Training PDF
Training PDF
1.
2.
3.
4.
Short-Circuit Exercise
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Page 1 of 2
STATEMENT OF LIABILITY
By registering for the Operation Technology, Inc. (OTI) ETAP seminar/workshop (seminar), attending
the seminar or making any use whatsoever of the material provided by OTI, the participant or user of
material acknowledges that the information and materials presented in the course of the seminar are for
information purposes only. Examples and data used in the seminar are just that, examples, which are
being used to help the participants to gain knowledge of product, materials and services available. OTI
makes no representation or warranties of any kind, whether express or implied, as to the correctness of
the information or materials provided. All title and intellectual property rights relative to these materials
remain those of the respective content owner and are protected by applicable laws and treaties. These
materials and information are provided for the sole use of the seminar attendee and are not to be copied,
printed or disseminated in a manner so as to be contrary to the limited rights granted by OTI.
In no event shall OTI, its subsidiaries or affiliates, or their respective officers, directors, employees,
representatives or agents (collectively called "OTI") be liable for special, incidental, consequential,
punitive, indirect, or other special damages, including but not limited to, loss of data, use, or profits,
however caused, whether for breach of contract, negligence, or otherwise.
Should a seminar participant or a user of the information or materials provided by OTI decide to purchase
any software, material, products or services referenced in the examples used during the seminar, in doing
so they acknowledge that no promise, representation, warranty, or undertaking has been made or given
by OTI in relation to the profitability of or any other consequences or benefits to be obtained from the
delivery or use of the software, material, product or services purchased and any accompanying materials.
Page 2 of 2
OTI Headquarters
OTI International
OTI
Headquarters
OTI Far-East
Who is OTI
Professionals with Advanced Degrees
Internationally Renowned Experts
Active in ANSI & IEC Standards Committees
Over 500 Years of Combined Experience
OTIs Mission
To p
provide state-of-the-art p
products and
superior engineering services by combining
cutting-edge technologies with the
highest standard in quality to
achieve overall customer satisfaction.
satisfaction
ETAP RealReal-Time
Power System Monitoring & Simulation
1986
1997
ETAP ARTTS
2004
ETAP iSub
S
2006
Operation Technology, Inc.
Consulting Services
Conceptual Design
User-Definable Dynamic
y
Models
Technical Support
An Extension of Your Electrical Engineering Dept.
Over
40 000 Li
40,000
Licenses
More Than
90 Cou
Countries
t es
User Services
Webinars
User Groups
Seminars
User Symposiums
ETAP Nuclear Utility User Conference
C f
Open Workshops
Irvine, Houston, Philadelphia, Canada,
China, Saudi Arabia, India, Indonesia,
Singapore, Thailand, Bahrain, Abu Dhabi,
Dubai, Venezuela, Peru, Chile, Colombia,
T k
Turkey,
France,
F
England,
E l d JJapan,
On-Site
On Site Workshops
Customized Training
Project Training
OTI Corporate Offices
ETAP Events
Consulting Firms
Generation Plants
Government
Manufacturing
Nuclear
Nuclear Non
Non--Utility
Distribution
Transportation
Education
Title
Titl 10 CFR 50,
50 A
Appendix
di B
United States Code of Federal Regulation
Quality Assurance Criteria for Nuclear Power Plants and
Fuel Reprocessing Plants
Title 10 CFR 21
United States Code of Federal Regulation
Reporting of Defects and Noncompliance
Performance Reporting
Zero Part 21 Reported Since QA Established in 1991
ETAP Library
Cable
Cable Fire Protection
Fire Coating
Fire Stop
Fire Wrap
HV Circuit Breaker
LV Circuit Breaker
Trip Device
Transmission Line
Phase Conductor
Ground Wire
Motor
Nameplate
CKT Model
Characteristic Model
Load Model
Fuse
Relay
Overload Heater
Solid State
Thermal Magnetic
Electro-Mechanical
Electro
Mechanical
Motor Circuit Protector
Harmonics
Interruption Cost
Reliability Index
Battery Characteristic
C t lS
Control
System
t
D i
Device
Control Relay
Solenoid
Contact
C t t
Operation Technology, Inc.
% Deviation
Data
0
0
0
0
0
0
0
0
0
0
TCC Curve
1
3
0
3
1
3
3
3
3
N/A
Operation Technology, Inc.
Alvin W
W. Vogtle
Arkansas Nuclear One
Beaver Valley
Braidwood
Browns Ferry
Brunswick
Bryon
Calvert Cliffs
Catawba
Clinton
Comanche Peak
Crystal River
Davis-Besse
Diablo Canyon
Donald C. Cook
Dresden
Duane Arnold
Fermi
Fort Calhoun
Grand Gulf
Indian Point
James A.
Fitzpatrick
Joseph M. Farley
Kewaunee
LaSalle
Limerick
McGuire
Mill t
Millstone
Nine Mile Pt.
North Anna
Oconee
O t Creek
Oyster
C k
Palo Verde
Peach Bottom
Perry
Pilgrim
Point Beach
Prairie Island
Quad Cities
R.E. Ginna
River Bend
Robinson
San Onofre
Seabrook
Sequoyah
q y
Shearon Harris
South Texas
Project
St Lucie
St.
L i
Surry
Susquehanna
Three Mile Island
Turkey Point
Vermont Yankee
Waterford 3
Watts Bar
Wolf Creek
ETAP Success
TVA Saved
$12.8 Million in
System Upgrade Costs
Case Study
TVA Watts Bar Nuclear Plant
ETAP
P d t
Product
Overview
AC Network
ETAP Overview
One-Line Diagram
Mode Toolbar
Toolbar Format
System Toolbar
Dumpster
Project View
Message Log
Project Toolbar
Select Mode
Edit Mode: Drag/Drop &
Connect Elements
Study Mode: Load Flow,
Short-Circuit, etc.
Project View
Edit Toolbar
AC Elements
DC Elements
Instrument
Devices
System
Toolbar
One-Line Diagram
In Edit Mode
Help Line
Displays the
description for
every entry field.
Message Logger
View the latest
messages related to
ETAP Projects.
It can be expanded
or reduced.
Pointer
2W XFMR
Cable
Reactor
Bus
Trans. Line
Impedance
Generator
MG Set
Induction Machine
Synch. Motor
Power Grid
Lumped Load
Static Load
Panels
Remote Connector
SVC
Composite Motor
Fuse
HVCB
Recloser
Overload Heater
SPST
Pointer
3W XFMR
Cable
Impedance
Converter
Battery
MOV
Capacitor
Harmonic Filter
Phase Adapter
Bus
Motor
Static Load
Lumped Load
Elementary Diagram
Composite
Motor
Composite Network
HVDC
Composite Network
CB
Contactor
LVCB
In-Line Overload Relay
SPDT
Instrumentation
Ground Grid
Display Options
SPST
UPS
Charger
Fuse
SPDT
VFD
Inverter
Current Transformer
Voltmeter
Potential Transformer
Ammeter
Multimeter
Voltage Relay 27 / 59
Frequency Relay 81
Motor Relay
Overload Heater
Taglink
1996-2009 Operation Technology, Inc. - Workshop Notes: AC Network
Slide 7
Report Manager
Device Settings Report
Stop Calculation
Sequence Viewer
1996-2009 Operation Technology, Inc. - Workshop Notes: AC Network
Slide 15
Add Elements
Example
A Circuit Breaker and Fuse are Inserted Between Bus1 and T1.
Creating a Project
Enter four new elements into the one-line diagram and proceed
to enter the input data for each element
Power Grid
1250 MVAsc
X/R = 120
Bus kV Rating
Bus 1 = 13.8
Bus 2 = 4.16
Transformer T1
20 MVA
%Z=6
X/R = 17
Lumped Load
5 MVA
% PF = 80
Rated kV= 4
70% Motor Load
Cable
NEC EPR 133%
5.0kV Mag
3/C CU
Size= 4/0
Length=200ft
Transformer T2
MVA= 1
Typical %Z & X/R
Bus kV Rating
Bus3= 4.16
Bus4= 0.480
Lumped Load Lump2
MVA= 0.5
%PF=85
Rated kV = 0.46
50% Motor Load
1996-2009 Operation Technology, Inc. - Workshop Notes: AC Network
Slide 35
Gen1
Rating:
5 MW
Voltage Control
%PF = 80
Generation Category:
Design
MW = 5
Qmax = 5
Qmin = 1
3D Database
1996-2009 Operation Technology, Inc. - Workshop Notes: AC Network
Slide 42
Study Conditions
Different Operating Requirements
Generator 1 in Voltage
Control Mode
Study Conditions
Different Loading Conditions
Summer Loading
Winter Loading
Study Conditions
Different Configurations
Configuration Normal
Configuration GenOFF
Study Conditions
Different Engineering Data
Revision Base
3-D Database
Configurations
Presentations
Symbol &
Annotation
Visibility,
Location,
& Size
Properties
Nameplate,
Rating, Loading,
Settings, Dimension, etc.
Presentations
Symbol &
Annotation
Visibility,
Location,
& Size
One-Line Diagrams
Impedance Diagrams
Relay Diagrams
Physical Diagrams
1996-2009 Operation Technology, Inc. - Workshop Notes: AC Network
Study Diagrams
Slide 48
Configurations
CB, Fuse, Switch,
Load, & Motor
Status
Properties
Properties
Nameplate,
Rating, Loading,
Settings, Dimension, etc.
Group 3 Functions
Change Phase/Ground mode in
Star View.
Compute Time Difference in Star
View.
View Alerts.
View Device Setting Reports.
Base Data
Revision Data
Group 1 Changes
Group 2 Changes
Group 3 Changes
Configuration Status
Library Data
Library Path
Base Data
Revision Data
Group 1 Changes
Group 2 Changes
Group 3 Changes
Configuration Status
Library Data
Library Path
X
X
Base Data
Revision Data
Group 1 Changes
Group 2 Changes
Group 3 Changes
Configuration Status
Library Data
Library Path
X
X
Cannot
Change
Base Data
Revision Data
Group 1 Changes
Group 2 Changes
Library Data
Library Path
Circuit Arrangements
Radial System
Loop System
Primary Selective System
Secondary Selective System
Radial System
Simple or Expanded Radial
Inverted tree
No duplications
Least Expensive
Simple in operation
Easy to analyze
Loop System
Interconnected / Open Point
Loads are tapped of the loop
Loop could be open or closed
More difficult for analysis
Reliable
Recommended
System Concepts
Slide 2
LN
S3
3
3
S1
V LL I *
jQ
Slide 3
Leading
Power
Factor
Lagging
Power
Factor
jQ
P - jQ
P + jQ
Slide 4
IB
ZB
(kVB )
MVA B
3VI
3ZI
IB
SB
3VB
VB2
SB
ZB
I pu
I actual
IB
Zpu
Zactual
ZB
Vpu
Vactual
VB
Spu
Sactual
SB
Slide 5
Example 1: The diagram shows a simple radial system. ETAP converts the branch
impedance values to the correct base for Load Flow calculations. The LF reports show
the branch impedance values in percent. The transformer turn ratio (N1/N2) is 3.31
and the X/R = 12.14
Transformer Turn Ratio: The transformer turn ratio is
used by ETAP to determine the base voltage for different
parts of the system. Different turn ratios are applied starting
from the utility kV rating.
kVB1
kV
kVB2
N1
kVB2
N2
Z pu
X pu
1
X
R
X
R
R pu
x pu
X
R
Slide 6
X pu
0.065(12.14)
1 (12.14)
0.06478
0.06478
12.14
R pu
0.005336
The transformer impedance must be converted to 100 MVA base and therefore the
following relation must be used, where n stands for new and o stands for old.
Znpu
Zopu
o
B
n
B
V
V
% Z 100 Z pu
n
B
o
B
S
S
(5.33 10
j0.06478)
13.8
13.5
100
5
(0.1115 j1.3538)
11.15 j135.38
Impedance Z1: The base voltage is determined by using the transformer turn ratio. The base
impedance for Z1 is determined using the base voltage at Bus5 and the MVA base.
VB
kVutility 13.5
4.0695
N1
3.31
N2
ZB
VB2
MVA
(4.0695) 2
100
0.165608
Slide 7
The per-unit value of the impedance may be determined as soon as the base
impedance is known. The per-unit value is multiplied by one hundred to obtain
the percent impedance. This value will be the value displayed on the LF report.
Z pu
Zactual
ZB
% Z 100 Z pu
(0.1 j1)
0.1656
(0.6038 j6.0382)
60.38 j603.8
The LF report generated by ETAP displays the following percent impedance values
in 100 MVA base
Slide 8
Slide 9
Basic Requirement
Power Flow in each line and transformer
Voltage Magnitude and Phase Angle at each bus
Slide 10
Power Factors
Transformer LTC Settings
Voltage Drops
Generators Mvar Demand (Qmax & Qmin)
Total Generation & Power Demand
Slide 11
Slide 12
Optimize Operating
Conditions
Bus Voltages are Within Acceptable Limits
Voltages are Within Rated Insulation Limits
of Equipment
Power & Current Flows Do Not Exceed the
Maximum Ratings
System MW & Mvar Losses are Determined
Circulating Mvar Flows are Eliminated
1996-2009 Operation Technology, Inc. Workshop Notes: Load Flow Analysis
Slide 13
Calculation Process
Non-Linear System
Calculated Iteratively
Assume the Load
Voltage (Initial Conditions)
Calculate the Current I
Based on the Current,
Calculate Voltage Drop Vd
Assume VR
Calc: I = Sload / VR
Calc: Vd = I * Z
Re-Calc VR = Vs - Vd
Slide 14
2.
3.
Fast-Decoupled Method
Newton-Raphson Method
Slide 15
kVARated
FLA3
FLA1
kWRated
PF Eff
kVARated
3 kV
kVARated
kV
HP 0.7457
PF Eff
kVA
PF
I3
I1
(kW ) 2 (kVar ) 2
kW
kVA
kVA
( 3 kV)
kVA
1000
kV
1000
Slide 16
Slide 17
Slide 18
Slide 19
Slide 20
Generic Loads
Exponential Load
Polynomial Load
Comprehensive
Load
Slide 21
Feedback Voltage
AVR: Automatic Voltage
Regulation
Fixed: Fixed Excitation
(no AVR action)
Slide 22
Slide 23
Isochronous Mode
Slide 24
Droop Mode
Slide 25
Droop Mode
Slide 26
Droop Mode
Slide 27
Slide 28
Adjusting Excitation
Slide 29
Slide 30
In the Swing Mode, the voltage is kept fixed. P & Q can vary
based on the Power Demand
In the Voltage Control Mode, P & V are kept fixed while Q &
are varied
In the Mvar Control Mode, P and Q are kept fixed while V &
are varied
Slide 31
Slide 32
Slide 33
Slide 34
Slide 35
Machine Rating
(Power Factor
Point)
Slide 36
Generation Categories
Generator/Power Grid Rating Page
10 Different Generation
Categories for Every
Generator or Power Grid
in the System
Slide 37
Power Flow
V*I
V1
V2
V2
1
2
jQ
V1*V2
*SIN(
X
P
V1
V *V
j 1 2 *COS(
X
V1*V2
*SIN( 1
X
V1*V2
*COS( 1
X
V2
X
)
2
V2
X
Slide 38
I
I
1000 j268
1000 j268
Slide 39
The following graph shows the power flow from Machine M2. This
machine behaves as a generator supplying real power and
absorbing reactive power from machine M1.
( V E)
X
sin
( V E)
cos
X
Power Flow
V
X
2
2
0
Slide 40
Bus Voltage
ETAP displays bus voltage values in two ways
kV value
For Bus4:
kVCalculated
100 97.83%
kVNo min al
For Bus5:
kVCalculated
V%
4.03
kVNo min al
4.16
kVCalculated
100 96.85%
kVNo min al
Slide 41
Slide 42
Slide 43
Reactor Impedance
Adjust reactor impedance based on specified tolerance
Overload Heater
Adjust Overload Heater resistance based on specified tolerance
Cable Length
Adjust Cable Impedance based on possible length variation tolerance
1996-2009 Operation Technology, Inc. Workshop Notes: Load Flow Analysis
Slide 44
Global
Temperature Correction
Cable Resistance
Transmission Line
Resistance
Slide 45
Slide 46
Slide 47
Slide 48
Slide 49
Cable
Reactor
Line
Transformer
UPS/Panel
Generator
Slide 50
Monitored parameters %
Condition reported
OverLoad
OverLoad
Fuses
Rated Current
OverLoad
Contactors
OverLoad
OverLoad
Slide 51
Slide 52
Advanced LF Topics
Load Flow Convergence
Voltage Control
Mvar Control
Slide 53
Slide 54
Voltage Control
Under/Over Voltage Conditions must be
fixed for proper equipment operation and
insulation ratings be met.
Methods of Improving Voltage Conditions:
Transformer Replacement
Capacitor Addition
Transformer Tap Adjustment
1996-2009 Operation Technology, Inc. Workshop Notes: Load Flow Analysis
Slide 55
Under-Voltage Example
Create Under Voltage
Condition
Method 2 - Shunt
Capacitor
Run LF
Voltage is improved
Run LF
Slide 56
Mvar Control
Vars from Utility
Close Switch
Open Switch
Run LF
Method 1 Generator
Change Generator from
Voltage Control to Mvar
Control
Set Mvar Design Setting to 5
Mvars
Slide 57
Panel Systems
Slide 58
Panel Boards
They are a collection of branch circuits
feeding system loads
Panel System is used for representing power
and lighting panels in electrical systems
Slide 59
Representation
A panel branch circuit load can be modeled as
an internal or external load
Advantages:
1. Easier Data Entry
2. Concise System
Representation
Slide 60
Pin Assignment
Pin 0 is the top pin of the panel
ETAP allows up to 24 external load connections
Slide 61
Assumptions
Vrated (internal load) = Vrated (Panel Voltage)
Note that if a 1-Phase load is connected to a 3Phase panel circuit, the rated voltage of the panel
circuit is (1/3) times the rated panel voltage
The voltage of L1 or L2 phase in a 1-Phase 3-Wire
panel is (1/2) times the rated voltage of the panel
There are no losses in the feeders connecting a
load to the panel
Static loads are calculated based on their rated
voltage
1996-2009 Operation Technology, Inc. Workshop Notes: Load Flow Analysis
Slide 62
Line-Line Connections
Load Connected Between Two Phases of a
3-Phase System
A
B
C
B
C
IB = IBC
IBC
Load
IC = -IBC
LoadB
SBC = VBC.IBC
PBC = VBC.IBC.cos
QBC = VBC.IBC.sin
SB = VB.IB
PB = VB.IB.cos ( - 30)
QB = VB.IB.sin ( - 30)
And, for load connected to phase C
SC = VC.IC
PC = VC.IC.cos ( + 30)
QC = VC.IC.sin ( + 30)
Slide 63
Info Page
NEC Selection
A, B, C from top to bottom or
left to right from the front of
the panel
Phase B shall be the highest
voltage (LG) on a 3-phase, 4wire delta connected system
(midpoint grounded)
Slide 64
Rating Page
Intelligent kV Calculation
If a 1-Phase panel is connected to a 3-Phase bus
having a nominal voltage equal to 0.48 kV, the
default rated kV of the panel is set to (0.48/1.732
=) 0.277 kV
Slide 65
Schedule Page
Slide 66
Description Tab
First 14 load items in the list are based on NEC 1999
Last 10 load types in the Panel Code Factor Table are user-defined
Load Type is used to determine the Code Factors used in calculating the total
panel load
External loads are classified as motor load or static load according to the
element type
For External links the load status is determined from the connected loads
demand factor status
Slide 67
Rating Tab
Slide 68
Loading Tab
For internal loads, enter the % loading for the selected loading category
For both internal and external loads, Amp values are
calculated based on terminal bus nominal kV
Slide 69
Slide 70
Feeder Tab
Slide 71
Action Buttons
Copy the content of the selected
row to clipboard. Circuit number,
Phase, Pole, Load Name, Link
and State are not copied.
Slide 72
Summary Page
Continuous Load Per Phase and Total
Non-Continuous Load Per Phase and Total
Connected Load Per Phase and Total (Continuous + Non-Continuous Load)
Slide 73
Output Report
Slide 74
Slide 75
Slide 2
Correction
Factors & Load
Variation
Sizing Results
Section
Larger
Short-Circuit
Impedance
limits
Consider
Growth Factor
for Max. MVA
Required
Smaller
Impedance
Slide 3
Temperature Correction
Ambient temperature in degree Celsius
For air cooled transformers use the air
ambient temperature
For water cooled transformers use the water
temperature
Based on C57.92-1981 and IEC 76-2
Slide 4
Altitude Correction
Derate the transformer capacity based on
altitude of the installation
Derating starts above 1000 m or 3300 ft
Based on C57.92-1981 and IEC 76-2
800
meter
900
meter
1000
meter
1100
meter
1200
meter
Slide 5
Load Variation
Growth Factor
Allowance for future load growth
Load Factor
The ratio of the average load to the peak load
over a designated period of time
Load Factor = 100 x ( kWi x Ti ) / ( kWp x Tt )%
Slide 6
Where:
I = interval of time when the load is non-zero
Slide 7
Short-Circuit Impedance
Size Requirement
Use Primary Short-Circuit kA and FLA to
Calculate Impedance
Primary 3-Phase FLA = MVA / (kVLL * 3)
Primary 1-Phase FLA= MVA / (kVprimary)
Slide 8
Operating Load
PowerStations load flow program determines the power
flow through the transformer
Automatically updated in the transformer required MVA
field (load flow study case info page option)
Can determine loading in radial or looped systems
1996-2009 Operation Technology, Inc. Workshop Notes: Transformer Sizing
Slide 9
Slide 10
Slide 11
Slide 13
System kV
Information
Primary / Secondary
Cable Impedance
Generator
Information
Auxiliary Load
Information
Optimization
Results Section
Slide 14
Slide 15
Slide 16
Slide 17
Slide 18
Slide 19
Unbalanced loads
Transmission System
Untransposed long transmission line
Abnormal operation with one phase out of service
Unbalanced loads (e.g., electrical railway traction
motors)
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 2
Transformer failure
Radio communication interference
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 3
Unbalance Factors/Indexes
System unbalance is considered by power
quality standards as a disturbance
Voltage/Current unbalance factors
Slide 4
Slide 5
Sequence Models of
3-Phase Machines
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 6
Unique Concepts of
3-Phase Machines
Swing Machine
The specified magnitude and the phase angle of the
positive sequence voltage only at the swing machine
terminal
PV Machine
The specified total output of 3-phase real powers and
the magnitude of the positive sequence voltage
PQ Machine
The specified total outputs of 3-phase real and reactive
powers
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 7
Concepts of Load
Connections
Single-Phase Loads
Connected in the phase connection types of
AB, BC, CA, AN, BN or CN
Three-Phase Loads
Slide 8
Modeling Capabilities
A mixture of 3-phase, 2-phase and singlephase network components
3-phase machines with internal impedance
being considered
Built-in calculator for overhead line
impedances
Mutual coupling among overhead lines
Transformers combined with load tap
changers (LTC) and phase shifters
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 9
Modeling Capabilities
2-winding and 3-winding transformers of
various winding connections
Lumped loads consisting of constant power,
constant impedance and constant current
components
Generator exciters with AVR or Mvar / PF
controllers
Robust library of of commonly used
overhead transmission lines and cables
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 10
Study Case
Same pretense as Balanced Load Flow with
more detailed modeling, calculations, and
results
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 11
Output Results
State-of-the-art graphic display of
results
Graphical display of marginal and
critical under/over voltages
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 12
Reporting
Customized output reports using Crystal Reports
Individual phase and sequence voltage, current,
and power
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 13
Example 1
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Example 2
IEEE Four Node Test Feeder
Characteristics of the Feeder
1. Two line segments with a 3-phase
transformer bank connected between the two
segments
2. Data is specified for balanced and
unbalanced loading at the most remote node
3. Transformer is specified for different
connection testing
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 15
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 16
Example 3
IEEE 13 Node Test Feeder
Characteristics of the Feeder
1. Short and relatively highly loaded for a 4.16
kV feeder
2. Overhead lines with variety of phasing
3. Shunt capacitor banks
4. In-line transformer
5. Unbalanced loading
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 17
1996-2009 Operation Technology, Inc. Workshop Notes: Unbalanced Load Flow Analysis
Slide 18
Short-Circuit
ANSI Standard
Short-Circuit Analysis
Types of SC Faults
Three-Phase Ungrounded Fault
Three-Phase Grounded Fault
Phase to Phase Ungrounded Fault
Phase to Phase Grounded Fault
Phase to Ground Fault
Fault Current
IL-G can range in utility systems from a few percent to
possibly 115 % ( if Xo < X1 ) of I3-phase (85% of all
faults).
In industrial systems the situation IL-G > I3-phase is rare.
Typically IL-G
.87 * I3-phase
Slide 2
Purpose of Short-Circuit
Studies
A Short-Circuit Study can be used to determine
any or all of the following:
Verify protective device close and latch capability
Verify protective device Interrupting capability
Slide 3
System Components
Involved in SC Calculations
Power Company Supply
In-Plant Generators
Transformers (using negative tolerance)
Slide 4
System Components
Involved in SC Calculations
Overhead Lines (at lower temperature limit)
Synchronous Motors
Induction Motors
Protective Devices
Slide 5
Synchronous Motors
Induction Machines
Lumped Loads
(with some % motor load)
Inverters
I0 from Yg-Delta Connected Transformer
1996-2009 Operation Technology, Inc. Workshop Notes: Short-Circuit ANSI
Slide 6
Slide 7
Short-Circuit Phenomenon
i(t)
v(t)
v(t) Vm Sin( t
Slide 8
v(t)
i(t)
di
v(t) Ri L
Vm Sin( t
) (1)
dt
Solving equation 1 yields the following expression
i(t)
R
- t
Vm
Vm
sin( t
- )
sin( - ) e L
Z
Z
Steady State
Transient
(DC Offset)
Slide 9
DC Current
Slide 10
Slide 11
Machine Reactance ( = L I )
AC Decay Current
Slide 12
Slide 13
ANSI
Slide 14
Models
All sources are modeled by an internal
voltage behind its impedance.
E = Prefault Voltage
R = Machine Armature Resistance
X = Machine Reactance (Xd, Xd, Xd)
1996-2009 Operation Technology, Inc. Workshop Notes: Short-Circuit ANSI
Slide 15
Synchronous Generators
Synchronous Generators are modeled
in three stages.
Induction Machines
Transient Reactance
Subtransient Reactance
Synchronous Reactance
Slide 16
Cycle Network
1 to 4 Cycle Network
This network is used to calculate the interrupting short-circuit current
and protective device duties 1.5-4 cycles after the fault.
30-Cycle Network
This is the network used to calculate the steady-state short-circuit
current and settings for over current relays after 30 cycles.
Slide 17
1 to 4 Cycle
30 Cycle
Xd
Xd
Xd
Xd
Xd
Xd
Hydro-Gen with
Amortisseur
winding
Xd
Xd
Xd
Hydro-Gen without
Amortisseur
winding
0.75*Xd
0.75*Xd
Xd
Xd
Xd
Xd
1.5*Xd
Utility
Turbo Generator
Condenser
Synchronous
Motor
Slide 18
1 to 4
Cycle
Xd
1.5*Xd
Xd
1.5*Xd
1.2*Xd
3.0*Xd
< 50 hp
1.67*Xd
Note: Xd = 1 / LRCpu
Slide 19
1 to 4 Cycle
Currents
(Transient Network)
HV Circuit Breaker
Interrupting
Capability
LV Circuit Breaker
Interrupting Capability
---
Fuse
Interrupting
Capability
SWGR / MCC
Bus Bracing
---
Relay
Instantaneous
Settings
---
---
Slide 20
Momentary Multiplying
Factor
Device Rating
HV CB
Asymmetrical RMS
Crest
C&L RMS
C&L RMS
HV Bus
Asymmetrical RMS
Crest
Asymmetrical RMS
Symmetrical RMS
Asymmetrical RMS
Symmetrical RMS
Asymmetrical RMS
LV Bus
Crest
Slide 21
Interrupting Multiplying
Factor
MFi is calculated based on:
Device Rating
Symmetrical RMS
HV CB
LV CB & Fuse
1996-2009 Operation Technology, Inc. Workshop Notes: Short-Circuit ANSI
Slide 22
HV CB Closing and
Latching Duty
Calculate Cycle Current (Imom, rms, sym) using Cycle Network.
Slide 23
HV CB Interrupting Duty
Calculate 1 to 4 Cycle Current (Imom, rms, sym) using Cycle Network.
Determine Local and Remote contributions (A local contribution is
fed predominantly from generators through no more than one
transformation or with external reactances in series that is less than
1.5 times generator subtransient reactance. Otherwise the
contribution is defined as remote).
Calculate no AC Decay ratio (NACD) and multiplying factor MFi
NACD = IRemote / ITotal
ITotal = ILocal + IRemote
Slide 24
HV CB Interrupting
Capability
CB Interrupting kA varies between Max kA and Rated kA
as applied kV changes MVAsc capability.
ETAPs comparison between CB Duty of Adj.
Symmetrical kA and CB capability of Adjusted Int. kA
verifies both symmetrical and asymmetrical rating.
Slide 25
LV CB Interrupting Duty
Slide 26
Slide 27
L-G Faults
Slide 28
L-G Faults
Symmetrical Components
Slide 29
Sequence Networks
Slide 30
If
3 Ia 0
If
3 VPrefault
Z1 Z 2 Z0
if Zg
Slide 31
Ia 2
I a1
If
3 VPrefault
Z1 Z 2
Slide 32
I a1 I a 0
VPrefault
Z0 Z 2
Z1
Z0 Z 2
if Zg
0 Ia
Slide 33
Slide 34
Z2 & Z0
Z1
I f1
Slide 35
Slide 36
Slide 37
Slide 38
Slide 39
Slide 40
Length
Adjustments
Cable Length
Transmission
Line Length
Temperature
Corrections
Adjust Fault
Impedance
Transmission
Line Resistance
L-G fault
Impedance
Cable Resistance
Slide 41
Tolerance Adjustments
Z 'Transformer
Z Transformer * (1 Tolerance)
Length'Cable
LengthCable * (1 Tolerance)
Length'TransmissionLine
LengthTransmissionLine * (1 Tolerance)
Slide 42
Temperature Correction
(234 .5 Tc )
R'Copper ' RBASE *
(234 .5 Tb )
(228 .1 Tc )
R' Alumi RBASE *
(228 .1 Tb )
RBASE
R'
Tb
Tc
Slide 43
Transformers
T1 X/R
PS =12
PT =12
ST =12
T2 X/R = 12
Gen1
Voltage Control
Design Setting:
%Pf = 85
MW = 4
Max Q = 9
Min Q = -3
Lump1
Y open grounded
Slide 44
Slide 45
Slide 46
Short-Circuit Alerts
Bus Alert
Protective Device Alert
Marginal Device Limit
Slide 47
Bus SC Rating
Type of Device
Monitored Parameter
Condition Reported
Bracing Asymmetrical
Bracing Crest
Bracing Symmetrical
Bracing Asymmetrical
LV Bus (<1000Volts)
LVCB
Breaking
Momentary C&L
Making
N/A
Breaking
Fuse
Breaking
SPDT
Making
SPST Switches
Making
HV CB
Slide 48
Slide 49
Slide 50
Short-Circuit Analysis
IEC Standard
Purpose of Short-Circuit
Studies
A Short-Circuit Study can be used to determine
any or all of the following:
Verify protective device close and latch capability
Verify protective device interrupting capability
Slide 2
Slide 3
Fault Current
IL-G can range in utility systems from a few percent to
possibly 115 % ( if Xo < X1 ) of I3-phase (85% of all
faults).
In industrial systems the situation IL-G > I3-phase is rare.
Typically IL-G
.87 * I3-phase
Slide 4
Short-Circuit Phenomenon
i(t)
v(t)
v(t) Vm Sin( t
Slide 5
v(t)
i(t)
di
v(t) Ri L
Vm Sin( t
) (1)
dt
Solving equation 1 yields the following expression
i(t)
R
- t
Vm
Vm
sin( t
- )
sin( - ) e L
Z
Z
Steady State
Transient
(DC Offset)
Slide 6
DC Current
Slide 7
Slide 8
Machine Reactance ( = L I )
AC Decay Current
Slide 9
Slide 10
IEC Short-Circuit
Calculation (IEC 909)
Initial Symmetrical Short-Circuit Current (I"k)
Peak Short-Circuit Current (ip)
Symmetrical Short-Circuit Breaking Current
(Ib)
Steady-State Short-Circuit Current (Ik)
Slide 11
IEC Short-Circuit
Calculation Method
Ik = Equivalent V @ fault location divided by
equivalent Z
Equivalent V is based bus nominal kV and c
factor
XFMR and machine Z adjusted based on
cmax, component Z & operating conditions
1996-2009 Operation Technology, Inc. Workshop Notes: Short-Circuit IEC
Slide 12
Transformer Z Adjustment
KT -- Network XFMR
KS,KSO Unit XFMR for faults on system
side
KT,S,KT,SO Unit XFMR for faults in auxiliary
system, not between Gen & XFMR
K=1 Unit XFMR for faults between Gen &
XFMR
1996-2009 Operation Technology, Inc. Workshop Notes: Short-Circuit IEC
Slide 13
Slide 14
Types of Short-Circuits
Near-To-Generator Short-Circuit
This is a short-circuit condition to which at least
one synchronous machine contributes a
prospective initial short-circuit current which is
more than twice the generators rated current, or
a short-circuit condition to which synchronous
and asynchronous motors contribute more than
5% of the initial symmetrical short-circuit current
( I"k) without motors.
1996-2009 Operation Technology, Inc. Workshop Notes: Short-Circuit IEC
Slide 15
Near-To-Generator Short-Circuit
Slide 16
Types of Short-Circuits
Far-From-Generator Short-Circuit
This is a short-circuit condition during which the
magnitude of the symmetrical ac component of
available short-circuit current remains essentially
constant.
Slide 17
Far-From-Generator Short-Circuit
Slide 18
Slide 19
Slide 20
Types of Short-Circuits
When these options
are selected
Maximum voltage factor is used
Minimum impedance is used (all negative
tolerances are applied and minimum
resistance temperature is considered)
1996-2009 Operation Technology, Inc. Workshop Notes: Short-Circuit IEC
Slide 21
Types of Short-Circuits
When this option is
selected
Minimum voltage factor is used
Maximum impedance is used (all positive
tolerances are applied and maximum
resistance temperature is considered)
1996-2009 Operation Technology, Inc. Workshop Notes: Short-Circuit IEC
Slide 22
Transformer taps
Static loads & capacitances
Generator & motor subtransient behavior
1996-2009 Operation Technology, Inc. Workshop Notes: Short-Circuit IEC
Slide 23
Calculation Method
Breaking kA is more
conservative if the option
No Motor Decay is
selected
Slide 24
Slide 25
Slide 26
Slide 27
L-G Faults
Slide 28
L-G Faults
Symmetrical Components
Slide 29
Sequence Networks
Slide 30
If
3 Ia 0
If
3 VPrefault
Z1 Z 2 Z0
if Zg
Slide 31
Ia 2
I a1
If
3 VPrefault
Z1 Z 2
Slide 32
I a1 I a 0
VPrefault
Z0 Z 2
Z1
Z0 Z 2
if Zg
0 Ia
Slide 33
Slide 34
Z2 & Z0
Z1
I f1
Slide 35
Slide 36
Slide 37
Slide 38
Slide 39
Slide 40
Slide 41
Slide 42
Slide 43
Slide 44
Slide 45
Slide 46
ETAP Workshop
Notes
1996-2009
Technology,
1996-2009
Operation
Technology,
Inc.Operation
Workshop
Notes: ArcInc.
Flash Analysis
Slide 1
Slide 2
Falls
Electric shocks and arc blasts can cause falls,
especially from ladders or unguarded
scaffolding.
1996-2009 Operation Technology, Inc. Workshop Notes: Arc Flash Analysis
Slide 3
Definitions
Limited Approach Boundary: A shock protection
boundary not to be crossed by unqualified persons
unless escorted by qualified personnel.
Restricted Approach Boundary: A shock protection
boundary to be crossed by only qualified persons.
Shock protection is required.
Prohibited Approach Boundary: A shock protection
boundary to be crossed by only qualified persons. The
use of techniques that may require direct contact with
energized equipment.
Slide 4
Definitions
Flash Protection Boundary: Distance at which the
incident energy equals 1.2 Cal/cm^2.
Incident Energy: The amount of energy impressed on
a surface, a certain distance from the source,
generated during and electrical arc event.
Working Distance: The dimension between the
possible arc point and the head and body of a worker
positioned in place to perform the task.
Bolted fault current: A short-circuit contact between
two conductors at different potentials in which the
impedance between the conductors is zero.
1996-2009 Operation Technology, Inc. Workshop Notes: Arc Flash Analysis
Slide 5
Definitions
Available fault current: The electrical current that can
be provided by the serving utility and facility-owned
electrical generating devices and large electrical
motors considering the amount of impedance in the
current path.
Arcing fault current: A fault current flowing through an
electrical arc-plasma, also called arc fault current and
arc current.
Voltage (Nominal): A nominal value assigned to a
circuit or system for the purpose of designating its
voltage class (I.e. 120/240 V, 480Y/277 V, 600V, etc).
Slide 6
Regulating Authorities
OSHA 29 CFR 1910.132 (d) requires
employers to assess the workplace to
determine if hazards are present, or likely to be
present and select and have each employee
use the types of PPE that will protect them.
OSHA 29 CFR 1910.333 Requires employees
who are exposed to electrical shock hazard to
be qualified for the specific task that they are
performing and use the appropriate PPE
1996-2009 Operation Technology, Inc. Workshop Notes: Arc Flash Analysis
Slide 7
Regulating Authorities
OSHA 29 CFR 1910.335 (a)(1)(I): Protective
equipment for specific body parts
OSHA 29 CFR 1910.335 (a)(2)(I): use of Insulated
tools when working around energized equipment.
NEC 110.6: equipment must be marked to warn
qualified persons of potential electrical arc-flash
hazards.
NFPA 70E-2000 Part II Chapter 2, paragraph 2-1.3.3
states that arc-flash analysis must be performed in
order to determine the level of hazard and appropriate
PPE for given tasks.
1996-2009 Operation Technology, Inc. Workshop Notes: Arc Flash Analysis
Slide 8
Slide 9
IEEE 1584-2002
208 15 kV (Empirical)
Voltage Range
208 V 600 V
Current Range
16 kA 50 kA
0.7 kA to 106 kA
No limit
No Limit
Installations
Open Air,
Cubic Box
Working Distance
18 inches +
18 inches +
Cal/cm2 or J/cm2
Cal/cm2 or J/cm2
Unit of Measure
Slide 10
20
Calorie/cm^2
15
NFPA 70E-2000
IEEE 1584-2002
10
5
0
0
10
20
Slide 11
20
Calorie/cm^2
15
NFPA 70E-2000
IEEE 1584-2002
10
0
0
10
20
Slide 12
Slide 13
Slide 14
Slide 15
NFPA
70E
IEEE
1584
Distance X Factor
System Grounding
(Grounded/Ungrounded)
Open/Enclosed Equipment
Working Distance
Slide 16
Slide 17
Additional Considerations
Up to date one-line-diagrams
Data similar to information required for Shortcircuit studies like MVAsc values of Utilitiy
including X/R, subtransient and transient
reactance, cable impedance, etc.
Include low voltage equipment which is often
not included in large systems
Slide 18
Slide 19
Slide 20
Slide 21
Slide 22
Arcing Current
In general, arcing current in systems below 15.0 kV will be less
than the 3-phase fault current because of arc impedance.
For buses with nominal kV in the range of 0.208 to 1.0 kV:
lg( Ia )
0.000526 * G
Slide 23
Arcing Current
For buses with nominal kV rating in the range of 1 to 15.0 kV:
Ia
1996-2009 Operation Technology, Inc. Workshop Notes: Arc Flash Analysis
I bf
Slide 24
Arc Duration LV CB
Slide 25
Arc Duration LV CB
Slide 26
Slide 27
Incident Energy
Empirical method (1.0 to 15.0 kV)
t
610
4.184 * C f * En
*
0.2
Dx
2.142 *10 *V * I bf
t
2
D
Slide 28
1.2
t
610
4.184 * C f * En
*
0.2
Dx
1 .2
2.142 *10 *V * I bf
t
2
D
Slide 29
Hazard Risk
Category
Total Weight
Oz/yd2
4.5 7
1.2
4.5 8
8 > cal/cm2
9 12
25> cal/cm2
16-20
24-30
5 > cal/cm2
cal/cm2
25
Slide 30
Slide 31
Pants (Long)
Safety Glasses
V-Rated Gloves
Insulated Tools
Slide 32
Slide 33
FR
FR
Slide 34
Category 3 (8 up to 25 Cal/cm2)
Category 2 Requirements
plus
Coveralls up to 2 Sets
Slide 35
Slide 36
Slide 37
Stoll Curve
Slide 38
FR Equipment Layering
Slide 39
ATPV Rating
(cal/cm^2)
EBT
(cal/cm^2)
HAF %
85
10
18
70
Slide 40
6.6cal / cm
Modified
Equipment
FR Shirt (long
Sleeve)
FR Raincoat
ATPV Rating
(cal/cm^2)
EBT
(cal/cm^2)
HAF %
85
15
22
70
Slide 41
Slide 42
Example1
Arc Fault at
Location A
Arc Fault at
Location B
1996-2009 Operation Technology, Inc. Workshop Notes: Arc Flash Analysis
Slide 43
Slide 44
Example1
Fault at location B
Slide 45
Example 2
Arc Fault at
Location C
Arc Fault at
Location D
Slide 46
Slide 47
Example 2
Fault at location C:
Slide 48
Slide 49
Slide 50
Slide 51
Slide 52
Class
500
00
kV 0.500 Bus kV
1000
7500
17000
26500
36000
Slide 53
Slide 54
Slide 55
Slide 56
Slide 57
Slide 1
Topics
Differential Relays
Slide 2
Differential Relays
Generator Differential Protection
Slide 3
Gen Differential
Relay
Slide 4
Transformer
Differential Relay
Slide 5
Bus Differential
Relay
Slide 6
ETAP System
1996-2009 Operation Technology, Inc. Workshop Notes: Arc Flash Analysis
Slide 7
Slide 8
Slide 9
Enclosures
Slide 10
Slide 11
Light Sensor
Only
Slide 12
Maintenance Modes
Reduce the Fault Clearing Time (FCT)
Slide 13
Slide 14
Maintenance
Mode
Normal
Operating
Mode
Slide 15
Normal
Operating
Mode
Slide 16
Normal
Operating
Mode
Slide 17
Maintenance
Mode
Slide 18
Maintenance
Mode
Slide 19
Analysis of Results
Consider all Configurations
Slide 20
Slide 21
Slide 22
Slide 23
Important Definitions
Bolted Fault Current: 3-Phase Short-circuit current
used to determine the arcing current
Arcing Current: current that flows in the event of an
arc fault and is typically less than the available SC
current
Source Protective Device: The upstream PD that
energizes a given bus. Multiple fed buses must have
multiple source PDs
FCT: Fault clearing time of the last protective device
to clear an arc fault (the FCT can only be determined
from source PDs
Slide 24
Slide 25
Slide 26
Slide 27
Slide 28
Slide 29
Slide 30
Slide 31
Slide 32
Level 4
Level 3
Level 2
Level 1
Slide 33
Short-circuit current
is too low or too high
Slide 34
Slide 35
Agenda
Concepts & Applications
Star Overview
Slide 2
Definition
Overcurrent Coordination
A systematic study of current responsive
devices in an electrical power system.
Slide 3
Objective
To determine the ratings and settings of
fuses, breakers, relay, etc.
To isolate the fault or overloads.
Slide 4
Criteria
Economics
Available Measures of Fault
Operating Practices
Previous Experience
Slide 5
Design
Open only PD nearest (upstream) of the fault
or overload
Provide satisfactory protection for overloads
Interrupt SC as rapidly (instantaneously) as
possible
Comply with all applicable standards and
codes
Plot the Time Current Characteristics of
different PDs
1996-2009 Operation Technology, Inc. Workshop Notes: Protective Device Coordination
Slide 6
Analysis
When:
New electrical systems
Plant electrical system expansion/retrofits
Coordination failure in an existing plant
Slide 7
Spectrum Of Currents
Load Current
Up to 100% of full-load
115-125% (mild overload)
Overcurrent
Abnormal loading condition (Locked-Rotor)
Fault Current
Fault condition
Ten times the full-load current and higher
1996-2009 Operation Technology, Inc. Workshop Notes: Protective Device Coordination
Slide 8
Protection
Prevent injury to personnel
Minimize damage to components
Quickly isolate the affected portion of the system
Slide 9
Coordination
Limit the extent and duration of service
interruption
Selective fault isolation
Slide 10
Coordination
C
D B
t
A
I
1996-2009 Operation Technology, Inc. Workshop Notes: Protective Device Coordination
Slide 11
Speed
Performance
Economics
Simplicity
1996-2009 Operation Technology, Inc. Workshop Notes: Protective Device Coordination
Slide 12
Required Data
Load Data
Fault Currents
Slide 13
Study Procedure
Prepare an accurate one-line diagram (relay
diagrams)
Obtain the available system current spectrum
(operating load, overloads, fault kA)
Determine the equipment protection guidelines
Select the appropriate devices / settings
Plot the fixed points (damage curves, )
Obtain / plot the device characteristics curves
Analyze the results
Slide 14
Slide 15
Slide 16
Question
What are the scaling factors to plot the 0.48 kV
and 13.8 kV TCC curves?
Slide 17
Slide 18
Fixed Points
Points or curves which do not change
regardless of protective device settings:
Cable damage curves
Cable ampacities
Transformer damage curves & inrush points
Motor starting curves
Generator damage curve / Decrement curve
SC maximum fault points
1996-2009 Operation Technology, Inc. Workshop Notes: Protective Device Coordination
Slide 19
It
I2t
I2 t
I22t
Motor
Xfmr
Cable
Gen
I
Slide 20
Cable Protection
Standards & References
IEEE Std 835-1994 IEEE Standard Power Cable
Ampacity Tables
Slide 21
Cable Protection
The actual temperature rise of a cable when exposed to
a short circuit current for a known time is calculated by:
2
t
T2 234
0.0297log
T1 234
Where:
A= Conductor area in circular-mils
I = Short circuit current in amps
t = Time of short circuit in seconds
T1= Initial operation temperature (750C)
T2=Maximum short circuit temperature
(1500C)
1996-2009 Operation Technology, Inc. Workshop Notes: Protective Device Coordination
Slide 22
Slide 23
Shielded
Cable
The normal tape
width is 1
inches
Slide 24
Slide 25
Transformer Protection
Slide 26
Transformer Category
ANSI/IEEE C-57.109
Slide 27
Transformer Categories I, II
Slide 28
Slide 29
Transformer
FLA
200
Thermal
I2t = 1250
t
(sec)
Infrequent Fault
(D-R LG) 0.58
Frequent Fault
Mechanical
K=(1/Z)2t
Inrush
2.5
Isc
25
I (pu)
Slide 30
Slide 31
Transformer Protection
MAXIMUM RATING OR SETTING FOR OVERCURRENT DEVICE
PRIMARY
SECONDARY
Over 600 Volts
Over 600 Volts
600 Volts or Below
Transformer
Rated
Impedance
Circuit
Breaker
Setting
Fuse
Rating
Circuit
Breaker
Setting
Fuse
Rating
Circuit Breaker
Setting or Fuse
Rating
600 %
300 %
300 %
250%
125%
(250% supervised)
More than 6%
and not more
than 10%
400 %
300 %
250%
225%
125%
(250% supervised)
Table 450-3(a)
source: NEC
Slide 32
Transformer Protection
Oil Level
Fans
Oil Pumps
Fault withstand
Harmonics
Devices 26 & 49
Differential Device 87
Slide 33
Recommended Minimum
Transformer Protection
Protective system
Above 10 MVA
Up to 10 MVA
Above
10 MVA
Instantaneous restricted
ground fault
Differential
Gas detection
Over excitation
Overheating
Slide 34
Question
Slide 35
Answer
For delta-delta connected transformers, with
line-to-line faults on the secondary side, the
curve must be reduced to 87% (shift to the
left by a factor of 0.87)
For delta-wye connection, with single line-toground faults on the secondary side, the
curve values must be reduced to 58% (shift
to the left by a factor of 0.58)
1996-2009 Operation Technology, Inc. Workshop Notes: Protective Device Coordination
Slide 36
Question
Slide 37
Frequent-Fault
Incidence Zone*
Slide 38
Motor Protection
Slide 39
Motor Protection
Motor Starting Curve
Thermal Protection
Locked Rotor Protection
Fault Protection
Slide 40
Slide 41
1
LOCKED
ROTOR
XS
Xd "
RELAY PICK UP
I PICK UP
I LOCKED ROTOR
1.6 TO 2
RELAY PICK UP
I PICK UP
I LOCKED ROTOR
1.2 TO 1.2
Slide 42
Slide 43
Fault Protection
(NEC Art / Table 430-52)
Slide 44
Slide 45
Low-voltage Motor
Ratings
Continuous amperes
Range of ratings
9-250
240-600
Horsepower
1.5-1000
00-9
Types of protection
Quantity
NEMA
designation
Overload: overload
relay elements
OL
Short circuit:
circuit breaker current
trip elements
CB
Fuses
FU
Undervoltage: inherent
with integral control
supply and three-wire
control circuit
Slide 46
12
12
759
10
1251
15
15
15
1
2
3
3.4
0
0
12
12
12
12
531
468
10
10
875
772
15
15
15
15
15
15
6
7
4.8
12
12
332
10
547
20
20
15
10
7.6
12
12
209
10
345
20
20
15
15
11
12
10
144
360
30
25
20
20
10
14
10
283
439
35
30
25
30
15
21
10
189
292
50
40
30
45
20
27
10
227
347
70
50
40
60
25
34
276
407
80
70
50
70
30
40
346
2/0
610
100
70
60
90
40
52
266
2/0
469
150
110
90
110
50
65
2/0
375
4/0
530
175
150
100
125
60
77
2/0
317
4/0
447
200
175
125
150
75
96
4/0
358
250
393
250
200
150
200
100
124
250
304
350
375
350
250
200
250
125
156
2/0
350
298
500
355
400
300
250
350
150
180
4/0
500
307
750
356
450
350
300
400
MAXIMUM
LENGTH FOR 1%
VOLTAGE
DROP WITH
LARGER WIRE
NEXT
LARGEST
WIRE
SIZE
USE NEXT
LARGER GROUND
CONDUCTOR
2.1
MAXIMUM
LENGTH FOR 1%
VOLTAGE
DROP
MINIMUM
WIRE
SIZE
STARTER
SIZE
CIRCUIT BREAKER
SIZE
MOTOR HP
MINIMUM
SIZE
GROUNDING
CONDUCTOR
FOR A 50 % CURRENT CAPACITY
250%
200%
150%
Slide 47
Service factor
Maximum locked rotor time (thermal limit curve) with the motor at ambient and/or
operating temperature
Slide 48
Class El
Class E2 (with
(without
fuses)
fuses)
2300-6900
0-8000
25-75
Quantity
2300-6900
0-8000
160-570
NEMA
Designation
Phase Balance
3
3
3
OL OC TR/O
OL
TOC relay
OC
TR/OC
Short Circuit:
Fuses, Class E2
IOC relay, Class E1
FU
OC
Ground Fault
TOC residual relay
Overcurrent relay with toroidal
CT
1
1
GP
BC
Negative-sequence voltage 1
relay (per bus), or both
Undervoltage:
Inherent with integral
control supply and threewire control circuit, when
voltage falls suffi-ciently to
permit the contractor to
open and break the seal-in
circuit
UV
Temperature:
Temperature relay,
operating from resistance
sensor or ther-mocouple in
stator winding
OL
GP
NEMA Class E1
medium voltage starter
Slide 50
Slide 51
Slide 52
Slide 53
(49)
I2T
O/L
tLR
MCP
(51)
ts
200 HP
Starting Curve
MCP (50)
LRAs
LRAasym
Slide 54
Protective Devices
Fuse
Overload Heater
Thermal Magnetic
Low Voltage Solid State Trip
Electro-Mechanical
Slide 55
Slide 56
Fuse Types
Expulsion Fuse (Non-CLF)
Current Limiting Fuse (CLF)
Electronic Fuse (S&C Fault Fiter)
Slide 57
Total Clearing
Time Curve
Minimum Melting
Time Curve
Slide 58
Slide 59
Ip
ta = tc tm
Ip
ta = Arcing Time
tm = Melting Time
tc = Clearing Time
ta
tm
tc
Time
(cycles)
Ip = Peak Current
Ip = Peak Let-thru Current
Slide 60
Let-Through Chart
Peak Let-Through Amperes
7% PF (X/R = 14.3)
230,000
300 A
100 A
12,500
60 A
5,200
100,000
Slide 62
Fuse
Generally:
CLF is a better short-circuit protection
Non-CLF (expulsion fuse) is a better
Overload protection
Electronic fuses are typically easier to
coordinate due to the electronic control
adjustments
Slide 63
Selectivity Criteria
Typically:
Non-CLF:
CLF:
Slide 64
Molded Case CB
Thermal-Magnetic
Types
Magnetic Only
Motor Circuit Protector
(MCP)
Integrally Fused (Limiters)
Current Limiting
High Interrupting Capacity
Non-Interchangeable Parts
Insulated Case (Interchange
Parts)
Frame Size
Poles
Trip Rating
Interrupting Capability
Voltage
Slide 65
MCCB
Slide 66
Slide 67
Thermal Maximum
Thermal Minimum
Magnetic
(instantaneous)
Slide 68
LVPCB
Voltage and Frequency Ratings
Continuous Current / Frame Size / Sensor
Interrupting Rating
Inst. Override
1996-2009 Operation Technology, Inc. Workshop Notes: Protective Device Coordination
Slide 69
LT PU
CB 2
CB 1
LT Band
CB 2
480 kV
ST PU
CB 1
IT
ST Band
If =30 kA
Slide 70
Inst. Override
Slide 71
Slide 72
Slide 73
Question
What is Class 10 and Class 20 Thermal
OLR curves?
Slide 74
Answer
At 600% Current Rating:
Class 10 for fast trip, 10
seconds or less
Class 20 for, 20 seconds or
less (commonly used)
20
Slide 75
Answer
Slide 76
Slide 77
Overcurrent Relay
Time-Delay (51 I>)
Short-Time Instantaneous ( I>>)
Instantaneous (50 I>>>)
Electromagnetic (induction Disc)
Solid State (Multi Function / Multi Level)
Application
Slide 78
Time-Overcurrent Unit
Ampere Tap Calculation
Ampere Pickup (P.U.) = CT Ratio x A.T. Setting
IL
= IR/A.T. Setting
= IL/(CT Ratio x A.T. Setting)
IR
51
Slide 80
Instantaneous Unit
Instantaneous Calculation
Ampere Pickup (P.U.) = CT Ratio x IT Setting
IL
= IR/IT Setting
= IL/(CT Ratio x IT Setting)
IR
50
Slide 81
Relay Coordination
Time margins should be maintained between T/C
curves
Adjustment should be made for CB opening time
Shorter time intervals may be used for solid state
relays
Slide 82
Situation
4.16 kV
CT 800:5
50/51
Relay: IFC 53
CB
Cable
CU - EPR
Isc = 30,000 A
DS
5 MVA
6%
Slide 83
Solution
Transformer:
IL
IR
5,000kVA
694 A
3 4.16kV
5
IL
4.338 A
800
IL
IR
CT
6 .0 A
(6/4.338 1.38)
TD 1
Inst (50) 8,328
5
800
52.1 A
55 A
Slide 84
Question
What T/C Coordination interval should be
maintained between relays?
Slide 85
Answer
B
t
A
CB Opening Time
+
Induction Disc Overtravel (0.1 sec)
+
Safety margin (0.2 sec w/o Inst. & 0.1 sec w/ Inst.)
I
1996-2009 Operation Technology, Inc. Workshop Notes: Protective Device Coordination
Slide 86
Recloser
Recloser protects electrical transmission systems from temporary
voltage surges and other unfavorable conditions.
Reclosers can automatically "reclose" the circuit and restore normal
power transmission once the problem is cleared.
Reclosers are usually designed with failsafe mechanisms that prevent
them from reclosing if the same fault occurs several times in succession
over a short period. This insures that repetitive line faults don't cause
power to switch on and off repeatedly, since this could cause damage
or accelerated wear to electrical equipment.
It also insures that temporary faults such as lightning strikes or
transmission switching don't cause lengthy interruptions in service.
Slide 87
Recloser Types
Hydraulic
Electronic
Static Controller
Microprocessor Controller
Slide 88
Recloser Curves
Slide 89
Motor Starting
Dynamic Acceleration
Why to Do MS Studies?
Ensure that motor will start with voltage drop
If Tst<Tload at s=1, then motor will not start
If Tm=Tload at s<sr, motor can not reach rated speed
Torque varies as (voltage)^2
Slide 2
Why to Do MS Studies?
Ensure motor feeders sized adequately
(Assuming 100% voltage at Switchboard or MCC)
LV cable voltage drop at starting < 20%
LV cable voltage drop when running at full-load < 5%
HV cable voltage drop at starting < 15%
HV cable voltage drop when running at full-load < 3%
Slide 3
Motor Sizing
Positive Displacement Pumps / Rotary Pumps
p = Pressure in psi
Q = fluid flow in gpm
n = efficiency
Centrifugal Pumps
Slide 4
Motor Types
Synchronous
Salient Pole
Round Rotor
Induction
Wound Rotor (slip-ring)
Single Cage CKT Model
Slide 5
Wound Rotor
Higher starting torque
Lower starting current
Speed varied by using external resistances
Slide 6
Slide 7
Wound Rotor
Slide 8
Operation of Induction
Motor
AC applied to stator winding
Creates a rotating stator magnetic field in air gap
Field induces currents (voltages) in rotor
Rotor currents create rotor magnetic field in air gap
Torque is produced by interaction of air gap fields
Slide 9
Slip Frequency
Slip represents the inability of the rotor to
keep up with the stator magnetic field
Slip frequency
S = (s-n)/s
where s = 120f/P
n = mech speed
Slide 10
Slide 11
Slide 12
Service Factor
Slide 13
Inrush Current
Slide 14
Slide 15
Resistance / Reactance
Torque Slip Curve is changed by altering
resistance / reactance of rotor bars.
Resistance by cross sectional area or
using higher resistivity material like brass.
Reactance by placing conductor deeper in
the rotor cylinder or by closing the slot at the
air gap.
Slide 16
Slide 17
Slide 18
Slide 19
Slide 20
Slide 21
Slide 22
Slide 23
Slide 24
Slide 25
Slide 26
Motor Efficiency
kW Saved = HP * 0.746 (1/Old 1/New)
$ Savings = kW Saved * Hrs /Year * $/kWh
Slide 27
Acceleration Torque
Greater
Acceleration
Torque means
higher inertia
that can be
handled by the
motor without
approaching
thermal limits
Slide 28
Acceleration Torque
Slide 29
Operating Range
Motor, Generator, or Brake
Slide 30
Rated Conditions
Constant Power
Slide 31
Starting Conditions
Constant Impedance
Slide 32
Voltage Variation
Torque is proportional to V^2
Current is proportional to V
Slide 33
Frequency Variation
As frequency decreases, peak torque shifts toward lower
speed as synchronous speed decreases.
As frequency decrease, current increases due reduced
impedance.
Slide 34
Slide 35
Rotor Z Variation
Increasing rotor Z will shift peak torque towards lower
speed.
Slide 36
Modeling of Elements
Switching motors Zlr, circuit model, or
characteristic model
Synch generator - constant voltage behind
Xd
Utility - constant voltage behind Xd
Branches Same as in Load Flow
Slide 37
Motor Modeling
1. Operating Motor
Constant KVA Load
2. Starting Motor
During Acceleration Constant Impedance
Locked-Rotor Impedance
Circuit Models
Characteristic Curves
After Acceleration Constant KVA Load
1996-2009 Operation Technology, Inc. Workshop Notes: Motor Acceleration
Slide 38
Locked-Rotor Impedance
ZLR = RLR +j XLR
(10 25 %)
Slide 39
Circuit Model I
Single Cage Rotor
Single1 constant rotor resistance and
reactance
Slide 40
Circuit Model II
Single Cage Rotor
Single2 - deep bar effect, rotor resistance and
reactance vary with speed [Xm is removed]
Slide 41
Slide 42
Circuit Model IV
Double Cage Rotor
DB2 independent rotor cages
Slide 43
Characteristic Model
Motor Torque, I, and PF as function of Slip
Static Model
Slide 44
Calculation Methods I
Static Motor Starting
Time domain using static model
Slide 45
Calculation Methods II
Slide 46
Slide 47
MS Simulation Features
Start/Stop induction/synchronous motors
Switching on/off static load at specified loading
category
Simulate MOV opening/closing operations
Change grid or generator operating category
Simulate transformer LTC operation
Simulate global load transition
Slide 48
Automatic Alert
Slide 49
Y/D Winding
Stator Resistor
Partial Wing
Stator Reactor
Soft Starter
Capacitor at Bus
Capacitor at Motor
Terminal
Torque Control
Voltage Control
Slide 50
Starting Device
Comparison of starting conditions
Slide 51
Slide 52
Slide 53
During Y connection Vs = VL / 3
Phase current Iy = Id / 3 and 3 to 1 reduction in torque
1996-2009 Operation Technology, Inc. Workshop Notes: Motor Acceleration
Slide 54
Slide 55
Slide 56
Slide 57
Slide 58
MOV Modeling I
Represented as an impedance load during
operation
Each stage has own impedance based on I, pf, Vr
User specifies duration and load current for each stage
Slide 59
MOV Modeling II
Five stages of operation
Opening
Closing
Acceleration
Acceleration
No load
Unseating
Travel
Stall
No load
Travel
Seating
Stall
Slide 60
MOV Closing
With Hammer Blow- MOV Closing
Slide 61
MOV Opening
With Hammer Blow- MOV Opening
Slide 62
Slide 63
Parameter Estimation
Xs
Xr
Xm
Single Cage
Rr/s
Rs
Xs
Xr1
Xr2
Rr1/s
Rr2/s
Xm
Double Cage
Slide 2
IZ eq (s)
( Rs
dE
dt
jX ) I
E
j( X s
X ) I
jT0 sE
Slide 3
E
X
Slide 4
Parameter Estimation
Methods
On-Line Estimation
Measurements
(Speed, I, V)
Parameter
Estimator
Off-Line Estimation
Nameplate Data
(Characteristics)
Parameter
Estimator
Slide 5
Slide 6
Tmax
Slide 7
Slide 8
Slide 9
Slide 10
Parameter Estimation
Results
Slide 11
Slide 12
Transient Stability
Slide 2
Introduction
TS is also called Rotor Stability, Dynamic
Stability
Electromechanical Phenomenon
All synchronous machines must remain in
synchronism with one another
TS is no longer only the utilitys concern
Co-generation plants face TS problems
Slide 3
Analogy
Slide 4
Introduction (contd)
System protection requires consideration of:
Critical Fault Clearing Time (CFCT)
Slide 5
Causes of Instability
Short-circuits
Loss of utility connections
Loss of a portion of in-plant generation
Starting of a large motor
Switching operations (lines or capacitors)
Impact loading on motors
Sudden large change in load and generation
Slide 6
Consequences of Instability
Synchronous machine slip poles
generator tripping
Power swing
Misoperation of protective devices
Interruption of critical loads
Low-voltage conditions motor drop-offs
Damage to equipment
Area wide blackout
1996-2009 Operation Technology, Inc. - Workshop Notes: Transient Stability
Slide 7
Synchronous Machines
Torque Equation (generator case)
T = mechanical torque
P = number of poles
Slide 8
Swing Equation
Slide 9
Synchronous Machines
(contd)
Swing Equation
= inertia constant
= damping constant
Pmech
Pelec
Slide 10
Slide 11
Slide 12
Slide 13
Slide 14
Slide 15
Slide 16
Slide 17
Slide 18
Slide 19
Slide 20
Slide 21
Slide 22
Slide 23
Generator Modeling
Machine
Equivalent Model / Transient Model / Subtransient Model
Slide 24
Slide 25
Factors Influencing TS
Post-Disturbance Reactance seen from generator.
Reactance Pmax
Generator Inertia.
Inertia Rate of change of Angle Kinetic Energy
Generator Internal Voltage
Internal Voltage Pmax
Slide 26
Factors Influencing TS
Generator Loading Prior To Disturbance
Loading Closer to Pmax. Unstable during acceleration
Slide 27
Solution to Stability
Problems
Improve system design
Increase synchronizing power
Slide 28
Solution to Stability
Problems
Reduction of Transmission System
Reactance
High Speed Fault Clearing
Dynamic Braking
Regulate Shunt Compensation
Steam Turbine Fast Valving
Generator Tripping
Adjustable Speed Synchronous Machines
1996-2009 Operation Technology, Inc. - Workshop Notes: Transient Stability
Slide 29
Solution to Stability
Problems
HVDC Link Control
Current Injection from VSI devices
Application of Power System Stabilizer
(PSS)
Add system protections
Fast fault clearance
Load Shedding
System separation
1996-2009 Operation Technology, Inc. - Workshop Notes: Transient Stability
Slide 30
User-Defined Dynamic
Models (UDM)
UDM
UDM is a tool that allows a client to create
his own dynamic models.
Governor UDM
Generator
Network
Exciter UDM
Slide 2
- Turbine/Governor Models
- Exciter/AVR Models
Slide 3
Slide 4
Slide 5
t = t + t
Slide 6
UDM Engine
Input Interface
Governor UDM
Exciter UDM
PSS UDM
Output Interface
t = t + t
Slide 7
ETAP
GUI
UDM Transfer
Block Diagram
UDM
Compiler
UDM File
1996-2009 Operation Technology, Inc. - Workshop Notes: User-Defined Dynamic Models
Slide 8
Slide 9
Slide 10
Slide 11
Slide 12
Slide 13
Slide 14
Slide 15
Slide 16
Slide 17
Slide 18
Slide 19
Slide 20
Slide 21
Slide 22
Governor UDM
Line
Generator
Exciter UDM
Load
Slide 23
Slide 24
Slide 25
Harmonic Analysis
Slide 2
Waveform Distortion
Primary Types of Waveform Distortion
DC Offset
Harmonics
Interharmonics
Notching
Noise
Slide 3
Harmonics
One special category of power quality
problems
Harmonics are voltages and/or currents
present in an electrical system at some
multiple of the fundamental frequency.
(IEEE Std 399, Brown Book)
Slide 4
Nonlinear Loads
Sinusoidal voltage
applied to a simple
nonlinear resistor
Increasing the
voltage by a few
percent may cause
current to double
Slide 5
Fourier Representation
Any periodic
waveform can be
expressed as a sum
of sinusoids
The sum of the
sinusoids is referred
to as Fourier Series
(6-pulse)
2 3
I ac
1
cos3 t
5
I d (cos t
I h cos(h t
1
1
1
cos7 t
cos11 t
cos13 t
7
11
13
h 1
1996-2009 Operation Technology, Inc. - Workshop Notes: Harmonics
Slide 6
Harmonic Sources
Utilities (Power Grid)
Known as Background Harmonic
Synchronous Generators
Due to Pitch (can be eliminated by fractionalpitch winding) and Saturation
Usually a voltage source
1996-2009 Operation Technology, Inc. - Workshop Notes: Harmonics
Slide 7
Slide 8
Slide 9
Harmonic I and V
Slide 10
Classification of Harmonics
Harmonics may be classified as:
Characteristic Harmonics
Generally produced by power converters
Non-Characteristic Harmonics
Typically produced by arc furnaces and discharge
lighting (from non-periodical waveforms)
Slide 11
Slide 12
Slide 13
Seventh Order
Slide 14
Slide 15
Characteristic Harmonics
Slide 16
Characteristic Harmonics
(contd)
Slide 17
Harmonic Spectrum
Slide 18
Harmonic-Related Problems
Motors and Generators
Increased heating due to iron and copper losses
Reduced efficiency and torque
Slide 19
Harmonic-Related Problems
(contd)
Transformers
Parasitic heating
Increased copper, stray flux and iron losses
Slide 20
Harmonic-Related Problems
(contd)
Power Cables
Involved in system resonance
Voltage stress and corona leading to dielectric
failure
Heating and derating
Fuses
Blowing
1996-2009 Operation Technology, Inc. - Workshop Notes: Harmonics
Slide 21
Harmonic-Related Problems
(contd)
Switchgears
Increased heating and losses
Reduced steady-state current carrying capability
Shortened insulation components life
Relays
Possibility of misoperation
Metering
Affected readings
1996-2009 Operation Technology, Inc. - Workshop Notes: Harmonics
Slide 22
Harmonic-Related Problems
(contd)
Communication Systems
Interference by higher frequency
electromagnetic field
System
Resonance (serial and parallel)
Poor power factor
1996-2009 Operation Technology, Inc. - Workshop Notes: Harmonics
Slide 23
Parallel Resonance
Total impedance at resonance frequency
increases
High circulating current will flow in the
capacitance-inductance loop
Slide 24
Parallel Resonance
Slide 25
Capacitor Banks
Slide 26
Capacitor Banks
Slide 27
Capacitor Banks
Slide 28
Capacitor Banks
Slide 29
Slide 30
Harmonic Distortion
Measurements
Total Harmonic Distortion (THD)
Also known as Harmonic Distortion Factor
(HDF), is the most popular index to measure the
level of harmonic distortion to voltage and
current
Ratio of the RMS of all harmonics to the
fundamental component
For an ideal system THD = 0%
Slide 31
Harmonic Distortion
Measurements (contd)
Good indicator of additional losses due to
current flowing through a conductor
Not a good indicator of voltage stress in a
capacitor (related to peak value of voltage
waveform, not its heating value)
Fi 2
THD
F1
Slide 32
Harmonic Distortion
Example
Find THD for this waveform
Slide 33
Harmonic Example
Find THD for this Harmonic Spectrum
Slide 34
Slide 35
Slide 36
Harmonic Distortion
Measurements (contd)
Individual Harmonic Distortion (IHD)
- Ratio of a given harmonic to fundamental
- To track magnitude of individual harmonic
IHD
Fi
F1
RMS
1
1996-2009 Operation Technology, Inc. - Workshop Notes: Harmonics
Slide 37
Harmonic Distortion
Measurements (contd)
Arithmetic Summation (ASUM)
Arithmetic summation of magnitudes of all
components (fundamental and all harmonics)
Directly adds magnitudes of all components to
estimate crest value of voltage and current
Evaluation of the maximum withstanding ratings
of a device
ASUM
Fi
1
Slide 38
Harmonic Distortion
Measurements (contd)
Telephone Influence Factor (TIF)
Weighted THD
Weights based on interference to an audio
signal in the same frequency range
Wi Fi
TIF
1
2
Fi
1
1996-2009 Operation Technology, Inc. - Workshop Notes: Harmonics
Slide 39
Harmonic Distortion
Measurements (contd)
I*T Product (I*T)
A product current components (fundamental
( I h Th )2
I T
h 1
Slide 40
Triplen Harmonics
Odd multiples of the
third harmonic
(h = 3, 9, 15, 21, )
Important issue for
grounded-wye systems
with neutral current
Overloading and TIF problems
Misoperation of devices due to presence of
harmonics on the neutral
Slide 41
Triplen Harmonics
Slide 42
Winding Connections
Delta winding provides ampere turn balance
Triplen Harmonics cannot flow
When currents are balanced Triplens
behave as Zero Sequence currents
Used in Utility Distribution Substations
Delta winding connected to Transmission
Slide 43
Implications
Neutral connections are susceptible to overheating
when serving single-phase loads on the Y side that
have high 3rd Harmonic
Measuring current on delta side will not show the
triplens and therefore do not give a true idea of the
heating the transformer is subjected to
The flow of triplens can be interrupted by appropriate
isolation transformer connection
Removing the neutral connection in one or both Y
windings blocks the flow of Triplen harmonic current
Three legged core transformers behave as if they have
a phantom delta tertiary winding
1996-2009 Operation Technology, Inc. - Workshop Notes: Harmonics
Slide 44
Modeling in Harmonic
Analysis
Motors and Machines
Represented by their equivalent negative
sequence reactance
Slide 45
Modeling in Harmonic
Analysis (contd)
Transformers
Leakage impedance
Magnetizing impedance
Loads
Static loads reduce peak resonant impedance
Motor loads shift resonant frequency due to
motor inductance
1996-2009 Operation Technology, Inc. - Workshop Notes: Harmonics
Slide 46
Reducing System
Harmonics
Add Passive Filters
Shunt or Single Tuned Filters
Broadband Filters or Band Pass Filters
Provide low impedance path for harmonic
current
Least expensive
Slide 47
Reducing System
Harmonics (contd)
Increase Pulse Numbers
Increasing pulse number of convert circuits
Limited by practical control problems
Slide 48
Reducing System
Harmonics (contd)
Apply Transformer Phase Shifting
Using Phase Shifting Transformers
Achieve higher pulse operation of the total
converter installation
In ETAP
Phase shift is specified in the tab page of the
transformer editor
Slide 49
Reducing System
Harmonics (contd)
Either standard phase shift or special phase
shift can be used
Slide 50
Reducing System
Harmonics (contd)
Add Active Filters
Instantly adapts to changing source and load
conditions
Costly
MVA Limitation
Slide 51
Distortion
(%)
THD (%)
69 kV and below
3.0
5.0
1.5
2.5
1.0
1.5
At
PCC
In ETAP:
Specify Harmonic Distortion Limits in Harmonic
Page of Bus Editor:
Slide 52
Slide 53
Underground Raceway
Systems
Raceway Systems
Slide 2
Slide 3
Slide 4
Cable Ampacity
Fundamentals
Cable Ampacity is the current a conductor can carry
continuously under the conditions of use without
exceeding its temperature rating.
Slide 5
Cable Ampacity
Fundamentals
Various thermal barriers:
1. Conductor insulation
Slide 6
Cable Ampacity
Fundamentals
Heat Transfer Equation
The rate of heat transfer is directly dependent on the difference
in temperature between the conductor (Tc) and the ambient
temperature (Ta)
Tc Ta (I 2 R).RHO
RHO is thermal resistance in degrees Centigrade-cm/watt
( TC
TA )
( R RHO)
Slide 7
Slide 8
Slide 9
Adjustment Factor
Heat Flow
Immediate Surrounding Environment
(Actual Installation Conditions)
Slide 10
Adjustment Factor
Cable Derating is based on a concept of an adjustment
(multiplying) factor that is applied against base ampacity.
The multiplying factor takes into account the differences in the
cables actual installation conditions from the base conditions.
I' F x I
I = Allowable cable ampacity for the actual installation conditions
F = Cable Ampacity Adjustment Factor
I = Base Ampacity specified by cable manufacturer or NEC under an
isolated condition with a soil thermal resistively (RHO) of 90 and a
specified ambient temperature
1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems
Slide 11
Adjustment Factor
Composition
F Ft x F x Fg
th
Ft = Adjustment factor to account for the
differences in the ambient and
conductor temperatures from the
base case
Fth = Adjustment factor to account for the
difference in the soil thermal
resistivity from RHO of 90
Fg = Adjustment factor to account for
cable grouping
1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems
Slide 12
Ta from 20 C to 30 C
Tc from 90 C to 75 C
Fth = 0.9 RHO of 90 to 120
Fg = 0.479 350 MCM Cable
Fg = 0.478 500 MCM Cable
350 MCM
F = 0.82 x 0.90 x 0.479 = 0.354
500 MCM
F = 0.82 x 0.90 x 0.478 = 0.354
I = 375 x 0.354 = 133 Amps
I = 450 x 0.353 = 159 Amps
Slide 13
Neher-McGrath Equation
I
Tc
Ta
Td
Rdc
Tc
Rca
=
=
=
=
=
=
=
Tc (Ta Td)
Rca'
Ampacity (kA)
I
Rdc (1 Tc)
Conductor temperature (Deg C)
Ambient Temperature (Deg C)
Conductor temperature rise due to dielectric loss (Deg C)
Conductor dc resistance (/ft)
Loss increment due to conductor skin & proximity effects
Thermal resistance between conductor & ambience (-ft)
Slide 14
Neher-McGrath Example
DC
0.292
DI
0.09
0.292
DI
0.382
Ri
Ri
0.56
DI
DC
0.19
1.315
Ds
2.16 DI
Ds
0.825
Slide 15
Neher-McGrath Example
Rsd
( n a)
Ds b
Rsd
9.457
Emissivity
E
0.95
Emissivity
Ds2
1.315 Conduit OD
Emissivity
9.5 ( n)
RE
[ 1 1.7 Ds2 ( E 0.41) ]
RE 7.054
Rca
Ri
Rca
17.071
RE
Rdc75
194
Rdc90
Rdc75
Rdc90
203.402
I
I
Rsd
( 234.5
( 234.5
90)
75)
( 90 40)
( 203.5 Rca)
0.12 kA with Ta = 30, I = 131 Amps
(Table 310-16 lists 130 Amps, Ta=30)
Slide 16
Cable Sizing
Determines the minimum size for each cable that will carry the
specified load current without violating the cable temperature
limit.
The sizing calculation is an
iterative process involving
adjustment of the cable size
and temperature.
Able to lock-in specific
cable sizes that cannot be
changed.
Slide 17
Load WKSHOP-EX4
Run Load Flow
Update Cable Load Amp
(Study Case)
Slide 18
Slide 19
Slide 20
Slide 21
UGS Presentation
UGS presentation is
conceptually a cross-section
of cable raceways.
Each UGS presentation is a
different cross-section of the
underground system.
If you delete a raceway from a UGS presentation
into the Dumpster, the raceway can be added to
other UGS presentations as an existing raceway.
In UGS, each presentation acts independently from
each other.
1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems
Slide 22
Slide 23
UGS Components
Heat Source
Slide 24
Inserting Cables
Three main methods for adding cables to the existing
conduits:
1. Drag the cable from OLV
using Ctrl+Shift Key
Slide 25
Cable Representation
3 Conductor / Cable and
3 Conductor / Phase
Symbol: 1, 2 and 3
1 Conductor / Cable and
1 Conductor / Phase
Symbol: 1A, 1B, 1C
Single Phase Cable
Symbol: 1F, 1R
DC Cable
Symbol: 1P, 1N
Slide 26
UGS Example
Duct Bank
X and Y = 30
Width = 15 Height = 8
Conduit
Conduit Size = 4
Y = 3.35
Pump Cable
From OLV
New Cable
5 kV Kerite 1/C
Operating Load = 200 Amps
Slide 27
Slide 28
Steady-State Calculation
Calculation Pre-Requisite: All cables have been carrying the specified load
long enough that the heat flow has reached its steady-state and no more
changes of temperature will occur throughout the raceway system.
Slide 29
Slide 30
Multiple Presentations
Slide 31
Slide 32
Slide 33
Slide 34
The transient temperature calculations are based upon a dynamic thermal model of the raceway system,
constructed mainly from thermal resistance, thermal capacitance, and heat sources.
Thermal resistance is used to represent different thermal layers from cable conductor to ambient soil.
Thermal capacitance is used to represent the capability of each layer to absorb heat.
1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems
Slide 35
Slide 36
Fill RHO = 60
1kV NEC Rubber2
1/C CU 3-phase
Magnetic
Class = 100%
Size = 350 AWG
Load = 284.5 Amps
per phase
Slide 37
Fill RHO = 60
1kVNEC Rubber2
1/C CU 3-phase
Magnetic
Class = 100%
Size = 750 AWG
Load = 334.9Amps
per phase
Slide 38
(Detail 2) in ETAP
Slide 39
Slide 40
Slide 41
Slide 42
Cable Pulling
Key Features
Integrated with one-line diagram cables
Integrated with underground raceway cables
Pull multiple cables
Slide 2
One-Line Diagram
Slide 3
Slide 4
Capabilities
Reduction factors for calculating allowable
tension when pulling multiple cables
Evaluate possible conduit jamming
Tolerance for cable weights and outside
diameters
Summary and alert windows
Slide 5
Slide 6
Slide 7
Cable Jamming
Jamming
No Jamming
No Jamming
Slide 8
Sidewall Pressure
Slide 9
Slide 10
Slide 11
Horizontal
Angles
Slide 14
Slide 15
Slide 16
New Results
Slide 17
Table of Contents
Review of Load Flow Solution
Optimal Power Flow Approach
Slide 2
Slide 3
Slide 4
Slide 5
Optimization Example 1
Objective function: Min. y(x) = 20x2 80x10
Control variable x range: 0
10
Non-constrained
1400
1200
1000
Y
800
600
400
Solution Found
200
0
-200 0
10
15
Slide 6
Optimization Example 2
Objective function: Min. y(x) = 20x2 80x10
Control variable x range: 0 x 10
Balance equation y = 60x 100
Constrained (Solution Found)
1400
1200
1000
Y
800
600
400
Solution Found
200
0
-200 0
10
15
Slide 7
Optimization Example 3
Objective function: Min. y(x) = 20x2 80x10
Control variable x range: 0 x 10
Balance equation y = 20x 300
Constrained (No Solution)
1400
1200
1000
Solution not
found!
(Infeasible)
800
600
400
200
0
-200 0
10
15
-400
X
Slide 8
and
Q=0
Slide 9
Control Variables
Slide 10
Objective Functions
Minimize Real Power Losses
- To minimize real power losses in the system
Slide 11
Objective Functions
Minimize Shunt var Devices
- To minimize var generation from available shunt
var control devices
Slide 12
Objective Functions
Minimize Load Shedding
- To minimize load to be shed from the available
bus load shed schedule
Slide 13
Objective Functions
Maximize Voltage Security Index
AllBuses
Vi Vi ,avg
dVi
2n
Where,
Vi ,avg
Vi ,max
Vi ,min
2
dVi
Vi ,max
Vi ,min
2
Slide 14
Objective Functions
Maximize Line Flow Security Index
AllBranches
Si
Si
2n
Slide 15
Other Constraints
Bus Voltage Constraints
Branch Flow Constraints
Interface Flow Constraints
Slide 16
Slide 17
Slide 18
Slide 19
Slide 20
Slide 21
Slide 22
Slide 23
Optimal Capacitor
Placement
Slide 2
Purposes of Shunt
Capacitor Applications
Var support Primary benefit for
transmission systems and secondary benefit
for distribution systems
Voltage control Primary benefit for both
transmission and distribution systems
System capacity increase Secondary
benefit for transmission systems and primary
benefit for distribution systems
1996-2009 Operation Technology, Inc. Workshop Notes: Optimal Capacitor Placement
Slide 3
Purposes of Shunt
Capacitor Applications
System power loss reduction Secondary
benefit for transmission systems and primary
benefit for distribution systems
Billing charge reduction Not applied to
transmission systems but a primary benefit
for distribution systems
Slide 4
Slide 5
Power Flow
Based
Optimal
Slide 6
Optimal Capacitor
Placement in ETAP
Genetic Algorithm - Use Genetic method to
find optimal (sub optimal) solution
Expert System Initialization- Use power
system knowledge to find a good initial
solution
Slide 7
Genetic Algorithm
An optimization technique based on the
theory of nature selection
An iterative procedure that maintains a
constant-size population of candidate
solutions
Slide 8
Slide 9
Slide 10
Slide 11
Display Results
LF results for maximum loads
New capacitor locations and sizes
Slide 12
Plot Results
Loss reduction savings during the planning
period
Capacitor operation cost during the planning
period
Profit during the planning period
Slide 13
Report Results
Load Flow related reports
Slide 14
Example
Run NR Load Flow and look at bus voltages
(critical under voltage is set to 95% and
marginal under voltage is set to 98%)
Switch to OCP mode and look at the study
case settings
Run OCP and look at the voltage
improvements
Slide 15
Slide 2
Objectives
Human and animal safety
Carry and dissipate current into earth under
normal and fault conditions
Grounding for lightning impulses and surges
Low resistance to ground for protective
relays
Slide 3
Construction
Slide 4
Common Definitions
Earth Current
Ground Fault Current
Ground Potential Rise
Step Voltage
Touch Voltage
Slide 5
Slide 6
4 aR
a
2a
a2
a
4b 2
a2
b2
Slide 7
Slide 8
Slide 9
Slide 10
Slide 11
Slide 12
Slide 13
S f * (3I o )
Slide 14
Decrement Factor
Accounts for the asymmetrical fault current
Slide 15
Slide 16
Slide 17
Slide 18
Slide 19
IEEE Methods
Empirical method; limited applications
Slide 20
Slide 21
Slide 22
Slide 23
Slide 24
Slide 25
Slide 26
Slide 27
ETAP Real-Time
ETAP Real-Time
Maintenance
Operations
Financial
Engineering
Planning
As a component of the Enterprise Resource Planning
(ERP) system, ETAP optimizes the exchange of
information between diverse tiers of an organization
while channeling domain sensitive information.
ETAP Real-Time
Market Solutions
ETAP Real-Time
Real-Time Objectives
ETAP Real-Time
Advantages
One Centralized Solution
Knowledge of System Topology, Ratings, & Limits
Intelligent One-Line Diagram
Powerful Electrical Calculation Engines
Smart Optimization Engines
Enforce Complex Time-Dependent Logic
ETAP Real-Time
Architecture Requirements
Seamless Integration
Enterprise-Wide Access
Robust Client/Server
Windows Platform
ODBC/SQL Compliant
Fast Data Transfer
Scalable Modular
Design
Hardware Independent
ETAP Real-Time
V&V Requirements
System Architecture
ETAP Real-Time
System Architecture
ETAP Real-Time
ETAP Real-Time
ETAP Consoles
System
ETAP Real-Time
T103
ModBus
NetDDE
NetBeui
UCA
DNP
IPX/SPX (Netware)
ICCP
TCP/IP
IEC 60870
OPC
IEC 61850
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
ETAP Real-Time
Advanced Monitoring
Energy Accounting
Real-Time Simulation
Event Playback
Load Forecasting
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Advanced Monitoring
Intelligent Graphical One-Line & User-Interface
Voltage, Current, Power, Energy, Frequency,
Tap Settings, Switching Status, Operating
Modes,
State Estimation & Load Distribution
Operation, Process & Performance Monitoring
Alarm & Notification Management
On-Demand Control
Trending
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Advanced Monitoring
Monitoring Capabilities
Multi-Console Server/Client Monitoring
Graphical Monitoring via ETAP One-Line Diagram
Visual Monitoring via Watch Windows (MMI)
Archived (Historical) Data Retrieval / Display
Multi-Access Levels
Virtual Monitoring
Virtual Monitoring
Virtual Monitoring
Advanced Monitoring
Advanced Monitoring
1996-2009 Operation
Technology,
Inc. Workshop
Notes:
1996-2009
Operation
Technology,
Inc.Real-Time
Workshop Notes: Real-Time
Advanced Monitoring
Load
Estimator /
Distributor
Advanced Monitoring
State Estimator
Load Estimator / Distributor
Error Detection
1996-2009 Operation
Technology,
Inc. Workshop
Notes:
1996-2009
Operation
Technology,
Inc.Real-Time
Workshop Notes: Real-Time
Advanced Monitoring
Flow Rate /
Pressure
RPM
Daily Energy
Consumption
(Max/Min)
Energy Accounting
Energy Accounting
Energy Accounting
Real-Time Simulation
Real-Time Simulation
Predict System Response Based on
Operator Actions
Perform What If Operating Scenarios
Real-Time Simulation
Simulation Modules
Load Flow
Sequence-of-Operation
Motor Acceleration
Harmonics
Short-Circuit ANSI/IEC
Transient Stability
Arc Flash
Reliability Assessment
More...
Real-Time Simulation
Real-Time Simulation
1996-2009 Operation
Technology,
Inc. Workshop
Notes:
Real-Time
1996-2009
Operation
Technology,
Inc.
Workshop Notes: Real-Time
1996-2009
Operation
Technology,
Inc.Real-Time
Workshop Notes: Real-Time
1996-2009 Operation
Technology,
Inc. Workshop
Notes:
Event Playback
Event Playback
Event Playback
Playback Forward
Playback Reverse
Step Reverse
Next Event
Previous Event
Scan Forward
Scan Reverse
Display Options
Event Playback
Event Playback
Replay Archived Historian Data
Improve Operator Knowledge
Predict System Behavior On-Demand
Investigate Cause & Effect
Explore Alternative Actions
Load Forecasting
Load Forecasting
Load Forecasting
Predict Loading Up to Seven Days Ahead
Forecast Multiple Load Areas per Individual Meters
User-Adjustable Weather Variables & Load Profiles
Revise Forecasts Based on Loading & Weather
Conditions
Pattern & Load Profile Libraries
Load Forecasting
Adaptive Forecasting
Load Forecasting
Trending
Load Forecasting
Trending
View Up to 20 Trends in One Window
Create & View Unlimited Trend Windows
Auto-Scale Trends & Auto-Center Plots
Movable Cross-Hair for Reading Data Values
Zooming, Scrolling Backward / Forward in Time
P1+jQ1
Gen1
Load 1
Load 2
P2+jQ2
Gen2
Load 3
P3+jQ3
Gen3
P+jQ
Load 4
Load 5
Pn+jQn
Load 6
Genn
Initial Condition
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
P+jQ
Load 1
Gen1
Load 2
Gen2
Load 3
P3+jQ3
Gen3
Load 4
P+jQ
Load 5
Pn+jQn
Load 6
Genn
Optimized Condition
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Secondary Control
Control tie-line flows to meet schedules
ED?
No
Calculate ACE
{ Fuel Costs,
Flow Constraints,
MW Limits,
}
Do ED
{ New
Base
Generation
Settings }
Do MW
Sharing
{ Scheduled Frequency,
Scheduled Interchange,
Measured Frequency,
Measured Interchange,
}
Calculate
MW Change
Distribute
MW
Do MW
Sharing
{ New Generation Settings }
G1
G2
Gn
Freq.
Isoch
P = - 1/R f
Droop
F1
P1 = Pload P2
Gen. 1
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
MW
P2
MW
Gen. 2
Energy Management System
Freq.
Isoch
Droop
F1
P1 = Pload
Gen. 1
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
MW
P2 = Pload
MW
Gen. 2
Energy Management System
Freq.
Droop
Droop
F1
P1 = Pload
Gen. 1
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
MW
P2 = Pload
MW
Gen. 2
Energy Management System
Freq.
Droop
Droop
F1
F2
P1 = Pload MW
Gen. 1
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
P2 = Pload MW
Gen. 2
Energy Management System
Freq.
Droop
Droop
F1
F2
P1 = Pload MW
Gen. 1
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
P2 = Pload MW
Gen. 2
Energy Management System
Freq.
Isoch
Isoch
F1
P1 = Pload P2
Gen. 1
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
MW
P2
MW
Gen. 2
Energy Management System
Freq.
Isoch
Isoch
F1
EMS Action
P1 = Pload MW
P2 = Pload
Gen. 1
Gen. 2
MW
Economic Dispatch
Fast Solution
Robust Algorithms
Economic Dispatch
Generating Cost
Generation Dispatch
Economic Dispatch
Optimization Control
Optimization Objectives
Bus Voltage Constraints
Economic Dispatch
Economic Dispatch
Detailed Nonlinear Cost Function Modeling
Considers All Losses (cable, transmission lines,
transformer, etc.)
Maintains Adequate Reserve Margins
Considers Line Constraints
Economic Dispatch
Generation Constraints to Maintain Adequate
Online Reserves
Transmission Line Congestion Limits to Prevent
Overloads
Incremental Heat Rate Characteristics for Each
Generation Unit
Detailed Nonlinear Cost Function Modeling
Supervisory Control
Automation
Requirements
Auto Ctrl
Real-Time
Data
System
System
Topology
Energy Management System
Supervisory Control
System Automation
Supervisory & Advisory Control
Software-Based User-Defined System Logic
Simple or Complex Breaker Interlock Logic
User-Friendly Logic
C# Logic
Supervisory Control
Operation & Process Control
Evaluate Control System Settings
Reduce Control System Commissioning Time
Interchange Scheduling
Tariff Analyzer
Rate Structure Builder
Transaction Scheduling
Transaction Contract
Invoicing
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Interchange Scheduling
Interchange Scheduling
Create Detailed Buy & Sell Transaction
Schedules
Detailed Energy Transaction Reports for
User-Defined Period of Time
Evaluate Energy Cost for Multiple Transactions
per Location (Regions, Areas, Zones)
Transaction Management Tools
Energy Cost Analysis & Reporting
Graphical & Tabular Transaction & Cost Views
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Reserve Management
Operating Reserve Analysis
Spinning Reserve
Non-Spinning Reserve
Fuel Pressure
Reserve Management
Reserve Management
Identify System-Wide Reserve Capacity
Requirements
Monitor & Maintain Regulating, Contingency,
Interruptible Imports, & On-Demand Reserves
Easily Replace Generating Capacity & Energy
Lost Due to Forced Outages
Compensate for Curtailment of Interruptible
Imports from Other Areas
Ensure Reliable System Operation
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Load Preservation
Load Restoration
Load Shedding Validation
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Operation Dependent
Fast Response
Optimal Load Shedding
Load Preservation
Optimal Load Preservation
Fast Response Time
Reliable Operation
CB
Trip
Trigger
Signal
to CB
Fault
Clearing
Local
PLC
10
10
Trigger
Received
by PLC
Remote
PLCs
Time
ms
60
20
70
PLC
Output
Triggers
Load
CB
Open
60
Time
ms
70
120
PLC
Output
Triggers
Load
CB
Open
20
Trigger
Received
by PLCs
Time
ms
CB
Trip
Trigger
Signal
to CB
Fault
Clearing
Local
PLC
0.5
0.5
Trigger
Received
by PLC
Remote
PLCs
Time
Cy
3.5
PLC
Output
Triggers
Load
CB
Open
3.5
Time
Cy
PLC
Output
Triggers
Load
CB
Open
1
Trigger
Received
by PLCs
Time
Cy
CB
Trip
Trigger
Signal
to CB
Fault
Clearing
Local
PLC
Trigger
Received
by PLC
Remote
PLCs
Time
ms
56
11
61
PLC
Output
Triggers
Load
CB
Open
26
Time
ms
31
81
PLC
Output
Triggers
Load
CB
Open
11
Trigger
Received
by PLCs
Time
ms
Load Restoration
Restart Inhibition
Logical Load Sequencer
Load Restoration Priority
Load Restoration
Limitations
Fixed load priority
Stage
1
2
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Frequency Delay
Hz
Sec.
58.5
0.25
57.5
2.00
MW
Shed
10
30
Intelligent Load Shedding
Features
Detects after effects of disturbances
Limitations
Slow response time
Advantages
Access to system loading
Gen
Load 2
Load 3
j QL
Load 2
Gen
P=0
Load 3
Gen
P > P
Q >> Q
Load 3
Load 2
Gen
Load 3
Load 2
Gen
Load 3
P1 + jQ1
Load 1
P2 + jQ2
Gen1
Load 2
P3 + jQ3
Load 3
P4 + jQ4
P + j Q
Gen2
Load 4
P5 + jQ5
Load 5
P6 + jQ6
Load 6
Study Condition
P1 + jQ1
Load 1
P2 + jQ2
Gen1
Load 2
P3 + jQ3
Load 3
P4 + jQ4
P + j Q
Gen2
Load 4
P5 + jQ5
Load 5
P6 + jQ6
Load 6
Study Condition
P1 + jQ1
Load 1
Gen1
Load 2
P3 + jQ3
Load 3
p + j q
Gen2
Load 4
P5 + jQ5
Load 5
Load 6
Study Condition
P1 + jQ1
Load 1
Gen1
Load 2
P3 + jQ3
Load 3
p + j q
Gen2
Load 4
P5 + jQ5
Load 5
Load 6
Actual Condition
P1 + jQ1
Load 1
Gen1
Load 2
P3 + jQ3
Load 3
p + j q
Gen2
Load 4
P5 + jQ5
Load 5
Load 6
Actual Condition
P1 + jQ1
Load 1
Gen1
Load 2
P3 + jQ3
Load 3
p + j q
Gen2
Load 4
P5 + jQ5
Load 5
Load 6
Actual Condition
Load 2
Load 3
p + j q
Gen2
Load 4
P5 + jQ5
Load 5
Load 6
Actual Condition
Dependencies
Operator Display
Load MW
Loads to Shed
Spinning Reserve
ILS Server
X
Frequency Relay
ILS Server
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Intelligent Substation
Substation Automation
Switching Management
Load Management
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Intelligent Substation
Substation Automation
Flexible Automation
Programmable Logic Editor
Online Control
Intelligent Substation
Intelligent Substation
Benefits of iSub
Minimize Outages
Reduces Operating & Maintenance Costs
Intelligent Substation
Intelligent Substation
Intelligent Substation
Intelligent Substation
Automatic Supervision of Interlocks
Graphical Presentations of Safety Procedures
Local & Global Alarm & Warnings
Detect Fault Location - Distribution Systems
Equipment Diagnostics
Intelligent Interlocking System
Diagnostics of Disturbances
Automation with Supervisory & Advisory Control
Intelligent Substation
Intelligent Substation
Enforce Complex Logic for Device Protection &
Coordination
Programmable Logic Editor with Online Compiling
& Execution
Automatic Generation of Switching Sequences
Enterprise-Wide View of System
Automated Retrieval of All Data from the Substation
Intelligent Substation
Intelligent Substation
Automation Applications
Automatic Voltage
Control
Capacitor Control
Algorithm
Synchronism
Tap Position Monitoring
Substation Maintenance
Mode
Fault Detection
Load Curtailment
Sequence of Event
Recorder
Intelligent Substation
Intelligent Substation
Predictive Maintenance Through Analysis of
Operating Conditions
Sophisticated Built-In Control & Protection
Algorithms
Intelligent Substation
Intelligent Substation
Intelligent Substation
Intelligent Substation
Intelligent Substation
Switching Management
Switching Sequence Management
Intelligent Substation
Intelligent Substation
User-Friendly Switching Plan Builder
Intelligent Substation
Intelligent Substation
Checking of Select Switching Plans Against
Forbidden or Potentially Hazardous Actions
Unlimited Switching Plans Each with an Unlimited
Number of Switching Actions
Switching Order Reports Include Switching Mode,
Start / Stop Time, & Nature of Work
Simulate & Evaluate Switching Plans in All States
Prior to Execution
Intelligent Substation
Intelligent Substation
System Switching
Required for Scheduled Outage & Restoration
Required for Feeder Balancing & Load Transfer
Intelligent Substation
Intelligent Substation
ETAP SSM Features
An Integral Tool to PSMS
Specify Sequence from User-Friendly Spreadsheet
Intelligent Substation
Intelligent Substation
Switching Sequence Editor
Spreadsheet Editor to
Create & Modify Sequence.
Action on Switching Devices
and System Logic &
Procedures.
Actions Sorted Automatically by Groups
and Delay Time.
Editing Functions for Rearranging and
Modifying Sequences.
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Intelligent Substation
Intelligent Substation
Create Sequence from OLV
Intelligent Substation
Intelligent Substation
Build in Device Interlock
Embed System Control Logic
and System Procedure in a
Sequence
Use System Procedure for
Non-Switching Actions
(Checking, Lock, & Logging)
Intelligent Substation
Intelligent Substation
Build in Device Interlock
Complicated Interlock Logic
Specified in Switching Device
Pre-Condition Logic based on
Status of Other Devices and
System Operating Conditions
Post-Action Logic to Chain Switching Actions
Pre-Condition Logic and Post-Action Logic
Specified Separately for Open & Closing Actions
1996-2009 Operation Technology, Inc. Workshop Notes: Real-Time
Intelligent Substation
Intelligent Substation
Switching Sequence Simulation
Step & Auto
Execution of
Sequence
Intelligent Substation
Intelligent Substation
On-Line Sequence Execution
Intelligent Substation
Intelligent Substation
380 kV Substation
Intelligent Substation
Intelligent Substation
230 kV Substation
Intelligent Substation
Intelligent Substation
69 kV Substation
Intelligent Substation
Intelligent Substation
Double-End Substation
Intelligent Substation
Load Management
Demand-Side Management
Intelligent Substation
Intelligent Substation
Intelligent Load Management
Reduce Energy Costs
Reduce Peak MWh Costs
Reduce Mvar & Power Factor Penalties
Improve System Operation & Stability
Intelligent Substation
Intelligent Substation
Demand-Side Management
Load 7
Load 6 Load 6
MW
Time
Intelligent Substation
Intelligent Substation
Demand-Side Management
Shed 1
MW
Hold 1
Start 3
Start 1
Load 6 Load 6
Load 1
Intelligent Substation
Intelligent Substation
Demand-Side Management
Shift 6
Shed 1
Hold 1
Start 3
Start 1
Shift 6
MW
Load 1
Intelligent Substation
ETAP Real-Time
ETAP Real-Time
ETAP Real-Time
Operation
Maintenance
Planning
ETAP Real-Time
Monitor
Simulate
Operate
Analyze
Predict
Optimize
Manage
Control
ETAP Real -Time
ETAP Real-Time
Power System Monitoring & Simulation
ETAP Real-Time
Maintenance
Operations
Financial
Engineering
Planning
As a component of the Enterprise Resource Planning
(ERP) system, ETAP optimizes the exchange of
information between diverse tiers of an organization
while channeling domain sensitive information.
Market Solutions
Oil Refineries
Oil Platforms
Oil Production Fields
Chemical Plants
Mining
Manufacturing Plants
Health Care Facilities
Generation Plants
Data Centers
Switchgear & Relay Manufacturers
ETAP Real -Time
Objectives
Optimize Operation
Optimal Load Shedding
Prevent Downtime
Minimize System Losses
Minimize Energy Costs
Predict System Response
Train & Assist Operators
Prevent Outage Due to Operator Error
Safe Operation & Avoid Penalties
Improve Equipment Life Time
Provide Data Accessibility
ETAP Real -Time
System Architecture
T103
ModBus
NetDDE
NetBeui
UCA
DNP
IPX/SPX (Netware)
ICCP
TCP/IP
IEC870
OPC
Monitoring Capabilities
Multi-Console Server/Client Monitoring
Graphical Monitoring via ETAP One-Line Diagram
Visual Monitoring via Watch Windows (MMI)
Archived (Historical) Data Retrieval / Display
Electrical & Non-Electrical Metering Tags
OPC Interface Layer
Multi-Access Levels
Advantages of ETAP
Intelligence
Simple to Modify the System
Option to Override Monitored Data
Online Switching & Breaker Operation
Visual Monitoring (MMI) by Watch Windows
Advanced Monitoring
State Estimator
Load Estimator / Distributor
Error Detection
Global (Server) & Local Alarm & Warning
Alarm & Warning Acknowledgement
Equipment Overload Detection
Over-Voltage & Under-Voltage Detection
Graphical Notification via One-Line Diagrams
Pinned Data (Override Monitored Data)
Power System Monitoring & Simulation
Real-Time Simulation
Predict System Behavior to Operator Actions
Open/Close Circuit Breakers
Reject Generators
Load Impact & Ramping
Accelerate Motors
Protective Device Sequence-of-Operation
Event Playback
Replay Archived Historian Data
Improve Operator Knowledge
Predict System Behavior On-Demand
Investigate Cause & Effect
Explore Alternative Actions
Replay What If Scenarios
Optimization
Requirements
EMS
System
Control
System Topology
Energy Management System
Savings
Reduce Energy Costs
Reduce Peak MWh Costs
Reduce Mvar / Power Factor Penalties
Improve System Operation & Stability
Increase Equipment Life Time
Increase System Capacity
Optimal CB Combination
Load
MW
Shed
Load
Req. to
Shed
16.00
ILS Group1
7.22
2.00
4.57
ILS Group2
3.25
PLC Based
7.22
2.00
4.57
8.23
17.04
-1.04
22.02
-6.02
ILS Configuration
ILS Server
X
Frequency Relay
ILS Server
Intelligent Load Shedding
ILS Response
Response to Mechanical & Electrical Disturbances
Generator Breaker Trip
Utility Main Breaker Trip
Fuel Availability
Process Alarms
Faults in the System
Spinning Reserve Availability
User-Customizable Triggers
Intelligent Load Shedding
COCO
Data Exchange
International Standards
Flexible Operation
User Friendly
Slide 2
Slide 3
Elements
&
External Project
Connections
ETAP Database
Conversion
Exceptions
XML
ETAP
PowerStation
Project File
Slide 4
Exceptions
XML
Data
Mapping
External Project
ETAP Data
Exchange
ETAP
Existing Data
Slide 5
Data
Mapping
External Project
ETAP Data
Exchange
Exceptions
XML
ETAP
Slide 6
Equipment
Attributes
ETAP
Element
ETAP
Element
Properties
Slide 7
Slide 8
GIS Capabilities
Database mapping via a graphic user
interface
Display unlimited GIS presentations
Perform add, modify, or delete actions
Slide 9
Slide 10
Slide 11
Slide 12
Slide 13
Slide 14
DC Load Flow
DC Short-Circuit
Slide 2
Slide 3
Type of Studies
Load Flow Determine system operating
conditions and verify equipment continuous ratings
Short-Circuit Calculation Determine system SC
current and verify equipment SC capability
Battery Sizing and Discharge Calculation (IEEE
Std 485) Determine sufficient battery size to
provide required power in specified time duration
Slide 4
DC System Elements
DC System Source
Charger/Converter and Battery
DC System Loads
Static Load, DC Motor, Lump Load , and DC Elementary
Diagram
DC System Branch
Cable and Impedance
Slide 5
Purpose of DC LF Study
To determine system operating conditions -bus voltages, branch flows, and power
provided by various sources
To verify equipment continuous ratings
Slide 6
LF -- Battery Model
Constant voltage source behind battery
resistance .
Active voltage source if Vbus < Vrate
Slide 7
LF -- Charger Model
Constant voltage source, if I < Imax
Constant current source, if I > Imax,
injecting Imax into system
Inactive if Vout < Vbus
Constant power load to AC system
Slide 8
LF -- Inverter Model
Constant voltage source to AC system
Constant power load to DC system
Slide 9
LF -- UPS Model
If auction diode option is checked, then DC
system provides power to UPS AC load if
Vdc > Vac.
If auction diode option is not checked
and UPS AC input bus is energized, then UPS
becomes a source to DC system, similar to a
charger.
and UPS AC input bus is not energized, then DC
system provides power to UPS AC load.
Slide 10
LF -- DC Converter Model
Constant voltage source to output bus, if
I<Imax
Constant current source to output bus, if
I>Imax, injecting Imax into the bus
Constant current load to the input bus
Slide 11
LF -- Load Model
Motor
Constant P load, if Vmin <V<Vmax;
Static Load
Constant resistance load
Lumped Load
Constant power, resistance, current load
Slide 12
Slide 13
Slide 14
Slide 15
LF -- Branch Model
Cable
Constant resistance at maximum operating
temperature
Impedance
Constant resistance
Slide 16
LF- Adjustments
Cable Length Tolerance
Positive adjustment for DCLF & DCBS
Slide 17
Purpose of DC SC Study
To determine short-circuit fault currents and
fault contributions from different sources.
Maximum fault current
System equivalent impedance at fault location
Slide 18
SC -- Battery Model
Constant voltage source -- (Voc) behind
battery resistance
Voc may be calculated based on battery specific
gravity (SG)
Open Circuit Voltage (Voc) from library
User-Defined value (% Vpc)
Slide 19
SC -- Charger Model
Constant voltage source behind AC system
impedance (converted to DC side)
Constant current source, Ksc * Ifl
Slide 20
Slide 21
SC -- DC Converter Model
Constant current source, Ksc * Ifl, to faults
on output side of the system
Short-circuit contribution calculation stops at
DC converters
Slide 22
SC -- Load Model
Motor constant voltage behind transient
impedance
Static load and ED load are considered in
calculation
Slide 23
SC -- Branch Model
Cable
Constant resistance at minimum operating
temperature
Impedance
Constant resistance
Slide 24
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 2
Cell Size
Rated capacity of a lead acid battery or number of
positive plates in a cell
Period
Time interval for which the load is assumed to be
constant
Vpc
Volts per cell (individual cell voltage)
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 3
Types of Loads
Constant Power
As battery voltage decreases, their current increases.
Constant Resistance
As battery voltage decreases, their current also
decreases.
Constant Current
Load current is invariant to battery voltage changes.
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 4
MOV operations
Critical ventilation system motors
Fire protection systems actuators
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 5
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 6
DC to AC Inverters
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 7
Slide 8
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 9
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 10
Battery Modeling
Battery voltage based on manufacturer
battery discharge characteristic curves
Enter battery characteristic curves in battery
library
Interpolation / extrapolation is performed to
obtain battery size and discharge voltage
profile
Different interpolation methods to obtain Vpc
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 11
Characteristic Curves
Battery Characteristic Curves
1.5
1000.00
1.6
Time (min.)
1.67
1.75
100.00
1.78
1.81
10.00
1.84
1.88
1.92
1.00
10.00
100.00
1000.00
1.96
Slide 12
Interpolation Methods
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 13
Slide 14
Correction factors
Battery minimum temperature
Aging compensation
Initial capacity
Design margin
Voltage Requirements
Maximum system voltage deviation (charging voltage)
Minimum system voltage deviation (depends on final
Vpc)
Battery minimum discharge voltage (final Vpc)
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 15
Correction Factors
Same as battery sizing (no design margin)
Slide 16
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 17
Displayed Results
Tabulated results for battery voltage, bus
voltage and power flows through the entire
system
One-line diagram displayed results (similar
to DC load flow)
Complete set of plots that include battery
voltage, current, discharged AH and system
flows
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 18
Things to Consider
Obtain as many battery characteristic curves
as possible
Obtain specific curves for battery model and
type
Understand limitations of interpolation
methods
Use most conservative approach for your
system (load flow method or load
summation)
1996-2009 Operation Technology, Inc. Workshop Notes: Battery Sizing & Discharge
Slide 19
Control relays
Can be either AC or DC control circuit
1996-2009 Operation Technology, Inc. Workshop Notes: Control Circuit System
Slide 2
Solenoids
Other Purpose
Auxiliary devices and special control circuits
Regulator and regulating systems
Slide 3
CSD Modes
Edit Mode
Add/Delete Elements
Change Connections
Modify Engineering Data
Simulation Mode
Run Simulations Simulation Triggered by Manual Action or
Clicking the Run Button
Update Source Duty Cycle
Generate Event View, Alert View, and Report
Slide 4
CSD Setup
CSD Elements
Device Coil, Solenoid, General Load and Light
Contact Fixed and Form-C; Macro-Controlled Contact
Branch Wire and Impedance
Bus and Node
PD CB and Fuse
CSD Source
Elementary Diagram (ED) brought in from DC System
Each ED can be placed in only one CSD
Slide 5
Slide 6
Slide 7
Device Property
Device Rating
Burden Rating and Inrush Rating
Burden Rating Can be Constant P, Z, or I
Inrush Rating Always Modeled as Constant Z
Inrush Duration length of Time Applying Inrush Rating
Vpickup & Vdropout Editor and Study Case Options
Slide 8
Control Logic
Control Logic Setup
A Coil/Solenoid Can Control State of Multiple Contacts
Library Contact, Library Overwrite Contact & User Defined Contact
Macro Controlled Contact Time Varying Switch
Contact Property
Data Hold by Controlling Device
Top Time Taken for Contact Switching to Off-Normal State
when V >= Vpickup is maintained for controlling device.
Trelease Time Taken for Contact Retuning to Normal State
when V <= Vdeopout is maintanined for controlling device.
Each contact has its own Top and Trelealse
Special Conditions
If Duty Cycle Model Used for a Device, Control Logical Does
Not Apply.
1996-2009 Operation Technology, Inc. Workshop Notes: Control Circuit System
Slide 9
CSD Simulation
Initial Steady State
Switching Device in Specified State, Macro-Controlled Contact
in Initial State, and Contact In Normal State
CSD Find Initial Steady state
V Limit Not Checked When Switching Mode
V Limit Checked When Clicking Run Button
Simulations
CSD Behaves as A Simulator
One Action Triggering Simulation From Current Steady State
to Next Steady State
When Run Button Clicked, Simulation Starts from the Initial
Steady State and Then Simulate Duty Cycle Actions
Slide 10
Simulation Method
Two Methods by CSD
Sequence of Operation Simulation
Sequence Simulation with Vd Calculation
Features
Seq Vd
Op
Logical Simulation
Slide 11
Alert
Voltage Alert Base Defined in Voltage Limit Section
Current Alert for Device, Contact, and Wire
Adjustment
R Adjustment for Contact and PDs
Temperature Adjustment for Wire R
Length Adjustment for Wire
Burden Rating Adjustment for Coil and Solenoid
1996-2009 Operation Technology, Inc. Workshop Notes: Control Circuit System
Slide 12
Alert View
Critical and Marginal Violation of Pickup and Dropout Voltage
Critical and Marginal Current Violation of Devices, Contact, and
Wire
Alerts are Generated only for Simulation with Vd Calculation
Crystal Report
Input Data
Voltage Drop and Power Flow Report for Each Step
All Alerts
Report is Generated only for Simulation with Vd Calculation
1996-2009 Operation Technology, Inc. Workshop Notes: Control Circuit System
Slide 13
Slide 14
Revision
Revision is Not Supported for All the Data in Device Contact
Page
Revision May Not Be Supported for Cable Schedule Data and
Wire Impedance Page Data
All Other CSD Data Are Supported by Revision
Slide 15
Slide 16
CSD Vd Calculation in BS
CSD Vd Calculation
Option to Perform Vd Calculation in BS Study Case
Vd Calculation Conducted for Each CSD with Bus Voltage from BS
Vd Calc Results for all CSDs Saved in One Report
CSD Vd Alert Also Available
All CSDs Use Same Time Reference as Battery Discharge
Slide 17
Special Considerations
Switching Events Must Be Triggered by Macro Controlled
Switch
Slide 18
Reliability Assessment
Slide 2
Slide 3
Slide 4
Slide 5
Slide 6
Slide 7
Simultaneous failure
of T5 & T6 and failure
of T5 or T6 at a time is
considered.
Slide 8
Component Model
A
P-
Slide 9
Component Model
Mean Time To Repair in hours (MTTR)
Time required to repair a component outage
and/or restore the system to its normal operating
state
Mean Repair Rate (No of repairs per year) ( )
= 8760/MTTR
A+ P)
Slide 10
Component Model
Mean Time Between Failure (Year) (MTBF)
MTBF = MTTF + MTTR/8760
Forced Outage Rate (Unavailability) (FOR)
FOR = MTTR/(MTBF*8760)
Switching Time
Time in hours for isolating a fault occurred at the
component
Assume that CB/Fuse trip a fault instantaneously
Time for replacing a failed element by a spare one,
in hours rP
1996-2009 Operation Technology, Inc. Workshop Notes: Reliability Assessment
Slide 11
Single-Component Concepts
Two-State Model
A two-state up/down representation is used for
the operation/repair cycle of a component (such
as lines, cables, transformers, breakers, fuses,
switches, loads and busbars)
=(
UP
Up
A+ P)
..
DOWN
Down
..
MTTF
MTTF
MTTR
MTTR
Slide 12
Component 2
1, r1
sys
rsys
1
r
11
2, r2
2
r ( r )( r )
2 2 11 2 2
sys
r
11
r
22
sys
Slide 13
2, r2
(r r )
12 1 2
sys 1 r
r
11 2 2
(r r )
12 1 2
rr
rsys 1 2
r r
1 2
Component 2
Slide 14
System Modeling
Fault Current Interruption
Only overcurrent protection devices (CB and
fuse) can interrupt fault current
Fault current interruption is assumed to be
instantaneous
Assumed to have no effect on components with
multiple source connection and isolated from
fault by CB/fuses
Slide 15
System Modeling
Fault Isolation
All switching devices can isolate faults. CBs and
fuses isolate fault instantaneously
Switches isolate fault at switching time of the
faulted component
Switching time for a load is equal to that of the
closest component
Slide 16
System Modeling
Normally Open Tie: Open tie PD can be closed
(switching time) to provide back up power
Two terminal buses should be energized
Can have several PDs connected in series and
with one or more open
Slide 17
Slide 18
Slide 19
Slide 20
i(f/yr)
j Ne e, j
r
e
,
j
ij
j Ne
Slide 21
The EENS and ECOST for a bus are calculated based on loads that
are directly connected to that bus due to the outage of that bus.
1996-2009 Operation Technology, Inc. Workshop Notes: Reliability Assessment
Slide 22
ECOSTi
EENSi
UN
i i
N
i
Slide 23
UN
i i
N
i i
Slide 24
EENSi
ECOSTi
Slide 25
System Interrupted
IEAR($/kWhr)
Energy
Assessment
EENS
i
N
i
Rate
Index,
IEAR ECOST
EENS
Slide 26
Slide 27
a=
0.003 failure/year
p=
0.002
= 0.001 failure/year
Slide 28
p CB1
a CB 2
a CB 3
Utility
Main Bus
Slide 29
U LP1
MTTR CB1
MTTR CB 3
a CB 3
p CB1
MTTR CB 2
MTTRUtility
a CB 2
Utility
Main Bus
0.334
0.013
25 .692 hours
Slide 30
Slide 31
Slide 32
Failure rates of the two transformers are taken to be 1; MTTR = 200 hr.
Therefore the failure rate at Bus 2 due to double contingency:
(r1 r2 )
8760
1r1
2 r2
8760
1 2
double
1 1 (200 200)
8760
1 200 1 200
1
8760
Slide 33
sin gle
U1
CB1
CB1
A
MainBus
Bus 2
CB 6
double
sin gle
Slide 34
Slide 35
Slide 2
Slide 3
Generating Voltage
WTG > 150 kW generate 0.69 kV or higher
Step-up transformer (outside or inside
tower) raises the voltage to 10-30 kV
Slide 4
Generator Technology
Induction Generator
Induction generator with
variable rotor resistant
Doubly fed induction
generator (DFIG)
Converter interfaced
gearless, multi pole
1996-2009 Operation Technology, Inc. Workshop Notes: Wind Turbine Generator
Slide 5
Slide 6
Slide 7
Rotor Designs
Options include:
Upwind vs downwind
Passive vs active yaw
Common option chosen is to
direct the rotor upwind of the
tower with a tail vane
Slide 8
Slide 9
Wind Power
The lift force (only) turns windmill blades
for useful power output
Windmill is a fan running backwards.
Slide 10
Wind Drag
If the angle of attack of a blade is too large,
the wind simply pushes against the blade,
exerting a drag force but no lift. When the
drag is too great, a stall occurs.
Wind turbines are designed to operate in
winds up to 35 mph, but must be able to
survive 100 mph gales.
Random turbulent winds create strong
torques that can fatigue the structure.
1996-2009 Operation Technology, Inc. Workshop Notes: Wind Turbine Generator
Slide 11
Power Curve
Electrical Power output at
different wind speeds
Field measurements
Site complexity makes it
difficult to produce power
curves exactly
Does not provide power at a
certain average wind speed
1996-2009 Operation Technology, Inc. Workshop Notes: Wind Turbine Generator
Slide 12
Slide 13
Slide 14
Slide 15
Example
Calculate how much more power is
available at a site where the wind speed is
12 mph than where it is 10 mph
P ~ V3
P2 /P1 = (V2 / V1)3
P2 = (12/10)3 * P1 = 1.73 * P1
Slide 16
Power Coefficient
Efficiency of wind to electric energy
conversion
Power Output W/ m2 = Power Curve / Rotor
Area
Electrical Output / Wind Input
Depends on pitch angle and AOA
Depends upon ratio of downstream to
upstream wind speeds (Vo/V)
1996-2009 Operation Technology, Inc. Workshop Notes: Wind Turbine Generator
Slide 17
Power Coefficient
Theoretical maximum value of 0.59
Slide 18
Cp Curves
Maximum power generated at P1 max and P2 max
Slide 19
Speed Control
To capture more energy
To protect the rotor, generator and electronic
equipment from overloading
Slide 20
Optimum Constant Cp
Speed-Limited
Power-Limited
Cut-out speed
Slide 21
Pitch Control
Large horizontal axis turbines
Pitch is varied to hold Cp at largest value possible
up to rated speed of the turbine
Slide 22
Slide 23
Wind Model
Slide 24
Converter Control
Slide 25
Slide 26
Slide 27
V2 = (H2/H1)
V1
Grasslands: 0.14
1996-2009 Operation Technology, Inc. Workshop Notes: Wind Turbine Generator
Slide 28
Hybrid System
Slide 29
Slide 30
T=4 sec
Load reduced to 100 kW
Frequency runaway
Shunt Load to be added
Slide 31
Operating Data
Slide 32