Design and Construction Standards Manual
Design and Construction Standards Manual
Standards Manual
Addendum to:
WSA 02 - 2002 Version 2.3 Sewerage Code of Australia
WSA 03 2011 Version 3.1 Water Supply Code of Australia
WSA 04 - 2005 Version 2.1 Sewage Pumping Station Code of Australia
WSA 07 - 2007 Version 1.1 Pressure Sewerage Code of Australia
TABLE OF CONTENTS
INTRODUCTION
Responsibilities
10
PART 3: CONSTRUCTION
12
14
15
15
15
PART 2: CONSTRUCTION
19
22
34
PART 3: CONSTRUCTION
35
36
37
37
PART 1: DESIGN
37
42
PART 3: CONSTRUCTION
43
45
Page 1 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
INTRODUCTION
Purpose and Scope
The following Water Services Association of Australia (WSAA) Codes and the WSAA
Product and Material Information Guides have been adopted by Grampians Wimmera
Mallee Water Corporation (GWMWater) and therefore apply to the design, construction
and maintenance of GWMWater water and wastewater infrastructure:
1)
2)
3)
4)
This Design and Construction Standards Manual describes the specific requirements of
GWMWater where the Codes refer to such requirements, or which alternative to use when
alternatives are offered in the Codes. This Manual is therefore an addendum to the Codes
and needs to be read in conjunction with them.
The Product and Material Information and Guidance documents are available on the
WSAA website (www.wsaa.asn.au). GWMWaters specific requirements for products and
materials are included in Part 2 of each section of this Manual.
Responsibilities
The term Developer refers to anyone who is responsible for the design and construction of
water and wastewater infrastructure. It refers to consulting engineers, contractors and
GWMWater personnel, as well as the owners of land being developed.
The term Infrastructure refers to constructed components of any development, project or
scheme. Developers are responsible for the design and construction process.
Alternative Products and Solutions
The WSAA Codes and this Manual essentially provide deemed-to-comply solutions for
the creation of GWMWater assets. Alternative solutions, practices, equipment and
methods will continue to evolve and offer opportunities to improve the creation of these
assets. GWMWater encourages any innovation that offers enhanced productivity and
serviceability. GWMWaters approvals process will consider innovative systems but
approval must be obtained before the system is installed.
It is the Developers responsibility to justify any deviation from the requirements set out in
the WSAA Codes and this Manual. If a variation is proposed to drawings which have been
Approved for Construction, the Developer is to obtain written approval prior to
construction.
GWMWater will only accept alternative products to those referred to at the WSAA website and this Manual if it can be demonstrated that such products comply with the
applicable standards or specifications and are equivalent to the products referred to.
Page 2 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 3 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Lot control
Maintenance hole
Maintenance shaft
Nature strip is used in Victoria instead of verge. It is the area between the
footpath and the kerb or road carriageway
Property connection sewer
Property service connection
Property sewer drain
Vertical riser
Page 4 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 5 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
150 mm
Tenements
Min.
Max.
2
221
6
208
11
196
16
186
22
178
28
170
35
164
42
158
49
152
61
143
225 mm
Tenements
Min.
Max.
18
23
29
36
43
51
59
73
90
113
145
186
609
580
553
530
510
492
475
446
422
401
374
339
A minimum 10% construction tolerance is to be allowed in the design grades. The number
of tenements to be serviced immediately as well as ultimately shall be considered.
Approval of proposed grades outside of these values will require engineering analysis.
4.6.3 (Pg 67) Vertical alignment of sewers - Minimum cover over sewers
As specified in Table 4.8 except the minimum cover is 600 mm in residential property not
subject to vehicle loading.
More severe requirements of the responsible road owner shall take precedence.
4.6.6.2 (Pg 72) Internal fall through MHs joining sewers of same diameter
Deflections through the MH of greater than 90 are not permitted.
5.3.1 (Pg 77) Methods of the property connection - General
Use the inspection opening interface method for the point of connection.
5.7 (Pg 78) Y - Property connection
Type Y Branch Connections are not permitted.
5.8 (Pg 79) Length of property connection sewers
For end-of-line road crossings, 100 mm property connection sewers up to 25 metres in
length are acceptable for individual properties only.
Page 6 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 7 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 8 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
1:500
1:1000
1:100
1:500
1:50
Page 9 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Joints
RRJ
Comment
SN 8 - DN 150 mm
SN 10 DN 100 mm
PVC - (Ribbed)
e.g. Ultra-rib
DICL (internal sealant and PE
sleeving)
Glass Reinforced Plastic e.g.
HOBAS
Polypropylene (Plain Wall)
Polypropylene (Profile)
e.g. SewerPro
Polyethylene (Plain Wall)
RRJ
SN 8 - DN 150 mm
RRJ
PN 20 - DN 150 mm
SP-SP
coupling
SN 10 - DN 150 mm
RRJ
SN 10 - DN 150 mm
RRJ
SN 10 - DN 150 mm
Welded
Note 1: The use of two or more types of pipe material on a single run of pipe between adjacent maintenance
holes is not acceptable.
Where soil conditions are likely to result in pipe movement following construction, the
maximum length of PVC pipe is limited to 3 metres for the following products
1. Plain Wall PVC Pipe
2. Ribbed PVC Pipe
The following Gravity Sewer Pipes are NOT approved
1. Steel Pipe e.g. Sintapipe
2. Fibre Reinforced Concrete pipe
3. ABS (Acrylonitrile Butadiene Styrene) Pipe
Solvent-welded PVC is not accepted
Non-return (reflux) valves are not to be used in gravity pipe systems.
Page 10 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 11 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
PART 3: CONSTRUCTION
12.1.4 (Pg 155) Quality - Inspection and test plans
The Developer shall provide GWMWater with a Notice of Commencement of Works at the
start of the construction. A representative of GWMWater will conduct pre-arranged
inspections associated with the excavation and pipelaying, construction of maintenance
holes and will conduct a final inspection audit before acceptance of assets.
The Developer, or their Consultant or Contractor, shall provide GWMWater with
certification of trench compaction, ovality and vacuum or air pressure test results. When
requested, the Developer shall provide GWMWater with quality assurance documentation
on activities such as materials handling and storage. All associated costs are to be borne
by the Developer, including rectification costs.
13.5.2 (Pg 159) Protection of other services
The Developer is responsible for satisfactorily repairing other Service Owner assets.
14.1 (Pg 164) Authorised products and materials
GWMWaters authorised products and materials are listed in Clause 10.6, above.
14.5.10 (Pg 167) Products and materials - Repair of blemishes
Sulphate resistant cement (with 25-30% total fly ash, by weight as cement replacement) is
to be used for repairs of all maintenance structures.
15.2 (Pg 169) Limits of excavation
Where minimum cover cannot be achieved alternative proposals are to be approved and
specified on the design drawings.
20.3.1 (Pg 183) Compaction of embedment - Methods
Flooding compaction of bedding material around pipe is not permitted.
21.1.3 (Pg 186) Compaction of trench fill
The Developer is required to specify the method of compaction used to achieve the
minimum compaction density index as outlined in Section 22.3 prior to approval of the
Design Drawing.
22.1 (Pg 188) Acceptance testing - General
The methods of rectification are to be approved by GWMWater.
22.3.1 (Pg 188) Compaction testing - General
Final certification from the NATA accredited tester and the location of all tests will be
required to demonstrate that the specified compaction was achieved at all test locations.
Page 12 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
SEW-1204
SEW-1206
SEW-1208
SEW-1300
SEW-1301
SEW-1302
SEW-1303
SEW-1304
SEW-1307
SEW-1314
Amendment
Add to note 2: Inspection opening to be located in serviced property.
This connection type is not used by GWMWater
Y Branch Connections are not permitted
Add note 5. Use marker tape on all property connection ends.
Delete note in Material Column of tables Bedding may be omitted if trench base is
granular sand or gravel of suitable grading.
Add Pipe embedment aggregates to be according to the following table:
Sieve Analysis Percent Passing
(Test Method Australian Standard 1141.11.1-2009 (Washed))
Sieve Size
Percent Passing Range
6.7mm
100
4.75mm
90-95
3.35mm
65-70
2.36mm
35-40
1.18mm
10-15
0.60mm
5-10
0.30mm
0-5
0.15mm
0-2
Add note 9. Type 10 support is not approved for plastic pipe.
Add to note 2. Concrete bulkheads subject to GWMWater approval.
Add note 8. Vertical risers subject to GWMWater approval.
Add note 13. Conversion slabs are not accepted by GWMWater.
Add note 10. Conversion slabs are not accepted by GWMWater.
Add note 9. A rocker pipe is required between a MH and all sewers connected to
the MH. The length of the rocker pipe shall be 600 mm for PVC and PP pipes, and
1,500 mm for DI and GRP pipes.
Add note 9. External drop junctions are not permitted by GWMWater.
Add note 10. A rocker pipe is required between a MH and all sewers connected to
the MH. The length of the rocker pipe shall be 600 mm for PVC and PP pipes, and
1,500 mm for DI and GRP pipes.
Add note 7. Deflections through the MH of greater than 90 are not permitted by
GWMWater without written approval.
Add note: 5. Step irons and ladders for maintenance holes are not permitted by
GWMWater.
Add note 6. Riser shaft cap to be screw type.
Page 14 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
4.3.2 (Pg 86) Ductile Iron Pipeline Systems Sizes and configurations
Pre-tapped connectors are not required.
5.2.4 (Pg 100) Reticulation design for water quality Reduced size mains
In reference to Fig 5.2, for courts, a closed loop of DN63 HDPE pipe is required. Fire
hydrants shall be installed before the loop on DN100 pipe.
5.4.1 (Pg 102) Location of water mains - General
Easements are required for water mains in private property.
5.4.2 (Pg 102) Location of water mains Water mains in road reserves
Where pipelines are to be constructed beneath existing or proposed road pavements any
of the following pipe materials shall be used:
1. Ductile iron cement lined (DICL) PN 20 pipes.
2. Modified PVC PN 15 Series 1 or PN 16 Series 2 pipes.
3. Oriented PVC PN 16 Series 2 pipes.
The pipes shall extend at least 500 mm behind the back of the kerb, or if there is no kerb, at
least 500 mm beyond where a future kerb is expected to be, i.e. beyond the road shoulder,
or open drain.
The use of these pipe materials shall apply to both the lateral crossing of roads and
longitudinally along the road or shoulder.
The minimum depth of cover beneath existing or proposed road pavements shall be 750
mm, or greater if required by the road authority.
5.4.4 (Pg 104) Location of water mains Water mains in easements
The Developer shall be responsible for all costs associated with the acquisition of
easements that are required within the development.
5.4.11 (Pg 110) Location of water mains Crossings of creeks or drainage reserves
It is the responsibility of the Developer to determine from the relevant Catchment
Management Authority (CMA) the design requirements for crossing the river, creek or
drainage reserves.
5.11 (Pg 120) General design Property services
Tapping of water mains greater than DN 300 is not permitted.
A single service to every property is required.
Property services are to be provided for each dwelling unit (e.g. house, unit, apartment) at
the front of the property and at right angles to the water main.
5.11.2 (Pg 121) Property services - Connections to water mains
Page 16 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
In rural areas, stop valves are to be installed in accordance with the GWMWater Rural
Pipeline Design Specification.
8.8.8 (Pg 218) Hydrants Hydrant spacing
The maximum hydrant spacing in urban districts shall be 90 m unless otherwise agreed by
the relevant local Council in consultation with GWMWater.
8.8.9 (Pg 219) Hydrants Hydrant location
In rural areas, above ground-type hydrants are to be installed in accordance with the
GWMWater Rural Pipeline Design Specification.
Fire plugs are to be marked FP or Fire Plug as approved by GWMWater in consultation
with the relevant Council.
The type of hydrant cover for non-trafficable conditions shown in Fig 8.33 is not approved
by GWMWater.
8.11.2 (Pg 227) Appurtenance location marking - Marker posts and plates
If marker posts for water meters are required by GWMWater, they shall be blue-coloured
with white caps, with the letter M on a marker plate in accordance with the Reference
Standard Drawing.
9.2.1 (Pg 228) Design drawings - General
Drawings shall be provided in AutoCAD format (with .dwg file extension) and PDF
format (with .pdf file extension). A hard copy shall also be provided.
Page 18 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
PART 2: CONSTRUCTION
11.2 (Pg 241) Order of construction, testing and commissioning
The Developer shall provide a Notice of Commencement of Works to GWMWater at least two
working days prior to the start of the construction. The Works Quality Controller will
conduct inspections associated with the excavation and pipe laying and will conduct a
final inspection audit before acceptance of assets.
The Developer, or their Consultant or Contractor, shall provide water pressure test results
and certification of trench compaction and materials handling and storage. All associated
costs are to be borne by the Developer, including rectification costs.
11.5.1 (Pg 242) Protection of property and environment Protection of other services
GWMWater does not provide information to the Dial Before You Dig service. The
Developer will need to engage GWMWater staff to locate underground services.
12.1 (Pg 250) Authorised products and materials
Only the following pipe materials are permitted within water supply systems:
Material
PVC-U (Series 1)
PVC-M (Series 1)
PVC-O (Series 2)
Steel
DICL (internal sealant and
PE sleeving)
HDPE
Joints
RRJ
RRJ
RRJ
Various
RRJ
Electrofusion or
Welded
Note: Pressure class is to be at least 1.5 times the maximum design pressure.
Any proposed materials or jointing systems not in this table need to be approved by
GWMWater before acceptance.
The following Pressure Pipes are not approved:
6. ABS (Acrylonitrile Butadiene Styrene) Pipe below ground
7. MDPE (Medium Density Polyethylene) rural poly pipe
Approved Pressure Pipe Fittings:
1. Ductile Iron (fusion coated or thermal bonded polymeric coated) - min. pressure
class PN 16
2. MSCL Welded or Elastomeric Seal (Fusion coated and factory tape applied external
coatings)
3. Electrofusion welded PE100 PN16 polyethylene.
Page 19 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
GWMWater requires spigot-socket elastomeric seals for PVC pipes. Elastomeric seals shall
be in accordance with supplier recommendations.
13.1 (Pg 255) Excavation - Precautions
The Developer is required to comply with the Occupational Health & Safety Legislation
and GWMWaters Occupational Health & Safety Policy and Procedures.
15.13 (Pg 269) Valves, hydrants and surface boxes and fittings
Surrounds for valves shall be painted yellow using road surface marking paint.
** The Country Fire Authority requires surrounds for hydrants to be white.
15.18 (Pg 270) Appurtenance location marking
If marker posts for isolation valves, scour valves and air release valves are required by
GWMWater, they shall be yellow-coloured with black caps, with black letters on white
marker plates in accordance with the Reference Standard Drawing.
19.3.1 (Pg 283) Compaction testing - General
The Developer is required to specify the method of compaction used to achieve the
minimum compaction density as specified in Table 19.1 prior to approval of the Design
Drawing.
Final certification from the NATA accredited tester and the location of all tests will be
required to demonstrate that the specified compaction was achieved.
19.4.1 (Pg 284) Hydrostatic pressure testing - General
The Contractor must supply all fittings necessary to execute the test.
20.1 (Pg 287) Disinfection - Application
Disinfection of new water mains and existing water mains taken out of service during
construction is required for all sizes of main.
22.1 (Pg 290) Connections to existing water mains - General
The Developer is required to give GWMWater a minimum of five (5) working days notice
before a connection to existing water mains is to proceed. This is to allow for the
resourcing of GWMWater operational staff and the provision of Interruption to Water
Supply notices to effected customers.
The interruption time is for a maximum of three (3) hours.
24 (Pg 295) Work-As-Constructed details
Work-As-Constructed drawings and documentation are required before Practical
Completion can be issued by GWMWater.
Page 20 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Drawings shall be provided in AutoCAD format (with .dwg file extension) and PDF
format (with .pdf file extension). A hard copy shall also be provided.
These drawings shall include the information as for the Design Drawings (Clause 9.2.4 [Pg
229] of the Code) amended to reflect the actual construction details.
Asset attribute data is to be captured for all assets created. Data is to be presented in a
Microsoft Excel spreadsheet. A template for this spreadsheet is available from the
Development Officer at the time plans are approved for construction.
Page 21 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
The design shall ensure that the level of hydrogen sulphide discharge from maintenance
holes is not likely to cause odours.
2.12 (Pg 57) Concept design - Access
The Developer shall confirm vehicle access requirements with GWMWater.
2.14 (Pg 58) Concept design - Signage
Signs identifying confined spaces must be provided. Each sign must display the
classification of the confined space and must be located in a prominent position adjacent to
the entry of the confined space.
No Parking signs may also be required.
2.17.1 (Pg 58) Commissioning plan - General
The Developer is to submit a commissioning plan at the concept design stage.
3.2 (Pg 62) Design tolerances
The required coordinate system is MGA Zone 54 for horizontal alignment in metres.
4.2.2 (Pg 70) Corrosion protection Concrete surfaces
Sulphate resistant concrete shall be used to provide corrosion protection. If no educt vent
is installed, exposed concrete surfaces in the wet-well shall be epoxy coated with Dulux
Luxepoxy 4 or an approved equivalent.
4.2.3 (Pg 70) Corrosion protection Metallic surfaces
Refer to Clause 16.3.1 in this Manual for details on discharge pipework and all other metal
work in the wet-well and valve chamber.
5.2.1 (Pg 71) Pumping station design Site selection
The Developer shall be responsible for liaising with all stakeholders to determine their
requirements, if any, at the preliminary design stage. Stakeholders may include the
relevant council, CMA, EPA, DSE, VicRoads, electricity authority and other interest
groups. Their requirements are to be included in the preliminary design presented for
approval of site location.
Avoid locating a pump station near overhead powerlines.
The design shall address environmental impacts and buoyancy effects.
A geotechnical investigation of the proposed site is required.
5.3.2 (Pg 73) Pumping station design - Inlet MH
Grit chambers, screens or isolation valves for inlet maintenance holes are not required.
Page 23 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 24 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 25 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
+50 C
-10 C
95 %
20 years
The Works shall function correctly within the supply system limits defined in the
Victorian Electricity Distribution Code (see www.esc.vic.gov.au ). The Works shall comply
with the requirements of the Victorian Service and Installation Rules (see
www.victoriansir.org.au).
7.2.5 (Pg 95) Power supplies - Emergency power
The Developer is to consult with GWMWater as to the need for an on-site emergency
power supply for any particular pumping station.
7.2.9 (Pg 96) Power supplies Power factor correction
Electrical and electronic equipment shall be capable of operating over the full range of
power supply quality defined in the Victorian Electricity Distribution (VEC) Code (see
www.esc.vic.gov.au), or appropriate power conditioning shall be provided to ensure the
correct function of the equipment.
As per the VEC Code:
11. The site power factor must be kept within the specified limits or a power factor
correction shall be provided if required to comply with this requirement.
12. The site harmonic distortion currents must be kept below the specified limits.
13. The three-phase supply phase currents must not deviate from the average of the
three-phase currents by more than 5%.
14. The site electrical equipment shall not cause voltage fluctuations at the point of
common coupling greater than that specified.
7.3.1 (Pg 96) Power and control cubicle - Design
The power and control cubicle shall:
15. be fabricated from 3.0 mm marine grade aluminium or approved equivalent.
16. be externally powdercoated Colorbond Rivergum Green.
17. be internally painted white
18. be continuously welded with radiussed corners and all visible joints ground smooth.
19. have stiffening provided to panels and doors where necessary to prevent distortion
or drumming.
20. have doors that swing open to 180and can be fixed in the 90 and 180 position.
21. have pad-lockable or key-lockable doors as advised by GWMWater.
Page 26 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
22. be level and plumb and bolted to a concrete plinth at least 75 mm high that is of
adequate thickness to support the switchboards.
23. have a minimum free space of 400 mm high by 600 mm wide by 300 mm deep for
the installation of the Remote Telemetry Unit.
24. have a minimum of 20% additional free useable space on the mounting plate for
future works.
25. be appropriately ventilated for when the ambient temperature inside the
switchboard is likely to exceed the rated value of any of the components installed
inside the switchboard.
26. have correctly sized cable glands fitted at all cable entry points.
27. be vermin proof.
28. have power mains cable entry from the bottom.
29. have a metal pocket inside the control door to hold an A4 binder.
30. be located so that doors can open safely and provide a safe working area away from
the wet-well.
A minimum of three conduits shall enter the wet well from the cubicle - one conduit for
pump power cables, one conduit for control cables and wet well lighting, and one conduit
for communication and instrumentation cables. The minimum conduit size shall be 63 mm
diameter for power and 40 mm diameter for control and communication. Conduits shall
be sealed to prevent gas entering the cubicle.
7.3.4 (Pg 98) Power and control cubicle - Lighting
Lights shall be provided in the wet-well (250 watt), and inside each cabinet of the cubicle.
When required, external lighting (80 watt) shall be installed overhead on a three metre
pole.
8.1 (Pg 99) Control and telemetry system General
Refer to Clause 8.6.1 in this Manual for details on telemetry.
8.3.1 (Pg 99) Pumping control - Control design
Refer to Clause 8.8.5 in this Manual for details on sensors.
8.3.2 (Pg 100) Pumping control - Control switches
The pump selection switch does not require a Flush with Manual position.
8.3.3 (Pg 100) Pumping control - Control systems
Add to (a):
The telemetry RTU shall be as per Clause 8.6.1 in this Manual.
Page 27 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 28 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 31 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 32 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 33 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Joints
RRJ
RRJ
RRJ
PN 20 - DN 100 mm
Welded
PN 12.5 - DN 100 mm
Comment
accepted on project by project
basis
Note: Pressure class is to be at least 1.5 times the maximum design pressure.
The following Pressure Pipes are NOT approved
76. Steel Pipe
77. ABS (Acrylonitrile Butadiene Styrene) Pipe
78. PVC-U Pipe
79. Glass Reinforced Plastic Pipe
Approved Pressure Pipe Fittings:
1. Ductile Iron (fusion coated or thermal bonded polymeric coated) - min. pressure
class PN 16
2. MSCL Welded or Elastomeric Seal (Fusion coated and factory tape applied external
coatings)
3. Electrofusion welded PE100 PN16 polyethylene.
GWMWater requires spigot-socket elastomeric seal PVC for all sewerage districts.
Page 34 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
PART 3: CONSTRUCTION
22.1 (Pg 235) Telemetry system Compliance with Authorities, statutes, regulations and
standards
GWMWater will advise on requirements to connection to its SCADA network.
30.14 (Pg 254) Pipe laying and jointing - Location markers
Isolation valves covers for all pressure mains shall be painted using orange road marking
paint.
If required by GWMWater, location marker posts for scour valves, gas release valves and
isolation valves shall be orange coloured with black coloured tops with marker plates in
accordance with Reference Standard Drawing WAT-1300.
31.1 (Pg 256) Wet-wells and maintenance holes - General
A 150 mm drainage layer shall be established below the in-situ base slab or the precast
concrete base slab, of compacted, approved coarse (approx. 20 mm) screenings.
34 (Pg 263) Connection to existing gravity sewers
The Developer shall not commence work which involves entry into live sewer mains or
maintenance structures until approval is given by the Works Quality Controller.
A minimum of two working days notice is required of intention to make a connection to
the existing sewer network.
36.3.1 (Pg 267) Compaction Testing - General
Final certification from the NATA accredited tester and the location of all tests will be
required to demonstrate that the specified compaction was achieved at all test locations.
37.1 (Pg 277) Commissioning - General
The Works Quality Controller or delegate must be in attendance for the commissioning.
Page 35 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Amendment
Buried valves are not permitted - a valve chamber is required.
Grit collection is not required.
Grit collection is not required.
Add note 11. The minimum cover to the top of the pressure main shall be
1000 mm in nature strips and footpaths and 1200 mm in roadways.
Page 36 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 37 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 38 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
The location of all isolation valves shall be in the nature strip at least 300 mm from any
kerb or trafficable area (if no kerb), unless otherwise approved. Where isolation valves are
installed at Tees, they should be located flush against the Tee, else at the nearest practical
location in the nature strip. The locations should minimise pedestrian hazards by avoiding
clustering of surface fittings in the footway at intersections.
5.4.3 (Pg 75) Isolation valve covers and surrounds
Valve box covers shall be painted orange with SEWER VALVE embossed (not painted),
and shall be rated for non-vehicle or vehicle loading as appropriate to the location.
5.6.2 (Pg 77) Flushing points and scours
Add to (c): On pressure mains with no customers (for example when transferring to a
treatment plant) an interval of greater than 500 m may be permitted.
Lockable covers are required for all flushing points in accordance with GWMWater
requirements, which shall be rated for non-vehicle or vehicle loading as appropriate to the
location.
5.7 (Pg 78) Flow meters
Depending on the types and numbers of property serviced GWMWater may require a
flow meter to be installed to collect system performance data. The Developer shall be
responsible for the costs of installation of the GWMWater approved flow meter.
6.1.1 (Pg 79) Property sewer service design
GWMWater requires Design Drawings to be submitted showing the on-property
components for each property as per drawing PSS 1100.
6.3 (Pg 79) On-property design - Vacant lots
Pressure sewer laterals shall not be installed from the pressure sewer main to vacant land
until the lot is developed.
6.5 (Pg 82) Design and layout of new on-property components
GWMWater will own and maintain on-property components in accordance with its
Servicing of Subdivisions and Developments policy.
Design of the property discharge line alignment shall be:
87. Aligned parallel to property boundaries or road frontage.
88. Located to maintain adequate clearance from structures.
89. Located to allow easy access for repairs and maintenance.
Page 40 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 41 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 42 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
PART 3: CONSTRUCTION
13.5.1 (Pg 124) Protection of people, property and environment Safety of people
The Developer is required to comply with the Occupational Health & Safety Legislation
and GWMWaters Occupational Health & Safety Policy and Procedures.
13.5.3 (Pg 125) Protection of people, property and environment Dis-used / Redundant
sewers, drains and tanks
The property owner is responsible for removing or decommissioning disused sewers,
sanitary drains and septic tanks.
13.6 (Pg 128) Affected party notifications
The Developer shall not commence work which involves entry into live sewer mains or
maintenance structures until approved by the Works Quality Controller. A minimum of
two working days notice of the connection being made to the existing sewer is required.
15.1. (Pg 133) Compliance with authorities, statutes, regulations and standards
Only electricians registered with the Office of the Chief Electrical Inspector shall install the
electrical equipment.
A Certificate of Electrical Safety shall be provided for the electrical installation work.
All work shall be carried out in accordance with AS/NZS 4836 Safe Working on Low-Voltage
Electrical Installations and the Office of the Chief Electrical Inspectors Code of Practice for
Safe Electrical Work on Low Voltage Electrical Installations (see www.esv.vic.gov.au ).
18.5 (Pg 140) System installation and jointing - Trenchless installation
Pipes installed by boring shall be of continuous length without joints.
18.7 (Pg 140) Thrust and anchor blocks and restrained joints
Thrust blocks are required at unrestrained joints including horizontal and vertical bends,
tees, crosses, dead ends and reducers. Timber blocks are not accepted. Recycled plastic
blocks may be used for pipes up to and including 110mm nominal diameter.
18.8 (Pg 140) Pressure sewer laterals, property boundary assemblies
GWMWater shall approve of the tapping process and fittings.
18.10 (Pg 141) Pipeline tracer wires and detectable marking tapes
For pipes installed by open trenching, marker tape with stainless steel tracer wire shall be
located 150 mm above the pipe in accordance with WSA PS318 (refer www.wsaa.asn.au ).
Page 43 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
Page 44 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.
PSS-1001
PSS-1007
PSS-1101
PSS-1102
Amendment
Add note 6. Refer to clause 9.2.2 in this Manual for minimum cover requirements.
Add Pipe embedment aggregates to be according to the following table:
Sieve Analysis Percent Passing
(Test Method Australian Standard 1141.11.1-2009 (Washed))
Sieve Size
Percent Passing Range
6.7mm
100
4.75mm
90-95
3.35mm
65-70
2.36mm
35-40
1.18mm
10-15
0.60mm
5-10
0.30mm
0-5
0.15mm
0-2
Add note 7. Concrete encased pipe is not permitted.
Add note 8. Lockable covers are required for all flushing points.
Add note 4. GWMWater responsibility for components is defined in Clause 6.5 in this
Manual.
Add note 8. Lockable covers are required for all boundary kits.
Page 45 of 46
Print Date: 28 May 2012
The controlled copy of this document is available on the intranet. Printed copies are only current as of the print date.