Daily Progress Report

Scope This standard prescribes minimum mandatory requirements for design and installation of grounding systems and lightning protection systems for Saudi Aramco facilities. This document may not be attached to nor made a part of purchase orders. 2 Conflicts, Deviations and Commentary 2.1 If there are any conflicts between this Standard and associated purchasing, project or engineering documents, this standard shall take precedence. The exception is if an approved Waiver has been included with the purchasing documents. 2.2 Any conflicts between this standard and other applicable Saudi Aramco Engineering Standards (SAESs), Materials System Specifications (SAMSSs), Standard Drawings (SASDs), or industry standards, codes, and forms shall be resolved in writing by the company or buyer representative through the Manager, Consulting Services Department of Saudi Aramco, Dhahran. 2.3 Direct all requests to deviate from this standard in writing to the company or buyer representative, who shall follow internal company procedure SAEP-302 and forward such requests to the Manager, Consulting Services Department of Saudi Aramco, Dhahran. 2.4 The designation “Commentary” is used to label a sub-paragraph that contains comments that are explanatory or advisory. These comments are not mandatory, except to the extent that they explain mandatory requirements contained in this SAES. 3 References The selection of material and equipment, and the design, construction, maintenance, and repair of equipment and facilities covered by this standard shall comply with the latest edition of the references listed below, unless otherwise noted.

Uploaded by

Prabu Baskaran
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
79 views

Daily Progress Report

Scope This standard prescribes minimum mandatory requirements for design and installation of grounding systems and lightning protection systems for Saudi Aramco facilities. This document may not be attached to nor made a part of purchase orders. 2 Conflicts, Deviations and Commentary 2.1 If there are any conflicts between this Standard and associated purchasing, project or engineering documents, this standard shall take precedence. The exception is if an approved Waiver has been included with the purchasing documents. 2.2 Any conflicts between this standard and other applicable Saudi Aramco Engineering Standards (SAESs), Materials System Specifications (SAMSSs), Standard Drawings (SASDs), or industry standards, codes, and forms shall be resolved in writing by the company or buyer representative through the Manager, Consulting Services Department of Saudi Aramco, Dhahran. 2.3 Direct all requests to deviate from this standard in writing to the company or buyer representative, who shall follow internal company procedure SAEP-302 and forward such requests to the Manager, Consulting Services Department of Saudi Aramco, Dhahran. 2.4 The designation “Commentary” is used to label a sub-paragraph that contains comments that are explanatory or advisory. These comments are not mandatory, except to the extent that they explain mandatory requirements contained in this SAES. 3 References The selection of material and equipment, and the design, construction, maintenance, and repair of equipment and facilities covered by this standard shall comply with the latest edition of the references listed below, unless otherwise noted.

Uploaded by

Prabu Baskaran
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Daily Progress Report

22.10.2016
Date:
Project : Replacement of 69 KV O/H Line in EOA, From Qatif BSP to KFIA.
Contract No. : 4400005462/00
Contractor : Nassir Manae Wabran Co. & Partners
[Section #1] POLE 45 - POLE 52
Pole Number
Activity
45
46
47
48
49
Insulator Assembly

Insulator Hoisting

Wire Pulling

Paying out (TOP Ckt 1)

Paying out (Middle Ckt 1)

Paying out (Bottom Ckt 1)

Paying out (TOP Ckt 2)

Paying out (Middle Ckt 2)

Paying out (Bottom Ckt 2)

Sagging
Clipping & Clamping
Final checking

50

51

57

58

52

Status
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed

[Section #2] POLE 52- POLE 57


Activity
Insulator Assembly
Insulator Hoisting
Wire Pulling
Paying out (TOP Ckt 1)
Paying out (Middle Ckt 1)
Final checking

Prepared By

Prabu Baskaran
QA/QC Electrical Engr.,
Contract No. 4400005462
Replacement of 69KV O/H Line In EOA,
From Qatif BSP to KFIA (Line 1)

Mobilie : +966 547809689

Pole Number
52

53

54

55

56

Status

ongoing

Remarkable event :
1. Circuit 1 & 2 ACSR Drake Conductor Pay in only done , Still Sagging is not prepared.
2. Pole No: 58 (Take Off Structure) - 1 No Pole, still not erected due to existing 69KV line clearance.