Specialist Services: Heavy Oil Production Facility at Umm Niqa (15049) CONTRACT NO. 15052398

The document provides instructions for revising structural drawings. It notes to remove certain items from the drawings including shackle sizes, notes, and dimensions. It also provides instructions to use the actual beam dimensions and check lifting centers. Dimensioning and numbering conventions for the drawings are specified.

Uploaded by

Naresh Kumar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
245 views

Specialist Services: Heavy Oil Production Facility at Umm Niqa (15049) CONTRACT NO. 15052398

The document provides instructions for revising structural drawings. It notes to remove certain items from the drawings including shackle sizes, notes, and dimensions. It also provides instructions to use the actual beam dimensions and check lifting centers. Dimensioning and numbering conventions for the drawings are specified.

Uploaded by

Naresh Kumar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

REMOVE

10 80 SHACKLE SIZE
NOTE
410
REMOVE NOTE

member missing
as per 3D model.

20,000 kg
19,000 kg
1000 kg

30,000 kg

check lifting
centers as per
hand markup
provided earlier. It
should be around
5850.

USE 1.use drawing template as


ACTUAL sent by sohail.
BEAM 2. Rev A- Issued for IDC
DIMENSION Rev B- issued for Approval
S Rev 0 - issued for
construction.

3. Skid Drawing number-


PRJ00XXXX-S-D-100
SPECIALIST Sht1/
x
SERVICES
Pipe Support drawing
PRJ00XXXX-S-D-101 Sht1/X
HEAVY OIL PRODUCTION FACILITY AT UMM NIQA (15049)
CONTRACT NO. 15052398
Grating Layout drawing
anchor bolt PRJ00XXXX-S-D-102 Sht1/X
SKID STRUCTURE BASE FRAME
dimension missing PLAN & ELEVATION
XXXX stands for project