Pre Comissioning Test of Power Transformer
Pre Comissioning Test of Power Transformer
CONDUCTED IN
APTRANSCO
By
D.SHALINI (08W91A0245)
N.AMALASRI (08W91A0202)
T.AVINASH (08W91A0206)
DEPARTMENT OF EEE
TO
ACKNOWLEDGMENT
Through this acknowledgment, we express our sincere gratitude to all those people who have
been associated with this assignment and helped us and made it worth wile experience. Firstly
we extend our thanks to various people who have shared their opinion and experience through
which we received the required information crucial for our report. Finally we express our sincere
thanks to Sri.Y.Rama Mohan, Assistant Divisional Engineer/MRT and Sri G.Naga Potha
Rao.Assistant Engineer/MRT who constantly guided us through this project sparing their
valuable time in spite of their busy schedule and gave us the opportunity to learn the subject in
practical approach and also we thank Sri.G.Sivaiah, Divisionl Engineer/MRT/TL&SS, Metro
Circle, APTRANSCO, Hyd, who gave us valuable suggestions in completing this project report.
ABSTRACT
A transformer is a static device consisting of a winding, or two or more coupled
windings, with, for inducing mutual coupling between circuits. Transformers are exclusively
used in electric power systems to transfer power by electromagnetic induction between circuits
of different voltage levels, at the same frequency. There are numerous types of transformers used
in various applications including audio, radio, instrument, and power. Now we deal exclusively
with power transformer involving the protection and the pre commissioning tests conducted on
power transformers.
The Pre Commissioning Tests were essential to the start up of any electrical system for
the first time, regardless of its size, type or industry.
An electrical installation work is complete only when the prescribed pre-commission
tests are conducted on different components and the test results are found satisfactory. By
carrying out the pre-commission tests, it is ensured that different components of the system have
their declared specifications/characteristics and also the system is fit for safe and reliable
operation. The pre-commission tests are broadly classified into pre-commission checks meant for
initial inspection covering visual inspection for damages, quality of workmanship, mechanical
operation etc. and the pre-commission tests meant for measurement or testing of various safety
parameters like insulation resistance, breakdown voltage of insulation, relay characteristics etc.
In addition to describing the procedure for pre commissioning checks and tests, attempt is also
made to give essential information about the specifications and characteristics of different parts
and components. Detailed description of the test procedures and interpretation of the test results
were given on Transformers. The test results obtained at commissioning stage of transformer will
be used as reference values /signatures for diagnosing the transformer during any internal faults
in its life time. Before carrying out the pre-commission tests it is always advisable to refer to the
manufacturers instructions. Products of different manufactures may have special features and
characteristics and it is necessary to have a good knowledge of these special features before
carrying out the tests.
CHAPTER I
INTRODUCTION:
The transformer works on the principle of electromagnetic induction. As the
name suggest it transfers electrical energy from one circuit to another at constant frequency and
power, at different voltage levels. Depending on upon the requirement, the voltage levels can be
stepped up (or) stepped down. This makes it possible to use very high voltages for transmission
lines resulting in a lower current. Higher voltage and lower current reduce the conductor size,
transmission line losses and improves the voltage regulation as well. Transformers have made
possible economic delivery of electric power over long distances.
In our country the electrical energy is usually generated at 6.6 or 11 or 33 kv,
stepped upto 132,220,400 or 765 kv with the help of step up transformers for transmission and
then stepped down the voltage to 11 kv for feeding distributing transformers stepping down the
voltage further to 400/230 volts for the consumer uses.
PRINCIPLE OF TRANSFORMER:
The physical basis of the transformer involves the Faradays laws of electro magnetism in
which an alternating flux induces voltage in the coil and Lenz Law which states that the effect
produced will oppose the cause. Combining the two laws stated above, the emf (back emf)
induced in a coil, with an alternating flux is given by:
(1.1)
The transformer consists of two inductive coils which are electrically separated but
magnetically linked through a path of low reluctance by mutual induction.
If one coil is connected to the source of alternating voltage an alternating flux is set up in
the laminated core most of which is linked with the other coil produces mutually induced emf. If
the second coil circuit is closed, a current flow in it and so electric energy is transferred from the
primary to secondary coil.
CHAPTER II
CONSTRUCTION AND PARTS OF TRANSFORMER
2(a) Transformer construction:
The transformer is simple in construction and consists of magnetic circuit linking
with two windings known as primary and secondary windings. Besides magnetic circuit and
windings it consists of a suitable tank for the assembled core and windings such as a tank, a
suitable medium for insulating the core and the windings from its container such as transformer
oil, suitable bushings (either of porcelain , oil filled or condenser type) for insulating and
bringing out terminals of the windings from the transformer tank, temperature
gauge for
measurement of temperature of hot oil or hottest spot temperature, and oil gauge to indicate the
oil level inside the tank. Transformers are also provided with the conservator tank in order to
slow down deterioration of oil and keep the main tank full of oil.
d) The winding should be mechanically stable in respect to the forces appearing when sudden
short circuit of the transformer occurs.
e) The winding should have the necessary electrical strength in respect to the over voltages.
Usually LV winding is placed near the core and HV &LV windings are assembled
alternately around the core with insulating paper between the two windings.
Transformer windings are made of solid or stranded copper or aluminum strip
conductors. Heavy current capacity needs conductors of large cross section .to reduce eddy
current losses in the conductors, several small wires or parallel straps are preferred to one large
strap. This gives rise to unequal reactance components of the conductor which can be eliminated
by transposition of conductors.
2.4 Bushings:
Bushings are incorporated to bring the Extra High voltage winding terminations through
the cover of the transformer tank. Variety of bushings used for various voltage classes were
mentioned below:
Table:2.4.1:various voltage classes
Voltage
Class
<33KV
<132KV
>132KV
Type of bushing
Porcelain bushing
Oil filled bushings
Oil impregnated
paper(OIP) Condenser
bushing
The oil filled bushing consists of a hollow porcelain cylinder with a conductor through its
centre. The space between the conductor and the porcelain is filled with oil, the dielectric
strength of which is greater than that of air.
The OIP Condenser bushing is constructed of thick layers of bakelized paper alternating
with thin graded layer of tin foil. The result is a series of capacitors formed by the conductor and
the first tin-foil layer, the first and second tin foil layers ...and so on. The bakelized paper and
the tin foil are arranged in such a way that the capacitances of the capacitors and hence dielectric
stress across each capacitor are uniform through out the radial depth of the insulator.
Table:2.4.2:parts of oip
Description of
Part
Oil impregnated
core
Center
metal
tube
Fixing flange
S.
No
10
Description
of
Part
Air releasing screw
11
Test tap
12
Top terminal
13
14
Porcelain
upper
Porcelain lower
15
Gaskets
16
Base plate/stress
shield
Upper arcing horn
Springs
17
Expansion bowl
18
Cable bolt
Nitrogen
plug
S.
No
1
2
3
4
filling
Description
Natural Oil cooling
Natural Air Cooling
Oil Natural with Natural air cooling
Oil Natural with Forced air cooling
by Cooling Fans/Blowers.
Forced Oil cooling by Oil pump
accompanied by cooler fans.
2.7 Conservator:
The oil level of a transformer changes with the changes in the temperature of the oil
which in turn depends upon the load on the transformer. The oil expands with the increase in
load and contracts when the load decreases. Large transformers are also liable to overloads which
may overheat the oil and consequently there is a sludge formation if air is present. This causes
the vaporization of a part of the oil. The oil vapors forms explosive mixture with air that ignites
and may cause a considerable damage. For these reasons it is necessary to prevent the oil from
having contact with air as well as the moisture. For this purpose some conservators are employed
11
with Air cell-a balloon like structure in the conservator tank to prevent mixture of air with
insulating oil.
14
The tips of arcing contacts are made of copper-tungsten alloy which has got excellent arc
resisting characteristics. Current limiting resistors consist of nickel chromium wire wound on
heat resisting bobbins held at both ends by insulating plates.
Oil in the diverter switch is maintained under a separate conservator head. The pipe
leading to the conservator from the diverter switch chamber is filled with a gas and oil operated
relay, the normally open, Velocity actuated contact of which is connected to trip circuit of the
transformer.
Selector switch:
The tap selector operates under no load condition and therefore, there need not be any
fear of arc generation, damage of contacts or deterioration of main transformer oil.
The tap lead wires from the winding of the transformer are brought and terminated at the
fixed contacts of the tap selector. Tap Change operation requires two rotary switches per phase.
The odd numbered tapings are connected to one switch and even numbered tapings to the other
in such a way that the two switches come into use alternately.
The selected odd and even numbered contacts are fitted on either insulating bars mounted
vertically to diverter switch chamber.
Principle of Operation:
The tap operation in a transformer is explained referring to fig .2.9.1. The odd moving
contact is on tap 7 and even side contact on tap 8 of the tap selector. The odd and even collector
contacts are connected to the diverter switch contacts O&E respectively. Since Diverter switch is
making contacts at O (odd) flow of current will be through tap 7.When a signal is given to the
driving mechanism for changing the tap from 07 to 06, it will first operate the even contact of tap
selector from tap 08 to 06 without changing the position of odd contact.
Simultaneously with the Operation of the tap selector, the spring mechanism, which is the energy
accumulator mounted on the top of the diverter switch will be charged.
On completion of tap selector operation, energy accumulated in the spring will be
released for instantaneous Transfer of the diverter switch moving contacts from tap O to E
through the resistor contacts OR and ER thus changing the flow current from tap 07 to 06.
For reverse operation i.e. for changing tap 6 to 7, the tap selector shaft
15
will not operate as its contacts is already on tap 07.But the transfer of the diverter switch moving
contacts from E to O via- ER-OR-O will take place
completing the tap changing operation.
16
Fig: 2.10.2: Tap Changeover process in a Diversion Switch of On Load Tap Changer
The Tap changeover from odd to even contacts in diversion switch can be observed from
fig 2.10.2(a) to Fig 2.9.2(e). At the time of transition Bridging resistors R1 &R2 Will come
across Tap section as in fig 2.10.2 (c). Load current IL splits S1, R1.T1 & S2, R2, and T2, thus
causing circulating current IC adding in R2 & subtracting in R1.
CHAPTER III
PROTECTION OF POWER TRANSFORMERS
A power transformer is subjected to various faults throughout its life time. The
protection of power transformer should be effective enough to isolate the power transformer
from internal and external faults of the transformer minimizing the fault clearing time as well as
increasing the life time of transformer. The protection incorporated for an oil immersed type
power transformer can be classified as shown in fig 3.1
Protection of
transformer
Against Internal
Faults
17
Against Through
Faults
Differential
Construction:
The relay comprises of flanged housing detachable front cover, terminal, box,
toughened glass windows, alarm and tripping device with mercury switches and valves for
venting and relay setting.
aluminum buckets which are hinged and the tilting of these buckets operates the mercury
switches.
18
Air release valve is provided at the top of the housing for releasing the trapped air and
for taking out the gas samples. One more valve is provided for introducing air inside the relay to
carry out the gas volume and surge tests
The front inspection glass is provided with scale to allow reading the accumulated
volume of the gas and observe color of the gas for fault analysis.IN Service/Test lock can be
selected in the form of movement of red indicator on the reading scale.
19
Gas Analysis:
Depending on the nature of fault i.e., with winding, paper insulation, oil flashover in the
transformer the nature of gases formed will vary. The type of fault formed in the transformer can
be detected by diagnosing the gases collected in the Buchholz relay.
Gases collected in the Buchholz relay is allowed to pass through a test tube filled with
Silver Nitrate (AgNO3) solution by releasing the Air release plug .The precipitate formed on the
walls of the test tube is observed for diagnosing the fault in the transformer as stated below.
Table3.1.1:Diagnosing the fault of transformer by precipitate
formed
Nature of gas
Colorless and odorless
Grayish white with pungent smell, non
flammable
Yellowish inflammable
Dark grey inflammable
Probable fault
Air trapped in oil or insulation.
over heating of insulation, press board
Decomposing of wood insulation
Flash over in oil or due to excessive
overheating of oil caused by a fault in
the winding or core.
20
21
S.N
o
1
2
3
4
5
6
7
8
9
10
11
12
Description
Base
Gasket
O Ring
Diaphragm
Cover
Springs
Rod retaining spring
Lock nut
Switch operating rod
Visual indicator
Stopper
Visual indicator
22
When the pressure inside the tank exceeds a preset limit, acts on the diaphragm inside
which in turn causes the diaphragm to lift up 4m from its seat. A movable rod attached to this
diaphragm operates a micro switch and makes the transformer to switch OFF. This lifting is
instantaneous and allows venting off the excess pressures inside the tank
It also gives a visual indication of the valve operation by raising a flag.
The diaphragm resets to its original position as soon as the pressure inside the tank drops
below the set limit.
23
Switch Nos
S1
S2
S3
S4
24
Wired to
Alarm
Tip
Cooler Control-1
Cooler Control-2
9,10,11
25
Unfortunately the circulating current protection mentioned above may operate even for
through faults due to the following factors which need careful consideration:
(a) Transformer vector group (i.e. phase shift between HV and LV)
(b) The possibility of zero sequence current entering the relay may destabilize the
differential for an External earth fault.
(c) Magnetizing in-rush currents (from one side only)
(d) Mismatch of HV and LV CTs
(e) Varying currents due to on-load tap changer (OLTC).
Factor (a) can be overcome by connecting the HV and LV CTs in star/delta respectively
(Or vice versa) opposite to the vector group connections of the primary windings, so
counteracting the effect of the phase shift through the transformer.
The delta connection of CTs provides a path for circulating zero sequence current,
thereby stabilizing the protection for an external earth fault as required by factor (b).
NOTE: To counter factors (a) & (b), the Thumb rule for differential protection is that the
CTs are to be connected in star for delta connected winding, and vice versa.
As the magnetizing current in-rush is predominantly 2nd, harmonic filters are utilized to
stabilize the protection for this condition (c).
And Finally, It is necessary to bias the differential relay to overcome the current
unbalances caused by factor (d) & (e) i.e. mismatch of CTs and taps of OLTC respectively. And
Hence a Percentage Biased Differential relay is preferred instead of a circulating current
principle.
The Percentage Bias Differential Protection applied for an YNyn0 Power Transformer is
mentioned in fig 3.4.3 below:
circulating current the higher will be the spill current required for tripping the realy as shown in
the relar charecteristics fig 3.4.4 .
Draw Back:
The problem with this philosophy is, the closer the fault to the source the higher the Fault
current, the slower the clearing time exactly the opposite to what we should be Trying to
achieve.
(2)Inverse Time Characteristic:
A relay having IDMT Characteristic will incorporate lower operating time for higher fault
currents. Various inverse characteristic curves can be selected among Normal Inverse, Very
Normal Inverse, and Extreme inverse curves. For a radial feeder, time grading by means of
relays having IDMT characteristics is shown in fig: 3.5.2 below.
Example: For a feeder having CT Ratio adopted=400/1, and Relay settings adopted for a relay
having nominal current of 1A as Pick up=100% and Time Lever=0.1, the relay
operating time for a fault current of 800Amps on feeder can be obtained as below:
Plug Setting Multiplier=800/ (400*100% of 1A) =2 & TL=0.1
Then, relay operating time (in secs) = (0.14*0.1)/ (20.02-1) =1sec.
Thus, for a fault current of 800Amps, the relay will operate in 1sec.
For protection of power transformer proper time gradation is to be provided for HV and
LV side IDMT relays. The CT connections on HV and LV side of transformer for over current
and Earth fault protection is shown fig 3.5.3:
29
CHAPTER IV
PRE COMISSIONING TESTS OF A POWER TRANSFORMER
Introduction:
Various tests are performed on power transformer at various stages starting from the first
stage of transformer construction to the commissioning stage at the site. The tests conducted can
be classified as Type Tests, Routine Tests, etc. The test results obtained for various tests at the
time of commissioning will be used as reference values for diagnosing the transformer during
any faults in the life time of transformer. Among various tests, Routine tests performed on power
transformer were mentioned in detail.
Routine Test performed on Power Transformer at site at the time of commissioning
includes:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
30
Configuration
1
2
3
HV-LV
HV-Body
LV-Body
Test arrangement:
This test is carried out to verify the voltage ratio between different windings on each
tapping which certifies correct no. of turns in the windings. For conducting the test, the
transformer neutrals are to be isolated from earthing and 3Ph, 4 wire 415 volts AC supply is
applied to the HV winding and corresponding phase and line voltages are measured at the LV
winding of power transformer.
Table4.2:Voltage ratio test
Voltage Ratio Test
Applied Voltage(volts)
TAP
Measured Voltage
NO
UN
VN
WN
UV
VW
31
WU
(volts)
w uv v
wu
1-25
240
240
240
415
415
415
n
--
n
--
n
---
---
w
---
---
Similarly apply 3 Phase, 4 wire 415 volts AC from LV side & keep HV, neutral isolated.
Measure magnetizing current in u, v &w phases of LV winding.
Table4.3.2:Magnetizing currents at
LV windings
Voltage applied
2u-2v Phase
415Volts
2v-2w phase
415 Volts
2w-2u phase
415 Volts
Ensure that primary and secondary windings are kept open. Apply 230Volt AC, on
primary/secondary winding in one phase and measure the voltages in remaining phases. Sum of
the measured voltages in two phases should be equal to the applied voltage.
Table4.4:Magnetic balance test
UN
Supply
Measured vltg
Measured vltg
VN
Measured vltg
Supply
Measured vltg
WN
Measured vltg
Measured vltg
Supply
33
(2) Measurement of currents during short circuit test should be done quickly as the
magnitude of currents produced would be of large value.
Connect the primary and secondary of one phase together and then apply 3Ph, 4wire 440Volts
AC supply to the HV winding of power transformer and measure the voltages as specified below.
IV1W:
1W1U:
Table4.6:vector group test
S.No
1
2
3
Verifying conditions
1U2n+1N2n=1U1N
1W2w=1V2v
1W2w<1W2v
Measured Values
Winding
HV
LV
Tap No
1 to 25
Winding Resistance
Phase U
Phase V
m
m
m
m
Phase W
m
m
The test results obtained from this test should be in agreement with the factory test results.
NOTE: Winding resistance test is to be conducted after conducting all the above mentioned
tests failing which the test results occurred would be erratic due to core magnetization in a
particular direction with the injected DC Current during this test.
draws a capacitive component of current, which leads the applied voltage by 90 0.But due to
absorption of moisture in the insulation; the dielectric material
components of currents and hence, the current flowing through the insulation leads the voltage
35
by some angle which is slightly less than 90 degrees. This small angle between pure capacitive
current and actual current represented by d (delta) is known as Loss angle.
Thus, the comparison of Resistive to Capacitive component of current is termed as Tan
is
Indicative of the Dielectric loss, ageing of insulation in a Lossy Dielectric material.
Tan =IR/IC.
Tan testing can be conducted in two modes:
(1).Ungrounded Specimen test (UST):- In this mode of testing, the Tan tap of test object is
isolated from the grounding and Capacitance, Tan is obtained for insulation with respect to
Tan tap of test object.
(2). Grounded specimen test (GST)
Capacitance ,Tan is obtained for insulation of test object with respect to ground.
Test Arrangement:
A 5KV Tan delta testing kit consists of a Standard Capacitor, HV cable, Induction
suppression circuit and a LV Cable (to conduct test in UST Mode).Tan testing is conducted for
transformer winding ,Transformer Bushings, Capacitive Voltage Transformers, Current
Transformers, Potential transformers insulation, etc.
(4.8.1) Testing of Transformer winding insulation:
For conducting Transformer Winding Insulation Tan test, the neutrals of the
transformer are to be isolated from grounding, and the following test procedure is to be followed:
(1)Before starting the test, the HV & LV bushings are to be shorted to their corresponding
neutrals to eliminate the inductance effect of the winding and create symmetrical balance of
voltage gradient on the HV &LV windings of transformer
(2).For testing insulation between HV and LV windings in UST mode, Connect 5KV HV cable
and LV cable of Tan testing kit to the HV winding and LV windings of power transformer.
(3). For testing insulation between winding and body in GST mode, Connect 5KV HV cable
of Tan testing kit to the winding of power transformer.
(4 Capacitance and Tan values are to be noted in each step.
36
(GST)
Capacitanc
e
Tan
(4.8.2)Testing of Bushing Insulation:
Tan test is conducted for OIP Bushings for 132KV and above voltage class .For
Insulation Tan test, the neutrals of the transformer are to be isolated from grounding, and the
following test procedure is to be followed:
(1).The Tan tap of the bushing should be isolated from the ground.
(2). For testing bushing insulation in UST mode, apply 5KV HV Cable & LV cable of Tan
testing kit to Bushing lead and Tan tap respectively and measure Capcitance, Tan of
bushing .
NOTE: After completion of Tan test, the bushing Tan tap must be tightened to earth
.
Capacitanc
e
Tan
37
B-ph (UST)
CHAPTER V (APPENDIX)
Type of cooling
Rating HV SLV(MVA)
No load voltage HV(KV)
No load voltage LV(KV)
Line current HV(Amps)
Line current LV(Amps)
Oil Temperature rise (0C)
Winding Temperature rise
(0C)
Phase
Frequency
Connection symbol
Ref ambient temperature
% Impedance
OFAF/ONAN
50/25
132
33
218.70/109.35
874.77/437.39
50
55
3
50HZ
YNyn0
500C max
12.58
transformer 50MVA,132/33KV
Insulation level
HV
230KV RMS/550KVp
LV
70 KV RMS/170KVp
HV(winding)
38 KV RMS/95KVp
LV(winding)
70 KV RMS/170KVp
38
(3-4),(1N-16)
(3-4),(1N-15)
(3-4),(1N-14)
(3-4),(1N-13)
No load HV
line voltage
(KV)
138.60
136.95
135.30
133.65
Rated HV
line current
(Amps)
208.28
210.79
213.36
216.06
(3-4),(1N-12)
132.00
218.70
(3-4),(1N-11)
(3-4),(1N-10)
(3-4),(1N-9)
(3-4),(1N-8)
(3-4),(1N-7)
(3-4),(1N-6)
(3-4),(1N-5)
(3-4),(1N-4)
(3u-16),(3-4),(1N-3)
(3-16),(1N-16)
(3-16),(1N-15)
(3-16),(1N-14)
(3-16),(1N-13)
(3-16),(1N-12)
130.35
128.70
127.05
125.40
123.75
122.10
120.45
118.80
118.80
118.80
117.15
115.50
113.85
112.20
221.47
224.30
227.22
230.20
233.28
236.43
239.67
243.00
243.00
243.00
246.42
249.94
253.56
257.29
(3-16),(1N-11)
(3-16),(1N-10)
(3-16),(1N-9)
(3-16),(1N-8)
(3-16),(1N-7)
(3-16),(1N-6)
(3-16),(1N-5)
(3-16),(1N-4)
110.55
108.90
107.25
105.60
103.95
102.30
100.65
99.00
261.13
265.09
269.17
273.37
277.71
282.19
286.82
291.60
Switch
position
Leads joined on
HV Winding
1
2
3
4
5
(Nr. tap)
6
7
8
9
10
11
12
13(A)
13(B)
13(C)
14
15
16
17
18
19
20
21
22
23
24
25
39
LV Winding
Line
Voltage(KV)
LV Winding
Rated
(Amps)
874.79
33
5KV
Configuration
HV-LV
HV-Body
LV-Body
UN
15 sec
1000M
2000M
1000M
W
N
UV
V
W
W
U
255
255
254
445
442
443
255
255
253
445
442
443
257
256
255
448
445
445
259
257
255
447
443
445
40
un
vn
wn
uv
vw
Wu
60
60
61
62
63
64
65
66
67
68
69
70
71
73
74
75
76
77
78
80
81
82
83
84
85
60
60
61
62
63
63
64
66
66
67
68
69
71
73
74
75
76
77
78
79
80
81
82
83
84
60
60
61
61
62
62
64
65
66
67
68
69
70
73
73
75
76
77
78
79
80
81
82
83
83
105
106
107
108
110
111
112
114
116
117
119
121
123
127
128
131
133
134
136
138
139
141
143
145
147
104
105
106
108
109
110
111
113
115
116
118
120
122
126
128
130
131
133
135
136
138
140
142
143
145
104
105
106
109
109
111
111
113
115
117
118
120
123
126
128
130
132
134
135
137
138
140
142
144
146
Magnetizing
Current measured
IV
1.9
1.8
2.5
3.6
(mA)
1W
2.5
2.5
3.3
4.7
VN
204
255
205
WN
51
133
254
VN
201
253
204
WN
53
132
252
VN
201
257
205
41
WN
56
133
256
AT TAP NO: 25
Table5.2.4.1:practical values of magnetic balance test at tap 25
UN
255
120
55
VN
194
255
195
WN
60
132
252
S.No
1
2
3
Verifying
conditions
1U2n+1N2n=1U
1N
1W2w=1V2v
1W2w<1W2v
Measured
Values
59+178=237
307308
305<365
42
Winding Resistance
Winding
Tap No
UN (m)
VN (m)
WN (m)
Winding
un (m)
vn(m)
wn(m)
HV
617
611
617
LV
25.7
25.7
25.6
609
608
609
602
597
602
594
593
594
587
582
588
579
578
580
572
568
573
565
563
565
43
558
553
558
10
550
550
550
11
543
539
544
12
535
535
535
13
527
526
527
14
535
536
535
15
543
539
544
16
549
550
550
17
557
554
558
18
564
565
565
19
571
569
572
20
578
580
578
21
586
583
586
22
592
594
593
23
600
597
601
24
607
609
607
25
615
612
615
44
HV
Bushing
Capacitance
Tan
4890pF
0.648
14040 pF
0.575
45
Given data:
p=50MVA
Rated HV voltage=132KV
Rated LV voltage =33KV
Rated HV current =218.70 Amps
Rated LV current =874.77
% impedance =12.58
Applied voltage=440 volts
No. of turns=4
HV Current at Applied voltage= (Rated HV Current/Impedance in volts)* Applied
Voltage
= (12.58*132KV)/100
=16.60KV
HV Current at Applied voltage= (Rated HV Current/Impedance in volts)* Applied Voltage
= (218.70/16.60KV)*440
= (218.70/16.60*103)*440
= (0.01317)*440
= 5.79 Amps
LV Current at Applied voltage=HV current at applied voltage*no. of turns
=5.79*4
=23.16 Amps
Hence the theoretical and practical values are similarly equal therefore the % impedance is
agreement with the name plate details on the power transformer. This test result indicates that
impedance of winding that is no fault with the winding.
vector group test it is clear that it satisfies the connection of YNyn0 as represented in the name
plate details of the transformer.
48
Chapter VI
BIBLIOGRAPHY
49
50