Scope Document
&
Concept Design
1 | Page
MM purchasing will be implemented for the Delhi office, which will integrate with other
Gujarat.
The SAP implementation team at both locations are discussing whenever required to
maintain the consistency and the integration of the business processes.
ABC will implement SAP R/3 without modifying any of the business processes of SAP R/3.
This in IT term will mean, the implementation team will not change any table or source code
which will touch the core design of the R/3 system.
ABC, thus will take advantage of the best business practice available with SAP and are being
used world-wide by 10,000 plus organisations. Also as SAP comes with regular upgrades
periodically, the implementation of such upgrades will be structured by SAP and thus be
nearly seamless from ABCs view point. The changing business scenario necessitates
new/additional business processes regularly. Also the technology developments changes the
way the business is carried out. Upgrades release periodically by SAP incorporates
additional business processes which are adopted as best practices and the technology
enhancements.
Any modification of the SAP code and/or table structure will make upgrades very involved
and rework.
2 | Page
Users of ABC (including Management) will access information directly from the R/3 system.
The system has excellent drill-down facilities and information can be traced from higher
levels to the source because of the tight integration. In addition R/3 system has number of
standard reports which can be displayed.
The SAP Implementation team will develop any specific reports which were earlier used for
internal purposes. The on-line information and standard SAP reports will meet the
requirements of earlier specific reports. However the presentations of the information will
now be different and ABC will make this as one of the change management point.
The R/3 System being completely integrated, information generated by a function or process
(department) will have immediate effect on other processes. The access to the information
either for create, change or display will through authorisation process. ABCs IT team has
been trained for the authorisation functions. The authorisation for the users from
Ahmedabad will be given by ABC s IT team at Ahmedabad. Training for the teams both for
Ahmedabad and Delhi has thus been provided.
The R/3 implementation scope is being categorised as:
Need to have
Nice to have
The go-live date will take only the need to have as the defined requirements and the
requirement s documented are only of the need to have categories. All nice to have
processes/functions will be excluded from the scope. They may be selectively taken for
implementation if the schedule for go-live permits the same.
XYZ along with SAP implementation team is committed to complete the implementation at
ABC within the target date. ABC and XYZ will provide all necessary resources to achieve the
same. Milestones will assessed through regular reviews with the ABC management.
3 | Page
Organizational Unit
Enterprises Structure:
Company code
Plants assigned to Company Code
Storage location assigned to Plant(s)
Purchasing organisation assigned to plant
MM-Material Management
MM Purchasing
MM Vendor Evaluation
MM Inventory Management
MM Invoice Verification and Material Valuation
MM Consumption-Based Planning
QM Quality Management
QM Procurement
Information System
Purchasing Information System
Inventory Controlling
4 | Page
Streamline the Purchase Process at ABC, Delhi using the best business practices in SAP
followed by thousands of Organisations worldwide.
To automate the existing process and get the incidental benefits of process re-engineering
using SAP implementation as a roadmap/template.
To achieve a seamless integration with other logistics and accounting modules like sales
and distribution module and accounting and controlling module, and thereby improve the
efficiency and effectiveness of business processes.
To achieve a site level material control, this is today carried out manually.
Benchmarks:
5 | Page
This document covers the business processes of purchasing from Delhi, which currently is
handling purchasing of:
All project related (purchases not used for manufacturing by Ahmedabad)
Capital items
Administrative items
The scope of the MM-purchasing will give only reference of inventory at site by a tracking
number. The scope excludes the complete site inventory management, as R/3 material
management does not provide this functionality unless integrated with the project system
module. The MM- purchasing implementation scope does not include project system and
6 | Page
For logical purpose, the business blueprint is structured to be represented in the following
approach:
Organizational Unit
Enterprise Structure
Company Code
Plants assigned to company code
Storage locations assigned to plant(s)
Purchasing organization assign to plant
LO Logistics General
LO Managing Material Master Data
Organizational Unit
Enterprises Structure:
Company code
Plants assigned to Company Code
Storage location assigned to Plant(s)
Purchasing organisation assigned to plant
MM-Material Management
MM Purchasing
MM Vendor Evaluation
MM Inventory Management
MM Invoice Verification and Material Valuation
MM Consumption-Based Planning
QM Quality Management
QM Procurement
Information System
Purchasing Information System
Inventory Controlling
7 | Page
Organizational Unit
Describe the current or the planned organizational units that have one of the following roles
within the enterprises.
Financial Accounting
Reporting responsibility
Balance Sheet (Internal/external)
Profit & loss statement (Internal/external)
Costs and profits
Stock responsibility
For invested capital (assets and material stock)
For bank accounts
Responsibility for running operation
Logistics
Responsibility for inventory management
Volume of material stock
Requirements planning
Material Valuation
Planning responsibility
Sales
Production
Responsibility for procurement
Vendor selection
Control management
Responsibility for sales
Processing customer orders
Creating customer billing documents
Defining sales and transfer prices of products
8 | Page
Central Functions
Mater data maintenance
The structure of the plants in R/3 is based on the structure of the company codes, since
plants must always be assigned uniquely to one company code. These assignment enables
material stock changes to be updated correctly to the G/L accounts in the G/L accounting
system.
The basic structure of the plants in R/3, which is determined by the requirements for
external accounts rendering, can be refined to ensure that the more stringent
requirements of the internal accounting or logistic systems are fulfilled.
The requirements for production planning and inventory management, in particular, must
be taken into account when the plants are defined and the business and plant location
structures of the enterprise are mapped in the R/3 architecture.
Production Planning:
One of the main requirements, from a production planning point of view, is the ability to
perform standardized, independent detailed production planning for areas of an
enterprise that have a high degree of integration from a production prospective.
An enterprises has a high degree of integration with regard to production over various
locations. Standardized detailed production planning is to be performed at a global level
for the various business locations of the enterprises. In this case, a cross-location plant
is created. In R/3, the locations within the plant are represented
o
o
An enterprise would like to carry out independent, detailed production and material
requirements planning for the various plant locations in a business location. In this
case, a plant can be set up in R/3 for each plant location in the business location.
General production planning can be carried out for all of the plant locations in a
business location or across all business locations.
In both cases, the effect on the logistic business processes and the strategic information
flows from the logistics to the accounting structures must be investigated. In the first
case, the compatibility of this solution with the relevant legal provisions (transport
papers etc.) must be ensured.
9 | Page
Inventory management
Precise assignment of the current assets (raw materials, semi-finished and finished
products) to the strategic business units and business locations of the enterprises can
often be an essential requirement with regard to inventory management. This
assignment is a prerequisite for determining management numbers, such as return on
investment, cash flow, and so on, which are used to assess the performance of the
various strategic business units and locations of an enterprise. Issues relating to
materials planning and the availability of materials can represent additional factors that
determine plant structure design.
In order to define plant structures from the point of view of inventory management, it is
essential to determine how the materials are used in a company. In this context, the
business area specific use of materials and the cross business unit use of materials play a
crucial role.
10 | P a g e
Plant oriented
Cross plant, within a company code
Cross company code
Cross system (in distributed system topologies only)
Assume that a business unit specific plant structure has been defined for the
enterprises. A separate purchasing organisation can then be created for each
plant. Furthermore, a cross-plant purchasing orgainsation can be created for
each legal entity, that is each company code. A central, cross company code
purchasing organisation is responsible for cross entity procurement.
11 | P a g e
Location
Guj
Guj
Guj
Delhi
Company Code
ABC
ABC
ABC
ABC
12 | P a g e
Assigned to plants
Ahm1, Ahm2, Ahm3
Ahm1, Ahm2, Ahm3
Ahm1, Ahm2, Ahm3
Ahm1, Ahm2, Ahm3
Ahm1, Ahm2, Ahm3
Ahm1
Ahm1, Ahm2, Ahm3
Ahm1, Ahm2, Ahm3
Ahm1, Ahm2, Ahm3
Del
The material master is the companys central source for retrieving material specific
data. It is used by all the components in the SAP Logistics System.
In the SAP logistics system, the data contained in the material master is required,
for example, for the following functions:
In
In
In
In
In
of tables.
Example: group
Company code:
13 | P a g e
Plant:
Storage location:
Purchasing organisation:
conditions
of
purchase
with
vendors,
and
is
Sales organisation:
Warehouse number:
An alphanumeric key defined a complex warehousing system
consisting of different organizational and technical units (storage
areas).
14 | P a g e
Storage type:
15 | P a g e
Material Type:
Materials with the same basic attributes are grouped together and assigned to a
material type. This allows you to manage different materials in a uniform
manner in accordance with your companys requirements. Examples of
materials types are raw materials, semi-finished products and finished
products.
When creating a material master record, you must assign the material to a
material type. The material type determines certain attributes of material and
has important control functions. For example, it is a factor determining the
screen sequence and field selection in a material master record.
The material type defines:
The material type also determines the materials procurement type, that is,
whether a material is manufactured in-house or procured externally, or both.
Together with the plant, the material type determines the materials inventory
management requirement, that is:
Whether changes in quantity are updated in the material master record.
Whether changes in value are also updated in the FA (i.e. financial
accounting) stock accounts
The accounts affected by a material entering or leaving the warehouse depend
on the material type.
Material Group:
Material groups allow to group together materials with the same attributes.
Material group can be used to:
16 | P a g e
Material Master
Material (Code) for project related, capital and Auxiliary items relevant for Delhi
The Material (code) will be internal nos.
o Decision on internal Nos. was arrived at:
The SACH No. assigned by XYZ is not completely available and hence
system will generate the material no. wherever the Sach Nos. are not
available.
Each material will be assigned to the following objects (for relevant material
type) from the Enterprise structure finalized:
Plant
Storage location
Purchasing organisation
Sales organisation
Storage type
Material Type
SAP standard material types will be used and assigned to each material.
An additional material type (AUXM) is created for auxiliary items.
The following material types will be used for ABC, Delhi purchase
For all material purchases, material type HIBE will be used.
For all services procured, material type DIEN will be used.
Material Type : HIBE Description: Bought out Material
Views relevant : Accounting
: MRP
: Purchasing
: Basic Data
: Quality Management
: Sales
: Plant stock
17 | P a g e
Numbering followed for ABC purchases will be internal, system generated, in case the
SACH number is not available.
Material type
Price Control
: Moving Average
Quantity updating
: Not Relevant
Value updating
: Not Relevant
Numbering
18 | P a g e
19 | P a g e
View relevant
: Accounting
: MRP
: Purchasing
: Basic Data
: Sales
: Quality Management
Quantity updating
: Not Relevant
Value updating
: Not Relevant
Numbering
20 | P a g e
Material type
Manufactured
Procured
in-house
Externally
Bought out(HIBE)
Yes
Services(DIEN)
Yes
Auxiliary (AUXM)
Yes
Both
Together with the plant, the material type determines the materials inventory
management requirement:
For the plant Delhi no material type will update inventory
Changes in value will update in the FA (Financial Accounting) accounts
The accounts affect by a material entering or leaving the warehouse depends on the
material type.
Material Type
For Account assigned
Bought-out (HIBE)
Auxiliary (AUXM)
Services (DIEN)
Price Control
Purchase Order
S
S
S
Accounts
Account
On Receipts
On Issue
42100
Multiple
42100
Not Relevant
Not Relevant
Not Relevant
Opening/Closing stock account and updates for the closing stock balance at period
end will be provided by the account department of ABC.
Material Group
To be finalized by Delhi.
21 | P a g e
The logistics chain will start at sales and distribution and with demand
management.
In sales and distribution, the sales orders containing concrete customer
requirements will be received. The sales order will enter with the details of the
functional modules.
In order to cover the requirements of the confirmed sales order and forecast, the
reorder quantities and dates will be calculated as well as the corresponding
procurement elements. The procurement element in the planning run is the
planned order, or for external procurement, the purchase requisitions. Both
procurement elements are internal planning elements are internal planning
elements that can be changed, rescheduled or deleted at any time.
Planning Strategies
Make to stock production (10/11)
Planning without final assembly (50)
Make to order production (20)
For the materials produced in house, the system will calculate the dependent
requirements, or the quantity of components required to produce the finished
product or the assembly, by exploding the BOM (i.e. bill of material). If a
material shortage exists, planned orders will be created at every BOM level to
cover requirements.
The progress of the order for materials produced in house will be controlled using
the production order. The production order will contain its own scheduling
procedures, capacity planning and status management. Cost accounting will be
also carried out via the individual production order.
22 | P a g e
Materials that are procured externally will trigger the procedure for purchasing. In
this case, suitable vendor will be chosen or outline agreements will be drawn up.
Planning run
The types of planning run that will be used are:
Net change planning (NETCH)
Net change planning in the planning horizon (NETPL)
The other type which will be used at the time of going live or in the event of
exceptional cases is:
Regenerative planning (NEUPL)
The planning file will contain a list of all materials relevant to the planning run.
This means that as soon as a material master record is created with MRP data
and a valid MRP type, this material is then automatically included in the
planning file.
When starting the planning run, it is defined whether all the materials that are
in the planning file are to be planned or net change planning is to be carried
out:
In a regenerative planning run, the system will plan all the materials that
are contained in the planning run
In a net change planning run, the system will only plan materials that
have undergone a change relevant to MRP since the last planning run
For the net change planning procedure, if a material is changed in any way that
is relevant to the planning run, it will be flagged with a total change indicator in
the planning file. The indicator will set by the system as soon as the material is
changed. The changes that will be relevant to the planning run will include:
Changes to stock, if these change the stock/requirements situation of the
material
23 | P a g e
forecast
requirements,
dependent
requirements
or
reservation
If fields are changed that are relevant to the planning run for these
receipts and issues or in the material master record
Deleting receipt or issue quantities
A planning horizon can be used to further limit the scope of the planning run.
In net change planning in the planning horizon, the system will only plan
materials that have undergone a change that is relevant to the planning run
within the period defined as the planning horizon. If a planning horizon is
specified, the system will set another indicator in the planning file if a material
is changed within the planning horizon, the net change planning indicator.
During the planning run, the system will check every entry for a material in the
planning file:
In a regenerative planning run, the system will plan all materials, which are
included in the planning file irrespective of all indicators.
In a net change planning run, the system will only plan those materials,
which are provided with the total change indicator.
In a net change planning in the planning horizon, the system will only plan
those materials provided with the net change planning indicator.
On completion of the planning run, the appropriate indicator will be
automatically deleted in the planning file.
The system will delete the total change indicator and the net change
indicator for a regenerative planning run and a net change planning run
The system will only delete the net change planning indicator for a net
change planning run in the planning horizon
requirements,
customer
requirements,
dependent
customer
requirement,
planned
independent
requirement,
requirements
planning
will
initiated
by
planning
with
the
25 | P a g e
controller. The MRP list will be stored in the system until it is either deleted
manually or replaced by a new list from subsequent planning run.
The system will display one of the selected options:
plant
Collective display with selection according to MRP controller, plant and
further selection criteria
Stock/requirements list
In the stock/requirement list, the most up to date development of stocks
and requirements is displayed. The layout of the list on the screen is the
same as that of the MRP list.
The main difference between the MRP list and the stock/requirements list is
that each time the stock/requirements list is called up, the system re-reads
the various MRP elements and displays the most up to date situation. As a
result the most recent availability situation for the material in the
stock/requirements list whereas the MRP list reflects the stock and
requirements situations situation at the time of the last planning run.
Changes, which have taken place after the planning date, are not included.
Calculating Basic Dates Using Backward Scheduling
For materials that are planned according to either the MRP or the
forecast based planning procedures, the requirement dates are always
known.
Finally, the opening period is subtracted from the order start date and
the result is the order opening date. The opening period represents the
time required by the MRP controller to covert the planned orders into
purchase requisitions. It is determined in customizing per plant as a
float.
26 | P a g e
27 | P a g e
planning)
Discounted Parts
Using Alternative and substitute parts
Easy to use functions for evaluating the planning result
Exception messages and rescheduling check
Availability check
Single and Multi level pegging
Single item planning for sales orders
and
consumption
based
Client
Currently: Test client= 400, Live client =120
Purchasing organisation
o At AHM
AHP1= Ahmedabad purchasing organisation for all plants in
Gujarat.
At Delhi
DPO1= Delhi purchasing organisation for all plants (Currently
Purchasing Group
o Each Buyer will be a purchasing group for Delhi plant
Assignment of organizational levels
o All the plants at Delhi (Currently only Delhi) are assigned to one
Purchasing Organisation.
o
28 | P a g e
Purchasing document
Scheduling
agreement:
Another
type
of
outline
agreement,
29 | P a g e
PRG
QPG
QCG
POPG
POCG
POXG
CVG
CQG
:
:
:
:
:
:
:
:
Delhi
o
PRG
QPG
QCG
POPG
POCG
POXG
CVG
CQG
:
:
:
:
:
:
:
:
2000000 to 2999999
6200000 to 6299999
6200000 to 6299999
4700000 to 4799999
4700000 to 4799999
4800000 to 4899999
4800000 to 4899999
4800000 to 4899999
o
30 | P a g e
o
o
o
o
contain
quotation
(wherever
31 | P a g e
Automatically
Through
setting
the
info
update
indicator
when
requisition
item
or
external
purchasing
The release code (denoting a release point) is a twocharacter ID allowing a person to release (clear, or
approve) a requisite item or an external purchasing
document. Who may work with which release codes is
basically controlled via a system of authorizations.
32 | P a g e
approval
by
the
department
manager
is
Condition technique
The condition technique is used to determine prices across
applications. The goal of the condition technique is to
calculate the effective price in a purchase order.
The condition technique consists of four main elements:
33 | P a g e
Condition types
Condition tables
Access sequences
Calculation schema (pricing procedure)
Access sequence
An access sequence is a search strategy that the system
uses to find condition records for a particular condition
type.
The access sequence determines the sequence in which the
system searches condition records for a valid price.
34 | P a g e
Prices
Maintain the conditions that determine the net price in a
single info record or contract.
35 | P a g e
Acknowledgments
Confirmations: General procedure
MRP initially will assume that delivery will be in accordance with the
data in the delivery schedule.
36 | P a g e
As soon as another confirmation is received, all the old data from the
preceding confirmation will be deleted and replaced by the data of the
current confirmation.
37 | P a g e
C1
38 | P a g e
It also access basic data in Material Management, such as goods receipt data
from inventory management.
The vendor evaluation system supports the optimization of procurement
processes in the case of both materials and services.
main criteria.
The main criteria available in the standard system are:
Price
Quality
Delivery
General service/support
These four main criteria serve as a basis for the evaluation of vendors
from whom materials are procured.
External Service
This main criterion serves as a basis for the evaluation of vendors
employed as external service providers.
39 | P a g e
Analyses
The results of vendor evaluation are displayed in the form of analyses.
Ranking lists of the best vendors according to overall score of ranking
lists for specific materials will be displayed by the system.
40 | P a g e
For each goods movement a document will create which is used by the
system to update quantities and values and serves as proof of goods
movements.
Physical Inventory
Different physical inventory methods:
Periodic inventory
Inventory sampling
Cycle counting
Inventory management
Inventory management manages the stocks by quantity and value.
Goods Movement
A good movement (also called a material movement or stock movement) will
be an event that will cause a change in stock.
41 | P a g e
Good receipt:
A good receipt (GR) is a good movement with which the receipt of goods
form a vendor or from production will be posted. A good receipt will lead to
an increase in warehouse stock.
Good Issue:
Stock Transfer:
A stock transfer will be the removal of material from one storage location
and its transfer to another storage location.
Transfer Posting:
A transfer posting will be a general term for stock transfers and changes in
stock type or stock category of a material.
Document concept
Accounting principle
Even in a computer supported inventory management system, the accepted
accounting principle of posting only with a document applies. According to the
document principle, a document will be generated and stored in the system for
every transaction/event that causes a change in stock.
Against each posting of a good movement in the SAP System, the following
documents will be created:
Material document
Accounting document
42 | P a g e
Document Numbers
A document numbers and the material document year will identify a material
document. The company code, the document number, and the fiscal year will
identify an accounting document. The material document number and the
accounting document number will be different.
A movement type will be a three digit SAP standard identification key for a
goods movement. The following table contains examples of movement types.
Good Movement
Good receipt for a purchase order
Release from quality inspection
Movement Type
102
342
stock
involved.
The movement relevant for financial accounting, one or more accounting
43 | P a g e
The
invoice
verification
component
will
be
part
of
the
Materials
Management (MM) system. It will provide the link between the Materials
Management component and the Financial Accounting, Controlling and
Asset Accounting components.
It will complete the materials procurement process which start with the
purchase requisition, continues with purchasing and goods receipt and
end with the invoice receipt.
Invoice verification will not handle the payment or the analysis of invoices.
The information required for these processes will be passed on to other
departments.
arithmetic
Executing the account posting resulting from an invoice
Updating certain data in the SAP system, for example, open items and
material prices
Checking invoices that were blocked because they varied too greatly
from the purchase order
The high degree of integration in the SAP system will allow these tasks to be
carried out smoothly and efficiently.
44 | P a g e
Material Valuation
The SAP system consists of various components that are linked, allowing
different departments within a company to work together.
The central task of Material Valuation will be to determine and record the
stock value of a material. The stock value will be calculated using the
following simple formula:
Stock value= stock quantity * material price
Thus, if the stock quantity or the material price changes, the stock value
changes.
In
45 | P a g e
o
o
System settings
Material master records
System Settings
By customizing the SAP system, material valuation will be adapted to
the requirements of company.
o
o
o
The stock quantity and value of a material and the material price will
also recorded in the material master record.
46 | P a g e
The reorder level (also known as the reorder point) will be made up of
the sum of the safety stock plus the expected average material
consumption within the replenishment lead time.
Safety stock must be set at a level, which covers both excess material
consumption within the replenishment lead time and the additional
requirements, which may occur during delivery delays.
The reorder level and safety stock level are central control parameters
within reorder point planning. They can be determined automatically
by the system or manually by the MRP controller. Depending on this
manual or automatic selection, following two procedures will be used:
Manual Reorder Point Planning
Automatic Reorder Point Planning
47 | P a g e
During the inspection process, the inspection lot will become the central
control record that will document the current status of the inspection. It
will be the repository for all inspection data, including the inspection
specifications, inspection results and usage decision.
Inspection Results:
Quality inspections will fulfill a variety of goals. These goals set the
parameters for the type and scope of expected inspection results. These
goals will include:
Determining
whether
products
adhere
to
predefined
quality
process (audit)
Determining the capability of processes, machines or production
resources (capability check)
QM Procurement
The QM module will be involved in the following decision making phases
of the procurement process: inquiry, vendor selection, purchase order,
goods receipt, incoming inspection and release of goods receipt quantity.
Vendor Selection:
The material management (MM) module will inform the purchasing
agent of the vendors delivery reliability and price behavior. The QM
module will provide information on the quality of the previously
delivered goods and the vendors quality management system. For
48 | P a g e
Purchase Order:
When the purchase order is issued, the vendor must have been
released by the quality department to deliver the material in
question (if this requirement has been specified). The release of the
supply relationship may be limited to a specific period of time and a
specified quantity. With the purchase order, the vendor will
automatically receive information about the latest technical delivery
terms and the currently valid quality assurance agreement, as well
as the vendors obligation to include a quality certificate with the
delivery.
Goods Receipt
If a certificate is required for a material, it must be available no later
than when the goods are received. A certificate may be required for
49 | P a g e
appropriate inspection plan and determine the sample size for all
inspection characteristics based on the quality level. The inspection
can now be initiated and the necessary documents, such as the
sample drawing instructions and inspection instructions, can be
printed out.
Quality inspection
When an inspection lot has been processed in the QM module, the
inspector must take a usage decision for the inspected goods. Under
special circumstances, the inspection lot quantity can be withdrawn
from the inspection stock in advance, providing the user has the
proper authorization to make the withdrawal. Normally, however,
the stock posting will take place after inspection completion in
conjunction with the usage decision.
Usage Decision
After the inspection has been completed, the accepted inspection lot
quantity will be posted to unrestricted use stock. A special posting is
possible for rejected quantities. When the goods receipt quantity has
been released, the QM module no longer has the responsibility for
managing the stock.
With the usage decision, the system will update the quality level and
make the inspection lot quality score available for the vendor
evaluation. It will also update all data in the quality information
record relating to material and vendor. For example, the status of the
supply relationship can be changed from prototype delivery to
production delivery, once the inspection lot has been accepted.
Follow-up Actions
After the usage decision has been made, the system may trigger an
additional series of individually programmed follow-up actions. For
example, if defective goods were received, a letter of complaint or a
system-supported quality notification can notify the vendor of this.
50 | P a g e
Vendor Master
The vendor master will contain information about the vendors that a
For procurement and purchasing functions, the system will first check
the vendor master record to determine if the vendor is blocked from
these functions. If the vendor is not blocked, the system will check the
parameters in the Q-info record, if necessary. The settings in the Qinfo record are only checked if a vendor release or quality assurance
agreement is specified in the material master record via the control
key for QM in procurement.
51 | P a g e
transactions
will
update
the
following
G.L.
Accounts/objects:
All purchase orders will be account assigned, to a Cost Center or Sales Order or to an
Asset
MM Transaction
generated manually
Order
Dr. Sales Order (P/L)
against-
Not applicable
Account
Assigned P.O.
Receipt of Capital Items
against-
Account
Assigned P.O.
Receipt of Auxiliary items
against-
w/o
against
P.O.-
Not applicable
Not applicable
Not applicable
Not applicable
Not applicable
Not applicable
No accounting entry
Not applicable
Not applicable
Not applicable
Not applicable
Not applicable
Account
Assigned P.O.
Issue of Project
against
w/o
Account
Assigned P.O.
Receipt of Capital Items
against
Not applicable
Account
Assigned P.O.
Receipt of Project Items
against-
Cr. Provision
items
Account
Assigned P.O.
Issue of Project
items
w/o
assigned P.O.
52 | P a g e
Account
Down
payment
P.O.
Receipt
of
against
Vendors
invoice Retention
Receipt
of
Vendors
Retention
53 | P a g e
Information System
Purchasing Information System:
In the standard system, the following information structures are available in
the Purchasing information system:
o
S012 Purchasing
This information structure forms the data basis for the material groups,
vendors and material analysis.
The analyses for long-term planning are based on planning data, which is
updated to a separate planning version of the information structure S012
from long term planning.
Inventory Controlling:
54 | P a g e
S031 Movement:
All key figures relating to material movements involving current valuated
stock and vendor consignment stock are updated to this information
structure. In the standard system, the period unit in this information
structure is month. You can define your own period unit for the updating
of this information structure.
S032 Stocks:
The current valuated and vendor consignment stocks are updated to this
information structure when a goods movement takes place. The stock
values are also updated to this info structure when a goods movement
and invoice verification/revaluation take place. This information structure
does not contain a period unit.
the
information
structure
S031,
structure
yet
also
S033
is
includes
identical
the
to
the
characteristic
55 | P a g e
S039 Planning
This information structure includes all of the key figures that are
available in inventory controlling, including all of the extra key figures
(range of coverage, inventory turnovers, key figures that are calculated
using the mean value). No actual data is written to this information
structure. This information structure provides the basis for flexible
planning.
If you wish to fill the information structure S039 with actual data, then
you can use the report RMCBS039. It is always advisable to fill the
information structure with actual data if you want to access actual data
for the forecast during planning, or if you want use the flexible analyses
to evaluate the extra key figures from inventory controlling.
standard
analyses
of
stock/requirements.
Data
relating
to
56 | P a g e
57 | P a g e