S.No Item Description Start Date Finish Date Status As On 02.04.2016 1 Walkway Around Buildings

This document provides a status update on the completion schedule for various civil works items for the Juaymah 380kv BSP project as of April 2, 2016. Key items include: GIS and control room buildings that are over 85% completed; 95% completion of communication duct banks; 65% and 55% completion of raft and wall concrete respectively for fire hydrant trenches; 90% completion of MV and LV duct banks; and ongoing work for other items like the SSD fence system, crash barriers, base course laying, asphalt pavement, and slope protection concrete, with estimated completion dates ranging from mid-May to end of June 2016.

Uploaded by

Tori Small
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
89 views2 pages

S.No Item Description Start Date Finish Date Status As On 02.04.2016 1 Walkway Around Buildings

This document provides a status update on the completion schedule for various civil works items for the Juaymah 380kv BSP project as of April 2, 2016. Key items include: GIS and control room buildings that are over 85% completed; 95% completion of communication duct banks; 65% and 55% completion of raft and wall concrete respectively for fire hydrant trenches; 90% completion of MV and LV duct banks; and ongoing work for other items like the SSD fence system, crash barriers, base course laying, asphalt pavement, and slope protection concrete, with estimated completion dates ranging from mid-May to end of June 2016.

Uploaded by

Tori Small
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

Balance Civil works Completion Schedule for Juaymah 380 kv BSP project

S.No

Item Description

Date : 30.04.2016

Start date

Finish date

Status as on 02.04.2016

1
1.1
1.2

Walkway around buildings


380kV GIS building - 94% completed and balance
230kV GIS building - 88% completed and balance

work is in progress
work is in progress

31.03.2016
31.03.2016

96% Completed.
95% Completed.

1.3

Control room buiding - 85% completed and balance

work is in progress

07.04.2016

85% Completed.

Communication duct bank and CMH/ CHH - 95% completed.

2.1

Duct bank between CMH 1 to CMH 3 - 85 % Completed.

30.03.2016

100% Completed.

2.2

Duct bank between CMH 2 to Guard house

07.04.2016

Yet to start

05.04.2016

65% completed.

3
3.1

Fire Hydrant trench - 1100 RM


Fire hydrant trench - Raft concrete - 65% Completed.

work is in progress

1000 RM raft concrete completed out of 1100 RM


3.2

Fire hydrant trench - Wall concrete - 55% Completed.

90% completed
work is in progress

20.04.2016

800 RM wall concrete completed out of 1100 RM

55% Completed.
75% completed

MV and LV duvt bank - 90% completed and balance

work is in progress

07.04.2016

90% Completed.

Pump house - room readiness.

work is in progress

20.04.2016

65% completed.

SSD 1 fence system.

work is in progress

30.04.2016

Corner 3 to 4 beam concrete 20% completed


Corner 3 to 4 post fixing work 100% completed
Corner 1 to 4 wire mesh fixing work 75% completed
Corner 1 to 2 wire mesh fixing work 15% completed

Corner 1 to 2 post fixing work 60% completed


Corner 2 to 3 beam lean preparation work in progress(Part-1)
8

Crash Barrier.

work is in progress

30.04.2016

Work is in progress

10.05.2016

207 nos completed out of 274


9

40% completed. Balance


is in progress.
75% completed. Balance
is in progress.

Base coarse laying and compaction


Base coarse laying and compaction 100% completed at part
1,2&3 area
Base coarse laying and compaction 50% completed at part 4
area

40% completed

Base coarse laying and compaction 25% completed at part 10


area
Select fill compaction in progress at part 5 area
10

Asphalt pavement for substation yard area

11

Slope protection concrete

Work is in progress

01.06.2016

22.05.2016

01% completed

30.06.2016.

0% completed