CAVSP Checklist
CAVSP Checklist
audiovisual system achieves the clients goals or objectives and that the system
performs in accordance with the system design. By providing this list to the audiovisual industry, InfoComm is establishing a set of commissioning guidelines to help industry professionals and their clients communicate effectively about their expectations for system performance.
In many projects, not all tests are required for each system or circumstance. Owners and designers can elect to include or exclude certain criteria, as they may not be meaningful for a particular system. In some instances,
certain performance capabilities are less critical and therefore stringent review of those capabilities is unnecessary. In other circumstances, certain elements of the system may require more critical review, and the performance
of that aspect of the system may need to exceed the general guidelines outlined here. The verification process for each system should be an agreed upon set of tests between the client and the designer.
Project Title
Description
Location
Architect
Designer
Date
Integrator
Client
VII
VIII
IX
X
XI
XII
XIII
IT
OP
PHYSE
PHYSI
SERV
WL
DOC
Information Technology
Operational
Physical Environment
Physical Installation
Serviceability
Wireless
Documentation
Item Title
Description
AP-100
Multi-channel Loudspeaker
System Output
Verify that the audio outputs of a multi-channel loudspeaker system are assigned correctly with
regards to designated outputs as defined in the project documentation.
AP-101
Phantom Power
Verify that phantom power is provided at the correct voltage and correct locations as defined in the
project documentation.
AP-102
Loudspeaker Zoning
Verify that loudspeaker zones are wired as defined in the project documentation.
AP-103
Loudspeaker Impedance
Verify that all loudspeaker circuits have the correct impedance as defined in the project
documentation
AP-104
Verify that audio signal is being distributed accurately through the system as defined in the project
documentation.
AP-105
DSP Programming
Verify that all DSP-based products have been programmed as defined in the project documentation
and that editable, non-compiled source copies of the program have been saved and delivered to
owner.
AP-106
Emergency Muting
Verify that any required muting or operational change of the installed sound system(s) are in
accordance with local regulations in the event of a life safety or similar emergency.
AP-107
Verify that the background acoustic noise levels within audiovisual spaces are within the required limits
as detailed in the project documentation. This test is specifically related to ambient noise levels and
not audio system quiescent noise which is tested separately.
AP-108
Verify that all devices that are part of the Assistive Listening System have been tested as a complete
end-to-end personal listening system. Verify that the Assistive Listening System complies with
regulatory requirements and adheres to project documentation.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Item Title
Description
AP-109
Verify calibration of permanent audio system inputs so there is minimal difference between any input
signal level after the first common gain adjustment.
AP-110
Speech Reinforcement
System Headroom
Verify that audio system is capable of performing above nominal operating levels without distortion, as
defined in the project documentation.
AP-111
Alignment of Microphones
Verify proper alignment, setup, and placement of microphones in the system as defined in the project
documentation.
AP-112
Microphone Level
Alignment
Verify calibration of microphones so there is microphone input level alignment as defined in the project
documentation between any input signal level after the first common level adjustment.
AP-113
Verify that the speech reinforcement system is operating without feedback and at audio levels as
defined in the project documentation.
AP-114
Conferencing Echo
Suppression Performance
Verify that a system with conference capability shall perform at nominal operating levels in a full duplex
mode without echo or latency.
AP-115
Physical Loudspeaker
Alignment
Verify that loudspeakers are placed and aimed as defined in the project documentation.
AP-116
Time Alignment
Verify that all loudspeaker time alignment is configured as defined in the project documentation.
AP-117
Loudspeaker Polarity
Verify that all loudspeakers are tested to ensure they all have correct polarity as defined in the project
documentation.
AP-118
Loudspeaker Circuit
Impedance Measurement
Measure the impedance of all loudspeaker circuits and compare the results with values defined in the
project documentation.
AP-119
Loudspeaker Transformer
Tap Setting
Verify the loudspeaker transformer tap setting is in constant voltage systems as defined in the project
documentation.
AP-120
Verify that in a conferencing audio application, the incoming audio level from the far-side is checked
and adjusted in the system as defined in the project documentation. The far-side audio should
come from a verified standard source that provides an audio signal at a level defined in the project
documentation. This source should also be used to check all conferencing rooms that will be
connected in conference.
AP-121
Verify that the total harmonic distortion of the installed audio system is less than the level defined in
the project documentation.
AP-122
Verify that the audio level provided by the AV system exceeds the background noise level as defined
in the project documentation.
AP-123
Verify that equalizers have been adjusted in accordance with the preferred acoustic response curves
as defined in the project documentation.
AP-124
Speech Reinforcement
System Electronic
Frequency Response
Verify that the electronic frequency response of the speech reinforcement system meets or exceeds
that which is defined in the project documentation.
AP-125
Verify that the electronic frequency response of the audio playback system meets or exceeds that
which is defined in the project documentation.
AP-126
Verify that no audible noise caused by improper installation of any equipment provided in completed
system(s) is evident. Perform buzzes and rattles test, monitoring for both direct, or indirect,
unintended noise generated as a result of the AV system operating within its designed parameters
in the room environment. Noise that may be present as a result of non-AV system related sources
(for example, air handler rattles due to excessive volume of air through it) is not in scope with this
verification.
AP-127
Measure latency of the audio system, and verify that latency does not exceed requirements defined in
the project documentation.
AP-128
Audio Dynamics
Verify use of audio dynamics, including but not limited to noise compensation, automatic gain control,
gating, feedback suppression, compression, limiting, delays, and levelers, and that an editable copy
of the program file is provided to the owner.
AP-129
Sound Masking
Verify that audio system sound pressure levels and equalization is calibrated as defined in the project
documentation to provide masking of speech.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Item Title
Description
AP-130
AV Room Reverberation
Time
Verify reverberation time and compare to expectations defined in the project documentation.
AP-131
Verify that the audio system provides speech reproduction as defined in the project documentation.
AP-132
Verify that coverage of the audio systems in listener areas meets the performance requirementsas
defined in the project as verified by ANSI/INFOCOMM 1M-2009, Audio Coverage Uniformity in
Enclosed Listener Areas. Perform separate tests for all independent systems within the project,
including but not limited to program sound, speech reinforcement, and show relay. Documented
project specific requirements will supersede ANSI/INFOCOMM 1M-2009, however it is strongly
recommended that the testing methodology from ANSI/INFOCOMM 1M-2009 be utilized.
AP-133
Verify that all audio routes are tested from endpoint to endpoint via the appropriate midpoint(s) for
operation and routing as defined in the project documentation.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Item Title
Description
VP-100
Verify that all displayed images do not have pixel failures (bright or dead pixels) that exceed the
requirements of the project documentation or the manufacturers specifications.
VP-101
Verify that the combined installation of projector and screen provides a displayed image that is
correctly aligned to the active projection screen surface without misalignment unless an alternative
condition is specified in the project documentation.
VP-102
Image Geometry
Verify that all displayed images are correctly focused, have the correct image geometry and are free
from distortion (e.g., stretching, keystone, barrel/pincushion). Any requirements for projection mapping
or image shaping to unusual surfaces should be validated in accordance with the requirements of the
project documentation.
VP-103
Projected Display
Brightness Uniformity
Verify that the combined installation of projector and screen provides a display to the viewer that
meets the project requirements for uniformity of brightness across the area of the display.
VP-104
Verify that the display(s) are sized appropriately to the distance relative to the viewer as defined in the
project documentation.
VP-105
Verify that all video routes are tested from endpoint to endpoint via the appropriate midpoint(s) for
operation and routing required by the project documentation.
VP-106
Colorimetry
Verify calibration of all video displays to ensure they display colors uniformly to a common reference
standard as defined in the project documentation.
VP-107
Verify that the system should conform to the appropriate viewing category as defined in the project
documentation and/or as verified by ANSI/INFOCOMM 3M-2011. Documented project specific
requirements will supersede ANSI/INFOCOMM 3M-2011, however it is strongly recommended that
the testing methodology from ANSI/INFOCOMM 3M-2011 be utilized. The projected image contrast
ratio should be measured for all projected images within the system.
VP-108
Multiple Resolution
Performance of Video
Displays
Verify that the system(s) display(s) all resolutions required by project documentation on all displays
within the system. Consideration should be given to maximum resolution and aspect ratio of each
display to ensure that the anticipated resolutions are within display tolerances of the display devices.
Any variation other than accurate display of resolutions should documented in the test report such
pixel shift, geometric distortion, artifacts from scaling, letterboxing, pillarboxing, windowboxing, or
similar distortion of the image.
VP-109
Verify that the EDID (Extended Display Idenification Data) management plan has been implemented
per the project documentation.
VP-110
Verify that the HDCP (High-bandwidth Digital Content Protection) management plan has been
implemented per the project documentation.
VP-111
Inspect camera image quality through the full lens operation. Check lens for proper operation. Check
proper operation of pan/tilt operation.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Item Title
Description
AVP-100
Verify that audio and video signals are being routed to the recording device and that the recording
device is operating correctly, as defined in the project documentation.
AVP-101
Audio/Video Sync
Verify that audio/video synchronization is maintained to ensure the proper time alignment of
signals during playback at the point of user experience or transmission as defined in the project
documentation.
AVP-102
Verify that the radio frequency and satellite intermediate frequency distribution systems provide all
services to all endpoints as defined in the project documentation.
AVP-103
Emergency
Communications
Verify that emergency communications systems properly receive inputs and information from other
systems including but not limited to life safety systems, security systems, and weather notifications,
and deliver appropriate notifications to target audiences, comply with regulatory requirements, and
adhere to requirements defined in the project documentation.
AVP-104
Source Testing
Verify that "real life" sources other than test generators have been tested on the completed system
using the common communication and/or media types the system is designed to support as defined
in the project documentation.
AVP-105
Genlocking (video
synchronization)
Verify that the video synchronization of the system is performing as defined in the project
documentation.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Item Title
Description
CABL-100
Cable Supports
Verify that all cables are adequately supported throughout their lengths as defined in the project
documentation.
CABL-101
AV Connector Verification
Verify that all cable terminations are made securely and meet the recommendations of the connector
and cable manufacturer, published standards, as well as in accordance with requirements defined
in the project documentation. Verify that terminations are appropriate for application with correct pin
configuration and connection to equipment with a minimum of adaptors.
CABL-102
Verify that all patch panels have been labeled as defined in the project documentation. Verify that all
labeling is machine-printed, consistent, durable, accurate, and legible.
CABL-103
Verify that all patch panels have been correctly wired and configured as defined in the project
documentation, having regard for connectivity, consistency of phase and normalization.
CABL-104
Verify that all AV equipment power cables are managed as defined in the project documentation. Verify
that cables are managed in a uniform and acceptable manor so as not to compromise safety/OEM
warranty, AV signal quality, and/or future field service.
CABL-105
AV Connector Seating
Verify that all connectors are correctly keyed, seated, and latched to respective connection points as
defined in the project documentation. Conditions where physical parameters exceed the connector's
ability to maintain full seating should be resolved as defined in the project documentation.
CABL-106
Cables Dressed
Verify that cables are dressed to ensure that all rack and site cables are installed to provide
serviceability, safety, and aesthetics as defined in the project documentation.
CABL-107
Verify all AV connector plate input and output labeling as defined in the project documentation.
CABL-108
Verify that all cables are identified by a unique ID as defined in the project documentation. Verify that
this unique ID is displayed permanently at both ends of the cable, is legible, and is positioned where it
can be seen without undue disturbance.
CABL-109
AV Connector Plate
Consistent Labeling
Verify that AV connector plates have consistent labeling throughout the project as defined in the
project documentation. Verify that all connector plates are given unique identifiers and that this
identifier is used as defined in the project documentation. Verify connector plate labeling is consistent
with control surfaces.
NOTE: Unique identifiers should be permanently marked on finished plates unless there are aesthetic
reasons not to.
Item Title
Description
CABL-110
Cable Ties
Verify that where appropriate, cable ties are used to secure the cables and that the correct type of
cable tie is usedin the projectas defined in the project documentation.
CABL-111
Cable Separation
Verify that both site and rack cables have appropriate separation according to signal type and level as
defined in the project documentation.
CABL-112
Verify that sufficient cabling is available so the device can be placed in a serviceable location as
defined in the project documentation.
CABL-113
Verify that cables are not bent beyond their minimum bend radius as specified in cable data sheet in
order to maintain signal integrity as defined in the project documentation. Project documentation may
state a larger radius to allow for a safety margin.
CABL-114
Termination Stress
Verify that all cable terminations have been completed and adequately supported so as tominimize
weight or stress on the termination point and/or connector.
CABL-115
Verify that cables are only bundled together when their construction, signal type, and signal level are
compatible and will not cause measureable crosstalk or interference between cables.
CABL-116
AV System Cabling
Verification
Verify that all cabling is of the correct type and routed correctly from point to point as defined in the
project documentation.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Item Title
Description
CON-100
System Response to
Emergency Condition
Verify that any required response of the installed Audio Visual system(s) in the event of a life safety
or similar emergency operates in accordance with local regulations and as defined in the project
documentation. This item specifically excludes sound system response to an emergency condition
which is covered under item AP-106.
CON-101
Verify that mobile devices that are to be supported are integrated and operating as defined in the
project documentation.
CON-102
Control System
Communications
Verify that all control communications are tested from endpoint to endpoint via the appropriate
midpoint(s) for operation and functionality as defined in the project documentation.
CON-103
Verify that the look and feel of the control system is consistent with requirements as defined in the
project documentation. This includes touch screen pages, buttons, navigation, gestures, and all other
ways the user will control the system and environment. Verify that the control system provides the user
response time and maximum latency as defined in the project documentation.
CON-104
Verify that all macro functions executed by the control system conform to requirements as defined in
project documentation.
CON-105
Verify that AV control system interfaces to and controls systems provided by others and conforms
to requirements as defined in the project documentation. This may require coordination with other
service providers or the owners support organization.
VI ELEC: Electrical
CAVSP Item
Number
Item Title
ELEC-100
AV Equipment Connected
to Proper Circuit
ELEC-101
Description
Verify that all AV equipment is powered from the designated power circuit and outlet as defined in the
project documentation. No additional (non-AV) equipment should be connected unless permitted in the
project documentation.
Verify that all electrical sub-distribution systems provided by the AV contractor in equipment racks,
furniture, etc. meet local regulatory requirements for electrical integrity.
NOTE: In this context "sub-distribution" refers to localized distribution systems providing power to
multiple items of equipment from a single outlet.
Item Title
Description
ELEC-102
Power Sources
Verify that the sources of mains voltage AC power to be used for the supply of audiovisual equipment
are correct per the project documentation and have been tested to the outlet in accordance with local
electrical standards.
ELEC-103
Grounding/Earthing
Verify that all elements of the audiovisual system are correctly bonded to an electrical ground/earth in
accordance with the requirements of regulatory authority.
ELEC-104
Power Sequencing
Verify that the power sequencing of devices is correct per the project documentation.
ELEC-105
DC Power Distribution
Verify that all DC powered devices are receiving the proper voltage and current for normal operation.
When distributing or extending DC power, the total current draw must not exceed the available
potential of the power supply.
ELEC-106
UPS Operation
Verify that the uninterruptible power supply (UPS) is performing to the specifications as defined in the
project documentation.
ELEC-107
Verify that the audiovisual systems for normal operation on the resumption of power following a hard
electrical power outage. Power loss recovery shall include the resumption state on power recovery.
Resumption state shall be the control system start up condition/start page (where applicable) and
resetting all devices to a known state as defined in the project documentation.
ELEC-108
Power Monitoring
Verify power monitoring equipment is working and reporting as defined in the project documentation.
Power monitoring equipment should be verified with a known electrical load where possible. If power
monitoring data is being collected for an energy management system, connectivity with the system
should be verified.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Item Title
Description
Verify that the network for audio, video, and control is of a suitable topology to support the services to
be delivered.
IT-100
Network Topology
Verify that real-time audio, video, and control supporting applications such as telepresence, medical
procedures and live television coverage are in real-time with the live event with no delay which requires
the correct network topology and low-latency encoding/decoding.
Verify that all networked systems have been installed on the proper network for AV devices as required
by the client and specified by the project documentation. The network and associated firewalls have
been configured to allow for the network traffic and transversal to associated networks as required for
proper operation as defined in the project documentation.
IT-101
Telephony
Verify that any required telephony connections to the AV system are in place and connectivity is verified.
IT-102
Unified Communications
Verify any connections to IT-based unified communication applications that will interface with the AV
system have been planned for and integrated. Coordination for voice, video, instant message systems,
and computer-based communication tools should be considered.
IT-103
Verify that PoE (Power over Ethernet) devices are supplied with correct power required for device
normal operation. Verify under practical conditions that the switch providing PoE has the capacity to
power all of the devices that are connected to it.
IT-104
AV IP Address Scheme
Verify and document that all network-connected equipment has the correct IP address, subnet mask,
hostname, and gateway configuration as required for correct operation. This can be by static, DHCP,
or reserved DHCP configuration.
IP address scheme can be generated based on a list of equipment, location, VLAN requirement and
MAC address.
IT-105
Verify that the correct and valid wireless network configuration (e.g., channel no., SSID, TX power) to
ensure legal operation in defined areas of use.
Verify that there is adequate channel separation between any client wireless networks that are required
to co-exist in the same area.
Item Title
Description
Verify that the required network bandwidth is available for control, audio, video, and data as part of
either a shared or a dedicated audiovisual network.
The peak load of the network will need to be determined, including how much bandwidth it consumes,
when it occurs, and what the duration is. This is especially critical on shared networks where total
load demands may be managed directly by IT staff or remain unknown. The peak load will need to be
factored into the overall bandwidth requirements. Periods of peak loads will need to be determined prior
to bandwidth testing or perform testing over a weekly or monthly cycle.
IT-106
Network Bandwidth
IT-107
Verify that the required Quality of Service (QOS) is in place for audio, video, and data as part of either a
shared network or a dedicated audiovisual network.
IT-108
Network Performance
Under Full Functional Load
Verify that the network can provide the required operational performance to carry control, audio, video,
and data under production load and at times of peak production load (refer 133 Network Bandwidth).
Verify that the shared or dedicated network is secure as defined in the project documentation and
accessible to suit the required audio, video and control systems.
IT-109
Network Security
IT-110
Verify the network is protected from potential Information Security risks including intrusion, remote
access, viruses, spy-ware, and malware, and that effective protection and homogenous policies are in
place and in use for infrastructure, servers, workstations, controllers, network connected equipment
and mobile devices.
Verify that the content delivery network is in place and provides the required connectivity, bandwidth
and Quality of Service (QOS) for the required audio, video and control systems.
Verify that all required content licensing has been acquired.
IT-111
Application Integration
Verify that the audiovisual and control systems have been integrated and fully configured with headend
software, including monitoring and asset management, databases, web-based front ends, digital
signage software and systems, content generation and distribution platforms, and appliances as
defined in the project documentation.
Verify that the wireless network is protected in accordance with the clients information security polices
from unauthorized access and provides the required connectivity for the audio, video, and control
systems.
IT-112
Many audio, video, and control platforms do not support the full suite of wireless security policies.
Verify with the client's information technology group that compatible wireless security protocols can be
deployed for each product set when using a shared wireless network.
Where a dedicated audiovisual wireless network is provided, verify that the potential IT wireless network
is coordinated to avoid interference.
IT-113
Verify that the Digital Enhanced Cordless Telephony (DECT)/Unlicensed Personal Communications
Services (UPCS) design can be implemented for the required number of channels given the limited
number of available channels and effects of interference on system reliability and channel count.
IT-114
Remote Access
Verify that remote access to AV and IT systems are configured as defined in the project documentation.
Accounts, networks, and other credentials are provisioned and configured to allow proper offsite or
off-network access. This will likely require coordination with the clients IT staff and require the client or
clients support staff to participate in the testing.
Verify that all systems authentication credentials are configured correctly. Any temporary credential used
during system installation and commissioning should be removed.
IT-115
Identity Management
IT-116
Remote Management
Verify that remote management tools such as virtual touch panels, internal web applications, or
manufacturers applications are configured and functional as required by the project documentation
and/or manufacturers specification.
IT-117
Enterprise Management
Tools
Verify that enterprise management tools such as central monitoring client/server or web-based
application have been installed and connected to all systems they are required to monitor or control
as specified in the project documentation. All functionality required by the project documentation,
including, but not limited to, control monitoring and reporting has been verified.
User and group authentication and authorization are verified based on the requirements from the project
documentation. Connectivity with the central directory, database or other identity authority should be
verified.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Item Title
Description
OP-100
Verify that a battery management plan has been completed and supplied in the project documentation
package to owner.
OP-101
Verify that any system content that will be used in initial operations has been supplied to the owner, AV
vendor, or third-party producer and that the system content has been has been loaded and tested in
the completed AV system.
OP-102
Verify there is a plan for managing the content to be delivered by the audiovisual systems including the
means to create content, change or modify content and update content when new information needs
to be conveyed.
OP-103
Software
Verify that all control programming code, DSP configuration files, and any other associated software has
been provided per the project requirements.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Item Title
PHYSE-100
HVAC Commissioned
PHYSE-101
Backing/Blocking/Framing
Description
Verify the HVAC system has been tested and balanced prior to completing checklist item AP-122 and
AP-107.
Verify that installed backing, blocking and framing meets project documentation requirements and
industry standards for installation means and methods.
Backing, blocking, and framing are installed architectural elements that supports the mounting of
audiovisual devices or elements, typically in walls or ceilings.
PHYSE-102
Verify that installed floor, wall and ceiling boxes meet project documentation and regulatory authority
requirements.
PHYSE-103
Device Enclosures
Verify that device enclosures are suitable to house the device intended and that all necessary
environmental controls are incorporated into the enclosure as defined in the project documentation.
PHYSE-104
Verify that human factor elements for audience and system users are installed and configured as defined
in the project documentation.
PHYSE-105
Structural Mounting
Verify configuration and compatibility for structural accommodations and all mounting hardware based
on the intended application. All equipment mounting hardware shall be installed in the manner specified
by the hardware manufacturer.
PHYSE-106
Divisible Spaces
Verify that the divisible spaces provide the functionality specified as defined in the project
documentation.
PHYSE-107
Vibration
Verify that the physical environment is suitable for the intended audiovisual systems in relation to all
sources of vibration affecting visual fidelity/stability of equipment such as video conferencing cameras,
document cameras and fixed screen and projector locations.
PHYSE-108
Lighting
Verify that that the lighting systems are suitable for the intended video and control systems for each type
of application (e.g., video conferencing, presentation, broadcast, performance) as defined in the project
documentation.
PHYSE-109
Verify that the area is clean and dust-free and suitable for equipment installation and that no further
work is planned that will release contaminants into the AV equipment area. Verify that the area released
is isolated from any areas not yet released.
PHYSE-110
Protection of Installed
Equipment
PHYSE-111
Finishes
Verify AV equipment, furniture, fixtures, and accessories against the project documentation.
PHYSE-112
HVAC Operations
Verify the HVAC system has begun continuous operations in advance of equipment operations.
PHYSE-113
Accessiblity
Verify that all systems are accessible in accordance with regulatory requirements.
PHYSE-114
Coordinated Construction
Elements
Verify that the elements, including but not limited to spatial requirements and building services required
by the AV system that are coordinated with other disciplines, have been provided per the project
documentation.
Item Title
Description
PHYSI-100
Cable Containment/Conduit
Verify that installed containment/conduit capacity and routes meet project documentation requirements
and industry standards for installation means and methods.
PHYSI-101
Verify that AV equipment is installed at the location and/or in the rack or enclosure by defined in the project
documentation. Equipment is installed per the elevation or other specification provided by the project
documentation or the manufacturers specification.
PHYSI-102
AV Equipment Labeling
Verify that all AV equipment has been labeled in accordance with the requirements of the project
documentation. All labeling must be consistent, durable, accurate and visible without dismantling of subassemblies, including but not limited to racks and desks.
PHYSI-103
Verify that the AV rack(s) thermal gradient has been inspected and all equipment is operating within
manufacturers guidelines.
PHYSI-104
Verify that all AV equipment has been installed, aligned, or angled correctly as defined in the project
documentation. Level and plumb are the default requirement unless particular angles or other alignment are
defined in the project design.
PHYSI-105
AV Rack Cleanliness
Verify that all components installed in AV equipment racks are free from dirt, dust, water, or any other
element that would compromise the performance and/or longevity of the AV system.
PHYSI-106
Optical Components
Cleanliness
Verify that all optical components, such as lenses and mirrors, are free from dirt, dust, damage, or markings
that would compromise the optical performance of those system components.
PHYSI-107
Turnover of Accessory
System Elements
Verify that any equipment that may be considered portable and/or otherwise not specifically incorporated
into the installed AV system(s) has been setup, configured, and tested.
PHYSI-108
Non-End-User Controls
Protection
Verify that installed items with user-facing controls that are not intended for end-user access have been
covered, disabled, or otherwise secured to prevent end-user operation. This includes items such as
amplifier controls, power switches, or other adjustment knobs or switches.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Verify that equipment in the project is secured per the project documentation. All security systems,
devices and manufacturer security accessories are installed and verified to be operating correctly within
manufacturer specification.
PHYSI-109
Equipment Security
Verify that keyed devices have been keyed as defined in the project documentation and other devices
requiring configuration have been configured per the project documentation and are verified to be operating
within specification.
PHYSI-110
Site Security
Verify that all elements of the AV system are free from loss, damage, or tampering.
PHYSI-111
Handling of Accessories
Otherwise Undefined
Verify that there is uniform handling of items that may have been pre-packaged with primary system
equipment from manufacturers but which have no documented planned use in the AV system(s).
Examples include extra (non-local) international power cords, additional remote controls and/or AV hookup
cables. Unless otherwise noted in design documentation, the owner should be given the opportunity to
take possession of these items in a bulk turnover during site inventory process.
XI SERV: Serviceability
CAVSP Item
Number
Item Title
Description
SERV-100
Verify that all input and output panels are accessible and meet all requirements for user access and
placement. This includes all mounting locations including walls, floors, racks, furniture, surfaces, and/or
other locations.
SERV-101
All equipment shall be accessible and capable of being maintained, serviced, cleaned, or adjusted
as necessary. All equipment requiring regular cleaning or maintenance shall be accessible without
requirement for special equipment or tools that would disrupt the normal use of the facility and systems
therein.
SERV-102
Rack Clearance
Verify rack placement and use for physical stability in accordance with the project documentation and
regulatory authority. Further, ensure the rack placement allows safe and complete working access for
technicians to perform upgrades and on-going servicing of the system.
SERV-103
Access Panels
Verify any panels that have been installed to provide access to any type of AV equipment are properly
sized and positioned as detailed in the project documentation.
Item Title
Description
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes
Verify that the environment is suitable for the required wireless services (RF and IR) to provide audio,
video, and control, and can be implemented for the required number of channels as defined in the
project documentation.
WL-100
Wireless Coordination
WL-101
Verify that the the operation of wireless audio systems (RF and IR) is as defined in the project
documentation. This includes the proper operation of receiver and transmitter elements, that operation
is free of interference, and that the wireless systems provide coverage for stationary or moving devices
throughout the area specified in the project documentation.
WL-102
Verify that the operation of wireless video systems (RF and IR) is as defined in the project
documentation. This includes the proper operation of receiver and transmitter elements, that operation
is free of interference and that the wireless systems provide coverage for stationary or moving devices
throughout the area specified in the project documentation.
WL-103
Verify that the operation of wireless control systems (RF and IR) is as defined in the project
documentation. This includes the proper operation of receiver and transmitter elements, that operation
is free of interference, and that the wireless systems provide coverage for stationary or moving devices
throughout the area specified in the project documentation.
All devices in the system that utilize wireless signals are coordinated with each other and the existing
wireless frequency spectrum (as well as with existing owner furnished equipment, equipment installed
by others, and systems or services that may exist in the same geographic area) to ensure a minimum of
interference or cross-talk between transmission paths.
Item Title
Description
DOC-100
As-Built Drawings
Complete
Verify that a complete set of accurate as-built drawings indicating all AV devices, AV device locations,
mounting details, system wiring and cabling interconnects, and all other details has been provided as
defined in the project documentation.
DOC-101
Integrator's Testing
Verify that any integrator's testing requirements have been performed and approved as defined in the
project documentation.
DOC-102
Third-Party Testing
Verify that any third party testing requirements have been performed and approved as defined in the
project documentation.
DOC-103
Final Acceptance
Verify that a final acceptance of the project has been issued by the owner or owner's representative,
acknowledging that the project is 100% complete and all required deliverables, services, checklists,
testing, verification and signoffs have been received, and all requirements defined in the project
documentation have been satisfied and completed.
DOC-104
Substantial/Practical
Completion
Verify that a conditional acceptance of the project has been issued by the owner or owner's
representative, acknowledging that the project or a designated portion is substantially/practically
complete and ready for use by the owner, however some requirements and/or deliverables defined in
the project documentation may not be complete.
DOC-105
Site Inventory of AV
Equipment
Verify that all equipment is in shop or on site as defined in the project documentation. List all equipment
in system NOT present, and why.
DOC-106
Owner's Testing
Verify that any owner's testing requirements defined in the project documentation have been performed
and approved.
DOC-107
Manufacturer's Testing
Verify that any manufacturer's testing requirements defined in the project documentation have been
performed and approved.
DOC-108
General Contractor's
Testing
Verify that any general contractor's testing requirements defined in the project documentation have been
performed and approved.
DOC-109
Consultant's Testing
Verify that any consultant's testing requirements defined in the project documentation have been
performed and approved.
DOC-110
Software Licensing
Verify that the usage and ownership rights have been assigned as defined in the project documentation.
Item Title
Description
DOC-111
Wireless Frequency
Licensing
Verify that the correct and valid wireless frequency licensing permits have been obtained to ensure legal
operation of the systems.
DOC-112
Verify that the video system test report has been completed and issued to the proper entity as defined in
the project documentation.
DOC-113
Verify that the audio system test report has been completed and issued to the proper entity as defined
in the project documentation.
DOC-114
Verify that the control system test report has been completed and issued to the proper entity as defined
in the project documentation.
Verify that samples of all equipment to be used as defined in the project documentation have been
submitted for approval.
DOC-115
Approval of Samples
DOC-116
DOC-117
User Manuals
Where samples of products have been required for approval, verify that the products that are delivered
are the same and of the same quality.
Verify that manufacturers user manuals are delivered to the owner in a format defined in the project
documentation (binders, PDFs, etc.) or disposed of in a responsible manner (recycling), if the owner
specifies that they do not wish to receive the manuals.
Integrator- or programmer-created manuals and documentation shall be delivered to the owner in a
format defined in the project documentation.
Verify that manufacturers product warranty cards are provided to the owner. The owner shall be notified
of the effective start date of the warranties and the coverage period.
Extended warranties that require activation shall be activated by the integrator or otherwise as defined
in the project documentation. If activated by the integrator, proof of activation and effective coverage
dates will be provided.
DOC-118
Warranties
Integrator provided warranties on labor and workmanship shall be provided to the owner with an
effective start date and coverage period.
Integrator provided extended warranties on products shall be provided to the owner with an effective
start date and coverage period.
Third-party warranty information shall be provided to the owner with an effective start date and coverage
period.
DOC-119
Final Commissioning
Report and System
Turnover
Verify that the final commissioning report has been completed, issued to the proper entity, and accepted
as defined in the project documentation.
DOC-120
Required Close-Out
Documentation
Verify that a complete set of as-built system documentation has been provided as defined in the project
documentation.
Criteria
Responsible Measurement/
Party
Pass/Fail
Notes