POST
"
TYP.
" STIFFENER `
4"
6"
3"
" `
6" MIN.
3"
"
2 "
SHIM AS REQUIRED
TRAFFIC
FACE OF
7"
"
BARRIER WALL
DRILL & SET "} GALVANIZED EXPANSION ANCHORS
ELEVATION
13"x6"x" BENT OR WELDED
1" (TYP.)
3"
3"
3"
1 "
6"
1 "
3" 3"
"
7"
PLAN
NOTES:
1. BASE PLATES, STIFFENERS AND EXPANSION ANCHORS FOR MOUNTING FENCE ON RETAINING
WALL SHALL BE INCLUDED IN THE COST OF CHAIN LINK FENCE.
2. IF NECESSARY THE SIZE OF THE BASE PLATE AND LOCATION OF THE EXPANSION ANCHORS
MAY BE ADJUSTED TO MISS THE WALL REINFORCEMENT.
3. BASE AND STIFFENERS SHALL BE FABRICATED FROM MATERIAL MEETING THE REQUIREMENTS
OF AASHTO M270 GRADE 36.
4. BASE PLATES, STIFFENERS AND POSTS SHALL BE HOT DIPPED GALVANIZED AFTER
FABRICATION IN ACCORDANCE WITH AASHTO.
FIGURE 22.3.1.5
ILLINOIS TOLLWAY
8"
4"
8"
" VIBRATION PAD (BY OTHERS)
2"
BUSHING
4'
-4"
6-#6 d(
E) BARS
2"
8"
MAX.
SECTION A-A
10 "
10"
10"
v1(E)
CL.
MIN.
MAX.
2"
1'
-0"
8"
1'
-8"
10"
d(E)
1'-3"
1'-3"
v(E)
2
2'-6"
MARCH, 2016
FIGURE 22.3.1.6
ILLINOIS TOLLWAY
6 MIL. POLYETHYLENE
BOND BREAKER
H)
V:
(
3'
-6"
M
MU
XI
A
M
2
1:
EXISTING OR PROPOSED
GROUND LINE IN
BACK OF WALL
6"
MARCH, 2016
FRONT FACE
GUTTER W/FRAME AND GRATE
AT DRAINAGE STRUCTURES
FIGURE 22.
5.
1.
1
BACK FACE
**
2
1:
SLOPED HEADWALL
UM
XIM
A
M
H)
V:
(
-0"
4'
9"
STANDARD SPECIFICATIONS.
VARIES
OUTLET SUBDRAIN,
1.0% MIN.
ILLINOIS TOLLWAY
EXCAVATION
OUTLET SUBDRAIN
FRONT FACE
BACK FACE
2" CL.
v (E)
w (E)
POINT OF MAX.
SOIL PRESSURE
HEEL REINFORCEMENT
BARS,t(E)
3" CL.
18" MIN.
#4n (E)
@ 1'-0"
CTS.
T1
2" CL.
SPECIFY MIN.
CONSTRUCTION JOINT
PROJECTION AND
1"x3" KEYWAY
n (E)
TOE REINFORCEMENT
BARS,t(E)
b
FIGURE 22.5.1.2
ILLINOIS TOLLWAY
2'-0"
(GUTTER )
0.
1'
6"
3'
-6"
CA6 AGGREGATE
PAD
BACK FACE OF
RETAINING WALL
1'-7"
MIN.
MARCH, 2016
FIGURE 22.5.1.3
ILLINOIS TOLLWAY
MARCH, 2016
1'-6"
1'-7"
13'-0"
E.O.P.
OR
LANE
SNOW STORAGE
NOISE ABATEMENT
WALL
F-SHAPE
PARAPET
**
1'-0"
6"
(GUTTER)
*
MIN.
2" (
MIN.
)
1'
-0" (
MAX.
)
2
1: X.)
A
M
(
11'-0" (SHOULDER)
1'
-6"
FIGURE 22.
12.
1
5%
2'-0"
FACE OF
RETAINING
WALL
ILLINOIS TOLLWAY
2"
1'-7"
3'
-6"
PAVEMENT.
La
1'
-4"
2" (
MIN.
)
1'
-0" (
MAX.
)
2
1: .)
AX
(M
HEEL OF SLAB
POINT OF ROTATION A
6"
1'-0"
Lw
FACE OF
RETAINING
WALL
5" +
_ 1"
16" +
_ 1"
TYP.
B
12"
12"
LONGITUDINAL JOINT
TYP.
" MAX.
5" +
_ 1"
" MIN.
PLAN DETAIL A
12" R
16" + 1"
" MIN.
" MAX.
SECTION A-A
SECTION B-B
FIGURE 22.14.1
ILLINOIS TOLLWAY
MIN.
POINT OF ROTATION
ha = MOMENT ARM
TO ACCOMODATE ADJACENT
**
TOP OF BARRIER TO
MARCH, 2016
MOMENT SLAB
1'-7"
2"
13'-0"
E.O.P. OR LANE
2'-0"
11'-0"
GUTTER
SHOULDER
#5 d(E) AT 7"
(MIN.)
#5 d1(E) AT 7"
PCC PAVEMENT
#5 w(E) AT 18"
**
1 "
CONSTRUCTION JOINT
(MANDATORY)
#6 a(E) AT 7"
1'
-4"
#8 e(E)
MIN.
2 " CL. (
| ")
3'
-6"
#5 e1(E)
(TYP.)
2'-4" | 1"
1 " CL.
STABILIZED
SUBBASE
2
1: .)
AX
(M
3"
2" (
MIN.
)
1'
-0" (
MAX.
)
TOP OF
EXPOSED
PANEL LINE
#5 e2(E)
CL.
2'
-5 "
FIGURE 22.
14.
2
2"
#5 a1(E) AT 14"
PIPE UNDERDRAIN
SUBGRADE
AGGREGATE
1'-0"
7"
R 2"
7"
R 2"
1'-2"
1'-2"
STRUCTURES.
5 "
PAVEMENT.
BAR d(E)
BAR d1(E)
**
2'
-7 "
"
-10
2'
**
8"
2'
-7"
-11"
2'
ILLINOIS TOLLWAY
2'
-10"
NOTES:
**
General
Noise abatement walls shall be designed in accordance with the latest AASHTO Guide
Specifications for Structural Design of Sound Barriers and Interims, AASHTO LRFD
Bridge Design Specifications, Sections 13 and 15 at Test Level 4 or 5 (TL-4 or TL-5) as
applicable and as amended herein.
The noise abatement wall shall be designed to attenuate the sounds generated by
highway traffic and achieve a minimum noise reduction of 5 decibels.
Panels shall be embedded a minimum 1-0 below grade. The noise abatement wall
material shall be manufactured from fire retardant material that meets State and local
requirements. Structure mounted or ground mounted noise abatement wall types shall
be one of the following:
Precast Concrete The precast concrete noise abatement wall shall consist of
either separate panels, or posts and panels spanning between vertical posts. The
precast concrete panels of the noise abatement wall may be conventionally
reinforced, pre-stressed, post-tensioned, or any combination thereof. The posts
of the noise abatement wall may be constructed of precast concrete or
galvanized, structural steel. If precast concrete posts are chosen, they may be
conventionally reinforced, pre-stressed, post-tensioned, or any combination
thereof.
March 2016
23-1
Illinois Tollway
Alternate Material Noise Abatement Wall This system allows the Contractor to
bid an alternate material noise abatement wall system that meets the
requirements stated in this section and as accepted by the Illinois Tollway.
Wooden noise abatement wall shall be designed for a minimum service life of 25 years;
precast concrete and alternate material noise abatement walls shall be designed for a
minimum service life of 50 years. The design shall be based on the consideration of the
potential long-term effects of weathering, corrosion, spray from de-icing chemicals, and
other potentially deleterious environmental factors on each of the material components
comprising the noise abatement wall.
Expansion and Contraction Devices
The noise abatement wall shall be designed with consideration of the movements in the
wall due to temperature changes, dead loads and wind loads. Locations and spacing of
expansion devices shall be as designed by the Contractor and approved by the Illinois
Tollway.
Stabilizers
Permanent stabilizers are required between posts and panels to maintain the vertical
positions of the panel while resisting the lateral loading primarily due to wind and vehicle
impact. The stabilizers shall be spaced at intervals not to exceed 4 feet, and shall have
a minimum height of 4 inches.
23.2
Design Criteria
March 2016
23-2
Illinois Tollway
23-3
Illinois Tollway
March 2016
23-4
Illinois Tollway
Plan Preparation
23.3.1 General
The Designer shall indicate the location of all required noise abatement walls on the
appropriate roadway and structure plans. Sufficient information shall be shown on the
plans and cross sections so that the manufacturer can design and detail the noise
abatement wall to accommodate each: ground-to-structure transition, overlap,
obstruction and utility or drainage interference. The Designer shall locate the beginning
and end of the noise abatement wall including overlaps and directional changes by
station and offset on the appropriate roadway, drainage and lighting plans including
cross sections. See Figure 23.3.1.1 for typical details.
An elevation view of each noise abatement wall shall be included in the plans. Each
elevation shall show top of noise abatement wall and proposed grade. The location of
transitions, overlaps, obstructions, utility or drainage interferences and changes in noise
abatement wall height shall also be shown. Changes in noise abatement wall height
shall be accomplished using increments no larger than 2 feet and no smaller than 1
foot. The top of wall shall remain horizontal between steps. For an elevation view
example, see Figures 23.3.1.2 and 23.3.1.3. The top of the wall shall remain above the
Acoustical Profile Line.
23.3.2 Naming Convention
Noise abatement walls shall be identified on the plans using the following format:
Illinois Tollway Milepost Wall Type, Direction (Ramp)
TOLLWAY: EW = Reagan Memorial Tollway (I-88)
NS = Veterans Memorial Tollway (I-355)
NW = Jane Addams Memorial Tollway (I-90)
TS = Tri-State Tollway (I-294 & I-294/I-80)
TN = Tri-State Tollway (I-94)
ES = Edens Spur (I-94)
EO = Elgin-OHare Tollway (IL 390)
WA = West OHare Access (I-490)
MILEPOST: Two-decimal lowest wall milepost to the tenth or hundredth if a mile
post (i.e. 14.75)
WALL TYPE: N = Noise Abatement Wall
DIRECTION: EB, SB, WB, NB - Inventory direction of the mainline roadway
RAMP:
EXAMPLE: TS38.40N,NB(R) for a noise abatement wall located along the Tri-State
Tollway (I-294) northbound at milepost 38.4 on a ramp
March 2016
23-5
Illinois Tollway
Specifications
The Designer shall modify the performance based special provisions furnished by the
Illinois Tollway to suit their particular location and conditions.
March 2016
23-6
Illinois Tollway
The Illinois Tollway crosses several railroads that have specific guidelines and drawings
for fencing requirements. The Designer shall coordinate with the railroads regarding the
need for fencing as early in the design stage as possible.
23.5.1 Waivers
The placement of fencing on top of the bridge parapet is not desirable because of traffic
safety concerns and inspection access limitations. The Designer shall propose the
following waivers to the railroad prior to initiating modifications to the standard bridge
rail:
Waiver Alternative I
Request a waiver from the Railroads standards to provide a 42-inch high F-Shape
parapet according to the Illinois Tollways Structure Design Manual. A waiver should be
warranted since the Illinois Tollway does not allow pedestrian traffic or sidewalks on the
Illinois Tollway system. Also, the Illinois Tollway provides an 11-foot to 12-foot shoulder
between the edge of traveled way and bridge parapet to minimize the likelihood of
objects being thrown onto railroad property. The 42-inch high F-Shape parapet meets
criteria for a Test Level 5, according to the AASHTO LRFD Bridge Design
Specifications, which satisfies freeway and large truck requirements.
Waiver Alternative II
Should Alternative I be found unacceptable by the railway, the Designer shall propose
that a 72-inch barrier wall be provided to control the amount of snow and debris falling
onto the track. This will provide for splash boards being provided on structures where
switching or other frequent railroad activities are performed. According to AASHTO
LRFD Bridge Design, parapets that are 6.0 feet above the surface of the pavement shall
meet crash Test Level 5. For this design scenario the bridge deck overhang shall be
limited to 2-0.
23-7
Illinois Tollway
March 2016
23-8
Illinois Tollway
MARCH, 2016
665
660
PROPOSED
PROFILE GRADE
1150+00
1151+
1152+
1153+
1154+
1155+
1156+
1157+
+32.
8 BEGIN STRUCTURE
630
635
TYP.
640
FIGURE 23.
3.
1.
2
645
N.
1'
-0" MI
650
0
+0 .
00
2
65
2'
-0" MAX.
0
+0 .
00
0
65
0
+0 .
00
6
65
0
+0 .
00
4
65
655
0
+9 .
00
8
65
8
2. 3
+3 .
3
0
64
1158+00
I
LLI
NOI
S TOLLWAY
MARCH, 2016
700
0
+5 .
00
6
69
695
690
0
+5 .
00
6
69
STRUCTURE MOUNTED
2170+00
2171+
PROPOSED TOP OF
PARAPET OR RETAINING
WALL
0
+7 .
20
7
67
LIGHT STANDARD
PROFILE GRADE
STA. 2175+46
STA. 2173+93
STRUCTURE MOUNTED
STRUCTURE MOUNTED
LIGHT STANDARD
LIGHT STANDARD
STA. 2176+39
STRUCTURE MOUNTED
LIGHT STANDARD
2172+
2173+
2174+
2175+
2176+
665
0
+7 .
00
8
68
670
0
+5 .
00
0
69
TYP.
STA. 2172+07
FIGURE 23.
3.
1.
3
680
N.
1'
-0" MI
685
675
2'
-0" MAX.
0
+5 .
40
7
68
2177+
2178+00
I
LLI
NOI
S TOLLWAY
OVERLAP
~ NOISE WALL
AND FOUNDATIONS
(4xW MIN.)
"W"
NOISE WALL
(
9'
-0" MIN.
)
NOISE WALL
~ NOISE WALL
AND FOUNDATIONS
PLAN
MARCH, 2016
FIGURE 23.3.3.1
ILLINOIS TOLLWAY
STATION
Y'
-Y"
W1
OFFSET
STATION
OFFSET
NOISE WALL
X'-X"
W2
X'-X"
MOUNTED
Y'
-Y"
NOISE WALL
GROUND
LANES
MOUNTED
SHLDR TRAFFIC
GROUND
4W2
4W
1
STRUCTURE
MOUNTED
STATION
NOISE WALL
OFFSET
GROUND MOUNTED
GROUND MOUNTED
STRUCTURE MOUNTED
T/NOISE WALL
EL.
T/NOISE WALL
EL.
T/STRUCTURE
NOISE WALL
T/FINISHED
EL.
STRUCTURE
~ NOISE WALL
~ NOISE WALL
FOUNDATION
FOUNDATION
ELEVATION
MARCH, 2016
FIGURE 23.3.3.2
ILLINOIS TOLLWAY
GRADE
T/STRUCTURE
GRADE
T/FINISHED
NOISE WALL
EL.
March 2016
Illinois Tollway
Design Specifications
24.2
Overhead sign structures for static signs without sign lighting (span and cantilever) shall
be designed to provide 26-5 from the high point of the roadway beneath the sign
structure to the centerline of the truss, which includes an allowance for 9 from the
centerline of the truss to the bottom of an 18 tall sign panel, regardless of the size of
the panel required for that particular location. This will usually provide extra clearance
when constructed and allow for either lighting or a larger panel to be added in the future.
Taller panels can be accommodated provided that the overall maximum sign area is not
exceeded and the vertical sign panel supports are checked for adequacy.
Sign structures that require lighting, such as those approaching a toll plaza, shall be
designed with a 17-5 vertical clearance to the bottom of the 2 luminaires and with the
sign panel(s) sized to accommodate the legend required for that particular location. For
March 2016
24-1
Illinois Tollway
Aluminum Span Type Sign Structures shall be selected and detailed in accordance with
Standard F1 of the latest Illinois Tollway Standard Drawings. Illinois Tollway Base Sheet
M-OHS-720 shall be used in combination with Standard F1. Aluminum Span Type
structures can span from 80 to 150 feet, and shall support static sign panels only. A
Barrier Warrant Analysis shall be completed in accordance with Article 5.5.9 of the
Illinois Tollway Traffic Barrier Guidelines.
The Illinois Tollways sign structure-span type is an aluminum trichord truss supported
by steel pipe columns, while IDOTs sign structure-span types are aluminum and steel
box, four chord span system.
The steel pipe column support has been designed to accommodate maximum heights
as shown in the table on Sheet 1 of Standard F1.
Illinois Tollway Standard F1 includes the foundations for the Span Type Sign Structures.
The foundations have been revised as follows:
The shoulder foundation has been redesigned, consisting of a grade beam (3-6
width x 18-0 length) supported on two 3-0 diameter drilled shafts for all size
truss spans. This design replaces the individual 4-0 diameter drilled shaft
foundations. This change provides constructability improvements to the
foundation system. The new detail establishes a standard size grade beam for all
span truss sizes, and eliminates the constructability issues related to tight
spacing between the caissons. This feature will also simplify the Traffic Barrier
Warrant analysis by having a fixed dimension for any size truss span type
structure.
The median foundations also have a new grade beam design and details to
match the new 7-0 wide concrete barrier base, supported on two 3-0 diameter
drilled shafts.
March 2016
24-2
Illinois Tollway
Cantilever Type
Cantilever Type Sign Structures shall be selected and detailed in accordance with
Standard F4 of the latest Illinois Tollway Standard Drawings. Illinois Tollway Base Sheet
M-OHS-721 shall be used in combination with Standard F4. Cantilever Type structures
can span from 20 to 50 feet, and shall support either static sign panels or 1 Type 2
DMS. A combination of static signs and DMS units is not permitted. A Barrier Warrant
Analysis shall be completed in accordance with Article 5.5.9 of the Illinois Tollway
Traffic Barrier Guidelines.
The Cantilever Type Sign Structure standard drawings incorporate a concrete and steel
post column support system. This detailing enables the maximum steel post to have a
24 diameter with a nominal wall thickness of 1 for cantilever design spans up to 50
feet in length. Also provided are alternate steel grades for the steel support post; API
5L, Grade B, X42 or X52, ASTM 106, Grade B or C and ASTM A53, Type E or S, Grade
B.
24.6
Monotube Type
Monotube Type Sign Structures shall be selected and detailed in accordance with
Standards F13, F15 or F16 of the latest Illinois Tollway Standard Drawings. Illinois
Tollway Base Sheets M-OHS-722, M-OHS-723, M-OHS-725, M-OHS-726 and M-OHS727 shall be used in combination with Standards F13, F15 or F16. See the latest Illinois
Tollway Standard Drawings for span limits and mounting details. Signs that do not meet
the requirements shown on the standard drawings are not permitted.
These structures are located at mainline and ramp toll plazas, and are used to support
electronic toll collection equipment. The foundations have been designed for both single
and double face barrier walls, supported by individual drilled shaft foundations of 3-6
diameter minimum.
24.7
Butterfly Type
Butterfly Type Sign Structures shall be selected and detailed in accordance with
Standard F14 of the latest Illinois Tollway Standard Drawings. Illinois Tollway Base
Sheet M-OHS-724 shall be used in combination with Standard F14. Butterfly lengths up
to 40 feet are permitted. Each face of a Butterfly Type structure may support either
static signs or 1 Type 2 DMS. A combination of static sign panels and DMS units on the
same face is not permitted. A Barrier Warrant Analysis shall be completed in
accordance with Article 5.5.9 of the Illinois Tollway Traffic Barrier Guidelines.
The Overhead Sign Structure-Butterfly Type shall be selected and detailed in
accordance with Standard F14 of the latest Illinois Tollway Standard Drawings. Details
have been developed for median and shoulder applications. These structures are
intended to support dynamic message signs.
March 2016
24-3
Illinois Tollway
Bridge Mounted Sign Structures shall be designed and detailed in accordance with the
latest IDOT Sign Structures Manual.
In cases where the depth of the fascia beam is shallow and/or the profile grade
approaches 5%, the location of the horizontal WF member between the web of fascia
beam and the back of the sign support may vary vertically in order to maintain the
luminaire supports in a level position (see Base Sheets M-BRG-503 and M-BRG-504).
Alternatively, the location of the horizontal leg of luminaire support could also be varied
to keep the luminaire supports level (see Figure 24.8.1).
24.9
Steel Span Type Sign Structures shall be selected and detailed in accordance with
Standard F17 of the latest Illinois Tollway Standard Drawings. Illinois Tollway Base
Sheet M-OHS-728 shall be used in combination with Standard F17. Steel Span Type
structures can span from 120 to 160 feet, and shall support 1 Type 1 DMS only. Static
sign panels are not permitted. A Barrier Warrant Analysis shall be completed in
accordance with Article 5.5.9 of the Illinois Tollway Traffic Barrier Guidelines.
24.10
Steel ITS Gantry Frame Sign Structures shall be selected and detailed in accordance
with the latest Illinois Tollway Base Sheets M-OHS-729 and M-OHS-730. See the latest
Illinois Tollway Base Sheets for span limits and mounting details. Signs that do not meet
the requirements shown on the base sheets are not permitted. A Barrier Warrant
Analysis shall be completed in accordance with Article 5.5.9 of the Illinois Tollway
Traffic Barrier Guidelines.
24.11
Span Type, overhead sign structures required to cantilever or overhang the supports at
one or both ends shall utilize a standard IDOT (box) truss, support legs and
foundations. The selected truss shall be analyzed for the proposed end conditions and
loads. The truss member sizes may be modified, if necessary, to accommodate the
proposed overhang(s) and sign(s). The Designer shall modify and complete required
information in the latest IDOT base sheets for the selected overhead truss, supports
and foundations for inclusion in the Contract plans.
24.12
Sign structures that do not fall within the criteria of the latest Illinois Tollway Standard
Drawings and/or the latest IDOT Sign Structures Manual shall be designed in
accordance with the latest AASHTO Standard Specifications for Structural Supports for
Highway Signs, Luminaires, and Traffic Signals.
The Designer shall notify the Illinois Tollway in writing prior to beginning the design of a
non-standard sign structure.
March 2016
24-4
Illinois Tollway
Naming Convention
Overhead sign structures shall be identified on the plans using the following format:
Illinois Tollway Milepost Structure Type, Direction (Ramp)
TOLLWAY: EW = Reagan Memorial Tollway (I-88)
NS = Veterans Memorial Tollway (I-355)
NW = Jane Addams Memorial Tollway (I-90)
TS = Tri-State Tollway (I-294 & I-294/I-80)
TN = Tri-State Tollway (I-94)
ES = Edens Spur (I-94)
EO = Elgin-OHare Tollway (IL 390)
WA = West OHare Access (I-490)
MILEPOST: Two-decimal milepost to the tenth or hundredth if a mile post (i.e. 14.75)
SIGN TYPE: B = Bridge Mounted
C = Cantilever and Butterfly Type Trusses
T = Span Type Trusses, Monotube and ITS Gantry
DIRECTION: EB, SB, WB, NB - Inventory direction of the mainline roadway
RAMP:
EXAMPLE: TS38.40T,NB(R) for a span type truss located along the Tri-State Tollway
(I-294) northbound at milepost 38.40 on a ramp
24.14
The foundation details shown in the Illinois Tollway Sign Structure Standard Drawings
(Section F) and the ITS Gantry Base Sheets M-OHS-729 and M-OHS-730 are designed
and detailed based on the common cohesive soil conditions (silty or sandy clay) with an
average unconfined compressive strength (Qu) > 1.25 Tons/sq. ft.
The Design Section Engineer (DSE) shall conduct a subsurface investigation at each
overhead sign structure foundation to determine the actual soil conditions. Should the
investigation reveal soil properties less than average unconfined compressive strength
(Qu) = 1.25 Tons/sq. ft. or indicate the presence of rock, the DSE shall design and detail
the drilled shaft foundations to meet the actual site conditions and modify the Illinois
Tollway Sign Structure Standard Drawings and Base Sheets accordingly.
March 2016
24-5
Illinois Tollway
EXISTING SUPER
STRUCTURE
W6x12 VERTICAL
SIGN SUPPORT
SIGN PANEL
LUMINAIRE
W10x22 HORIZONTAL
VARIES
SIGN SUPPORT
W6x12 LUMINAIRE
SUPPORT
MARCH, 2016
FIGURE 24.8.1
ILLINOIS TOLLWAY
General
Shop drawings are detailed fabrication and erection plans prepared by the fabricator,
supplier or Contractor which are interpreted from the engineering drawings in the
Contract plans. When contracted, the Designer shall be responsible for reviewing the
shop drawings for compliance with the design plans and project specifications only.
It is the responsibility of the Engineer to ascertain that the fabricator is supplying the
items specified, while it is the Contractors responsibility to verify that all items are per
contract plan and specifications and fabricated to the correct dimensions. See Article
105.04(d) of the latest Illinois Tollway Supplemental Specifications. Approved shop
drawings shall be archived with the as-built plans for each project.
25.2
PPC IBeams
Elastometric Bearings
Anchor Rods
Fixed Bearings
Other project-specific items not included in this list may also require approved shop
March 2016
25-1
Illinois Tollway
Framing plan, showing general layout of the steel beams, cross frames, location
of field splices and marking scheme for identifying members.
The details of all splices, showing the number, size and type of bolts, hole
diameters, the type, size and length of all welds and a section showing the size
of all splice materials.
The details of all field connections, showing number, size and type of bolts, hole
diameters, and the locations where reaming is required.
The number, size and spacing of shear developers. The use of shop welded
shear developers is acceptable for embedded bearing plates and expansion
joints.
Verify ordinates and geometry at abutments, field splices and interior at piers.
The steel surface preparation and the type of shop and/or field coating to be
applied.
All notes that appear on the design plans shall be reflected on the shop
drawings.
March 2016
25-2
Illinois Tollway
The number, size and type of prestressing strands or rods, and the forces in
these prestressing elements.
The location and the details of lifting devices and of support points, if the beam
does not rest on its bearings while being transported.
The layout of the casting bed to be used for casting the prestressed beams.
All notes that appear on the design plans shall be reflected on the shop
drawings.
25.2.3 Bearings
At a minimum the following information shall be reviewed:
Location diagram, showing the general layout of the structure and the locations
of the bearings.
The details of the bearings, showing all materials, dimensions and welding.
Notes listing the material specifications for all parts of the bearings, and the
design and specifications used for the design of the bearings.
25.3
The Contractor and/or his supplier are responsible for designing and detailing the
following items, which shall bear the seal and signature of an Illinois Licensed Structural
Engineer. Shop drawings and computations shall be submitted for review and
acceptance by the Designer. Approved shop drawings shall be archived with the asbuilt plans for each project.
Mechanically Stabilized Earth (MSE) Retaining Walls, Soldier Pile and Lagging
Retaining Walls with facing and Sheet Pile and Tie-Back Retaining Walls with
facing.
March 2016
25-3
Illinois Tollway
Pedestrian/Bicycle Truss designs and shop drawings for structures crossing over
a state or federal route, placed on Illinois Tollway right-of-way, or having spans
150 ft. or longer, shall be submitted for review and approval. If these structures
are constructed by another governmental unit (IDOT, county, municipality, park
district, IL Dept. of Natural Resources, etc.), that agency is responsible for the
review and approval of the designs and drawings.
25.4
Miscellaneous Items
Shop Drawings for the following items need not be submitted for review unless specified
or special (non-standard) details are proposed for routine items:
Fabric Reinforced Elastometric Mats and/or steel anchor plates for the back of Integral
Abutments:
The fabricator shall furnish installation and detail drawings to the Contractor and
Engineer for field verification of locations and dimensions. These drawings shall
be included in the project record. Shop fabrication inspection is not required, and
the Engineers final acceptance may be based on proper fit and an overall visual
inspection of the finished product. The material supplier is responsible for
submitting samples to the BMPR for lot testing.
Bridge Railing & Drainage Systems:
Steel Bridge Rail, Aluminum Bridge Rail, Pedestrian/Bicycle Railing, PreFabricated Inspection Platforms, Scuppers, Drain Piping, Navigation Lights and
Mounting Hardware.
The fabricator shall furnish installation and detail drawings to the Contractor and
Engineer for field verification of locations and dimensions. These drawings shall
be included in the project record. Shop fabrication inspection is not required, and
the Engineers final acceptance may be based on proper fit and an overall visual
inspection of the finished product.
Standard design base sheet notes require permanent tubular steel bridge traffic
rail and rail posts to have Charpy-Vee Notch (CVN) toughness values certified by
test. Test results, along with mill certification documentation, are to be submitted
to the Engineer. CVN testing is not normally required for bicycle/pedestrian
railing. All steel for railing, bolts, anchor bolts and posts shall be domestic. Any
March 2016
25-4
Illinois Tollway
25.5
25.5.1 General
The Contractor shall submit structural steel erection plan to the Engineer and Designer
for each structure in the Contract, in accordance with Article 7.2.2 of this Manual and
Article 105.04 (c) of the Illinois Tollway Supplemental Specifications. Copies shall be
sent to any railroad company or public agency affected by the proposed erection
procedure for their review and comment. These plans shall be received at least 60 days
prior to the proposed beginning of erection. All comments or revisions required by the
Designer, railroad company, or public agency shall be incorporated in the final
submission, for review and acceptance by the Engineer and Designer.
25.5.2 Required Information
The following minimum information shall be placed on the erection drawings for each
individual structure. Erection procedures for twin bridges may be shown on the same
sheet.
Title block with contract number, design project number, project and structure
name and county.
Plan of the work area showing support structures, roads, railroad tracks, canals
or streams, utilities or any other information relative to erection.
Erection sequence for main members and secondary members (cross frames,
diaphragms, lateral bracing, portals, etc.), noting use of holding cranes or
temporary supports, falsework, and bents.
Capacity chart for each crane and boom length used in the work. Cranes lifting
over active railroad facilities shall have a minimum lifting capacity of 150 percent
of the lift weight.
March 2016
25-5
Illinois Tollway
Lift and setting radius for each pick (or maximum lift radius).
Bolting requirements, including the minimum number of bolts and erection pins
required to stabilize members during the erection sequence.
The method and location of temporary support for field spliced or curved beams,
including shoring, falsework, holding cranes, guys, etc. The designer shall
examine, but not approve details of temporary supports. The design, erection,
and stability of these supports shall be the sole responsibility of the Contractor.
For Complex Structures, geometric control including the elevations and positions
that will be monitored during construction to verify that the structural steel is
being erected according to plan.
No crane shall be operated in a manner that will exceed its rated capacity at any
radius as specified by the crane manufacturer.
The table or chart prepared by the crane manufacturer to describe the maximum
lift at all conditions of loading shall be posted in each crane cab in clear view of
the operator.
The Contractor shall be responsible for verifying the weight of each lift and for
insuring the stability of each member during all phases of erection.
Members shall be subject to only light drifting to align holes. Any drifting that
results in distortion of the member or damage to the holes shall be cause for
rejection of the member.
Field reaming of holes shall not exceed the amount permitted in Article 505.08(I)
of the Standard Specifications.
The final alignment and profile of the erected steel shall conform to the
requirements of the Contract Documents. Measurements and elevations shall be
taken to verify the requirements of the Contract.
March 2016
25-6
Illinois Tollway
General
When extensive repairs to a structural member appear necessary, to the extent that the
structural capacity of the member during construction may be in doubt, provisions shall
be made to temporarily support the member during construction. This also applies to
concrete member repairs, whether it is pneumatically applied mortar or formed concrete
repairs. The location of proposed temporary supports shall be indicated on the plans.
Refer to the latest edition of the Structural Services Manual by the IDOT Bureau of
Bridges and Structures. The manual contains information and guidelines for the types
of repairs most often required to adequately maintain typical bridge structures during the
service life. The Designer and/or Contractor are encouraged to use guidelines provided
in the above referenced manual in preparing final repair details associated with the
rehabilitation project.
The most common types of repairs/rehabilitation tasks associated with Illinois Tollway
projects are listed below, including applicable sections from the above referenced
manual.
26.2
March 2016
26-1
Illinois Tollway
Refer to Manual for the Evaluation and Repair of Precast, Prestressed Concrete Bridge
Products published by PCI. The Manual also addresses evaluation and repair for
damage caused by imperfections or damage occurring during production, handling,
transportation and erection. This Manual serves as a resource and a base for
developing repair options. The designer and/or Fabricator is required to prepare repair
procedures and details using guidelines provided in the above referenced manual while
applying sound engineering judgment. The repair procedures and details shall be
submitted to the Illinois Tollway for review and approval.
In addition to the types of damage discussed above and the normal deterioration due to
aging, collisions between over-height vehicles and bridges are becoming more
commonplace and can be catastrophic. Collision damage, however, is generally far
from catastrophic although sound repair techniques are critical if additional damage
(typically related to corrosion) is to be mitigated. A comprehensive study was recently
completed by NCHRP to develop criteria to evaluate whether to repair or to replace a
prestressed concrete girder damaged by a vehicular impact, identify the gaps in the
available information and practices related to repair of collision damage of prestressed
girders and prepare a recommended practice report guide. Results of the study are
presented in the NCHRP 20-07/Task 307 report, entitled Updated Research for
Collision Damage and Repair of Prestressed Concrete Beams, dated May 2012.
The primary deliverable of the NCHRP 20-07/Task 307 report is the Guide to
Recommended Practice for the Repair of Impact-Damaged Prestressed Concrete
Bridge Girders, which is included in Appendix A of the report. The Guide serves to
update the 1985 NCHRP Report 280: Guidelines for Evaluation and Repair of
Prestressed Concrete Bridge Members, which remains a primary reference for this
topic.
Nine repair techniques are described in the Guide of the NCHRP 20-07/Task 307
report; four are generally recommended as being practical for repairing impact damaged
prestressed concrete girders: externally bonded carbon fiber reinforced polymer
(EBCFRP); externally bonded post-tensioned CFRP (bPT-CFRP); post-tensioned steel
(PT-steel); and internal strand splicing. In addition, external repairs in combination with
strand splicing are discussed. The Designer is required to prepare repair procedures
and details using guidelines provided in the NCHRP 20-07/Task 307 reference, while
applying sound engineering judgment. The repair procedures and details shall be
submitted to the Illinois Tollway for review and approval.
26.3
Refer to Figures 26.3.1 through 26.3.4 regarding suggested details for repairing existing
aluminum sign trusses. These details are to be used as guidelines in preparing repair
plans for sign trusses. Figure 26.3.5 provides guidelines for installing damping devices
for existing aluminum trusses.
March 2016
26-2
Illinois Tollway
When resurfacing an existing approach slab, the surface of new overlay shall be string
lined to provide a smooth transition from the ends of bridge to the existing road.
Before resurfacing, the spalled areas of existing approach slabs shall be repaired with
partial-depth concrete patches and completely deteriorated areas shall be repaired with
full-depth patches. Top reinforcement bars exposed in repair areas that show a 50%
loss of section due to corrosion or that were damaged during concrete removal shall be
supplemented with additional bars equal to the area of the original deteriorated or
damaged bar(s) (see Figure 26.4.1). Bottom reinforcement bars exposed in repair areas
that show a 20% loss of section due to corrosion or that were damaged during concrete
removal shall be supplemented with additional bars equal to the area of the original
deteriorated or damaged bar(s).
Existing reinforcement bars that have been cut or damaged by the Contractor shall be
provided with supplemental bars at no additional cost to the Illinois Tollway. Otherwise,
supplemental bars shall be paid for as Reinforcement Bars or Reinforcement Bars,
Epoxy Coated.
Those areas of approach slabs showing settlement at the abutment backwall shall be
removed and replaced in accordance with the details shown in Figure 26.4.2. Existing
preformed filler joints at the bridge end of approach slabs shall be replaced wherever
possible with the detail shown in Figure 26.4.3.
26.5
See Figure 26.5.1 for suggested details for repairing eroded or damaged slope paving.
26.6
See Figures 26.6.1 through 26.6.4 for suggested details to temporarily repair metal arch
or half round culverts until they can be programmed for replacement or lining.
26.7
Bearing Repairs
Frequently, existing rocker bearings are found to be tilted and in need of adjustment.
The magnitude of the adjustment is determined by comparing the measured horizontal
displacement of the rocker with the theoretical displacement for similar temperature
conditions. No adjustment is necessary unless the measured displacement exceeds the
theoretical by inch or more. Adjustment is usually made by repositioning the sole
plate; however, if a bearing stiffener is present, the stiffener shall remain within the
middle third of the repositioned sole plate.
26.8
March 2016
26-3
Illinois Tollway
FRP shall not be used in conjunction with patching of bridge deck underside. Such
defects shall be scaled and left untreated, if they are minor and do not affect structural
capacity or addressed with full depth patches, if there are concerns with structural
capacity. Partial depth patching of bridge deck underside is not allowed.
26.9
Deck Drains
Repair plans for major maintenance projects on deck surface of a structure such as
overlay projects shall contain details to provide for elimination of existing deck drains, or
adjustment of existing deck drains to direct drainage away from the main load-carrying
member of the superstructure and substructure units.
.
March 2016
26-4
Illinois Tollway
MARCH, 2016
FIGURE 26.3.1
ILLINOIS TOLLWAY
SI
NGLE VERTI
CAL DI
AGONAL REPAI
RWI
THOUT GUSSET
MARCH, 2016
FIGURE 26.3.2
ILLINOIS TOLLWAY
DOUBLE VERTI
CAL DI
AGONAL REPAI
RWI
THOUT GUSSET
MARCH, 2016
FIGURE 26.3.3
ILLINOIS TOLLWAY
SI
NGLE VERTI
CAL DI
AGONAL REPAI
RWI
TH GUSSET
MARCH, 2016
FIGURE 26.3.4
ILLINOIS TOLLWAY
DOUBLE VERTI
CAL DI
AGONAL REPAI
RWI
TH GUSSET
March 2016
Illinois Tollway