Reclamation Specifiaction
Reclamation Specifiaction
1.0
SCOPE OF WORKS
The areas to be reclaimed are as shown in the drawings consisting mainly:
(a)
Parcels A (comprising of A1 & A2), Parcel B (comprising of B1 & B2) and Parcel
C and C1.
(b)
The filling operation shall be by hydraulic pumping method and shall follow the recommended
EIA guidelines.
It is expressly stated that the Contractor shall be fully responsible to investigate, identify sand
borrow sources, and secure necessary permit or approval for supply of fill materials all at his own
costs.
2.0
SEABED CLEARING
This work shall consist of wreck clearing (whether visible or hidden) unless of historical value,
large obstruction/debris clearing, existing jetty structures and fishtraps clearing.
Incombustible material, including where appropriate the remains of burning, shall be disposed of
in a safe and tidy manner at solid waste dumps approved by the Local Town Council but outside
the Site, unless otherwise approved or directed by the Engineer. The Contractor shall be solely
responsible for making the necessary agreements, and paying expenses and claims arising from
the use of such solid waste dumps whether on Government or private land.
3.0
4.0
indicating the grading of sand obtained from such trial dredging shall be submitted to the
Engineer for his approval prior to the reclamation works.
The strength tests shall be carried out also:
1.
Compaction tests.
2.
Shear box tests.
And the minimum effective shear strength of c'= 0 and '= 30 shall be achieved unless
otherwise agreed by the Engineer.
Once placed, the fill material shall be sampled and tested at regular intervals not less than once
every placed 5,000 cubic metres as directed by the Engineer to determine its
uniformity/conformity with the source samples. Materials found not conforming with the approved
samples shall be removed from the Site and replaced at the Contractor's own costs.
The frequency of laboratory testing on the fill material samples shall be as directed by the
Engineer, depending on the uniformity of sand fill materials at source and as delivered to the site
by the Contractor.
The original soil at the reclamation area is of relatively low strength. The filling procedure which
the Contractor intends to adopt shall take cognisance of this and shall avoid inducing slips,
slides, mudwaves, erosion or displacement of the original soil and the rates and prices entered in
the Bill of Quantities are deemed to allow for carrying out the work in such a manner. The
Contractor should also submit a full detailed method statement of the reclamation for the
Engineer's approval.
It is of importance that the procedure should allow for depositing the hydraulic fill uniformly over
the site in thin layers with height agreed by the Engineer and with sufficient interval between
successive increases in the depth of fill so as to ensure that the underlying soil does not fail.
Under no circumstances should the first layer of fill result in abrupt differences in surface
elevations or more than 0.6m anywhere over distances of less than 6.0 metres.
4.1
Compaction
Compaction of hydraulic fill below water level or +1.8m CD whichever is higher shall be by tidal
flooding with sea water or with sea water ponding as applicable.
Compaction shall be by mechanical means for above water where practicable in accordance to
Clause 2.6. The Contractor shall submit his proposals for compaction for the approval of the
Engineer.
Hydraulic fill material placed at approximately the top 2 metres of the reclamation shall be
densified to achieve an in-situ density 90% of the maximum possible density (4.5kg hammer)
derived from compaction tests according to B.S. 1377 Part 4: 1990.
5.0
5.1
Filling Procedure
(a)
Prior to commencement of actual construction, the Contractor shall submit to
the Engineer for his approval the proposed construction method.
(b)
The filling procedures that the Contractor intends to adopt shall take cognisance
of the soil condition and marine environment at the Site and shall avoid inducing slips,
slides and excessive mud waves.
(c)
The Contractor shall indicate the intended sequence of filling from the starting
CRS2
point and the direction which the filling is expected to progress until completion.
(d)
Whatever method initially proposed by the Contractor, a trial section is to be
carried out to prove his feasibility.
5.2
Methods to be Approved
(a)
(i)
(ii)
(iii)
The general layout, and detailed design of all temporary works including bunds,
drains, sluices, pipelines, culverts, access roads and bridges, docks, jetties,
sumps, etc. which the Contractor intends to establish for handling and placing the
reclamation fill.
(iv)
(v)
(vi)
Such other information as the Engineer may require for the proper control and
supervision of the Works.
(vii)
All settlement markers and rod settlement gauges if so desired by the Contractor
shall be set in position and level just prior to filling and the details recorded and
shown on a drawing of 1:200 shall be subject to the approval of the Engineer.
(viii)
Field (In-situ) testing method to determine the strength profile of the subsoils
during staged construction. The locations and frequency of testing shall be
discuss and agreed by the Engineer.
(b)
These submissions shall be made at least three (3) weeks before the intended
date for commencement of the reclamation works in order that any modification which
may be required by the Engineer be given effect to. No claim for delay in commencing
the reclamation works can be entertained arising from these requirements. The cost of
preparing and submitting the above to the Engineer and of making whatever
modifications may be required by the Engineer before giving his approval shall be
deemed to have been allowed for in the Contract Sum.
(c)
Approval of the Contractor's proposed Method of Construction shall not in any
way relieve the Contractor of his responsibilities under the Contract. Nor can the
Contractor claim any loss in time and money, if his proposed method is not successful in
actual construction, even though prior approval has been obtained.
5.3
Loss of Fill
The Contractor shall allow in the Contract Sum for all risks and for any loss of fill which may
occur during the course of the works including but not limited to marine erosion and loss of fill
around the seaward perimeter, wind erosion, drainage, losses due to any settlement which may
not be disclosed by the method of measurement specified. No claims for payment for filling other
CRS3
than in accordance with the Specifications and in the Preamble to the Bills of Quantities will be
allowed.
5.4
5.5
Resting Period
Resting period is the time required for the subsoil to gain strength after each stage of filling.
Contractor shall not be allowed to proceed to next stage of filling until the following have been
submittal and approved by the Engineer:
(a)
(b)
5.6
6.0
NON-HYDRAULIC FILLING
6.1
General
Non-hydraulic filling may be performed after the underwater filling at the reclamation area has
been completed to a stage above the water level if approved and directed by the Engineer. Nonhydraulic fill may be placed within the tidal range provided the work is performed during periods
of non-submergence and only with the approval of the Engineer.
Non-hydraulic filling materials shall be obtained from borrow areas approved by the Engineer. All
fill materials under this category shall be deposited in layers as determined from trial compaction
tests. Each layer shall be compacted layer and shall be maintained at all times with a sufficiently
even surface in order to drain away the surface water.
All fill materials shall be compacted as soon as practicable after being placed and spread.
Compaction shall be undertaken to the requirements of this Section by equipment approved by
the Engineer. All compaction requirements shall be controlled by means of field density
measurements.
6.2
Compaction Trials
The B.S. 1377 compaction Test (4.5kg rammer method) shall be used in determining the
CRS4
6.3
Degree of Compaction
Based on the in-situ density measurements, the materials shall be compacted to not less than
90% of the maximum dry density determined in accordance to B.S. 1377 Compaction Test
(4.5kg rammer method).
The earthfill shall be processed as necessary to bring its moisture content to a uniform level
throughout the material, suitable for compaction. The optimum moisture content as determined
by the B.S. 1377 Compaction Test (4.5kg rammer method) shall be used as a guide in
determining the proper moisture content at which each soil type shall be compacted.
Field density tests on each layer of compacted earthfill as specified elsewhere and at a minimum
rate of once in every 200 sq.m. shall be carried out using the sand replacement method in
accordance with B.S. 1377 or other means of testing of comparable accuracy approved by the
Engineer.
Work on subsequent layers shall not proceed until satisfactory compaction of the preceding
layers have been confirmed by the Engineer. The Contractor shall supply all samples to the
Engineer from locations and depths as directed for the necessary tests.
7.0
CRS5
All surveys to be used as basis for progress payment shall be carried out jointly between the
Contractor's competent surveyor and the Engineer's representative. The Contractor shall give
notice (minimum one week) to the Engineer and shall send approved Licensed Surveyor with all
necessary equipment to carry out the joint survey. All readings shall be mutually verified by the
Contractor and the Engineer representative to the agreement of both parties.
Notwithstanding sub-paragraph 6.3 above, the Engineer may when he requires the joint survey
to be carried out, give notice to the Contractor or his authorised agent/representative, who shall
forthwith attend or send a qualified agent and an approved competent surveyor to carry out the
survey jointly with the Engineer or his representative. Should the Contractor not attend, or
neglect/omit to send such agent and neglect/omit to send such competent surveyor, then the
survey made by the Engineer or approved by him shall be taken to be correct and be used for
the measurement.
The Contractor shall confirm the correctness of the Site with the Engineer before proceeding with
the setting out and reclamation works. Notwithstanding whatever assistance or checks on the
surveys/setting out by the Engineer or his representative, the Contractor shall not be relieved of
his responsibility for the correctness of the setting out and levelling. The Contractor shall remedy
any work wrongly performed as a result of incorrect setting out or levelling at his own costs.
The surveys and the location, number and construction of bench marks and survey points shall
be carried out and completed as directed and to the satisfaction of the Engineer, and the survey
plans executed to his approval. All surveys relating to the beach nourishment works shall be
reduced to Chart Datum (ACD).
8.0
PRE-RECLAMATION SURVEY
The pre-nourishment survey shall be carried out before commencement of the beach
nourishment works by a Licensed Surveyor to be approved by the Engineer and the survey of the
site shall be plotted to a scale of 1:500 or to other scale approved by the Engineer.
Survey lines shall be set out spaced at 20m intervals. Levels shall be taken at not more than
10m intervals along the survey lines; these levels shall be recorded on the Survey Drawing.
Additional levels shall be taken where there are significant changes in level or gradient or for the
purpose of identifying ground features. Cross-sections of the reclaimed land profile shall be
plotted as directed by the Engineer and shall extend up to at least 100 metres beyond the toe of
the sandfill.
The limit of reclamation may be pegged out and used as base line for the Survey. Grid
references, bearing, lines of sight and reduced levels of survey stations and bench marks shall
be shown on the Survey plan. All existing roads, tracks, structures, drains and other salient
features within the construction limits shall also be shown.
The Pre-reclamation Survey drawings shall be submitted to the Engineer for approval at least
three (3) weeks prior to the intended date of commencement of filling works. The limits and
extent of the reclamation areas shall be determined and confirmed by the Engineer after
examining the pre-reclamation survey plans.
In all cases, NO filling work under this Contract can commence until the complete Primary Survey
drawings have been submitted to the Engineer and his approval, which shall not be withheld
unreasonably, has been obtained.
9.0
INTERIM SURVEYS
Interim surveys of the reclaimed site shall be carried out jointly between the Contractor's
competent surveyor and Engineer's representative in connection with interim monthly payments
or as and when directed by the Engineer.
CRS6
9.1
10.0
11.0
The said whole or part of the reclamation areas has been filled to the design level or
such other level approved by the Engineer within the tolerance of +150mm.
The reclamation edge has satisfied the specified limits lines and slopes.
The subsoil has achieved the 95% degree of consolidation unless otherwise specified by
the Engineer.
The above completion shall be verified by the monitoring results and joint post-reclamation
survey.
12.0
12.1
General
(a)
The Contractor shall construct and maintain all diversion and protective works
which are necessary for construction and to prevent surface, drainage and ground water
from entering the various parts of the Works and shall furnish all materials and
equipment required therefore, in accordance with the requirements of this Clause.
(b)
It is pointed out to the Contractor that high water levels can be expected in the
rivers, streams and drains and adjacent swamp or non-swamp areas during rainy
season and at other times following heavy rain. The Contractor shall take note of this
and other information made available to him to construct and maintain diversion and
protection works so that the river or drainage discharge may be safely controlled without
overtopping any part of the embankment or other constructional work.
(c)
(i)
Diversion and protection works shall comprise, but are not necessarily limited to
cofferdams, levee banks, channels, flumes, conduits, drains and when required,
settling ponds.
(ii)
Where diversion and protection works constructed by the Contractor are not
required as components of the Permanent Works, they shall be removed and
disposed of or levelled to give a sightly appearance and so as not to interfere with
the operation or usefulness of the Permanent Works as approved by the
CRS7
Engineer.
12.2
12.3
Dewatering
(a)
The Contractor shall furnish, install, maintain and operate all necessary
pumping and other equipment for dewatering and maintaining the various parts of the
Works free from water during construction and, as required, for inspection and safety
and for any reason determined to be necessary by the Engineer after any part of the
Works is completed.
(b)
All diverted and pumped water shall be discharged at location on the surface
from which it cannot re-enter the works and in a manner which does not cause erosion,
pollution or nuisance to landowners, other contractors employed by the Employer or
other persons within or adjacent to the Site.
12.4
Pollution
The Contractor shall construct, maintain and operate suitable settling ponds, bunded areas,
separating plant or other works necessary to prevent any discharge into rivers, streams or
existing drainage systems of water containing polluting matter or visible suspended materials.
12.5
13.0
SOIL FAILURE
Should slips, slides or displacements occur the Contractor shall do everything necessary to
rectify the defect and stabilise the ground to the satisfaction of the Engineer and shall bear all
expenses and with no claim for extension of time, including replacing at his own expense any fill
lost or rendered unsuitable as a consequence of the defect or providing any additional fill which
would not have been necessary had the defect not occurred.
No claim shall be allowed for rectification of slips and displacements and the rates and prices
entered in the Bill of Quantities and the Contractor Programme and the Completion Times
CRS8
entered in the Tender are deemed to provide for all costs, expenses and delays which may be
incurred.
14.0
15.0
MUD WAVE
Filling shall be carried out in an approved manner so as to ensure the minimum loss of the
original ground and to avoid, as far as possible, the formation of a mud wave due to the
displacement of the original ground. In this connection the advancing face of the fill should be
restricted in height and kept as flat as possible.
Should such a mud wave develop, the Engineer may direct the removal of the excess material
and the cost of so doing shall be borne by the Contractor and the expense incurred shall be
deemed to have been allowed in the rates and prices entered in the Bill of Quantities.
16.0
EROSION
When placing hydraulic fill care shall be taken not to erode or wash out the existing soil. Should
this occur the cost of replacing the eroded material shall be borne by the Contractor.
17.0
18.0
19.0
SURCHARGING
Where indicated in the Drawings, the Contractor shall fill to the levels and outlines of the
surcharge areas or as directed by the Engineer. Such surcharge shall be placed and compacted
all in accordance with Clauses 2.4 and 2.5 hereof as appropriate.
When settlement designed for has taken place the surplus surcharge materials shall be removed
and placed elsewhere on the site as and when directed by the Engineer. The site after removal
CRS9
of surcharge materials shall be trimmed to the required finished levels, properly compacted and
graded all to the satisfaction of the Engineer. This however, shall be carried out only when it is
within the completion period.
20.0
20.1
General
Where shown on the Drawings prefabricated vertical drains shall be installed after partial
placement of the drainage layer or from levels as stated in the Drawing.
20.2
20.3
Fill
Fill shall be placed and properly compacted according to the rate and height of each stage of
filling to be agreed by the Engineer according to the design.
CRS10
Extra fill shall be placed to thickness specified on the Drawings as surcharge to speed up rate of
embankment settlement depending on the design. Surcharging fill shall be maintained for a
period of time indicated in the Drawing and shall be removed only with the approval of or when
instructed by the Engineer.
20.4
Material
Prefabricated vertical drains shall be from an approved manufacturer and consist of an polymer
core and an external non-woven filter membrane, and shall comply with the requirements as
indicated on the Drawing and Table 1.
Property
Material
Dimension of
drain
Unit
Specified
Requirements
Remarks
Core
Filter
Wrapped in non-woven
geotextile material
Width
Mm
100 2
Thickness
Mm
3 to 4
Coefficient of permeability of
drain filter
M/s
> 5 x 10-5
M3/s
25 x 10-6
Microns
75
Dry
kg/10cm
> 100
Wet
kg/10cm
> 100
Dry
Kg/cm
>3
At elongation minimum 2%
maximum 10%
Wet
Kg/cm
>3
< 10
At 100kg/10cm width
< 10
At 3kg/cm
Tensile
strength of
entire drain
Tensile
strength of
filter
Dry
Wet
TABLE 1
21.0
21.1
CRS11
and water pressures in the soil. Instrumentation is part of the permanent works and shall remain
in good condition and operational both during and after the construction contract, unless as
agreed by the Engineer.
The Contractor shall be responsible for and shall follow the instructions of the manufacturer and
the requirements of this specification in the installation, calibration and testing of all measuring
instruments and equipment, which shall be carried out under the direct supervision of the
Engineer. The Contractor shall inform the Engineer at least 2 day prior to undertaking installation
of the equipment. The Contractor shall make due allowances in his construction programme for
delays which may arise on account of the installation of the instruments and of their
maintenance.
21.2
21.3
21.4
21.5
21.6
CRS12
Boreholes for instruments may be drilled by approved method provided that it results in a clean
and stable hole of the required diameter to the correct depth. Boreholes shall be cased to their
full depth unless strata are sufficiently competent for the hole to stay open under dry conditions.
Boreholes shall be drilled using clean water. Drilling mud or polymer additives shall only be
used with the approval of the Engineer. In the case of installation of piezometers, drilling mud
or polymer additives shall not be permitted.
During drilling care shall be taken to ensure that minimum material is lost from outside the
casing. Surging of casing shall not be allowed, and flushing of drilling water up the outside of
the casing shall be minimised.
The method of forming boreholes, including the procedure for advancing casing, shall be
submitted to the Engineer for approval before commencement of the works.
21.7
GROUTING OF BOREHOLES
For all instruments placed in boreholes, grouting is required of part or all of the borehole during
installation. The grout shall be a bentonite : cement mixture with sufficient water to achieve a
pumpable mix. The proportions of the mix shall be such as to imitate as closely as possible the
strength or consistency of the natural soils present. The Contractor shall conduct trials on
different mixes of bentonite : cement (from 4:1 to 8:1) to ascertain the relationship with strength.
Specimens shall be cured and stored, then tested in undrained triaxial compression after 1 day,
2 days, 7 days, 14 days, 1 month and 3 months. 3 specimens shall be tested on each
occasion, and the sources of bentonite and cement shall be the same as used for eventual
installation. On the basis of these trials, the Engineer shall decide on the bentonite : cement
proportions to be used, which may be varied depending on the application. Grout shall be
poured or pumped into boreholes using a tremie pipe.
For inclinometer installed in the wall, the annulus between inclinometer access tube and wall
shall be filled up with neat grout of grade 35.
21.8
CRS13
Should a rod settlement gauge be damaged or should the Contractor fail to extend the gauge
when required, he shall stop all filing in the vicinity of the gauge until the necessary remedial
works have been carried out. The Contractor shall be liable for any delay in his programme, or
any additional work that has to be done as a result of such damage.
Should any rod settlement gauge be damaged in such a way as to make it useless for its
purpose, the Engineer shall assess the settlement for measurement purposes and this
assessment shall be accepted by the Contractor as final.
Rod settlement gauges shall be monitored by precise levelling techniques. Levels shall be taken
of the top of the rod itself and the fill adjacent to the gauge on each occasion. The datum used
shall preferably require only one set up of the level, and levelling shall be closed back to the
datum. When rods are extended, levels shall be measured immediately before and immediately
after adding the extension.
21.8.3 Inclinometers
The Contractor shall install inclinometer at locations, and with depths and details as specified by
the Engineer.
Inclinometer access tube shall consist of broached PVC tubing with four keyways set at right
angles to each other and shall be supplied in 3.0m lengths with 0.3m long couplings and end
caps. The spiral twisting of the keyways shall not exceed 0.75 degrees per metre length of the
tubing. Where necessary, the Engineer may instruct the Contractor to obtain spiral metric
measurements of the keyways in the inclinometer tubing after installation. After assembly joints
and rivets shall be coated in sealing mastic and wrapped in sealing tape. The tube shall be
coated with thick grease over its upper part when it passes through compressible subsoils. The
assembled tube shall be lowered into a 125mm diameter borehole backfilled with a suitable
bentonite : cement grout mix. Alternatively the tube may be placed in an open borehole and
grout placed afterwards. In granular material, the backfill may be sand or pea gravel. The
keyways shall be orientated such that movements are measured parallel to and right angles to
the embankment/slope axis.
Where the access tube passes through upper stiff crusts or fill material, it shall be sleeved by a
larger diameter tube so that it can pass freely through these materials as settlement takes place.
Where the access tube passes through fill which is being placed, the access tube and outer
sleeve shall be extended in lengths which are multiples of 0.5m as filling progresses. The top of
the access tube, and the larger diameter sleeve where present, shall be protected with a suitable
cover.
Angular movements shall be measured by an inclinometer torpedo which shall be a biaxial type
with a gauge length of 500mm, and the system shall be capable of measuring lateral deformation
to an accuracy of 10mm over a depth of 30m. The casing of the inclinometer probe shall be
constructed of stainless steel and the probe shall be fully waterproof and corrosion proof. The
inclinometer probe shall be supplied with a rigid carrying case fully lined with shockproof padding.
The cable supplied for use with the inclinometer shall be a polyurethane sheathed cable with a
minimum length of 40m, incorporating a central kelvar straining wire. The cable shall be
graduated in intervals of 500mm and shall be supplied complete with a portable cable reel.
The inclinometer data logger unit shall display the readings from the inclinometer torpedo on an
alphanumeric display. The readout unit shall be powered by a re-chargeable battery with a
minimum life of 12 hours continuous use between charges. A suitable automatic battery charger
shall be supplied with the readout unit. The readout unit shall incorporate an RS232C port and a
solid state data storage unit with the capacity to store at least 30000 readings directly from the
inclinometer probe together with time and date of reading. The following facilities are also
required within the readout unit :
a.
b.
CRS14
c.
d.
e.
Display of mean deviation and cumulative deviation of any one set of readings.
Graphical display of displacement profile between any two sets of readings.
Backlit LCD display.
CRS15
from the top of the tube. The position of each magnet shall be measured twice, once while
moving upwards and once while moving downwards towards the magnet. Immediately before
or after taking a series of readings, the level of the top of the access tube shall be measured by
standard levelling technique.
CRS16
The pneumatic readout unit shall be capable of storing 500 readings and shall incorporate an
electronic pressure transducer, backlit digital display, RS232C interface and cable link,
rechargeable battery providing at least 12 hours continuous are between charges, a
rechargeable gas reservoir bottle, a reservoir pressure gauges, return + flow indicator, flow
control valve and quick release self sealing leads for connection to the supply and return
manifolds of the terminal panel. The readout unit shall be housed in a rigid weatherproof case
with carrying handles and shall be capable of resolving readings to 1 kPa. An automatic charger
for the readout unit battery shall be supplied suitable for 240V, 50Hz electricity supply. The
Contractor shall make facilities available for recharging the gas reservoir with nitrogen.
Before installation and taking initial readings the Contractor shall pressure test the pneumatic
piezometer tip in a container of water after connection to the tubing with a pressure of 500 kPa to
check for leaks or poor connections. The ceramic element shall be deaired under vacuum and
precautions shall be taken to ensure that it remains saturated during installation. During
installation readings shall be taken when the piezometer tip is lowered down the borehole, when
it is pushed in or placed in the sand pocket and at various times after installation to check the
response of the piezometer and help find the static pressure value before the initial base
readings are taken.
Readings shall be taken by and stored on the readout device. Care shall be taken to ensure that
the flow and return leads are connected correctly.
21.9
Instrumentation Records
Project name
Contract name and number
Instrument reference number and type
Dates of installation, reading or summary
Times of installation or reading
Chainage and Offset (or coordinates if appropriate)
Personnel responsible
Relevant comments or remarks
Reduced level
CRS17
The Contractor shall submit to the Engineer the specified number of copies of each installation
report within one working day of completion on the installation, including taking of base readings.
A text describing the scope of work, the site, the work carried out and the types
of instrument installed
All installation record sheets
Plans and cross section drawings at a scale of 1:200 or other agreed scale
showing the locations, elevations and details of all instruments
Photographs of all the instruments used, illustrating installation and method of
reading
Values of all base readings taken together with any subsequent readings up to
the time of submission
21.9.5 Readings
On each occasion that readings are taken from an instrument or set of instruments, the
measured values shall be recorded on a record sheet. The format of the record sheet for each
type of instrument shall be prepared by the Contractor and submitted to the Engineer for
approval at least one week before readings commence. For readings that are recorded on data
loggers, a record sheet shall be required giving references to the data stored. A computer
system including interfaces, plotter, printer and software shall be available to make the data
transfers, listings and plots required.
The format of plotted results shall be submitted to the Engineer for approval. Details of
information and values to be stored on each record sheet in addition to the general information
CRS18
Data required
Instrument
Settlement
marker
Displacement
Survey station
Deep datum
Rod settlement
Inclinometers
Standpipe piezometer
Magnetic
Extensometer
Combined magnetic
extensometer and
inclinometer
Pneumatic
piezometers
CRS19
The Contractor shall submit to the Engineer the specified number of copies of each record sheet
with necessary listings and graphs within one working day of taking the readings unless
otherwise directed by the Engineer.
21.9.6
Frequency of Measurement
The frequency or the interval of measurement is dependent on the rate of settlement of a subsoil.
Close intervals are used during and shortly after fill has been laid. The intervals are increased
with increase in the duration of lapse time. The following can be used as a guide.
a)
During filling
- Every morning before subsequent filling commences.
b)
Instrument
CRS20
Settlement
marker
Rod settlement
gauge
Displacement
marker
wall
Survey station
Deep datum
Inclinometer
Magnetic
extensometer
Combined magnetic
extensometer and
inclinometer
Standpipe piezometer
Pneumatic
piezometer
All plots where time is the horizontal axis shall have the same scale for the time axis. Where fill
thickness, settlement and excess water head are all available at the same location, the plots shall
be combined on the same sheet where possible. Final layouts, scales and details shall be
agreed with the Engineer at the time of submitting the format.
The Contractor shall submit the required number of copies of the monthly monitoring report to the
Engineer within 7 working days of the end of the month being reported. If there are anomalies
or sudden significant changes in the results, the Engineer should be informed within 1 day after
monitoring.
21.9.9
CRS21
The Contractor will have to submit to the Engineer for comment on the graphic presentation of
the monitored readings. The presentation will have to be agreed by the Engineer prior to the field
work. Hand plotted graphs are not acceptable.
CRS22
TABLE OF CONTENTS
Description
Page
1.0
2.0
3.0
4.0
5.0
6.0
5.2
5.3
5.4
5.5
5.6
6.2
6.3
7.0
8.0
9.0
10.0
11.0
12.0
12.2
12.3
12.4
12.5
13.0
14.0
15.0
16.0
17.0
18.0
19.0
20.0
CRS i
21.0
20.2
20.3
20.4
21.2
21.3
21.4
21.5
21.6
21.7
21.8
21.9
S2-2