Factory Acceptance Test (FAT) Guide
Factory Acceptance Test (FAT) Guide
APPENDIX H
403
The FAT team leader should present the list of requirements to the vendor
thmugh written correspondence prior to the scheduled FAT. The vendor may
wish to modify some items, but this should only be done with the agreement
of all team members. The final document may be referred to as the FAT
Preparation Document.
404
H.5 RESPONSIBILITIES
The general assignment of responsibilities should depend on the application.
Table H.1 indicates several scenarios of distribution. The FAT Preparation
Document should identify the general responsibility assignments. In all instances, the user should approve the test(s).
I Table H.l
Case No.
Software
Programming/
Configuration*
Responsible
for Conducting
Test
Hardware
Corrections
Software
Correction
s/u
s/ u
Case 1:The vendor is responsible for integrating the hardware and programming (or configuring) the software. The test is run by the vendor, and problems are corrected by the vendor. The user team members witness the test.
Case 2: Responsibilities are the same as Case 1 except the user team members
conduct the test, and the vendor corrects any problems found.
C u e 3: Responsibilities are the same as Case 2 except that the vendor team
members assist the customer in conducting the test.
405
If possible, the FAT team should be separated into two groups: one p u p
conducting the test; the second group correcting the problems identified by
the first. The benefit of this method is that the FAT may continue nearly
uninterrupted for one shift while problems are com:cted on the following
shift. This will require some overlapping of the hours of work of the two teams
to ensure information is transferred in a timely and accurate manner.
Each individual team inember should be assigned specific tasks during the
FAT. The FAT Preparation Document should define these task assignments as
clearly as possible.
H.7 DOCUMENTS
The purchase order for the system should list the documents required for the
test. An example of such a list follows:
System Functional Requirements Specification
System 1 / 0 List
Process Control Description
Control Logic Specification Sheets
Configuration Worksheets
Logic Flow Diagrams
Instrument Specifications
Process Flow Sheets
Graphic Design Drawings
Program Listings (Documented)
System Self-documentation Printouts
System Arrangement Drawings
Termination Lists
Vendor Manuals
Punch-list Form
406
Usage
Device
~~~~
Digital Multi-meter
DC m A Source
DC mV Source
IPulse G n e r a tor
Thermocouple or other
low-voltaac input simulation
1 Input
. p. u l s e T"m a l s
RTD sinlulation
(instrument simulation)
Bred kou t Box
Troubleshoot ddld
communication links
I
I
I
407