Site Erected Atmospheric Pressure Storage Tank
Site Erected Atmospheric Pressure Storage Tank
EPCMD-2-QM00-JEP-ME-026
00
09.04.2012
PPP
SNS
Rev
Date
Revision
Prepared
By
Checked By
Approved
By
Reliance
Contents
1.
Purpose ....3
2.
Scope ..3
3.
References ....3
4.
5.
Responsibilities ...4
6.
Methodology ..4
1. Annexure I ...11
2. Annexure II
..16
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 2 of 16
Reliance
1.
Purpose
The purpose of this procedure is to provide uniform approach and step by step
guidelines during fabrication, Erection inspection and final Testing of Storage
Tanks designed as per API 650.
2.
Scope
The scope of this procedure covers identification of material to be used for the
construction of storage tanks, inspection and testing procedures to be followed
during fabrication, erection and Testing of Floating Roof, Cone roof storage
tanks. This document is applicable to all personnel of Reliance involved in the
construction inspection of storage tanks designed as per API 650.
3.
4.
Reference
ASME Sec. VIII Div. I
ASME Sec. V
API 650
API 620
SMPV
EPCMD-2-QM00-JEP-ME-010-
EPCMD-2-QM00-ITP-ME-050-
FOR
MT
PMI
PSI
PT
PWHT
QMD
RT
Radiographic testing.
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 3 of 16
Reliance
5.
6.
UT
Ultrasonic Testing.
VBT
WPS
Responsibilities
Methodology
The following inspection procedure shall be adopted during fabrication and
erection of storage tanks designed as per API 650, in addition to stage
inspection activities specified in relevant Inspection and Test plan.
6.1
Tank Foundation
Before laying of the plates on the tank foundation, Reliance engineer shall
review and ensure the availability of the following documents.
And Mechanical contractor along with Reliance engineer shall carry out
surveillance of tank pad / foundation for variation of foundation level. Incase if
any variation is observed clearance for of tank bottom plate erection shall not
be given till the rectification work is completed.
6.2
Material Identification
Wherever the material used in tank fabrication is in the scope of the contractor,
the same shall be identified by review of mill TCs followed by mill identification
marks on the plates (as applicable) by Reliance engineer. In case of client
supplied material, the contractor shall identify the material by mill marks and
maintain the records.
6.3
6.3.1
Plate materials used for shell and tank bottom shall be either grit or sand
blasted to achieve required surface cleaning. Priming of the surface cleaned
material shall be carried out with in 4 hrs (provided Relative humidity (RH) shall
be with in 85% or as recommended by the manufacturer). Inspection shall be
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 4 of 16
Reliance
carried out as per relevant inspection and test plan number EPCMD-2-QM00ITP-ME-024. In addition to this the following tests are to be conducted as per
the requirement.
6.3.2
Allow the surface to dry and then proceed next coats of paint as per
specification
6.4
Erection of Tank
6.4.1
Stitch welding of backing strip with under side of annular plate (as shown
in the drawing).
Visual Inspection of all bottom / annular plate welds shall be carried out
as per clause 8.5 of API 650.
Vacuum testing or any other testing as specified in clause 7.3.3 of API 650
of completed annular joints shall be carried out. (In addition of vacuum
DPT can be carried out in shell resting portion of annular joint).
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 5 of 16
Reliance
6.4.2
Lap welded joints of all bottom, sketch and sketch to annular joints shall
be lapped at least five times the nominal thickness of the thinner plate
joined (as per clause 5.1.3.5 of API 650) or as specified in the drawing.
All connected fillet welds shall be done with minimum two runs.
All bottom plate fillet weld joints shall be vacuum tested at specified
pressure (vacuum).
Weld map shall be prepared for tank bottom and leaks if any observed
during vacuum test shall be repaired by approved repair procedure and re
tested to ensure its soundness.
Shell
All plates used for shell shall be squared and beveled before erecting at site.
Fabrication contractor shall nominate a person responsible for all fabrication
inspection, verification of correctness of the job and recording. RELIANCE
engineer responsible for fabrication inspection shall conduct surveillance audit
to ensure quality of the fabricated job. During each course of shell erection,
the respective discipline engineer shall verify the following activities.
In addition to shell joint fit ups, individual joint plumb, roundness of shell,
shell inner diameter shall be measured by the discipline engineer.
Peaking, banding of all shell weld joints shall be measured. Wherever any
divination is observed, the same shall be repaired and re-inspected for its
acceptance by RELIANCE engineer.
Wherever buckling in the shell plate is observed, mark that area and check
the plate with radius (peaking), banding gauges. If the measured values are
out of the specified limits then that plate / buckled portion (as applicable)
shall be replaced with newly rolled plate.
Clearance shall not be given for further erection of subsequent shell course
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 6 of 16
Reliance
until unless the preceding course is inspected and cleared in all respects.
RELIANCE discipline engineer shall verify the orientation and elevation of all
shell nozzles and wind girders. Soundness of the nozzle welds shall be
ensured by any other approved NDT method and leak proof ness of nozzle
pads ensured by pneumatic test.
A detailed weld map shall be prepared for tank and spot radiography of shell
joints are to be transferred on the weld map. Penalty shall be imposed on
repair of each spot radiography as per code requirement.
The soundness of the initial weld pass of shell to bottom, shell inside weld
shall be ensured with oil chalk penetration test or any other approved
method as specified in clause 7.2.4.1 of API 650 and other side final weld
with DPT.
In order to avoid cracks in butt weld joints of curb angle, first welded all
butt joints of curb angle from over head position (O/H) and then back-chip
to sound weld from down hand (D/H) position and carried out welding.
Gauge well / Still well pipes verticality shall be measured and ensure that
values are with in the acceptable limit. The pipe weld bead shall have
smooth profile and drilled holes are free of burs. Pipe external surface shall
be free of any cleats and tacks.
In order to avoid spark between deck sleeve and Gauge well / Still well pipe
assembly (in case of Floating roof tanks), spark arrest plates shall be
provided (as per the requirement of design / drawing), between the deck
sleeve and Gauge well assembly to avoid steel to steel direct contact and
act as spark proof.
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 7 of 16
Reliance
6.4.3
The above points shall be taken care during fabrication and erection of tank
shell. Also points (before Hydro test) mentioned in check list enclosed as
annexure I shall be completed before releasing the tank for Hydro test.
Deck
Deck plates shall be laid on stage with required slope (as per drawing). During
deck erection QMD engineer shall ensure the following points.
All deck seams lap length shall meet the requirement of approved drawing.
All deck seams (only bottom deck seams incase of double deck) shall be
vacuum tested and rim joints, bulk head joints shall be penetration tested
to ensure the soundness of the welds.
Incase of double deck, clearance for erection of top deck plates shall be
given after ensuring that the bottom deck plates, structures and all
connected welds are free of any defects or damages.
A seal run between deck plate and sleeve / nozzle (down hand side of
bottom deck) shall be done for all deck (only bottom deck incase of double
deck) openings or welding shall be carried our as per weld detailed drawing.
Random inspection shall be carried out before Reinforcement (RF) Pad fit
up.
The soundness of root welding of all bottom deck openings shall be ensured
by conducting penetration test. Leaks if any found shall be repaired and retested.
Visual inspection of all deck seams including O/H (over head) welding of
sleeve / nozzles with deck plate shall be carried out as per clause 8.5 of API
650.
Arc strikes on deck (especially bottom deck) and sleeve / nozzle neck shall
be avoided. In case if any arc strikes are observed, it shall be grounded (do
fill up if required) and close visual inspection is to be carried out.
Wherever arc strikes are observed on deck, sleeve pipe / nozzle neck, the
same shall be removed by grinding and do fill up if required. The soundness
of the affected area shall be tested by penetration test or PT or vacuum test
as applicable.
All T joints of deck under side seams (only bottom deck incase of double
deck) and all deck seams of outer periphery shall be welded as per weld
detail drawing including the stitch welding of remaining length of deck under
side seams.
In order to avoid the arc strikes on deck (i.e. inside the pontoon boxes)
during welding, contractor shall ensure that only fully insulated cables and
capped / covered electrode holders are used. QMD will monitor it by regular
surveillance.
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 8 of 16
Reliance
6.4.4
All swivel joints used for tank roof drain system shall be tested for leak
proof ness by internal pressure before installing into the system.
Roof drain system shall be tested before and after tank hydro test at
specified test pressure by contractor to ensure leak proof ness of the
system.
Cone Roof
RELIANCE engineer shall clear the self-supported cone roof structure before
erecting, if being assembled on the ground.
6.4.5
All structural members used shall be free of any type of visual defects.
All connected bolting holes shall be made elliptical as shown in the drawing.
Bolt holes shall be properly drilled and gas cutting is not permitted.
In order to avoid leakage of all nozzle connections with tank roof plate
during roof test, care shall be exercised during fit-up of nozzle, a seal weld
is to be done between nozzle neck to roof plate before fit-up of
reinforcement pad plate (wherever applicable).
Wherever applicable roof test of any cone roof tank shall be carried out
before application of roof paint, i.e. all weld joints shall be free from grease,
paint etc.
with
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 9 of 16
Reliance
client / client authorized representative is completed and signed on the
respective format.
6.4.6
Hydro test shall be carried as per approved hydro test procedure or EPCMD2-QM00-JEP-ME-010.
Water used for hydro test shall have salt content with in the acceptable
limit.
All weld joints of tank including bottom deck (deck in contact with water)
shall be witnessed for leakage.
Leaks if any observed during hydro test shall be repaired with approved
procedure or as per clause 8.1.7 of API 650. The repair of the tank shall be
carried out as per clause 7.4.4 of API 650.
After Tank hydro test, roof drain system shall be re-tested at the same
pressure as was tested to confirm the leak proof-ness.
In case of cone roof tanks, wherever applicable roof test (pneumatic test
at recommended test pressure) shall be carried out on all weld joints
connecting roof plates and roof to shell (as applicable). Weld joints covering
by this test method shall be free from paint, grease etc.
Full tank vacuum test shall be carried if the tank is designed for partial
vacuum. Contractor shall prepare separate procedure with necessary safety
precautions before proceeding for the test.
Quality Records
Quality Records for tank before and after hydro test shall be compiled as per
the requirement of relevant EPCMD-2-QM00-ITP-ME-050. Tank system dossier
(for civil and mechanical activities) shall be compiled as per Annexure-II of this
document.
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 10 of 16
Reliance
Annexure-I
Check List For Tank Final Clearance
Tank Number:
Date:
Area:
Unit Number:
I.
Verification and
Certification
Contractor Client
1. Tank bottom
a) Material identification reports of tank bottom plates
b) Under side blasting and painting reports for annular,
sketch and bottom plates, as applicable
c) Visual inspection of all tank bottom weld joints
d) NDE of tank bottom welding, incl. off annular plate
(PT, RT and VBT)
e) Water fill up test for bottom sump to be conducted
before installation.
f) Removal of deck staging angles.
g) Visual and NDE clearance of tank bottom plate as
applicable.
h) Fixing of anode cleats and its clearance wherever
applicable.
i) DP test for the tank bottom sump attachment weld.
j) Checking the gap between the sump and drain pipe
prior to and after hydro to ensure settlement within
limits.
k) Tank bottom and sump cleaning.
l) Visual inspection of all deck leg support bearing plate
welds.
m) Clearance to ensure that all legs are to bearing
plates free without any tacks
n) Weld map with welder Id, RT and VBT details
2. Tank shell
a) Material identification reports of tank shell plates
b) Weld visual of all circumferential and vertical seam
welds
c) Banding and peaking reports of all the courses
d) RT clearance for all circumferential and long seam
welds
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 11 of 16
Reliance
Verification and
Certification
Contractor
Client
Page 12 of 16
Reliance
Verification and
Certification
Contractor
Client
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 13 of 16
Reliance
Verification and
Certification
Contractor
Client
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 14 of 16
Reliance
II.
1.
Verification and
Certification
Contractor Client
Activity
Verification and
Certification
Contractor Client
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 15 of 16
Reliance
Annexure-II
Records Compilation
Activity
contractor
Client
EPCMD-2-QM00-JEP-ME-026, Rev: 00
Confidential Reliance. All rights reserved
Page 16 of 16