2016-Private Sector Initiated Power Projects-Luzon-Committed 09302016..
2016-Private Sector Initiated Power Projects-Luzon-Committed 09302016..
COMMITTED
As of 30 September 2016
Committed/
Indicative
Project Proponent
Location
Rated
Capacity
(MW)
2720
COAL
Project Status
Target Commercial
Operation
Between May to
November 2017
November 2017
Committed
SMC Consolidated
Power Corporation
300
Committed
Pagbilao Coal-Fired
Thermal Power Plant
Pagbilao Energy
Corporation
420
Committed
San Buenaventura
Power Ltd. Co. (SBPL)
Mauban, Quezon
500
December 2018
December 2019
December 2019
(Target Testing and
Commissioning)
FINANCING ARRANGEMENTS:
Financing arrangements is expected to be secured only after the ERC issues the final approval; Financially closed December 1, 2015
Project cost is Php37.8B
GROUNDBREAKING SCHEDULES:
December 10, 2015
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
Owner's Engineer selected; EPIC bids received in November 2013
EPC Contract signed October 2014;
COMMENCEMENT OF CONSTRUCTION:
Award EPC contract estimate September 2013;
End of 2014
Expect to commence construction only after the ERC issues the final approval
4 years to fully complete the construction of the plant;
FEASIBILITY STUDY:
Completed February 2011
ARRANGEMENT FOR SECURING THE REQUIRED LAND:
No additional land will be aquired as the expansion will be inside the existing Masinloc Power Plant Complex.
NPC/PSALM, however, is still continuing the titling process and land registration for some parcels of land
Committed
Zambales
300
Committed
Mariveles, Bataan
1200
FINANCING ARRANGEMENTS:
Project cost is $1B
Provided bank certification which was received by DOE-EPIMB-PPDD on 18 March 2016
With Financial Closing, agreed by GNPD and banks/financial institutions on 17 December 2015
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
On-going finalization of EPC Contract
EPC Contract was signed on Oct 27, 2015
1100
NATURAL GAS
Committed
450
April 2016
Oct 2016
(Awaiting ERC-COC)
U1 - Feb 2017
U2 - May 2017
U3 - Aug 2017
U1 - Feb 2017
U2 - May 2017
U3 - Aug 2017
(Target Testing and
Commissioning)
February 2019
February 2019
COMMENCEMENT OF CONSTRUCTION:
16 December 2013;
98.8% completed as of March 2016
FEASIBILIY STUDY:
Completed
'ARRANGEMENT FOR SECURING THE REQUIRED LAND:
Land is already secured with a long lease entered into since 2007
MARKETING OF GENERATING CAPACITIES:
No specific off taker yet but already have a discussion with Federation of Philippine Industries, intended to supply power into the Wholesale Electricity Spot Market but is also open to discussing potential off take
arrangements as well
100% WESM
Energy World
Corporation
650
62.5
HYDROPOWER
Committed
Kapangan
Cordillera Hydro
Electric Power
Corporation
60
COMMENCEMENT OF CONSTRUCTION:
On-going civil works of hydro facilities
Committed
Prismc
PNOC-Renewables
Corporation
GROUNDBREAKING SCHEDULES:
Ground breaking held on 11 July 2014; Confirmed DOC on 4 September 2014; Rehabilitation
Rizal, Nueva Ecija
September 2019
September 2019
March 2020
March 2020
Committed
Tubao
Tubao Mini-Hydro
Electric Corporation
Tubao, La Union
1.5
GROUNDBREAKING SCHEDULES:
Ground breaking held on 8 November 2014
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
Pending submission of requirements for construction
SOLAR
Committed
52.975
18
Committed
NV Vogt Philippines
Solar Energy Four, Inc.
(NV VOGT 4)
7.48
Committed
NV Vogt Philippines
Solar Energy Three,
Inc. (NV VOGT 3)
8.84
Committed
CW Marketing &
Development Corp.
(CW)
1.675
Committed
3.82
Morong, Bataan
Jobin-Sqm Inc.
Committed
Committed
Committed
March 2016
(On-going Testing and
Commissioning)
April 2016
(On-going Testing and
Commissioning)
April 2016
(On-going Testing and
Commissioning)
September 2016
(On-going Testing and
Commissioning)
July 2016
(On-going Testing and
Commissioning)
June 2016
(On-going Testing and
Commissioning)
October 2016
October 2016
October 2016
October 2016
October 2016
October 2016
October 2016
December 2016
October 2016
December 2016
CONSTRUCTION:
On-going construction (see FIT Monitoring Board)
0
43
WIND
GEOTHERMAL
Committed
Maibarara 2 Geothermal
Project
Maibarara Geothermal
Inc.
Batangas
12
August 2017
August 2017
December 2018
December 2018
(Target Testing and
Commissioning)
October 2016
FINANCING ARRANGEMENTS:
Project cost estimated PhP 1,848.30 Million
Committed
Bacman 3 (Tanawon)
Geothermal Project
Energy Development
Corporation
Guinlajon, Sorsogon
31
22.9
BIOMASS
Tarlac
1.5
Committed
Camarines Sur
4.5
CONSTRUCTION:
On-going construction
Committed
AseaGas Corporation
Batangas
6.1
CONSTRUCTION:
On-going construction
October 2016
June 2017
(Subject to FIT)
July 2017
(Subject to FIT)
Dec 2016
Dec 2017
Committed
FINANCING ARRANGEMENTS:
Project Cost Php1.234B
Brgy. Tulat, San Jose, Nueva Ecija
10.8
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
EPC w/ Engcon of Singapore
Pre-construction (100% completed as of 31 August 2014 );
Phase I - Estimated Accomplishment of Construction 98 % completed as of 31 August 2014 )
Remaining major equipment in-progress is the installation of travelling gate
On-going installations of the feed water piping system, chemical dosing pipeline, three control elements of the boiler and other field instruments
Expected arrival of switchyard is on May 2014
Interconnection (100% completed as of 31 August 2014 )
On-going construction as of 30 September 2014
Pre-Construction - 100%; Construction-98%; Interconnection-100%)
10
Battery
Masinloc, Zambales
10
* Committed Project(s)
COAL
DIESEL / OIL
NATURAL GAS
GEOTHERMAL
HYDROPOWER
SOLAR
WIND
BIOMASS
BESS
4001.375
2720
1100
43
62.5
52.975
0
22.9
10
4001.375
TRUE