Formulas - Math For PMP
Formulas - Math For PMP
If you think a formula is missing here but required in PMP exam. Post a comment and we will add to this table.
1. PERT
2. Standard Deviation
3. Variance
4. Float or Slack
5. Cost Variance
6. Schedule Variance
7. Cost Perf. Index
8. Sched. Perf. Index
9. Est. At Completion (EAC)
Percentage complete
EV/ BAC
11. Var. At Completion
BAC - EAC
12. To Complete Performance Index TCPI Values for the TCPI index of less then 1.0 is good
because it indicates the efficiency to complete is
less than planned. How efficient must the
project team be to complete the remaining
work with the remaining money?
( BAC - EV ) / ( BAC - AC )
Bigger is better (NPV)
FV / (1 + r)^n
Bigger is better (IRR)
Bigger is better ((BCR or Benefit / Cost) revenue
or payback VS. cost)
Or PV or Revenue / PV of Cost
Less is better
18. BCWS
19. BCWP
20. ACWP
21. Order of Magnitude Estimate
22. Budget Estimate
Sigma
-5% - +10%
N(N -1)/2
Probability * Impact
((Ceiling Price - Target Price)/buyer's Share
Ratio) + Target Cost
1 = 68.27%
2 = 95.45%
3 = 99.73%
6 = 99.99985%
Net Income Before Taxes (NEBT) / Total Sales OR
Net Income After Taxes ( NEAT ) / Total Sales
NEBT / Total Assets OR
NEAT / Total Assets
NEBT / Total Investment OR
EF = (ES + Duration - 1)
EVA = Net Operating Profit After Tax - Cost of Capital (Revenue - Op. Exp - Taxes) - (Investment Capital X % Cost of
Capital) EVA - Economic Value Add Benefit Measurement - Bigger is better