Method of Statement
Method of Statement
Method of Statement
(Mechanical & Electrical)
Revision 0
Prepared for:
____________
December 2016
Table of Content
1
3
4
Description
ELECTRICAL
1.1
Installation of cable conduit works
1.2
Installation of cable trunking works
1.3
Installation of cable tray works
1.4
Installation of cable ladder works
1.5
Installation of cable and termination works
1.6
Installation of sub distribution board works
1.7
Installation of LT Main Switchboard works
HVAC EQUIPMENT INSTALLATION
2.1
Installation of Chiller works
2.2
Installation of cooling tower works
2.3
Installation of pump works
2.4
Installation of air handling unit (AHU) works
2.5
Installation of Heat Exchanger works
PIPEWORK INSTALLATION
DUCTWORK INSTALLATION
PAGE
3 - 16
17 - 30
31 - 35
36 - 44
1.
ELECTRICAL
1.1
Purpose
To define the method of installation for Cable Conduits.
Document/Drawing/Standard Reference
Working Drawings.
Singapore Standard CP5: 1988 (Code of practice for electrical
Installation)
Equipment/Tools/Material Requirements
Concrete Drill.
Hand Tools.
Hand Drills.
Hacksaw.
Measuring Tape.
Scaffolding.
Ladder.
Marker Pen.
3
Pre-Preparation Work
Ensure that site access and location is clear and free of debris and obstruction.
Marked out all relevant positions or locations on the working drawings for the
installation to proceed.
Safety Precautions
Proper ladder should be secured by tight rope/wire, proper roller clamp on suitable
hook.
Work Procedures
1.
Refer to working drawings and marked out the position of conduit saddle on the
Working drawings.
2.
Marked out the relevant positions to install the conduit saddle at the walls and
ceilings.
3.
Cut the conduit to the required length. Use the conduit Reamer or half round file to
smoothen the sharp edges at both end of the conduit.
4.
Confirm actual location of conduit. Drill the required diameter at the walls and
ceilings.
5.
6.
Install conduit box by turning the conduit box in to the threaded conduit. Use
monkey pliers it tightens up the conduit box.
4
By making use of the conduit bender, fabricate 90-degree bend. Off set to meets the
site condition.
8.
Insert the raw plugs into the drilled holes of walls and ceilings.
9.
10. Touch up the edges, bending and scratches areas of conduit ends to touch up with
2nd layer of final coat paint.
1.2
Purpose
Document/Drawing/Standard Reference
Working Drawings.
Equipment/Tools/Material Requirements
Hand Tools.
Concrete Drill.
Hand Drills.
Hack Saws.
Measuring Tapes.
Fiber Cutter.
Scaffolding.
5
Ladder.
Marker Pen.
Pre-Preparation Work
Ensure that site access and location is clear and free of debris and obstruction.
Marked out all relevant positions or locations on the working drawings for the
installation to proceed.
Safety Precautions
Proper ladder should be secured by tight rope/wire, proper roller clamp on suitable
hook.
Work Procedures
1.
Refer to the Working drawings and marked out the trunking bracket supports
position on the Working Drawings.
2.
Marked all positions and locations of trunking bracket supports on the walls and
ceiling.
3.
Drill all the relevant holes for anchor bolts or inserts on walls and slab areas.
4.
Mount the supporting bracket or threaded rod by making use of the anchor bolt or
insert.
6
Measure, mark and cut the cable trunking according to shop drawing and site
condition.
6.
7.
Install the cable trunking together with the necessary factory made 90- degree
elbow, tee or reducer joints accordingly.
8.
Install all the points with copper earth link to maintain the earth continuity
1.3
Purpose
To define the method of installation for Cable Trays.
Document/Drawing/Standard Reference
Working drawings.
Equipment/Tools/Material Requirements
Hand Tools.
Impact Drill.
Hand Drill.
7
Hack Saw.
Measuring Tape.
Fiber Cutter.
Scaffolding.
Ladder.
Marker Pen.
Expansion Bolts
Pre-Preparation Work
Ensure that site access and location is clear and free of debris and obstruction.
Marked out the relevant positions or locations on the working drawings for the
installation to proceed.
Safety Precautions
Identify the proper voltage to use, where hand tools, equipment are concerned.
Work Procedures
1.
Refer to the Working drawings and marked out the tray bracket supports position.
2.
Marked out all positions and locations of tray bracket supports on the walls and
ceiling.
3.
Drill all the relevant holes for expansion bolts on walls and ceilings.
4.
Mount expansion bolts and bracket supports to walls and ceilings. Tightened to
required torque where necessary.
5.
6.
1.4
Purpose
Working Drawings.
Equipment/Tools/Material Requirements
Impact Drill.
Hand Tools.
9
Hand Drill.
Hack Saw.
Measuring Tape.
Fiber Cutter.
Scaffolding.
Ladder.
Marker Pen.
Expansion bolts.
Pre-Preparation Work
Ensure that site access and location is clear and free of debris and obstruction.
Marked out all relevant positions or locations on the working drawings for the
installation to proceed.
Safety Precautions
Identify the proper voltage to use, where hand tools, equipment are concerned.
Work Procedures
1.
Refer to the Working drawings and marked out the ladder bracket supports position
on the Working Drawings.
2.
Marked out the position of Cable Ladder bracket supports at the slab.
3.
4.
Install the expansion bolts and bracket supports. Tighten to the required torque
where necessary.
5.
Mount cable ladder and fittings with bolts, nuts, and washer.
6.
1.5
Purpose
Cable Schedule.
11
Equipment/Tools/Material Requirements
Impact Drill.
Hand Tools.
Hand Drill.
Hack Saw.
Measuring Tape.
Masking Tape.
Scaffolding.
Ladder.
Marker Pen.
Cable Cutter.
Ensure that site access and location is clear and free of debris and obstruction.
Marked out all relevant positions or locations on the working drawings for the
installation to proceed.
Safety Precautions
Identify the proper voltage to use, where hand tools, equipment are concerned.
Work Procedures
12
Check Working drawings, Electrical Single Line Diagram, and Cable Schedule to
identify the cable routing and type of cable sizes required.
2.
Identify all the cable length required for cable laying and termination for the various
locations on drawings.
3.
4.
With the aid of a suitable marker pen write down the Equipment Number, Cable Size
& Type, and Cable Run Length on the masking tape.
5.
Next, marked the length of the cable. Affixed one piece of the masking tape at the
beginning of the cable.
6.
Record the Equipment Number, Cable Size and Type, Cable Run Length in an
appropriate form.
7.
Now, unroll the cable drum and lay the cables on the cable trays.
8.
Cut the cable to the required length after the cable was laid. Marked the other end of
the cable with the piece of masking tape Affixed it at the position where the cable
was cut at the point.
9.
Secure the cable that was laid by temporarily affixing with wires. When all required
cables are completely laid, secure the cables permanently to the cable tray with
cable ties.
10. Terminate the cables to panels with suitable cable glands, cable adapter, cable lugs,
and colored sleeves, where required.
1.6
Purpose
Working Drawing.
13
Equipment/Tools/Material Requirements
Hand Tools.
Hand Drill.
Crane/Lorry crane.
Measuring Tape.
Sling belt.
Scaffolding.
Ladder.
Marker Pen.
Rubber Mat.
Pre-Preparation Work
Check plinth size, height level and location according to working drawings.
Safety Precautions
Work Procedures
1.
Check sizes and hole position of mounting base frame for SP and DB panel.
2.
Mark out the Expansion Anchor Bolt positions onto the plinth based on the base
frame holes.
3.
Install the Expansion Anchor Bolt according to Method Statements mentioned in the
document.
14
1.7
Purpose
Working Drawings
Equipment/Tools/Material Requirements
Hand Tools
Measuring Tape
Ladder
Spirit-Level
Pre-Preparation Work
Ensure that site access and location is clear and free of debris and obstruction
Marked out all relevant positions or locations on the working drawings for the installation
to proceed.
Check plinth size, height level and location according to working drawing.
Safety Precautions
Work Procedures
1.
Position the lorry crane at the 1st Basement and set up the crane rigger.
16
Tie up the belt on the C-Channel base frame of the panel to be hoist and lift the panel to
ground floor by lorry crane.
3.
4.
5.
Mark out the first point and last point on the plinth for LT Main Switchboard
6.
Check panel in section labeled with 1, 2, 3 and refer to Panel Layout Arrangement
Drawing attached.
7.
Position the panel section on the plinth follow by 1, 2, 3 from left to right.
8.
9.
10.
Cover all the rear PVC, fiber cover and metal door with the screw.
17
2.
Purpose
Document/Drawing/Standard Reference
Equipment/Tools/Material Requirements
Measuring Tape.
Impact Drill.
Torch Lamp.
Water Level.
Winch.
Hydraulic Jack.
Protective Sheet
Pre-Preparation work
Check Chiller for the correct model and type upon delivery at site.
Check Chillers plinth size, location and height according to Plinth Layout and working
drawings.
Check and verify the correctness in type, size & quantity of vibration isolators.
Check on the clearance of delivery route of chillers from ground level to the plant room.
Apply for clearance for mobile crane, low bay trailer, at least one day before the actual
lifting activities is carried out.
18
Safety Precautions
Confirm documentation for mobile crane gear equipment before use is required.
Only qualified lifting supervisor, signaller and rigger shall be in command and control the
lifting activities.
Work Procedure
1.
Check for chiller orientation and alignment where concrete plinth dimensions provided is
in accordance with the shop drawing.
2.
Mark, drill and install anchor bolts for vibration isolators to correct position.
3.
Check that size and hole positions of vibration isolators are correct.
4.
Install Expansion Anchor Bolt to the inertia base according to the Method Statement for
Installation of Expansion Anchor Bolt.
5.
6.
7.
8.
9.
Connect electrical supply wiring and other field control wiring system.
10. Cover the Chiller with protective sheet. For prevention of damaged to corners especially
when Chiller is located at the common material /equipment delivery route, plywood
covers are ideal for protection.
11. Check and adjust the level of Chiller after water filling.
19
2.2
Purpose
Document/Drawing/Standard Reference
Equipment/Tools/Material Requirements
Measuring Tape.
Impact Drill.
Torch Lamp.
Water Level.
Crane
Catch Pallet.
Hydraulic Jack.
Chain Block
Protective Sheet
Pre-Preparation work
Check Cooling Tower for the correct model and type upon delivery at site.
Check Cooling Towers plinth size, location and height according to Plinth Layout drawing.
20
Check and verify the correctness in type, size & quantity of vibration isolators.
Check on the clearance of delivery route of Cooling Towers from ground level to the
location where the Towers are erected.
Apply for clearance for mobile crane, low bay trailer, at least one day before the actual
lifting activities is carried out.
Safety Precautions
Only qualified lifting supervisor, signaller and rigger shall be in command and control the
lifting activities.
Work Procedure
1.
Check for Cooling Tower orientation and alignment where concrete plinth dimensions
provided is in accordance with the shop drawing.
2.
Mark, drill and install anchor bolts for vibration isolators to correct position.
3.
Check that size and hole positions of vibration isolators are correct.
4.
Install Expansion Anchor Bolt to the inertia base according to the Method Statement for
Installation of Expansion Anchor Bolt.
5.
6.
7.
Lift Cooling Tower Bottom Module onto the Base Channel and fix by Bolts / Nuts.
8.
Lift Cooling Tower Upper Module onto the bottom module connect both modules by bolts
& nuts.
9.
Lift the fan deck and discharge cowl onto the upper module.
Document/Drawing/Standard Reference
Equipment/Tools/Material Requirements
Measuring Tape.
Impact Drill.
Torch Lamp.
Water Level.
Catch Pallet.
Hydraulic Jack.
Protective Sheet
Pre-Preparation work
Check Pump for the correct model and type upon delivery at site.
22
Check Pump plinth size, location and height according to Plinth Layout drawing.
Check and verify the correctness in type, size & quantity of vibration isolators and inertia
block for the pump.
Safety Precautions
Only qualified lifting supervisor, signaller and rigger shall be in command and control the
lifting activities.
Work Procedure
1.
Cast the concrete to inertia base and leave it set and harden for at least one week.
2.
Setting out the inertia base position on the plinth. Once completed, shift inertia base
onto the plinth.
3.
4.
Install Expansion Anchor Bolt to the inertia base according to the Method Statement for
Installation of Expansion Anchor Bolt.
5.
Shift the pump onto the inertia base position. Secure Pump to the inertia base by
Expansion Anchor Bolt and nut.
6.
7.
8.
Align and centre the Pump before actual start up. Pump shall be aligned and centred in
water-filled condition. (Alignment procedure and inspection report enclosed).
23
Document/Drawing/Standard Reference
Equipment/Tools/Material Requirements
Grinding/Cutting Machine
Mechanical Toolkit
Drill machine
Valves
Pre-Preparation work
1. Check the AHUs/FAHUs foundation and ensure it is as per approved drawings.
24
Safety Precautions
Only qualified lifting supervisor, signaller and rigger shall be in command and control the
lifting activities.
Work Procedure
Installation of Air Handling Units AHU
1. Shift the AHUs to the place of installation in safe manner using fork lift and crane as
applicable.
2. Ensure that the correct AHU is shifted to the place of installation.
3. Air inlet, outlet, fresh air connection and chilled water connection orientation are as per
approved drawings.
4. If the AHUs are shipped in multiple sections, the AHUs will be assembled strictly as per
the manufacturers instructions, and also consider: The AHUs/FAHUs are placed
correctly on foundation with vibration isolator rubber pads at right location. Identify the
correct sections that are to be bolted together.
5. Position fan section on housekeeping pad.
6. Install gaskets at all bolted joints that are required to be joined.
25
Work shall be carried out by the site MEP staff under the guidance of respected Engineer
and shall further be checked and approved by quality engineer.
An inspection request for the AHUs/FAHUs installation shall be submitted at least 1-2
days prior to the client/consultant or as agreed.
Check the unit model number and relevant accessories are available. Unit name plate as
per order.
Verify the construction of the house keeping base is as per the specification & drawing
for floor mounted AHU.
Verify the presence of approved vibration isolators, installed before the installation of
AHU.
Check the level of the AHU and verify the minimum slope as per drawing in the direction
of condensate pipe. Check the drain connection with U trap.
Verify the electrical connection of AHU with control panel as per construction drawing.
After installation inspect the AHU for physical internal and external damages.
Verify the absence of any vibration in AHU and its inner like fan, motor and coils etc.
Verify the process pipe connection with AHU along with valves, accessories and flow
switch etc.
Confirm the additional adequate support for all fittings and valves near AHU as per
construction drawings.
27
Verify the installation of 2-way modulating & gate valve of approved brand and quality as
per approved material.
Verify the presence of identification labels, safety and warning signs at their positions as
per approved materials.
Document/Drawing/Standard Reference
Equipment/Tools/Material Requirements
Measuring Tape.
Impact Drill.
Torch Lamp.
28
Water Level.
Lifting Gears.
Hydraulic Jack.
Protective Sheet
Pre-Preparation work
Check Heat Exchanger for the correct model and type upon delivery at site.
Check Heat Exchangers plinth size, location and height according to Plinth Layout and
working drawings.
Check on the clearance of delivery route of Heat Exchanger from ground level to the
respective location required.
Apply for clearance for mobile crane at least one day before the actual lifting activities is
carried out.
Safety Precautions
Only qualified lifting supervisor, signaller and rigger shall be in command and control the
lifting activities.
Work Procedure
Installation procedure shall follow the Plate type Heat exchanger Procedure issued by
specialist vendor
1. When the pipe system is connected with the heat exchanger make sure that no piping
loads (including torque effects) are transferred from the piping system to the heat
exchanger. The pipe system must be isolated against pressure pulsations, vibrations and
any thermal shock when connected to the heat exchanger.
2. Brazed heat exchangers must be mounted in a vertical position. In order to support the
heat exchanger it is advisable to use a mounting bracket fitted at the bottom of the heat
29
Installation procedure shall follow the Shell & Tube type Heat exchanger Procedure
issued by specialist vendor
1. The nozzles and end caps are covered to protect internal parts against damage in
shipping. Do not remove the covers until the piping is ready to be bolted to the
exchanger.
30
31
3.
PIPEWORK INSTALLATION
3.1
Purpose
The purpose of this procedure is to determine and control piping installation and
inspection activities. The piping installation refer to the construction, erection of all major
piping work carried out throughout the duration of the project.
Drawing
The drawing applicable for piping installation and work shall be as follows:
Pre-Preparation Work
Prior to commencement of any piping activity, Acromec shall provide and ensure that
AMECFW representative approves respective working drawings, Welding Procedure
Specification (WPS) and procedures.
Pre-insulation, cutting and preparation of pipe sections shall be carried out as per:
33
Pipe fitter shall use line up clamp to align the pipes (bridge tack-above the weld/bevel).
Temporary support and attachment if necessary shall be established prior to tacking. The
temporary attachment, support and bracket, which are to be welded to pipe, shall be
same as pipe material.
Tacking shall be carried out by approved Gas Tungsten Arc Welding (GTAW) Welder
(other may specify by respective WPS) Minimum tacking length shall be 2 x of pipes
thickness or 25mm, whichever is lesser. Minimum 4 nos. of tack weld shall be carried out
around circumferences of pipes.
Welding shall be carried out by qualified welder, with the guidelines of approved WPS, SC
Welder Qualification test procedure.
Identification such as spool no, joint no., welder no and inspection status shall be clearly
marked (by permanent marker pen) according to the sketch drawing for joint to be
welded. (see attached).
No welding shall be done if there is impingement on the weld area of rain, sleets, and
excessive wind or if the weld area is frosted/wet and not properly cleaned. Any paint, oil
34
Erection shall be carried out by safe manners and comply with safety requirements.
Installation of pipes supports shall be accompanied and in line with piping erection to
prevent unsafe working condition.
As far as practicable, all permanent specified item such as valves, gasket, strainer and
etc. shall be installed during erection. Temporary parts (gaskets, bolts and etc.) may be
installed if testing such as pressure test; leak test or flushing will affect the item.
Temporary item shall be identified and to be replaced after completion of respective
testing.
Pre-commissioning
Hydrostatic test
Testing / Records
The following inspection and testing shall be carried out to fulfill the Inspection and Test
Plan:
Material Receiving Inspection.
Fit up inspection applicable to joint prior to welding. Criteria such as bevel preparation,
root gap and root face shall be in accordance with the approved WPS.
Material shall be checked and shall comply with approved technical submittal.
Dimension measurement and slope shall confirm with approved working drawing.
Any non-conformances of works arise shall be stopped and rectified immediately. NCR
may be issued by QA/QC rep. for unresolved site non -conformance / deficiency.
Upon completion of welding, the weldment and adjacent area shall be properly cleaned
for Visual Inspection.
Visual inspection shall be carried out prior to commencement of any NDT work.
Inspection Form: Weld Visual Inspection Record For Piping
Line verification walk down/inspection shall be carried out upon completion of line(s).
This is to ensure complete installation and punch list item identification.
Outstanding items and major punch list identified shall be recorded and copy to be
handed over to the respective subcontractor for further action.
36
The above activities shall be carried out in accordance to Hydrostatic/Air leak test
procedure.
Forms
DUCTWORK INSTALLATION
4.
4.1
Purpose
To define the methodology and procedure of installation of HVAC ducts and accessories,
and to ensure that all concerned persons are familiar with the sequence of activities,
utilization of resources, and execution of the works in compliance with applicable Safety
and Quality Procedures, and Project Documents and Specification.
37
SMACNA
Scope of works
This document covers the following scope of works:
Outline the activities and the methods used for installation of HVAC ducts and
accessories. All activities will be carried out in accordance with the contract details and in
full compliance to the Contract Specifications and Documents. All work within the rights-ofway of the standards and specifications will be done in compliance with requirements
issued by authorities.
Equipment/Tools Requirements
Measuring Tape.
Grinding/Cutting Machine
Riveting tools
Water Level.
Lifting Gears.
Scaffolding
Materials Requirements
Acoustic Liner
Lagging Adhesive
38
Stuck up pins
Pre-Preparation work
Check all material delivered to site is inspected properly by QA/QC Engineer and check if
it is stored properly as per manufacturers recommendations.
Work shall be carried out by the site staff under strict supervision and guidance of the
concerned Supervisors / Foremen / Engineers.
The quality Engineer shall check all the installations as per the Installation Check list.
Safety Precautions
Confirm documentation for lifting gear equipment/ scaffolding before use is required.
Only qualified lifting supervisor, signaller and rigger shall be in command and control the
lifting activities.
Work Procedure
1. Ducts insulation and cladding materials, thickness and density, shall comply project
specification Sections.
41
drawing
3. Mark the location of ducting as per the approved layout and site conditions.
4. Install insulated ducts as per approved layout and conforming to site conditions.
5. S-cleat, C-Clamp, duct mate, flanges and angle shall be used for jointing ducts and
plumbed to duct. Jointing shall be in accordance with SMACNA standards.
6. Approved duct mastic will be used in the joints to avoid air penetrations.
7. Volume Control Dampers, Fire Dampers, and accessories shall be installed as per
approved shop drawings and manufacturers recommendations.
8. Insulate all the joints and make air flow labeling with approved materials as per project
specification.
9. Apply insulation for ducts continuously crossing walls and partitions except the fire
rated walls.
10. For exposed duct work in non-conditioned areas apply approved cladding
over the insulated ducts as per specification.
11. Fire dampers will be installed in the ducting layout which is passing through the fire
rated walls with access door provided.
12. Non-insulated ducts shall be provided in fire rated walls, fire dampers shall be fixed
with insulated ducts. Minimum 25mm gap shall be maintained on all sides of the
ducts.
13. Gap between the walls and ducts Fiber Glass Insulation will be rammed properly and
sealed with approved mastic both sides of walls.
14. Access panels shall be provided near to all fire dampers for future cleaning,
inspecting and maintenance purpose.
15. Flexible ducts shall be connected from branch duct to air outlet as per approved shop
drawings and the same shall be supported properly as per manufacturer
recommendations.
16. Approved Flexible Duct Connector, shall be installed in expansion joints and between
connections of HVAC equipment (packaged units, exhaust fans, etc..) and HVAC
ducts by means of S-type cleat joints and will be riveted and sealed with approved
duct sealant.
17. Duct leak test shall be carried out after the completion of duct installation.
18. Raise inspection request for installation of HVAC Ducts with Accessories to the client.
44
45
The following inspection and testing shall be carried out to fulfill the Inspection and Test
Plan:
46