Aggregate Planning: Aggregate Planning Is The Determination of The Quantity and Timing of Production For The
Aggregate Planning: Aggregate Planning Is The Determination of The Quantity and Timing of Production For The
CHAPTER
Aggregate
Planning
DISCUSSION QUESTIONS
1.
(a)
(b)
(c)
2.
(a)
(b)
Aggregate planning is the determination of the quantity and timing of production for the
immediate future (often from 3 to 18 months ahead)
Demand optionsan attempt is made to manipulate demand
n
Influence demand: employ advertising, promotion, personal selling, price cuts, etc., to
either change the magnitude of demand, or shift it in time
n
Back order during high demand periods
n
Counterseasonal product mixing: produce lawn mowers and snow blowers
Capacity optionsattempt to absorb fluctuations in demand
n
Change inventory levels
n
Vary size of workforce by hiring and firing
n
Vary production rate through use of overtime or idle time
n
Subcontract
n
Use part-time workers
A pure strategy manipulates only a single variableinventory, production rates, manpower
levels, capacity, etc.whereas a mixed strategy manipulates two or more variables
simultaneously.
Four not mixed strategies are:
n
Change inventory levels
n
Vary workforce size
n
Vary production rate by use of overtime and idle time
n
Subcontract
Other pure strategies were described in the answer to question 1, above.
3.
Mathematical models are not more widely used because they tend to be relatively complex and are
seldom understood by those persons performing the aggregate planning activities.
4.
The advantage of varying the size of the workforce as required to adjust production capacity is that
one has a fundamental ability to change production capacity in relatively small and precise
increments. The disadvantages are that a ready supply of skilled labor is not always available,
newly hired personnel must be trained, and firings or layoffs undermine the morale of all employees
and can lead to a widespread decrease in overall productivity.
5.
Aggregate planning is usually considered to encompass several production cycles. Some products,
large ships or nuclear reactors, for example, have very long production cycles (years or tens of
years). Other products, such as lawn mowers or jewelry have production cycles measured in days.
6.
The Master Production Schedule (MPS) is produced by disaggregating the aggregate plan.
227
7.
8.
Aggregate planning in services differs from aggregate planning in manufacturing in the following
ways:
n
Most services are perishable and cannot be inventoried. It is virtually impossible to produce
the service early in anticipation of higher demand at a later time.
n
Demand for services is often difficult to predict. Demand variations are typically more severe
and more frequent.
n
Services are more customized than manufactured goods and can be offered in many different
forms. This variability makes it difficult to allocate capacity. Units of capacity may also be
hard to define.
n
Because most services cannot be transported, service capacity must be available at the
appropriate place as well as at the appropriate time.
n
Service capacity is generally altered by changes in labor, rather than by equipment or space,
and labor is a highly flexible resource.
9.
Graphical aggregate planning methods, while based on trial and error, are useful because they
require only limited computations and usually lead to optimal solutions.
10.
Limitations of the transportation method include that it does not work well when one attempts to
include the effect of hiring and layoffs in the model.
11.
12.
Varying inventory levels and back ordering have this disadvantage in common: customers may go
elsewhere.
13.
Yield management adds another set of decisions to the aggregate plan, to capacity planning, and to
scheduling. However, of these yield management issues, the aggregate plan may be the one least
affected. Auto rental companies, airlines, and hotels now all vary inventory (autos, seats, rooms)
and prices to reflect ways to maximize their yield (profit). Lead time (vacationers price shop more
and are willing to do so earlier) days of the week, seasons, holidays, and conventions all impact the
yield. In many cases, the aggregate supply is the least affected.
228
END-OF-CHAPTER PROBLEMS
13.1 Month
Jan
Feb
Mar
Apr
May
Jun
Expected Demand
900
700
800
1,200
1,500
1,100
6,200
Production Days
22
18
21
21
22
20
124
6,200
50 units/day
124
. hours/unit
Constant workforce of 6 persons; overtime to meet extra demand: Labor 16
Average daily production requirement
hours day
8
6
30 units/day
hours unit
16
.
Overtime
240
160
170
570
840
500
2,480
Cost analysis:
Regular Production:
CR 6 persons $40 124 $29,760
Overtime:
CO 2,480 units 0.2 man-days/unit $56 /man-day = $27,776
Total cost:
CT 29,760 27,776 $57,536
229
. hours/unit
13.2 Constant workforce of 7 persons; subcontract to meet extra demand: Labor 16
Production rate/day = persons
Month
Jan
Feb
Mar
Apr
May
Jun
hours day
8
7
35 units/day
hours unit
16
.
Subcontract
130
70
65
465
730
400
1,860
Cost analysis:
Regular production:
CR 7 persons $40 124 $34,720
Subcontracting:
CS 1860
,
units $10 $18,600
Total cost:
CT 34,720 18,600 $53,320
Comparing:
Carrying cost
Reg. time
Overtime
Subcont.
Hire
Layoff
Total cost
Plan 1
9,250
49,600
0
0
0
0
58,850
Plan 2
0
37,696
0
14,880
0
0
52,576
Plan 3
0
49,600
0
0
8,000
9,000
66,600
Plan 4
400
39,680
13,888
0
0
0
53,968
Plan 5
0
29,760
27,776
0
0
0
57,536
Plan 6
0
34,720
0
18,600
0
0
53,320
Based simply upon total cost, Plan 2 is preferable. From a practical viewpoint, Plans 2, 4, and 6
will likely have equivalent costs. Practical implementation of Plan 2 may, for example, require the
employment of eight full-time employees, rather than seven full-time and one part-time employee.
When several plans have roughly equivalent costs, other parameters gain importancesuch as the
amount of control one would have over production and excess wear on equipment and personnel.
Plan 3 should be avoided.
13.3
Period
1
2
3
4
5
6
7
8
Expected Demand
1,400
1,600
1,800
1,800
2,200
2,200
1,800
1,400
14,200
Plan A
Production
(Result of
Previous
230
Hire
Fire
Extra
Period Demand
1
1,200*
2
1,600
3
1,800
4
1,800
5
2,200
6
2,200
7
1,800
8
1,400
*
Month)
1,600
1,200
1,600
1,800
1,800
2,200
2,200
1,800
(Units) (Units)
400
Cost
30,000 (cost to go from 1,600 in Jan. to 1,200 in Feb.)
400
20,000
400
30,000
400
30,000
Total Extra Cost: $140,000
400
200
Note: Period 1 demand was given as 1,400 units. Because we have 200 units in beginning inventory, the demand to be met by
production is only 1,200 units.
13.4
Period
0
1
2
3
4
5
6
7
8
Demand
Production
1,400
1,600
1,800
1,800
2,200
2,200
1,800
1,400
1,400
1,400
1,400
1,400
1,400
1,400
1,400
1,400
13.5 (a)
Period
0
1
2
3
4
5
6
7
8
Demand
Production
1,400
1,600
1,800
1,800
2,200
2,200
1,800
1,400
1,775
1,775
1,775
1,775
1,775
1,775
1,775
1,775
Plan B
Ending Inv.
200
200
0
0
0
0
0
0
0
Plan C
Ending Inv.
200
575
750
725
700
275
0
0
375
Subcon (Units)
Extra Cost
400
400
800
800
400
4,000
30,000
30,000
60,000
60,000
30,000
Stockouts (Units)
150
25
Total Extra Cost:
$214,000
Extra Cost
11,500
15,000
14,500
14,000
5,500
15,000
2,500
7,500
$85,500
All other things being equal, it would appear that Plan C, with a cost of $85,000, should be
recommended over Plan A (cost = $130,000) or Plan B (cost = $214,000).
231
(b)
Graph of Plan C
2,200
2,100
2,000
1,900
1,800
1,775
1,700
1,600
1,500
1,400
0
Jul Aug
Period
0
1
2
3
4
5
6
7
8
Demand
Reg.
(Units)
1,400
1,600
1,800
1,800
2,200
2,200
1,800
1,400
1,600
1,600
1,600
1,600
1,600
1,600
1,600
1,600
Plan D
O.T.
End Inv.
(Units) (Units)
200
400
400
200
320
320
200
200
Stockouts
(Units)
Extra
Cost
8,000
8,000
4,000
0
280
44,000
280
44,000
10,000
4,000
Total Extra Cost: $122,000
Noting that the additional cost of a stockout is much greater than the sum of the additional costs for
overtime plus inventory storage, one might look ahead and schedule overtime where possible.
The resulting aggregate plan would be:
Reg.
Period Demand (Units)
0
1
1,400
1,600
2
1,600
1,600
3
1,800
1,600
4
1,800
1,600
5
2,200
1,600
6
2,200
1,600
7
1,800
1,600
8
1,400
1,600
(b)
232
O.T.
End Inv.
(Units) (Units)
200
400
400
200
400
200
400
320
120
320
200
200
Stockouts
(Units)
Extra
Cost
8,000
8,000
18,000
18,000
18,400
160
32,000
10,000
4,000
Total Extra Cost: $116,400
Plan E
Period
0
1
2
3
4
5
6
7
8
Demand
1,400
1,600
1,800
1,800
2,200
2,200
1,800
1,400
1,600
1,600
1,600
1,600
1,600
1,600
1,600
1,600
Ending Inv.
200
400
400
200
Extra Cost
8,000
8,000
4,000
0
45,000
45,000
15,000
4,000
$129,000
600
600
200
200
Total Extra Cost:
All other things being equal, it would appear that Plan D, with a cost of $122,000, should be
recommended over Plan E (cost = $129,000).
Note that of all the plans discussed, it would appear that Plan C, with a cost of $85,500,
should be recommended over all others.
13.7
Period
Jun
Jul
Aug
Sep
Oct
Nov
Dec
(b)
Beg.
Inventory
Over
(Short)
150
150
10
10
20
0
0
Unit
Demand
400
500
550
700
800
700
Units
Required
Hours
Required
at 4
each
Personnel
Required
at
20 days
at 8 hrs
250
510
540
680
800
700
1,000
2,040
2,160
2,720
3,200
2,800
6.25
12.75
13.50
17.00
20.00
17.50
Personnel
on
staff
8
6
13
14
17
20
17
Units
Produced
Production
Over
(Short)
240
520
560
680
800
680
10
10
20
0
0
20
Hire
$40
7
1
3
3
Fire
$80
2
3
Total Extra Cost:
Costs
Hire: 40
Layoff: 80
$160
$280
$40
$120
$120
$240
$960
Note: In computing cost, we assumed that, if the capacity of a fraction of a worker was
needed (was excess), one worker was hired (fired).
Aggregate plan, overtime only:
Period
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Demand
Production
(Regular)
Production
(Overtime)
400
500
550
700
800
700
320
320
320
320
320
320
110
230
380
480
380
Ending
Inv.
150
70
Extra
Cost
560
2,640
5,520
9,120
11,520
9,120
Total Extra Cost: $38,480
233
Period
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Unit
Demand
400
500
550
700
800
700
Beg.
Inventory
Over
(Short)
150
150
70
90
60
80
0
Units
Required
Hours
Required
at 4
each
Personnel
Required
at
20 days
at 8 hrs
250
430
460
640
720
700
1,000
1,720
1,840
2,560
2,880
2,800
8.00
13.00
13.00
18.00
18.00
18.00
Personnel
on
staff
8
8
13
13
18
18
18
Units
Produced
Production
Over
(Short)
320
520
520
720
720
720
70
90
60
80
0
20
Hire
$40
Fire
$80
Costs
Hire: 40
Layoff: 80
0
$560
5
$920
0
$480
5
$840
0
0
0
$160
Total Extra Cost: $2,960
Students should be encouraged to consider the long-range implications of any aggregate planning
strategy involving planned hiring/firing with respect to the development of an appropriate labor
pool, etc.
13.9
Month
Apr
May
Jun
Jul
Aug
Sep
(a)
Expected Demand
1,000
1,200
1,400
1,800
1,800
1,600
234
Demand
1,000
1,200
1,400
1,800
1,800
1,600
Plan A
Production Ending Inv. Subcont. (Units)
1,000
0
1,000
0
200
1,000
0
400
1,000
0
800
1,000
0
800
1,000
0
600
Total Extra Cost:
Extra Cost
0
12,000
24,000
48,000
48,000
36,000
$168000
(b)
Demand
1,000
1,200
1,400
1,800
1,800
1,600
Plan B
Production (Existing) Hire (Units)
1,300
1,000
200
1,200
200
1,400
400
1,800
1,800
13.10 (a)
Period
Mar
Apr
May
Jun
Jul
Aug
Sep
(b)
Demand
Production
(Units)
1,000
1,200
1,400
1,800
1,800
1,600
1,300
1,300
1,300
1,300
1,300
1,300
Plan C
Subcont.
(Units)
400
300
Fire (Units)
300
Extra Cost
18,000
6,000
6,000
12,000
200
12,000
Total Extra Cost: $54,000
Ending Inv.
300
600
700
600
100
0
0
Total Extra Cost:
Extra Cost
15,000
17,500
15,000
2,500
24,000
18,000
$92,000
Month
Apr
May
Jun
Jul
Aug
Sep
Demand
Reg.
(Units)
1,000
1,200
1,400
1,800
1,800
1,600
1,300
1,300
1,300
1,300
1,300
1,300
Plan D
O.T.
(Units) End Inv.
100
260
260
260
180
180
180
0
0
0
Subcont.
(Units) Idle Time
Extra
Cost
120
100
11,700
10,500
8,500
60
14,000
240
24,800
40
12,800
Total Extra Cost: $82,300
If our object in comparing the plans is to identify the elements of an optimal plan, we must
consider the following:
Plans A, B, and D begin with zero initial inventory, Plan C begins with an initial
inventory of 300 units. It is therefore inappropriate to compare directly the results of Plan C
with those of Plans A, B, and D.
In addition, we can assume that the warehouse constraint introduced in Plan D would
have affected the costs of Plan A and Plan C had it been in effect in those plans.
What one can say is that the aggregate planning options should be utilized as available,
in the following order:
n
Carryover of inventory: $25/unit
n
Overtime: $40/unit
n
Hiring: $30/unit
n
Firing: $60/unit
n
Subcontracting: $60/unit
n
Stockout: $100/unit
235
13.11 The intent of the authors is that this problem be solved using the transportation problem format.
Assuming that back orders are not permitted, the solution is:
To Demand
From
Month 1
Reg. Time
5
Month 1
1,000
Overtime
7
Month 1
200
Subcont.
8
Month 1
50
Reg. Time
Month 2
Overtime
Month 2
Subcont.
Month 2
Reg. Time
Month 3
Overtime
Month 3
Subcont.
Month 3
Demand
1,250
Demand
Month 2
6
50
Excess
0
10
5
1,000
7
200
8
50
1,250
1,000
200
Demand
Month 3
7
1,250
100
100
0
0
100
300
Supply
1,000
200
150
1,000
200
150
1,000
200
150
Reg. Time
Month 2
Overtime
Month 2
Subcont.
Month 2
Reg. Time
Month 3
Overtime
Month 3
Subcont.
Month 3
Demand
40
Demand
Month 2
4
Demand
Month 3
8
Excess
0
104
10
154
108
158
204
208
100
35
150
5
200
104
154
50
204
100
30
150
10
200
40
10
5
7
5
0
0
0
5
32
Supply
20
30
10
5
35
12
5
30
10
5
236
13.13 Assuming that back orders are not permitted, the solution is:
To Demand
From
Month 1
Initial
0
Inventory
500
Reg. Time
70
Month 1
1,100
Overtime
110
Month 1
400
Subcont.
120
Month 1
Reg. Time
Month 2
Overtime
Month 2
Subcont.
Month 2
Reg. Time
Month 3
Overtime
Month 3
Subcont.
Month 3
Reg. Time
Month 4
Overtime
Month 4
Subcont.
Month 4
Demand
2,000
Demand
Month 2
4
Demand
Month 3
8
Demand
Month 4
12
Excess
0
74
400
114
78
82
118
122
124
128
132
70
1,600
110
400
120
100
74
78
114
118
124
128
70
750
110
200
120
550
74
114
124
2,500
1,500
70
1,600
110
400
120
100
2,100
600
500
50
0
0
500
1,150
Supply
500
1,500
400
600
1,600
400
600
750
200
600
1,600
400
600
237
Reg. Time
Month 2
Overtime
Month 2
Subcont.
Month 2
Reg. Time
Month 3
Overtime
Month 3
Subcont.
Month 3
Reg. Time
Month 4
Overtime
Month 4
Subcont.
Month 4
Demand
2,000
Demand
Month 2
4
Demand
Month 3
8
Demand
Month 4
12
Excess
0
74
78
82
114
400
124
118
122
128
132
74
78
114
118
124
128
70
750
110
200
120
550
74
114
124
70
1,600
110
400
120
100
2,500
1,500
70
1,600
110
400
120
100
2,100
600
500
50
0
0
0
500
1,150
Supply
500
1,500
400
600
1,600
400
600
750
200
600
1,600
400
600
238
13.14 Assuming that back orders are not permitted, the solution is:
To Demand Demand Demand Demand
From
Month 1 Month 2 Month 3 Month 4
Reg. Time
985
1,085
1,185
1,285
Month 1
235
Overtime
1,310
1,410
1,510
1,610
Month 1
20
Subcont.
1,500
1,600
1,700
1,800
Month 1
Reg. Time
985
1,085
1,185
Month 2
255
Overtime
1,310
1,410
1,510
Month 2
24
Subcont.
1,500
1,600
1,700
Month 2
15
Reg. Time
985
1,085
Month 3
290
Overtime
1,310
1,410
Month 3
26
Subcont.
1,500
1,600
Month 3
5
Reg. Time
985
Month 4
300
Overtime
1,310
Month 4
1
Subcont.
1,500
Month 4
Demand
255
294
321
301
Excess
0
Supply
235
0
12
20
12
255
24
15
290
0
10
26
15
0
23
17
62
300
24
17
Reg. Time
May
Overtime
May
Reg. Time
June
Overtime
June
Demand
3,000
Demand
May
4
Demand
June
8
Excess
0
104
108
144
148
100
2,750
140
104
30
144
2,750
100
2,760
140
160
2,950
285
0
315
0
0
145
745
Supply
50
2,880
355
2,780
315
2,760
305
239
13.16 Assuming that back orders are not permitted, the solution is:
To
From
Reg. Time
Jan
Overtime
Jan
Reg. Time
Feb
Overtime
Feb
Reg. Time
Mar
Overtime
Mar
Reg. Time
Apr
Overtime
Apr
Reg. Time
May
Overtime
May
Reg. Time
Jun
Overtime
Jun
Subcont.
Demand
Jan
1
12
700
16
300
Feb
2
13
100
17
Mar
3
14
Apr
4
15
May
5
16
Jun
6
17
Excess
0
18
19
20
21
13
14
15
16
17
18
19
20
12
800
16
300
13
14
15
17
18
19
12
800
16
300
13
14
17
18
12
800
16
300
12
11
1,100
16
300
18.5
18.5
1,000
1,200
18.5
150
1,250
18.5
350
1,450
18.5
1,400
17
11
1,100
16
300
18.5
1,400
100
0
0
100
0
0
Supply
800
300
800
300
800
300
800
300
1,100
400
1,100
400
500
200
240
13.17 Even though back orders are permitted, note they are not used. One of the multiple optimal
solutions is:
To Demand Demand Demand Demand
From
1
2
3
4
Initial
0
200
400
600
Inventory
4
Reg. Time
2,000
2,200
2,400
2,600
1
25
Overtime
2,475
2,675
2,875
3,075
1
3
2
Subcont.
3,200
3,400
3,600
3,800
1
Reg. Time
2,600
2,000
2,200
2,400
2
28
Overtime
3,075
2,475
2,675
2,875
2
2
2
Subcont.
3,800
3,200
3,400
3,600
2
Reg. Time
3,200
2,600
2,000
2,200
3
30
Overtime
3,675
3,075
2,475
2,675
3
8
Subcont.
4,400
3,800
3,200
3,400
3
1
Reg. Time
3,800
3,200
2,600
2,000
4
29
Overtime
4,275
3,675
3,075
2,475
4
6
Subcont.
5,000
4,400
3,800
3,200
4
4
Demand
32
32
40
40
End
Inv
800
Excess
0
2,800
3,275
4,000
2,600
3,075
3,800
2,400
2,875
3,600
2,200
2,675
3,400
3
3
Supply
4
25
5
6
28
4
6
30
8
6
29
6
7
17
241
13.18 Assuming that back orders are not permitted one solution, of multiple optional solutions, is:
To
From
Subcont.
Demand
1
135
Demand
2
135
Demand
3
135
Demand
4
135
Reg. Time
1
Overtime
1
Reg. Time
2
Overtime
2
Reg. Time
3
Overtime
3
Reg. Time
4
Overtime
4
Reg. Time
5
Overtime
4
Demand
100
150
125
103
106
109
Demand
5
135
50
112
128
131
134
137
140
100
150
125
10
103
106
109
112
128
131
10
103
20
128
10
100
150
125
10
134
137
106
109
131
134
103
106
128
131
100
150
125
10
210
103
128
100
130
125
150
160
130
200
End
(Dummy)
Inv
Excess
135
0
20
30
115
0
20
20
Supply
100
150
20
150
20
150
10
150
10
150
10
50
Type
242
Summary Table
Units
$0
$0
Incres
Decres
0
20
35
10
0
0
10
0
75
0
0
0
0
0
10
0
10
20
0
Cost
Regtm
Ovrtm
Subcon
Holdng
Shortg
Incres
Decres
(b)
Type
Regtm
Ovrtm
Subcon
Holdng
Shortg
Incres
Decres
(c)
2,260
$2,260,000
189
$245,700
57
$85,500
0
$0
0
$0
75
$0
20
$0
Total cost = $2,591,200
$0
$0
Incres
Decres
0
20
0
0
0
0
0
0
20
0
0
0
0
0
0
0
0
0
0
0
$0
$0
Incres
Decres
0
20
35
10
0
0
10
0
75
0
0
0
0
0
0
10
0
10
20
0
Summary Table
Units
Cost
2,180
$2,180,000
187
$243,100
90
$135,000
0
$0
49
$0
20
$0
0
$0
Total cost = $2,558,100
243
Holdng
Shortg
Incres
Decres
0
$0
0
$0
75
$0
20
$0
Total cost = $2,610,100
$0
$0
$0
Shortg
Incres
Decres
0
0
0
0
0
0
0
0
0
0
0
20
35
10
0
0
10
0
75
0
0
0
0
0
0
10
0
10
20
0
CASE STUDIES
SOUTHWESTERN UNIVERSITY: F
This case provides the student with quantitative information to develop an aggregate capacity plan, but, as
often occurs in services, demand is so variable that there are not many viable staffing alternatives.
Students may also be frustrated by the lack of detailed data on the nature of service demand and the
resources required to meet demand. Even with these drawbacks, the student should be able to gain insight
into the aggregate planning problem and help the chief justify his personnel requests. Students may want
to talk with the police department at their own university to see how it handles similar problems.
244
1.
Which variations in demand for police services should be considered in an aggregate plan for
resources? Which variations can be handled with short-term scheduling adjustments?
An aggregate plan should set full-time staffing levels; estimate part-time and overtime needs for
budget purposes; determine times of the year for training, vacations, and other nonessential duties;
and establish an agreed-upon level of police services for the university community (i.e., What role
is the police officer to play? What response time to calls for service is appropriate? What services
should be provided?). Short-term scheduling adjustments can be made for different days of the
week, shifts, and special events.
2.
In what terms would you define capacity for the department? What additional information do you
need to determine capacity requirements?
Capacity would probably be expressed in terms of man-hours available. To determine what capacity
is required, we need information on the numbers of calls for service, types of calls, how long it
takes to service different types of calls, patrol expectations, and other duties such as escort services.
3.
Evaluate the current staffing plan. What does it cost? Are 26 officers sufficient to handle the
normal workload?
Cost of current staffing plan:
Salaries:
= $728,000
26 officers $28,000 per year
Overtime:
= $43,200
2,400 hours per year $18 per hour
Subcontractors:
= $32,400
40 officers 9 hours $18 per hour 5 football games per year
25 part-timers 9 hours $9 per hour 5 football games per year = $10,125
$813,725
Normal workload during fall and spring semesters:
1st shift
2nd shift
3rd shift
Weekday
5
5
6
Weekend
4
6
8
7-day Average
4.7
5.3
6.6
16.6
Weekday
3
3
3
Weekend
2
3
4
7-day Average
2.7
3.0
3.3
9.0
What would be the additional cost of the chiefs proposal? How would you suggest that the chief
justify his request?
245
How much does it currently cost the university to provide police services for football games? What
would be the pros and cons of subcontracting this work completely to outside law enforcement
agencies?
Cost of police officers for football games:
18 officers work 8 hours overtime @ $18.00/hr
8 officers work 16 hours overtime @ $18.00/hr
40 outside officers work 9 hours @ $18.00/hr
25 part-timers work 9 hours @ $9/hr
5 football games per year
Cost 18 8 18 8 16 18 40 9 18 25 9 9 5
2.592 1,024 6,480 2,025 5
12,121 5 $60,605
Subcontracting security for football games would relieve the weary campus police and allow them
to perform their normal duties more effectively. However, football security is highly visible, and the
absence of campus police may hurt their image in the university community and rob them of the
opportunity to work closely with law enforcement personnel from agencies in a noncrisis situation.
It may also be difficult for the university to maintain the same level of control over subcontracted
work, especially in terms of discretionary treatment of students and alumni.
In terms of cost, it is doubtful that the work could be subcontracted as cheaply as it is currently
performed because the cost of supervisory and managerial personnel would have to be included in
the package (and currently no supervisors or managers are paid overtime for their work).
6.
Can you propose any other alternatives? What suggestions do you have for duties of police officers
in nonpeak hours?
Many of the innovative suggestions for handling the variability in demand for services involve
using part-time workers. Police officers require extensive training, so this alternative usually means
hiring off-duty police officers from other agencies. Under these circumstances, the hours that offduty officers can moonlight are limited, and, except for football Saturdays, may be hard to schedule
(i.e., all part-time agencies are busy at the same time). Another way to handle part-time or seasonal
requirements for work is to find complementary work for the full-time employees that follows a
different demand pattern. In this case, the nonpeak period for police services falls during the
summer months. What other university services increase during those months? Perhaps the idled
officers could be used as campus guides during summer orientation, as aides for the summer camps
and other summer programs held on campus, or as part of the grounds crew. At least one small
private college utilizes its police officers in this expanded fashion. It certainly increases the officers
involvement with the university community.
ANDREW-CARTER, INC.
This case presents some of the basic concepts of aggregate planning by the transportation method. The
case involves solving a rather complex set of transportation problems. Four different configurations of
246
operating plants have to be tested. The solutions, although requiring relatively few iterations to optimality,
involve degeneracy if solved manually.
The costs are:
Configuration
All plants operating
1 & 2 operating, 3 closed
1 & 3 operating, 2 closed
2 & 3 operating, 1 closed
Total Cost
$220,730
222,430
217,430
221,360
The lowest weekly total cost, operating plants 1 and 3 with 2 closed, is $217,430. This is $3,300 per
week ($171,600 per year) or 1.5% less than the next most economical solution, operating all 3 plants.
Closing a plant without expanding capacity of the remaining plants means unemployment. The optimum
solution, using plants 1 and 3, indicates overtime production of 4,000 units at 1 and 0 overtime at 3. The
all-plant optima have no use of overtime and include substantial idle regular time capacity: 11,000 units
(55%) in plant 2 and either 5,000 units in 1 (19% of capacity) or 5,000 in 3 (20% of capacity). The idled
capacity versus unemployment question is an interesting, nonquantitative aspect of the case and could lead
to discussion of the forecasts for the housing market and thus the plants product.
The optimum producing and shipping pattern is:
From
Plant 1 (R.T.)
Plant 3 (R.T.)
Plant 3 (O.T.)
To (Amount)
W2 (13,000); W4 (14,000)
W1 (5,000); W3 (11,000); W4 (1,000); W5 (8,000)
W1 (4,000)
CorelPhotoPaint.Image.9
mergeformat
STUDY
\s
\*
INTERNET CASE
CORNWELL GLASS
Entering the data provided into software, then toggling the pure strategies and trying them yields the
following costs.
Plan 1 (smooth production): $849,077
Plan 2 (meet demand exactly): $104,575
Plan 3 (produce 1,900 as base, then use OT and subcontracting): $82,858
At this point, the question is, can we do better with trial and error? A better solution follows.
Aggregate Planning
Time periods 52
Shortages: Back ordersCarry shortages from period to period
1,900
0
0
$0
$8.00
$10
All pds
Schedule
Pd
Demnd Regtm
Ovrtm
Subcon
Regtm
Ovrtm Subcon
Init
73
1,900
0
0
$0.12
Units
Holdng
$20.0
$5.63
$15.7
Shortg
Incres
Decres
247
A15
22
29
M6
13
20
27
J3
10
17
24
J1
8
15
22
29
A5
12
19
26
S2
9
16
23
30
O7
14
21
28
N4
11
18
25
D2
9
16
23
30
J6
13
20
27
F3
10
17
24
M3
10
17
24
31
A7
Tot
1,829
1,900
250
1,820
1,900
250
1,887
1,900
250
1,958
1,900
250
2,011
1,900
250
2,063
1,900
250
2,104
1,900
250
2,161
1,900
250
2,258
1,900
250
2,307
1,900
250
2,389
1,900
250
2,434
1,900
250
2,402
1,900
250
2,385
1,900
250
2,330
1,900
250
2,323
1,900
250
2,317
1,900
250
2,222
1,900
250
2,134
1,900
234
2,065
1,900
165
1,973
1,900
73
1,912
1,900
12
1,854
1,900
0
1,763
1,900
0
1,699
1,900
0
1,620
1,900
0
1,689
1,900
0
1,754
1,900
0
1,800
1,900
207
1,864
1,900
250
1,989
1,900
250
2,098
1,900
250
2,244
1,900
250
2,357
1,900
250
2,368
1,900
250
2,387
1,900
250
2,402
1,900
250
2,418
1,900
250
2,417
1,900
250
2,324
1,900
250
2,204
1,900
250
2,188
1,900
250
2,168
1,900
250
2,086
1,900
186
1,954
1,900
54
1,877
1,900
0
1,822
1,900
0
1,803
1,900
0
1,777
1,900
0
1,799
1,900
0
1,803
1,900
0
1,805
1,900
0
107,544
98,800
8,931
Subtotal Costs
0
0
0
0
0
0
0
0
0
0
0
0
0
0
15
173
167
72
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
427
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
1,900
98,800
250
250
250
250
250
250
250
250
250
250
250
250
250
250
250
250
250
250
234
165
73
12
0
0
0
0
0
0
207
250
250
250
250
250
250
250
250
250
250
250
250
250
250
186
54
0
0
0
0
0
0
0
8,931
71,448
0
0
0
0
0
.0
0
0
0
0
0
0
0
0
15
173
167
72
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
427
4,270
394
724
987
1,179
1,318
1,405
1,451
1,440
1,332
1,175
936
652
400
165
0
0
0
0
0
0
0
0
46
183
384
664
875
1,021
1,328
1,614
1,775
1,827
1,733
1,526
1,308
1,071
819
551
284
110
56
18
0
0
0
23
101
198
321
422
519
614
32,949
3,953.9
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
248