2016-Private Sector Initiated Power Projects-Luzon-Committed 09302016..

The document provides an overview of several committed private sector power projects in Luzon, Philippines. It lists details such as the project name, proponent, location, rated capacity, project status, target testing and commissioning dates, and permits and regulatory requirements. The largest project is the Limay Power Plant Phase I with a rated capacity of 2720 MW. Other major projects include the Pagbilao Coal-Fired Thermal Power Plant, San Buenaventura Power Ltd. Co. Project, and Masinloc Expansion Project. Most of the projects involve coal-fired power and aim to be operational between 2016-2020.

Uploaded by

Francis Cheng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
132 views

2016-Private Sector Initiated Power Projects-Luzon-Committed 09302016..

The document provides an overview of several committed private sector power projects in Luzon, Philippines. It lists details such as the project name, proponent, location, rated capacity, project status, target testing and commissioning dates, and permits and regulatory requirements. The largest project is the Limay Power Plant Phase I with a rated capacity of 2720 MW. Other major projects include the Pagbilao Coal-Fired Thermal Power Plant, San Buenaventura Power Ltd. Co. Project, and Masinloc Expansion Project. Most of the projects involve coal-fired power and aim to be operational between 2016-2020.

Uploaded by

Francis Cheng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

PRIVATE SECTOR INITIATED POWER PROJECTS (LUZON)

COMMITTED
As of 30 September 2016
Committed/
Indicative

Name of the Project

Project Proponent

Location

Rated
Capacity
(MW)
2720

COAL

Project Status

Target Testing &


Commissioning

Target Commercial
Operation

Unit 1 - 150 MW October 2016


Unit 2 - 150 MW April 2017

Unit 1 - 150 MW November 2016


Unit 2 - 150 MW July 2017

Between May to
November 2017

November 2017

FEASIBILITY STUDY: Completed;


'ARRANGEMENT FOR SECURING THE REQUIRED LAND: Completed;
MARKETING OF GENERATING CAPACITIES:
On-going electric power supply contract negotiation with prospective off-takers (DUs);
For Unit 1 - ISECO-10MW, TARELCO I-10MW, TARELCO II-15MW, PENELCO-10MW, REAL STEEL-7MW, SMC (Various Facilities)-60.3MW; For Unit 2 PENELCO-10MW, OCEANA GOLD-12.5MW, REAL STEEL-17MW,
SMC (Various Facilities)-37.1MW; 188.9 TOTAL

Committed

Limay Power Plant Project


Phase I

SMC Consolidated
Power Corporation

Brgy. Lamao, Limay, Bataan

300

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Environmental Impact Assessment completed;
Topographic and Hydrographic completed;
Soil Investigation completed;
GIS/SIS submitted last 12 July 2013, under review of NGCP;
Facility Study already sent to NGCP for review;
EPC was executed in January 2013; awarded;
ECC was issued on 17 September 2013;
SEC issued last 19 August 2011
Clearance to Underatake GIS from DOE issued on 13 February 2013;
Addendum for the re run of SIS was submitted to NGCP last Jan 30, 2015 for review;
GROUNDBREAKING SCHEDULES:
Groundbreaking was held September 2014;
FINANCING ARRANGEMENTS:
Financial Arrangement Secured (65% Loan / 35% Equity);
Project cost is $622.15M / Php25.508B
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
Construction of the Project has been underway since January 2014;
Construction Activities of Unit 1&2 2 x 150MW Power Plant - 2.30%;
Design and Construction of Pier and Jetty Structure is 99.55%;
Overall Piling Works is 52.29%;
Turbine and Generator Building is 58.47%;
Ash Dump Design and Construction - 100%;
COMMENCEMENT OF CONSTRUCTION:
March 2014;
FEASIBILITY STUDY:
Feasibility Study completed;
Estimated Net Capacity: 400MW
ARRANGEMENT FOR SECURING THE REQUIRED LAND: Completed;
MARKETING OF GENERATING CAPACITIES:
Contract with off-takers completed, Suppy agreement executed;
50% of the plant's capability will be sold to Therma Luzon Inc.
50% will be sold to TeaM (Phils.) Energy Corporation;

Committed

Pagbilao Coal-Fired
Thermal Power Plant

Pagbilao Energy
Corporation

Pagbilao Power Station, Nrgy.


Ibabang Polo, Pagbilao, Quezon

420

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Environmental Compliance Certificate was issued on 18 June 2013;
Secured endorsement from Sangguniang Barangay of Ibabang Polo, Sangguniang Bayan of Pagbilao, Sangguniang Panlalawigan of Quezon;
ECC issued on 18 June 2013
In final negotiations with NPC, PSALM, TeaM Energy Corporation and Therma Luzon, Inc. to co-locate the plant in the existing Pagbilao Power Station;
GROUNDBREAKING SCHEDULES:
23 July 2014
FINANCING ARRANGEMENTS:
Financial Arrangement Secured with various lenders on 30 July 2014; On-going draw downs for planned milestones and progress payments;
Estimated Project Cost: US$ 1,000,000,000.00
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
Construction Contracts for Plant & Equipment:Completed and executed;
Notice to Proceed and Commencement
Notice issued to EPC Contractor; Down Payment already released to EPC contractor;
Commencement of EPC and Construction: May 2014; Approximately 71% completed as of February 2016;
84.32% completion as of 25 July 2016
86.49% completion as of 26 August 2016

FEASIBILITY STUDY: Completed


Completed Selection Study in 2012; Technology selection study completed 2012
Coal Sourcing Study completed in 2012
Facility Study to be done in 2014; System Impact Study completed 2007 and revalidated 2013
ARRANGEMENT FOR SECURING THE REQUIRED LAND:
Project will be located within the existing site
MARKETING OF GENERATING CAPACITIES:
20 years + 5-year extension PSA with MERALCO as offtaker;
Awaiting for the ERC approval of their PSA with MERALCO;
SBPL has signed a PSA with Meralco on 29 May 2014; PSA approved by ERC on March 27, 2015 and released May 19, 2015

Committed

San Buenaventura Power


Ltd. Co. (SBPL) Project

San Buenaventura
Power Ltd. Co. (SBPL)

Mauban, Quezon

500

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Clearance to Underatake GIS from DOE issued on 7 March 2013;
System Impact Study completed in 2007 and is being revalidated in 2013;
ECC (Ref.Code 0610-012-4021) issued on 4 June 2007;
ECC extension of validity issued on 31 May 2012 and valid until 4 June 2015; ECC for SBPL issued on 11 November 2014
Reguest for Amendment to upgraded technology submitted to EMB on 17 February 2014
Request to assign the ECC for new project was requested on 2 June 2014;
Additional information requested by EMB on 7 August 2014;QPL is in the process of preparing the documents;
Secured Sanggunian Bayan Resolution No. 2014-269 endorsing the project to expand;
SIS completed in 2007 and is being revalidated;
Municipal LGU endorsement issued April 19, 2005;
Certificate of Non-Overlap was issued by the NCIP to Quezon Power on 5 February 2014; Request to assign the CNO was endorsed by the DOE and submitted to the NCIP on 15 July 2014; Certificate of Non-overlap
issued on 29 August 2014
ERC application was filed on 2 June 2014; Financing arrangements is expected to be secured only after the ERC issues the final approval; BOI Certificate of Registration issued on 15 October 2015

December 2018

December 2019

Unit 3 - September 2019

December 2019
(Target Testing and
Commissioning)

Unit I - Oct 2018


Unit II - 2019

Unit I - March 2019


Unit II -January 2020

FINANCING ARRANGEMENTS:
Financing arrangements is expected to be secured only after the ERC issues the final approval; Financially closed December 1, 2015
Project cost is Php37.8B
GROUNDBREAKING SCHEDULES:
December 10, 2015
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
Owner's Engineer selected; EPIC bids received in November 2013
EPC Contract signed October 2014;
COMMENCEMENT OF CONSTRUCTION:
Award EPC contract estimate September 2013;
End of 2014
Expect to commence construction only after the ERC issues the final approval
4 years to fully complete the construction of the plant;
FEASIBILITY STUDY:
Completed February 2011
ARRANGEMENT FOR SECURING THE REQUIRED LAND:
No additional land will be aquired as the expansion will be inside the existing Masinloc Power Plant Complex.
NPC/PSALM, however, is still continuing the titling process and land registration for some parcels of land

Committed

Masinloc Expansion Project

AES Masinloc Power


Partners Co., Inc.

Zambales

300

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Grid Impact Studies obtained on 7 January 2011
ECC Amendment was released by DENR on April 23, 2012
The amended DOE Certificate of Endorsement for BOI was released on May 7, 2012
Secured CoE for ERC on September 2011
On-going processing of Certificate of Precondition from NCIP
SAPA amendment is still pending with DENR
FINANCING ARRANGEMENTS:
Provided bank certification for financial closing status to DOE dated 24 August 2016;
Project cost is Php49.45B
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
Selection of EPC Contractor on going
COMMENCEMENT OF CONSTRUCTION:
2nd Qtr 2014
PERMITS AND OTHER REGULATORY REQUIREMENTS:
On-going presentation/proposal submissions to potential customers
Clearance to Undertake GIS from DOE issued on 26 June 201;
Obtained LGU endorsements; BOI registration for 600 MW pre-approve
On-going SI;
On-going EIS for ECC application
On-going securing DOE of Endorsement for DENR-ECC Arrangements for securing the required land will be acquired by an affiliate Filipino company of GNPower;
On-going negotiation with tenders

Committed

GNPower Dinginin 2 x 660


MW Supercritical CoalFired Power Plant

GNPower Dinginin Coal


Plant Ltd. Co.

Mariveles, Bataan

1200

FINANCING ARRANGEMENTS:
Project cost is $1B
Provided bank certification which was received by DOE-EPIMB-PPDD on 18 March 2016
With Financial Closing, agreed by GNPD and banks/financial institutions on 17 December 2015
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
On-going finalization of EPC Contract
EPC Contract was signed on Oct 27, 2015

1100

NATURAL GAS

MARKETING OF GENERATING CAPACITIES:


Discussion with target off takers targeted for the first half of 2014; still on-going (17 June 2015); looking at teaming up with MERALCO and other potential offtakers and/or offer the available capacity to the spot
market (WESM).

Committed

San Gabriel Power Plant


(Phase II)

First NatGas Power


Corp.

Santa Rita, Batangas

450

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Secured Clearance from DOE for the conduct of GIS on 18 February 2013
Engineering, Procurement and Construction (EPC) and Operations Maintenance (O&M) contracts already awarded on December 16, 2013
Ongoing application for the Permit to operate mechanical equipment such as boilers, pressure vessels etc from City Engineers office of Batangas;
Ongoing application for COE and MOA from DOE;
Ongoing application for ERC point to point connection of transmission lines for Sta. Rita, San Lorenzo switchyard;
Ongoing negotiations with NGCP for contract metering and Transmission Service Agreement;
SIS was approved by NGCP on 11 December 2013.
Processing of the application of COC with ERC is ongoing. Technical inspection is targeted to be done in the 3rd week of May 2016
The application of First NatGas Power Corp (FNPC) to be a direct memer of WESM was approved on 26 February 2016
San Gabriel achieved its first GT firing on 11 April 2016
First synchronization to the grid was achieved on 13 April 2016
Targeting to conduct its first combined-cycle operation on 04 May 2016
Awaiting approval from DENR Central Office of the assignment of foreshore lease between First Gas Power Corp and FNPC
Permit to Operate application to the City Engineer's Office is ongoing.
FINANCING ARRANGEMENTS:
Financial Arrangement with kfW Secured on 4 September 2014
Project cost is US$600 Million; bilateral contracts on the grid and NGCP for station-use/feed-back power

April 2016

Oct 2016
(Awaiting ERC-COC)

U1 - Feb 2017
U2 - May 2017
U3 - Aug 2017

U1 - Feb 2017
U2 - May 2017
U3 - Aug 2017
(Target Testing and
Commissioning)

February 2019

February 2019

COMMENCEMENT OF CONSTRUCTION:
16 December 2013;
98.8% completed as of March 2016
FEASIBILIY STUDY:
Completed
'ARRANGEMENT FOR SECURING THE REQUIRED LAND:
Land is already secured with a long lease entered into since 2007
MARKETING OF GENERATING CAPACITIES:
No specific off taker yet but already have a discussion with Federation of Philippine Industries, intended to supply power into the Wholesale Electricity Spot Market but is also open to discussing potential off take
arrangements as well
100% WESM

Pagbilao Combined Cycle


Gas Fired Power Plant
Committed
Proposed 3x200 MW CCGT
Power Plant

Energy World
Corporation

Brgy. Ibabang Polo, Grande Island,


Pagbilao, Quezon

650

PERMITS AND OTHER REGULATORY REQUIREMENTS:


GIS for 300MW issued by NGCP on 8 August 2013 and revised on 3 July 2013 for 600MW
Issued DOE Endorsement for Revised Capacity on 3 July 2013;
Revised DOE clearance for GIS submitted to NGCP on January 2014
GIS from NGCP for the 600MW was released on August 2014;
Several Resolutions has been issued on May 2014 (Sangguniang Barangay Resolution, Sangguniang Bayan Resolution and Sangguniang Panlalawigan Resolution) interposing no objection for the construction of a 600
MW Liquified Natural Gas (LNG) Power Plant;
On-going processing of ECC for power plant
FINANCING ARRANGEMENTS:
Financial Arrangement Secured
Syndicated Loan
Project Cost:$300M
Signing of loan agreement last 18 Sep 2015
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
Entered into a Sale and Purchase Agreement last October 2012 with Siemens Energy for two 200 MW gas turbines and the first 200MW turbine is expected to arrive by September 2014;
LNG Tank is currently at 50% construction completed as of August 2014;
COMMENCEMENT OF CONSTRUCTION:
December 2013
Completed

62.5

HYDROPOWER

Committed

Kapangan

Cordillera Hydro
Electric Power
Corporation

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Issued Confirmation of Commerciality on 13 February 2014
Kapangan & Kibungan, Benguet

60

COMMENCEMENT OF CONSTRUCTION:
On-going civil works of hydro facilities

Committed

Prismc

PNOC-Renewables
Corporation

GROUNDBREAKING SCHEDULES:
Ground breaking held on 11 July 2014; Confirmed DOC on 4 September 2014; Rehabilitation
Rizal, Nueva Ecija

September 2019

September 2019

March 2020

March 2020

CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:


On-going construction activities

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Issued Confirmation of Commerciality on 19 March 2015

Committed

Tubao

Tubao Mini-Hydro
Electric Corporation

Tubao, La Union

1.5

GROUNDBREAKING SCHEDULES:
Ground breaking held on 8 November 2014
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
Pending submission of requirements for construction

SOLAR

Committed

52.975

Next Generation Power


Bataan Solar Power Project
Technology Corp.
Brgy. Alas-asin, Mariveles, Bataan
(NGPT)

18

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Awarded with RE Service Contract (SESC No. 2014-04-076) on 12 May 2014
Certificate of Commerciality No. SCC- 2016-03-048 dated 11 March 2016

Committed

Dalayap Solar Power


Project

NV Vogt Philippines
Solar Energy Four, Inc.
(NV VOGT 4)

Brgy. Dalayap, Tarlac City, Tarlac

7.48

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Awarded with RE Service Contract (SESC No. 2016-02-278) on 19 Feb 2016
Certificate of Commerciality No. SCC- 2016-03-049 dated 14 March 2016

Committed

Armenia Solar Power


Project

NV Vogt Philippines
Solar Energy Three,
Inc. (NV VOGT 3)

Brgy. Armenia, Tarlac City, Tarlac

8.84

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Awarded with RE Service Contract (SESC No. 2016-02-227) on 19 Feb 2016
Certificate of Commerciality No. SCC- 2016-03-050 dated 14 March 2016

Committed

CW Home Depot Solar


Power Project

CW Marketing &
Development Corp.
(CW)

CW Home Depot, Brgy. Pulong, Sta.


Rosa City, Laguna

1.675

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Awarded with RE Service Contract (SESC No. 2016-02-228) on 07 Mar 2016
Certificate of Commerciality No. SCC- 2016-03-054 dated 31 March 2016

Committed

San Rafael Solar Power


Plant

SPARC Solar Powered


Agri-Rural
Communities
Corporation

San Rafael, Bulacan

3.82

Morong Solar Power Plant

SPARC Solar Power AgriRural Communities

Morong, Bataan

Sta. Rita Solar Phase 1


Power Project

Jobin-Sqm Inc.

Morong and Hermosa, Bataan

Sarrat Solar Power Project

Bosung Solartec, Inc.


(BOSUNG)

Committed

Committed

Committed

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Awarded with Solar Energy Service Contract (SESC No. 2012-03-012) on 03 May 2012
Certificate of Commerciality No. SCC- 2015-10-035 dated 10 November 2015
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
On-going construction (see FIT Monitoring Board)

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Awarded with Solar Energy Service Contract (SESC No. 2012-03-012) on 03 May 2012
Certificate of Commerciality No. SCC- 2015-10-037 dated 10 November 2015
5.02
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
On-going construction (see FIT Monitoring Board)

March 2016
(On-going Testing and
Commissioning)

April 2016
(On-going Testing and
Commissioning)

April 2016
(On-going Testing and
Commissioning)

September 2016
(On-going Testing and
Commissioning)

July 2016
(On-going Testing and
Commissioning)

June 2016
(On-going Testing and
Commissioning)

October 2016

October 2016

October 2016

October 2016

October 2016

October 2016

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Awarded with Solar Energy Service Contract (SESC No. 2013-10-039) on 30 October 2013;
Certificate of Commerciality No. SCC- 2015-09-021 dated28 August 2015;
7.14

October 2016

December 2016

October 2016

December 2016

CONSTRUCTION:
On-going construction (see FIT Monitoring Board)

Brgy. 21 San Marcos, Sarrat, Ilocos


Norte

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Awarded with RE Service Contract (SESC No. 2016-02-276) on 19 Feb 2016
Certificate of Commerciality No. SCC- 2016-03-052 dated 22 March 2016

0
43

WIND
GEOTHERMAL

FEASIBILITY STUDY: On-going


MARKETING OF GENERATING CAPACITIES:
The off-taker for generated power is still under negotiation

Committed

Maibarara 2 Geothermal
Project

Maibarara Geothermal
Inc.

Batangas

12

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Project is within the existing DOE Service Contract within GRESC # 2010-02-012
LGU endorsement
Land Use permits
DENR-ECC and water rights obtained
Secured Certificate of Non-overlap from NCIP regional Office IV
Confirmation of Commerciality obtained from DOE on 21 September 2015;

August 2017

August 2017

December 2018

December 2018
(Target Testing and
Commissioning)

Phase 1 - October 2016


Phase 2 - TBD

Phase 1 - October 2016


(Target Testing and
Commissioning)
Phase 2 - TBD

October 2016

October 2016 (Target


Testing and
Commissioning)

FINANCING ARRANGEMENTS:
Project cost estimated PhP 1,848.30 Million

Committed

Bacman 3 (Tanawon)
Geothermal Project

Energy Development
Corporation

Guinlajon, Sorsogon

31

PERMITS AND OTHER REGULATORY REQUIREMENTS:


DOE Service Contract within GRESC # 2009-10-003;
LGU endorsement
Land Use Permits,
DENR-ECC
Water Rights obtained;
Turnkey Contract pending result of feasibility study under negotiation;
Submitted Declaration of Commerciality (DOC) on 17 June 2014, evaluation by DOE of the DOC is still on-going;
FINANCING ARRANGEMENTS:
Project to be finance by EDC;
Project cost estimated $140M-180M

22.9

BIOMASS

FINANCING ARRANGEMENTS: Closed


Committed

ACNPC WTE Biomass


Power Plant Project

Asian Carbon Neutral


Power Corporation

Tarlac

1.5

Committed

Bicol Biomass Energy


Corporation

Bicol Biomass Energy


Corporation

Camarines Sur

4.5

CONSTRUCTION:
On-going construction

FINANCING ARRANGEMENTS: Closed


CONSTRUCTION:
On-going construction

Committed

AseaGas Biogas Power


Plant Project

AseaGas Corporation

Batangas

6.1

CONSTRUCTION:
On-going construction

October 2016

October 2016 (Target


Testing and
Commissioning)

June 2017
(Subject to FIT)

July 2017
(Subject to FIT)

Dec 2016

Dec 2017

PERMITS AND OTHER REGULATORY REQUIREMENTS:


BREOC No. 2011-01-013
ECC, LGU, Land Use Permit
Secured Clearance from DOE for the conduct of GIS on 21 July 2011
Issued Certificate Confirmation of Commerciality on 2 Sept 2013
GROUNDBREAKING SCHEDULES:
Groundbreaking on 12 Oct 2013

Committed

SJCiPower Rice Husk-Fired


Biomass power Plant
Project Phase 2

San Jose City I Power


Corporation

FINANCING ARRANGEMENTS:
Project Cost Php1.234B
Brgy. Tulat, San Jose, Nueva Ecija

10.8
CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:
EPC w/ Engcon of Singapore
Pre-construction (100% completed as of 31 August 2014 );
Phase I - Estimated Accomplishment of Construction 98 % completed as of 31 August 2014 )
Remaining major equipment in-progress is the installation of travelling gate
On-going installations of the feed water piping system, chemical dosing pipeline, three control elements of the boiler and other field instruments
Expected arrival of switchyard is on May 2014
Interconnection (100% completed as of 31 August 2014 )
On-going construction as of 30 September 2014
Pre-Construction - 100%; Construction-98%; Interconnection-100%)
10

Battery

PERMITS AND OTHER REGULATORY REQUIREMENTS:


Secured GIS on June 2, 2015; COE issued 16 December 2015 (10MW BESS)
GROUNDBREAKING SCHEDULES:
Ground breaking ceremony 15 December 2015
Committed

AES Battery Storage Masinloc Project

AES Philippines Power


Partners Co., LTD.

Masinloc, Zambales

10

CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:


Construction on going
COMMENCEMENT OF CONSTRUCTION:
Target Commencement of Construction: June 2016

Total Committed Rated Capacity

* Committed Project(s)
COAL
DIESEL / OIL
NATURAL GAS
GEOTHERMAL
HYDROPOWER
SOLAR
WIND
BIOMASS
BESS

4001.375

2720
1100
43
62.5
52.975
0
22.9
10
4001.375
TRUE