Study On The Optimization of The Bidding Program of The EPC Engineering Project
Study On The Optimization of The Bidding Program of The EPC Engineering Project
Engineering Project
LIU Hongyong, HAN Neng, HAN Xia
Southwest Petroleum University, Chengdu, China, 610500
Abstract This article has provided a detailed analysis of the contractors unbalanced bidding strategies
and the two evaluation methods currently used in project evaluation process in China, including the
method of comprehensive evaluation and the method of winning bid at the lowest price. Likewise, based
on the difference in the time of contractors engaged in the project, contracts, the time of constructions,
and the scope of the owners rights between EPC Engineering and Chinese traditional engineering, the
article has proposed the theory and method of value engineering (VE) at the tendering stage to
contractors, used the life-cycle cost approach and the decision tree method to select the program object,
applied the direct functional assessment approach to calculate the function value coefficient, exercised
the value index method to calculate the function value, and finally selected the projects, which Vi is less
than 1, to optimize.
Keywords: EPC, Bidding, Value Engineering
Currently, the international engineering contracts and awards market is bearing various kinds of contract
models, but is increasingly inclined to use the EPC contract format, namely the
engineering-procurement-construction, to contract and award the large scale engineering projects[1].
First emerged in Japan in 1980s, the EPC program has been favored by many owners after introduced to
America and has gradually expanded its influence in the international engineering contracts and awards
market due to the early determination on the investment amount and construction cycle. In China, there
is also an increasing amount of engineering programs constructing in the way of EPC.
1.1 The contractors bidding strategy under current engineering contract model
Most of contractors take unbalanced bidding strategies. In the way of Chinese traditional engineering
construction model, contractors take responsibilities only for the construction of projects, and the
program was settled on the unit-price (total price=unit price * quantity in the bidding document).
However, in fact, the project quantity was settled on the basis of real quantity. Owners always provide
detailed construction drawings and prospective design reports when bidding. On the basis of existing
materials, the experienced contractor is able to quote in accordance with the Bill of Quantities. Normally,
contractors quote an unbalanced bidding to achieve the goal of cost efficiency, which is, after
determining the total price of the project, adjusting the price of each segment in business tenders of the
tender book according to terms of payment; collecting project funds as soon as possible and minimizing
investment risks without raising the total price. Constructors only take emphasis on lower quotation,
regardless of the connections between program designing, purchasing and construction.
380
bidder equals the sum of each factor score multiplied by different weights, and the owner of the highest
score wins the bidding. However, its difficult to quantize the reputation of contractors.
2) Method of winning bid at the lowest price indicates that the bidding document can satisfy the
substantive requirements of tendering document and be the lowest among all analyzed and judged prices,
but not applying to the condition that the bidding price is lower than the cost of entities. The bidding
price which is the lowest among evaluated prices is not always the lowest one in bidding quotations.
However, it is difficult to define whether the bidding price is lower than the rational price of costs.
Evaluated price is the quantitative indicator represented in currency format and used for measuring the
competitiveness of bidding. Apart from the price factor, designs of construction, quality assurance,
projects duration, previous experiences of contractors and use of new technologies are also considered
comprehensively. At present, EPC programs are mostly evaluated in the method of winning bid at the
lowest price worldwide, which provides the most economic tendering to the owner.
Compared with Chinese traditional model of project contract awards, the EPC model, namely the
engineering-procurement-construction model of award, has several features. They are as follows:
381
representatives take limited responsibilities to the construction of programs. Rights of owner
representative have diminished, and management charging and risks also have decreased respectively.
Likewise, the conflict among each part of projects has been abated as a result of the contractors
management for the whole process (Detailed actions including clearly defining the responsibility of each
party, clarifying rights and obligations of owners, etc.)[5]. Meanwhile, in EPC program, owners only
make requests of scope of projects, technical standards and requirements instead of directly engaging in
the project.
On account of conventions and characteristics of international EPC program evaluation, Chinese
contractors who are familiar with unit-price contracts valuation need to alter the tendering strategy
correspondingly when bidding for the program.
The biggest characteristic for EPC program is the owners control of all the designing, purchasing and
building stages, shortening the duration of projects and assuring qualities of project Thus the cost
control of projects not only means the cost reduction, and the value engineering needs to be applied for
optimizing the tender strategy when bidding.
V, F and C, we have many choices on enhancing the value of functions. According to the PRC National
Standard GB8223-87: Value Engineering- General Terms and Work Program, the program has been
divided into four stages: preparation, analysis, innovation and implementation and twelve procedures,
including object selection, Value Engineering team building, work planning, information collection,
function system analyzing, function valuation, design innovation, strategy valuation and proposal
compiling, etc[6].
382
Engineering by using the life-cycle cost approach and the decision tree method.
Construcion
Design
structure technique
selection
Project
project life cycle Completed
Detailed procedures are shown in figure 1: In the way of life-cycle approach, EPC program progresses
in four stages, namely designing, purchasing, building and preoperation, and these stages are combined
together in logical relationship by the decision tree method. Contractors hire experienced engineers and
value analysts to analyze every stage on the decision tree and choose the factor which can effectively
smooth the construction process and maximize the profit.
3.2.3 Functional Analysis
Functional analysis, a key factor of Value Engineering, includes function definition, function
classification and function valuation.
1) Function definition and classification could be realized directly through FAST (Function Analysis
System Technique). As it is shown in figure 2, by using FAST, function definition, classification and
subdivision could be realized to operate basic and supplementary functions. In order to seek the
alternation, costs of each function are above the standards in the figure.
independent
HOW function WHY
x.xx
lowest lower lowest
cost function function
scope of optimization
Figure 2 The FAST
2) Function Valuation
383
It usually lasts three to four weeks from the issue of invitation for bids of Chinese EPC program till the
deadline of bidding. Compiling technical suggestion letters and business proposal in short times, taking
use of the 8-day or 5-day value researching models and adopting complicated function analysis and
evaluation, effectiveness could not be satisfied by optimization the tendering strategy. So the 3-day
value researching model to optimize the EPC program tendering strategy has been applied widely in
China, and contractors choose internal experienced and professional engineers and external experts who
are full of EPC program experiences to grade the program and calculate Function Coefficient by using
direct functional assessment approach. In chart 1, the highest score is 3 and the lowest is 1.
Evaluation
Persons Function value
Function A B C D score
coefficient
F1 1 2 2 1 1.5 0.18
F2 3 2 3 3 2.75 0.32
F3 2 1 2 2 2.25 0.26
F4 2 2 2 2 2 0.24
4 Conclusion
Compared with traditional Chinese construction projects, EPC projects are different in many aspects,
such as construction management models, contracts management and the role of each party engaged in
the project. Currently, the majority of EPC projects have required that contractors should contract with
money or prepay the money and that the tendering time has been shortened. Chinese engineering
tendering valuation and international convention both apply the method of winning bid at the lowest
price to select contractors. Value management should take emphasis on the research of functions,
especially in the phase of project designing[8].Therefore, using Value Engineering theory, considering the
EPC project tendering proposal based on the whole life cycle, choosing Vi<1 as an alternation, not only
does it optimize the project designing, decrease quotations and give bases to contractors for choosing
customized techniques, bust also diminish financial pressures of contractors.
384
References
[1]. Chen Jianxi. Analysis on Risk Management Based on EPC Projects[J]. Railway Investigation and
Surveying No.2, 2009: 94-97.
[2]. WEI Zhong-xin, GUAN Baihai. Research on the Effect of General Contracting on Construction
Project PeriodTaking the House-building Project as an Example[J]. JOURNAL OF RA
ILWAY ENGINEER ING SOCIETY, No.3, 2009: 96-99.
[3]. Zhou Ren qing. The Problems and Solutions of the EPC General Contract Project Management.
Petroleum and Chemical Construction, 2006(04), vol.28, No.2:10-13.
[4]. CHENG Hu, WU Jiuming. Operation Process and Contract Analysis of a General Contract Project
Item[J]. CONSTRUCTION TECHNOLOGY, 2004(12), Vol.33, No.12:1-3.
[5]. QI Baoku, GUO Liangliang, BAI Shu. The Analysis of Application of EPC in the Engineering
Construction Field in Our Country[J]. Journal of Shenyang Jianzhu University Social Science ,
2009(04),Vol.11, No.2:167-169.
[6]. Zhang Caijiang. Complex Value Engineering Theory and New Application Methods[M]. Beijing:
Science Publisher, 2006.
[7]. Liu Jiuxian. To Apply on Value Engineering in the Investment Control for Project Construction[J].
Value Engineering No.9, 2008: 67-69.
[8]. Zhou Dapeng, Wang Guoqing. To Apply on the Value Engineering in Layout and Design of the
Construction ProjectsBased on the Perspective of Strategy Canvas Analysis[J]. Value
Engineering No.7, 2009:68-71.
385