TITLE
Method Statement Excavation to Line and Grade
2. SCOPE OF WORK
2.1
General Description
2.2.2..2 Utilities
As-built underground utility drawings checked and
confirmed with Area Owner, E/I Maintenance
supervisor, ISD Supervisor, or another Qualified
Person.
Location of utilities are marked and clearly
identified.
Prior to the use of excavating equipment,
underground utilities have been located by hand
digging.
Underground utilities are protected, supported or
removed when excavation is open.
Excavation works may proceed without danger to
electrical power line, water pipeline, gas line,
telephone, sewers, and other utilities, etc.
2.2.3 Demobilization