Infrastructure Method of Construction
Infrastructure Method of Construction
1. Introduction
This document illustrates the method of construction for
Pk#100 under the contract of Mivida.
2.Purpose
3. Scope Statement
4. Sequence of work
3rd Phase
4th
Phase
2nd
Phase
1st Phase
4-1 Illustrative layout
f)
g)
h)
i)
j)
t) Before handing over part of pipeline, pass through if rubber disc plunger
or swab and in the case of jointed pipelines, simultaneously flush the
line with clean water.
u) Both ends then be closed by temporary plugs or bulkheads to prevent
entry of dirty or foreign matter.
1. Placing of Subbase
a) Prior to placing any Lower Subbase material, the
underlying subgrade shall be shaped and compacted
in accordance to the specifications.
b) The material shall be placed over the full width of the
formation to the required thickness as shown in the
drawings in one layer or more, each layer not
exceeding 200mm compacted thickness.
c) Each layer of Lower Subbase shall be process as
necessary to bring its moisture content to a uniform
level throughout the material suitable for compaction.
d) The Lower Subbase shall be compacted using suitable
compaction equipment approved by the Engineer to
not less than 95% of the maximum dry density
determined in the B.S. 1377 Compaction Test (4.5 km
rammer method).
e) The top of Lower Subbase shall have the required
thickness, shape, super elevation, levels and grades
as required in the drawings and shall be within the
tolerances as specified in the specifications.
f) In the course of the construction, the level shall be
checked using control/dipping pegs, set out at regular
interval along both sides of the pavement.
Cable pulling and splicing can occur any time after the duct
banks and vaults are completed. Prior to installation of the
cable, the conduit is tested and cleaned by pulling a mandrel
and swab through each of the ducts. A typical setup is to lace
the reel of cable at the transition structure or at one of the
vaults and the winch truck at the next vault. The cable is then
pulled from the transition structure to the nearest vault.
Direction of pull between vaults is based on the direction that
results in the lowest pulling and sidewall tensions. Cable
lengths are spliced within the vaults.
5) Backfilling
A special backfill material is used instead of soil in the trench
around the cables to ensure sufficient heat transfer to the
surrounding soils and groundwater.
TRANSFORMERS
A. GENERAL:
1. Transformers shall have all-copper windings.
2. Electric panels shall not be mounted inside transformer
enclosures.
3. All transformers are to be new.
4. Transformers shall be Radially fed only, with an upstream SF-6
switch to de-energize the design shall only be utilized for
simplifying the wiring congestion within the High Voltage
compartment. When the transformer is internally wired as a
Radial feed transformer,
5. All conduits shall enter & exit transformer from beneath the pad.
B. TESTING
6t