PWD 203a
PWD 203a
Variation
Valuation of variation
All variation instructed in writing by
the S.O in accordance with clause 24
hereof shall be measured and valued
by the S.O. the valuation of variations,
unless previously or otherwise agreed,
shall be made in accordance with the
following rules:
a) The rates in the bills of
quantities after adjustment if
necessary as provided in
clauses 26.6 and 26.7 hereof,
shall determine the valuation of
work of similar character and
executed under similar
conditions as work priced
therein
b) The said rates, where work is
not of similar character or
executed under similar
conditions as aforesaid, shall be
the basis of rates for the same,
so far as may be reasonable,
failing which a fair valuation
thereof shall be made by the
SO
c) The rates in the bill of
quantities shall determine the
valuation of items omitted,
provided that if the omission
substantially vary the
conditions under which any
remaining items of work are
carried out, the rates of such
remaining items shall be valued
under rule (b)
PAM
Variation
All variation shall be measured and
valued by the quantity surveyor. Where
any recording of site information and/or
site measurements are carried out at the
site, the contractor shall provide the QS
with such assistance as may be
necessary to carry out the works and the
contractor shall be given the opportunity
to be present to take such notes and
measurements as he may require.
The valuation of variation and work
executed by the contractor for which a
provisioanal quantity is included in the
contract and expenditure of provisional
sums shall be made in accordance with
the following rules:
a) Where work is of a similar
character to, is executed under
similar conditions as, and does not
significantly change the quantity of
work as set out in the contract
documents, the rates and prices in
the contract documents shall
determine the valuation
b) Where work is of a similar
character to work as set out in the
contract document but is not
executed under similar conditions
but there is a sifnificant change in
the quantity of work carried out,
the rates and prices in the contract
documents shall be the basis for
determining the valuation which
shall include a fair adjustment in
the rates to take into account such
difference
c) Where work is not of a similar
character to work as set out in the
contract documents, the valuation
shall be at fair market rates and
prices determined by the QS
Extension of time
Extension of time
43.1Upon it becoming reasonably apparent that
the progress of the Works is delayed, the
Contractor
shall forthwith give written notice to the S.O
as to the causes of delay and relevant
information
with supporting documents enabling the
said officer to form an opinion as to the
cause
and
calculation of the length of delay. If in the
opinion of the S.O the completion of the
Works
is
likely
to be delayed or has been delayed beyond
the Date for Completion stated in Appendix
1
or
beyond any extended Date for Completion
previously fixed under this Clause due to
any
or
more
of the following events:
(a) force majeure as provided under
clause 58;
(b) exceptionally inclement weather;
(c) suspension of Works under clause
50;
(d) directions given by the S.O.,
consequential upon disputes with
neighbouring owners
provided the same is not due to
any act, negligence or default of
the
Contractor
or
any
sub-contractor,
nominated
or
otherwise;
(e) S.O.s instructions issued under
clause 5 hereof, PROVIDED
THAT
such
instructions
are not issued due to any act,
negligence, default or breach of
this
Contract
by
the
Contractor or any sub-contractor,
nominated or otherwise;
(f) the Contractor not having received
in due time instructions in regard
to
the
nomination
of
sub-contractors and/or suppliers
provided
in
this
Contract,
necessary
instructions,
drawings or levels for the
execution of the Works from the
S.O. due to any negligence or
default of the S.O. PROVIDED
THAT the Contractor shall have
specifically
applied
in
writing on a date which having
regard to the Date for Completion
stated
in
Appendix
or
to any extension of time then fixed
under this clause, was neither
unreasonably
distant
from nor unreasonably close to
the date on which it was
necessary for him to receive the
same;
(g) delay in giving possession of the
Site as provided under clause
38.4
hereof
other
than
claim in effecting insurance and
Performance Bond;
(h) delay on the part of artists,
tradesmen or others engaged by
the
Government
in
executing work not forming part of
this Contract;
(i) the Contractors inability for reason
beyond his control and which he
could
not
reasonably have foreseen at the
date of closing of tender of this
Contract
to
secure
such
goods, materials and/or services
as are essential to the proper
carrying
out
of
the
Works; or
(j) delay on the part of the Nominated
Sub-contractors
and/or
Nominated
Suppliers
to
perform their works, due to
reasons as stated above in subclauses (a) to (i),
Works.
PROVIDED THAT all such delays are not
due to any act, negligence, default or
breach
of
contract by the Nominated Sub-contractor
and/or Nominated Supplier and/or the
Contractor,
or
any of the servants or agents of such
Nominated Sub-contractor or Nominated
Supplier
or
the
Contractor.
satisfaction of
the Architect to prevent and reduce delay
or further delay in the completion of the
Works
beyond the Completion Date.
The Architect shall notify every
Nominated Sub-Contractor in writing of
each decision of
the Architect when fixing a later
Completion Date.
Site representative
Unless otherwise provided elsewhere
in this Contract, the Contractor shall
keep constantly on the
Site a competent, efficient, suitability
qualified, experienced and good
character site agent and
Fluctuation of price
Possession of site
38.1 No work under this Contract
shall commence unless and until the
Performance Bond stipulated
under clause 13 and such insurance
policy as specified under clauses 15
and 18 shall have been
Site representative
8.1
The Contractor shall appoint
a competent person to be the Site Agent.
The Site Agent for
the purposes of the Contract shall be
deemed to be the Contractors
authorised site
representative. The Site Agent shall be
assisted by such assistants and
supervisory staff as
necessary to execute the Works
efficiently and satisfactorily. The Site
Agent shall be
employed full time on Site and in the
event that he has to be temporarily
absent from the
Site, the Contractor shall designate a
deputy in his place.
The Contractor shall ensure that the Site
Agent and such assistants and
supervisory staff are
capable of receiving directions or
instructions in English or Bahasa
Malaysia. The Site
Agent shall be deemed to be authorised
by the Contractor to receive any
directions given by
the Site Staff or instructions given by the
Architect and any such directions and
instructions
given shall be deemed to have been
Possession of site
relevant
certificates and/or vouchers to prove that
the materials and goods comply with the
Specification.
35.2The Contractor shall, entirely at his own
cost, provide samples of materials and
goods
for
testing
purposes. The Contractor shall, when
instructed by the S.O. to open up for
inspection
any
work
covered up, or arrange for or carry out any
test of any materials or goods (whether or
not
already
incorporated in the Works) Or of any
executed work which the S.O. may in
writing
require
and
the
cost of such opening up or testing (together
with the cost of making good in
consequence
thereof) shall be added to the Contract Sum
unless provided for in the Bills of Quantities
by
way
of Provisional Sums or otherwise or unless
the inspection or test shows that the work,
materials
or goods are not in accordance with this
Contract.
35.3The Contractor shall pay all duties and
taxes which may be imposed by law, such
as
customs
duties and sales tax, on all materials, goods
and equipment, whether purchased or
imported
in
the Contractors name or his agent, which
are incorporated in the Works or used
directly
in
the
construction, completion or maintenance of
the Works.
35.4Except where otherwise specified, the
Contractor shall pay all tonnage and other
royalties,
rent
fees and other payments or compensation
(if any) for getting stone, sand, gravel, clay
or
other
materials required for the Works.
Workmanship
All works, materials, goods and
workmanship shall be of the respective
quality and
standards described in the Contract
Documents and required by the Architect
in accordance
with the provisions of the Contract.
The Contractor shall upon the request of
the Architect, provide him with vouchers
or such
other evidence to prove that the
materials and goods comply with Clause
6.1.
The Contractor shall provide samples of
materials and goods for testing before
incorporation into the Works. The
Architect may issue an AI requiring the
Contractor to
open up for inspection any work covered
up, or to arrange for or carry out any test
on any
materials and goods already incorporated
in the Works or of any executed work.
The cost
of such opening up or testing together
with the cost of making good shall be
added to the
Contract Sum unless:
6.3(a) the cost is provided for in the
Contract Bills;
Termination of contract
Termination of contract