Productivity Rate
Productivity Rate
No. of working days : 6 days/ week (Saturday to Thursday, Friday is day off)
Working shifts : one shift / day
Working hours : 8 hours / day
Over time and Fridays shall be used if necessary to keep on schedule or to compensate for any unexpected events.
No
Division
Productivity
Rate per day
Item Describtion
Crew (Manpower/Equipment)
Div 02
Excavation Works
350 m
1nos Loader
Div 02
Shoring
50 m
4 shoring labours
Div 02
Backfilling
80 m
Div 02
Preparation of blinding
200 m
3 Labours + 1 Compactor
Div 02
600 m
1 labour
Div 02
Kerbstones
75m
3 Masons
Div 02
Inerlock Tiles
30m
Div 02
Asphalt
Div 03
Concrete Slab
30m
4 Masons
1 Asphalt paver + Roller + Pnuematic wheel
+ compacter & compressor
4 carpenters + 2 labour + 4 Steel Fixers
10
Div 03
Concrete Columns
5 nos
11
Div 03
60m
6 mason + 1 crane
12
Div 03
40m
5 concreter + 1 finisher
13
Div 03
60m
6 concreter + 1 finisher
14
Div 04
Block Works
15m
15
Div 04
5m
1 Mason + 1 Helper
16
Div 05
Handrails
10m
17
Div 07
Waterproofing membrane
60m
1 WP mason
18
Div 07
Protection Board
60m
1 WP mason
19
Div 07
Building Insulation
100m
1 Mason + 1 Helper
20
Div 07
30m
21
Div 07
30m
22
Div 07
Aluminium Flashing
60m
1 Mason + 1 Helper
23
Div 07
Fire Stop
40mr
1 Mason + 1 Helper
24
Div 08
Door Frames
5 Nos
25
Div 08
Door Leaves
5 Nos
26
Div 08
Door Hardware
5 Nos
27
Div 08
30m
28
Div 09
60m
29
Div 09
30m
30
Div 09
12m
31
Div 09
Ceramic Skirting
30mr
32
Div 09
20m
2 mason + 1 Helper
33
Div 09
50m
2 mason + 1 Helper
34
Div 09
20m
1 Mason + 1 Helper
35
Div 09
30m
1 Mason + 1 Helper
36
Div 09
Paint preparation
40m
1 Painter
37
Div 09
Painting Coats
40m
1 Painter
38
Div 09
Vinyl Tiles
25m
2000m
111
Productivity
Rate per day
No
Division
Item Describtion
39
Div 09
Rubber Tiles
25m
40
Div 09
Marble Tiles
12m
41
Div 09
Marble Skirting
30mr
42
Div 09
Marble Threshold
20mr
43
Div 09
Marble Counter
15mr
44
Div 09
Granite Flooring
12m
45
Div 09
Terrazzo Tiles
15m
46
Div 09
5m
47
Div 09
Carpet Tiles
40m
48
Div 09
Wood Flooring
10m
1 Mason + 1 Helper
49
Div 10
7 nos
1 Mason + 1 Helper
50
Div 10
Toilet Accessories
5 nos
1 Mason + 1 Helper
51
Div 10
Access Flooring
20m
1 Mason + 1 Helper
52
Div 10
Internal Signage
12 Nos
1 Signage Mason
53
Div 12
Lab Furnitures
10 seats
54
Div 13
Shelter Doors
1 nos
55
Div 15
30m
1 plumber + 1 helper
56
Div 15
24m
1 plumber + 1 helper
57
Div 15
24m
58
Div 15
70 kg
59
Div 15
Duct Insulation
20 m
60
Div 15
HVAC Piping
20m
61
Div 16
15m
1 Electrician + Helper
62
Div 16
Electrian Conduiting
24m
1 Electrician + Helper
63
Div 16
Wiring Works
400m
3 Electricians + 3 helpers
64
Div 16
Laying Cables
20m
3 Electricians + 3 helpers
112
Crew (Manpower/Equipment)
3 Mason + 1 Helper