Productivity Rate

The document outlines productivity rates for various construction divisions over 6 working days per week with one 8-hour shift per day. It includes 64 items with descriptions of work, expected productivity per day, and crew or equipment required for each item. Productivity rates range from excavating 350 cubic meters of earth per day to installing 12 signs. Crews typically include laborers, masons, carpenters, electricians, and helpers along with necessary equipment. Overtime and Fridays may be used to keep the project on schedule or make up for delays.

Uploaded by

Syed Viqar Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
88% found this document useful (52 votes)
30K views2 pages

Productivity Rate

The document outlines productivity rates for various construction divisions over 6 working days per week with one 8-hour shift per day. It includes 64 items with descriptions of work, expected productivity per day, and crew or equipment required for each item. Productivity rates range from excavating 350 cubic meters of earth per day to installing 12 signs. Crews typically include laborers, masons, carpenters, electricians, and helpers along with necessary equipment. Overtime and Fridays may be used to keep the project on schedule or make up for delays.

Uploaded by

Syed Viqar Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Productivity Rates

No. of working days : 6 days/ week (Saturday to Thursday, Friday is day off)
Working shifts : one shift / day
Working hours : 8 hours / day
Over time and Fridays shall be used if necessary to keep on schedule or to compensate for any unexpected events.

No

Division

Productivity
Rate per day

Item Describtion

Crew (Manpower/Equipment)

Div 02

Excavation Works

350 m

1nos Loader

Div 02

Shoring

50 m

4 shoring labours

Div 02

Backfilling

80 m

2 Roller + 2 compactor + 4 labors

Div 02

Preparation of blinding

200 m

3 Labours + 1 Compactor

Div 02

Anti Termite Control

600 m

1 labour

Div 02

Kerbstones

75m

3 Masons

Div 02

Inerlock Tiles

30m

Div 02

Asphalt

Div 03

Concrete Slab

30m

4 Masons
1 Asphalt paver + Roller + Pnuematic wheel
+ compacter & compressor
4 carpenters + 2 labour + 4 Steel Fixers

10

Div 03

Concrete Columns

5 nos

2 carpenters + 2 steel Fixers + 2 Labours

11

Div 03

Precast Concrete Cladding

60m

6 mason + 1 crane

12

Div 03

Concrete Topping / Screed

40m

5 concreter + 1 finisher

13

Div 03

Leight weight concrete

60m

6 concreter + 1 finisher

14

Div 04

Block Works

15m

1 Block work mason + 1 Labour

15

Div 04

Glass Block Works

5m

1 Mason + 1 Helper

16

Div 05

Handrails

10m

1 Handrail mason + 1 helper

17

Div 07

Waterproofing membrane

60m

1 WP mason

18

Div 07

Protection Board

60m

1 WP mason

19

Div 07

Building Insulation

100m

1 Mason + 1 Helper

20

Div 07

Concrete Pavers for Roof

30m

1 Tile Layer + 1 Helper

21

Div 07

Metal panels cladding

30m

1 Cladding Mason + 1 Helper

22

Div 07

Aluminium Flashing

60m

1 Mason + 1 Helper

23

Div 07

Fire Stop

40mr

1 Mason + 1 Helper

24

Div 08

Door Frames

5 Nos

1 Doors carpenters + 1 helper

25

Div 08

Door Leaves

5 Nos

1 Doors carpenters + 1 helper

26

Div 08

Door Hardware

5 Nos

1 Doors carpenters + 1 helper

27

Div 08

Frameless Glass panels

30m

2 Metal Masons + 1 helper

28

Div 09

Cement plaster 1st stage

60m

1 Plaster mason + 1 Helper

29

Div 09

Cement plaster 2nd stage

30m

1 Plaster mason + 1 Helper

30

Div 09

Ceramic walls for wet areas

12m

1 ceramic mason + 1 helper

31

Div 09

Ceramic Skirting

30mr

1 ceramic mason + 1 helper

32

Div 09

G.B partition Studs+1st Layer +Insulation

20m

2 mason + 1 Helper

33

Div 09

G.B parititions Closing

50m

2 mason + 1 Helper

34

Div 09

Gypsum false ceiling

20m

1 Mason + 1 Helper

35

Div 09

Metal false ceiling

30m

1 Mason + 1 Helper

36

Div 09

Paint preparation

40m

1 Painter

37

Div 09

Painting Coats

40m

1 Painter

38

Div 09

Vinyl Tiles

25m

1 Tile Layer + 1 Helper

2000m

111

Productivity
Rate per day

No

Division

Item Describtion

39

Div 09

Rubber Tiles

25m

1 Tile Layer + 1 Helper

40

Div 09

Marble Tiles

12m

1 Tile Layer + 1 Helper

41

Div 09

Marble Skirting

30mr

1 Tile Layer + 1 Helper

42

Div 09

Marble Threshold

20mr

1 Tile Layer + 1 Helper

43

Div 09

Marble Counter

15mr

1 Tile Layer + 1 Helper

44

Div 09

Granite Flooring

12m

1 Tile Layer + 1 Helper

45

Div 09

Terrazzo Tiles

15m

1 Tile Layer + 1 Helper

46

Div 09

Insitu Terrazo tiles

5m

1 Tile Layer + 1 Helper

47

Div 09

Carpet Tiles

40m

1 Tile Layer + 1 Helper

48

Div 09

Wood Flooring

10m

1 Mason + 1 Helper

49

Div 10

Wall & Corner guards

7 nos

1 Mason + 1 Helper

50

Div 10

Toilet Accessories

5 nos

1 Mason + 1 Helper

51

Div 10

Access Flooring

20m

1 Mason + 1 Helper

52

Div 10

Internal Signage

12 Nos

1 Signage Mason

53

Div 12

Lab Furnitures

10 seats

1 Finishing Carp. + 1 helper

54

Div 13

Shelter Doors

1 nos

55

Div 15

Laying Water supply pipes

30m

1 plumber + 1 helper

56

Div 15

Laying Drainage pipes

24m

1 plumber + 1 helper

57

Div 15

Laying Fire Fighting Pipes

24m

1 FF Pipe Fitter + helper

58

Div 15

Laying HVAC Ducts

70 kg

1 Duct Fitter + 1 helper

59

Div 15

Duct Insulation

20 m

1 Duct Fitter + 1 helper

60

Div 15

HVAC Piping

20m

1 Pipe Fitter + 1 helper

61

Div 16

Installing Cable Trays

15m

1 Electrician + Helper

62

Div 16

Electrian Conduiting

24m

1 Electrician + Helper

63

Div 16

Wiring Works

400m

3 Electricians + 3 helpers

64

Div 16

Laying Cables

20m

3 Electricians + 3 helpers

112

Crew (Manpower/Equipment)

3 Mason + 1 Helper