0% found this document useful (0 votes)
307 views

Prince2 Practitioner Resource Book v3.5

Prince2
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
307 views

Prince2 Practitioner Resource Book v3.5

Prince2
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 237

PRINCE2 Practitioner

Resource Book
Version: 3.5
030412

COPYRIGHT NOTICE
This document is the copyrighted intellectual property
of ILX Group plc and may not be copied,
disassembled or in any way modified
without the express and written permission
of ILX Group plc.

PRINCE2 is a Registered Trade Mark of the Office of the Cabinet Office.

2009 ILX Group plc

PRINCE2 Practitioner Resource Book

2009 ILX Group plc

Table of Contents
PRINCE2 Practitioner Resource Book

TOPIC

PAGE

Introduction

Session 1 - Course Introduction

Session 2 - PRINCE2 Walkthrough

Session 3 - PRINCE2 Project Simulation

PRINCE2 Project Scenario


Exercise 1 - Organisation simulation
Exercise 2 - Business Case simulation
Exercise 3 - Product Based Planning simulation
Exercise 4 - Management of Risk simulation
Exercise 5 - Quality in a Project Environment simulation

8
10
12
14
18
21

Session 4 - Marking Up the PRINCE2 Manual

23

Session 5 - Practical Practitioner Exercises

58

Session 6 - Practitioner Exam Technique

82

Session 7 - Practitioner Exam Simulator

83

Session 8 - Practitioner Exam Questions

84

8(a) - Question Styles

85

8(b) - Sample Exam Papers

89

Practitioner Exam Scenario 1: Pleasure Park Project

89

Practitioner Exam Scenario 2: Calendar Project

154

2009 ILX Group plc

Introduction
PRINCE2 Practitioner Resource Book

Introduction
Welcome to the PRINCE2 Practitioner Resource book. This document is intended to support students
studying the ILX e-learning PRINCE2 Practitioner course and as such, access to a copy of the elearning should be considered a prerequisite.
The book reflects the structure and sequence of the e-learning course and where appropriate provides
easy access to the relevant supporting information including:
o
o
o
o
o

Project Scenarios
Project information including, meeting transcripts, diagrams and project communications
PRINCE2 Process Map
PRINCE2 Practitioner exercises
PRINCE2 Practitioner exam questions and answers

Students should work through each of the lessons completing all questions, exercises simulations and
exam questions prior to sitting the Practitioner examination.
You should allow 25 40 hours to complete the full PRINCE2 Practitioner course.
There are three objectives that you need to achieve prior to attending the revision/exam workshop.
These are:
o
o
o

Develop your basic knowledge of PRINCE2


Convert from e-learning to the PRINCE2 Manual
Complete Practitioner style exercises

Course prerequisites

It is anticipated that students will have completed PRINCE2 Foundation level study prior to
commencing this course.
ILX Group can provide Foundation level courses in the following format:
o
o

E-learning
Classroom based

If you would like to discuss your requirements further, please call +44 (0)1270 611600.

2009 ILX Group plc

PRINCE2 Practitioner Resource Book

2009 ILX Group plc

PRINCE2 Practitioner Resource Book

Course Introduction
2

Course Introduction
Introduction
Welcome to the Practitioner section of this PRINCE2 e-learning course.
This section of the course is intended to help you apply your knowledge of PRINCE2 in practical terms
using, amongst other things, activities, exercises and simulations.
By this point you should have completed all the lessons in the Foundation section of the course and
you should be feeling confident about your knowledge of PRINCE2.
If you havent already completed your Foundation exam, we recommend that you periodically practice
in the Foundation Exam Simulator, to top up your knowledge and further familiarise yourself with the
style of the Foundation exam questions.
You will have noticed that this section of the course contains several lessons intended to help you with
your Practitioner studies.
Well take a few moments to describe each in a little more detail.

An Advanced PRINCE2 process model walkthrough

This lesson takes a detailed step-by-step look at what is considered by many, as the heart of the
PRINCE2 method, the Process Model. The lesson looks at the processes, sub processes, inputs,
outputs and main decision points which form the cornerstones of the PRINCE2 method.

PRINCE2 Practitioner Simulations

Putting PRINCE2 in to practice is the subject here. This group of simulations shows how the method is
applied in practical terms whilst testing your understanding.
Based on a typical project scenario, this suite of six simulation based exercises is intended to test and
extend your knowledge of PRINCE2 and to provide a level of understanding required to pass the
Practitioner exam.
The exercises are based on a variety of topics including PRINCE2 Processes, the preparation of a
Business Case, Risk Analysis, Quality, Product Breakdown Structures and Product Descriptions. Each
exercise is stand-alone, and once completed, provides useful feedback and pointers on further
revision and study.

Marking Up The Manual

This lesson explains how to highlight all the key PRINCE2 manual references. Key information
becomes easier to find, making the best use of your time in the Practitioner exam.

Practical Practitioner Exercises

This lesson consists of a suite of six exercises intended to test and extend your knowledge of
PRINCE2 and to provide a level of understanding required to pass the Practitioner exam. The
exercises are based on a variety of topics including PRINCE2 Processes, the preparation of a
Business Case, Risk Analysis, Quality, Product Breakdown Structures and Product Descriptions.
Each exercise is stand-alone, and once completed, provides useful feedback and pointers on further
revision and study.

2009 ILX Group plc

PRINCE2 Practitioner Resource Book

Course Introduction
2

Practitioner Exam Technique

This lesson begins by outlining the PRINCE2 qualification structure and the awarding bodies and
associated accrediting organizations. It goes on to take a detailed look at the make up of the
Practitioner examination questions, the paper based documents used in the examination and provides
practical guidance on how to approach and answer the Practitioner level examination questions.

PRINCE2 Practitioner Exam Simulator

Weve also included a full electronic version of the PRINCE2 Practitioner exam plus two further mini
exams to help familiarise you with the style and nature of the Practitioner exam.
The Exam Simulator is timed and scored, just like the real exam, providing you with as near to exam
conditions as possible.

2009 ILX Group plc

PRINCE2 Practitioner Resource Book

PRINCE2 Walkthrough

PRINCE2 Walkthrough

Introduction
Welcome to this chronological walkthrough of a project managed using the PRINCE2 method.
This lesson starts by introducing the major processes identified in PRINCE2. The second part of the
walkthrough will cover the main management products input to and output from each of the
processes.
In a nutshell, this is a summary of the context diagrams of the sub processes in the PRINCE2 Manual.
We call our map PRINCE2 on a Page!
Although there is much more detail of the sub processes and the appropriate Management Products in
the PRINCE2 manual, our process map is analogous to a jigsaw puzzle which could be printed on the
front of the PRINCE2 Manual. It explains the individual pieces of the PRINCE2 method and how they
link together as a composite picture when applied to running projects.
This lesson also explains the symbols used on the process map and the significance of the colour
scheme.

2009 ILX Group plc

PRINCE2 Practitioner Resource Book

An Advanced PRINCE2 process model walkthrough

2009 ILX Group plc

PRINCE2 Walkthrough

PRINCE2 Practitioner Resource Book

PRINCE2 Project Simulation

PRINCE2 Walkthrough

Introduction
Welcome to the PRINCE2 Practitioner Simulation.
At the centre of this multifaceted simulation is a project scenario typical of those youll encounter in the
PRINCE2 Practitioner examination. The scenario introduces you to an organisation intent on
improving its operational efficiency and increasing its range of customer services. You will take the
role of a consultant project manager hired to advise the organisation on its facilities project.
The simulator also contains several complex activities on some key practitioner-level subject areas,
including Business Case, Management of Risk, Organisation, Product Based Planning and Quality.
Each activity is stand-alone and provides valuable feedback on your given answers.
You should reference the scenario and any supporting documents whenever you see fit. Feel free to
attempt the scenarios in any order.

2009 ILX Group plc

PRINCE2 Practitioner Resource Book

PRINCE2 Walkthrough

Project Scenario

Recent changes to the lending criteria of an international bank have made it financially advantageous
for one of its customers to make some strategic changes. The organisation intends to reduce its
dependency on overdraft and capital loans services, improve its operating efficiency and increase its
range of customer services.
Proposals by senior managers have resulted in a decision to use a programme to bring about these
changes. Currently there are three projects in this programme:
These are project 1 Accounts, project 2 Facilities and project 3 Staff.

The objective of the Accounts project is the integration of the numerous accounting practices
into one coherent process. This will use a software package now under development by an
external software house.

The Facilities project intends to bring about a reduction in the space utilisation and associated
running costs by:

constructing an extension to the North West branch building

upgrading the facilities of the North West branch building

transferring all operations and necessary staff to the North West branch

and disposal of un-required assets

Finally the Staff project involved the assessment of the staffing needs of the organisation for the
next five years. This project closed a few days ago having produced the confidential document
known as Proposed Staffing Needs which was approved at the highest level.

You are a consultant Project Manager hired to advise the organisation on the second project Facilities. It is your responsibility to help the organisation use PRINCE2 as its preferred project
management method.
Several people have been trained to Foundation level and one has been successful at Practitioner
level. However, most employees are unfamiliar with projects so you will need to mentor them in the
best use of PRINCE2.
Whilst discussing the situation with the Chief Executive you touched on the companys growth
predictions. She indicated that although they are realistic in the current economic climate it would not
take much for demand to rise sharply.
The Project Mandate recommended that the project should be undertaken in three stages.

Stage 1. This is the Initiation Stage for the development of the Project Initiation Document and
the Stage Plan for Stage 2.

Stage 2 this stage will include the following:

Upgrading the facilities at the North West branch.

Inviting tenders from external construction companies for the extension to the North West
branch and choosing the successful contractor.

Obtaining market values for the South East branch building and putting the building up for
sale.

Stage 3 this stage will include the following:

2009 ILX Group plc

PRINCE2 Practitioner Resource Book

PRINCE2 Walkthrough

Building the extension to the North West branch building.

Moving all necessary staff and operations to the North West site.

Closing the project.

Early estimates suggest that this project may take 15-18 months to complete.

2009 ILX Group plc

PRINCE2 Practitioner Resource Book

Exercise 1 Organisation Simulation

PRINCE2 Walkthrough

Summary Details of all Candidates

Angela Brown (Chief Executive) Ive benefited from the organisations growth over the past few
years with promotion from Service Delivery Manager through Head of Operations to Chief Executive. I
see it as my responsibility to ensure that the programme is a success so I can hand onto my
successor a thriving and efficient organisation.
Debbie Davies (Head of Finance) I joined the organisation a few months ago from a senior position
in the finance sector and have been tasked with ensuring that the organisation spends every penny on
projects and business as usual in the most cost effective way.
George Goldman (Head of Services) Ive worked my way up from maintenance electrician and fully
intend replacing Angela when she retires. This project is my chance to show what I can do and Ill
push it through at all costs if need be. I fully understand the needs of external suppliers.
Steven Chang (Head of Operations) After seven years in the job I have eventually got the
Operations division into reasonable shape. I know its not perfect and changes are still required. I have
fully researched the services we deliver and have formed some business based views on how we
might improve them.
Amrit Sond (Accountant) I enjoy my job and dont want promotion as I have huge domestic
responsibilities. Nonetheless there are times in my day when I could undertake investigative type
work. I really enjoy analysing the actual state of things and recommending appropriate courses of
action especially in areas involving finance.
Joe Simmons (Book-keeper) (A note handed to you by someone in Human Resources reads: Joe
is likeable and enthusiastic but makes costly mistakes. He is too focused on becoming Head of
Finance and thinks that his move from Mechanical Services was a promotion. He may not last long in
the organisation!).
Emily Duncan (Personal Assistant) Now that Ive organised Stevens office activities I have more
time to devote to other aspects of the business which need someone to pay attention to detail. I would
like to use the PRINCE2 understanding I gained on my Foundation course.
Brian Hardman (Buildings Manager) Ive got over twenty years experience in building construction
and maintenance. My company went into liquidation in the last downturn and I have decided to remain
as an employed person. During the last five years in this position I have brought all the data on the
buildings up to date.
Jeff Wall (Mechanical Services) Im keen to be involved with the refurbishment of the buildings we
have. My team of people has the whole range of technical skills necessary for refurbishment work but
we may have to employ some contract staff at peak workload times.
Monica Shapiro I headed up the work to update the data on the electrical services for Brian and
can now confidently organise my staff to alter any of the facilities to meet future needs.

2009 ILX Group plc

10

PRINCE2 Practitioner Resource Book

PRINCE2 Walkthrough

2
Stacey Brewins (Service Designer) Ive designed all but one of the services we provide to clients. I
know what our clients need and can translate that into proposals for service delivery. I have an
impressive background in project work, have been released from the technical work of the
organisation and recently passed my PRINCE2 Practitioner exam.
Michael Hanes (Service Delivery Manager) Ive made some improvements to the North West
(NW) branch over the last few months and have made it the most efficient part of Service Delivery. We
could do better but that would need some amalgamations with all that implies.
Richard Gamble (Service Delivery Manager) I look after the South East (SE) branch but dont
agree with all the paperwork imposed on me. I take a few short cuts but I get the work done. I
usually answer to my nickname Risk.

2009 ILX Group plc

11

PRINCE2 Practitioner Resource Book

Exercise 2 Business Case Simulation

PRINCE2 Walkthrough

Interview Transcript

Interviewer

Hi Angela, Its good of you to take the time to tell us about your vision for the
company, especially your views on the Facilities Rationalisation project which is just
getting underway.

Angela

Thank you. As you know this project is part of a programme of initiatives I have
sponsored to ensure that we are well placed to take advantage of the market over
the next seven years. We have just completed a study into the possible ways we
could move forward. One of the major problems facing us has been the time and
money incurred between our two north west sites. It doesnt seem to matter where
you were located; the person you needed to talk to always seemed to be in the other
building.
Additionally, the cost of running two buildings has escalated significantly in the last
two years.

Interviewer

Indeed Ive noticed that extra travelling time myself it can be very frustrating. Are
there any other drivers for this initiative?

Angela

Oh, yes. We have recently concluded a project looking at staffing needs and the
consolidation of the accounts package will bring significant advantages.

Interviewer

Can we be assured that redundancies are not part of the proposals?

Angela

Oh yes, whilst there are significant advantages to be gained if we implement the


recommendations of the staffing project, redundancies are not part of the equation.

Interviewer

How much do you think the project will cost?

Angela

Well its difficult to estimate it exactly at this stage, but we estimate building costs at
1,000 per square metre and were allowing for a 4,000 square metre extension,
which will cater for 400 people. Thats 200 staff from the satellite building and allows
for expansion in the future. So were allowing a total of 4m in the budget.

Interviewer

I can see the rationale in that, but it seems like a lot of money. Did you consider any
other solutions?

Angela

Yes. The study considered a number of things. Firstly, moving location altogether,
but as we own both the buildings this seemed excessively costly and very disruptive
for staff.
Secondly we considered staying as we were, but re-organising into different work
streams. However as we are a matrix type of organisation this seemed a backward
step.
Or, by extending, we can co-locate all the staff for a modest investment in the
building and sell off the satellite site. This provides us with cost savings almost from
day one. This was documented as our preferred option.

2009 ILX Group plc

12

PRINCE2 Practitioner Resource Book

PRINCE2 Walkthrough

We costed out a further option which was do nothing. This ensured


that the
2
selected option was both cost effective and offered value for money.
Interviewer

So when do you expect the extension to be ready?

Angela

Assuming that the planning permission goes to plan in the next 4 months, Im
hoping that the build will be completed in 12 months and weve allowed a couple of
months for moving and finalising the extension. So a total of 18 months.

Interviewer

So how have you justified this expenditure to the board?

Angela

Well there are a number of things I reported.


The consolidation of the accounts software will only cost 250,000 and we shall
save approximately 100,000 p.a. in reconciliation activities. This includes the time
wasted by my Accounts team.
Most importantly we will save 250,000 per annum on rent and rates.
We expect to realise 2.5m from the sale of the satellite building and the savings on
expenses should amount to about 25,000 per annum. Saved time by integrating
the work of both offices amounts to another 50,000 per annum, so we expect to get
payback within 5 years.
Additionally, the general improvement in staff morale will provide a number of
benefits to us.

Interviewer

I understand that we are using PRINCE2. Will that ensure we deliver on time and
on budget?

Angela

Itll certainly help. Assuming that everything goes to plan then well be spot on.
However, whilst the extension is relatively problem free we could have difficulties
with selling the old site and it is very important that we address the communication
with the staff so that they integrate and enjoy the new premises.

Interviewer

How do you propose to address these issues?

Angela

This interview is the first of a series of communication initiatives. We also intend to


run a series of road shows that we hope all staff will attend to keep everyone
informed of project progress and will encourage feedback from the staff.

Interviewer

Thank you for your time Angela.

Angela

Thank you.

2009 ILX Group plc

13

PRINCE2 Practitioner Resource Book

PRINCE2 Walkthrough

Exercise 3 Product Based Planning Simulation

Planning Workshop Transcript

Stacey

Welcome to this project planning workshop. As you know Im the project manager
and Id like to discuss the requirements for the project with a view to establishing a
product breakdown structure and flow diagram.
Before we start, Emily will take notes and just to make sure she knows who you all
are can we just have a roll call for Emily, just for the record?

Brian

Hi Im Brian Hardman and my responsibility is to provide Assurance to George


Goldman, the Senior Supplier.

Jeff

Jeff Wall, Team Manager for the mechanical side of things.

Monica

Hello, Im Monica, Team Manager for electrical services.

Michael

Mike Hanes, Service Delivery Manager, doing assurance for the Senior User. This
is all a bit new to me Stacey, could you just explain what you mean by a Breakdown
Structure?

Stacey

No problem Mike. All I want to achieve today is to generate a list of products or


deliverables that we need to create in order to complete the project. Its a first pass
to help us identify the scope of the project and the work involved. Because were
dealing with products we call it a product breakdown structure and its basically a
structured list of things to make, build or buy in.

Monica

Whats the Flow diagram?

Stacey

This is like a network of activities in MSProject, except that its a network of


products. It shows the order that well develop the products.

Michael

Thanks Stacey, thats cleared it up for me. How are we going to go about it then?

Stacey

Id like you just to think about the project for a few minutes and then shout out your
products and Ill draw them up on the flipchart.
TIME PASSES

Jeff

I guess the first thing will be getting the plans sorted out and then therell be
planning permission.

Monica

Yes, and then theres all the decorating to sort out.

Stacey

What do you think that will entail?

Michael

Well last time we had a dcor plan. I need to make sure we get the right furniture
items flat-pack desks, chairs and storage units for example. And the carpets
need to tie in with the colour scheme.

Jeff

Therell have to be a contract and that means an Invitation to Tender, we call it an


ITT. Well have to evaluate the replies. The Contracts Manager normally does
that.

2009 ILX Group plc

14

PRINCE2 Practitioner Resource Book

PRINCE2 Walkthrough

Monica

Ill need to get all the IT sorted out, Cables, PCs, Printers and the Servers.

Michael

Yes, thats very important. My lot will want to get involved in the testing.

Stacey

Dont forget the building works. Therell be foundations for a start, walls and the
roof of course.

Emily

What about the old building, isnt that being sold?

Michael

Yes, quite right, Angela wants it sold so well have to place an advert and get an
agreed sale. Then when its all done we can move the staff so well need a contract
with a removal company.

Stacey

Thanks for that everybody, I think weve gone as far as we can for now. Perhaps
youll be thinking about the risks opportunities and threats please before our next
meeting. Emily will get this written up and out to you by close of play today. Bye for
now.

Jeff
Monica
Michael
Emily

Bye everybody, see you later.

2009 ILX Group plc

15

2009 ILX Group plc

Desks

Walls

Chairs Storage

Dcor
Plan

Replies

Contract

Roof

Infrastructure
Group

Advert

Agreed
Sale

Foundations

Removal
Contract

Sale
Group

PCs

Printers

Servers

IT
Group

Cables

Sample Product Breakdown Structure

Carpets &
Flooring

ITT

Planning
Permission

Plans

Furniture / Flooring
Group

New Building

Product Breakdown Structure

PRINCE2 Practitioner Resource Book

3
PRINCE2 Walkthrough

16

PRINCE2 Practitioner Resource Book

PRINCE2 Project Simulation

Sample Product Flow Diagram

Product Flow Diagram


ITT

Contract

Replie
s

Foundations

Planning
Permission

Dcor
plan

Walls

Roof

Printers

Carpets &
Flooring

Cables

PCs

Chairs
Plans

Servers

Advert
Storage Units

New Building

Desks

Removal
Contract
Agreed Sale

2009 ILX Group plc

17

PRINCE2 Practitioner Resource Book

PRINCE2 Project Simulation

Exercise 4 Management of Risk Simulation

Communication Transcript

Communications to Stacey
No.

Method

Detail

From

Phone

Hi Stacey.

Brian Hardman

Just a thought. There may be some objections to the planning


application causing a delay to the project.

Email

Dear Stacey.

Angela (CEO)

For your information. Due to the fall in property prices the sale
of the old building has been postponed.
Regards
Angela

Email

Hi Stacey,

Brian Hardman

There may be problems with the foundation work for the


extension resulting in delays and additional costs.
Brian Hardman

Phone

Hello Stacey, its Michael Hanes here.

Michael Hanes

I was thinking about the buildings project and it occurred to


me that the staff may not actually like the dcor plan.

Email

Dear Stacey,

Michael Hanes

I had a meeting earlier today with some of the staff


representatives. I thought I should let you know that the
Unions are unhappy about the proposed move. This is
something that we will have to address.
Let me know your thoughts.
Regards
Michael

Meeting

2009 ILX Group plc

We have discovered that the IT system hasnt enough


capacity to cater for the additional users.

Monica Shapiro

18

PRINCE2 Practitioner Resource Book

Phone

PRINCE2 Project Simulation

Hi Stacey, Mike here.

Michael Hanes

Following on from my earlier email and the meeting I had with


the staff representatives
Well, have we considered involving the staff in discussions
about the new extension they might have some good ideas.
Id appreciate your thoughts.

Email

Dear Stacey,

Angela (CEO)

I hope all is going well for you on the building extension


project.
If the cost savings have been exaggerated the project will not
pay for itself as suggested in the Business Case. This will need
to be considered.
Best Regards
Angela

Meeting

The staff from the other building may not integrate and morale
will suffer.

Mike Hanes

10

Email

Hi Stacey,

Brian Hardman

Ive just been informed that the structural engineers have found
a problem with the architects proposal. It concerns the access
route into the extension.
Could you get back to me when its convenient?
Thanks
Brian.

2009 ILX Group plc

19

PRINCE2 Practitioner Resource Book

PRINCE2 Project Simulation

Risk Parameters

Parameters for probability and impact have been identified as follows:

Probability:

Low not very likely to happen


Medium it has a 50/50 chance of happening
High very likely to happen

Impact on Time:

Low less than 3 weeks delay


Medium 3 to 7 weeks delay
High more than 7 weeks delay

Impact on Cost:

Low increase less than 10% in cost


Medium 10 - 20% increase in cost
High more than 20% increase in cost

Impact on benefit:

Low benefits reduced by less than 5%


Medium benefits reduced by 5 - 10%
High benefits reduced by more than 10%

2009 ILX Group plc

20

PRINCE2 Practitioner Resource Book

PRINCE2 Project Simulation

Exercise 5 Quality in a Project Environment Simulation

Meeting Transcript

Stacey

Hi, Claire. Thanks for coming in this morning.

Claire

No problem Stacey. Were really looking forward to this job. I just want to make sure
we get it right first time and that youre pleased with the result.

Stacey

Thats great. Were starting the planning of the project and one of the most important
things that PRINCE2 suggests we do is write Product Descriptions for each of the
products were having delivered. One of the key aspects of each description is the
quality criteria as this makes sure that what we get is what we wanted. Hence our
meeting as I want to produce a Description for the Dcor Plan, which is something
that you will be doing for us.

Claire

Sounds great to me. It sounds like itll save a lot of confusion to-ing and fro-ing
between me and you as I try to get to grips with what you want. How can I help?

Stacey

Well I know that the reason for having a dcor plan is to make sure we can sign off
your designs before you start work, but how does it help you?

Claire

Well, itll make sure that I know what colours are going where and Ill be able to order
the right amount of materials, which should keep the costs to a minimum.

Stacey

Thats great. Im assuming that the architect will tell you what the colours will be?

Claire

Thats correct. It would also be useful if he were to provide a set of drawings


showing the relationships between the colours.

Stacey

Is there anything else that would be useful?

Claire

Yes, it would be useful to have a list of RAL colours and swatches so you can see
exactly what the colours will look like. An artists impression of the main areas would
also be good for you too.

Stacey

Okay, lets include those as well, although I guess we could do without the artists
impression. Where will you get them from?

Claire

The RAL numbers and artists impression from the architect, and Ill provide the
swatches.

Stacey

When will you have completed the dcor plan Claire?

Claire

It wont take me any longer than three weeks from now.

2009 ILX Group plc

21

PRINCE2 Practitioner Resource Book

PRINCE2 Project Simulation

Stacey

Thats good news itll have to be in the standard format. How will we know that
youve done it properly then Claire?

Claire

Well Im hoping that the architect will check it and also your Senior User and maybe
some of the people within the departments. Thats what usually happens with my
clients and it makes sure that the end users have bought into the scheme.

Stacey

I guess theyll have to check that youve included everything and that the colours are
correct. Well use the quality review technique for this, I think.

Claire

Sounds good to me! Well, if thats all Ill be getting along Ill hear from you in a
couple of days then?

Stacey

Yes you will. Thanks for your time.

2009 ILX Group plc

22

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Marking Up the PRINCE2 Manual

Marking up Exercise - Table of Contents

Overview:

Introduction to the exercise

PRINCE2 manual
chapter

Chapter title

Chapter 1

24
P2 manual
page
number

Resource
book page
number

Introduction

25

Chapter 2

Principles

11

26

Chapter 3

Introduction to PRINCE2 Themes

17

28

Chapter 4

Business Case

21

28

Chapter 5

Organization

31

30

Chapter 6

Quality

47

33

Chapter 7

Plans

61

35

Chapter 8

Risk

77

38

Chapter 9

Change

91

41

Chapter 10

Progress

101

42

Chapter 11

Introduction to processes

113

45

Chapter 12

Starting up a Project

121

45

Chapter 13

Directing a Project

135

47

Chapter 14

Initiating a Project

149

49

Chapter 15

Controlling a Stage

167

51

Chapter 16

Managing Product Delivery

185

53

Chapter 17

Managing a Stage Boundary

193

54

Chapter 18

Closing a Project

205

55

Chapter 19

Tailoring PRINCE2 to the project environment

215

56

Appendix A

Product Description Outlines

235

56

Appendix C

Roles and responsibilities

269

57

2009 ILX Group plc

23

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Overview:
This document has been compiled to provide students who are using the ILX Group Computer based
Training or On-line Study programme to gain the PRINCE2 Foundation qualification or in preparation
for the PRINCE2 Practitioner Exam.
The purpose of the document is to provide students with an insight into the PRINCE2 manual and to
identify many of the key statements in the manual; it also serves as an exercise for those going on to
the Practitioner Exam to break them out of the CBT and into the manual.
Candidates may take a copy of the PRINCE2 manual into the Practitioner examination. If students are
not familiar with the contents of the manual, valuable time may be lost, trying to find the appropriate
information during the exam. Highlighting the manual will act as a reference to key statements and
areas of the manual that are required for the Practitioner paper.
Task:
Work through the exercise reading and highlighting the PRINCE2 manual as suggested, annotating
the margin with any notes you feel will assist you.
Hint:
It is suggested that the student refers to the e-learning material on a section at a time basis, and then
refers to the manual and highlights the appropriate elements as suggested. This will help to
emphasise the context of the information and, through reading the supporting text, facilitate further
learning, familiarisation and appreciation of the PRINCE2 method.
Many of the suggested highlighted sections of the manual relate directly to Foundation Exam
questions. In many cases, the context of the statement to be highlighted has been left deliberately
vague in this document. This is to ensure that the student reads and understands the full text involved
and also reads the text associated with the highlighted element.
It is suggested that, prior to undertaking the e-learning Foundation course and highlighting exercise,
the manual chapters should be tabbed up for ease of reference this will be especially useful when
progressing to the Practitioner Exam.
Walk Through Example:
The PRINCE2 manual is a bound guide, although the table of contents is very comprehensive, we
have found that students who put tabs into the manual can find their way round much quicker. E.g.
using small post-it-notes adding one per Process and one per Theme along the long edge, and one for
the Tailoring chapter and Appendices along the short edge. Now, with a highlighter and pencil work
through the exercise below.
Materials Required:
Highlighter Pen, Pencil/pen, small post-it-notes
PRINCE2 Manual.
Time Required:
Approx 4-5 hours in total.
It should be noted that the highlighting exercise is intended as a revision aide, and should not in itself
be considered as a guide to passing either of the PRINCE2 exams. It should be used in conjunction
with other learning materials to provide an all round learning experience.

2009 ILX Group plc

24

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 1 INTRODUCTION

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

1.3

TB

A project is a temporary organization..

1.3

There are a number of

1.3

Change

Word only

1.3

Temporary

Word only

1.3

Cross functional

Words only

1.3

Unique

Word only

1.3

Uncertainty

Word only

1.4

TB

Project management is the planning ..

1.5.2

There are six variables involved ..

1.1

Project Management

1.5.2

1.6.1

Headings only : Costs, Timescales,


Quality, Scope, Risk, Benefits
It is not intended (or possible)

6/7

1.6.1

Headings only : Specialist aspects,


Detailed techniques, Leadership Capability

1.3

OGC best-practice guidance

1.6.1

Detailed techniques

Words only

1.6.1

Leadership capability

Words only

1.7

BENEFITS OF PRINCE 2

1.7

Before introducing the structure of the

1.7

All fourteen bullet points

2009 ILX Group plc

NOTES

Words only

25

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 2 PRINCIPLES
Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

NOTES

11

Principles are characterized as:

11

All three bullet points

11

The seven PRINCE2 principles can be


summarised as:

11

All seven bullet points

11

2.1

TB

A PRINCE2 project ..

11

2.1

A requirement for a PRINCE2 project ..

11

2.1

All three bullet points

11

2.1

In PRINCE2, the justification

11

2.1

If, for whatever reason, the project ..

12

2.2

TB

PRINCE2 project teams learn ..

12

2.2

In PRINCE2, learning from

12

2.2

Words only

12

2.2

When starting a project


As the project progresses

12

2.2

As the project closes

Words only

12

2.2

It is the responsibility

12

2.3

TB

A PRINCE2 project ..

12

2.3

To be successful, projects must have an

12

2.3

All projects have the following primary

12

2.3

Business sponsors

Words only

12

2.3

Users

Word only

12

2.3

Suppliers

Word only

13

2.4

TB

A PRINCE2 project is planned ..

13

2.4

At the end of each stage,

13

2.4

Planning can only be done to a level

13

2.4

PRINCE2 overcomes the planning

13

2.4

All three bullet points

13

2.4

PRINCE2 requires there to be a minimum of

13

2.5

TB

A PRINCE2 project has defined tolerances ..

13

2.5

PRINCE2 enables appropriate governance ..

13

2.5

Delegating authority from one management ..

13

2.5

Time, Cost, Quality, Scope, Risk, Benefit

Words only

Headings of bullet points

CHAPTER 2 PRINCIPLES (continued)

2009 ILX Group plc

26

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

13

2.5

Setting up controls

13

2.5

Putting an assurance mechanism in place

14

2.6

TB

A PRINCE2 project focuses on

14

2.6

A successful project is output-oriented ..

14

2.6

The purpose of a project is to fulfil

14

2.6

The product focus supports almost

14

2.7

TB

PRINCE2 is tailored to suit ..

14

2.7

The value of PRINCE2 is that

14

2.7

If PRINCE2 is not tailored, it is unlikely

14

2.7

The purpose of tailoring is to:

14

2.7

Both bullet points

14

2.7

Tailoring requires the Project Manager

14

2.7

To ensure that all those people involved ..

2009 ILX Group plc

NOTES

27

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 3 INTRODUCTION TO PRINCE2 THEMES


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

NOTES

17

3.1

The PRINCE2 themes describe aspects ..

17

3.1

17

3.1

The PRINCE2 processes address


The PRINCE2 themes

17

3.1

Themes: Business Case to Progress

All Theme headings

17

3.1

Answers: Why to Should we carry on?

All Answer headings

CHAPTER 4 BUSINESS CASE


Page

Section
Heading

4.1

S
P
B
D
H
TB
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box
The purpose of the Business ..

21
21

4.1

It is a PRINCE2 principle

21

4.1

The business justification is

21

4.1

The reasons for undertaking

21

4.1

This is based on whether the project

21

4.1

The Senior User(s) is responsible ..

21

4.1

In PRINCE2, the Business Case is ..

21

4.2.1

Since this viability question ..

21

4.2.2

All three bullet points

22

4.2.3

The reasons for undertaking projects .

22

4.1

Relationship between outputs, outcomes and


benefits

22

4.3

In PRINCE2, the Business Case

22

4.3.1

In PRINCE2 the Executive

23

4.2

23

4.3.1

The development path of the Business Case


If not, then the Project

23

4.3.1

Due to the inputs

23

4.3.2

The Business Case drives

23

4.3.2

To drive the decision making ..

23

4.3.2

All eight bullet points

23

4.3.2

It is the responsibility of the Executive

NOTES

CHAPTER 4 BUSINESS CASE (continued)

2009 ILX Group plc

28

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

24

4.3.3

The approach to confirming benefits is to:

24

4.3.3

All four bullet points

24

4.3.3

By default, the Executive is responsible

24

4.3.3

The Benefits Review Plan is first created

24

4.3.3

The benefits that can be measured during

25

4.3.3

The post-project benefits review(s) will

25

4.3.4

It typically contains:

25

4.3.4

All nine bullet points

25

4.3.4.1

Reasons

25

4.3.4.1

The Business Case should explain ..

25

4.3.4.2

Business options

25

4.3.4.2

All three bullet points

25

4.3.4.3

Expected benefits

25

4.3.4.3

The Business Case should list each

25

4.3.4.3

Benefits can be financial and non-financial

25

4.3.4.3

26

4.3.4.3

All five bullet points


If the project includes benefits that cannot ..

26

4.3.4.3

All three bullet points

26

4.3.4.4

Expected dis-benefits

26

4.3.4.4

A dis-benefit is an

26

4.3.4.5

Timescale

26

4.3.4.5

Corporate and/or programme

26

4.3.4.5

All five bullet points

26

4.3.4.6

Costs

27

4.3.4.7

Investment appraisal

27

4.3.4.8

Major risks

27

4.4

TB

Investment appraisal techniques

28

4.1

Responsibilities relevant to the Business


Case

2009 ILX Group plc

NOTES

29

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 5 - ORGANIZATION
Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

31

5.1

TB

The purpose of the Organization theme ..

31

5.1

PRINCE2 is based on a customer/supplier ..

31

5.1

One of the principles of PRINCE2 is

31

5.1

A successful project management

31

5.1

All four bullet points

31

5.2.1

Project

31

5.2.1

PRINCE2 defines a project as

31

5.2.2

A project which forms part of

31

5.2.4

In order to be flexible

31

5.2.4

It defines roles, each .

31

5.2.5

Three project interests

32

5.2.5

Figure 5.1 shows the three primary interests..

32

5.1

The three project interests

32

5.2.5

Business

Highlight heading

32

5.2.5

User

Highlight heading

32

5.2.5

Supplier

Highlight heading

32

5.2.5

Customer can usually be interpreted

32

5.3.1

Levels of organization

32/
33

5.3.1

The project management structure has

33

5.2

The four levels of management within the


project management structure

33

5.3.1

Corporate or programme management

Highlight heading

33

5.3.1

Directing

Highlight heading

33

5.3.1

Managing

Highlight heading

33

5.3

Project management team structure

34

5.3.1

Delivering
Project management team structure

34

5.3.2.1

34

5.3.2.1

A project management team is a temporary


structure

34

5.3.2.1

The Executive (representing the

34

5.3.2.1

Some of the PRINCE2 responsibilities ..

34

5.3.2.1

For example:

34

5.3.2.1

Highlight both bullet points

NOTES

Highlight heading

CHAPTER 5 ORGANIZATION (continued)

2009 ILX Group plc

30

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

NOTES

34

5.3.2.1

PRINCE2 provides role description outlines

34

5.3.2.2

PRINCE2 defines the duties

34

5.3.2.2

All eight bullet points

34

5.3.2.2

A good Project Board should

34

5.3.2.2

Authority

Word only

35

5.3.2.2

Credibility

Word only

35

5.3.2.2

Ability to delegate

Words only

35

5.3.2.2

Availability

Word only

35

5.3.2.2

The frequency and detail

35

5.3.2.2

Executive

35

5.3.2.2

Although the Project Board is responsible ..

35

5.3.2.2

The Executives role is to ensure

35

5.3.2.2

Throughout the project, the .

35

5.3.2.2

Senior User

35

5.3.2.2

The Senior User(s) is responsible for specifying ..

35

5.3.2.2

The Senior User role commits user

35

5.3.2.2

The Senior User(s) specifies the benefits and is


held

35

5.3.2.2

35

5.3.2.2

Senior Supplier
The Senior Supplier(s) represents the interests ..

36

5.3.2.2

If necessary, more than one person

36

5.3.2.3

Project Board members are responsible

36

5.3.2.4

Change Authority

36

5.3.2.4

One consideration at project initiation

36

5.3.2.4

To facilitate this, the Project Board

36

5.3.2.4

All four bullet points

37

5.4

Possible reporting structure using user and


supplier groups

38

5.3.2.6

Project Manager

38

5.3.2.6

The Project Manager is the single focus

38

5.3.2.6

The Project Manager manages the Team


Managers

38

5.5

The many facets of the Project Manager role

38

5.3.2.7

Team Manager

38

5.3.2.7

The Team Managers primary responsibility ..

CHAPTER 5 ORGANIZATION (continued)

2009 ILX Group plc

31

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

38

5.3.2.7

The Team Manager role may be assigned to


the Project Manager

38

5.3.2.7

Among these are the size of the project

39

5.3.2.7

If the Team Manager comes from

39

5.3.2.8

Project Support

39

5.3.2.8

Project Support is the responsibility ..

39

5.3.2.8

It is important to stress that the role of Project

39

5.3.2.8

Project Support and Project Assurance roles

39

5.3.3

Working with the project team

39

5.3.3.1

Balancing the project, team and individual

40

5.3.3.2

Training needs for project teams

40

5.3.3.3

Part-time teams

40

5.3.4

Working with the corporate organization

40

5.3.4.1

Line management/functional management

41

5.3.4.2

Centre of excellence

41

5.3.4.2

The concept of a centre of excellence is that ..

41

5.3.4.2

A centre of excellence can be useful where :

41

5.3.4.2

All four bullet points

41

5.3.5

41

5.3.5.1

Working with stakeholders


Types of stakeholder

41

5.3.5.1

There are likely to be individuals or groups ..

41

5.3.5.1

All four bullet points

41

5.3.5.2

Stakeholder engagement

41

5.3.5.2

Stakeholder engagement is the process of ..

42

5.3.5.3

The Communication Management Strategy

42

5.3.5.3

The Communication Management Strategy


contains

43

5.1

Responsibilities relevant to the Organization


theme

2009 ILX Group plc

NOTES

32

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 6 - QUALITY
Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

47

6.1

TB

The purpose of the

47

6.1

The Quality theme defines ..

47

6.1

Both bullet points

47

6.2

QUALITY DEFINED

47

6.2.1

Quality

47

6.2.1

Quality is generally defined as

47

6.2.2

Scope

47

6.2.2

The scope of a plan is

47

6.2.3

Quality management and quality management


systems

47

6.2.3

Quality management is defined .

48

6.2.4

Quality planning

48

6.2.4

To control anything, including quality ..

48

6.2.5

Quality control

48

6.2.5

Quality control focuses on the

48

6.2.5

Both bullet points

48

6.2.6

Quality assurance provides a check ..

48

6.2.6

Quality assurance activities are outside the

48

6.2.6

The term quality assurance ..

48

6.2.6

Both bullet points

48/49

6.2.6

Quality assurance should not be confused

48

6.1

The relationship between Project Assurance and


quality assurance

49

6.2.6

However, Project Assurance and..

49

6.3

All three bullet points

49

6.3

49

6.1

The first two of these are covered ..


The quality audit trail

50

6,3,1

Quality planning

50

6.3.1

The purpose of quality planning

50

6.3.1

Project Board agreement

Words only

50

6.3.1

Communicating

Word only

50

6.3.1

Control

Word only

50

6.3.1

Quality planning comprises:

50

6.3.1

All six bullet points

50

6.3.1.1

The customers quality expectations

2009 ILX Group plc

NOTES

33

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 6 QUALITY (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

50

6.3.1.1

To avoid misinterpretations

50

6.3.1.1

All three bullet points

51

6.3.1.2

Acceptance criteria

51

6.3.1.2

The projects acceptance criteria ..

51

6.3.1.2

Acceptance criteria should be ..

51

6.3.2.1

TB

Example of a prioritization technique MoSCoW

51

6.3.1.3

The Project Product Description

51

6.3.1.3

The Project Product Description includes:

51

6.3.1.3

All five bullet points

52

6.3.1.4

The Quality Management Strategy

52

6.3.1.4

The Quality Management Strategy is prepared ..

52

6.3.1.4

The Quality Management Strategy is maintained,


subject ..

52

6.3.1.5

Product Descriptions

52

6.3.1.5

Once detailed planning gets underway, ..

52

6.3.1.5

The level of detail in a Product Description ..

52

6.3.1.5

Care should be taken not to write ..

52

6.3.1.5

Quality criteria

52

6.3.1.5

The quality criteria should be of sufficient

52

6.3.1.5

Quality tolerances

52

6.3.1.5

Quality tolerances for a product can be

53

6.3.1.5

Quality methods

53

6.3.1.5

The quality methods section of the Product ..

53

6.3.1.5

53

6.3.1.5

Quality responsibilities
The responsibilities will fall

53

6.3.1.5

Highlight headings in all three bullet points

53

6.3.1.6

The Quality Register

53

6.3.1.6

The Quality Register is effectively a diary

53

6.2

Example of a Quality Register

54

6.3.2

Quality control

54

6.3.2

Quality control comprises:

54

6.3.2

All three bullet points

54

6.3.2.1

Quality methods

54

6.3.2.1

In-process methods

2009 ILX Group plc

NOTES

This heading only

Bold heading only

34

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 6 QUALITY (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

NOTES

54

6.3.2.1

Appraisal methods

Bold heading only

54

6.3.2.1

A systematic but flexible

54

6.3.2.1

All three bullet points

55

6.3.2.1

TB

All text box contents

56

6.3.2.1

TB

All text box contents

56

6.3.2.1

The formal approval of a product ..

56

6.3.2.1

The PRINCE2 quality review

56

6.3.2.1

Stakeholder engagement

Bold heading only

56

6.3.2.1

Leadership

Bold heading only

57

6.3.2.1

Team Building

Bold heading only

57

6.3.2.1

Developing individuals

Bold heading only

57

6.3.2.1

Quality documentation

Bold heading only

57

6.4.2.1

Quality culture

Bold heading only

57

6.3.2.2

Quality records

57

6.3.2.2

The records support entries in the Quality

57

6.3.2.2

All five bullet points

57

6.3.2.3

Approval records

57

6.3.2.3

While quality records provide

57

6.3.2.4

57

6.3.2.4

Acceptance records
But during the Closing a Project process

57

6.3.2.4

PRINCE2 uses the term acceptance to

57

6.3.2.4

Acceptance may be qualified, and documented .

58

6.3

Responsibilities relevant to the Quality theme

CHAPTER 7 PLANS
Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

61

7.1

TB

The purpose of the ..

61

7.1

Planning provides all personnel involved

61

7.1

All four bullet points

61

7.2.1

What is a plan?

2009 ILX Group plc

NOTES

35

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 7 PLANS (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

61

7.2.1

A PRINCE2 plan is more comprehensive

61

7.2.1

Plans are the backbone of the management ..

61

7.2.2

What is planning?

61

7.2.2

Planning is the act or process of

61

7.2.3

Levels of plan

61

7.2.3

PRINCE2 recommends three levels of plan ..

62

7.1

PRINCE2s planning levels

62

7.2.3

The Project Plan is created ..

62

7.2.3

The Initiation Stage Plan is created

62

7.2.3

Team Plans are created

62

7.2.3

The only other plan in PRINCE2 is ..

62

7.2.4

The Project Plan

62

7.2.4

The Project Plan:

62

7.2.4

All three bullet points

62

7.2.5

Stage Plans

62

7.2.5

The stage plan is similar ..

62

7.2.5

This approach allows the Stage Plan to:

62

7.2.5

All three bullet points

62

7.2.6

Team Plans

62

7.2.6

A Team Plan is produced

62

7.2.6

Team Plans are optional;

63

7.2.6

PRINCE2 does not prescribe the format ..

63

7.2.7

Exception Plans

63

7.2.7

An Exception Plan is a plan prepared ..

63

7.2.7

If a Stage Plan is being replaced, this ..

63

7.2.7

It picks up from the current plan ..

63

7.2

64

7.3.1

The PRINCE2 approach to plans


The philosophy behind

64

7.3.2

Prerequisites for planning design the plan

64

7.3.3

Define and analyse the products

65

7.3.3

The benefits of product-based planning include:

65

7.3.3

All eight bullet points

65

7.3.3.2

Create the product breakdown structure

65

7.3.3.2

When creating a product breakdown structure..

2009 ILX Group plc

NOTES

These words only

36

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 7 PLANS (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

65

7.3.3.2

First two bullets

65

7.3.3.2

Fourth bullet starting It is useful ..

First two sentences only

66

7.3.3.2

When using product-based

First sentence of bullet

66

7.3.3.2

When presenting the product ..

First two sentences only

66

7.3.3.2

If the project is broken down ..

First sentence of bullet

66

7.3.3.2

In some cases, the organizations ..

First sentence of bullet

66

7.3.3.3

Write the Product Descriptions

66

7.3.3.3

A Product Description is required

66

7.3.3.3

Product Descriptions should be written .

First sentence of bullet

66

7.3.3.3

A Product Description should be baselined .

First sentence of bullet

66

7.3.3.3

Although the responsibility

First sentence of bullet

66

7.3.3.3

Successful Product Descriptions

First sentence of bullet

66

7.3.3.3

If a detailed requirements specification

First sentence of bullet

67

7.3.3.3

For a small project

67

7.3.3.3

Quality criteria, aimed at

67

7.3.3.4

Create the product flow diagram

67

7.3.3.4

A product flow diagram needs to

67

7.3.3.4

When creating a product flow diagram ..

67

7.3.3.4

All four bullet points

67

7.3.4

Identify activities and dependencies

67

7.3.4.1

Activities

67

7.3.4.1

67

7.3.4.1

There are several ways ..


Both bullet points

67

7.3.4.2

Dependencies

67

7.3.4.2

External dependencies may, for example, be

67

7.3.4.2

All three bullet points

68

7.3.4.2

TB

Examples of estimating techniques

68

7.3.5

Prepare estimates

68

7.3.5

A decision about how much time

68

7.3.5

Both bullet points

68/69

7.3.5

TB

Basic rules for estimating

69

7.3.6

Prepare the schedule

69

7.3.6.1

Define activity sequence

69

7.3.6.1

Identifying a plans critical path ..

2009 ILX Group plc

NOTES

First sentence of bullet

All points

37

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 7 PLANS (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

69

7.3.6.1

Both bullet points

69

7.4

Simple activity-on-node diagram

70

7.3.6.2

Assess resource availability

70

7.3.6.3

Assign resources

70

7.3.6.4

Level resource usage

70

7.3.6.4

TB

The critical chain technique

70

7.3.6.5

Agree control points

70

7.3.6.6

Define milestones

71

7.3.6.7

Calculate total resource requirements and costs

71

7.3.6.7

The budget should include:

71

7.3.6.7

All four bullet points

71

7.3.6.7

The use of risk budgets and

71

7.3.6.8

Present the schedule

71

7.3.7

Analyse the risks

71

7.3.7

TB

Examples of presentation formats for the


schedule

72

7.3.7

TB

Examples of planning risks

72

7.3.8

Document the plan

73

7.1

Responsibilities relevant to the Plans theme

NOTES

CHAPTER 8 RISK
Page

Section
Heading

8.1

S
P
B
D
H
TB
H

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box
PURPOSE

77
77

8.1

TB

The purpose of the Risk ..

77

8.2.1

What is a risk?

77

8.2.1

A risk is an uncertain event ..

77

8.2.1

Threat

Word only

77

8.2.1

Opportunity

Word only

77

8.2.3

What is risk management?

77

8.2.3

The term risk management ..

77

8.2.3

For risk management to be

2009 ILX Group plc

NOTES

38

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 8 RISK (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

NOTES

77

8.2.3

Identified

Word only

77

8.2.3

Assessed

Word only

77

8.2.3

Controlled

Word only

78

8.1

Organizational perspectives

78

8.3.1

All nine bullet points

78

8.3.2

An organizations risk management policy should

First sentence only

78

8.3.2

An organizations risk management process ..

First sentence only

79

8.3.3

A key decision that needs to be recorded

79

8.3.4

Risk Register

79

8.3.4

All eleven bullet points

79

8.3.5

Risk management procedure

79

8.3.5

All five bullet points

80

8.3.5.1

The following will have an influence

80

8.3.5.1

All seven bullet points

80

8.3.5.1

The Risk Management Strategy will include ..

80

8.3.5.1

All twelve bullet points

80

8.3.5.1

Early warning indicators could include ..

80

8.3.5.1

All eight bullet points

81

8.3.5.1

TB

Risk identification techniques

81

8.3.5.1

Identify risks

81

8.3.5.1

All three bullet points

81

8.3.5.1

A useful way of expressing risk ..

81

8.3.5.1

Risk cause

Words only

81

8.3.5.1

Risk event

Words only

81

8.3.5.1

Risk effect

Words only

82

8.3.5.2

Assess

82

8.3.5.2

Estimate

82/83

8.3.5.2

TB

Risk estimation techniques

83

8.3.5.2

PRINCE2 recommends that the following ..

83

8.3.5.2

83

8.3.5.2

TB

All four bullet points


Risk evaluation techniques

83

8.3.5.3

Plan

84

8.5

Probability impact grid

84

8.6

Summary risk profile

2009 ILX Group plc

39

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 8 RISK (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

85

8.7

Threat and opportunity responses

85

8.3.5.4

Implement

85

8.3.5.4

Risk owner

Words only

85

8.3.5.4

Risk actionee

Words only

86

8.2

Risk responses

86

8.2

Avoid (threat)

Words only

86

8.2

Reduce (threat)

Words only

86

8.2

Fallback (threat)

Words only

86

8.2

Transfer (threat)

Words only

86

8.2

Accept (threat)

Words only

86

8.2

Share (threat or opportunity)

Words only

86

8.2

Exploit (opportunity)

Words only

87

8.2

Enhance (opportunity)

Words only

87

8.2

Reject (opportunity)

Words only

87

8.3.5.5

Communicate

87

8.3.5.5

Risks are communicated as part of the

87

8.3.5.5

All four bullet points

87

8.3.5.5

A projects exposure to risk is never

87

8.3.5.5

Effective risk management is dependent on ..

87

8.3.6

Risk budget

87

8.3.6

A risk budget, if used, is a sum of money ..

88

8.3

Responsibilities relevant to the Risk theme

2009 ILX Group plc

NOTES

First sentence only

40

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 9 CHANGE
Page

Section
Heading

9.1

S
P
B
D
H
TB
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box
The purpose of ..

91
91

9.1

Change is inevitable during the life ..

91

9.1

Issue and change control is a continual ..

91

9.1

The aim of issue and change control ..

91

9.2.3

Issues

91

9.2.3

PRINCE2 uses the term issue to

92

9.1

Types of issue

92

9.1

Request for change

Words only

92

9.1

Off-specification

Words only

92

9.1

Words only

92

9.3.1

Problem/concern
Establish controls

92

9.3.1

The following management products are

92

9.3.1

All six bullet points

92

9.3.1.1

Configuration Management Strategy

92

9.3.1.1

All seven and three bullet points

93

9.3.1.1

TB

Example of priority and severity

Also highlight inside box


MoSCoW

93

9.3.1.1

Change Authority

Words only

93

9.3.1.1

Change budget

Words only

93

9.3.1.2

Configuration Item Records

93

9.3.1.3

Product Status Account

93

9.3.1.4

Daily Log

94

9.3.1.5

Issue Register

94

9.3.1.6

Issue Report

94

9.3.2

Configuration management procedure

94

9.3.2

Planning

Word only

94

9.3.2

Identification

Word only

94

9.3.2

Control

Word only

94

9.3.2

Status accounting

Words only

94

9.3.2

Verification and audit

Words only

94

9.3.3

Issue and change control procedure

95

9.1

Issue and change control procedure

95

9.3.3.1

Capture

95

9.3.3.1

The purpose of distinguishing between

2009 ILX Group plc

NOTES

Also all five headings

41

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 9 CHANGE (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

95

9.3.3.1

All three bullet points

95

9.3.3.2

Examine

95

9.3.3.2

The impact analysis should

95

9.3.3.2

All three bullet points

96

9.3.3.2

The Issue Register and Issue Report ..

96

9.3.3.3

Propose

96

9.2

Options analysis

96

9.3.3.4

Decide

96

9.3.3.4

The escalation could be in the form of an Issue ..

96

9.3.3.5

Implement

96

9.3.3.5

Both bullet points

96

9.4

RESPONSIBILITIES

97

9.2

Project Board decisions

97

9.3

Responsibilities relevant to the Change theme

NOTES

CHAPTER 10 PROGRESS
Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

101

10.1

TB

The purpose of the ..

101

10.2

PROGRESS DEFINED

101

10.2.1

What is progress?

101

10.2.1

Progress is the measure of the

101

10.2.2

What are progress controls?

101

10.2.2

Progress controls ensure that for

101

10.2.2

All six bullet points

101

10.2.3

Exceptions and tolerances

101

10.2.3

An exception is a situation where ..

101

10.2.3

Tolerances are the permissible deviation ..

102

10.1

The six tolerance areas by level

102

10.3

THE PRINCE2 APPROACH TO PROGRESS

NOTES

CHAPTER 10 PROGRESS (continued)

2009 ILX Group plc

42

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

NOTES

102

10.3

PRINCE2 provides progress

102

10.3

All four bullet points

102

10.3.1

Delegating authority

102

10.3.1.1

The four levels of management

103

10.3.1.1

All four bullet points

103

10.3.1.2

Project Board controls

103/
104

10.3.1.2

All bullet points

103

10.1

Delegating tolerance and reporting actual and


forecast progress

104

10.3.1.3

Project Manager controls

104

10.3.1.3

Authorizations

Word only

104

10.3.1.3

Progress updates

Words only

104

10.3.1.3

Words only

104

10.3.2

Exceptions and changes


Use of management stages for control

104

10.3.2

Management stages:

104

10.3.2

All four bullet points

104

10.3.2.1

Number of stages

104

10.3.2.1

The use of management stages in a PRINCE2 ..

104

10.3.2.1

Defining management stages is

104/
105

10.3.2.1

All bullet points

105

10.3.2.2

Length of stages

105

10.3.2.2

The planning horizon at any point in time

These words only

105

10.3.2.2

The technical stages within the project

These words only

105

10.3.2.2

Alignment with programme activities

These words only

105

10.3.2.2

The level of risk

These words only

105

10.3.2.3

Technical stages

105

10.3.2.3

Technical stages often overlap

106

10.2

Specialist work defined in technical stages

106

10.3

Specialist work crossing management stage


boundary

106

10.4

Specialist work aligned to management stages

106

10.3.3

Event-driven and time-driven controls

106

10.3.3

Event-driven controls

These words only

CHAPTER 10 - PROGRESS (continued)

2009 ILX Group plc

43

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

NOTES

106

10.3.3

Timedriven controls

These words only

106

10.3.3.1

Baselines for progress control

106/
107

10.3.3.1

Headings: Project Plan, Stage Plans, Exception


Plan, Work Packages

107

10.3.3.2

Reviewing progress

107

10.3.3.2

107

10.3.3.2

The following management products assist


Headings : Daily Log, Issue Register, Product
Status Account, Quality Register, Risk Register

108

10.3.3.3

Capturing and reporting lessons

108

10.3.3.3

Headings : Lessons Log and Lessons Report

108

10.3.3.4

Reporting progress

108

10.3.3.4

The following management products are used ..

108/
109

10.3.3.4

Headings : Checkpoint Report, Highlight Report,


End Stage Report, End Project Report

109

10.3.4

Raising exceptions

109

10.3.4

Headings : Work-Package-level exceptions,


Stage-level exceptions, Project-level exceptions

110

10.2

Responsibilities relevant to the Progress theme

2009 ILX Group plc

44

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 11 INTRODUCTION TO PROCESSES


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

113

11.1

PRINCE2 is a process based ..

113

11.1

Figure 11.1 shows

113

11.1

The PRINCE2 processes

115

11.2

PRINCE2 process model Notes 1 and 2

115

11.4.1

Purpose

115

11.4.1

This section

115

11.4.2

Objective

115

11.4.2

This section ..

115

11.4.4

Activities

115

11.4.4

PRINCE2 processes comprise

115

11.4.4

The relationship between ..

116

11.3

Relationship between processes, activities and


actions

116

11.4.4

Each activity is concluded ..

116

11.4.4

Note that management products

116

11.1

An example of a table of responsibilities

117

11.2

Key to process diagrams

NOTES

CHAPTER 12 STARTING UP A PROJECT


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

121

12.1

The purpose of the Starting

121

12.1

The aim is to do the minimum

121

12.2

The objective of the Starting up ..

121

12.2

All seven bullet points

121

12.1

Overview of Starting up a Project

122

12.3

PRINCE2 calls the trigger ..

122

12.3

122

12.3

The term project mandate


The project mandate should provide the

122

12.3

The preparation of the outline Business Case .

2009 ILX Group plc

NOTES

45

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 12 STARTING UP A PROJECT (continued)


Page
Section S
Sentence beginning
Heading P
Paragraph beginning
B
Bullets
D
Diagram
H
Heading
TB
Text Box
122

12.3

The contents of the Project Brief ..

122

12.4

The activities within the Starting up ..

122

12.4

All six bullet points

123

12.4.1

Appoint the Executive and the Project Manager

123

12.4.1

To get anything done in the project ..

123

12.4.1

The appointment of a Project Manager ..

123

12.1

Appoint the Executive and the Project Manager :


responsibilities

124

12.4.2

Capture previous lessons

124

12.4.2

A number of lessons may have

124

12.4.2

It may be useful

124

12.4.2

Attendees could include any interested

124

12.4.3

Design and appoint the project management team

124

12.4.3

The project needs the right ..

124

12.3

Capture previous lessons: activity summary

125

12.2

Capture previous lessons: responsibilities

125

12.4

Design and appoint the project management


team: activity summary

126

12.4.4

Prepare the outline Business Case

126

12.4.4

When setting up, and particularly ..

126

12.3

Design and appoint the project management


team: responsibilities

127

12.5

Prepare the outline Business Case : activity


summary

127

12.4

Prepare the outline Business Case :


responsibilities

128

12.4.5

Select the project approach and assemble the


Project Brief

128

12.4.5

Before any planning of the project ..

128

12.4.5

For example, will ..

128

12.4.5

An agreed Project Brief ..

129

12.6

Select the project approach and assemble the


Project Brief: activity summary

129

12.5

Select the project approach and assemble the


Project Brief: responsibilities

2009 ILX Group plc

NOTES

46

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 12 STARTING UP A PROJECT (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

130

12.4.6

Plan the initiation stage

130

12.4.6

130

12.7

Initiating a Project takes ..


Plan the initiation stage: activity summary

131

12.6

Plan the initiation stage: responsibilities

NOTES

CHAPTER 13 DIRECTING A PROJECT


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

135

13.1

PURPOSE

135

13.1

The purpose of the

135

13.2

The objective of the Directing ..

135

13.2

All six bullet points

135

13.3

The Directing a Project process ..

135

13.3

The Project Board manages by exception.

135

13.3

There should be no need for other ..

135

13.3

There needs to be a two-way flow ..

135

13.3

This need, and how it is

135

13.1

Overview of Directing a Project

136

13.3

The Project Board is responsible

136

13.4

ACTIVITIES

136

13.4

The activities within the Directing ..

136

13.4

All five bullet points

136

13.4.1

Authorize initiation

136

13.4.1

Projects take time and cost ..

136

13.2

Authorize initiation: activity summary

137

13.4.2

This activity will be triggered by a

137

13.1

Authorize initiation: responsibilities

138

13.3

Authorize the project: activity summary

139

13.2

Authorize the project: responsibilities

2009 ILX Group plc

NOTES

47

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 13 DIRECTING A PROJECT (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

139

13.4.3

Authorize a Stage or Exception Plan

139

13.4.3

It is important that

139

13.4.3

Approval of Stage Plans occurs ..

139

13.4.3

If an exception has occurred during

140

13.4

Authorize a Stage or Exception Plan: activity


summary

141

13.4.4

Give ad hoc direction

141

13.4.4

Project Board members may offer .

141

13.4.4

Ad hoc direction may be ..

141

13.3

Authorize a Stage or Exception Plan:


responsibilities

142

13.5

Give ad hoc direction: activity summary

143

13.4.5

Authorize project closure

143

13.4.5

143

13.4.5

The controlled close of a project ..


All three bullet points

143

13.4

Give ad hoc direction: responsibilities

144

13.6

Authorize project closure: activity summary

145

13.5

Authorize project closure: responsibilities

2009 ILX Group plc

NOTES

48

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 14 INITIATING A PROJECT


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

149

14.1

PURPOSE

149

14.1

The purpose of the Initiating ..

149

14.2

The objective of the Initiating

149/
150

14.2

All ten bullet points

149

14.1

Overview of initiating a Project

150

14.3

CONTEXT

150

14.3

Initiating a Project is aimed ..

150

14.4

The activities within the Initiating ..

150

14.4

All eight bullet points

150

14.4.1

Prepare the Risk Management Strategy

150

14.4.1

The Risk Management Strategy ..

151

14.2

Prepare the Risk management Strategy: activity


summary

151

14.1

Prepare the Risk Management Strategy:


responsibilities

152

14.4.2

Prepare the Configuration Management Strategy

152

14.4.2

Configuration management is essential ..

152

14.3

Prepare the Configuration Management Strategy:


activity summary

153

14.4.3

Prepare the Quality Management Strategy

153

14.4.3

A key success factor of any ..

153

14.2

Prepare the Configuration Management Strategy:


responsibilities

154

14.4

Prepare the Quality Management Strategy:


activity summary

154

14.3

Prepare the Quality Management Strategy:


responsibilities

155

14.4.4

Prepare the Communication Management


Strategy

155

14.4.4

The Communication Management Strategy ..

155

14.5

Prepare the Communication Management


Strategy: activity summary

156

14.4.5

Set up the project controls

156/
157

14.4.5

The level of control required

NOTES

CHAPTER 14 INITIATING A PROJECT (continued)

2009 ILX Group plc

49

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

156

14.4

Prepare the Communication Management


Strategy: responsibilities

157

14.6

Set up the project controls: activity summary

158

14.5

Set up the project controls: responsibilities

159

14.4.6

Create the Project Plan

159

14.4.6

Before committing to major ..

159

14.7

Create the Project Plan: activity summary

160

14.6

Create the Project Plan: responsibilities

161

14.8

Refine the Business Case: activity summary

161

14.4.7

Refine the Business Case

161

14.4.7

The outline Business Case ..

162

14.7

Refine the Business Case: responsibilities

162

14.4.8

Assemble the Project Initiation Documentation

162

14.4.8

There needs to be a focal point ..

162

14.4.8

Both bullet points

163

14.9

Assemble the Project Initiation Documentation:


activity summary

164

14.8

Assemble the Project Initiation Documentation:


responsibilities

2009 ILX Group plc

NOTES

50

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 15 CONTROLLING A STAGE


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

167

15.1

PURPOSE

167

15.1

The purpose of the Controlling a Stage ..

167

15.2

OBJECTIVE

167

15.2

The objective of the Controlling a Stage ..

167/
168

15.2

All five bullet points

167

15.1

Overview of Controlling a Stage

168

15.3

The Controlling a Stage process ..

168

15.3

Towards the end of each stage ..

168

15.3

Work Packages are used to ..

168

15.4

ACTIVITIES

168

15.4

Controlling a Stage activities are ..

168

15.4

All three bullet points

168

15.4.1

Authorize a Work Package

168

15.4.1

It would be chaotic to ..

168

15.4.1

It is therefore important that ..

169

15.2

Authorize a Work Package: activity summary

170

15.4.2

Review Work Package status

170

15.4.2

170

15.1

This activity provides the means ..


Authorize a Work Package: responsibilities

171

15.3

Review Work Package status: activity summary

171

15.2

Review Work Package status: responsibilities

172

15.4.3

Receive completed Work Packages

172

15.4.3

Where work has been allocated ..

172

15.4

Receive completed Work Packages: activity


summary

173

15.3

Receive completed Work Packages:


responsibilities

173

15.4.4

Review the stage status

173

15.4.4

If the project is not checked ..

174

15.5

Review the stage status: activity summary

175

15.4

Review the stage status: responsibilities

175

15.4.5

Report highlights

175

15.4.5

The Project Manager must provide ..

NOTES

CHAPTER 15 CONTROLLING A STAGE (continued)

2009 ILX Group plc

51

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

176

15.6

Report highlights: activity summary

176

15.4.6

Capture and examine issues and risks

176

15.4.6

In the course of managing ..

177

15.5

Report highlights: responsibilities

178

15.7

Capture and examine issues and risks: activity


summary

178

15.6

Capture and examine issues and risks:


responsibilities

179

15.4.7

Escalate issues and risks

179

15.4.7

A stage should not exceed the tolerances ..

179

15.8

Escalate issues and risks: activity summary

180

15.4.8

Take corrective action

180

15.4.8

Changes and adjustments ..

180

15.7

Escalate issues and risks: responsibilities

181

15.9

Take corrective action: activity summary

182

15.8

Take corrective action: responsibilities

2009 ILX Group plc

NOTES

52

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 16 MANAGING PRODUCT DELIVERY


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

185

16.1

PURPOSE

185

16.1

The purpose of the Managing Product ..

185

16.2

OBJECTIVE

185

16.2

The objective of the Managing ..

185

16.2

All four bullet points

185

16.3

CONTEXT

185

16.3

185

16.1

Managing Product Delivery


Overview of Managing Product Delivery

186

16.2

Accept a Work Package: activity summary

186

16.1

Accept a Work Package: responsibilities

186

16.4

ACTIVITIES

186

16.4

The activities within ..

186

16.4

All three bullet points

187

16.4.1

Accept a Work Package

187

16.4.1

The fundamental principle is that ..

187

16.3

Execute a Work Package: activity summary

188

16.4.2

Execute a Work Package

188

16.4.2

The work has to be executed ..

188

16.2

Execute a Work Package: responsibilities

189

16.4

Deliver a Work Package: activity summary

189

16.3

Deliver a Work Package: responsibilities

190

16.4.3

Deliver a Work Package

190

16.4.3

Just as the Work Package was accepted ..

2009 ILX Group plc

NOTES

53

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 17 MANAGING A STAGE BOUNDARY


Page

Section
Heading

17.1

S
P
B
D
H
TB
H

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box
PURPOSE

193
193

17.1

The purpose of the Managing a Stage ..

193/194

17.1

Projects do not always go to plan ..

193

17.1

Overview of Managing a Stage Boundary

194

17.2

OBJECTIVE

194

17.2

The objective of the Managing a Stage ..

194

17.2

All eight bullet points

194

17.3

CONTEXT

194

17.3

A project, whether large or small, ..

194

17.3

A positive decision not to ..

194

17.4

ACTIVITIES

194

17.4

The activities within the Managing a Stage ..

194

17.4

All five bullet points

194

17.4.1

Plan the next stage

194

17.4.1

The Stage Plan for the next

195

17.2

Plan the next stage: activity summary

195

17.1

Plan the next stage: responsibilities

196

17.4.2

Update the Project Plan

196

17.4.2

The Project Plan is updated ..

196

17.3/
17.2

Update the Project Plan: activity summary and


Update the Project Plan: responsibilities

197

17.4.3

Update the Business Case

197

17.4.3

The Project Board is ordinarily

198

17.4

Update the Business Case: activity summary

198

17.3

Update the Business Case: responsibilities

199

17.4.4

Report stage end

199

17.4.4

The results of a stage should ..

199

17.5

Report stage end: activity summary

200

17.4.5

Produce an Exception Plan

200

17.4.5

If a stage or the project is forecast ..

200

17.4

Report stage end: responsibilities

201

17.6

Produce an Exception Plan: activity summary

201

17.4.5

Exception Plans are requested ..

202

17.5

Produce an Exception Plan: responsibilities

NOTES

CHAPTER 18 CLOSING A PROJECT

2009 ILX Group plc

54

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

205

18.1

PURPOSE

205

18.1

The purpose of the Closing a Project ..

205

18.2

OBJECTIVE

205

18.2

The objective of the Closing a ..

205

18.2

All five bullet points

205

18.3

A clear end to a project:

205

18.1

Overview of Closing a Project

206

18.3

All three bullet points

206

18.4

The activities within the Closing

206

18.4

All five bullet points

206

18.4.1

Prepare planned closure

206

18.4.1

Before closure of the project ..

206

18.2

Prepare planned closure: activity summary

207

18.1

Prepare planned closure: responsibilities

207

18.4.2

Prepare premature closure

207

18.4.2

In some situations, the .

207

18.3

Prepare premature closure: activity summary

208

18.4.3

Hand over products

208

18.4.3

The projects products must

208

18.2

Prepare premature closure: responsibilities

209

18.4

Hand over products: activity summary

209

18.3

Hand over products: responsibilities

210

18.4.4

210

18.4.4

Evaluate the project


Successful organizations learn from ..

210

18.5

Evaluate the project: activity summary

211

18.4

Evaluate the project: responsibilities

211

18.4.5

Recommend project closure

211

18.4.5

Once the Project Manager ..

212

18.6

Recommend project closure: activity summary

212

18.5

Recommend project closure: responsibilities

2009 ILX Group plc

NOTES

55

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

CHAPTER 19 TAILORING PRINCE2 TO THE PROJECT ENVIRONMENT


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

215

19.1

WHAT IS TAILORING

215

19.1

PRINCE2 can be used ..

215

19.1

Tailoring refers to the appropriate ..

NOTES

APPENDIX A PRODUCT DESCRIPTION OUTLINES


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

235

A.1

BENEFITS REVIEW PLAN

237

A.2

BUSINESS CASE

238

A.3

CHECKPOINT REPORT

239

A.4

COMMUNICATION MANAGEMENT STRATEGY

240

A.5

CONFIGURATION ITEM RECORD

241

A.6

CONFIGURATION MANAGEMENT STRATEGY

242

A.7

DAILY LOG

243

A.8

END PROJECT REPORT

244

A.9

END STAGE REPORT

245

A.10

EXCEPTION REPORT

245

A.11

HIGHLIGHT REPORT

246

A.12

ISSUE REGISTER

247

A.13

ISSUE REPORT

248

A.14

LESSONS LOG

249

A.15

LESSONS REPORT

250

A.16

PLAN

251

A.17

PRODUCT DESCRIPTION

253

A.18

PRODUCT STATUS ACCOUNT

253

A.19

PROJECT BRIEF

254

A.20

PROJECT INITIATION DOCUMENTATION

256

A.21

PROJECT PRODUCT DESCRIPTION

257

A.22

QUALITY MANAGEMENT STRATEGY

2009 ILX Group plc

NOTES

56

PRINCE2 Practitioner Resource Book

Marking Up a PRINCE2 Manual

APPENDIX A PRODUCT DESCRIPTION OUTLINES (continued)


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

258

A.23

QUALITY REGISTER

259

A.24

RISK MANAGEMENT STRATEGY

260

A.25

RISK REGISTER

261

A.26

WORK PACKAGE

NOTES

APPENDIX C ROLES AND RESPONSIBILITIES


Page

Section
Heading

S
P
B
D
H
TB

Sentence beginning
Paragraph beginning
Bullets
Diagram
Heading
Text Box

269

C.1

PROJECT BOARD

270

C.2

EXECUTIVE

270

C.3

SENIOR USER

271

C.4

SENIOR SUPPLIER

271

C.5

PROJECT MANAGER

272

C.6

TEAM MANAGER

273

C.7

PROJECT ASSURANCE

274

C.8

CHANGE AUTHORITY

274

C.9

PROJECT SUPPORT

2009 ILX Group plc

NOTES

57

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Practical Practitioner Exercises

Introduction
This section of the course contains a selection of Practitioner based exercises. These are intended to
extend your ability to apply PRINCE2 in a practical manner.
Each exercise is stand-alone and is intended to increase your knowledge of the PRINCE2 manual in
specific areas. Subjects include Risk Analysis, Organisation and the Business Case.
Feel free to attempt the exercises in any order. You may find they provide a useful departure from the
e-learning course.
Suggested answers to each exercise are provided towards the end of this lesson. The suggested
answers are intended to provide you with valuable feedback on how you should have approached
each activity and why.

2009 ILX Group plc

58

PRINCE2 Practitioner Resource Book

Exercise 1

Practical Practitioner Exercises

PRINCE2 Processes
Overview: Success in the Foundation Exam requires a good understanding of what makes up the
PRINCE2 method and the flows of documents, i.e. Management Products, within it.
Task: For this exercise you are to produce an overall process map for the seven PRINCE2
processes showing the main products and information flows.
Hints: a) You do not need to produce a detailed map showing each individual activity within a given
process. Your map should show in which process where the important Management Products are
created and their subsequent flow into further processes. In other words, a good high level overview
of the method is required.
b) Start your map by drawing the seven PRINCE2 Processes on an A4 sheet splitting them into the
three management levels in a project structure prior to adding what you think are the important
Management Products.
The main benefits from this exercise will be knowledge gained from the research you will need to do
into each process. You should feel confident when dealing with PRINCE2 by gaining a clear
understanding of the relationships between the processes and information flow, expressed on a single
page.

Answer/Notes:

2009 ILX Group plc

59

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Answer/Notes:

2009 ILX Group plc

60

PRINCE2 Practitioner Resource Book

Exercise 2

Practical Practitioner Exercises

Business Case
Scenario:
The Government has brought in a great deal of new Social Services legislation. The local council has
realised belatedly that their current Social Services information systems (SSIS) will not cope with this
legislation. Central Government has given councils one more year to meet the new requirements, after
which failure to provide the necessary returns could result in substantial fines. A new system to meet
the requirements will also automatically collate data that currently requires three administration staff to
do manually.
Up to now the different Social Services functions have held their own records on small computers,
offering only basic facilities. Duplications and omissions are a big problem. This has led to many costly
mistakes in payments in the past. These records will have to be corrected by Social Workers before
transferring to the new system when the latter has been installed.
It has been decided to place a contract with an external supplier for hardware and software. This will
replace all the current small computers with one powerful machine, which offers many extra facilities
plus operating economies. The supplier is already part way through the design of a system, based on
specifications agreed with two other councils. The purchase order will be signed as soon as the
Project Initiation Document is approved. The supplier also uses PRINCE2.
The old and new programs use the same database software, so no major conversion work will be
needed.
Five computer operators and seven other SSIS staff will need training in the new hardware and
software. There will then be further significant work by SSIS staff to prepare the new system for
operational use.
The supplier, in the tender, has offered to make small adjustments at no cost at certain points in the
new software to fit in with local practices. From the suppliers point of view these have to be carefully
monitored in order to stay within a very tight timescale and budget if the supplier is to make a profit.
The Council must specify these changes within three months of the contract being signed. Two
hundred Social Services staff need to be trained to use the new software.
a) Based on the above scenario, give the information that you would expect to see in the Customers
Business Case under the headings of Reasons, Costs, Timescale and Expected benefits.
b) Identify the PRINCE2 activities and products that create, modify or use the Business Case.

Answer/Notes:

2009 ILX Group plc

61

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Answer/Notes:

2009 ILX Group plc

62

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Exercise 3

Organisation
Scenario:
Sunny View Caravans Limited is a small but successful specialist firm producing very high quality
static caravans. They have been producing the caravans for over 30 years at a factory unit that has
been rented from a property company.
They have been given warning that the property company has sold the land on which the factory is
based for housing development and that they must have vacated the property by 1st July.
Since receiving notice of termination, the owner of the business has identified new premises, which
are located some 10 miles away. The new factory is a brand new unit on a small industrial estate
which is being developed by the local authority. At present, the roadways onto the estate are not
completed, so access is restricted to light vehicles. The local authority expects the roadways to be
finished by 31st May.
The unit is just a shell at the moment and it will be necessary to partition off offices within the shell
this work will be done by the workers who build the caravans and the production manager estimates
that six of his workers will be able to complete the work within 10 days of the drawing office completing
the designs. It is planned that a sub-contractor will be brought in to fit the services, computer network
and decorate the offices.
All the factory machinery will require moving to the new site during the month of June (ie. after the
roads have been completed, but before the deadline for vacating the old premises). A three-phase
electricity supply will also have to be installed by special arrangement with the local electricity
company.
A further complicating factor is that there are twelve caravans in the process of construction these
will have to be transported in their part-finished condition from the old to the new factory. A suitable
transport contractor with a large enough low-loader and crane has already been identified. The firm
estimates that each caravan will take one day to transport and they only have one low-loader and
crane capable of doing the job.
The owner of the business is concerned that they do not have the necessary skills to manage such an
important project and they have retained your services, as a professional Project Manager, to manage
the whole re-location. Today is your first day of work on the project and the date is 1st May.

a) Draw an Organisation Structure for the project, identifying the people who would fill each role.
b) Briefly explain any other project organisation options that you might consider.
c)

Answer/Notes:

2009 ILX Group plc

63

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

2009 ILX Group plc

64

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Answer/Notes:

2009 ILX Group plc

65

PRINCE2 Practitioner Resource Book

Exercise 4

Practical Practitioner Exercises

Risk Analysis
Based on the Sunny View Caravans scenario (see Exercise 3):
a) Select three risks associated with this scenario and using the PRINCE2 approach, carry out a
risk analysis giving reasons for each step for each risk.
b) Make proposals for the implementation of the risk response and the subsequent communication
activities..
c) Identify when risks are considered throughout a project.
Answer/Notes:

2009 ILX Group plc

66

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

2009 ILX Group plc

67

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Answer/Notes:

2009 ILX Group plc

68

PRINCE2 Practitioner Resource Book

Exercise 5

Practical Practitioner Exercises

Quality
Scenario:
You work for a large company that has a history of delivering poor quality products. In particular the
company seems to get a lot of poor quality work from its sub-contractors, but things are so muddled

that it is difficult to pin down who did the work. On return from a PRINCE2 course you are given an
existing project to manage where a major slippage has been announced, but too late for senior
management to do much about it. The previous project manager has been moved to other work, but is

available for information about the project. The project has not been run under PRINCE2 .
The senior management in charge blame the previous project manager, but the chairman tells you in
confidence that she believes there is a lack of senior management control. At the first chat with the
previous project manager he says, "Its such a huge, complex plan for a 12-month project. Its
impossible with such a timescale to spot small slippages until the accumulative effect ruins the
schedule. As it is I am spending nearly all of my time trying to keep this monster plan up-to-date."
The problem is made worse because the project in question is working to a very tight deadline.
Management is worried that a competitor might beat them to the market with a similar product.

a) How does PRINCE2 address the problem of delivering poor quality products? Be specific in
terms of components, processes and techniques that would contribute.

b) How would PRINCE2 tackle the problem of sub-contractors delivering poor quality products?

Answer/Notes:

Answer/Notes:

2009 ILX Group plc

69

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

2009 ILX Group plc

70

PRINCE2 Practitioner Resource Book

Exercise 6

Practical Practitioner Exercises

Product Breakdown Structures


Based on the Sunny View Caravans scenario (see Exercise 3):
a) Create a Product Breakdown Structure and a Product Flow Diagram for the specialist products of
the project.

Answer/Notes:

2009 ILX Group plc

71

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Answer/Notes:

2009 ILX Group plc

72

PRINCE2 Practitioner Resource Book

Exercise 7

Practical Practitioner Exercises

Produce a Product Description


Based on the Sunny View Caravans scenario (see Exercise 3):
Produce a Product Description for the new office design.
Answer/Notes:

2009 ILX Group plc

73

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

2009 ILX Group plc

74

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Answer/Notes:

2009 ILX Group plc

75

PRINCE2 Practitioner Resource Book

Exercise 1 - Suggested Answer

Practical Practitioner Exercises

In order to check your finished map, please compare it with the Process Model diagram printed in
Session 2 of the e-learning. Apart from the triggers shown on the Process Model, your map should be
similar. The three levels of management in a PRINCE2 project team are Direction, Management and
Delivery, represented by the Project Board, Project Manager and Team Managers respectively.

2009 ILX Group plc

76

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Exercise 2 - Suggested Answer

a) Reasons:
New SS legislation
Government mandating compliant systems (avoid fines)
Operational economies and improvements
Cost:
Hardware & software costs
Project Management costs
Correcting existing duplications & omissions
Training operators (5+7)
Training 200 staff to use the new software
Preparing new system for use
Timescale:
System changes to be specified within three months
System must be fully operational within one year
Expected benefits:
Avoidance of fines
Ability to cope with new legislation
Additional facilities
Operational economies
Proven solution (with two other councils)
Improvement to quality of data
b) PRINCE2 Activities within Processes that create, modify or use the Business Case:
Starting Up a Project process:
Prepare the outline Business Case
Select the project approach and assemble the Project Brief
Directing a Project:
Authorize initiation
Authorize the project
Authorize a Stage or Exception Plan
Give ad-hoc direction
Authorize project closure
Initiating a Project:
Refine the Business Case
Assemble the Project Initiation Documentation
Controlling a Stage:
Review Stage status
Capture and examine issues and risks
Escalate issues and risks

2009 ILX Group plc

77

PRINCE2 Practitioner Resource Book

Exercise 2 - Suggested Answer (continued)

Practical Practitioner Exercises

Managing a Stage Boundary:


Update the Business Case
Report Stage End
Closing a Project:
Hand over products
Evaluate the project

2009 ILX Group plc

78

Practical Practitioner Exercises

PRINCE2 Practitioner Resource Book

Exercise 3 - Suggested Answer

2
PROJECT BOARD

Snr. User
Production
Manager

Executive
Business
Owner

Snr. Supplier
3 x Sub-Cont.
Reps

Project Assurance
Project Manager
Contract
Project Manager
Team Manager
Electric
Company

Reasons:

Team Manager
Transport
Contractor

Team Manager
Drawing Office
Manager

Project Support
Office Staff

Team Manager
Office
Sub-Contr

Team Manager
Production
Manager

Senior
User:
Senior
Supplier:

The Production Manager has been chosen because he/she will be most
affected by the outcome of the project.
The three major contractors for this project are the electricity company, the
transportation company and the office fitters. A representative from each of
these has been chosen.

Executive
& Change
Authority:

The owner had the main business interest in the outcome and carries full
accountability for the project. With such a small project as this it is likely that
the first choice for the Change Authority would be the Executive. However,
some limited delegation may be made to the Project Manager.

Project
Assurance:

No suitable candidate is mentioned within the scenario, so as this is a small


project, it is recommended that the Project Board fulfil their own PA role.

Project
Support:

The contract Project Manager should be able to use existing office staff to
maintain project files and organize configuration management.

Team
Managers:

Several Team Managers will be needed for this project, some external to the
company, some internal. The Production Manager, who also acts as Senior
User, will act as Team Manager for the team of workers who he has nominated
to build the offices. The Team Managers chosen are representative of the main
discrete Work Packages that can be identified from the scenario.

b) It would not be unreasonable for the owner of the business to act as both Executive and
Senior User thus combining those roles.
Consideration has been given to nominating a single Senior Supplier to represent the three main
sub-contractors. However, no suitable candidate is obvious and the three suppliers are so
disparate that it is unlikely they would be able to agree on a single person.
The Project Manager could do the Project Support function if resources were not readily available.
The Project Manager could also act as Team Manager for some or all of the internal Work
Packages. It would not be a good idea for the Project Manager to Team Manage external Work
Packages.
No reference is made within the scenario to the companys Quality Management System. If a
formally accredited system exists then the use of PRINCE2 to manage projects would be
referenced within that system. It is therefore possible that someone from the QA function could
act in a Project Assurance role for this project.

2009 ILX Group plc

79

Practical Practitioner Exercises

PRINCE2 Practitioner Resource Book

Exercise 4 - Suggested Answer

a) Three identified risks in this project are shown in the Risk Register below:

Risk
identifier

Risk
author

Date
registered

Risk
category

Risk description

R1

PM

Date

Schedule

R2

PM

Date

Schedule

The completion of
the roadway may
be delayed
resulting in a delay
to transporting
machinery and
work in progress
The transport
contractor has only
one crane and lowloader capable of
moving the work in
progress
caravans. If either
of these were
unavailable there
would be a delay in
transporting the
WIP

R3

PM

Date

Financial

2009 ILX Group plc

The part-completed
caravans may be
damaged during
transportation serious damage
which may result in
expensive re-work
or even the
scrapping of the
unit

Probability,
impact and
expected
value
Probability 2
Impact 2
Expected
value not
used

Proximity

Risk
response
categories

Risk response

Risk
status

Risk
owner

Risk actionee

Close

Fallback

Maintain contact with


the Local Authority
and plan for work to
continue in old
factory until road is
completed

Active

Executive

PM

Probability 2
Impact 2
Expected
value not
used

When
machinery
due to
move

1. Fallback
2. Transfer
3. Fallback

Active

PM

1. PM
2. PM to
negotiate
the
Contractor
to take
action
3. PM

Probability 3
Impact 1
Expected
value not
used

During
transport

Fallback

1. Negotiate
weekend working if
needed
2. Negotiate
compensation with
the contractor in
the contract
3. Identify alternative
contractor that
could be
considered in the
event of a major
failure
Negotiate
compensation with
the contractor in the
contract

Active

Production
manager

PM to
negotiate then
contractor to
take action.

80

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

The Risk Register shown is based on the Product Description outline given 2
in the PRINCE2
Manual. The scores are 1=Low, 2=Medium and 3=High. Any contingency actions should have a
contingency budget allocated.
Answer/Notes:
Reasons:
Risk 1: Local authority road projects are often delayed, although the indication on this fairly small
development is good so probability has been assessed at 2. The impact has also been assessed
at 2 since while a delay could cause serious problems there are about two weeks worth of float on
the activity before it would actually delay completion.
The Executive (Owner of the business) has been nominated the owner because he/she would be
affected by the outcome and has also been the primary contact with the local authority regarding
the lease of the new factory. The PM has been chosen to take the action.
Risk 2: The transport equipment is relatively new and reliable so probability has only been
assessed as 2 (Medium). The impact will also be medium since there is float on this activity.
The Project Manager has been chosen as the owner because he/she is best positioned to monitor
the risk. The PM will also take the actions. For the second action, once the action has been
implemented the Contractor will be responsible for making sure the work is completed.
Risk 3: Whilst the probability of this risk occurring is low (1) the impact, in terms of cost, if it does
could be considerable, so impact has been assessed at 3.
Work in progress is the responsibility of the Production Manager who has therefore been chosen
to own this risk. The PM and the contractor will take the actions as described above in risk 2.
b) Implementing the response involves adding appropriate actions into the Plan and monitoring
the new situation for any change in the risk status and to check that the actions are having the
desired effect..
Risk 1: The Project Plan should make allowance for the fact that the roadways may be
completed later than expected and contingency resources must be assigned if, for example
weekend working is required to catch up on the schedule. The PB Executive must allow time
in his/her schedule for maintaining pressure on the local council to ensure completion on time.
Responsibility for monitoring the progress of the roads will rest with the owner of the risk (The
PB Executive) who will inform the Project Manager of any problems.
Risk 2: The Stage Plan covering the movement of the caravans and machinery needs to
include provision for weekend working of that becomes necessary and also should specify the
back-up transportation company. All the response activities associated with this risk can be
resourced by the Project Manager. The Project Manager will keep the Project Board informed
of the status off this risk via Highlight Reports, or an Exception Report if the risk materialises.
Risk 3: The PM will be responsible for negotiating the contract and the Executive should
check that the actions have been included. Once implemented the Production manager will
keep in contact with the contractors and advise the PM of any problems.
During a project risks are considered:
1.
2.
3.
4.
5.

During Starting Up a Project when early risks are recorded in the Daily Log
During the Initiation Stage when the Risk Management Strategy and Risk Register are created.
As the Plans are produced risks are identified, assessed, responses planned and implemented.
Risks are considered when work packages are authorised, reviewed during Controlling a Stage.
Checkpoint, Highlight, End Stage, End Project and Lessons Reports all contain useful information
about risks, their management and status.

2009 ILX Group plc

81

PRINCE2 Practitioner Resource Book

Exercise 5 - Suggested Answer


a) Theme:

Practical Practitioner Exercises

Quality
Is there a customer/supplier QMS?
The quality audit trail, Chapter 6.3, figure 6.1
Organisation (Project Board check on quality at each End Stage Assessment)
Table of responsibilities Chapter 6.4, Table 6.3
Configuration Management

Techniques:

Quality Review
Product-Based Planning:
Helps identify quality products
Product Descriptions demand quality criteria, tolerance, method skills and
responsibilities
Change Control (use of Issue Reports to record quality problems)

Processes:
& Products

Customer Quality Expectations identified in SU


Acceptance Criteria (SU)
Project Product Description (SU)
Quality Management Strategy (IP)
Product Descriptions (PL)
Quality Register (IP)
During Controlling a Stage
Update Quality Register in Authorize a Work Package
Check the Quality register in Review Work Package status, Receive completed Work
Packages, Review the stage status, Report highlights.
.
Quality checks in Managing Product Delivery, Quality Register updated

b) The establishment of Product Descriptions with good quality criteria and defined quality
checking methods.
The use of Work Packages to ensure that quality requirements and reporting were clearly
identified.
The use of a Quality Register that the sub-contractor has to complete for all products.
Project Assurance planning the involvement of the correct reviewers to check the quality of the
sub-contractors deliverables.
Ensuring the correct use of the issue and change procedure by the sub-contractor. The
insistence on the use of team plans and the need to inspect these at draft time in order to
check the suitability and adequacy of quality checking procedures.

2009 ILX Group plc

82

Practical Practitioner Exercises

PRINCE2 Practitioner Resource Book

Exercise 6 - Suggested Answer


a) Product Breakdown Structure

New Factory

Factory Machinery
Grouping

New Roads

Factory Building
Grouping

Transported
WIP Group

Dismantled Machinery

Transport Contract

Moved Machinery

Transported WIP

Recommissioned Machinery

Office
Grouping

Electricity
Grouping

Office Designs

Electricity Supply Contract

Office Shell

Installed Electricity Supply

Decorated Office
Services/Wiring

Sub-Contractor Contract
Installed Cabling

Moved Contents
Product Flow Diagram
Transport Contract

Transported WIP

New Roads
Moved Machinery

Recommissioned Machinery

Dismantled Machinery
NEW FACTORY
Electricity Supply Contract

Installed Supply

Installed Cabling

Sub-Contractor Contract

Office Designs

2009 ILX Group plc

Office Shell

Services/Wiring

Decorated Office

Moved Contents

83

PRINCE2 Practitioner Resource Book

Practical Practitioner Exercises

Exercise 7 - Suggested Answer

b) Product Description
Title: Office Designs
Identifier: SC/00234
Purpose:
To document the proposed layout and structure of the new offices so that they can be agreed
by all project stakeholders.
Composition:
The designs will be made up drawing of the physical layout, wiring diagrams, furniture
positioning diagrams and technical specifications for materials to be used.
Derivation:
The designs will be produced by the Drawing Office staff under the supervision of the
Production Manager.
Format & presentation:
The main drawing will be on A0 "blue-prints" and the technical specifications will be in
accompanying A4 Ring Binders.
Development skills required: Drawing and design skills.
Quality criteria:
1) Design must be acceptable to and agreed by project stakeholders
2) Must satisfy all workplace Health & Safety legislation
3) Designs must comply with current Government Planning Standards
Quality tolerance:
Layouts may be indicative. Actuals can be refined on site.
Quality method:
The designs will be subjected to Quality Review before being submitted to the business owner
for final sign-off.

Quality skills required: Attention to detail. Ability to comment on behalf of the users of
the offices.
Quality responsibilities: To be advised - but will include the Production Manager as a
reviewer.

2009 ILX Group plc

84

PRINCE2 Practitioner Resource Book

Practitioner Exam Technique

Practitioner Exam Technique

Introduction
Welcome to the lesson on PRINCE2 Exam Technique.
The objective of this lesson is to provide you with a thorough understanding of:
o

the structure of the PRINCE2 Practitioner examination

the level of competence required to pass the Practitioner exam

This lesson looks at the nature of the practitioner examination itself and takes a detailed look at the
documents youll encounter in the examination, including the Scenario, Question and Answer
booklets.
Finally, this lesson looks at the format of the examination itself and looks in some detail at the format
of the questions. The lesson concludes by looking at the guidelines provided to candidates when
answering questions and how best to manage your time in the exam .

2009 ILX Group plc

85

PRINCE2 Practitioner Resource Book

Practitioner Exam Simulator

Practitioner Exam Simulator

Introduction
Welcome to the PRINCE2 Practitioner Exam Simulator.
In order to help with your study and provide you with the best chance of passing the Practitioner
examination, the course includes an electronic version of the Practitioner exam.

2009 ILX Group plc

86

PRINCE2 Practitioner Resource Book

a) Question Types

Practitioner Exam Questions

Introduction
The objectives of the examination are to enable a candidate to demonstrate an understanding of
PRINCE2 and an ability to apply the methodology in an appropriate way in a given set of
circumstances described in a scenario. The Practitioner exam uses objective test questions which
require a candidate to choose a response to a question from a set of choices for which the correct
answer is pre-determined.
The following paragraphs explain the format of the question papers, and the different types of question
asked. There are also some suggestions on how to approach answering the various types of question.

Structure of the Paper

The examination paper consists of three booklets.


The Scenario Booklet will contain one scenario providing a description of the organisation, the
business rationale for the project and the project objectives. The Scenario Booklet may also provide
additional information for one or more of the nine questions. Where this additional information is
required it will be clearly referenced within the relevant question and should only be used for that
question.
The combination of the scenario, each question and any additional information referenced in the
Scenario Booklet will always position both the candidate (to consider a particular PRINCE2 role) and
the project (in terms of the timescale, e.g. in the middle of a stage or at the end of a project). The role
to be considered will be at a level suitable for a candidate who has recently attended the PRINCE2
Practitioner course.
The Question Booklet will contain nine questions, each has a potential 12 marks available, and is
broken down into a number of sections. One mark is assigned to each sub-part. Each question has a
suggested duration of 15 minutes. It is suggested that candidates allow 5 minutes to familiarise
themselves with the project scenario, which leaves 10 minutes from the 150 minutes allowed, to
review your answers at the end of the examination.
The Answer Booklet will contain the answer sheets on which your answers must be given. There will
only ever be one answer to each question unless it is otherwise clearly stated within the question.
There may be questions where the candidate is required to select one answer, but feels that more
than one answer is correct. Because of the flexible nature of PRINCE2 this is inevitable on some
topics. The exam does recognise this and for this reason some questions say 'Which of the following
is MOST LIKELY.....' or partial marks are awarded for the less suitable but correct choice. One answer
is still only required for these questions. If more than one answer is indicated in the answer booklet the
response line will be void.

PRINCE2 Syllabus Areas Addressed

The PRINCE2 Syllabus contains 15 defined syllabus areas covering each of the seven themes, each
of the seven processes and an overview area also covering the principles and tailoring PRINCE2 to a
project environment
Within the Practitioner Examination, there will be 7 theme questions, each testing one of the 7
themes, and 2 process group questions, which will test 2 of the 3 groups of processes as identified
below. Each of the nine questions will test a minimum of 2 syllabus topics from within the syllabus
area.
The Overview, Principles and Tailoring PRINCE2 to the project environment syllabus area will not be
examined separately but details from this syllabus section may be included in the questions on each of
the other syllabus areas. The full PRINCE2 syllabus is available from the APM Group or from an
Accredited Training Organization.

2009 ILX Group plc

87

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Types of Question

There are a number of different test types used with the paper.
The test types are:
Classic Multiple Choice Questions choose one from a list of possible answers. The
example given below requires a candidate to refer to some additional information provided in
the scenario booklet and then answer questions about it by selecting the correct response from
a list of 3 to 5 options.

Using the additional information and the Product Breakdown Structure (PBS) provided in the
Scenario Booklet, answer the following question.
1

How should the Photo Design Ideas correctly be shown?


A
B
C
D

an External product
a Source
an Internal Product developed by an external supplier
removed as it is not a product

Yes/No requires the candidate to assess whether a statement is correct Yes or No (chosen
as the standard for True/False type questions). There are only 2 options in this question type.

Column 1 is a list of true and false statements about when the Business Case is updated. For
each of the statements in Column 1 select either A (Yes, this is correct) or B (No, this is
incorrect).
Column 1

Column 2

When raising an Exception Report.

When preparing for an End Stage Assessment. B

When examining a Project Issue.

Yes, this is correct


No, this is incorrect

When updating the Communication Plan.

2009 ILX Group plc

88

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Multiple Response choose the correct options from a list. Candidates must remember to
limit the number of responses to that requested in each question. If more responses
are given
2
than required by the question, the answer will be void. This question follows exactly the same
format as the Classic style, but more than one answer is required. It is the only question style
that requires more than one answer. The number of correct answers is clearly stated in the
question.

Answer the following question about the organisation within a PRINCE2 project.
Remember to limit your answers to the number of selections requested in each question.
1

Which 2 of the following statements should be recorded under the heading of Customers
quality expectation?
A
B
C
D
E

Photos should include members of staff.


10% more calendars should be printed than required to allow for any late additions
to the list of customers.
Project Assurance will monitor the use of applicable corporate standards.
The calendar should reflect the company image.
The calendar will increase orders by at least 10% with a further minimum of 10
orders from the list of prospective customer within 12 months.

Matching involves linking items in one list to items in a second list. There is only one correct
response to each question, but options can usually be used more than once or not at all. The
example below provides the headings of a Business Case in column 2. The candidate is
required to read each statement about the project in column 1 and decide which, if any,
Business Case heading it should be recorded under. Some of the statements may be recorded
under the same heading in the Business Case and there may be some headings under which
none of the statements are relevant.

Column 1 lists 5 statements, some or all of which will be included in this projects Business Case.
Determine for each statement in Column 1, if it will be included and select from Column 2 under
which heading it is most likely to be recorded. A selection from Column 2 may be used more than
once or not at all.
Column 1

Column 2

MNO is experiencing a fall in orders due in part to the


increased marketing operations of its competitors.

Reasons

The Calendar Pack must be ready for printing by


November 30th.

Options

Benefits

Risks

Costs

Timescales

Not applicable

A competitor may also be producing a Calendar


for its customers.

The Marketing Department forecast that issuing


a Calendar to our customers will increase our
orders for next year by 10%.

Staff availability for the Photo Session may cause


delays to the completion date.

2009 ILX Group plc

89

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Sequencing events to be positioned in a sequence. There are two alternative styles of


sequencing questions, one based on the Matching style and the other on
2 the Classic style
question.

The example below demonstrates a Sequencing question based on the Matching style. The activities
in column 1 have to be placed in the sequence in which they should be performed by the Project
Manager. The candidate selects an option from column 2 for each activity in column 1.
Even when the Project Manager is not undertaking a quality review role, the Project Manager has
a number of activities to perform for a quality review. Consider the activities listed in Column 1
and decide if they are the responsibility of the Project Manager. For those activities that are the
responsibility of the Project Manager, identify the sequence in which they should take place.
Match your answer to the options provided in Column 2.
Column 1

Column 2

Get agreement on responsibility for follow-up action


and sign-off.

Not the Project


Managers responsibility

Agree agenda with the review chairperson.

First activity

Update the Stage Plan with the actual date that the
product was reviewed.

Second activity

Third activity

Create an entry in the Quality Log and add the


planned dates for the quality review.

Fourth activity

Add the quality review to the relevant Stage Plan.

Fifth activity

The example below demonstrates a Sequencing question based on the Classic style. Within the
introduction to the question is a list of activities that should be performed. The question then presents
a number of sequence options from which the candidate is required to select the correct sequence.
There have been rumours of a competitor launching a similar marketing product to our customers
before us. These rumours have now been confirmed and will have a major impact on the
success of the Calendar. The following activities will now need to be undertaken.
1
2
3
4
5
1

Raise an Exception Report for the Project Board presenting the options available to them.
Evaluate the Project Issue in terms of its impact on the stage and project tolerances.
Hold an Exception Assessment.
Raise a Project Issue and log it in the Issue Log.
Produce an Exception Plan.
Which of the following sequences correctly represents the order in which the above
activities should be carried out?
A

4, 2, 1, 5, 3

4, 2, 1, 3, 5

2, 4, 1, 5, 3

2, 4, 1, 3, 5

4, 1, 2, 5, 3

2009 ILX Group plc

90

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Assertion/Reason each item consists of two statements, an assertion and a reason that are
linked by the word because. First the candidate must determine whether
the assertion
2
statement is true or false and then whether the reason statement is true or false. If either
statement is false, the answer can be selected from options C, D or E. However, if both
statements are true, a third step is required. To determine between options A or B, the
candidate must determine whether or not the reason is a correct explanation for the assertion.
There is only one correct response to each question, but options may be used once, more
than once or not at all.

Using the Project Scenario, answer the following question.


Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For
each line identify the appropriate selection from options A to E that applies. A selection may be
used more than once or not at all.
Selection

Assertion

A
B
C
D
E

True
True
True
False
False

Reason
True
True
False
True
False

AND the reason explains the assertion


BUT the reason does not explain the assertion

Assertion

Reason

The Business Case should be


revised if Marketings forecast for
increased orders changes.

BECAUSE

The Business Case is an input to the


Project Board in the decision to
authorize a Stage or Exception Plan.

If the paper supplier changes there


may be a review of, and possible
changes to, the Business Case.

BECAUSE

The Business Case includes options for


the delivery of the Calendar solution.

The Business Case will no longer


be viable if the Prepared Calendar
Pack is only available for printing in
the first week of December.

BECAUSE

The fact that the projects aim is to


try to counter the fall in orders
should be documented in the
Project Brief.

BECAUSE

The Business Case is deemed no


longer viable if stage tolerances are
exceeded during the project.

The outline Business Case contains the


reasons why the project is needed and
forms part of the Project Brief.

A useful tip when tackling this type of question is to cover up the Reason column and go down the
Assertions individually, as stand alone statements, marking each as True or False.
Similarly, do the same for the Reasons statements by covering up the Assertion column.
Having established whether each statement is true of false, it is easy to see if a numbered pair is
option C, D or E, as these contain false statements.
You only have to think about the pairs that are both true by deciding if the reason explains the
assertion or both statements are independent of each other.

2009 ILX Group plc

91

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Sample Practitioner Exam Question

Project Scenario 1
EX01 Pleasure Park
Pleasure Parks Ltd (PPL) operates a number of family theme parks in the UK. Visitor numbers have
been static over the last financial year and all the company directors have expressed concern because
their overall strategy has been aimed at a 10% increase in visitor numbers year on year. This strategy
started two years ago. Six months ago (the end of the last financial year) PPL initiated a feasibility
study to determine if any new rides or attractions should be installed.
The feasibility study has recommended that PPL install a new ride at each location. The North East
Theme Park (NETP) has been selected for the installation of a new ride called Explosion a roller
coaster suspended from a rail incorporating two 360 degree spins within the ride.
You have worked for PPL for 4 years and have been selected by the PPL Board to manage the
installation of Explosion.
Rides Galore have been selected to supply the new ride. Planning permission has been granted. The
installation will be undertaken by a specialist contractor which you will have to select as part of the
project.
The project is to start without delay. Estimates from the feasibility study indicate a total cost of 8m
with a 9 month timescale.
It is now the end of May. The directors of PPL want the new ride ready for the start of the next season
in 10 months time.
You have completed the work involved in the Starting up a Project process and after discussion with
the PPL Board you have agreed that the project will comprise of five management stages.

Stage 1
Stage 2

Initiation activities as shown in Initiating a Project.

Plan Stage 2.

Finalise the civil engineering plans for the ride.


Finalise the IT, electrical and mechanical services plans.
Prepare Invitation to Tender to issue to the specialist
contractors.
Select a specialist contractor.
Prepare a revised cost forecast for the project.

Duration 10 weeks

Site works excavation and erection of mechanical


structure.
Inspection and acceptance of structure.

Duration 15 weeks

Duration 10 weeks

Installation of IT and supporting electrical and mechanical


services.
Landscaping.
Installation of roller coaster suspended seating.

Final testing and commissioning.


Demonstration to PPL Board.
Opening ceremony.
Close project.

Duration 3 weeks

Stage 3

Stage 4

Stage 5

2009 ILX Group plc

Duration 3 weeks

92

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

A budget of 8m has been allocated for the project. A change budget of 500k has been agreed for
the project.
2
PPLs Board has also agreed a project tolerance of +20% and -10% on costs. In terms of time the
project is scheduled to complete by the second week of April. The PPL Park Director has insisted that
the opening ceremony should take place by the end of April. The earliest the project can be completed
is the end of March. Therefore the time tolerance for the project is -2 / +2 weeks.

2009 ILX Group plc

93

PRINCE2 Practitioner Resource Book

Business Case Theme - Question 1 - additional information

Practitioner Exam Questions

Extract from the feasibility study into the consolidation project.


3 options were considered:

Do nothing: Taking this option does nothing to generate an increase in visitor numbers. It
may even make matters worse as the public may perceive the lack of investment and view the
Theme Park as tired and out of date.

Do minimum. A number of options were considered in this category of which one was taken
forward for further consideration. This option involved providing a new range of rides for
children that would not be classified as white knuckle rides. Analysis of the customer profile
indicated that whilst this may give a 10% rise in family visitors there would be a corresponding
decrease in the age range that came for the white knuckle experience. This latter group is
the higher spending group. The option was rejected as overall income would decrease
despite numbers remaining the same or, at best, increasing slightly.

Do something. Install a new white knuckle ride. Various options were considered and the
Explosion ride has been selected. This is a suspended roller coaster including a double
helix.
These benefits have been estimated as:
1. Increased visitor numbers of 10% in the first year.
2. Assuming the year 1 experience is satisfactory the increase in visitor numbers will
increase in a similar manner for the following two years.
3. Increase in revenue of 5% per annum from no ticket attractions such as food, drinks,
and slot machines.
4. Increase in visitor numbers to the park will also help the local community due to
increased visitor numbers and spending in the locality, estimated at 2,000 visitors
spending 20,000 pa.

Our recommendation is to install the new roller coaster Explosion as it supports the business
strategy, provides long term benefits and assists with our drive to help the local community.

2009 ILX Group plc

94

PRINCE2 Practitioner Resource Book

Organization Theme - Question 2 - additional information

Practitioner Exam Questions

The following staff are available to help with the project:


Board Members
Cyril Stead Park Director. Cyril has been with Pleasure Parks Ltd for ten years. He has lots of
drive and enthusiasm coupled with a sound business background. He has an MA in Business
Studies. It was his idea to establish the feasibility study and he is very excited by the new ride. He
expects to be closely involved with the project.
Barry Fletcher Finance Director. Barry has an accountancy degree and understands the theme
park business very well. He has recently been promoted to Financial Director after four years as the
Chief Accountant. He has total responsibility for the Pleasure Parks accounting systems.
Sam Ohuru Sales & Marketing Director. Sam is new to the company although he has known Cyril
for many years as they are both keen tennis players. He has an impressive track record in sales and
marketing having worked for leading industry players. He joined PPL 6 months ago. He is very keen
on the new project as he sees it as his opportunity to prove himself. He expects to take a leading role
and is promoting the new ride in the Parks publicity and marketing material.
Julia McKenzie Health and Safety Director. Julia has worked with Cyril for ten years and takes
full responsibility for all health and safety matters. She wants to make sure all the safety margins have
been built into the new ride.
Lucy Large Operational Director. Lucy has been with the company for three months and is
responsible for the day to day management of the Park. Her staff will be supervising the new ride once
it opens and is keen that all park staff are suitably trained in the new ride, its operation, and safety
features.
Robert Roller Account Director, Rides Galore. Robert has been assigned to manage the
Pleasure Parks account. He is a trained roller coaster engineer and will be able to liaise with the
specialist contractors who will be installing the ride.
Unit Heads
David Webb Chief Accountant. David has been in post since Barry was promoted. He is very
methodical and makes sure that the accounts are always in excellent order. He is a great asset to the
company. He was instrumental in introducing quality procedures into the company 2 years ago.
Tracy Currie Sales Manager. Tracy is responsible for all the sales in Park. She is keen to improve
sales after the ride is installed. She has been with the company 5 years.
Heather OConnor Marketing Manager. Heather joined the company on the same day as Tracy
and they have been close friends and colleagues ever since. She is keen to promote the new ride.
Walter Gabriel HR Manager Walter is an easy-going person who thoroughly enjoys his job. He has
little ambition and enjoys working with the team. He has been in post for 6 years and knows
everybody who works in the Park. Walter has to refer all major decisions to Cyril.
Others
Robert Roller Account Director, Rides Galore. Robert has been assigned to manage the
Pleasure Parks account. He is a trained roller coaster engineer and will be able to liaise with the
specialist contractors who will be installing the ride.
Fred Winter Freelance consultant. Fred is a freelance consultant to construction companies and a
specialist team leader.
Sue George Manager in Coaster Constructors.

2009 ILX Group plc

95

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Plans Theme - Question 5 additional information

Stage 2 is almost complete and is going to plan. The specialist installation contractor Coaster
Constructors has been appointed. They have assigned a senior engineer to work with Robert Roller
from Rides Galore to identify the products and work involved in the construction stage (Stage 3).
You are preparing the Stage 3 plan based on this product summary.
Product Summary
In order to build the Explosion ride, site offices will be erected first. Once this is accepted by Coaster
Constructors the existing ride layout plan provided by Rides Galore will be used to establish the
foundations for the steelwork. The steelwork consists of supports, rails and maintenance platforms.
Once the foundations are inspected and approved, the supports will be erected and encased at their
base in reinforced concrete.
Once the concrete has set, the rails will be installed between the supports and so that the
maintenance platforms can be built. A crane will be hired to hoist the steelwork into position. It will be
necessary to place a contract with the plant hire firm for this equipment.
After acceptance of the foundations, the ride entry/exit platform will be built. This must be completed
before the final section of rail can be installed inside the platform.
Extract from Product Breakdown Structure (contains errors)

Roller
Coaster

Steelwork
products
Ride
layout
plan

Site
offices
Maintenance
platforms

Supports

Rails

Foundation
products

Foundations

Build entry/exit
platform

Acceptance
certificate

Reinforced
concrete
Key
External
Product

2009 ILX Group plc

Product

96

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Quality Theme - Question 6 - additional information

Quality notes from the Project Managers Daily Log


I know nothing about building foundations and acceptance certificates. Ill have to make sure I get
some help in that area.
The Park Director has insisted that we do everything to the best possible standard. It all sounds a bit
subjective. I know we have to use Ride Standards 231/2 but Ill ask the Health and Safety Director for
some more precise acceptance criteria as safety must be the prime concern.
Our Sales and Marketing Director has specified that the structure must be painted emerald green with
red seats. He has given me the RAL colour numbers RAL 6001 (green) and RAL 3026 (red).
Whoever we get to undertake to build the new ride must have the appropriate certification in this type
of construction work.
All documentation must be reviewed and the Operational Director wants to review the plans
personally.
We must use the PPL standard version numbering system and make sure all the documents are filed
in accordance with our standards.

Extract from the Quality Management Strategy (may contain errors or information which is
under the incorrect heading)
Introduction
1. This document describes PPLs approach to quality management for the Roller Coaster
project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance to the Project Board that the Quality Management
Strategy is being implemented correctly.
Tools and techniques
4. All specialist work must be tested or checked by competent personnel.
5. All project management documentation should be reviewed by the Project Assurance every 6
weeks.
Quality management procedure quality standards
6. All paint used should conform to RAL compliant colours.
Roles and responsibilities
7. Team managers will provide details of quality checks that have been carried out.
8. The Operational Director will check the plans.
9. The Project Manager will ensure that all quality reviews have the appropriate user
representation.

2009 ILX Group plc

97

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Syllabus Area

Question Number

Business Case Theme

Part 2

Marks

Use the scenario and the additional information relating to the Business Case question answer the
following six questions.
Each question contains a list of true statements about the Explosion project, but only 2 statements
are appropriate entries for that heading of the Business Case.
1

Which two statements should be recorded under the Reasons heading?


A. The new ride will increase visitor numbers by 10% in the first year.
B. Visitor numbers have remained static for the last financial year.
C. The forecast increase in visitor numbers supports the corporate strategy of a 10%
increase year on year.
D. Installing childrens rides will decrease overall income.
E. Installing the new ride will increase sales of non ticket attractions.

Which two statements should be recorded under the Business Options heading?

A. Do nothing, has been rejected as PPL have no confidence in marketing activities.


B. Use Rides Galore to supply the new ride.
C. Installing a range of childrens rides is not considered appropriate for the PPL core
market.
D. Recruit a specialist supplier to install the ride.
E. Contract Rides Galore to plan the new ride.
Which two statements should be recorded under the Expected Benefits heading?
A.
B.
C.
D.
E.

Increased attendance of 10% in first year.


Families with small children will go to a park with childrens attractions.
The ride will cost 8m to install and commission.
The new ride supports the local community through increased local spending.
Benefits will begin to be realized within the first year.

Which two statements should be recorded under the Costs heading?


A.
B.
C.
D.
E.

We have estimated the costs at 8m.


The project will be funded from the investment budget.
The new ride will generate increased revenue of 3m per annum.
If bad weather affects the build then the delays could cost 500,000 per month.
The use of a risk budget will be considered when the Project Plan is completed.

Question continues

2009 ILX Group plc

98

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

2
5

Which two statements should be recorded under the Major Risks heading?
A. The project might take longer than 10 months.
B. If the weather is very bad when the foundations are being laid then work will be delayed
resulting in delays to the completion of the project.
C. Some visitors will not like the new ride.
D. Some families may now perceive that PPL is not a child friendly park and go elsewhere,
resulting in a loss of revenue.
E. The project may cost more than 8m.

Which two statements should be recorded under the Timescales heading?


A. The project will run for 10 months.
B. The project Manager will be employed for 12 months to oversee the transfer into the live
environment and sort out any issues which arise.
C. The Executive has stated that there will be no tolerance on scope.
D. Benefits will be realized over the first year of operation and continue at the same rate for
the next three years.
E. If a suitable installation company cannot be found in the UK then an overseas contractor
will be considered.

Question

Part

1
2
3
4
5
6

2009 ILX Group plc

99

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Business Case Theme

Marks
6

Use the scenario and the additional information relating to the Business Case question answer the
following question.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion
1

Reason

The Do nothing option should NOT be


considered for this project.

BECAUSE

If the forecast number of visitors changes


then the Business Case should be
reviewed.

BECAUSE

The Benefits Review Plan should indicate


when an assessment of the number of
visitors should be made following the
opening of the ride.

It is only necessary to review the


Business Case if there is a major change
to the project.

Once the decision is made on the


appointment of the installation contractor
and the costs fully understood, the
business case should be reviewed.

The Executive should delegate


responsibility for the projects Business
case to the Senior User.

2009 ILX Group plc

BECAUSE

BECAUSE

The Do nothing option is an


optional part of the business
options section of the Business
Case.
Any change that affects the
benefits will result in a review of the
Business case.
The Benefits Review Plan does
NOT contain details of baseline
measures from which
improvements can be calculated.
If Cost tolerance for the project is
exceeded then the corporate body
must be informed.

BECAUSE

The Business Case is reviewed at


each stage boundary.

BECAUSE

The Senior User is responsible for


realising the benefits.

100

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6

2009 ILX Group plc

101

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Syllabus Area

Question Number

Organization Theme

Part 2

Marks

Use the scenario and the additional information relating to the Organization question answer the
following six questions.
1

In a PRINCE2 environment which two of these people are


best suited to the role of the Executive?

In a PRINCE2 environment which two of these people are


best suited to role of Senior User?

In a PRINCE2 environment which two of these people are


best suited to provide Business Assurance for the
Executive role?

In a PRINCE2 environment which two of these people are


best suited to perform User Assurance for the Senior User
role?

In stage 3 which two of these people are best suited to


perform the Senior Supplier role?

Which two of these people are best suited to perform


Supplier Assurance for the Senior Supplier during stage
3?

2009 ILX Group plc

Cyril Stead

Barry Fletcher

Sam Ohuru

Julia McKenzie

Lucy Large

Lucy Large

Robert Roller

Sam Ohuru

Julia McKenzie

Barry Fletcher

Lucy Large

Julia McKenzie

David Webb

Barry Fletcher

Lucy Large

Sam Ohuru

David Webb

Lucy Large

Julia McKenzie

Rep from Specialist

Robert Roller

Robert Roller

Rep from Specialist

Julia McKenzie

Walter Gabriel

102

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6

2009 ILX Group plc

103

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Organization Theme

Marks
6

Use the scenario and the additional information relating to the Organization question answer the
following question.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion
1
The Executive could be Cyril Stead or
Barry Fletcher.
2

The Senior User should be Walter


Gabriel.

When the company undertaking the


installation of the ride is appointed they
should not be represented on the Project
Board as a Senior Supplier.

Julia McKenzie should take the Project


Support role.

In this project it will be necessary to


combine the role of Executive and Senior
User.

During stages 1 and 2 the installation


contractor could be represented by
Robert Roller performing the Senior
Supplier role.

2009 ILX Group plc

Reason
BECAUSE

BECAUSE

Whoever takes the Executive roles


should be able to represent the
business and commit funds on its
behalf.
The Senior User should be able to
represent all user interests.

BECAUSE

There is no need to have anyone in


the Senior Supplier role as
contracts are agreed.

BECAUSE

Senior Managers should always be


involved in Project Support.

BECAUSE

Project Board roles can be


combined on smaller projects.

BECAUSE

The Senior Supplier should be


represented by someone who
understands the specialist interests
prior to their appointment.

104

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6

2009 ILX Group plc

105

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Risk Theme

Part 2
A

Marks
4

The project is now at the end of Stage 2. The project manager has heard about a hurricane in
America and the weather forecasters have suggested that this might cause a period of
torrential rain which will hit the UK soon. There is a threat that torrential rain may cause
localised flooding on the site during the excavation of the foundations which will cause
delays to the construction of up to 4 weeks.
PPL have an operational manager (Sandy) who watches the weather forecasts as weather
affects visitor numbers.
Column 1 contains a number of risk responses identified by the Project Manager following an
assessment of the risk. Column 2 contains a list of threat response types. For each risk response in
Column 1, select from Column 2 the type of response it represents. Each option in column 2 may be
used once, more than once or not at all.
Column 1

Column 2

Hire a pump for the period of the excavation so that work


can continue.

Avoid

Record the risk in the Risk Register and monitor the


situation.

Reduce

Fallback

Transfer

Accept

Share

Carry on as planned but prepare a plan to bring in a pump


if there are signs of flooding.

Ask the contractor, as part of his contract, to make


alternative arrangements in the event of poor weather
causing flooding.

Question

Part

1
2
3
4

2009 ILX Group plc

106

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Risk Theme

Marks
4

The project is now at the end of Stage 2. The project manager has heard about a hurricane in
America and the weather forecasters have suggested that this might cause a period of
torrential rain which will hit the UK soon. There is a threat that torrential rain may cause
localised flooding on the site during the excavation of the foundations which will cause
delays to the construction of up to 4 weeks.
PPL have an operational manager (Sandy) who watches the weather forecasts as weather
affects visitor numbers.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion
1

Reason

The project manager should record this


news as an Issue Report.
If the risk cant be mitigated and the
analysis shows that it exceeds the risk
tolerance for the project then the PM
should raise an Exception Report.

BECAUSE

All new risks are recorded in the


Risk Register.

BECAUSE

All deviations from agreed


tolerances require reporting to the
Project Board.

A suitable risk owner for this risk is the


operational manager (Sandy).

BECAUSE

The Risk owner will not only


monitor the risk but will also take all
the mitigating actions.

It is never appropriate to accept a risk of


this type.

BECAUSE

It is not possible to do anything


about events outside the project.

Question

Part

1
2
3
4

2009 ILX Group plc

107

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Risk Theme

Marks
4

The project is now at the end of Stage 2. The project manager has heard about a hurricane
in America and the weather forecasters have suggested that this might cause a period of
torrential rain which will hit the UK soon. There is a threat that torrential rain may cause
localised flooding on the site during the excavation of the foundations which will cause
delays to the construction of up to 4 weeks.
PPL have an operational manager (Sandy) who watches the weather forecasts as weather
affects visitor numbers.
Column 1 contains a number of items from the risk assessment identified by the Project Manager
and team following an assessment of the risk. Column 2 contains a list of headings from the Risk
Register. For each item in Column 1, select from Column 2 the heading under which it should be
recorded. Each option in column 2 may be used once, more than once or not at all.
No
1

Column 1
Record the risk in the Risk Register and monitor the situation.

Column 2
A Risk category

Torrential rain is expected in November.

B Probability

This is a risk to the schedule.

C Proximity

This risk is active.

D Risk response
E Risk status
F Risk Owner

Question

Part

1
2
3
4

2009 ILX Group plc

108

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Progress Theme

Part 2

Marks

The project is now at the end of Stage 3. Using the project scenario answer these questions.
1

At the end of Stage 3, 10% of the cost tolerance has been used. Which statement is true?
A. The remaining 10% MUST be allocated to stage 4.
B. The Project Board can allocate as much or as little of the remaining cost tolerance to
stage 4.
C. Any deviation within the tolerances allocated will require an Exception Report.
D. Additional cost tolerance can be generated by speeding up the project.

Having planned Stage 4 the project Manager has to do a number of other activities. Which of
these is true?
A. Raise an Exception Plan to cover the Project Plan updates for Stage 4.
B. Consider whether the Project Product Description should be updated.
C. Update the Project Plan and reflect any changes in the Project Plan in the Business
Case.
D. Update the Quality Register with the results of the stage 3 reviews.
Having reviewed the amount of work to be undertaken in Stage 4 the Project Manager has
been told that the Project Board require more control. Which two of these actions would give
the Project Board more control?
A.
B.
C.
D.
E.

Increase the frequency of Checkpoint Reports.


Split Stage 4 into two smaller management stages.
Increase the frequency of Exception reporting.
Increase the frequency of Highlight Reports.
Make sure all issues are handled formally.

Having looked at the Work Packages planned for Stage 4 the Project Manager wants to make
sure they are under control. Which two actions will give the Project Manager more control?
A.
B.
C.
D.
E.

Increase the frequency of Checkpoint Reports.


Reduce the degree of tolerance for the Work Package.
Increase the frequency of Exception Reports.
Increase the frequency of Highlight Reports.
Make sure all issues are handled formally.

Question

Part

1
2
3
4

2009 ILX Group plc

109

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Progress Theme

Marks
4

Half of the positive (project) cost tolerance has been used in Stages 2, 3 and 4. The project is
scheduled to complete 1 week before the end of April so there is 1 week positive (project)
time tolerance remaining. Using the project scenario answer these questions.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion

Reason

Any remaining project tolerance for


time and cost should always be
allocated to the final stage of the
project.

All of the positive tolerance can be


allocated to Stage 5.

BECAUSE

There is no need for the project manager


to maintain the Daily Log in the final
stage.

BECAUSE

All issues MUST be noted in the


Issue Register.

BECAUSE

The Product Status Account is a


report of the status of all products
including their version number.

BECAUSE

Benefit tolerance defines the range


of a benefit.

If the Project Manager wants to review the


version number of the projects products
then s/he may request a Product Status
Account from Project Support.

When reviewing the tolerances for Stage


5 Plan with the Project Board the PM
must check that the benefits tolerance for
the stage is allocated.

Question

Part

1
2
3
4

2009 ILX Group plc

110

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Progress Theme

Marks
4

The project is now at the end of Stage 3. Use the project scenario to answer these questions.
Column 1 contains a number of true statements that should be included within the End Stage Report.
Select from Column 2 the appropriate heading for each statement. Each option in column 2 may be
used once, more than once or not at all.
No
1

Column 1
The project is scheduled to complete 1 week before the end of
April.

Column 2
A Review of team
performance

The excavation works took longer than expected we should


have done a more detailed survey of the site.

B Quality records

If the IT system doesnt require reconfiguring it is possible that


the contractor can speed up the installation of the IT and this
would save 3 weeks on the schedule.

C Issues and risks


D Lessons Report
E Forecast
4

During Stage 3 fifty tests were undertaken of which only 3 failed.


The rework was completed within tolerance.

Question

Part

C
1

2
3
4

2009 ILX Group plc

111

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Plans Theme

Part 2

Marks

Using only the Product Summary and extract from the Product Breakdown Structure provided as
additional information, answer the following four questions
Column 1 is a list of some of the entries in the product breakdown structure. Determine whether
each entry in Column 1 has been correctly shown (or not) in the product breakdown structure. Select
from Column 2 the appropriate statement that correctly describes that entry. Each selection in
column 2 may be used once, more than once or not at all.
Column 1

Column 2

Ride layout plan

Reinforced concrete

External product
incorrectly shown

Build entry/exit platform

Acceptance certificate

Internal product
incorrectly shown as
an external product

Site offices

NOT a product

Rails

Correctly shown entry

Incorrectly shown in a
one to one relationship

Question

Part

1
2
3
4
5
6

2009 ILX Group plc

112

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Plans Theme

Marks
6

Use the scenario answer the following questions.


Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion
1
2

The plan for Stage 3 should be produced


during the initiation stage.
The activities required to close the project
should be included within the Stage 5
plan.
The fact that the rollercoaster can be
completed up to 2 weeks earlier than the
second week of April would be recorded
under the Tolerances section of the
Project Plan.

4
Stage 1 activities do NOT require a plan.

Reason
BECAUSE
BECAUSE

BECAUSE

BECAUSE

All Stage plans should be produced


in Initiation.
Project closure is part of the final
stage of a project and its activities
should be included within the stage
plan.

All tolerances are recorded in the


Project Plan.

An Exception Plan may be required


if a Stage Plan is forecast to
exceed its tolerance.

The completion of the invitation to tender


and having it ready for issue may be a
suitable milestone.

BECAUSE

Milestones represent the


completion of key activities.

When planning Stage 3 the products


should be broken down into a product
breakdown structure for the Stage.

BECAUSE

The schedule is derived from the


product breakdown structure.

2009 ILX Group plc

113

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6

2009 ILX Group plc

114

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Quality Theme

Part 2

Marks

Using the information in the project scenario and the additional information for the Quality
question (quality notes from the Project Managers Daily Log) answer the following questions.
Each of the following questions relates to entries in the Product Descriptions of the projects
products.
1

Which is a correct statement for the quality criteria entry in the ride seats product description?
A.
B.
C.
D.

They must be painted red.


They must be painted in RAL 3026 (red).
They must be comfortable.
The MD must like them.

Which is a correct statement for the quality responsibilities entry in the plans product
description?
A. The Park Director must check the plans to make sure they are correct.
B. The Operational Director should be involved in reviewing the plans to confirm they are
acceptable.
C. The Project Manager should check that the plans conform to current building
regulations.
D. It is not necessary to check that the plans are correct we can take the suppliers word
for it.
Which is a correct statement for the quality tolerance entry in the plans product description
A. All plans must be to scale 1:50.
B. All plans must be to scale 1:50 but if necessary the overall layout plans can be produced
at 1:100 scale.
C. Plans must be produced at A0 size.
D. The plans must be checked by the Operational Director.

Which is a correct statement for the quality method entry in the ride seats product
description?
A.
B.
C.
D.

Ask the staff if they like them.


Wait until the ride is ready for use and then check to make sure they are adequate
Ask the Park Director to check them.
Visual Inspection of each seat for damage prior to installation.

Question

Part

1
2
3
4

2009 ILX Group plc

115

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Quality Theme

Marks
4

Using the information in the project scenario and the additional information for the Quality
question (quality notes from the Project Managers Daily Log and the extract from the Quality
Management Strategy) answer the following questions.
1

Which statement applies to the Introduction section?


A. Delete entry 1 because this is related to the project approach and should be recorded
in the Project Brief.
B. Delete entry 2 because the project board roles are not included here.
C. Move entry 3 to the Roles and responsibilities section.
D. Delete entries 2 and 3 because assurance roles are documented in the PID.

Which statement applies to the Tools and techniques section?


A. Move entry 4 to roles and responsibilities as specialist staff need to know their delegated
authority.
B. Move entry 5 to quality management procedure.
C. Move entry 4 and 5 to roles and responsibilities as these clarify roles for project quality.
D. Add the architect will check the materials.

Which statement applies to the Quality management procedure - quality standards section?
A.
B.
C.
D.

Delete entry 6 as this describes a product.


Add the contractor will check that the work meets the standards.
Add there must be enough light.
Add all modifications must comply with current building regulations.

Which statement applies to the Roles and responsibilities section?


A. Delete entry 7 because external suppliers cannot provide quality checking.
B. Delete entry 8 because this is the responsibility of corporate or programme
management.
C. Delete entry 9 because this is a responsibility of the Project Board.
D. Move entry 7 to reporting because checkpoint reports contain an extract of the Quality
Management Strategy.

Question

Part

1
2
3
4

2009 ILX Group plc

116

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

2
Syllabus Area

Question Number

Part

Marks

Quality Theme

Using the information in the project scenario and the additional information for the Quality
question (quality notes from the Project Managers Daily Log and the extract from the Quality
Management Strategy) answer the following questions.
1

Which statement is a correctly defined acceptance criterion for the ride?


A.
B.
C.
D.

Which statement is a correctly defined acceptance criterion for the plans?


A.
B.
C.
D.

The health and safety plan has been approved by the regulatory authority.
They are at the right scale.
They are complete.
All parties are satisfied with them.

Which statement is a correct example of an in process method of checking the ride seats?
A.
B.
C.
D.

It must be safe.
Strong bolts must be used.
The fixings must comply with the Ride Standards 231/2 para 22.
It must be painted the right colour.

Project Assurance will check the seats.


As the seats are installed they are checked for damage.
The Project Manager will review the Quality Register periodically.
All seats will be painted red (RAL 3026).

Which statement is a correct example of an appraisal method of checking the ride seats?
A. Check the seats during installation to check they are the right colour.
B. The seats are to be painted red (RAL 3026).
C. Once the seats are installed they will be tested against the relevant standard (see the
product description).
D. The Health and Safety Officer will inspect the seats.

Question

Part

1
2
3
4

2009 ILX Group plc

117

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Syllabus Area

Question Number

Processes Starting up a Project, Initiating a Project

Part 2
A

Marks
5

Each of the following 5 questions includes a list of true statements made during the Starting up a
Project process.
1

Which statement is an appropriate entry for the Lessons Log?


A. The last time PPL installed a ride staff wanted extra pay and there was trouble with the
unions.
B. PPL have never installed such a complex in ride in such a short timeframe before.
C. The suppliers that will be used to supply the new ride are new to PPL.
D. The Park Director wants the installation to be implemented with minimum disruption to
the business.

Which statement is an appropriate entry for the Project Product Description?


A. Sub-contract the work to an experienced builder.
B. The representative from the ride supplier will take the Senior Supplier role on the
Project Board.
C. It is expected that Stage 2 will take six weeks.
D. The Park Director has stated that there must be no compromise on the standard of
finishes.

Which statement is an appropriate entry for the Project Product Description?


A. The project must be completed within two weeks of the target date.
B. Four coats of paint have been requested on all aspects of the ride but if costs are
threatened three coats will be acceptable.
C. The seats on the ride must be capable of supporting up to 30 stones weight.
D. The Park Director has stated that the project must be kept secret for now.

Which statement is an appropriate entry for the project approach contained in the project
Brief?
A. When the contractor is appointed they should be represented on the Project Board.
B. The materials for the work must comply with current environmental regulation.
C. The PPL legal department will negotiate the lease and then following a tender process
a suitable builder will be contracted to undertake the work at the new offices.
D. There may be problems with negotiating the contract causing work on the ride to be
delayed.

Which is an appropriate entry for the Stage Plan for the initiation stage?
A. The Daily Log has been updated with new risks to the project that were identified when
preparing the Project Brief.
B. The plan is based on the ride supplier being available to assist with planning the
project.
C. The initial cost estimate for the project is 8m.
D. The Park Director has stated that the project must be completed in time for Easter.

2009 ILX Group plc

118

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

2
Question

Part

1
2
3
4
5

2009 ILX Group plc

119

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Processes Starting up a Project, Initiating a Project

Marks
2

Each of the following 2 questions includes a list of true statements made during the Initiating a
Project process.
1

Which statement is an appropriate entry for the Business Case?


A.
B.
C.
D.

Installing more childrens rides would have incurred a decrease in high spending visitors.
Bad weather may delay the work in Stage 3.
All plans must be checked by the Health and Safety Director.
The quoted timescales are based on the understanding that funding can be made
available immediately approval is granted.

Which statement is an appropriate entry for the Configuration Management Strategy?


A. The Health and Safety Director must approve all plans.
B. Any threats that cause more than 4 weeks delay should be classified as Very High
Impact.
C. All contracts must be approved by the legal department.
D. Any new requirements incurring costs over 250,000 must be referred to the Project
Board.

Question

Part

1
2

2009 ILX Group plc

120

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Processes Starting up a Project, Initiating a Project

Marks
5

The project is now near the end of the Initiation Stage. All the work has been completed and it
just remains for the Project Initiation Documentation to be assembled and the stage 2 Plan to
be finalised.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion

Reason

The Risk Register should have been


created before the Initiation Stage.

BECAUSE

The Business Case cannot be finalised


until the Project Plan is completed.

BECAUSE

The Communications Management


Strategy does not include people outside
the PPL organisation.

BECAUSE

If the PPL Project Board decide to


delegate to a Change Authority, the
person(s) will be identified in the
Configuration Management Strategy.

The Risk Management Strategy should


define scales for probability and impact.

Question

Part

The Risk Management Strategy


describes the specific techniques
and standards to be applied.
The Project Plan determines the
duration and cost of the project and
this information is required in the
Business Case.
Only people working within the
project should be included in the
Communications Management
Strategy.

BECAUSE

Every project must have separate


person or group designated as a
dedicated Change Authority.

BECAUSE

All risks associated with Stage 2


should have an owner.

1
2
3
4
5

2009 ILX Group plc

121

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

2
Syllabus Area

Question Number

Part

Marks

Processes DP, CS, SB, MP & CP

The project has completed Stage 2 successfully and has moved into Stage 3. The contractor
will be excavating the site and erecting the structure.
Each of the following 2 questions includes a list of true statements made during the Controlling a
Stage process.
1

Which statement is an appropriate entry for the Foundations Work Package?


A.
B.
C.
D.

The steelwork will be erected when the concrete has been signed off.
Access to the site can only be arranged via the site agent.
Stage 3 will take 15 weeks.
The Park Director wants the work to be implemented with minimum disruption to the
business.

Which statement is an appropriate entry for the first Highlight Report in stage 3?
A.
B.
C.
D.

The contractor has been appointed.


The Contractor has taken the Senior Supplier role on the Project Board.
The work in Stage 2 completed ahead of schedule by 3 days.
None of the stage tolerance has been used to date.

The project is coming to the end of Stage 3. It is 10 days ahead of schedule and the works
are being inspected.
Each of the following 2 questions includes a list of true statements made during the Managing a
Stage Boundary process.
3

Which statement is an appropriate entry for the End Stage Report?


A. Anyone working on the site until the work is completed must arrange access with the
Site Agent.
B. The Park Director is very pleased with the work done in stage 2.
C. The contractor joined the Project Board during stage 2.
D. The ride will be operational on 1 April, two weeks ahead of schedule.

Which is an appropriate entry for the Lessons Report produced at the end of Stage 3?
A. All the work so far in the project has been done on or ahead of schedule.
B. We incorporated suggestions from rides galore about the installation and this has saved
8 days on the schedule.
C. We have heard that there may be delays with the IT system.
D. Business has not deteriorated during the building period.

Question

Part

1
2
3
4

2009 ILX Group plc

122

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

2
Syllabus Area

Question Number

Part

Marks

Processes DP, CS, SB, MP & CP

The installation has completed as planned. The Project Manager is now working through the
Closing a Project activities.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion

Reason

Any unfinished work should be recorded


in the Daily Log for action by the
appropriate business department.

The End Project Report will be produced


when all the benefits of the new ride have
been realised.

The Stage Plan for stage 5 should contain


details of the products to be created or
updated during the Closing a Project
process.

As part of the handover of the ride to the


customer arrangements should be made
for the ongoing management of the ride.

Question

Part

BECAUSE

BECAUSE

BECAUSE

BECAUSE

The Daily Log provides a means for


the Project Manager to record
informal issues.
The End Project Report documents
whether all the benefits have been
achieved.
Work Packages will be required for
the production of the End Project
Report and to update the Benefits
Review Plan.
Part of handing over the finished
products is to ensure that the
appropriate support and
maintenance systems are in place.

1
2
3
4

2009 ILX Group plc

123

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Processes DP, CS, SB, MP & CP

Part 2
C

Marks
4

The project is in Stage 4. It is on schedule.


Column 1 contains a number of true statements that should be included within the second weekly
Checkpoint Report to be produced for the IT Installation Work Package. Select from Column 2 the
appropriate heading for each statement. Each option in column 2 may be used once, more than
once or not at all.
Column 1

Column 2

The cable installation is on schedule but we are


forecasting a 2 day delay against the target due to the next
part of the work being more complex than anticipated.

Follow ups

This reporting period

The outstanding documentation from last week has been


completed.

Next reporting period

If the IT system doesnt require reconfiguring it is possible


that we can bring the testing forward by 2 weeks.

Work Package
tolerance status

Next week we shall test the cable installation.

Issues and risks

Question

Part

1
2
3
4

2009 ILX Group plc

124

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Change Theme

Part 2
A

Marks
4

The project is now in Stage 3.


Use the project scenario to answer the following 4 questions.
Column 1 contains a number of issues for this project. Select from Column 2 the appropriate
category for each issue. Each option in column 2 may be used once, more than once or not at all.
Column 1

Column 2

Although not previously considered, the Park Director


wants a water feature to be included within the
landscaping work.

Problem or concern

Request for change

Whilst installing the new electrical services it was


discovered that the incoming supply is faulty causing a
serious delay.

Off-specification

The ride seating was signed off now it appears that the
paint colour used does not match that stated in the
product description.

The operational staff have asked for a different type of IT


system to that previously agreed.

Question

Part

1
2
3
4

2009 ILX Group plc

125

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Part

Change Theme

Marks
4

The project is now in Stage 4. The MD has decided that the seats should be painted the same
colour as the ride steelwork (green). Work has already started painting the seats red and
whilst this can be achieved within the timeframes specified there will be an additional cost of
25,000. There is 300,000 left in the Change Budget. The Change Authority specified in the
Configuration Management Strategy is the Project Board.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion
1

Reason

The change in requirements should be


treated as a request for change.

BECAUSE

An Exception Plan at project level must


be produced to reflect this change.

BECAUSE

If the Project Manager needs to see if any


other products are affected s/he should
look in the Configuration Item Record.

As the change can be paid for by the


Change Budget the Project Manager can
authorise the change.

Question

Part

BECAUSE

BECAUSE

Something that should be provided


by the project, but currently is not
provided is an off-specification.
All deviations from agreed
tolerances require an Exception
plan.
The Configuration Item record
contains the relationship with other
items.
The Change Authority only deals
with changes that require funding.

1
2
3
4

2009 ILX Group plc

126

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Change Theme

Part 2

Marks

The project is now in Stage 4. The MD has decided that the seats should be painted the same
colour as the ride steelwork (green). Work has already started painting the seats red and
whilst this can be achieved within the timeframes specified there will be an additional cost of
25,000. There is 300,000 left in the Change Budget. The Change Authority specified in the
Configuration Management Strategy is the Project Board. This issue will be handled formally.
Column 1 contains a number of statements that should be included within the Issue Report. Select
from Column 2 the appropriate heading for each statement. Each option in column 2 may be used
once, more than once or not at all.
Column 1

Column 2

The Project Board have approved the request and


transferred the funds into the project budget.

Issue description

Changing the colour of the seats will require the work


already started to be scrapped.

Impact analysis

Recommendation

Severity

Decision

As work has started the Project Manager believes that the


best option will be to continue with the original colour
scheme.

The cost of this change is outside the authority level of the


Project Manager and must be escalated.

Question

Part

1
2
3
4

2009 ILX Group plc

127

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Suggested Answers

Practitioner Exam Pleasure Park

Question

Part

Question

Part

2009 ILX Group plc

128

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

2009 ILX Group plc

129

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

Question

Part

2009 ILX Group plc

130

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

Question

Part

2009 ILX Group plc

131

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

2009 ILX Group plc

132

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

Question

Part

2009 ILX Group plc

133

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

Question

Part

2009 ILX Group plc

134

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

Question

Part

2009 ILX Group plc

135

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

Question

Part

2009 ILX Group plc

136

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Pleasure Park Project Rationale

Question 1 Business Case Theme


Question

Part

Answer

1a

incorrect

Is a benefit.

1b

correct

Is a reason for doing the project it describes the current situation.

1c

correct

Is a reason for doing the project it describes how the project supports
achievement of corporate strategies and objectives. (A 2.2 p237)

1d

incorrect

Is a reason for rejecting another business option, not a reason for doing the
project.

1e

incorrect

Is a benefit.

Question

Part

Answer

2a

correct

This is a business option.

2b

incorrect

This relates to the project approach.

2c

correct

This is a business option.

2d

incorrect

This relates to the project approach.

2e

incorrect

This also relates to the project approach.

Question

Part

Answer

3a

correct

A is a measureable benefit and is directly attributable to the move.

3b

incorrect

B is an expected dis-benefit.

3c

incorrect

C is a cost.

3d

correct

D is a measurable benefit of this project.

3e

incorrect

E relates to timescales of the project.

Question

Part

Answer

4a

correct

Both A and B are relevant to the cost heading as per appendix A2.2.

4b

correct

Both A and B are relevant to the cost heading as per appendix A2.2.

4c

incorrect

C is a benefit.

4d

incorrect

D is a risk.

4e

incorrect

E is just a statement about the risk budget and is not relevant to the Business
Case.

2009 ILX Group plc

137

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

5a

incorrect

This is just a statement of uncertainty not a risk.

5b

correct

Is a risk as it has event, cause and effect.

5c

incorrect

Is a statement.

5d

correct

Is a risk it has event, cause and effect.

5e

incorrect

This is a statement of uncertainty not a risk.

Question

Part

Answer

6a

correct

Both A and D relate to the timescales of this project and the benefits realisation
period.

6b

incorrect

Is not relevant to the Business Case.

6c

incorrect

This is a statement about scope and will be included in the Project Plan.

6d

correct

Both A and D relate to the timescales of this project and the benefits realisation
period.

6e

incorrect

Is a contingency plan for a risk.

2009 ILX Group plc

138

PRINCE2 Practitioner Resource Book

Question

Part

FALSE - do nothing is always part of the


Business Case see A.2.2

TRUE - This is a possible change to the


business benefits and the business case
should be checked (see also Change
Theme para 9.3.3.2)

TRUE - the ability to increase sales (or


otherwise) is a benefit of this project and
should be included within the Benefits
Realization Plan

FALSE - When considering a request for


change the effect on the Business case
must be considered. (see 9.3.3.2)

TRUE - The costs may/will have changed


and this will affect the business case costs
and benefits.

2009 ILX Group plc

Practitioner Exam Questions

Assertion

FALSE - This cannot be delegated. App


C2.1

Reason

FALSE - The Do Nothing option is required as


part of the Business Case options section
see A 2.2
TRUE - the reason correctly explains the
Assertion (see para 9.3.3.2)

FALSE - see A1.2

TRUE - see 10.3.1.1

TRUE - The reason is also true but does not


describe the reason for the assertion. The BC
is reviewed at each stage boundary see figure
4.2
TRUE - Appendix C 3.1

139

PRINCE2 Practitioner Resource Book

Question 2 Organisation Theme

Practitioner Exam Questions

Question

Part

Answer

1a

correct

Both nominees have the appropriate authority to make decisions and commit
resources on behalf of the business.

1b

correct

Both nominees have the appropriate authority to make decisions and commit
resources on behalf of the business.

1c

incorrect

Sams role in Sales and marketing is linked to the users (public) of the ride and
can represent their views.

1d

incorrect

Julia is more concerned with the supply side safety etc that than the users.

1e

incorrect

Lucy can clearly represent the users (public) and the staff operating the ride.

Question

Part

Answer

2a

correct

Lucy can clearly represent the users (public) and the staff operating the ride.

2b

incorrect

Robert Roller is the supplier.

2c

correct

Sams role in Sales and marketing is linked to the users (public) of the ride and
can represent their views.

2d

incorrect

Julia is more concerned with the supply side safety etc that than the users.

Question

Part

Answer

3a

correct

Both Barry and David have the financial skills to monitor the financial aspects of
the project and maintain an eye on the business aspects. David can also
oversee the use of the quality systems.

3b

incorrect

Lucy is associated with the Operation aspects, rather than the financial and
business aspects.

3c

incorrect

Julia is associated with the supply side rather than the business

3d

correct

Both Barry and David have the financial skills to monitor the financial aspects of
the project and maintain an eye on the business aspects. David can also
oversee the use of the quality systems.

Question

Part

Answer

4a

incorrect

Barry is associated with business and finance rather than the user aspects

correct

As directors for two significant areas of the business they will be able to see
that the users interest are being considered. Barry and David are concerned
with finance and business so would be better doing assurance for the
Executive.

4c

correct

As directors for two significant areas of the business they will be able to see
that the users interest are being considered. Barry and David are concerned
with finance and business so would be better doing assurance for the
Executive.

4d

incorrect

David is associated with business and finance rather than the user aspects

4b

Question

Part

2009 ILX Group plc

140

PRINCE2 Practitioner Resource Book


2

Practitioner Exam Questions

Answer

5a

incorrect

Lucy Large is better suited to the senior User role.

5b

incorrect

Julia Mackenzie is again better suited to Project assurance for the Senior User,
making sure that the ride fulfils its safety.

5c

correct

The newly appointed installation contractor should be represented on the Board


along with Robert Roller.

5d

correct

The newly appointed installation contractor should be represented on the Board


along with Robert Roller.

Question

Part

Answer

6a

correct

Robert and the rep for the supplier can provide their own assurance as
suppliers.

6b

correct

Robert and the rep for the supplier can provide their own assurance as
suppliers.

6c

incorrect

Julia is better suited to provide assurance for the Senior User.

6d

incorrect

Walter is not suitable for an assurance role.

Question

Part

Assertion

Reason

TRUE - Both Cyril and Barry could be the


Executive for the reason stated

TRUE this is a key responsibility of the


Executive (see 5.3.2.2 and C.2.1). Both
nominees fulfill these criteria

FALSE - Walter is not in a position to


represent all the users, neither does he
have the authority to commit resources.

TRUE - see 5.3.2.1

FALSE - because this company will be


supplying the skills to undertake the work
and should be represented on the Project
Board.

FALSE - none of the PRINCE2 roles are


optional, although it is possible to have one
person taking more than one role.
FALSE - as the Organization theme does not
state this.

FALSE - as clearly Julias position as a


director of Health and Safety means she is
at too high a level in the organization to
provide project support in this type of
project.

FALSE - this is a large project where it


would be preferable to have separate
people in the role.

TRUE - see 19.5.1.1

TRUE and correctly explains the assertion

TRUE - Robert Roller represents the


supplier of the roller coaster and will
understand the installation requirements
and interests and as such can represent
their interests. This is explained correctly
by the reason.

2009 ILX Group plc

141

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 3 Risk Theme

Question

Part

Answer

1a

incorrect

This does not avoid the risk as flooding can still occur.

1b

correct

Flooding will be significantly reduced.

1c

incorrect

This is not a fallback action as it is taken before the risk is likely to occur.

1d

incorrect

This does not transfer the risk.

1e

incorrect

As we are doing something it is not acceptance.

1f

incorrect

We are not sharing the risk.

Question

Part

Answer

2a

incorrect

No effective action is taken so we have not avoided it.

2b

incorrect

No effective action is taken so we have not reduced the risk.

2c

incorrect

No effective action is taken so we have not made a fallback plan.

2d

incorrect

No effective action is taken so we have not transferred it.

2e

correct

No effective action is taken accept.

2f

incorrect

We are not sharing the risk.

Question

Part

Answer

3a

incorrect

No action is taken unless the risk occurs so we have not avoided it.

3b

incorrect

No action is taken unless the risk occurs so we have not reduced the risk.

3c

correct

A plan B has been established fallback.

3d

incorrect

No action is taken unless the risk occurs so we have not transferred the risk.

3e

incorrect

As we are doing something it is not acceptance.

3f

incorrect

We are not sharing the risk.

Question

Part

Answer

4a

incorrect

Asking the contractor does not prevent the risk occurring so we have not
avoided it.

4b

incorrect

Asking the contractor does not prevent the risk occurring so we have not
reduced it.

4c

incorrect

Asking the contractor does not prevent the risk occurring so we have not
defined a fallback action.

4d

correct

It is now the suppliers job to deal with the risk transfer.

4e

incorrect

As we are doing something it is not acceptance.

4f

incorrect

We are not sharing the risk as we are asking the contractor to deal with it.
However, this does not transfer the effect of the risk.

2009 ILX Group plc

142

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Assertion

FALSE - New risks are captured in the Risk


Register (15.4.6)

TRUE See 15.4.6


TRUE See assertion

TRUE - All forecast deviations should be


escalated to the Project Board via an
Exception report and this is accurately
reflected by the reason. (15.4.7/10.3.3.1)

TRUE - The operational manager will be


able to keep the project informed of any
adverse weather forecasts.

FALSE - The risk owner does not always take


the mitigating actions. There may be a risk
actionee. - see 8.3.5.4

FALSE - risks can always be accepted,


although it may not be a sensible thing to
do.

FALSE - events outside the project can be


addressed and actions taken to mitigate their
effects.

Reason

Question

Part

Answer

1d

correct

This is a risk response it describes the action that is being taken (albeit
acceptance) (A25.2)

2c

correct

This relates to when the risk may happen i.e. in November which is the
proximity (A25.2)

3a

correct

This is a category of risk (schedule) A25.2.

4e

correct

Active is a valid status for a risk (A25.2)

2009 ILX Group plc

143

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 4 Progress Theme

Question

Part

Answer

1a

incorrect

Is false there is no need for all the remaining tolerance to be allocated to the
final stage.

1b

correct

The Project Board can allocate the project tolerance however it wishes.

1c

incorrect

An Exception report is only required if tolerances are forecast to be exceeded.

1d

incorrect

Speeding up the project will not create more cost tolerance.

Question

Part

Answer

2a

incorrect

An Exception Plan is only required when a plan is in exception. This is not


required at the normal end of a stage.

2b

incorrect

The Risk register will have been updated already when the Stage Plan was
prepared.

2c

correct

These activities need to be completed as the Project Plan should be updated to


reflect the Stage 3 Plan.

2d

incorrect

Updates to the Quality Register are done as the reviews take place, not at the
end of the stage.

Question

Part

Answer

3a

incorrect

Checkpoint Reports are sent from the Team Manager to the Project Manager.
Increasing these in frequency will only improve the control of the Project
Manager.

3b

correct

This will mean the stage is shorter and provide an additional control point at the
end of the smaller stage so the Project Board will have more control.

3c

incorrect

This will only happen if the stage exceeds tolerances and is not done on a
regular basis. Therefore, the Board will not have increased control.

3d

correct

This will give the Board more detail of progress and therefore give them more
control.

3e

incorrect

This will have no effect on Project Board control.

Question

Part

Answer

4a

correct

These reports from the team manager will give the Project Manager updates
more frequently and therefore more control.

4b

correct

Having a plan which s/he can monitor from the Team Manager will give the
project Manager more control.

4c

incorrect

Exception Reports are not appropriate between Team Managers and Project
Managers.

4d

incorrect

This will give the Board more detail of progress not the Project Manager.

4e

incorrect

This will have no effect on Project Managers control.

2009 ILX Group plc

144

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part B

Answer

TRUE - Tolerance can be allocated


however the Project Board directs.

FALSE - The Project Manager should


maintain the Daily Log throughout. It
is closed in Recommend project
closure (see Figure 18.6).

FALSE - Not all issues require an issue Report


and an entry in the Issue Register some can
be handled informally. 9.3.3.1.

TRUE - Assertion is true and is


correctly explained by the reason.
See A18.1/2.

TRUE - see Reason.

FALSE _ Benefit tolerance only


applies to the Project and is noted in
the Business Case.

TRUE - (see Table 10.1).

2009 ILX Group plc

Assertion

Reason

FALSE - Although this is the final stage


tolerance can be applied to stages however the
Project Board wishes.

145

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

1e

correct

This is a forecast of performance when the project will finish. (A9.2).

2d

correct

This reflects something we should have done and should be included within the
Lessons Report. (A9.2).

3c

correct

This reflects an opportunity and should be discussed under issues and risks.
(A9.2)

4b

correct

This statement reflects the number of quality checks done and their result
quality records. (A9.2)

2009 ILX Group plc

146

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 5 Plans Theme

Question

Part

Answer

1d

correct

The Ride layout plan already exist. It is a correctly shown external product.

2e

correct

This is shown as a sub product of Supports in a one to one relationship which


is incorrect.

3c

correct

Build entry platform is an activity, not a product.

4d

correct

Acceptance certificate is part of your project it is a correctly shown product.

5b

correct

Site offices are required as part of your project. It is incorrectly shown as an


external product.

6d

correct

Rails are part of your project. It is correctly shown.

Question

Part

Assertion

FALSE - Stage plans are produced


towards the end of the previous stage - see
7.2.5.

FALSE - Stage plans are produced towards


the end of the previous stage - see 7.2.5.

TRUE - The final stage of the project


includes the closure activities (see 18.3).

TRUE - This correctly explains the assertion.

TRUE The earliest the ride can be


completed is the end of March. The project
is scheduled to finish by the second week
of April.

FALSE - Only time, cost, scope and maybe risk


tolerances, at project level, are recorded in the
project plan (see A16.2).

FALSE - All stages should be planned


including the initiation stage. (see 12.4.6).

TRUE - If a stage is forecast to exceed its


tolerances then an exception plan may be
required - see 7.2.7 / 10.3.1.1.

TRUE - The ITT is a significant piece of


work and its completion would be a
suitable milestone.

TRUE - This is first step in the planning


procedure (see 7.3.3.2).

2009 ILX Group plc

Reason

TRUE - (see 7.3.6.6) this is the right reason for


the assertion.
FALSE - The schedule is derived from the list
of activities and dependencies and estimates
(see figure 7.2 and 7.3.6).

147

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 6 Quality Theme

Question

Part

Answer

1a

incorrect

Is not measurable there are many shades of red.

1b

correct

Is measureable and reflects the information supplied.

1c

incorrect

Is subjective.

1d

incorrect

Is subjective.

Question

Part

Answer

2a

incorrect

There is no specified requirement that says the Park Director must check the
plans.

2b

correct

This is a stated requirement in the scenario additional information.

2c

incorrect

The PM does not have these skills.

2d

incorrect

All products should be quality checked in some form.

Question

Part

Answer

3a

incorrect

This is statement of requirement not a tolerance.

3b

correct

This provides a range of quality.

3c

incorrect

This is statement of requirement not a tolerance.

3d

incorrect

This is statement of requirement not a tolerance.

Question

Part

Answer

4a

incorrect

This is not an objective test.

4b

incorrect

This would be too late and is inappropriate.

4c

incorrect

This is a valid method, rather a statement of responsibility.

4d

correct

This is a valid and objective test.

Question

Part

Answer

1a

incorrect

Entry 1 is correct as it stands.

1b

incorrect

Entry 2 is correct as the Introduction section should include this.

1c

correct

Entry 3 should be recorded under Roles and responsibilities and is correct.

1d

incorrect

Entry 2 is correct.

2009 ILX Group plc

148

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

2a

incorrect

Whilst this is correct on its own c is correct because entry 5 is also in the
wrong place.

2b

incorrect

Whilst this is correct on its own c is correct because entry 4 is also in the
wrong place.

2c

correct

Both entry 4 and 5 are about roles and responsibilities and not Tools and
techniques.

2d

incorrect

This is a responsibility.

Question

Part

Answer

3a

incorrect

Entry 6 These are relevant standards.

3b

incorrect

This relates to a responsibility and would not be noted under Standards.

3c

incorrect

This is a quality criterion.

3d

correct

This is a quality standard.

Question

Part

Answer

4a

incorrect

Entry 7 is a responsibility and correctly located.

4b

incorrect

Entry 8 is a responsibility and correctly located.

4c

correct

This is a responsibility of Project Assurance not the Project Manager (see


C7.1).

4d

incorrect

See A above.

2009 ILX Group plc

149

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

2
Question

Part

Answer

1a

incorrect

Whilst being safe is important this statement is not measureable and is


therefore not a valid acceptance criterion.

1b

incorrect

Whilst strong bolts are important this statement is not measureable and is
therefore not a valid acceptance criterion.

1c

correct

This is measurable and is therefore a valid acceptance criterion.

1d

incorrect

Being the right colour is important but what is the right colour? This statement
is not measureable and is therefore not a valid acceptance criterion.

Question

Part

Answer

2a

correct

This is measurable and is therefore a valid acceptance criterion.

2b

incorrect

What is the right scale? This statement is not measureable and is therefore
not a valid acceptance criterion.

2c

incorrect

What represents complete? This statement is not measureable and is


therefore not a valid acceptance criterion.

2d

incorrect

Who are all parties and what makes them satisfactory? This statement is
not measureable and is therefore not a valid acceptance criterion.

Question

Part

Answer

3a

incorrect

This is a responsibility.

3b

correct

This is valid in process method (see 6.3.2.1).

3c

incorrect

This is a responsibility for managing the project and not relevant.

3d

incorrect

This is a quality criterion.

Question

Part

Answer

4a

incorrect

This is an in process method.

4b

incorrect

This is a quality criterion.

4c

correct

This is a valid appraisal method (see 6.3.2.1).

4d

incorrect

This is a quality responsibility.

2009 ILX Group plc

150

PRINCE2 Practitioner Resource Book

Question 7 Processes SU & IP

Practitioner Exam Questions

Question

Part

Answer

1a

correct

Is a lesson that can be usefully applied to this project consideration must be


given to the staff and union views as part of the project.

1b

incorrect

Is just a statement of fact.

1c

incorrect

Is just a statement of fact.

1d

incorrect

Is a quality expectation of the Park Director and should be analysed and


included in the Project Product Description.

Question

Part

Answer

2a

incorrect

Is related to how the work will be done and should be included in the project
approach.

2b

incorrect

Relates to the project team structure.

2c

incorrect

Relates to the stage 2 plan.

2d

correct

This is a quality expectation of the Park Director and should be recorded under
customers quality expectations.

Question

Part

Answer

3a

incorrect

Is a statement of Project Tolerance and should be included within the Project


Plan.

3b

correct

This is a range of quality and should be included within the Project Product
Description under the Project-level quality Tolerances heading.

3c

incorrect

This is a quality criterion for the seats product, not the project and therefore
would be noted in the Product Description for the seats.

3d

incorrect

This is just a statement and not relevant to the Project Product Description.

Question

Part

Answer

4a

incorrect

This is not relevant to the approach. It should be noted in the Daily Log and
implemented when the contractor is appointed.

4b

incorrect

This is a quality criterion for the materials and should be included in the
(Project) Product Description.

4c

correct

This describes the way in which the project will be undertaken and should be
included within the project approach.

4d

incorrect

This is a risk and should be included within the Daily Log and transferred to the
Risk Register in Initiation.

2009 ILX Group plc

151

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

5a

incorrect

This describes how risks are managed in Starting up a Project and is not an
entry for the Stage Plan.

5b

correct

This is an assumption for the Stage and it should be included with the Stage
Plan (see A 16.2).

5c

incorrect

This is a cost estimate for the project and will form part of the outline Business
Case in the Project Brief.

5d

incorrect

This is an acceptance criterion and should be included within the Project


Product Description.

Question

Part

Answer

1a

correct

This is a description of a Business Option (A2.2).

1b

incorrect

This is a risk for Stage 3 and should be recorded in the Risk Register.

1c

incorrect

This should be recorded in the Quality Management Strategy (roles and


responsibilities).

1d

incorrect

This is an assumption for the Project Plan.

Question

Part

Answer

2a

incorrect

Is a statement for the Quality Management Strategy

2b

incorrect

Relates to the scales for risk impact and should be noted in the Risk
Management Strategy

2c

incorrect

Relates to the Quality Management Strategy

2d

correct

Relates to the Change Authority and will be included within the Roles and
Responsibilities entry.

2009 ILX Group plc

152

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

FALSE - the Risk Register is created in


Prepare the Risk Management Strategy.
(see 14.4.1).

TRUE - Assertion is correctly explained by


the Reason. (see 14.4.6 & 7).

FALSE - The Communications


Management Strategy defines
communications for all stakeholders. (See
A4.1).

FALSE - The Communications Management


Strategy defines communications for all
stakeholders. (See A4.1).

TRUE - the Change Authority is defined in


the Configuration management Strategy
(see A6.2).

FALSE - Whether a separate Change Authority


is established is decided by the Project Board
on a project by project basis (see 5.3.2.4).

TRUE - by definition (see A24.2 Scales).


The Reason is also true.

TRUE - all risk should have an owner but this is


not the reason for the assertion.

2009 ILX Group plc

Assertion

Reason

TRUE - This is the purpose of the Risk


Management Strategy. (see A24.1).
TRUE - this correctly explains the assertion
Assertion is correctly explained by the Reason.
(see 14.4.6 & 7).

153

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 8 Processes DP, CS, SB, MP & CP

Question

Part

Answer

1a

incorrect

Is a statement of fact and will be reflected in the Stage Plan.

1b

correct

Is a constraint and should be recorded as such in the Work package.

1c

incorrect

Is just a statement of fact.

1d

incorrect

Is a quality expectation of the MD and should be analysed and included in the


Project Product Description.

Question

Part

Answer

2a

incorrect

This relates to work completed in Stage 2 and would not be discussed in a


Highlight report for Stage 3.

2b

incorrect

B This would have been decided at the End Stage Assessment between stages
2 and 3 and is not relevant to the Highlight Report.

2c

incorrect

This would have been noted in the End Stage Report for Stage 2. (see A9.2).

2d

correct

This would be noted in the highlight Report under Project and stage tolerance
status. (see A 11.2).

Question

Part

Answer

3a

incorrect

This is a constraint and should be included in the relevant work packages.

3b

incorrect

This information should be recorded in the End Stage Report for Stage 2.

3c

incorrect

This information should be recorded in the End Stage Report for Stage 2.

3d

correct

This is a correct entry for the End Stage report for Stage 3. It should be
recorded under forecast. (see A9.2).

Question

Part

Answer

4a

incorrect

This is a statement of fact and should be recorded in the End Stage Report.

4b

correct

This is a lesson which could be applied to other projects.

4c

incorrect

This is a rumour and should be recorded as a risk?

4d

incorrect

This is a statement of fact.

2009 ILX Group plc

154

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

B
D

FALSE - unfinished work should be


recorded as a follow on action
recommendation. (see 18.4.3)

TRUE - (see A7.1)

FALSE - The End Project Report is


produced before the project closes.
Benefits are normally achieved post project
as will the case with the PQR move.

FALSE - Only benefits achieved at closure are


noted in the End Project Report. (see A8.2)

TRUE - Closure is part of the final stage


and therefore the activities involved should
be included within the Stage Plan.

FALSE - Work Packages are not used to


produce management products.

TRUE - Assertion is true and correctly


explained by the reason - answer A. (see
18.4.3)

TRUE - Assertion is true and correctly


explained by the reason - answer A. (see
18.4.3)

Question

Part

Answer

1d

correct

This relates to the amount of time tolerance being used - actuals and forecast.
(A3.2).

2a

correct

This refers to outstanding work from last week the checkpoints are weekly.
(A3.2).

3e

correct

This reflects an opportunity and should be discussed under issues and risks.
(A3.2)

4c

correct

This refers to quality work to be carried out in the next period. (A3.2)

2009 ILX Group plc

Assertion

Reason

155

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question 9 Change Theme

Question

Part

Answer

1b

correct

This is a new requirement and should be classified as a request for change.

2a

correct

This is a problem or concern as it is an unforeseen event. It requires attention.

3c

correct

Despite being signed off against the PD it seems a mistake was made and the
paint colour is not correct. This is an off-specification.

4b

correct

Something different is required from that currently agreed so this is a request


for change.

Question

Part

TRUE - this is a proposal to change the


requirements.

TRUE - by definition (Table 9.1) but it is not the


reason for the assertion. Answer B

FALSE - An Exception may be required at


stage level but as the change can be
handled within the project tolerances then
the assertion is false.

FALSE - Raising an Exception Plan is only one


of many options open to the project Board in
such a situation (Table 9.2)

TRUE - And is correctly explained by the


reason. (See A5.2).

TRUE - And correctly explains the assertion


(see A.5.2)

FALSE - All changes must be referred to


the Change Authority and in this scenario
that is the Project Board.

FALSE - The Change authority deals with all


change requests.

Question

Part

Answer

1e

correct

This statement reflects the decision made by the Change Authority (in this case
the Project Board). (A13.2)

2b

correct

This is part of the impact analysis the effect of incorporating the change.
(A13.2)

3c

correct

This is a recommendation. (A13.2)

4d

correct

This statement reflects the severity the level of management required to


make a decision on the issue. (A13.2)

2009 ILX Group plc

Assertion

Reason

156

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Sample Practitioner Exam Question

Project Scenario 2
EX02 - The Calendar Project
(Note: The companies and people within the scenario are fictional.)
There has been a reduction in the number of orders at the MNO Manufacturing Company due in part
to the increased marketing activities of its competitors. To help counter this, the company has decided
to create a promotional calendar for next year for all its current and prospective customers.
The end product of this project will be a prepared calendar pack, ready for printing. The design of the
calendar will be similar to one sent out previously, and must reflect the company image as described
in the existing corporate branding standards. Another project is currently producing a new company
logo which is to be printed on each page of the promotional calendar.
The prepared calendar pack will consist of:
Design for each month - correctly showing all public holidays and new company logo
Selected photographs - 12 professionally-produced photographs, showing different members of
staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - competition to design a label be held as part of this project
List of customers - names and addresses of customers to whom the calendar will be sent
The project is currently in initiation and will have two further stages:
Stage 2 will include the activities to:
o
o
o
o
o
o
o

Create the customer list using information from the Accounts and Marketing
departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic
session schedule
Prepare a production cost forecast
Select paper and envelope.

Stage 3 will include the activities to:


o
o
o

Produce and select the professionally-taken photographs


Hold the label design competition and choose the label design
Assemble the prepared calendar pack

A production cost forecast, based on the options and costs for the paper, envelope, printing and
mailing of the calendar is to be produced in stage 2. However, the actual production and distribution of
the calendars is not within the scope of this project. The production cost forecast will be reviewed by
the Project Board to determine whether the project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30
November, to enable printing and distribution of the calendar in time for Christmas. The cost of the
activities to develop the specialist products and the cost of the project management activities are
estimated to be 20,000. There is a project time tolerance of +1 week / -2 weeks and a project cost
tolerance of +6,000 / -6,000. A change budget of 500 has been allocated but there is no risk
budget.

2009 ILX Group plc

157

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 1: Business Case Theme - Additional Information

During the initiation stage the Project Manager met with the Marketing Director to find out more about
the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the number of orders at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and replacement
staff have not been recruited due to the reduced operation. If the project is successful, a recruitment
campaign will be required to fill the existing staff vacancies and there may be a requirement for
additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult
to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an average
profit of 2,000. The Marketing department believes that sending a promotional calendar to the
companys current and prospective customers would increase orders by at least 10%, with a minimum
of 10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She believes
that the effect of a good company image portrayed by a successful calendar would last into a second
year. She has forecast the same increase in orders for a second year and predicts that the annual
employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
20% discount for all repeat customers - not cost-effective and very short term
A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
A series of television and press advertisements would be too expensive
Creation of an internet website - would not suit all customers.
The calendar is seen as the favoured option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the
project management team must be aware of the cost this will incur.

2009 ILX Group plc

158

PRINCE2 Practitioner Resource Book

Question 2: Organization Theme - Additional Information

Practitioner Exam Questions

Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well.
He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he
has an overall perspective of the business strategic requirements and the authority to commit
resources as required.
Marketing Director: She has been with the company for three years, following a successful career
with a publicity company. She has the ability to represent the needs of the business, particularly as
this is a marketing project. She has the authority to commit the annual business marketing budget,
from which the project will be funded, as she sees appropriate. She will be responsible for monitoring
the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company
and is still as keen and energetic as the day he started. Whilst he will not be part of the project team,
his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They
now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Portraits Ltd: This is a professional photographic company with a number of excellent photographers
and a history of successful work. This company has been selected to take the photos for the company
calendar. It has yet to be decided which of the photographers to use.

2009 ILX Group plc

159

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 3: Quality Theme - Additional Information

Extract from the Project Product Description (with errors)

Composition

1.
2.
3.
4.
5.
6.
7.
8.

Design for each month


100gsm glossy paper
Full colour
Selected envelope
Chosen label design
List of customers
Selected photographs
Photo session schedule

Derivation

9.
10.
11.
12.

New company logo design


Previous calendar designs
Internal creative team
Production cost forecast

Development Skills Required

13. Photographer
14. Internal creative team
15. Printer

Customers Quality Expectations

16. Professional photographs


17. 10% more calendars than required should be
printed to allow for any late additions to the list of
customers
18. Compliance with applicable corporate standards
19. The calendar should reflect the company image as
described in the corporate branding standards
20. The calendar will increase orders by at least 10%
with a minimum of 10 further orders from the list of
prospective customers within 12 months.

Acceptance Criteria

21. Appearance: each photograph should be sufficiently


attractive and humorous that the customer wants to
display it.
22. Appearance: new company logo promotes strong
image
23. Security: complies with Data Protection Act
24. Accuracy: public holidays match the list supplied by
marketing

2009 ILX Group plc

160

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 5: Risk Theme - Additional Information

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract for
their services has been set up and is being monitored by the Purchasing Manager, and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting with
the Engineering Manager to establish a schedule for the photographic sessions to minimize the impact
on the Engineering staff. This meeting should have occurred week ago. The photographic sessions
are scheduled to take place in two days time.
The Engineering Manager was made aware of this requirement. However, when asked by the Project
Manager, he reported that he had received no communication from the photographer. The Project
Manager has tried to call the photographer and has had no response. The Project Manager believes
there is a risk that Portraits Ltd are overbooking work and prioritizing other clients work. If Portraits Ltd
do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.

2009 ILX Group plc

161

PRINCE2 Practitioner Resource Book

Question 6: Plans Theme - Additional Information

Practitioner Exam Questions

Product Summary
A list of customers will be collated. This will use existing information from the Accounts department
about current customers, and existing information from the Marketing department about prospective
customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be
produced to allow the CEO and the Marketing Director to decide whether to continue with the project.
If they decide to continue, they will give the approval to launch the internal label design competition.
Competition rules will be drawn up and details of the competition will be communicated to the staff.
The chosen label design will then be chosen from the competition entries.
The photographs for the calendar must be based on existing photograph design ideas available from
the Marketing department. Designs for each month will be created to show the required layout of each
page.

2009 ILX Group plc

162

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question 6: Plans Theme - Additional Information

Extract from Stage Plan for Stage 3.


(All entries are true statements but may not be shown under the correct heading or in the correct
document).
Plan description

1.

Stage 3 is the final stage of the project and will deliver the
photographs, the label design competition entries, the
winning label design and the prepared calendar pack.

Plan prerequisites

2.
3.

Increase in orders and improved company image.


The production cost forecast must be acceptable to the
Project Board if the photography and the label design
competition are to go ahead.
The customer list is accurate and complete.

4.
External dependencies

5.

6.

7.

A separate project has been reviewing the company's


branding. The company logo, required for the label design
competition, is being updated. The new company logo is to
be supplied by the other project in two weeks time.
Customer details will be supplied from the Accounts
department and the Marketing department customer
databases for the customer list.
The label design must contain the new company logo.

Planning assumptions

8.

Monitoring and control

11. The Project Plan is to be updated with actuals throughout


the stage.
12. A Highlight Report will be created every two weeks.
13. The Stage Plan will be reviewed at the end of each day, to
assess forecast against actuals.
14. Product Status Accounts will be produced by Project
Support, at the request of the Project Manager, to
summarize current and historical data concerning each of
the projects products.

Budgets

15. Cost
16. Time
17. Risk

2009 ILX Group plc

A suitable entry will be received from the label design


competition.
9. The photographic session schedule created two weeks ago
correctly reflects the availability of the engineering staff.
10. Each photograph must feature different members of the
Engineering team.

5,000 for specialist products


4 weeks
0

163

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Syllabus Area

Question Number

Business Case Theme

Part 2

Marks

Using the Project Scenario and the additional information provided for this question in the
Scenario Booklet, answer the following questions.
Each question provides a list of only true statements about the Calendar project, but only 2
statements are appropriate entries for that heading of the Business Case.
Remember to select 2 answers to each question.
1

Which 2 statements should be recorded under the Reasons heading?


A

The Marketing department believes that sending a promotional calendar to current


and prospective customers will increase orders by at least 10%.

10% of customers have not re-ordered in this financial year.

1,500 orders are expected, each with an average profit of 2,000.

The Marketing department believes that the effect of a good company image,
portrayed by a successful calendar, would last into a second year.

MNO Manufacturing is experiencing a reduction in order numbers due in part to the


increased marketing activities of its competitors.

Which 2 statements should be recorded under the Business options heading?


A

Produce a promotional calendar as a free Christmas gift to current and prospective


customers.

Use a professional photographer to create the photographs for the calendar.

Create the photographs for the calendar internally.

Outsource the creation of the calendar to a professional marketing company.

Do nothing.

Which 2 statements should be recorded under the Expected benefits heading?


A

Increase orders by at least 10% with a minimum of 10 further orders from the list of
prospective customers within 12 months.

The calendar will be similar to calendars sent out in previous years.

The Marketing department believes that the benefits of a good company image, as
portrayed by a successful calendar, would last into a second year and bring the same
increase in orders.

The calendar will contain photographs of both staff and company products.

The Marketing department want a very high quality, glossy product as they believe this
will be more appealing to customers.

Question continues on next page

Question continued

2009 ILX Group plc

164

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

2
4

Which 2 statements should be recorded under the Expected dis-benefits heading?


A

A high quality, glossy product will involve additional costs.

Individuals in the engineering team who are not selected to appear in the calendar
photographs will become de-motivated.

The calendar may not result in the expected 10% increase in orders.

As the Calendar project is a priority for the MNO Manufacturing Company, the delivery
of other projects within the Marketing department will be delayed.

The calendar may not result in the 10 further orders from the list of prospective
customers in 12 months.

Which 2 statements should be recorded under the Timescale heading?


A

Benefits will be lost if the project is not completed on time.

A recruitment campaign to fill the existing staff vacancies will need to take place in the
next 12 months.

Additional 10% increase in orders in year two.

The prepared calendar pack must be delivered by the first week in December.

The print company requires a 2 week notification period of the calendar pack delivery.

Which 2 statements should be recorded under the Costs heading?


A

The MNO marketing budget this year is 120,000.

The project will be funded from the business marketing budget.

10 further orders with an average profit of 2,000 will deliver a benefit of 20,000 in
the first year.

The new company logo is estimated to cost 4,000.

Project costs are estimated to be a total of 26,500.

Which 2 statements correctly define a Business Case risk which should be recorded under the
Major risks heading?
A

Operational costs will increase as a result of the recruitment campaign.

The prepared calendar pack is to be delivered to the printers by the first week in
December.

If the calendar quality is poor customers will not use it, creating the reverse effect and
reducing orders further.

If any competitors launch a calendar at the same time this will reduce the impact of the
MNO calendar and benefits will be reduced.

Staff morale will improve as a result of the promotional calendar.

2009 ILX Group plc

165

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6
7

2009 ILX Group plc

166

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Business Case Theme

Part 2
B

Marks
5

Using the additional information provided for this question in the Scenario Booklet, answer
the following question.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion
1

Reason

If the calendar option is changed there


should be a review of, and possible
changes to, the Business Case.
The Business Case will no longer be
viable if the prepared calendar pack is
not available for printing until the first
week of December.
The fact that the projects aim is to try
to counter the fall in orders should be
documented in the Project Brief.
The Benefits Review Plan should
include an assessment in 12-months
time of the increase in orders.
The expected improvement in staff
morale should NOT be recorded as a
benefit in the Business Case.

Question

Part

The Business Case includes options


for the delivery of the chosen solution.

BECAUSE

The Business Case is no longer viable


if stage tolerances are exceeded during
the project.

BECAUSE

The outline Business Case contains


the reasons why the project is needed
and forms part of the Project Brief.
The Benefits Review Plan contains
details of benefits reviews to be
conducted during the project.
Only those benefits that can be
measured in financial terms should be
defined in the Business Case.

BECAUSE

BECAUSE

BECAUSE

1
2
3
4
5

2009 ILX Group plc

167

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Syllabus Area

Question Number

Organization Theme

Part 2
A

Marks
7

The following questions include only true statements about an individual from the project
organization. Only 2 statements explain why, in the context of roles and responsibilities within a
PRINCE2 organization structure, the individual is a suitable candidate for that role.
Remember to select 2 answers to each question.
1

Which 2 statements explain why the Marketing Director would be appropriate as the Executive
for this project?
A

She has been with the company for three years.

She previously had a successful career in publicity.

She is able to represent the business needs of MNO Manufacturing.

She has authority to commit the marketing budget, from which the project will be
funded.

She requires more experience working with the engineering industry.

Which 2 statements explain why the CEO would be appropriate as the Executive for this
project?
A

He started the company 25 years ago.

He knows his job very well.

He restricts his visits to the engineering area.

He has the authority to commit resources as required.

He has an overall perspective of the business's strategic requirements.

Which 2 statements explain why the Marketing Director would be appropriate as a Senior User
for this project?
A

She can represent the Marketing department.

She previously had a successful career in publicity.

The Marketing department will help to deliver the benefits of this project.

The project will be funded from the business marketing budget.

A number of the products will be produced by the Sales department and the Marketing
department.

Question continues on next page

2009 ILX Group plc

168

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question continued

Which 2 statements explain why the Sales Manager would be appropriate as a Senior User for this
project?
A

He joined the company last year with huge enthusiasm.

He would like to move into the Marketing department in the future and sees this as an
opportunity to work closely with the Marketing Director.

The launch of a company calendar will impact the Sales department.

He reports directly to the Marketing Director.

He is able to represent current and prospective customer interests.

Which 2 statements explain why the Purchasing Manager would be appropriate as a Senior
Supplier for this project?
A

He is responsible for advising on the acceptance methods to be included in supplier


contracts.

He will procure the resources and materials required for the project's products.

He was an engineer and worked in that area before taking up his current position.

He can monitor the production cost forecast against the Business Case and ensure
value for money.

He is not appropriate for the role of Executive or Senior User.

Which 2 statements explain why the Sales Manager would be appropriate in a user assurance role
for this project?
A

He joined the company last year with huge enthusiasm and is keen to increase sales.

He can provide an evaluation of the potential impact the calendar will have on sales.

He is able to advise on suitable stakeholder engagement of current and prospective


customers.

He would like to move into the Marketing department in the future and sees this as an
opportunity to work closely with the Marketing Director.

He can resolve any conflict in requirements between the Sales department and the
Marketing department.

Which 2 statements explain why Central Records would be appropriate in a Project Support role
for this project?
A

They have knowledge of specialist tools and techniques that are required for this project.

The department already exists within the organization and its staff members have been
with the company for many years.

They will ensure compliance with all company policies and procedures.

They perform a quality assurance function across all projects.

They have knowledge of the organizational standards that will be applicable to the project.

2009 ILX Group plc

169

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6
7

2009 ILX Group plc

170

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Organization Theme

Part 2
B

Marks
5

Using the additional information provided for this question in the Scenario Booklet, answer
the following question.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion

Reason

The Executive role should be shared


by the CEO and the Marketing
Director.

BECAUSE

The Executive is responsible for


securing the funding for the project.

The Senior User role should be


shared by the Marketing Director and
the Engineering Manager.

BECAUSE

Those who provide specialist resources


to the project development teams
should perform a Senior User role.

Bright Lights and Portraits Ltd are both


stakeholders on the Calendar project.

BECAUSE

Anyone who can affect a project is a


stakeholder on that project.

A single member of Central Records


should NOT perform both a Project
Support and a Project Assurance role
on this project

The Engineering Manager should be


included in the Communication
Management Strategy.

Question

Part

BECAUSE

BECAUSE

It is necessary to keep Project Support


and Project Assurance responsibilities
separate.
The Communication Management
Strategy describes the communication
tools to be used.

1
2
3
4
5

2009 ILX Group plc

171

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Quality Theme

Part 2

Marks

Column 1 is a list of objectives. For each objective in Column 1, select from Column 2 the quality
activity that addresses it. Each selection from Column 2 can be used once, more than once or not at
all.
Column 1

Column 2

Understanding the customers quality expectations.

Quality assurance

Approval of the project's products.

Quality control

Confirmation that corporate management standards


and policies are being adhered to.

Quality planning

Question

Part

1
2
3

2009 ILX Group plc

172

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Quality Theme

Part 2
B

Marks
4

An address label is required for the envelope. The design of the label will be selected from
entries to an internal label design competition. The winning label design will be included in
the prepared calendar pack given to the printing company. The label should be half the size of
the selected envelope (+5% / - 5%), and use an attractive, large font for the customers name
and address. The new company logo must be integrated into the label design. The Project
Board will be asked to review all entries and select the winning label design.
The information in Column 1 may be entered in the Product Description for the chosen label design.
Column 2 is a list of the quality headings (excluding Quality Method) in a Product Description. For
each entry in Column 1 decide if it should be included under one of the Product Description headings
shown and select the appropriate answer from Column 2.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1

Column 2

Half the size of the selected


envelope.

NOT included

Quality criteria

Printing company.

Quality tolerance

Project Board.

Quality skills required

+5% / -5% of the required label size.

Quality responsibilities

Question

Part

1
2
3
4

2009 ILX Group plc

173

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Area
Question provided
Number for this
Part question Marks
Using the Project Syllabus
Scenario
and the additional information
in the
2 Description.
Scenario Booklet, answer the following 5 questions about the Project Product
Quality Theme

Remember to select 2 answers to each question.


1

4.

Which 2 statements apply to the Composition section?


A

Amend entry 2 to 'Selected paper'.

Delete entry 3 because this is NOT a major product to be delivered by this project.

Move entry 6 to Derivation because this product already exists.

Delete entry 7 because these will be produced by the photographer.

Add 'Calendars distributed to customers'.

Which 2 statements apply to the Derivation section?


A

Move entry 9 to Composition because this is within the scope of the project.

Delete entry 10 because this is NOT a source product for this project.

Delete entry 11 as this is already correctly shown under Development Skills


required.

Move entry 12 to Composition, because this is within the scope of this project.

Add Professional photographer.

Which 2 statements apply to the Development skills required section?


A

Move entry 13 to Composition because the appointment of the photographer is within


the scope of this project.

Move entry 13 to Derivation because this is a source of information for this project.

Delete entry 14 because this skill is NOT required within this project.

Delete entry 15 because this skill is NOT required within this project.

Add 'Knowledge of Data Protection Legislation'.

Which 2 statements apply to the Customer's quality expectations section?


A

Delete entry 16 because this should be shown on the Product Description for the
photos.

Delete entry 17 because this is beyond the scope of this project.

Delete entry 18 because standards should NOT be shown here.

Delete entry 19 because this should appear in the Product Description for the calendar
and not the Project Product Description.

Delete entry 20 because this is an expected benefit and should be recorded in the
Business Case.

Question continues on next page

Question continued

2009 ILX Group plc

174

PRINCE2 Practitioner Resource Book

5.

Practitioner Exam Questions

Which 2 statements apply to the Acceptance criteria section?


A

2
Amend entry 21 to Appearance - 12 photographs each showing different
members of
staff.

Move entry 21 to Composition because the photographs are part of the project
product.

Delete entry 22 because the development of the new company logo is not within the
scope of the Calendar project.

Move entry 23 to Derivation because the Data Protection Legislation already exists.

Delete entry 24 because this is NOT a suitable acceptance criteria for this project.

Question

Part

1
2
3
4
5

2009 ILX Group plc

175

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Starting Up a Project + Initiating a Project Processes

Part 2

Marks

Column 1 is a list of decisions to be made within the project. For each decision in Column 1, decide
whether or not it is made in the Starting up a Project process and indicate in which order the
decisions will occur.
Column 1

Column 2

Approval of the feasibility study by the Project Board before any


work on the project can commence.

Assess which parties should be involved during the project, as


suggested by previous development projects.

Evaluate possible candidates for Project Manager and decide


which should be appointed.

Question

Part

Not made in
the Starting
up a Project
process
First

Second

Third

1
2
3

2009 ILX Group plc

176

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Starting Up a Project + Initiating a Project Processes

Part 2
B

Marks
3

Using the Project Scenario answer the following question.


The Project Manager has been asked to prepare the Project Brief for the Calendar project. The
following questions include only true statements about the project, but only one statement is an
appropriate entry for that heading of the Project Brief.
1.

Which statement should be recorded under the Project definition heading?


A
This project must interface with the project that is producing a new company logo.
B
The design of the calendar will be derived from the design used to create previous
calendars.
C
The calendar will be designed by the internal creative team.
D

2.

Which statement should be recorded under the Outline Business Case heading?
A
B
C
D

3.

A professional photographer will be commissioned to take the photographs.

10% more calendars than required should be printed to allow for any late additions to
the list of customers.
A production cost forecast will be reviewed by the Project Board to determine whether
the project should continue.
There has been a reduction in the number of orders due in part to the increased
marketing activities of competitors.
The Project Board have stated that the project cost tolerance can be used to speed up
the project if necessary.

Which statement should be recorded under the Project approach heading?


A

The end product of this project will be a prepared calendar pack, ready for printing.

The photography for the calendar is to be outsourced to a professional photographer.

A production cost forecast, based on the costs for the materials, printing and mailing is
to be produced in stage 2.

The actual production and distribution of the calendars is not within the scope of this
project.

Question

Part

1
2
3

2009 ILX Group plc

177

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Syllabus Area

Question Number

Starting Up a Project + Initiating a Project Processes

Part 2

Marks

Using the Project Scenario, answer the following 6 questions about the Starting up a Project
and the Initiating a Project process.
Decide whether the actions taken represent an appropriate application of PRINCE2 for this project
and select the response that supports your decision.
1

When designing the project management team, the Project Manager created a Team Manager
role description for the Team Manager role which the professional photographer will perform in
stage 3. Is this an appropriate application of PRINCE2 for this project?
A
B
C

No, because the professional photographer should create their own role description
when they are appointed in stage 2.
No, because the professional photographer is external to the corporate organization.
Yes, because role descriptions help to identify candidates for each of the project
management team roles, and can be used when proposing the most appropriate
people for them.
Yes, because the Project Manager should create role descriptions for all members of
the project management team.

When creating the Project Plan, the Project Manager identified the new company logo as an
external dependency.
Is this an appropriate application of PRINCE2 for this project?
No, because the new company logo should be identified in the Business Case as part
A
of the reasons for undertaking the project.
B
No, because the new company logo should be identified in the Project Plan as an
internal dependency.
Yes, because the new company logo is required to produce the calendar and is being
C
produced by another project.
D
Yes, because the production of the new company logo will need to be controlled by
the Project Manager.

During the initiation stage, the Project Manager created the Product Description for the
designs for each month.
Is this an appropriate application of PRINCE2 for this project?
A

No, because all Product Descriptions should be created during the Managing a Stage
Boundary process, when preparing the Stage Plan.

No, because it is the Project Product Description that should be created to define
what the project must deliver in order to gain acceptance.

Yes, because the Project Manager should create Product Descriptions for all of the
products to be delivered by the project as part of the Project Plan.

Yes, because Product Descriptions for the major products of the project should be
created when preparing the Project Plan.

Question continues on next page

2009 ILX Group plc

178

PRINCE2 Practitioner Resource Book

When setting up the project controls, the Project Manager identified dates for
2 two end stage
assessments, one for each of the management stages following initiation.
Is this an appropriate application of PRINCE2 for this project?
A
No, because the Closing a Project process is used at the end of the final stage.
B
C
D

Practitioner Exam Questions

No, because there are three stages in this project.


Yes, because the Project Manager needs to report how the stage performed and
provide an update on the Business Case.
Yes, because the Project Board needs to be made aware of these dates so as to
ensure its availability.

The Project Manager has now completed the Project Plan which contains the Work
Packages for each of the project's products.
Is this an appropriate application of PRINCE2 for this project?
A
No, because Work Packages should be created during the Starting up a Project
process to support the Project Product Description.
B

No, because the Project Plan does not contain the content of each Work Package.

Yes, because the tolerance(s) set in the Project Plan are derived from the Work
Package tolerance(s).

Yes, because the Project Board will require this information in order to set
tolerance(s) for the Team Manager(s).

At the end of the initiation stage, the Project Manager has updated the Project Plan to show
how and when all of the expected benefits of the promotional calendar will be measured and
captured.
Is this an appropriate application of PRINCE2 for this project?
A
No, because any changes to the Project Plan should be approved by the Project
Board.
B
C
D

No, because most of the expected benefits will be achieved after the project has
closed.
Yes, because it is important to define each benefit in quantifiable terms so that
measurable improvements can be made.
Yes, because the expected benefits of the promotional calendar can be measured
during the life of the project.

Question

Part

1
2
3
4
5
6

2009 ILX Group plc

179

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Risk Theme

Part 2

Marks

The project is now in stage 2. The Project Manager has heard about the possibility of a
competitor also producing a calendar to be delivered earlier than the target date for this
project. There is a threat that the early release of a competitor's calendar may weaken the
impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated
benefits of the Calendar project.
Column 1 contains a number of risk responses identified by the Project Manager following an
assessment of this risk. Column 2 contains a list of threat response types. For each risk response in
Column 1, select from Column 2 the type of response it represents. Each option from Column 2 can
be used once, more than once or not at all.
Column 1

Column 2

Record the risk in the Risk Register and monitor the situation.

Avoid

Decide not to compete and cancel the project.

Reduce

Bring the target date of this project forward.

Fallback

Wait for confirmation of the rivals calendar and, if required,


include additional gifts with the calendar as an extra incentive.

Transfer

Accept

Carry on with the project as planned on the basis that the MNO
Manufacturing Company calendar is believed to be of better
quality.

Share

Add a unique reference number to every calendar and hold a


prize draw each month.

Question

Part

1
2
3
4
5
6

2009 ILX Group plc

180

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Risk Theme

Part 2
B

Marks
6

Using the additional information provided for this question in the Scenario Booklet, answer
the following question.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion

Reason

The fact that there has been no contact


with the photographer should have been
raised as an issue.

As the person monitoring the contract, the


Purchasing Manager would be an
appropriate owner for the risk.

BECAUSE

The photographer should have raised any


concerns about their availability for the
work as a risk before accepting the Work
Package.

BECAUSE

If estimation of the risk shows that it is


likely to impact upon time, the Project
Manager will need to raise an Issue
Report.

Regular Checkpoint Reports from the


photographer will help the Project
Manager manage the risk.

As a Work Package has been agreed


with the photographer, responsibility for
the risk will automatically have been
transferred to this third party.

2009 ILX Group plc

BECAUSE

BECAUSE

Any forecast to exceed the agreed


stage tolerances should be
escalated to the Project Board.
A risk actionee should be the
person most capable of managing
the risk.
A separate Risk Register should be
created for each Work Package to
monitor specialist risks associated
with the creation of specialist
products.
When the impact of a risk has been
identified, an Issue Report will be
required to implement any agreed
risk actions.

BECAUSE

Checkpoint Reports should provide


early warning of any delay in the
photographers work.

BECAUSE

When selecting the most


appropriate risk response to take,
the best option is usually the least
expensive.

181

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6

2009 ILX Group plc

182

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Plans Theme

Part 2
A

Marks
2

Answer the following questions about plans.


Remember to select 2 answers to each question.
1

During which 2 activities should a plan be produced?


A

When a Work Package is authorized, in the Controlling a Stage process.

When preparing for planned closure, in the Closing a Project process.

When a Work Package is accepted, in the Managing Product Delivery process.

When escalating issues and risks, in the Controlling a Stage process.

When planning project closure, in the Managing a Stage Boundary process.

Which 2 statements concerning responsibility for creating plans are correct?


A

The Team Manager is responsible for creating Stage Plans.

The Team Manager is responsible for creating Team Plans.

Project Support is responsible for creating Team Plans.

The Project Board is responsible for creating the Project Plan.

The Project Manager is responsible for creating the Project Plan.

Question

Part

1
2

2009 ILX Group plc

183

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Syllabus Area

Question Number

Plans Theme

Part 2

Marks

Using the Project Scenario and the Product Summary provided as additional information for
this question in the Scenario Booklet, answer the following 5 questions about the plan for
this project.
Decide whether the statements reflect an appropriate application of the product-based planning
technique for this project and select the response that supports your decision.
1

'Production cost forecast' has been shown as an external product in the product flow diagram.
Is this an appropriate application of product-based planning for this project?

No, because the 'production cost forecast' is required for making the decision.

No, because the 'production cost forecast' is being created within the scope of the
plan.

Yes, because the 'production cost forecast' is dependent on the external product.

Yes, because the 'production cost forecast' is required for making a decision.

'Tariff of mailing costs' has been shown in the product breakdown structure as a product to be
created or modified by the project.
Is this an appropriate application of product-based planning for this project?
A

No, because the tariff of mailing costs is being supplied by the Post Office.

No, because the tariff of mailing costs already exists.

Yes, because the 'tariff of mailing costs' will be used to create the production cost
forecast.

Yes, because the project costs may change.

Question continues on next page

2009 ILX Group plc

184

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question continued

'Accounts information' has been shown on the product flow diagram as an external
dependency for the 'list of customers'.
Is this an appropriate application of product-based planning for this project?
A
No, because 'accounts information' already exists and should not be shown on the
product flow diagram.
B

No, because the 'accounts information' should be shown as an internal dependency


for the list of customers.

Yes, because accounts information is being supplied by the Accounts department.

Yes, because accounts information already exists and will be required to produce
the list of customers.

'Choose label design' has been shown on the product breakdown structure as a product to
be created or modified by the project.
Is this an appropriate application of product-based planning for this project?
A

No, because choose label design is an activity.

No, because the competition entries are external to the scope of the plan.

Yes, because the label design will be chosen from entries to the competition.

Yes, because the competition entries are within the scope of the plan.

'Prepared calendar pack' has been shown as the final product on the product flow diagram.
Is this an appropriate application of product-based planning for this project?
A
No, because the 'prepared calendar pack' should appear as the first product at the
top of the product breakdown structure.
B

No, because the calendars still require printing.

Yes, because 'prepared calendar pack' is the final product of the project.

Yes, because all other products are dependent on the prepared calendar pack.

Question

Part

1
2
3
4

2009 ILX Group plc

185

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Syllabus Area

Question Number

Plans Theme

Part 2

Marks

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional
information for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst
photographs are being taken of the engineering staff performing their everyday duties and
operating machinery. Two weeks ago the professional photographer produced the
photographic session schedule based on the operational staff schedule. The operational staff
schedule is produced weekly and maintained by the Engineering Manager.
None of the 500 change budget has been used to date and this is available for the stage.
Remember to select 2 answers to each question.
1

Which 2 statements apply to the Plan prerequisites section?


A

Delete entry 2 because these are project benefits not prerequisites of the stage.

B
C

Delete entry 3 because the production cost forecast is a deliverable of stage 2, not a
prerequisite for stage 3.
Delete entry 4 because the customer list is NOT needed to start the work in stage 3.

D
E

Add 'Engineering team must be made available for the photographic session.
Add Compliance with the Data Protection Legislation.

Which 2 statements apply to the External dependencies section?


A

Delete entry 5 because the new company logo is being delivered by a separate
project and will be detailed in the plans for that project.

Move entry 5 to Plan prerequisites because the new company logo will influence the
label designs.

Move entry 5 to Plan description because the new company logo will be delivered
during stage 3.

Delete entry 6 because the customer details were used in stage 2 to create the
customer list.

Delete entry 7 because it should be shown in the Product Description for the label
design.

Question continues on next page

2009 ILX Group plc

186

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question continued

Which 2 statements apply to the Planning assumptions section?


A

No change to entry 8 because this cannot be confirmed until all of the label designs
entries have been received and an assessment made.

Move entry 8 to External dependencies because the label designs are created
outside of the scope of the project.

Delete entry 9 because the photographic session schedule should have been
approved as part of stage 2.

Move entry 9 to External dependencies because the photographic session


schedule is created by the professional photographer.

Delete entry 10 because the inclusion of different members from the Engineering
team in each photo should be shown in the Product Description for the photographs.

Which 2 statements apply to the Monitoring and control section?


A

Delete entry 11 because this relates to the monitoring and controlling of the Project
Plan, not the Stage Plan.

No change to entry 12 because this describes how the Project Board will control the
stage.
Move entry 12 because the Highlight Reports are deliverables of this stage and
should be shown under Product descriptions.
Delete entry 13 because this is part of the Controlling a Stage process.

C
D
E

Delete entry 14 because the Product Status Account is NOT an ad-hoc report. It is
produced at the end of each stage to identify any variations between planned status,
reported status and actual status of the stage's products.

Which 2 statements apply to the Budgets section?


A

Amend entry 15 because it should also include the cost of management activities.

Delete entry 16 because timescales should NOT be shown under the heading of
budgets.

Delete entry 17 because the risk budget should be shown in the Risk Management
Strategy.

Add Change budget - 500.

Add Cost tolerance - +6,000 / -6,000.

Question

Part

1
2
3
4
5

2009 ILX Group plc

187

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

2
Syllabus Area

Question Number

Part

Marks

Progress Theme

Using the Project Scenario, answer the following 6 questions about the use of PRINCE2
controls in this project.
1

At the end of initiation there is +1 week / -2 weeks time tolerance for this project. Which
statement is true?
A

There can be no time tolerances for any of the stages.

All of the project level time tolerance can be allocated to stage 2.

The Stage Plan for stage 2 could create some additional project time tolerance by
allowing no time tolerance in Team Plans.

Additional time tolerance for the project could be found by adding extra resources
without affecting other tolerances.

During stage 2, if the Project Manager decides to recommend that the Project Plan is revised
to finish three weeks later, which statement is correct?
A

The tolerances stated in the Project Plan CANNOT be changed.

The Executive needs to seek formal approval from corporate management to


implement this change.

The current project must close prematurely and be restarted with a new Project Plan,
a new Business Case and new Risk Register.

The revision of the Project Plan would have to wait until the end stage assessment of
stage 2.

During stage 2, an early review of the photograph design ideas from the Marketing department
has highlighted the need for engineering machinery to be operating in the background during
the photographic sessions. This requires a change to the baselined Product Description for the
photographs. What action should the Project Manager take?
A

Log the change in the Issue Register as a request for change.

Raise an Exception Report to the Project Board.

Revise the Product Description for the photographs and issue it to the Engineering
Manager to ensure that the machinery will be operating during the photographic
sessions.

Include this requirement on the next Checkpoint Report to the photographer.

Question continues on next page

2009 ILX Group plc

188

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question continued

As the project approaches the end of stage 2, the Project Manager has requested a Product
Status Account to ensure that all products are at their expected point of development.
Although the list of customers has been quality reviewed, it has not been baselined because
the Marketing department has not provided all of the prospective customers' details. What
initial action should the Project Manager take?
A

Delay producing the End Stage Report until the list of customers has been
baselined.

Raise an Exception Report to the Project Board to highlight the issue.

Check the target sign-off date for the list of customers.

Update the product status to baselined and obtain a commitment from the
Marketing department to finish this work within the next few days.

Whilst identifying the mailing costs for the calendars the Project Manager was surprised to
find the costs could vary considerably depending on the size of the package and the delivery
service used. For the purpose of this project, the Project Manager has selected an
appropriate service but feels that a corporate standard for postage would have reduced the
time and effort invested. It could reduce the company's overheads by up to 20,000 per year.
How should the Project Manager record this observation within the project?
A

Produce a project mandate, outlining the potential savings to be achieved by the


introduction of a corporate standard.

Make a note of the observation in the Daily Log to be transferred to a Benefits


Review Plan at the end of the project.

Record the observation in an Exception Report to the Project Board.

Make an entry in the Lessons Log for future consideration by corporate


management.

The team member collating the list of customers has now forecast that it will NOT be
complete by the end of this stage as originally planned, due to a number of new prospective
customers' details not yet being available. What action should the team member take?
A

Report the forecast delay in the next Checkpoint Report to the Executive.

Add the product to the next Stage Plan in order to allocate additional resources and
complete the work.

Make an entry in the Risk Register so the Project Manager can decide on
appropriate action.

Raise an issue to inform the Project Manager.

2009 ILX Group plc

189

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6

2009 ILX Group plc

190

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Progress Theme

Part 2
B

Marks
6

Using the Project Scenario, answer the following question.


Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion
1

The label design competition should be


planned and managed as two
management stages.

Reason
BECAUSE

A decision can only be made by the


Project Board at the end of a
management stage.

Quality tolerances allocated to the


photographs can be used to remedy a
forecast threat to time tolerance.

BECAUSE

Any forecast threat to time


tolerance should first be resolved
by use of any available quality
tolerance.

A suitable point for a stage boundary


would be after the production cost
forecast has been produced.

BECAUSE

A stage boundary represents a


go/no go decision point.

With +1 week / -2 weeks time tolerance,


the project is permitted to finish two
weeks later than 30 November.

BECAUSE

If the project is forecast to exceed the


cost tolerance of +6,000, the Project
Manager should send an Exception
Report straight to corporate management.

BECAUSE

The production cost forecast should be


reviewed by the Project Board during the
Directing a Project process to determine
whether the project should continue.

BECAUSE

2009 ILX Group plc

A negative project time tolerance


indicates the total permissible delay
to a project schedule before an
exception situation occurs.
If the forecast is for project
tolerances to be exceeded, the
Project Board no longer has the
authority to continue with the
project.
The Project Board reviews all
products at the end of each stage.

191

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6

2009 ILX Group plc

192

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Change Theme

Part 2
A

Marks
6

Using the Project Scenario, answer the following question. The Plan for stage 3 has been
approved and work has commenced.
Column 1 contains a number of issues for this project. Select from Column 2 the appropriate
category for each issue. Each selection from Column 2 can be used once, more than once or not at
all.
Column 1
1

Column 2

Although NOT previously considered, the Engineering


Manager now wants to amend the Product Description
for the photographs to include images of his latest
production machinery.

The Marketing Director feels that the calendar may NOT


be of sufficient quality to achieve the projected benefits.

The Marketing department has identified some new


customers and wants to include them in the approved
list of customers.

The photographer has ignored the agreed photographic


session schedule. He has interrupted the work of the
engineering staff to take the photographs for the
calendar.

The chosen label design has been signed-off in error as


the old company logo has been used. Inclusion of the
new company logo was specified.

The Project Manager has received notification of a


postal strike occurring in December.

Question

Part

Problem or concern

Request for change

Off-specification

1
2
3
4
5
6

2009 ILX Group plc

193

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Change Theme

Part 2

Marks

There is a major concern over an apparent lack of control of project documentation.


For each concern listed in Column 1, select from Column 2 the configuration management task that
could help address the problem. Each selection from Column 2 can be used once, more than once
or not at all.

Column 1

Column 2

As a number of people are involved in the


project it is becoming increasingly difficult to
keep track of what documentation each person
has.

Produce a Product Status


Account

Maintain a record of all copies


issued

Record the link between version


and the Issue Report that
caused its change

Notify copy holders of any


changes

Recall and archive superseded


product copies

Retain master products, issuing


copies only

Maintain a record of
relationships between products

Both current and previous versions of the


photographic session schedule are in
circulation.

A revised list of customers has been issued but


it is not clear what was wrong with the previous
one.

The Marketing department has lost the chosen


label design and no copy was made.

The Marketing department staff cannot say with


any certainty which photographs were approved
and which still require work.

The Marketing Director has complained that the


accounts information has been changed and
that no consideration has been given to the
impact this will have on the list of customers.

Question

Part

1
2
3
4
5
6

2009 ILX Group plc

194

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Syllabus Area

Question Number

Part

Directing a Project + Managing a Stage Boundary +


Closing a Project Processes

Marks
6

Using the Project Scenario, answer the following question.


It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to
choose the winning label design and the 12 photographs for the calendar.
The Executive has learned that two competitors are issuing calendars to MNO's customers by
the middle of November. After analysing the impact of this issue, one of the options the
Project Manager has presented to the Project Board is to close the project prematurely. There
are a number of key facts relating to this project that would need to be recorded if the project
were to be closed early.
Column 1 contains key facts recorded in the projects Daily Log. For each fact in Column 1, select
from Column 2 the activity within the Closing a Project process, which, if applied appropriately, should
capture this fact. A selection from Column 2 may be used once, more than once or not at all.
Column 1
1

The staff photographs are suitable for use in future


promotional materials. The photographer will be
asked to provide all photographs into a useable
format before this Work Package is approved.
Staff photographic sessions were disruptive to the
Engineering Department as they had been
scheduled during peak work times without
consultation with the Engineering Manager.

If anybody has any remaining resource costs to be


charged to the project, they should ensure this is
done by 10 November.

The project has not achieved the objectives defined


in the Project Initiation Documentation.

Staff morale will be further affected if a winning label


design is not selected and announced. This should
be completed before the project is closed.

The risk of a competitor producing a calendar at the


same time was identified at the beginning of the
project but the assessment and management of this
risk was poor.

Column 2
A

Prepare planned closure.

Prepare premature closure.

Hand over products.

Evaluate the project.

Recommend project closure.

Question continues on next page

2009 ILX Group plc

195

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question continued

Question

Part

1
2
3
4
5
6

2009 ILX Group plc

196

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Syllabus Area

Question Number

Directing a Project + Managing a Stage Boundary +


Closing a Project Processes

Part 2
B

Marks
6

Using the Project Scenario, answer the following question.


The Calendar project was delivered as originally planned, and is now preparing for planned
closure.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used once,
more than once or not at all.
Option

Assertion

Reason

True

True

AND the reason explains the assertion

True

True

BUT the reason does not explain the assertion

True

False

False

True

False

False

Assertion
1

Whether the calendar achieves its


objective of countering the decline in
orders will be confirmed in the Closing a
Project process.

A formal quality review meeting, chaired


by the Project Manager, should be held
for the Project Board to compare the final
deliverable against the Project Product
Description.

The End Project Report must be


completed before 30 November.

The Stage Plan for stage 3 should


contain details of the products to be
created or updated during the Closing a
Project process.
As part of the handover of the final
product, a contract should be agreed with
Marketing for ongoing support of this
product.

At the end of stage 3, the Managing a


Stage Boundary process should be used
to update the Project Plan with actuals
from the final stage.

2009 ILX Group plc

Reason
BECAUSE

BECAUSE

BECAUSE
BECAUSE

BECAUSE

BECAUSE

The Benefits Review Plan is


created in the Closing a Project
process.
The Project Product Description is
used by the Closing a Project
process to verify that the project
has delivered what was expected of
it.
An End Project Report should be
produced before a project closes.
Closure activities should be
planned as part of the Stage Plan
for the final management stage.
A service agreement or
maintenance contract should
always be included as a product of
the final stage.
An objective of the Managing a
Stage Boundary process is to
review, and if necessary, update
the Project Initiation
Documentation.

197

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
A

1
2
3
4
5
6

2009 ILX Group plc

198

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Suggested Answers

Practitioner Exam Calendar Project

Question

Part

Question

Part

2009 ILX Group plc

199

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

2009 ILX Group plc

200

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

Question

Part

2009 ILX Group plc

201

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

Question

Part

2009 ILX Group plc

202

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

2009 ILX Group plc

203

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

Question

Part

2009 ILX Group plc

204

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

2009 ILX Group plc

205

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

2009 ILX Group plc

206

Practitioner Exam Questions

PRINCE2 Practitioner Resource Book

Question

Part

Question

Part

2009 ILX Group plc

207

PRINCE2 Practitioner Resource Book

Calendar Project Rationale

Practitioner Exam Questions

Question 1 Business Case Theme


Question

Part

Answer

1a

incorrect

This is an Expected Benefit of this project. The Reasons should show why the
project outcome is needed, the background. Ref. A.2.1 / 4.3.4.1.

1b

correct

This is an explanation of why the project is required. Ref. A.2.1 / 4.3.4.1.

1c

incorrect

1d

incorrect

1e

correct

Question

Part

Answer

2a

correct

2b

incorrect

2c

incorrect

2d

incorrect

2e

correct

Question

Part

Answer

3a

correct

3b

incorrect

3c

correct

3d

incorrect

3e

incorrect

2009 ILX Group plc

This is the total number of orders last year, the position to measure against. It
is not the expected benefit for this project. Ref. Scenario Booklet / 4.3.4.3.
This is an Expected Benefit of this project. The Reasons should show why the
project outcome is needed, the background. Ref. A.2.1 / 4.3.4.1.
This is an explanation of why the project is required. Ref. A.2.1 / 4.3.4.1.

This is one of the options considered to achieve the project outcome.


Ref. 4.3.4.2 / A.2.1.
This is an approach to deliver the required products and should
therefore be documented in the Project Brief. Ref. A.19.2.
This is an approach to deliver the required products and should
therefore be documented in the Project Brief. Ref. A.19.2.
This is an approach to deliver the required products and should
therefore be documented in the Project Brief. Ref. A.19.2.
This option is always considered in the Business Case as a starting
point to act as a comparison for other options. Ref. 4.3.4.2 / A.2.1.

This is a stated measurable benefit anticipated from this project. Ref.


4.3.4.3 / A.2.1.
Using a similar format to previous years may have contributed to the
selection of the business option but it is not a project benefit. Ref.
4.3.4.3 / A.2.1.
This is a stated measurable benefit anticipated from this project. Ref.
4.3.4.3 / A.2.1.
The Business Case does not contain a breakdown of the products to be
delivered within the project. This would be documented under
'Composition' in the associated Product Description. Ref. A.17.2.
This is a requirement of the project product which should be stated in
the Project Product Description. Ref. A.21.2.

208

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

4a

incorrect

This relates to the cost of quality within the deliverables. It is NOT a


negative consequence of the project. Ref. 4.3.4.4.

4b

correct

This is a negative consequence of the calendar project. Ref. 4.3.4.4 /


A.2.1.

4c

incorrect

This is a threat to the expected benefits, NOT a negative consequence


of the project. Ref. 4.3.4.4 / 8.2.1.

4d

correct

This is a negative consequence of the calendar project. Ref. 4.3.4.4 /


A.2.1.

4e

incorrect

This is a threat to the expected benefits, NOT a negative consequence


of the project. Ref. 4.3.4.4 / 8.2.1.

Question

Part

Answer

5a

incorrect

5b

incorrect

5c

correct

5d

correct

5e

incorrect

Question

Part

Answer

6a

incorrect

6b

correct

6c

incorrect

6d

incorrect

6e

correct

2009 ILX Group plc

This is a risk. It has not happened yet, but the impact should be
considered and recorded under Major Risks'. Ref. 8.2.1.
The recruitment campaign is likely to be a follow-on action that is not
within the scope of this project. Ref. 18.4.4.
When benefits are expected to be achieved should be stated under the
Timescale heading in the Business Case. Ref. 4.3.4.5 / A.2.1.
This is the timescale for project delivery and should be stated here
under the heading of Timescale. Ref. 4.3.4.5 / A.2.1.
This is not a timescale for project delivery. Ref. 4.3.4.5 / A.2.1.

The fact that MNO have allocated 120k to the marketing budget for
this year is not a cost of the project. Ref. 4.3.4.6 / A.2.1.
The Business Case should show the funding arrangements under the
heading of Costs within the Business Case. Ref. 4.3.4.6 / A.2.1.
This is an Expected Benefit, it is not a cost of the project, i.e. expected
income rather than outgoings. Ref. 4.3.4.3 / A.2.1.
The new company logo is not within the scope of this project. Ref.
Scenario Booklet.
The costs section of the Business Case should include the total of
forecast costs, including allocated tolerances, risk and change budgets.
Ref. 4.3.4.6 / A.2.1.

209

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

7a

incorrect

7b

incorrect

7c

correct

7d

correct

7e

incorrect

2009 ILX Group plc

This is a dis-benefit of the project outcome, not a risk to the project.


Ref. 4.3.4.4 / 8.2.1.
This is not a risk, this is stated as fact in the Project Scenario. Ref.
Project Scenario / 8.2.1.
This is a risk to the project. Risks facing the project can either
reduce/enhance the benefits or reduce/increase the cost. Ref. 4.3.4.8 /
A.2.1.
This is a risk to the project. Risks facing the project can either
reduce/enhance the benefits or reduce/increase the cost. Ref. 4.3.4.8 /
A.2.1.
This is stated as a fact and not an uncertainty/potential threat. Ref.
8.2.1.

210

PRINCE2 Practitioner Resource Book

Question 1 Business Case Theme


Question

Part

2009 ILX Group plc

Assertion

True - Each option considered within


the Business Case would represent a
different project and investment Ref
4.3.4.3 / 9.3.3.2

False - Printing within the first week of


December remains within the projects
time tolerance of +1 week. Ref. 10.2.3
/ 4.3.4.6.

Practitioner Exam Questions

2
Reason

False - Options considered for the delivery


of the chosen solution should be covered
in the project approach (Project Brief). The
business options in the Business Case
refer to the various solutions considered.
Ref. A.2.2 / A.19.2.
False - Further tolerance may be available
for the stage in which case the Business
Case may still be viable. Ref. 10.2.3.

True - The outline Business Case


contains the reasons why the project is
needed and forms part of the Project
Brief. Ref. 4.3.1 / A.19.2.

True - The Project Brief includes high-level


information on what needs to be done,
why, who will need to be involved, and
how and when it will be done. This reason
explains the assertion, therefore the
answer is A. Ref. A.19.2.

True - The Benefits Review Plan is


used to define for the Executive how
and when a measurement of the
achievements of the projects benefits
can be made. Ref. A.1.2.

True - At the end of each stage the


Benefits Review Plan will be examined
and reviewed for the results of any
benefits reviews undertaken during the
stage. The assertion refers to some-time
after the project has closed. Therefore the
answer is B. Ref. 17.4.3.
False - All benefits, both financial and nonfinancial, should be recorded in the
Business Case. Ref. A.2.2.

False - This is a positive consequence


of the Calendar project which is
measureable and should therefore be
recorded in the Business Case. A.2.2 /
4.3.4.3.

211

PRINCE2 Practitioner Resource Book

Question 2 Organisation Theme

Question

Part

Answer

1a

incorrect

1b

incorrect

1c

correct

1d

correct

1e

incorrect

Question

Part

Answer

2a

incorrect

2b

incorrect

2c

incorrect

2d

correct

2e

correct

Question

Part

Practitioner Exam Questions

The length of service of an individual is not a PRINCE2 reason for the


appointment of an Executive. Ref. 5.3.2.2.
Although this may be useful from a specialist knowledge point of view,
this is not a PRINCE2 reason for the appointment of an Executive. Ref
5.3.2.2.
An Executive should be able to represent the business interests on a
project. Ref. 5.3.2.2.
The Executive should be able to commit resources to the project and
make decisions on behalf of the business. Ref. 5.3.2.2.
The development needs of an individual is not a PRINCE2 reason for
the appointment of an Executive. Ref 5.3.2.2.

The length of service of an individual is not a PRINCE2 reason for the


appointment of an Executive. Ref. 5.3.2.2.
Knowledge of a functional position is not a PRINCE2 reason for the
appointment of an Executive. Ref. 5.3.2.2.
Physical involvement is not a PRINCE2 reason for the appointment of
an Executive. Ref. 5.3.2.2.
The Executive should be able to commit resources and make decisions
on behalf of the business. Ref. 5.3.2.2.
The Executive has knowledge of the business strategic requirements
and a responsibility to ensure that the project is aligned to these
strategies. Ref. 5.3.2.2.

Answer

3a

correct

3b

incorrect

3c

correct

3d

incorrect

3e

incorrect

2009 ILX Group plc

The Senior User should be able to make decisions on behalf of the


users and, as a representative of the main users of the deliverable from
the project, the Marketing Director would be suitable for this role. Ref.
5.3.2.2.
This would be useful for the role responsible for supplying the specialist
knowledge for this project. The Senior User role does not require
specialist knowledge. Ref. 5.3.2.2.
The Senior User should represent those for whom the product will
achieve an objective or those who will use the products to deliver
benefits. Ref. 5.3.2.2.
The Executive role represents the funding of the project, not the Senior
User. Ref. 5.3.2.2.
Those producing the products within the project are suppliers and
should be represented by the Senior Supplier. Ref. 5.3.2.2.

212

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

4a

incorrect

4b

incorrect

4c

correct

4d

incorrect

4e

correct

Question

Part

Answer

5a

correct

5b

correct

5c

incorrect

5d

incorrect

5e

incorrect

Question

Part

Answer

6a

incorrect

6b

correct

6c

correct

6d

incorrect

6e

incorrect

2009 ILX Group plc

The length of service and motivation of an individual are not PRINCE2


reasons for the appointment of a Senior User. Ref. 5.3.2.2.
The development needs of an individual are not a PRINCE2 reason for
the appointment of a Senior User. Ref. 5.3.2.2.
The Senior User should represent those who are affected by the
project. Ref. 5.3.2.2.
PRINCE2 does not recognise reporting structures within the business
or hierarchies. The reporting structure within the project will be agreed
within the project. Ref. 5.3.2.2.
The Senior User should represent the interests of those who will use
the final product(s) of the project. Ref. 5.3.2.2.

The Senior Supplier role is responsible for advising on the selection of


design, development and acceptance methods. Ref. C.4.1.
The Senior Supplier role is responsible for ensuring that supplier
resources required for the project are made available. Ref. C.4.1. The
Senior Supplier(s) represents the interests of those designing,
developing, facilitating, procuring, and implementing the projects
products. Ref 5.3.2.2.
The Purchasing Manager's experience of Engineering has no bearing
on the project or the role of Senior Supplier within the project. Ref.
5.3.2.2.
It is the Executive that has to ensure that the project gives value for
money, ensuring a cost-conscious approach to the project, balancing
demands of the business, user and supplier. Ref. 5.3.2.2.
Just because an individual is not appropriate for the role of Executive or
Senior User, does not make them appropriate as a Senior Supplier.
Ref. 5.3.2.2.

The length of service and motivation of an individual are not PRINCE2


reasons for the appointment of a Project Assurance role. Ref. 5.3.2.2.
As a user of the project's product(s), the Sales Manager would be well
placed to evaluate the impact of potential changes from the user point
of view on behalf of the Senior User, which is a Project Assurance
responsibility. Ref. 5.3.2.2.
Current and prospective customers are stakeholders within the project
and the Sales Manager is well placed to advise on how best to
communicate with them, a role of the User Assurance. Ref. 5.3.2.2.
The development needs of an individual are not a PRINCE2 reason for
the appointment of a Project Assurance role. Ref. 5.3.2.2.
The resolution of conflicts between users is a responsibility of the
Senior User, not Project Assurance. Ref. 5.3.2.2.

213

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

2
Question

Part

Answer

7a

correct

7b

incorrect

7c

incorrect

7d

incorrect

7e

correct

Question

Part

2009 ILX Group plc

One of the key competencies required of Project Support is the


knowledge of specialist tools and techniques. Having this knowledge
makes Central Records an appropriate resource for this role. Ref.
C.9.2.
The length of service and general existence are not PRINCE2 reasons
for the appointment of a Project Support role. Ref. 5.3.2.8.
This is a quality assurance responsibility which may be delegated to
Project Assurance, but NOT Project Support. Ref. 6.2.6.
The quality assurance function may be delegated to Project Assurance,
but NOT Project Support. Ref. 6.2.6.
This is a competency required of Project Support. Ref. C.9.2.

Assertion

Reason

False - The Executive role is vested in


one individual so that there is a single
point of accountability for the project.
Ref. 5.3.2.2.
False - The Senior User role can be
shared by more than one individual,
but the Engineering Manager does not
represent a user on this project. Ref.
5.3.2.2.

True - The Executive is ultimately


responsible for the project and would seek
approval for the investment from corporate
or programme management. Ref. C.2.1.
False - The Senior User commits user
resources for the purpose of quality
checking. It is the Senior Supplier role that
provides specialist resources for the
design and development of the project's
products. Ref. 5.3.2.2.
True - The term 'Stakeholder' applies to
any individual, group or organization that
can affect, be affected by, or perceive
itself to be affected by, a project. Ref
Glossary. Bright Lights and Portraits Ltd
will interact with, and may affect, the
project. This is the reason for the
assertion. The answer is therefore A.
True - Project Assurance must be kept
separate from Project Support in order to
maintain their independence. This is an
explanation of the assertion. Therefore the
answer is A. Ref. 5.3.2.8.
True - The Communication Management
Strategy describes the tools to be used for
each step in the communication process.
This is not why the Engineering
Manager should be included. Therefore
the answer is B. Ref. A.4.2.

True - They each need to interact with


the project and can affect the project
outcome. They are therefore
stakeholders. Ref. 5.3.5.1.

True - Project Support and Project


Assurance roles should be kept
separate in order to maintain the
independence of Project Assurance.
Ref. 5.3.2.8.
True - The Engineering Manager is a
stakeholder from within the
organization, but external to the project
management team. He is not a
supplier or a user, but he does have an
interest and some influence. Ref.
5.3.5.3.

214

PRINCE2 Practitioner Resource Book

Question 3 Quality Theme

Question

Part

Answer

Question

Part

Answer

Practitioner Exam Questions

Quality Planning This covers agreement on overall quality


expectations, the products required with their associated quality criteria,
the means by which quality will be achieved and assessed. Ref 6.3.1.
Quality Control This covers the activities undertaken by the project
team to ensure that the products meet their respective quality criteria.
Ref 6.3.2.
Quality Assurance This activity manages the organization's Quality
Management System, not part of the project. Ref 6.2.6.

This states a measurable requirement of the product and should be


noted under Quality Criteria. Ref A17.2.
The product is to be given to the printing company. The printing
company is not involved in the creation or review of the product. Ref
A17.2.
The Project Board will be asked to review the label entries and will
therefore appear as reviewer under quality responsibilities. Ref A17.2.
Given the quality criteria, this is a measure of what would be
acceptable as a quality tolerance. Ref A17.2.

Question

Part

Answer

1a

correct

The product is selected paper, and not the paper itself. Ref A.21.2.

1b

correct

This is not a major product to be delivered by this project. Ref A.21.2.

1c

incorrect

1d

incorrect

1e

incorrect

2009 ILX Group plc

This is a major product to be delivered by this project, derived from


Marketing and Accounts information. Ref A.21.2.
Regardless of the source, this is a major product to be delivered by the
project. Ref A.21.2.
This is beyond the scope of this project. The final product will be the
prepared calendar pack. Ref A.21.2.

215

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

2a

incorrect

2b

incorrect

2c

correct

2d

correct

2e

incorrect

Question

Part

Answer

3a

incorrect

3b

incorrect

3c

incorrect

3d

correct

3e

correct

Question

Part

Answer

4a

incorrect

4b

correct

4c

incorrect

4d

incorrect

4e

correct

2009 ILX Group plc

The new logo design is being created by another project and therefore
is not within scope. Ref A.21.2.
This already exists and it provides the basis upon which this calendar
will be designed. The design of the calendar will incorporate the design
of the new logo.
It is therefore a derivation and should not be moved. Ref A.21.2.
The Internal Creative team will be required to create products and are
therefore already correctly shown under Development skills required.
Ref A.21.2
This is a product to be delivered by this project. Ref A.21.2.
This is not a source product from which the project is derived. Ref
A.21.2.

This is a supplier to this project, it is not a major product to be delivered


by this project. Ref A.21.2.
This is a supplier to this project, it is not a derivation or source of
information for this project. Ref A.21.2.
This skill is required in the project. Ref A.21.2.
The printing of the calendar is outside of the scope of this project. Ref
A.21.2.
This skill/person/group is required to help create the customer list. Ref
A.21.2.

This is one of the quality expectations stated, the photos are to be


professional. Ref A.21.2.
Printing is beyond the scope of this project. Ref A.21.2.
Customer's quality expectations is a description of the quality expected
of the Project Product and the standards and processes that will need
to be applied to achieve that quality. Ref A.21.2.
This is stated as a customer quality expectation, a description of the
quality expected of the Project Product and the standards and
processes that will need to be applied to achieve that quality. Ref
A.21.2.
This is an expected benefit (positive consequence) of this project and
should not be recorded under customer's quality expectations. Ref
A.21.2.

216

PRINCE2 Practitioner Resource Book

Question

Part

Practitioner Exam Questions

2
Answer

5a

correct

5b

incorrect

5c

correct

5d

incorrect

5e

incorrect

2009 ILX Group plc

The existing entry is not measurable, 'attractive' and 'humorous' are not
defined. This amendment is a measurable definition of the attributes
that must apply to the set of products to be acceptable to key
stakeholders. Ref A.21.2.
Acceptance criteria can be expressed as many things, including
appearance. This is not a composition item. Ref A.21.2.
The new company logo is being produced by another project. It is
required for inclusion within the Calendar project but the quality of it will
not be assessed during this project. Ref A.21.2.
This is a measurable definition of the criteria that the Project Product
must meet before the customer will accept. Derivation provides the
source from which the product will be created. Ref A21.2.
Acceptance criteria can be expressed as many things, including
accuracy, as long as it is measurable. Dates are to be shown correctly
as stated in the Scenario Ref A.21.2.

217

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 4 Starting Up a Project & Initiating a Project Processes


2
Question

Part

Answer

The term project mandate applies to whatever information is used to


trigger the project, be it a feasibility study or the receipt of a request for
proposal in a supplier environment. The project mandate is what
triggers the Starting up a Project process. Ref 12.3/19.8.3
Capturing previous lessons is the responsibility of the Project Manager
during the Starting up a Project process. The Project Manager must
therefore have been appointed prior to this activity. Ref 12.4.2
The appointment of the Project Manager allows for the project to be
managed on a day-to-day basis on behalf of the Executive. Ref 12.4.1

Question

Part

Answer

1a

correct

The Project definition includes interfaces. Ref A.19.2

1b

incorrect

This information should be recorded in the Product Description for the


calendar design. Ref A.17.2

1c

incorrect

This should be recorded under the Project approach heading. Ref


A.17.2

1d

incorrect

This should be recorded under the Project approach heading. Ref


A.19.2

Question

Part

Answer

2a

incorrect

2b

incorrect

2c

correct

2d

incorrect

Question

Part

Answer

3a

incorrect

3b

correct

3c

incorrect

3d

incorrect

2009 ILX Group plc

The printing of the calendars is not within the scope of the project.
Project scope, and any scope tolerance, should be recorded under the
Project definition heading. Ref A.19.2
This information would be captured in the Project Plan, during the
Initiating a Project process. Ref A.16.2
This is the reason why the project is needed and should be recorded
under the Outline Business Case heading. Ref A.19.2
This relates to the Project controls and should be recorded in the
Project Initiation Documentation. Ref A.20.2

This is the required outcome and should be recorded under the Project
definition heading. Ref A.19.2
To define the choice of solution that will be used within the project to
deliver the selected business option, taking into consideration the
operational environment into which the solution must fit. Ref A.19.2
This is a deliverable within the project it may be recorded under
Project definition heading, as part of Project scope and exclusions. Ref
A.19.2
This should be recorded under the Project definition heading, as part of
Project scope and exclusions. Ref A.19.2

218

PRINCE2 Practitioner Resource Book

Question

Part

Answer

incorrect

1b

incorrect

1c

correct

1d

incorrect

Part

When designing and appointing the project management team,


consideration should be given to whether or not separate Team
Managers are needed, or whether the Project Manager will be filling
this role. If appropriate, role descriptions should be created. Ref.
12.4.3. It is the responsibility of the Project Manager and the
Executives to produce project management team role descriptions. Ref
12.4.3
If selected as a Team Manager, the professional photographer will
become a member of the project management team. Both internal and
external resources can be members of the project management team.
Ref. 5.3.2.2
Consideration should be given to whether or not separate Team
Managers are needed, or whether the Project Manager will be filling
this role. If appropriate, role descriptions should be created. Ref.
12.4.3.
The Executive is responsible for preparing a role description for the
Project Manager. Ref. 12.4.1.

Answer

2a

incorrect

2b

incorrect

2c

correct

2d

incorrect

2009 ILX Group plc

Practitioner Exam Questions

1a

Question

The Business Case should contain the reasons for undertaking the
project and explain how the project will enable the achievement of
corporate strategies and objectives. Ref. A.2.2. The production of a
new company logo by another project is not the reason for the
Calendar project. Ref. Project Scenario.
Internal dependences are those under the control of the Project
Manager. The new company logo is being produced by another project
and is therefore an external dependency. Ref. Glossary / Project
Scenario.
When creating the Project Plan, the Project Brief should be checked for
understanding of any prerequisites, external dependences, constraints
and assumptions. Ref. 14.4.6. / A.16.2. External dependences are
those dependencies outside the control of the Project Manager - for
example, the delivery of a product required by this project from another
project. Ref. Glossary / Project Scenario.
External dependences are those dependences outside the control of
the Project Manager - for example, the delivery of a product required by
this project from another project. Ref. Glossary / Project Scenario.

219

PRINCE2 Practitioner Resource Book

Part

Answer

3a

incorrect

3b

incorrect

3c

incorrect

3d

correct

Part

When producing the Project Plan, during initiation, Product Descriptions


for the major products of the project should be created. If necessary,
these are then updated when planning the relevant stage. Ref. 14.4.6.
The Project Product Description should be created during the Starting
up a Project process. However, when producing the Project Plan,
during initiation, Product Descriptions for the major products of the
project should be created. Ref. 14.4.6 / 14.4.7.
When producing the Project Plan, during initiation, Product Descriptions
for the major products of the project should be created. Ref. 14.4.6.
When producing the Stage Plan for the next stage, Product
Descriptions are created or updated for the products to be delivered by
the next stage. Ref. 17.4.1.
When producing the Project Plan, during initiation, Product Descriptions
for the major products of the project should be created. If necessary,
these are then updated when planning the relevant stage. Ref. 14.4.6.

Answer

4a

correct

4b

incorrect

4c

incorrect

4d

incorrect

2009 ILX Group plc

Practitioner Exam Questions

Question

Question

The Managing a Stage Boundary process is used at the end of the


initiation stage and repeated at the end of each subsequent stage,
except the final stage. The end of the final stage is managed by the
activities of the Closing a Project process. Ref. Fig. 11.1 / 11.2.4.
The end of the initiation stage is recorded in the Initiation Stage Plan
and agreed prior to commencing initiation. It is only the remaining end
stage assessments that need to be agreed during initiation. Also, the
end of the final stage will be managed by the Closing a Project process.
Fig 11.1 / 12.4.6.
Towards the end of each management stage, except for the final one,
the Project Manager provides information to the Project Board in order
for it to assess the continuing viability of the project and make a
decision to authorize the next stage. During the final stage, this
information is provided within the closure activities which are planned
and approved as part of the stage approval for the final stage. Ref. 11.1
/ 11.2.4.
The Project Board does need to schedule these dates and be available.
However, there is only one end stage assessment to be scheduled
following initiation. Ref Project Scenario. The end of the final stage is
managed by the activities of the Closing a Project process. Ref 11.1 /
11.2.4

220

PRINCE2 Practitioner Resource Book

Question

Part

Answer

incorrect

5b

correct

5c

incorrect

5d

incorrect

Part

Work Packages are agreed between the Project Manager and Team
Manager (s) during the Controlling a Stage process and Managing
Product Delivery process. Ref 15.4.1 / 16.4.1. A Work Package is used,
by the Project Manager, to define and control the work to be done, and
also to set the tolerances for the Team Manager(s).
The Project Board does not require Work Packages as part of the
Project Plan. Work Packages are agreed between the Project Manager
and Team Manager(s) during the Controlling a Stage process and
Managing Product Delivery process. Ref 15.4.1 / 16.4.1.
Project tolerances are set by corporate or programme management.
Ref 10.3.1.1. Project tolerances should be derived from the project
mandate and documented in the Project Brief. Ref 12.4.5.
Work Packages are agreed between the Project Manager and Team
Manager(s) during the Controlling a Stage process and Managing
Product Delivery process. Ref 15.4.1 / 16.4.1. A Work Package is used,
by the Project Manager, to define and control the work to be done, and
also to set the tolerances for the Team Manager(s).

Answer

6a

incorrect

6b

correct

6c

incorrect

6d

incorrect

2009 ILX Group plc

Practitioner Exam Questions

5a

Question

Once approved, any changes to a baselined document should be


approved by the Project Board, or delegated Change Authority. The
Project Manager should review the Business Case to create the
Benefits Review Plan. This should contain details of how and when
benefits are to be measured. Ref. 14.4.7.
During initiation, the Project Manager should review the Business Case
to create the Benefits Review Plan. This should contain details of how
and when benefits are to be measured. Ref. 14.4.7.
During initiation, the Project Manager should review the Business Case
to create the Benefits Review Plan. This should contain details of how
and when benefits are to be measured. Ref. 14.4.7.
Projects benefits may be measured during the life of a project.
However, on this project the calendar is not despatched until after the
project has closed. Therefore, any benefits will be achieved after the
project has closed. Ref. Scenario Booklet / 4.3.3.

221

PRINCE2 Practitioner Resource Book

Question 5 Risk Theme

Question

Part

Answer

2009 ILX Group plc

Practitioner Exam Questions

Accept - A conscious decision to do nothing but monitor and ensure


that the threat remains tolerable. Ref Table 8.2.
Avoid - By not completing the project or changing some aspect of the
project so that the threat can no longer have an impact or can no longer
happen. Ref Table 8.2.
Reduce - Bringing the delivery date forward is a form of proactive
action taken to reduce the probability and/or the impact of the event
should it occur. Ref Table 8.2.
Fallback - Waiting to see if a rival calendar is produced and
developing a plan for extra incentives to be implemented after the risk
occurs will reduce the impact, but not the probability. Ref Table 8.2.
Accept - A conscious decision to do nothing but monitor and ensure
that the threat remains tolerable. Ref Table 8.2.
Reduce - This does not stop the risk from occurring but is a form of
proactive action taken to reduce the probability and/or the impact of the
event should it occur. Ref Table 8.2.

222

PRINCE2 Practitioner Resource Book

Question

Part

2009 ILX Group plc

Practitioner Exam Questions

2
Assertion

True - This could have an effect on the


project and should therefore be
recorded as an issue (problem). Ref
9.2.4.
True - The Purchasing Manager
should be monitoring the contract
situation and is therefore the person
best situated to manage, monitor and
control this risk. Ref 8.3.5.4.
True - When accepting a Work
Package a Team Manager should
perform a risk analysis identifying any
risks, and the means of managing
them. Ref 16.4.1.
False - If a risk is likely to impact upon
time, the risk response should mitigate
this and be added to the Risk Register.
Only when the risk occurs, does it
become an issue. Ref 8.3.5.
True - The Checkpoint Report is a
major data-gathering tool for the
Project Manager and should contain a
summary of the risk status. Ref 8.3.5.5
/ 16.4.1.
False - Transfer is a risk response
where a third party takes on the
responsibility for some of the financial
impact of a threat. Agreeing a Work
Package does not automatically
transfer the responsibility for a risk.
Ref. Table 8.2.

Reason

True - At stage level, exception situations


should be escalated to the Project
Board in an Exception Report. This does
not explain the assertion. The answer is
therefore B. Ref 10.3.4.
False - The person most capable of
managing the risk is the risk owner, not
the risk actionee. Ref. 8.3.5.4.

False - There is only one Risk Register for


the project, created during Initiating a
Project. Ref 14.4.1.

False - Risk action may be implemented


within tolerance or risk budget if there is
one. There is no need for an Issue Report.
Ref 8.3.5.
True - The Checkpoint Report will provide
a summary of actual and forecast
progress, highlighting any potential areas
for concern. This explains the assertion,
the answer is therefore A. Ref A.3.
False - When selecting the risk response,
it is a question of balancing the cost of
taking that response against the likelihood
and impact of allowing the risk to occur.
Ref 8.3.5.3.

223

PRINCE2 Practitioner Resource Book

Question 6 Plans Theme

Question

Part

Answer

1a

incorrect

1b

incorrect

1c

correct

1d

incorrect

1e

correct

Question

Part

Answer

2a

incorrect

2b

correct

2c

incorrect

2d

incorrect

2e

correct

2009 ILX Group plc

Practitioner Exam Questions

Only the Work Package is authorized by the Project Manager during


the Controlling a Stage process. Team Plans are created during the
Managing Product Delivery process. Ref 15.4.1
The Project Plan should be updated with actuals, but no plan is
produced. Ref 18.4.1
The Team Manager will produce a Team Plan while accepting a Work
Package during the Managing Product Delivery process. Ref 16.4.1
An Exception Report and Issue Report is used to escalate issues and
risks in the Controlling a Stage process. Ref 15.4.7. If the Project Board
requires an Exception Plan, this is produced during the Managing a
Stage Boundary process. Ref 17.4.5
The Stage Plan for the next stage is produced near the end of the
current stage. Closure activities should be planned as part of the Stage
Plan for the final stage. Ref 17.4.1 / 18.3

The Project Manager is responsible for producing the Stage Plans, but
this is not something that is done in isolation from other project
management team members. Ref 17.4.1 / C.5.1
The Team Manager will produce a Team Plan while accepting a Work
Package during the Managing Product Delivery process. Ref. 16.4.1 /
7.2.6
Project Support may contribute expertise in specialist planning tools
and techniques, but they are not responsible for the creation of any
plans. Ref C.9.1. The Team Manager will produce a Team Plan while
accepting a Work Package during the Managing Product Delivery
process. Ref. 16.4.1 / 7.2.6
The Project Manager is responsible for producing the Project Plan, but
this is not something that is done in isolation from other project
management team members. Ref 14.4.6 / C.5.1
The Project Manager is responsible for producing the Project Plan, but
this is not something that is done in isolation from other project
management team members. Ref 14.4.6 / C.5.1

224

PRINCE2 Practitioner Resource Book

Question

Part

Answer

incorrect

1b

correct

1c

incorrect

1d

incorrect

Part

The 'production cost forecast' is required to allow the CEO and


Marketing Director to decide whether to continue with the project, but
this does not determine whether or not it an external product. External
products already exist or are being created or updated outside of the
scope of the project. Ref 7.3.3.2
The 'production cost forecast' is being created within the scope of the
project and does not already exist. It should not therefore be shown as
an external product. Ref 7.3.3.2
The 'production cost forecast' is required to allow the CEO and
Marketing Director to decide whether to continue with the project, but
this does not make it an external product. External products already
exist or are being created or updated outside of the scope of the
project. Ref 7.3.3.2
The 'production cost forecast' is required to allow the CEO and
Marketing Director to decide whether to continue with the project, but
this does not make it an external product. External products already
exist or are being created or updated outside of the scope of the
project. Ref 7.3.3.2

Answer

2a

incorrect

2b

correct

2c

incorrect

2d

incorrect

2009 ILX Group plc

Practitioner Exam Questions

1a

Question

Although the 'tariff of mailing costs' is being supplied by a third party,


this is not the reason that it should be shown as an external product.
Products both within and external to the plan can be supplied by a third
party. External products already exist or are being created or updated
outside of the scope of the plan. Ref 7.3.3.2
If a product already exists or is being created or updated outside the
scope of the plan, it should be shown as an external product. Ref
7.3.3.2
An external product is one that already exists or is being created or
updated outside the scope of the plan and are required in order to
create one or more of the plan's products. The 'tariff of mailing costs'
already exists and should therefore be shown as an external product.
Ref 7.3.3.2
The 'tariff of mailing costs' already exists and is being supplied by the
Post Office. The Project Manager is not accountable for the creation of
this product. Ref 7.3.3.2

225

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

3a

incorrect

3b

incorrect

3c

incorrect

3d

correct

Question

Part

Answer

4a

correct

4b

incorrect

4c

incorrect

4d

incorrect

Question

Part

Answer

5a

incorrect

5b

incorrect

5c

correct

5d

incorrect

2009 ILX Group plc

All of the products of the plan should appear on the product flow
diagram. The product flow diagram also identifies dependencies on any
products outside of the scope of the plan. Ref 7.3.3.4
Internal dependencies are those within the control of the Project
Manager. External dependencies are those outside the control of the
Project Manager. The 'accounts information' is not being created or
updated within the plan, but it is required by the project in order to
produce one or more project products. It is therefore an external
dependency. Ref 7.3.4.2 / Glossary
Products being produced both within and external to the plan can be
supplied by third party suppliers. It is not the fact that a product is being
supplied by a third party that makes it an external product. Ref 7.3.3.2
'Accounts information' already exists (external product) and will be
required to produce the 'list of customers' (dependency). This is
correctly shown. Ref 7.3.4.2 / Glossary

'Choose label design' is an activity and therefore not a product. The


product would be 'chosen label design'. Ref 7.3.3
The entries would be external products, in that they are outside of the
scope of the plan and are not controlled by the Project Manager.
However, the 'chosen label design' is within the scope of the plan and
within the control of the Project Manager. 'Choose label design' is an
activity and therefore not an appropriate application of product-based
planning. Ref 7.3.3
'Choose label design' is an activity and therefore not a product. The
product would be 'chosen label design'. Ref 7.3.3
Although the 'label design competition' is within the scope of the plan,
the Project Manager has no control over the creation and submission of
the 'label design entries'. The entries should be shown as external
products. Ref 7.3.3.2.

The 'prepared calendar pack' is the final project product and should be
shown as the exit on the product flow diagram. Ref 7.3.3.4
The final deliverable of this project is the 'prepared calendar pack'. Ref.
Scenario.
The 'prepared calendar pack' is the final project product and should be
shown as the exit on the product flow diagram. Ref 7.3.3.4
The 'prepared calendar pack' is dependent on all of the other project
products. It is the final project product. Ref 7.3.3.4

226

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

1a

correct

1b

incorrect

1c

correct

1d

incorrect

1e

incorrect

Question

Part

Answer

2a

incorrect

2b

incorrect

2c

incorrect

2d

correct

2e

correct

2009 ILX Group plc

Whilst the Project Board would, in Directing a Project, assess whether


the planned benefits could still be achieved, the actual benefits
themselves are clearly not a prerequisite for the stage. Ref A16.2.
Whilst this is a deliverable of stage 2, the Project Board must agree to
this in their decision to progress to stage 3. It is a major product of this
project and the reason for the stage boundary. It is a pre-requisite of
stage 3. Ref A16.2.
This is not a plan prerequisite for stage 3. As a product of stage 2 this
should have been quality-checked and signed-off, but work can
commence on stage 3 even if this product is incomplete. Ref A16.2.
This is not a prerequisite of the stage. The stage can commence
without the engineering staff, but may be delayed if they are not
available when required. This may be identified as a risk. Ref A16.2.
This is confirmed during stage 2. The results of this check are not a
prerequisite for stage 3. Work can commence without this. Ref A16.2.

This is a deliverable that is not created within the scope of this project,
but may influence the plan, it is therefore an external dependency. Ref
A16.2.
This is not required for the stage 3 to start. This is a deliverable that is
not created within the scope of this project, but may influence the plan.
Ref A16.2.
The logo is required during stage 3, but is not created within the scope
of this project. Ref A16.2.
This is within the scope of this project and as a product of stage 2 this
should have been quality checked and signed-off. Ref 16.4.2 / A16.2.
Whilst the company logo is an external dependency, the composition of
the label design should be shown in the relevant Product Description.
Ref A17.2.

227

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

3a

correct

3b

incorrect

3c

incorrect

3d

incorrect

3e

correct

Question

Part

Answer

4a

correct

4b

correct

4c

incorrect

4d

incorrect

4e

incorrect

Question

Part

Answer

5a

correct

5b

incorrect

5c

incorrect

5d

correct

5e

incorrect

2009 ILX Group plc

The label designs are to be delivered during this stage, however, the
results of the competition are unknown and cannot be qualified. This is
therefore an assumption. Ref A16.2.
The label designs are within the scope of this project. If external
resources are required to create a product, the product does not then
become external, it is still within the scope of this project. Ref 7.3.3.2.
The operational staff schedule on which the photographic session is
based is updated weekly. The availability of staff shown in the
photographic session schedule may now be incorrect. Ref A16.2.
This product is produced by an external resource, within the scope of
this project. It is not an external dependency. Ref 7.3.3.2.
Whilst this is a requirement, the composition of the photographs should
be shown in the relevant Product Description. Ref A16.2.

It is the Stage Plan that is updated with actuals throughout the stage.
Ref 15.4.4. The Project Plan is updated at the end of each stage. Ref
17.4.2.
The Stage Plan covers the products, resources, activities and controls
specific to the stage and is used as a baseline against which to monitor
stage progress. The Highlight Report is a control for the Project Board.
Ref A.16.2
The Highlight Report is a management product. The Product
Descriptions section shows the specialist products of the plan. A16.2.
The frequency at which the stage will be reviewed should be recorded
here. Ref A16.2.
Product Status Account can be requested by the Project Manager at
any time. This is likely to be required to support the Highlight Report.
Ref 15.4.5.

The stage budget should cover both the costs of products and the
resources and management required to deliver them. A16.1.
The budgets section of the Stage Plan covers time and cost, including
provisions for risks and changes. Ref 16.2.
The budgets section of the Stage Plan covers time and cost, including
provisions for risks and changes. Ref A16.2.
The budgets section of the Stage Plan covers time and cost, including
provisions for risks and changes. Ref A16.2.
Time, cost and scope tolerances for the level of plan should be shown
under a separate heading of Tolerances. Ref A16.2.

228

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

2
Question 7 Progress Theme
Question

Part

Answer

1a

incorrect

1b

correct

1c

incorrect

1d

incorrect

Question

Part

Answer

2a

incorrect

2b

correct

2c

incorrect

2d

incorrect

Question

Part

There is a positive tolerance of 1 week which can be allocated to any of


the stages, as appropriate. Ref 10.3.1.2.
Tolerance is allocated based on the level of risk and confidence of
estimates for any given stage. All project tolerance can be allocated to
a single stage, but the risk of doing so must be assessed. Ref 10.3.1.2.
The project tolerance is approved by corporate/programme
management. This cannot be affected by early completion of stages or
Work Packages. Ref 10.3.1.1.
If a project has +1 week tolerance (e.g. its target completion date is 4
February, but 11 February would be acceptable), it doesn't matter how
much extra resource is used. The target date for the project and the
allowable deviation does not change. Ref 15.4.8

Tolerances stated in the Project Plan can be changed through formal


change control and approval of corporate/programme management.
Ref 10.3.4.
Tolerances stated in the Project Plan can be changed through formal
change control and approval of corporate/programme management.
Ref 10.3.4.
Where tolerance is forecast to be exceeded, the exception procedure is
followed and an Exception Plan created to replace the Project Plan. Ref
10.3.4.
Exception situations are dealt with as they occur and not left until the
end of the stage. An exception assessment would be scheduled. Ref.
10.3.4.

Answer

3a

correct

A Product Description should be baselined when the plan containing


the creation of that product is baselined. If the product is later changed,
the Product Description must also pass through change control. Ref
7.3.3.3

3b

incorrect

The project is not forecast to exceed tolerance. Ref 10.3.4.

3c

incorrect

3d

incorrect

2009 ILX Group plc

Any change to a baselined product should first pass through change


control. Ref 9.3.2
Checkpoint Reports are created by the Team Manager, not the Project
Manager. Ref 10.3.3.4.

229

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question

Part

Answer

4a

incorrect

If a product has not been delivered to agreed timescales as a result of


rework, the stage should not be delayed, the rework should be planned
into the next stage. Ref 17.4.4.

4b

incorrect

There is no indication that the stage is forecast to exceed tolerance.


Ref 10.3.4.

4c

correct

By checking the target sign-off date the Project Manager will know if
there is an actual delay or whether the Marketing department has
exceeded the time allocated for follow-up actions. Ref 17.4.4 / 10.3.3.2.

4d

incorrect

No products should be baselined until they are signed-off. Ref 9.3.2.

Question

Part

Answer

5a

incorrect

5b

incorrect

5c

incorrect

5d

correct

Question

Part

Answer

6a

incorrect

6b

incorrect

6c

incorrect

6d

correct

2009 ILX Group plc

There is no indication that a further project has been agreed and the
production of a project mandate is not within the scope of the Calendar
project.
This is not an expected benefit of this project and would not therefore
appear in the Benefits Review Plan. Also, the Benefits Review Plan is
updated at the end of each stage, not just the end of the project. Ref
A1.
Exception Reports provide information to the Project Board when
tolerance is forecast to be/or has been exceeded. Ref 10.3.4.
The Lessons Log captures lessons learned during the project that can
usefully be applied to other projects. Notes should be made of any
good and bad experiences in the use of the management and specialist
products and tools as they occur. Ref 10.3.3.3.

Checkpoint Reports are provided to the Project Manager, not the


Executive. Also, an issue should be raised to the Project Manager if
tolerance is forecast to be exceeded. Ref 10.3.3.4. / 10.3.4.
Team members do not have the authority to change a Stage Plan. If a
product is late, the Project Manager may plan the remaining work into
the next stage and amend the Work Package accordingly. Ref 10.3.3.1.
The Team Manager should raise this as an issue. If the Project
Manager determines it is a project risk, the Project Manager should
record it in the Risk Register. Ref 10.3.3.4.
All problems, questions and queries should be raised as an issue. Ref
10.3.4.

230

PRINCE2 Practitioner Resource Book

Question

Part

2009 ILX Group plc

Practitioner Exam Questions

2
Assertion

False - Management stages are


determined primarily by the level of
risk, major decision points and
commitment of resources. The label
design competition does not justify this
level of control. Ref 10.3.2.1.
True - It may be cheaper to produce
black and white photographs, rather
than full colour, thus reducing quality
but saving cost. Ref 15.4.8.
True - Stage boundaries should be
scheduled around key decision points
for the Project Board. Ref 10.3.2.1.

False - There is +1 week project


tolerance, indicating the project can
complete one week later than planned,
NOT two, and still remain within
tolerance.
False - The Project Manager should
first escalate exception situations to
the Project Board. They may then
need to escalate to corporate
management. Ref 10.3.1.1.
True - The projected costs will
influence the Project Board decision to
proceed with stage 3. All Project Board
decisions are made during the
Directing a Project process. Ref
10.3.1.2.

Reason

False - The Project Board can make a


decision whenever it needs to do so. Ref
13.4.4.

False - The use of one tolerance to


resolve the issues with another tolerance
will depend on the objectives of the
project. If quality is the focus then this will
not be the first to go.
True - The production cost forecast
provides a key decision point for the
Project Board whether to continue with the
project. This reason explains the
assertion, therefore the answer is A. Ref
10.3.2.
False - Negative project time tolerance
does NOT indicate the latest permissible
date, it indicates the earliest acceptable
completion date, before exceeding
tolerance. Ref 10.3.4.
True - Project tolerance is set by corporate
or programme management. Any forecast
to exceed this must be escalated
accordingly. Ref 10.3.1.1.
False - Products are reviewed and
approved by nominated parties as and
when they are completed, not at the end
of each stage. Ref 16.4.2.

231

PRINCE2 Practitioner Resource Book

Question 8 Change Theme

Question

Part

Answer

Question

Part

Answer

2009 ILX Group plc

Practitioner Exam Questions

The Plan is approved, this includes the PD for the photographs. This
requirement was not included within the original composition of the
photographs, it is therefore a request for change. Ref. Tab 9.1
May tells us this has not yet happened, and is therefore a concern at
this time. A problem or concern is any other issue (not an Offspecification or an RFC) that the Project Manager needs to resolve or
escalate. Ref Table 9.1.
The list of customers has been approved. Once approved a product
should not be changed without an authorized request for change. Ref
Table 9.1.
There is not a problem with the schedule, this is not off-specification.
There is an issue with the performance of a team member. This is a
problem that needs to be addressed by the Project Manager. Ref Table
9.1.
The chosen label design is off-specification because the product does
not contain the correct data, as specified. Ref Table 9.1.
The probability of this risk is 100%. This is neither a request for change
nor an off-specification. It is therefore a problem. A problem or concern
that the Project Manager needs to resolve or escalate. Ref Table 9.1.

Maintaining a record of all copies issued will provide a list of who has
been issued products and which versions they have. Ref 9.3.2.
The recall of superseded versions from all copyholders would ensure
that only the correct products are in circulation. Ref 9.3.2.
The Record of links between version and the Issue Report that caused
its change will provide an audit between each version of a product and
a reference to further information regarding the change. Ref A5.2
The Retention of all master copies ensures that the original is
protected, traceable and always available. Ref 9.3.2.
The Product Status Account tracks products through their design,
development, review and approval, providing a summary of product
status. Ref 9.3.1.3
Maintaining a record of relationships between configuration items
ensures that no product is changed without being able to check for
possible impacts on related products. Ref 9.3.1.2.

232

PRINCE2 Practitioner Resource Book

Practitioner Exam Questions

Question 9 Directing a Project, Managing a Stage Boundary & Closing a


2
Project Processes

Question

Part

Answer

2009 ILX Group plc

Work is not simply abandoned. The means for recovering products that
have been completed or are in progress is agreed. Ref 18.4.2
Nothing can be done to resolve this now, but future projects may learn
from this experience. A review of what went well, what went badly and
any recommendations for corporate/programme management
consideration are recorded in the Lessons Report during the Evaluate
the Project activity. Ref 18.4.4
The Project Board advises those who have provided the support
infrastructure and resources for the project that these can now be
withdrawn. This should indicate a closing date for costs being charged
to the project. (13.4.5/18.4.5)
An End Project Report is created during the Evaluate the Project
activity to review how the project performed against the version of the
Project Initiation Documentation used to authorize the project. A review
of the project objectives are recorded in the End Project Report. Ref
18.4.4
When closing a project prematurely the Project Manager must ensure
that work in progress is not simply abandoned. The project should
salvage anything of value created to date. Ref 18.4.2
Future projects may learn from this experience. A review of what went
well, what went badly and any recommendations for
corporate/programme management consideration are recorded in the
Lessons Report during the Evaluate the Project activity. Ref 18.4.4

233

PRINCE2 Practitioner Resource Book

Question

Part

2009 ILX Group plc

Practitioner Exam Questions

2
Assertion

False - Countering the decline in


orders is a positive consequence
(benefit) of this project that cannot be
measured until 12 months after the
project has closed.
False - The Acceptance Method in the
PPD will state the means by which the
acceptance will be confirmed. This
could simply be done by confirming all
the products have been approved.
False - The Project Scenario explains
that the prepared calendar pack must
be ready by 30 November, but there is
also a time tolerance of +1 week.

True - The final management stage of


a PRINCE2 project should include the
products of project closure. The
Closing a Project process takes place
within the final management stage. Ref
11.2.4.
False - Whilst handover of
responsibility for the products is
necessary during the Closing a Project
process, this contract is not in the
scope of this project. The product
should be handed over to the
Marketing department.
False - The Closing a Project process
should be followed at the end of stage
3, rather than the Managing a Stage
Boundary process, as this is the final
stage. Ref 17.2 / 18.3

Reason

False - The Benefits Review Plan is


created in the Initiating A Project process.
Ref 14.4.7. It is reviewed and may be
updated at the end of each stage and
during the Closing a Project process. Ref
18.4.3.
True - The PPD contains the Acceptance
Criteria of the Project Product and the
standards and processes that will need to
be applied to achieve this. Ref A21.1 /
18.4.1.
True - This report is produced by the
Project Manager towards the end of the
project, during the Closing a Project
process, and is used by the Project Board
to evaluate the project and authorize
closure. Ref A8.1.
True - The Closing a Project process
takes place towards the end of the final
management stage. Closure is not a
stage, it is a process. This is the reason
for the assertion. The answer is A. Ref
18.3.
False - Where a product requires a lot of
potentially expensive support and
maintenance, the Project Manager should
ensure that a suitable service agreement
or contract is in place. Ref 18.4.3.

True - At the end of each stage the Project


Manager should update the Project
Initiation Documentation (e.g. the
Business Case, Project Plan, project
approach, strategies, project management
team structure and role descriptions). Ref
17.2.

234

You might also like