Rate Analysis - P$C
Rate Analysis - P$C
Assumptions
1
2
3
4
Sl no.
1
2
3
3.1
3.2
3.3
4
4.1
4.2
4
4.1
4.2
5
6
7
8
9
Measurements
L
B
Description
Unit
Excavation
PCC M 10 Grade
Brick Work
Pillars
Walls below GL
Walls above GL
Sub Total Brick Work
Plaster 20 mm thick
Walls
Pillars
Sub Total Plaster
M15 grade Concrete
Coping
Grouting
Sub Total M 15 concrete
Shuttering for Coping
Structural Steel Post ISA 50*50*5
Barbed Wire ( Mat + Lab )
Line Wire 4 mm thk ( Mat + Lab )
Hardwares & Fittings
Sub Total - 40 M length
CuM
CuM
4
4
10.46
10.46
0.46
0.46
CuM
CuM
CuM
16
4
4
0.46
8.16
8.16
0.46
0.46
0.23
SqM
SqM
2
16
40
0.8
CuM
CuM
1
16
40
0.23
0.23
0.23
SqM
Kg
M
M
LS
8
16
3
2
1
10
1.02
40
40
40
0.15
3.925
Nos
Sl no.
1
2
3
3.1
3.2
3.3
Description
Excavation
PCC M 10 Grade
RRM walls
Pillars
Walls below GL
Walls above GL
Sub Total Brick Work
Unit
Nos
Measurements
L
B
CuM
CuM
4
4
10.46
10.46
0.46
0.46
CuM
CuM
CuM
16
4
4
0.46
8.16
8.16
0.46
0.46
0.35
4
5
5.1
5.2
6
7
8
9
10
Flush Pointing
M15 grade Concrete
Coping
Grouting
Sub Total M 15 concrete
Shuttering for Coping
Structural Steel Post ISA 50*50*5
Barbed Wire ( Mat + Lab )
Line Wire 4 mm thk ( Mat + Lab )
Hardwares & Fittings
Sub Total - 40 M length
SqM
40
CuM
CuM
1
16
40
0.23
0.23
0.23
SqM
Kg
M
M
LS
8
16
3
2
1
10
1.02
40
40
40
0.15
3.925
Sl no.
1
2
3
4
4.1
4.2
5
6
7
8
Measurements
L
B
Description
Unit
Excavation
PCC M 10 Grade
RCC M20 in foundations
Structural Steel Post ISA 50*50*5
Straight
Inclined
Sub Total
GI Chain Link Fencing
Barbed Wire ( Mat + Lab )
Line Wire 4 mm thk ( Mat + Lab )
Hardwares & Fittings
Sub Total - 40 M length
CuM
CuM
CuM
24
24
24
0.45
0.45
0.45
0.45
0.45
0.45
Kg
Kg
16
8
2.58
2
3.925
3.925
SqM
M
M
LS
1
3
5
1
40
40
40
40
1.8
Nos
Sl no.
Description
Unit
Nos
Measurements
L
B
1
2
3
4
4.1
4.2
5
6
7
8
Excavation
PCC M 10 Grade
RCC M20 in foundations
Structural Steel Post ISA 50*50*5
Straight
Inclined
Sub Total
Barbed Wire Straight
Barbed wire inclined
Line Wire 4 mm thk ( Mat + Lab )
Hardwares & Fittings
Sub Total - 40 M length
CuM
CuM
CuM
24
24
24
0.45
0.45
0.45
0.45
0.45
0.45
Kg
Kg
16
8
2.58
2
3.925
3.925
SqM
M
M
LS
12
32
5
1
40
3.5
40
40
Description
Unit
CuM
Cum
Cum
Kg
Kg
Kg
Kg
Sqm
Kg
Kg
Nos
2
2
2
2
2
2
2
2
2
LS
Measurements
L
B
0.6
0.6
0.6
2.6
6.39
3.195
0.59
1.395
6.39
0.6
0.6
0.6
33.6
4.43
0.95
0.59
1.8
0.98
Sl no.
1
1.1
1.2
Description
Excavation
Footings
Plinth Beams
4
2
2
1.8
3.5
2.87
1.8
0.23
0.23
M3
M3
M3
M3
4
2
2
1
1.7
3.5
2.87
3.07
1.7
0.23
0.23
2.87
M3
M3
M3
4
4
2
1.5
0.3
3.5
1.5
0.23
0.23
Sub Total
2
2.1
2.2
PCC
Footings
Plinth Beams
2.3
Grade Slab
Sub Total
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
Plinth Beams PB 2
Tie Beams TB 1
Tie Beams TB 2
Slabs
Grade Slab
M3
M3
M3
M3
M3
2
2
2
1
1
2.87
3.5
2.87
5
3.57
0.23
0.3
0.3
3.4
2.87
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
4
2
2
2
2
2
1
2
1
2
2
1
1.5
0.3
3.5
2.87
3.5
3.5
2.87
2.87
4.77
3.17
4.77
2.87
2
2
2
2
4
3.5
2.87
4.03
3.33
0.45
0.23
0.23
0.23
0.23
0.115
4.77
3.27
Sub Total
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
0.23
Sub Total
5
Reinforcement
MT
Brick work
M3
M3
M3
M3
M3
Plaster 20 mm thick
M2
M2
M2
Sub Total
9
M2
10
M2
11
M2
4.07
2.97
12
M2
3.17
2.87
13
M2
3.17
2.87
14
HMPS Doors
M2
1.2
15
Boulder Soling
M3
5.97
3.07
16
LS
17
IPS Flooring
M2
3.57
2.87
18
M2
3.57
2.87
Total Cost
Sl no.
1
1.1
1.2
Description
Excavation
Footings
Plinth Beams
4
2
2
2.1
5.9
3.07
2.1
0.23
0.23
M3
M3
M3
M3
4
2
2
1
1.9
5.9
3.07
5.97
1.9
0.23
0.23
3.07
M3
M3
M3
M3
M3
M3
M3
M3
4
4
2
2
2
2
1
1
1.8
0.3
5.9
3.07
5.9
3.07
7.4
5.97
1.8
0.23
0.23
0.23
0.3
0.3
3.4
3.07
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
4
2
2
2
2
2
1
2
1
2
2
1
1.8
0.3
Sub Total
2
2.1
2.2
PCC
Footings
Plinth Beams
2.3
Grade Slab
Sub Total
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
Sub Total
4
4.1
4.2
Footings
Columns
4.3
4.4
4.5
Plinth Beams PB 1
Plinth Beams PB 2
Tie Beams TB 1 sides
Tie Beams TB 1 bottom
Tie Beams TB 2 sides
Tie Beams TB 2 bottom
Roof Slab side
4.6
4.7
Sub Total
0.23
5.9
3.07
5.9
5.9
3.07
3.07
7.33
3.53
6.8
3.07
Reinforcement
MT
Brick work
M3
M3
M3
M3
M3
Plaster 20 mm thick
M2
M2
M2
2
2
2
2
4
5.9
3.07
7.1
3.53
0.45
0.23
0.23
0.23
0.23
0.115
6.8
3.07
Sub Total
9
M2
10
M2
11
M2
6.8
3.07
12
M2
5.97
3.07
13
M2
5.97
3.07
14
HMPS Doors
M2
1.2
15
Boulder Soling
M3
5.97
3.07
16
LS
17
M2
5.97
3.07
18
M2
5.97
3.07
Total Cost
Brick Manhole : 1000 x 1000 x 1650 mm
Measurements
Description
Nos
L
B
Unit
Sl no.
1
2
3
Excavation
PCC
Brick work
Sub Total
Plaster from Inside
m3
m3
m3
m3
1
1
2
2
1.76
1.56
1.46
1
m2
1.76
1.56
0.23
0.23
4
5
m3
1.46
1.46
Sub Total
RCC Cast In situ - Manhole : 1000 x 1000 x 1650 mm
Measurements
Description
Nos
L
B
Unit
Sl no.
1
2
3
3
4
5
Excavation
PCC
RCC M 20 Grade
Sub Total
Form work
RCC Preacst Cover
RCC M 25 incl shuttering & R/f
Structural Steel Frames
m3
m3
m3
m3
1
1
1
4
1.6
1.4
1.15
1.15
m2
1.15
m3
Kg
1
1
1.46
4.6
1.6
1.4
1.15
0.15
1.46
0.25
Sub Total
RCC Precast Manholes - 1000 mm dia x 1650 mm
Measurements
Description
Nos
L
B
Unit
Sl no.
1
2
3
4
4
Excavation
PCC
Preacst Hume pipe
Erection of Hume pipe
RCC Preacst Cover
RCC M 25 incl shuttering & R/f
m3
m3
m
m
1
1
1
1.6
1.4
1.5
1.6
1.4
m3
1.46
1.46
Sub Total
Shetlter / Container Paltform 100 Sq ft 3800 x 3100 mm size
Measurements
Description
Nos
L
B
Unit
Sl no.
1
2
3
4
4.1
Eaxcavation
Boulder Soling
PCC 50 mm thcik
RCC
Inverted Beams
4.2
5
Platform Slab
Sub Total
Formwork
Reiinforcement
m3
m2
m3
1
1
1
3.8
3.3
3.8
3.1
2.6
3.1
m3
m3
m3
2
2
1
3.8
2.6
3.3
0.25
0.25
2.6
m2
m2
2
2
3.8
3.1
Kg
Total
Shetlter / Container Paltform 200 Sq ft 6200 x 3300 mm size
Sl no.
Description
1
2
3
4
4.1
Eaxcavation
Boulder Soling
PCC 50 mm thcik
RCC
Inverted Beams
4.2
5
Platform Slab
Sub Total
Formwork
Reiinforcement
Measurements
L
B
Unit
Nos
m3
m2
m3
1
1
1
6.2
5.7
6.2
3.3
2.8
3.3
m3
m3
m3
2
2
1
6.2
2.8
5.7
0.25
0.25
2.8
m2
m2
2
2
6.2
3.3
Kg
Total
DG Foundations
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Description
Excavation
PCC
RCC M25
Shuttering
Shuttering
Reinforcement
brick work 115 mm thick
brick work 115 mm thick
Sand Filling
Sand Filling
PCC for Plinth Protection
PCC for Plinth Protection
RCC M 15 for Plinth Protection
RCC M 15 for Plinth Protection
Unit
m3
m3
m3
m2
m2
kg
m3
m3
m3
m3
m3
m3
m3
m3
Measurements
Nos L
B
1
1
1
2
2
4.13
3.13
2.50
2.50
1.25
2.88
1.88
1.25
2
2
2
2
2
2
2
2
2.72
1.47
2.60
1.35
4.15
2.75
4.00
1.25
0.115
0.115
0.1
0.1
0.61
0.61
0.75
0.75
ED
CST
12.36%
1%
Transp
& Hand
3%
11.89
1.08
2.89
Total
Sr. No.
1
COST OF CABLES
Cost /
mtr
Cables
2
26.82
2.44
6.51
4
5
6
7
58.71
5.34
14.25
80.46
7.31
19.53
114.45
10.40
27.78
936
115.69
10.52
28.08
22.37
2.03
5.43
13.60
1.24
3.30
ements
Qty
Rate
0.75
0.15
14.43
2.89
160
3700
2,310
10,682
2.4
0.5
1.9
8.13
7.51
14.26
3400
101,647
210
13,146
4400
300
85
15
10
10
6,929
3,600
5,466
1,800
800
400
146,779
29.90
1.9
1.9
43.90
18.70
62.60
0.15
0.23
Kg/M
Amount
1.38
0.19
1.57
12.00
64.31
120
80
40
3,669
dary Wall
ements
Qty
Rate
0.75
0.15
14.43
2.89
160
3700
2,310
10,682
2.4
0.5
1.9
8.13
7.51
21.71
2890
107,908
37.34
Amount
1.9
43.90
0.15
0.23
1.38
0.19
Kg/M
1.57
12.00
64.31
120
80
40
100
4,390
4400
300
85
15
10
10
6,929
3,600
5,466
1,800
800
400
144,284
3,607
ements
Qty
Rate
0.9
0.15
0.9
4.37
0.73
4.37
160
3700
5100
700
2,697
22,307
Kg/M
Kg/M
161.77
75.36
85
125
15
10
10
20,156
9,000
1,800
2,000
400
59,061
237.13
72.00
120
200
40
Amount
1,477
ements
H
Qty
Rate
Amount
0.9
0.15
0.9
4.37
0.73
4.37
Kg/M
Kg/M
161.77
75.36
237.13
480
112
200
40
160
3700
5100
700
2,697
22,307
85
15
15
10
10
20,156
7,200
1,680
2,000
400
57,141
1,429
ements
H
1.05
0.15
0.9
kg / m
kg / m
kg / m
7.85 kg/m
kg / m
Qty
Rate
0.76
0.11
0.65
174.72
56.62
6.07
5.47
5.022
12.52
10
160
3700
5100
85
85
85
85
125
85
85
Amount
121
400
3,305
14,851
4,812
516
465
628
1,065
850
27,012
2
ements
H
1.075
0.3
0.3
Qty
160
2,369.77
3700
6,466.06
0.87
0.12
0.10
0.66
1.75
0.3
3.17
0.3
Amount
13.93
0.48
0.40
14.81
0.075
0.075
0.075
0.075
Rate
2.7
0.87
0.48
0.3
0.23
0.23
0.15
0.15
0.40
0.48
0.40
2.55
1.54
9.42
0.3
3.17
3.17
0.3
0.3
0.08
0.3
0.08
0.3
0.15
0.15
3.1
3.1
0.45
0.45
3.1
5100
48,041.62
27.98
300
8,395.29
1.18
64500
75,948.15
11.25
3500
39,370.94
48.91
210
10,270.68
64.51
117
7,547.19
64.51
70
4,515.41
48.91
50
2,445.40
12.09
400
4,835.16
9.10
500
4,548.95
9.10
350
3,184.27
3.24
3500
11,340.00
4.22
365
1,538.63
1.80
1.90
1.46
2.10
1.72
0.56
1.05
0.46
0.86
1.43
0.95
13.69
4.99
4.09
0.83
0.69
0.64
###
###
2.7
0.23
1.00
1500
1,500.00
10.25
230
2,356.56
10.25
500
5,122.95
###
2
ements
Qty
Rate
Amount
H
1.075
0.3
0.3
18.96
0.81
0.42
20.20
0.075
0.075
0.075
0.075
3700
10,238.11
5100
70,185.31
300
11,748.72
3.89
0.87
0.81
0.42
0.81
0.42
3.77
2.75
13.76
0.3
3.17
3.17
0.3
0.3
0.08
0.3
0.08
0.3
0.15
0.15
3,232.14
1.08
0.20
0.11
1.37
2.77
0.3
3.17
0.3
0.3
0.23
0.23
0.15
0.15
160
2.16
1.90
1.46
3.54
1.84
0.94
1.77
0.49
0.92
2.20
1.06
20.88
39.16
1.72
64500
110,954.71
15.63
3500
54,716.66
67.97
210
14,273.91
88.85
117
10,395.10
88.85
70
6,219.29
67.97
50
3,398.55
20.88
400
8,350.40
18.33
500
9,163.95
18.33
350
6,414.77
2.7
3.24
3500
11,340.00
0.23
4.22
365
1,538.63
1.00
1500
1,500.00
18.33
230
4,215.42
18.33
500
9,163.95
3.1
3.1
0.45
0.45
3.1
8.41
4.38
1.47
0.73
0.64
67.97
20.88
###
0 mm
ements
Qty
Rate
Amount
H
1.725
0.075
1.5
1.5
1.5
5.34
0.18
1.01
0.69
1.70
6.00
160
3700
854.94
675.32
3500
210
5,940.90
1,260.00
0.15
0.32
10000
3,197.40
###
x 1650 mm
ements
H
1.725
0.075
0.15
1.5
Qty
Rate
Amount
160
3700
706.56
543.90
1.5
4.42
0.15
0.20
1.04
1.23
3.45
5100
300
6,290.21
1,035.00
0.15
31.3 kg/m2
0.32
36.00
10000
85
3,197.40
3,059.58
###
1650 mm
ements
Qty
Rate
Amount
H
1.725
0.075
4.42
0.15
1.50
1.50
160
3700
3450
230
706.56
543.90
5,175.00
345.00
0.15
0.32
10000
3,197.40
9,967.86
x 3100 mm size
ements
H
0.28
0.05
0.5
0.5
0.15
0.2
0.2
Qty
3.30
8.58
0.59
0.95
0.65
1.29
2.89
1.52
1.24
2.76
288.7
Rate
Amount
160
365
3700
527.74
3,131.70
2,179.30
5100
14,723.70
300
64.5
18621.15
###
x 3300 mm size
ements
Qty
Rate
Amount
H
0.28
0.05
0.5
0.5
0.15
0.2
0.2
5.73
15.96
1.02
1.55
0.70
2.39
4.64
2.48
1.32
3.8
464.4
160
365
3700
916.61
5,825.40
3,785.10
5100
23,684.40
300
64.5
1,140.00
29953.8
###
Qty
H
1.1
0.1
1.2
1.2
1.2
0.9
0.9
0.9
0.9
0.05
0.05
0.1
0.1
Rate
13.08
0.59
3.75
6
3
375.00
0.56
0.30
0.47
0.24
0.25
0.17
0.60
0.19
160
3700
5100
300
300
64.5
3500
3500
1150
1150
3700
3700
4450
4450
Amount
2,093.41
2,177.23
19,125.00
1,800.00
900.00
24,187.50
1,967.02
1,061.39
538.20
279.45
936.66
620.68
2,670.00
834.38
###
Sub
Total
Contractor's
OH@P
Total
112.06
11.21
123
252.77
25.28
278
553.30
55.33
609
758.31
75.83
834
1078.64
107.86
1187
1090.29
109.03
1199
210.84
21.08
232
128.13
12.81
141
Description
Excavation in Or
Upto 1.50m
Excavation rate in m3
50.00
75.00
50.00
75.00
Earth Filling
Filling
earth
Description
Material
Earth
Sand
Soling
Chips
with
available Filling
with
earth
brought from outside
Available
110.00
40.00%
0
110
Labour
40.00
40.00
Total
Consolidation
40.00
150.00
0.80
3.00
40.80
153.00
2.00%
Disposal
Description
75.00
75.00
CC 1:5:10
40mm & downsize
Description
Material
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Aggregate Constant (cft)
Aggregate Rate
Wastage
1.00%
2.00%
CC 1:4:8
40mm & downsize
2.85
641.25
16.77
402.48
33.54
402.48
1446.21
14.46
3.5
787.50
16.51
396.24
33.02
396.24
1579.98
15.80
1460.67
1595.78
150.00
175.00
40.00
40.00
1650.67
33.01
1683.69
1810.78
36.22
1847.00
Column footing
Material
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Aggregate Constant (cft)
Aggregate Rate
Total for material in m3
Labour per m3
Cost of Mixer machine per m3
Sub Total
Tools &plants
Water and curing charges
1.00%
2.00%
Column
6.5
1462.50
19.93
478.30
30.66
735.84
2676.64
6.5
1462.50
19.93
478.30
30.66
735.84
2676.64
165.00
300.00
45.00
45.00
2886.64
28.87
57.73
3021.64
30.22
60.43
2.00
193.68
3166.92
Column footing
Material
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Aggregate Constant (cft)
Aggregate Rate
Total for material in m3
Labour per m3
Cost of Mixer machine per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum
1.00%
2.00%
Labour per m3
Cost of Mixer machine per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum
1.00%
2.00%
Column
8.2
1845.00
19.02
456.46
29.27
702.48
3003.94
8.2
1845.00
19.02
456.46
29.27
702.48
3003.94
165.00
300.00
45.00
45.00
3213.94
32.14
64.28
2.00
193.68
3504.03
3348.94
33.49
66.98
13.00
1,678.56
5127.96
Column footing
Material
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Aggregate Constant (cft)
Aggregate Rate
Total for material in m3
13.00
1,678.56
4790.85
Column
11.4
2565.00
13.41
321.84
26.83
643.92
3530.76
11.4
2565.00
13.41
321.84
26.83
643.92
3530.76
165.00
300.00
45.00
45.00
3740.76
37.41
74.82
2.00
193.68
4046.66
3875.76
38.76
77.52
13.00
1,678.56
5670.59
Description
Material
CC 1:3:6
M10
2289
2364
2289.00
2364.00
Labour per m3
40.00
2329.00
23.29
46.58
40.00
2404.00
24.04
48.08
2398.87
2476.12
Tools &plants
Water and curing charges
1.00%
2.00%
Column footing
Material
Total for material in m3
Labour per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum
1.00%
2.00%
2670
2670
2670.00
2670.00
30.00
250.00
2700.00
27.00
54.00
2.00
193.68
2974.68
2920.00
29.20
58.40
13.00
1,678.56
4686.16
Column footing
Material
1.00%
2.00%
Column
Column
2799
2799
2799.00
2799.00
30.00
250.00
2829.00
28.29
56.58
2.00
193.68
3107.55
3049.00
30.49
60.98
13.00
1,678.56
4819.03
Column footing
Column
Material
Total for material in m3
Labour per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum
1.00%
2.00%
M30
1.00%
2.00%
M35
M40
Material
Total for material in m3
2877.00
2877.00
30.00
250.00
2907.00
29.07
58.14
2.00
193.68
3187.89
3127.00
31.27
62.54
13.00
1,678.56
4899.37
1.00%
2.00%
Column
2978
2978
2978.00
2978.00
30.00
250.00
3008.00
30.08
60.16
2.00
193.68
3291.92
3228.00
32.28
64.56
13.00
1,678.56
5003.40
Column footing
Material
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum
2877
Column footing
Material
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum
2877
Column
3134
3134
3134.00
3134.00
30.00
250.00
3164.00
31.64
63.28
2.00
193.68
3452.60
3384.00
33.84
67.68
13.00
1,678.56
5164.08
Column footing
Column
3185
3185
3185.00
3185.00
Labour per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum
1.00%
2.00%
M45
30.00
250.00
3215.00
32.15
64.30
2.00
193.68
3505.13
3435.00
34.35
68.70
13.00
1,678.56
5216.61
Column footing
Material
Total for material in m3
Labour per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum
1.00%
2.00%
Column
3240
3240
3240.00
3240.00
30.00
250.00
3270.00
32.70
65.40
2.00
193.68
3561.78
3490.00
34.90
69.80
13.00
1,678.56
5273.26
STEEL WORK
Description
Basic Rate for reinforcement steel
Wastage
Binding wire @ Rs.30 /kg (10kg - 1MT)
Material Cost
Labour rate in Kg
Sub total
Reinforcement steel
3.00%
10.00
Structural steel
26,000.00
780.00
380.00
32000
960
27,160.00
32960
2,250.00
14000
29,410.00
46,960.00
MASONRY
Description
Material
Masonry constant ( Nos)
125
125
Masonry cost
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Boulders Constant (in cft)
Boulders Rate
Total for material in m3
500.00
1.8
405.00
17.28
414.72
6.00
54.00
1373.72
500.00
1.8
405.00
12.96
311.04
6.00
54.00
1270.04
Labour per m3
175.00
175.00
1,548.72
15.49
30.97
1,595.18
1,445.04
14.45
28.90
1,488.39
Sub Total
Scaffolding
Water and curing charges
Total per Cum
1.00%
2.00%
500
1,988.39
PLASTERING
CM 1:4
12mm thick masonry in 15mm thick masonry in
CM 1:4
CM 1:4
(in m2) with lime
(in m2)
Description
Material
Cement Constant (bags/m2)
Cement Rate
Sand Constant (cft)
Sand Rate
Lime cost
Sponge
0.1
22.50
0.60
14.40
3.00
0.15
33.75
0.80
19.20
3.00
39.90
55.95
Labour per m2
43.04
43.04
82.94
0.83
1.66
85.43
98.99
0.99
1.98
101.96
Sub Total
Scaffolding
Water and curing charges
Total per SQM
1.00%
2.00%
Internal plastering
External plastering
Material
Cement Constant (bags/m2)
Cement Rate
Sand Constant (cft)
Sand Rate
Lime cost
Sponge
0.18
40.50
0.90
21.60
3.00
65.10
70.00
Labour per m2
43.04
53.80
108.14
1.08
2.16
111.38
123.80
1.24
2.48
127.51
Sub Total
Scaffolding
Water and curing charges
Total per SQM
0.2
45.00
1.00
24.00
1.00
1.00%
2.00%
JOINERY
D1
Item No
Basic Cost of TW
Frame Section Size
Cutting Size
Plank
Wastage %
Frame Qty
Styles & Rails Sect
Cutting Size
Styles & Rails Qty
Planks Cutting Size
Planks Qty
Lipping Section
Lipping length
Lipping Qty
Total TW Qty
TW Cost
SS Hinges
T Bolt
Handle (Only fixing)
Lock (Only fixing)
Stoppers
PVC Bush
Eye piece
Labour for Making
Labour for fixing
Hold fasts
Glass
Shutters Area
Shutter Basic Rate
D2
Double Leaf
Main Door
1800
9 x 3
1800
9 x 2.5
0.2088
1
5
39.5
4.5 x 1.5
0.06
52.50
0.10
48
0
0
0.00
17.09
30763.36
600
875
125
250
150
40
75
3840
720
360
0
0
0
0.1766
0
5
23.5
0
0
0
0
0
0.0061
46
0.28
4.65
8374.16
600
875
125
250
150
40
0
2880
720
360
0
56
122
Shutter Rate
Size
OH & P @ 25%
Total
Cost per Sft
0
37198.36
48.00
9299.59
46497.95
968.71
6832
20662.16
56.00
5165.54
25827.70
461.21
10423.29
4962.61
FLOORING
Description
Basic Rate of Material
Wastage %
Wastage
Nosing
Sub Total
Cement Constant
Cement Basic Rate
Cement Rate
Sand Constant
Sand Basic Rate
Sand Rate
Labour i/c polishing
Aquamix Sealer Coat
POP protection
Cleaning
Water and curing charges
Total per Sqft
Total per Sqm
Flooring in sft
2.00%
Italian Marble
Skirting 4 in rft
300.00
10.00
30.00
99.90
10.00
9.99
330.00
0.13
225.00
29.93
0.52
24.00
12.48
35.00
6.00
5.00
5.00
423.41
8.47
431.87
109.89
0.04
225.00
9.98
0.17
24.00
4.16
25.00
2.00
0.00
0.00
151.03
3.02
154.05
4646.95
505.27
Upto 1.50m
1.50m - 3.0m
3.0m - 4.5 m
85.00
130.00
750.00
900.00
1050.00
85.00
130.00
750.00
900.00
1050.00
Sand filling
1101.83
1101.828
45.00
1146.83
22.94
1169.76
423.78
257.09
680.8732
250.00
930.87
65.22
996.09
19.92
1016.01
233.68
0.4559012
0.93502227
CC 1:3:6
20mm & downsize
CC 1:2:4
DPC 1:2:4 50mm thk
20mm & downsize 20mm & downsize
4.5
1012.50
16.10
386.40
32.20
772.80
2171.70
21.72
6.5
1462.50
15.33
367.92
30.66
735.84
2566.26
25.66
2193.42
2591.92
129.60
250.00
300.00
25.00
40.00
40.00
2483.42
49.67
2533.09
2931.92
58.64
2990.56
40.00
0.22
28.41
223.00
4.46
227.46
Plinth Beam
Roof Beams
Roof slabs
Staircase
Lintel
6.5
1462.50
19.93
478.30
30.66
735.84
2676.64
6.5
1462.50
19.93
478.30
30.66
735.84
2676.64
6.5
1462.50
19.93
478.30
30.66
735.84
2676.64
6.5
1462.50
19.93
478.30
30.66
735.84
2676.64
6.5
1462.50
19.93
478.30
30.66
735.84
2676.64
250.00
110.00
110.00
150.00
275.00
45.00
45.00
45.00
45.00
45.00
2971.64
29.72
59.43
2831.64
28.32
56.63
2831.64
28.32
56.63
2871.64
28.72
57.43
2996.64
29.97
59.93
14.00
1,807.68
4868.47
Plinth Beam
###
1,807.68
4724.27
Roof Beams
8.00
860.80
3777.39
Roof slabs
10.00
1,614.00
4571.79
Staircase
15.00
1,936.80
5023.34
Lintel
8.2
1845.00
19.02
456.46
29.27
702.48
3003.94
8.2
1845.00
19.02
456.46
29.27
702.48
3003.94
8.2
1845.00
19.02
456.46
29.27
702.48
3003.94
8.2
1845.00
19.02
456.46
29.27
702.48
3003.94
8.2
1845.00
19.02
456.46
29.27
702.48
3003.94
250.00
110.00
110.00
150.00
275.00
45.00
45.00
45.00
45.00
45.00
3298.94
32.99
65.98
14.00
1,807.68
5205.58
3158.94
31.59
63.18
###
1,807.68
5061.38
3158.94
31.59
63.18
8.00
860.80
4114.50
3198.94
31.99
63.98
10.00
1,614.00
4908.90
3323.94
33.24
66.48
15.00
1,936.80
5360.45
Plinth Beam
Roof Beams
Roof slabs
Staircase
Lintel
11.4
2565.00
13.41
321.84
26.83
643.92
3530.76
11.4
2565.00
13.41
321.84
26.83
643.92
3530.76
11.4
2565.00
13.41
321.84
26.83
643.92
3530.76
11.4
2565.00
13.41
321.84
26.83
643.92
3530.76
11.4
2565.00
13.41
321.84
26.83
643.92
3530.76
250.00
110.00
110.00
150.00
275.00
45.00
45.00
45.00
45.00
45.00
3825.76
38.26
76.52
14.00
1,807.68
5748.21
3685.76
36.86
73.72
###
1,807.68
5604.01
3685.76
36.86
73.72
8.00
860.80
4657.13
3725.76
37.26
74.52
10.00
1,614.00
5451.53
3850.76
38.51
77.02
15.00
1,936.80
5903.08
Plinth Beam
Roof Beams
Roof slabs
Staircase
Lintel
2670
2670
2670
2670
2670
2670.00
2670.00
2670.00
2670.00
2670.00
175.00
60.00
60.00
60.00
250.00
2845.00
28.45
56.90
14.00
1,807.68
4738.03
2730.00
27.30
54.60
###
1,807.68
4619.58
2730.00
27.30
54.60
8.00
860.80
3672.70
2730.00
27.30
54.60
10.00
1,614.00
4425.90
2920.00
29.20
58.40
15.00
1,936.80
4944.40
Plinth Beam
Roof Beams
Roof slabs
Staircase
Lintel
2799
2799
2799
2799
2799
2799.00
2799.00
2799.00
2799.00
2799.00
175.00
60.00
60.00
60.00
250.00
2974.00
29.74
59.48
14.00
1,807.68
4870.90
2859.00
28.59
57.18
###
1,807.68
4752.45
2859.00
28.59
57.18
8.00
860.80
3805.57
2859.00
28.59
57.18
10.00
1,614.00
4558.77
3049.00
30.49
60.98
15.00
1,936.80
5077.27
Plinth Beam
Roof Beams
Roof slabs
Staircase
Lintel
2877
2877
2877
2877
2877
2877.00
2877.00
2877.00
2877.00
2877.00
175.00
60.00
60.00
60.00
250.00
3052.00
30.52
61.04
14.00
1,807.68
4951.24
2937.00
29.37
58.74
###
1,807.68
4832.79
2937.00
29.37
58.74
8.00
860.80
3885.91
2937.00
29.37
58.74
10.00
1,614.00
4639.11
3127.00
31.27
62.54
15.00
1,936.80
5157.61
Plinth Beam
Roof Beams
Roof slabs
Staircase
Lintel
2978
2978
2978
2978
2978
2978.00
2978.00
2978.00
2978.00
2978.00
175.00
60.00
60.00
60.00
250.00
3153.00
31.53
63.06
14.00
1,807.68
5055.27
3038.00
30.38
60.76
###
1,807.68
4936.82
3038.00
30.38
60.76
8.00
860.80
3989.94
3038.00
30.38
60.76
10.00
1,614.00
4743.14
3228.00
32.28
64.56
15.00
1,936.80
5261.64
Plinth Beam
Roof Beams
Roof slabs
Staircase
Lintel
3134
3134
3134
3134
3134
3134.00
3134.00
3134.00
3134.00
3134.00
175.00
60.00
60.00
60.00
250.00
3309.00
33.09
66.18
14.00
1,807.68
5215.95
3194.00
31.94
63.88
###
1,807.68
5097.50
3194.00
31.94
63.88
8.00
860.80
4150.62
3194.00
31.94
63.88
10.00
1,614.00
4903.82
3384.00
33.84
67.68
15.00
1,936.80
5422.32
Plinth Beam
Roof Beams
Roof slabs
Staircase
Lintel
3185
3185
3185
3185
3185
3185.00
3185.00
3185.00
3185.00
3185.00
175.00
60.00
60.00
60.00
250.00
3360.00
33.60
67.20
14.00
1,807.68
5268.48
3245.00
32.45
64.90
###
1,807.68
5150.03
3245.00
32.45
64.90
8.00
860.80
4203.15
3245.00
32.45
64.90
10.00
1,614.00
4956.35
3435.00
34.35
68.70
15.00
1,936.80
5474.85
Plinth Beam
Roof Beams
Roof slabs
Staircase
Lintel
3240
3240
3240
3240
3240
3240.00
3240.00
3240.00
3240.00
3240.00
175.00
60.00
60.00
60.00
250.00
3415.00
34.15
68.30
14.00
1,807.68
5325.13
3300.00
33.00
66.00
###
1,807.68
5206.68
3300.00
33.00
66.00
8.00
860.80
4259.80
3300.00
33.00
66.00
10.00
1,614.00
5013.00
3490.00
34.90
69.80
15.00
1,936.80
5531.50
Brick Masonry in CM
1:6 (230mm thick)
in m3
500
Brick Masonry in
CM 1:4 (115mm
thick)
in m2
50
63
12.5
12.5
1,750.00
1.3
292.50
9.36
224.64
175.00
0.2
45.00
0.96
23.04
1,921.50
1.3
292.50
9.36
224.64
287.50
0.2
45.00
1.44
34.56
218.75
0.2
45.00
0.96
23.04
2267.14
243.04
2438.64
367.06
286.79
175.00
35.00
225.00
40.00
35.00
2,442.14
24.42
48.84
2,515.40
278.04
2.78
5.56
286.38
2,663.64
26.64
53.27
2,743.55
407.06
4.07
8.14
419.27
321.79
3.22
6.44
331.44
CM 1:4
18mm thick masonry
20mm thick
25mm thick masonry
12mm thick
15mm thick masonry
in CM 1:4
masonry in CM 1:4
in CM 1:4
masonry in CM 1:5
in CM 1:5
(in m2)
(in m2)
(in m2)
(in m2) with lime
(in m2)
0.18
40.50
0.90
21.60
3.00
0.2
45.00
1.00
24.00
0.21
47.25
1.10
26.40
1.00
1.00
65.10
70.00
43.04
108.14
1.08
2.16
111.38
Ceiling plastering
(in m2) with lime
0.099
22.28
0.599
14.38
3.00
0.149
33.53
0.799
19.18
3.00
74.65
39.65
55.70
53.80
53.80
43.04
43.04
123.80
1.24
2.48
127.51
128.45
1.28
2.57
132.30
82.69
0.83
1.65
85.17
98.74
0.99
1.97
101.70
CM
0.18
40.50
0.90
21.60
3.00
65.10
48.42
113.52
1.14
2.27
116.93
D4
Single Leaf
D4a
Single Leaf
1800
9 x 2.5
0.1766
0
5
19.5
0
0
0
0
0
0.0061
23
0.14
3.76
6774.55
300
350
125
250
150
40
0
2880
720
270
0
28.8
122
1800
5 x 2.5
0.1003
0
5
19.5
0
0
0
0
0
0.0061
23
0.14
2.20
3959.24
300
350
125
250
150
40
0
2640
720
270
0
28.8
122
D4b
Single Leaf
D5
Single Leaf
1800
5 x 2.5
0.1003
0
5
19.5
0
0
0
0
0
0.0061
23
0.14
2.20
3959.24
300
350
125
250
150
40
0
2640
720
270
150
28.8
122
1800
5 x 2.5
0.1003
0
5
19.5
0
0
0
0
0
0.0061
23
0.14
2.20
3959.24
300
350
125
250
150
40
0
2640
720
270
0
28.8
90
Flooring Sft
3513.6
15101.95
28.00
3775.49
18877.44
674.19
3513.6
12046.64
28.00
3011.66
15058.30
537.80
3513.6
12196.64
28.00
3049.16
15245.80
544.49
2592
11125.04
28.00
2781.26
13906.30
496.65
7254.33
5786.69
5858.74
5343.99
Flooring
88.00
0.13
225.00
29.93
0.52
24.00
12.48
22.00
3.00
0.00
2.00
157.41
3.15
160.55
29.30
0.04
225.00
9.98
0.17
24.00
4.16
12.00
2.00
0.00
2.00
59.44
1.19
60.63
80.00
10.00
8.00
30.00
118.00
0.13
225.00
29.93
0.52
24.00
12.48
24.00
3.00
0.00
2.00
189.41
3.79
193.19
1727.55
198.86
2078.76
Jaisalmer Marble
Skirting 4
90.00
29.97
10.00
10.00
9.00
3.00
99.00
0.13
225.00
29.93
0.52
24.00
12.48
22.00
0.00
2.00
2.00
167.41
3.35
170.75
32.97
0.04
225.00
9.98
0.17
24.00
4.16
12.00
0.00
3.00
2.00
64.10
1.28
65.38
1837.30
214.46
1.50m - 3.0m
3.0m - 4.5 m
1150.00
1500.00
1750.00
1150.00
1500.00
1750.00
Chejja
6.5
1462.50
19.93
478.30
30.66
735.84
2676.64
275.00
45.00
2996.64
29.97
59.93
14.00
1,506.40
4592.94
Chejja
8.2
1845.00
19.02
456.46
29.27
702.48
3003.94
275.00
45.00
3323.94
33.24
66.48
14.00
1,506.40
4930.05
Chejja
11.4
2565.00
13.41
321.84
26.83
643.92
3530.76
275.00
45.00
3850.76
38.51
77.02
14.00
1,506.40
5472.68
Chejja
2670
2670.00
250.00
2920.00
29.20
58.40
14.00
1,506.40
4514.00
Chejja
2799
2799.00
250.00
3049.00
30.49
60.98
14.00
1,506.40
4646.87
Chejja
2877
2877.00
250.00
3127.00
31.27
62.54
14.00
1,506.40
4727.21
Chejja
2978
2978.00
250.00
3228.00
32.28
64.56
14.00
1,506.40
4831.24
Chejja
3134
3134.00
250.00
3384.00
33.84
67.68
14.00
1,506.40
4991.92
Chejja
3185
3185.00
250.00
3435.00
34.35
68.70
14.00
1,506.40
5044.45
Chejja
3240
3240.00
250.00
3490.00
34.90
69.80
14.00
1,506.40
5101.10
Hollow Block
Masonry in CM 1:6
(200mm
8" thk inthick)
m3
63
12.5
Hollow Block
Masonry in CM 1:6
(200mm
4" thk inthick)
m2
12.5
1,386.00
1.3
292.50
9.36
224.64
231.25
0.2
45.00
1.44
34.56
175.00
0.2
45.00
0.96
23.04
1903.14
310.81
243.04
200.00
35.00
30.00
2,103.14
21.03
42.06
2,166.23
345.81
3.46
6.92
356.18
273.04
2.73
5.46
281.23
CM 1:5
18mm thick masonry 20mm thick masonry 25mm thick masonry
12mm thick
15mm thick
in CM 1:5
in CM 1:5
in CM 1:5
masonry in CM 1:6 masonry in CM 1:6
(in m2)
(in m2)
(in m2)
(in m2) with lime
(in m2)
0.179
40.28
0.899
21.58
3.00
0.199
44.78
0.999
23.98
0.209
47.03
1.099
26.38
0.0984
22.14
0.60
14.36
3.00
0.1484
33.39
0.80
19.16
3.00
1.00
1.00
64.85
69.75
74.40
39.50
55.55
43.04
53.80
53.80
43.04
43.04
107.89
1.08
2.16
111.13
123.55
1.24
2.47
127.26
128.20
1.28
2.56
132.05
82.54
0.83
1.65
85.02
98.59
0.99
1.97
101.55
CM 1:6
mer Marble
Staircase
90.00
10.00
9.00
Sand Stone
Polished Slate Stone
Flooring(pathway) Flooring
Skirting 3
60.00
80.00
10.00
10.00
6.00
8.00
99.00
0.13
225.00
29.93
0.52
24.00
12.48
24.00
0.00
4.00
3.00
172.41
3.45
175.85
66.00
0.13
225.00
29.93
0.52
24.00
12.48
20.00
0.00
0.00
3.00
131.41
2.63
134.03
88.00
0.05
225.00
11.25
0.52
24.00
12.48
10.00
7.00
4.00
3.00
135.73
2.71
138.44
29.30
0.03
225.00
5.63
0.17
24.00
4.16
10.00
9.00
4.00
3.00
65.09
1.30
66.39
88.00
0.05
225.00
11.25
0.52
24.00
12.48
10.00
9.00
5.00
4.00
139.73
2.79
142.52
1892.18
1442.20
1489.66
217.76
1533.56
CM 1:6
18mm thick
masonry in CM
(in1:6
m2)
0.1784
40.14
0.90
21.56
3.00
20mm thick
25mm thick
masonry in CM masonry in CM
(in1:6
m2)
(in1:6
m2)
0.1984
44.64
1.00
23.96
0.2084
46.89
1.10
26.36
1.00
1.00
64.70
69.60
74.25
43.04
53.80
53.80
107.74
1.08
2.15
110.97
123.40
1.23
2.47
127.10
128.05
1.28
2.56
131.89
ed Slate Stone
Skirting 3
Flooring
26.64
15.00
4.00
30.64
0.03
225.00
5.63
0.17
24.00
4.16
10.00
9.00
4.00
3.00
66.42
1.33
67.75
222.22
340.62
3240.27
29.30
0.06
225.00
13.38
0.25
24.00
6.00
15.00
0.00
4.00
3.00
70.68
1.41
72.10
1742.38
236.47
ished Granite
Ceramic tile
Pressed Clay Tile
for Staircase
Dadooing
Flooring
Skirting 3
Flooring
80.00
45.00
40.00
13.32
20.25
10.00
7.50
7.50
8.00
8.00
8.00
3.38
3.00
1.07
1.62
30.00
88.00
48.38
43.00
14.39
21.87
0.12
0.02
0.02
0.01
0.02
225.00
225.00
225.00
225.00
225.00
26.76
3.38
4.05
2.03
4.50
0.52
0.40
0.40
0.13
0.40
24.00
24.00
24.00
24.00
24.00
12.48
9.60
9.60
3.20
9.60
0.00
8.00
8.00
7.00
8.00
0.00
0.00
0.00
0.00
2.00
5.00
0.00
4.00
0.00
2.50
3.00
1.50
1.50
1.00
2.50
135.24
70.85
70.15
27.61
50.97
2.70
1.42
1.40
0.55
1.02
137.94
72.27
71.55
28.16
51.99
1484.24
777.59
769.91
92.37
559.41
57.44
0.01
225.00
2.25
0.40
24.00
9.60
8.00
0.00
0.00
2.00
79.29
1.59
80.88
207.00
0.02
225.00
4.50
0.40
24.00
9.60
12.00
0.00
4.00
5.00
242.10
4.84
246.94
68.93
0.01
225.00
2.25
0.13
24.00
3.20
9.60
0.00
0.00
2.00
85.98
1.72
87.70
44.00
0.05
225.00
11.25
0.40
24.00
9.60
12.00
0.00
4.00
3.00
83.85
1.68
85.53
14.65
0.03
225.00
5.63
0.13
24.00
3.20
10.20
0.00
3.00
3.00
39.68
0.79
40.47
2267.48
265.28
2657.10
287.66
920.27
132.74
36.63
0.03
225.00
5.63
0.13
24.00
3.20
12.00
0.00
3.00
3.00
63.46
1.27
64.72
1655.61
212.30
Analysis of Rate
A
RCC. WORK
1 R.C.C for M-30 as per Mix Design
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
Sand
Bags
Cum
7.600
0.707
249.00
1166.00
Agg (AI+AII)
Cum
0.615
725.00
Labour:
Foreman
Beldar (M)
Coolie (F)
Mason
Each
Each
Each
Each
0.040
0.700
0.700
0.070
260.00
135.00
125.00
260.00
Waterman
Each
0.035
135.00
Total (M+L)
Add for Eqn
6.00%
15.00%
Total Amt.
Cost Per 1 Cum (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
A)
B)
C)
Materials:
1 Cement
2 Sand
Bags
Cum
6.300
0.440
0.00
1166.00
3 Agg (AI+AII)
Cum
0.880
725.00
Each
Each
Each
Each
Each
Each
Each
8 Lift operator
Each
0.04
0.04
0.13
1.40
0.04
0.04
0.04
0.04
300.00
300.00
260.00
150.00
150.00
350.00
300.00
300.00
hour
hour
0.50
0.50
hour
0.50
250.00
75.00
100.00
15.00%
Total Amt.
Cost Per 1 Cum (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
Sand
Bags
Cum
10.71
0.37
230.00
600.00
Agg (AI+AII)
Cum
0.74
625.00
Each
0.040
300.00
Labour:
Foreman
Beldar (M)
Coolie (F)
Mason
Each
Each
Each
0.700
0.700
0.070
200.00
200.00
260.00
Waterman
Each
0.035
200.00
Total (M+L)
Add for Eqn
8.00%
15.00%
Total Amt.
Cost Per 1 Cum (Rs.)
Descritption
Qty
Material
1 Rein.Steel Bars + 5% wastage
2 Binding Wire
Unit
1.05 Mt
5.00 Kg
Rate
28,000.00
30.00
10.00 Day
250.00
2 Beldar
10.00 Day
150.00
Material
1 18 mm thk.Marine Ply
2 Vertical Ballis (Saru)
3 Wood Patlis 25 x100mm
Sqm
Nos
Cum
230.00
150.00
2.40
495.00
144.00
28,248.00
4 4" thk.Chabbis
5 Shikanja
Cum
Nos
0.45
95.00
28,248.00
200.00
Nos
Nos
23.00
23.00
300.00
200.00
Total - M
Assuming usage 10times
B
Labours
6 Carpenter
7 Helper
Total- L
Total
C
D
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
Sand
Aggregate
Colour Pigment & Hardener
Bags
Cum
Cum
Kgs
0.83
0.03
0.06
5.00
249.00
1158.00
698.00
30.00
Shuttering
Sqm
0.30
160.00
Labour:
Mason
Skilled Labour
Unskilled Labour
Each
Each
Each
0.01
0.06
0.06
250.00
135.00
125.00
Carpenter
Each
0.06
250.00
C)
Mechinary
Mixer with Operater
Vibrator with Operater
Cum
Cum
0.12
0.12
200.00
100.00
Sqm
1.00
135.00
Sub-Total of Mechinary
D)
Total (M+L)
Add W.C & Electricity
1.50%
15.00%
BRICKWORK
1 9'' Brick work With Silpoz (1 :6)
Sr.
no
A)
Item
Unit
Materials:
9" thk Brick
Cement
Nos
Bags
Silpoz
Quantity
Rate
(Rs.)
110.00
0.35
3.12
249.00
Cft
2.10
65.27
Sft
10.76
7.00
Labour:
Labour
Sub-Total of Labour (L)
Total (M+L)
C)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
1.00%
1.00%
15.00%
B)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
4" thk Brick
Cement
Nos
Bags
5320.00
14.45
4.00
249.00
Silpoz
Cum
2.02
1175.00
Each
Each
0.50
16.00
300
260
Helper
Each
23.00
200.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost Per 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Descriptions
8" thk. Siporex Blocks (1:4)
8" Blocks (200x240x650 mm)
Less Discount @ 33%
Unit
Qty.
Rate (Rs.)
No.
No.
6.06
-6.06
157.00
51.81
No.
6.06
7.59
Bag
0.125
249
Total
Add Tax @ 12.5%
Add Transport @ 3000/- per Truck
Total
5% Wastage
Total Block Cost
Cement
Sand
C.ft.
0.50
32.26
Labour
S.ft.
10.76
7.00
Descriptions
9" thk. Bricks (1:4)
9" thk. Bricks
5% Wastage
Total Bricks Cost
Cement
Sand
Labour
Unit
Qty.
Rate (Rs.)
No.
110.00
3.12
Bag
C.ft.
0.35
1.40
249.00
32.36
S.ft.
10.76
7.00
Item
Unit
Materials:
Cement
Sand
bag
Cum
Brick
Nos
Quantity
Rate
(Rs.)
25.00
4.38
249.00
1113.00
5000.00
3.70
Labour:
Mason
Each
8.50
235.00
Helper
Each
16.00
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P & Taxs
Total Amt.
0.50%
1.00%
15.00%
PAINTS
Date : 130908
1 Comparative between Elastoseal Paint v ICI Weather Sheild Max
Sr.No
1
2
3
4
5
Description
Rate Per Sqft + Taxes
Labour cost per Sft
Total Amt
Protection Against Fungus & Algae
Guarantee (Water Proofing)
Colour
Coat
7
8
9
ICI
Weather
Elastose Sheild Max
al Paint Acrylic
13.25
7.25
2.00
2.00
15.25
9.25
5 Years 7 Year
5 Years No Guarantee
White
Various Colour
1 Coat 1 Coat Self
Elasto
Priming +2
Prime 25 Coat
For 1 Litre
+ 2 Coat Weater
Paint +300
Elastose Sheild
Max
ml Clean
al+Stain
No Requi Water
er
26-28 Sqf 50-60 Sft/litre
In House Not Available
2 3 Coat Ext. Paint with Asian Weather Shield for 100 Sqm
Sr.
no
A)
Item
Quantity
Materials:
Prime Coat
Prime Paint one coat
Litre
6.00
80.00
Litre
30.00
165.00
Unit
Rate
(Rs.)
Labour:
Painter
Each
17.00
200.00
Male Coolie
Each
17.00
135.00
Male Coolie
C)
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost For 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
C)
Labour:
Painter
Male Coolie
Sub-Total of Labour (L)
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost For 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Each
Each
Quantity
Rate
(Rs.)
6.00
30.00
80.00
60.00
17.00
17.00
200.00
135.00
1.00%
1.00%
15.00%
Rate
(Rs.)
Litre
1.25
237.50
Each
Each
0.60
0.50
250.00
135.00
C)
Sr.
no
A)
Labour:
Painter
Male Coolie
Sub-Total of Labour (L)
Total (M+L)
Add for Sundries & Contingencies
Brushes Sand Paper Putty Etc.
Add for Scaffolding Ladder Etc.
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost For 10Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Materials:
Asian Brand
Primer
Oil Paint
3.00%
5.00%
2.50%
0.50%
15.00%
0.75
1.25
100
180.00
Each
Each
0.60
0.50
250.00
135.00
C)
Labour:
Painter
Male Coolie
Sub-Total of Labour (L)
Total (M+L)
Add for Sundries & Contingencies
Brushes Sand Paper Putty Etc.
Add for Scaffolding Ladder Etc.
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost For 10Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
PLASTER
3.00%
5.00%
2.50%
0.50%
15.00%
Date :- 130908
1 12mm thk Internal Plaster with 5 mm thk Birla Putty CM 1:4 per 100 Sqm Material Only
Sr.no
A
Item
Unit
Internal Palster
1 Cement
2 Sand
Quantity
Rate (Rs.)
Bag
Cum
12.00
1.60
249.00
1139.00
Kg
72.00
72.00
Total Amt
5% Wastage
Total Amt with Wastage
Total Amt per Sqm
Total Amt per Sft
2 12mm thk Internal Plaster with 8 mm thk (1st POP) CM 1:4 per 100 Sqm material only
Sr.no
A
Item
Unit
Internal Palster
1 Cement
2 Sand
Quantity
Bag
Cum
8 mm 1 st POP
Kg
Rate (Rs.)
12.00
1.60
249.00
1139.00
115.00
5.50
Total Amt
5% Wastage
Total Amt with Wastage
Total Amt per Sqm
Total Amt per Sft
Item
Materials:
Cement
Unit
Bags
Quantity
12.00
Rate
(Rs.)
249.00
Sand
M3
1.60
1139.00
Brila Putty
Kg
600.00
29.00
Labour:
1st Class Mason
Belder
Each
Each
13.00
13.00
260.00
135.00
Waterman
Each
1.50
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost For 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
4 12 mm thk Internal Plaster with POP (1st) CM 1:4 per 100 m2
Sr.
no
A)
Item
Unit
Materials:
Cement
Sand
Bags
M3
Pop (1st)
Kg
Quantity
Rate
(Rs.)
12.00
1.60
249.00
1139.00
600.00
5.50
Labour:
1st Class Mason
Belder
Each
Each
13.00
13.00
260.00
135.00
Waterman
Each
1.50
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
1.00%
1.00%
15.00%
Total Amt.
Cost For 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
Bags
0.16
249.00
Silpoz
Cum
0.06
2304.94
10.76
7.5
Labour:
Sft
1.00%
1.00%
15.00%
Total Amt.
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
6 Plaster (1:4) with Sand 15mm thk.Ex.Scaffolding
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
Bags
0.16
249
sand
Cum
0.03
1139
B)
Labour:
Sft
10.76
7.5
1.00%
1.00%
15.00%
Total Amt.
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
Sand
bag
Cum
14.10
1.41
249.00
1113.00
Scaffolding
Sqm
100.00
25.00
Labour:
Mason
Each
17.50
260.00
Helper
Each
25.00
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add vat & Service tax
Add for OH & C.P & Taxs
Total Amt.
Cost for 100 Sqm (Rs.)
0.50%
1.00%
9.12%
15.00%
Unit
Quantity
Bags
M3
Lts
Bags
Rate
0.17
0.022
0.04
0.06
Add wastage
245.00
1113.00
155.00
155.00
5%
Total Material
B
Labour
Labour cost
Subtotal Labour
Total Labour
M2
45.00
Total M+L
Total Cost per M2
Add contigencies water electricity
Add T & P
2%
2%
Tax
Add profit
10%
15%
Total Cost per M2
Say
Rs.
Item
Materials:
Cement
Sand
Scaffolding
Unit
Qty.
Rate
bag
Cum
Sqm
20.00
2.40
100.00
249.00
1113.00
31.00
Each
17.50
260.00
Labour:
Mason
Helper
Each
25.00
135.00
TILING
1 Marble Mosaic
Sr.
no
A)
Item
Unit
Materials:
Marble Mosaic
Sqm
Tonne
Cum
Cement
Rate
(Rs.)
Quantity
1
162.00
0.0033
0.03
80000.00
1300.00
Bags
0.14
249.00
Labour:
Tile mason
Each
0.5
250.00
Coolie (M)
Each
0.5
135.00
Total (M+L)
Add Carriage of Tiles cement etc.
0.50%
0.50%
1.00%
1.00%
15.00%
Item
Unit
Materials:
Kota Stone
Sqm
Tonne
Cum
Cement
Rate
(Rs.)
Quantity
1
485.00
0.0033
0.03
80000.00
1300.00
Bags
0.14
249.00
Labour:
Tile mason
Each
0.5
250.00
Coolie (M)
Each
0.5
135.00
Total (M+L)
Add Carriage of Tiles cement etc.
0.50%
0.50%
1.00%
1.00%
15.00%
3 Glaze Ceramic
Sr.
no
A)
Item
Materials:
Unit
Quantity
Rate
(Rs.)
Glaze Ceramic
Sqm
250.00
Tonne
Cum
0.0033
0.03
80000.00
1300.00
Cement
Bags
0.14
249.00
Labour:
Tile mason
Each
0.5
250.00
Coolie (M)
Each
0.5
135.00
Total (M+L)
Add Carriage of Tiles cement etc.
0.50%
0.50%
1.00%
1.00%
15.00%
4 Supply & Fixing PVC Door with Baroda Green Marble frame (2.1x 0.75) with hardware & lab.
Sr.no
Item
1 PVC Door Shutter
2 Laminate
3 baroda Green Marble (20 mm)
4 French Polish
a Wooden Frame
b Shutter Edge
5 Lipping Patti
Unit
Sqm
Sqm
-
Total Amt
5% Wastage on Marble
1
Hardware
Fixing
Total Amt for 1.58 Smq
Item
Unit
Materials:
Baroda Green Marble
Sqm
Tonne
Cum
Cement
Rate
(Rs.)
Quantity
1
538.00
0.0033
0.03
80000.00
1300.00
Bags
0.14
249.00
Labour:
Tile mason
Each
0.5
250.00
Coolie (M)
Each
0.5
135.00
Total (M+L)
Add Carriage of Tiles cement etc.
0.50%
0.50%
1.00%
1.00%
15.00%
6 Supply & Fixing PVC Door with Nazarana Marble frame (2.1x 0.75)
Sr.no
Item
1 PVC Door Shutter
2 Laminate
Unit
Sqm
-
Rmt
5 Lipping Patti
5.25
538.00
Quantity
Rate
(Rs.)
Total Amt
5% Wastage on Marble
Total Amt for 1.58 Smq
Total amt for 1 Sqm
Total Amt for 1 Sft
7 Tremix Paving of 150mm thk per m2(1:1:2)
Sr.
no
A)
Item
Unit
Materials:
Cement
Sand
Bags
Cum
0.91
0.06
249.00
1139.00
Aggregate
Cum
0.12
753.35
Labour:
Mason
Female Coolie
Male Coolie
Each
Each
Each
0.02
0.12
0.12
250.00
200.00
200.00
Waterman
Each
0.05
200.00
Sqm
Sqm
0.15
0.15
0.00
0.00
Trimix
Sqm
1.00
0.00
C)
Total (M+L+Me)
Add W.C & Electricity
Add for OH & C.P
Cost per Sqm (Rs)
Cost per Sft (Rs)
1.50%
15.00%
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Paving Block
Sand
Nos
Cum
40.00
0.05
14.00
1139.00
Fine Sand
Cum
0.01
1139.00
Labour:
Mason
Each
0.02
250.00
Male Coolie
Each
0.11
135.00
B)
Total (M+L)
Add W.C & Electricity
1.50%
15.00%
9 Vitrified Tiles
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Tile (600 mm X 600 mm) + 5%
Wastage
Sand
Sqm
Cum
1
0.03
300.00
600.00
Cement
Bags
0.2
230.00
Each
0.5
250.00
Labour:
Tile mason
Coolie (M)
Each
0.5
135.00
Total (M+L)
Add Carriage of Tiles cement etc.
0.50%
0.50%
1.00%
1.00%
15.00%
Item
Unit
Rate
(Rs.)
Quantity
Materials:
Tile (600 mm X 600 mm) + 5%
Wastage
Sqm
Tonne
Cum
Cement
3766.00
0.0033
0.03
80000.00
1139.00
Bags
0.14
249.00
Labour:
Tile mason
Each
0.5
250.00
Coolie (M)
Each
0.5
135.00
Total (M+L)
Add Carriage of Tiles cement etc.
0.50%
0.50%
1.00%
1.00%
15.00%
11 20mm thk Granite cutting & fixing with sand for 5 Sqm C:M 1:6 Curved Surface Lab.only
Labour Only
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Sand
Cum
0.17
1113.00
Labour:
Tile mason
Helper
Each
Each
6.73
6.73
250.00
135.00
Supervisor
Each
1.00
300.00
Total (M+L)
Add Carriage of Tiles cement etc.
Add Mortar for pointing in
White/colour cement
0.50%
0.50%
5.00%
12.36%
1.00%
15.00%
12 20mm thk Granite cutting & fixing with sand for 5 Sqm CM 1:6 Flat Surface lab.only
Sr.
no
A)
Item
Materials:
Unit
Quantity
Rate
(Rs.)
Sand
Cum
0.17
1113.00
Labour:
Tile mason
Helper
Each
Each
5.97
5.97
250.00
135.00
Supervisor
Each
1.00
300.00
Total (M+L)
Add Carriage of Tiles cement etc.
0.50%
0.50%
5.00%
12.36%
1.00%
15.00%
13 20mm thk Pebble fixing with sand for 100 Sqm Lab.only
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Sand
Cum
5.52
1113.00
Labour:
Tile mason
Helper
Each
Each
10.5
20
250.00
135.00
Supervisor
Each
2.00
300.00
Total (M+L)
Add Carriage of Tiles cement etc.
0.50%
5.00%
12.36%
1.00%
15.00%
14 Granite Skirting cutting & fixing with sand of 4" for 50 Rmt CM 1:6 lab. only
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Sand
Cum
0.17
1113.00
Labour:
Tile mason
Helper
Each
Each
6.73
6.73
250.00
135.00
Supervisor
Each
1.00
300.00
Total (M+L)
Add Carriage of Tiles cement etc.
0.50%
0.50%
5.00%
12.36%
1.00%
15.00%
Unit
Qty
Rate
Bag
Cum
Bag
15.91
3.30
6.00
249.00
1,158.00
249.00
Nos
Nos
Nos
25.00
35.00
1.00
250.00
200.00
300.00
Total
Add 5 % Wastage
Total M
Labour
1 Mason
2 Mazdoor
3 Supervisor/HeadMason
Total L
Total M+L
Item
1 Block Board
2 Laminate
3 Wooden Frame
4 French Polish
Unit
Sqm
Sqm
Rmt
a Wooden Frame
b Shutter Edge
Sqm
Rmt
1.98
5.70
48.50
24.60
5 Lipping Patti
Rmt
5.70
82.00
Total Amt
5% Wastage
1
Hardware
Fixing
Total Amt for 1.58 Smq
Total Amt for 1 Sqm
Total Amt for 1 Sft
Date :- 130908
2 Supply & Fixing Wooden Door with Wooden frame (2.1x 0.75)
Without labour & hardware
Sr.no
Item
1 Block Board
2 Laminate
3 Wooden Frame
4 French Polish
a Wooden Frame
b Shutter Edge
Unit
Sqm
Sqm
Rmt
5 Lipping Patti
Sqm
Rmt
1.98
5.7
48.5
24.6
Rmt
5.7
82
Total Amt
5% Wastage
Total Amt for 1.58 Smq
Total Amt for 1 Sqm
Total Amt for 1 Sft
Item
Materials:
Windows 3 track
Handles
6mm clear float glass
Unit
Kg
Nos
Sqm
Quantity
15.74
2.00
6.39
Rate
(Rs.)
175.00
50.00
387.36
PVC Gasket
Wheel
Screws
Rmt
Nos
Cent
51.10
8.00
50.00
16.40
10.00
1.00
Power Coated
Kg
15.74
43.75
Labour:
Carpanter
Mistry
Each
Each
1.89
1.10
260.00
260.00
Helper
Each
1.10
135.00
1.00%
1.00%
15.00%
Total Amt.
Cost for 2.19 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Quantity
Materials:
Marine Ply shutter (35mm thick)
Laminate
Wooden Frame
Hinges
Tower bolt
Handles
Sqm
Sqm
Rmt
Nos
Nos
Nos
1.58
3.15
4.95
3.00
1.00
2.00
1291.20
235.00
211.68
75.00
75.00
120.00
Screws
Cent
48.00
1.00
Unit
Rate
(Rs.)
Labour:
Carpenter
Beldar
Each
Each
0.40
0.40
260.00
135.00
Mistry
Each
0.05
260.00
1.00%
1.00%
15.00%
Total Amt.
Cost Per 1.58 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
35 mm thick FRP Door with Vinayl
Finsih
Marble Frame (60 mm wide)
Hinges
T-tower bolt
Handles
Sqm
Rmt
Nos
Nos
Nos
1.58
4.95
3.00
1.00
2.00
3550.80
1076.00
75.00
75.00
120.00
Screws
Cent
48.00
1.00
Labour:
Carpenter
Beldar
Each
Each
0.40
0.40
260.00
135.00
Mistry
Each
0.05
260.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost Per 1.58 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
MS Angle (50x30x5mm)
20 G Ms Sheet
Hinges
Tower bolt
Handles
Rmt
Sqm
Nos
Nos
Nos
7.80
5.04
3.00
1.00
1.00
165.00
400.00
75.00
75.00
125.00
Screws
Cent
48.00
1.00
Labour:
Fabricated
Beldar
Each
Each
2.00
2.00
225.00
135.00
Mistry
Each
0.05
260.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost Per 2.52 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
1.00%
1.00%
15.00%
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Door
Hinges
Tower bolt
Handles
Sqm
Nos
Nos
Nos
2.52
3.00
1.00
1.00
1829.20
75.00
75.00
125.00
Screws
Cent
48.00
1.00
Labour:
Carpenter
Each
0.40
225.00
Beldar
Each
0.40
135.00
Mistry
Each
0.05
260.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost Per 2.52 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Windows 4 track
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws
Kg
Nos
Sqm
Rmt
Nos
Cent
40.87
2.00
6.39
21.30
8.00
50.00
210.00
150.00
387.36
16.40
10.00
1.00
Sqm
6.39
215.20
Labour:
Carpanter
Mistry
Each
Each
5.50
3.20
260.00
260.00
Helper
Each
3.20
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost for 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Windows 4 track
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws
Kg
Nos
Sqm
Rmt
Nos
Cent
40.87
2.00
6.39
21.30
8.00
50.00
210.00
150.00
387.36
16.40
10.00
1.00
Sqm
6.39
215.20
Labour:
Carpanter
Mistry
Each
Each
5.50
3.20
260.00
260.00
Helper
Each
3.20
135.00
C)
1.00%
1.00%
15.00%
Total Amt.
Cost Per 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Windows 4 track
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws
Kg
Nos
Sqm
Rmt
Nos
Cent
40.87
2.00
6.39
21.30
8.00
50.00
210.00
150.00
387.36
16.40
10.00
1.00
Sqm
6.39
215.20
Labour:
Carpanter
Mistry
Each
Each
5.5
3.2
260.00
260.00
Helper
Each
3.2
135.00
B)
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost Per 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
1.00%
1.00%
15.00%
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Windows 4 track
Handles
6mm clear float glass
Alu. Insect Net
PVC Gasket
Kg
Nos
Sqm
Sqm
Rmt
40.87
2.00
3.19
3.19
21.30
210.00
150.00
387.36
215.20
16.40
Wheel
Screws
Nos
Cent
8.00
50.00
10.00
1.00
Sqm
6.39
215.20
Labour:
Carpanter
Mistry
Each
Each
5.5
3.2
260.00
260.00
Helper
Each
3.2
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost Per 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Materials:
Unit
Quantity
Rate
(Rs.)
Sqm
Sqm
Rmt
Nos
Nos
Nos
Nos
2.52
5.04
5.40
3.00
1.00
2.00
1.00
1291.20
235.00
211.68
75.00
225.00
350.00
15.00
Screws
Cent
48.00
1.00
Labour:
Carpenter
Beldar
Each
Each
0.40
0.40
260.00
135.00
Mistry
Each
0.05
260.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost Per 1.58 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Materials:
Marine Ply shutter (35mm thick)
Laminate
Wooden Frame
Hinges
Tower bolt
Handles
Rubber buffer
Unit
Sqm
Sqm
Rmt
Nos
Nos
Nos
Nos
Quantity
2.88
5.76
5.60
3.00
1.00
2.00
1.00
Rate
(Rs.)
1291.20
235.00
211.68
75.00
225.00
350.00
15.00
Screws
Cent
48.00
1.00
Labour:
Carpenter
Beldar
Each
Each
0.60
0.60
260.00
135.00
Mistry
Each
0.10
260.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost Per 1.58 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Top & bottom horizontal frame
127x38.1x1.74mm Wt/rmt= 1.518
Vertical frame 50x50x2mm thk (4' c/c)
Wt/rmt = 1.036
Sutter
Frame wt/rmt =0.593
6mm clear float glass (0.97x 2.8)
Handles
PVC Gasket
Hinges
Tower bolt
Alu.Stopper
Screws
Kg
Sqm
Nos
Rmt
Nos
Nos
Nos
Cent
13.22
2.72
1.00
7.54
3.00
1.00
1.00
50.00
210.00
387.36
150.00
16.40
100.00
225.00
225.00
1.00
Sqm
2.72
215.20
B)
Labour:
Carpanter
Mistry
Each
Each
5.5
3.2
260.00
260.00
Helper
Each
3.2
135.00
Total (M+L)
Add for Sundries & Contingencies
Add Vat & Serivce Tax
Add W.C & Electricity
1.00%
9.12%
1.00%
15.00%
Total Amt.
Cost Per 2.72 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Windows 4 track
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws
Kg
Nos
Sqm
Rmt
Nos
Cent
40.87
2.00
6.39
21.30
8.00
50.00
210.00
150.00
387.36
16.40
10.00
1.00
Sqm
6.39
215.20
Labour:
Carpanter
Mistry
Each
Each
5.5
3.2
260.00
260.00
Helper
Each
3.2
135.00
B)
C)
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost Per 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Frame of RCC (0.6 x 0.75= 0.42)
Nos
1.00
364.50
Labour:
Mason
Each
1.00
260.00
Helper
Each
2.00
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add vat & Service tax
Add for OH & C.P & Taxs
Total Amt.
Cost for 0.42 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
FALSE CEILING
0.50%
1.00%
9.12%
15.00%
Rmt
Rmt
Sqm
Sqm
Sqm
12.24
6.98
3.55
1.22
0.70
67.00
67.00
603.00
124.00
124.00
nos.
nos.
2.25
3.50
260.00
165.00
Rmt
Rmt
Sqm
12.24
6.98
3.55
67.00
67.00
75.00
nos
nos
2.00
2.50
275.00
200.00
Total
Add 5 % wastage
Screws & Suspenderes 5%
Total-M
Labours
Carpenter
Male majdoor
Total-L
Total M+L
2% for Equip.Ele.etc.
Add 15% for O.H.& Profit
Total for 3.55sqm.Rs
Total for 1 sqm.Rs
Total for 1 sqft.Rs
2 Rate Anly for POP False Ceiling 3.55 sqmt.
Material
L-Patti 18 guage
T-Patti
POP Sheet 4mm
Total
Add 5% for Wastage
Screws & Suspenderes 5%
Total -M
Labours
Carpenter
Male majdoor
Total-L
Total-M+L
2% for Equip.Ele.etc.
Add 15% for O.H.& Profit
Total for 3.55 sqm.Rs
Total for 1 sqm.Rs
Total for 1 sqft.Rs
Rmt
Rmt
Sqm
12.24
6.98
3.55
67.00
67.00
135.00
nos
nos
2.00
2.50
260.00
165.00
Total
Add 5% for Wastage
Screws & Suspenderes 5%
Total -M
Labours
Carpenter
Male majdoor
Total-L
Total-M+L
2% for Equip.Ele.etc.
Add 15% for O.H.& Profit
Total for 3.55 sqm.Rs
Total for 1 sqm.Rs
Total for 1 sqft.Rs
H
Description
Unit
Qty
Rate
Material
1 50 mm UPVC Pipe
2 Coupling
Rmt
Nos
100.00
17.00
55.00
14.00
Labour
1 Fitter
2 labour
Nos
Nos
1.00
1.00
200.00
150.00
Total
Add 2% Contengencies
Add Vat & S.Tax 9.12%
Add OH & Profit 15%
G.Total
Rate Per/Rmt.
Description
Material
1 50 mmG.I. Pipe
2 Coupling
Unit
Rmt
Nos
100.00
17.00
276.00
97.00
Labour
1 Fitter
2 Labour
Nos
Nos
1.00
1.00
200.00
150.00
Total
Add 2% Contengencies
Add Vat & S.Tax 9.12%
Add OH & Profit 15%
G.Total
Rate Per/Rmt.
Qty
Rate
Description
Material
1 50 mmHDPE Pipe
Unit
Qty
Rate
Rmt
100.00
133.00
Labour
1 Fitter
Nos
1.00
200.00
Total
Add 2% Contengencies
Add Vat & S.Tax 9.12%
Add OH & Profit 15%
G.Total
Rate Per/Rmt.
4 PVC 110mm dia.of 6kgf/cm2 for 6 Rmt with Pocket in wall & Grouting
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Pipe (6M)
Bend
Coupler
PVC Solution
rmt
No
No
Ls
1.00
1.00
1.00
1.00
1562.00
260.00
75.00
100.00
Grouting
No
1.00
225.00
Each
Each
1.00
1.00
200.00
135.00
Labour:
Plumber
Helper
For trenching and refilling etc:-
Helper
Each
1.00
135.00
0.50%
1.00%
9.12%
15.00%
Total Amt.
Cost for 6 Rmt(Rs.)
Cost Per 1 Rmt (Rs.)
Cost per 1 Rft (Rs.)
Date: 3rd D
5 160 mm dia Supreme UPVC (6 kg pressure) Pipe line (6 Mtr Long)
Sr.
no
A)
B)
Item
Unit
Materials:
1 Pipe (6kg)
2 Bend
3 Coupler
Nos
Nos
Nos
4 Pvc Solution
Ls
Quantity
1.00
1.00
1.00
3297.00
1108.00
230.00
Ls
100.00
6.00
90.00
Mts
Rate
(Rs.)
Total (M+L)
Add
Vat & other Taxes
5%
Contractor Profit
10%
B)
Item
Unit
Materials:
1 Pipe (6kg)
2 Bend
3 Coupler
Nos
Nos
Nos
4 Solution
Ls
Quantity
Rate
(Rs.)
1.00
1.00
1.00
1914.00
1108.00
230.00
Ls
100.00
6.00
90.00
Mts
Total (M+L)
Add
Vat & other Taxes
5%
Contractor Profit
10%
SANITARY WARE
Item
Materials:
W.C
Unit
Nos
Quantity
1.00
Rate
(Rs.)
4500.00
Nos
1.00
900.00
Clamp
Nos
4.00
75.00
Labour:
Plumber
Mistry
Each
Each
1
0.5
225.00
260.00
Helper
Each
135.00
B)
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
9.12%
15.00%
Total Amt.
Cost Per No (Rs.)
FABRICATION
Date: 3rd D
1 Fabricated M.S. Man- hole Cover
Sr.
no
A)
B)
Item
Unit
Quantity
Materials:
M.S Angle (65x65x6mm)
Rmt
8.00
319.00
Sqm
1.00
4000.00
Each
2.00
225.00
Coolie
Each
1.00
135.00
Rate
(Rs.)
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
1.00%
1.00%
15.00%
Total Amt.
Cost Per 1 Sqm (Rs.)
Cost per 1 sft (Rs.)
B)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
M.S Angle (65x65x6mm)
Rmt
2.60
319.00
No
1.00
6124.00
Each
1.00
225.00
Coolie
Each
1.00
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
10.00%
Item
1 B/W Video Door Phone with Fitting
Unit
Nos
Quantity
1.00
Rate
(Rs.)
7000.00
Sr.
no
Item
Unit
Quantity
Nos
1.00
Rate
(Rs.)
13000.00
WATERPROOFING
1 Inclined Surface Gradient Available
Date
Sr.No. Description
Material
For 100 Sqmt.
1 Dr Fixit Pidiproof 2k for BaseCoat
2 Screed Plaster 1:3 (15mm thk.)
a Cement
b Fine & Coarse Agg.
c Dr Fixit Pidiproof LW 200ml Per Bag
Unit
Kg
Qty
Rate
154.00
110.00
Bag
Cum
Kg.
18.00
1.80
3.60
249.00
1,158.00
84.00
Nos
Nos
Nos
15.00
21.00
0.63
250.00
150.00
300.00
Total
Add 5 % Wastage
Total M
Labour
1 Mason
2 Mazdoor
3 Supervisor/HeadMason
Total L
Total M+L
Date
Sr.No. Description
For 100Sqm
A
Material
1 Dr Fixit Pidiproof 2k for Base Coat
2 Screed Plaster 1:3 (15mm thk.)
a Cement
b Fine & Coarse Agg.
c Dr Fixit Pidiproof LW 200ml Per Bag
3 BrickBat 110 mm thk.70%
Unit
Kg
Qty
Rate
154.00
110.00
Bag
Cum
Ltrs.
Cum
18.00
1.80
3.60
7.70
249.00
1,158.00
84.00
1,129.00
4.13
30.00
3.09
6.00
249.00
1,158.00
84.00
37.00
59.00
2.00
250.00
150.00
300.00
Total
Add 5% For Wastage
Total M
B
Labour
1 Mason
2 Mazdoor
3 Supervisor /Head Mason
Nos
Nos
Nos
Total L
Total M+L
Date
Sr.No. Description
Material
For 100 Sqmt.
1 Dr Fixit Pidiproof 2k for BaseCoat
2 Screed Plaster 1:3 (40mm thk.)
a Cement
b Fine & Coarse Agg.
c Dr Fixit Pidiproof LW 200ml Per Bag
Unit
Kg
Qty
Rate
154.00
110.00
Bag
Cum
Kg.
48.00
4.80
9.60
249.00
1,158.00
84.00
Nos
Nos
Nos
25.00
35.00
1.00
250.00
150.00
300.00
Total
Add 5 % Wastage
Total M
Labour
1 Mason
2 Mazdoor
3 Supervisor/HeadMason
Total L
Total M+L
Landscaped Area
DateSr.No. Description
For 100Sqm
A
Material
1 Filling 25 Sqm 1:4 25mm thk
Cement
Unit
Bag
Qty
Rate
8.00
249.00
Coarse Agg.
Cum
2 Dr Fixit Pidiproof 2k for Base Coat
Kg
3 Screed Plaster 1:4(15mm thk.)
a Cement
Bag
b Fine & Coarse Agg.
Cum
c Dr Fixit Pidiproof LW 200ml Per Bag Ltrs.
4 BrickBat 110 mm thk.70%
Cum
4 Mortar 30% of 1:4 & add 25 % for Wet Cum
a Cement
Bag
b Fine & Coarse Agg.
Cum
c Dr Fixit Pidiproof LW 200ml Per Bag Ltrs.
5 Metal 15 mm thk 70%
Cum
Mortar 30% of 1:4 & add 25 % for Wet Cum
a Cement
Bag
b Sand
Cum
6 Rough Finish Plaster 1:4(15mm thk.)
a Cement
Bag
b Fine & Coarse Agg.
Cum
0.78
154.00
725.00
110.00
18.00
2.40
3.60
7.70
4.13
30.00
4.12
6.00
1.05
0.56 30.00
4.12
249.00
1,158.00
84.00
1,129.00
249.00
1,158.00
84.00
1,158.00
18.00
2.40
249.00
1,158.00
50.00
77.00
4.00
250.00
135.00
300.00
249.00
1,158.00
Total
Add 5% For Wastage
Total M
B
Labour
1 Mason
2 Mazdoor
3 Supervisor /Head Mason
Nos
Nos
Nos
Total L
Total M+L
Date
Sr.No. Description
Unit
Detail of cost of demolihing 1 cum brick work
Labour
2 Mazdoor (M)
Nos
3 Mazdoor (F)
Nos
4 Supervisor/HeadMason
Nos
Qty
Rate
0.95
0.85
0.10
135.00
125.00
300.00
Total L
Total L
Add for Cost & Sharpening of
Chisels sledge hammers
Add for Service Tax
Add for sundries & Contingencies
Contractors Profit & O.H.15%
5%
10.30%
3%
15%
Dismantling Doors, Windows of area 3 sqm and below & stacking with in 50 m lead
Date
Sr.No. Description
Unit
Detail of cost of Dismantling Doors, Windows
Labour
1 Carpenter
Nos
2 Mazdoor (M)
Nos
4 Supervisor/HeadMason
Nos
Total L
Total L
Qty
Rate
0.10
0.25
0.10
260.00
135.00
300.00
3%
10.30%
3%
15%
Demolishing Tile flooring laid in cement mortar inculiding disposal of material with in 50 m
Date
Sr.No. Description
Unit
Detail of cost of demolishing 10 Sqm
Labour
2 Mazdoor (M)
Nos
3 Mazdoor (F)
Nos
4 Supervisor/HeadMason
Nos
Qty
Rate
1.50
0.65
0.10
135.00
125.00
300.00
Total L
Total L
Add for Service Tax
Add for sundries & Contingencies
Contractors Profit & O.H.15%
10.30%
3%
15%
Water Proofing in Lift Pit with Socket Grouting & Metal Coving
Sr.No. Description
Unit
Qty
Rate
Kg
29.57
110.00
Bag
Cum
Ltrs.
Cum
3.00
0.30
0.60
0.88
249.00
1,158.00
84.00
698.00
0.47
3.35
0.35
0.67
249.00
1,158.00
84.00
Ltrs.
Ltrs.
6.00
0.03
251.00
84.00
Nos
Nos
Nos
9.50
15.00
0.50
250.00
150.00
300.00
Total
Total M
B
Labour
1 Mason
2 Mazdoor
3 Supervisor /Head Mason
Total L
Total M+L
Contractors Profit & O.H.15%
G.Total for 23.4Sqm
Rate For 1Sqm
Rate For 1Sft
Rate
100.00
2.00
Total- M
Labours
Male mazdoor
Supervisor
nos
nos
4.00
0.10
135.00
300.00
Total-L
Total-M+L
1% Add for Sundries & Contingencies
Add Tax Vat & Service Tax
Add 10% for O.H.& Profit
1.00%
9.12%
10.00%
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Sand Bed 1x10x0.1
Cum
1.00
1176.00
Cum
0.33
1176.00
Each
0.13
260.00
Labour:
Mason
Mazdoor
Each
1.10
135.00
Each
0.10
300.00
15.00%
Total Amt.
Cost Per 2.3 Cum (Rs.)
Cost Per 1 Cum (Rs.)
Cost per 1 Cft (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
Bag
0.32
249.00
Sand
Cum
0.03
1176.00
Labour:
Mason
Mazdoor
Each
Each
2.00
2.15
260.00
135.00
Supervisor
Each
0.10
300.00
15.00%
Sr
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Stone
Cement
Cum
Bag
12.5
10.50
700
249.00
Sand
Cum
2.20
1175.00
Labour:
Mason
Mazdoor
Each
Each
25.00
35.00
260.00
135.00
Supervisor
Each
0.50
300.00
D)
15.00%
9.12%
Total Amt.
Cost Per 10 Cum (Rs.)
Cost Per 1 Cum (Rs.)
Cost per 1 Cft (Rs.)
Date: 26.06.09
Aluminium Louvers (0.6 x 0.9) with 5mm Clear Float Glass using Powder Coating
Sr
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Aluminium Louver (0.6 x 0.9)
Nos
1.00
1300.00
Sqm
Cent
0.59
50.00
388.00
1.00
Sqm
0.41
108.46
B)
Labour:
Fitter
Mazdoor
Each
Each
0.40
0.40
260.00
135.00
Supervisor
Each
0.10
300.00
Total (M+L)
Add for S & C
Add for W.C & Elec.
1.00%
1.00%
15.00%
Total Amt.
Cost Per 0.54 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Materials:
Cement
Sand
Agg (AI+AII)
Steel
materials:
Unit
Quantity
Rate
(Rs.)
Bags
Cum
Cum
Kg
Sqm
0.370
0.026
0.053
2.160
1.230
249.00
1175.97
643.10
45.00
250.00
Each
Each
Each
Each
0.002
0.043
0.043
0.004
260.00
135.00
125.00
260.00
Labour:
Foreman
Beldar (M)
Coolie (F)
Mason
Waterman
Each
0.002
135.00
Total (M+L)
Add for Eqn
6.00%
15.00%
Total Amt.
Cost Per 1 Cum (Rs.)
Est.Dpt
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Stone
Cement
Cum
Bag
12.5
10.50
700
249.00
Sand
Cum
2.20
1175.00
Labour:
Mason
Mazdoor
Each
Each
12.00
20.00
260.00
135.00
Supervisor
Each
0.50
300.00
D)
15.00%
0.00%
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Stone + wastage 15%
Cum
2.59
700.00
Cum
0.56
1175.00
Labour:
Mason
Mazdoor
Each
Each
2.10
4.00
260.00
135.00
Each
0.10
300.00
15.00%
Total Amt.
Cost Per 10 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Asian Brand
Plastic Emulsion Paint
Litre
1.67
162.00
Labour:
Painter
Male Coolie
Each
Each
0.80
0.60
250.00
135.00
Supervisor
Each
0.20
300.00
Total (M+L)
Add for Sundries & Contingencies
Brushes Sand Paper Putty Etc.
Add for Scaffolding Ladder Etc.
Add W.C & Electricity
3.00%
5.00%
5.00%
0.50%
15.00%
Total Amt.
Cost For 10Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Asian Brand
Plastic Emulsion Paint
Litre
1.82
149.85
Scaffolding Eraction
Sqm
10.00
35.20
Labour:
Painter
Male Coolie
Each
Each
0.80
0.60
250.00
135.00
Supervisor
Each
0.20
300.00
Total (M+L)
Add for Sundries & Contingencies
3.00%
5.00%
0.50%
15.00%
Total Amt.
Cost For 10Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Materials:
Plaster of Paris
Scaffolding
Qty.
Rate
bag
Sqm
4.12
10.00
70.00
31.00
Labour:
Mason
Helper
Each
Each
1.65
2.29
260.00
135.00
Supervisor
Each
0.15
300.00
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
bag
25.00
249.00
Sand
Cum
4.38
1176.00
Brick
Nos
5000.00
3.22
Labour:
Mason
Each
8.50
235.00
Helper
Each
16.00
135.00
Supervisor
Each
1.00
300.00
3.00%
3.00%
1.00%
15.00%
Total Amt.
Cost for 10 Cum (Rs.)
Cost Per 1 Cum (Rs.)
Addition 1% per floor till 21st floor
(Terrace)
21%
Item
Unit
Qty.
Rate
A)
Materials:
Cement
bag
20.00
249.00
Sand
Cum
2.40
1113.00
Scaffolding
Sqm
100.00
31.00
Mason
Each
17.50
260.00
Helper
Each
25.00
135.00
Labour:
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
Bags
4.560
249.00
Sand
Cum
0.470
1175.00
Agg (AI+AII)
Cum
0.930
643.00
Kgs
52.000
35.12
Each
0.040
260.00
Labour:
Foreman
Beldar (M)
Each
0.700
135.00
Coolie (F)
Each
0.700
125.00
Mason
Each
0.070
260.00
Waterman
Each
0.035
135.00
6.00%
15.00%
Total Amt.
Cost Per 1 Cum (Rs.)
Cost per 1 Sqm (Rs.) of 150mm thk
Cost Per 1 Sft (Rs.)
21%
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Timber
Cum
0.0363
27519
Labour:
Carpenter 1 Class
Each
0.65
260.00
Beldar
Each
0.65
135.00
3.00%
1.00%
15.00%
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Assian Varnish
Litre
0.228
141
turpentine oil
Litre
1.63
70
Labour:
Painter
Each
3.20
200.00
Supervisor
Each
0.20
300.00
7.50%
3.00%
1.00%
15.00%
Item
Unit
Quantity
Rate
(Rs.)
A)
Materials:
Casecase Windows
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws
Kg
Nos
Sqm
Rmt
Nos
Cent
11.20
2.00
1.43
11.44
8.00
50.00
175.00
145.00
387.36
16.40
10.00
1.00
Power Coated
Kg
11.20
43.75
Labour:
Carpanter
Mistry
Each
Each
1.89
1.10
260.00
260.00
Helper
Each
1.10
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost for 1.43qm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
bag
4.43
249.00
Sand
Cum
0.47
1175.00
M-I,M-II
Cum
0.92
644.00
Each
0.14
260.00
Labour:
Mason
Helper
Each
2.00
200.00
0.50%
1.00%
15.00%
Total Amt.
Cost for 1 Cum (Rs.)
Cost per 1 Cft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
bag
20.00
249.00
Sand
Cum
4.20
1175.00
Brick
Nos
5000.00
3.70
Labour:
Mason
Each
8.50
235.00
Helper
Each
16.00
135.00
15.00%
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
bag
13.00
249.00
Sand
Cum
4.74
1175.00
Brick
Nos
5000.00
3.70
Labour:
Mason
Each
8.50
235.00
Helper
Each
16.00
135.00
0.50%
1.00%
15.00%
Total Amt.
Cost for 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 sft (Rs.)
Item
Quantity
Materials:
Cement
bag
19.00
249.00
Sand
Cum
4.05
1176.00
Brick
Nos
5000.00
3.70
Unit
Rate
(Rs.)
Labour:
Mason
Each
8.50
235.00
Helper
Each
16.00
135.00
0.50%
1.00%
15.00%
Total Amt.
Cost for 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 sft (Rs.)
Rate
32,239.00
50.00
10.00 Day
10.00 Day
250.00
135.00
Crazy Pattern Flame Granite /Ikon Brown Flooring 18mm thk on the C.C.1:2:4 Bed
Sr.
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Subgrade -For 10Sqm ,25mm thk
Cement
Sand
Coarse Agg.
bag
Cum
Cum
1.53
0.11
0.21
249.00
1139.00
643.00
Sqm
Sqm
Kg
Kg
10.00
0.50
40.00
36.50
1725.00
1725.00
5.00
12.00
Kg
2.55
30.00
Labour:
Supervisor
Mason
Each
Each
0.9
1.75
300
235.00
Male Coolie
Each
5.12
135.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
0.50%
1.00%
15.00%
Total Amt.
Cost for 10 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
A)
Materials:
Wood 20mm thk.
Cum
0.02
35000.00
Cum
Cum
0.03
0.01
35000.00
35000.00
Screws/Hardware
L.S.
1.00
100.00
Carpenter
Beldar
Each
Each
0.30
0.30
260.00
135.00
Supervisor
Each
0.05
260.00
Labour:
1.00%
1.00%
15.00%
Total Amt.
Cost Per 1.08 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
B)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
4" thk Brick
Cement
Nos
Bags
5,320.00
14.45
4.00
249.00
Sand
Cum
2.02
1,175.00
Each
Each
0.50
16.00
300.00
260.00
Helper
Each
23.00
200.00
C)
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost Per 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
B)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Cement
Bags
10.72
249.00
Sand
Cum
1.56
1,175.00
Each
Each
0.25
17.50
300.00
260.00
Helper
Each
25.00
200.00
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
1.00%
15.00%
Total Amt.
Cost Per 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
Item
Unit
Quantity
Rate
(Rs.)
A)
B)
Materials:
Channel (100 x 50 mm)
Baseplater
Anchor Fastern
Kgs
Kgs
No
230.00
15.00
16.00
50.00
55.00
50.00
Gypsum Sheet
Sqm
14.00
135.00
35%
0.35
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
1.00%
3.00%
15.00%
Total Amt.
Cost Per 10 Rmt (Rs.)
Cost Per 1 Rmt (Rs.)
Cost per 1 Rmt (Rs.)
B)
Item
Unit
Materials:
Channel (1" x 1 "x2.5 mm)
Glass
Track 2
Rmt
Sqm
Rmt
Fitting
LS
Quantity
3.00
10.00
3.00
82.00
1,560.78
1,198.00
1.00
2,700.00
25%
0.25
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Rate
(Rs.)
1.00%
1.00%
15.00%
B)
Item
Unit
Materials:
rate per rolling per sq.mt. =22.5/for 100 sq.mt.
nail
Rmt
Sqm
kg.
jute rassi
Quantity
Rate
(Rs.)
100.00
0.50
22.50
45.00
kg.
10.00
10.00
0.60
C)
Total (M+L)
Add transportation charges
3.00%
15.00%
Total Amt.
Cost Per 100 Sqmt. (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sqm (Rs.)
RATE ANALYSIS
Rate analysis of providing and laying of 25mm thick shalitex board for expansion
sr.no.
unit
quantity
rate
no.
no.
no.
no.
100
625
10
625
4
0.5
4
4
200
350
300
250
B)
Item
Unit
Materials:
Channel (1" x 1 "x2.5 mm)
Glass
Track 2
Rmt
Sqm
Rmt
Fitting
LS
Quantity
3.00
10.00
3.00
82.00
1,560.78
1,198.00
1.00
2,700.00
25%
0.25
Total (M+L)
Add for Sundries & Contingencies
Rate
(Rs.)
1.00%
1.00%
15.00%
Total Amt.
Cost Per 10 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sqm (Rs.)
Filling of Siprox Block with 110 Thk C:M 1:4 for 1.32 Cum
Sr
no
A)
Item
Unit
Quantity
Rate
(Rs.)
Materials:
Siprox Block
Cum
1.21
3600.00
Sand
Cum
0.60
1590.00
Labour:
Mason
Helper
Each
Each
0.66
4.80
300.00
200.00
Each
0.10
350.00
15.00%
Filling of Siprox Block with 400 thk C:M 1:4 with top slurry of 12 mm thk C:M 1:4 for 4.8 Cum
Sr
no
A)
Item
Unit
Rate
(Rs.)
Quantity
Materials:
Siprox Block
Cum
4.32
3780.00
Sand
Cum
0.60
1590.00
Labour:
Mason
Helper
Each
Each
2.40
15.00
300.00
200.00
Each
0.25
350.00
15.00%
Total Amt.
Cost Per 4.8 Cum `
Cost Per 1 Cum `
Cost per 1 Cft `
Item
Unit
Quantity
-
A)
Materials:
Sq.mt.
B)
each
Rate
(Rs.)
350
coolie
each
2.1
D)
5%
15%
250
Sr.
no
A)
1892.40
824.59
445.52
3162.52
Item
Materials:
Cement
Sand
Bags
Cum
Agg (AI+AII)
Cum
10.4
94.5
87.5
18.2
Labour:
Foreman
Beldar (M)
Coolie (F)
Mason
Each
Each
Each
Each
4.725
Waterman
Each
215.33
3377.84
202.67
C)
506.68
Total (M+L)
Add for Eqn
Add for OH & C.P & Tax
4087.19
Total Amt.
4087.19
1
Amount.
(Rs.)
Unit
0.00
513.04
638.00
1151.04
12.00
12.00
32.50
210.00
6.00
12.25
12.00
12.00
308.75
125.00
37.50
50.00
212.50
1672.29
250.84
1923.13
1923.13
Sr.
no
A)
2463.30
222.00
462.50
3147.80
Unit
Materials:
Cement
Sand
Bags
Cum
Agg (AI+AII)
Cum
12.00
Item
Labour:
Foreman
Each
140.00
140.00
18.20
Beldar (M)
Coolie (F)
Mason
Each
Each
Each
7.00
Waterman
Each
317.20
3465.00
277.20
519.75
Total (M+L)
Add for Eqn
Add for OH & C.P & Tax
4261.95
Total Amt.
4261.95
29,400.00
150.00
Sr.
no
A)
29,550.00
2,500.00
1,500.00
Item
Materials:
Cement
Sand
Bags
Cum
Agg (AI+AII)
Cum
4,000.00
33,550.00
671.00
5,032.50
Labour:
Foreman
Beldar (M)
Coolie (F)
Mason
Each
Each
Each
Each
Waterman
Each
39,253.50
C)
113,850.00
21,600.00
67,795.20
Unit
12,711.60
19,000.00
234,956.80
23,495.68
6,900.00
4,600.00
11,500.00
34,995.68
699.91
699.91
36,395.51
5,459.33
41,854.83
279.03
25.93
Date: 11.02.09
Tremix Paving of 75 mm thk per m2 using M25 grade concrete
Amount.
(Rs.)
Sr.
no
A)
206.67
34.74
41.88
150.00
48.00
481.29
Item
Unit
Materials:
Cement
Sand
Aggregate
Colour Pigment & Hardener
Bags
Cum
Cum
Kgs
Shuttering
Sqm
Labour:
Mason
Skilled Labour
Unskilled Labour
Each
Each
Each
15.00
Carpenter
Each
32.85
2.25
8.10
7.50
C)
24.00
12.00
Mechinary
Mixer with Operater
Vibrator with Operater
Cum
Cum
135.00
171.00
Sub-Total of Mechinary
685.14
10.28
Total (M+L)
Add W.C & Electricity
D)
102.77
798.19
74.181
Sr.
no
A)
Item
Unit
343.20
87.15
Materials:
Brick-4"X3.5"X9"
Cement
Nos
Bags
137.07
Sand
Cum
567.42
Labour:
Supervisor
Mason
Nos
Nos
75.32
Mazdoor
Nos
75.32
659.90
Total (M+L)
C)
19.80
13.20
98.98
791.88
Total Amt.
791.88
73.59
Amount.
(Rs.)
21280.00
3598.05
2373.50
27251.55
150
4160
4600
4600.00
31851.55
138.00
92.00
690.00
32771.55
32771.55
327.72
30.46
Sr.
no
A)
928.28
-313.97
614.31
76.79
46.00
737.10
36.85
773.95
31.125
Item
Unit
Materials:
Block-4"X8"X26"
Cement
Nos
Bags
Sand
Cum
B)
Labour:
Supervisor
Mason
Nos
Nos
16.13
Mazdoor
75.32
896.53
83.32
Amount.
(Rs.)
6225.00
4874.94
18500.00
29599.94
1997.50
2160.00
4157.50
33757.44
168.79
339.26
5114.51
39379.99
Nos
39379.99
3938.00
111.62
Amount.
(Rs.)
480.00
4950.00
5430.00
3400.00
2295.00
5695.00
11125.00
333.75
222.50
1668.75
13350.00
13350.00
133.5
12.41
Amount.
(Rs.)
0.00
1800.00
1800.00
3400.00
2295.00
5695.00
7495.00
224.85
149.90
1124.25
8994.00
8994.00
89.94
8.36
Amount.
D-200309
(Rs.)
ates)
296.88
296.88
150.00
67.50
217.50
514.38
15.43
25.72
12.86
2.57
77.16
648.11
648.11
64.81
6.02
Amount.
D-200309
(Rs.)
75
225.00
225.00
150.00
67.50
217.50
442.50
13.28
22.13
11.06
2.21
66.38
557.55
557.55
55.76
5.18
Date :- 130908
nly
Amount. (Rs.)
2988.00
1822.40
5184.00
9994.40
499.72
10494.12
104.94
9.75
Amount. (Rs.)
2988.00
1822.40
632.50
5442.90
272.145
5715.045
57.15
5.31
Amount.
(Rs.)
2988.00
1822.40
17400.00
22210.40
3380.00
1755.00
202.50
5337.50
27547.90
826.44
550.96
4132.19
33057.48
33057.48
330.57
30.72
Amount.
(Rs.)
2988.00
1822.40
3300.00
8110.40
3380.00
1755.00
202.50
5337.50
13447.90
403.44
268.96
2017.19
16137.48
16137.48
161.37
15.00
Sr.
no
A)
Item
Unit
Materials:
Cement
Bags
138.30
Silpoz
Cum
178.14
39.84
B)
80.7
80.70
Labour:
Supervisor
Mason
Nos
Nos
Mazdoor
Nos
258.84
Total (M+L)
C)
6.57
4.38
32.85
302.64
Total Amt.
302.64
28.13
Amount.
(Rs.)
Sr.
no
A)
Item
Unit
39.84
Materials:
Cement
Bags
34.17
sand
Cum
74.01
B)
80.7
80.70
Mazdoor
Nos
Total (M+L)
C)
12.11
Nos
Nos
154.71
2.42
1.61
Labour:
SuperVisor
Mason
170.85
Total Amt.
170.85
15.88
Amount.
(Rs.)
3510.90
1569.33
2500.00
7580.23
4550.00
3375.00
7925.00
15505.23
77.53
155.83
1414.08
2349.16
19501.82
19501.82
195.02
18.12
Amount.
41.65
24.49
6.20
9.30
81.64
4.08
85.72
45.00
45.00
45.00
130.72
130.72
2.61
2.61
135.95
13.59
20.39
169.93
165.00
Amount.
4,980.00
2,671.20
3,100.00
10,751.20
4,550.00
3,375.00
7,925.00
18,676.20
373.52
2,801.43
21,851.15
21,851.15
218.51
20.31
Amount.
(Rs.)
162.00
264.00
32.50
34.86
493.36
125.00
67.50
192.50
685.86
3.43
3.43
6.86
6.86
102.88
809.31
75.22
Amount.
(Rs.)
485.00
264.00
32.50
34.86
816.36
125.00
67.50
192.50
1008.86
5.04
5.04
10.09
10.09
151.33
1190.45
110.64
Amount.
(Rs.)
250.00
264.00
32.50
34.86
581.36
125.00
67.50
192.50
773.86
3.87
3.87
7.74
7.74
116.08
913.15
84.87
2979.84
276.94
Amount.
(Rs.)
538.00
264.00
32.50
34.86
869.36
125.00
67.50
192.50
1061.86
5.31
5.31
10.62
10.62
159.28
1252.99
116.45
Amount. (Rs.)
2765.00
-
2824.5
5589.50
141.23
5730.73
3627.04
337.09
Tremix Paving of 100mm thk per m2(1:1:2)
Amount.
(Rs.)
Sr.
no
A)
Item
Unit
226.59
72.90
Materials:
Cement
Sand
Bags
Cum
87.39
Aggregate
Cum
386.87
Labour:
Mason
Female Coolie
Male Coolie
Each
Each
Each
Waterman
Each
0.00
0.00
Sqm
Sqm
0.00
Trimix
Sqm
0.00
4.50
24.00
24.00
9.00
61.50
C)
448.37
6.73
D)
Total (M+L+Me)
Add W.C & Electricity
67.26
522.36
48.546
Sr
no
A)
560.00
56.95
11.39
628.34
Item
Unit
Materials:
Paving Block
Sand
Nos
Cum
Fine Sand
Cum
Labour:
Mason
Each
15.12
Male Coolie
Each
19.32
4.20
647.66
9.71
C)
Total (M+L)
Add W.C & Electricity
97.15
754.52
70.12
Amount.
(Rs.)
300.00
15.00
46.00
361.00
125.00
67.50
192.50
553.50
2.77
2.77
5.54
5.54
83.03
653.13
60.70
Amount.
(Rs.)
3766.00
264.00
28.48
34.86
4093.34
125.00
67.50
192.50
4285.84
21.43
21.43
42.86
42.86
642.88
5057.29
470.01
d Surface Lab.only
Amount.
(Rs.)
183.65
183.65
1682.50
908.55
300.00
2891.05
3074.70
15.37
15.37
153.73
380.03
30.75
461.20
4131.16
826.23
76.79
rface lab.only
Amount.
(Rs.)
183.65
183.65
1492.50
805.95
300.00
2598.45
2782.10
13.91
13.91
139.10
343.87
27.82
417.31
3738.02
747.60
69.48
Amount.
(Rs.)
6143.76
6143.76
2625.00
2700.00
600.00
5925.00
12068.76
29.63
296.25
732.33
59.25
888.75
14074.97
140.75
13.08
. only
Amount.
(Rs.)
183.65
183.65
1682.50
908.55
300.00
2891.05
3074.70
15.37
15.37
153.73
380.03
30.75
461.20
4131.16
82.62
25.19
Amount
0.00
3,821.40
0.00
3,821.40
191.07
4,012.47
6,250.00
7,000.00
300.00
13,550.00
17,562.47
1,601.70
2,634.37
21,798.54
217.99
20.26
ng and hardware
Amount. (Rs.)
1126.13
1050.53
2609.25
96.03
140.22
467.4
5489.55
274.48
2600.00
540.00
8904.03
5635.46
523.74
Date :- 130908
Amount. (Rs.)
1126.13
1050.53
2609.25
96.03
140.22
467.4
5489.55
274.48
5764.03
3648.12
339.04
Sr.
no
A)
Item
Materials:
Windows 3 track
Handles
6mm clear float glass
Unit
Kg
Nos
Sqm
838.04
80.00
50.00
PVC Gasket
Wheel
Screws
Rmt
Nos
Cent
688.73
Kg
6985.97
491.03
285.48
Labour:
Carpanter
Mistry
Each
Each
148.23
Helper
Each
924.74
7910.70
Total (M+L)
C)
79.11
79.11
1186.61
9255.52
Total Amt.
9255.52
4226.27
392.78
Amount.
(Rs.)
2033.64
740.25
1047.82
225.00
75.00
240.00
48.00
4409.71
104.00
54.00
13.00
171.00
4580.71
45.81
45.81
687.11
5359.43
5359.43
3392.04
315.25
Amount.
(Rs.)
5592.51
5326.20
225.00
75.00
240.00
48.00
11506.71
104.00
54.00
13.00
171.00
11677.71
116.78
116.78
1751.66
13662.92
13662.92
8647.42
803.66
Amount.
(Rs.)
1287.00
2016.00
225.00
75.00
125.00
48.00
3776.00
450.00
270.00
13.00
733.00
4509.00
45.09
45.09
676.35
5275.53
5275.53
2093.46
194.56
Amount.
(Rs.)
4609.58
225.00
75.00
125.00
48.00
5082.58
90.00
54.00
13.00
157.00
5239.58
52.40
52.40
785.94
6130.31
6130.31
2432.66
226.08
Amount.
(Rs.)
8582.70
300.00
2474.26
349.32
80.00
50.00
1374.59
13210.87
1430.00
832.00
432.00
2694.00
15904.87
159.05
159.05
2385.73
18608.70
18608.70
2912.16
270.65
Amount.
(Rs.)
8582.70
300.00
2474.26
349.32
80.00
50.00
1374.59
13210.87
1430.00
832.00
432.00
2694.00
15904.87
159.05
159.05
2385.73
18608.70
18608.70
2912.16
270.65
Amount.
(Rs.)
8582.70
300.00
2474.26
349.32
80.00
50.00
1374.59
13210.87
1430.00
832.00
432.00
2694.00
15904.87
159.05
159.05
2385.73
18608.70
18608.70
2912.16
270.65
Amount.
(Rs.)
8582.70
300.00
1237.13
687.30
349.32
80.00
50.00
1374.59
12661.04
1430.00
832.00
432.00
2694.00
15355.04
153.55
153.55
2303.26
17965.39
17965.39
2811.49
261.29
Amount.
(Rs.)
3253.82
1184.40
1143.07
225.00
225.00
700.00
15.00
48.00
6794.30
104.00
54.00
13.00
171.00
6965.30
69.65
69.65
1044.79
8149.40
8149.40
5157.85
479.35
Amount.
(Rs.)
3718.66
1353.60
1185.41
225.00
225.00
700.00
15.00
48.00
7470.66
156.00
81.00
26.00
263.00
7733.66
77.34
77.34
1160.05
9048.39
9048.39
5726.83
532.23
Amount.
(Rs.)
2775.99
1052.07
150.00
123.66
300.00
225.00
225.00
50.00
585.34
5487.06
1430.00
832.00
432.00
2694.00
8181.06
81.81
746.11
81.81
1227.16
10317.95
10317.95
3793.36
352.54
Amount.
(Rs.)
8582.70
300.00
2474.26
349.32
80.00
50.00
1374.59
13210.87
1430.00
832.00
432.00
2694.00
15904.87
159.05
159.05
2385.73
18608.70
18608.70
2912.16
270.65
Amount.
(Rs.)
364.50
364.50
260.00
270.00
530.00
894.50
4.47
8.99
81.58
135.52
1125.06
1125.06
2500.14
232.36
820.34
467.77
2,140.65
151.28
86.80
3,666.85
183.34
183.34
4,033.53
585.00
577.50
1,162.50
5,196.03
103.92
779.40
6,079.36
1,712.49
159.15
820.34
467.77
266.25
1,554.37
77.72
77.72
1,709.80
550.00
500.00
1,050.00
2,759.80
55.20
413.97
3,228.97
909.57
84.53
Est Dpt
820.34
467.77
479.25
1,767.37
88.37
88.37
1,944.10
520.00
412.50
932.50
2,876.60
57.53
431.49
3,365.62
948.06
88.11
Amount
5,500.00
238.00
200.00
150.00
6,088.00
121.76
555.23
913.20
7,678.19
76.78
Sr.No.
27,600.00
1,649.00
1
2
200.00
150.00
1
2
29,599.00
591.98
2,699.43
4,439.85
37,330.26
373.30
Amount
13,300.00
200.00
13,500.00
270.00
1,231.20
2,025.00
17,026.20
170.26
Sr.
no
A)
1562.00
260.00
75.00
100.00
225.00
2222.00
B)
200.00
135.00
135.00
470.00
2692.00
C)
13.46
27.05
245.51
407.86
3385.88
3385.88
564.31
172.05
Amount.
(Rs.)
3297.00
1108.00
230.00
100.00
4735.00
540.00
540.00
5275.00
263.75
553.875
6092.63
1015.44
94.37
Amount.
(Rs.)
1914.00
1108.00
230.00
100.00
3352.00
540.00
540.00
3892.00
194.6
408.66
4495.26
749.21
69.63
Amount.
(Rs.)
4500.00
900.00
300.00
5400.00
225.00
130.00
135.00
490.00
5890.00
58.90
58.90
537.17
883.50
7428.47
7428.47
Amount.
(Rs.)
2552.00
4000.00
6552.00
450.00
135.00
585.00
7137.00
71.37
71.37
1070.55
8350.29
8350.29
776.05
Amount.
(Rs.)
829.40
6124.00
6953.40
225.00
135.00
360.00
7313.40
73.13
73.13
731.34
8191.01
22752.80
2114.57
Amount.
(Rs.)
7000.00
Amount.
(Rs.)
13000.00
16,940.00
4,482.00
2,084.40
302.40
23,808.80
1,190.44
24,999.24
Sr.No.
Descripti
Material
For 100 Sqmt.1:3 (15mm thk.
1 Dr Fixit Pi
2 Screed Plaster 1:3 (15mm thk
a Cement
b Fine & Coa
Total
Add 5 % Wastage
3,750.00
3,150.00
189.00
Total M
Labour
1 Mason
2 Mazdoor
3 Superviso
7,089.00
32,088.24
Total L
Total M+L
2,926.45
4,813.24
39,827.92
398.28
37.01
Sr.No.
A
16,940.00
4,482.00
2,084.40
302.40
8,693.30
Total
7,470.00
3,578.22
504.00
44,054.32
2,202.72
46,257.04
9,250.00
8,850.00
600.00
18,700.00
64,957.04
5,924.08
Descripti
For 100Sqm
Material
1 Cement
2 Sand
a Aggraegat
b Cement Sl
9,743.56
80,624.67
806.25
74.93
Date-160109
Amount
16,940.00
11,952.00
5,558.40
806.40
35,256.80
1,762.84
37,019.64
6,250.00
5,250.00
300.00
11,800.00
48,819.64
4,452.35
7,322.95
60,594.94
605.95
56.31
Date-02.03.09
Amount
1,992.00
565.50
16,940.00
4,482.00
2,779.20
302.40
8,693.30
7,470.00
4,770.96
504.00
1,215.90
7,470.00
4,770.96
4,482.00
2,779.20
66,659.92
3,333.00
69,992.92
12,500.00
10,395.00
1,200.00
24,095.00
94,087.92
9,408.79
103,496.71
1,034.97
96.19
Est.Dpt
lead
Date-190309
Amount
128.25
106.25
30.00
264.50
264.50
13.23
27.24
7.94
39.68
352.58
352.58
9.99
h in 50 m lead
Date-190309
Amount
26.00
33.75
30.00
89.75
89.75
2.69
9.24
2.69
13.46
117.84
117.84
202.50
81.25
30.00
313.75
313.75
32.32
9.41
47.06
402.54
40.25
3.74
Amount
3,252.70
747.00
347.40
50.40
612.70
834.15
408.20
56.28
1,506.00
2.52
7,817.35
7,817.35
2,375.00
2,250.00
150.00
4,775.00
12,592.35
1,888.85
14,481.20
618.85
57.51
Est Dpt
Dt : 080609
Amt.
3,700.00
80.00
3,780.00
540.00
30.00
570.00
4,350.00
43.50
400.69
479.42
5,273.61
175.79
16.34
5.39
Est Dpt
Amount.
(Rs.)
1176.00
382.20
1558.20
33.80
148.50
30.00
212.30
1770.50
265.58
2036.08
2036.08
885.25
25.09
5.77
Amount.
(Rs.)
79.68
35.28
114.96
520.00
290.25
30.00
840.25
955.21
143.28
1098.49
1098.49
109.85
10.21
Amount.
(Rs.)
8750.00
2614.50
2585.00
13949.50
6500.00
4725.00
150.00
11375.00
25324.50
3798.68
2656.03
31779.21
31779.21
3177.92
90.08
Date: 26.06.09
er Coating
Amount.
(Rs.)
1300.00
230.47
50.00
44.90
1625.37
104.00
54.00
30.00
188.00
1813.37
18.13
18.13
272.01
2121.65
2121.65
3928.98
365.15
Est.Dpt
Date-270609
Rev-00
.15mx0.15 m
Amount.
(Rs.)
92.13
31.14
34.06
97.20
307.50
562.03
0.63
5.76
5.34
1.11
0.29
13.13
575.16
34.51
86.27
695.95
695.95
Est.Dpt
Amount.
(Rs.)
8750.00
2614.50
2585.00
13949.50
3120.00
2700.00
150.00
5970.00
19919.50
2987.93
0.00
22907.43
22907.43
2290.74
64.93
Est Dpt
Amount.
(Rs.)
1813.00
658.00
2471.00
546.00
540.00
30.00
1116.00
3587.00
538.05
4125.05
4125.05
412.51
38.34
Est Dpt
m (2Coates)
D-200309
Amount.
(Rs.)
270.54
270.54
200.00
81.00
60.00
341.00
611.54
18.35
30.58
30.58
3.06
91.73
785.83
785.83
78.58
7.30
(2Coates)
D-200309
Amount.
(Rs.)
272.73
352.00
624.73
200.00
81.00
60.00
341.00
965.73
28.97
48.29
4.83
144.86
1192.67
1192.67
119.27
11.08
Amount.
288.40
310.00
598.40
429.00
309.15
45.00
783.15
1,381.55
27.63
207.23
1,616.41
1,616.41
161.64
15.02
Date: 03.08.09
Amount.
(Rs.)
6225.00
5150.88
16100.00
27475.88
1997.50
2160.00
300.00
4457.50
31933.38
958.00
958.00
319.33
4790.01
38958.72
38958.72
3895.87
818.13
4714.01
133.62
30.73
Est.Dpt
Date:03.08.09
Amount.
4,980.00
2,671.20
3,100.00
10,751.20
4,550.00
3,375.00
7,925.00
18,676.20
373.52
2,801.43
21,851.15
21,851.15
218.51
45.89
264.40
24.57
Est Dpt
Date: 03.08.09
Amount.
(Rs.)
1135.44
552.25
597.99
1826.24
4111.92
10.4
94.5
87.5
18.2
4.725
215.33
4327.25
259.63
649.09
5235.97
5235.97
785.39
72.99
15.33
88.32
Est.Dpt
Amount.
(Rs.)
998.94
998.94
169.00
87.75
256.75
1255.69
37.67
12.56
188.35
1494.27
59770.83
1694.18
Amount.
(Rs.)
32.148
114.10
146.25
640.00
60.00
700.00
846.25
63.47
25.39
8.46
126.94
1070.50
107.05
9.95
Amount.
(Rs.)
1960.00
290.00
553.92
187.62
80.00
50.00
490.00
3611.54
491.03
285.48
148.23
924.74
4536.28
45.36
45.36
680.44
5307.44
5307.44
3711.50
344.93
Amount.
(Rs.)
1103.07
552.25
592.48
2247.80
36.40
400.00
436.40
2684.20
13.42
26.98
406.68
3131.27
3131.27
88.75
Amount.
(Rs.)
4980.00
4935.00
18500.00
28415.00
1997.50
2160.00
4157.50
32572.50
4885.88
37458.38
37458.38
3745.84
106.17
Amount.
(Rs.)
3237.00
5569.50
18500.00
27306.50
1997.50
2160.00
4157.50
31464.00
157.32
316.21
4767.03
36704.57
36704.57
367.05
34.14
Amount.
(Rs.)
4731.00
4762.80
18500.00
27993.80
1997.50
2160.00
4157.50
32151.30
160.76
323.12
4871.16
37506.34
37506.34
375.06
34.89
Amount
33,850.95
250.00
34,100.95
2,500.00
1,350.00
3,850.00
37,950.95
759.02
5,692.64
44,402.61
Amount.
(Rs.)
380.97
120.73
136.32
17250.00
862.50
200.00
438.00
76.50
19465.02
973.25
20438.27
270
411.25
691.20
1372.45
21810.72
109.05
218.11
3271.61
25409.49
25409.49
2540.95
236.15
Amount.
(Rs.)
756.00
945.00
210.00
100.00
2011.00
78.00
40.50
13.00
131.50
2142.50
21.43
21.43
321.38
2506.73
2506.73
2321.04
215.71
Amount.
(Rs.)
21,280.00
3,598.05
2,373.50
27,251.55
150.00
4,160.00
4,600.00
4,600.00
31,851.55
955.55
637.03
4,777.73
38,221.86
38,221.86
382.22
35.52
Amount.
(Rs.)
2,669.28
1,836.53
4,505.81
75.00
4,550.00
5,000.00
5,000.00
9,505.81
150.00
100.00
750.00
10,505.81
10,505.81
105.06
9.76
Amount.
(Rs.)
11,500.00
825.00
800.00
1,890.00
15,015.00
5,255.25
5,255.25
20,270.25
608.11
405.41
3,040.54
24,324.30
24,324.30
2,432.43
741.59
Amount.
(Rs.)
246.00
15,607.80
3,594.00
2,700.00
22,147.80
5,536.95
5,536.95
27,684.75
830.54
553.70
4,152.71
33,221.70
33,221.70
3,322.17
308.64
Amount.
(Rs.)
2,250.00
22.50
100.00
2,372.50
1,423.50
1,423.50
3,796.00
113.88
569.40
4,479.28
4,479.28
44.79
4.16
62500
6250
800
175
1200
1000
71925
2157.75
10788.75
84871.5
84871.5
848.715
Amount.
(Rs.)
246.00
15,607.80
3,594.00
2,700.00
22,147.80
5,536.95
5,536.95
27,684.75
830.54
553.70
4,152.71
33,221.70
33,221.70
3,322.17
308.64
Amount.
(Rs.)
4356.00
954.00
5310.00
198.00
960.00
35.00
1193.00
6503.00
975.45
7478.45
7478.45
5665.49
160.59
720.00
3000.00
87.50
3807.50
21091.10
3163.67
24254.77
24254.77
5053.08
143.23
525
1925
1925
96.25
2021.25
303.1875
2324.4375
` 2500
` 25
`2.3
Quantity
Rate
(Rs.)
Amount.
(Rs.)
6.320
0.440
230.00
600.00
1453.60
264.00
0.880
625.00
550.00
2267.60
0.040
0.700
0.700
0.070
250.00
135.00
125.00
250.00
10
94.5
87.5
17.5
0.035
135.00
4.725
214.23
6.00%
2481.83
148.91
15.00%
372.27
3003.01
3003.01
Quantity
Rate
(Rs.)
Amount.
(Rs.)
8.000
0.420
249.00
1176.00
1992.00
493.92
0.850
645.00
548.25
3034.17
0.040
300.00
12
0.700
0.700
0.070
200.00
200.00
260.00
140
140
18.2
0.035
200.00
7
317.20
8.00%
3351.37
268.11
15.00%
502.71
4122.19
4122.19
Quantity
Rate
(Rs.)
Amount.
(Rs.)
11.000
0.900
249.00
1176.00
2739.00
1058.40
0.780
645.00
503.10
4300.50
0.040
0.700
0.700
0.070
300.00
200.00
200.00
260.00
12
140
140
18.2
0.035
200.00
7
317.20
4617.70
8.00%
369.42
15.00%
692.66
5679.77
5679.77
25 grade concrete
Quantity
Rate
(Rs.)
Amount.
(Rs.)
0.83
0.03
0.06
5.00
249.00
1945.00
775.00
30.00
206.67
58.35
46.50
150.00
0.30
160.00
48.00
Sr.
no
A)
Item
Materials:
Cement
Sand
Aggregate
Colour Pigment & Hardener
Shuttering
509.52
0.01
0.06
0.06
300.00
200.00
200.00
2.70
12.00
12.00
Labour:
Mason
Skilled Labour
Unskilled Labour
0.06
250.00
15.00
Carpenter
41.70
C)
24.00
12.00
Mechinary
Mixer with Operater
Vibrator with Operater
135.00
171.00
Sub-Total of Mechinary
1.50%
722.22
10.83
Total (M+L)
Add W.C & Electricity
15.00%
108.33
841.39
78.196
0.12
0.12
1.00
Quantity
200.00
100.00
135.00
Rate
(Rs.)
Amount.
(Rs.)
500.00
1.32
2.00
230.00
1000.00
303.60
0.28
600.00
165.60
1469.20
0.5
0.8
250
225
125
180
1.6
150.00
240
545.00
2014.20
1.00%
1.00%
20.14
20.14
15.00%
302.13
2356.61
2356.61
66.74
D)
Quantity
Rate
(Rs.)
Amount.
(Rs.)
75.00
0.40
114.00
249.00
8550.00
99.60
0.09
1139.00
97.04
8746.64
0.5
0.8
300
250
150
200
1.6
150.00
240
590.00
9336.64
1.00%
93.37
1.00%
93.37
15.00%
1400.50
10923.87
10923.87
309.37
lding
Quantity
Rate
(Rs.)
Amount.
(Rs.)
7.93
249.00
1,974.57
2.16
2,182.80
4,714.85
6,689.42
0.50
10.00
300.00
250.00
150.00
2,500.00
15.00
150.00
2,250.00
4,900.00
11,589.42
1.00%
1.00%
115.89
115.89
15.00%
1738.41
13559.62
135.60
12.60
m Ex.Scaffolding
Quantity
Rate
(Rs.)
Amount.
(Rs.)
14.28
249.00
3,555.72
2.00
1,139.00
2,278.00
5,833.72
0.50
10.00
300.00
250.00
150.00
2,500.00
15.00
150.00
2,250.00
4,900.00
10,733.72
1.00%
1.00%
107.34
107.34
15.00%
1610.06
12558.45
125.58
11.67
Quantity
Rate
(Rs.)
Amount.
(Rs.)
0.83
0.03
249.00
1945.00
206.67
58.35
0.06
755.00
45.30
310.32
0.02
0.12
0.12
300.00
200.00
200.00
5.40
24.00
24.00
0.05
200.00
9.00
62.40
0.15
0.15
200.00
100.00
30.00
15.00
1.00
135.00
135.00
180.00
1.50%
552.72
8.29
15.00%
82.91
643.92
59.844
m2
Quantity
Rate
(Rs.)
Amount.
(Rs.)
25.00
0.05
15.00
1984.00
375.00
99.20
0.01
1984.00
19.84
494.04
49.40
543.44
0.02
350.00
5.88
0.11
200.00
22.40
28.28
1.50%
571.72
8.58
15.00%
85.76
666.06
61.90
Quantity
15.74
2.00
6.39
Rate
(Rs.)
175.00
50.00
387.36
Amount.
(Rs.)
2754.93
100.00
2474.26
51.10
8.00
50.00
16.40
10.00
1.00
838.04
80.00
50.00
15.74
93.00
1464.05
7761.28
1.89
1.10
260.00
260.00
491.03
285.48
1.10
135.00
148.23
924.74
8686.02
1.00%
1.00%
86.86
86.86
15.00%
1302.90
10162.64
10162.64
4640.48
431.27
Nos
Nos
Total
Qty
Rate
100.00
17.00
1.00
1.00
Amount
276.00 27,600.00
97.00 1,649.00
200.00
150.00
200.00
150.00
29,599.00
Add 2% Contengencies
591.98
2,699.43
4,439.85
G.Total
37,330.26
Rate Per/Rmt.
373.30
PVC 110mm dia.of 6kgf/cm2 for 6 Rmt with Pocket in wall & Grouting
Unit
Quantity
Rate
(Rs.)
Amount.
(Rs.)
Item
Materials:
Pipe (6M)
Bend
Coupler
PVC Solution
rmt
No
No
Ls
1.00
1.00
1.00
1.00
1562.00
260.00
75.00
100.00
1562.00
260.00
75.00
100.00
Grouting
No
1.00
225.00
225.00
2222.00
1.00
1.00
200.00
135.00
200.00
135.00
Helper
Each
1.00
135.00
470.00
Total (M+L)
Add for
Sundries &
Contingencies
Add W.C & Electricity
Add Vat & Service Tax
135.00
2692.00
0.50%
1.00%
9.12%
13.46
27.05
245.51
15.00%
407.86
Total Amt.
3385.88
3385.88
564.31
172.05
Qty
Rate
Date-220409
Amount
110.00
16,940.00
249.00
1,139.00
3,984.00
1,913.52
22,837.52
1,141.88
23,979.40
Add 5 % Wastage
Nos
Nos
Nos
13.00
19.00
0.63
250.00
150.00
300.00
3,250.00
2,850.00
189.00
6,289.00
30,268.40
2,760.48
4,540.26
37,569.13
375.69
34.92
of 75mm thk
Unit
Qty
Date-220409
Amount
Rate
For 100Sqm
Bag
Cum
Cum
Bag
46.00
3.20
6.40
15.00
249.00
1,139.00
698.00
249.00
11,454.00
3,644.80
4,467.20
3,735.00
23,301.00
1,165.05
24,466.05
Nos
Nos
Nos
37.00
50.00
1.88
250.00
150.00
300.00
9,250.00
7,500.00
562.50
17,312.50
41,778.55
3,810.20
6,266.78
51,855.54
518.56
48.19
Est.Dpt.
Item
Materials:
Unit
Quantity
Rate
(Rs.)
Hinges
Nos
3.00
75.00
Tower bolt
Handles
Nos
Nos
1.00
2.00
75.00
120.00
Screws
Cent
48.00
1.00
C)
Labour:
Carpenter
Each
0.40
260.00
Beldar
Each
0.40
135.00
0.05
260.00
Mistry
Each
Add for
Sub-Total of Labour (L)
Sundries &
Total
(M+L)
Contingencie
s
1.00%
1.00%
15.00%
Unit
Quantity
Rate
(Rs.)
Bags
Cum
Cum
Kgs
1.10 249.00
0.04 1945.00
0.08 775.00
6.68
30.00
Sqm
0.40
160.00
Amount.
(Rs.)
273.90
77.80
62.00
200.40
64.00
678.10
Each
Each
Each
0.01
0.06
0.06
300.00
200.00
200.00
2.70
12.00
12.00
Each
0.06
250.00
15.00
41.70
Cum
Cum
0.12
0.12
200.00
100.00
24.00
12.00
Sqm
1.00
135.00
135.00
171.00
1.50%
890.80
13.36
15.00%
133.62
1037.78
96.45
Amount.
(Rs.)
225.00
75.00
240.00
48.00
588.00
104.00
54.00
13.00
171.00
759.00
7.59
7.59
113.85
888.03
888.03
562.04
52.23
ILA + ROADM
Rate Analysis - Maharashtra
Sl No.
1
1.1
1.2
Skilled
Unskilled
Material Rates
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
Cement
Aggregate 20 mm Dn
Sand
Bricks
Boulders
Reinforcement Steel
Structural Steel
Ply Wood 10 Mm thk
Hard Wood
Wire Nails
Sl no.
1
2
3
4
5
6
Rate
M-Day
M-Day
232
225
Bags
CuM
CuM
Nos
CuM
MT
MT
Sq M
Cft
Kg
300
850
1000
3.5
800
48000
50000
650
400
60
Sl no.
Description
Unit
1
2
3
4
5
6
USL excavation
manday
manday
manday
Supervisor
Sub Total
Contractor's OH & P
Sub Total
per m3
Description
Unit
1
2
3
USL excavation
manday
manday
manday
Supervisor
4
5
6
Sub Total
Contractor's OH & P
Sub Total
Sl no.
Description
1
1.1
1.2
1.3
2
3
4
4.1
4.2
5
6
7
8
8.1
8.2
8.3
8.4
8.5
9
10
11
Material per sq ft
Ply 10 mm thk
Hard wood
Wire nails
Sub total
Wastage
Manpower
Carpenter
Helper
Sub Total cost per sq m
Nos of repetitions
Cost per repetition
Cost of fixing
Carpenter
Helper
Wire nails
Shuttering oil
Leads & Lifts & Transportation
Sub Total
Contractor's OH & P
Total
per m3
Unit
Sq m
Cuft
kg
Form Work
Measurements
Nos
L
B
1.00
2.00
0.625
2%
man days
man days
man days
man days
kg
LS
15%
Sl no.
Description
Unit
1
2
3
4
5
6
7
8
9
10
11
12
Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
USL
Sueprvisor
Sub Total
Contractor's OH & Profit
Total Cost of RMC M10
bag
m3
m3
3%
5%
LS
man day
manday
PCC M 10 Grade
Measurements
Nos
L
B
1
0.1
(1 manday per m3 )
Sl no.
Description
Unit
1
2
3
4
5
6
7
8
9
10
11
12
Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Tools & Tackles
USL
Sueprvisor
Sub Total
Contractor's OH & Profit
Total Cost of M15
bag
m3
m3
3%
5%
LS
man day
manday
Sl no.
Description
Unit
1
2
3
4
5
6
7
8
9
10
11
12
Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
USL
Sueprvisor
Sub Total
Contractor's OH & Profit
Total Cost of M20
bag
m3
m3
Sl no.
Description
3%
5%
LS
man day
manday
Unit
1
0.1
(1 manday per m3 )
RCC M 20 Grade
Measurements
Nos
L
B
1
0.1
(1 manday per m3 )
Reinforcement
Measurements
Nos
L
B
-
5
10
11
12
13
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
cost of brick
cement
sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total
Sl no.
Description
Unit
1
2
3
4
5
6
7
8
9
10
11
cement
sand
sub total
wastage
skilled mason
unskilled
Lead and lifts
Scaffolding
sub total
contractor's OH & P
Total
bag
cft
Sl no.
Description
1
2
3
4
5
6
7
8
9
cement
sand
sub total
wastage
skilled mason
unskilled
Lead and lifts
Scaffolding
sub total
3%
mandays
mandays
0.67
1.33
Flush Pointing
Measurements
Nos
L
B
0.07
0.13
0.07
0.13
10
11
contractor's OH & P
Total
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
cement
sand
sub total
wastage
manpower for 1st coat
skilled mason
unskilled
manpower for 2nd coat
skilled mason
unskilled
sand facing
Lead & Lifts
Scaffolding
sub total
contractor's OH & P
Total
0.07
0.13
mandays
mandays
0.07
0.13
Sl no.
Description
Unit
1
2
3
4
5
6
7
8
9
10
11
Rubble
Breaking
Cement
sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total
m3
m3
bag
cft
Rubble masonary
Measurements
Nos
L
B
1.35
1.35
1.80
11.00
3%
mandays
mandays
Sl no.
Description
Unit
1
2
Cost of Materials
Wastage Unacountable
MT
MT
0.67
1.33
Structural Steel
Measurements
Nos
L
B
1
1
2%
3
4
5
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
6.12
Wastage acountable
Scrap Value Realisation
Sub Total Cost of Materials
Fabrication & Erection
Fitter
Gas Cutter
Welder
Helper
Riggers
Consumables ( Past Experience )
Power
Cranage & Handling
Galvanisation - Zinc
Galvanisation Manpower
Transportation to Site
Sub Total
Vendor's OH & P
MT
MT
MT
1
1
1
M-day
M-day
M-day
M-day
M-day
MT
MT
1
1
1
3
7
Kg
MT
MT
60
3%
-3%
Output 1 MT/Day
Output 1 MT/Day
Output 1 MT/Day
Output 1 MT/Day
Output 1 MT/Day
LS Considered
@15%
Total
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
11
Rubble
Breaking
sub total
wastage
Sub Total Materials
Cost of 230 mm thick soling
skilled mason
unskilled
sub total
contractor's OH & P
Total
Sl no.
Description
1
Cost of M 15 grade concrete
2
Shuttering for panels
3
sub total
4
wastage
5
Sub Total Materials
6
Addl Cement
7 Addl Manpower for smooth finish
9
sub total for 9 m2
10 contractor's OH & P on addl items
11
Total
Unit
m3
m2
0.07
0.13
IPS 40 mm thick
Measurements
Nos
L
B
1.00
3
3
2.00
3
3%
m2
m2
1.00
1.00
3
3
3
3
12
Cost per m2
f surplus earth
ts
H
avate 2 m3 /day )
ckfill 15 m3 /day )
or per 10 USL )
Qty
0.50
0.07
0.05
Rate Amount
225
225
232
113
15
12
139
21
160
al of surplus earth
ts
Qty
Rate Amount
H
vate 0.75 m3 /day )
1.33 225
300
ckfill 15 m3 /day )
0.07 225
15
or per 10 USL )
0.13 232
31
346
52
398
511
77
588
ts
H
Qty
Rate Amount
1.00
###
0.625
650
400
60
650
800
38
1,488
30
232
225
15
15
1,548
10
155
232
225
60
23
23
38
5
10
253
38
291
ts
H
Qty
Rate Amount
4.20 300
0.52 1000
0.85 850
1
0.1
225
232
1,260
520
723
2,503
75
125
250
225
23
3,201
480
3,681
0.21
0.934
ts
H
Qty
Rate Amount
6.20 300
0.52 1000
0.85 850
1
0.1
ts
H
Qty
225
232
ts
H
Qty
1.00
0.03
0.05
-0.02
5
10
###
0.31
Rate Amount
8.00 300
0.52 1000
0.85 850
1
0.1
1,860
520
723
3,103
93
155
250
225
23
3,849
577
4,426
225
232
2,400
520
723
3,643
109
182
250
225
23
4,432
665
5,097
Rate Amount
48000 ###
48000 1,440
48000 2,400
48000 (720)
###
225
232
60
1,125
2,320
360
1,000
0.4
15%
ts
H
Qty
###
8,389
###
Rate Amount
450
1.80
11
3.5
300
28
0.67
1.33
232
225
15%
1,575
540
308
2,423
73
155
300
2,950
443
3,393
0.0625
0.311
8.784
ts
H
helpers can do
ck work per day
Qty
Rate Amount
0.05
0.26
300
28
0.07
0.13
232
225
15%
15
7
23
1
15
30
5
5
79
12
91
0.1446759259
0.00736
Is it for per m2 ??
ts
H
helpers can do
ck work per day
Qty
Rate Amount
0.10
0.51
300
28
0.07
0.13
232
225
31
14
45
1
15
30
5
5
102
15%
oats
ts
H
Qty
15
117
Rate Amount
0.17
0.85
300
28
51
24
75
2
helpers can do
ck work per day
0.07
0.13
232
225
15
30
helpers can do
ck work per day
0.07
0.13
232
225
15
30
5
5
5
183
27
210
15%
ts
H
Qty
1.35
1.35
1.80
11.00
0.67
1.33
Rate Amount
800
50
300
28
232
225
15%
ts
H
1,080
68
540
308
1,996
60
155
300
2,510
377
2,887
Qty
Rate Amount
1
0.02
50000
50000
###
1,000
0.03
-0.03
50000
50000
1,500
###
51,000
1 MT/Day
1 MT/Day
1 MT/Day
1 MT/Day
1 MT/Day
1
1
1
3
7
232
232
232
225
232
60
225
onsidered
232
232
232
675
1624
1500
200
500
13500
1500
2000
73,195
10,979
###
ts
H
Qty
1.35
1.35
helpers can do 15
RM per day
0.07
0.13
Rate Amount
800
50
232
225
15%
ts
H
0.04
0.04
3 kg/m2
Qty
Rate Amount
0.36 ###
0.24
300
27
9
1,080
68
1,148
34
1,182
272
15
30
317
48
365
6
10
15%
1,620
72
1,692
51
1,743
162
90
1,995
37.80
2,033
226
4.976
Sl.
Short
No.
Description
A Earth Work
1 EXCAVATION IN
SOIL-NGL TO 3M
DEPTH
B Disposal
2 CARTING beyond
3KM LEAD
3 EXTRA FOR
CARTING
BEYOND
C Filling
SPECIFIED LEAD
4 BACKFILL MURRUM/YELLO
W EARTH
BROUGHT FROM
OUTSIDE
D Formwork
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 1 of 557
Sl.
No.
Short
Description
5 P&F FORMWORK
BLW FGL
6 P&F FORMWORK
ABOVE FGL TO
10M HT
7 P&F FORMWORK
> 10M TO 20M HT
8 P&F FORMWORK
20M AND ABOVE
10 Extra for
CurvedShuttering
- Plywood
E Reinforcement
Reliance Engineering Group
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 2 of 557
Sl.
No.
Short
Description
11 FIXING OF
REBAR - BELOW
FGL
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 3 of 557
Sl.
No.
Short
Description
G Plum Concrete
24 P&L M10 GRADE
PLUM
CONCRETE
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 4 of 557
Sl.
No.
Short
Description
27 P&LAYING M30
RCC RMC
ABOVE FGL TO
upto 10M HT
28 P&LAYING M30
RCC RMC >10M
UPTO 20M HT
29 P&LAYING M30
RCC RMC >20m
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 5 of 557
Sl.
No.
Short
Description
36 S,F,P&E OF MS
INSERT PLATES
J Miscellaneous Items
37 P&F SHALITEX
BOARD 12MM
THICK
38 P&F SHALITEX
BOARD 25MM
THICK
39 P&F SHALITEX
BOARD 50MM
THICK
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 6 of 557
Sl.
No.
Short
Description
40 P&A
PRECONSTRUCT
ION
ANTITERMITETR
EATMENT
43 Dismantling&Disp
osal-RCC in
Substructure
44 Dismantling&Disp
osalRCCinSuperstruct
45 Forming
Isolation
ure
Joints
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 7 of 557
Sl.
No.
Short
Description
46 POCKET
0.025SQM AREA
& UPTO 300MM
47 DPTH
POCKET >0.0250.05SQM & DPTH
>300-600MM
48 SUPPLY &
FABRICATION OF
MS TEMPLATES
49 C13601-P/F
FOUNDATION
BOLT
50 Providing,MIXING
& LAYING
CEMENT GROUT
51 P&A NS GROUT
AT EQP
FOUNDATIONS
52 P&L Sand
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 8 of 557
Sl.
No.
Short
Description
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 9 of 557
Sl.
No.
Short
Description
59 Core Cutting
250mmDia >200
to 300mmDepth
60 Core Cutting
250mmDia >300
to 400mmDepth
61 Expansion Joints
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 10 of 557
Sl.
No.
Short
Description
65 P & F Barricading
K Masonry
P&L BW 230MM
66 AT ALL
ELEVATIONS
P&C BW 115MM
67 AT ALL
ELEVATIONS
P & L LIGHT
WEIGHT BLOCK
68
MASONRY
200MM TK.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 11 of 557
Sl.
No.
Short
Description
P&L BW 350MM
69 AT ALL
ELEVATIONS
70
C1060401-P&L
DPC 40mm & M15
L Plastering
P&L 12MM THK
71 smooth PLASTER
- CM 1:4
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 12 of 557
Sl.
No.
Short
Description
C11302-P/A
72 gypsum Plaster 12
mm
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 13 of 557
Sl.
No.
Short
Description
P&F GI CHICKEN
76 WIRE MESH
300MM WIDE
8MM X 8MM
77 GROOVE IN
PLASTER
P&F ALU.PLATE
OVER
78
EXPSN.JOINT3MMX100MM
M Waterproofing and Insulation
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 14 of 557
Sl.
No.
Short
Description
P&L POLYMER
BASED
WATERPROOFIN
79
G-TERRACE
WITH BRICKBAT
COBA
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 15 of 557
Sl.
No.
Short
Description
P&L MEMBRANE
80 TYPE WP
TREATMENT
Protective layer
81 M15 screed with
neat cement finish
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 16 of 557
Sl.
No.
Short
Description
82
83
P&L CHINA
MOSAIC
FLOORING
Reliance Engineering Group
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 17 of 557
Sl.
No.
Short
Description
P&L CHINA
MOSAIC
FLOORING
84
P&L
WATERPROOFIN
85 G-POLYMER
BASED IN
TOILETS
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 18 of 557
Sl.
No.
Short
Description
P&L BRICKBAT
86 COBA FOR SUNK
PORTION
S&A OF WP
87 TREATMENT IN
SERVER HALLS
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 19 of 557
Sl.
No.
Short
Description
S&F110MM LEAF
TRAP W/UPVC
88
KHURRA
W/FLANG
S&F160MM LEAF
TRAP W/UPVC
89
KHURRA
W/FLANG
N Roof sheeting and cladding
S&F PRECOATED
90 GALVALUME
SHEET IN ROOF
S&F PRECOATED
GALVALUME
91 SHEET IN
RIDGE/GUTTER/
FLASING
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 20 of 557
Sl.
No.
Short
Description
S&F PRECOATED
91-a GALVALUME
SHEET IN RIDGE
S&F PRECOATED
GALVALUME
91-b
SHEET IN
FLASING
S&F PRECOATED
GALVALUME
91-C
SHEET IN
FLASING
S&F PRECOATED
GALVALUME
91-D
SHEET IN
GUTTER
O Painting
Reliance Engineering Group
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 21 of 557
Sl.
No.
Short
Description
92
P&A - Whitewash
2 coats
P&A INTERNAL
93 ACRYLIC
EMULSION PAINT
S&A EXTERIOR
94 GRADE ACRYLIC
EMULSION PAINT
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 22 of 557
Sl.
No.
Short
Description
P&A ANTI
95 CARBONATION
PAINT
P FLOORING
96
P&L GRANITE IN
FLOORING
P&L VITRIFIED
97 TILES IN
FLOORING
P&L NON-SKID
98 VITRIFIED TILES
IN FLOORING
99
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 23 of 557
Sl.
No.
Short
Description
P/L IPS
100 FLOORING 50MM
IN CC1:2:4
101
P&L KOTA
102 STONE IN
FLOORING
103
S&A OF EPOXY
FLOORING
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 24 of 557
Sl.
No.
Short
Description
P&L COMPOSITE
106 MARBLE
FLOORING
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 25 of 557
Sl.
No.
Short
Description
P&F GRANITE IN
110 SKIRTING-100MM
HIGH
P&L KOTA
STONE IN
111
SKIRTING-100MM
HIGH
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 26 of 557
Sl.
No.
Short
Description
P/L 100 MM
112 VITRIFIED TILE
SKIRTING
P&L KOTA
STONE IN
113
SKIRTING-300MM
HIGH
P&L KOTA
STONE IN
114
SKIRTING-300MM
HIGH
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 27 of 557
Sl.
No.
Short
Description
P&L KOTA
STONE IN
115
TRAPEZOIDAL
SKIRTING
116
P&L VITRIFIED
TILES IN DADO
117
P&L GLAZED
TILES IN DADO
118
P&F GRANITE IN
TREAD
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 28 of 557
Sl.
No.
Short
Description
119
P&F GRANITE IN
RISER
P&L KOTASTONE
120 IN STAIRCASE
TREAD
P&L KOTASTONE
121 IN STAIRCASE
RISER
P&L GRANITE IN
122 PANTRY
PLATFORM
124
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 29 of 557
Sl.
No.
Short
Description
125
Q STRUCTURAL STEEL
SHOP - LIGHT
STEEL
STRUCTURE
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 30 of 557
Sl.
No.
Short
Description
SHOP - MEDIUM
STEEL
STRUCTURE
SHOP - HEAVY
STEEL
STRUCTURE
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 31 of 557
Sl.
No.
Short
Description
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 32 of 557
Description of Job
Excavation from NGL up to 3m depth using contractor owned P&M in all types of soil including hard murrum, soft rock and disintegrated rock but
excluding hard rock, including necessary dewatering, demucking, shoring/strutting, segregation of reusable excavated earth from vegetation and
debris, disposal up to 200m lead including spreading, stacking the excavated material, removing loose excavated matter from the excavated area etc.
complete as per drawing, specifications and as directed by EIC.
Note: Measurement shall be made as per theoretical maximum plan dimensions of PCC details in the drawing. Separate/ extra payment shall not be
made for working space.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 33 of 557
Description of Job
Providing and fixing below FGL to correct level, line & plumb, plain formwork made of plywood/ MS shuttering/ planks for horizontal/ vertical RCC
members for all RCC works including necessary staging, strutting, scaffolding, bracing etc., keeping the same in position during concreting and
removing after the specified curing period and including all consumables etc. complete as per drawing, specifications and as directed by EIC. Note:
Form work measurement will be on contact area of concrete only.
Providing and fixing above FGL up to 10m height to correct level, line & plumb, plain formwork made of plywood/MS shuttering/planks for horizontal/
vertical RCC members for all RCC works including necessary staging, strutting, scaffolding, bracing etc., keeping the same in position during
concreting and removing after the specified curing
period and including all consumables etc. complete as per drawing, specifications and as directed by EIC. Note: Form work measurement will be on
contact area of concrete only.
Providing and fixing above 10m up to 20m height to correct level, line & plumb, plain formwork made of plywood/MS shuttering/planks for horizontal/
vertical RCC members for all RCC works including necessary staging, strutting, scaffolding, bracing etc., keeping the same in position during
concreting and removing after the specified curing
period and including all consumables etc. complete as per drawing, specifications and as directed by EIC. Note: Form work measurement will be on
contact area of concrete only.
Providing and fixing above 20m height to correct level, line & plumb, plain formwork made of plywood/MS shuttering/planks for horizontal/ vertical RCC
members for all RCC works including necessary staging, strutting, scaffolding, bracing etc., keeping the same in position during concreting and
removing after the specified curing
period and including all consumables etc. complete as per drawing, specifications and as directed by EIC. Note: Form work measurement will be on
contact area of concrete only.
Extra over for providing, making and fixing in position Formwork made of plywood in circular/ curved shape. Note: Form work measurement will be on
contact area of concrete only
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 34 of 557
Description of Job
Fixing in position below FGL MS/ Tor Steel/ HYSD bar for RCC Work including transportation, handling and stacking at designated place, straightening,
cleaning, cutting, bending, placing and tying in position, binding to shape and length as per approved drawing details, binding with contractors own 1820 SWG black soft annealed binding wire, placing with approved quality cover blocks, supports, chairs, spacers, cost of necessary staging/ scaffolding
etc. complete as per drawing, specifications and as directed by EIC.
Fixing in position above FGL to 10m height MS/ Tor Steel/ HYSD bar for RCC Work including transportation, handling and stacking at designated
place, straightening, cleaning, cutting, bending, placing and tying in position, binding to shape and length as per approved drawing details, binding with
contractors own 18-20 SWG black soft annealed binding wire, placing with approved quality cover blocks, supports, chairs, spacers, cost of necessary
staging/ scaffolding etc. complete as per drawing, specifications and as directed by EIC.
Fixing in position at height greater than 10m upto 20m height MS/ Tor Steel/ HYSD bar for RCC Work including transportation, handling and stacking at
designated place, straightening, cleaning, cutting, bending, placing and tying in position, binding to shape and length as per approved drawing details,
binding with contractors own 18-20 SWG black soft annealed binding wire, placing with approved quality cover blocks, supports, chairs, spacers, cost
of necessary staging/ scaffolding etc. complete as per drawing, specifications and as directed by EIC.
Fixing in position at height greater than 20m height MS/ Tor Steel/ HYSD bar for RCC Work including transportation, handling and stacking at
designated place, straightening, cleaning, cutting, bending, placing and tying in position, binding to shape and length as per approved drawing details,
binding with contractors own 18-20 SWG black soft annealed binding wire, placing with approved quality cover blocks, supports, chairs, spacers, cost
of necessary staging/ scaffolding etc. complete as
per drawing, specifications and as directed by EIC.
Concrete
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 35 of 557
Description of Job
Providing and laying RMC/ weigh-batched machine-mixed M-10 grade plain cement concrete below FGL in any shape, position, thickness and
including side shuttering, tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing and finishing the top surface etc.
complete as per drawing, specifications and as directed by EIC.
Providing and laying RMC/ weigh-batched machine-mixed M-15 grade plain cement concrete below FGL in any shape, position, thickness and
including side shuttering, tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing and finishing the top surface etc.
complete as per drawing, specifications and as directed by EIC.
e
Providing and laying RMC/ weigh-batched machine-mixed M-10 grade plum concrete consisting of 80% PCC mix 1:3:6 and 20% rubble stone
maximum size of 150mm laid in layers at all depths below FGL up to plinth level in foundations, drains, fillings, pavements and ramps etc. in any
shape, position, thickness and including side shuttering, tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing and
finishing the top surface etc. complete as per drawings, specifications and as directed by EIC.
ment Concrete
Providing & Laying Contractor supplied RMC of M - 30 Grade Reinforced Cement Concrete below FGL in any shape, position, thickness and
including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing etc. complete as per drawing, specifications and as
directed by EIC.
Providing & Laying Contractor supplied RMC of M20 grade Reinforced Cement Concrete above FGL upto 5m Height in any shape, position, thickness
and including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing, cost of necessary scaffolding etc complete as
per drawing, specifications and as directed by EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 36 of 557
Description of Job
Providing & Laying Contractor supplied RMC of M - 30 Grade Reinforced Cement Concrete above FGL up to 10m height in any shape, position,
thickness and including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing, cost of necessary scaffolding etc.
complete as per drawing, specifications and as directed by EIC.
Providing & Laying Contractor supplied RMC of M - 30 Grade Reinforced Cement Concrete above 10m up to 20m height in any shape, position,
thickness and including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing, cost of necessary scaffolding etc.
complete as per drawing, specifications and as directed by EIC.
Providing & Laying Contractor supplied RMC of M30 grade Reinforced Cement Concrete at height greater than 20m in any shape, position, thickness
and including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing, cost of necessary scaffolding etc complete as
per drawing, specifications and as directed by EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 37 of 557
Description of Job
Supply, fabrication, painting and erection of MS insert plates at all heights including (i) Supply of structural steel as per Indian Standard. (ii) Fabrication:
Straightening (if required), cutting to required size, grinding, drilling of holes, welding or bolting of joints and completing the work as per drawings,
specifications, relevant codes and directions of the EIC. Minor detailing/ layout if required for fabrication shall be carried out. Trial assembly if required
shall be in contractor's scope. Provision of all type to staff and workmen, provision of all required lifting tools-tackles including P&M, all type of welding
and cutting consumables and gases are in contractor's scope. (iii) Painting: including blasting of steel with grits & shots with one coat of red oxide
primer and two coat of enamel paint using airless spray gun as per specification & directed by EIC. (iv) Erection: includes of all structural steel/ panels/
modules at all heights including fixing & removal of safety net, cutting, trimming, drilling, grinding, fit up, welding, alignment & levelling with temporary
staging, bolting to required torque, touch up painting, completing the work in all respect as per drawings, specifications and codes as per the
instructions of EIC and fulfilling owner's safety norms & practices at work site including NDT as per requirement & specification.
Items
Providing and Fixing 12mm thick Shalitex board of Shalimar make or approved equivalent conforming to IS: 1834 (Part 1) 1983 in expansion joint
including any wastage complete as per drawing, specification and as directed by EIC.
Providing and Fixing 25mm thick Shalitex board of Shalimar make or approved equivalent conforming to IS: 1834 (Part 1) 1983 in expansion joint
including any wastage complete as per drawing, specification and as directed by EIC.
Providing and Fixing 50mm thick Shalitex board of Shalimar make or approved equivalent conforming to IS: 1834 (Part 1) 1983 in expansion joint
including any wastage complete as per drawing, specification and as directed by EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 38 of 557
Description of Job
Providing and applying pre-construction anti termite treatment under and around foundation pits, wall trenches, basement excavation, top surface of
plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, surrounding areas of pipes, ater conduits and at all
other locations identified by EIC. Work will be carried out by approved specialised agency for termite/ pest control using chloropyriphos emulsifiable
1.0% concentration by weight applied as per specifications and as directed by EIC. The work shall carry a guarantee for satisfactory performance for a
minimum period of 10 (Ten)years on Rs. 100 Stamp Paper.
Note: Plinth area of the treated building at Ground level excluding open courts, porches and basements shall be measured for payment.
Providing and laying plinth protection around building with average 75mm thick M-15 grade cement concrete broom-finished on top, laid to proper line
and level over 230 mm thick bed of hard core rubble and 300mm thick layer of consolidated murrum complete as per specifications, drawing etc.
complete as directed by EIC.
Providing and laying dry rubble soling of average thickness 230 mm in plinth, foundation etc. including hand packing, filling of voids with stone chips
and crusher dust blindage on top, watering, ramming, rolling using rollers, compacting etc. complete as per drawing, specifications and as directed by
EIC.
Dismantling of RCC in substructure including cutting of reinforcement steel with all consumables and disposal of debris within 5KM lead complete as
directed by EIC. All P&M is in the scope of the Contractor
Dismantling of RCC in superstructure including scaffolding, cutting of reinforcement steel with all consumables and disposal of debris within 5KM lead
complete as directed by EIC. All P&M is in the scope of the Contractor
Forming isolation joints around equipment's foundations / columns / pedestals / trenches, etc. including cleaning the joints of all loose material, filling
clean sand for the full depth except for top to enable sealing with approved polysulphide liquid sealing compound etc. or any other equivalent all
complete as shown on drawing and specified in manifacturer's recommendations and as directed by EIC.
Reliance Engineering Group
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 39 of 557
Description of Job
Providing & fixing Pockets at all heights in correct position of plan area up to 0.025 Sqmt and up to 300mm depth in concrete for fixing foundations
bolts as per drawings & specifications including providing, fixing & removing of necessary form works and cleaning the site etc.complete as directed by
EIC.
Providing & fixing Pockets at all heights in correct position of plan area up to 0.025 Sqmt and up to 300mm depth in concrete for fixing foundations
bolts as per drawings & specifications including providing, fixing & removing of necessary form works and cleaning the site etc. complete as directed by
EIC.
Fabrication of MS Templates including supplying, cutting, grinding, edge preparation, drilling, assembly, fit-up and welding, cost of consumables etc.
complete as per drawing, specifications and as directed by EIC.
Providing & Fixing of foundation bolts with necessary cutting, fabricating, welding, hoisting and threading including all accessories like washer ,nut
angle, flat,I section, channel etc. during concreting including all cost of labour, centering and shuttering true to line, level and plumb etc. complete in all
leads and lifts as per drawings and specifications and as directed by EIC.
(Note-Templates
will be provided at no extra cost .)
Providing,Mixing and laying cement grout in 1:2 at all heights for foundation pockets, under base plates, machine frames, steel columns along with
shimplates for leveling purpose, curing, cleaning out surface as per drawing, specifications and as directed by EIC.
Providing and applying Grouting of equipment foundations at all heights with non-shrink grout of Fosroc Conbextra GP2 or approved equivalent
including surface preparation, shuttering, deshuttering, curing, cleaning, etc. complete as per manufacturer's specifications and as directed by EIC.
Providing, filling, laying and spreading approved quality sand in pits, foundations and pipe trenches etc including cost of leveling, compaction etc all
complete as directed by the EIC
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 40 of 557
Description of Job
Providing & Laying Screed Concrete (RMC) of average thickness 50mm to 75mm at all levels to proper line, level and slope and including cost of side
shuttering if any, finishing, pond curing etc complete as per drawings, specifications and as directed by EIC.
Providing & Placing in position Thermocol/ Polysterene Sleeves around Foundation Bolts, providing and fixing mastic tape around the sleeves and
removal of sleeves after completion of the job complete as per specifications and as directed by EIC
Charges for Core Cutting 150mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth upto 200mm with Contractor-owned core cutting
machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if required, barrel end
connection, all labour, consumables etc complete as per drawing and as directed by EIC
Charges for Core Cutting 150mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth greater than 200mm upto 300mm with Contractorowned core cutting machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if
required, barrel end connection, all labour, consumables etc complete as per drawing and as directed by EIC
Charges for Core Cutting 150mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth greater than 300mm upto 400mm with Contractorowned core cutting machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if
required, barrel end connection, all labour, consumables etc complete as per drawing and as directed by EIC
Charges for Core Cutting 250mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth upto 200mm with Contractor-owned core cutting
machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if required, barrel end
connection, all labour, consumables etc complete as per drawing and as directed by EIC
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 41 of 557
Description of Job
Charges for Core Cutting 250mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth greater than 200mm upto 300mm with Contractorowned core cutting machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if
required, barrel end connection, all labour, consumables etc complete as per drawing and as directed by EIC
Charges for Core Cutting 250mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth greater than 300mm upto 400mm with Contractorowned core cutting machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if
required, barrel end connection, all labour, consumables etc complete as per drawing and as directed by EIC
Forming expansion joints in all types of structures including cleaning the joints of all loose material, filling Shaltex board or equivalent inside the gaps
and sealing with approved polysulphide liquid sealing compound etc. or any other equivalent all complete as shown in drawing and specified in
manufacturerers recommendations & as directed by EIC.(Refer REG Specification No. SS-CS-63002) with 50mm thick filler materials. All materials in
contractors scope.
Providing and fixing 1.5mm thick 450mm wide aluminium sheet for covering expansion joint including cost of bending, groove making, consumables
etc complete as directed by EIC.
Providing & fixing in position 230mm wide dumb bell shaped white PVC water bar of CALICO or equivalent with central bulb as per drawing,
specifications and as directed by EIC
Chipping of pile concrete 600mm dia above cut off level manually/contractor owned P&M and removing debris from area and dozing at designated
disposal yard
upto lead of 2km including making of grooves with chisel upto required
level/profile as per drawing ,excess reinforcement cutting, straightning
of reinforcement in piles applying of bonding agent etc all complete as
per instructions of EIC.(Lenght of the pile cut will be considered for payment)
Reliance Engineering Group
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 42 of 557
Description of Job
PROVIDING AND FIXING BARRICADING STRUCTURES AS PER APPROVED DRAWING ,DRILLING IN EXISTING RCC PAVEMENT, GROUTING
OF STRUCTURAL MEMBER,PROVIDING AND FIXING GI SHEETING WITH PIPE, ENCASING BASE OF BARRICADING PIPES WITH M20
CONCRETE ETC. ALL AS PER APPROVED DRAWING AND INSTRUCTION OF EIC.INCLUDING 1 COAT OF PRIMER & 2 COATS OF ENAMEL
PAINT (STRUCTURAL STEEL REQUIRED FOR THIS JOB SHALL BE PAID UNDER RELEVANT ITEM)
Providing and constructing minimum 230mm thick Brick Masonry at all elevations with approved quality bricks (having minimum crushing strength @
50Kgf/Sqcm) in 1:4 cement mortar and including necessary scaffolding, mixing of mortar, raking out joints, curing etc. complete as per drawing,
specifications and as directed by EIC.
Providing and laying 115mm thick Brick Masonry at all elevations with approved quality bricks (having crushing strength of 50 Kgf/Sqcm) in 1:4 cement
mortar and including mixing of mortar, raking out joints, curing, laying of 2 Nos 6mm dia MS Rod at every 4th layer, necessary scaffolding etc. complete
as per drawing, specifications and as directed by EIC.
Providing & Laying of aerated concrete block (Siporex or equivalent) of 200MM thick, having minimum crushing strength of 30 kg/sqcm in cement
mortar 1:4, in superstructure, including all necessary scaffolding, raking out joints, curing etc. complete as per specifications and as directed by
Engineer In Charge.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 43 of 557
Description of Job
Providing and constructing brick masonry, 350 MM thick, at all elevations with common burnt clay bricks having minimum crushing strength of 50
kg/sqcm in cement mortar 1:4, in superstructure, including all necessary scaffolding, raking out joints, curing etc. complete as per specifications and as
directed by engineer in charge.
Providing & laying damp proof coarse (DPC) 40mm thick with cement concrete M-15 grade with necessary side shuttering, compaction, curing,
deshuttering etc. complete in all lead and lifts as per drawings and specifications and as directed by EIC with water proofing material 'Impermo' or
equivalent in cement concrete work @ 1 kg per 50 kg. of cement.
Providing and laying 12mm thick smooth finish plaster at all heights in CM 1:4 in proper line and level including surface preparation, providing drip
mould & groove if any, curing, erection and removal of scaffolding etc. complete as per drawing, specifications and as directed by EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 44 of 557
Description of Job
Providing, preparing and plastering readymade proprietary Gypsum plaster of approved manufacturer to internal walls and ceilings average 12mm
thick to wall surfaces of concrete, masonry work (Gypsum consumption 2.14 Kg/Sft), including doing jambs, sills, grooves, wattas, rounding of corners
etc. all complete as per architectural drawing, specification and directed by EIC, at all lift, lead and depth, doing independent double legged scaffolding,
making gypsum plaster mix as per approved EIC, providing and fixing 20 gauge GI chicken mesh 150 mm wide to junctions of concrete and masonry,
hacking closely concrete surfaces, apply chemical adhesive coating on concrete surfaces and apply scratch coat plaster etc. complete as approved by
EIC. Plastering shall be to correct line, levels and plumb including curing, cleaning etc. complete to entire satisfaction of EIC.
(To Internal surfaces)
Providing and laying 6-8mm thick single-coat plaster in ceiling at all heights in CM 1:3 in proper line and level including surface preparation, curing,
erection and removal of scaffolding etc. complete as per drawing, specifications and as directed by EIC.
Providing and laying 20mm thick sand faced waterproof plaster at all heights in two coats with base coat of 12mm thickness in CM 1:4 mixed with
Accoproof waterproofing compound (@ 2% of weight of cement of base coat) or approved equivalent and finish coat of 8mm thickness in CM 1:3
including drip mould, normal groove, curing, cost of necessary scaffolding etc complete as per drawing, specifications and as directed by EIC.
Providing and Applying two or more coats of birla white or equivalent cement based putty of approved make at all heights. Items including cost of
scaffolding, curing etc. complete as per drawing, specification and directed by EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 45 of 557
Description of Job
Providing & Fixing 300mm wide GI chicken wire mesh of 5mmx5mm mesh and 20 gauge thickness (weight @ 0.25Kg/ Sqmt) at junctions of concrete
and masonry surface prior to plastering and including cost of consumables etc. complete as directed by EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 46 of 557
Description of Job
Providing cementitous polymer based waterproofing treatment to terrace of RCC slab including brick bat coba. Job consists of cleaning the RCC slab
using wire brush, chisels to make it perfectly clean. Grouting slab by fixing 20 mm dia. GI nipple at construction joint of RCC slab / any weak spot ( if
observed ) then pumping cement slury into it. Opening up any cracks in V shape & filling the same with polymer modified mortar. Providing and laying
two coats of highly flexible two components of polymer based waterproofing treatment having a coverage of 3.0 kg per sqm. or as per manufacturer's
specs over terrace. Brick bat shall then be laid in required slope to drain water for any span after cleaning and applying a coat of cement slurry
admixed with approved water proofing compound and laying brick bats in bottom layer in CM 1:5 admixed with approved waterproofing compound ,
applying cement slurry over this layer , jointing of brickbats with C.M 1 :3 admixed with approved water proofing compound and finally top finishing
average 20 mm thick layer of same mortar and providing 300 x 300 mm lining / making it rough to receive any further treatment all complete as
specified and directed. No separate treatment for bundwalls / junction of parapet wall & slab. All Material required for the job like brick bats, polymer,
sand, and any other consumables shall be arranged by contractor. Average thickness of brickbat coba water proofing is 150 mm and minimum
thickness is 50 mm.he contractor shall give ten years guarantee against all defects All above operations to be done in order and as directed and
specified by the Engineer-in-Charge.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 47 of 557
Description of Job
Providing & Laying membrane type waterproofing treatment using Moply Mineral Finish APP Modified Membrane - 4Kg/Sqm of Texsa or equivalent
make. Job includes removal of loose particles and dust by wire brush over a pre sloped surface, Priming by providing & applying bituminous adhesive
Tikitar or equivalent product (0.3 Ltr/Sqm), providing & applying APP modified membrane Moply - Mineral Finish - 4Kg/Sqm, 3.3mm thickness of Texsa
or equivalent make by using Torch Method. The overlap for membrane shall be minimum on length side - 75mm, width side - 100mm. For termination
at edge & parapet / drop down - up to 200mm extended towards outer side of parapet including cost of all materials, manpower, consumables, tools &
tackles etc. all complete as per drawings, specifications, application methodology & as per direction of EIC. Measurement shall be considered for
actual laid area. Contractor shall carry out 1st Pond Test on completion of work and 2nd Pond Test prior to start of next monsoon as per instruction of
EIC. Contractor will provide 5-year maintenance guarantee against any defects.
Providing and laying in-situ M15 Grade (1:2:4) with 12mm down aggregates floor Screed 25mm thick laid to proper level and slope in alternate bays
floated neat with cement and providing 300 x 300 mm grid and 8mm deep lining all complete including compaction, filling joints as per specifications
and as directed by engineer in charge.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 48 of 557
Description of Job
Providing and applying cellular light weight concrete (pumpable) ( Minimum thickness 100 mm , Maximum thickness : 180 mm ,average 140 mm thk)
of approved density of type 2 as per IS 6598 to be placed in situ over the surface of RCC slab / Brick bat coba and laid in a slope of 1:120 & cured at
ambient temperature and pressure by water etc.complete at all heights and locations.
Material shall be of grade A as per IS of density apprx.320 kg / M3. Crushing strength of dry cellular concrete shal be 0.25 MPa when tested in
accordance to IS 5688. The thickness of cellular concrete shall be min 100 mm and max to achieve a thermal conductivity ( at 50 Degree C) of 0.07
W/M Deg C per Sqm.
Finished product shall for perform for the ambient temperature of range 10 deg C to 60 Deg C. Finish of top surface shall be made ready to receive the
protective screed layer ( not covered under this item for measurment and payment) Detail product specification and application procedure shall be as
per RI-ID- MHMUMB001-C-SP-210 enclosed for ready reference.
All material, machinery and consumables required for the job except cement is in the scope of contractor.The treatment shall include making vata at
the junction of floor and wall as per standard specification for which no extra payment shall be made. Rate of shall include vata making.
Providing & laying China mosaic flooring for fast drainage of rainwater on the terrace with proper ridge & valley arrangement including thorough
cleaning of the area of work, laying of cement slurry, laying bedding mortar with mix of Cement mortar (1:4) mixed with @ 200 gms of waterproofing
compound ""Pidiproof LW or equivalent"" per bag of cement & @25 Kg of neeru per bag of cement, sprikling evenly powdered cement over wet
bedding for a thickness of 5-6 mm, laying tile chips of mix colour and material, about 4 to 5 mm thk, washing with water jet and ramming with wooden
mallet for perfect adhesion with the bedding without any hollow spots beneath and the required slope & pattern, Cleaning with saw dust to get a clean
surface. complete as per drawing, specification and as directed by EIC.
China mosaic treatment is to be turned around at the interface of the parapet wall for height of minimum 12 inches with proper coving at the junction.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 49 of 557
Description of Job
Curing shall be carried out after 24 hours of floor laying and shall be done by method of ponding with minimum depth of 75 mm water column and shall
be cured for minimum 10 days period. After curing period is over water to be drained out and tiles shall be cleaned with diluted HCL acid to get a
sparkling china mosaic surface. If any air holes are observed at the joints or some chips
are displaced, local repairs shall be done. Parapet/Bund walls on the periphery of the terrace slab shall be provided with the W/p plastering with drip
mould at the junction of the china mosaic (Water proof plaster shall be measured under seperate item)
China mosaic flooring shall be directly provided on screeding
All material required for the job is in the scope of contractor.
(e) The whole terrace so finished shall be flooded with water for a minimum period of two weeks for curing and for final test. The rate shall also include
curing and testing by water ponding for water tightness as required by EIC.The contractor shall give ten years guarantee against all defects All above
operations to be done in order and as directed and specified by the Engineer-in-Charge.
Providing and laying cementitous based polymer waterproofing treatment on roofs , toilets including protective cement mortar / concrete screed layer
.Job includes surface preparation consisting of cleaning the RCC slab using wire brush, chisels to make it perfectly clean, Grouting slab by fixing 20
mm dia. GI nipple at construction joint of RCC slab / any weak spot ( if observed ) and then pumping cement slury into it, Opening up any cracks in V
shape & filling the same with polymer modified mortar and than applying one coat of primer (if specified by Manufactuerer) and applying two coats of
highly flexible two components of polymer based waterproofing treatment as per manufacturer's specification for all heights and locations . Coverage
of primer and Polymer coating including Thickness of polymer shall be as per manufarturer's specifications . After 24 hrs of drying waterproof coating is
to be protected with 25 to 30 mm thick cement mortar screed using cement , sand and 6 mm stone aggregate to protect polymer coating. All Material
required for the job like polymer, sand,
and any other consumables shall be arranged by contractor. The contractor shall give ten years guarantee against all defects for the waterproofing
work done.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 50 of 557
Description of Job
Providing and filling Brickbat in 1:6 cement mortar for sunken portion of Toilet with all material at all location and heights. The item includes:
* 20mm thick bottom screed in CM 1:5
* Filling brick bats in CM 1:3 in a layers of 200 mm thick
* 20mm thick screed in CM 1:5 on top of each brickbat layer
All above operations to be done in order and as directed and specified by the Engineer-in-Charge.
Waterproofing in Server Halls :- Providing waterproofing treatment in Server Halls below False Flooring under Precission Air Conditioners having slope
1:200 with minimum thickness of 25mm (a)Providing and laying cementitous based polymer waterproofing treatment on,
including protective cement mortar / concrete screed layer .Job includes surface preparation consisting of cleaning the RCC slab using wire brush,
chisels to make it perfectly clean , Grouting slab by fixing 20 mm dia. GI nipple at construction joint of RCC slab / any weak spot ( if observed ) and
then pumping cement slury into it, Opening up any cracks in V shape & filling the same with polymer modified mortar and than applying one coat of
primer and applying two coats of highly flexible two components of polymer based waterproofing treatment as per manufacturer's specification for all
heights and locations .
Coverage of primer and Polymer coating including Thickness of polymer shall be as per manufarturer's specifications .
(b) Finishing the surface with 20 mm thick jointless cement mortar of mix 1:3 (1 cement :3 coarse sand) admixed with proprietary water proofing
compound conforming to IS : 2645 and finally finishing the surface with trowel with neat cement slurry including treating vertical surface of walls for
rounding at corners etc.
(c) All above operations to be done in order and as directed and specified by the Engineer-in-Charge.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 51 of 557
Description of Job
Supplying and fixing of Leaf trap with khurra made out of UPVC with flange and grating for rainwater outlets on terrace including all necessary
grounting with sealants to make it absolutely water proof.
110 mm
Supplying and fixing of Leaf trap with khurra made out of UPVC with flange and grating for rainwater outlets on terrace including all necessary
grounting with sealants to make it absolutely water proof.
160 mm
and cladding
Supply and fixing 0.55mm thick precoated Galvalume sheets of approved quality and shade in roof and cladding including supply and fixing of
approved quality translucent FRP sheets for skylights, polycoated GI J-bolts/ L-bolts/ SDST screws, polymer washers, cost of drilling, cutting, all tools
and tackles, scaffolding etc. complete as per drawings, specifications and as directed by EIC.
Note: Net area of roof/ cladding will be measured for payment.
Supply and fixing 0.55mm precoated Galvalume sheets of approved quality and shade in ridge/ gutter/ flashing/ corner pieces etc including supply and
fixing of approved quality translucent FRP sheets for skylights, polycoated GI J-bolts/ L-bolts/ SDST screws, polymer washers, cost of drilling, cutting,
all tools and tackles, scaffolding etc. complete as per drawings, specifications and as directed by EIC.
Note: Net plan area will be measured for payment.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 52 of 557
Description of Job
For Ridge
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 53 of 557
Description of Job
Providing and applying 3 coats whitewash on walls at all heights including scafffolding as directed by EIC.
Providing & Applying 2-Coat of Premium Plastic Emulsion of Asian paint (Or any other approved manufacturer) of approved shade & colour on wall
Including surface preparation consisting of cleaning the surface to be painted using brush and sand the surface using emery paper 180 to remove all
the loose particles, apply a coat of Asian Paints Decoprime Primer (Water/solvent thinner), allow to dry for 6 to 8 Hours, smoothen the surface with 2
coats of wall Putty, allow drying for 4 to 6 Hours, sand the surface with emery paper 180 and apply another coat of Asian paints Decoprime Primer
and allow it to dry for 6 to 8 Hours. Top Coat application: Apply one coat of Asian paint Premium Plastic Emulsion Paint brush followed by Roller. Allow
drying for 3 to 4 hours and apply another coat of Premium Plastic emulsion all complete as per drawing and as directed by Engineer in Charge.
including cost of scaffolding etc. complete as per drawings, specifications and as directed by EIC.
Note: Application of acrylic emulsion paint by brush or roller.
Application gap of 8 hours is to be observed between two coats of acrylic emulsion paint and approved at every stage of painting by EIC.
Supply and application of one coat of primer and 2 coats of external acrylic decorative and protective emulsion paint of approved or equivalent of
approved shade, including surface preparation,curing, minor putty work, scaffolding etc. complete as per drawings, specifications and as directed by
EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 54 of 557
Description of Job
Providing and applying 2 coats of anti carbonation paint approved
equivalent make of approved colour and shade at all heights to
internal/external surfaces including erection & removal of scaffolding, surface preparation, providing and applying 1 coat of primer of dulux or
approved equivalent make including erection & removal of staging or scaffolding, etc. complete as per detailed drawing, manufacturer's specification
and as directed by EIC.
Providing and laying 18-20mm thick granite in flooring laid over 20-30 mm thick 1:4 cement mortar, including cost of stone cutting, filling joints with
matching colour pigments, mirror polishing etc. complete as directed by EIC. Landed Rate of Granite @ Rs. 175/- per SQFT including VAT
Providing and laying Vitrified Tiles 600mmx600mm of approved quality & shade in flooring including cost of tile cutting, 25mm - 30mm bedding in CM
1:4, filling the joints in matching colour pigments etc. complete as per drawing, specifications and as directed by EIC. Landed rate of tiles @
Rs.70/SQFT including vaT.
Providing and laying non-skid Vitrified Tiles 600mmx600mm of approved quality & shade in flooring of pantry, toilet, store, passage etc including cost of
tile cutting, 25mm - 30mm bedding in CM 1:4, filling the joints in matching colour pigments etc. complete as per drawing, specifications and as directed
by EIC. Landed rate of tiles @ Rs.45/-per SQFT including vAT
Providing and laying 40mm thick M-15 Grade IPS Flooring to proper line, level and slope in alternate bays and including cost of channels for side
shuttering, vibration, compaction, pond curing, smooth finishing, string marking if any as required etc. complete as per drawing, specifications and as
directed by EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 55 of 557
Description of Job
Providing & laying 50 mm thick I.P.S. flooring in cement concrete of proportion M15 laid in bays as per I.S.I. Specification including providing & fixing
4mm thick glass strip if required for paneling with all tools and tackles, PPE's as per the instruction of EIC.
Providing and Laying M20 Grade 75mm thick screed to proper line, level and slope in alternate bays and including vibration, compaction, pond curing,
side shuttering, smooth finishing, cutting of grooves or string marking if any etc. complete as per drawing, specifications and as directed by EIC
Providing and laying 28-32mm thick machine cut machine polished kota stone of reqired size in flooring laid over 20-30 mm thick 1:4 cement mortar,
including cost of stone cutting, filling joints with matching colour pigments, mirror polishing etc. complete as directed by EIC.
Supply and application of self leveling Epoxy flooring consisting of primer coat and floor topping forming total thickness of 2 mm of Sika, Ciba Geigy,
Pidilite or approved equivalent make on existing IPS flooring at all elevations & locations , including minor repairing work as required, filling dents,
holes, undulations etc. with epoxy repair mortar, surface preparation etc. complete as per manufacturer's specifications and as directed by EIC.
Providing and laying RMC/ weigh-batched machine-mixed M-15 grade plain cement concrete in floor screed of average thickness 40mm at all levels to
proper line, level and slope and including cost of side shuttering if any, finishing, pond curing etc. complete as per drawings, specifications and as
directed by EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 56 of 557
Description of Job
P & L 12mm thick Acid / Alkali Resistant Tiles of size size 300 mm x 300 mm x12 mm thick using furacin cement confirming to IS 4457 Class 1 over
the concrete surface, complete as per specification, drawings and as directed by the EIC
Providing and laying of Composite marble (Artificial / Engineered) approx. 20 mm thick of approved quality, type and colour for flooring at various
location, including cutting to the required sizes, shapes & pattern as per the architectural drawings and laying to the required level / slope including all
surface preparation, laying cement mortar (1:4) bed of average thickness 25mm with cement slurry / paste spread on the top of mortar using cement
of standard specification, cleaning joints of tiles and grouting them in Temax. Sides to be cleaned with polish paper to smoothen the tiles before laying.
A thin layer of white cement to be applied over base of cement morter before placing of marble slab. Flooring is in combination of - TIBERIO (max.
size 2400 x 1200 mm) and ARCADIO (max. size 1800 x 1200 mm) of Kalingastone series of Classic Marble Company of approved variety & lot, all
complete including Polishing of Composite marble. contratctor shall follow below menioned procedure for Polishing of composite marble:- 1.Cleaning
of the Marble using required chemicals and pads. 2.Vacuuming dirty water & slurry. 3.Cutting of Marble using 800 grit diamond pads 4.Vacuuming of
dirty water & slurry. 5.Cutting of Marble using 1500 grit diamond pads 6.Vacuuming of dirty water & slurry 7. Cutting of Marble using 3000 grit diamond
pads. 8. Polishing of Marble using required buffing pads 9. Buffing tp Glossy finishes aas directed by Engineer in Charge. landed rate of stone Rs.250
per sft including VAT
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 57 of 557
Description of Job
Providing and Fixing Artifical Marble ARCADIO of Kalingastone series of classic marble company or any other approved make for Skirting 12 mm thick
of Height 600 mm of approved quality, type & colour as per the approved sample including cutting to the required sizes, shapes & pattern as per the
architectural drawings including all surface preparation like chipping of Plaster / masonary, providing & laying cement mortar (1:3) bed of average
thickness 12 to 15 mm, tile to be fixed with white cement slurry / paste as per standard specification, cleaning joints and grouting them cement paste
with pigmented additives to match shade of the stone, Mirror Polishing etc. The rate also includes curing, cleaning etc complete as directed by
Engineer in Charge.
Providing and laying 18-20mm thick granite in skirting of height upto 100mm flushed with plaster including cost of stone cutting, cutting of masonry/
RCC, cement mortar of 1:4 of 12-15mm thk, filling the joints with matching colour pigments, mirror polishing, making 6mmx6mm grooves etc. complete
as per specification and as directed by EIC. Landed Rate of Granite @ Rs. 175/- per SQFT. including VAT
Providing and laying kota stone in skirting of height upto 100mm flushed with plaster including cost of stone cutting, cutting of masonry/ RCC, cement
mortar of 1:4, filling the joints with matching colour pigments, mirror polishing, making 6mmx6mm grooves etc. complete as per specification and as
directed by EIC.
?
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 58 of 557
Description of Job
Providing and laying 100 mm high skirting of vitrified tiles including cutting of tiles & masonry work, making grooves( if required) , tiles are to be laid for
cement mortar bedding 12-15mm of 1:4, filling joints with matching pigments etc. complete as directed by the engineer-in-charge. Landed cost Rs.70/including VAT
P&L Kota Stone Skirting: Providing and fixing Kota stone 18 to 20 mm thick for Skirting of Height 300 mm of approved quality, type & colour as per
the approved sample including cutting to the required sizes, shapes & pattern as per the architectural drawings and to be fixed on cement board with
epoxy based adhesive surface preparation, cleaning joints, grouting the joints with cement paste with pigmented additives to match shade of the stone,
Mirror Polishing etc.completed as directed by engineer in charge. The Flooring joint to match that of flooring.
P&L Kota Stone Skirting: Providing and fixing Kota stone 18 to 20 mm thick for Skirting of Height 300 mm of approved quality, type & colour as per
the approved sample including cutting to the required sizes, shapes & pattern as per the architectural drawings including all surface preparation like
chipping of Plaster / masonary, providing & laying cement mortar (1:4) bed of average thickness 12 to 15 mm, tile to be fixed with cement slurry / paste
as per standard specification, cleaning joints and grouting them cement paste with pigmented additives to match shade of the stone, Mirror Polishing
etc completed as directed by engineer in charge. The Flooring joint to match that of flooring.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 59 of 557
Description of Job
Providing and laying kota stone in trapezoidal skirting 100mm/250mm high on staircase flushed with plaster including cutting of stone, cutting of
masonry/ RCC, cement mortar 1:4 with cement mortar bedding of 12-15mm thk, filling joints with matching color pigments, mirror polishing etc.
complete as directed by EIC.
Providing and laying Vitrified Tiles of approved quality & shade in dado with 1:4 cement mortar including cost of tile cutting, filling the joints in matching
colour pigments etc. complete as per drawing and as directed by EIC. Landed rate of tiles @ Rs. 70/SQFT including VAT.
Thickness
Providing and laying Glazed Tiles of approved quality & shade in dado with 1:4 cement mortar including cost of tile cutting, filling the joints in matching
colour pigments etc. complete as per drawing and as directed by EIC. Landed rate of tiles @ Rs. 45/SQFT including VAT.
Providing and fixing in staircase tread 300mm wide 18-20mm thick flame finished Granite Stone of approved quality and shade including 20-30mm
thick bedding in CM 1:4, filling the joints with matching colour pigments, full round moulding, polishing, providing 3 nos. of 4mm wide non-slip grooves
at the nosing end etc. complete as per drawings, specifications and as directed by EIC.
Landed rate of granite@ Rs.175/Sqft including VAT.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 60 of 557
Description of Job
Providing and fixing in staircase riser 150mm high 18-20mm thick
pre-polished Granite of approved quality and shade including 10-12mm thick 1:3 Cement Mortar, filling the joints with matching colour pigments,
polishing etc. complete as per drawings, specifications and as directed by EIC.
Landed cost of granite @ Rs. 175/Sqft including VAT.
Providing and laying 300 mm wide kota stone in stair case treads including 20-30mm bedding in 1:5 cement mortar, filling joints with matching colour
pigments, full round nosing, 3 nos. of 3mm non-slip grooves, mirror polishing etc. complete as per drawing, specifications and as directed by EIC.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 61 of 557
Description of Job
Lift Archatrive:- Providing & fixing 20mm thk PORTORO of Kalingastone series of Classic Marble Company or of approved variety & lot for Lift
Archatrive ( Jambs, Soffit and Sill) with epoxy based addhesive over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand), with cement
slurry / paste spread over using to proper level and a true plumb including rubbing all complete as per drawing and as directed by Engineer in
Charge. Landed cost is Rs.250/- including vAT
STEEL
Supply, fabrication, painting and erection of light weight structures(sections wt. <= 25 Kg/m), plates <= 10mm thick including (i) Supply of structural
steel as per Indian Standard. (ii) Fabrication: Straightening (if required), cutting to required size, grinding, drilling of holes, welding or bolting of joints
and completing the work as per drawings, specifications, relevant codes and directions of the EIC. Minor detailing/ layout if required for fabrication shall
be carried out. Trial assembly if required shall be in contractor's scope. Provision of all type to staff and workmen, provision of all required lifting toolstackles including P&M, all type of welding & cutting consumables and gases are in contractor's scope. (iii) Painting: including blasting of steel with grits
& shots to SA 2.5 with approved make of one coat of inorganic zincsilicate primer after Sand Blasting/Shot Basting, DFT (Microns): 75, one coat of
High Build MIO Epoxy Intermediate DFT (Microns): 125 , final coat of Aliphatic Urethane Finish DFT (Microns): 75 using airless spray gun as per
specification & directed by EIC. (iv) Erection: includes of all structural steel/ panels/ modules at all heights including tools,tackles,P&M, fixing &
removal of safety net, cutting, trimming, drilling, grinding, fit up, welding, alignment & levelling with temporary staging, bolting to required torque, touch
up painting, completing the work in all respect as per drawings, specifications and codes as per the instructions of EIC and fulfilling owner's safety
norms & practices at work site including NDT as per requirement & specification.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 62 of 557
Description of Job
Supply, fabrication, painting and erection of medium weight structures (sections wt. 25 < >=75 kg/m), plates 10 < >= 20mm thick including (i) Supply of
structural steel as per Indian Standard. (ii) Fabrication: Straightening (if required), cutting to required size, grinding, drilling of holes, welding or bolting
of joints and completing the work as per drawings, specifications, relevant codes and directions of the EIC. Minor detailing/ layout if required for
fabrication shall be carried out. Trial assembly if required shall be in contractor's scope. Provision of all type to staff and workmen, provision of all
required lifting tools-tackles including P&M, all type of welding and cutting consumables and gases are in contractor's scope. (iii) Painting: Painting:
including blasting of steel with grits & shots to SA 2.5 with approved make of one coat of inorganic zincsilicate primer after Sand Blasting/Shot Basting,
DFT (Microns): 75, one coat of High Build MIO Epoxy Intermediate DFT (Microns): 125 , final coat of Aliphatic Urethane Finish DFT (Microns): 75 using
airless spray gun as per specification & directed by EIC. (iv) Erection: includes of all structural steel/ panels/ modules at all heights including
tools,tackles,P&M, fixing & removal of safety net, cutting, trimming, drilling, grinding, fit up, welding, alignment & levelling with temporary staging,
bolting to required torque, touch up painting, completing the work in all respect as per drawings, specifications and codes as per the instructions of EIC
and fulfilling owner's safety norms & practices at work site including NDT as per requirement & specification.
Supply, fabrication, painting and erection of heavy weight structures (sections wt. 75 < >=150 kg/m), plates 20 < >= 50mm thick including (i) Supply of
structural steel as per Indian Standard. (ii) Fabrication: Straightening (if required), cutting to required size, grinding, drilling of holes, welding or bolting
of joints and completing the work as per drawings, specifications, relevant codes and directions of the EIC. Minor detailing/ layout if required for
fabrication shall be carried out. Trial assembly if required shall be in contractor's scope. Provision of all type to staff and workmen, provision of all
required lifting tools-tackles including P&M, all type of welding and cutting consumables and gases are in contractor's scope. (iii) Painting: Painting:
including blasting of steel with grits & shots to SA 2.5 with approved make of one coat of inorganic zincsilicate primer after Sand Blasting/Shot Basting,
DFT (Microns): 75, one coat of High Build MIO Epoxy Intermediate DFT (Microns): 125 , final coat of Aliphatic Urethane Finish DFT (Microns): 75 using
airless spray gun as per specification & directed by EIC. (iv) Erection: includes of all structural steel/ panels/ modules at all heights including
tools,tackles,& P&M, fixing & removal of safety net, cutting, trimming, drilling, grinding, fit up, welding, alignment & levelling with temporary staging,
bolting to required torque, touch up painting, completing the work in all respect as per drawings, specifications and codes as per the instructions of EIC
and fulfilling owner's safety norms & practices at work site including NDT as per requirement & specification.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 63 of 557
Description of Job
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 64 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
3750
6800
2640
1100 21090
UOM
IDC
CUM
6800
CUM
1360
750
1360
525
220
4215
CUKM 5440
3000
5440
2115
880
16875
CUM
3250
4300
2370
810
16430
5700
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 65 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
2700
5825
1710
1342 14827 (Rs.)
UOM
IDC
SQM
3250
SQM
1600
1800
3890
1645
3565
12500
SQM
1550
900
1945
570
2375
7340
SQM
1200
SQM
1200
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 66 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
60
188
35
32
415 (Rs.)
UOM
IDC
MT
100
MT
190
40
130
30
60
450
MT
180
20
65
10
51
326
MT
132
132
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 67 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
50
300
115
64
729 (Rs.)
UOM
IDC
CUM
200
CUM
100
10
10
130
CUM
250
50
60
10
10
380
CUM
1100
500
2500
270
291
4661
CUM
50
370
850
275
1550
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 68 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
430
640
175
430
2935 (Rs.)
UOM
IDC
CUM
1260
CUM
1260
CUM
1285
Nos.
100
20
50
50
20
240
Nos.
100
20
50
50
20
240
145
215
60
290
1970
1285
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 69 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
3
8
3
2
40
(Rs.)
UOM
IDC
MT
24
SQM
SQM
SQM
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 70 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
2100
2200
1100
10
9810 (Rs.)
UOM
IDC
SQM
4400
SQM
100
175
196
65
SQM
4400
2100
3300
85
45
9930
CUM
10
10
10
10
10
50
CUM
10
10
10
10
10
50
RM
50
10
20
86
536
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 71 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
5
5
5
5
30
(Rs.)
UOM
IDC
EA
10
EA
10
30
MT
EA
CUM
CUM
CUM
10
15
10
20
10
65
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 72 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
85
110
30
5
240 (Rs.)
UOM
IDC
CUM
10
SQM
Nos.
10
30
Nos.
10
30
Nos.
Nos.
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 73 of 557
UOM
IDC
Nos.
Nos.
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
1
1
1
1
5
(Rs.)
Sqm
20
15
20
55
RM
10
10
35
55
RM
RM
420
647
200
232
48
420
97 1224
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 74 of 557
UOM
IDC
SQM
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
3000 (Rs.)
CUM
2100
530
SQM
50
50
CUM
800
450
90
3170
100
800
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 75 of 557
UOM
IDC
CUM
400
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
515 (Rs.)
50
65
60
SQM
60
26450
SQM 20000
4020
1980
450
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 76 of 557
UOM
IDC
SQM
100
SQM 10000
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
200 (Rs.)
100
2525
656
13181
15265
SQM
8200
3770
2040
1255
26450
SQM 20000
4020
1980
450
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 77 of 557
UOM
IDC
RMT
1000
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
2250 (Rs.)
700
300
250
10000
RMT
7500
1500
1000
50
RMT
50
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 78 of 557
UOM
IDC
SQM
4200
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
4200 (Rs.)
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 79 of 557
UOM
SQM
IDC
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
2170 (Rs.)
1420
750
2170
SQM
1420
750
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 80 of 557
UOM
IDC
SQM
4000
SQM
4200
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
1420
750
6170
6170
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 81 of 557
UOM
IDC
SQM
4200
SQM
225
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
6170
100
325
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 82 of 557
UOM
IDC
CUM
200
SQM
2000
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
26
226
2000
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 83 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
UOM
IDC
EA
EA
20
12
40
SQM
1770
1770
RMT
300
300
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 84 of 557
UOM
IDC
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
RMT
100
100
RMT
200
200
RMT
200
200
RMT
200
200
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 85 of 557
UOM
IDC
SQM
1200
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
300
150
1650 (Rs.)
SQM 20200
6440
1980
685
29305
SQM
3760
2040
1255
15255
8200
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 86 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
UOM
IDC
SQM
1800
SQM
520
SQM
1500
120
1620
SQM
150
70
220
SQM
5250
1200
850
3850
520
200
5450
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 87 of 557
UOM
IDC
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
SQM
1400
1400
SQM
300
750
100
1150
SQM
700
140
75
915
SQM
7000
750
500
8250
SQM
1000
440
50
1490
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 88 of 557
UOM
IDC
SQM
100
SQM
375
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
100
50
250
375
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 89 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
UOM
IDC
RMT
50
50
RMT
200
200
RMT
1720
160
140
70
2090
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 90 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
UOM
IDC
RMT
900
RMT
925
925
RMT
750
750
50
950
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 91 of 557
UOM
IDC
RMT
50
SQM
150
SQM
45
RMT
420
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
60
25
35
170
150
40
85
420
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 92 of 557
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
UOM
IDC
RMT
420
RMT
80
250
15
40
385
RMT
80
250
18
40
388
SQM
15
15
SQM
1900
1900
420
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 93 of 557
UOM
IDC
SQM
200
MT
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
200
245
106
351
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 94 of 557
UOM
IDC
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
MT
87
38
125
MT
105
45
150
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 95 of 557
UOM
IDC
Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
SA
10069-SOQ-NA2CF-001
Date: 08-04-2015
Rev. 1
Sheet 96 of 557
SI no.
Description
UOM
Rate
1
1.1
1.2
1.3
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.1
2.11
Labour Rates
Skilled labour
Semi Skilled labour
Unskilled labour
Material Rates
M-day
M-day
M-day
348
316
288
Cement
Sand
Aggregates 10mm,20mm, 40mm
Reinforcement bars
Boulder 9"
Murrom
Good earth
Structural steel
Ply wood 9 mm THK
Hard Wood
Wire Nails
EA
Cum
Cum
MT
cum
CUM
Cum
MT
Sq m
Cft
Kg
350
3500
750
36000
500
250
300
40000
700
Sl no.
Description
1
3
4
5
6
USL excavation
Supervisor
Sub Total
Contractor's OH & P
Sub Total
Sl no.
Description
USL excavation
Excavation in SOIL
Measurements
Unit
Nos
L
B
H
manday
0.5 ( I USL can excavate 2 m3 /day )
manday
0.05
( 1 supervisor per 10 USL )
Qty
Rate
0.5
0.05
288
0
per m3
Excavation in SOFT ROCK
Measurements
Unit
Qty
Nos
L
B
H
manday 1.33333
( I USL can excavate 0.75 m3 /day1.333333333
)
Rate
288
3
4
5
6
Supervisor
Sub Total
Contractor's OH & P
Sub Total
Sl no.
Description
1
3
4
5
6
USL excavation
Supervisor
Sub Total
Contractor's OH & P
Sub Total
Sl no.
1
2
3
4
5
Description
manday 0.13333
0.133333333
0
per m3
Excavation in HARD ROCK
Measurements
Unit
Nos
L
B
H
manday
2 ( I USL can excavate 0.5 m3 /day )
manday
0.2
( 1 supervisor per 10 USL )
Qty
Rate
2
0.2
288
0
per m3
Sl no.
Description
Unit
1
1.1
1.2
Material
Good Earth
Murram
m3
m3
Qty
Rate
?
?
15%
Backfilling
Measurements
Nos
L
B
Qty
Rate
300
250
2
3
4
5
6
7
Unskilled labour
Supervisor
water charges for consolidation
Sub Total
Contractor's OH & P
Sub Total
Sl no.
Description
1
1.1
1.2
1.3
2
3
4
4.1
4.2
5
6
7
8
8.1
8.2
8.3
8.4
9
10
11
Material per sq ft
Ply 9-12 mm thk
Hard wood
Wire nails
Sub total
Wastage
Manpower
Carpenter
Helper
Sub Total cost per sq m
Nos of repetitions
Cost per repetition
Cost of fixing
Carpenter
Helper
Wire nails
Shuttering oil
Sub Total
Contractor's OH & P
Total
manday
manday
0.07
0.007
288
0
per m3
Form Work (below FGL)
Measurements
Unit
Nos
L
B
Sq m
Cuft
kg
1
2
0.25
Qty
Rate
1
2
0.25
700
2%
man days
man days
0.07
0.13
0.07
0.13
348
288
man days
man days
kg
LS
0.1
0.2
0.25
0.1
0.2
0.25
348
288
15%
Sl no.
Description
Unit
1
2
LS
LS
9
10
11
Sl no.
Description
1
2
9
10
11
Sl no.
Description
1
2
9
10
11
Sl no.
Description
Nos
Measurements
L
B
Qty
15%
Rate
Qty
Rate
15%
Qty
Rate
15%
Qty
Rate
1
9
10
11
Curve shuttering
Sub Total
Contractor's OH & P
Total
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
11
12
13
Reinforcement
Wastage
Rolling Margin
Realisation of scrap
Sub Total cost of reinforcement
Labour for cutting bending & fixing
Skilled
Unskilled
binding wires
Transportation
Sub Total cost of reinforcement
contractor's OH & P
Total
Sl no.
Description
1
2
3
4
5
1
15%
mandays
mandays
kg
4
8
6
Qty
Rate
1
0.03
0.05
-0.02
36000
36000
36000
36000
4
8
6
348
288
40
Qty
Rate
Sl no.
Description
Unit
1
2
3
4
5
Sl no.
Description
1
2
3
4
5
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
11
12
Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
Unskilled labour
Supervisor
Sub Total
Contractor's OH & Profit
Total Cost of RMC M 10
Nos
Measurements
L
B
Qty
Rate
Qty
Rate
PCC M 10 Grade
Measurements
Unit
Nos
L
B
bag
m3
m3
0.03
0.05
LS
man day
manday
1
0.1
(1 manday per m3 )
supervisor can handle 10
labours in 1 manday
Qty
Rate
4.2
0.52
0.85
350
3500
750
1
0.1
288
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
11
12
Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
Unskilled labour
Supervisor
Sub Total
Contractor's OH & Profit
Total Cost of PCC M 15
Sl no.
Description
1
1.1
1.2
1.3
2
3
4
5
6
7
8
9
PCC M10
Cement
Sand
Aggregate (coarse)
Plum aggregate (Boulder)
Boulder breaking charge
Sub Total cost of materials
Wastage
Water & Power
Tools & Tackles
Unskilled labour
Supervisor
PCC M 15 Grade
Measurements
Unit
Nos
L
B
bag
m3
m3
0.03
0.05
LS
man day
manday
1
0.1
(1 manday per m3 )
supervisor can handle 10
labours in 1 manday
Qty
Rate
6.2
0.52
0.85
350
3500
750
1
0.1
288
3%
5%
LS
man day
manday
Qty
Rate
3.36
0.416
0.68
0.2
350
3500
750
500
0
0
1
0.1
(1 manday per m3 )
supervisor can handle 10
labours in 1 manday
1
0.1
288
10
11
12
Sub Total
Contractor's OH & Profit
Total Cost of RMC M 15
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
11
12
Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
USL
Sueprvisor
Sub Total
Contractor's OH & Profit
Total Cost of M30
Sl no.
Description
1
2
3
4
5
6
7
8
9
Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
USL
Sueprvisor
1
0.1
Qty
Rate
350
3500
750
(1 manday per m3 )
supervisor can handle 10 labours
1
0.1
288
1
0.1
(1 manday per m3 )
Qty
Rate
8
0.52
0.85
350
3500
750
1
0.1
288
11
12
13
Sub Total
Contractor's OH & Profit
Total Cost of M20
Sl no.
Description
1
2
3
4
5
Sl no.
Description
1
2
3
4
5
Sl no.
Description
1
2
3
4
5
Sl no.
Description
Qty
Rate
Qty
Rate
Qty
Rate
Qty
Rate
Sl no.
Description
1
2
3
4
5
Sl no.
Description
1
2
2.1
2.2
2.3
3
4
4.1
4.2
5
6
7
Sl no.
Description
1
2
2.1
2.2
2.3
3
Unit
Nos
Qty
Rate
Qty
Rate
each
each
mandays
mandays
0
Qty
Rate
4
4.1
4.2
5
6
7
Sl no.
Description
1
2
3
4
5
Board
Labour
Sub Total
Contractor's OH & Profit
Total Cost of Treatment
Sl no.
Description
1
2
3
4
5
Board
Labour
Sub Total
Contractor's OH & Profit
Total Cost of Treatment
Sl no.
Description
1
2
3
4
Chemical cost
Labour
Sundries and sprayer
Sub Total cost of materials
mandays
0
Qty
Rate
354
Qty
Rate
710
Qty
Rate
5
6
7
Sub Total
Contractor's OH & Profit
Total Cost of Treatment
Sl no.
Description
1
2
3
4
5
6
7
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
11
Rubble
Breaking
Cement
sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total
Sl no.
Qty
Rate
0.67
1.33
Qty
Rate
1.35
1.35
1.8
0.31
500
350
3500
0.67
1.33
348
288
0
Qty
Rate
Sl no.
Description
Unit
1
2
3
4
5
6
7
labour
Supervisor
Transporation
Tools & Tackles
Sub Total
contractor's OH & P
Total
mandays
mandays
Sl no.
1
2
3
4
5
6
7
Nos
Qty
Rate
LS
0
Sl no.
Description
Unit
1
2
3
4
5
6
7
Sand
Polysulphide Sealent
USL
Supervisor
sub total
contractor's OH & P
Total
m3
Kg
Isolation Joints
Measurements
Nos
L
B
Qty
Rate
Qty
Rate
3500
400
mandays
0
Pockets
Sl no.
Description
1
2
3
4
5
6
Formwork
USL
Supervisor
sub total
contractor's OH & P
Total
Sl no.
Description
Unit
Description
1
2
3
4
NS Grout
Water & Power
Tools & Tackles
USL
Qty
Rate
mandays
0
1
Cement
2
Sand
3
Sub Total cost of materials
4
Wastage
0.03
5
Water & Power
0.05
6
Tools & Tackles
LS
7
USL
man day
8
Sueprvisor
manday
9
Formwork
sqm
10
Sub Total
11
Contractor's OH & Profit
12Total Cost of Mixing & laying Cement Grout
Sl no.
Nos
Measurements
L
B
1
(1 manday per m3 )
0.1 1 supervisor can handle 10 labours
Qty
Rate
13.68
0.95
350
3500
1
0.1
1
288
348
118
0
Qty
Rate
2220
20
288
5
Sueprvisor
manday
6
Formwork
sqm
7
Sub Total
8
Contractor's OH & Profit
9Total Cost of Mixing & laying Cement Grout
Sl no.
Description
1
2
3
4
5
Concrete M15
Formwork
Sub Total
Contractor's OH & Profit
Total
Sl no.
Description
1
2
4
6
7
8
3
5
0.1
1
348
118
0
Qty
Rate
1
1
6079
118
0
Expansion Joints
Measurements
Unit
Nos
L
B
Sqm
1
kg
manday
Qty
Rate
354
400
288
0
kg
LS
180
Sl no.
Description
Unit
1
2
2.1
2.2
2.3
2.4
MS Sheet
Others materials
Horizontal
Vertical
Bracing
Sub Total
kg
3
4
5
Prime Coat
Enamal Paint (2 Coat)
semi Skilled Labour
sqm
sqm
6
7
8
9
Supervisor
Sub Total
Contractor's OH & Profit
Total
manday
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
cost of brick
cement
sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total
Barricading
Measurements
Nos
L
B
1
2.5
2
H
0.00163
m
m
m
Qty
Rate
67.18
40
5
4
3.2
41.0
40
316
0.1
348
0
0.67
1.33
Qty
Rate
496
1.9
0.26
6
350
3500
0.67
1.33
348
288
0
Sl no.
Description
1
2
3
4
cost of brick
cement
sand
sub total
MS Rod
skilled mason
unskilled
sub total
contractor's OH & P
Total
6
7
8
9
10
Sl no.
Description
1
2
3
4
6
7
8
9
10
cost of brick
cement
sand
sub total
skilled mason
unskilled
sub total
contractor's OH & P
Total
Sl no.
Description
1
2
cost of blocks
cement
mandays
mandays
0.67
1.33
Qty
Rate
57
0.22
0.03
6
350
3500
6
0.67
1.33
348
288
0
0.67
1.33
Qty
Rate
174
0.66
0.09
6
350
3500
0.67
1.33
348
288
0
Qty
1.00
1.87
Rate
3200
350
3
4
5
6
7
8
9
10
sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total
m3
0.31
3%
mandays
mandays
0.67
1.33
0.26
3500
0.67
1.33
348
288
0
Sl no.
Description
cement
bag
0.090
350
2
3
4
5
6
7
8
9
10
11
sand
sub total
wastage
skilled mason
unskilled
Lead and lifts
Scaffolding
sub total
contractor's OH & P
Total
m3
0.012
3500
Sl no.
Description
1
2
3
4
5
cement
sand
sub total
wastage
skilled mason
3%
mandays
mandays
LS
LS
0.07
0.13
Qty
0.07
0.13
Rate
348
288
0.07
Qty
0.075
0.008
0.07
Rate
350
3500
348
6
7
8
9
10
11
unskilled
Lead and lifts
Scaffolding
sub total
contractor's OH & P
Total
Sl no.
Description
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
cement
sand
sub total
wastage
manpower for 1st coat
skilled mason
unskilled
manpower for 2nd coat
skilled mason
unskilled
sand facing
Lead & Lifts
Scaffolding
sub total
contractor's OH & P
Total
mandays
LS
LS
0.13
0.13
288
Qty
Rate
0.16
0.02
350
3500
3%
mandays
mandays
0.07
0.13
0.07
0.13
348
288
mandays
mandays
LS
LS
LS
0.07
0.13
0.07
0.13
348
288
Amount
144
0
144
21.6
165.6
Amount
384
0
384
57.6
441.6
Amount
576
0
576
86.4
662.4
Amount
Amount
0
0
20.16
0
20.16
3.024
23.184
Amount
700
0
0
700
14
23.2
38.4
775.6
10
77.56
34.8
57.6
10
102.4
15.36
117.76
Amount
102.4
102.4
15.36
117.76
Amount
102.4
102.4
15.36
117.76
Amount
102.4
102.4
15.36
117.76
Amount
0
0
0
0
Amount
36000
1080
1800
-720
38160
1392
2304
240
42096
6314
48410
Amount
42096
0
42096
6314
48410
Amount
42096
42096
6314
48410
Amount
42096
42096
6314
48410
Amount
1470
1820
638
3928
118
196
288
0
4530
679
5209
Amount
2170
1820
638
4628
139
231
288
0
5286
793
6079
Amount
1176
1456
510
100
0
3242
97
162
288
0
3789
568
4358
Amount
0
0
0
0
0
0
288
288
43.2
331.2
Amount
2800
1820
634
5254
158
263
288
0
5962
894
6857
Amount
6857
6857
1029
7885
Amount
288
288
43.2
331.2
Amount
288
288
43
331
Amount
Amount
288
288
43
331
Amount
Amount
Amount
354
Amount
710
Amount
6
Amount
6079
Amount
675
0
630
1085
2390
72
232
384
3078
462
3539
Amount
Amount
Amount
Amount
Amount
Amount
4788
3325
8113
243
406
288
35
118
9203
1380
10583
Amount
44400
2220
288
35
118
47061
7059
54120
Amount
6079
118
6196
929
7126
Amount
0
0
0
1221874
79676
610847
180
Amount
2687
1640
0
0
0
35
4362
654
5016
Amount
2,979
655
910
4,544
136
232
384
5,296
794
6,091
Amount
343
75
105
523
232
384
1,139
171
1,309
Amount
1,043
229
319
1,590
232
384
2,206
331
2,537
Amount
3,200
655
910
4,765
143
232
384
5,524
829
6,353
Amount
31
44
75
2
23
38
139
21
160
Amount
26
27
54
2
23
38
117
18
134
Amount
58
71
129
4
23
38
23
38
256
38
294