This document outlines the phasing plan for the Delhi-Mumbai Industrial Corridor (DMIC) project, which involves constructing two rail corridors - the Western Corridor from Rewari to JNPT and the Eastern Corridor from Khurja to Ludhiana. The corridors will be constructed simultaneously and are planned to be fully operational by 2018-2019. The corridors have been divided into multiple phases, with specific sections targeted for completion between 2011-2019.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views1 page

Home About Us DFCC Project Performance Organisation Tenders Public Notices Careers Vigilance Photogallery

This document outlines the phasing plan for the Delhi-Mumbai Industrial Corridor (DMIC) project, which involves constructing two rail corridors - the Western Corridor from Rewari to JNPT and the Eastern Corridor from Khurja to Ludhiana. The corridors will be constructed simultaneously and are planned to be fully operational by 2018-2019. The corridors have been divided into multiple phases, with specific sections targeted for completion between 2011-2019.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Page 1 of 1

Home | About Us | DFCC Project | Performance | Organisation | Tenders | Public Notices | Careers | Vigilance | Photogallery

Background
Project Phasing
Salient features
Both corridors will be constructed simultaneously. It is envisaged that the corridors will be fully operational over their entire length by
Eastern Corridor
2018-19. The following table indicates the tentative phasing of the project:-
Western Corridor

Project Phasing Western Corridor Year

Project Funding
Phase I Rewari- Vadodara (920 Kms) 2011-2017
Project Status
Phase II Vadodara- JNPT(430Kms) 2012-2018

Phase III Rewari Dadri(140 Kms) 2013-2018

Eastern Corridor

Phase I-APL1 Khurja - Kanpur (343 Kms) 2011-2017

Phase II-APL2 Kanpur - Mughalsarai (390 Kms) 2013-2018

Phase III-APL3 Khurja-Ludhiana (397 Kms) 2014-2019

Phase IV (Funding through PPP) Dankuni - Sonnagar (550 Kms) 2014-2019

Phase Ia ( Funding by Ministry of


Sonnagar - Mugal Sarai (125 Kms) 2010-2016
Railways)

Site Map | RTI| DFCC Mail | News Letter | Important Links | Contact Us | Disclaimer

Designed, developed and hosted by : CRIS

http://dfccil.org/DFCC/Projects/Project%20Phasing 9/29/2013

You might also like