Project Management: Project Is Something Complicated That You Haven't Done Before
Project Management: Project Is Something Complicated That You Haven't Done Before
P
l
a
n
n
i
n
g
Steps
Brainstorm
Write out a WBS
Ask other people
Example
Suppose the electrical work on a house was ongoing.The electricians
perform a whole job doing various things. If it is part of plan, it means
there is no control over electricians. If there is a need to check after a
couple of weeks, and there's wires everywhere. How do we know they're
on schedule or not.
So the fact is that the "O" word for electricians means that we need to
granulate them down, break their work down into smaller subtasks. Once
that is done, we have control and can see how long each task is meant to
take, and we can keep up with the schedule. So the good thing about
awareness of the fact you mustn't say the "O" word, is that it's a sign, it
tells you when you need more granularity. Divide that task down into
Solution
Think about the project you're working on at the moment. Are there any
tasks that you are currently referring to as "ongoing?". what you're really
saying is you don't know when it's going to finish. And if you think about
it, if you're going to plan a project, you have to know when every task
starts and finishes.And therefore, granulate those tasks down into smaller
pieces and get more control of them? That's what I want you to do. Ask
yourself do you ever use the "O" word? Are you using it at the
moment, and could you use granularity as a substitute?
Example
What would be the probabilitydistribution of all journeys? it'll most probably be a skewed normal d
Solution
Estimate with 90% confidence interval, between average and worst-case
Fig 4: PERT
Fig 5: CPM
The Steps
Consider dependencies and draw the CPA network: and find the
float of the non-critical tasks
PERT is customer focused, CPM is more focused on the person
doing the work.
You can add milestones or events to your CPM diagram if you
wish, and once the diagram is make into a Gantt chart then you
can have as many events as you want, so the lack of events on
CPM is not really an issue.
Make the diagram by putting post-its onto a white board or large
sheet of paper, with a group. Its another chance to involve your
Example
team.
For a distribution centre:
Gantt Charts
Purpose
Communication: to show everyone when their tasks will be started
and finished
Loading: to be able to look vertically at any given week or month
and consider whether you have the resources for all the tasks
being done at that time
Monitoring Progress: by colouring in the Gantt chart and trying to
keep up with the Today line
Once we've got a list of all the possible risks, assess which ones to
worry about. A good way to do this is to give scores for how likely
and how serious, both out of five. If the multiplied score goes into
double figures, then it is a risk you should be concerned about. If it's
not very likely or not very serious, you probably won't need to worry
about it.
For reducing risks. You can either make it less likely to happen, or
less serious if it does happen. Either one of those is fine, the
objective is to get it down below the double figures.
Keep risk plan up to date throught thee project. Some of the risks
that you identify at the start will reduce over time past danger
Monitoring Costs
Assume linear spend, but then just in the back of your mind, bear in
mind that sometimes spend isn't linear and you need to just keep an
eye on that. So there we are, that's how to monitor the finance of your
project. And what I recommend is have a look at your existing project
now, have a look at the finance figures that you've got coming in, but
pair them up with the Gantt chart and see what they've really
mean,and never again judge projects just by the money, always look at
the Gantt chart as well.
Review/Reschedule