Al Ain Stadium & Mixed Use Development Phase 1.1: Inspection & Test Plan For Installation & Termination of Cables & Wires

This document provides an inspection and test plan for the installation and termination of cables and wires at the Al Ain Stadium & Mixed Use Development Phase 1.1 project. It outlines 5 items to be inspected, including material approvals, installation, inspection of completed work, cleaning/protection, and document review. Responsibilities for inspection are assigned to the main contractor BAM International, subcontractor ETA, and consultant. Inspections will verify that the work meets specifications, approved shop drawings, and the referenced method statement. Inspection reports and test certificates will be reviewed for approval and sign-off before work is handed over.

Uploaded by

midhun murali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
264 views

Al Ain Stadium & Mixed Use Development Phase 1.1: Inspection & Test Plan For Installation & Termination of Cables & Wires

This document provides an inspection and test plan for the installation and termination of cables and wires at the Al Ain Stadium & Mixed Use Development Phase 1.1 project. It outlines 5 items to be inspected, including material approvals, installation, inspection of completed work, cleaning/protection, and document review. Responsibilities for inspection are assigned to the main contractor BAM International, subcontractor ETA, and consultant. Inspections will verify that the work meets specifications, approved shop drawings, and the referenced method statement. Inspection reports and test certificates will be reviewed for approval and sign-off before work is handed over.

Uploaded by

midhun murali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 5

ALAINSTADIUM&MIXEDUSEDEVELOPMENTPHASE1.

Ref.No.

TITLE

: ITPMEP09

Rev.No. : 00
INSPECTION&TESTPLANFOR
INSTALLATION&TERMINATIONOFCABLES&
Date
: 18.09.2012
WIRES

ALAINSTADIUM&MIXEDUSEDEVELOPMENTPHASE1.1

INSPECTION&TESTPLANFOR
INSTALLATION&TERMINATIONOFCABLES&WIRES

ITPMEP09

MAINCONTRACTOR:
BAMINTERNATIONAL

SUBCONTRACTOR:
ETA

ALAINSTADIUM&MIXEDUSEDEVELOPMENTPHASE1.1

Ref.No.

TITLE

: ITPMEP09

Rev.No. : 00
INSPECTION&TESTPLANFOR
INSTALLATION&TERMINATIONOFCABLES&
Date
: 18.09.2012
WIRES

REVISIONRECORD

Thiscoverpageisarecordofallrevisionsofthedocumentidentifiedabovebynumberandtitle.Allpreviouscover
pagesareherebysupersededandaretobedestroyed.

Thecontractorhasthefullrighttomodify,amendorchangeMethodStatementandsupportingdocumentsasrequired
orasdeemednecessary.Allsuchdocumentswillbesubmittedtothe"Consultant's"forapproval.

Rev.
No.

Date

Prepd'By

00

18.09.12

MOHIDEEN

Chkd'By
BAMApproval DescriptionandPageNumbersofRevisions

ANA

MAINCONTRACTOR:
BAMINTERNATIONAL

SUBCONTRACTOR:
ETA

INSPECTION & TEST PLAN

AL AIN STADIUM & MIXED USE DEVELOPMENT PHASE 1.1

REF. No. : ITP-MEP-09


REV. No.: 00
DATE
: 18.09.2012

INSPECTION & TEST PLAN FOR


INSTALLATION & TERMINATION OF CABLES & WIRES
AREA

LEVEL

ITEM NO.
1

DESCRIPTION

Material Approvals

Material submittals

Quality Documents

Method Statement ref. MS-MEP-09

Materials Verification

BAM

CON

Approved material submittals

Inspection of Materials Received at site

Project Specification

Storage

Manufacturer's Recommendations &


Method Statement no.MS-MEP-09

ETA

Document Approvals

Quality Control Procedure ref. QCP-MEP-09


2

INSPECTION & ACCEPTANCE

SPECIFICATION / CRITERIA

Installation
Safety Clearance

Project Safety Plan

Installation

Project Specification
Method Statement ref. MS-MEP-09
Approved shop drawings

VERIFYING
DOCUMENT

Project Specification
Inspection of Installation & Termination of
Cables & Wires

of the area
MEP-09

Approved shop drawings


Mehtod statement MS-

FM-MEP-09A

INSPECTION & TEST PLAN

AL AIN STADIUM & MIXED USE DEVELOPMENT PHASE 1.1

REF. No. : ITP-MEP-09


REV. No.: 00
DATE
: 18.09.2012

INSPECTION & TEST PLAN FOR


INSTALLATION & TERMINATION OF CABLES & WIRES
AREA

LEVEL

ITEM NO.
4

DESCRIPTION

ETA

Cleaning Protection
Cleaning on completion of the activity

Method statement No. MS-MEP-09

Protection (if required) against possible

Method statement No. MS-MEP-09

damages till Commissioning/Handing-over


5

VERIFYING
DOCUMENT

INSPECTION & ACCEPTANCE

SPECIFICATION / CRITERIA

BAM

CON

Document Review

LEGEN :

Site Inspection Reports

Signed & Approved

Test Certificates (if applicable)


Pressure Test Report (if applicable)
NCRs (if any)

Handed-over
Signed & Approved
All NCRs Closed & Signed off

H
H
H

R
R
R

R
R
R

H - HOLD FOR INSPECTION

W - WITNESS INSPECTION

SUBCONTRACTOR :

ETA APPROVAL

BAM APPROVAL

CONSULTANT APPROVAL

NAME :

NAME

NAME :

SIGN

SIGN

SIGN

DATE

DATE

DATE

ETA

S - SURVEILLANCE INSPECTION

- REVIEW