LIGHTNING PROTECTION
OF AN INDUSTRIAL PLANT
Robert Kane
MESA Conference
Brisbane 8th July 2015
RISK CALCULATIONS
AS1768 provides a spreadsheet with in-built formulae for calculating
the risks and comparing to predetermined acceptable levels of risk for:
Loss of Human Life
Loss of Cultural Heritage
Structure Attributes
Service Lines
Loss Categories
Protection Level
PL
LPS Efficiency
Sphere Radius
a (m)
0.98
20
II
0.95
30
III
0.90
45
IV
0.80
60
10
11
13
15
The LPS was designed using a 30m rolling sphere, making use of
the pipe rack structure and air terminals mounted on 5 freestanding masts.
16
17
Cooling Tower:
Cooling tower structures are made from fibreglass
and not designed to carry the additional loads of
metal lightning masts. Also have to ensure
protection over cooling water pumps.
18
19
Chiller:
The chiller structure was mostly metal, but we
wanted to also protect the exposed pipe work (not
protected by installation within pipe racks).
Risk assessment using PLII showed acceptable risk
levels.
The LPS was designed using a 30m rolling sphere
and making use of the pipe rack structure and air
terminals mounted on 2 free-standing masts.
20
21
GT & HRSG:
The GT comprises several large steel structures and metal-clad
enclosures, which:
o Are bonded to the buried site earth grid at regular intervals.
o Act as air terminals and a down conductor network.
o Provide appropriate protection and comply with AS1768.
However specific equipment and areas need to be protected
from a direct strike, eg:
o Instruments, silencers and exposed steam lines.
o Hazardous areas (above the gas vents at the GT and HRSG
structures).
22
24
25
27
28
29
Water Tanks:
This applied to the Raw Water Tanks, Demin Water Tank and
Potable Water Tank.
Floodlighting:
The Floodlight Poles around the plant had not been bonded to the
buried earth grid instead connected to the earth conductor in
the power cable to the light.
Recommended that all poles not within the zone of protection, be
bonded to the buried earth grid, and that surge protection be
fitted to the outgoing light cable at the DB.
31
32
QUESTIONS
???
Acknowledgement for 3D Modelling in SolidWorks
Tony Gibson, Gibson Design & Drafting Pty Ltd, Gladstone.