Daily Progress Report
Daily Progress Report
22.10.2016
Date:
Project : Replacement of 69 KV O/H Line in EOA, From Qatif BSP to KFIA.
Contract No. : 4400005462/00
Contractor : Nassir Manae Wabran Co. & Partners
[Section #1] POLE 45 - POLE 52
Pole Number
Activity
45
46
47
48
49
Insulator Assembly
Insulator Hoisting
Wire Pulling
Sagging
Clipping & Clamping
Final checking
50
51
57
58
52
Status
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Prepared By
Prabu Baskaran
QA/QC Electrical Engr.,
Contract No. 4400005462
Replacement of 69KV O/H Line In EOA,
From Qatif BSP to KFIA (Line 1)
Pole Number
52
53
54
55
56
Status
ongoing
Remarkable event :
1. Circuit 1 & 2 ACSR Drake Conductor Pay in only done , Still Sagging is not prepared.
2. Pole No: 58 (Take Off Structure) - 1 No Pole, still not erected due to existing 69KV line clearance.