Equipment Program For Well Completion
Equipment Program For Well Completion
Major equipment systems used to complete oil and gas wells include:
Subsurface packers,
Subsurface flow control and safety valves,
Subsurface accessories,
Tubing and
Wellhead equipment.
Components of each of these systems and their functions will be described here.
69
3.1 Packers
A packer may be defined as a subsurface tool used to provide a seal between the
tubing and the casing of a well to prevent the vertical movement of fluids past this
sealing point.
Packers are used for the following reasons:
BASIC MECHANICS
For a packer to perform its designated function, two things must happen. A cone must
be driven behind a tapered slip to force the slip out and into the casing wall. A
packing element must then be compressed to affect a seal against the casing wall. The
two most important basic components of packer construction are then obviously the
slips and the sealing element.
Packer slips can be unidirectional or designed to resist force from either direction
(Fig. 3.1).
Sealing elements may be of either one-piece construction, or composed of multiple
elements of different degrees of hardness.
PACKER TYPES
There are three basic types of production packers:
Mechanical set,
Hydraulic-set and
Permanent.
All packers fall into one of, or a combination of, these three classifications. Selection
of one type in preference to another for a given production application should be
based on design for those parameters critical to the successful performance of this
equipment in a particular completion situation. Select the packer that will most
economically satisfy the conditions dictated by each individual completion situation.
70
71
TENSION-SET PACKERS
1. Setting
Tension-set packers (Fig. 3.3) are set by pulling tension on the tubing.
2. Retrieving
With most varieties, release is accomplished by simply slacking off on the
tubing. Most models also have some form of "emergency release" mechanism.
3. Selection Considerations
Tension packers are excellent for use in reasonably shallow wells where
moderate differential pressures from below are anticipated. Pressure from
below only serves to increase the setting force on the packer.
72
These packers are often used in water injection wells, and in wells where
stimulation work is planned. They receive frequent use in shallow wells where
available tubing weight is not sufficient to compress the packing element of a
weight-set packer.
73
ROTATIONAL-SET PACKERS
1. Setting
Tubing rotation obviously plays a major role in setting and retrieving
rotational-set packers. Once set, compression and pack-off are mechanically
"locked in". Upward or downward movement of the packer is prevented
regardless of application of weight or tension via the tubing.
Figure 3.4 shows a typical rotational-set packer. Setting can be accomplished
by weight-assisted rotation, or by rotation alone.
2. Retrieving
Right-hand rotation is required to retrieve the packer.
3. Selection Considerations
A rotational-set packer can be used to isolate bad order casing in a pumping
well and, by applying tension, serve also as a tubing anchor-catcher.
In water-flood injection wells, the use of a rotational set packer permits
landing of the tubing in a neutral weight state. This eliminates the possibility
of unseating the packer due to elongation of the tubing, or of parting due to
contraction.
Rotational-set packers are excellent for use in shallow to medium depth
straight holes where high differential pressures are not expected. Their biggest
disadvantage or drawback is generally felt to be that they must be released by
rotation of the tubing string. Solids settling on top of the packer can make it
impossible to work any tubing rotation down the hole. However, this
limitation with regard to solids settling versus retrievability would also apply
for at least weight-set and hydraulic-set packers. Use of either brine water, oil,
or unweighted low-solids mud as the packer fluid will assist retrievability.
74
75
2. Retrieving
Most hydraulic-set packers are released by picking up on the tubing. There are
varieties that require tubing rotation for release.
3. Selection Considerations
The principal advantage of hydraulic-set packers is that the production tubing
string can be run in the well and the tree installed before the packer is set. In highpressure wells, this permits bringing in the well without swabbing by displacing
the tubing with a fluid of lower density than that required to contain the formation.
Hydraulic-set packers are excellent for use in deviated or crooked holes, where
tubing movement is restricted or undesirable.
Hydraulic-set packers permit the tubing to be hung in neutral tension. This results
in a straight tubing string, which assists the performance of future wireline or
concentric work. An additional advantage is that multiple completion strings may
be run and landed simultaneously. This is of particular assistance in triple or
quadruple completions.
76
Fig. 3.5 Single hydraulic-set packer, schematic of setting and releasing mechanism.
77
78
79
Liner
Collapsed
Casing
80
81
1. Setting
(a) WIRELINE SETTING PROCEDURE (Fig. 3.10):
The packer, adapter kit and pressure-setting assembly are connected to an
electric wireline and run in the hole to the desired setting depth. An electric
current ignites a powder charge within the setting tool. Gas pressure then
transmits a setting force to the packer. Shearing a release stud frees the setting
assembly from the packer. It is then removed from the wellbore on the
wireline.
(b) TUBING SETTING PROCEDURE:
Various methods are employed to set permanent packers on drillpipe or
tubing. They can be set hydraulically, hydraulically with upward pull assist, or
by combination of sequential rotation and upward pull.
2. Accessories
Figures 3.11(a & b) show a permanent packer plus companion accessories, which
include a locator sub or anchor sub, seal nipples, and production tube.
3. Retrieving
Until recently, permanent packers were not retrievable. Most varieties still cannot
be retrieved. However, there are opposed-slip type packers available now that can
be retrieved.
Figure 3.12 illustrates the method of how one manufacturer's model is retrieved.
A J-slot pulling tool run on tubing is used to release the packer mandrel collet.
Upward pull releases both sets of slips.
4. Selection Considerations
Permanent packers are excellent for use in wells with high pressure differentials or
large tubing load variations. They permit precise control as to setting depth. Trip
times are faster because the tubing may be run separately from the packer.
Permanent packers can be set at deeper depths than other packer types. The
"permanence" of these packers is no longer the problem it once was. Wireline and
concentric "through-tubing" remedial techniques have eliminated the necessity for
packer removal much of the time. Permanent packers are often used to test, treat,
and/or squeeze on remedial workover. Where bad order casing exists above a
permanent packer, it is possible on workover to gravel pack perforations, hang a
long screen-liner assembly on a second permanent packer above the bad order
casing point, and use the original packer to complete the isolation of the bad order
section (Fig. 3.13).
82
83
84
85
casing
upper (isolation)
permanent packer
locator sub
partially collapsed
casing
seal assembly
original
permanent
packer
tell-tale screen
screen
perforations
gravel
Fig. 3.13 Gravel pack screen and liner assembly hanging on permanent packer.
86
conventional dual
completion with
casing leak
conventional remadial
completion: cement
squeeze to exclude
casing leak, recomplete
as dual with two strings
of tubing & two packers
"cement packer":
run 2 strings of tubing
cement in place
and perforate
Fig. 3.14 Cement packer technique to isolate a casing leak in a dual completion.
87
88
Ball valves,
Flapper valves,
Valve and
Seat principle, etc.
Tubing size,
Setting depth of valve,
Flowing temperature at setting depth,
Fluid production at the desired closing rate,
Wellhead flowing pressure at the desired closing rate,
Gas/liquid ratio and
Specific gravity of each of the produced fluids.
89
Direct controlled subsurface safety valves are generally set between 1000 and
3000 feet. They should be retrieved and inspected for damage periodically.
Fig. 3.16 Direct controlled valve-and-seat type subsurface tubing safety valve.
90
91
Fig. 3.18 Surface control manifold for remote controlled subsurface tubing safety valves.
92
The primary disadvantage related to the restricted bore through these devices:
The valve does present a restriction to flow, and can cause plugging or
paraffin problems.
surface
control
manifold
wellhead
Safety valve
Hydraulic landing
nipple
casing
tubing
Packer
Fig. 3.19 Wireline retrievable remote operated subsurface tubing valve installation.
93
Fig. 3.20 Wireline retrievable remote controlled subsurface tubing valve with pressure
balancing line.
Fig. 3.21 Wireline retrievable remote controlled subsurface tubing safety valve.
94
95
Fig. 3.22 Tubing removable remote operated subsurface tubing safety valve installation
Fig. 3.22 Tubing removable remote controlled subsurface tubing safety valve.
control line
96
control line
landing nipples
shear pin
snap ring
shifting sleeve
spring
ball
spring
Fig. 3.24 Dual application remote controlled subsurface tubing safety valve.
97
98
BOTTOM-HOLE REGULATORS
Figure 3.26 shows a bottom-hole regulator. This device consists of a valve and a
spring-loaded seat. A predetermined spring tension is loaded against the valve.
The amount of spring tension is dependent upon the pressure differential to be
carried across the regulator. When this differential is reached, the seat moves up
and off the valve, permitting the well to flow.
This device differs from a bottom-hole choke, in that it maintains a constant
pressure differential across the valve regardless of flow rate.
Regulators can be installed in the tubing string in a landing nipple, slip-type
mandrel, or collar-lock mandrel. Pressure differentials up to 1500 psi can be taken
across a single regulator. Flow couplings are often placed above or above and
below landing nipples, which are intended for bottom-hole choke or regulator
service.
99
100
Sitting nipples,
Sliding sleeves and
Blast joints
SEATING NIPPLES
There are three main types of seating nipple used as integral parts of the tubing
string:
Pump-seating nipples
Selective landing nipples
Nonselective or no-go landing nipples
Seating nipples:
Seating nipples, that are used to accommodate a pump, plug, hanger, or flow
control device, consist of a polished bore with an internal diameter just less than
the tubing drift diameter. Usually a lock profile is also required, especially for
landing nipples. Heavy-duty tubing sections, called flow couplings, are often run
on either end of a seating nipple to minimise the effects of turbulence (Fig. 3.28).
Seating nipples and the devices that are set inside them are used for the following
purposes:
101
102
103
SLIDING SLEEVES
Also referred to as sliding side doors or circulating sleeves, these tubing
components are used to obtain access from the tubing to the tubing/casing annulus
either for fluid circulation or to permit a previously isolated zone to be produced
(Fig. 3.30). They are opened and closed with a wireline tool that has a locating
key that engages the profile in the sleeve. A through-flow line (TFL) version is
also available for subsea completions.
These devices are typically placed above each packer in the well. Obviously they
are an essential requirement of multizone completions scheduled for selective
production. Many producers run sliding sleeves in each string in a multistring
completion to increase production flexibility.
A sleeve above the upper packer is particularly useful for the following
operations:
The quality of the elastomer seals in sliding sleeves has improved greatly over the
last decade. They are now much easier to open and less prone to failure. Special
elastomers are needed for some well fluids and suitable design procedures are now
available for elastomers.
A ported nipple is sometimes used in place of a sliding sleeve. Alternatively,
some completion engineers prefer to use a side pocket mandrel and valve as a
circulation point above the packer.
104
105
106
Fig. 3.31 (a) Blast joints; (b) polished nipples; (c) schematic of polished nipple run to
provide sealing surface in case of blast joint erosion.
107
Fig. 3.32 Wellhead and Xmas tree for a dual completion utilizing clamp-type connections.
108
109
110
Figure 3.34
111
TUBING HANGER
The second component is a tubing hanger. Multiple casing heads may be
provided, one for each full string of casing that will be landed in the well. The
tubing head is installed immediately above the last casing head. The tubing head is
almost identical in design to the casing head, with the exception that it is bored for
receiving a tubing hanger. A common tubing hanger is the bowl type, which
resembles a large donut with packing on the outside, that screws directly onto the
top of the tubing. After the tubing has been run in the well and spaced out, this
donut is threaded onto the top of the tubing, the tubing lowered back into the
packer at the bottom of the well, and the donut lowered into the tubing head. The
packing on the donut provides a pressure-type seal for the annulus between the
tubing and the casing. Because of changes in temperature and pressure, the tubing
head donut is usually held down with lock-down screws. There are a variety of
other types of tubing hangers, but the two basic types are designed either to allow
pickup of a tubing string through blowout preventers or to manipulate a tubing
string through the tree or a live well by use of a slick joint.
The bore and size of the top flange are generally determined by completion and
well servicing requirements (BOP size, packer, and tool ODs) rather than the
Christmas tree flange size.
Like the casing, the pressure rating of the tubing head spool is often dictated by
stimulation pressure requirements and may therefore be of a higher rating than the
Christmas tree, which can be removed or protected during stimulation.
In offshore, a compact wellhead, or unihead, is often used to combine both the
casing and tubing spool's function and reduce the overall height of the wellhead.
Three types of tubing hangers are commonly used:
The wrap around hanger, which is hinged to permit installation onto any
part of the tubing other than a coupling.
The dual hanger, either multibore mandrel or split hanger. The mandrel
types are the most common (Fig. 3.36).
It is highly desirable to have an internal thread in the tubing hanger to allow the
installation of a back-pressure valve while removing, repairing, or pressure testing the
tree. This can be installed and removed under pressure with a special tool.
112
113
114
Flange
Master valve(s)
Tee or flow cross
Swab valve
Crown plug
Wing valve
Bean box or choke
Flow line valve
For high-rate wells the flow tree is often Y-shaped to reduce turbulence and erosion.
Similarly, a flow control valve may be installed in a straight run rather than in the
conventional right-angled bean arrangements.
A second side outlet is often used on high-pressure wells as a connection for a tubing
kill line. Similarly, two master valves are often used in severe operating conditions.
This is often a regulatory requirement in sour or high-pressure wells.
Full opening gate valves are used for the master and swab valves (Fig. 3.38). These
should not be opened when a significant differential pressure exists across the closed
valve.
The throughbore of the tree is specified by the API and is generally 1/16 larger than
the tubing ID to facilitate installation of a back-pressure valve in the tubing hanger.
Although the body of a Christmas tree is normally pressure tested to twice the
working pressure for trees rated at 5000 psi (34.4 MPa) or less, and 1.5 times the
working pressure for 7500 to 20,000 psi (52 to 140 MPa) ratings, the flange bolts and
valves may not necessarily have the same rating. Therefore, it is extremely imprudent
to overload Christmas trees when stimulating a well. Similarly, many valves are
unidirectional and this should be taken into account when planning pressure test
sequences. Valve gates can be damaged by applying significant pressure from the
wrong side.
115
116
117
Over the short term (generally one to three months) the well rate is fixed, and
a single monthly test is representative of the entire producing period
Test separator conditions need not be the same as the bulk separator to ensure
a representative test, since fluctuations in downstream pressure do not affect
THP at sonic velocity
Lower pressure ratings can be used for flow lines and separators
The disadvantages relate primarily to lower pressure wells and gas wells:
Flow lines may need to be larger to accommodate the higher flow velocities
without excessive erosion or pressure loss
To meet the last objection, motorised or manual variable chokes or flow control
valves are often used on key wells so that the operator can quickly change the field
flow rate.
3.3.4 Wellhead Ratings
API RATINGS
At the present time, there are seven nominal ratings of wellheads available: 2000,
3000, 5000, 10000, 20000 and 30000 psi working pressure. These pressure ratings
are applicable at temperatures from 50oF to + 250oF. Because of the high
pressure and possible high temperatures involved, ring-type seal gaskets are
provided. These are available in two basic types (Fig. 3.39). The lower pressure
118
ratings - 2000 through 5000 psi are equipped with a type 6B ring joint. A 6B
ring joint may be provided with a type R or type RX ring type gasket. The type R
ring joint gaskets are available in either octagonal or oval shape. The type RX
gasket is a pressure-energized gasket. The 5000 through 15,000-psi flanges are
available in type 6 BX ring joints. 6 BX ring joints use API type BX pressureenergized ring joint gaskets. Pressure rating changes are made using restricted
area rings (Fig. 3.34).
TYPES OF STEEL
Although API and USASI ring joints are dimensionally the same, there is a
significant difference in their rating. API material yield strength ranges from
36,000 to 75,000 psi, depending upon the type of steel specified, whereas USASI
material does not exceed 30,000-psi yield strength.
INSTALLATION
Because the wellheads and ring joints are installed basically to provide pressure
control, extreme care must be exercised in installing and making up the ring
joints. It is absolutely essential that the ring be clean, smooth, and free of burs and
that the gasket be new. Nicks or dings on a ring gasket may cause leaks when the
ring joint is tested.
SPECIAL PROBLEMS
Providing wellheads for multiple completions introduce special problems in
landing the separate tubing strings. This is usually solved by segmenting the
hanging flange, or landing bushing (Fig. 3.36), or providing each string with
separate sealing segments that land in multiple head flanges. Similarly, the
individual master valves must have separate conduits for each stream, which
involves simultaneous sealing of two or more ring gaskets. These problems have
been solved successfully with commercially available equipment that operates
reliably and satisfactorily. Most produced fluids are corrosive, and in some
environments, particularly where CO2 is produced in the gas, rapid deterioration
of the tubing hanger and master valves may occur. In these situations, special
materials are frequently used, the most common being a 410 stainless steel,
although for sour service K monel or 316 stainless steel is required.
UNDERWATER WELLHEADS
Underwater wellhead is basically no different from the land or above water
wellhead, except that the landing system is spread out over a considerable vertical
distance and involves the use of items that are installed on the casing string as it is
run. Most hanging and manipulating operations are conducted blind because the
wellhead normally is installed on the ocean bottom, which ranges from 200 to as
much as 1000 ft below the surface of the rig floor. Although only a limited
number of underwater producing completions have been successfully performed
to date, the equipment is available, has been tested for reliability, and operates
satisfactorily. Although functionally the equipment is much the same, the
operational details involved in the remote assembly make manipulation of the
equipment rather complex. If more information is required, a detailed analysis of a
specific manufacturer's equipment and procedures should be studied.
119
120
GAUGE - This gauge shows the pressure (in psi) contained in the
tubing at the surface.
[Detail 2]
[Detail 3]
121
CASING - This lines or cases off the hole that has drilled to the
formation. The external diameter of some of the most commonly used
sizes of casing are 5, 5, 6 5 8 , 7, 7 5 8 , 8 5 8 , 9 5 8 and 10.
[Detail 8]
TUBING - The tubing serves as a conductor to allow the oil and/or gas
to come to the surface. Tubing is available in various external
diameters of from through 4 and larger.
[Detail 9]
[Detail 10]
CHOKE BOX - This houses the surface choke. The choke is an orifice
that restricts or controls the rate of flow coming from the wellbore.
These chokes are usually sized in 1 64 increments.
[Detail 11]
FLOW LINE - This is simply the surface pipe that serves as the
conductor for the well content (oil and gas) to take it to the storage
tanks, pipelines, etc.
[Detail 12]
[Detail 13]
[Detail 14]
122
[Detail 16]
[Perforations] Perforations are holes that have been "shot" through the casing and
cement in order to allow the formation content to enter the wellbore.
123
124
125
REFERENCES
1. Hammerlindl, D.T., 1997: Movement, Forces and Stress Associated with Combination
Tubing Strings Sealed with Packers. JPT (February).
2. Lubinski, A., Althouse, W.S., Logan, T.L., 1962: Helical Buckling of Tubing Sealed in
Packers. JPT (June).
REVIEW QUESTIONS
1. What are packers used for?
2. Describe the setting and retrieving procedures of hydraulic-set packers?
3. In what situations would you consider using permanent packers?