Bid Data Sheet (BDS) : Section - Iii
Bid Data Sheet (BDS) : Section - Iii
TSFP
Section - III
Page - 1 / 14
SECTION III
INTRODUCTION
ITB 1.1
ITB 1.1
ITB 2.1
Name of Employer:
Tendaho Sugar Factory Project,, P O box 2574, Salfaz building (in
front of Atlas hotel), Cape Verde road, Addis Ababa, Ethiopia
ITB 2.4
ITB 3.2
ITB 6.1
City:
Country:
TEL:
Section - III
Page - 2 / 14
ITB 6.4
Date:
Time:
09:00 h
PREPARATION OF BIDS
ITB 8.1
Section - III
Page - 3 / 14
Item of equipment
Description, make, and age (years)
Condition (new, good, poor) and number available
Owned, leased (from whom?), or to be purchased (from
whom?)
Position
Name
Qualifications
Type of experience in similar functions
Years of experience (general)
Years of experience in proposed position
Section - III
Page - 4 / 14
Section - III
Page - 5 / 14
ITB 11.3
Schedule No. 2
Schedule No.3
Schedule No. 4
Ocean Transportation
Schedule No. 5
Local Transportation
Section - III
Page - 6 / 14
Schedule No. 6
Schedule No. 7
Schedule No. 8
Bidders shall note that the plant and equipment included in Schedule
Nos. 1 and 2 above exclude materials used for civil, building and
other construction works. All materials required for installation and
other purposes shall be included and priced under Schedule No. 6,
Installation Services.
ITB 11.4 (a)
i)
ii)
iii)
i)
ii)
iii)
ITB 11.6
Section - III
Page - 7 / 14
ITB 13.2
ITB 14.1
Bid validity period 120 days from the date of bid opening.
ITB 16.1
Bidders shall not have the option of submitting their bids only
electronically but with hard copies as indicated under BDS 15.1.
ITB 17.1
City:
Country:
Addis Ababa
Ethiopia
TEL:
Fax:
Email:
[email protected]
[email protected]
Section - III
Page - 8 / 14
Contact person:
ITB 22.5
Bid Responsiveness
Responsiveness are those important points which conform to the
major conditions set out in the Bid, without which, the Bid is
considered as non-responsive and will not be considered for further
evaluation. Following six points are considered under this category.
Table-1 below is to be filled for marking Yes I No against each
points for each Bidder.
Table- 1
Sl. No.
1
2
3
4
5
6
Description
Bid form
Bid security and its validity
Bid validity
Scope of work including amendments
Technical data
Price schedule
Bidder # 1
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Section - III
Page - 9 / 14
ITB 23.2
ITB 24.1
80
20
----100
Technical Evaluation
The technical evaluation shall be carried out in the following four
major categories:
1) Technical specification which covers Technical specification,
Technical Schedule, Drawings and flow diagrams, Scope of
work, Terminal points of supply, Performance Parameters,
Erection and Commissioning, etc.
2) Project Time Schedule
3) Training
4) Bidders Company Structure & Profile which includes
Company reputation, Financial position, Shop facility and set up,
Key personnel CV, Experience in similar jobs, Document
presentation, Resource Level, Quality plan, Confidence in
method statement, understanding the requirement, etc.
Following merit point system shall be followed for Technical
Evaluation. Upon completion of evaluation, the marks will be
corrected to level of 80 from 200.
Section - III
Page - 10 / 14
Sl.No
Description
1.
1.1
1.2
1.3
1.4
1.5
Technical Specification
Technical Schedule
Drawings / Flow Diagrams
Terminal points of supply
Performance parameters
Erection & Commissioning
2.
3.
4.
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
Max.
Marks
Sub Total
Sub Total
Total Score (1+2+3+4)
Technical evaluated score corrected to 80
20
25
25
10
15
25
100
10
10
5
10
5
10
15
5
5
10
10
5
80
200
80
ITB 25.2
Evaluated Price
A)
Section - III
Page - 11 / 14
evaluation purpose.
ii)
For those figures, which were not filled by the bidders, the
corresponding maximum value of other bidder shall be filled for
evaluation purpose.
iii)
=
=
=
=
xxxxx
xxxxx
xxxxx
xxxxx
-------xxxxx
--------
20 x [1 (P P min)/Pmax ]
Section - III
Page - 12 / 14
Where,
P
Pmin
Pmax
Particulars
Max. Marks
Bidder #
Evaluated Price
Financial Evaluated score
3.0
20.00
xx . xx
Particulars
Max. Marks
Bidder #
80
20
xx . xx
xx . xx
100
xx . xx
4.0
Winning Bidders
Award of Contract
The 1st successful and qualified bidder shall be invited for AWARD
OF CONTRACT.
ITB 25.3 (b)
Time schedule:
Time to complete the facilities from the effective date specified in
Article 3 of the Contract Agreement for determining time for
completion of pre-commissioning activities shall be as under.
a)
Section - III
Page - 13 / 14
period shall be 0.2 % for each week of delay from that minimum
period.
In case of earlier delivery, a credit of 0.2% per week will be given
counting from minimum period.
ITB 25.3 (c)
ii)
iii)
iv)
i)
ii)
iii)
iv)
B)
i)
Section - III
Page - 14 / 14
ii)
iii)
iv)
The following adjustment factors will be used for the process house
in both options.
a) Addition of US Dollars 100,000 for each one percent [1%]
reduction in throughput or prorated for less than one
percent [ 1% ] of capacity indicated above
b) Addition of US Dollars 100,000 for each half percent [0.5 %]
reduction in reduced process house recovery or prorated for
less than one half percent [ 0.5 % ] of reduced process
house recovery indicated above.
c) Addition of US Dollars 50,000 for each half percent [0.5 %]
reduction in refinery yield or prorated for less than one half
percent [ 0.5 % ] of refinery yield indicated above.
d) Addition of US$ 5000 / 100 kW excess power consumption
when compared to the bid with lowest power consumption
within the battery limits.
Nil
CONTRACT AWARD
ITB 33