Time Limits Actions Flow Chart 001 Fidic Red Book 1999 PDF
Time Limits Actions Flow Chart 001 Fidic Red Book 1999 PDF
28 Days
Date
(Sub-Clause
LatestBase
Stated
Date
for Tender1.1.3.1)
Submission
Max 42 Days
Max 28 Days
Min 7 Days
Max 21 Days
Max 42 Days
Within 28 Days
Max 28 Days
Works Complete,
Defects Remedied,
Documents Submitted
(Sub-Clause 11.9)
Before
Max 28 Days
Before
Works Pass Tests On Completion & Report Submitted (Sub-Clause 9.1) Works Reach Completion (Sub-Clause 8.2 & 10.1)
Max 21 Days
Max 14 Days
Min 21 Days
Contractor to Submit
Documents Prior to Tests On
Completion (Sub-Clause 9.1 &
4.1d)
Max 28 Days
Time For Completion (Sub-Clause 8.2) including any extension thereto granted by the Engineer (Sub-Clause 8.4) (See also Sub-Clause 1.1.3.3)
Max 42 Days
Max 21 Days
Max 28 Days
DAB to be
appointed (SubClause 20.2)