Merritt-Chapman & Scott Corporation v. Pennsylvania Turnpike Commission, 387 F.2d 768, 3rd Cir. (1967)
Merritt-Chapman & Scott Corporation v. Pennsylvania Turnpike Commission, 387 F.2d 768, 3rd Cir. (1967)
2d 768
Martin S. Michelson, Michelson & Kane, Hartford, Conn. (J. Paul Kane,
Hartford, Conn., McNees, Wallace & Nurick, by Francis B. Haas,
Harrisburg, Pa., on the brief), for appellant.
Robert L. Rubendall, Metzger, Hafer, Keefer, Thomas & Wood,
Harrisburg, Pa., for appellee.
Before HASTIE, FREEDMAN and SEITZ, Circuit Judges.
OPINION OF THE COURT
FREEDMAN, Circuit Judge.
The district court granted defendant's motion to stay the action pending
arbitration. From this order plaintiff has appealed. We have held that such an
order in an action at law is appealable as an interlocutory injunction under 28
U.S.C. 1292(a)(1), although it is not a final judgment. Kirschner v. West
Company, 300 F.2d 133 (3 Cir. 1962).
I.
4
Plaintiff contends that its claims are not within the scope of the arbitration
provision of the contract. The provision is comprehensive in its inclusion of the
controversies which must be submitted to arbitration. It provides for what
amounts to an appeal to a Board of Arbitration taken within fifteen days after
the decision of the Chief Engineer on claims submitted to him in writing.1 The
claims which are thus made subject to arbitration are described in the contract:
"All claims for additional compensation, or for damages, arising out of this
contract or in any manner related thereto, or any breach of said contract,
including claims for additional compensation for any work performed which
was or was not covered by the approved drawings, specifications or contract, or
for any other cause, including damages for delay".2
This language is very broad and includes the present claims which are "for
additional compensation" and "damages", and clearly are in some manner
"related" to or arise out of the contract, and also fall within the description of
claims for additional compensation "for any other cause, including damages for
delay". They are not excluded from the arbitration provision because they are
alleged to have been occasioned by fraud or negligence or unwarranted
interference by the defendant.3
We therefore approve the conclusion of the district court that the subject matter
of this action falls within the scope of the arbitration provision of the contract.
II.
7
Plaintiff argues that its claim of fraud in the inducement of the contract
prevents the use of arbitration to decide the question, because if fraud is proven
the entire contract, including the arbitration provision, would fall.
The district court held that a number of specific provisions of the contract
The district court held that a number of specific provisions of the contract
placed upon plaintiff complete responsibility for the soil conditions which
might affect the nature of the work and therefore barred a claim of fraud or
negligence against defendant. Evidently the parties in their briefs called the
district court's attention to what they deemed to be controlling provisions of the
contract, although the record before us contains merely the complaint and the
motion to stay the proceedings pending arbitration. But since the district court
held that the action should be stayed pending arbitration we assume that it did
not decide the important question of fraud but left it to be determined by the
Board of Arbitration.
10
We conclude, therefore, that either under federal or Pennsylvania law the claim
of fraud in the inducement of the contract is not enough to prevent the
invocation of the arbitration provision of the contract.
III.
11
Since the claims asserted in the action fall within the arbitration provision of
the contract it was proper for the district court to grant defendant's motion to
stay the proceeding pending arbitration.
12
The district court indicated that it took this action by virtue of the Pennsylvania
Arbitration Act of April 25, 1927,6 2 of which provides that where a suit is
brought on an issue which is referable to arbitration, "the court in which such
suit is pending * * * shall * * * stay the trial of the action" until arbitration is
had in accordance with the agreement.7 At this point we are presented with a
serious problem regarding the jurisdiction of a federal court to act under this
provision and the extent to which such action might rest under the substantially
similar provision of 3 of the United States Arbitration Act.8 The federal
statute applies only to contracts evidencing "a transaction involving
commerce".9 It is therefore inapplicable to the present case if there was no
commerce involved in the contract. Bernhardt v. Polygraphic Company of
America, Inc., 350 U.S. 198, 76 S.Ct. 273, 100 L.Ed. 199 (1956); see also
Prima Paint Corporation v. Flood & Conklin Manufacturing Company, supra.
The jurisdictional allegations of the complaint are founded on diversity of
citizenship and make no reference to commerce. Defendant's motion to dismiss
asserts no other basis for jurisdiction, nor does it make any claim that the
contract between the parties constituted a transaction involving commerce.
However much we may speculate on what may have been the nature of the
performance required by the contract, it is impossible for us to determine on
appeal whether the United States Arbitration Act applies. For to do so would
require us to make an initial factual determination whether the contract
evidenced "a transaction involving commerce" within the meaning of 2 of the
Act.
13
jurisdiction,13 because we were enforcing the contract which the parties had
made rather than the Pennsylvania statute which they had contracted should
apply.
14
15
16
We hold, therefore, that the district court had power to stay the action pending
arbitration.
IV.
17
18
The present record affords no foundation for any sound judgment regarding the
qualification of the Consulting Engineer to act as a member of the Board of
Arbitration or to designate another engineer as a member in his place.
Moreover, the requirement of arbitration would not fail even if the Consulting
Engineer is disqualified to act directly and to designate another engineer in his
place. Here again, however, we encounter the difficulty which we have already
discussed. The United States Arbitration Act, 5,16 provides for the filling of
vacancies in the office of arbitrator by the courts. But the absence of a finding
that there is here involved a transaction involving commerce makes it
impossible to justify the filling of the vacancy by a district court under the
United States Arbitration Act. The Pennsylvania Arbitration Act of 1927, 4,17
contains the same authority with the additional express specification of the
disqualification of an arbitrator to sit as one of the reasons for which the court
may appoint an arbitrator. There is no doubt of the power of the Pennsylvania
courts to fill a vacancy in the office of arbitrator under this provision. See J. M.
Davis Co. v. Shaler Twp., 332 Pa. 134, 2 A.2d 708 (1938). Bias or
disqualification of an arbitrator therefore does not by itself require the
invalidation of an arbitration provision. But here arises again the limitation
created by 18 of the Pennsylvania statute in defining "court" as the common
pleas court of the county having jurisdiction of the parties or the subject matter.
19
At this stage of the proceeding, however, we are not called upon to determine
the power of the district court to disqualify the Consulting Engineer or an
appointee whom he may designate, or to fill a vacancy.18 For the attack on the
Consulting Engineer is directed only to the validity of the arbitration provision.
There has been no application to disqualify the Consulting Engineer and
consequently no request that the court fill a vacancy in the office of arbitrator.
The appeal before us is from the granting of the stay of proceedings and not
from a refusal to disqualify the Consulting Engineer or to appoint a successor to
him.
20
We conclude, therefore, that the stay of the action in the district court pending
Notes:
1
Section 1.9.9
See Robert Lawrence & Co. v. Devonshire Fabrics, Inc., 271 F.2d 402, 410-411
(2 Cir. 1959), cert. granted, 362 U.S. 909, 80 S.Ct. 682, 4 L.Ed.2d 618, cert.
dismissed, 364 U.S. 801, 81 S.Ct. 27, 5 L.Ed.2d 37 (1960); Maxwell Shapiro
Woolen Co. v. Amerotron Corp., 339 Mass. 252, 158 N.E.2d 875 (1959)
It was presented but not decided in Jefferies v. Tucker, 7 D&C2d 172 (C.P.
Phila.), aff'd, 387 Pa. 234, 127 A.2d 657 (1956). There are, of course, certain
issues, such as the existence of any agreement at all between the parties, which
by their very nature cannot fall within the scope of arbitration. See Goldstein v.
International Ladies' Garment Workers Union, 328 Pa. 385, 196 A. 43 (1938)
9 U.S.C. 3
2, 9 U.S.C. 2
10
11
Cf. Gerr v. Emrick, 283 F.2d 293, 297-298 (3 Cir. 1960) (construing "proper
courts at the county of Dauphin" to include federal district court); Markham v.
City of Newport News, 292 F.2d 711, 712-713 (4 Cir. 1961)
12
See also Formigli Corp. v. Alcar Builders, Inc., 236 F.Supp. 586 (E.D.Pa.1964)
13
14
Section 16 provides:
"The provisions of this act shall apply to any written contract to which the
Commonwealth of Pennsylvania, or any agency or subdivision thereof, or any
municipal corporation or political division of the Commonwealth shall be a
party."
15
16
9 U.S.C. 5
17
18
See Formigli Corp. v. Alcar Builders, Inc., 236 F.Supp. 586 (E.D.Pa.1964)