Generator Sync
Generator Sync
GE Drive Systems
AUTO: the system will automatically match voltage and speed, and then close
the breaker at the appropriate time to hit top dead center on the synchroscope.
All three of the following functions must agree for this
closure to occur: 25X -- synch check relay
25 -- auto synch relay
25P -- synch sequencing
AUTO mode has a sub-mode, which is defined as "SYNCH MONITOR. It is
selectable, ON and OFF, from the GENSYNCH display on the CRT. When in this
mode, all of the automatic calculations and control functions, including voltage
and speed matching, are performed; however the breaker closure is inhibited. This
sub-mode of AUTO synch allows the operator to observe where the control
would close the breaker when the SYNCH MONITOR is switched to OFF. In
other words the SYNCH MONITOR selection inhibits the actual breaker closure,
allowing for observations on the performance of the system.
FUNCTIONS:
(a) Dead bus, generator voltage within limits , bus voltage is dead;
- - manual breaker closure, optional.
- - auto breaker closure, optional.
(b) speed matching with dual rates (fast and slow , based upon error,
to eliminate overshoot).
(c) voltage matching with dual rates (fast and slow via pulse width , based upon
error, to eliminate overshoot
(d) auto synch permissive include the following:
- under/over- voltage- for Gen;
- under/over voltage f o r Bus;
- under/over freq for Gen;
- under/over freq for Bus;
- difference voltage;
(e) breaker closure includes the following relay functions; their characteristics are
described elsewhere in this writeup:
25P -- synch permissive, i.e. complete sequence,
etc.
25X -- synch check, i.e. allowable window,
25 --auto synchronizing, precision synch.
(f) self adaptive adjustment of the breaker delay
constants, one for each breaker, up to limits; if the
limits are reached, a diagnostic alarm will be given.
4 - SYNCH CHECK (25X):
(a) functionally it is equivalent to the GXS check relay.
-2-
GE Drive Systems
(b) this function is performed based upon phase lock loop techniques in the
three controllers (R,S,T). It has a high degree of tolerance to noise and signal
distortion;
(c) it performs limit checks against adjustable constants (with appropriate security)
as follows:
-under voltage for Gen;
-under voltage for Bus;
-voltage error;
-frequency error (slip), max value of 0.33 hz,
typically set to 0.27 hz;
-phase error , max value of 30 degrees, typically set to 10 degrees;
(d) Arming logic to enable function;
(e) Bypass logic to provide for dead bus closure.
(f) A typical setting would provide a synch window as follows:
SLIP
+0.27 hz
PHASE
+10 deg
-10
-0.27 hz
5 - AUTOSYNCH (25) :
(a) This function is performed based upon zero voltage crossing techniques
on the three Protection modules ( X , Y , Z ).
It uses the same proven algorithms that were used on the Mark IV system,
with breaker delay time defined by two adjustable constants with logic selection
between the two values ( for two breaker applications) ;
(b) The calculations include phase, slip, acceleration, and anticipated time lead
to compensate for the breaker delay.
(c) Arming logic to enable the function, based upon system sequencing given in
the system documentation;
(d) Bypass logic to provide for deadbus or manual closure.
(e) Provides self-adaptive correction to the breaker close time up to certain limits;
if limit is reached, a diagnostic alarm is given;
-3-
GE Drive Systems
(f)
Gen Lag
The projected window is based upon the current phase, the current slip, and
the current acceleration. In addition, the Generator must currently be lagging
and have been lagging for the last 10 consecutive cycles; when the "trigger is
pulled , it will stay true for a minimum of 12 cycles to ensure that the
Breaker has adequate time to close.
(g) it will not allow the breaker to close with negative slip ; speed matching will
typically aim at something around +0.12 hz slip ( 8 second scope). The
synchronizing will be fast and may go before this speed is reached.
6. SYNCHRONIZATION DISPLAY:
There is a special CRT display to monitor and control generator synchronization.
It will include a set of critical system parameters common to all displays, as well
as display or provide easy access to the following:
(a) Dynamic Parameters:
Voltages:
Gen, Bus, Difference
Frequencies: Gen, Bus, Slip (difference)
Phase:
Diff angle, degrees
(b) Status Indication:
Mode: synch OFF, MANUAL, AUTO;
SYNCH Monitor: OFF, ON
Dead Bus;
Breaker: open/close;
Second Breaker if applicable: open/close;
Synch Permissive, L25P;
Auto Synch enabled;
Speed adjust, raise/lower;
Voltage adjust, raise/lower;
-4-
GE Drive Systems
To be illustrated graphically.
GE Drive Systems
9.
CONTACT RATING:
The breaker closing output contact is rated to make and carry 10 amperes
at125 VDC. However it is only rated to interrupt 0.5 amperes at 125 VDC and
it is therefore a requirement to interrupt the breaker close coil with a series NC
auxiliary contact of the breaker itself.
TM Drummond
Jan 9, 1992
-6-
GE Drive Systems
OMAR ZAMBRANO
POWER SYSTEMS ENGINEER
CARTER &CRAWLEY
&
MOHAMMED SALEH
SR. SYSTEMS ENGINEER
GE DRIVE SYSTEMS
OCTOBER, 1991
SUMMARY
This guide represents the protection options most commonly used for GE
gas turbines/stag generators. The guide is primarily concerned with the application of
relays and with the nomenclature used to represent them on the one-line diagrams.
GENERAL NOTES
1.
The basic generator control panel is 36" x 36" x 90". Adding options has
a tendency to fill up the spare space in this panel. If too many optional
relays are included one generator control panel will not be sufficient to
mount all relays. Options 4 breaker failure relays is especially prone to
this problem due to the presence of several Large relays.
2.
Those relays provided with a power supply failure alarm contact will have
that contact wired out to terminal boards points for connection to a
common alarm on the turbine control panel.
3.
The current state of art for the turbine control panel is the Mark V TCP.
The following write up is written with the Mark V in mind.
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
16.0
17.0
18.0
19.0
20.0
21.0
22.0
23.0
24.0
25.0
REFERENCES
1.0
The timer (21Y), which is used, is 12SAM206A1A.It has two timing units and
three targets. The time delay range is 0.03 - 99.0 seconds.
FIGURE 1.1 illustrates the one line details for this option when
using CEB relays. Figure 1.2 illustrates the one-line details for
this option when using a SLY relay.
2.0
At levels between 1.10 and 1.18 p.u., the inverse time characteristic curve of
the relay is utilized.
1
Note:
1.0 pu Volts per Hertz on typical 13.8KV 60HZ system with 14.4KV/120
Volts PTs corresponds to 13.8KV x (120) / 14.4KV / 60HZ -1.9 volts/hertz.
i.e. pu range is .95 to 1.3 pu volts per hertz on this system.
SYS
3.0
Under voltage conditions can be present in a system due to faults to ground, sudden
energization of a considerable load onto a loaded system, primary and backup regulator
failure, and when running up or coasting to a stop.
HGA relays (27B-1, 2) are used with the turbine panel synchronizing scheme to provide
additional inputs to help determine whether the generator can be synchronized to a live
or dead station bus. The turbine panel logic alarms when under voltage conditions are
present after the breaker has closed.
If additional under voltage protection is desired, the relay commonly used is
12IAV54E1A, which has an adjustable dropout, range of 55.0 - 140.0 volts. The IEEE
function number is 27 [1]. Figure 3.1 shows the application to detect station bus under
voltage conditions.
4.0
current flow (0.5 - 5.0 AMPS) preset for a default value o f 100 msec and 0.5 amps.
Under normal conditions as soon as the generator main relaying see a fault, the
generator breaker should trip. To initiate the breaker failure backup cycle, an aux NGA
relay is added in parallel with the breaker trip coil as shown in figure 4.2. If the generator
breaker remains closed and/or the (configurable) level current detectors sense a current,
then theSBC23 r e l a y starts timing. At the end of that time period the SBC23 operates
a HEA lockout relay (6 N.O. and 8 N.C. contacts) 86BF. 86BF trips the turbine and all
customer associated breakers. Figure 4.3 shows a logic diagram, which explains the
SBC23 operation.
In both schemes, the aux NGA (94BFI) relay will stay picked up until the fault is cleared
and the main relays are reset. The four current detectors in the SBC23 relay should be
set for 67% or less than the minimum fault current for which the breaker failure
protection must operate. It should be recognized that the function of the current detector
is to establish whether or not current is flowing in the associated circuit breaker. In this
sense, the most sensitive setting is desirable.
See also section 6.0
5.0
6. 0
This protection scheme is intended for use with vacuum circuit breakers such as
furnished in the POWER/VAC metalclad switchgear. The relay commonly used
on this option is a 125VC, which is designed to detect current flow due to
inadequate vacuum and subsequent insulation breakdown in the circuit breaker.
When the breaker opens (either manually or by relay action) and current
continues to conduct through the vacuum bottle(s), zero sequence current will
flow through the residual of Y connected current transformers above the breaker
as shown in figure 6.1. An 'A' contact of the circuit breaker is wired in parallel with
the input of the SVC relay for proper operation. The relay operates when the
breaker opens and zero sequence currents above the pickup level exist longer
than the normal clearing time of the breaker. The relay picks up at a current
value greater than 150 milliamps RMS.
The IEEE device function number for an AC over current relay is 51 [1].
7.0
10
8.0
A widely used option is an extra signal from all tripping relays to the sequence of
events recorder. The current input (1.0 Amps.) trip relay commonly used is an EMAX CTX-2 as shown in figure 8.1. The relay coil is rated 10 amps DC
continuous:
The CTX -2 Contact Time Extender provides a long (1-3 second) output contact
closure for an instantaneous (greater than 2 msec) input current. The output
contact closes within 5 milliseconds after the input. The output contacts are rated
to withstand 125 VDC. , 0.5 Amp resistive; therefore, the CTX-2 aux relay cannot
be used in a trip function.
If the main relay function is not to trip a lockout relay, but an auxiliary relay (i.e.
HFA. NGA or AR type) an extra resistors added to the circuit in order to pull
enough current (more than 1 Amp.) to trigger the CTX-2 relay as shown in figure
8.2.
11
9.0
12
10.0
This protection scheme is designed to protect the system (station bus) from faults
to ground. The synchronous generator is connected through a breaker to a stepup transformer. The low voltage side of this transformer is usually connected in a
delta configuration to the station bus at 13.8 KV. If one phase of the system
should connect to ground, virtually no fault current would flow. However voltage
reference in the delta connection will be fixed at the ground fault location thus
causing the voltage vectors to be shifted. One set of PT's connected in a Wye Broken Delta configuration, in conjunction with an overvoltage 12IFV51DD2A
relay, are used to detect such a fault. The voltage across the open delta
secondary under normal non fault conditions is approximately zero while under
ground fault conditions it can be as high as three times the line to ground voltage.
The relay is rated 208 VAC continuous and pickup is adjustable between 14.5 65.0 volts. The function device nomenclature is 59BN [1].
13
The "Norm" for this option is to change the bus PT'S from 2 PT'S open delta to
three PT's connected Y-Y. The normal metering and relaying are connected to
the secondary of the Y and a set of auxiliary PT's are supplied and mounted in
the generator control panel in conjunction with the 59BN relay as shown in figure
10.1. As required, an additional single phase AUX PT is added in the generator
control panel for synchronizing circuit isolation.
A 60 ohm resistor is placed on the secondary of broken delta to keep ferroresonance down.
14
11.0
Each lockout tripping circuit is fused independently in the generator control panel.
If the fuse of a particular tripping bus is blown, the associated protective relays
operate but cannot trip the lockout relay.
15
12.0
OUT-OF-STEP PROTECTION
Generator per unit reactances have steadily increased over the years,
and inertia constants have decreased as machine ratings have increased. This,
in turn, has reduced critical clearing times and increased the need for out-of-step
relaying for modern generators. Viewed from the terminals of a large modern
machine, the OHMS will, in general, fall within the machine or within the unit
transformer when the machine is out of step with the system.
This protection scheme is designed to isolate the machine from the system after
swings from which the synchronous generator cannot recover.
Loss of excitation relay (40) provides a measure of out-of-step protection and will
operate if the swing OHMS fall inside the relay characteristic circle. On the other
hand, if the swing is stable (the generator recovers from it) and falls inside the
relay circle, it is desirable that relay 40 does not operate.
If swing OHMS pass through the unit transformer, out of step detection may not
be possible with either a loss of excitation or an impedance distance relay. Thus,
it is advisable t o add angle impedance relaying at the terminals of the machine
to detect out-of-step conditions when the swing locus passes through the
machine or step-up transformer,
16
The CEX- GSY relays combination utilizes an impedance measuring unit and
logic circuitry to evaluate the progressive change in impedance as would occur
during a loss of synchronism and to initiate tripping when the angle between
generator and system voltages is 90 degrees or less. Switching at this angle (90
degrees or less) is generally recommended in order to minimize the duty on the
circuit breaker. When properly applied this scheme is capable of initiating tripping
during the first half slip cycle of a loss of synchronism condition. Since this
condition is essentially a balanced three phase phenomenon, the relay units
used in this scheme are, and only need be, single phase devices. Figure 12.1
shows the one line diagram details for this scheme.
The OST relay is a microprocessor based positive sequence static distance relay
designed to provide tripping and out-of -step blocking protection. Since the OST
relay measures positive sequence impedance as seen at the relay location, there
is less chance of setting up blocking for non-swing conditions than there is for the
conventional CEX and GSY combinations, which measure phase impedance
only.
17
Typical non-swing conditions that may cause fault impedance to vary greatly are
close-in single-phase-to-ground faults on series compensated lines where gap
flashing and capacitor reinsertion occurs. Figure 12.2 illustrates the suggested
one line diagram connections for this scheme.
If this option is purchased the customer is responsible for calculating and setting
the relay.
18
13.0
19
14.0
Transformer differential relays are highly selective zone protective relays. The
relays used in gas turbine application have both a percentage and a harmonic
restraint coil. The percentage restraint permits accurate discrimination between
internal and external faults at high current. The harmonic restraint enables the
relays to differentiate between normal transformer magnetizing inrush current
and fault current.
This option is commonly used with two sets of CT's which connect three single
phase differential relays 12STD15C3A (2 restraint coils) and a lockout relay
12HEAV36X2 (6 N.O. and 8 N.C. contacts) as shown in figure 14.1. One set of
CT's is usually connected on the high side of the main step up transformer. The
second set of CT's is connected below the generator breaker.
20
For the case where the auxiliary transformers are fed from the high side of the
generator breaker as depicted in fig 14.3. The recommended approach is to
ignore this feed relative to the 87T protective scheme. IE. Don't add a 3rd set of
CTS. The function of the 3rd set of CTS is t o perfectly measure all the currents
leaving and entering the protective zone. For normal conditions the current to the
aux transformers is so small compared to the other currents, it has no effect on
the 87T relay. For faults on the feed to the aux transformers or inside the aux
transformer, currents will be of larger magnitude. Without the 3rd set of CTS this
fault current will register as a significant difference between the current entering
and leaving the protective zones as measured by the existing two sets of CTS
and cause the 87T relay t o operate. The 87T/867 relay inturn trips the 52G and
line breakers isolating the fault: just what we want to happen.
Alternatively, the third set of CTS can be added as shown in Fig 14.3. This has
the effect of preventing the 87T relay from operating for faults on the aux
transformer side of the 3rd set of CTS. This actually is a reduction of protection
but possibly is justifiable depending on the auxiliary transformer low side
configuration and protection scheme.
21
There is also a three restraint single phase optional 87T relay (12STD16C3A)
which can be supplied when a 3 restraint (versus 2 restraint) relay is required. As
this relay is more expensive than the 2 restraint relay, it is not normally
recommended but is shown in Fig. 14.2 for reference only. Separate restraints are
justifiable only to prevent misoperation under transformer current inrush
conditions where significant inrush is seen by each of the CTS present. The
auxiliary transformers being small compared to everything else renders the aux
transformer CTS current insignificant.
22
15.0
This protection scheme is designed to protect the auxiliary transformer and/or the
cranking motor. The auxiliary power protective devices should trip a lockout relay
that in turn clears the fault. A commonly used lockout relay HEA (6 N.O. and 8
N.C.) is shown in figure 15.1.
Three single phase time overcurrent relays 12IFC53B1A with a very inverse time
characteristic are commonly used to protect the station transformers, bus, and
cables against phase overcurrent. These relays have an instantaneous unit
range of 6.0 - 150.0 Amps and an inverse time pickup tap range of 1.0 - 12.0
amperes. The function device number is 50/51AT4-1, 2,3.
The auxiliary power transformer is protected against ground faults and on the
larger transformers (optional) protected with fault pressure relays for oil filled
(over temperature for dry type). Faults to ground are detected by connecting one
single phase time overcurrent relay 12IFC53A1A in the secondary side of the CT
detecting currents flowing to ground as shown in figure 15.1. This relay has a
1.0 - 12.0 ampere tap range. The IEEE faction device number is 51TN-2. The
fault pressure relay installed in the transformer (63PT-2) provides the signal to an
auxiliary target relay 12HAA16B2F (63PT-2X) which trips the aux power
transformer lockout relay ((86T-4) as shown in figure 15.1.
23
Alternatively, if there is already another transformer lockout relay for the main
step up transformer that can be used in lieu o f 86T-4.
An optional set of three single phase time overcurreat relays 12IFC53B1A are
used to protect the auxiliary power transformer against phase overcurrent as
shown in figure 15.1. The function device number is 50/51AT2-1, 2,3.
The cranking -motor transformer similarly is protected against ground faults and
fault pressure conditions. Faults to ground are detected by connecting one single
phase overvoltage relay 12IFV51DD1A in the secondary side of the neutral
grounding transformer as shown in figure 15.1. This l20 volts rated relay has a
pickup range of 9.5 - 42.0 volts. The function device number is 59CM. The fault
pressure relay installed in the transformer (63PT-1) provides the signal to an
auxiliary target relay 12HAA16B2F (63PT-1X) which trips the aux power lockout
relay (86T-4) as shown in figure 15.1.
In the event a fault happens in either the aux power transformer or the cranking
motor. 86T-4 will open the generator breaker and other associated line breakers
as well as send an alarm contact to the turbine control panel.
24
The exact protection scheme recommended is, of course, dependent on the bus
feed arrangement and type for the 2 transformers i.e. as shown, independent
feed, etc.
25
16.0
This protection scheme protects against inadvertent breaker closure while the
unit is at standstill, running up or down in speed.
The turbine control panel standard relay 52GTX provides a form of accidental
energization protection as described in section 24.0.
This protection is felt to be adequate but if additional protection is sought the
following is recommended. IEEE generator protection working group has studied
the different possible techniques to protect against an inadvertent energization.
The frequency supervised is recommended.
One three phase instantaneous overcurrent relay 12CHC12A2A is
supervised by two over frequency 12SFF201A1A relays with built in time
delay on pickup.
26
27
17.0
The IFV relay (59GN) supplied as a standard on gas turbine jobs provides
detection of generator ground faults for approximately 95% of the generator
stator windings. The 5% portion of the winding not protected is that part with the
least electrical stress, i.e. that portion that sees 0 to 5% of the nominal generator
voltage. Experience has proved this protection (59GN) is adequate. However, if
desired one means of detecting faults on the remaining 5% of stator windings
that are near the generator neutral is by monitoring the third harmonic voltage on
the generator neutral. The ABB relay ITE-27GN is an undervoltage relay that is
sensitive to the third harmonic voltage. When a fault occurs near or at the
generator neutral the relay will drop out since the third harmonic voltage will fall
below its pickup point. To prevent false trips from occurring when the generator
excitation is off, 27GN is supervised by a voltage relay (ITE-59G) that is
connected across the generator PTs. This scheme is shown in figure 17.1.
28
18.0
29
As part of the auto tracking DC regulator Option, the generator control panel has
three devices added: 43SR/CS, 90R6/CS and TVM. 43SR/CS allows the
operator to transfer between the two regulators. A contact from this switch is also
sent to the turbine control panel for alarm. Note that if the DC regulator is
selected via the selector switch 43SR/CS, the closing of the generator breaker is
inhibited. (This is done to assure during test, primarily, and during normal
operation that the exciter doesn't overexcite based on the DC Manual Reg on line
setting as the breaker is closed.)
90R6/CS is a switch allowing operator control of the DC regulator. The Transfer
Voltmeter (TVM) is a meter that is driven by a current or voltage from the
excitation system. This current or voltage is proportional to the error between the
AC and DC regulators. By monitoring the TVM the operator can transfer between
DC & AC regulators without causing any system disturbance.
The rotating exciter, brushless, gas turbine excitation is basically the same as the
above described static potential source system. There are some basic minor
deviations.
30
For Example: on black start units that require excitation below 90% speed, the
unit is started on the AC Regulator (which contains a constant volts per hertz
function).
31
19.0
32
33
34
21.0
35
22.0
Ref FIG 22.1 The "norm is to provide synchronization only across the
generator breaker (52G). If the generator and power system became
isolated via the line breaker (52L) opening normal practice is to :
(1) Trip 526
(2) Manually close 52L without need to synchronize
(3) Synchronize across open 52G. Where interruption to the customers load
as shown in Fig. 22.1 cannot be tolerated even momentarily, this normal
practice is unacceptable. Synchronization must be provided across the line
breaker 52L.
The turbine control panel offers the auto line breaker synchronizing as a
standard option. Manual line breaker synchronizing could also be
implemented as a nonstandard option and it is available only by special
customer request.
Note that only the line side PTS are switched. The customer must provide
the phase angle correcting PTS in the event a step up transformer exists
between the line and generator breakers.
36
The turbine control panel monitors the status of both the generator and line
breakers and has the functionality to allow the operator to select the line breaker
to become the breaker being synchronized. It will attempt to synchronize the line
breaker only when the generator breaker is closed and the line breaker is open.
To implement the manual line breaker synchronizing the operator needs to be
capable of closing the line breaker from the generator control panel; therefore, an
extra breaker control switch and the respective indicating lights are added in the
generator control panel or alternatively turbine panel display.
Care must be taken to insure ground loops and phase to ground
interconnections do not exist. Phase B of the synchronizing bus PT is tied to
Phase B of the generator PT is the generator control panel. It is also grounded
at either the GAC or the generator control panel. The customer must ensure
the synchronizing PT signal supplied is isolated from ground. An isolation PT
can also be supplied in the generator control panel upon request.
37
23.0
On units where the gas turbine exhaust gases are used for a process it may not
be desirable to shut down the turbine for all those electrical faults that are
traditionally turbine shutdowns. Two lockout relays are usually supplied on this
option as shown in figure 23.1, one for non turbine shutdowns and one for faults
where the turbine must be shutdown.
Lockout 86G-1 trips the generator breaker, the turbine, and the excitation
system. This lockout is tripped by either one of the two functions 87G or 59GN.
The reasoning behind this is that if a differential or stator ground fault occurs the
structural integrity of the generator may have been compromised and continued
operation will potentially lead to more devastating results.
The second lockout relay 86G-2 trips the generator breaker and excitation,
and alarms at the turbine control panel. The turbine is left running at full speed no
load to feed the process. This lockout is tripped by either 40, 51V, 59EX or other
electrical fault monitoring relays.
The turbine control panel logic monitors this lockout. When the lockout is reset
the turbine controller logic is configured to re-initiate electrical operation of the
turbine generator set. (i.e. flash the field, set up excitation regulators, etc.).
38
24.0
The first electrical sequence initiated by the turbine control panel is flashing.
(Field flashing is connecting an external DC source to the generator field winding
temporarily to build up DC field winding current). Field flashing is initiated by the
turbine control panel relay 41FX, which is dependent on the speed relay 14HF.
Field flashing is activated at 95% speed for 15 seconds on a standard unit. On a
black start option unit flashing takes place at 50% speed for 15 seconds. At the
end of the 15 seconds of field flashing the excitation power supply feed is
transferred from a house source to the unit PPT via transfer relay 83VR-1X.
Provided the unit is at operating speed (complete sequence) the turbine
control panel initiates excitation DC to AC regulator transfer via relay 83SrX at
this time.
39
A short time later auto synchronizing is initiated in the turbine control panel. Auto
synchronizing is initiated if the following permissive are met/received:
The above assumes latest state of the art Mark V turbine control panel.
40
Immediately upon the generator breaker closing the turbine panel acts to raise the load
set point to assure some positive flow of power to prevent the inadvertent operation of
the reverse power relay. When the operator gives the unit a shutdown signal, the turbine
control panel will proceed to reduce the Watt and var loads to zero. Should the operator
interfere by activating the excitation manual raise/lower hand switch, the turbine control
panel will stop adjusting vars. The turbine control panel senses this reverse power via
transducer 96CG-1 and opens 52G once the watts reach a certain negative value
(Software constant). The reverse power (32) relay in the GCP serves as a less sensitive
backup.
As a backup, should the turbine controller load counter reach minimum and 52G has not
opened, the turbine controller will open the breaker via relay 52GTX. This relay is also
kept energized at speeds below 95%, thus acting as a simple accidental energization
protection.
The excitation system AC regulator counter is preset when the generator breaker is
open and speed is below 14HF via relay 90RB, which picks up 94Z-1 and 94Z-2 in the
excitation system.
41
25.0
REFERENCES
[1].
[2].
[3].
42