An Analysis On Resource Planning, Cost Estimation and Tracking of Project by Earned Value Management
An Analysis On Resource Planning, Cost Estimation and Tracking of Project by Earned Value Management
I. INTRODUCTION
Construction industry is important at both global and
national level. It provides huge employment to the people
and plays very significant role in country economy. Project
delay is most common problem in construction industry.
Project overruns due to time and cost result in delays during
project execution. In developing countries project overrun is
serious problem where implementation of project faces
many uncertainties. It result in wastage of scare financial
resource, delays in providing facilities, development and
also makes construction costlier [4]. EVM is the process of
measuring performance of project work against a baseline
plan. EVM application helps in providing performances
standard for the evaluation of progress report project and it
also acts as a control device to take care of time and cost
schedule by responsibility defined Organization Breakdown
Structure (OBS). It provides better performance picture of
project and gives better forecast of the final completion
cost. Earned value is an enhancement over traditional
process of cost accounting [9]. Traditionally budgeted cost
is evaluated by computing the difference between planned
cost and actual cost incurred in a project. The focus was on
planned expenditures and actual cost. Earned value reveals
future opportunities and it also examines actual
accomplishment. With help of EVM, project managers get
sufficient help to have deep intuitive understanding into
potential risk areas. So that with help of clearer picture of
project performances, managers can create risk mitigation
42
ISSN: 2277-3754
ISO 9001:2008 Certified
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 4, Issue 4, October 2014
document, Bill of Quantities and abstract sheets provides
It develops the production information for
necessary data for project cost and scheduling activities.
materials, labour and equipment that can be used
Total area is 7881 sq.ft. The work should be completed
as inputs for future estimates.
within 160 working days. The project was schedule from
It generates information so that one may study to
27th January 2014 to 10th July 2014 and four sets of tracking
take corrective measures to minimize the cost at
are done at different intervals and final tracking was till 30 th
any step.
June 2014. The main objective of study is to understand the
role of EVM for monitoring and control in progress and
COST ESTIMATE INPUTS
timely completion of construction project goals are
achieved through literature review and methodology
a) Using the Work Breakdown Structure
involved in Earned Value Management.
b) Relying on the resource Requirements
c) Calculating Resource Rates
VI. METHODOLOGY AND ANALYSIS OF EVM
d) Estimating Activity Duration
The construction projects are so vast and complex in
e) Historical Information
nature and therefore for simplification of work, use of
softwares came into existence. The project was scheduled
ESTIMATING PROJECT COSTS
and monitored using Primavera P6 software. Primavera is
the Project Management software use for Planning,
a) Analogous Estimating
Scheduling and Controlling the Construction Project. The
b) Parametric Modeling
steps involved in Duplex Apartment are as follows:
c) Bottom-up Estimating
Brickwork, Plastering, Flooring, Cabinetry, False Ceiling
d) Computerized Tools
and Terrace works. The WBS for the project is created and
several activities are identified. The durations of the
OUTPUTS FROM COST ESTIMATION
activities are estimated on basis of Historical data,
interviews with project manager, applying labour
a) Cost Estimates
productivity factor formulae and application of analysis of
b) Supporting details
rates. The relationships are examined and applied to the
c) Cost management plan
activities. The following procedure involved in scheduling
and monitoring projects.
IV. CONCEPTS OF EVM
Table 1 PROCEDURE IN PRIMAVERA
Earned value analysis is a method of performance
measurement. Earned value is a program management
1
Create Project
technique that uses work in progress to indicate what will
2
Define WBS
happen to work in future. EVM is system for planning and
3
Creating Calendars
controlling the project cost performances. EVM establish
work packages earned value baseline by integrating project
4
Define Activities
scope, time and cost objectives [6, 8]. This baseline is called
5
Appoint Activity Durations
as cost control and is used for performance evaluation of
6
Assign Logic Links
project on a given date. Analysis of variance from the
7
Perform Scheduling
baseline provides the cost related informations for problem
identification, trend analysis and corrective actions such as
8
Allocating Resources/Budgeting
re-planning and revising budget. Earned value analysis
9
Creating Baselines
serves two main purposes, it analyses cost changes which is
10
Updating schedule
resulting in time and cost over-run or under-run so that
11
Earned Value Analysis
timely corrective actions are taken such as modification of
cash flow, updating financial forecast and project
12
Publishing Reports
profitability expectations. Analysis of variance from
baseline using earned value management systems given
variety of variances which are analyzed to provide current
SCHEDULE ANALYSIS: Earned value is a technique
status of project, to initiate corrective actions and to forecast
for measuring project performance according to project cost
future trends [6].
and schedule. The comparison between budgeted and actual
performance is performed. There are three earned value
parameters as shown below.
V. CASE STUDY
The case study is a Duplex Apartment of Windmills of
Your Mind at Whitefield, Bangalore. The useful
informations has been taken from actual project. Tender
43
ISSN: 2277-3754
ISO 9001:2008 Certified
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 4, Issue 4, October 2014
Planned Value (PV): It is the cost of the project
SPI = Earned Value / Planned Value
according to the schedule of the project. It is also called
SPI = 1 means Project is on Schedule
Budgeted Cost of Work Schedule (BCWS).
SPI < 1 means Project is behind Schedule
44
ISSN: 2277-3754
ISO 9001:2008 Certified
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 4, Issue 4, October 2014
VII. RESULTS
Table 2 RESULTS OBTAINED FROM PRIMAVERA P6
EVM Paramater
Tracking 1
Tracking 2
Tracking 3
Tracking 4
Budgeted at Completion
Rs. 80,12,225
Rs. 80,12,225
Rs. 80,12,225
Rs. 80,12,225
Planned Value
Rs. 7,02,334
Rs. 27,68,881
Rs. 61,94,005
Rs. 77,29,472
Earned Value
Rs. 7,02,334
Rs. 25,54,523
Rs. 56,13,448
Rs. 68,17,173
Actual Cost
Rs. 7,02,334
Rs. 28,15,802
Rs. 64,51,565
Rs. 80,36,983
Schedule Performance
Index
0.92
0.90
0.88
Schedule Variance
Rs. 2,14,358
Rs. 5,80,557
Rs. 9,12,299
0.90
0.87
0.84
Cost Variance
Rs. 2,61,279
Rs. 8,38,117
Rs. 12,19,810
Estimate at Completion
Rs. 80,12,225
Rs. 82,73,504
Rs. 88,50,342
Rs. 92,32,035
Planned Schedule %
Complete
8.77%
34.5%
77.3%
96.4%
Actual Schedule %
Complete
8.77%
32%
70%
85%
45
ISSN: 2277-3754
ISO 9001:2008 Certified
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 4, Issue 4, October 2014
Table 3 CUMULATIVE COST AFTER TRACKING 4 FROM PRIMAVERA P6
1JAN 2014
1 FEB 2014
1 MAR 2014
1 APR 2014
1 MAY 2014
1 JUN 2014
1 JUL 2014
Planned Value
Cost
Rs. 33,428
Rs. 4,97,046
Rs. 4,33,150
Rs.18,05,257
Rs. 34,25,124
Rs. 15,35,467
Rs. 2,82,753
Cumulative
Planned Value
Cost
Rs. 33,428
Rs. 5,30,474
Rs. 9,63,624
Rs. 27,68,881
Rs. 61,94,005
Rs. 77,29,472
Rs.80,12,225
Earned Value
Cost
Rs. 33,428
Rs. 4,97,046
Rs. 3,34,898
Rs. 16,89,151
Rs. 30,58,925
Rs. 12,03,725
Cumulative
Earn Value
Cost
Rs. 33,428
Rs. 5,30,474
Rs. 8,65,372
Rs. 25,54,523
Rs. 68,17,173
Actual Cost
Rs. 33,428
Rs. 4,97,046
Rs.3,89,548
Rs. 18,95,780
Rs. 36,35,763
Rs. 15,85,418
Cumulative
Actual Cost
Rs. 33,428
Rs. 5,30,474
Rs. 9,20,022
Rs. 28,15,802
Rs. 64,51,565
Rs. 80,36,983
46
ISSN: 2277-3754
ISO 9001:2008 Certified
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 4, Issue 4, October 2014
VIII. CONCLUSION
EVM provides important information for project work
package decision making.
The efficiency of project is demonstrated by SPI is 0.88
which is less than 1 hence project performed less
efficiently and running at about 88% of the planned
schedule.
Schedule Variance of the project is Rs. 9, 12,299 the
negative sign determines that project is lagging behind
the original schedule.
CPI indicates the project efficiency of project
utilization. For best case scenario, it must be equal to 1
or higher. However for current project is 0.84, this
shows that project has low cost efficiency as compared
to its spending.
47
ISSN: 2277-3754
ISO 9001:2008 Certified
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 4, Issue 4, October 2014
AUTHORS PROFILE
IX. RECOMMENDATION for FUTURE
RESEARCH
The future research in general will include probably new
metrics in the EVM methodology to take into account issues
like Risk Analysis or Quality and technical performance for
an efficient project control. Implementation of EVM creates
lot of extra work where it is difficult to integration of
companys planning, scheduling, budgeting, work
authorization and cost accumulation processes with each
other. All these project management constrains likely to
Mr. Shaik Mohammad Masood has
obtained his Bachelor of Engineering (Civil Engineering) from
exist on most projects. So future research should be aimed
Islamia Institute of Technology Bangalore and Master in Technology
to reduce the extra work.
(Construction Technology) from Government Engineering College,
Hassan. He secured College Second Rank in B.E. He has worked at
Total Environment Building System Private Limited and has gain
experience in civil construction works of luxury Apartments and
Villas.
ACKNOWLEDGEMENT
The project data used in this study was made available by
Mr. Manoj Kumar General Manager at Total Environment
Building System Pvt Ltd and Dr. Karisiddappa Principal
Government Engineering College, Hassan. I am indebted to
these gentleman for their contribution to this study.
REFERENCES
[1] PMI. Practice Standard for Earn Value Management,
Project Management Institute, USA 2005.
[2] Frank T Anbari (Dec 2003), Earned Value Project
Management Method and Extensions, Project Management
Journal, Vol-3.
[3] T.N Weerasinghe Mohottige,( Nov 2013) Standard Practice
of Earn Value Management and its Impact on Construction
Industry, International Journal of Recent Technology and
Engineering ISSN:2277-3878, Volume-2.
48