100% found this document useful (1 vote)
408 views

ProQC ExampleReport TS16949 Audit PDF

The audit report summarizes an ISO/TS 16949 audit conducted at a supplier's facility. Key findings include: - The supplier's quality management system was found to comply with requirements at a rate of 92.93%, with areas needing minor improvement at 4.07% and no major non-conformances. - The supplier's system is well-documented and effective, though some opportunities for improvement were identified, such as updating quality objectives and competence records. - Overall the audit found the supplier has an acceptable quality system and the capabilities to address identified issues, recommending the client could start or continue business with this supplier.

Uploaded by

pandajay
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
408 views

ProQC ExampleReport TS16949 Audit PDF

The audit report summarizes an ISO/TS 16949 audit conducted at a supplier's facility. Key findings include: - The supplier's quality management system was found to comply with requirements at a rate of 92.93%, with areas needing minor improvement at 4.07% and no major non-conformances. - The supplier's system is well-documented and effective, though some opportunities for improvement were identified, such as updating quality objectives and competence records. - Overall the audit found the supplier has an acceptable quality system and the capabilities to address identified issues, recommending the client could start or continue business with this supplier.

Uploaded by

pandajay
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 39

ISO/TS 16949 Audit Report

* Example Report *

North America
+1-813-252-4770
Latin America
+52-1-333-2010712
Europe & Middle-East
+49-8122-552 9590
Asia & Asia Pacific
+886-2-2832-2990
Email
[email protected]

www.proqc.com

ISO/TS 16949 Quality Management System Audit

Rev.

GUIDELINES

PURPOSE:
This audit checklist was created based on requirements defined in the following standards:
- ISO/TS 16949 standard
- AIAG Standard
The intent of the audit is to assess the compliance level of suppliers to these requirements, and to provide adequate
information to the client for use in business decisions.
SCORING:
Scores are assigned based on what is done for the Pro QC client regardless of what is done for other clients. For
example, if control plans are developed for other clients but not for the Pro QC client, the score must be NC. Scoring
must be explained to the supplier at the opening meeting.
Complies with the Requirements = C
Improvement Needed = I
Non-Conformance Found = NC
N/A = Does Not Apply
GUIDELINE FOR SCORING CONFORMANCE:
Each question is assessed for conformance to the requirements of the applicable standards, and the auditors
knowledge of the product and/or process This must be clear to the supplier at the opening meeting.
Complies with Requirements =
- Has objective evidence to support the question, and
- Has a written procedure (when required).
Improvement Needed =
- Has objective evidence, but procedure needs improvement.
- Has objective evidence, but no written procedure.
- Has written procedure, but is lacking some objective evidence to support the question.
Non-Conformance =
- No objective evidence to support the question (regardless of the procedure).
- Lacking some objective evidence and no written procedure.
RESULTS/RECOMMENDATIONS: (Automatically Calculated)
The score is based on the percent of questions that Complies with Requirements, percent that Needs Improvement,
and the percent that have a Non-Conformance. Each client should review how the supplier was evaluated for each
question and base their decisions on factors that are important to their organization and product(s).
AUDIT REPORT:
The following sections are completed by the auditor:
- Scope of the Audit
- Recommendations
- Strengths of the Supplier's Quality System and Manufacturing Process
- Opportunities for Improvement (Weaknesses in the Supplier's Quality System and/or Manufacturing Process)
RESULTS REVIEW WITH SUPPLIER:
The auditor should review the audit results with the supplier, but cannot provide the supplier a copy of the audit. The
audit is the property of the client.
CORRECTIVE ACTIONS:
It is recommended that the client request a corrective action (improvement plan) based on the results of the audit. The
improvement plan should include the following:
- Detailed description of action plan.
- Name of the person responsible for the improvement activity.
- Date when the improvement will be completed.

ISO / TS 16949 QMS Audit Form

Rev.

SUMMARY

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

SUPPLIER'S INFORMATION

CLIENT'S INFORMATION

NAME : XXXXXXXXXXXXXXX
ADDRESS : XXXXXXXXXXXXXXX
XXXXXXXXXXXXXXX
CITY : XXXXXXXXXXXXXXX
COUNTRY: XXXXXXXXXXXXXXX
PHONE : XXXXXXXXXXXXXXX
FAX : XXXXXXXXXXXXXXX

NAME : XXXXXXXXXXXXXXXXX
ADDRESS : XXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXX
CITY : XXXXXXXXXXXXXXXXX
COUNTRY: XXXXXXXXXXXXXXXXX
PHONE : XXXXXXXXXXXXXXXXX
FAX : XXXXXXXXXXXXXXXXX

SUPPLIER'S PERSONNEL PARTICIPATING


Mr./Mrs.
Mr./Mrs.
Mr./Mrs.
Mr./Mrs.

XXXXXXXXXXXXXXX
XXXXXXXXXXXXXXX
XXXXXXXXXXXXXXX
XXXXXXXXXXXXXXX

Title:
Title:
Title:
Title:
Title:

Mr./Mrs.

XXXXXXXXXXXX
XXXXXXXXXXXX
XXXXXXXXXXXX
XXXXXXXXXXXX

Email:
Email:
Email:
Email:
Email:

XXXXXXXXXXXXXX
XXXXXXXXXXXXXX
XXXXXXXXXXXXXX
XXXXXXXXXXXXXX

Email:
Email:

XXXXXXXXXX
XXXXXXXXXX

Pro QC Personnel
Mr./Mrs.
Mr./Mrs.

XXXXXXXXXXXXXX
XXXXXXXXXXXXXX

Title:
Title:

XXXXXXXXXX
XXXXXXXXXX

AUDIT RESULTS =
Category
Complies ( C )
Needed
Improvement ( I )
Not-complies
(NC)
Not Applicable
(N/A)

92.93%

4. QUALITY
8 MEASUREMENT, ANALYSIS
7. PRODUCT
AND 6.
IMPROVEMENT
RESOURCE
REALIZATION
5. MANAGEMENT
MANAGEMENT
RESPONSIBILITY
MANAGEM
4. QUALITY MANAGEMENT SYSTEM
ENT
96.5%
91.67%
88.46%
91.89%
96.77%

5. MANAGEMENT RESPONSIBILITY

6. RESOURCE MANAGEMENT

3.5%

7.58%

11.54%

8.11%

3.23%

0.0%

0.76%

0.00%

0.00%

0.00%

1.8%

12.12%

0.00%

0.00%

0.00%

7. PRODUCT REALIZATION

8 MEASUREMENT, ANALYSIS AND IMPROVEMENT


0%

Complies)()C)))

10%

20%

Needed)Improvement)()I)))

30%

40%

50%

60%

70%

Not3complies)(NC))

RECOMMENDATIONS
1
2
3
4

The system is well documented and implemented effectively. You could start or
continue business with this supplier.
The system is acceptable, with minor nonconformities noted. You could use this supplier
and keep pushing them for improvement.
System has several major issues noted. You could temporarily use this supplier and
request immediate corrective action in case of long-term business.
There are serious majors issues noted with this supplier that could impact your business.
This supplier will need significant time and resources to be compliant to requirements.
The best solution will be to source another supplier.

80%

90%

100%

ISO/TS 16949 QMS Audit

Rev.

AUDIT REPORT

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

Scope of Audit:
To evaluate the Quality Management System of the supplier.
Summary / Recommendations:
The audited factory is located in XXXXXX. The factory has approximately 500 to 600 people working full-time.
There are two various productions, with one already certified to ISO/TS 16949.
Tthe 2nd, XXXXXXXX, is ongoing in the process to be included in this certification before the end of this current year.
There is sufficient evidence demonstrating that the audited site has an effective QMS functioning according
to requirement of TS, with staff well trained in the maintenance of QMS. The factory has experience working with
world class track maker and various others clients which has enhanced to keep themselves at
the international standard level. The auditor has full confidence that this organization has enough capability to
overcome few improvements listed here below in order to further reduce quality risk.
Strengths:
1. The factory is TS certified, with the system controlled by well qualified people / auditors (12).
2. The people in charge of QM has clear understanding of PDCA and have evidences of their implementation.
3. Visualizing system to communicate with worker in the clear language of the importance of client.
4. Great history of cooperating with major world-class clients.
5. Adequate manufacturing area, well spaced and in good working condition.
6. Testing center with necessary equipment in place and calibrated, with tags.
7. Multi-functional team applied in the development of process (APQP / PPAP).
8. Excellent supplier management / control, with one supplier TS certified, two committed to complete within a couple
of months, 13 out of 21 ISO 9001 certified.
Opportunities for Improvement:
1. Quality objectives: KPIs should be updated and published on a monthly basis at various workshops.
2. Competence of people: Skill matrix should be defined and published at testing center.
3. Human resources: Must have a replacement staff, when key people are not available.
4. Management review input: Use PFMEA as input during management review meeting.
5. Predictive maintenance: Tool life circle time to be defined in the tooling CV.
6. Control of changes: Must specify a list documents that could be affected by specific changes.
7. Calibration: Should have a calibration program with an alert sign when approaching the expiration date.
8. Calibration: Internal calibration to be traceable to external source.
9. Recording: In-house calibration to be recorded by hand, not in the computer.
10. Calibration: Employees must have a plan when an equipment is found out of calibration or damaged.
11. Testing method: Could provide specific work instruction for some testing devices with images.
12. TS Certification: The organization should submit a plan for the completion of the TS certification of the
2nd facility to client, and keep them updated on the progress.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
4

EVIDENCE TO CHECK

FINDINGS

QUALITY MANAGEMENT SYSTEM

4.1

General Requirements
Has the organization established,
Evidences of this question can be demonstrated
documented, implemented and
throughout the audit.
maintained a QMS and continually
improved its effectiveness in accordance
with ISO/TS 16949:2009?

Yes, the organization has established,


documented, implemented and maintains a
QMS according to ISO / TS requirements
(Exclude 7.3), and has evidences of
continually improving its effectiveness.

4.1q2a

Has the organization identified the


processes needed for the QMS and their
application throughout the organization?
[ISO/TS 16949:2009, Art 4.2.2]

Yes, the organization identified the


processes needed for the QMS, in their
Quality Manual (Q/YCQP1001-2011, page
14/36), and their application throughout the
organization. SEE PHOTO #2.

4.1q2b

Has organization determined the


sequence and interaction of QMS
processes?
[ISO/TS 16949:2009, Art 4.2.2]

Yes, the organization determined the


sequence and interaction of processes in
the Quality Manual (Q/YCQP1001-2011,
page 15/36). SEE PHOTO #3.

4.1q2c

Has the organization defined criteria and


methods to uses to ensure that the
operation and control of QMS processes
are effective?

Yes, the organization applies the approach


of PDCA to monitor performance of
processes for effectiveness. Each process
has procedures and guidelines and with
defined KPIs.

4.1q2d

Has the organization provided resources


and information needed to support the
operation and monitoring of QMS
processes? (See Section 6)

Yes, resources are provided, with qualified


operators under an organization chart and
with adequate two facilities, with necessary
equipments. SEE PHOTOS #4, #5 & #6.

Does the organization monitor, measure


and analyze QMS processes? (See
Section 8)

Yes, each process identified has specific


KPI, with responsibility for their monitoring,
for improvement, as general KPI and as
KPIs distributed to each process and
department. It should the status of
satisfaction for the year 20XX, and planning
for the year 20XX. SEE PHOTOS #7 AND
#8.

4.1q1

4.1q2e

4.1q2f

4.1q3

Does the Organization implemented


actions necessary to achieve planned
results and continual improvement of
processes needed for the QMS?

Yes, the Organization has evidences of


implementation of continual improvement
thought effective management review

Are processes needed for the QMS


managed by the organization in
accordance with the requirements of
ISO/TS 16949:2009?
When the organization outsources any
process that affects product conformity
with requirements, how is control
ensured over such processes? (See 7.4)

Yes, processes are managed with KPIs.


SEE PHOTOS #7 and 8.

4.1q4

4.1q5

SCORE

Where is the control of outsourced


processes that affect product conformity
with requirements identified within the
QMS? (See 7.4)

The organization purchases few


components from others suppliers, and gets
support from external service for calibration
of equipment. All of these external
outsources are managed according to the
requirements of the Purchase Procedure
(Q/YCQP2019-2011).

It is identified in the purchase.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES

T4.1.1q1

4.2
4.2.1q1a

4.2.1q1b

4.2.1q1c

4.2.1q1d

4.2.1q1e

4.2.2q1b

4.2.2q1c

SCORE

Documentation Requirements
a) Review where it's written and note the doc, if
any.
b) Check if the QP/QO posted in a visible place
for all employee to view.
c) Take a photo.

Yes, the Quality Policy is documented in


the Quality Manual (Q/YCQP1001-2011, rev
C), published and signed by GM. SEE
PHOTO #9. Quality objectives are also
listed, with a distribution to each
department. SEE PHOTO #7.

Does Organization have a quality


manual? ISO/TS 16949:2009, Art
4.2.1(b)

Review the Quality Manual, and note the doc.


and rev.

Yes, the factory has a Quality Manual 20XX


(Q/YCQP1001-2011, rev C) published in 2009-30.

Does the organization have the


documented procedures required by ISO
9001:2008?
ISO/TS 16949:2009, Art 4.2.1(c)

a) Review the procedure master list and confirm Yes, the factory has about 26 procedures as
that all mandatory procedures are included.
guidelines for the implementation of QMS
b) Take a photo of the master list.
according to TS requirements, listed in QM,
page 35/36. SEE PHOTO #10.

Are adequate documents in place to


ensure the effective planning, operation
and control of t organizations
processes?
ISO/TS 16949:2009, Art 4.2.1(d)
Does documentation include the records
required by ISO 9001:2008?
ISO/TS 16949:2009, Art 4.2.1(e)

Evidences of this question could be


demonstrated throughout the audit.

Yes, documentation is visible at each place


as guideline.

a) Review the master list for record and confirm Yes, the factory has procedure for the
that all records monitored are included.
control of record (Q/YCQP2013-2011, Rev.
b) Take photo of the master list.
B/0.) There is a master list of ten pages
describing all Quality Record to save,
including saving place, and time. SEE
PHOTO #11.

Quality Manual
If any, is the scope of the quality
management system identified in the
QMS, including details of and
justification for exclusions?
ISO/TS 16949:2009, Art 4.2.2(a)

If any justification for exclusions, then note the


page of QM in which is written.

Does the quality manual (QM) contain or


reference the documented procedures
established for the QMS?
ISO/TS 16949:2009, Art 4.2.2(b)

Check if doc numbers of procedures are written Yes, the QM contains references of
at relevant section of the QM to indicate
procedures/documents to use. The name of
appropriate procedure applied.
the procedures are written as link.

Does the quality manual include a


description of the interaction between
the processes of the QMS?
ISO/TS 16949:2009, Art 4.2.2(c)

a) Check if there a document in annex of QM or


out of the QM, as document describing
interaction between processes.
b) Take photo of the map.

Are the documents required by the QMS


controlled?
ISO/TS 16949:2009, Art 4.2.3

a) Ask if there is a master list containing all


documents for QMS, with doc title, current
revision and distribution record / name of users.
b) Select few docs from the master list, and
cross check on site (user hands) if these docs
have same doc. nb, rev. nb, and accurate nb of
copy distributed.

4.2.3
4.2.3q1

FINDINGS
Yes, incoming inspections are conducted
per random sampling. Suppliers are
selected per requirement, and are
evaluated on an annual basis.

Does the organization have documented


statements of a quality policy (QP) and
quality objectives (QO)?
ISO/TS 16949:2009, Art 5.3, 5.4.1

4.2.2
4.2.2q1a

EVIDENCE TO CHECK

Does the organization have adequate


control over outsourced processes to
ensure conformity to all customer
requirements?
(See 7.4)

Yes, the scope of the QMS is described in


the TS certification, with exclusion of 7.3,
See page 10/36, where it declared to
exclude 7.3, 7.3.2.1, 7.3.3.1.

Yes, there is process map described in the


QM page 14/36, with five Customer related
processes (C1, C2, C3, C4), supporting
processes, and management processes,
including their relation in page 15/36 of the
QM. SEE PHOTOS #2 & #3.

Control of Documents
Yes, there is procedure for the control of
document (Q/YCQP-2012-2011). Checked
mold maintenance document (Q/YCQP3007-01-20XX) distributed in 20XX-03-13,
and has signature of related department.
Record are written in form (Q/YCQP-401202, A/0).

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
4.2.3q2a

4.2.3q2f

4.2.3q2g

Is there a documented procedure that


defines the controls needed for approve
INTERNAL documents for adequacy
prior to issue?
ISO/TS 16949:2009, Art 4.2.3

T4.2.3.1q2

T4.2.3.1q3

FINDINGS

Is there a documented procedure that


defines the controls needed for ensure
that documents of EXTERNAL origin are
identified and their distribution
controlled?
ISO/TS 16949:2009, Art 4.2.3

a) Ask if there is a masterlist containing all


documents for QMS, with doc title, doc. Nb.
Current revision. And distribution record / name
of users.
b) Select few docs from the masterlist, and
cross check on site (User hands) if these docs
have same doc. nb, rev. Nb, and accurate nb of
copy distributed.

Yes, the is requirements for the control of


external documents (Q/YCQP-2012-2011,
step 6.8). There is a masterlist of external
document written in form (Q/YCQP-401207, a/1). An obsolete stamp is putted in the
drawing for identification. SEE PHOTO #12
of drawing Nb. SA14056-D as example.

Is there a documented procedure that


defines the controls needed for prevent
the unintended use of obsolete
documents, and to apply suitable
identification to them if they are retained
for any purpose?
ISO/TS 16949:2009, Art 4.2.3

a) Ask the responsible to explain how to prevent


the use of obsolete documents.
b) Check
if there is a documented procedure for:
- Identification of obsolete doc.
- Retention period and location
c)
Note the doc nb. and current rev. in this report.

Yes, there are requirements for the control


of external documents (Q/YCQP-20122011, step 6.8). There is a master list of
external documents written in form
(Q/YCQP-4012-07, a/1). An obsolete stamp
is putted in the drawing for identification.
SEE PHOTO #12.

Is there any evidences of how to easily


identify obsolete documents to prevent
them for unintended use?
ISO/TS 16949:2009, Art 4.2.3

a) Check if there is visible "UNDER CONTROL" Yes, document has OBSOLETE stamp
stamp on new revised doc, and if there is
putted in the drawing, SEE PHOTO #12 of
"OBSOLETE" stamp on old rev. of same doc.
drawing Nb. SA14056-D as example.
b) Note doc. Nb reviewed and take photo of
those stamps if any.

Does the company have a process to


assure the timely review, distribution and
implementation of customer
specifications and changes?
Does it meet customer-required
schedule(s)?
ISO/TS 16949:2009, Art 4.2.3.1

a) Check if this process is included in any


document, note its doc. nb and rev.
b) Check if FMEA, Control Plansetc are
included as potential document to review as per
customer-required schedule(s).

Yes, the company has a process (SP1) with


detail described in the procedure
(Q/YCQP2012-2011, section 6.8) for update
and timely distribution of updated customer
specification and changes.
It does not have clarification of what others
documents could be affected by specific
changes.

Does the review occur in two weeks or


less?
ISO/TS 16949:2009, Art 4.2.3.1

Check if the company includes time spent to


implement.

Yes, the requirement to complete the


review and distribution is been defined for
two weeks in the (Q/YCQP2012-2011,
section 6.8.2)

What records do you have showing


implementation dates of changes? Is
there evidence showing that documents
are updated? ISO/TS 16949:2009, Art
4.2.3.1

a) Check if the company maintains a record of Yes, records are available.


changes in engineering specifications from
customers or regulatory or industry documents?
b) Randomly select two cases from the list, and
ask them to show you record of implementation
of such changes in others documents (ie
FMEA, Control Plans...etc).

4.2.3.1
T4.2.3.1q1

EVIDENCE TO CHECK

a) Ask for the procedure of document control,


Yes, it described in the procedure (Q/YCQPand note its doc. nb and current revision in the 2012-2011), step 6.2. The authority
report.
regarding document review and approval is
b) Check if this procedure contain clear
defined in the procedure (Q/CYQP-2012requirements need for:
- 2011, B/0) page 6/6.
Ensuring the legibility and identification
- Authorities for approve prior to issue
Ensure that only latest rev. at workplace
- Ensure the identification of changes

SCORE

Engineering Specifications

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
4.2.4
4.2.4q1

4.2.4q2

4.2.4q3

T4.2.4.1q1

Are records legible, readily identifiable


and retrievable?
ISO/TS 16949:2009, Art 4.2.4

5.1q1c

5.1q1d

5.1q1e

T5.1.1q1

a) Check if the company has a masterlist that


with all quality records with detail of:
- Name / template nb.
- Creation method (handwriting / elec)
- Resp. for initiate and approve.
- Retention period / location
- Saving form (in paper or electronic)
- Disposal method after expiration.
b) Take photo of the masterlist

SCORE

Should be reviewed throughout the audit.

The company has a masterlist of records


that must be maintained in the factory, with
details of their location and retention period,
SEE PHOTO #11.
C

Yes, records are available


C

Does Organization have a documented


procedure defining the controls needed
for the identification, storage, protection,
retrieval, retention time and disposition
of records?
ISO/TS
16949:2009, Art 4.2.4

Review the procedure and note its doc. nb and Yes, the procedure (Q/YCQP2013-2011)
current revision.
provide guidelines for the control of records
listed in the masterlist.

Have the record requirements been


reviewed to ensure conformance with
regulatory and customer requirements?
ISO/TS 16949:2009, Art 4.2.4.1

Should be reviewed throughout the audit.


Yes, records are to be review by a
Review few records at every process to see if supervisor, with signature as conformity.
there is signature / name of the operator and for
the reviewer and approver.

5.1q1b

FINDINGS

Control of Records
What records exist that provide evidence
of conformity to requirements and of the
effective operation of the QMS? (Should
be reviewed throughout the audit)
ISO/TS 16949:2009, Art 4.2.4

MANAGEMENT RESPONSIBILITY

5.1
5.1q1a

EVIDENCE TO CHECK

Management Commitment
Does top management communicate the
importance of meeting customer and
statutory and regulatory requirements to
the organization?

a) Review records (with attendance) of meeting


held by top management.
b)
Review records of meeting related to any new
project.

Yes, the communication of customer will be


communicated to members following the
APQP process, to be checked during
product/ process realization, with record
attached.

Has a company quality policy (QP) been


established? (See 5.3)

a) Check if there QP documented, hand signed


by top management.
b) Check if QP is posted in public board for all
employees to view. And, eventually take a
photo of it.

Yes, the Quality Policy is documented in


the Quality Manual (Q/YCQP1001-2011, rev
C), published and signed by GM. SEE
PHOTO #9.

Has company established quality


objectives and communicated all
members? (See 5.4.1)

a) Check if the quality objectives are hand


signed by all managers and published.
b) Ask them to explain and demonstrate that
quality objectives are aligned to fit with policy.

Yes, quality objectives are also listed, with a


distribution to each department. SEE
PHOTO #7.

Does top management conduct


management reviews? (See 5.6)

a) Check if there a documented as guideline to


conduct management reviews, and note the
doc. nb / rev.
b) Review record of last two management
reviews.

Yes, the factory has a procedure for


management review (Q/YCQP-2016-2011,
B/0). The last management review was
conducted in 20XX-12-21. There is a form
for plan. (Q/HLQP-4016-01)

a) Manpower list at each position


b) Machine and facility

The factory does not have a replacement


person for lab testing.

Does top management ensure the


availability of resources to support and
continually improve the QMS?
Does top management review product
realization and support processes to
ensure effectiveness and efficiency?
(5.6?)

Yes, the factory uses a multi-functional


team, with a delegate to supervise the
process. Records are available.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
5.2
5.2q1

5.3q1b

5.3q1c

5.3q1d

5.3q1e

a) Check if there is any responsible person or


group dedicated for identification of customer
requirements.
b) Check if there any records showing a list of
identified requirements per customer, and
related procedures or method applied to fit
them.

Does the quality policy include a


commitment to comply with
requirements and continually improve
QMS effectiveness?

Read the quality policy.

Are the contents of the quality policy


relevant to the organization and
measurable?

Read the quality policy and ask them to explain Yes, the contents of the quality policy
how the company measures them.
relevant to this factory are measurable with
KPIs defined, SEE PHOTOS #7 AND #8 for
the year 20XX. There is plan of how these
KPIs are monitored. SEE PHOTO #8.

Is the quality policy communicated and


understood within the organization?

a) Check if there is QP documented and hand


signed by top management.
b) Check if QP is posted in public board for all
employees to view.

Is there an established process to review


the quality policy for continuing
suitability?

Has top management established quality


objectives (including those needed to
meet requirements for product) at
relevant functions and levels within the
organization?
Are the quality objectives consistent with
the quality policy? What are the
measurements?

Are quality objectives and metrics


included in the business plan?

5.4.2

Yes, the quality policy is well appropriate,


and applicable to their facility.

Yes, the quality policy includes a


commitment to comply with requirements
and continually improve QMS effectiveness.

Yes, the Quality Policy is documented in


the Quality Manual (Q/YCQP1001-2011, rev
C), published and signed by GM, posted in
published place visible by all. SEE PHOTO
#9.

Planning

5.4.2q1a

Yes, from management review meeting.

Quality Objectives

T5.4.1.1q1

SCORE

Quality Policy
Read the quality policy.

5.4

5.4.1q2

Yes, the company has nominated a


responsible party to act as Customer Rep.
with responsibility to ensure that customer
requirements are determined. SEE PHOTO
#13. (Q/YCQP1001-2011, page 5/36).
The factory also maintains a record
describing all customer requirement
records. (Q/YCQP-4003-32-2012) SEE
PHOTO #14.

Does top management ensure that the


quality policy is appropriate to the
purpose of the organization?

5.4.1
5.4.1q1

FINDINGS

Customer Focus
Has top management ensured that
customer requirements are determined
and met with the aim of enhancing
customer satisfaction?

5.3
5.3q1a

EVIDENCE TO CHECK

Check if the quality objectives are hand signed Yes, quality objectives are also listed, with a
by all managers and published.
distribution to each department. SEE
PHOTO #7.

a) Ask them to explain how quality objectives


are aligned to fit with quality policy.
b) Review record of measurement of last year,
and for this year.
c) Check if the result are published and take a
photo of quality objectives.

Yes, the quality objectives are consistent


with the quality policy. SEE PHOTO #8.
C

Check if the quality objectives are hand signed Yes, it is included. SEE PHOTO #8.
by all managers and published.

Quality Management System Planning


Does the company ensure that the
planning of the QMS is carried out in
order to meet the requirements given in
ISO /TS 16949:2009 section 4.1, as well
as the quality objectives?

Yes, the factory uses the strategy of internal


audit, process audit, and product audit to
monitor the effectiveness of QMS as input
for management review.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
5.4.2q1b

How do you ensure that the integrity of


the QMS is maintained when changes to
the QMS are planned and implemented?

5.5

T5.5.1.1q1

T5.5.1.1q2

T5.5.1.1q3

5.5.2q1a

5.5.2q1b

5.5.2q1c

T5.5.2.1q1

T5.5.2.1q2

SCORE

Responsibility and Authority


Are responsibilities and authorities
defined and communicated within the
organization? (Verify throughout audit)

a) Check the organization chart and take photo.


b) Check if there is detailed job description for
every position within the organization.
c) Check if there is a planning for replacement
in the absence of key person, and related
training record / qualifications.

Yes, there is an Organization Chart in the


Quality Manual (Q/YCQP1001-2011, page
6/36) and detail of job description in pages
8/36, 9/36. However, there is no document
detailing replacement people in the event of
the absence of a key person, for example at
the Testing Center.

Are managers responsible for corrective


action informed of nonconforming
products or processes?
Are they informed in a timely manner?

a) Check if there a document that describes the Yes, it is implemented accordingly and
flow for the communication of quality issues,
records are available.
and note the doc. nb / rev.
b) Check if a record of internal / external
complaints are maintained.

Do personnel responsible for product


quality have the authority to stop
production to correct quality problems?

Review JD for Quality Manager / Supervisor


and check if this is included.

What personnel on each shift have


responsibility for ensuring product
quality?

Check if there is a representative of the Quality Yes, each facility under this organization
Department in charge of quality for the whole
has responsibility of quality to ensure the
company. Note his/her name.
quality of product.

Is there a ISO/TS 16949 Management


Representative (MR)?

Check if there is nomination letter and take


photo.

Does the MR have responsibility and


authority to ensure that processes
needed for the QMS are established,
implemented and maintained?
Does the MR have the responsibility to
report to top management on the
performance of the QMS and any need
for improvement?

Review JD for MR and check if this is included. Yes, it is included.

5.5.2
5.5.2q1

FINDINGS
Yes, following the procedure (Q/YCQP20102011), with responsibility under Manager of
Technical Department.

Responsibility, Authority and Communication

5.5.1
5.5.1q1

EVIDENCE TO CHECK
a) Check if there is a document as guideline to
handle any changes that could potentially
happen, note doc. nb / rev.
b) Check if the company has a reaction plan
with responsible for implementing changes.

Yes, it is defined in the JD of the Quality


Department, No. 9.
C

Management Representative

Does the MR have the responsibility to


ensure the promotion of awareness of
customer requirements throughout the
organization?
Has top management designated as
Customer Representative to ensure that
customer requirements are addressed?
Does their responsibility and authority
include selection of special
characteristics, setting quality objectives
and related training, corrective and
preventive actions, product design and
development?

Yes, it documented in the QM, page 4/36.


Mr. XXX is nominated as Management
Representative.

C
a) Review the organization chart and the
position of MR, including report line.
b) Review his last report submitted to top
management (Is this signed by the MR?)

Yes, it is included.
C

Review JD for MR, and check if this is included. Yes, it is included.


c
Check if there is nomination letter, take photo of Yes, it is defined in the QM, page 5/36.
that letter.

Review JD for customer representative and


check if this is included.

Yes, it is included.
C

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
5.5.3
5.5.3q1

5.6.1q2

5.6.1q3

T5.6.1.1q1

T5.6.1.1q2

T5.6.1.1q3

SCORE

Management Review

What kinds of information are reviewed


in management reviews? (Must include
suitability, adequacy and effectiveness of
QMS; improvement; & changes to the
QMS, quality policy and objectives)

Check the scope of management review


suitability, adequacy and effectiveness of QMS;
improvement; & changes to the QMS, quality
policy and objectives.

Can you show me records from recent


management reviews?

Check records of last two management reviews Yes, reviewed the record of last
and compare status of improvement between
management review conducted in 20XX-12both.
22.

Do management reviews include all


requirements of the quality management
system and performance trends? (Verify
records)

Verify records of last two management reviews. Record of review are checked for the year
20XX. Performance trends of the year 20XX
recorded in document ( Q/YCQP-4016-05,
B/0).

Can you show management review


records including monitoring of quality
objectives, and cost of poor quality
metrics? (Verify records)

Verify records of last two management review.

Can you show records providing


evidence of achievement of the quality
objectives specified in the business plan,
and customer satisfaction with product
supplied?

Verify records performance of each objectives


and take photo.

Can you show me that each of the


following were included in review(s)?

a) Verify if there is document specifying the type Yes, all inputs are included in the file
of input for the management review and note
Q/YCQP-4016-03 (a/0).
the doc. nb/ rev.
b)
Verify if all mandatory inputs are listed, and
include evidences for the last two management
review meeting.

According to the last management review


conducted in 20XX-12-21, following are
reviewed written in Q/YCQP-4016-03 (a/0):
- Policy and objective
- Last internal audit record
Improvement opportunity

Yes, recorded in the form Q/YCQP-401605, B/0)


C
Record are available. SEE PHOTO #16.
C

Review input

Do records show input to management


review includes analysis of actual and
potential field-failures and their impact?
(See also 7.3.4.1)

5.6.3
5.6.3q1

The method of communication is defined in


related procedure, and change depending
to the type of information. Email, ERP
system mainly is used, including public
board, to inform about performance. SEE
PHOTO #15.

Check if it documented to conduct management It is written in the procedure that the


review at least one time per year and in specific management review will be conducted one
circumstances. Note the doc. nb / rev.
time per year.

a) results of audits,
b) customer feedback
c) process performance and product conformity
d) status of preventive and corrective actions
e) follow-up actions from previous management
reviews
f) changes that could affect the quality management
system, and
g) recommendations for improvement

T5.6.2.1q1

a) Check if the company has defined clear


methods (email, fax, telephone, meeting, paper
record) for communication of information.
b) Check if the implementation of these are
effective and their efficiency monitored (On time
delivery, accuracy).

What is the frequency that top


management reviews the organization's
QMS?

5.6.2
5.6.2q1

FINDINGS

Internal Communication
How is information regarding the
effectiveness of the QMS communicated
within the organization?

5.6
5.6.1q1

EVIDENCE TO CHECK

Did not include PFMEA as input to


management review.
I

Review Output
What decisions or actions have resulted
from management reviews for each of
the following?
a) improvement of the effectiveness of the quality
management system and its processes
b) improvement of product related to customer
requirements, and
c) resource needs

a) Verify if there is document specifying the type Yes, decision of output are listed in the form
of output for the management review, note the Q/YCQP-4026-02 (a/0).
doc. nb/ rev.
b)
Verify if all mandatory outputs are listed, and
with evidences for the last 2 management
review meeting.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
6

6.1q1b

Review factory profile.

What resources has the organization


provided to ensure that customer
requirements are met?
(See 6.2, 6.3, 6.4)

Evidence on question (See 6.2, 6.3, 6.4) will be The factory has all necessary workshops,
acceptable.
and equipment, including lab service. SEE
PHOTOS #5, #6, AND #17. TESTING
CENTER - SEE PHOTOS #18, #19, #20,
#21, #22.

6.2.2q1c

6.2.2q1e

T6.2.2.1q1

T6.2.2.1q2

T6.2.2.2q1

General
What are the education, training, skills
and experience required by this
job/task?
How does this person meet those
qualifications?

a) Verify of the factory has skill matrix defined


for key personnel.
b) While auditing, select some personnel
performing work affecting product quality.

How do you determine the necessary


education, training, skills and experience
for people performing work affecting
product quality?

Verify if the factory has system for identification The factory has procedure (Q/YCQP2017of training need.
2011) for guideline for the identification of
training. Training are for new hiring people
and for annual training.

What training or other actions do you


provide to satisfy the needs of
personnel?

a) Verify if a periodical (annual) training plan is


documented.
b) Take a photo of the training program.

When you provide training or other


actions to satisfy competence needs,
how do you evaluate the effectiveness of
those actions? (records)

a) Verify if there is method for evaluating


The method of evaluation is defined in the
effectiveness of training provided, and name of file (Q/YCQP-4017-14-2012). SEE PHOTO
examiner.
#26.
b) Verify of the trainer is the same peron that
conduct evaluation.

Where do you maintain records of


education, training, skills and
experience?

Select three training topics from the training


program, and verify if related training records
are available and fit with the program.

What tools and techniques has the


organization identified as necessary for
product design personnel?

a) Verify if Autocad, Pro/EERP system or any The factory has identified specific design
similar system is applied for design personnel. software such as PRO / E, Autocad and
b) Note revision number of those design tools. solid work.

What records do you have showing that


product design personnel are competent
to design and are skilled in the identified
tools and techniques?

Verify design personal skill matrix and related


certificate / training record.

6.2.2

6.2.2q1b

The factory provided manpower resource


for the QMS, and ERP system for internal
communication, etc.

Human Resources - General

6.2.1

6.2.2q1a

SCORE

Provision of Resources
What resources has the organization
provided to implement and maintain the
QMS and continually improve its
effectiveness?

6.3
6.2.1q1

FINDINGS

RESOURCE MANAGEMENT

6.2
6.1q1a

EVIDENCE TO CHECK

The factory has defined skill matrix for each


level of employee, documented in the file
(Q/YCQP-4017-14-2012). SEE PHOTO
#24.

Competence, Awareness and Training

Can you show me documented


procedures for identifying training needs
and achieving competence of all
personnel performing activities affecting
product quality?

There is an annual training program


documented in the file (Q/YCQP-4017-142012) for the year 20XX, and approved by
the leader in 20XX-01-07. SEE PHOTO
#25.

Yes, records are available. SEE PHOTO


#27.
C

Training of technical people has been


planned in the document (Q/YCQP-4-17-142012) for the current year, for Autocad,
GB2828, ERP system, SEE PHOTO #28.
No record to attest the capability of
employee having skill in PRO / E. for
example.

Check the existence of the procedure, and note Yes, the record of training are available in
doc. nb / rev.
the document (Q/YCQP-4017).
C

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
T6.2.2.2q2

T6.2.2.3q1

T6.2.2.3q2

T6.2.2.4q1

T6.2.2.4q2

T6.2.2.4q3

EVIDENCE TO CHECK

FINDINGS

a) Verify record of training / certificate of


personnel performing key process (for
example).
b) Verify record of training / certificate of
personnel for specific client requirement, note
the specific client is possible.

Training of technical people has been


planned in the document (Q/YCQP-4-17-142012) for the current year, for Autocad,
GB2828, ERP system. SEE PHOTO #28.
No record to attest the capability of
employee having skill in PRO / E, for
example.

What kinds of on-the-job training do you


provide for people in new or changed
jobs? Does this include contract and
agency personnel?

Review the records, if any.

Record of training are available. Contract


and agency are not used in this factory.

How do you inform personnel about the


consequences to the customer of
nonconformity to quality requirements?
(Sample throughout organization)

Select a few workers at the manufacturing area, By meeting, and posting of process files on
and ask them to show the defect part and
site as work instruction and red sign on
explain the consequence of this defective part. specify product/process characteristic. SEE
PHOTOS # 29 & #30.

What process has been established to


motivate employees to
- achieve quality objectives
- to make continual improvements, and
- to create an environment to promote
innovation

a) Any promotion activities?


b) Employee satisfaction survey and record?
c) Are KPIs published at each workplace for
employee to review?

1. Salary increase of 10% to 15%


2. KPIs are published on site.
3. Employee satisfactory survey
(Q/YCQP 4021-05) conducted in 20XX-1120, and summarized in Q/YCQP4021-06.

Does the process include the promotion


of quality and technological awareness
throughout the whole organization?

a) Is the promotion documented and


communicated ?
b) Any evidence records for quality /
technological?

Yes, a promotion is planned to enforce


quality and technological awareness
throughout the whole organization. SEE
PHOTO #31.

What records do you have that


personnel performing specific assigned
tasks are qualified - especially to meet
customer requirements? (See 6.2.2e)

6.3q1b

6.3q1c

a) Is there any questionnaire test for employee Yes, there is questionnaire test applied as
to evaluate their knowledge?
part of test exam. SEE PHOTO #26.

Are the buildings, workspace and utilities


provided appropriate to achieve
conformity to product requirements?
How are they maintained?

a) Visit the facility, specially the condition of how Yes. SEE PHOTO #5, #6 & #17.
product / material are stored.
b) Verify if the factory has a maintenance
program.

What kind of process equipment (both


hardware and software) is necessary to
conform to product requirements? How
is the equipment maintained?

Listed in the factory profile, take photos.

What supporting services (such as


transport or communication) are needed
to ensure that product meets
requirements? How are they
maintained?

Listed in the factory profile and take photos.

What groups are involved in developing


plant, facility and equipment plans?
(Must be multidisciplinary)

Verify if there is map route describing position


of machine, storage of material, moving of
people.

Infrastructure

6.3.1
T6.3.1q1

What process has been established to


measure the extent to which personnel
are aware of the relevance and
importance of their activities and how
they contribute to the achievement of the
quality objectives?
(See 6.2.2d)

6.3
6.3q1a

SCORE

Yes, for client, only need an assembly line.


SEE PHOTOS #32, #33 & #34. The factory
also has a stamping workshop. SEE
PHOTOS #5 & #6.

Yes, the factory use automatic conveyor at


the painting process.
C

Plant, Facility and Equipment Planning


The maintenance department is in charge
of this. There is visible map route and
layout at each workshop. SEE PHOTO #35.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
T6.3.1q2

T6.3.1q3

Yes, the plant layouts optimize material


travel, handling and floor space use, and
facilitate synchronous material flow. SEE
PHOTOS #5 & #6.

What methods are used to evaluate and


monitor the effectiveness of existing
operations?

Record of periodical evaluation of time used to


move material from this location to another
place, a long a certain pathway.

With periodical evaluation of each process.

Can you show contingency plans for


each of the following?
- Utility interruptions
- Labor shortages
- Key equipment failure(s)
- Field returns

a) Verify if there is a documented plan to handle Yes, there is contingency plan for labor
sudden short down in the planning, take photo shortage, key equipments failureetc.
of the plan.
b) Ask
if such situation happen, and what was the
impact.
c)
Does the contingency plan describe
responsibility?

Has the organization defined the


adequate work environment required to
achieve conformity to product
requirements? How is this environment
managed and maintained?

a) Verify is adequate temperature / humidity,


noise, odors, cleanliness, lighting, etc. are
defined as basic condition for work
environment.
b) Verify if those conditions are checked and
recorded.

T6.4.1q1

T6.4.2q1

How are product safety and potential


risks to employees addressed by the
organization?

7.1q3a

7.1q3b

Yes, as required in the procedure.


(Q/YCQP2018-2011)
C

Each machine has user manual visible.


Could better be written with images that
indicate what to do when using it, both at
workshop and testing center.

Does the organization maintain the state


of order, cleanliness and repair needed
for products and manufacturing
processes? (Verify throughout audit)

Yes, it is clean and well organized at the


stamping plant and assembly plant.
C

PRODUCT REALIZATION

7.1

7.1q2

Work Environment

7
7.1q1

SCORE

Contingency Plans

6.4
6.4q1

FINDINGS

a) Is the pathways visible defined for material


storage, machines position and peoples
rotation? Take photo.
b) Is the direction of moving clearly marked?

6.3.2
T6.3.2q1

EVIDENCE TO CHECK

Can you show that plant layouts


optimize material travel, handling and
floor space use, and facilitate
synchronous material flow?

Planning of Product Realization


Are the processes needed for product
realization identified?

Verify if there a process map or flow chart for


product realization and note doc nb / rev.

Yes, the guidelines are described in the


procedure (Q/YCQP2004-2011), under
responsibility of production department.

Is the planning of product realization


Check the relation between this process with
consistent with the requirements of the others process. Define where it gets input and
other processes of the QMS? Verify
where its output goes.
there are no inconsistencies or conflicts
between quality system procedures.

Defined with previous process as marketing


dev, order review, product development,
and with next process as continuous
improvement.

Where in the product realization process a) Verify if the step for the identification of product
do you determine the quality objectives requirements are planned.
and requirements for products?
b) Check if there a record as example of any
product.

Yes, it planned, as for example of the


development of product / project #198911E. SEE PHOTO #36. The identification is
planned with the output recorded in the
form (Q/YCQP-4003-32-2012).

When planning for product realization,


how do you establish processes,
documents, and provide resources
specific to the product?

The planning of production realization is


documented as project planning such as for
the case of project #198911-E. SEE
PHOTO #36.

a) Verify if there is planning.


b) Check if there a record as example of any
product.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
7.1q3c

7.1q3d

7.1q4

EVIDENCE TO CHECK

How do you determine verification,


validation, monitoring, inspection and
test activities specific to the product, and
the criteria for product acceptance?

FINDINGS
The stage of verification, validation and
monitoring of production realization are
documented as project planning such as for
the case of project #198911-E. SEE
PHOTO #36.

What records exist showing that both the Check if there a record as example of any
realization processes and the product
product.
meet requirements?

Records of the four stages are available,


example of the project #198911-E.

What are the outputs of product


Verify if there a documented planning.
realization planning? Are they in a form
suitable for the organization?

Yes, forms are used to record output of the


product realization.

7.1.1
T7.1.1q1

a) Verify if there is planning defining method for


verification, validationetc.
b) Check if there a record as example of any
product.

Yes, it included, example of the project


#198911-E

7.1.2

Acceptance Criteria
Where are acceptance criteria defined? Check a record of such acceptance criteria, and Acceptance criteria are defined for each
When required, does the customer
check if there is an evidence that it was approved stage as guideline to accept the completion
approve them?
by the customer.
of each stage
When attribute data sampling, is the
acceptance level zero defects?

Check the inspection criteria.

7.1.3
T7.1.3q1

T7.1.4q3

T7.1.4q5

7.2.1q1c

Yes, the acceptance level zero defects is


applied.

Change Control
What process is there to control and
react to changes that impact product
realization?

Changes that happen during process


development are monitored according to
guidelines detailed in the procedure.
(Q/YCQP-2003-2011)

Are changes validated before


implementation?

Yes, changes re-validated by a group of


team members before to process.

Do you have evidence that any


additional verification/identification
requirements required by the customer
are met?

Yes, records are available.

Customer-Related Processes

7.2.1

7.2.1q1b

By customer property (Q/YCQP2005-2011).

7.2
7.2.1q1a

Confidentiality
How does the organization ensure the
confidentiality of customer-contracted
products, projects under development,
and related product information?

7.1.4
T7.1.4q1

Planning of Product Realization Supplemental


Does the quality plan include customer Review the quality plan
requirements and reference to technical
specifications?

T7.1.2q1

T7.1.2q2

SCORE

Determination of Requirements Related to the Product


Does the organization determine
requirements specified by the customer,
including the requirements for delivery
and post-delivery activities?

Yes, the organization determines


requirements specified by the customer,
including for delivery and PPM, as required
by the procedure (Q/YCQP3001-2008) and
document them in (Q/YQCP-4003-322012). SEE PHOTO #14.

Does the organization determine not


stated by the customer but necessary for
specified or intended use, where known?

Yes, it included in the document (Q/YQCP4003-32-2012). SEE PHOTO #14.

Does the organization determine


statutory and regulatory requirements
related to the product?

Yes, it is included in the document


(Q/YQCP-4003-32-2012). SEE PHOTO
#14.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
7.2.1q1d

T7.2.1.1q1

7.2.2q1b

7.2.2q4

T7.2.2.2q1

Does the organization meet customer


requirements for designation,
documentation and control of special
characteristics?

Yes, all requirements are meet according to


the PSW signed by CVGS.

A feasibility review is conducted involving all


departments, and each department will
review product requirements and sign to
conform that they have the capability to
meet client requirements.

How do you ensure that product


requirements are defined and reviewed
before committing to supply product?

The procedure Q/YCQOP-2003-2011 is


been developed to required a mandatory
step to conduct the feasibility before
launching the project.

When product requirements are


changed, how do you ensure that
relevant documents are changed and
that relevant personnel are made aware
of the changes?
What documents do you have that show
investigation and confirmation of
manufacturing feasibility in the contract
review process for proposed products,
including risk analysis?

According to change procedure. There are


a few examples of how changes were
implemented.

7.3.1q2b

7.3.1q2c

Customer Communication
Procedure (Q/YCQP2021-2011), via
customer representative.

Do your customers require information to


be communicated in specific languages
and/or formats?
If so, how do you meet those
requirements?

Yes, specific format to use, and in English


must of the time. The factory has people
with English capability, such as Ms. XXX,
the Customer Rep.

Design and Development

7.3.1

7.3.1q2a

Yes, there are few case where feasibility


were conducted.

What method(s) are used to


communicate with customers regarding
- product information
- enquiries, contracts, or order handling
including amendments?
- feedback, including customer
complaints

7.3
7.3.1q1

SCORE

Review of Requirements Related to the Product


What kind of review is done to ensure
that the organization has the ability to
meet requirements before committing to
supply product?

7.2.3
7.2.3q1

FINDINGS
Yes, it is included in the document
(Q/YQCP-4003-32-2012). SEE PHOTO
#14.

7.2.2
7.2.2q1a

EVIDENCE TO CHECK

Does the organization determine any


additional requirements determined by
the organization.

Design and Development Planning


Can you explain to me the process used
by the organization to plan and control
the design and development of product?

There is a procedure Q/YCQP-2003-2011


for development of process according to
APQP / PPAP.

What are the stages in the design and


development process?

There are four stages for the development,


for example of the project CVGS (OEM), for
part 198911-E, the plan is documented in
Q/YCQP4003-04.

Are the review, verification and validation


activities appropriate to each design and
development stage planned?

Yes, there are review, verification and


validation at each stage. Example of part
198911-E, the plan is documented in
Q/YCQP4003-04.

Are design and development


responsibilities and authorities defined?

Yes, responsibility is well defined. Example


of part 198911-E, the plan is documented in
Q/YCQP4003-04.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
7.3.1q3

T7.3.1.1q1

How does the organization ensure


effective communication and clear
assignment of responsibility between
different groups involved in design and
development?
Do you use a multidisciplinary approach
to prepare for product realization? Does
it include:
- development/finalization and
monitoring of special characteristics
- development and review of FMEAs,
including actions to reduce potential
risks,
- development and review of control
plans.

7.3.2
7.3.2q1a

7.3.2q2

EVIDENCE TO CHECK

FINDINGS
Yes, responsibilities are well defined.
Example of part 198911-E, the plan is
documented in Q/YCQP4003-04.

SCORE

NOTE A multidisciplinary approach typically


Yes, there is multidisciplinary approach,
includes the organization's design, manufacturing, with mission to develop and finalize special
engineering, quality, production and other
characteristic, record are available
appropriate personnel.
C

Design and Development Inputs


What are the design inputs relating to
each of the following product
requirements?
a) functional and performance
requirements
b) applicable statutory and regulatory
requirements
c) where applicable, information derived
from previous similar designs, and
d) other requirements essential for
design and development.
Where are they recorded?
How & when are the design inputs
reviewed for adequacy?

The factory does not have design


responsibility.

N/A

The factory does not have design


responsibility.
N/A

7.3.2q3

How does the organization ensure that


requirements are complete,
unambiguous and dont conflict with
each other?

7.3.2.1
T7.3.2.1q1

NOTE: Special characteristics (see 7.2.1.1) are


included in this requirement.

The factory does not have design


responsibility.
N/A

Product Design Input


Where are product design input
requirements documented?
(including the following:
- contract reviews of requirements such
as special characteristics, identification,
traceability and packaging
- a process to deploy information gained
from previous design projects,
competitor analysis, supplier feedback,
internal input, field data, and other
relevant sources, for current and future
projects of a similar nature
- targets for product quality, life,
reliability, durability, maintainability,
timing and cost.)
Can you show me they are reviewed?

7.3.2.3

The factory does not have design


responsibility.

N/A

Special Characteristics

T7.3.2.3q1a Can you show me that all special


characteristics are identified and
included in drawings, FMEAs, control
plans, and operator instructions?

Special characteristics are defined in the


form (Q/YCQP4003-08).

T7.3.2.3q1b Are the customer-specified (or


equivalent) symbols used?

Yes, customer-specified symbols are used


in PFD, PFMEA, CONTROL PLAN and
work instruction. SEE PHOTOS #29 & #30.

Yes, customer-specified symbols are used


in PFD, PFMEA, CONTROL PLAN and
work instruction. SEE PHOTOS #29 & #30.

T7.3.2.3q1d Do they include process steps that affect


special characteristics?

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
7.3.3
7.3.3q1

T7.3.3.1q1

EVIDENCE TO CHECK

FINDINGS

Design and Development Outputs


How can design and development
outputs be verified against the inputs?
(see 7.3.5q1) Are these outputs
approved prior to release?

Outputs of development are verified by


dimensional checking, and compared to
requirements. Records are maintained.

Can you show that the product design


outputs include

Not applicable.

- design FMEA, reliability results


- product special characteristics, specifications
- product error-proofing, as appropriate
- product definition including drawings or
mathematically based data
- product design reviews results, and
- diagnostic guidelines where applicable
Are the outputs expressed in terms that can be
verified and validated against product design input
requirements?

T7.3.3.1q1

Can you show that the manufacturing


process design outputs include
- specifications and drawings,
- manufacturing process flow chart/ layout,
- manufacturing process FMEAs,
- control plans,
- work instructions,
- process approval acceptance criteria,
- data for quality, reliability, maintainability and
measurability
- results of error-proofing activities, as appropriate,
and
- methods of rapid detection and feedback of
product/manufacturing process nonconformities.

7.3.4
7.3.4q1a

SCORE

N/A

The manufacturing process design output shall be


expressed in terms that can be verified against
manufacturing process design input requirements
and validated.

Yes, the outputs include all the data, full


dimension report (Q/YCQP-4003-13), PFD,
PFMEA, Control plan (Q/YCQP-4003-30),
Ppk (Q/YCQP-4003-18), etc.

Design and Development Review


At what stages of design and
development do you perform reviews to
evaluate if the results meet
requirements? (See 7.3.1q2b)

The review is performed to evaluate the


progress of the APQP planning. It can be
done at each stage.
C

Can you show me some problems that


have been identified and actions
proposed at these reviews?
7.3.4q2

7.3.4q3

What functions are represented at these


reviews?
At each stage, are all functions
concerned with that stage represented?

All function are represented.

Can you show me records of the results


of the reviews and any necessary
actions taken?

SEE PHOTO #39.

7.3.5
7.3.5q1

7.3.5q2

7.3.6q3

Design and Development Verification


What verification activities are performed
to ensure that the design and
development outputs have met the input
requirements? (See 7.3.3q1)

Verification is performed by checking size,


functionality and visual appearance and
comparing it to requirements in the drawing.

Can you show me records of the results


of the verification activities and resulting
actions?

SEE PHOTO #40.

7.3.6
7.3.6q1

Design and Development Validation


What design and development validation
activities are performed to ensure that
the product is capable of meeting the
requirements for the intended use?

The validation is done by the client, after


sending the PPAP document and sample to
them. The client will send a PSW as sign of
approval.

Can you show me records of the


validation activity results and any followup actions?

SEE PHOTO #41.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
T7.3.6.1q1

7.3.7
7.3.7q1

7.3.7q2

EVIDENCE TO CHECK

Is design and development validation


performed in accordance with customer
requirements, including program timing?

Control of Design and Development Changes


How are design and development
changes identified? Where are the
records kept?

Changes could be identified from internal or


from customer, and will be handled
according to the procedure (Y/QCDP20102011)

Are changes reviewed, verified,


validated, and approved before
implementation?

Yes, changes are reviewed, verified,


validated, and approved before
implementation. Records are available.

How do you ensure that purchased


product conforms to specified purchase
requirements?

The factory has a procedure as guideline


for ensuring the conformity of product
(Q/YCQP2019-2011).

How do you determine the type and


extent of control applied to the supplier
and the purchased product?

The factory has a master list of qualified


supplier recorded in the form Q/YCQP-401903. SEE PHOTO #42.

How do you evaluate and select


suppliers based on their ability to supply
product in accordance with the
organizations requirements?

The factory will conduct investigation of the


supplier and record it in the Q/YCQP-401905.

Can you show me the criteria for


selection, evaluation and re-evaluation
of suppliers?

Yes, records are available.

Can you show me records of the results


of supplier evaluations and any
necessary actions? Verify that criteria
have been met.

Yes, recorded in the form Q/YCQP-401906, conducted in 20XX-01-20 as yearly


evaluation approved by General Manager,
with hand signed by himself. SEE PHOTO
#43.

What evidence is there that all


purchased products or materials used in
product conform to regulatory
requirements?

The factory conduct monthly evaluation of


each supplier about QUALITY (40),
DELIVERY(20), SERVICE(20) and
PRICE(10), and data is recorded
automatically in the ERP system in the form
Q/YCQP-4019-07.

7.4

PURCHASING
Purchasing Process

7.4.1q2

7.4.1q3

7.4.1q4

7.4.1q5

T7.4.1.1q1

T7.4.1.2q1a What supplier development actions are


being taken toward the goal of supplier
conformity with TS 16949?

T7.4.1.2q1b Do your suppliers quality management


systems conform with ISO 9001:2000?

T7.4.1.2q2

SCORE

7.4.1
7.4.1q1

FINDINGS
Yes, the customer will conduct the
validation .

Are all of your suppliers registered to


ISO 9001:2000?
If not, do you have written waivers from
applicable customer(s)?

Yes, two suppliers have provided


commitment to achieve the goal of TS
certification by the end of the year 20XX.
One out of twenty-one has passed the TS,
SEE PHOTO #44.

NOTE: The prioritization of suppliers for


Yes, 13 suppliers are certified to ISO 9001,
development depends upon, for example, the
and those suppliers are more important.
suppliers quality performance and the importance
of the product supplied.

Yes, 13 suppliers are certified to ISO 9001,


and those suppliers are more important.
C

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
T7.4.1.3q1

7.4.2
7.4.2q1a

7.4.2q1b

7.4.2q1c

7.4.2q2

T7.4.3.1q1

T7.4.3.2q1

7.5.1q1c

Yes, reviewed the order number


2014030757 and all information are
included.

Do require any qualification of supplier


personnel? If so, can you show where
the requirement is documented?

Yes, completed.

Do you have any QMS requirements of


your suppliers? If so, can you show me
where they are required?

Yes, documented.

How does the organization ensure the


adequacy of purchasing requirements
before communicating them to the
supplier?

Communication is done by email, or


physically with sign from supplier in the
purchase order.

Incoming inspections are conducted


following criteria defined in file (Q/YCQP 3023-03-2012), SEE PHOTO #45.

Must include one or more of following:


- evaluation of supplier statistical data
- receiving inspection and/or testing
- second- or third-party audits of suppliers, along
with records of acceptable quality
- laboratory part evaluation
- another method agreed with the customer

Incoming inspections are conducted


following criteria defined in file (Q/YCQP 3023-03-2012). SEE PHOTO #45. And
records are maintained in form (Q/YCQP 4023-03-2012). SEE PHOTO #46.

Must include the following indicators:


- delivered product quality
- customer disruptions including field returns
- delivery schedule performance (including
incidents of premium freight)
- special status customer notifications related to
quality or delivery issues

The factory conducts monthly evaluation of


each supplier about QUALITY (40),
DELIVERY(20), SERVICE(20) and
PRICE(10). Data is recorded automatically
in the ERP system in the form (Q/YCQP4019-07). SEE PHOTO #47.

Verification of Purchased Product


What inspection or other activities are
used to ensure that purchased product
meets your purchasing requirements?
What processes are in place to assure
the quality of purchased product?

How do you monitor supplier


performance?

Production and Service Provision

7.5.1

7.5.1q1b

SCORE

Purchasing Information

7.5
7.5.1q1a

FINDINGS
Yes, all information is included in the plan.
The factory has a written program to
monitor suppliers.

Do orders/contracts include
requirements for approval of product,
procedures, processes and equipment?

7.4.3
7.4.3q1

EVIDENCE TO CHECK

Do your customer(s) specify supplier(s)


in contracts/ purchase orders?
This includes products, materials,
services, tooling, & gages, etc.
If so, can you show that the customerdesignated sources are being used as
required?

Control of Production and Service Provision


When carrying out production (or
service) is information that describes the
characteristics of the product available?

Yes, information that describes the


characteristics of the product available in
work Instruction, for example of part
752116400.

When carrying out production (or


service) are appropriate work
instructions available if needed? (See
7.5.1.2)

Yes. SEE PHOTO #29.

When carrying out production (or


service) is suitable equipment used for
carrying out production (or service)?

Yes, equipment is available.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
7.5.1q1d

7.5.1q1e

T7.5.1.1q2

T7.5.1.1q3

T7.5.1.1q4

When carrying out production (or


service) are appropriate kinds of
monitoring and measurement done?
(See 8.2.4)

Yes, necessary monitoring is conducted,


according to in-process inspection.

T7.5.1.2q2

T7.5.1.3q2

Review control plans to ensure they:


- list controls used for manufacturing process
control
- include methods for monitoring of control of
special characteristics
- include customer-required information, if any

Yes, there is control plan developed for


each product in which a PPAP is been
required. SEE PHOTO #48.
C

Yes, there is a control plan developed for


each product in which a PPAP has been
required. SEE PHOTO #48.

Can you show how the control plans


take into consideration design FMEA
and process FMEA information?
(See Annex A)

Yes, there is control plan developed for


each product in which a PPAP is been
required. SEE PHOTO #48.

Can you show that specified reaction


plans have been carried out when a
process becomes unstable or not
statistically capable?

SEE PHOTO #48.

C
Work Instructions

Do all employees responsible for


Verify throughout audit.
processes that impact product quality
have documented work instructions? Are
they accessible for use at the
workstation?
How are the work instructions
developed?

Yes. SEE PHOTOS #29 & #30.


C
SEE PHOTOS #29 & 30.
C

Verification of Job Setups


Can you show me records of job setups
that are being performed?
Do they occur at the initial run of a job,
material changeover, or job change?

Yes, records are written. See photo of U771066-MJ-01.

What work instructions do you have for


job setup personnel?

Yes. SEE PHOTOS #29 & #30.

7.5.1.4
T7.5.1.4q1

Can you show me control plans for both


pre-launch and production?

7.5.1.3
T7.5.1.3q1

SCORE

Control Plan
Can you show me control plans for
system, subsystem, and component/
material levels for product supplied?

7.5.1.2
T7.5.1.2q1

FINDINGS
Yes, gages are available.

7.5.1.1
T7.5.1.1q1

EVIDENCE TO CHECK

When carrying out production (or


service) are appropriate gages, etc.
used in production (or service)? (See
7.6)

C
Preventive and Predictive Maintenance

How do you identify key process


equipment? Can you walk me through
your total preventive maintenance
system?

Verify that the TPM system includes the following:


- planned maintenance activities
- packaging and preservation of equipment,
tooling and gauging
- availability of replacement parts for key
manufacturing equipment
- documenting, evaluating and improving
maintenance objectives

There is a procedure Q/YCQP-2006-2011,


B/0 that defined key process equipment in
section 3.1 and provided guideline for their
maintenance and reparation.
C

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
T7.5.1.4q2

7.5.1.5
T7.5.1.5q1

T7.5.1.5q2

T7.5.1.5q3

T7.5.1.5q4

T7.5.1.5q5

T7.5.1.5q6

EVIDENCE TO CHECK

What predictive maintenance methods


do you use? Can you demonstrate that
predictive maintenance has resulted in
continual improvement of the
effectiveness and efficiency of
production equipment?

FINDINGS
Accident occurrence are recorded in the
form Q/YCQP4006-08 and their root cause
is investigated in the form Q/YCQP-4006-06
(B/0). See example of machine #YC29.
Data collected are not properly used to
develop an efficient predictive action.

SCORE

Management of Production Tooling


What resources have the organization
provided for tool and gage design,
fabrication and verification activities?

The factory has capability for tooling design


and production, but will also assigned the
design and production responsibility to an
external supplier.

Does the production tooling


management include maintenance and
repair facilities and personnel?

There is procedure for Q/YCQP-2007-2011


for the maintenance of mold, fixtures,
tooling. Specified in the section 3.1

Do you have space for storage, recovery


and set-up of tooling?

Yes, the factory has special place for the


storage of tooling.

Do you have perishable tool change


programs?

There is accumulation time of use in the


record CV of each tooling, for example
345844-SHEET2-M1-01, with indication of
some per production and its accumulate,
but not standard number of time. No
reaction of what do to after reach the time.

Does tool design modification


documentation, including engineering
change level, tool modification and
revision to documentation monitored?

Yes, controlled by technical department.

Tool identification, defining the status,


such as production, repair or disposal.

Tool are well identified and protected. SEE


PHOTOS #17 & #49.

C
T7.5.1.5q3

Are any tooling management activities


outsourced? If so, how are these
activities monitored?

7.5.1.6
T7.5.1.6q1

Yes, some tolling is outsourced.


C

Production Scheduling
Can you demonstrate that customer
scheduling requirements (such as just-intime) are being met?

7.5.3

Yes, the factory uses public board to display


the status of each order, with principle of
JIT.

Identification and Traceability


How do you identify product throughout
your processes? Verify in production,
storage, segregation areas, etc.

Products are identified as required in the


procedure (Q/YCQP2008-2011).

How is product inspection status


identified? Verify in production, storage,
segregation areas, etc.

Each product has label to indicate its detail


and status. SEE PHOTO #50.

Can you show me unique identification


records for products requiring
traceability?

SEE PHOTO #50.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
7.5.4
7.5.4q1

7.5.4q2

T7.5.4.1q1

T7.5.5.1q2

7.6q2

7.6q3a

7.6q3c

7.6q3e

7.6q4

7.6q5

7.6q6

SCORE

Customer Property
Yes, the factory use customer drawing,
tooling as customer property.

How do you ensure that customerowned property is identified, verified,


protected, and safeguarded?

Customer property is controlled as defined


in the procedure (Q/YCQP2005-2011).

How are customer-owned tools and


equipment identified?

Customer-owned tools and equipment


identified are identified with customer name
and part number.

N/A

Preservation of Product, Storage and inventory


Can you walk me through your inventory
management system?
How does the system optimize inventory
turns over time and assure stock
rotation?
How is obsolete product controlled to
prevent its unintended use or delivery?
(See 8.3).

7.6
7.6q1

FINDINGS

Do you use any customer-owned


property, such as product, packaging,
drawings, tooling, gages, etc
If so, ask questions below.

7.5.5
T7.5.5.1q1

EVIDENCE TO CHECK

Inventory is conducted via ERP system that


can provide in real-time the status of stock,
and send information to purchase
department.

Obsolete product is stored in "red" room to


avoid them to be mixed with others.
C

Control of Monitoring and Measuring Devices


How do you determine the
measurements to be taken and the
measuring equipment needed to
demonstrate conformity with
requirements?
What process is in place to ensure that
measurements are taken per the
requirements?

Measuring devices are controlled according


to procedure (Q/YQCP2020-2011).
C
A calibration program is in place to ensure
it. The factory is experiencing an Excel
support tools to alert in the approach of
expiration date, but formulas in this system
are wrongly defined.

How do you ensure that measuring and


test equipment is calibrated or verified
proper frequencies with NIST traceable
standards? If no such standards exist,
where do you record the basis used for
calibration or verification?

External calibration is conducted as


planned, and are traceable to external
national institute.

How are measuring tools identified to


enable the calibration status to be
determined?

With tags visible at each device.

How do you ensure that measuring its


test equipment is protected from
damage and deterioration during
handling, maintenance and storage?

Equipment is well protected in the testing


center under acceptable room condition.
SEE PHOTOS #18, #19, #20, #21, #22 &
#23.

When equipment is found to be out of


calibration, how do you assess and
record the validity of the previous
measuring results?

There is no specific plan as reaction plan in


the case of out of calibration found, and
others damage.

NC

What actions do you take on the


equipment and any product affected?

There is no specific plan as reaction plan in


the case of out of calibration found, and
others damage.

Can I see your records of the results of


calibration and verification?

Yes, record of in-house are available by


computerized. No signature of the person
assigned for the in-house calibration.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
7.6q7

T7.6.1q1

T7.6.1q2

FINDINGS

SCORE

Do you use computer software for


monitoring and measurement? If so, is
its ability to perform that function
confirmed prior to initial use and
reconfirmed as necessary?

External calibration is conducted as


planned, and are traceable to external
national institute, while calibration in house
does not provide evidence of such
traceability to that external national institute.

Can you show me R&R studies for each Is there other statistical studies analyzing the
type of measuring and test equipment
variation in measurement & test results?
system referenced in the control plan?

GR&R is conducted for related equipment


used to conduct product to which PPAP
were required.

Do the methods and acceptance criteria


conform to those in customer reference
manuals on MSA or does the customer
approve them?

Yes, the AIAG format is no longer used.

7.6.2
T7.6.2q3

T7.6.2q6

EVIDENCE TO CHECK

Calibration / Verification Records.


Can you show that calibration records
include equipment identification,
including the measurement standard
against which the equipment is
calibrated.

Calibration record are available both for


external. SEE PHOTO #51. Record for inhouse calibration is also available, but with
no proper traceability of standard used.

Statements of conformity to specification


after calibration / verification.

SEE PHOTO #51.

C
T7.6.2q7

Notification to the customer if suspect


product or material has been shipped?

Not planned, but has never happened.


I

7.6.3
T7.6.3.1q1

T7.6.3.1q2

T7.6.3.2q1

T7.6.3.2q2

Laboratory Requirements
Does the organization have an internal
laboratory?
If so, can you show a documented
laboratory scope including its capability
to perform inspection, test, or calibration
services?
Where
are laboratory technical
requirements specified for
- adequacy of laboratory procedures
- competency of the laboratory
personnel
- testing of the product,
- capability to perform these services
correctly, traceable to the relevant
process standard, and
- review of the related records
Have these requirements been
implemented?
Can you show me laboratory scope(s)
for external/commercial/independent
laboratory facilities that include the
capability to perform the required
inspection, test or calibration?
Can I see evidence that each laboratory
is either accredited, or is acceptable to
the customer(s)?

The factory has testing center, not a


laboratory, SEE PHOTO 19, 20, 21, 22, 23.
C

Adequacy of listable procedure with


images, and competency of lab people is
not visible. Not visible is also the capability
to perform services correctly and traceable
to respective standard.
I

The lab is for internal use, not external or


commercial. There is no scope.
N/A
The lab is for internal use, not external or
commercial. There is no scope.
N/A

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
8

T8.1.1q1

General
Have appropriate statistical tools for
each process been determined and
included in the control plan? (See
7.5.1.1)

T8.2.1.1q1

8.2.2q2

8.2.2q3

8.2.2q4

Appropriate statistical tools for each


process has been determined in the
procedure (Q/YCQP2024-2011).

Monitoring and Measurement


Customer Satisfaction
How do you obtain information about
customer perception as to whether the
organization has met customer
requirements? How is this information
used?

The organization defined a plan to obtain


customer feedback in the (Q/YCQP20242011) through customer satisfaction survey.
The information is used as input to
management review meeting.

What realization process performance


Do they include at least:
indicators are used to monitor customer - delivered part quality performance
satisfaction?
- customer disruptions including field returns
- delivery schedule performance (including
incidents of premium freight), and
- customer notifications related to quality or
delivery issues

Client complaint log and customer


satisfaction surveys are used, including
internal OTD.

How do you monitor manufacturing


processes to demonstrate compliance
with customer requirements for product
quality and process efficiency?

The manufacturing is monitored with daily


rate evaluation and at some process with
SPC system.

8.2.2
8.2.2q1

Knowledge of Basic Statistical Concepts

8.2

T8.2.1.1q1

Yes, appropriate statistical tools for each


process has been determined in the
procedure (Q/YCQP2024-2011), where
SPC are used at process, and graphical
statistic of conformity rate applied to each
process and result displayed. SEE PHOTO
#15.

How does the organization ensure that


basic statistical concepts are understood
and utilized throughout the organization?
Verify throughout audit,

8.2.1
8.2.1q1

SCORE

Identification of statistical tools

8.1.1
T8.1.2q1

FINDINGS

MEASUREMENT, ANALYSIS AND IMPROVEMENT

8.1
8.1.1

EVIDENCE TO CHECK

Internal Audit
Are internal audits being conducted at
planned intervals? Do they determine
whether the QMS conforms to the
requirements of ISO 9001 and to the
other requirements established by the
organization? Do they determine
whether the QMS is effectively
implemented and maintained?

Reviewed records to demonstrate


conformance.

Can you show me an audit plan that


takes into consideration the importance
of the processes and areas to be
audited, and the results of previous
audits?
Where are the audit criteria, scope,
frequency and methods defined?

Yes, there is the audit plan described in


Q/YCQP-4022-01 (a/0), nb. 2013001, and
approved in 20XX-02-09.

Can you demonstrate that selection of


auditors and the conduct of audits are
objective and impartial, and that auditors
dont audit their own work?

The factory has 12 auditors. And it requires


to avoid auditors to be organized
independently to their process.

Yes, the scope of the audit is described in


the Q/YCQP-4022-01 (a/0).

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
8.2.2q5

8.2.2q6

T8.2.2.1q1

EVIDENCE TO CHECK

FINDINGS

Can you show me your internal audit


procedure? Can you show me the
records of internal QMS audits?

Yes, records of internal audit are available,


see photo Q/YCQP-4022-08.

Who ensures that actions are taken to


eliminate detected nonconformities and
their causes? Are they being taken care
of in a timely manner? (verify with
records)

The MR is in charge to ensure that NCF are


solved, and recorded maintained, see photo
, Report nb. 2013-NA-001 for article
TS16949-7.3.6

Do you have audit records showing that


the entire QMS is being audited?

Yes, records are available.

SCORE

C
T8.2.2.2q1

T8.2.2.3q1

T8.2.2.4q1

T8.2.2.4q2

T8.2.2.5q1

Do you have records showing that each


manufacturing process is being audited
to determine its effectiveness?

Yes, each process was audited.

Are there records showing that products


are being audited at appropriate stages
of production and delivery? Do the
audits verify conformity to all specified
requirements?

Yes.

Can you show me an annual audit plan?


Does it show that audits cover all QMS
processes, activities and shifts?

Yes.

Is there evidence that audit frequency is


increased due to nonconformances or
customer complaints?

No, not stated in the procedure.

How do you determine competence of


internal auditors to audit the
requirements of TS 16949? (See 6.2.2.2
also customer specific requirements).

Certificate of audit is used as evidence.

8.2.3
8.2.3q1

8.2.3q2

8.2.3q3

T8.2.3.1q1

T8.2.3.1q2

Monitoring and Measurement of Processes


What methods are used to monitor and
measure the QMS processes?

Can you show that they have achieved


the desired results?

The internal audit is used as method to


monitor and measure the QMS processes,
as required in the procedure (Q/YCQP20222011). Apart from that, each process has
KPIs assigned with a monitoring plan and
responsible.

Some processes has KPIs displayed, with


acceptable result such as for Supplier
Monitoring, while customer satisfaction
survey shows some need in improvement.

When the desired results are not


achieved, what actions are taken to
ensure that the product meets
requirements?

The result was reviewed during a


management review meeting, and actions
are defined for improvement.

Can you show me process studies that


have been performed on new
manufacturing processes?

SEE PHOTO #52.

Can you show examples of results of


process studies being documented with
specifications? Are they used for
instructions?

SEE PHOTO #52.

N/A

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
T8.2.3.1q4

T8.2.3.1q5

8.2.4q2

8.2.4q3

FINDINGS
Yes, there are record that show that
process capability was evaluated and
approved by the client, thought PSW, see
the case of the client CVSG.

May I have a copy of the process flow


diagram and control plan for (mfg.
process) to review the production line
with? Review for adherence to specified
requirements.

The copy of PFD, and Control Plan are


available.

8.2.4
8.2.4q1

EVIDENCE TO CHECK

Do records show that manufacturing


process capability or original customerapproved performance is being
maintained?

SCORE

Monitoring and Measurement of Product


What characteristics are checked to
verify that product requirements have
been met?

Characteristics to check are clearly


documented at various, check plan, for IQC,
IPQC and FQC, as required in procedure
(Q/YCQP2023-2011).

At what stages of the product realization


process do monitoring and measuring
activities take place?

At incoming Inspection (IQC), In-process


inspection (IPQC) and final inspection
(FQC), mainly. SEE PHOTO #45.

How is evidence of conformity with


acceptance criteria maintained?

Record are available. SEE PHOTO #46.

C
8.2.4q4

8.2.4q5

T8.2.4.1q1

T8.2.4.2q1

Can you show me records that indicate


who has authorized release of product to
the next stage of the process?

Record are available, SEE PHOTO #46

How do you ensure that product is not


NOTE: When selecting product parameters to
released until the all requirements have monitor compliance to specified internal and
been met? If product must be released external requirements, the organization
prior to this, how is it approved?
determines the types of product characteristics,
leading to
- the types of measurement
- suitable measurement means, and
- the capability and skills required

At incoming inspection (IQC), in-process


inspection (IPQC) and final inspection
(FQC), mainly. Work Instruction for the
implementation of such operation are
available. SEE PHOTO #45.

Can you show me layout inspection and NOTE: Layout inspection is the complete
The layout inspection is documented. SEE
functional verification results?
measurement of all product dimensions shown on PHOTO #45.
Do they address applicable customer
the design records.
specifications and correlate with the
control plan requirements?
Are results available for customer
review?
Do you provide parts designated by
If so can you show that you have:
customer(s) as appearance items? If so, - appropriate resources including lighting for
what support to you have?
evaluation
- masters for color, grain, gloss, metallic brilliance,
texture, distinctness of image (DOI), as
appropriate
- maintenance and control of appearance masters
and evaluation equipment, and
- verification that personnel making appearance
evaluations are competent and qualified to do so

8.3
8.3q1

Yes, there are master for comparison, and


these master (standard) product are
approved by the client and put with proper
identification to avoid mixing with others
product.
C

Control of Nonconforming Product


How do you ensure that nonconforming
products are identified and controlled to
prevent unintended use or delivery?
(Verify product throughout audit)

The procedure Q/YCQP2024-2011 is been


developed as guideline to control nonconform product

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
8.3q2

8.3q3

8.3q4

8.3q5

8.3q6

When you have nonconforming product,


what methods do you use to deal with it?

a) by taking action to eliminate the detected


nonconformity
b) by authorizing its use, release or
acceptance under concession by a relevant
authority and, where applicable, by the
customer
c) by taking action to preclude its original
intended use or application.

Records are available, product is stored


with label at segregate area. SEE PHOTOS
#53 & #54.

When nonconforming product is


corrected, can you demonstrate that it is
re-verified to ensure it conforms to
requirements?

Yes, records are available.

When nonconforming product is


detected after shipment, what actions
are taken, such as containment?
(Verify corrective action records)

Yes, actions are defined as to inform the


client.

Control of Reworked Product


Yes, there is special place for the
reworking, specially for welding reworking.

Customer Information
Do you have evidence that customers
are promptly notified if nonconforming
product is shipped?

No evidence saved.
I
Analysis of Data

What data is collected and analyzed to


demonstrate the suitability and
effectiveness of the QMS and to
evaluate where continual improvement
of its effectiveness can be made?

Internal / external PPM, OTD record,


supplier performance evaluation, NCF from
internal audit, amounts others KPIs
assigned, and customer satisfaction are
collected.

What information does this analysis


provide relating to:
- customer satisfaction (See 5.6)
- conformity to product requirements
(See 5.6)
- characteristics and trends of processes
and products (See 5.6)
- suppliers (See 7.4.1)

Internal / external PPM, OTD record,


supplier performance evaluation, NCF from
internal audit, amounts others KPIs
assigned, and customer satisfaction are
collected.

8.4.1
T8.4.1q1

Can you show me instructions for


rework? Do they include re-inspection
requirements? Are they accessible and
utilized?

8.4
8.4q1

SCORE

Can you show me records of


nonconforming product and any actions
taken? Are there any records of
concessions obtained?

8.3.3
T8.3.3q1

FINDINGS
The procedure Q/YCQP2024-2011 is
available and defines responsibilities.

8.3.2
T8.3.2q1

EVIDENCE TO CHECK

Can you show me your documented


procedure defining the controls for
dealing with nonconforming product?
Does it include related responsibilities
and authorities?

Analysis and Use of Data


How do you compare trends in quality
and operational performance with
progress toward objectives?
Does the comparison lead to action to
supporting the following?
- development of priorities for prompt
solutions to customer-related problems
- determination of key customer-related
trends and correlation for status review
decision-making and longer term
planning
- an information system for the timely
reporting of product information arising
from usage.

Data is used to compare trends in monthly /


annual basis and to display opportunities
from improvements. Decisions are taken
during management review meetings.

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES

EVIDENCE TO CHECK

8.5

Improvement

8.5.1

Continual Improvement

8.5.1q1

T8.5.1.1q1

T8.5.1.2q1

Can you demonstrate that


Organizations QMS effectiveness
continually improves?
What tools do you use?
(See 5.6, 8.2.2, 8.4, 8.5.2, 8.5.3)
Where has Organization defined a
process for continual improvement?

The internal audit is used a basic tool to


demonstrate that the organization's QMS
run effectively.

Can you show that CI efforts focus on


control and reduction of variation in
product and process characteristics after
capability, stability, and conformity?

Yes, there are records of continual


improvement. SEE PHOTO #31.

8.5.2
8.5.2q1

8.5.2q2

8.5.2q3

8.5.2q4

T8.5.2.1q1

T8.5.2.1q2

T8.5.2.2q1

FINDINGS

The process for continual improvement is


defined in the procedure (Q/YCQP20262011).

SCORE

Corrective Action
Do corrective actions records identify
and address root cause(s)? Do root
causes match actions?

Yes. Verified.

Are actions taken appropriate to the


severity of the problem?

Yes, for example of the case #130060 on


the part number 204327.

Can you show me a documented


procedure defining requirements?

a) Reviewing nonconformities (including customer Yes, the procedure (Q/YCQP2026-2011).


complaints)
b) Determining the causes of nonconformities
c) Evaluating the need for action to ensure that
nonconformities do not recur
d) Determining and implementing action needed
e) Records of the results of action taken
f) Reviewing corrective action taken

Can you show me records of corrective


actions taken?

Yes, and 8D report is used to identify root


cause of problem, for example of the case
#130060 on the part number 204327.

Where is the process for problem solving


defined?
Does it lead to root cause identification
and elimination? (Review records)

Yes, the procedure (Q/YCQP2026-2011)

If one or more customer requires a


specific problem-solving format can you
show me records documented as
required?

Yes, and 8D report is used to identify root


cause of problem. For example, the case
#130060 on the part number 204327.

Can you show that error-proofing


methods are used in the corrective
action process?

Yes. SEE PHOTO #31.

8.5.2.4

C
Rejected Product Test/Analysis

T8.5.2.4q1a Can you show me records of analysis of


parts rejected by customer
manufacturing plants, engineering
facilities and dealerships?

Yes, an 8D report is used to identify root


cause of problem. For example, the case
#130060 on the part number 204327.

T8.5.2.4q1b How long does the analysis take?


Are records made available (to
customers) upon request?

The lead time has been defined as couple


of weeks in the procedure (Q/YCQP20262011).

T8.5.2.4q1c Is the time consistent with the


determination of root cause, corrective
action and monitoring the effectiveness
of implementation?

Yes, the time is sufficient.


C

ISO/TS 16949 QMS Audit Form

Rev.

AUDIT CHECKLIST

Supplier Name
XXXXXXXXXXXXXXX

Audit Date

Report No.

XX/XX/XXXX

XXXXXXXXX

C = Complies with the requirements, I = Improvement Needed, NC = Not Complies, N/A = Not Applicable
QUESTIONNAIRES
8.5.3
8.5.3q1

8.5.3q2

8.5.3q3

EVIDENCE TO CHECK

FINDINGS

SCORE

Preventive Action
How do you determine potential
nonconformities to take action one?
Do preventive action records identify and
address root cause(s)?

PFMEA is used as mean tool to determine


potential nonconformities, and proposal
action are recorded.

Are actions taken appropriate to the


severity of the problem?

Yes, actions are taken in consideration of


the value RPN obtained from the Severity
(S), Occurrence (O) and Current Detection
Method (D).

Can you show me a documented


procedure defining requirements for
each of the following?
a) determining potential nonconformities
and their causes
b) evaluating the need for action to
prevent occurrence of nonconformities,
c) determining and implementing action
needed
d) records of results of action taken (see
4.2.4), and
e) reviewing preventive action taken

Yes, the procedure is Q/YCQP2026-2011.

ISO / TS 16949 QMS Audit Form

Rev.

FACTORY PHOTOS

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

1. Factory's main gate

2. Process map

3.Subsequence between processes

4. Organization

5. Stamping workshop

6. Stamping process & layout

ISO / TS 16949 QMS Audit Form

Rev.

FACTORY PHOTOS

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

7. Policy & Quality Objectives

8. Distribution of KPIs

9. Company policy posted at a public board

10. Master list of quality procedures

11. Master list of quality records

12. Evidence of identification of file under control

ISO / TS 16949 QMS Audit Form

Rev.

FACTORY PHOTOS

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

13. Nomination letter of management representative

14. List of identified customer special requirement

15. Status of KPIs published at workshop

16. Status of KPI as input for management Review

17. Storage of tooling

18. Meaurement device CMM

ISO / TS 16949 QMS Audit Form

Rev.

FACTORY PHOTOS

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

19. Salt spray test device

20. Function test

21. Project profile

22. Hardness test

23. UV machine

24. Training program

ISO / TS 16949 QMS Audit Form

Rev.

FACTORY PHOTOS

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

25. Training program for special job position

26. Traing test record

27. Training record

28 Document

29. Work instruction at assembly line

30. Work instruction at assembly line

ISO / TS 16949 QMS Audit Form

Rev.

FACTORY PHOTOS

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

31. Record of continual improvement.

32. A view of assembly line

33. A view of client's product

34. A view of packaging process for client's product

35. A view of layout at workshop

36. APQP file

ISO / TS 16949 QMS Audit Form

Rev.

FACTORY PHOTOS

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

37. List of special characteristic

39. Record of review at the 1st phase of APQP

40. Record of status of pahse 4th of APQP

41. PSW signed by the client for approve

42. List of qualified suppliers

43. Record of supplier evaluation

ISO / TS 16949 QMS Audit Form

Rev.

FACTORY PHOTOS

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

44. Suppliers certification program

45. Inspection criteria for IQC

46. Record of IPQC

47. Record of annual performance of supplier

48. Control plan

49. Indication of tooling status

ISO / TS 16949 QMS Audit Form

Rev.

FACTORY PHOTOS

Supplier Name

Audit Date

Report No.

XXXXXXXXXXXXXXX

XX/XX/XXXX

XXXXXXXXX

50 A view of material handling and identification

51. A view of Inspection device & calibration certificate.

52. Record of client feedback about quality

53. Non-conforming storage and identification

You might also like