10 Risk Review Process
10 Risk Review Process
Background
As with many large, public projects, FTA
experienced a significant amount of project cost
overrun
In this environment of overrun risk, planning a cost
budget has been difficult
The risk review process is intended to:
Inform the FTA about the projects risk
General Specific
Total Uncertainty Total Certainty
Uncertainty Uncertainty
Risk Review vs. Risk Assessment
Risk Review
FTA provides a review of the risk and contingency plan
within a Grantees project management plan
This review evaluates the 4 fundamental parts of risk
management, i.e., Identification, Assessment, Response,
Management
Risk Assessment
1 of the 4 parts that quantifies the impact of all risks
FTA treatment of risk assessment depends on the projects
size
Risk Management Process
Identifying risk situations for which outcomes
are likely to vary in amounts that may
significantly affect the projects goals
Assessing the likelihood and magnitude of
such variance
Responding by developing plans for
minimizing hazard and maximizing gain
Managing the execution of those plans
Risk Review Benefits
Schedule
Grantees Review Grantees
Project Project Scope (OP-34) Project
PMP Review Risk Review
Management and Capacity Management
(OP-20) (OP-40)
Plan (OP-32) Plan
(PMP) (PMP)
Estimate
Review
(OP-33)
Grantee
Technical
Capacity
(OP-21)
Schedule
Grantees Review Grantees
Project Project Scope (OP-34) Project
PMP Review Risk Review
Management and Capacity Management
(OP-20) (OP-40)
Plan (OP-32) Plan
(PMP) (PMP)
Estimate
Review
(OP-33)
Requires:
Scope checklist
Cost Estimate Review
E = P*M
Risk Factoring
Identification Assessment
Cost Schedule
Probability Expected Expected
Magnitude Magnitude
(A) Value Value
(B) (C)
SCC Code
Risk event Risk
description Type 3 = high 3 = high 3 = high
Schedule
2 = medium 2 = medium 2 = medium Cost Score
Score
1 = low 1 = low 1 = low
4
Risk Review
Risk assessment by PMOC
after risk identification
workshop with Grantee
Grantee
Technical
Capacity
(OP-21)
Schedule
Grantees Review Grantees
Project Project Scope (OP-34) Project
PMP Review Risk Review
Management and Capacity Management
(OP-20) (OP-40)
Plan (OP-32) Plan
(PMP) (PMP)
Estimate
Review
(OP-33)
50 Systems
70 Vehicles
80 Professional Services
90 Unallocated Contingency
SCC 10 Guideway
2.00
Market Risk, =0.25
1.75
Early, =0.40
1.50
Constr. Risk, =0.70
Mid, =0.15
1.25
Late, =0.15
SCC 10 Guideway
10.04 Guideway: Aerial Structure 51,900 0.00 0.50 0.25 0.70 0.05 2.50
10.11 Track: Ballasted 45,176 0.00 0.50 0.25 0.70 0.05 2.50
20.07 Elevators, escalators 9,248 0.00 0.50 0.25 0.70 0.05 2.50
Conditioned
base estimate, PMOC
in standard SCC adjustments to Adjusted YOE
categories raw YOE estimate Betas
Betasassigned
assigned
estimate without totoBetas
Betasassigned
SCC
SCC assigned
contingency to SCC
Categories
to SCC by
Categories
Categories byby
phase Categories by
phase Risk reduction
phase
phase graph
Cost Risk Assessment
Cost Risk Assessment
Project is forecasted out to each stage of development to identify
potential risk reduction; the results are plotted across the project life-
cycle, as if all mitigation is successful
Cost Risks
Project Project
Conception Completion
Schedule Risk Assessment
Criticality = 37%
Activity Two
8 10 8
Schedule Risk Assessment
3. The duration range is established based on the risk register
and applied to the summarized schedule
MOST
Orig Dur Rem Dur % Comp Early Start Early Finish OPTIMISTIC PESSIMISTIC
LIKELY
Pico/Aliso Station
9815 Segment 2 Utility diversions and duct banks 225 71 68 30NOV05A 10DEC07 65 75 93
9835 Segment 2 1st Street bridge track bed/track 129 129 0 08JAN07A 28FEB08 100 129 149
9819 Segment 2a/b Complete systems installation 221 221 0 11DEC07 14OCT08 199 221 243
Station
980 Pico/Aliso Final design and MTA approvals 118 0 100 30NOV05A 11MAY06A
981 Traffic plan approvals and street closures 61 0 100 15MAY06A 31JUL06A
9830 Peco/Aloso MEP and Str restore and punch list 190 190 0 07NOV07* 29JUL08 180 200 212
Schedule Risk Assessment
4. Range-loaded activities are then simulated
(using Monte Carlo methods) to yield likely
project outcomes
The results are reviewed and rerun as necessary
for schedule integrity
The results may affect the cost analysis
FTA Schedule Risk Assessment
The results indicate the likelihood of meeting the target completion date
Grantee
Technical
Capacity
(OP-21)
Schedule
Grantees Review Grantees
Project Project Scope (OP-34) Project
PMP Review Risk Review
Management and Capacity Management
(OP-20) (OP-40)
Plan (OP-32) Plan
(PMP) (PMP)
Estimate
Review
(OP-33)
Risk response
monitoring
4 Risk Responses (Risk Aversion Order)
1. Avoidance
Pursue a different project or project element
Alternatives Analysis is used here
2. Transfer
By contract or agreement with the performing parties
Major concepts to be considered:
Efficient allocation of risk
Equitable allocation of risk
4 Risk Responses (Risk Aversion Order)
3. Reduce
Modify either the probability (P) or magnitude
(M), or both, reducing the expected value (E) of
the risk
E = P*M
Modify the design or PMP
Protect against theft or damage
Influence the projects environment
4 Risk Responses (Risk Aversion Order)
4. Retain/absorb
Recognize a risk event, but take no action
If it appears to be of minimal consequence
Retain it and protect against it
Where risks are unavoidable
Establish contingencies that can absorb realized risks
Develop a Plan B in case risks become realized
Risk Response Recommendations
30%
25%
20%
15%
10%
5%
0%
PE Phase FD Phase FFGA Award 100% Bid 50% Construction
Cost Contingency
An additional analysis of specific, potential
project risks is conducted to determine how
contingency must be maintained and at what
amounts throughout the project completion
This is called the backward pass method
This analysis identifies points during the
construction period at which certain
minimums of contingency should maintained
to protect the project;
Schedule Contingency
FTA also established criteria for suggested
minimum schedule contingency levels
The targeted amount of schedule contingency,
for the project as a whole, is 20% of the
stripped duration from Final Design through
Construction completion
Schedule Contingency
Target @ Entry
into FD=
30% likely value
Mitigation in
amount of gap
must be available
Grantees
estimate
including
contingency
Risk Management Planning
General process for risk management begins with a written
Risk and Contingency Management Plan (RCMP):
Documentation of the various analyses
Listing of major project risks, their description and the
nature of their consequences
How they are to be handled (by whom, when)
Watch List
A list of secondary and/or residual minor risks that need to be
kept an eye on
Timing for re-examination of the Risk Management portion
of the PMP
RCMP Requirements
Section of the Grantees Project Management Plan (PMP)
Fully updated and active PMP
Highlight specific areas of management focus as identified
through the risk review process
Means for monitoring Grantees progress
Actions to strengthen technical capacity and capability, project
performance, cost and schedule analyses, mitigations of identified
project risks, and others.
Information contained within the RCMP should complement
and not be in conflict with information contained elsewhere
within the PMP or in other FTA guidance documents
RCMP Overview
Topics:
Primary Mitigation, organized by significant
project activities, such as:
Technical Capacity
Project Scoping and Design;
Delivery Methods and Contracting;
Construction Process;
Project Tracking, including:
Cost Estimating, Financing and Financial Management;
and
Project Schedule Management.
RCMP Overview
Insurance:
Professional services, construction phase, wrap-up, or other specialized
insurances purchased for reduction of risk exposure
Contingency Management:
Cost Contingency Management Plan; and
Schedule Contingency Management Plan
Secondary Mitigation:
Establishment of Secondary Mitigation actions and cost targets which
may trigger the implementation of Secondary Mitigation
Risk Management:
Risks management and mitigation monitoring, change identification,
and management controls
Risk Management Planning