Specification Building Works 2014 PDF
Specification Building Works 2014 PDF
PAGE
SECTION A
A/1 - A/30
SECTION B
B/1 - B/14
SECTION C
C/1 - C/42
SECTION D
: CONCRETE WORKS
D/1 - D/44
SECTION E
E/1 E/10
SECTION F
: SEWERAGE WORKS
F/1 F/10
G/1 - G/8
SECTION H
H/1 - H/30
SECTION I
: CEILING WORKS
I/1 - I/10
SECTION J
J/1 - J/6
SECTION K
K/1 - K/14
SECTION L
L/1 - L/14
M/1 - M/6
SECTION N
: GLAZING WORKS
N/1 - N/4
O/1 - O/8
SECTION P
P/1 - P/11
Q/1 - Q/2
SECTION R
R/1 - R/10
SECTION S
: DRAINAGE WORKS
S/1 - S/8
SECTION T
: SIGNAGE WORKS
T/1 -T/4
TABLE OF CONTENTS
SECTION A: PRELIMINARIES AND GENERAL CONDITIONS
PAGE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
Scope Of Works
Abbreviations
Standards
Contract Documents
Adjoining Property
Goods, Materials And Workmanship
Use Of Local Materials
Sustainable Materials And Products
Metrication
Ordering
Supply Of Materials By Government
Shop Drawings, Samples And Mock-Ups
Contractors Plant
Construction Plan
Project Signboard
Progress Photographs
Sufficient Notice To Local Authorities
Access And Temporary Roads
Temporary Diversion And Relocation Of Existing Overhead And
Underground Services
Temporary Water And Power Supplies For The Works
Site Security
Care And Protection
Legislation And Regulations
Drainage, Erosion And Sediment Control
Access Roads And Maintenance Of Existing Roads
Control Of Workmen, Plant And Machinery At Site
Particulars Of Employees
Contractors Temporary Accommodation And Facilities For Workmen
Living On Site
Contractors Office And Storage
Office Accommodation For S.O.
Telephone For S.O.
Site Items For S.O./ Office Equipment And Facilities
Material Testing Laboratory And Staff
Survey Instruments And Personnel
Safe Working Area
Safety, Health And Welfare
Sanitation
Waste Management
Environmental Protection Works
TABLE A1
40.
41.
42.
43.
44.
45.
46.
: Submission Of Documents
A/1
A/1
A/1
A/2
A/3
A/3
A/3
A/4
A/4
A/4
A/4
A/5
A/5
A/5
A/6
A/6
A/7
A/7
A/7
A/7
A/7
A/8
A/8
A/8
A/9
A/10
A/10
A/10
A/11
A/12
A/12
A/13
A/14
A/14
A/15
A/16
A/17
A/17
A/17
A/18
A/18
A/19
A/21
A/21
A/22
A/22
A/23
TABLE OF CONTENTS
SECTION A: PRELIMINARIES AND GENERAL CONDITIONS
PAGE
APPENDIX A/1 :
APPENDIX A/2 :
APPENDIX A/3 :
APPENDIX A/4 :
APPENDIX A/5 :
APPENDIX A/6 :
APPENDIX A/7 :
A/24
A/25
A/26
A/27
A/28
A/29
A/30
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/1
1. Scope Of Works
1.1
The Works covered in this Contract comprise the provision by the Contractor at his
own risk and cost of all materials, scaffolding, tools, plant, labour, transport, water,
light and everything else necessary for the construction and completion of i.
.all to the approval of the S.O.
1.2
The Conditions of Contract for the Works, which is embodied in the Form of
Contract (Form PWD 203 / Form PWD 203A), shall be read in conjunction with this
Specification. A copy of the Form of Contract is available for inspection on the
Tender Table on any working day up to the time appointed for receiving tenders. If
the tenderer considers that any of the clauses of the Contract involves expenses, he
shall allow for the money value of such clauses in his Tender.
2. Abbreviations
2.1
B.Q.
CIAST
CIDB
CoW
DGFR
DOE
DOSH
EMP
JKR
MOH
MSMA
MTIB
PDRM
P.E.
R.O.W.
S.O.
S.P.
SIRIM
SPAN
- Bills of Quantities
- Pusat Latihan Pengajar dan Kemahiran Lanjutan
- Construction Industry Development Board
- Clerk of Works
- Director General of Fire and Rescue
- Department of Environment
- Department of Occupational Safety and Health
- Environmental Management Plan
- Jabatan Kerja Raya
- Ministry of Health
- Manual Saliran Mesra Alam
- Malaysian Timber Industry Board
- Polis Diraja Malaysia
- Professional Engineer
- Right Of Way
- Superintending Officer
- System Provider
- Standards and Industrial Research Institute of Malaysia
- Suruhanjaya Perkhidmatan Air Negara
3. Standards
3.1
All Standards referred to in this Specification together with any addenda issued shall
be deemed to be the editions current at the time of Tender. If the Malaysian
Standard (MS) exists, which the S.O. deems to be equivalent to the British or other
Standard specified, then the MS shall be followed. Other equivalent standards
specifying superior material may be used with the approval of the S.O.
3.2
In the event of any discrepancy between the provision of this Specification and the
provision within the relevant Standards or Codes of Practice (CP) as mentioned in
this Specification, then the provision of this Specification shall take precedence.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
3.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/2
AASHTO
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
ANSI
API
AS/NZS
ASTM
AWWA
BS
(viii) CNS
(ix) CP
(x)
(xi)
DIN
EN
(xii) JIS
(xiii) MS
4. Contract Documents
4.1
The documents shall be taken as mutually explanatory of each other and in case of
any discrepancy or inconsistency, the following rules shall apply:
(i)
(ii)
(iii)
(iv)
(v)
The Conditions of Contract (PWD Form 203/ PWD Form 203A) shall take
preference over all other documents.
Special Provisions to Conditions of Contract shall take preference over
Conditions of Contract.
In Drawings, large scale details shall take preference over small scale
Drawings.
The Addendum Specification shall take preference over the Standard
Specifications and Drawings.
Drawings shall take preference over Standard Specifications.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
4.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/3
Any discrepancies shall be referred as soon as possible to the S.O. who shall
decide which shall be followed.
5. Adjoining Property
Where the property adjoining the Site is in constant use by the Employer/adjoining owners
and occupiers, the Contractor shall arrange and carry out the Works so as to cause
minimum interference or interruption to the use of adjoining properties including roads,
footpaths, other access and any existing services thereto. He shall comply with all
instructions or directions given by the S.O. in these matters.
Materials and workmanship throughout the Works shall be in accordance with the
Drawings and Specifications and to the approval of the S.O.
6.2
Where required, all works shall be executed by competent and skilled workers in the
related field.
6.3
6.4
If, however, the Contractor has shown beyond reasonable doubt that the specified
goods or materials cannot be obtained and the S.O. is satisfied with regard to the
non-availability of the goods and materials, the benefit of cost savings, if any,
resulting from the Contractors proposal or substitution of goods or materials
approved by the S.O., shall be deducted from the Contract Sum.
The Contractor shall use locally manufactured materials and goods as listed in the
Senarai Bahan/Barangan Binaan Buatan Tempatan issued by IKRAM QA Services
Sdn. Bhd. and/or Senarai Bahan/Barangan Buatan Tempatan issued by SIRIM QA
Services Sdn. Bhd., whichever is relevant. If the Contractor fails to comply with this
requirement, a penalty shall be imposed and/or the materials supplied shall be
rejected.
7.2
The locally manufactured materials and goods which are not listed aforesaid, may
be permitted if the materials have been tested and certified by IKRAM QA Services
Sdn. Bhd. or SIRIM QA Services Sdn. Bhd. whichever is relevant. If the testing
cannot be carried out by IKRAM QA Services Sdn. Bhd. or SIRIM QA Services Sdn.
Bhd., the Contractor may apply and, subject to the approval of the S.O., carry out
the testing by other agencies.
7.3
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/4
7.4
The Contractor shall ensure that the procurement of approved imported materials,
plant, equipment, or other goods are obtained directly from the country of origin
based on Free On Board (F.O.B) or other similar basis. The transportation and
insurance of such imported materials, plant, equipment, or other goods from the
country of origin to the Site shall be arranged by the Contractor through approved
Governments Multi Modal Transport Operators (MTO). The Contractor shall allow in
his tender all costs and time required in complying with the requirements of this
clause including the cost required for the services provided by the MTO.
7.5
The Contractor shall submit documentary evidence of compliance with this clause to
the S.O. within one (1) month from the date of each delivery to the Site of such
materials, plant, equipment, vehicles or other goods.
9. Metrication
Unless otherwise specified hereinafter or shown on the Drawings, only materials of metric
dimension shall be used for the Works. Materials of equivalent imperial dimension may only
be used if the Contractor can satisfy the S.O. that the required materials are not available
in metric dimension.
10. Ordering
The Contractor shall place his orders for specified materials at the earliest possible date
after notification of acceptance of tender or at such times as may be specifically stated for
any particular material.
If the Contractor fails for any reason to supply any materials, which he has
contracted to supply, or if he fails to supply any such materials in sufficient time to
enable the Contract to be completed by the agreed date for completion, the
Government may supply any portion, or all of such materials.
11.2
If the Government supplies such material, the cost in respect thereof to be borne by
the Contractor shall be either the current market rates or the actual cost to the
Government, whichever is greater, plus 5% on cost charges.
11.3
The cost to be borne by the Contractor, as detailed above, shall be deducted from
any money due or to become due to the Contractor under this Contract and failing
which such costs shall be recovered from the Performance Bond or as a debt due
from the Contractor.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
11.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/5
No action by the S.O. under this clause shall be deemed in any way to affect or
modify the right of the Government to claim for damages in the event of the
Contractors failure to complete the Works by the agreed date of completion.
The Contractor shall submit for approval relevant shop drawings as requested by
the S.O.
12.2
12.3
12.4
The Contractor shall submit for approval as requested by the S.O., manufacturer's
specifications, installation instruction, general recommendation for the work,
including certified laboratory test reports and other data required to show
compliance with these specifications.
The Contractor shall provide, erect, keep insured, maintain and remove on
completion all requisite scaffolding, hoist, ladder, staging, tarpaulins, tools, vehicles,
tackles and other plants and apparatus (excluding piling and pile testing equipment),
as required by all trades as are necessary for the execution of the Works.
13.2
All mechanical plant used by the Contractor shall be of such type, size and capacity
suitable to the type and nature of the Works and site conditions where the Works
are to be executed.
13.3
The Contractor shall take note the required cranage for the erection and completion
of precast components and to ensure that the said cranes are or will be available
during the construction stages.
Within fourteen (14) days after the receipt of the Letter of Acceptance, the
Contractor shall submit to the S.O. for his approval the following:
14.1.1
Programme of Works
14.1.1.1
14.1.1.2
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
14.1.2
14.1.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/6
Method statements
14.1.2.1
14.1.2.2
14.1.4
Schedules
14.1.4.1
16.2
The Contractor shall supply six (6) sets of bound printed copies of the approved
photographs, all properly titled and dated. The photographs shall also be provided
in jpeg or other approved format with each image set at minimum size of 1280 x
960 pixels and at resolution of 72 pixels per inch and submitted to the S.O.
monthly, in compact discs or removable storage.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/7
The Contractor shall give sufficient notice to the relevant Local Authorities/Utility
Providers/Regulatory Bodies before commencing or to inspect any works in
relation to their scope of services. Failure to give sufficient notice shall not entitle
the Contractor to extension of time due to any subsequent delays in connection
with the Works.
17.2
Any notice given to the above mentioned authorities shall also be copied to the
S.O.
Before commencing any excavation, et cetera, the Contractor shall enquire from
the various authorities whether any underground pipes, cables, et cetera are
present on the Site and if so, he shall make arrangements for the disconnection,
removal and if necessary, the relocation and reconnection of such services and
pay all necessary cost and fees in connection with all temporary diversion and
relocation of existing services.
19.2
The Contractor shall provide adequate power supplies for temporary lighting and
for the execution of the works. Electricity shall be obtained from Tenaga Nasional
Berhad (TNB) or the local electricity supply company. Where such electricity supply
cannot be provided, generator set(s) may be used but safety precautions must be
taken. The use of kerosene lamps shall not be allowed.
20.2
The Contractor shall provide all water required for the use in the Works including
paying all associated costs and fees and providing and removing all temporary
plumbing and storage facilities on completion.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/8
The Contractor shall at all times comply with the provisions of all statutes and other
related legislation currently in force regarding the environment, safety and health
as listed in APPENDIX A/1 including any revisions to the current regulations.
23.2
The Contractor shall be liable for and shall indemnify the Government against any
damages, expenses, liability, losses, claims, prosecution, proceedings, fines and
penalties caused by any non-compliance or contravention of the above legislation
and regulations.
The Contractor shall execute the Erosion and Sediment Control Plan (ESCP) and
all control measures as shown on the Drawings in such a manner and order as
directed by the S.O. that will minimize accelerated erosion and sedimentation
during the construction phase. The Contractor shall be responsible for compliance
with MSMA relating to erosion and sediment control.
24.2
The Contractor shall execute ESCP which provides for inspection of erosion and
sediment control devices and facilities on a weekly basis and following precipitation
events, as well as maintenance, replacement or repairs to inadequate or damaged
controls and devices to ensure effective and efficient operation.
24.3
The contractor shall maintain all the temporary works regularly throughout the
construction period, or as directed by the S.O. and making good of any damaged
portions during the course of the works.
24.4
The Contractor shall make proper provision for the drainage of surface water from
the work site including rainwater from surrounding areas which drain on to the site.
24.5
The Contractor shall provide, form, fix and maintain such pumps, chutes, walls,
drains, bunds and other temporary works necessary for the proper drainage of the
Site so that no ponding, flooding or other damage or disturbance is caused to
areas surrounding the works throughout the duration of the Contract.
24.6
24.7
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/9
The Contractor shall construct wash trough as shown on the Drawing unless
otherwise directed by the S.O. for cleaning all debris, dirt and mud from the wheels
and tyres of Contractors vehicles leaving the Site. The position of the wash trough
shall be as indicated on the site plan or as approved by the S.O. The wash trough
shall be maintained regularly throughout the contract period as directed by the S.O.
24.9
24.10
The Contractor shall install check dam as shown on the Drawings unless otherwise
directed by the S.O., for preventing erosion by reducing the velocity of storm water
flows in diversion channel in steep terrain. The check dam shall be constructed of
rocks or logs which are secured against damage during significant floods. It shall
be of sufficient height and spacing to allow small pools to form between each one
and also promote sedimentation behind the dam. The check dam shall be
inspected after each rainfall and when a sediment accumulation of approximately
one third (1/3) of the check dam height is observed, the sediment shall be
removed.
24.11
The Contractor shall construct protection works to the drainage inlets and outlets
as shown on the Drawings unless otherwise directed by the S.O. for trapping
sediment and debris. The drainage inlet and outlet protection works may consist of
rock, grouted rip-rap, concrete rubble, gravel, sand bag, wire mesh or trash screen
shall be constructed in such a manner that will facilitate cleanout and disposal of
trapped sediment / debris and minimizes interference with construction activities.
All access roads to the site shall be built away from the existing watercourses,
streams and rivers with proper drainage system and be paved for a distance of at
least 10 m from where these access roads join existing roads.
25.2
The Contractor shall maintain all access roads including the drainage system
throughout the construction period to the satisfaction of the S.O.
25.3
25.4
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
25.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/10
If the Contractor fails to carry out his obligations as stated above, the S.O. shall
carry out such maintenance and restoration and all costs incurred shall be borne
by the Contractor or deducted from any money due or to become due to the
Contractor under this Contract.
The Contractor shall be responsible for controlling all persons under his
employment and those employed by his sub-contractors, merchants and haulers at
the work site and shall take all necessary precautions to prevent damage and
nuisance of any kind and shall indemnify the Government against any claim arising
therefrom.
26.2
The Contractor shall ensure, so far as is practicable, the safety, health and welfare
at work of all his workmen including:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
The provision and maintenance of plant and system of work that is safe and
without risks to health;
Ensuring safety and absence of risks to health in connection with the use or
operation, handling, storage and transport of plant and substances;
The provision for such information, instruction, training and supervision as is
necessary to ensure the safety and health at work of his workmen;
The maintenance of place of work condition, the provision and maintenance
of the means of access to and egress from place of work that are safe and
without risks;
The provision and maintenance of a working environment for his workmen
that is safe, without risks to health, and adequate as regards facilities for
their welfare at work;
Ensuring all workmen have a valid CIDB Green Cards before entering the
construction site.
28. Contractors Temporary Accommodation And Facilities For Workmen Living On Site
28.1
The Contractor shall provide and maintain all temporary accommodation and
facilities including temporary lighting, plumbing and water storage for his labour
and staff living on Site. Such accommodation shall be in the form of standard
cabins or constructed of plywood and/or metal deck or of other materials approved
by the S.O. and provided with adequate facilities to the approval of the S.O., in
accordance with the following requirements:
(i)
(ii)
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/11
(iii)
(iv)
The accommodation quarters shall not be more than two storeys high.
Common areas for dining, recreation and praying purposes shall be
provided.
(v)
Plywood used shall be new and of minimum thickness 12 mm. The external
walls shall be painted.
(vi)
The Contractor shall provide adequate temporary toilets (not less than one
(1) no. for every twenty five (25) workmen) and bathing place with necessary
water, septic tank and drainage in accordance with DOE and/or Local
Authority requirements. It shall be maintained in a clean and sanitary
condition at all times to the satisfaction of the S.O./ Ministry of Health (MOH)/
Local Authority. All wastewater must be treated such that its effluent meets
the requirements of all existing legislation and regulations.
(vii)
(viii) Water used for consumption shall be obtained directly from water authority
mains. Where such water supply is not available, potable water shall be
provided from sources approved by the S.O. Potable water shall comply with
the requirements of the guidelines issued by the MOH.
(ix)
(x)
(xi)
Proper provision shall be made for the disposal of all waste and refuse.
The Contractor shall provide and maintain on the Site in positions as approved by
the S.O. the following adequate, secure and weatherproof temporary building(s) for
use during the execution of the Contract.
(i)
(ii)
(iii)
(iv)
(v)
(vi)
29.2
The Contractor shall store or stack at all times, all materials, tools, et cetera in a
safe and orderly manner so as not obstruct any passageway or place of work.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/12
The Contractor shall provide and maintain a site office for the use of the JKR
supervisory staff all in accordance with JKR design type as shown on the relevant
Drawings inclusive of all fittings and furniture as stated therein.
30.2
30.3
Where relocatable site office is to be provided, the Contractor shall submit details
of the relocatable site office together with his tender. Such details shall include the
name of the manufacturer, floor area and layout, list of fittings and furniture and
brochures (if available). The Contractor shall also indicate whether the proposed
site office is new or had been previously used.
30.4
Unless otherwise shown on the Drawings, the office is to be sited, positioned and
constructed as approved by the S.O.
30.5
The Contractor is also permitted to rent a premise of equivalent floor area and
standard not inferior to the JKR design type and equipped with similar furniture,
fittings and equipment. Where a rented premise is to be provided, the Contractor
shall submit details, which shall include the layout and a list of furniture and fittings
to be provided to the S.O. for approval.
30.6
The Contractor shall make proper arrangement for and pay all charges in
connection with conservancy. The site office shall comply with local building bylaws. It shall be erected or provided by the Contractor and approved by the S.O.
within four (4) weeks from the date of possession of Site.
30.7
On completion of the Works, unless otherwise instructed, the site office with all
fittings and furniture shall become the property of the Contractor and shall be
removed from the Site forthwith.
31.1
The Contractor shall provide a telephone at the S.O.s site office for the sole use of
the S.O. and his representatives in connection with the supervision and
administration of the Contract and pay for all installation, rental, call charges and
disconnection.
31.2
The Contractor shall arrange for the installation of a permanent telephone line
including provision of internet access for the exclusive use of the S.O. and his
representatives in connection with the supervision and administration of the
Contract and pay for all installation, rental, call charges and disconnection.
31.3
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/13
Safety Facilities
32.1.1
The Contractor shall provide the following items for the use of the S.O.
and his supervisory staff throughout the duration of the Contract which
comply with the DOSH requirements:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
(x)
32.1.2
32.2
32.3
Safety boots
Safety helmets
Safety harness and life lines
Protective gloves
Safety goggles
Safety jackets of reflective type
Ear plugs and muffs
Dust masks
.
.
32.2.2
32.2.3
Upon six (6) months after the issuance of the Certificate of Practical
Completion, the equipment shall be returned to the Contractor.
32.2.4
32.3.2
The Contractor shall ensure that the vehicle(s) is/are in a good and well
maintained condition subject to certification from PUSPAKOM at every
six (6) months.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/14
32.3.3
The vehicle(s) shall be in the custody of the Contractor at all times and
be readily available for the use of the S.O and his staff.
32.3.4
32.3.5
32.3.6
Upon six (6) months after the issuance of the Certificate of Practical
Completion, the vehicle(s) shall be returned to the Contractor.
Where specified, the Contractor shall provide a testing laboratory within the site
with a minimum floor area 60 m2 all in accordance with the relevant drawings
including water and electricity supply. The Laboratory shall be equipped with the
necessary equipment required to carry out the tests as identified in APPENDIX A/4
(List of Laboratory Equipment). The Contractor shall be responsible for the
maintenance of the Laboratory and all equipment including all necessary
calibration throughout the duration of the Contract. The laboratory may be jointly
used by the S.O. and the Contractor.
33.2
Alternatively the Contractor may rent a premise of equivalent floor area and
standard not inferior to that of the JKR specified type with similar fittings and
necessary equipment as identified in APPENDIX A/4.
33.3
All tests shall be carried out by qualified laboratory assistant(s) / technician(s) and
shall be witnessed and approved by the S.O.
33.4
Subject to the S.O.s approval, the Contractor may also propose an accredited
laboratory approved by SIRIM as an alternative to the construction of a testing
laboratory.
33.5
All works subject to laboratory test shall not be permitted to commence until the
laboratory and necessary equipment have been provided or the accredited
laboratory has been approved by the S.O.
33.6
All equipment shall be returned to the Contractor six (6) months after the issuance
of the Certificate of Practical Completion.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/15
The Contractor shall supply, erect, maintain and remove on completion of the
Works, adequate, protective and security hoarding and such other safety measures
necessary to ensure the safety of the public and others who may be on or within
the vicinity of the Site.
35.2
The Contractor shall supply, erect and dismantle scaffolding and working platform
with safety nettings by competent person(s) under the direct supervision of a
designated person under the relevant Act.
35.3
For construction works above 15 m high, the Contractor shall submit scaffolding
and working platform design certified by a P.E. to the S.O.
35.4
The Contractor shall supply, erect, maintain and dismantle catch platform during
demolition of structure or other related exterior works at more than 12 m high and
shall be constructed and maintained not more than 6 m below the storey from
which the demolition works are being carried out. Such platform shall be designed
and certified by a P.E. for safety prior to erection. Catch platform shall not be used
for storage of material or be used as working platforms or walkways.
35.5
The Contractor shall erect, maintain and remove safety barricades, fencing, railing,
screen wire netting and toe board for maintaining safe working environment during
the works.
35.6
The Contractor shall provide, maintain and remove guardrails or board fences and
temporary foot walks with adequate overhead protection for public walkways and
thoroughfares during the Works.
35.7
The Contractor shall cordon off working areas and provide public control and safety
measures where lifting operations, moving, shifting, transferring works are carried
out outside the hoarded up area of the worksite.
The Contractor shall provide and maintain safe working conditions with sufficient
illumination wherever persons are required to work or pass. For passageways,
stairways and landings, the illumination shall be not less than 50 lux.
35.8
35.9
The Contractor shall ensure that all electrical and mechanical tools and equipment
are inspected by a competent or designated person where relevant.
35.10
The Contractor shall hold a valid certificate of fitness for steam boiler, unfired
pressure vessel or hoisting machine other than a hoisting machine driven by
manual power so long as such machineries remain in service.
35.11
Ensure that closed tanks with restricted means of entry and exit, open
manholes, trenches, pipes, flues, ducts, ceiling voids, basements and
other places where there is inadequate ventilation and/or the air is either
contaminated or oxygen deficient, be tested before entry to determine
that there are adequate levels of oxygen present, and that dangerous
amounts of flammable and or poisonous gases are not present.
35.11.2
Establish a safe work system and adopt entry permit system for workers
who will be carrying out their work in confined spaces.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/16
The Contractor shall be required to provide a complete First Aid Kit as stated under
Factory and Machinery (Safety, Health And Welfare) Regulation 1970 which shall
be kept and properly maintained in the Contractors site office. The kit shall be in
the charge of either the Contractors site representative or some other responsible
person who shall be on the Site during all working hours to ensure that the first aid
facilities are available without delay at all times when Works is in progress. At least
one (1) designated person of the Contractors staff shall be trained in first aid
duties.
36.2
The Contractor shall refrain from dumping and/or depositing any form of materials
that are capable of collecting water which afford breeding places for mosquitoes,
rodents, insects and vermin of any kind. All excavation and any portion of the site
where water stagnates or accumulates shall be kept dry by pumping, bailing or
other operations. The Contractor shall pay all charges as may be required by the
MOH and/or Local Authority and employ whatever destructive measures as are
necessary.
36.3
All Works shall be carried out without unreasonable noise level and dust emission.
The Contractor shall take measures to ensure that all equipment and machinery
are in proper working condition so as to minimize the amount of noise and dust
generated. The S.O. may require the Contractor to submit a proposal on how to
reduce excessive noise and dust.
36.4
The Contractor is prohibited from discharging oil and grease to any water course.
Storage tanks for oil and grease shall be placed on concrete base with upstand
edges to contain any spillage. Any spilled oil and grease shall be promptly
removed by the Contractor. The Contractor shall collect and store used oil, grease
and other scheduled wastes and dispose these according to methods approved by
DOE.
36.5
Where the contract period is more than six weeks, the Contractor shall register with
DOSH within seven (7) days after commencement of Works.
36.6
All safety measures shall be carried out in accordance with Occupational Safety
and Health Act (OSHA) 1994 and relevant local by-laws. The Contractor shall be
held solely responsible for all accidents arising from any negligence in this respect.
The Contractor shall employ throughout the entire contract period a competent and
qualified person as Safety and Health Practitioner as below:
(i)
(ii)
Site Safety Supervisor (SSS) to be stationed minimum 15 hours a week for all
projects.
Safety and Health Officer (SHO) to be stationed full time for contracts worth
more than RM20 million.
36.7
The Contractor shall ensure all sub-contractors who employ more than 20 persons
shall appoint a Contractor Safety Supervisor (CSS) to be stationed minimum 5
hours a week;
36.8
The Contractor shall submit Safety and Health Plan (S-Plan) in writing duly signed
by the Director of the company to the S.O. within one (1) month after the receipt of
the Letter of Acceptance. The S-Plan shall be as per APPENDIX A/5. The
Contractor shall submit revised S-Plan whenever required.
36.9
The Contractor shall form a Safety and Health Committee in accordance with the
Occupational Safety and Health Regulations 1996 and organise meetings at
minimum once in every three (3) months.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/17
36.10
The Contractor shall conduct Occupational Safety and Health (OSH) related
training and programmes for the workmen including sub-contractors.
36.11
The Contractor shall carry out site safety and health inspections and submit
monthly safety and health reports to the S.O. in accordance with APPENDIX A/6.
36.12
The Contractor shall provide and maintain safety and health statistic scoreboard at
the entrance of site office and workplace.
36.13
The Contractor shall provide and maintain adequate traffic safety signage, warning
signs and warning lights at place of Works and close proximity to public.
36.14
The Contractor shall provide and maintain traffic control by competent persons
including provision of flagmen where Works is in close proximity to public roads.
36.15
The Contractor shall carry out site safety and health audits as per DOSH
requirements and/or instructed by the S.O.
37. Sanitation
37.1
37.2
All wastewater must be treated such that its discharged effluent meets the
requirements of all existing legislation and regulations.
The contractor shall ensure all waste generated on site shall be managed in
accordance with the Solid Waste And Public Cleansing Management Act 2007 and
Environmental Quality Act 1974 as follows:
(i)
The Contractor shall submit in the approved format the Construction Waste
Management Plan (CWMP) to the S.O. for approval within fourteen (14) days
from the date of site possession.
(ii) The Contractor shall provide Roll-On Roll Off (RORO) for construction waste
and Mobile Garbage Bin (MGB) for domestic waste
(iii) The Contractor shall provide a minimum of one (1) location on site for
segregation and collection of construction and domestic waste.
(iv) The Contractor shall appoint a licensed contractor(s) to collect the
construction waste, scheduled waste and domestic waste from the site to
approved locations for disposal or to recycle the waste.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/18
(ii)
39.1.3 The Contractor shall submit the following documents as per TABLE A1 to
the S.O. for approval:
TABLE A1: SUBMISSION OF DOCUMENTS
Documents
EMP
Environmental Quality
Report (EQR)
Environmental Monitoring
And Audit Report
(EMAR)
Closure Audit Report
(CAR)
No. Of
Copies
Reporting Frequency
Timing
Once only ( to be
updated when necessary)
Monthly
Quarterly
Once Only
The Contractor shall carry out monitoring of water and air quality, noise and
vibration as indicated in the EMP and tests to be carried out by accredited
laboratories. Parameters to be tested are as specified in TABLE A2 (APPENDIX
A/7).
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/19
The Contractor shall allow in his tender price for attendance and facilities upon all
Nominated Sub-contractors. Such attendance and facilities shall include the
following:
(i)
(ii)
Making good of walls, ceilings, floors, roofs, et cetera and finishes thereto
including touching up of all paintwork necessitated, damaged or disturbed by
the Nominated Sub-contractors work.
Affording free and full use of standing scaffolding whilst it remains erected on
the Site.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/20
(vi) Affording free and full use of storage accommodation for materials, equipment
and plant which are for incorporation into the Works and/or which require
protection against weather and deterioration, messrooms, sanitary and welfare
facilities.
(vii) Providing site space only for Nominated Sub-contractors temporary office,
workshops, workmens accommodation and storage of materials, tools, plant
and equipment which are not for incorporation into the Works and not requiring
protection against weather or deterioration.
(viii) Providing temporary water supply, electric power supply, artificial lighting and
paying all fees and charges for fuel, water and electricity consumed including
for testing and commissioning of the whole Nominated Sub-contractors works.
(ix) Liaising with the relevant supply/service authorities for the expeditious
installation of the connections for permanent water and electricity supplies in
the Works making available such supplies to the Nominated Sub-contractors;
and paying all fees and charges for such installation, deposits for such
supplies/services on behalf of the Government. All such payments made, shall
be reimbursed to the Contractor on production of receipted bills.
(x)
(xi) Protecting, watching and taking full responsibility for all Nominated Subcontractors work and unfixed materials and goods intended for use thereon.
(xii) Removing rubbish and debris off the Site and cleaning the Works internally and
externally.
41.2
Unloading, getting in, storing and all handling and hoisting of these materials,
plant and tools into required positions.
(ii)
(iii) Connecting to temporary water and power supplies made available by the
Contractor for the execution of the Works, supplying and running distribution
pipes, hoses, cables, leads, electrical gear, et cetera but excluding payment for
water and electricity consumed.
(iv) Provision of fuel, gas, steam, oil lubricants, chemicals and everything else
necessary (other than water and electricity) for the test running and
commissioning of the Sub-contract Works.
(v)
Any scaffolding, staging, et cetera that are required for the Sub-contract Works
not covered by sub-section 41.1(v) above.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/21
General
This section shall describe the scope of works, qualifications, competency, roles and
responsibilities of the Mechanical and Electrical (M & E) Services Coordination
Team.
43.2
43.3
Scope Of Work
43.2.1
43.2.2
43.2.3
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/22
The Contractor shall make every effort to keep the Site in a reasonably clean and
tidy condition for the duration of the Works. He shall, in addition, from time to time
and on the completion of any area of the Works or where directed by the S.O.,
remove rubbish, surplus materials, or any other construction debris from such areas
as may be attributable to his work under this Contract and generally maintain the
Site in a satisfactory condition, to the approval of the S.O.
44.2
The Contractor shall gather up and clear away all rubbish as it accumulates during
the progress of the Works at least twice each week at times approved by the S.O.
The services shall be continued until the completion of the Works. Garbage or
construction waste shall be disposed in a locally available landfill or hauled to
disposal sites approved by the S.O.
The Contractor shall provide and deliver to the S.O. approved As-built drawings
after completion of each section of the Works in the form of :
(i)
45.2
The As-built drawings supplied shall be comprehensive and to the satisfaction of the
S.O. as to allow for a complete understanding of the Works as they were actually
built incorporating all Works arising from variations, expenditure of Provisional Sums
and Prime Cost Sums.
45.3
The
As-built
drawings
shall
be
endorsed
by
a
Professional
Architect/Engineer/Surveyor registered with the respective Professional Boards in
Malaysia.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/23
The Contractor shall ensure the existing roadside drains bounding the Site are clear
of any building debris, earth, et cetera, at all times before handing over of the Works
to the S.O. upon completion.
46.2
Upon completion of the Works, the Contractor shall remove and clear away from
Site all temporary buildings, temporary works, temporary installation and equipment,
and ensure the Site is in a clean and tidy condition.
46.3
Before handing over of the Works, the Contractor shall scrub all floors, pavings,
staircases et cetera and clean out all gutters, gulleys, manholes, sumps and drains.
The Contractor shall also clean all glass panes and leave every part of the
completed Works included in this Contract in a clean, sound and tidy condition to
the approval of the S.O.
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/24
APPENDIX A/1
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/25
APPENDIX A/2
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/26
APPENDIX A/3
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/27
APPENDIX A/4
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/28
APPENDIX A/5
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/29
APPENDIX A/6
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS
JKR MALAYSIA
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
A/30
APPENDIX A/7
Aspects
Soil loss
Soil
Water
Parameter
1,2
Air3
Turbidity
Suspended
Solid
Biochemical
Oxygen
Demand 5 @
20C (BOD)5
Chemical
Oxygen
Demand
(COD)
pH
Environment Quality
(Sewage) Regulations,
2009
National Water
Quality Standards
(NWQS)
Standard A
Standard B
Class IIA
Class IIB
Minimum earthwork
Phase construction
6 berms/benches
for slopes ( 6m per
berm) Reuse topsoil
200 NTU
50 NTU
100 mg/l
50 mg/l
100 mg/l
50 mg/l
50 mg/l
20 mg/l
50 mg/l
3 mg/l
100 mg/l
120 mg/l
200 mg/l
25 mg/l
5.5 9
69
5.5 9
6-9
100
counts/
100ml
400
counts /
100 ml
E-Coli
400 counts /
100 ml
Dissolved
Oxygen(DO)
4 mg/l
5-7 mg/l
10 mg/l
5 mg/l
10mg/l
40 g /l, N
Ammoniacal
Nitrogen (river)
10 mg/l
20mg/l
0.3 mg /l
Noise4
Vibration5
Reference:
nd
1) 2 Schedule (Regulation 7), Environmental Quality (Sewage) Regulations 2009, Environmental Quality Act 1974.
(i) Standard A: For location with downstream water intake
(ii) Standard B: For location with no downstream water intake
2) National Water Quality Standards for Malaysia
(i) Class IIA: Water Supply II conventional treatment required
a) Fishery II sensitive aquatic species
(ii) Class IIB: Recreational use with body contact
3) Recommended Malaysian Guidelines on Ambient Air Quality
4) Schedule 1 & Schedule 6, Planning Guidelines for Environmental Noise Limits & Control, (DOE, 2004)
5) Planning Guidelines for Vibration Limits and Control of the Environment (DOE, 2004)
Note: N - No visible floatable materials or debris or no objectionable odour, or no objectionable taste
TABLE OF CONTENTS
SECTION B: EXCAVATION AND EARTHWORKS
PAGE
1.
2.
3.
4.
5.
6.
7.
General
Site Clearing, Grubbing And Stripping Topsoil
Demolition Of Existing Structures
Relocation Of Existing Utilities And Services
Excavation Works
B/1
B/1
B/2
B/2
B/2
B/6
Filling Works
B/8
B/11
B/13
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/1
1. General
1.1
This work shall consist of all the required excavation within the limits of the Works. It
shall include the removal and proper utilization and hauling, or disposal of all
excavated materials, and constructing, shaping and finishing of all earthworks over
the entire extent of the Works, in conformity with the Drawings and these
Specifications.
1.2
The excavation and earthworks shall be executed in such a manner and order as
approved by the S.O. The Contractor shall be responsible for compliance with bylaws and regulations relating to earthworks.
1.3
Excavation in rock and/or hard material shall respectively be measured and paid for
as extra over to excavation and earthworks in accordance with the Provisional B.Q.
The Contractor shall give reasonable notice to the S.O. to examine, classify the
excavation and to take measurement prior to breaking up.
1.4
1.5
For contract based on Quantities, the pricing shall be in accordance with the B.Q.
1.6
1.7
The Contractor shall comply with all statutory requirements and regulations such as
payment of royalties and environmental protection for removal of unsuitable material
and borrow materials.
This work shall consist of clearing, grubbing and stripping topsoil in the areas within
the limits of Works designated hereunder and/or shown on the Drawings and/or
directed by the S.O., and of clearing only in other areas designated hereunder
and/or shown on the Drawings and/or directed by the S.O., all as specified herein
and as required by the S.O. The work shall also include the demolition and disposal
of structures in the said areas, except where otherwise provided for in the Contract,
as specified herein and as required by the S.O.
2.1.1
Site clearing
Clearing shall consist of cutting and/or taking down, removal and disposal
of everything above ground level, including objects such as walls, fences,
drains and other obstructions, except such trees, vegetation, structures or
parts of structures and other things which are designated in the Contract to
remain, to be protect as satisfied under SECTION R : LANDSCAPING AND
TURFING WORKS. The material to be cleared shall include but not
necessarily be limited to trees, stumps (parts above ground), logs,
brushwood, undergrowth, long grasses, crops, loose vegetable matter and
structures (except those structures whose removal or clearance is
otherwise provided for in the Contract). Clearing shall also include levelling
of obsolete dikes, terraces, ditches, et cetera, unless otherwise directed by
the S.O.
2.1.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/2
Grubbing
Grubbing shall consist of removal and disposal of surface vegetation, bases
of stumps, roots, underground parts of structures, and other obstructions to
a depth of at least 0.50 m below ground level, with the agreement of the
S.O.
2.1.3
Stripping topsoil
Stripping topsoil shall consist of the removal of topsoil to an average depth
of at least 100 mm below ground level, and its stockpiling for use in the
Works, and/or its disposal, as directed by the S.O.
2.1.4
Disposal
All materials resulting from site clearing, grubbing and stripping topsoil shall
be removed and disposed of as approved by the S.O. in accordance with
Environmental Quality Act 1974(Act 127) and Solid Waste and Public
Cleansing Management Act 2007 (Act 672).
Major structures are those which cannot practicably be cleared by bulldozer and/or
hydraulic excavator, whose demolition requires pneumatic tools, explosives and/or
other specialized equipment. A brief description of each major structure (if any) and
depth to which extent it shall be demolished is given in the B.Q.
3.2
All fences, buildings, structures, and encumbrances of any character within the
limits of the limits of the Works, except those to be removed by others or designated
to remain, shall be demolished and removed by the Contractor.
3.3
The Contractor's attention is specially drawn to his responsibilities under the Clause
headed Damage to Property' of the Condition of Contract.
4.2
4.3
If during excavation, the Contractor's workmen uncover any cables, water or other
service pipes, work shall be stopped immediately and shall not be again started until
the matter has been reported to the S.O. who will notify the appropriate local
authority, and subsequently issue whatever directions he deemed appropriate.
5. Excavation Works
5.1
General Requirements
5.1.1
The work shall include the excavation of all types of material, backfilling,
compaction, forming embankments and slopes, et cetera, as is necessary
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/3
5.2
5.1.2
5.1.3
In pumping water out from excavation and in the lowering of water table
the Contractor shall pay due regard to the stability and settlement of all
structures.
5.1.4
5.1.5
5.1.6
Definitions
5.2.1
Formation level
Formation level means the final earthwork level after cutting or filling.
5.2.2
Common excavation
Common excavation shall mean excavation in any materials which are not
rock or hard materials as defined in sub-sections 5.2.5 and 5.2.6.
5.2.3
Unsuitable materials
5.2.3.1
5.2.3.2
Materials that are soft or unstable merely because they are too
wet or too dry for effective compaction shall not to be classified
as unsuitable, unless otherwise classified by the S.O.
5.2.4
5.2.5
5.2.6
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/4
Suitable materials
5.2.4.1
5.2.4.2
5.2.4.3
Hard material
5.2.5.1
This shall mean any hard material which can be excavated using
an excavator with minimum weight of 44 tonnes and nett
horsepower rating of 321 brake horsepower with production rate
not exceeding 50 m3 / hour. The excavator unit is to be in good
condition and operated by experienced personnel.
5.2.5.2
Hard material shall exclude individual masses less than 0.5 m3.
5.2.5.3
Rock
5.2.6.1
(ii)
Ripping unit
The ripper to be attached to the above mentioned tractor
shall have a minimum penetration force of 120 kN. The
ripper shall have a single shank in good working condition
with sharpened cutting point.
5.2.6.2
5.2.6.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/5
Dimensional Tolerances
Slopes in cutting shall be trimmed mechanically to neat and even surfaces which
shall have gradients not steeper than that shown on the Drawings. Widths of
excavations shall not exceed the dimensions shown on the Drawings by more than
300 mm with encumbrance free to complete the Work, unless otherwise approved
by the S.O.
5.4
5.5
5.6
5.7
5.5.2
5.6.2
Unsuitable material shall be excavated to such depth and over such area
as shown on the Drawings and/or directed by the S.O. and be transported
and disposed off in an approved manner. Unless approval of the S.O. to
dump and spread the unsuitable material within the Site is obtained, the
Contractor shall be responsible for providing his own dump site for such
unsuitable material.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/6
5.8
% Passing By Weight
100
85 100
0 20
05
100
90 100
45 80
10 30
2 - 10
Sides Of Excavation
The Contractor shall ensure that at all times, the sides of the excavation are
maintained in a safe and stable condition, and shall be responsible for the adequate
provision of all shoring and strutting including sheet piling required for this purpose.
All temporary works shall comply with the requirements of BS 5975.
5.9
5.10
Widening Cuts
5.9.1
The S.O. may instruct the Contractor or the Contractor himself may elect to
obtain material for the Works by widening cuts. In the latter case, the
Contractor shall first request permission in writing from the S.O.
5.9.2
Widening of cuts shall not be permitted beyond the limits of the road
reserve.
5.9.3
Any additional costs and time incurred that resulted from widening cuts shall
be borne by the Contractor.
Excavation Of Rock
5.10.1 Rock excavation shall be carried out by methods appropriate to site
requirements as approved by the S.O. As far as is practicable the
Contractor shall not use blasting methods for excavations.
5.10.2 Where the excavation is too hard to be performed by digging, dozing,
scraping, ripping, splitting, breaking, jack picking or other such methods, the
Contractor may make a written request to the S.O. for permission to blast.
Such permission will be granted only if the S.O. is satisfied that all
reasonable measures have been tried to carry out the excavation by
methods other than blasting.
5.10.3 Where explosives are used, the Contractor shall provide a method
statement and shall comply fully with requirements of these Specifications,
or any direction, order, requirement or instruction given by the PDRM or any
other authority competent to do so under any written law.
5.10.4 All material from rock excavations shall be used as far as is practicable in
the Works.
5.10.5 Where the rock is of satisfactory quality, the Contractor may elect to crush
and screen it to produce aggregates required for concrete, road base, sub-
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/7
base, or other purposes with the prior approval of the S.O. Excavated rock
needed for earthwork construction which the Contractor elects so to use for
producing aggregate materials shall be replaced at the Contractor's own
expense by borrow materials of satisfactory quality from alternative
locations approved by the S.O.
5.10.6 Otherwise, excavated rock shall be used in the construction of embankment
and fill, to the fullest practical extent, in either of the two (2) following ways:
(i)
(ii)
5.10.7 The Contractor may only waste excavated rock with the approval of the
S.O. Excavated rock needed for earthwork construction which the
Contractor elects to waste shall be replaced at the Contractor's own
expense by borrow materials of satisfactory quality from alternative
locations approved by the S.O.
5.11
5.12
Blasting
5.12.1 Explosives shall be used in the quantities and manner recommended by the
manufacturers and blasting specialist. Blasting shall be restricted to such
periods as the S.O. may prescribe and to comply with all authorities
requirement. If, in the opinion of the S.O., blasting would be dangerous to
persons or properties or to any finished work, or is being carried on in a
reckless manner, he may prohibit it, and order the rock to be excavated by
other means. The use of explosives in large blasts, that is exceeding 9 kg of
explosive, as in seams, drifts, shafts, pits, or large holes, is prohibited
unless authorised in writing by the S.O. Such authorisation shall not in any
way relieve the Contractor of his liabilities under the Conditions of Contract.
5.12.2 All necessary precautions shall be taken to preserve the materials below
and beyond the lines of all excavations in the soundest possible condition.
Delayed blasting to reduce shock waves shall be used to avoid damage to
concrete and other works already completed. As the excavation approaches
its final lines, blasting with pre-splitting technique of approved drill hole
spacing shall be carried out to reduce blast damage and create reasonably
even finished surface by means of parallel drill holes perpendicular to the
toe of the excavation and parallel to the finally required face.
5.13
Safety Measures
5.13.1 When blasting is carried out close to properties or roads, safety rules
complying to authorities requirements shall be strictly adhered to. Where
necessary or as directed by the S.O., heavy mesh blasting mats shall be
used to ensure that no damage is caused to persons or properties on or off
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/8
Site. Special care shall be taken in wet ground to ensure that individual
explosions are reduced to such size as to preclude damage to any buildings
or structures. Plaster shooting will not be permitted within 400 m of any
building or structure. If traffic on any road or railway has to be interrupted for
blasting operations, the Contractor shall obtain approval of his schedule for
such interruption from the appropriate authorities and shall prove to the S.O.
that he has obtained it, prior to the interruption.
5.13.2 When blasting is carried out with close proximity to sensitive structures and
environmental sensitive areas, thresholds and criteria of vibration impact
shall be established for monitoring purpose.
5.14
Insecure Material
The cut slopes shall be cleared of all rock fragments which move when pried with a
crow-bar. The Contractor shall excavate any insecure material to an approved depth
and build up the resulting spaces with Grade 15P/20 concrete or masonry using
rock similar to the adjoining natural rock so as to ensure a solid face.
6. Filling Works
6.1
6.2
Material
6.1.1
6.1.2
The fill material shall be free from roots, grass, other vegetable material,
clay lump or material of particles size larger than 150 mm.
6.1.3
Sand shall not be used as fill materials at outer edges of the embankment.
Borrow Pits
6.2.1
6.2.2
The Contractor shall keep the borrow pits free from water ponding and the
excavation neat and tidy. The contractor shall make sure the side-wall of the
borrow pits is stable, protect the slope surface by turfing and shall carry out
other necessary erosion and environmental protection measures following
the agreed method statement or as instructed by the S.O.
6.2.3
The following tests should be carried out for each 1,500 m3 of material to be
placed or more frequent tests as required by the S.O. :
(i) Atterberg limits
(ii) Gradation analysis
(iii) M.S 1056 Compaction Test (2.5 kg rammer method)
6.3
6.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/9
All fill materials shall be deposited in layers and brought up at a uniform rate
so that all parts of the Site reach finished level at the same time. The loose
depth for each layer of fill shall be determined from the trial compaction.
Each layer shall extend over the full width of the fill area and shall be
compacted in accordance with the requirements of sub-section 6.4. Each
compacted layer shall be maintained at all times with a sufficiently even
surface of longitudinal and cross slope in order to drain away the surface
water.
6.3.2
6.3.3
Compaction
6.4.1
6.4.2
General
6.4.1.1
6.4.1.2
Compaction trials
6.4.2.1
6.4.2.2
The Contractor shall submit to the S.O. for his agreement the
proposed method of compaction for each main type of material to
be used in the embankment. This shall include the type of
compaction plant for each type of material and the number of
passes in relation to the loose depth of material to achieve
desired compaction. The maximum loose thickness for fill shall
generally be limited to 300 mm unless trial compaction shows
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/10
compliance with larger loose thickness and with the approval from
the S.O. The Contractor shall carry out field compaction trials,
supplemented by any necessary laboratory investigations, as
required by the S.O. This shall be done by using the procedures
proposed by the Contractor for earthworks and shall demonstrate
to the S.O. that all the specified requirements regarding
compaction can be achieved. Compaction trials with the main
types of material likely to be encountered shall be completed
before the works with the corresponding materials will be allowed
to commence. Each trial area shall be not smaller than 8 m x 15
m.
6.4.2.3
6.4.3
Degree of compaction
The whole of the fill area shall be compacted to not less than 90% (for
cohesive material) or 95% (for cohesion less material) of the maximum dry
density determined in the latest MS 1056: Compaction Test (2.5 kg-rammer
method), unless otherwise as shown on the Drawings.
6.4.4
6.4.5
6.4.6
Moisture control
6.4.5.1
6.4.5.2
If the natural water content of suitable material is too high for the
proper compaction to be carried out, the Contractor can either
bring down the moisture content by aeration or drying or
alternatively replace it with suitable materials of compactable
moisture range at his own cost.
Air voids
To reduce potential of collapse compression of unsaturated cohesive fill due
to wetting, the moisture content range at fill placement shall be controlled to
achieve a compacted fill with allowable air void content not exceeding 5 %.
6.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/11
For each compacted fill materials, the frequency of control tests shall be in
accordance with TABLE B2. The control tests shall be evenly allocated to
each compacted layer of the entire compacted fill. Each control test shall
provide moisture content, dry density and air void content.
6.6
6.7
Type of Material
Frequency of Test
Compacted material
6.5.2
For California Bearing Ratio (CBR), the frequency of test shall not be less
than one test per 4000 m2 of compacted subgrade surface completed or
otherwise as directed by the S.O.
6.5.3
If certain test methods are used for the reasons of speed and economy,
calibration between such tests and the master test method as per latest MS
1056 shall be carried out at the interval of every 100 tests subject to the
S.O. agreement. The calibration is material specific and shall be performed
for each material type. The non-master test method with variation of more
than 5 % shall be rejected.
6.6.2
There shall be a transition layer between rock fill and earth fill or the top 300
mm of subgrade of at least 300 mm compacted thickness. This shall consist
of uniformly graded crushed rock between 6 mm and 150 mm as approved
by the S.O.
6.6.3
Foundation treatment
6.7.1.1
Prior to forming embankment over soft ground, the soil over which
fill material shall be placed shall be given strength improvement
treatment as specified and to the details as shown on the
Drawings or as directed or approved by the S.O. Treatment by
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/12
6.7.2
6.7.1.2
The first layer of fill materials shall be deposited over the full width
of the embankment and berms in thicknesses not more than 500
mm or as approved by the S.O. to sufficiently support earthwork
machineries.
6.7.1.3
6.7.3
6.7.4
Geotechnical instrumentations
6.7.3.1
6.7.3.2
Monitoring records
6.7.4.1
6.7.4.2
For the measurement of the volume that has settled below the
original level of the foundation of the embankment, the measured
settlement of each settlement gauge shall be used for volume
computation following the method shown on the Drawings.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/13
7.2
Hydroseeding
7.2.1
Hydroseeding shall be carried out after the proposed slope surface exceeds
1000 m2 or within two (2) weeks after cutting or one (1) week during
monsoon season, whichever is earlier on all slopes and other areas as
shown on the Drawings and/or directed by the S.O. Every measure should
be taken to ensure that the grass seed properly germinate at the intended
location as shown on the Drawings at Contractors expense.
7.2.2
The Contractor shall submit to the S.O. for his consideration and approval,
at least four (4) weeks in advance of the proposed work, full details of his
proposed method of hydroseeding. The information submitted shall include,
but not necessarily be limited to, a full description of the following aspects of
the work:
(i)
(ii)
(iii) the types of grass and legume (if any) and strains of seed to be used,
and the function, root and growth characteristics of each type;
(iv) the rates of application of the grass and legume seeds;
(v)
(xi) the equipment and methods to be used in preparing and placing the
hydroseeding mix and other materials;
(xii) the cultivation and after-care of the seeded areas, including rates and
frequencies of watering, fertilising, grass cutting and general
maintenance for at least one (1) year after hydroseeding;
(xiii) the time after hydroseeding required for establishing permanent, dense
growth of grasses, which will require minimal maintenance;
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
B/14
(xiv) the temporary erosion protection materials used for protecting the
seeds;
(xv) guarantees the success of the hydroseeding work.
7.2.3
7.3
Creepers
7.3.1
7.3.2
The Contractor shall submit to the S.O. for his consideration and approval,
at least four (4) weeks in advance of the proposed work, full details of his
proposed method of planting the creepers. The information submitted shall
include, but not limited to, a full description of the following aspects of the
work:
(i)
(ii)
(iii) the types of creepers to be used, and the function, root and growth
characteristics of each type;
(iv) the composition of fertilizer to be used at the time of planting the
creepers and its rate of application;
(v)
7.4
TABLE OF CONTENTS
SECTION C: FOUNDATION WORKS AND WORKS BELOW LOWEST
FLOOR LEVEL
PAGE
1.
2.
3.
4.
5.
6.
7.
Shallow Foundations
Deep Foundations
Subterranean Termites Treatment
Damp Proof Membrane (DPM)
Damp Proof Course (DPC)
Filling Under Floors, Aprons Et Cetera
Hardcore
C/1
C/1
C/36
C/37
C/37
C/38
C/38
TABLE C1
TABLE C2
APPENDIX C/1
TABLE C3
TABLE C4
C/39
C/39
C/40
C/40
TABLE C5
TABLE C6
C/41
C/41
C/42
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/1
1. Shallow Foundations
1.1
1.2
General
1.1.1
Shallow foundations are defined as those where the depths are less than 3
m below the finished ground level.
1.1.2
1.3
1.4
Excavation
1.3.1
1.3.2
Materials
1.4.1
Concrete
The materials and workmanship for concrete shall be as specified in
SECTION D: CONCRETE WORKS.
1.4.2
Reinforcement
The steel reinforcement shall be as specified in SECTION D: CONCRETE
WORKS.
2. Deep Foundations
2.1
General
Deep foundations are defined as those where the depths are more than 3 m below
the finished ground level.
2.2
Piling Works
All piling works shall conform to BS 8004 and MS 1314 unless otherwise specified.
2.2.1
Definitions
2.2.1.1
Preliminary pile
A preliminary pile is a pile installed before the commencement
of the main piling work for the purpose of establishing the
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/2
Working pile
A working pile is a pile which is installed as part of the
permanent foundation work.
2.2.1.3
2.2.1.4
Ultimate load
(i)
(ii)
Working load
The Working Load is the Design Load modified to allow for
group effect, pile spacing or any other factors changing the
efficiency of the total foundation from that of a single isolated
pile, and is at least equal to the dead plus imposed loads on the
pile together with downdrag or uplift loads as appropriate.
2.2.2
2.2.3
2.2.2.2
The Contractor shall study the given soil report in detail and
make his own interpretation of the information provided and to
make due allowance for the effect of site conditions on his
construction operations.
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/3
2.2.4
2.2.3.2
2.2.3.3
The Contractor shall not change the methods which have been
approved by the S.O. Approval by the S.O. of the Contractors
proposed methods of construction shall not in any way relieve
the Contractor of any of his duties or responsibilities under the
contract.
Setting out
Setting out shall be carried out using the data and reference points as
shown on the Drawings. The pile position shall be marked with suitable
identifiable pins, pegs or markers at least 300 mm length. The pins, pegs
or markers should be driven to ground level and the location marked with
contrasting material. If raking piles are to be installed then the setting out
pins, pegs or markers is located in an offset position at piling platform level
taking into account of depth to cut-off level and rake value of the pile. In
addition, the alignment of pins, pegs or markers shall indicate the direction
of the rake. Immediately before installation of the pile, the pile positions
shall be checked by the Contractor again.
2.2.5
Position
For a pile cut off at or above ground level the maximum permitted
deviation of the pile centre from the centre points shown on the Drawings
shall not exceed 75 mm in any direction. For a pile cut off below ground
level an increase in this tolerance of 150 mm is permitted in accordance
with sub-sections 2.2.6 and 2.2.7 herein. No pile edge shall be nearer than
150 mm from the edge of any pile cap.
2.2.6
Verticality
The maximum permitted deviation of the finished pile from the vertical is 1
in 75.
2.2.7
Rake
The piling rig shall be set and maintained to attain the required rake. The
maximum permitted deviation of the finished pile from the specified rake
or the rake shown on the Drawings is 1 in 25.
2.2.8
Forcible corrections
Forcible corrections to concrete piles shall not be permitted. Forcible
corrections may be permitted to specific types of piles if approved by the
S.O. However, no forcible corrections shall be made to piles which have
deviated beyond the permissible limits specified in sub-sections 2.2.5,
2.2.6 and 2.2.7.
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.2.9
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/4
2.2.10
2.2.11
2.2.12
Adjacent structures
2.2.11.1
2.2.11.2
2.2.11.3
The Contractor shall be responsible for and shall bear the cost
incurred including claims for damages arising from his
execution of the piling works.
Existing services
The Contractor shall give all required notices to the appropriate utility
authorities before commencement of piling works. The Contractor shall
also locate existing services by piloting, protect existing services, rectify
any damage or interference to them and provide temporary support while
repairs are being carried out if so required.
2.2.13
Materials
2.2.13.1
Concrete
The materials and workmanship for concrete shall be as
specified in SECTION D: CONCRETE WORKS.
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.2.13.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/5
Reinforcement
The steel reinforcement shall be as specified in SECTION D:
CONCRETE WORKS.
2.2.13.3
Pile shoes
(i)
(ii)
Supply of piles
The contractor shall only use precast concrete piles supplied by approved
manufacturers. Before the commencement of piling work, the contractor
shall notify the S.O. the name of the manufacturers. The Contractor shall
provide the manufacturer mill certificate. All piles found damage during
supplied should be taken out from site.
2.2.15
2.2.16
2.2.15.2
2.2.15.3
Welding
Unless otherwise specified, all welds shall be full penetration butt welds
complying with the requirements of BS EN 12334.
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.2.17
2.2.18
2.2.19
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/6
Welders qualifications
2.2.17.1
2.2.17.2
Damage to piles
2.2.18.1
2.2.18.2
Safety precautions
The Contractor shall take safety precautions throughout the piling
operation in accordance with the requirements of the relevant laws and bylaws.
2.2.20
Records
The Contractor shall keep records of the installation of each pile and shall
submit two (2) signed copies of these records to the S.O. not later than the
next working day after the pile has been installed. The signed records shall
form part of the records for the Works. Any unexpected driving or boring
conditions shall be noted in the records.
2.2.21
2.3
Pitching of piles
Piles shall be pitched accurately in the positions as shown on
the Drawings. At all stages during driving and until the pile has
set or been driven to the required length, all exposed piles
shall be adequately supported and restrained by means of
leaders, trestles, temporary supports or other guide
arrangements to maintain position and alignment and to
prevent buckling and damage to the piles.
2.3.1.2
Driving of piles
(i)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/7
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/8
(vii) In soils that dilate when disturbed e.g. silts and some
shales, negative pore pressure can be set up temporarily
and the driving resistance may fall as these pore pressure
return to normal. In clays disturbance can cause positive
pore pressure to develop and the strength of the soil may
increase as these dissipate. The necessary time interval
before redriving may vary from one (1) hour to two (2)
hours for non-cohesive soils or two (2) days or more for
clays.
(viii) The resistance at the start of redriving is more likely to be
representative of the true bearing value of the pile, and
each redriving result should be taken into consideration
when deciding the pile penetration length.
(ix) Piles shall be driven in an approved sequence to minimise
the detrimental effects of heave and lateral displacement
of the ground. When required, careful levelling from a
datum unaffected by the piling shall be made on the pile
heads already driven, before and after driving subsequent
piles. Piles which have been displaced vertically by more
than 3 mm as a result of driving adjacent piles shall be
redriven to the required resistance.
2.3.1.3
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/9
2.3.1.5
Lengthening of piles
(i)
(ii)
2.3.1.6
Care shall be taken to form the joint between the old and
new concrete as specified hereinbefore. The old concrete
shall be adequately roughened and all loose particles shall
be removed by wire brushing, followed by washing with
clean water. The extension shall be truly in line at all
stages of handling and driving with the remainder of the
pile and be properly cured and allowed to harden
sufficiently to develop the strength necessary for further
driving.
Pile joint
The bending strength test of pile joint shall be done for laterally
loaded pile only to determine the bending capacity at each
respective joint. The test shall be done as in 2.3.1.7 provided
that the joint is positioned at the centre of the span. The
bending capacity at the pile joint shall be greater than the
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/10
2.3.1.8
Butt welding
aa) The extension bars shall butt on the projecting
bars in true alignment and shall be butt welded
in accordance with sub-section 2.7.4 of this
Specification.
ab) Redriving of the piles shall only be allowed after
the welded joints have sufficiently air cooled to
100C or below.
b)
Splicing
The projecting bars shall be stripped of all
surrounding concrete as necessary to allow splices
of length 60 diameters with extension bars. The
extension bars shall be securely bound to the
projecting bars with 1.63 mm soft annealed iron wire.
The concrete of the pile shall be made good either
before or together with the casting of the pile cap, all
to the satisfaction of the S.O. Care shall be taken to
avoid cracking or otherwise damaging the rest of the
pile. Any cracked or defective concrete shall be cut
away and made good with new concrete properly
bonded to the old.
2.4
Materials
2.4.1.1
Concrete
The materials and workmanship for concrete shall be as
specified in SECTION D: CONCRETE WORKS.
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.4.1.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/11
Reinforcement
(i)
(ii)
Transfer of prestress
The minimum concrete cube strength at transfer should be 30
N/mm2. All test cubes should be stored under same conditions
as the piles.
2.4.1.4
End plates
Details of end plates of each length of pile shall be as shown on
the Drawings. Each end plate shall be machine-finished and
provided with a chamfer to accommodate the welding when two
(2) lengths of pile are jointed.
2.4.1.5
Pile shoes
If specified, the type of pile shoes to be used shall be as shown
on the Drawings and shall be in accordance with sub-section
2.2.13.3.
2.4.2
2.4.2.2
Lengthening of piles
Where lengthening of piles is required, the details of the joint
shall be as shown on the Drawings and in accordance with subsection 2.7.4. When two (2) lengths of pile are jointed, the end
plates shall bear over their complete areas. Shims for packing
shall not be accepted. For laterally loaded pile, the pile joint
shall be in accordance with sub-section 2.3.1.5.
2.4.2.3
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/12
Description
This work shall comprise the boring or grabbing, with or without casing,
and subsequently filling the hole with plain or reinforced concrete to form
bored cast-in-situ piles, all in accordance with this Specification and to the
details shown on the Drawings.
2.5.2
Materials
2.5.2.1
Concrete
The materials and workmanship for concrete shall be as
specified in SECTION D: CONCRETE WORKS. The grade of
the concrete shall be as shown on the Drawings.
2.5.2.2
Reinforcement
The steel reinforcement shall be as specified in SECTION D:
CONCRETE WORKS. The details of the steel reinforcement
shall be as shown on the Drawings.
2.5.2.3
Permanent casings
Permanent casings which form part of the designed pile shall
be as specified on the Drawings.
2.5.2.4
Support fluid
(i)
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.5.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/13
Boring Operations
2.5.3.1
2.5.3.2
Diameter of piles
(i)
(ii)
Boring
(i)
(ii)
(iii) Piles shall not be bored at a distance less than three (3)
times diameter close to other piles which have recently
been cast and which contain workable or unset concrete.
2.5.3.3
Drilling in rock
The Contactor shall submit a method statement when drilling in
rock. Chiselling of rock may cause micro cracks in surrounding
rock and is not allowed.
2.5.3.4
2.5.3.5
Temporary casings
(i)
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/14
2.5.3.7
(ii)
Pumping of boreholes
Pumping from the borehole shall not be permitted unless a
casing has been placed into the stable stratum to prevent the
further ingress of water in significant quantities from other strata
into the boring, or, unless it can be shown that pumping will not
have a detrimental effect on the surrounding soil or its
properties.
2.5.3.8
2.5.3.9
Continuity of construction
(i)
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.5.3.10
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/15
2.5.3.11
Inspection
For dry boreholes, each hole shall be inspected prior to the
placing of concrete in it. The inspection shall be carried out from
the ground surface in the case where the borehole diameter is
less than 1500 mm. Where the borehole diameter exceeds
1500 mm, adequate equipment shall be provided to enable the
Contractor and the S.O. to descend into the borehole for the
purpose of inspection. All works shall conform to the
requirement of BS 5537: Safety Precaution in the Construction
of Large Diameter Borehole for Piling and Other Purposes. For
wet boreholes, i.e. holes filled with drilling fluid or water, a
suitable probe shall be provided to ascertain the evenness and
cleanliness of the pile base.
2.5.4
Placing of reinforcement
2.5.4.1
2.5.4.2
2.5.5
Positions of reinforcement
(i)
(ii)
Concreting operations
2.5.5.1
Placing concrete
The method of placing and the workability of concrete shall be
such that a continuous monolithic concrete shaft of the full
cross-section is formed.
2.5.5.2
Workability of concrete
(i)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
(ii)
2.5.5.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/16
Compaction
Internal vibrators shall not be used to compact concrete unless
it can be satisfied that they will not cause segregation or
arching of the concrete.
2.5.5.4
2.5.5.5
(ii)
(ii)
(iii) The hopper and pipe of the tremie shall be clean and
watertight throughout. The pipe shall extend to the base of
the boring and a sliding plug or barrier shall be placed in
the pipe to prevent direct contact between the first charge
of concrete in the pipe of the tremie and the water or
support fluid. The tremie pipe shall at all times penetrate
the concrete which has previously been placed and shall
not be withdrawn from the concrete until the completion of
concreting.
(iv) At all times, a sufficient quantity of concrete shall be
maintained within the tremie pipe to ensure that the
pressure from it exceeds that from the water or support
fluid. The internal diameter of the tremie pipe shall not be
less than 150 mm for concrete made with 20 mm
aggregate and not less than 200 mm for concrete made
with 40 mm aggregate.
(v)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/17
Extraction of casing
2.5.6.1
Workability of concrete
Temporary casings shall be extracted while the concrete within
them remains sufficiently workable to ensure that the concrete
is not lifted.
2.5.6.2
Concrete level
(i)
(ii)
Vibrating extractors
The use of vibrating extractors shall be permitted subject to the
condition that work shall be carried out in such a manner and
at such times as to minimise nuisance and disturbance.
2.5.7
Water levels
In the event of the ground water level being higher than the
required pile head casting level shown on the Drawings, the
Contractor shall submit his proposals for approval prior to
placing concrete. The pile head shall not be left below the
ground water level unless approved precautions are taken.
2.5.7.2
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.5.7.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/18
2.5.7.4
Piling records
(i)
(ii)
b)
Date of concreting
Concrete mix
Method of concreting
Standing ground water level
Length of temporary casing
Length of permanent casing
Details of soil strata penetrated.
Soil samples taken and in-situ tests carried out.
Length and details of reinforcement.
Estimated and actual volume of concrete required to
form the pile shaft.
(iii) All record shall bear the names of person who records and
person who checks.
2.5.8
2.5.8.2
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.6
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/19
Description
This work shall comprise the supply and installation of steel H-section
piles, inclusive of pitching and driving, lengthening and preparation of pile
heads, all in accordance with this Specification and to the details shown on
the Drawings.
2.6.2
Materials
All steel H-bearing piles shall comply with the requirement of BS EN 10025
and or BS EN 10029, BS EN 10210, BS EN 10113, BS 7668 or JIS A5526.
The profile and grade to be used are as specified or as shown on the
Drawings.
2.6.3
2.6.3.2
Manufacturing tolerances
(i)
(ii)
Straightness of sections
(i)
(ii)
Strengthening of piles
Unless otherwise approved by the S.O., the strengthening of
the toe of the pile in lieu of a shoe or the strengthening of the
head of a pile shall be made from material of the same grade as
the pile and to the details as shown on the Drawings.
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.6.3.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/20
Marking of piles
Each pile shall be clearly marked with white undeletable
marking at the flanged head showing its reference number and
overall length. In addition, each pile shall be marked at intervals
of 500 mm along its length before being driven. The length of
piles to be supplied shall be as shown on the Drawings subject
to revision by the S.O.
2.6.3.5
2.6.4
(ii)
2.6.4.2
Lengthening of piles
(i)
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
(ii)
2.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/21
Description
This work shall comprise the supply and installation of steel pipe piles,
inclusive of pitching and driving, lengthening and preparation of pile
heads, all in accordance with this Specification and to the details shown
on the Drawings.
2.7.2
Materials
All steel pipes shall comply with BS EN 10296, BS EN 10297 and BS
EN 10305 with regard to sectional dimensions and the steel shall
comply with the requirements of BS EN 10113 or BS EN 10025.
2.7.3
Welding
Unless otherwise specified, all welds shall be full penetration
butt welds complying with the requirements of BS EN 12334.
2.7.3.2
Fabrication of piles
(i)
(ii)
(iii) For tubular piles where the load will be carried by the wall
of the pile, and if the pile will be subjected to loads that
induce reversal of stress during or after construction, the
external diameter at any section as measured by using a
steel tape on the circumference shall not differ from the
theoretical diameter by more than 1%.
(iv) The ends of all tubular piles as manufactured shall be
within a tolerance on ovality of 1% as measured by a
ring gauge for a distance of 100 mm at each end of the
pile length.
(v)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.7.3.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/22
2.7.3.4
Straightness of piles
For standard rolled sections the deviation from straightness
shall be within the compliance provisions of BS EN 10034 and
in accordance with sub-section 2.6.3.2.
2.7.3.5
2.7.3.6
2.7.3.7
Marking of piles
Each pile shall be clearly marked with white undeletable
marking near the pile head showing its reference number and
overall length. In addition, each pile shall be marked at intervals
of 500 mm along its length before being driven. The length of
piles to be supplied shall be as shown on the Drawings subject
to revision by the S.O.
2.7.4
Workmanship
2.7.4.1
Welding procedures
(i)
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/23
2.7.4.3
Welders' qualifications
(i)
(ii)
Weld tests
(i)
(ii)
b)
For tubes of any wall thickness, continuous ultrasonic examination over the whole weld,
supplemented where necessary by radiographs to
investigate defects revealed by the ultrasonic
examination.
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/24
2.7.5
Circumferential welds
a)
b)
Protective coatings
2.7.5.1
The term coating shall include the primer and the coats
specified. If protective coatings are specified, the preparation of
surfaces and the application of the coatings shall be carried out
by skilled labour having experience in the preparation of the
coatings specified.
2.7.5.2
2.7.5.3
(ii)
2.7.5.5
Surface preparation
(i)
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/25
2.7.5.6
2.7.5.7
(ii)
Part to be welded
The coating within 200 mm of a weld shall be applied after
welding. The method of application shall comply with the
manufacturers recommendations.
2.7.5.8
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
(ii)
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/26
2.7.6.2
2.7.6.3
Lengthening of piles
(i)
(ii)
2.7.6.4
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.8
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/27
Micropiles
2.8.1
Description
This work shall comprise the drilling of a hole, placing of reinforcement unit
and subsequently filling the hole with grout to form micropiles, all in
accordance with this Specification and to the details shown on the
Drawings.
2.8.2
Materials
2.8.2.1
Reinforcement
The type of reinforcement to be used, the diameter and/or
thickness, grade, yield strength and working stress shall be as
specified or as shown on the Drawings.
2.8.2.2
2.8.3
Grout
(i)
(ii)
Drilling operations
2.8.3.1
Diameter of piles
The diameter of piles shall not be less than the
specified/designed diameter at any level throughout its length
and shall be in accordance with sub-section 2.5.3.1.
2.8.3.2
Drilling
The Contractor shall submit to the S.O. details of drilling
equipment and drilling procedure for approval before
commencement of works. Drilling operations shall be carried
out in accordance with the relevant requirements of sub-section
2.5.3.
2.8.4
Grouting operations
2.8.4.1
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/28
Testing grout
(i)
(ii)
Lengthening of piles
Where lengthening is required, the pile reinforcement unit shall
be connected on Site to the details shown on the Drawings.
Other means of jointing reinforcement shall be to the approval
of the S.O.
2.8.5.2
2.9
Pile Testing
2.9.1
2.9.2
General
2.9.1.1
In order to verify the working load, the Contractor shall carry out
pile load test as shown on the Drawings and / or as instructed
by the S.O. The Contractor shall give at least 48 hours notice of
the commencement of construction of any preliminary pile
which is to be test-loaded.
2.9.1.2
Notice of construction
The Contractor shall give at least 48 hours notice of
commencement of construction of any preliminary pile which is
to be tested.
2.9.2.2
Method of construction
Each preliminary test pile shall be constructed in a manner
similar to that to be used for the construction of the working
piles and by the used of similar equipment and material. Extra
reinforcement and concrete of increase strength will be
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/29
2.9.2.4
2.9.2.5
2.9.2.6
Three (3) test cubes shall be made from the concrete used
in the preliminary test pile and from the concrete used for
building up the working pile. If the concrete pile is
extended or capped for the purpose of testing, a further
three (3) cubes shall be made from the corresponding
batch of concrete. The cube shall be made and tested in
accordance with SECTION D: CONCRETE WORKS of
this Specification.
(ii)
The pile test shall not be started until the strength of the
cubes taken from the pile exceed twice the average direct
stress in any pile section under the maximum required test
load and the strength of the cubes taken from the pile
head or cap exceed twice the average stress at any point
in the pile head or cap under the same load.
Cut-off level
(i)
(ii)
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/30
2.9.2.8
Supervision
(i)
(ii)
Notice of test
The Contractor shall give at least 24 hours notice of the
commencement of the test. No load shall be applied to the test
pile before the commencement of the specified test procedure.
2.9.3.2
Prevention of disturbance
Construction activities and person who are not involved in the
testing processes shall be kept at a sufficient distance from the
test to avoid disturbance to any unavoidable activity and its
effects.
Test load
(i)
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/31
2.9.4.2
2.9.4.3
Measuring apparatus
(i)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/32
2.9.4.4
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
2.9.4.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/33
Auxiliary systems
(i)
b)
c)
ab)
ac)
Alternative systems
Any other type of electrical or optical gauge yielding
a precision equivalent to the primary system is
acceptable as and alternative, provided prior
written approval is obtained from the S.O.
2.9.4.6
Measurement of load
(i)
(ii)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/34
2.9.4.7
Measurement of settlement
Settlements shall be measured by use of a reference beam or
wire supported independently of the load test pile, reaction pile
or piles supporting reaction loads. Settlements shall be
measured to the nearest 0.1 mm for reference beams or 0.5
mm for reference wires. The reference beam supports shall be
located at least 3 mm from the load test pile, reaction pile or pile
supporting reaction loads. The reference beams or wires shall
be protected from the effects of temperature changes.
2.9.5
Testing procedure
2.9.5.1
2.9.5.2
General
(i)
(ii)
b)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/35
2.9.6
c)
d)
e)
f)
g)
Submission of results
2.9.6.1
Full test data and results from the readout unit shall be jointly
signed by the S.O.s representative and the Contractors
authorised agent immediately upon completion of the maintain
load test, and shall consist of the following:
(i)
(ii)
(iii)
(iv)
Stage of Loading
Period for which the load was held
Final load and load increment
Maximum settlement
2.9.6.2
2.9.6.3
b)
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
c)
2.9.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/36
Completion of a test
2.9.7.1
2.9.7.2
(ii)
The Contractor shall only appoint termite management company (TMC) that has
adequate equipment, competency and skilled workers to perform expeditiously. The
Contractor shall also ensure that the TMC engage workers who are licensed to
apply the termiticide by the relevant authorities.
3.2
3.3
The Contractor shall submit a termite management programme and provide the
following in writing:
(i) a termite infestation report;
(ii) details of methods proposed and termiticides to be used.
3.4
The Contractors termite management company shall submit the above proposal
with the Material Safety Data Sheet, product label and brochure indicating the
termiticide to be used to the S.O for approval.
3.5
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/37
3.6
Treatment shall not be performed just before or after heavy rain, unless the area to
be treated can be physically protected to avoid leaching and runoff before the
termiticide chemical has bound to the soil.
3.7
Immediately after spraying the chemical, all surfaces exposed to direct sunlight or
rain shall be covered with an impervious black PVC sheet of minimum thickness of
0.08 mm to reduce the loss of chemical by UV light, alkaline wet concrete, leaching
and runoff caused by rain on exposed treated soil. In the case of areas receiving
blinding, the coverings shall be removed immediately prior to the placement of the
blinding concrete.
3.8
As soon as practicable after the completion of anti-termite treatment and prior to the
issuance of the Certificate of Practical Completion, the Contractor shall submit to
the S.O., the anti-termite treatment specialists Guarantee against any termite attack
to the Works which may arise during a period of two (2) years from the date of
Practical Completion of Works due to any defect, fault or ineffective anti-termite
treatment. The terms of the Guarantee shall be such as shall be approved by the
S.O.
3.9
The Contractor shall verify the ground-water table before soil treatment. For this
purpose, the Contractor shall excavate trial holes of not less than 0.5 m deep
measured from the level below the level of the soil to be treated. The restriction to
soil treatment by virtue of this requirement shall not in any way affect or diminish the
Contractor from any indemnity against termite attacks.
DPM shall be installed below the ground concrete floor level or as shown on the
Drawings to prevent the rise of moisture or damp through the structure flooring.
4.2
Unless otherwise specified in the Drawings, the DPM shall be extruded polythene
film with a nominal thickness of 0.5 mm. The nominal weight shall not be less than
0.45kg/m and the tensile strength shall be not less than 44 MPa in accordance with
ISO 527.
4.3
Unless the application surface is smooth it shall be blinded with compacted soft
sand to guarantee a soft bed, free from any objects that may puncture the
membrane during the installation or when concrete is applied.
4.4
When laying two (2) sheets of DPM, a minimum of 150 mm overlap shall be
provided between each of the sheets and sealed with 100 mm wide jointing tape.
4.5
Any punctures in the membrane shall be patched with sheets of identical thickness
lapped at least 150 mm away from the perforation edge and sealed with double
sided pressure sensitive tape.
4.6
The DPM shall be covered with a protective layer or screed as soon as possible
after the membrane has been installed. Care shall be taken when applying concrete
or screed on top the DPM to avoid stretching or the DPM being displaced.
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/38
7. Hardcore
Where shown and required, approved hardcore consisting of good, sound broken bricks or
stones shall be provided and laid to the thickness shown on the Drawings, well rammed,
compacted and blinded with sand. All hardcore shall be well watered immediately prior to
the depositing of concrete thereon.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/39
Class
Minimum
Concrete
Strength
(N/mm2)
45
400
45
400
60
420
60
420
60
420
60
420
60
420
60
55
45
400
45
400
Piles
Type
Minimum
Cement
Content
(kg/m3)
RC
Spun
pile
PC
PCS
RCS
Minimum
N/mm2
Minimum
2
N/mm
effective
prestressed
of
3.5
effective
prestressed
of
3.5
420
420
Type of
Driving
Hammer
driven
Hammer
driven
Hammer
driven
Hammer
driven
Hammer
driven
Hammer
driven
Hammer
driven
Hammer
driven
Jacked-in
Hammer
driven
Jacked-in
NOTES:
1 Concrete strength means characteristic compressive strength at 28 days.
2 The nominal sizes and length for each class of piles are specified in Parts 3, 4, 5 or 6 of Malaysian
Standard, whichever relevant.
Definitions:
1 Precast reinforced concrete square pile (RC pile)
A pile made of concrete cast in a uniform four-sided cross section before driving into the ground. It
shall be suitably reinforced mainly with steel bars.
2 Precast prestressed concrete square pile (PC pile)
A pile described in definition No. 1 but suitably reinforced mainly with prestressing steel.
3 Precast pretensioned spun concrete pile (Spun pile)
A hollow cylindrical pile made of concrete cast by centrifugal spinning before driving into the
ground. It shall be suitably reinforced mainly with pretensioned prestressing steel.
4 Small prestressed concrete square pile (PCS pile)
A small PC pile for sizes 200 mm and less.
5 Small reinforced concrete square pile (RCS pile)
A small RC pile for sizes less than 200 mm.
Slump Range
(mm)
Placed into water-free unlined bore. Widely spaced reinforcement leaving room for
free movement between bars.
75 to 125
Where reinforcement is not spaced widely enough to give free movement between bars.
Where casting level of concrete is within the casing.
Where pile diameter is less than 600 mm.
100 to 175
150 to collapse
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/40
APPENDIX C/1
1
P 3L
WL
1
40
4 5
Where,
M is the applied bending moment (kNm);
W is the weight of pile (kN);
L is the length of pile (m); and
P is the applied load (kN)
The cracking bending moment (Mc)
The pile shall be designed to withstand the cracking bending moment calculated based on the
maximum allowable crack width as shown in TABLE C3. The pile is considered to have passed
the requirement to withstand the cracking bending moment if when subjected to a test load
equal to the cracking load (Pc) corresponding to the appropriate Mc, no crack exceeding the
values in TABLE C3 occurs. The calculated values of Mc are given in TABLE C4, TABLE C5
and TABLE C6.
TABLE C3: MAXIMUM ALLOWABLE CRACK WIDTH
1
2
3
4
Types of pile
RC pile
Spun pile
PC and PCS pile
RCS pile
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/41
TABLE C4: CRACKING BENDING MOMENT (MC) AND FACTOR f FOR PRECAST
REINFORCED CONCRETE SQUARE PILES (RC PILES)
Nominal Pile Size
(mm x mm)
200 x 200
225 x 225
250 x 250
275 x 275
300 x 300
325 x 325
350 x 350
375 x 375
400 x 400
450 x 450
Class J
7.3
11.6
19.6
29.8
42.5
57.8
Class M
Class J
1.5
1.8
2.0
TABLE C5: CRACKING BENDING MOMENT (MC) AND FACTOR f FOR PRECAST
PRETENSIONED SPUN CONCRETE PILES (SPUN PILES)
Nominal
Diameter
(mm)
250
300
350
400
450
500
600
700
800
900
1000
1200
Class
Minimum Concrete
Strength
(N/mm2)
Cracking Bending
Moment (Mc) (kNm)
Factor
'f'
Effective
Prestress
(N/mm2)
B
A
B
A
B
A
B
C
A
B
C
A
B
C
A
B
C
A
B
C
A
B
C
A
B
C
A
B
C
A
B
C
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
12
17
20
26
30
38
43
54
53
60
76
74
84
106
123
141
177
191
218
273
278
318
399
390
445
558
527
601
755
853
973
1217
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.8
1.5
1.5
1.8
1.5
1.5
1.8
1.5
1.5
1.8
1.5
1.5
1.8
1.5
1.5
1.8
1.5
1.5
1.8
1.5
1.5
1.8
1.5
1.5
1.8
5.0
4.0
5.0
4.0
5.0
4.0
5.0
7.0
4.0
5.0
7.0
4.0
5.0
7.0
4.0
5.0
7.0
4.0
5.0
7.0
4.0
5.0
7.0
4.0
5.0
7.0
4.0
5.0
7.0
4.0
5.0
7.0
SECTION C : FOUNDATION
WORKS AND WORKS BELOW
LOWEST FLOOR LEVEL
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
C/42
TABLE C6: CRACKING BENDING MOMENT (MC) AND FACTOR f FOR PRECAST
PRESTRESSED CONCRETE SQUARE PILES CLASS PC-X, CLASS PC-Y, SMALL PILES
Size
(mm)
Class of
Pile
Minimum
Concrete
Strength
(N/mm2)
Minimum
Effective
Prestress
(N/mm2)
Cracking Bending
Moment, Mc
(kNm)
Factor 'f'
PCS-1
60
3.5
2.9
1.5
PCS-2
55
3.5
2.9
1.5
PCS-1
60
3.5
4.9
1.5
55
3.5
1.5
1.5
PCS-1
60
3.5
7.8
1.5
PCS-2
55
3.5
7.8
1.5
PCS-2
55
3.5
11.7
1.5
PC-X
60
5.0
13.7
1.5
PC-Y
60
7.0
16.4
1.7
PC-X
60
5.0
26.5
1.5
PC-Y
60
7.0
31.7
1.7
PC-X
60
5.0
45.2
1.5
PC-Y
60
7.0
54.2
1.7
PC-X
60
5.0
70.9
1.5
PC-Y
60
7.0
85.2
1.7
PC-X
60
5.0
104.5
1.5
PC-Y
60
7.0
125.9
1.7
PC-X
60
5.0
147.0
1.5
PC-Y
60
7.0
177.4
1.7
125
150
PCS-2
175
200
250
300
350
400
450
TABLE OF CONTENTS
SECTION D: CONCRETE WORKS
PAGE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
General
Material
Concrete Conformity And Identity Testing
Production Of Concrete
Construction With Concrete
Steel Reinforcement
Formwork And Surface Finish For Structure
Mass And Lean Concrete
Building Accuracy
Apparatus
Precast Concrete Construction
Other Concrete Works
D/1
D/1
D/5
D/10
D/16
D/19
D/22
D/28
D/28
D/28
D/28
D/30
D/31
D/32
D/32
D/35
D/36
D/36
D/36
D/37
D/38
D/38
D/39
D/40
D/40
D/40
D/40
D/40
D/41
D/41
D/41
D/42
D/42
D/42
D/43
D/43
D/43
D/43
D/44
D/44
D/44
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/1
1. General
This section shall apply to the construction of all structures or parts of structures to be
composed of concrete with or without steel reinforcement. The work shall be carried out all
in accordance with this specification and the lines, levels, grades, dimensions and crosssections shown on the Drawings and as required by the S.O.
2.
Material
2.1 Cement
2.1.1
The cement to be used throughout the Work shall be cement obtained from
SIRIM-certified manufacturer. The cement shall be described and complied
with MS EN 197-1 as shown in TABLE D1.
2.1.2
Certificates of test
2.1.2.1 Manufacturers' certificates of test shall in general be accepted as
proof of soundness. Additional tests shall be carried out on any
cement which appears to have deteriorated through age, damage to
containers, improper storage, or any other reason. The test shall be
carried out at any approved laboratory in accordance with MS EN
196 at the expense of the Contractor. Any batch of cement that has
been sampled and tested and found not to have complied with the
requirements shall be rejected and removed from the Site.
2.1.2.2 The S.O. may, without tests being made, order that any bag of
cement, a portion of the contents of which has hardened, or which
appears to be defective in any other way, be removed from the Site.
2.1.3
2.2 Aggregates
2.2.1
2.2.2
Coarse aggregates
Coarse aggregates shall comply with MS EN 12620. For work below ground
level, only crushed granite shall be used. Unless otherwise specified in the
Drawings, tests shall be carried out according to MS 30. The property limits
shall be as specified in TABLE D2. The maximum nominal size of aggregate
shall be as specified in the Drawings.
2.2.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/2
Fine aggregates
Fine aggregates shall comply with MS EN 12620. In the context of MS EN
12620, the term 'sand' is used to mean 'fine aggregate'. Unless otherwise
specified in the Drawings, tests shall be carried out in accordance with MS 30.
The property limits shall be as specified in TABLE D2.
2.2.4
Grading
2.2.4.1 Coarse aggregates
The grading of coarse aggregates shall be analysed as described in
MS 30 and shall be within the limits specified in TABLE D3.
2.2.4.2 Fine aggregates
The grading of fine aggregates shall be analysed as described in
MS 30 and shall be within the limits specified in TABLE D3A.
However, for prescribed mixes Grading Limit M shall only be used.
2.2.5
2.2.6
Storage of aggregates
2.2.6.1 Separate storage facilities with adequate provision for drainage shall
be provided for each different size of aggregate used.
2.2.6.2 Aggregate shall be handled and stored so as to minimize
segregation and contamination.
2.3 Water
Water shall comply with the requirements of MS EN 1008. It shall be clean and free
from materials deleterious to concrete in the plastic and hardened state and shall be
from a source approved by the S.O. The S.O. may instruct the Contractor to carry out
chemical tests at any approved laboratory at the expense of the Contractor. The
Contractor shall make adequate arrangement to supply and store sufficient water at
the Site for use in mixing and curing of concrete.
2.4 Admixtures
2.4.1
Suitable admixtures may be used in concrete mixes with the prior approval of
or as directed by the S.O.
2.4.2
The admixtures, the sampling and testing of the admixtures and the
information to be provided with the admixture supplied shall comply with MS
EN 934/ BS EN 934-2
2.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/3
2.4.3
2.4.4
Before allowing the admixture to be used in the Work, relevant tests based on
trial mixes shall be carried out. A control mix shall be made using a
conventional trial mix that is without using the admixture, to determine the free
water: cement ratio and mix proportion required to give the specified strength
with the required slump. Using the same mix proportion as in the control mix
but with a modified water: cement ratio whenever necessary, a test shall be
carried out using the recommended dosage of the admixture. The results of
the relevant test obtained from the control mix and test mix shall be
compared. The S.O. may allow the use of the admixture only when the
results are found to be satisfactory and comparable to the effects as claimed
by the manufacturer. The admixture acceptance test shall comply with the
requirements specified in TABLE D4.
2.4.5
The uses of admixtures that are chloride based are not permitted for structural
concrete containing reinforcement, prestressing tendons or other embedded
metal. The Contractor shall submit documentary evidence on the contents of
the admixture to be used.
2.4.6
2.4.7
2.5.2
When other than CEM I cement is specified to be used, the concrete mix shall
be of designed concrete only.
2.6.2
For small volume concreting work, volume batching is permitted provided prior
approval of the S.O. is obtained. The proportion shall be as specified in
TABLE D5A.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/4
2.7.2
Concrete grade
The grade of concrete to be used in the work shall be as stated in the
Drawings and /or in the B.Q. (Concrete shall be designated as Grade X/Y
where 'X' is minimum characteristic cylinder strength in N/mm2, and 'Y' is
minimum characteristic cube strength in N/mm2. For prescribed mix, a suffix
'P' shall be added after 'X').
2.8.2
Cement content
2.8.2.1 Cement content in this specification shall refer to the total quantities
of cement as approved in sub-section 2.1, or the total quantities of
cementitious materials comprising Portland cement and other
constituents complying to MS EN 197-1.
2.8.2.2 Minimum cement content
The minimum cement content shall be in accordance with TABLE D6
and D6A, unless otherwise shown on the Drawings
2.8.2.3 Maximum cement content
The maximum cement content shall not exceed 550 kg/m3 unless
otherwise shown on the Drawings or as approved by the S.O.
2.8.3
Consistence
2.8.3.1 The consistence of the fresh concrete shall be judged by its
suitability for the condition of handling and placing so that after
compaction, it surrounds all reinforcement, tendons and ducts and
completely fills the formwork. Consistence of the concrete shall be
within one of the following limits:
(i) Slump classes (Refer to TABLE D7)
(ii) Compacting classes (Refer to TABLE D7A)
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/5
2.8.5
General
3.1.1.1 The contractor is responsible for the evaluation of conformity for
specified requirements of the concrete. For this purpose, the
contractor shall carry out the following tasks:
(i) Initial test,
(ii) Production control including conformity control
3.1.2
3.1.3
Initial tests
3.1.3.1 Frequency of initial tests
Initial test shall be repeated if there has been a significant change
either in the constituent materials or in the specified requirements on
which the previous test were based.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/6
(ii)
(ii)
(iii) The consistence of the concrete shall be within the limits of the
consistence class, at the time at which the concrete likely to be
placed or in the case of ready mixed concrete, delivered.
(iv) For other properties that are specified, the concrete shall meet
the specified values with an appropriate margin.
3.2 Conformity Control For Designed Concrete
3.2.1
(ii)
(v)
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/7
(ii)
(ii)
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/8
The following actions shall be taken by the Contractor in the event of nonconformity:
(i)
(ii)
General
Identity testing indicates whether the defined volume of concrete in question
belongs to the same population as that verified as conforming with the
characteristic strength via conformity assessment.
3.4.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/9
(ii)
(ii)
3.4.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/10
(ii)
3.4.5
4. Production Of Concrete
4.1 General
4.1.1
selection of materials.
concrete design.
concrete production.
inspection and tests.
the use of the results of test on constituent materials, fresh and
hardened concrete and equipment.
(vi) For ready-mixed concrete, inspection of equipment used in
transporting fresh concrete.
4.2 Production Control System
The production control system shall contain adequately documented procedures and
instructions. These procedures and instructions shall, where relevant, be established
in respect of the control requirement as given in the TABLES D10, D11 and D16.
4.3 Supervision
The Contractor shall ensure the required standard of control over materials and
workmanship. The S.O. shall be afforded all reasonable opportunities and facilities to
@HAKCIPTA JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/11
inspect the constituent materials and the production of concrete and to take samples
for testing.
4.4 Site Mixed Concrete
4.4.1
4.4.2
The batch weight of aggregate shall be adjusted to allow for the moisture
content of the aggregate being used. All measuring equipment shall be
calibrated on site or their calibration status established by certificates from
accredited laboratories.
4.4.3
The mixing time shall be not less than two minutes and not more than five
minutes or any other time recommended by the mixer manufacturer after all
the ingredients have been placed in the mixer.
4.4.4
Mixers that have been out of use for more than 30 minutes shall be thoroughly
cleaned before any fresh concrete is mixed. Unless otherwise agreed by the
S.O., the first batch of concrete through the mixer shall contain only two thirds
of the normal quantity of coarse aggregate. The mixer shall be thoroughly
cleaned before changing from one type of cement to another.
4.4.5
Ready mixed concrete are batched, either dry or wet, at a control plant and
transported in purpose-made agitators operating continuously or truck mixers
to the Site.
4.5.2
4.5.3
4.5.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/12
Rejected concrete shall be removed from the Site. The delivery ticket shall be
marked 'REJECTED'.
4.6 Transporting
Concrete shall be transported from the mixer to the formwork as rapidly as practicable
by methods, which will prevent segregation or loss of any constituents or ingress of
foreign matter or water and maintain the required workability. It shall be deposited as
near as practicable in its final position to avoid rehandling or moving the concrete
horizontally by vibration. The concrete shall be conveyed by chutes or concrete
pumps only with permission from the S.O.
4.7 Placing
4.7.1
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/13
4.7.1.6 The Contractor shall maintain an experienced steel fixer at the site of
reinforced concrete works during the placing of concrete to
reposition any reinforcement which may be displaced.
4.7.2
(ii)
The tremie pipe shall be large enough with due regard to the
size of aggregate. For 20 mm aggregates, the Tremie pipe shall
be of a diameter not less than 150 mm and for larger
aggregates, a bigger diameter Tremie pipe approved by the
S.O. shall be used.
(iii) Freshly placed concrete shall be protected from direct sunlight and from
loss of moisture by covering, shading or other means.
(iv) No concrete shall be placed when the air temperature at the point of
deposition exceeds 36C
4.8.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/14
4.9 Compaction
4.9.1
4.9.2
4.9.3
The internal vibrators shall be inserted and withdrawn slowly and at a uniform
pace of approximately 100 mm per second. Compaction shall be deemed to
be completed when cement mortar appears in an annulus around the vibrator.
Over vibration leading to segregation of the mix must be avoided. The internal
vibrators shall be inserted at points judged by the area of mortar showing after
compaction, with a certain allowance made for overlapping and they shall not
be allowed to come into contact with the formwork or the reinforcement and
shall be inserted at a distance of not less than 75 mm from the formwork.
4.9.4
The pan vibrator shall be placed on the surface of the concrete, which shall
have previously been tamped and leveled leaving an allowance in height for
compaction until the cement mortar appears under the pan. The vibrator shall
then be lifted and placed on the adjoining surface and this operation shall be
repeated until the whole surface has been compacted. Alternatively, a
vibrating screen spanning the full width of the surface may also be used.
4.9.5
4.9.6
4.9.7
4.9.8
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/15
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/16
to prove that curing can start earlier by furnishing all the relevant
supporting data to the S.O. The rise in temperature within any period
of 30 minutes shall not exceed 10C and maximum temperature
attained shall not exceed 70C unless it can be proven that any
deviation from this provision shall not result in any detrimental effect
to the concrete work. The rate of subsequent cooling shall not
exceed the rate of heating. The use of accelerated curing methods
for concrete containing other types of cement or any admixture or
any additional materials shall be to the approval of the S.O.
Construction joints shall be made at the location as shown on the drawing and
concreting work shall be carried out continuously up to the construction joints.
If the position and detail of any construction joints is not described in the
drawings, the Contractor shall propose and obtain the approval of the S.O.
prior to commencement of concreting. The construction joints shall be made
as few as possible with reasonable precautions against shrinkage. The joints
shall be at right angles to the general direction of the member and shall take
due account of shear and other stresses.
5.1.2
Concrete shall not be allowed to run to a feather edge and vertical joints shall
be formed against a stop end. The top surface of a layer of concrete shall be
level and flat unless design considerations make this undesirable. Joint lines
shall be so arranged that they coincide with features of the finished work,
wherever possible.
5.1.3
5.1.4
5.1.5
5.1.6
Where the S.O. considers that special preparation is necessary, e.g. for an insitu structural connection, preparation shall be carried out, preferably when
the concrete has set but not hardened, by spraying with a fine spray of air and
water or brushing with a stiff brush sufficiently to remove the outer mortar skin
and expose the larger aggregates without disturbing them. Where this
treatment is impracticable, sand blasting or a needle gun shall be used to
remove the surface skin and laitance. Hardened surfaces shall be chipped
manually or mechanically to be free from laitance and properly roughened to
the extent that the coarse aggregates are being exposed.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/17
All fixing blocks, brackets, built in bolts, holes, chases, et cetera shall be
accurately set out and formed and carefully sealed prior to the concrete being
placed. It is the responsibility of the Contractor to obtain all such information
for these items of work and to obtain the approval of the S.O. before
incorporating such work prior to the concrete being placed.
5.2.2
Bolts and other inserts to be cast into the concrete shall be securely fixed to
the formwork in such a way that they are not displaced during the concreting
operations and that there is no loss of materials from the wet concrete through
holes in the formwork.
5.2.3
5.2.4
Temporary plugs shall be removed and the threads of built in bolts shall be
cleaned and greased before handing over any part of the Work.
5.3.2
When forming movement joints, joint filler shall be fixed firmly to the firstplaced concrete. If more than one strip is used within a joint, it is essential to
butt the ends tightly or tape them together to prevent grout leakage restricting
the closure of the joint.
5.3.3
It is essential that the concrete on both sides of the joint, when placed, is
thoroughly compacted to form a dense uniform mass. Where stop ends
comprise more than one element, particular care is necessary to ensure that
joints between elements are sufficiently tight to allow no grout loss through
them during compaction of the concrete.
5.3.4
Where flexible water stops are used, they shall be fixed so as to ensure that
they are not displaced from their intended position during compaction of the
concrete and that the concrete surrounding them is fully compacted. The
design of the water stop should be practical and take account of the problems
often associated with integral water stop construction in difficult placing
conditions.
5.3.5
Water stops laid horizontally and located within the concrete mass shall be
avoided since they attract the greatest risk of local honeycombing.
5.3.6
Unless otherwise shown on the Drawings, all exposed expansion joints shall
be covered with 0.7 mm thick aluminium cover strips fixed with masonry nails
at 300 mm centers.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/18
General
The installation method and the selection, mixing, application and curing of all
joint waterproofing materials shall be in accordance with the manufacturer's
recommendations. The Contractor may propose to use alternative joint
waterproofing materials by submitting supporting technical information, test
reports and samples of the proposed waterproofing materials to the S.O. for
approval
5.4.2
Waterproofing materials
All waterproofing materials used at public access areas shall be protected
with non-shrink grout covering
5.4.3
Water stops
5.4.3.1 Water stops shall be as specified in the Drawings and shall be
installed and butt jointed according to BS 8007 and the
manufacturer's recommendation.
5.4.3.2 Water stops shall be securely positioned in the formwork to prevent
displacement during concreting.
5.4.4
Conformance to BS 4254
Minimum joint movement capacity of 27.5% of joint width at
27.5C;
(iii) Shore 'A' Hardness of 25 at 27.5C;
(iv) Resistance to dilute acids, alkali and all kind of fuel
5.4.5
5.4.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/19
5.4.8
Bituminous sheeting
5.4.8.1 Bituminous sheeting with non-asbestos fibre shall comply with the
following requirements:
(i)
Resistant to lime water (no visual effect after two (2) weeks
immersion)
(ii) Maximum water absorption of 10% of dry weight
(iii) Minimum tensile strength of 50 kg/cm
(iv) Ozone and ultraviolet resistant
5.4.9
6. Steel Reinforcement
6.1 General
The Work shall consist of furnishing and placing reinforcing steel in accordance with
this specification and in conformity with the Drawings or as directed by the S.O.
6.2 Materials
6.2.1
Hot rolled mild steel and high yield bars shall comply with the requirements of
MS 146. Cold worked steel bars shall comply with the requirements of BS 4461.
Hard drawn mild steel wire shall comply with the requirements of MS 144.
6.2.2
Steel fabric reinforcement shall comply with the requirements of MS 145 and
shall be delivered to the Site in flat sheets, unless otherwise specified.
6.2.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/20
6.2.4
Before any reinforcement steel is brought to Site, the Contractor shall furnish
the mill certificates of tests and these shall be submitted for acceptance by the
S.O. In addition Contractor shall on request, furnish the S.O. with a test sheet
from approved laboratories for any batch of bars, giving the results of each of
the mechanical tests and/or chemical composition analysis required under the
MS or any equivalent international standards approved by the S.O. The
specified characteristic strength of steel reinforcement shall be as given in
TABLE D17.
6.2.5
6.2.6
Steel reinforcement shall be stored in clean and dry conditions. When placed
in the work it shall be clean and free from loose rust, mill scale, oil, grease,
paint, dirt or anything which may reduce its bond with concrete. If directed by
the S.O., the steel bars shall be brushed or otherwise cleaned before use, at
the Contractor's expense.
6.2.7
Binding wire shall be 1.6 mm diameter soft annealed steel wire complying with
the requirements of BS 1052.
6.3.2
Fixing of reinforcement
6.3.2.1 The number, size, length, shape, type and position of all reinforcing
bars, links, spacer bars and other parts of the steel reinforcement,
shall be in accordance with the Drawings.
6.3.2.2 Reinforcements shall be secured against displacement. Unless
specified otherwise, the actual concrete cover shall be taken as the
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/21
distance between face of concrete and the nearest steel surface. All
intersecting bars shall be tied together with binding wire and the
ends of the wire shall be turned into the main body of the concrete.
6.3.2.3 Reinforcement temporarily left projecting from the concrete at
construction or other joints shall not be bent out of position during
the periods in which concreting is suspended except with the
approval of the S.O.
6.3.2.4 The Contractor shall take particular care that the reinforcement is
laid out correctly in every aspect and temporarily suspended by
annealed wire or supported on concrete blocks or other approved
spacers in the forms to prevent displacement during the placing and
compacting of concrete. Links shall tightly embrace the longitudinal
reinforcement to which they shall be securely wired or spot welded.
The top reinforcement in slabs shall be rigidly supported on mild
steel 'chairs' or equivalent spaced in each direction to prevent
sagging during concreting.
6.3.2.5 No concrete shall be placed until the reinforcement has been
inspected and approved by the S.O.
6.3.3
Splicing
6.3.3.1 Joints to reinforcement bars shall be effected by lapping of bars at
positions shown on the Drawings. Where other types of joints are to
be used, prior approval of the S.O shall be obtained and their use
shall be strictly in accordance with manufacturer's recommendation,
at the positions approved by the S.O.
6.3.4
6.3.5
Welding of reinforcement
6.3.5.1 Welding workmanship, including welder qualification shall comply
with sub-section 5 of JKR Standard Specification for structural Steel
Work JKR No. 200600-0019-99.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/22
Description
7.1.1.1 Formwork shall include all temporary or permanent forms required
for forming the concrete, together with all temporary construction
required for their support.
7.1.1.2 The Contractor is deemed to have made a study of the Drawings at
tender stage and is aware of all areas of construction, requiring
heavy and specially designed propping to provide the support and
the necessary bracing for the stability of such propping.
7.1.1.3 The design and construction of formwork shall be carried out by a
competent person. The Contractor shall identify all critical formwork
design and submit the strength and deflection calculations and
Drawings or the proposed design, certified by a Professional
Engineer to the S.O. for prior approval. Notwithstanding any
approval by the S.O. with respect to the design submitted by the
Contractor, the responsibility or the adequacy and safety of the
design shall remain with the Contractor. The Contractor shall also
appoint a competent formwork coordinator whose duties would be
similar to those outlined in BS 5975.
7.1.1.4 When the use of proprietary type of formwork is proposed by the
Contractor, the design shall be certified by a Professional Engineer.
7.1.1.5 The formwork shall be sufficiently rigid and tight to prevent loss of
grout or mortar from the concrete at all stages of construction and
shall be appropriate for the methods of placing and compacting.
7.1.1.6 Formwork (including supports) shall be sufficiently rigid to maintain
the forms in their correct position, shape, profile and dimensions.
The supports shall be designed to withstand the worst combination
of forces due to self-weight, formwork weight, formwork forces,
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/23
Form lining
7.1.2.1 The type and treatment of any lining (plywood, metal, plastic,
Controlled Permeability Formwork liner, et cetera) of the forms shall
be appropriate to the concrete finish required.
7.1.2.2 The Controlled Permeability Formwork (CPF) liner shall have the
following requirements:
(i)
(v)
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/24
The concrete cast against the CPF liner shall have an even
uniformly textured matt finish and shall be free of blowholes and
other surface blemishes. The use of the CPF liner shall meet
the following performance requirements which should be
demonstrated by the supply of test certificate:
a) The mean surface strength for the CPF cast face shall
exceed that for the control face by at least 70%.
b) The mean 10 minute ISAT result for the CPF cast face shall
be not more than 15% of that for the control face.
c) The mean depth of carbonation for the CPF cast face shall
be not more than 15% of that for the control face.
d) The mean concentration of chlorides at a depth of 11mm
from the CPF cast face shall be not more than 15% of that
for the control face.
(vi) The CPF liner shall be used once only. Release agents shall
not be used with the liner and any residual release agent
remaining on forms from previous use shall be removed.
(vii) To ensure conformity with the performance requirements, the
CPF liner is to be used in accordance with the manufacturer's
technical guidelines.
(viii) The CPF liner shall unless otherwise directed, be left in place
on the concrete after formwork removal for the curing period
specified by the S.O. It shall be kept wet and covered with
plastic sheeting to promote efficient curing.
7.1.3
Control of colour
When specified in the Drawings, the Contractor shall obtain each constituent
material from a single consistent source. The aggregates shall be free of any
impurities that may cause staining. The mix proportions and the grading,
particularly of the fine aggregate, shall be maintained constant. The same
type of plywood or timber shall be used in formwork throughout similar
exposed areas.
7.2.2
Formed surfaces
7.2.2.1 Formed concrete surfaces shall have one of the following classes of
finish.
7.2.2.2 Unless otherwise specified, all exposed concrete surfaces shall be of
Class F12, all unexposed surfaces shall be of Class F1. Other
classes of finishes shall be used only where shown on the Drawings:
(i)
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/25
Class F1
This finish shall be obtained by the use of properly designed
forms of closely joined sawn timber or other approved material.
Small blemishes caused by entrapped air or water may be
expected but the surface shall be free from voids and
honeycombing.
(ii)
Class F2
This finish shall be obtained by the use of properly designed
forms of closely jointed wrought boards, approved plywood or
other approved material. Only very minor surface blemishes
shall occur, with no staining or discoloration.
(iii) Class F3
a) This finish shall be obtained by the use of properly
designed steel forms or plastic coated plywood or wrought
boards or other approved material.
b) The surface shall be improved by carefully removing all fins
and other projections, thoroughly washing down and then
filling the most noticeable surface blemishes with a cement
and fine aggregate paste to match the colour of the original
concrete. Form release agents shall be carefully chosen to
ensure that the surface shall not be stained or discolored.
After the concrete has been properly cured, the surface
shall be rubbed down where necessary, to produce a
smooth and even surface.
(iv) Class F4
The requirements for Class F4 are as for Class F3 except that
internal ties and embedded metal parts will be permitted. The
ties shall be positioned only in rebates, or in other positions as
shown on the Drawings or as agreed by the S.O.
(v)
Class F11
The requirements for Class F11 surface finish are identical to
those for Class F1 except that it shall be achieved using
Controlled Permeability Formliners.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/26
Unformed surfaces
7.2.3.1 Class U1
The concrete shall be uniformly leveled and screened to produce a
plain, ridged or broom roughened surface. No further work shall be
applied to the surface unless it is used as the first stage for a Class
U2 or Class U3 finish.
7.2.3.2 Class U2
After the concrete has hardened sufficiently, the concrete Class U1
surface shall be floated by hand or machine to produce a uniform
surface free from screed marks.
7.2.3.3 Class U3
When the moisture film has disappeared and the concrete has
hardened sufficiently to prevent laitance from being worked to the
surface, a Class U1 surface shall be steel-trowelled under firm
pressure to produce a dense, smooth uniform surface free from
trowel marks.
7.2.3.4 Class U4
This finish is for surfaces that are to receive waterproofing systems.
The concrete shall be levelled and floated to produce a uniform
surface and immediately before the waterproofing operation this
surface shall be water jetted or grit blasted to provide a lightly
textured finish. The finished surface shall not deviate from the
required profile by more than 5 mm over a 3 m gauge length or have
any abrupt irregularities of more than 3 mm.
7.2.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/27
Before concreting, all forms shall be thoroughly cleaned out, free from
sawdust shavings, dust, mud or other debris. The inside surfaces of forms
shall, unless otherwise approved by the S.O., be coated with an approved
non-staining form oil or other approved material to prevent adhesion of the
concrete Such release agents shall be applied strictly in accordance with the
manufacturer's recommendation and shall not come into contact with the
reinforcement or prestressing tendons and anchorages. For any exposed
surface only one release agent shall be used throughout the entire area.
7.3.2
All formwork shall be inspected by the S.O. after preparation and immediately
prior to depositing concrete and no concrete shall be deposited until approval
of the formwork has been obtained
The Contractor shall inform the S.O. and obtain his approval before striking
any formwork, but such approval shall not relieve the Contractor of his
responsibilities for the safety of the work.
7.4.2
7.4.3
The minimum periods between concreting and the removal of forms are given
in TABLE D18. The periods stated in this table are based on the use of
Ordinary Portland Cement. They may be changed with the approval of the
S.O., if other types of cement as described in sub-section 2.1, admixtures as
described in sub-section 2.4 are used. The result of the compressive strength
obtained from cube strength at 7 days as described in sub-section 4.4.2.2
may also be used for early removal of forms provided always the Contractor
provide proof of calculation to the S.O for approval.
7.4.4
7.4.5
Where it is intended that forms are to be reused, they shall be cleaned and
made good to the approval of the S.O.
7.4.6
Following the removal of forms, no further loads shall be imposed upon the
concrete until at least after the completion of the curing period or until such
later time as in the opinion of the S.O. the concrete shall have attained
sufficient strength to safely withstand such loads. Full design loads shall not
be applied to any structure until all load bearing concrete is at least 28 days
old.
The surface of the concrete shall be inspected for defects and for conformity
to the surface finish specified and where appropriate, with approved sample
finishes.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/28
7.5.2
Subject to the strength and durability of the concrete being unimpaired, the
making good of surface defects may be permitted but the level of acceptance
shall be appropriate to the type and quality of the finish specified and ensure
satisfactory permanence and durability.
7.5.3
9. Building Accuracy
After removal of formwork, the Contractor shall take measurements as directed by the S.O.
to check the deviation of the reinforced concrete works from specified dimensions shown
on the Drawings. All measurements shall be recorded and submitted to the S.O. Any
deviation in building accuracy shall comply with BS EN 13670.
10. Apparatus
10.1 The Contractor shall provide the following apparatus for use on the Site at all times:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
Concrete slump test apparatus or flow test apparatus complying with MS 26. One
set of the apparatus shall be provided for each concreting location.
At least twelve (12) numbers of steel or cast iron moulds for casting 150 mm
concrete test cubes and six (6) numbers of 100 mm mortar or grout test cube
moulds complete with tamping bars and base plates in accordance with MS 26.
A minimum number shall be provided such that no stripping of cubes is required
prior to 24 hours setting and hardening period.
Three (3) measuring cylinders of 250 ml capacity, graduated to measure to the
nearest 2.0 ml., for determination of silt content (field setting method).
An approved apparatus for measuring moisture content in fine aggregate.
One (1) electronic calculator with statistical functions.
One (1) 300 mm steel rule.
One (1) set of sieves in compliance with BS 410.
Scale or balance 25 kg maximum capacity and weights.
Trowel, shovel, spanner and other tools
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/29
11.1.2 The Contractor shall inform the S.O. in advance of the date of
commencement of manufacture and casting of each type of precast concrete
component.
11.1.3 When the S.O. requires tests to be carried out, none of the precast concrete
components to which the tests relate shall be dispatched to the site until the
tests have been completed and the results approved by the S.O.
11.1.4 All precast concrete components shall be indelibly marked to show the
identification marking as specified in the Drawings, the production batch
on which they were manufactured and the date on which the concrete was
cast. If the components are symmetrical, the face that will be uppermost
when the member is in its correct position in the work shall be clearly
identified.
11.2 Storage
11.2.1 When the precast concrete components are stored, they shall be firmly
supported only at the points specified in the Drawings. No accumulation
of trapped water and deleterious matter shall be allowed in the components.
Care shall be taken to avoid rust staining and efflorescence.
11.2.2 The precast concrete components shall be stacked in such a manner that
their removal in correct order of age is facilitated.
11.3 Handling And Transport
The precast concrete components shall be lifted only at points specified in the
Drawings or otherwise approved by the S.O. and shall be handled and placed without
impact. The method of lifting, the type of equipment and transport to be used, and the
minimum age of the components to be handled shall be to the approval of the S.O.
11.4 Assembly And Erection
11.4.1 The method of assembly and erection specified in the Drawings shall be
strictly adhered to on site.
11.4.2 Immediately a unit of precast concrete component is in position, and before
the lifting equipment is removed, temporary supports or connections between
components as necessary, shall be provided. The final structural connections
shall be completed as soon as is practicable.
11.5 Forming Structural Connections
11.5.1 For structural purposes, cement mortar shall compose of one (1) part of
cement to one (1) part of sand (1:1), mixed with water so that the free water:
cement ratio does not exceed 0.4 by weight and cement grout shall have a
water: cement ratio between 0.4 and 0.6, or such other proportions as shall be
directed by the S.O.
11.5.2 No structural connections shall be made until approval has been given by the
S.O.
11.5.3 Unless otherwise approved by the S.O., the composition and the free water:
cement ratio of the in-situ concrete or mortar used in any connection and the
packing of joints shall be in accordance with the assembly instructions.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/30
11.5.4 Levelling devices shall be released or removed only with the approval of the
S.O.
11.5.5 Non load bearing joints between precast concrete components and adjoining
structures shall be filled with appropriate grout and/or mortar protected by
proprietary sealants and backing rod. They shall be waterproof.
11.5.6 Load bearing joints and connection shall be grouted, mortar packed or
concreted. The respective mix design shall be free of lime and chloride. They
shall be durable, waterproof, non-shrink and possess strength higher than that
of precast concrete. Curing for at least three (3) days shall be provided.
Designed mixes shall be submitted to the S.O. for approval.
11.5.7 The method of sampling and testing of grout and mortar shall be carried out
according to MS 26. The compressive strength shall be determined by
crushing test on 100 mm cubes. For each casting day and for each grade of
grout and mortar, three samples shall be taken from three (3) separate
batches. Two (2) cubes shall be cast from each sample for testing at seven
(7) and 28 days. The appropriate strength requirement shall be considered
to be satisfied if the average strength is greater than the specified
characteristic strength.
11.6 Protection
At all stages of construction, precast concrete components and other concrete
associated therewith shall be properly protected to prevent damage to permanently
exposed surfaces, especially arises and other decorative features.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/31
Reinforced concrete
enclosure on all sides
Firemens
Lift
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/32
Wd
k
*k = + 30 mm,
- 30 mm
Wd = Well Depth
Highest Floor
Lowest Floor
Structural
Opening
Structural
Opening
Floor
Level
Landing Door
x = + 12.5 mm, - 0 mm
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/33
12.4 Floors
12.4.1 After initial set, the upper surface of cast-in-situ reinforced concrete floors
shall be trowelled smooth with a steel float to true level and even surface. No
screeding of any kind shall be applied to the floor slabs except where
specified. Care shall be taken to ensure that the steel reinforcement is not
displaced or lowered during trowelling.
12.4.2 For areas, which are to receive rendering or other finishes, the fresh concrete
shall be trowelled to true level or as required using a long timber trowel.
Before it hardens it shall be brushed with a stiff broom in one direction to give
a rough and tidy surface.
12.4.3 The reinforced concrete ground floor slab shall not be laid directly onto earth
surfaces. A blinding layer of 50 mm minimum thick of lean concrete as
specified in sub-section 9.0 shall be laid on well prepared firm ground. Plastic
sheeting or other suitable material with sufficient overlaps at joints, shall be
laid on the blinding layer before any reinforcement is placed in position.
12.5 Toilet Floors
12.5.1 The Contractor shall ensure that all suspended floor for toilet areas are
constructed to be watertight and leak proof. All construction method or
alternative details proposed by the Contractor must be based on his
acceptance of and compliance with the requirements for watertightness. The
Contractor shall ensure that holes and fixings are properly constructed.
12.5.2 The floor must be concreted in one sequence of operation. No construction
joints for toilet floor are to be allowed. All pipes and fittings encased in the
concrete floor shall be provided with sleeves to the approval of the S.O and
shall be built in-situ. No holes shall be left for later incorporation of fittings and
no subsequent hacking of floor shall be made. Notwithstanding whatever
shown on the Drawings, all toilet floor slabs shall have a minimum thickness
of 150 mm.
12.5.3 Testing for watertightness
The toilet floor areas should be ponded with water continuously over a period
of 7 days. During this period the exposed soffit shall show no signs of leakage
and remain dry. If any area is found not to be watertight, the Contractor must
repair at his own expense.
12.6 Roofs
12.6.1 Reinforced concrete roofs shall be constructed to fall as shown on the
Drawings and finished with steel trowelling, leaving the surface smooth and
free from mortar droppings.
12.6.2 The base slab shall be concreted as described for concrete generally,
ensuring thorough compactions by the use of a pan vibrator or a vibrating
screen. Concrete shall be poured continuously between pre-determined
construction joints as decided by the S.O., or as shown on the Drawings.
Expansion joints, where applicable, shall be allowed and constructed exactly
as indicated in the Drawings.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/34
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/35
Portlandslag cement
CEM II
/A-S
CEM II
/B-S
Portlandsilica fume
cement
CEM II
/A-D
90 94
CEM II
/A-P
CEM II
/B-P
CEM II
/A-Q
CEM II
/B-Q
CEM II
/A-V
CEM II
/B-V
CEM II
/A-W
CEM II
/B-W
CEM II
/A-T
CEM II
/B-T
CEM II
/A-L
CEM II
/B-L
CEM II
/A-LL
CEM II
/B-LL
CEM II
/A-M
CEM II
/B-M
CEM III
/A
CEM III
/B
CEM III
/C
CEM IV
/A
CEM IV
/B
CEM V
/A
CEM V
/B
80 94
65 79
80 94
65 79
80 94
65 79
80 94
65 79
80 94
65 79
80 94
65 79
80 94
65 79
80 94
65 79
35 64
20 34
Portland
types pozzolana
cement
CEM
II
Portland-fly
ash cement
Portlandburnt shale
cement
Portlandlimestone
cement
Portlandcomposite
c)
cement
CEM
III
Blastfurnace
cement
CEM
IV
Pozzolanic
c)
cement
CEM
V
Composite
c)
cement
a)
b)
c)
5 - 19
65 89
45 64
40 64
20 38
Minor additional
constituents
LL
610
6
20
21 35
620
21 35
620
21 35
620
21 35
b)
620
21 35
620
21 35
Limestone
Burnt shale
Natural
calcine
Natural
calcareous
CEM I
K
95 100
80 94
65 79
siliceous
Portland
cement
Silica fume
CEM
I
Notation of 27 products
(types of common
cement)
Blast-furnace
slag
Main
Clinker
a)
620
21 35
620
21 35
6 to 20
21 to 25
36 65
66
80
81
95
18
30
31 50
11 to 35
36 to 66
18 to 30
31 to 50
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
05
The values in the table refer to the sum of the main and minor additional constituents
The proportion of silica fume is limited to 10%
In Portland composite cements CEM II/A-M and CEM II/B-M, in Pozzolanic cements CEM IV/A and CEM IV/B and in composite
cements CEM V/A and CEM V/B the main constituents other than clinker shall be declared by designation of the cement
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/36
Type of
Aggregate
Both
Coarse
Coarse
Both
Coarse
Fine
Fine
Test
Methods
MS30
MS30
MS30
MS30
MS30
MS30
MS30
Coarse
MS30
MS30
Soundness Test
Coarse
Chloride Content
Both
MS30
Sulphate Content
Both
MS30
Limits
Table 3 and Table 4
Not exceeding 30%
Not exceeding 35%
Not exceeding 8%
Not exceeding 1% by weight
Not exceeding 3% by weight or 8% by vol.
Not exceeding 0.4%
Not exceeding 40%
Loss in mass after 5 cycles shall not be more
than 12% for sodium sulphate or 18% for
magnesium sulphate.
Not exceeding 0.06% by weight of chloride
ions
Not exceeding 0.44% by weight of SO3
Sieve size
(BS410)
50.0 mm
37.5 mm
20.0 mm
14.0 mm
10.0 mm
5.0 mm
2.36 mm
Sieve
size
(BS410)
10.0 mm
5.0 mm
2.36 mm
1.18 mm
600 m
300 m
150 m
#
Increase to 20% for crushed rock fines, except when they are used for heavy-duty floors.
For prescribed mix only Grading Limit M is applicable. See also sub-section 2.2.3(b)
NOTE:
Individual sands may comply with the requirements of more than one grading. Alternatively some
sands which satisfy the overall limits but may not fall within any one of the additional limit C, M or F
may also be used provided that the supplier can satisfy the S.O that such materials can produce
concrete of the required quality.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/37
Categories of
Admixture
Water
Reduction
Stiffening Time
Time from completion of
mixing to reach a
resistance to penetration of:0.5N
/mm
Type 1:
Accelerator
Type 2:
Retarder
Type 3:
Normal
waterreducing
Type 4:
Accelerating
waterreducing
Type 5:
Retarding
waterreducing
At least
5%
At least
5%
At least
5%
More
than
1hr.
3.5N
/mm
Within
1hr.and
3hrs.
earlier
than
control
mix
27.5
/mm
Compressive
At
least
1hr.
earlier
than
control
mix
125
125
100
100
Within
1hr.and
3hrs.
later
than
control
mix
Not
more
than
3hrs.
later
than
control
mix
Within +
1hr.
and 1hr.of
control
mix
Within +
1hr.
and 1hr.of
control
mix
Within
+ 1hr.
and 1hr.of
control
mix
More
than
1hr.
Within
1hr.and
3hrs.
earlier
than
control
mix
At
least
1hr.
earlier
than
control
mix
At least
1hr.later
than
control
mix
Within
1hr.and
3hrs.
earlier
than
control
mix
Not
more
than
3hrs.
later
than
control
mix
At least
1hr.later
than
control
mix
Minimum
Strength as a
percentage of
the control
mix
90
90
95
110
110
110
125
125
100
100
110
110
110
Age
Length change,
Maximum
shrinkage
% of
control
Increase
135
0.010
3 days
7 days
28 days
135
0.010
3 days
7 days
28 days
135
24 hrs.
3 days
7 days
28 days
24 hrs.
3 days
7 days
28 days
3 days
7 days
28 days
135
135
0.010
0.010
0.010
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/38
Grades of
Concrete
28-day
Strength of
Concrete
(N/mm2)
15P
15
20P
20
25P
25
30P
30
Consistence
CEM I (kg)
Total
aggregate(kg)
*Fine aggregate
(%)
CEM I (kg)
Total
aggregate(kg)
*Fine aggregate
(%)
CEM I (kg)
Total
aggregate(kg)
*Fine aggregate
(%)
CEM I (kg)
Total
aggregate(kg)
*Fine aggregate
(%)
Max
free
water:
cement
ratios
25 - 75
75 125
280
1800
35 - 50
310
1750
35 - 50
0.6
320
1800
25 - 40
350
1750
20 - 45
0.55
360
1750
25 - 40
390
1700
30 - 45
0.5
400
1700
25 - 40
430
1650
30 45
0.45
*Fine aggregate is expressed as a percentage by weight to the total weight of the dry aggregate
Proportion
(Grade)
1:1:2(30P)
1:1.5:3(25P)
1:2:4(20P)
1:3:6(15P)
Slump
Limits
(mm)
25 - 50
25 - 50
25 - 50
25 - 50
Cubic Meters of
Aggregate Per 50
kg of CEM I
Fine
Coarse
(20mm)
0.035
0.05
0.07
0.10
0.07
0.1
0.14
0.20
Max.
Free
Water:
Cement
Ratio
Quantity
Of
Water
(Litres)
0.45
0.5
0.55 - 0.6
0.6
22.5
25
27.5 - 30
30#
# or as approved by S.O.
Strength
of Concrete
At 7
Days
(N/mm2)
20
17
14
11
At 28
Days
(N/mm2)
30
25
20
15
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/39
Nominal
cover b)
mm
15 +c
20+c
25+c
30+c
35+c
40+c
45+c
50+c
Cement/
combination
types
C20/25
0.70 240
C20/25
0.70 240
C20/25
0.70 240
C20/25
0.70 240
C20/25
0.70 240
C20/25
0.70 240
C20/25
0.70 240
C20/25
0.70 240
All in Table D1
XC2
C25/30
0.65 260
C25/30
0.65 260
C25/30
0.65 260
C25/30
0.65 260
C25/30
0.65 260
C25/30
0.65 260
All in Table D1
XC3
C40/50
0.45 340
-
C30/37
0.55 300
C40/50
0.45 340
C28/35
0.60 280
C30/37
0.55 300
C25/30
0.65 260
C28/35
0.60 280
C25/30
0.65 260
C25/30
0.65 260
C25/30
0.65 260
C25/30
0.65 260
C25/30
0.65 260
C25/30
0.65 260
All in Table D1
except IVB-V
IVB_V
Corrosion induced by chlorides (XS from sea water, XD other than sea water)
Also adequate for any associated carbonation induced corrosion (XC)
XD1
C40/50
0.45 360
XS1
XD2 or
XS2
XD3
XS3
C32/40
0.55 320
C28/35
0.60 300
C28/35
0.60 300
C28/35
0.60 300
C28/35
0.60 300
C45/5
0.35 380
C40/50
0.35 380
C32/40
0.40 380
C32/40
0.40 380
C35/45
0.45 360
C32/40
0.45 360
C25/30
0.50 340
C28/35
0.50 340
C32/40
0.50 340
C28/35
0.50 340
C25/30
0.50 340
C25/30
0.50 340
C32/40
0.50 340
C25/30
0.55 320
C25/30
0.55 320
C25/30
0.55 320
C32/40
0.50 340
C25/30
0.55 320
C25/30
0.55 320
C25/30
0.55 320
C40/50
0.40 380
C35/45
0.40 380
C32/40
0.40 380
C32/40
0.50 340
C28/35
0.50 340
C25/30
0.50 340
C28/35
0.55 320
C25/30
0.55 320
C20/25
0.55 320
C28/35
0.55 320
C25/30
0.55 320
C20/25
0.55 320
C28/35
0.55 320
C25/30
0.55 320
C20/25
0.55 320
C40/50
0.40 380
C32/40
0.45 360
C28/35
0.45 360
C35/45
0.45 360
C28/35
0.50 340
C25/30
0.50 340
C45/55
0.35 380
C35/45
0.40 380
C32/40
0.40 380
-
C45/55
0.35 380
C32/40
0.45 360
C28/35
0.45 360
C40/50
0.40 380
C28/35
0.50 340
C25/30
0.50 340
C35/45
0.40 380
C32/40
0.40 380
All in Table D1
IIIB
IVB-V
IIIB, IVB-V
IIIB, IVB-V
IIIB, IVB-V
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/40
TABLE D6A: MINIMUM CEMENT CONTENT FOR MAXIMUM AGGREGATE SIZES OTHER
THAN 20 MM
Limiting values given for 20 mm maximum aggregate size
Maximum w/c ratio
0.70
0.65
0.60
0.55
0.50
0.45
0.40
0.35
Slump in mm
10 to 40
50 to 90
100 to 150
160 to 210
220
Degree Of Compactibility
1.46
1.45 to 1.26
1.25 to 1.11
1.10 to 1.04
Flow Diameter In mm
340
350 to 410
420 to 480
490 to 550
560 to 620
630
Maximum aggregate
size
> 40
14
10
mm
mm
mm
240
260
280
240
280
300
260
300
320
280
320
340
300
340
360
300
340
360
320
360
380
320
360
360
340
380
380
360
380
380
380
380
380
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/41
Form of compaction
Tamping
Poker or beam
vibration
Poker or beam
vibration and/or
tamping
Self-weight
compaction
Consistence class
Normal-weight
Lightweight
concrete
concrete
S1
S2
S2
S3
S3
S3
S3
S3
S3
S3
S3
S4
S4
S2
F5
S3
-
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/42
Compressive
strength class
Production
Initial
Continuous
Number n of test
results for
compressive
strength in the
group
3
15
Criterion 1
Criterion 2
Mean of n results (
cm)
N/mm2
ck +4
ck +1,48
ck
ck
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/43
Grades of
Concrete
20P
25P
30P
Cube Strength at 7
Days*
N/mm2
14
17
20
1
2-4
5-6
Not applicable
ck +1
ck +2
Criterion2
Any individual test result
(cl)
N/mm2
ck 4
ck 4
ck 4
NOTE: The identity criteria of table 13 give probability that a conforming concrete volume is rejected.
Tolerance
For composite samples taken in
For spot samples taken from
accordance with BS EN 12350-1
initial discharged
-20, +30
-30, +40
-30, +40
-40, +50
-40, +50
-50, +60
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
D/44
All sizes
All sizes
All sizes
Up to and including 12
Specified Characteristic
Strength, fy (N/mm2)
250
460
460
485
3 days
4 days
10 days
8 days
21 days
Note: This table is applicable only for CEM1 cement. Where other types of cement, admixtures or
additional material are to be used, the minimum periods between concreting and removal of forms shall
be as approved by the S.O.
TABLE OF CONTENTS
SECTION E : NON-STRUCTURAL WALL SYSTEM
PAGE
1.
2.
3.
General
Bricks and Blocks
Walling
E/1
E/3
E/4
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/1
1. General
1.1
Cement
The cement, unless otherwise described, shall be CEM 1 complying with MS EN
197-1 and as specified under SECTION D: CONCRETE WORKS.
1.2
Sand
Sand for mortar shall comply with MS EN 12620 and as specified in SECTION D:
CONCRETE WORKS.
1.3
1.4
1.5
Mortar
1.3.1
Mortar shall consist of one (1) part of cement to six (6) parts of sand, with
the addition of an approved mortar plasticizer used strictly in accordance
with manufacturers recommendation. The ingredients for mortar shall be
measured in proper gauge boxes and shall be mixed on a clean boarded
platform or in an approved mechanical batch mixer.
1.3.2
All mortar shall be used within forty five (45) minutes of mixing and no
remaking up of mortar shall be permitted thereafter.
1.3.3
Mortar for brickwork below damp proof course or ground floor level shall be
in the proportion of one part of cement and three parts of sand.
1.4.2
Bitumen damp proof course shall be in rolls to suit the thickness of walls or
brickwork. The damp proof course shall be bedded on a level bed of
cement mortar (1:1) and lapped at least 150mm or the width of the damp
proof course at running joints and intersections.
1.4.3
In all cases of doubt as to the exact location of the damp proof course, the
Contractor shall refer to the S.O. before laying the damp proof course. The
damp proof course above ground shall be continuous for the whole length
and thickness of the wall and be at least 150 mm above finished ground
level to prevent moisture from the ground rising through the foundation to
the wall above ground, which otherwise would make wall surfaces damp
and damage wall finishes.
Loading
All internal lightweight partitions shall be constructed only for their intended
purposes and any additional loadings shall be referred to the S.O. for approval.
1.6
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
1.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/2
1.6.2
1.6.3
1.6.4
1.6.5
Fire Rating
1.7.1
Unless otherwise specified or shown on the Drawings, fire rated walls and
partitions system shall be constructed and calculated according to
requirements and approval of the DGFR and compliance to the Uniform
Building By-Law (UBBL).
1.7.2
The glass wool and stone wool insulation materials used shall comply with
BS 476 - Fire tests on building materials and structures:
(i) Non-combustibility test for materials
(ii) Method of test for fire propagation for products
(iii) Method of test to determine the classification of the surface spread of
flame of products
1.8
1.9
Unless otherwise shown in the Drawings, all plastering works for brick
walls shall include the wall surface area above ceiling finish level.
1.8.2
1.9.2
The samples and mock-up for walls and partitions shall include
connections between the following components where applicable:
(i) Floor to floor to a minimum of 5 meter length
(ii) Wall corners
(iii) Lintels
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/3
(iv) Stiffeners
(v) Door and window frames
(vi) All other walls between different materials
General
All brick walls shall have G.I expanded/exmet mesh reinforcement with 750 mm x
5 mm diameter brickwork dowel bar complete with 75 mm right angle bent to hook
onto brickwork at every 4th course.
2.2
Samples
Separate samples of each type of bricks and blocks taken at random from the load,
shall be submitted to the S.O. for approval before the bricks and blocks are used. All
subsequent deliveries shall generally be up to the standard of the samples
approved. No soft, broken, twisted or otherwise defective bricks and blocks will be
permitted to be used.
2.3
Clay Bricks
All ordinary clay bricks shall be machine-made, wire cut and shall be hard, well
burnt, sound, square and clean all in accordance with MS 76.
2.4
All cement sand bricks and hollow blocks shall comply with MS 27.
2.4.2
2.4.3
Wherever blocks are used, a modular sized block shall be used and
constructed in accordance with the manufacturers standards,
requirements and method statements.
2.4.4
The composition of cement sand bricks and hollow blocks shall consist of a
uniform mixture of sand and cement. The sand cement shall be mixed in
the ratio of six (6) parts of sand to one (1) part of cement by volume in a
mechanical mixer capable of taking one (1) bag of cement (50 kg of
cement shall be taken as 0.035 cube). The sand used shall be as
described hereinbefore and the maximum size shall pass through a 4.8
mm mesh BS sieve. The cement used shall be CEM 1 as described under
SECTION D: CONCRETE WORKS.
2.4.5
The Contractor shall only use cement sand bricks and hollow blocks
supplied by approved manufacturer.
2.4.6
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
2.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/4
2.5.2
Where autoclaved aerated concrete blocks are used in lieu of clay bricks, a
modular sized block shall be used according to manufacturers standards,
requirements and method statements.
2.5.3
2.6
2.7
3. Walling
3.1
Brick Walling
3.1.1
3.1.2
All clay bricks shall be soaked in a suitable tank or pit to be provided by the
Contractor for at least half an hour before being laid and shall be kept wet
whilst being laid. The top of walls left off shall be thoroughly wet before
work is resumed. All constructed walling must be left wet and properly
protected from the direct sunlight during the following day. The Contractor
shall provide sufficient means to ensure that this is done.
3.1.3
Cement sand bricks shall not be soaked but dipped in water before being
laid and all constructed brickwork shall be protected from direct sunlight
during the day on which it is laid and also during the following day and the
contractor shall provide sufficient means to ensure that this is done.
3.1.4
All bricks shall be properly bedded in mortar and all joints shall be
thoroughly flushed up and raked out to a depth of 13 mm as the works
proceeds. No joint shall exceed 10 mm in thickness.
3.1.5
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/5
work proceeds. The vertical points of every alternate course shall be kept
perpendicular over one another, and all perpends, quoins, et cetera shall
be kept strictly true and square.
3.2
3.3
3.1.6
All intersections and angles of walls shall be properly bonded together, and
all walls and piers of lengths not multiples of brick sizes shall be cut and
bonded in the best approved manner. No broken bricks shall be used
except where required to form bonds.
3.1.7
All half brick (113 mm) walls shall be reinforced at every fourth course with
approved reinforcement (for example exmet) commencing two courses
above floor level. For block walling, reinforcement shall be at every second
course commencing one course above floor level.
3.1.8
3.1.9
3.1.10
3.1.11
Facing Brickwork
3.2.1
All facing brickwork shall be executed in first quality approved facing bricks
in Stretcher or Flemish Bond as shown on the Drawings, properly bonded
into any backing walls, piers, et cetera. Joints shall be racked out to a
depth of 13 mm and point up in coloured cement mortar to approved tints,
finished with a neat struck weathered joint.
3.2.2
Stonework
3.3.1
3.3.2
3.3.3
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
3.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/6
3.5
3.5.2
3.5.3
3.5.4
The autoclaved aerated concrete block work shall be laid in a manner that
the vertical joint of the lower course shall be staggered at least 100 mm
relative to the vertical joint of the overlaying course.
Unless otherwise directed and/or shown, where concrete block walls abut
concrete faces, the face shall be flushed.
3.5.5
3.6
3.5.6
Control joints should be built into walls at spacing not greater than 8 m
centres, and at locations in accordance with manufacturers
recommendation.
3.5.7
Care must be taken to keep the walls clean, strictly in accordance with the
manufacturers recommendation. Excess adhesive must be removed
progressively.
3.5.8
In lieu of cement sand plastering, the wall surfaces may be finished with
suitable surface coating that has the dual properties of being waterproof
and water vapour permeable and shall be applied in accordance with the
manufacturers recommendation.
Any parapet and freestanding wall consisting of 155 mm thick brick wall
including plastering on both sides shall only be constructed to a maximum
height of 900 mm.
3.6.2
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
3.7
3.8
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/7
3.6.3
3.6.4
3.7.2
Fasteners
Unless otherwise shown on the Drawings, fasteners or cramps for frames, metal
windows and precast units shall be built in at 1 m centres on the vertical side of the
frame. Mild steel cramps shall be 25 mm x 3 mm x 225 mm long for fixing wooden
frames, etc. One end of the cramp shall be turned up and screwed to back of the
frame and the other end shall be split and fish-tailed for building in. Cramps which
are to be fixed to concrete shall be embedded in concrete and built into brickwork as
the work proceeds.
3.9
Cutting
All cuttings such as arches, sinks, setbacks, and projections shall be properly
formed. Chases and holes through walls and slabs for the passage of pipes, wiring
and the like shall be neatly cut or formed. Upon the installation of the services pipes,
the chases and holes through walls shall be properly sealed (Fire Stop) to prevent
fire spread as required by the DGFR and UBBL. Where plastering works are done
on the cuttings, the surface shall be smooth and seamless.
3.10
All timber used for the timber stud framings for partition walls shall be as
specified in SECTION H: TIMBER, JOINERY AND IRONMONGERY
WORKS.
3.10.2
3.10.3
The top most horizontal frame, referred to as the top plate shall be bolted
or nailed to the ceiling and continuously erected using timber or metal
stiffener securely fixed to the slab to the S.O's approval. The timber and
metal stiffeners shall be spaced at 1200 mm centres maximum.
3.10.4
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/8
strap to the floor to the S.O.'s approval. All fixings to timber slabs shall be
fixed at 600 mm centres maximum.
3.11
3.10.5
Unless otherwise specified, dimension for timber panels shall comply with
MS 1064.
3.10.6
3.10.7
Steel sections such as, but not limited to metal framing and studs shall
comply with ASTM C645, BS EN 14195, BS 7364 or other approved
equivalent standards as appropriate, and to the approval of the S.O.
3.11.2
3.11.3
The stud which is to support a joint shall have a minimum fixing face width
of 32 mm for screw fixing and all other framing members shall not be less
than 30 mm. Drywall screws shall be at least 10 mm longer than total
thickness of plasterboards on each side of the partition wall. The
plasterboards are laid staggered and fixed to the metal frames using
drywall screws not exceeding 300 mm centres.
3.11.4
The top most U-frame (horizontal) shall be screwed to the ceiling and
continuously erected using metal stiffener securely fixed to the slab. The
metal studs directly supporting plasterboard sheets shall be spaced at 600
mm centres maximum. The bottom U-frame (horizontal) shall be securely
fixed to the floor slab using bolts or screws. All fixing to slabs, M12
expansion bolts shall be used at 1200mm centres maximum with
galvanized mild steel strap to the floor and to the S.O.'s approval.
3.11.5
3.11.6
Partition above ceiling shall allow for cut out opening for service ducts or
trunks and cable trays. The contractor shall coordinate with all
subcontractors on the exact location and size of the openings. Any gaps
around any pipe ducts through the partition shall be properly sealed with
and approved fire smoke stop system. by the penetration collar protection
specialist.
3.11.7
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/9
support frame of the duct. In such cases, space between the duct and
reinforced concrete soffit need not be sealed up.
3.11.8
3.12
The deflection of the metal frame partition system under service condition
shall be controlled by the limit for the calculated deflection of the element
chosen for the system and its intended use. The deflection shall not
exceed L/240 or L/360 subject to the finishing material attached to the
partition. Any system wall partition selected shall be installed strictly
according to the manufacturer's specifications and details to the S.O.s
approval.
Plasterboard Partition
3.12.1
The type of plasterboard used shall comply with BS EN 520. The specified
plasterboard shall carry class O approval from DGFR. Unless otherwise
specified the plasterboards used for the works shall be 12.5 mm thick with
standard length of 3000 mm and shall be free of defects.
3.12.2
3.12.3
The appropriate type of sealant shall be used for the required type of
plasterboard. Elastomeric sealants shall be used at the perimeter of the dry
lining or partitioning to provide an airtight construction and to the approval
of the S.O.
3.12.4
3.12.5
Jointing tape for plasterboards shall not be less than 48 mm wide and not
exceeding 60 mm in accordance with ASTM C475 and the approval of the
S.O.
3.12.6
3.12.7
3.12.8
3.12.9
3.12.10 Plasterboard sheets shall be laid out to minimize butt joints and waste. Butt
joints on adjoining sheets shall be staggered. Butt joints on opposite sides
of the wall shall be staggered. The sheet shall be laid so that the vertical
joints fall a minimum of 200 mm from the edge of the opening.
@HAKCIPTA JKR MALAYSIA
SECTION E : NON-STRUCTURAL
WALL SYSTEM
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
E/10
3.12.11 Fire resisting systems comprising of more than one layer of plasterboards,
the joints in successive layers should be staggered. In the case of walls
sheeted on both sides joints should be staggered on opposite sides of the
wall.
3.12.12 Penetrations in the system shall only be allowed if installed in accordance
to manufacturers recommendation and tested at the Contractors
expenses. Penetration shall be strictly carried out in accordance with the
requirements of the DGFR and to the recommendationapproval of the S.O.
3.12.13 Fasteners shall have a corrosion-resistant finish and be appropriate for
intended use, also in accordance with BS EN 14566 and BS 8212. The
heads of fasteners shall be shaped so that they can be driven slightly
below the surface of the plasterboard without punching through the paper
liner.
3.12.14 Impact resistance of a partition system including gypsum plasterboard shall
be determined in accordance with ISO 7892 and BS 5234-2.
3.12.15 The Contractor shall submit to the S.O., a manufacturers warranty against
any defect or damage to the proprietary plasterboard partition system
which may arise during the period of five (5) years from the date of
Certificate of Practical Completion. Terms of the warranty shall be such as
shall be approved by the S.O.
3.13
Glass Partitions
3.13.1
Unless otherwise specified or shown on the Drawing, all fixed glass wall
systems shall be 8 mm thick minimum, erected with stainless steel framing
system for sizes up to 1200 mm x 4800 mm maximum installed to
manufacturers recommendation and to S.O.s approval. For sizes more
than 4800 mm, the panels shall be constructed according to
manufacturers recommendation and the installation shall be certified by a
P.E.
3.13.2
TABLE OF CONTENTS
SECTION F : SEWERAGE WORKS
PAGE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
General
Material
Layout
Excavation
Pipes And Fittings
Joint For Sewer Pipes
Pipe Laying
Bedding, Haunching And Surround
Connections
Manholes, Inspection Chambers And Valve Chambers
Septic Tank And Sewage Treatment System
Connections To The Public Sewerage Line
Testing For Sewer Pipes Installation
Backfilling
F/1
F/1
F/1
F/1
F/3
F/3
F/3
F/4
F/5
F/5
F/6
F/7
F/7
F/9
F/10
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/1
1. General
The work to be done under this section unless otherwise shown or described in the B.Q.
shall consist of the supply, delivery, construction and testing of all sewerage works and
ancillary works, and all necessary works up to the point of final discharge of the effluent. In
the case of discharge into the public sewer or the package sewage treatment plant, the
work shall terminate up to and including the last manhole or intercepting trap of the system.
This section of the work shall be carried out strictly in accordance with the appropriate bylaws and to the approval of the S.O.
2. Material
2.1 Cement, Sand, Aggregates And Bricks
2.1.1
The Contractor shall only use sewer pipes from suppliers approved by
SPAN and all materials shall be inspected and approved by the S.O.
before being installed.
2.2.2
The Contractor shall submit the certificate and test report of sewer pipe
to the S.O. for approval.
2.2.3
The Contractor shall make sure the sewer pipe is stored and/or stacked
in such manner to prevent breakage.
3. Layout
The whole sewerage work shall be carried out according to the layout as shown on the
Drawings.
4. Excavation
4.1
4.2
The Contractor shall carry out survey work to determine the sewer pipe alignment.
Clearance from the building/road shall be 1 m. The pipe alignment shall be
approved by the S.O. before the contractor starts the excavation works.
4.3
The trench shall be excavated to the depths intended or as shown on the Drawings
and shall be finished and trimmed to the correct level and grade. Unless indicated
otherwise, the bottom of the trench shall be graded so that the pipe invert slopes
evenly between the appropriate outlet invert of the preceding manhole and the inlet
invert of the next manhole.
4.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/2
4.5
The sides of all excavation unless otherwise approved by the S.O. shall be cut
vertical and where necessary shall be protected against caving in by timbering to
the approval of the S.O. If the trench is more than 1.5 m, the contractor shall
provide support for the trench to avoid collapse, settlement or movement of the
banks.
4.6
The trench excavation shall not advance more than 100 m ahead of the completed
backfilled pipeline. Pipe shall be laid in all trenches that have been excavated at
the end of each days work, unless the Contractor get approval from the S.O. to do
otherwise.
4.7
It shall be the responsibility of the Contractor to protect and support all existing
water pipes, gas and other conduits crossed by the excavation or work to be
performed and to arrange for their temporary removal and subsequent
replacement.
4.8
The trench should be excavated precisely to ensure the sewer pipe will be in the
centre of the trench. The bottoms of the trenches for all sewers shall be carefully
and truly graded, formed and lined according to the grades and dimensions as
shown on the Drawings.
4.9
Should the ground be so wet or soft, and does not form a firm base for the pipe, if it
is necessary in the opinion of the S.O. then the trench shall be excavated 225 mm
below the level intended or shown on the Drawings and then brought to the correct
level with good selected earth, quarry dust or sand well rammed into place. Such
deepening of pipe trench and filling back shall be treated as a variation under the
terms of the Contract. Should the bottom of the trench be inadvertently excavated
below the specified level, it shall be brought back at the Contractor's expense to
the correct level with good selected earth, quarry dust or sand carefully rammed
into place.
4.10
The Contractor shall remove any water which collects in the trenches while sewer
pipes are being laid. Water encountered shall be disposed of by the Contractor in a
manner satisfactory to the S.O.
4.11
Excess material from the trench excavation shall be located 600 mm (minimum)
away from the trench.
4.12
When excavating pipe trenches in roadway or other paved surfaces, the Contractor
shall first remove all metal, slabs or bricks forming the existing pavement to the
width of the trenches and reinstate to the approval of the S.O. after the trenches
have been backfilled. The Contractor must make sure that not more than half of the
width of a roadway shall be disrupted at any one time during the sewerage work.
4.13
4.14
If the works required pipe jacking, the Contractor shall provide method statement
for S.O.s review and approval.
4.15
The Contractor shall ensure that the work performed is safe and in compliance with
Occupational Safety and Health Act (OSHA).
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/3
Generally, all sewer pipes unless otherwise shown on the Drawings, shall be
vitrified clay pipes (VCP) and fittings complying with MS 1061 and SPAN
guidelines.
5.2
Sewer pipes used for gravity types of sewer shall be a minimum size of 150 mm for
service connection and 225 mm for public sewer complying with Malaysian
Sewerage Industry Guideline (MSIG).
Unless otherwise approved by the S.O., joints of flexible and watertight type shall
be used on all sewer pipes. The spigot and socket of each pipe shall be cleaned
and lubricated before the running of each joint.
6.2
Couplings shall be made either of the same materials as the pipe or other material
to the approval of the S.O. The pipes and coupling shall have accurately machined
or molded tapered ends, the internal taper of the couplings matching the external
taper of the pipes.
7. Pipe Laying
7.1
All pipes shall be laid in compliance with MS 1228 and in accordance with the
sizes, locations, dimensions, grades and other particulars as shown in the
Drawings. Each pipe shall be carefully inspected upon arrival at site. Sewer pipes
shall be carefully stored. Defective pipes shall be marked and removed from the
site forthwith.
7.2
Prior to fixing or laying all pipes and fittings shall again be carefully inspect for
damage and only those found to be sound in every aspect shall be fixed or laid.
Any pipes, specials, et cetera found to be damaged in any way shall be clearly
marked, set aside and removed from the site.
7.3
No pipe shall be laid until the trench has been inspected and approved by the S.O.
7.4
The pipes shall be gently lowered into the trench by means approved by the S.O.
No pipes shall be rolled or dropped into the trench. The pipe shall be laid true to
alignment as shown in the Drawings or as instructed by the S.O. Interior and
exterior of each pipe at the joint shall be thoroughly cleaned before the joint is
made. Pipes shall be laid from the downstream end towards the upstream end.
7.5
To prevent the entry of earth and other materials into the pipes, the Contractor
shall provide and fix suitable stops for efficiently closing all open ends of pipes in
the trench while work is not actually being carried out at such open ends.
7.6
Socketed pipes shall be laid with the sockets laid against the direction of flow. At
every position of pipe joints, the bedding shall be recessed sufficiently.
7.7
7.8
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/4
The sewer pipes shall be laid to the gradients as shown on the Drawings. Where
the gradients are not shown in the drawings, the pipe shall be laid to the following
gradients:
Size diameter (mm)
100
150
225
250
300
375
450
Gradient
1 : 60
1 : 80
1 : 110
1 : 120
1 : 140
1 : 170
1 : 200
7.9
The invert level of each pipe laid shall be checked during laying and immediately
after laying as shown on the Drawings.
7.10
Where sewer pipes are laid above ground, they shall be supported at intervals to
the details as shown on the Drawings or to the approval of the S.O.
7.11
All external underground sewer pipes shall have a minimum cover of 450 mm
unless otherwise shown on the Drawings.
7.12
Clearance between sewer pipes and other services shall be a minimum of 100 mm
(vertical and horizontal clearance).
7.13
Other Requirements
7.13.1
7.13.2
pipe
laying
during
and
after
8.2
Typical bedding is to be used for all pipes under normal site condition unless
directed by the S.O.
8.3
8.4
The bedding material shall be placed as soon as possible after the base of the
trench is prepared and excess water has been removed.
8.5
Whenever the bedding is disturbed, the pipe shall be raised to allow for repair
works to be done.
8.6
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/5
Any pegs or other temporary aids for levelling works shall be removed before any
pipe being laid.
9. Connections
9.1
The Contractor is to allow and provide for all bends, junctions, traps, gullies as
shown on the Drawings or where necessary. If a gully is used, it shall be of the inlet
type, and shall be set level on a concrete base, with a riser to finish 50 mm above
the surrounding surface level, complete with concrete surrounds rendered on all
sides and galvanized iron grating. Bends turned up to receive various stacks shall
be set on concrete bases to the approval of the S.O. The bends at the foot of
vertical stacks shall be of gentle radius type.
9.2
Manholes, inspection chambers and valve chambers shall be constructed with the
sizes shown on the Drawings and MSIG guidelines. Unless otherwise shown or
specified, all dimensions on the plan shall be the inside measurement.
10.2
10.3
Manholes
10.3.1
10.3.1.2
10.3.2
10.3.2.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/6
Inspection Chambers
Unless otherwise as shown on the Drawings, inspection chambers shall be
constructed in brickwork in cement mortar (1:2) and the brickwork shall be of clay
bricks and constructed on Grade 20P concrete foundation. The thicknesses and
sizes shall be as shown on the Drawings. Each inspection chamber shall have
channels and open channel junctions of sizes as shown on the Drawings. Concrete
benching shall be to a gradient of 1:6 and shall be of Grade 20P concrete finished
with 19 mm steel troweled water proofed cement and sand (1:3) rendering. The
internal sides of the inspection chambers shall be lined with 20 mm thick PVC,
HDPE or epoxy coating. Externally, the exposed concrete or brick surfaces shall be
rendered with 12 mm cement and sand mortar (1:3) and terminated 150 mm below
the finished ground level. All internal angles shall be rounded off. Inspection
chambers shall be provided with covers and unless specified or as shown on the
Drawings, covers shall be medium duty 450 mm x 600 mm cast iron covers with air
tight frames.
Septic tank and sewage treatment system shall be constructed as shown on the
Drawings and to the approval of the S.O.
11.2
All septic tank and sewage treatment system shall be approved only by SPAN.
Prefabricated system by the S.P. shall be from the latest Treasury Contract
Circular.
11.3
The quality limit for sewage effluent at the discharge point shall comply with
Environmental Quality Act (EQA) 1974 or latest. The limit for sewage effluent at the
discharge point shall comply with Standard A of EQA as in APPENDIX F/1.
11.4
11.4.2
11.4.3
11.4.4
by
the
Local
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/7
Connections to the public sewerage line, if any, shall be strictly carried out in
accordance with requirements of the SPAN guidelines and to the approval of the
S.O.
The Contractor shall carry out tests to the sewer pipes installation in accordance
with the method of statement and requirements as described hereinafter. The
Contractor shall give reasonable notice in writing to the S.O. before such tests to
be carried out.
13.2
Testing of pipework shall be carried out and wherever possible, such testing shall
be carried out from manhole to manhole. Short branch pipes connected to a main
sewer between manholes shall be tested as one system with the main sewer. Long
branches and manholes, shall be separately tested.
13.3
Subject to type of pipe and size, pipes shall be subjected to either low water
pressure tests, CCTV test or any other test required by the MSIG guidelines and to
the approval of the S.O.
13.4
The low water pressure test is commonly used for checking the water
tightness of the joints and the integrity of the sewer pipes.
13.4.2
For the water test, the pipe shall be subjected to an internal test pressure
of 2 m head of water above the crown of the pipe at the higher end but not
more than 7 m at the lower end. Steeply graded pipe shall be tested in
such a manner that the above maximum heads is not exceeded.
13.4.3
The test shall be carried out by filling the sewer with water slowly to the
required head and bleed air from behind the upstream plugs. Maintain the
water head for two (2) hours. Top up the water as required.
13.4.4
Check the leakage at the plugs and the test apparatus during the
pressurizing period and the constant pressure holding period. Release the
water pressure if leakage occurs. Make the necessary repairs and
adjustments before pressurizing again.
13.4.5
Commence the test immediately after the last adjustment of water head in
the preceding two (2) hours period.
13.4.6
Add water to maintain the starting water head every five (5) minutes
during the test period of 30 minutes. Record the total amount of water
required for readjustment.
13.4.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/8
The loss of water does not exceed 1 litre per hour linear meter per
meter internal diameter for VCP and reinforced concrete pipes.
(ii) There shall be no loss of water for pipe other than VCP and
reinforced concrete pipes.
(iii) There is no visible leakage at the joints for all pipe types.
13.5
General
CCTV inspection where required shall be carried out to enable detection
of sewer defects such as cracks, deformations, collapse, dislocation and
et cetera which are not detected by normal means.
13.5.2
Inspection requirements
13.5.2.1
13.5.2.2
13.5.2.3
13.5.3
Witness
Witness from the SPAN, S.O., consultant and contractor responsible for
the construction of sewer shall be present during CCTV inspection.
13.5.4
Documentation
13.5.4.1
13.5.4.2
13.5.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/9
14. Backfilling
14.1
After the pipes have been tested and approved, the trench shall be backfilled with
approved fill material, free from rock and other hard material, well compacted
around the pipes up to a level of at least 300 mm above the top of the pipes. After
this has been approved, the remaining excavation shall be backfilled in 300 mm
layers, each layer being well compacted. The bedding details and the types of fill
material shall in accordance to Drawings and MSIG guidelines.
14.2
14.3
There shall be at least 300 mm of cover over the sewer pipe before light
mechanical compaction can commence.
14.4
There shall be at least 1000 mm of cover (depth of backfill) over the sewer before
heavy mechanical compaction can commence.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
F/10
APPENDIX F/1
BOD5
SS
COD
AMN
Nitrate
Nitrogen
Total
Phosphorus
O&G
Standard B
Absolute
Design
50
20
100
40
200
100
20
10
50
20
N/A
N/A
N/A
N/A
10
10
10
Notes :
1)
2)
3)
*Stagnant water bodies refer to enclosed water bodies such as lakes, ponds and slow moving
watercourses where dead zone occur
4)
5)
TABLE OF CONTENTS
SECTION G : ROOFING WORKS
PAGE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
General
Interlocking Concrete Tiles
Clay Tiles
Pre-painted Aluminium Roofing Sheet
Concrete Flat Roofs
Pre-painted Steel Roofing Sheet
Roofing Sheet For Marine Environment (Coastal Areas)
Bituminous Corrugated Roofing Sheets
Bituminous Corrugated Roofing Tiles
Fibre-cement Corrugated Sheets
Heat Insulation
G/1
G/1
G/1
G/1
G/1
G/2
G/4
G/5
G/5
G/5
G/6
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
G/1
1. General
1.1
Unless otherwise stated, the pitch and laps for each type of roof covering shall be
strictly in accordance with the manufacturers recommendation.
1.2
Unless otherwise approved, all roof covering pieces or accessories such as eaves,
hips, ridges, valley et cetera, shall be of the same material as the general covering.
Interlocking concrete roof tiles shall be laid on timber or steel battens approved for
roofing at spacing and tightly nailed or screwed as recommended by the
manufacturer.
2.2
Unless otherwise specified, the concrete roof tiles shall be laid to slope in
accordance to the manufacturers recommended pitch and to the S.Os approval.
The roof tiles shall conform to MS 797 and unless otherwise specified on the
Drawings, it shall be laid on metal trusses system to engineers detail and S.Os
approval.
2.3
Tiling fillers consisting of 1:3 cement mortar as specified under SECTION E: NONSTRUCTURAL WALL SYSTEM, shall be provided at the feet of the rafters.
2.4
Verges, ridges, hips, valley tiles and complete with all roofing accessories shall be
provided and laid to bond with the general roof tiling works in accordance with the
manufacturers recommendation.
3. Clay Tiles
3.1
Unless otherwise stated in the Drawings, clay tiles shall be of 470 mm (length) x
284 mm (horizontal width) pattern confirming to BS 402 and shall be free from
cracks, chips and warps.
3.2
Clay tiles shall be laid with a minimum head lap of 95mm on timber or steel battens
approved for roofing at spacing as recommended by the tile manufacturer. The tiles
shall be firmly screwed or nailed at intervals as recommended by the roofing tile
manufacturer and as approved by the S.O.
3.3
Ridge capping, hip and valley tiles complete with all roofing accessories shall be
provided to match the general tiling works in accordance with the manufacturers
recommendation. All these shall be bedded in matching 1:3 coloured cement
mortar.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
G/2
Unless otherwise stated, the metal roof decks shall comply with the following:
6.1.1
6.1.2
Materials
6.1.1.1
6.1.1.2
6.1.1.3
6.1.1.4
6.1.1.5
6.1.1.6
6.1.1.7
6.1.2.2
6.1.3.1
6.1.3.2
(ii)
6.1.3.3
6.1.3.4
Metallic swarf and all other debris including nail, screws, mortar,
construction materials et cetera shall be swept away from the
roof area and gutters regularly, particularly at the end of each
days work and at completion of the installation works.
6.1.4.2
6.1.4.3
6.1.5
JKR 20800-0183-14
01
00
29 Januari 2014
G/3
Fixing
(i)
6.1.4
:
:
:
:
:
6.1.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
- 1000 hours
- 15 cycles.
- 1000 hours.
- 2000 hours.
6.1.6
Sealants
Only neutral cure silicone rubber sealant type Dow Corning 780 or
equivalent shall be used conforming to AS 3902.
6.1.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
G/4
Lightning conductors
Aluminium lightning conductor is recommended for use on steel roof
system.
6.2
All fixing accessories shall be rust-resistant and of suitable design and construction
as recommended by the manufacturer for the roofing system and as approved by
the S.O. All fasteners and screws shall be of the self-drilling type either concealed or
screwed fixing, complete with preassembled EPDM rubber washers.
6.3
Identification, storage and packaging of alum/zinc steel roof decking shall be strictly
in accordance with the manufacturers recommendation and comply with the S.O.s
requirements.
6.4
All roof decking sheets, capping, flashing et cetera or wall cladding shall be new,
clean, regular, straight and true to shape with sharp defined profiles, free from
cracks, chips, bends and defects detrimental to practical use or from other surface
imperfections.
6.5
At Site, the sheets shall be lifted from the transport carrier by a crane and properly
stacked clear of the ground, ready to be lifted up to the roof structure for laying.
Where sheets are to be manually lifted, care should be taken not drag the sheets to
avoid scraping away the surface coating.
6.6
Where storage is necessary, stack heights shall be kept to a minimum and the
sheets shall be stacked in a sloping position. Sheets shall be stacked off a dry firm
ground, under cover by tarpaulin or polythene sheets but ventilated and away from
building operations. Should the stack sheets become wet, they shall be immediately
dried to prevent staining and degradation of the surface coatings.
6.7
The Contractor shall be responsible for the absolute water-tightness of the roof and
must ensure that the method of installation, fixing and fastening decking sheets,
caps, flashings et cetera including acoustical, insulation and expansion joints,
whenever required shall conform strictly to the manufacturers recommendation.
6.8
The completed portions of the roof shall be clear of all metallic particles such as
blind rivet shanks, screws, nuts, nails et cetera and dirty foot prints should be wiped
off to avoid early deterioration/corrosion and discolouration. Damages to the coating
shall be repaired with touch-up paint as recommended by the manufacturer and
approved by the S.O.
The Contractor shall select the correct type of metal sheet profile to be installed for
coastal areas as recommended by the roof manufacturer and approved by the S.O.
7.2
Unless otherwise specified or shown in the Drawings, the roofing sheet for marine
environment shall be metallic coated steel with minimum aluminium/zinc alloy
coating mass of 200 g/m (Coating Class AZ 200) on both surfaces conforming to
ISO 9223 Category 4 (C4) and Category 5 (C5) environment.
7.3
7.4
The pre-painted finish (super polyester paint) type shall be used over the
aluminium/zinc alloy coated base steel shall conform to MS 2383: Prefinished/Pre-
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
G/5
painted Sheet Metal Products for Interior/Exterior Building Applications Performance Requirements and AS/NZS 2728: Prefinished/Pre-painted Sheet
Metal Products for Interior/Exterior Building Applications - Performance
Requirements
7.5
Fasteners used shall comply with AS 3566 Class 4 and be certified as such by the
supplier of fasteners and to the approval of the S.O.
7.6
Unless otherwise shown on the Drawing, the bituminous corrugated roofing sheets
shall have the following minimum requirements:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
Length
Width
Cover width
Thickness
Weight of material
Thermal resistance R- value
Thermal conductivity
= 2000 mm
= 950 mm
= 855 mm
= 3 mm
= 3.3 kg/m2
= 0.04 mK/W
= 0.066 W/mk
8.2
8.3
Ridge capping, nails and screws shall be provided to match the roofing sheets while
ridges, verges, eaves, hips, valleys, side-wall and end-wall details shall be fixed
strictly in accordance with the manufacturers recommendation.
Unless otherwise shown on the Drawing, the bituminous corrugated roofing tiles
shall have the following minimum requirements:
(i)
(ii)
(iii)
(iv)
Length
Width
Wave height
Thickness
= 1060 mm
= 400 mm
= 40 mm
= 3 mm
9.2
Bituminous roofing tiles shall be laid at a minimum roof pitch of 9 and on timber or
steel battens approved for roofing at spacing and tightly nailed/screwed as
recommended by the manufacturer.
9.3
Ridge capping, nails and screws shall be provided to match the roofing tiles while
ridges, verges, eaves, hips, valleys, side-wall and end-wall details shall be fixed
strictly in accordance with the manufacturers recommendations.
Fibre-cement corrugated sheets shall comply with MS 1224. The thickness of the
sheets shall be 3 mm thick for shallow corrugation and 4 mm thick for medium
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
G/6
corrugation. The cement shall comply with MS 522: Part 1. Asbestos processed or
unprocessed shall not be added to fibre-cement sheets.
10.2
The surface intended to be exposed to the weather shall have a generally smooth
finish. Variations of the surface appearance which do not impair the characteristics
of the sheets as defined in MS 1224 are permitted.
General
Heat insulation system shall comply with MS 1020. Samples of the insulation
material shall be submitted to the S.O for approval before they are used and
subsequent delivery shall be up to the standard of samples approved.
11.2
Reflective Foil
11.2.1 Reflective foil shall be fire retardant double sided aluminium reflective foil
bonded to reinforced high density polyethylene woven fabric.
11.2.2 The reflective foil materials used shall conform to fire safety requirements
and BS 476: Fire Test on Building Materials and Structures on the following
test:
(i) Non-combustibility test for materials.
(ii) Method of test for fire propagation for products.
(iii) Method of test to determine the classification of the surface spread of
flame.
11.2.3 Reflective foil properties shall conform to the following:
(i) Thickness : 137 20 micron thick.
(ii) Grammage : 163 10g / m2.
(iii) Tensile strength : 500 N / 50 mm (MD), 500 N / 50 mm (Cross
Direction).
(iv) Emissivity ASTM E408 0.05(972%) / Reflectivity = 95%
(v) Initial Tear resistance: ASTM D1004 >30N
(vi) Tear Propagation: DIN53363 > 600 N/mm (CD) / 800 N/mm (MD)
11.2.4 Reflective foil material may be used on its own with all types of roofs except
with metal decking roof. Where roof is of metal decking, the reflective
insulation material shall be laid below stone wool or glass wool for effective
thermal and acoustic performance.
11.2.5 The reflective foil material shall be installed strictly in accordance with the
manufacturers recommendation. A uniform air space of 20 mm between
the tile roof covering and the insulation material shall be provided to ensure
the effectiveness of the reflective surface. All punctures shall be effectively
sealed with similar reflective material to prevent air leakage and moisture
transfer.
11.2.6 The reflective foil surface shall be free from any thin film of oil, plastic or
lacquer coatings. All dust and/or moisture, if any, shall be thoroughly
cleaned prior to installation. All dust and/or trademarks shall be limited to a
maximum of 5% of the total reflective area. The insulation material shall be
fitted closely around electrical outlet boxes, plumbing and et cetera, and
taped securely to eliminate gaps or voids through which air or water vapour
might pass into the cooler space.
11.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
G/7
11.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
G/8
TABLE OF CONTENTS
SECTION H: TIMBER, JOINERY AND IRONMONGERY WORKS
PAGE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
General
Timber Grades And Size Tolerances
Treatment Of Timber
Moisture Content And Storage
Structural Assemblies Of Timber
Timber Joints
Prefabricated Timber Roof Truss System
Glued Laminated Timber For Structures
Carpentry Works
Joinery Works
Timber Floor Finish
Ceiling Timber Battens
Timber Partitions
Fascia And Barge Boards
External Boarding
Staircase And Balustrades
Timber Solid Panel Doors
PVC Doors
Products And Materials
Ironmongery
Built-in Furniture
H/1
H/1
H/1
H/3
H/3
H/4
H/5
H/7
H/12
H/13
H/13
H/13
H/14
H/14
H/14
H/14
H/15
H/15
H/15
H/17
H/17
TABLE H1
TABLE H2
H/20
TABLE H3
TABLE H4
TABLE H5
TABLE H6
TABLE H7
TABLE H8
APPENDIX H/1
H/21
H/22
H/23
H/24
H/25
H/26
H/28
H/29
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/1
1. General
1.1
Unless otherwise specified or shown in the Drawings, the timber species used for
the Works shall be as stated hereinafter in the TABLE H1. The strength grouping for
timber shall be in accordance with MS 544 as shown hereinafter in the TABLE H2.
1.2
All carpentry and joinery work shall include all necessary notching, halving,
morticing and tenoning, wedging, scarfing, dovetailing, sinking for heads of bolts
and nuts and trimming for opening.
1.3
All carpentry work shall be left with a sawn surface except where particularly
described to be wrot. All joinery shall be wrot and finished with sand paper as
required and all sizes stated are the finished sizes. Sizes for carpentry shall be
within the tolerances stated in sub-section 2.1 and sizes for joinery shall be within
the tolerances stated in sub-section 2.2.
1.4
Unless otherwise indicated in the Drawings, all fire protection materials and systems
must show evidence that they have been subjected to the fire resistance test in
accordance with BS 476 or other approved equivalent standards.
Unless otherwise specified, sawn timber for carpentry work shall be as stated
hereunder:
(i)
(ii)
(iii)
(iv)
2.2
Grading shall be carried in accordance with the Malaysian Grading Rules (MGR) by
timber graders registered with the MTIB. Every timber consignment shall be
accompanied by the Grading Summary certified by the registered timber grader.
The sizes of sawn timber, except where otherwise specified, shall be within the
margin of permissible variations stated hereunder:
(i) For widths, depths or thicknesses not exceeding 75 mm - within 3 mm of the
specified size
(ii) For widths, depths or thicknesses exceeding 75 mm - within 5 mm of the
specified size.
2.3
2.4
Unless otherwise specified, sawn timber for joinery work shall be of Sound Grade
(General Market Specification (GMS) and Strips) and Serviceable Grade
(Scantlings). The finished size for joinery, unless otherwise specified, shall be within
the margin of permissible variation stated hereunder:
(i) For widths, within 3 mm of the specified finished size.
(ii) For thicknesses, within 2 mm of the specified finished size.
3. Treatment Of Timber
3.1
All timber except the heartwood of the naturally durable timbers as scheduled in
TABLE H2 hereinafter and timber for formwork, scaffolding, and other temporary
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/2
3.3
Unless otherwise specified, the average moisture content for all timber shall not
exceed 25% in accordance with MS 360. The moisture content shall be determined
in accordance with one of the methods given in MS 837.
3.4
All timber shall be sawn or planed before treatment to achieve the finished crosssection required. As far as possible, all cross-cutting, boring, drilling or other
processing should be carried out before treatment.
3.5
The pH value of the treating solution shall not be higher than 3.0 when determined
by a glass electrode or pH paper at ambient temperature in accordance with MS
360.
3.6
The net dry salt retention shall be determined in accordance with one of the
methods given in MS 360 and MS 821. The minimum salt penetration shall be
determined by one the test methods given in MS 833.
3.7
No
i)
ii)
iii)
3.7.2
3.8
The minimum nett dry salt retention for CCA shall be as shown in the table
below:
Use
Interior and above the ground
Exterior and above the ground
Exterior and in contact with the
ground (other than foundation
piles)
The Contractor, when required by the S.O. shall produce a certificate from a
preservative treatment plant which certifies that timber required to be impregnated
by means of vacuum pressure processes has been impregnated and has achieved
the necessary nett dry salt retention. Notwithstanding the certificate, the S.O.
reserves the right to carry out independent tests to determine the nett dry salt
retention and the result so obtained shall be conclusive.
3.8.1
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/3
Treatment certificate
3.8.1.1
3.8.1.2
At the time of installation, the moisture content of the timber for the various
applications shall not exceed that as specified in TABLE H3.
4.2
Moisture content for foundation piles, formworks and temporary works is not critical
for these applications and therefore is not specified.
4.3
4.4
On delivery to the site, all timber other than timber for foundation piles, formworks
and temporary works shall be properly open-stacked, under cover. Kiln dried timber
shall be properly wrapped and stored under cover if it is not used immediately.
The quality of the surface, as finished, shall be appropriate to the position and
use of the timber.
(ii)
When grade or other necessary marks are removed, provisions shall be made
for remarking in accordance with Malaysian Grading Rules. Surfaces at any
joint in an assembly shall be such that the parts may be brought into contact
over the whole area of the joint before connectors are inserted or any pressure
or restraint from the fastening is applied. These surfaces shall have a good
sawn or planed finish.
(iii) Bearing surfaces of notches and other cuttings shall be true and smooth and in
appropriate relation to the other surfaces of the piece.
5.2
Notches other than at the ends of beams shall be U-shaped formed by parallel cuts
to previously drilled holes. The diameter of the hole shall be equal to the width of the
required notch.
5.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/4
6. Timber Joints
6.1
When solid timber members are to be jointed together using mechanical fasteners,
the workmanship and method of assembly shall be in accordance with MS 544 Part
5. The mechanical fasteners are as listed below:
6.1.1
Nailed joint
Where necessary to avoid splitting, nails shall be driven into pre-drilled
holes or diameter not greater than four-fifths of the diameter of the nails.
Care shall be taken to avoid placing nails in any end split.
6.1.2
Screwed joint
Lead holes shall be used to ensure good workmanship in making screwed
joints. The diameter of the hole for the shank shall be equal to the diameter
of the shank, and for the threaded portion, the diameter of the hole shall
not be greater than seven-eighth of the diameter of the root diameter of the
screw thread adjacent to the shank. Care shall be taken to avoid placing
screws in any end split.
6.1.3
Bolted joint
6.1.3.1
6.1.3.2
A washer shall be fitted under the head of each bolt and under
each nut. The minimum sizes of washers are as given in Part 6
of MS 544. Where joints using split-rings are to be used, as
shown in the Drawings, the members of the joints shall be fitted
together in their appropriate positions and clamped or spiked
together before drilling. Alternatively, drilling jigs or multiple
head boring machines may be used, or individual members
may be marked out from the setting-out or by use of prepared
templates.
6.1.3.3
6.1.3.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/5
6.1.3.5
6.1.3.6
6.1.3.7
Care shall be taken to ensure that all chips and shavings are
removed, and rings shall be expanded before being placed in
the grooves.
6.1.3.8
6.1.3.9
6.1.3.10
6.1.3.11
6.1.3.12
6.1.3.13
7.2
System Provider
7.2.1
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/6
7.4
Fabricator
All trusses shall only be assembled by licensed fabricators approved by the S.P.
and registered with CIDB. A copy of the CIDB registration certificate shall be
submitted to the S.O. for verification.
7.5
Installer
All installation works shall be executed and supervised by qualified personnel with
valid certificates issued by CIDB. The S.O. shall verify the identification and
qualification of the installer prior to the installation.
7.6
Prior to any pre fabricated timber roof trusses works, the following general
limitation shall be applied:
(i)
(ii)
(iii)
(iv)
7.7
The S.P. through the Contractor shall propose to the S.O. or his approval a
roof truss system which is safe, functional and conforming to design
standard. Submission of proposal shall include truss analysis, design
report, and construction drawings. The truss analysis shall indicate all
loads, load combinations, connections criteria, bracings and tie-down of
the truss. Design output of the truss members, battens, connections, tiedown and wall plates, anchors, bracings, truss accessories, splicing and
stiffeners where related to the analysis shall be included in the design
report. (Refer to Appendix 3 of JKR 20601-0190-12)
7.7.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/7
anchor, tie-down and anchoring details and all types of connection details
including the connection of all attachments to the trusses.
7.7.3
7.8
Technical specifications for fastener and anchor of which the design refers
to shall also be submitted. Verification test certificate from an approved
accredited laboratory on the technical parameter specified in the technical
specifications shall be submitted upon request by the S.O.
Warranty
7.8.1
When a prefabricated timber roof truss system is used, the Contractor shall
submit to the S.O. a warranty from the S.P. with the following provisions:
(i)
(ii)
The products used are genuine and free from manufacturing defects;
The prefabricated timber roof truss system is installed in accordance
with the S.P.s instructions, guidance and specifications that will deliver
the specified level of performance;
(iii) The warranty certificate shall cover a period of ten (10) years from the
date of Certificate of Practical Completion against any defect or failure
due to the installation and workmanship by the S.P.s registered panel
installer.
8.2
General
8.1.1
8.1.2
8.1.3
8.1.4
Prior to fabrication, the Contractor shall notify the S.O. on the dates of tests
that shall be carried out. The S.O. may appoint a representative in the
event the S.O cannot be present during the tests. The Contractor shall
forward a copy of the test results jointly certified by the manufacturer for
the S.O.s acceptance and approval.
Material
8.2.1
Timber
8.2.1.1
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/8
8.2.2
8.2.3
8.2.4
8.2.1.2
8.2.1.3
8.2.1.4
The visual strength grading for all timber used for structural
works should be visually graded based on the grading
requirements of MS 1714: Specification for Visual Strength
Grading of Tropical Hardwood Timber. The visual grading shall
be carried out by timber graders registered with MTIB.
8.2.1.5
8.2.2.2
8.2.3.2
Adhesive
8.2.4.1
8.3
The individual laminations shall be end jointed to the final length before
planing.
8.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/9
8.3.2
8.3.3
8.3.4
8.3.5
8.3.6
8.3.7
8.3.8
Cramping
8.4.1
The cramping arrangement shall ensure a uniform pressure over the glue
line. The pressure shall be that specified in the adhesive manufacturers
instructions for the adhesive used but in no case shall it be less than 0.7
N/mm2. The application of pressure at a suitable temperature shall be
completed within the closed assembly time, when a continuous squeeze
out or bead along the edge of each glue line shall be produced.
8.4.2
8.5
8.6
8.7
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/10
Preservative Treatment
8.5.1
Where the timber used is not naturally durable (as specified in TABLE H2),
it shall be preservative treated. The treatment of timbers shall be as
specified in sub-section 3: Treatment of Timber of this specification.
8.5.2
Coating Specification
8.6.1
All glued laminated timber members shall be coated with a minimum of two
coats of clear construction sealer. The sealer shall be applied in
accordance with the manufacturers specification and to the S.O.s
approval. The Contractor shall rectify any damage to the coating after the
erection has been carried out. The Contractor shall also provide details of
the sealer used to the S.O. for record.
8.6.2
Submission Of Documentation
8.7.1
Prior to the manufacture and fabrication of the glued laminated timber, the
Contractor shall provide two (2) copies of the following documents for the
S.O.s approval:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
8.8
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
8.8.2
From each work shift and each production line, a representative sample of
end joint shall be drawn and tested in flatwise bending as described in BS
EN 385. For each production line and shift the bending strength is
acceptable is if one of the condition stated in sub-section 7.1.2 of MS
758:2001 is met.
8.8.3
Also, from each shift which gluing is carried out, one full cross-sectional
specimen shall be taken for every press load or every 10 m3 of production.
The specimen shall be cut from a cured glued laminated timber member
produced during each work shift. If all tests for a three-month period satisfy
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/11
the requirements the number of samples may be reduced to not less than
half the number prescribed above.
8.9
8.8.4
The Contractor shall provide information on the glue line integrity, results of
delamination tests and results of glue line shear test which shall not be
less than as stipulated in MS 758.
8.8.5
The values for manufactured glued laminated timber shall not be less than
the value for designed glued laminated timber. The values of the
manufactured glued laminated timber properties shall be determined in
accordance with MS 544: Part 2 or AS/NZS 4063.
8.9.2
Qualification tests
8.9.3
8.10
8.9.2.1
8.9.2.2
8.9.2.3
The Contractor shall submit the method statement of installation for the
approval of the S.O. The method statement shall explain the sequence of
erection of glued laminated timber and required safety measures. Glued
laminated timber members shall be installed in accordance with the
Assembly Drawings.
8.10.2
8.10.3
During on-site storage, glued laminated timber members shall be stored off
the ground with spacer blocks spaced between members. The Contractor
shall be responsible for the storage of glued laminated timber members
properly at site to prevent bending, tipping or toppling of the members.
JKR 20800-0183-14
01
00
29 Januari 2014
H/12
8.10.5
8.10.6
During erection, glued laminated timber frame shall be properly braced that
is permanent and temporary bracing to provide stability in accordance with
the method statement prepared by the Contractor and approved by the
S.O.
The Contractor shall ensure the accuracy of the prepared foundation,
position of glued laminated timber structure, base plate and holding down
bolts. Any discrepancies and deviations shall be remedied by the
Contractor to S.O.s approval before erection commences.
8.10.8
8.12
:
:
:
:
:
8.10.4
8.10.7
8.11
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
Glued laminated timber structures shall not have any debonding. Glued
laminated timber structures affected by debonding shall be marked as
Rejected and removed from site.
8.11.2
8.11.3
Warranty
8.12.1
9. Carpentry Works
9.1
All carpentry shall be accurately set out in strict accordance with the Drawings and
shall be framed together and securely fixed to the approval of the S.O. Timber
framing shall be properly braced and checked, halve, screwed or bolted together as
required. Longitudinal joints in plates, ridge, fascias, et cetera shall be formed over
supports. Those timber members with lapped joints shall lap at least 150mm or
twice the depth of the timber whichever is the greater. The brads, nails, screws,
spikes, plugs, bolts, framing anchors and timber connectors shall be provided
wherever necessary and as detailed. Other than those detailed, no joints are
permitted in structural work unless prior permission is obtained from the S.O. No
structural member shall be notched unless instructed by the S.O.
9.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/13
For the carpentry works, timbers shall, as far as possible be in piece between
continuing lengths. At corners, timbers shall be halved for materials of the same
thickness, and sufficiently lapped for materials of different thicknesses.
All doors, windows, louvers, screens and the like shall be constructed as shown in
the Drawings. Frames shall be assembled at the commencement of the work and all
members shall be carefully morticed and tenoned together but no wedging, pinning
or gluing shall be done until the framing is prepared in readiness for immediate
fixing. All doors, windows, louvers, screens and the like shall be properly stored on
site.
10.2
Immediately before fixing in its final position, joinery shall be wedge and pinned by
drawn hole pinning with 10 mm diameter Strength Group 1 and 2 timber dowels
pins. The pins shall be left projecting until permission is given for flushing off. The
methods of framing and putting together of all Works shall be approved by the S.O.
before being executed. Any portions that warp, twist or develop any other defects
shall be replaced before wedging up. All framed work shall be pinned before being
framed together.
10.3
The choice of species for joinery should be based on working properties of timbers
that is maximum percentage of shrinkage.
10.4
Jointing or connection for joinery that is nailed joint, screwed joint, coach screwed
joint or bolted joint shall comply with MS 544 Part 5.
Unless otherwise shown in the Drawings, timber floors shall be constructed using
100 mm x 38 mm wrot, tongued and grooved boardings, well cramped up and
secret nailed to each joist or batten with 62 mm wire nails. Floor boarding shall be in
long lengths with splayed heading joints and no two adjacent joints shall occur over
the same joist. On completion, the flooring shall be planed, sanded and all gaps
sealed with an approved sealer. The floor shall then be cleaned off and unless
otherwise specified, it shall be finished with three coats of approved polyurethane
paint applied strictly in accordance with the manufacturer's instructions.
11.2
Wrot timber skirting shall be provided where shown and as detailed in the Drawings.
Skirting shall be in long lengths with splayed heading joints and with mitres, returns
and ends neatly cut and fitted and fixed to grounds.
11.3
Where engineered timber flooring are specified or shown in the Drawings, it shall be
finished with high abrasive protective overlay and a moisture barrier balancing film
to be applied on timber flooring backing in accordance with the manufacturers
recommendations and S.Os approval.
11.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/14
beading. Ceiling panels shall be set out symmetrically from the centre line of the ceiling.
Suspended ceiling systems shall be as specified in SECTION I: CEILING WORKS.
Unless otherwise shown on the Drawings, all external boarding shall be formed with
150 mm x 19 mm horizontal, vertical or diagonal boarding in wrot pressure-treated
timber in long lengths and to the sectional profile as detailed in the Drawings.
15.2
Unless otherwise shown, lapping for plain weather boarding shall be 38 mm.
Boarding shall be secured to the frames using 75 mm galvanized steel nails and in
the case of plain weather boarding, nails shall not be driven through the lapped
portions. The exposed bottom ends of all external vertical boarding shall be splayed
inward at an angle of 30 degrees and treated with preservatives.
15.3
The timber boarding shall be cleaned off and unless otherwise specified, it shall be
finished with approved polyurethane base paint with UV protection applied strictly in
accordance with the manufacturer's recommendations. The strength grouping for
external timber flooring shall be in accordance with the Properties of Malaysian
Timber as shown hereinafter in TABLE H6.
15.4
15.5
Unless otherwise shown in the Drawings, the Contractor shall prepare Shop
Drawings as required for the Works. Prior to the fabrication and installation works,
the Contractor shall submit the Shop Drawings to the S.O. for approval.
16.2
The preferred sizes for modular staircase and stair openings shall comply with MS
1064: Part 3.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/15
All fire doors shall be of the appropriate Fire Resistance Period (FRP) in accordance
with the Ninth Schedule of the Uniform Building By-Laws.
17.2
All fire doors including frames shall be constructed to a specification of the relevant
FRP in accordance with MS 1073 and shall be tested by a laboratory, approved and
certified by DGFR and have obtained a Product Certification Scheme from an
accredited certification body.
17.3
All double leaf doors with rebated meeting stiles shall be provided with coordinating
device so as to fit fully within the door openings with a gap of not more than 3mm
between the frame and the edge of the door when closed.
17.4
Where shown on the Drawings, approved vision panel of suitable size shall be
incorporated in the Fire Rated Door.
17.5
Flush doors shall generally comply with MS 1506: Specification for Wooden Door
with plywood facing and strength group 1 and strength group 2 timber lipping, mitred
around all edges. The plywood and strength group 1- 4 shall in all respects with the
Specifications mentioned hereinbefore.
17.6
The preferred sizes for modular door sets shall comply with MS 1064: Part 4 and for
modular windows shall comply with MS 1064: Part 5.
Unless otherwise specified in the Drawings, PVC doors shall be of strong impact
resistance and waterproof/moisture resistant laminated timber finish on both sides.
Unless otherwise shown in the Drawings, the door shall be 38 mm thick.
18.2
PVC toilet doors shall be of full single panel of flush type. It shall be 100%
waterproof, strong impact resistance and not be discoloured easily. Unless
otherwise shown on the Drawings, the door shall be 38 mm thick. PVC door shall be
delivered to the site complete with ironmongery as listed in the TABLE H7.
Plywoods
19.1.1
Unless otherwise specified, plywood used for interior and exterior purposes
other than for formworks and temporary works shall be manufactured with
Moisture Resistant (MR) bond and Weather and Boil Proof (WBP) bond
respectively in compliance with MS 228. Boards which are to be painted or
varnished shall be properly sanded down and holes and crevices filled with
approved wood putty or filler.
19.1.2
Plywood intended for use as shuttering board shall be of the Weather and
Boil Proof (WBP) type.
19.1.3
19.1.4
19.2
19.3
19.4
19.5
19.6
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/16
Blockboard
19.2.1
19.2.2
Chipboards
19.3.1
19.3.2
All fibre building boards namely, Hard Board, Medium Board and Medium
Density Fibre Board (MDF) shall comply with MS 1429 and MS 1912. The
type and quality of Fibre building boards shall be as approved by the S.O.
Perforated hardboards shall be not less than 3.2mm thick with maximum of
4.8mm perforation at 19mm centers unless otherwise stated in the
Drawings.
19.4.2
All fibre building boards shall be fixed strictly in accordance with the
manufacturers instruction. Unless otherwise detailed in the drawings, the
ceiling boards shall be butt and `V jointed.
Composite Boards
19.5.1
The type and quality of composite boards shall be as approved by the S.O.
and shall be fixed strictly in accordance with the manufacturers instruction.
19.5.2
Woodwool Slabs
19.6.1
19.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
Woodwool slab shall comply with MS 1036 and shall be of the type and
quality as approved by the S.O. Unless otherwise specified in the
Drawings, the slab shall be laid with its length at right angles to support,
fixed strictly in accordance with the manufacturers instruction.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/17
19.8
19.9
Boards which are to be painted shall be lightly sanded and any dust shall
be removed from the surface with a piece of clean coarse cloth. Any filling
compounds used shall be alkali-resistant. Fixing of the board shall be in
accordance with the manufacturers instructions.
WPC shall be made from minimum 70% rice husk and balance recycled
HDPE. WPC solid decking system shall be of 145 mm (w) x 25 mm (t)
fixed onto 300 mm c/c on Suspended Leveling System with hot dipped
zinc-aluminium alloy coated steel with a minimum coating mass of AZ150
to AS/NZS 1397-2002 steel sheet grade G300 on to flat concrete slab with
ENSS03 stainless steel clip, all in accordance with manufacturer's
recommendation and S.Os approval.
20. Ironmongery
20.1
Unless otherwise shown on the Drawings, the Contractor shall supply and fix all
ironmongery as listed in the TABLE H7 attached hereinafter, complete with fixing
screws of the same material and finish.
20.2
Proper sockets shall be provided for all bolts to fix flush in floors, cills and door and
window frames. Each lock shall be provided with three keys and no locks shall have
identical keys, unless specifically required by the S.O.
20.3
All doors, windows, gates, joinery, et cetera, shall be provided with anti-rust heavy
duty ironmongery appropriate for its function, complete with fixing screws of the
same material and finish.
20.4
All doors shall be provided with door-stops, door-closers and other appropriate
ironmongery where applicable or as shown on the Drawings.
20.5
The submission of ironmongery set shall have been tested and certified by SIRIM
QA Services Sdn. Bhd. or approved equivalent.
General
21.1.1
21.1.2
21.2
21.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/18
21.1.3
21.1.4
21.1.5
Built-in furniture materials and loose furniture delivered to the site shall be
properly stored by arranging them in stacks, keeping them properly
wrapped and stored under cover if they are not used or assembled
immediately.
Materials
21.2.1
21.2.2
The formaldehyde emission for all composite wood products and wood
based panels shall comply with MS 1787.
21.2.3
21.2.4
21.2.5
Adhesive for wood and composite wood products shall be phenolformaldehyde resin adhesive classified as weather-proof and boil-proof, in
accordance with MS 908.
21.2.6
21.2.7
21.2.8
Where timber species are used it shall be constructed and properly framed
in wrot timber as detailed in the Drawings.
Component Assemblies
21.3.1
21.3.2
Screws shall have countersunk heads which shall comply with MS ISO
1482.
21.3.3
Hinges shall have a spring mechanism to lock the door in a close or open
position, remain completely hidden behind the door and enable the door to
open to 120 degrees.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/19
21.3.4
Drawer slides shall be epoxy powder coated metal, mounted from the
bottom and provided with friction bearing-mounted nylon rollers.
21.3.5
21.3.6
21.3.7
Drawers for storing small kitchen cutlery shall have thermoplastic inserts
with subdivided compartments.
21.3.8
21.3.9
21.3.10 Unless otherwise specified, worktops and countertops shall have a flat
edge finishing at the perimeter. Worktops and countertops shall be
provided with holes and cut-outs for plumbing components, where
applicable. All joints shall be inconspicuous and use the manufacturers
recommended adhesive and silicone sealant.
21.3.11 Built-in furniture sliding doors shall be fitted with guides or similar fittings,
rollers or ball bearings, pull handles, stops and locking mechanisms.
21.3.12 Cabinet doors with glass inserts and/or panels shall be constructed with
proper support to ensure that the glass remains securely fixed. Support
shall be bedded in mastic with all interstices completely filled.
21.3.13 Glass inserts and/or panels and glass shelves, where applicable, which
needs to be structurally strong shall be tempered glass. Tempered glass
shall comply with MS 1498.
21.3.14 Cupboards, wardrobes, cabinets and shelves shall have peg-holes on
either side internally, allowing for adjustable shelf height. Adjustable legs, if
applicable, shall be of a proprietary system type as approved by the S.O.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/20
Typical Usage
Species
Structural frames
1.1 All columns, stilts and beams
SG4
SG5
SG5
SG5
SG5
Flooring
4.1 Floor bearers, joists and strutting for joists
4.2 Floor boardings
4.3 Gymnasium floor boarding
4.4 Parquet flooring
4.5 Skirtings
SG5
SG5
SG4
SG5
SG5
Walling
5.1 Wall and partition framings
5.2 External wall boardings
5.3 Internal wall boardings
SG5
SG5
SG7
Roof structures
6.1 Roof trusses, rafters, purlins, wall plates and other roof members
6.2 Fascia boards
SG4
SG5
Ceiling frames
7.1 Ceiling joists and spacers
7.2 Cover battens to joints of ceiling sheets
7.3 Ceiling strips and soffit battens
SG5
SG7
SG7
SG5
SG7
Furniture fitting
9.1 Built-in fittings and furniture in general
9.1.1 Carcassing
9.1.2 Lining/Panelling
9.1.3 Top
9.2 Workshop furniture top
SG5
SG7
SG5
SG5
SG5
10
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/21
S.G 3
S.G 4
S.G 5
Balau
Belian
Bekak
Giam
Jati
Bitis
Mata Ulat
Delek
Malabera
Tembusu
Cengal
Kekatong
Keranji
Merbau
Penaga
S.G 6
S.G 7
Resak
B) Requiring Treatment
Dedaru
Kempas
Merbatu
Mertas
Agoho
Balau Merah
Kelat
Kembang
Semangkuk
Berangan
Dedali
Derum
Alan Bunga
Babai
Balik Angin Bopeng
Bayur
Damar Minyak
Durian
Ara
Batai
Geronggang
Kapur
Bintangor
Jelutung
Laran
Kulim
Kasai
Brazil Nut
Jenitri
Pelajau
Pauh Kijang
Keruntum
Gerutu
Jongkong
Pulai
Penyau
Mempening
Kundur
Kasah
Sesenduk
Perah
Kedondong
Macang
Terentang
Petaling
Meransi
Meranti
Bakau
Keledang
Ranggu
Merawan
Keruing
Ru
Merpauh
Ketapang
Medang
Melantai/
Kawang
Meranti Merah
Muda
Surian Batu
Nyalin
Kungkur
Meranti kuning
Tualang
Perupuk
Melunak
Mersawa
Punah
Mempisang
Sengkurat
Rengas
Mengkulang
Terap
Simpoh
Notes :
1. For naturally durable timbers, sapwood should be excluded. If sapwood is included, preservative treatment is
necessary.(Source: MS 360:1986)
2. For timber requiring treatment, they should be amenable to preservative treatment.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/22
Structural Components
Columns, beams, bearer,
studs, joists, ties and struts
Roofing
battens
Staircase
balustrades
Flooring
skirtings
Walling
fascia boards
Ceiling Frames
workshop furniture
25%
Not applicable
25%
Not applicable
19%
12%
19%
12%
19%
19%
12%
12%
19%
19%
19%
19%
12%
Not applicable
12%
Not applicable
25%
Not applicable
19%
12%
19%
12%
19%
12%
19%
12%
19%
19%
12%
12%
19%
12%
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/23
Class 2
Class 3
Class 4
Durable (5 to 10
years)
Balau
Bekak
Bitis
Kasai
4a
Kapur
6a
Nyatoh
Merbau
Mersawa
Merbau lalat
2
Delinsem
Malabera
5a,b
Medang
Penaga
Pelawan
Ranggu
Surian batu
Teak
Agoho
Balau, red
Bakau
Bungor
Derum
Dedali
Dedaru
Delek
Dungun
3
Acacia
Pauh kijang
4b
Kapur
Kelat
Kembang
semangkok
Kempas
Keranji
Gegatal
Kulim
Rengas
Sepetir
Tumu
Tualang
Telor buaya
Pelong
Kerukup
2
Brazil nut
Keruntum
8a,b,c
Keruing
9a,b
Keledang
Mata ulat
5c
Medang
7a,b,c,d,e
Meranti,
dark red
Mempening
Mengkulang
Meransi
Merbatu
Tembusu
Kungkur
Merawan
Leban
Nyalas
Pauh kijang
Petaling
Punah
Merbau kera
Meranti, white
Mertas
6b
Nyatoh
Nyireh
Nipis kulit
Pelajau
Nyatoh
Perapat
Perah
Perupok
Petai
Podo
Pulai
Putat
Ramin
Samak
Sena
Sawa luka
Sepul
Geronggang
Sesenduk
Gerutu
Gading
Gapis
Meranti bakau
Meranti, light
red
Jenitri
Jongkong
Kasah
Kekabu
Kawang
9c,d,e
Keledang
4c
Kapur
Kayu malam
Kedondong
Kungkur
Meranti, yellow
Sentang
Simpoh
Sempilor
Terentang
Laran
Lelayang
Lilin
2
Limpaga
Ludai
Merpauh
5e
* The results were obtained from the graveyard test from the Forest
Research Institute Malaysia test site.
6b
All samples taken from heartwood area except for the timber
which their sapwood and heartwood cannot be differentiated.
Timber of the same species but from different regions in Malaysia
may have different durability classifications.
2
4a
6c
Api-api
Ara
Berangan
Balek angin
Bintangor
Batai
Bayur
Damar minyak
Dungun paya
Durian
Engkabang
Jelutong
Gaham badak
Tapus
Terap
Tuai
Tulang daing
Ketapang
Rubberwood
3
Pine
3
Yemane
Coconut
Tengkurung
Penarahan
8d,e
Keruing
Meranti
tembaga
Machang
5d, e
Medang
Mempisang
Merbatu
Melantai
Minyak berok
Litsea megacarpa
Palaquium impressinervium
Palaquium maingayi
6c
Palaquium gutta
7a
Shorea uliginosa
7b
Shorea platyclados
7c
Shorea pauciflora
7d
Shorea singkawang
7e
Shorea curtisii
8a
Dipterocarpus sublamellatus
8b
Dipterocarpus crinitus
8c
Dipterocarpus verrucosus
8d
Dipterocarpus kerrii
8e
Dipterocarpus lowii
9a
Artocarpus interger
9b
Artocarpus lanceifolius
9c
Artocarpus dadah
9d
Artocarpus rigidus
9e
Artocarpus heterophyllus
6a
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/24
Class 2
Class 3
Class 4
Durable (5 to
10 years)
Moderately durable (2 to 5
years)
Kapur bukit
Kapur
kelansau
Baru
Kapur paji
Acacia
Bindang
Bedaru
Kapur paya
Alan
Geronggang
Asam
Jadap
Bajan
Jelawai
Bayur
Jelutong
Bengang
Kayu cina
Benuah
Kayu malam
Binuang
Kelampayan
Kawi
Kandis
Luis
Kasai
Lun runcing
Leban
Mertama
Nyireh
Nyatoh
Rhu
Selangan
batu4a
Pelajau
Resak
membangun
Luis/Chengal
pasir
Medang luis
kasar
Mengkulang
Mersawa
kunyit
Petai belalang
Sempilor
Seladah
Bintangor
Selumar
Bintawak
Kembang
semangkok
Kepayang babi
Selunsur
Dungun
Keranji
Tapang
Durian
Keruing
Urat mata
Empenit
Ketiau
Entuyut
Kumpang
Litoh
Legai
Meranti, light
red
Yellow flame
4b, c
Medang
Menggris
Mersawa
paya
Minggi
Ngilas
Mergasing
Peran/bilat
5a, b
Meranti, yellow
Nyatoh
Segera
Pelai
Seladah6a, b
Perah
Sentang
Perupok
Simpoh Tampoi
Petai
Tekalong
Pitoh
Teruntum Ubah
Ramin
Resak
paya
Sawih
Upi
The results were obtained from the graveyard test from Oya Road, Sibu test site. All samples taken from
heartwood area except for the timber which their sapwood and heartwood cannot be differentiated.
Timber of the same species but from different regions in Malaysia may have different durability
classifications.
Shorea pulricostata
Palaquium rivulare
4a,b,
c Shorea flava, S. laecis, S. spp
5a,b
Dacryodes incurvata, Santira laevigata
6a,b
Palaquium pseudorostratum, Ganua motleyana
3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/25
No
Species
1
Balau
2
Merbau
3
Red Balau
Medium Hardwoods
1
Kelat
2
Kempas
3
Keruing
4
Mengkulang
5
Merpauh
Light Hardwoods
1
Bintagor
2
Dark Red Meranti
Air-dry
density
(kg/m3)
850-1155
515-1040
800-880
Strength
Tangential
Movement
Very strong
Strong
Strong
2.1 2.5%
2.1 2.5%
2.1 2.5%
Strong
Very strong
Strong
495-1010
770-1120
690-945
Strong
Strong
2.1 2.5%
> 3.1%
2.6 3.0%
3.1%
2.1 2.5%
1.5 2.0%
Moderately strong
Moderately strong
1.5 2.0%
< 1.5%
495-865
560-865
625-895
640-880
1.5 2.0%
3
4
5
Gerutu
Mersawa
Yellow Meranti
Moderately strong
Moderately strong
Moderately strong
2.6 3.0%
2.1 2.5%
1.5 2.0%
575-880
515-735
575-735
( Source: Choo KT, Gan KS & Lim SC, Movement of Seasoned Timber in Service, FRIM
Technical Information Handbook No 18 )
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/26
3. PVC Door To
/Bathroom Cubicles
Toilet
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/27
Escape
8. Glass Door
9. Aluminium Door
Door/
a)
b)
c)
d)
11. Wardrobe
a)
b)
c)
d)
e)
12. Drawer
a) Top or bottom running set sliding and folding door gear, complete with tracks,
channel, brackets, roller guides, hangers and all necessary butt hinges, flush
bolts and flush door pulls, etc. as recommended by the manufacturer.
b) 1 No. upright 3 lever rebated mortice lockset for sliding and folding door with
satin chrome lever handle furniture with 2 Nos. keys of different serial number
for each building.
a) Top or bottom running set straight sliding door gear complete with tracks,
brackets, hangers, roller guides, channels, door stops, flush brass bolts, brass
flush pull etc. as recommended by the manufacturer.
b) 1 No. upright 3 lever mortice lockset with satin chrome finish for straight sliding
door with 2 Nos. keys of different serial number for each building.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/28
Strength class
Mengkulang
D40
Merbau
Keruing
D50
Kapur
Kempas
D60
Balau
D70
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/29
APPENDIX H/1
Any defect claims shall be made in writing and delivered by post or by hand to the
Manufacturer.
ii)
A technical team from the Manufacturer will be dispatched to evaluate the nature of the claim.
Should our findings conclude the defects as within the scope of warranty, then the Manufacturer
shall make good such defects.
iii)
Should the Manufacturers technical team conclude that the defects falls outside the scope of
the warranty, the Manufacturer shall not be held responsible for the claim.
iv)
Should the Government disagree with the conclusion of the technical team pertaining to the
defects in particular, then an independent third party competent in such technical evaluation
shall be appointed to investigate the disputed defects.
v)
The appointment of independent third party competent in such technical evaluation shall only be
appointed upon the mutual agreement between the Government and the Manufacturer.
vi)
The findings of the third party shall be conclusive and mutually accepted by the Government
and the Manufacturer.
vii)
If the findings of the independent third party are within the coverage of this performance
warranty, all cost shall be borne by the Manufacturer or otherwise such cost shall be borne by
the Contractor.
viii)
All claims for the defects must be received by the Manufacturer not later than fourteen (14) days
from the expiry of the warranty period.
MANUFACTURER
..
Company Stamp
..
..
Signature
Name:
Date:
WITNESS
..
Company Stamp
..
..
Signature
Name:
Date:
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
BLANK PAGE
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
H/30
TABLE OF CONTENTS
SECTION I: CEILING WORKS
PAGE
1.
2.
3.
4.
5.
6.
General
Submittals
Setting Out
Acoustic Requirements
Materials And Ceiling Components
Ceiling Suspension System
I/1
I/1
I/1
I/2
I/2
I/5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/1
1. General
1.1
Unless otherwise specified or shown on the Drawings, all ceilings shall be Mineral
Fiber Boards or as approved by the S.O. with class O fire rating and all ceiling
installation shall comply with the classification of fire spread as stipulated in the 8th
Schedule Uniform Building By-Law 1984.
1.2
All ceilings shall be provided with service access to the ceiling void for maintenance
of services above the ceiling space in accordance to the Drawings and approval of
the S.O.
1.3
All sprinkler heads (drops) shall have 12.5 mm diameter oversize ring, sleeve or
adaptor through the ceiling tile to allow for free movement of the sprinkler pipes. It
shall also comply with the local fire regulations and to the S.Os approval.
1.4
The Contractor shall not commence the ceiling installation works until the building is
effectively weather-tight and the work area of wet trades has been completed and
dried.
2. Submittals
2.1
Unless otherwise specified, the Contractor shall submit shop drawings and design
calculations for the complete proprietary ceiling system showing compliance to all
specifications including the method of installation of the ceiling board/panels,
hangers, fittings and all accessories duly certified by a P.E. registered with the
Board of Engineers Malaysia.
2.2
The Contractor shall also submit floor plans showing the proposed location of the
anchors prior to the casting of the floor slab for the approval of the S.O. The plans
shall be endorsed by the P.E.
2.3
3. Setting Out
3.1
The ceiling layout shall be planned prior to installation to determine the grid
configuration, direction et cetera to ensure that all fixings points are compatible with
the structural members or other services, or both.
3.2
3.3
The shop drawings used for the ceiling installation shall contain sufficient
information to allow the installer to set out the ceiling grid. The finished height of the
ceiling shall be shown clearly on the drawings.
3.4
3.5
The ceiling height in each area shall be marked in relation to the elevation
benchmarks and then transferred by means of a water level, rotating laser or other
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/2
approved devices. Setting out lines should be in both directions and squared
accurately at the outset.
4. Acoustic Requirements
4.1
4.2
A full test report shall be submitted to the S.O as proof of compliance. It shall relate
to the entire specified system. Any variations shall be endorsed by the test
laboratory or field testing. Test reports, comments and the testing authority shall be
stated in the manufacturers trade literature or be made available upon request or
both.
5.2
5.3
5.4
Plasterboard
5.3.1
All plasterboards dimensions, its tolerances and flexural breaking load shall
comply with BS EN 520. The board shall carry class 'O' approval from
DGFR.
5.3.2
Unless otherwise specified in the Drawings the size for plasterboard ceiling
shall be 600 mm x 1200 mm x 9 mm thick minimum and shall be suspended
from the soffit with adjustable hanger rods in accordance to manufacturers
recommendation and S.Os approval.
5.5
5.6
5.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/3
5.6.2
Surface coating of the board shall be applied with vinyl latex paint in white
colour at factory and the surface design of the board shall be to S.O.s
approval.
5.8
5.9
5.9.2
5.10
Cornice
5.10.1 Unless otherwise specified, cornice shall be provided of the same ceiling
material for all plaster ceiling materials.
5.10.2 Cornice shall be fixed to the walls and ceiling using proprietary adhesive or
as recommended by the manufacturer and approved by the S.O.
5.10.3 Large cornices shall be fixed using screws together with cornice adhesive
as recommended by the cornice manufacturer and to SOs approval.
5.10.4 Cornice should be carried and handled carefully to avoid cracking the core
or wrinkling the paper liner. Where possible, the contractor shall use full
lengths of cornice and mitre all joints.
5.10.5 The Contractor shall ensure accurate and level placement by marking
ceilings and walls with a line at the cornice edge.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/4
5.10.6 Cornice with shorter length shall be installed first followed by the longer
lengths by bowing out to spring mitres fit into place.
5.11
Reinforcing/Jointing Tape
The tape shall not be less than 50 mm wide perforated paper tape in accordance
with ASTM C475 from an approved manufacturer, and to the approval of the S.O.
5.12
Jointing Compound
Jointing compound shall be pre-mixed multi-purpose gypsum based air drying type
compound, in accordance with BS EN 13963 and to the approval of the S.O.
5.13
Sealants
Fire sealant for plasterboard with improved core adhesion at high temperature
(Type F) and wet area sealant for plasterboard with reduced water absorption (Type
H) shall be in accordance with BS 8212 and to the approval of the S.O. The
appropriate type of sealant shall be used for the required type of plasterboard.
Elastomeric sealants can be used at the perimeter of the dry lining or partitioning to
provide an airtight construction and to the approval of the S.O.
5.14
Control Joint
Unless otherwise specified, control joints shall be provided in a long continuous runs
of ceiling, spaced at not more than 9 m centers maximum and recommended by the
manufacturer and to the approval of the S.O.
5.15
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/5
General
The Contractor shall provide 12 mm diameter Grade 4.6 black hexagon bolt and nut
as specified in BS 4190: ISO Metric Black Hexagon Bolts, Screws and Nuts as
anchors. The anchors shall be installed in the concrete slab during the casting of the
floor at depth of not less than 75 mm measured from the soffit of the floor or as
otherwise specified in the drawing.
6.2
6.3
All timber materials used shall be treated and as specified under SECTION
H: Timber, Joinery & Ironmongery Works. Ceiling boards shall be fixed to
the frames with butt V joint using nails or screws as recommended by the
ceiling manufacturer and to S.Os approval.
6.2.2
6.3.2
6.3.1.2
6.3.1.3
Where black hexagon anchors cast in the soffit of the floor slab
are not provided, pre-drilled galvanized mild steel z-shaped
soffit cleat 25 mm x 50 mm x 25 mm with minimum base metal
thickness of 2 mm shall be provided. The mild steel soffit cleat
shall be fixed by drilling and inserting M6 x 30 mm zinc plated
proprietary alternative anchor to the structural soffit at a
distance 200 mm away from the wall and then spaced equal to
or not more than 1200 mm centre to centre (c/c) to form the grid
of the ceiling hanger.
6.3.1.4
6.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/6
6.4.2
6.4.1.2
6.4.1.3
Where black hexagon anchors cast in the soffit of the floor slab
are not provided, pre-drilled galvanized mild steel z-shaped
soffit cleat 25 mm x 50 mm x 25 mm with minimum base metal
thickness of 2 mm shall be provided. The mild steel soffit cleat
shall be fixed by drilling and inserting M6 x 30 mm zinc plated
proprietary alternative anchor to the structural soffit at a
distance 100 mm away from the wall and then spaced equal to
or not more than 1000 mm c/c to form the grid of the ceiling
hanger.
6.4.1.4
6.4.2.2
6.4.2.3
6.4.2.4
6.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/7
6.5.2
6.6
6.5.1.2
6.5.1.3
Where black hexagon anchors cast in the soffit of the floor slab
are not provided, pre-drilled galvanized mild steel z-shaped iron
soffit cleat 25 mm x 50 mm x 25 mm with minimum base metal
thickness of 2 mm shall be provided. The mild steel soffit cleat
shall be fixed by drilling and inserting M6 x 30 mm zinc plated
proprietary alternative anchor to the structural soffit at a
distance 200 mm away from the wall and then spaced equal to
or not more than 1000 mm c/c to form the grid of the ceiling
hanger.
6.5.1.4
6.5.2.2
6.5.2.3
6.5.2.4
Suspended ceiling systems are not designed for and shall not be regarded
as structural elements. Electrical wiring systems, including cable trays,
conduits, junction boxes, lighting fixtures, air-conditioning ducts, air diffusers
and other appurtenances shall not be placed directly on the ceiling and shall
be independently supported.
6.7
6.8
6.9
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/8
6.6.2
6.6.3
6.6.4
Where not specified, tolerances for the ceiling shall comply with BS EN
13964. The maximum deflection between two suspension points shall not
exceed L/500 where L is the suspension distance between the two points.
6.6.5
The top fixing of all suspension components shall be made to the primary
structural framing element, unless specifically designed otherwise. The
contractor shall ensure the fixings are of a corrosion-resistant material
suitable for the intended application, and fixings shall be compatible with the
material of the structure to which they are to be fitted.
Self-drilling screws are not allowed for structural steel, unless specifically
designed otherwise. These screws shall not be placed in tension unless
specifically designed for that purpose.
6.7.2
Penetrations made into the structural steel by drilling shall be duly approved
by the S.O.
6.7.3
Fixings to cold formed trusses shall be made of steel plate straps. Selfdrilling screws are not allowed unless specifically designed otherwise. For
the case of proprietary truss systems, the Contractor shall obtain written
approval from the S.P. and the S.O.
6.8.2
Fixings to timber joists shall be made into the side of the timber, with five
times the diameter of the fastener clear edge distances.
6.10
Concrete Fixing
6.10.1 No fasteners, either shot-fired or drilled into are allowed to be installed
directly to a flat roof slab. Separate structural framing element shall be
specifically designed, and approved by the S.O.
6.10.2 Fixing to aerated/lightweight concrete shall only be made in accordance
with the manufacturers recommendations.
6.11
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/9
Purlin Fixing
6.11.1 Fixings shall be made of steel plate straps. No connections requiring
drillings to the web/lip of the purlins are allowed, unless specifically
designed otherwise.
6.11.2 Where flange connections are necessary, they should be made as close as
possible to the web of the purlin, and design calculations shall be provided
to ensure the structural capacity of the purlin is not compromised.
6.11.3 Fixings shall be selected and installed in accordance
manufacturers specification and approved by the S.O.
with
the
6.12
All concrete expansion bolts shall be installed in accordance with the manufacturers
recommendations taking due care to maintain minimum edge distances, spacing
and embedment depth.
6.13
6.14
In areas where the suspended ceiling is adjacent to rooms or areas with twenty four
(24) hours air-conditioning and the concrete soffits are applied with PU foam, the
ceiling suspension hanger shall be secured to the concrete soffit using M6 x 30 mm
A4 stainless steel (DIN17440) anchor bolts as specified or shown on the Drawings.
6.15
6.16
6.17
Warranty
6.17.1 When a proprietary ceiling system is used, the Contractor shall submit to
the S.O. a warranty from the manufacturer with the following provisions :
(i)
(ii)
The products used are genuine and free from manufacturing defects;
The ceiling system is installed in accordance with the manufacturers
recommendation, guidance and specifications that will deliver the
specified level of performance;
(iii) The warranty certificate shall cover a period of ten (10) years from the
date of Certificate of Practical Completion against any defect or failure
due to the installation and workmanship by the manufacturers
registered panel installer.
@HAKCIPTA JKR MALAYSIA
BLANK PAGE
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
I/10
TABLE OF CONTENTS
SECTION J: STRUCTURAL STEEL AND METAL WORKS
PAGE
1.
2.
3.
4.
5.
6.
General
Hot Rolled Structural Steelworks
Prefabricated Cold Formed Steel Roof Trusses
Metal Frames For Doors And Windows
Collapsible Gates, Roller Shutters And Et Cetera
Sundries
J/1
J/1
J/1
J/3
J/5
J/5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
J/1
1. General
This section provides the generally applicable requirements for steel and metal for the
construction of structures, building components and related works. All materials shall
conform to the relevant Malaysian or British or European Standards.
2.2
2.3
Drawings
2.3.1
2.3.2
2.4
Records
2.4.1
The Contractor shall submit to the S.O., document and records which shall
include but not limited to:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
3.
Document register;
Drawings and design calculations and documentation registers;
Certificates for materials and consumables;
Calibration of equipment;
Weld procedures, concessions et cetera;
Inspection and test reports;
Delivery schedules and method statements;
Surveys and final inspection results;
Completion of erection and hand over certification.
3.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
J/2
System Provider
The System Provider (S.P) is a supplier of a proprietary roof truss system appointed
by the Contractor and approved by the S.O, which employs Quality Assurance
procedures in the design, detailing, connection, bracing, erection criteria and
manufacture of truss components for the structural roof truss system.
3.3
The S.P. shall appoint a Professional Engineer (P.E.) whose duties shall
include the following:
(i)
(ii)
(iii)
(iv)
(v)
3.4
Fabricator
All trusses shall only be assembled by licensed fabricators approved by the S.P. and
registered with CIDB. A copy of CIDB registration certificate shall be submitted to the
S.O. for verification.
3.5
Installer
All installation works shall be executed and supervised by qualified personnel with
valid certificate issued by CIDB. The S.O. shall verify the identification and
qualification of the installer prior to the installation.
3.6
Prior to any pre fabricated cold formed roof trusses works, the following
general limitation shall be applied:
Maximum unsupported truss span 13 m with permitted deviation of +
0.05 m.
(ii) Maximum truss spacing of 1.2 m with permitted deviation of +0.025 m.
(iii) The minimum basic wind speed shall be 35 m/s. However, the
minimum basic wind speed shall be increased to 41 m/s for lightweight
roof covering.
(iv) Minimum base steel thickness for main truss member shall be:
(i)
a)
b)
(v)
Minimum base steel thickness for other truss element shall be:
a)
b)
c)
3.7
The S.P. through the Contractor shall propose to the S.O. for his approval
a roof truss system which is safe, functional and conforming to design
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
J/3
3.8
3.7.2
3.7.3
Warranty
3.8.1
When a prefabricated cold formed steel roof truss system is used, the
Contractor shall submit to the S.O. a warranty from the S.P. with the
following provisions:
(i)
(ii)
The products used are genuine and free from manufacturing defects;
The prefabricated cold formed steel roof truss system is installed in
accordance with the S.P.s instructions, guidance and specifications
that will deliver the specified level of performance;
(iii) The warranty certificate shall cover a period of ten (10) years from the
date of Certificate of Practical Completion against any defect or failure
due to the installation and workmanship by the S.P.s registered panel
installer.
4.
Steel Frames
4.1.1
The Contractor shall supply, assemble and fix steel frames for doors and
windows as shown on the Drawings. The steel frames shall comply with
BS 6510, and shall be from an approved source and shop-primed with two
coats of red lead oxide or other approved rust resisting primer.
4.1.2
The steel frames shall be manufactured from sections rolled from good
commercial grade galvanized mild steel in single sections, mechanically
straightened with all corners pre-cut with a 45 degrees mitre joint giving a
snug and accurate fit, fully electrically welded, and carefully ground and
cleaned, or shall be mechanically jointed by an approved method.
4.1.3
4.1.4
4.2
4.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
J/4
Aluminium Frames
4.2.1
The Contractor shall supply, assemble and fix aluminium frames for doors
and windows as shown on the Drawings. Unless otherwise specified, all
aluminium frames for windows shall be fabricated from sections extruded
from aluminium alloy conforming to MS 832. All aluminium frames for glass
sliding doors shall be fabricated from sections extruded from aluminium
alloy and in compliance with MS 1017.
4.2.2
4.2.3
4.2.4
4.2.5
All fasteners such as bolts and screws shall be of stainless steel type A270 (minimum) in compliance with ISO 3506 or other suitable materials as
specified in the Drawings. Rivets shall be stainless steel or aluminium alloy
appropriate to the applications.
4.2.6
4.2.7
Where friction stays and hinges are fastened onto the framing section, the
portion that receives the fastener shall not be less than 2.5 mm thick.
The Contractor shall supply, assemble and fix frames for adjustable louvre
windows as shown on the Drawings in compliance with MS 1057.
4.3.2
4.3.3
The operating rods shall be 2.13 mm thick (14 SWG). The handle and lock
shall be 2.642 mm thick (12 SWG) steel.
4.3.4
4.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
J/5
Accessories
4.4.1
Accessories for each steel or aluminium frame for doors and windows shall
be supplied complete with:
(i)
Samples
Samples of steel or aluminium sections with complete accessories for the doors and
windows, together with complete set of shop drawings of all works shall be
submitted to the S.Os for approval prior to the commencement of any work.
4.6
5.
Installation
4.6.1
4.6.2
All joints on the window and door frames shall be sealed using
polyurethane (PU) type joint sealant.
4.6.3
Where buildings are located near to the coastal area, the bolts, nuts and
screws used shall be of stainless steel unless otherwise specified.
4.6.4
6.
Sundries
6.1
Unless otherwise specified in the Drawings, mild steel shall be used for balustrades
to staircases, verandahs, balconies, et cetera and shall be fixed as shown on the
Drawings.
6.2
All iron and steel for the sundries shall be of the quality approved by the S.O.
Screws and bolts shall have washers where appropriate. Hooks for carrying ceiling
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
J/6
fans shall be formed from 13 mm diameter mild steel rods bolted to timber ceiling
members or ragged into concrete.
6.3
Welded mesh, expanded metal, aluminium sheets et cetera shall be provided and
fixed as shown on the Drawings.
6.4
Mild steel grilles, drain cover gratings shall be provided and fixed as shown on the
Drawings. Unless otherwise stated, all steelwork shall be jointed by continuous
welding.
6.5
Ant caps shall be of 16 gauge galvanised iron sheets formed to shape as shown on
the Drawing. The caps shall be fixed between concrete stumps/brick piers or walls
and timber posts or plates as required. The caps shall project 60 mm and inclined at
450 from the surface.
TABLE OF CONTENTS
SECTION K: PLASTERING, PAVING AND TILING WORKS
PAGE
1.
2.
3.
4.
General
Plaster Work
Paving Work
Tiling Work
K/1
K/3
K/5
K/8
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/1
1. General
1.1
1.2
Cement
1.1.1
1.1.2
Plasticiser
The plasticizer shall be of approved manufacture and used strictly in accordance
with the manufacturers recommendation.
1.3
Plasterlime
The plasterlime shall be of approved manufacture and shall comply with BS 890 and
shall be applied strictly in accordance with the manufacturers recommendation.
1.4
Sand
The sand for external rendering, internal plastering and floor screeding shall comply
with MS 29 for fine aggregates. Sand for plastering using gypsum shall comply with
MS 701.
1.5
Water
Water for mixing shall be clear and free from harmful matter as specified in
SECTION D: CONCRETE WORKS.
1.6
1.7
Mixing
1.6.1
All mixing of mortar for plaster and screed shall be done by machine. Hand
mixing shall only be allowed for small quantities and with the approval of
the S.O. Hand mixing shall be done on a clean platform. The water content
of the mix shall be only the minimum required to give a workable mix.
1.6.2
Mortar for plaster and screed shall be used up within forty five (45) minutes
after mixing.
1.6.3
For gypsum plaster, mixes shall be used up within one (1) hour after
mixing.
1.6.4
Surface Preparation
1.7.1
1.7.2
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
1.7.3
1.8
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/2
Bay
Paving and screeding shall be laid in alternate bays. On hardened concrete bases,
each bay shall not exceed 15 m2. On the surface where the concrete is still green,
each bay shall not exceed 30 m2. Where bays are not square, the ratio of the length
between adjacent sides of each bay shall be approximately 1:1.5. The joints in
paving screed shall coincide as nearly as possible with joints in the base.
1.9
1.10
1.11
Making Good
1.10.1
Defective screeds shall be cut out and made good with fresh screed and
sufficient time shall be allowed for the screed to dry prior to the laying of
the floor finish.
1.10.2
Defective plastering and rendering shall be made good by cutting out the
defective part to a rectangular shape, and the edges shall be undercut to
form dovetail-key and finished flush with the surrounding work.
Samples
The Contractor shall supply the S.O. with samples of materials and/or sample of
finished work for approval. Approved samples shall be kept at site for reference.
1.12
Tools
Proper tools shall be used for all scribing, scoring, splicing, smoothing edges,
making angles et cetera of tiles, bricks and others so as to produce neat and fit
joints.
1.13
Types Of Finishes
The appropriate type of finishes to be used in the various locations of the works
shall be as shown on the Drawings or as tabulated in the schedule of finishes.
Unless otherwise shown on the Drawings or described in the B.Q., the finishes and
their dimensions shall be as specified hereinafter.
1.14
The cornices and moulded work shall be clean and accurately formed to
the section shown on the Drawings. All mitres, stops and enrichments and
moulding shall follow the details as shown on the Drawings, all to the
approval of the S.O.
1.14.2
All rounded and moulded angles shall be of the same material mix as the
adjacent finish. For narrow reveal, splays and returns under 30 mm wide,
Class D plaster to BS 1991 shall be used.
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/3
2. Plaster Work
2.1
2.2
2.3
Plain Plaster
2.1.1
Plain plaster shall consist of one (1) part masonry cement to six (6) parts
sand by volume. Where CEM 1 is used, plasticizer or plasterlime shall be
added to the mix in accordance with the manufacturers instruction.
2.1.2
2.1.3
2.1.4
All external walls, unless otherwise specified shall be finished with rough
surface cement plastering.
2.1.5
All internal walls, unless otherwise specified shall be finished with smooth
skimmed surface cement plastering.
Granolithic Plaster
2.2.1
Granolithic plaster shall consist of by volume, two (2) parts cement, one (1)
part sand, five (5) parts granite chipping passing 6mm mesh and retaining
upon 3 mm mesh, applied in two (2) coats to a total thickness of 10 mm to
a backing coat, finished smooth with wood float.
2.2.2
2.2.3
Shanghai plaster shall consist of two (2) parts approved coloured cement,
one (1) part sand and five (5) parts of selected lime-stone chipping passing
6 mm mesh and retaining upon 3 mm mesh by volume applied in two (2)
coats to a total thickness of 10 mm to the backing coat, finished smooth
with wood float.
2.2.4
Shanghai Plaster
2.3.1
Shanghai plaster shall consist of two (2) parts approved coloured cement,
one (1) part sand and five (5) parts of selected lime-stone chipping passing
6 mm mesh and retaining upon 3 mm mesh by volume applied in two (2)
coats to a total thickness of 10 mm to the backing coat, finished smooth
with wood float.
2.3.2
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
2.4
2.5
2.6
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/4
2.4.2
For rough cast finish, the mix shall consist of selected cement, sand and
aggregate in the proportion to give the required finish to the approval of the
S.O.
2.4.3
For Tyrolean finish, the mix shall consist of one (1) part selected coloured
cement, and two (2) parts sand by volume applied to the backing coat by
means of a Tyrolean machine in accordance with the manufacturers
recommendation. The finish shall be built up in three (3) layers to a total
thickness of not exceeding 6 mm. Each coat shall be allowed to dry before
the application of a subsequent coat.
2.4.4
For pebble-dash finish, the dry pebble for the finish shall be thrown onto
the backing coat while the latter is still wet. The pebbles to be used shall
be clean and of size and quality approved by the S.O.
2.4.5
For pebble-wash finish, the selection of pebbles shall be clean and of size,
colour and quality approved by the S.O. The selected pebbles shall be
mixed with plain plaster and applied while it is still wet in a single coat
generally to a total thickness of 12 mm to a backing coat. The applied
surface is tapped to set the pebbles in position. The pebbles shall be
brushed and washed lightly to achieve the required texture after it has
reached the initial set. Loose pebbles shall be placed back in position and
by tapping the surface to set.
Gypsum Plaster
2.5.1
2.5.2
The setting of unmodified plaster starts about ten (10) minutes after mixing
and is complete in about forty five (45) minutes; but not fully set for seventy
two (72) hours. The total gypsum plaster thickness for vertical and
horizontal masonry and concrete surfaces shall be 16 mm.
2.5.3
2.5.4
Gypsum plaster is renowned for its use as an art medium and is often use
in conservation works especially for decorative embellishment. It is also
used to simulate the appearance of surfaces of wood, stone or metal.
Lime Plaster
2.6.1
Typical lime plaster mix shall consist of one (1) part lime putty to three (3)
parts of washed, well graded sand. The lime putty is mixed at one (1) to
three (3) ratios, creates a compact plaster.
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
2.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/5
2.6.2
2.6.3
2.6.4
Barium Plaster
The plastering of internal surfaces of X-Ray room walls shall be of barium plaster
consisting of one (1) part cement, one (1) part barytes (barium sulphate) fines and
three (3) parts barytes sand by volume.
2.8
3. Paving Work
3.1
3.2
Cement Paving
3.1.1
3.1.2
Granolithic Paving
3.2.1
3.2.2
The chipping shall be washed and free from dust. The paving shall be
trowelled smooth to proper level or fall where appropriate. After initial set
the surface shall be brushed lightly to achieve the required textured finish.
3.2.3
3.2.4
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/6
3.4
In-situ Terrazzo
3.3.1
In-situ terrazzo shall consist of one (1) part approved coloured cement and
three (3) parts selected limestone chipping passing through 12 mm mesh
and retained upon 3 mm mesh by volume.
3.3.2
3.3.3
3.3.4
When sufficiently hard but not less than two (2) days after being laid it shall
be rubbed down to a smooth surface by means of carborundum stone.
3.3.5
3.3.6
3.5
3.6
3.5.2
3.5.3
The joints between the paving slabs shall be 20 mm wide filled with cement
mortar (1:3) and raked to a depth of 6 mm.
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/7
3.7
3.8
3.6.2
3.6.3
3.6.4
The grade of the concrete and thickness of the paving blocks shall be as
detailed in the Drawings.
3.6.5
3.6.6
The paving blocks are placed side by side on the sand bed with gaps of
approximately 2 mm between adjoining blocks. The gap between the
paving blocks shall be filled with fine sand of different grading to that
required for the bedding sand.
3.6.7
The paving blocks can be cut to fit edges and awkward corners. The
pavement which has been laid shall be compacted with a hand-guided
plate vibrator until it is firmly embedded in the sand layer.
3.6.8
3.7.2
The concrete shall be well compacted and floated with a wooden float to
smooth and even finish. After the concrete has achieved the initial set, the
surface shall be brushed with stiff broom or wire brush to give a rough
finish.
3.7.3
The joints between the panels shall be filled with approved cold-poured
polyurethane joint filler.
Brick Paving
3.8.1
3.8.2
The bricks shall be soaked as specified in SECTION E: NONSTRUCTURAL WALL SYSTEM before laying and shall be laid flat on 25
mm semi-dry cement and sand (1:3) screed with 6 mm spacing to the
pattern as shown on the Drawings or as approved by the S.O.
3.8.3
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/8
4. Tiling Work
4.1
Ceramic Tile
4.1.1
In general all ceramic tiles manufactured locally are using the `dry-pressed
manufacturing process and the ceramic tiles are categorized based on
their water absorption rate as defined in the MS 1294, MS ISO 13006 or
the International Standard Organization (ISO) Standards (ISO 13006).
4.1.2
The methods and materials used in the installation of ceramic tiles under
normal internal conditions shall comply with MS 1294-1 and the installation
of ceramic tiles under normal external conditions shall comply with MS
1294-2.
4.1.3
4.1.4
4.1.5
4.1.6
4.1.7
4.1.8
Unless otherwise shown on the Drawings, ceramic tiles for internal walls
shall be scuff-resistant glazed vitrified tiles with water absorption less than
6% [Classification Group BIb or BIIa] shall comply with MS ISO 13006.
Unless otherwise specified, the minimum tile size shall be of 300 mm x 300
mm.
4.1.9
Unless otherwise shown on the Drawings, ceramic tiles for external walls
up to first floor height shall be scuff-resistant glazed vitrified tiles with water
absorption less than 3% [Classification Group BIa or BIb] and shall comply
with MS ISO 13006. The tiles maximum size shall be of 300 mm x 300
mm.
4.1.10
Unless otherwise shown on the Drawings, ceramic tiles for external walls
used above first floor height shall be scuff-resistant glazed vitrified tiles
with water absorption less than 0.5% [Classification Group BIa] shall
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/9
comply with MS ISO 13006. The tiles maximum size shall be of 300 mm x
300 mm.
4.1.11
Unless otherwise specified in the Drawings, all ceramic tiles for walls and
floors shall be of 1st Grade or Grade A with approved surface finish &
texture, colour and manufacture.
4.1.12
Ceramic tiles used for walls which have high water absorption
characteristics shall be bedded with approved tile adhesive to the
manufacturers specification on 20 mm thick cement and sand (1:3) render
which has sufficiently cured. The tiles shall be laid with 2 mm to 3 mm gap
and all joints shall be filled with approved tile proprietary grout to match.
Exposed edges of tiling shall be finished with rounded on edge tiles.
Ceramic tiles of Classification Group BIII with water absorption >10% shall
not be used under any conditions.
4.1.13
Porous tiles shall be soaked before fixing to prevent rapid suction and
subsequent failure in bonding with the mortar bed. Tiles should be
removed from their cartons and completely immersed in clean water for at
least thirty (30) minutes. After soaking, they should be stacked tightly
together, with the end tiles face outwards, on a clean surface and allowed
to drain. Tiles classified in MS ISO 13006 in Groups BIIb and BIII require
this saturation treatment; soaking of tiles of Group BIa, BIb and BIIa is
unnecessary, refer to MS 1294-1.
4.1.14
4.1.15
4.1.16
Tiles shall be laid with joints not exceeding 3 mm wide to be filled with
coloured grout. Admixtures shall be used in accordance with the
manufacturers recommendation and they shall not be added to the
proprietary grout unless approved by the grout manufacturer. Admixtures
are added for improving the resilience and reducing the water permeability
of the hardened grout mortar.
4.1.17
4.1.18
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/10
4.2
4.1.19
4.1.20
Where large format ceramic tiles are required for walls and to be fixed
above first floor height, they shall be secured by mechanical means. When
the thickness of tile exceeds 12.5 mm and the weight of tile is more than
32 kg/m2, mechanical fixing is recommended. All mechanical fixing
methods shall be certified by a competent Professional Engineer and to the
approval of the S.O.
4.1.21
Pull-out test shall be carried out after twenty eight (28) days installation for
every maximum area 500 m2 or on the tiles that are suspected of
hollowness, at the instruction of the S.O.
4.1.22
Adhesion strength of the pull-out test shall exceed 0.5 N/mm2 for walls with
cement:sand mortar bedding or 1.0N/mm2 with adhesive bedding. Pull-out
test shall be carried out in accordance to MS ISO 13007-2 and as
recommended by the tile adhesive manufacturer. Location and number of
test point for the pull-out test shall be as requested by the S.O.
4.2.2
The tiles shall be soaked prior to laying and shall be laid butt jointed on 20
mm thick semi-dry cement and sand screed. The laying shall be done
while the screed is still green. All joints between the tiles shall be grouted
with coloured cement to match.
4.2.3
The tiles shall be rubbed down to a smooth surface after a minimum of two
days or laying by means of Carborundum stone. Tile impregnator shall
then be applied strictly in accordance with the manufacturers
recommendation on to the terrazzo surface to prevent future staining.
4.2.4
Unless otherwise stated in the Drawings, nosing and edging tiles to edges
of flooring and treads of concrete stairs shall be of an approved type and to
match with the flooring accessories such as skirting (bull nose or cove
base), step tiles, step nosing, edging strips, angle tiles (internal and
external), etc. shall be of an approved type from the same material to
match flooring.
4.2.5
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
4.3
4.4
4.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/11
Mosaic
4.3.1
4.3.2
4.3.3
4.3.4
4.3.5
4.3.6
During bedding, the surface of the mosaic shall be checked and any
unevenness shall be made good. Any misaligned or defective tiles shall be
adjusted or replaced. All joints shall be grouted with approved proprietary
grout or coloured cement and sand grout to match. The tiling shall be
allowed to mature under damp condition for at least four (4) days before
cleaning down.
4.3.7
The selection and application of tile adhesives for internal and external
mosaic installations on walls and floors shall comply with MS ISO 13007-1.
The selection and application of tile grouts for mosaic installations on walls
and floors shall comply with MS ISO 13007-3.
Quarry Tiles
4.4.1
4.4.2
All skirting shall be 100 mm high with rounded top edge to match the tiles
flooring. The tiles required to form angles to skirting shall be neatly cut and
fit to all abutments.
PVC Tiles/Sheets
4.5.1
PVC tiles or sheets shall be of approved type, pattern and colour. PVC tiles
or sheets are to be of non-slip type and shall comply with MS 602. Tiles
shall be 250 mm x 250 mm x 2 mm thick minimum. Sheets shall be 2 m roll
width x 2 mm thick minimum.
4.5.2
Accessories such as skirting, stair nosing, edging strips etc. shall be of the
same manufacture from similar material to match flooring. Unless
otherwise described skirting shall be 100 mm high; stair nosing shall be 60
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/12
mm wide laid full length of the treads and of bullnose profiles; and edging
strips shall be 25 mm wide.
4.5.3
4.5.4
Installation area for the flooring must be clean, fully enclosed, weathertight
and maintained at uniform temperature at least forty eight (48) hours prior
to, during and after the installation is completed.
4.5.5
The tiles or sheet shall be laid and jointed on 20 mm thick cement and
sand (1:3) screed subfloor with an approved proprietary waterproof
adhesive strictly in accordance with manufacturer's recommendation. The
screed shall be finished smooth with a steel trowel to an even surface and
shall be dry, clean and free from dust and sand before laying the tiles and
sheets. A self-leveling sub-floor smoothing compound shall be applied on
uneven surfaces to provide a quality finish to receive the floor coverings or
as recommended by the manufacturer.
4.5.6
4.5.7
4.5.8
4.5.9
In areas that are subjected to spillages of water onto the wall surfaces, the
top of the covering is finished with aluminium trimming, a specially
designed section for forming water-tight joint in conjuction with the surface
of the wall finishes. It is recommended that the aluminium trim to be
screwed on the wall surface.
4.5.10
4.5.11
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
4.6
4.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/13
4.6.2
4.6.3
4.6.4
The face edges of the flooring shall be lined with wrot timber edging to
match. The edging strips shall be 38 mm wide approximately x 12 mm
thick fixed to the base using adhesive as specified hereinbefore, projecting
12 mm from the finished sides of floor slabs. Edging strips shall be jointed
using glued splayed butt joints.
4.6.5
After sanding the flooring shall be cleaned, any gap sealed with approved
sealer, stained and finished with three (3) coats of approved polyurethane
paint. Each coat shall be applied strictly in accordance with the
manufacturer's recommendation.
Unless otherwise shown on the Drawings, parquet tiles shall be readymade 120 mm x 120 mm x 10 mm thick consisting of 120 mm x 25 mm x
10 mm pressure treated kempas, keruing or other approved
medium
hardwood timber battens. The timber species for use in parquet flooring
shall be as specified in SECTION H: TIMBER, JOINERY AND
IRONMONGERY WORKS.
4.7.2
4.7.3
SECTION K : PLASTERING,
PAVING AND TILING WORKS
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
K/14
below the surface and the holes filled with approved putty. Any jointing of
the skirting shall use splayed butt joints.
4.8
4.9
4.7.4
The face edges of the flooring shall be lined with wrot timber edging to
match. The edging strips shall be 38 mm wide approximately x 12 mm
thick fixed to the base using adhesive as specified hereinbefore, projecting
12 mm from the finished sides of floor slabs. Any edging strips shall be
jointed using glued splayed butt joints.
4.7.5
After sanding the flooring shall be cleaned, any gap sealed with approved
sealer, stained and finished with three (3) coats of approved polyurethane
paint and sanding between coats. Each coat shall be applied strictly in
accordance with the manufacturer's recommendation. The required type of
flooring finish shall be to S.O.s approval.
Granite Slabs
4.8.1
Unless otherwise shown on the Drawings, granite slabs for flooring shall be
600 mm x 600 mm x 25 mm thick shall be bedded with cement: sand
mortar or alternatively with 9 mm thick approved proprietary tile adhesive
onto 25 mm thick cement and sand (1:3) screed as described
hereinbefore. The slabs shall be laid butt-joint. Any gap shall be filled with
approved mixture of adhesive and grout powder. After grouting, the surface
then shall be polished, buffered and finished with a layer of impregnator.
4.8.2
4.8.3
The reverse side of granite slabs in contact with the ground floor or
exposed wet wall surface shall be applied with approved waterproof
coating.
Marble Slab
4.9.1
Unless otherwise shown on the Drawings, marble slabs for flooring shall be
600 mm x 600 mm x 25 mm thick shall be bedded with cement: sand
mortar or alternatively with 9 mm thick approved tile adhesive onto 25 mm
thick cement and sand (1:3) screed. The slabs shall be laid butt-joint. Any
gap shall be filled with approved mixture of the adhesive and grout powder.
After grouting, the surface then shall be polished, buffered and finished
with a layer of impregnator.
4.9.2
4.9.3
The reverse side of marble slabs in contact with the ground floor or
exposed wet wall surface areas shall be applied with approved waterproof
coating.
TABLE OF CONTENTS
SECTION L : WATER RETICULATION, INTERNAL PLUMBING SYSTEM
AND SANITARY FITTINGS
PAGE
1.
2.
3.
4.
5.
6.
General
Products And Materials
Inspection
Water Reticulation
L/1
L/1
L/1
L/1
TABLE L1
L/2
L/10
L/10
L/12
JKR MALAYSIA
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/1
1. General
The water reticulation and internal cold water plumbing works shall be executed by
personnel with valid permits issued by SPAN as stipulated under Water Service Industry
Act 2006. The Contractor shall be responsible for employing such personnel and all the
work performed by them.
All products and materials to be incorporated in the work shall be new and unused.
Materials to be used within the scope of work shall be those approved by SPAN.
When the quality of a material or process is not specifically set forth in the approved
products and materials list, the Drawings, or the Specifications, the best available
quality of the material or process shall be provided, subject to the approval of the
S.O.
2.2
All products and materials shall be supplied by suppliers registered with SPAN. The
Contractor shall provide proof to the S.O. in the form of a valid Confirmation Letter
or Certificate of Registration issued by SPAN to the supplier. The products and
materials shall also be subjected to other terms and conditions mentioned in these
specifications.
2.3
All products and materials shall be of the makes and models tested and approved
for use. It is the Contractor's responsibility to verify that products and materials
received for the job conform to the current approved products and materials
supplied by SPAN registered suppliers.
2.4
All products and materials furnished shall be subject to inspection for compliance
with these specifications and all other appropriate specifications. The Contractor
shall make application to the S.O. for inspection at least five (5) days in advance of
starting any work.
3. Inspection
The S.O. shall at all times have access to the work wherever it is in preparation or progress
and the Contractor shall provide proper facilities for such access and for inspection. The
Contractor shall provide safe means to inspect the work. Failure or oversight of the S.O. or
his representative to reject defective materials at the time of use, or to reject improper work
at the time it is performed, shall not diminish the Contractor's obligations to comply with
Drawings and Specifications. The Contractor shall remove and replace any faulty materials
and work at no additional cost to the Government upon discovery of the defects or upon
receipt of notice from the S.O. to do so.
4. Water Reticulation
4.1
Setting Out
All setting out for pipe laying works shall be performed by the Contractor's surveyor.
Generally, stakes for alignment and grade shall be set at 10 m intervals. The survey
shall conform to the lines, grades, and dimensions shown on the Drawings. The
Contractor shall preserve all monuments, benchmarks, survey markers and stakes.
In case of their removal or destruction by the Contractor or his employees, agents or
subcontractors, the Contractor shall be liable for the cost of their replacement.
JKR MALAYSIA
4.2
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/2
Excavation
4.2.1
General
All general excavation works shall be as specified in SECTION C:
EXCAVATION AND EARTHWORKS.
4.2.2
(ii)
4.2.2.3
Width of Trench
D+300mm
D+600mm
4.2.2.4
4.2.2.5
4.2.2.6
JKR MALAYSIA
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/3
4.2.3.2
4.2.3.3
4.2.3.4
4.2.3.5
4.2.3.6
4.2.3.7
4.2.3.8
JKR MALAYSIA
4.2.4
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/4
4.2.5
Pipe bedding
The pipe bedding and foundation shall be prepared according to the
Drawings. No pipes shall be laid until the S.O. has inspected and approved
the pipe bedding and foundation. Any work that has been carried out
without the approval of the S.O. shall, on the instructions of the S.O., be
uncovered or removed by the Contractor and reinstated to the S.O.s
approval at the Contractor's own expense
4.2.6
4.2.7
After the pipe laying has been approved by the S.O. and before
the pipelines are tested, sufficient backfilling of the trenches will
be permitted to prevent "snaking" and to maintain the pipes in
position, but all joints shall be left exposed. In any other locality
where the trench may be filled with water and cause flotation of
the pipes, or elsewhere as may be decided by the S.O .the
backfilling shall follow the pipe alignment as closely as possible.
4.2.7.2
JKR MALAYSIA
4.2.8
4.2.9
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/5
4.2.7.3
4.2.7.4
4.2.7.5
4.2.8.2
Road reinstatement
4.2.9.1
4.2.9.2
4.2.9.3
JKR MALAYSIA
4.3
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/6
4.2.9.4
4.2.9.5
4.2.9.6
Pipeworks
4.3.1
4.3.2
Testing of pipelines
4.3.2.1
The Contractor shall provide all water required for filling, testing
and retesting the pipelines, and any pumps, pipework fittings
and pressure gauges required for the purpose.
4.3.2.2
4.3.2.3
JKR MALAYSIA
4.3.3
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/7
4.3.2.4
4.3.2.5
After the section of the pipeline has been filled with water for a
period of not less than seven (7) days, more water shall be
pumped into the section to raise the pressure slowly in
increments of 10 m head of water with pause of one minute
between each increment.
4.3.2.6
4.3.2.7
4.3.2.8
4.3.2.9
4.3.2.10
JKR MALAYSIA
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/8
purpose shall be obtained from the Local Water Authority and the
Contractor shall pay all the charges incurred in connection therewith.
4.3.4
4.3.5
4.3.4.2
Precast chambers
Precast valve chambers shall be as shown on the Drawings and in
accordance with SECTION D: CONCRETE WORKS. Chamber covers
shall comply with BS EN 124.
4.3.6
4.3.7
4.3.8
Hot tapping
4.3.8.1
4.3.8.2
JKR MALAYSIA
4.3.9
4.4
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/9
4.3.8.3
4.3.8.4
Pipe jacking
4.3.9.1
4.3.9.2
4.4.2
The type of tanks that may be supplied and installed shall be only from the
following type:
No
Product Name
(Glass Fused/Glass
Coated/Epoxy
Lining/HDPE) Lining
Polyethylene Storage
Tanks
(PE Storage Tanks)
4.4.3
The tank shown on the Drawings and specified herein shall be fabricated,
supplied and installed by a manufacturer with a valid registration with
SPAN.
JKR MALAYSIA
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/10
4.4.4
4.4.5
4.4.6
Contract
Drawings
and
The installation of the abovementioned system shall comply with JKR 20500-001010 Standard Technical Specification for Internal Cold Water and Sanitary Plumbing
System or the latest edition published by JKR.
5.2
All water supply plumbing and installation shall be executed in accordance with the
relevant state water supply rules and to the approval of the state water authority /
SPAN, notwithstanding any approval given by the S.O.
5.3
(ii)
Part 1
Part 2
Part 5
6. Sanitary Fittings
6.1
Fittings
6.1.1
6.1.2
Unless otherwise shown on the Drawings, the colour of sanitary ware shall
be in white.
JKR MALAYSIA
6.2
6.3
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/11
Vanity Tops
6.2.1
6.2.2
Wash Basin
6.4.1
6.4.2
JKR MALAYSIA
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/12
APPENDIX L/1
Item
Wash Basin
Description
(i)
(ii) Clinical wash hand basins shall be wall hung vitreous type and not less
than 600 mm in width complete with a wall mounted 175 mm long elbow
action lever mixer with premix function. Clinical wash hand basins shall not
have any overflow outlet, soap recess nor basin plug.
Vanity tops
(i)
(ii) Vanity top as specified, but with holes pre-punched to receive an undercounter vanity basin and tap respectively, as shown in the Drawings,
complete with 555 mm x 415 mm under-counter vanity basin in vitreous
china, complete with chromium-plated tap, 30mm p trap with 40mm seal,
waste fittings with chrome-plated brass pop up waste and painted bracket
supports.
Sinks
(i)
915 mm x 460 mm, single bowl single drainer stainless steel sinks shall be
to BS 1244, stainless steel grade 304 (0.8 to 0.9 mm) minimum thick, with
satin finish to the size and configuration shown on the drawings with
overflow and sound deadening pads under the sink and drainers.
(ii) Metal sinks in stainless steel to size and shape as shown in the Drawings,
complete with chromium plated tap as required, 40 mm waste water outlet,
chrome-plated brass pop up waste and painted mild steel frames support.
Water closet
(i)
Urinal
(i)
(ii) Urinal range of 2 or more bowls as (a) but with white vitreous china division
between bowls.
Cistern for
Water Closet
(i) Single flush 6 litres or dual-flush 6/3 liters low level vitreous china.
(ii) Cistern conforming to MS 795 with 40 mm flush pipe, water inlet valve, 20
mm diameter overflow for discharge externally and chrome flushing lever
handle.
JKR MALAYSIA
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/13
(iii) 6 litres high level vitreous china cistern conforming to MS 795 with 40 mm
flush pipe, water inlet valve, 20mm diameter overflow for discharge
externally and chromed lever handle.
(iv) Each flush cistern for w/c shall be tested as stipulated in the requirements
of MS 795.
Cistern for
urinal
Single flush 2.5 litres urinal flushing cistern in white vitreous china conforming to
MS 795 complete with chromium plated flushing inlet pipe, 20 mm diameter
overflow for discharge externally and chrome lever handle.
Flush valve
for Water
Closet
(i)
Unless specified, W/C flush valve shall be low pressure single flush 6 litres
gravity flush water closet valve. It shall have a non-hold-open feature or an
automatic shut-off system.
(ii) Vacuum Breaker is optional, only applicable to w/c flush valves intended to
be connected to direct potable water mains. Its performance requires
proper match of valve and w/c pan conforming to MS 1522.
(iii) Each flush valve shall be made of metal (preferably copper alloy) and
corrosion resistant. All exposed surfaces to the users shall be chromed
plated or made of stainless steel.
Flush valve
for urinal
(i)
Urinal flush valve shall be Single flush 2.5 litres gravity flush valve. urinal It
shall have a non-hold-open feature or an automatic shut-off system.
(ii) Each urinal flush valve shall be made of metal (preferably copper alloy) and
corrosion resistant. All exposed surfaces to the users shall be chromed
plated or made of stainless steel.
10
Shower
fittings
Shower fittings shall be approved chromium plated brass easy clean valve, with
3 diameter shower face and Chromium plated stainless steel grade 304 arm.
11
All types of
taps
12
Hand Bidet
Bidet shall be chromium plated copper alloy nozzle, 1.2 m heavy duty double
interlock stainless steel grade 304 flexible hose, chromium plated ABS plastic
wall hanger and quarter turn angle valve.
13
Sanitary
appliances
(i)
Floor trap, Robe Hook, Towel Rail, Safety Grab Bar and Handicap
Safety Grab Bar shall be in stainless steel grade 304 chrome plated.
Soap Dispenser shall be in uPVC (LEAD FREE).
Soap holder and toilet roll holder shall be in white earthenware
(ceramic).
JKR MALAYSIA
SECTION L : WATER
RETICULATION, INTERNAL
PLUMBING SYSTEM AND
SANITARY FITTINGS
BLANK PAGE
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
L/14
TABLE OF CONTENTS
SECTION M : RAINWATER COLLECTION
PAGE
1. Rainwater Goods
2. Rainwater Harvesting System
3. Testing and Commissioning
M/1
M/4
M/5
SECTION M : RAINWATER
COLLECTION
JKR MALAYSIA
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
M/1
1. Rainwater Goods
1.1
1.2
Flashing
1.1.1
1.1.2
All steel sheets used for flashing shall be 0.8 mm thick minimum. Flashing
shall have a minimum depth of 200 mm with the upper edge turned into the
wall and pointed in cement or approved sealant. Where nails or screws are
used for fixing, they shall be of the heavily galvanized type.
1.1.3
All fasteners to be concealed where possible. Install work with laps, joints
and seams that will be permanently watertight and weatherproof. All laps
shall be at a minimum of 200 mm. The flashing work shall be performed by
skilled workmen.
1.1.4
All fasteners used near marine environment shall comply with AS 3566
Class 4 and be certified as such by the supplier of fasteners and to the
approval of the S.O.
1.1.5
Gutters
1.2.1
General
1.2.1.1
1.2.1.2
1.2.1.3
1.2.1.4
SECTION M : RAINWATER
COLLECTION
JKR MALAYSIA
1.2.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
M/2
Aluminium gutters
1.2.2.1
1.2.3
1.2.4
1.2.3.2
1.2.4.2
1.2.4.3
1.2.4.4
SECTION M : RAINWATER
COLLECTION
JKR MALAYSIA
1.2.5
1.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
M/3
1.2.5.2
1.2.5.3
Rainwater Downpipes
1.3.1
1.3.2
General
1.3.1.1
1.3.1.2
1.3.2.2
1.3.2.3
1.3.2.4
SECTION M : RAINWATER
COLLECTION
JKR MALAYSIA
1.3.2.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
M/4
2.2.
2.3.
2.4.
General
2.1.1.
2.1.2.
Harvested rainwater shall be strictly used for non-potable uses only. Non
potable may include landscape irrigation, exterior washing and flushing of
toilets.
2.1.3.
Pre Filtration
2.2.1.
2.2.2.
All pre filtration devices may include the first-flush diversion systems, filters
and screens designed to remove debris and dust from the captured
rainwater before storage tank and should be of low maintenance.
2.3.2.
A filter unit system consists of a chamber and shall be filled with filtering
media such as carbon fibre, coarse sand and gravel layers to remove
debris and dirt from rainwater before it enters the storage tank. The
selection and type of filtering media shall be to the S.O.s approval.
Storage Tank
2.4.1.
2.5.
Water Backup
2.5.1.
The water backup system from the main water supply shall be provided to
supply water when rainwater is not available in the rainwater tank
2.5.2.
Any service pipe conveying potable to top-up a rain water tank containing
non-potable water shall have a backflow preventer of the dual check valve
type; and the service pipe shall terminate at least 255 mm above the
overflow level of the rainwater tank.
SECTION M : RAINWATER
COLLECTION
JKR MALAYSIA
2.6.
2.7.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
M/5
Piping Works
2.6.1.
The Contractor shall provide pipe works as shown on the Drawings and as
described under SECTION L: WATER RETICULATION, INTERNAL
PLUMBING SYSTEM AND SANITARY FITTINGS.
2.6.2.
2.6.3.
Taps and outlets for non-potable water shall be clearly identified as Not
For Drinking Purposes.
2.7.2.
The Contractor shall supply and install electrical motors, starters and
electrical switchboard for the pumping system as described in VOLUME 2:
ELECTRICAL WORKS.
3.2.
The Contractor shall carry out testing and commissioning to the S.O.s approval as
described in SECTION L: WATER RETICULATION, INTERNAL PLUMBING
SYSTEM AND SANITARY FITTINGS.
SECTION M : RAINWATER
COLLECTION
JKR MALAYSIA
BLANK PAGE
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
M/6
TABLE OF CONTENTS
SECTION N: GLAZING WORKS
PAGE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
General
Sealants
Glazing
Glazing Work To Timber Frames
Glazing Work To Metal Frames
Glazing Works To Louvred Window
Glazing To UPVC Frame
Frameless Glazing
Glazing Works To Patented Windows, Doors, Panels And Sky Lights.
Fixing Of Glass Blocks
Cleaning Upon Completion
N/1
N/1
N/1
N/1
N/2
N/2
N/2
N/2
N/3
N/3
N/3
APPENDIX N/1 :
N/4
Schedule Of Glass
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
N/1
1. General
1.1.
Generally, all glass shall conform to MS 1135 and shall be free from bubbles,
specks and other defects. Samples shall be submitted for the approval of the S.O.
1.2.
Unless otherwise specified or shown on the Drawings, the type and minimum
thickness of glass shall be as stated in the Schedule of Glass in APPENDIX N/1.
2. Sealants
2.1.
2.2.
2.3.
2.4.
Joint sealant for non-structural use in building shall be and approved type and shall
comply with BS EN 15651-2.
2.5.
Joint sealant for structural use in building shall be an approved type and shall
comply with BS EN 13022.
3. Glazing
3.1.
All doors and windows, et cetera except louver windows shall be glazed as shown
on the Drawings or the Schedule of Doors and Windows.
3.2.
All glass shall be cut to size with 2 mm clearance all around the rebates. All
exposed edges glass panes shall be rounded off.
3.3.
All glazing works shall be carried out strictly in accordance with the manufacturers
instruction.
3.4.
Figured or textured glass surface for windows shall be installed facing the interior.
The grooves and rebates to be glazed shall first be cleaned, primed with wood
primer, painted with one coat of oil paint and allowed to dry, followed by the
application of a thin bed of putty or synthetic sealant.
4.2.
The glass panes shall then be properly placed and secured in the grooves or
rebates with timber beadings as detailed in the Drawings.
4.3.
Where the glass panes is to be secured with putty or synthetic sealants, the glass
shall be placed and held in the grooves or rebates with approved sprigs driven at
intervals of not exceeding 300 mm centres. The glass shall then be finally secured
with back-putty or sealants finished true to profile or as detailed in the Drawings.
4.4.
Installation of timber frames for doors and windows shall refer to SECTION H:
TIMBER, JOINERY AND IRONMONGERY WORKS.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
N/2
The grooves and rebates to be glazed shall first be cleaned of rust and primed with
an approved metal primer and allowed to dry, followed by the application of a thin
bed of glazing putty or sealant. The glass panes shall then be placed and secured in
the grooves and rebates with metal, aluminium beadings or neoprene rubber in
accordance with the manufacturers instructions or as detailed in the Drawings.
5.2.
Where the glass panes is to be secured with putty, the panes shall be placed and
held in the grooves or rebates with spring clips sets in holes in the frame. The glass
shall then be finally secured with back-putty or synthetic sealants finished true to
profile or as detailed in the Drawings.
5.3.
Installation of metal frames for doors and windows shall refer to SECTION J:
STRUCTURAL STEEL AND METAL WORKS.
The glass blades for fixed louvred window shall be properly housed in the grooves
of the timber frames and secured in position with timber beadings as shown on the
Drawings.
6.2.
In the case of adjustable louvred windows, the louvred frames shall be fixed on to
the vertical members of the window frame and secured with 20 mm long dome
headed galvanized screws fixed at 200 mm centres. The louvre blades shall then be
inserted and secured in the flanged clips, all in accordance with the manufacturers
instructions.
6.3.
Generally, all glazing work to uPVC frame shall conform to BS EN 12608. All
glazing works shall be carried out strictly in accordance with the manufacturers
instructions.
7.2.
Unless otherwise specified in the Drawings, the frame shall be fitted at least 10 mm
inwards from the outside edge of the face of the brickwork. It is essential that the
windows are installed true and square by measuring the windows diagonals after
the installation.
7.3.
The gap between the window frame sill and brickwork shall be sealed with silicone
sealant as approved by the S.O.
8. Frameless Glazing
8.1.
Where shown, approved frameless glazing must conform to BS 5234, BS 6180 and
BS 6399.
8.2.
Unless otherwise shown on the Drawings, the jointing method for frameless glazing
shall be strictly in accordance to the manufacturers instructions.
8.3.
The Contractor shall submit method statement for the fixing and installation of the
frameless glazing system for the S.O.s approval.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
N/3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
N/4
APPENDIX N/1
SCHEDULE OF GLASS
No.
Type of Glass
Minimum
Glass
Thickness
(mm)
1.
2.
3.
Clear Figured
(obscured) Glass
Grey/Tinted Figured
Glass
Toughened/Tempered
Glass
4.
5.
6.
Laminated Glass
6
7.
8.
Wired Glass
i. Clear & Polished
ii. Figured and
Translucent
Lead Glass
Laminated crystal
clear glass with
minimum 2 mm
thick lead sheeting
sandwiched in
between.
Application
External use windows and doors
Interior framed glass screens, partitions
Display windows, showcases, display
shelves
Furniture: Table-tops
External use on windows and doors
Interior framed glass screens, partitions
Display windows, showcases, display
shelves
Furniture: Table-tops
Windows
Furniture, display bases, house fittings,
partitions etc.
Decoration eg. Front doors, display etc.
Windows
Furniture, display bases, house fittings,
partitions etc.
Decoration eg. Front doors, display etc.
Furniture, interior decorations, table tops,
showcases, partitions etc.
Skylights, glass roofs and the like
Animal observatory windows & aquariums
High security places eg. Burglar resistant
showcases and the like.
Places where safety necessary eg.
Verandah side panels and the like.
Places where safety and security are
important.
X-Ray rooms
9 mm
total thickness
TABLE OF CONTENTS
SECTION O: PAINTING WORKS
PAGE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
General
Painting To Timberwork
Painting To Metalwork
Painting To Masonry Work
Treatment To Fair Face Surfaces
Epoxy Coatings
Silicone Paint
Painting On Floor Surfaces
Painting To Timber-based Products
Painting To Gypsum Board and The Like
Painting To Laboratory Bench Tops
Varnishing
Painting Works For Buildings In Coastal Areas.
Painting Works To Clinical Areas (Hygienic Areas)
Completion Of Painting Works
O/1
O/2
O/2
O/3
O/4
O/4
O/4
O/4
O/5
O/5
O/6
O/6
O/6
O/7
O/7
O/8
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
O/1
1. General
1.1
1.2
Prior to commencing painting work, the Contractor shall submit the following to the
S.O.:
(i)
Name of the paint manufacturer and the manufacturers certification that the
paint conform to the relevant standard as specified in sub-section 1.1 hereof
together with the proof that such certification have been verified by tests
carried out by SIRIM or ISO in the last three (3) years.
(ii) The performance warranty by the manufacturer to the Government on the
performance of the paint against any peeling, cracking, fungus/ algae growth
and discoloration which may arise during a period of five (5) years or more
from the date of practical completion due to insufficiency in material or
workmanship. The terms of the performance warranty shall be as stipulated in
APPENDIX O/1 and as approved by the S.O.
(iii) Name of the painting applicator as approved by the paint manufacturer
including written evidence of the current approval.
(iv) A copy of the method statement including procedure for the painting works in
accordance with these specification and manufacturers instructions.
1.3
All paints shall be delivered to the Site in the manufacturer's original sealed
containers unopened and shall be used strictly in accordance with the
manufacturer's instructions.
1.4
Paints shall not be adulterated and any paint that has deteriorated shall not be used
and shall be removed from the Site forthwith.
1.5
Unless otherwise specified in the Drawings, the types of paints to be sued for the
work on exposed surfaces shall be as stated in the `Schedule of Paint Finish
attached hereinafter.
1.6
The colours and tints of paints shall be selected by the S.O. and the priming,
undercoats and finishing coats shall be of approved differing tints and shall be
obtained from the same manufacturer.
1.7
No painting shall be done under conditions which may jeopardize the quality of
finish paintwork.
1.8
During painting, care shall be taken to prevent stain or damage to other works.
1.9
Surfaces to be painted shall be dry, free from dirt, oil, grease, old loose paint and
other deleterious matter. All cracks shall be raked out and stopped and all holes and
dents shall be filled.
1.10
1.11
1.12
All prime surfaces shall be inspected and approved by the S.O. before
commencement of painting works.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
O/2
1.13
Finish surfaces shall be uniform in finish and colour and be free from brush marks or
other defects.
1.14
Sample areas showing all tints of paints to be used shall be prepared by the
Contractor as and when required by the S.O.
2. Painting To Timberwork
2.1
2.2
2.1.2
Before painting to new timberwork, all knots shall be covered with knotting
and all nail holes, cracks, et cetera shall be stopped with white lead and
putty (1:3) and shall be primed with aluminium wood primer well brushed in.
2.1.3
Unless otherwise specified, the prepared surface shall be painted with one
undercoat (alkyd undercoat) and shall be finished with two coats of premium
semi-gloss fungus resisting alkyd paint or three (3) coats UV protection, low
odour alkyd wood finish.
2.1.4
2.1.5
2.1.6
3. Painting To Metalwork
3.1
3.2
3.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
O/3
3.2.2
If the old paint is in a bad, deteriorated condition the whole paint shall be
removed by the use of approved paint remover or by scraping as approved
by the S.O. The surface shall be thoroughly cleaned and shall be applied
with one coat approved metallic primer, by one (1) coat of premium alkyd
undercoat unless specified, and shall be finished with two (2) finishing coats
of gloss/semi-gloss fungus resisting alkyd or gloss enamel paint.
3.4
3.4.2
When the surface is completely clean, it shall be applied with one coat
approved metallic primer, unless otherwise specified, shall be finished with
two finishing coats of gloss/semi-gloss fungus resisting alkyd paint or gloss
enamel paint.
4.1.2
The cleaned surfaces of the external walls shall be applied with one coat of
approved alkaline resisting primer and unless otherwise specified in the
Drawings, followed with two (2) coats of ultra-violet (UV) weather resistant
emulsion paint.
4.1.3
The external wall surfaces shall be applied with one (1) coat of approved
alkaline resisting primer, unless otherwise stated in the Drawings, followed
with two (2) coats of 100% acrylic with heat reflective and UV protected, and
temperature reduction weather resistant emulsion paint for Green Ratings
Certification as approved by the S.O.
4.1.4
4.2
4.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
O/4
The internal wall surfaces shall be applied with one (1) coat of approved
modified acrylic sealer, and unless otherwise as shown on the Drawings,
followed with two (2) coats of low VOC acrylic paint.
4.2.2
The surface shall then be applied with two (2) coats of any other type of
water based emulsion paint as described hereinbefore for Painting New
Plastered/Masonry Surfaces and as approved by the S.O.
Textured Wall
4.3.1
Natural Spray Granite textured wall shall be applied with one (1) coat of
approved alkaline resisting acrylic primer, unless otherwise stated in the
Drawings, followed with two (2) layers natural fine stone and ceramic chips
texture with high build acrylic resin and two (2) clear finish coats.
4.3.2
Spray Tile textured wall shall be applied with one (1) coat of approved
alkaline resisting acrylic primer, unless otherwise specified in the Drawings,
followed with one (1) coat of spray tiles texture and two (2) coats of pure
acrylic water based premium weather paint.
6. Epoxy Coatings
Epoxy coatings shall be applied with one (1) coat of approved transparent epoxy sealer,
followed with two (2) coats epoxy topcoat.
7. Silicone Paint
Silicone paint for external walls and ceiling shall be applied with one (1) coat of Pigmented
Water Base Penetration Water Repellent and two (2) finishing coats of Breathable Silicone
Paint of approved colour applied strictly in accordance with manufacturers instruction.
Painting on concrete drive way shall be applied with one (1) coat of floor primer at
100 m DFT, followed by one (1) coat of floor glass flake at 300 m DFT or floor
non-slip aggregate (fine/medium) and followed with two (2) coats of floor
polyurethane (PU) topcoat at 50 m DFT per coat.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
O/5
8.2
Painting on car park parking bay floors shall be applied with one (1) coat of floor
primer at 100 m DFT, than followed with two (2) coats of floor polyurethane (PU)
topcoat at 50 m DFT per coat.
8.3
Painting on TNB sub-station internal floors shall be applied with one (1) coat of
approved two-pack epoxy sealer, followed with two (2) coats of two pack epoxy floor
coating at 50 m DFT per coat, unless otherwise stated in the drawings
9.
9.1
Chipboard Surfaces
9.2
9.1.1
Before painting, all nail holes, crevices and the like shall be stopped with
white lead and putty (1:3). The surface shall then be smoothened by
rubbing down with fine sand paper and finally cleaned to remove dust.
Where the board is to be finished with enamel paint, one (1) undercoat and
two (2) finishing coats of gloss enamel paint shall be applied. If the board is
to be finished with emulsion paint, one (1) undercoat and two (2) coats of
emulsion paint shall be applied.
9.1.2
9.1.3
Where cracking and flaking has occurred, the entire existing paint shall be
removed by burning off, as approved by the S.O. The surfaces shall then
thoroughly cleaned and shall be applied with one (1) undercoat and finished
with two (2) coats of gloss enamel paint.
9.1.4
Hardboard Surfaces
Before painting to hardboard, all nail holes, crevices and the like shall be filled with
approved putty. The surface shall then be applied with one (1) undercoat and two
(2) coats of emulsion paint unless otherwise specified.
9.3
Before painting the surfaces shall be clean and free from dirt. The surfaces shall
then be applied with one (1) undercoat and two (2) coats of emulsion paint. Similar
procedure shall be followed where repainting to existing painted surfaces is
required.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
O/6
11.2
12. Varnishing
12.1
12.2
External walls shall be applied with one (1) coat of approved pliolite based alkaline
resisting primer sealer, unless otherwise specified in the Drawings, followed with
two (2) coats of elastomeric weather resistant paint of approved colour applied
strictly in accordance to manufacturers instruction.
13.2
Unless otherwise specified in the Drawings, the internal walls shall be applied with
one (1) coat of approved water based alkaline resisting acrylic wall sealer, followed
with two (2) coats of low volatile organic compounds (VOCs), alkylphenolethoxylate
(APEO) free, formaldehyde free acrylic premium emulsion paint of approved colour
applied strictly in accordance to manufacturers instruction.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
O/7
13.3
Mild steel shall be applied with one (1) coat of zinc rich epoxy, one (1) coat of
surface tolerance epoxy mastic and followed with two (2) coats of polyurethane
topcoat.
13.4
Galvanized steel shall be applied with one (1) coat of surface tolerance epoxy
mastic and followed with two (2) coats of polyurethane topcoat.
13.5
13.6
Coatings of fasteners used shall comply with AS 3566 Class 4 and be certified as
such by the supplier of fasteners and as approved by the S.O.
All external walls shall be applied with one (1) coat of approved siloxane primer
sealer, unless otherwise stated in the Drawings, followed with two (2) coats of
silicone emulsion water repellent paint applied strictly in accordance to
manufacturers instruction.
14.2
Internal walls shall be applied with one (1) coat of approved ultra-low VOCs alkaline
resisting primer sealer, followed with two (2) coats of anti-bacteria, anti-fungus, low
VOCs, 100% APEO free, formaldehyde free acrylic premium emulsion paint.
On completion of paintwork, all paint marks inadvertently left on glass, floors, tiles
and other surfaces shall be removed. Any stain or marking on finished paintwork
shall be removed and touched up to the approval of the S.O.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
O/8
APPENDIX O/1
2.
Peeling
This condition is manifested when the paint film peels away or detaches from the substrate.
(ii)
Cracking
This condition is manifested by any visible cracking on the paint film other than that caused by
plastering cracks and structural defects.
(iii)
Fungus/Algae Growth
This condition is established when there is a growth of micro-organisms on the surface of the
paint films which would result in the marring of the appearance of the paint film through
discoloration.
(iv)
Discoloration
This condition occurs when the coating loses its original colour in patches and excessive
discoloration appears.
Any defect claims shall be made in writing and delivered by post or by hand to the
Manufacturer.
(ii) A technical team from the Manufacturer will be dispatched to evaluate the nature of the claim.
Should our findings conclude the defects as within the scope of warranty, then the Manufacturer
shall make good such defects.
(iii) Should the Manufacturers technical team conclude that the defects falls outside the scope of
the warranty, the Manufacturer shall not be held responsible for the claim.
(iv) Should the Government disagree with the conclusion of the technical team pertaining to the
defects in particular, then an independent third party competent in such technical evaluation
shall be appointed to investigate the disputed defects.
(v) The appointment of independent third party competent in such technical evaluation shall only be
appointed upon the mutual agreement between the Government and the Manufacturer.
(vi) The findings of the third party shall be conclusive and mutually accepted by the Government
and the Manufacturer.
(vii) If the findings of the independent third party are within the coverage of this performance
warranty, all cost shall be borne by the Manufacturer or otherwise such cost shall be borne by
the Contractor.
(viii) All claims for the defects must be received by the Manufacturer not later than fourteen (14) days
from the expiry of the warranty period.
MANUFACTURER
..
Company Stamp
..
..
Signature
Name:
Date:
WITNESS
..
Company Stamp
..
..
Signature
Name:
Date:
TABLE OF CONTENTS
SECTION P: ROADS AND HARDSTANDING
PAGE
1.
2.
3.
4.
5.
6.
7.
General
Flexible Pavement
P/1
P/1
TABLE P1
TABLE P2
TABLE P3
TABLE P4
P/2
P/3
P/4
P/6
:
:
:
:
P/8
TABLE P5
P/8
Shoulders
Concrete Pavement
Road Furniture
Street Lighting
P/8
P/10
P/10
P/10
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/1
1. General
The construction of roads and hardstanding shall generally be carried out only after
completion of all drainage systems, services and ducts which may affect the Works, unless
otherwise agreed by the S.O.
2. Flexible Pavement
2.1
Subgrade
2.1.1
2.1.2
Material for the top 300 mm of subgrade shall have a minimum soaked
laboratory California Bearing Ratio (CBR) as shown on the Drawing when
compacted to 95% of the maximum dry density determined in the BS 1377
Compaction Test (4.5 kg Rammer Method). In the event CBR value not
mentioned on the Drawing, a minimum CBR value of 5% shall be adopted.
2.1.3
2.1.4
In cut area, the top 300 mm of the subgrade shall be scarified and
recompacted to 95% of the maximum dry density determined in the BS
1377 Compaction Test (4.5 kg Rammer Method). If the S.O. is fully
satisfied that the subgrade in its natural state possesses a density
exceeding the requirements, then the surface of the subgrade shall be
trimmed and rolled to obtain a smooth finish.
2.1.5
Where the material in cut area is found to be unsuitable for use in the top
300mm of subgrade or to a suitable level to be determined by the S.O., it
shall be removed and replaced with suitable material which shall be
compacted as indicated above. Alternatively, stabilizing agent may be used
subjected to the S.O. approval.
2.1.6
The subgrade shall be finished in a neat and workmanlike manner, and the
widths of embankments and cuts shall be everywhere at least of those
specified or shown in the Drawings on both sides of the centre line. The
top surface of the subgrade shall have the required shape, superelevation,
levels and grades and shall be finished everywhere to within + 10 mm and
- 30 mm of the required level.
2.1.7
(ii)
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/2
2.2
Drainage Layer
2.2.1
2.2.2
Coarse aggregate shall be screened crushed hard rock and fine aggregate
shall be screened quarry dust or sand. The aggregate shall be well graded
and lie within the limits as shown in TABLE P1.
TABLE P1: GRADATION LIMITS FOR DRAINAGE LAYER
2.3
2.2.3
2.2.4
2.2.5
The drainage layer shall be placed and compacted to the required width
and thickness as shown on the Drawings, in one single layer.
2.2.6
The material shall be spread and lightly compacted with tracked spreading
plant or other approved equipment with consideration given to the
protection of the subgrade.
Sub-base
2.3.1
2.3.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/3
(i)
The CBR of the sub-base shall not be less than 30% or as shown on
the Drawings when compacted to 95% of the maximum dry density
determined in the B.S. 1377 Compaction Test (4.5 kg rammer
method) and soaked for 4 days under a surcharge of 4.5 kg. This
shall involve carrying out a series of CBR tests at various dry
densities, using the field moisture content. The field density must
then be measured at a number of points using the sand replacement
method and the CBR deduced from the mean of the field density
measurements.
(ii) If more than 10% of the material is retained on the BS 20.0 mm sieve,
the whole material can be assumed without test to have a CBR value
of 30% or more.
(iii) The plasticity index when tested in accordance with BS 1377 shall be
not more than 12.
(iv) The 10% fines value when tested in accordance with MS 30 shall be
not less than 30 kN.
(v) The sand equivalent of aggregate fraction passing the No. 4 (4.75
mm) sieve when tested in accordance with ASTM D 2419 shall be not
less than 45%.
TABLE P2 : GRADATION LIMITS FOR SUB-BASE
BS Sieve Size (mm)
Percentage Passing by Weight
75.0
100
37.5
85 - 100
20.0
65 - 100
10.0
45 - 100
5.0
25 - 85
0.600
8 - 45
0.075
0 - 10
The particle size shall be determined by the washing and sieving method of BS 1377.
2.3.3
2.3.4
2.3.5
Sub-base material shall be placed over the full width of the formation to the
required thickness as shown on the Drawings or directed by the S.O. in
one layer or more, each layer not exceeding 200 mm compacted
thickness. Where two or more layers are required, they shall be of
approximately equal thickness and none shall be less than 100 mm
compacted thickness.
2.3.6
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/4
2.4
2.3.7
All loose, segregated or other defective areas shall be removed to the full
thickness of the layer, and new sub-base material laid and compacted.
2.3.8
2.4.2
(v)
(vi)
(vii)
The particle size shall be determined by the washing and sieving method of BS 1377.
@HAKCIPTA JKR MALAYSIA
2.5
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/5
2.4.3
2.4.4
2.4.5
2.4.6
2.4.7
2.4.8
2.4.9
2.4.10
2.4.11
2.4.12
The surface shall be to the required level and grade and comply with the
tolerances as specified in sub-section 3.2.
Wet-Mix Roadbase
2.5.1
2.5.2
2.5.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/6
50.0
37.5
20.0
10.0
5.0
2.36
0.060
0.075
100
95 - 100
60 - 80
40 - 60
25 - 40
15 - 30
8 - 22
0-8
The particle size shall be determined by the washing and sieving method of BS 1377.
2.5.4
2.5.5
2.5.6
2.5.7
2.5.8
2.5.9
2.6
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/7
2.5.10
2.5.11
2.5.12
The surface shall be to the required level and grade and comply with the
tolerances specified in sub-section 3.2.
2.6.2
2.6.3
2.6.1.2
2.6.2.2
Asphaltic concrete
2.6.3.1
2.6.3.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/8
Horizontal Alignment
The horizontal alignment shall be determined from the centerline of the pavement
surface shown on the Drawings. The edges of the pavement as constructed and all
other parallel construction lines shall be correct within a tolerance of + 50 mm and 0 mm from the centre-line, except for kerbs, channel blocks and edge lines which
shall be laid with a smooth alignment within a tolerance of + 25 mm and - 0 mm
from the centre-line.
3.2
The design levels of pavement courses shall be calculated from the vertical
profile, crossfall and pavement course thicknesses shown on the
Drawings. The level of any point on the constructed surface of a pavement
course shall be the design level subject to the appropriate tolerances given
in TABLE P5.
Tolerance
+ 5 mm
+ 5 mm
+ 0 mm to - 20 mm
+ 10 mm to - 20 mm
4. Shoulders
4.1
This work shall consist of furnishing, compacting and shaping earth, gravel or paved
shoulder material on a prepared and accepted sub-base or subgrade, all in
accordance with this Specification and the lines, levels, grades, dimensions and
cross-sections as shown on the Drawings and/or as required by the S.O.
4.2
Materials
4.2.1
Paved shoulders
The bituminous surfacing and underlying pavement courses shall be
constructed as described in the appropriate sections of this Specification.
4.2.2
Gravel shoulders
Gravel shoulder material shall conform to the requirements for gravel
surfacing material set forth in JKR Specification No. JKR/SPJ/2008-S4,
sub-section 4.1.3 or the latest edition published by JKR.
4.2.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/9
Earth shoulders
Earth shoulder material shall be suitable material as described in JKR
Specification No. JKR/SPJ/2013-S2, sub-section 2.2 or the latest edition
published by JKR.
4.2.4
Construction
4.2.4.1
4.2.4.2
4.2.4.3
4.2.4.4
4.2.4.5
4.2.4.6
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
P/10
5. Concrete Pavement
Concrete Pavement works shall be in accordance with JKR Specification No.
JKR/SPJ/1988, section 5: Portland Cement Concrete Pavement or the latest edition
published by JKR.
6. Road Furniture
6.1
6.2
Traffic Signs
The supply and method of installation of traffic signs shall be in accordance with
JKR Specification No. JKR/SPJ/1988, section 6, sub-section 6.2 or the latest edition
published by JKR.
6.3
Road Markings
The supply and application of road markings shall be in accordance with JKR
Specification No. JKR/SPJ/2012-S6, section 6, sub-section 6.3 or the latest edition
published by JKR.
6.4
Concrete Kerb
The supply and installation of concrete kerb shall be in accordance with JKR
Specification No. JKR/SPJ/1988, section 6, sub-section 6.4 or the latest edition
published by JKR.
7. Street Lighting
The supply and installation of street lighting shall be in accordance with JKR Specification
No. JKR/SPJ/2011-S7: Road Lighting or the latest edition published by JKR.
TABLE OF CONTENTS
SECTION Q: FENCING AND GATES
PAGE
1.
2.
3.
4.
5.
6.
General
Mild Steel Post And Bracings
Chain Link Mesh, Straining
Fencing
Gates
Painting Of Fence And Gates
Q/1
Q/1
Q/1
Q/1
Q/2
Q/2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
Q/1
1. General
1.1
Unless otherwise as shown on the Drawings, fencing shall be of chain link type as
specified hereunder.
1.2
Unless otherwise as shown on the Drawings, the height of the fence shall be 1500
mm from the ground up to the full height of the chain link.
1.3
The fence shall be erected to the extent and location as shown on the site plan.
Where fencing is to be located on the boundary of the Site, the Contractor shall
ensure that its construction shall not infringe the adjoining properties.
Unless otherwise as shown on the Drawings, mild steel angle posts and bracings
shall be of size 57 mm x 57 mm x 6 mm. All steel members for fencing and gates
shall be free from rust, scales and other defects and shall be to the approval of the
S.O. Previously used steel members shall not be used in the construction of new
fencing and gates. Before delivery to the Site, the steel members for fencing and
gates shall be pre-cut and assembled at the Contractor's workshop and painted with
one coat of approved metallic primer.
2.2
Where three strands of barbed wires are required, a mild steel angle arm 430 mm
long, of the same cross sectional dimension as the post shall be welded at the top of
the post at 450 inclination. Where six strands of barbed wires are required, two
pieces of mild steel angle arms as specified hereinbefore shall be welded to the top
of each post forming the shape Y with each arm having three strands of barbed
wires. The welding used shall be of continuous fillet welds. Necessary holes shall be
made in the posts, arms and bracings for insertions of fixing bolts and clips.
4. Fencing
4.1
Unless otherwise as shown on the Drawings, the mild steel angle posts shall be
erected at 3000 mm centres commencing from the gate post and the posts shall be
embedded plumb in 1:3:6-25 mm concrete footings of size 250 mm x 250 mm x 600
mm deep. Mild steel angle bracings of the same cross sectional dimensions as the
post shall be fixed at all corners, bends, junctions, gate posts and at every five bays
of straight fencing.
4.2
The bracings shall be fixed at an inclination of 450 to the horizontal with top end
bolted to the post, 300 mm below the top of the post and the bottom end encased in
concrete footing as described hereinbefore.
4.3
The chain link mesh shall be stretched across the posts and secured in place using
approved fencing clips. The end of chain link fencing abutting mild steel gate posts
shall be fixed by means of 19 mm x 3 mm mild steel flat straps drawn through the
mesh and bolted using 10 mm diameter mild steel bolts to 25 mm x 25 mm x 6 mm
mild steel plates welded to the posts at equal intervals of 300 mm. Where gate posts
are non-metal, the termination of the fencing at the gate shall be by means of
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
Q/2
another mild steel angle post fixed to one side of the gate post and strengthened by
bracing as described hereinbefore. The chain link mesh shall then be strained by
three strands of 4.06 mm (8 gauges) diameter galvanized steel straining wires
threaded through the mesh and fixed to the posts.
4.4
Where shown on the Drawings, the bottom of the chain link mesh shall be buried in
continuous 1:3:6-25 mm concrete curbs. Unless otherwise detailed in the Drawings,
the cross-sectional dimension of curbs shall be 125 mm wide x 375 mm high with
150 mm protruding above the ground. The portion of the curb above the ground
shall be rendered with 13 mm thick 1:6 cement render to a wood float finish.
5. Gates
The gates shall be constructed as shown on the Drawings.
TABLE OF CONTENTS
SECTION R: LANDSCAPING AND TURFING WORKS
PAGE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
General
Classifications And Characteristics Of Plants
Size Of Plants
Handling And Planting
Soil Mixture, Soil Conditioners And Chemical Fertilizers
Turfing
Football And Playing Fields
Relocation And Protection Of Existing Tress
Maintenance Of Plant And Turf
Final Handing Over
R/1
R/1
R/1
R/3
R/4
R/4
R/5
R/8
R/8
R/10
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
R/1
1. General
1.1
All landscaping works shall be as shown on the Drawings. Turfing works and tree
planting shall be carried out in such a manner as to minimize risks of damage to
turfs and plants, and stunted growth. Turfing on all slopes shall be carried out
immediately after slopes are formed. Tree planting shall be carried out as soon as
practicable.
1.2
All landscaping works shall start as early as possible so that trees and plants are
well- grown, and fully adapted to the new environment when the project concerned
is handed over upon completion.
1.3
All landscaping works shall be furnished, installed and maintained by the Contractor
as specified herein, or as shown on the Drawings, using the best horticultural
management, giving special attention to planting practices, soil mixtures, and
application of agricultural chemicals.
1.4
Existing water elements such as lakes, ponds and streams shall be incorporated
into the landscape design. Unless otherwise specified, mature existing trees shall
be retained and incorporated into the landscape design. Replantation and relocation
of the trees removed shall be considered as part of the landscaping works.
2.2
Plants shall mean trees, palms, shrubs, ground covers, and plants of others
descriptions to be provided by the Contractor, as shown on the Drawings or listed in
the plant schedules.
2.1.1
Each tree shall possess characteristics of its variety and growth typical to
such tree. All trees shall be well-branched, with straight trunks
characteristic of the species, with well-shaped top and intact leader. The
height shall be measured from the stems earth line to the top of the tree.
2.1.2
Palms shall have vigorous root system, crown of new leaves, proper color
of leaves of adult palms, and sufficient hardlines. The height of palms shall
be measured from the stems earth line to the base of the first frond.
2.1.3
Shrubs and vines shall possess characteristics and growth habits typical of
their species. All shrubs shall be well-shaped and bushy, with well-spaced
branches, and not skinny. The height of shrubs or vines shall be measured
from the stems earth line to the top branches.
2.1.4
All plants shall be in healthy growth condition, free from pests and diseases, and
shall be representatives of their normal species or variety. All plants shall have wellbranched heads and vigorous root systems, and shall be injury-free. Unless
otherwise shown or specified in the Drawings, only nursery-grown plants shall be
used. Plants which are potted or plastic-bag-grown shall not be root-bound.
3. Size Of Plants
3.1
The size of plants refers to plant table size that is the size that is required for
planting out on sites. All plants shall have the following sizes:
3.1.1
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
R/2
Ground covers
Ground cover plants can be supplied in plastic bags. If supplied in 150 mm
- size bags they shall have at least nine (9) cuttings per bag, and not less
than 150 mm long.
3.1.2
Shrubs
Height of shrubs shall range between 150 mm and 1000 mm.
3.1.3
Trees
3.1.3.1
Tree saplings
Tree saplings shall mean grown from seedlings or
cuttings. They shall have straight main stems of not less
than 1200 mm in height from the soil level to the lowest
branch, and a stem diameter of not less than 12 mm, and
a well-branching system.
ii)
iii)
Instant trees
An instant tree is generally referred, to the semi-mature
tree with a minimum trunk height of 2000 mm for palms
(measured from earth line to first frond) and 3000 mm for
other which shall have well-spread branches.
3.1.4
Palms
3.1.4.1
Single-stem palm
These refer to palms with single main trunk. Their trunk
height shall be not less than 1200 mm measured from the
earth line to the base of the first front.
ii)
Cluster palms
The Palms referred to are those which grow in clusters.
They shall have a minimum of three (3) palms clustered
together, measuring 750 mm to 1000 mm from the earth
line to the base of the first frond.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
R/3
Handling
Plants shall be transported, handled and stored in such a manner as to prevent
deterioration, damage or contamination. All plant materials shall be carefully
protected and, if necessary, wrapped with hessian or gunny cloth during lifting,
transportation, unloading and storage on site.
4.2
Planting
4.2.1
4.2.2
Pits/holes
4.2.1.1
Generally all pits for palms and trees shall not be less than
1000 mm x 1000 mm or 1/3 size bigger than the root ball,
spaced at intervals as shown on the Drawings or approved by
the S.O.
4.2.1.2
4.2.1.3
4.2.1.4
4.2.1.5
4.2.1.6
4.2.1.7
For ground covers, planting works shall be carried out in zigzag manner at distance between 100 mm to 150 mm unless
otherwise specified.
Transplanting
4.2.2.1 Transplanting shall not be carried out in very hot, dry weather
conditions which may result in initial drying out of the root system
and/or scorching of leaves.
4.2.2.2 Immediately before transplanting, the plants shall be carefully
removed from the nursery bags or pots. The plants shall be
placed into the pits and the surround filled with approved black
earth making sure that the roots are not excessively disturbed.
The earth around the base of the stems shall be recessed
slightly to facilitate watering.
4.2.3
Plants supports
All newly plants shall be supported either by staking, tying or guying.
Stakes shall be of wood, still or plastic of an approved type, driven into the
ground before planting so as not to damage the root ball or aerial parts of
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
R/4
plants. Stakes shall be long enough to the plants, with one (1) tie per stake
set 150 mm from the bottom.
Soil Mixture
Soil mixture for ground planting and backfill shall be in the ratio of 1:3, i.e. 1 part to
soil conditioner or organic materials to three (3) parts of top soil. Planter box soil
mixture shall be in the ratio of 1:2:3, i.e. one (1) part of sand of sand to two (2) parts
soil conditioner or organic materials to three (3) parts top soil.
5.2
Top Soil
Top soil shall consist of fertile and friable topsoil obtained from a well-drained floodfree site excavated from not more than 300 mm deep from ground level. It shall be
of medium texture and without admixture of stones, lumps, plants or roots, and other
extraneous matter. Topsoil material shall be obtained from excavated topsoil
sourced or, if not available, from other sources as approved by the S.O.
5.3
5.4
Chemicals Fertilizers
Chemicals fertilizers shall be granular slow release compound fertilizers with a
minimum four (4) months release period at 320 C. They shall be stored in waterproof
sealed bags and kept under shelter. The Contractor shall submit manufacturers
technical data on the proposed fertilizer for the S.O.s approval prior to the
application of the fertilizer.
6. Turfing
6.1
Unless otherwise shown in the Drawings, turfing shall be provided to all exposed
earth surfaces throughout the site. All surfaces to be turfed shall be completely
cleared of all incidental Contractors debris, stone and other obstructions.
6.2
The ground to be turfed shall be graded to fall toward surface water discharge line
as shown in the Drawings, or approved by the S.O.
6.3
6.4
6.5
All turfs shall be of good, healthy, dense indigenous cow grass (Axon Opus
Compresses) from an approved source. The grass shall be of even density,
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
R/5
vigorous growth and green in color, forming a turf sufficiently fibrous to hold together
when installed. They shall be free from mimosa, weeds or other foreign vegetation.
6.6
Each turf shall be approximately 300 mm x 300 mm x 50 mm thick with roots still
attached to the soil. They shall be kept moist and in shade, and shall be planted
within 24 hours of lifting. Samples of turfs to be used shall be submitted to the S.O.
for approval before any turfs are brought in for use. The sources of material shall be
stated by the Contractor.
6.7
Unless otherwise shown in the Drawings, close turfing shall be provided to slopes,
and extending 2 m of the platform at the top and bottom of the slope, 1 m the sides
of all drains, and 2 m wide of road shoulders, so that they cover the whole area
without any space/gap between them.
6.8
Each sod shall be pegged in place with wooden/bamboo pegs 12 mm diameter and
200 mm long through the sod and into the soil base. These pegs shall be removed
after the turf have firmly established. On steep slopes, netting in shall be laid onto
the turfed areas for protection.
6.9
Unless otherwise shown in the Drawings, spot turfing shall be carried out on all level
ground. The turf shall be laid at 450 mm center, embedded 25 mm in the top soil.
6.10
Turf shall be fertilized with approved slow release fertilizers high in Nitrogen content,
one (1) month after planting at the rate of 60 gm/m2 and evenly spread over the
whole area. Turfs shall be well watered after each fertilizer application which shall
be done once in every three months after grass cutting.
6.11
Grass cutting shall be done every three weeks after one (1) month
growth/establishment by grass cutter/mover as often as in required to give a well
trimmed sod not more than 25 mm in height for flat surface and not less than 50 mm
on slope. All clippings shall be removed from the site before watering is carried out.
7.2
General
7.1.1
Unless otherwise specified hereinafter, turfing for football and playing fields
shall be as specified hereinbefore. Turfing works shall start as soon as
possible and shall be completed and fully established not later than three
(3) months before the date of completion of the works.
7.1.2
Materials
7.2.1
7.2.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
R/6
Filter materials
Filter Materials shall consist of an angular, clean, hard and durable crush
rock with uniformly sized particle of 14 mm, free form lumps of clay or
organic matter.
7.2.3
7.3
Site Preparation
The site area shall be completely cleared of all debris, large stones, discarded
gravel and other unacceptable materials. The site shall then be graded to form a
crown at the centre of the field with a minimum gradient of 1:300. The soil shall be of
good texture and structure with the majority of the crumbs of size 1 mm to 2 mm and
not contaminated with seeds, stolon or rhizomes of noxious weeds.
7.4
7.5
7.6
Backfilling
The trench shall be backfilled with the filter material in layers not exceeding 150 mm
loose thickness and uniformly compacted by suitable method approved by the S.O.
to the level as shown in the Drawings. Care shall be taken that the pipe is not
damaged or displaced.
7.7
Outlets
Outlets shall be constructed as shown in the Drawings and to the S.O.s approval.
7.8
The prepared surface of the field shall be laid with a first layer of 100 mm
thick river sand or other suitable course grained granular materials and a
second layer of 100 mm thick turf mixture before receiving the turf.
7.8.2
The Contactor surface shall carry out final gradient check prior to the
turfing works.
7.8.3
7.8.4
7.9
JKR 20800-0183-14
01
00
29 Januari 2014
R/7
The Contractor shall give not less than twenty-four (24) hour notice prior to
the commencement and upon completion of the under mentioned works.
The Contractor shall not proceed with the next succeeding operation until
specific approval has been given for the following:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
7.11
:
:
:
:
:
Inspections
7.9.1
7.10
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
Trench excavation.
Trench lining with geo textile fabric and laying of subsoil drain pipe
Filter material backfill
Sand laying
Turf mixture
Turfing work
Leveling Of Field
7.10.1
The Contractors shall water the turf at least twice a day or as instructed by
the S.O. The rate of application and frequency of watering shall be
sufficient to maintain the turf mixture in a moist condition to ensure proper
and healthy growth of the turf even during the dry weather.
7.10.2
Water shall be applied as fine spray by means of suitable pumps and hose
or sprinkler or any other method approved by the S.O so as not to disturb
the turf mixture.
Weed Control
Weeding shall be carried out on the newly turfed area about ten (10) days after
planting to get rid of foreign species and maintain a pure culture of Axonopus
Compressus (Cow Grass). Weeding on a Continuous basis shall be carried out to
prevent weeds from growing.
7.12
Fertilization
The first fertilization shall be carried out two (2) weeks after planting, using
mechanical spreader. Subsequently, the fertilizer shall be applied at three (3) weeks
interval.
7.13
7.14
Mowing
7.13.1
7.13.2
The first cut shall be carried out when the turf reaches 50 mm 70 mm in
height. The turf shall be cut to 25 mm 30 mm in height. Subsequently,
mowing shall be done at least once in every two (2) weeks.
Top Dressing
The Contractor shall, from time to time or whenever directed by the S.O. check the
flatness of the field and if found uneven, rectify by top dressing with turf mixture and
followed by proper compaction.
7.15
7.15.2
7.16
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
R/8
8.2
Relocation Of Trees
8.1.1
Where shown in the Drawings or if directed by the S.O, all existing trees
having girth of 300 mm and below identified and marked for relocation,
shall not be cut, but shall be dug up, prepared for, and relocated by the
Contractor to other areas within, or in the vicinity of the site. In the event of
any such trees being accidentally cut or damaged, the same shall be
replaced with trees of equivalent size and species by the Contractor.
8.1.2
The Contractor shall protect and maintain the relocated trees by fencing to
a height of 1.2 m, watering, manuring, pruning, and other necessary
treatments throughout the contract period (including the Defects Liability
Period) until satisfactory, growth is established. Any relocated trees which
are accidentally damage, or fail to re-grow satisfactorily within the Defect
Liability Period, Shall be replaced accordingly at the Contractor own cost.
All existing trees having girth of 800 mm and above identified and marked
by the S.O. or as shown in the Drawings to be retained on site, shall be
protected and maintained by fencing to a height of 1.2 m, watering
manuring, pruning and other necessary treatments throughout the contract
(including the Defects Liability Period) so as not to jeopardize their growth.
8.2.2
General
9.1.1
After planting and prior to the onset of the maintenance period, the
Contractor shall be responsible for carrying out all necessary measures to
ensure that all plant materials and turfing thrive and become established,
and that the landscaped areas are kept in a clean and tidy condition.
9.1.2
The Contractor shall protect and maintain the plants and turfing from any
damage and destruction, by way of watering, manuring and tilling, any by
staking and fencing, where necessary, to support and protect the plants,
until the end of the Defects Liability Period. All plants and turfs which are
defective and/ or fail to grow within the Defect Liability Period or as
instructed by the S.O. shall be replaced immediately and/ or replanted
accordingly, at the Contractors own cost.
9.1.3
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
R/9
(iii)
(iv)
(v)
(vi)
(vii)
9.2
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
9.1.4
The Contractor shall provide persons who are competent and experienced
for organizing and running the maintenance programs during the Defects
Liability Period, at the Contractors own cost.
9.1.5
The Contractor shall be responsible for the use of all materials, labour and
equipment. Any injury to plants caused by such materials, labour and
equipment shall be corrected and repaired at the Contractors own cost.
9.1.6
The Contractor shall carry out all necessary measures to ensure that all
plants thrive and become established within this period. All landscaped
areas shall be inspected at monthly intervals and lists of remedial works
shall be issued upon each inspection within seven (7) working days. All
items on the remedial work list shall be executed before the next
scheduled inspection.
9.3
9.3.2
Six (6) applications shall be required during the maintenance period. The
first shall be carried out during the second (2nd) month after planting. The
second and subsequent applications shall be worked into the soil above
the roots and lightly watered in. the fertilizer shall be applied, preferable,
when the plants are in their active stage of growth.
9.3.3
9.3.4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
R/10
The Contractor shall take note that plant feeding shall be carried out only
after all other maintenance works like weeding, hoeing and trimming or
pruning have been carried out.
Two weeks before the expiry of the Defects Liability Period a joint final inspection
shall be held with the S.O. to review the requirements for any alteration or
replacement in order to gain approval for Final Handing Over.
10.2
At the time of Final Inspection, all areas under this contract shall be free from
weeds, neatly cultivated and raked, and all plant boxes in good order. Grass shall
be neatly cut and all clippings removed. No bare patches of earth shall be visible in
turf or planting areas unless otherwise specified.
10.3
If any portions of the works are found to be not acceptable, under the terms and
intent of the Drawings and specifications, the Contractor shall carry out immediate
remedial works to S.Os acceptance before the date of Final Handing Over. The
cost of all remedial works shall be borne by the Contractor.
TABLE OF CONTENTS
SECTION S: DRAINAGE WORKS
PAGE
1. General
2. Excavation And Backfilling
3. Materials
TABLE S1 :
TABLE S2 :
Subsoil Drain
Sumps
Culverts
On-site Detention Pond
S/1
S/1
S/3
S/3
S/4
S/4
S/5
S/6
S/6
S/6
S/7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
S/1
1. General
1.1
All drainage works shall be in accordance with the JKR Standard Specification for
Drainage Works in Building Projects No. 20601-0195-13 or the latest edition
published by JKR and the requirements of the MSMA.
1.2
The works shall include the construction of surface drains, sumps, culverts, subsoil
drains, and other drainage structures in accordance with these Specifications or as
directed by the S.O.
1.3
Drainage works shall be constructed to the lines, levels, grades and cross-sections
shown on the Drawings or as directed by the S.O.
1.4
Final discharge point shall be identified and approved by the S.O. Where necessary,
the existing drainage system shall be upgraded in order to ensure they are fully
functional.
The Contractor shall notify the S.O. sufficiently in advance of the beginning of any
excavation so that cross-section elevations and measurements shall be taken of
undisturbed ground. The natural ground adjacent to the structure shall not be
disturbed without permission of the S.O. The excavation works shall be carried out
so as not to cause any danger or obstruction to the traffic or public.
2.2
All excavation shall be inspected and approved by the S.O. prior to further work
being carried out.
2.2.1
2.2.2
2.2.1.2
2.2.1.3
2.2.3
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
S/2
2.2.3.2
2.2.4
2.2.5
2.2.6
2.3
2.2.4.2
Trench method
2.2.5.1
The trench to receive culvert shall have sufficient width and depth
to enable the placing of bedding material. The bottom of the trench
shall be trimmed to suitably smooth plane surface which shall be
kept free from water, all to the satisfaction of the S.O.
2.2.5.2
2.2.6.2
Backfilling
2.3.1
2.3.2
Backfilling with approved fill materials shall be placed evenly in layers not
exceeding 150 mm. To provide uniform support, loose thickness of fill
materials on both sides of the drain shall be thoroughly compacted with
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
S/3
mechanical rammers. This procedure shall be followed for the whole depth of
drain section.
2.3.3
3. Materials
3.1
3.1.2
Concrete
Concrete for blinding, bedding and cast-in-situ drains shall be as shown in
the Drawings and as specified in SECTION D : CONCRETE WORKS.
3.1.3
3.1.4
3.1.3.2
Materials from swamps, peats or top soils and other highly organic
clay or silt, materials containing logs, stumps or boulders, which
are susceptible tocombustion, and any other materials which, by
virtue of their physical or chemical composition or at their moisture
content will not compact properly, shall not be used for filling.
% Passing By Weight
100
90 - 100
45 - 80
10 - 30
2 - 10
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
S/4
B.S
Sieve Size
A
100
70 -100
60 - 90
45 - 75
30 - 60
20 - 50
10 - 30
0-2
37.5 mm
28.0 mm
20.0 mm
10.0 mm
5.0 mm
2.0 mm
425 m
75 m
3.1.4.2
B
100
70 - 100
45 - 75
35 - 65
25 - 50
10 - 30
0- 2
C
100
45 - 75
30 - 60
15 - 35
0-2
Surface drains shall be constructed with regard to both operation and ease of
maintenance and adequate gradient shall be provided to enable self-cleansing flow.
4.2
Where gradient designed is not practical or above the finished level, the Contractor
shall submit their proposal for the approval of the S.O.
Reinforced concrete struts shall be provided for all drain side walls exceeding 1.0 m
height. Handrails shall be provided for open drains more than 1.5 m width.
4.3
4.4
4.4.2
4.4.2.2
4.4.2.3
4.4.2.4
The sides of cut drain shall not be steeper than 1:1.5 (V:H), while
fill slopes shall not be steeper than 1:2 (V:H).The surface water
shall be discharges to a stable outlet such that soil erosion is
prevented from occuring.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
S/5
4.4.3
Lined drain
4.4.3.1
Vertical
Stone Pitching
1:1.5
1:2
4.4.3.2
4.4.3.3
b)
a)
b)
c)
d)
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
S/6
5. Subsoil Drain
5.1
This work shall include supply and installation of subsoil drains, constructed in
accordance with these Specifications at locations as shown on the Drawing and/or as
directed by the S.O.
5.2
Minimum gradient of 1:100 shall be provided for the drain to discharge into existing
stormwater system, open drain, creek or pond in the area. The discharge shall not
create an unwanted bog.
5.3
The lateral drain shall have a minimum slope of 1:100 to ensure water always flowing
even though there are undulations and laid at 2 m spacing at 450 to the main
pipes/collector drain.
6. Sumps
6.1
6.2
Unless otherwise as shown on the Drawings, sumps of depth less than 1.5 m
(internal depth) shall be made up of brickwalls of minimum 225 mm thickness. Sump
of depth (internal depth) more than 1.5 m shall use reinforced concrete Grade 20P.
7. Culverts
7.1
The work shall comprise of supply and installation of either reinforced concrete pipe
culverts or precast box culverts, including the end treatment components such as
headwall, wingwalls, aprons and sumps and channel protection works, all in
accordance with these Specifications and details as shown on the Drawings.
7.2
Culvert Bedding
7.3
7.2.1
Type A bedding shall consist of Grade 20P concrete and complying with
SECTION D: CONCRETE WORKS.
7.2.2
Culvert Components
Culvert shall be constructed with barrel and end treatments including headwalls,
endwalls, wingwalls, outlet protection, inlet improvement and debris control
structures.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
S/7
7.4
7.5
Pipe Culverts
7.4.1
7.4.2
The S.O. reserves the right to request for test certificates and to request for
tests to be carried out on samples, all at the Contractor's own cost.
7.5.2
7.5.3
7.5.4
Precast box culverts shall be laid on Type B bedding with layer of crushed
aggregate of maximum particle size not exceeding 50 mm as shown on the
Drawings or directed by the S.O.
7.5.5
The maximum gap between each culvert shall not be more than 13 mm and
the difference in level shall less than 3 mm. The gap shall be filled with
cement mortar (1:3) with smooth finished.
7.5.6
To ensure uniform bearing, a layer of cement grout shall be spread along the
top of the walls of the invert where the lid shall sit.
8.2
Unless otherwise stated in the Drawings, the side slopes of basins shall not be
steeper than 1 (V): 6 (H). Fence and warning signs shall be provided.
8.3
The construction of detention pond shall include the system components at the inlet,
storage and outlet zone to cater outflow discharges without causing adverse effects
on downstream properties.
8.4
Maintenance shall be done periodically or as and when the silt has accumulated to
half of the pond height.
BLANK PAGE
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
S/8
TABLE OF CONTENTS
SECTION T: SIGNAGE WORKS
PAGE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
General
Copper Plating
Aluminium
Paint Finish
Screen Printing Works
Vinyl Graphic Stickers
Stainless Steel
Acrylic
Installation And Fixing Works
Labeling For Registration Of Immoveable Asset
Components
T/1
T/2
T/2
T/2
T/3
T/3
T/3
T/3
T/3
T/4
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
T/1
1. General
1.1
All interior architectural signage shall be of acrylic plastic as approved by the S.O.
unless otherwise specified in the Drawings. All panel sign surfaces shall be flat and
smooth, constructed to remain flat under installed conditions within tolerance of plus
or minus 1 mm measured diagonally.
1.2
All signage works shall comply with the regulatory requirements currently enforced
and shall comply with MS 1184: Universal Design and Accessibility in The Built
Environment - CP and Government Immoveable Asset Code System (Sistem Kod
Aset Tak Alih - SKATA) as referred to sub-section 10.
1.3
Unless otherwise stated in the Drawings, the panel and lettering size, profiles and
dimensional requirements of interior panel signage shall be as follows:
1.4
1.3.1
The standard thickness of cast-acrylic matt clear sheets shall be not less
than 4 mm.
1.3.2
1.3.3
The type of panel material and size of letterings shall be as indicated in the
Schedule of Signage prepared by the manufacturer to the S.O.s approval.
Graphic content and style of signage shall be in accordance with the Schedule of
Signage, Shop Drawings and comply with the requirements indicated below:
1.4.1
1.4.2
1.4.3
1.5
Location, accessories and mounting positions of signs shall comply with MS 1184,
manufacturers recommendations and as approved by the S.O.
1.6
Wall mounted panel signs shall be mounted to wall surfaces using methods
indicated below:
(i)
(ii)
(iii)
Vinyl-tape mounting: use double-sided very high bond (VHB) tape to adhere
signs to smooth, non-porous surfaces.
Silicone-adhesive mounting: Use liquid-silicone adhesive recommended by
manufacturer to attach signs to porous, irregular, or vinyl-coated surfaces.
Use double-sided foam tape to hold sign in position until silicone adhesive
has fully cured.
Mechanical fasteners: Use non-removable mechanical fasteners placed
through pre-drilled holes in sign face, or through shim plate. Use proper
anchors at masonry walls as recommended by manufacturer. Attach sign
panel to shim plate using vinyl-tape method as described above.
(iv)
(v)
1.7
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
T/2
During the Contractors drawings preparation phase, the Contractor shall provide full
size mock-up samples of each type as required for inspection and subsequent
approval by the S.O.
2. Copper Plating
2.1
2.2
Where grainy texture is required, the copper plate should be allowed to run in
copper sulphate bath or copper cyanide based solution bath for a longer period.
3. Aluminium
3.1
3.2
3.3
Aluminium sheets used shall comply with the requirements of MS 2040: Aluminium
and Aluminium Alloys - Sheets and Coiled Sheets - Specification. The alloy selected
will be of a temper suitable for cutting.
3.4
Where signs required more than one standard size aluminium panel, the jointing
shall be performed in accordance to BS 1473 by using rivets or screws with welded
angles to the main panels. The joint shall than be fine sand, smoothen to be flushed
to be seen as one and no butt-line joint, division or separation is to be seen.
3.5
All aluminium sections shall be fabricated from aluminium alloy B6063-T5 complying
with the requirements of MS 2289: Aluminium and Aluminium Alloy-Extruded
Shapes.
3.6
The aluminium shall be electronically anodized in matte finish for etched aluminium
required for the fire door sign.
4. Paint Finish
Unless otherwise specified, all painting works shall be carried out as specified in SECTION
O: PAINTING WORKS.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
T/3
5.2
Silkscreen ink shall be of two (2) pack-serical poly-screen with Ultra Violet protective
agents against colour fading. All finished screen printed text or graphics shall be
coated with a layer of 2-pack polyurethane clear coat matte finish.
Unless otherwise specified in the Drawings and Specifications, vinyl graphic stickers
shall be used as recommended by the manufacturer and approved by the S.O.
6.2
6.3
All vinyl graphics shall be precision cut by computers with no jagged edge. Minimum
performance of vinyl stickers shall be to the approval of the S.O.
7. Stainless Steel
7.1
7.2
Stainless steel plate and component for all external signs shall be of marine grade
316 with alloy addition of molybdenum to prevent specific forms of corrosion.
7.3
Stainless steel fasteners, bolts, screws, bolts, washers and other fixing components
shall be of Grade A2 or Grade A4 to BS EN ISO 3506.
8. Acrylic
8.1
Acrylic used for the external signage shall be of high impact acrylic. Extruded acrylic
shall not be acceptable. The Contractor shall comply with the required thickness of
the acrylic as shown on the Drawings.
The Contractor shall submit a works programme and method statements for the
installation of all internal and external signs. The Contractor is to include in their
method statement on safety processes, measures to be taken and procedures while
erecting the external signs.
9.2
Unless otherwise shown on the Drawings, all base plates for external signs shall be
galvanized steel plates with drawings and calculation certified by P.E.
No. Dokumen
No. Keluaran
No. Pindaan
Tarikh
Muka Surat
:
:
:
:
:
JKR 20800-0183-14
01
00
29 Januari 2014
T/4
The code and format for labelling of components shall be as stipulated in the
Governments:
(i)
(ii)
Immoveable Asset Code System (Sistem Kod Aset Tak Alih SKATA); and
Immoveable Asset Data Collection Guidelines (Garis Panduan
Pengumpulan Data Aset Tak Alih PeDATA).
10.2
All labels for the registration of the asset components shall comply with the
regulatory requirements currently enforced and shall comply with the relevant
International and/or Malaysian Standards.
10.3
Labels for the assets must be durable and withstand exposure to extreme conditions
such as chemicals, temperature, weather, oils and detergents. The labels must also
be able to withstand the rigour of cleaning schedule, maintenance and repairs.
10.4
10.5
Asset component labels shall be affixed to the asset in a position that is easily
accessible for readability while the asset is in normal operating position (Refer to
PeDATA).
10.6
Labels shall be located on clean, smooth, flat surfaces where possible, and on
surfaces that provide direct visual access to a label scanner and its operator.