Thatta Cement Company LTD Thatta Mechanical Department Daily Activity Report

The daily activity report from Thatta Cement Company's Mechanical Department summarizes work carried out by the Coal Mill section on May 16th. Three men repaired the BC 02 belt joint and two men repaired the reject belt joint. Four men were working on upgrading the reject coal hopper which was in progress. Two men repaired an explosive sheet on the bag filter and all work was reported as completed or in progress without issues.

Uploaded by

zain140
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
55 views2 pages

Thatta Cement Company LTD Thatta Mechanical Department Daily Activity Report

The daily activity report from Thatta Cement Company's Mechanical Department summarizes work carried out by the Coal Mill section on May 16th. Three men repaired the BC 02 belt joint and two men repaired the reject belt joint. Four men were working on upgrading the reject coal hopper which was in progress. Two men repaired an explosive sheet on the bag filter and all work was reported as completed or in progress without issues.

Uploaded by

zain140
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

THATTA CEMENT COMPANY LTD THATTA

MECHANICAL DEPARTMENT
DAILY ACTIVITY REPORT
Section _Coal Mill
S.No

JOB DESCRIPTION

MEN POWER

1 BC 02 belt joint repairing work carriedout

2 reject belt joint repairing work carriedout

3 reject coal hopper upgradation work carriedout.

4 bag filter explosive sheet repaired

Date: _16-05-16
STATUS

REMARKS

completed

ok

completed

ok

inprogress
completed

ok

____________________
Area Incharge