Project Name Project No.: Eekly Eport
Project Name Project No.: Eekly Eport
Project Name
Period
Project No.
From : 05/01/2013
To : 10/01/2013
Contractor Name:
Original Contract Amount
L.E. 20,000,000
L.E. 20,000,000
N/A
Starting Date :
Anticipating:
Actual:
Contract Duration:
Original:
6 Months
Days
Extension:
N/A
Days
Actual:
N/A
Days
N/A
CES
Total Works
No.
Report No.
Date
Const. works
Earth works
06/01/201
3
07/01/201
3
08/01/201
3
09/01/201
3
10/01/201
3
Base Course
Curbs
Prime
Coat
Binder
Cours
e
Tack
Coat
Wearing
surface
LOG
T ON SITE:
CONTRACTORS FORCE:
Equipment
pe
Total Number
Total Working
Hours/week
Comments
Staf
Position
Total Number
Total Working
Hours/week
48
Project Manager
48
Site Manager
60
12
96
Engineers
nk
12
96
Admin
57
57
Surveyors
12
96
ucks
18
144
Controls Engineer
Safety Officer
60
12
96
Foreman
18
171
Office Boys
16
Operator
Mechanic
12
114
ader
mpactor
ctor
Direct Labor
Total Number
Comm
rane
RACTOR
FORCE:
Manpower
tion
Total Number
CTION
Total Working
Hours/week
Comments
Electrician
57
Truck Drivers
Other Drivers
60
600
Unskilled
Total Number
Night Watchman
12
120
Cleaner
12
120
57
Gate Keeper
LOG:
No.
Ins. No.
Date
1.
225
05/01/2013
2.
226
05/01/2013
3.
227
05/01/2013
4.
228
05/01/2013
5.
229
05/01/2013
6.
230
05/01/2013
7.
231
05/01/2013
8.
232
06/01/2013
9.
233
06/01/2013
10.
234
08/01/2013
11.
235
08/01/2013
Description of Inspection
Revision
No.
No. of
Copies
SUBMITTALS LOG:
No.
1.
2.
Sub.
No.
Description
Type
98
3.
4.
CONSTRUCTION PROBLEMS:
Description:
Rev. No.
Date
Submitted
Received
Action Required/Taken:
Letter ref.EG/ECG/GHPNC/RW/012013/LT-104
2- Letter ref.EG/ECG/GHPNC/RW/012013/LT-107
3- Letter ref.EG/ECG/GHPNC/RW/012013/LT-110
1-
Copy to:
Head Office
Consultant
QS
Other
____________