Method Statements For Reinforcement Bars
Method Statements For Reinforcement Bars
Make some arrangement to curing for cover blocks. ( we have to 7 days curing)
Order the reinforcements by sending the bar schedule to bar bending yard.
Check the R/F which is coming from the yard by using get pass and bar schedule.
Clean the formwork before we lay the slab and beam reinforcements.
In slab we have to select lap placement in both sides symmetrically. Place it one
by one in both sides.
Place the covering blocks and chairs with in proper spacing. (minimum spacing
between two chairs or two cover blocks less than 900mm)
Check the reinforce placement according to bar schedule and structural drawing.
Reinforcements (slab net) lay with the proper spacing and check the bar sizes, if
the correct bars are place in correct direction. Keep the reinforcement bars always
align. Supervisor has to check the alignment of slab reinforcement bars.
After the placement of all R/F bars we have to remove all binding particles and
other debris.
The shear reinforcements are place with proper spacing and correct way. The lap
positions are changing by using different length of bars.
Safety Activities