The delay analysis report highlights activities from a target program that are delayed. Several activities for installing mechanical, electrical and plumbing works in the basement levels of Building C are shown in red as delayed, with their actual/forecasted start and finish dates now 8-23 days later than the baseline plan. While some activities in the basement levels are on track, the majority displayed are delayed against the original schedule.

Uploaded by

shijinrajagopal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
308 views

Delay Analysis Report 29-December-2016

The delay analysis report highlights activities from a target program that are delayed. Several activities for installing mechanical, electrical and plumbing works in the basement levels of Building C are shown in red as delayed, with their actual/forecasted start and finish dates now 8-23 days later than the baseline plan. While some activities in the basement levels are on track, the majority displayed are delayed against the original schedule.

Uploaded by

shijinrajagopal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16

VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BuildingC BC 160 0.00% 0.00% 27Nov16 31May17 23Nov16A 1Jun17 1 0 OnTarget
Basement02 97 0.00% 0.00% 27Nov16 19Mar17 27Nov16A 28Mar17 8 56 OnTarget
MEPWorks 83 0.00% 0.00% 27Nov16 2Mar17 27Nov16A 12Mar17 8 70 OnTarget
MEP2ndFixing 52 0.00% 0.00% 27Nov16 25Jan17 27Nov16A 4Feb17 8 101 OnTarget
BCB2MEP1000 BC Basement2 InstallElectricalWiring 10 100.00% 62.00% 27Nov16 7Dec16 27Nov16A 3Jan17 23 119 Delayed
BCB2MEP1010 BC Basement2 InstallLowCurrentWiring 12 100.00% 60.00% 28Nov16 11Dec16 27Nov16A 7Jan17 23 119 Delayed
BCB2MEP1020 BC Basement2 InstallHot&ColdWaterPiping 7 100.00% 86.00% 7Dec16 14Dec16 27Nov16A 10Jan17 23 119 Delayed
BCB2MEP1030 BC Basement2 InstallHVACPipes 10 100.00% 88.00% 7Dec16 18Dec16 27Nov16A 14Jan17 23 119 Delayed
BCB2MEP1040 BC Basement2 InstallDuctsandHangers 10 100.00% 100.00% 11Dec16 21Dec16 27Nov16A 28Dec16A 5 0 OnTarget
BCB2MEP1050 BC Basement2 InstallCableTraysandTrunking 10 100.00% 100.00% 14Dec16 25Dec16 27Nov16A 28Dec16A 2 0 OnTarget
BCB2MEP1060 BC Basement2 InstallLVCables 7 100.00% 0.00% 21Dec16 28Dec16 31Dec16 7Jan17 8 18 Delayed
BCB2MEP1070 BC Basement2 InstallDroppers 12 0.00% 0.00% 10Jan17 23Jan17 19Jan17 1Feb17 8 23 OnTarget
BCB2MEP1080 BC Basement2 MeggeringTest 7 0.00% 0.00% 16Jan17 23Jan17 25Jan17 1Feb17 8 23 OnTarget
BCB2MEP1090 BC Basement2 InstallEarthpit 21 0.00% 0.00% 2Jan17 25Jan17 11Jan17 4Feb17 8 18 OnTarget
MEPFinalFixing 13 0.00% 0.00% 16Feb17 2Mar17 26Feb17 12Mar17 8 18 OnTarget
BCB2MEP2000 BC Basement2 InstallLightFittings 8 0.00% 0.00% 16Feb17 25Feb17 26Feb17 6Mar17 8 18 OnTarget
BCB2MEP2010 BC Basement2 InstallFireCabinets 6 0.00% 0.00% 20Feb17 26Feb17 1Mar17 7Mar17 8 18 OnTarget
BCB2MEP2020 BC Basement2 InstallFireAlarmsandSpeakers 8 0.00% 0.00% 18Feb17 26Feb17 27Feb17 7Mar17 8 18 OnTarget
BCB2MEP2030 BC Basement2 InstallSprinklers 6 0.00% 0.00% 21Feb17 27Feb17 2Mar17 8Mar17 8 18 OnTarget
BCB2MEP2040 BC Basement2 InstallSwitchesandSockets 8 0.00% 0.00% 21Feb17 1Mar17 2Mar17 11Mar17 8 18 OnTarget
BCB2MEP2050 BC Basement2 InstallLowCurrentEquipments 8 0.00% 0.00% 22Feb17 2Mar17 4Mar17 12Mar17 8 18 OnTarget
BCB2MEP2060 BC Basement2 InstallGrillesandDiffussers 8 0.00% 0.00% 22Feb17 2Mar17 4Mar17 12Mar17 8 18 OnTarget
BCB2MEP2070 BC Basement2 InstallPlumpingFinalTittings(FloorDrains,Gratings,F 8 0.00% 0.00% 22Feb17 2Mar17 4Mar17 12Mar17 8 18 OnTarget
Basement01 101 0.00% 0.00% 29Dec16 25Apr17 27Nov16A 28Mar17 24 41 OnTarget
MEPWorks 72 0.00% 0.00% 27Nov16 2Mar17 27Nov16A 12Mar17 8 70 OnTarget
MEP2ndFixing 43 0.00% 0.00% 27Nov16 25Jan17 27Nov16A 4Feb17 8 101 OnTarget
BCB1MEP1000 BC Basement1 InstallElectricalWiring 10 10.00% 68.00% 29Dec16 9Jan17 27Nov16A 3Jan17 6 15 OnTarget
BCB1MEP1010 BC Basement1 InstallLowCurrentWiring 12 0.00% 19.00% 31Dec16 12Jan17 27Nov16A 10Jan17 2 11 OnTarget
BCB1MEP1020 BC Basement1 InstallDrainagepipes 10 0.00% 77.00% 5Jan17 16Jan17 27Nov16A 14Jan17 2 11 OnTarget
BCB1MEP1030 BC Basement1 InstallHot&ColdWaterPiping 7 0.00% 66.00% 12Jan17 19Jan17 27Nov16A 17Jan17 2 11 OnTarget
BCB1MEP1040 BC Basement1 Firefightingpipes 10 0.00% 92.00% 9Jan17 19Jan17 27Nov16A 17Jan17 2 11 OnTarget
BCB1MEP1050 BC Basement1 InstallHVACPipes 10 0.00% 71.00% 12Jan17 23Jan17 27Nov16A 21Jan17 2 11 OnTarget
BCB1MEP1060 BC Basement1 InstallDuctsandHangers 10 0.00% 80.00% 16Jan17 26Jan17 27Nov16A 24Jan17 2 11 OnTarget
BCB1MEP1070 BC Basement1 InstallCableTraysandTrunking 10 0.00% 96.00% 19Jan17 30Jan17 27Nov16A 28Jan17 2 11 OnTarget
BCB1MEP1080 BC Basement1 InstallLVCables 7 0.00% 0.00% 26Jan17 2Feb17 23Jan17 31Jan17 2 11 OnTarget
BCB1MEP1090 BC Basement1 InstallDroppers 12 0.00% 0.00% 4Feb17 16Feb17 31Jan17 14Feb17 2 11 OnTarget
BCB1MEP1100 BC Basement1 MeggeringTest 7 0.00% 0.00% 9Feb17 16Feb17 6Feb17 14Feb17 2 11 OnTarget
MEPFinalfixing 15 0.00% 0.00% 16Feb17 2Mar17 26Feb17 12Mar17 8 18 OnTarget
BCB1MEP2000 BC Basement1 InstallLightFittings 8 0.00% 0.00% 6Mar17 14Mar17 2Mar17 12Mar17 2 11 OnTarget
BCB1MEP2010 BC Basement1 InstallFireCabinets 6 0.00% 0.00% 9Mar17 15Mar17 6Mar17 13Mar17 2 11 OnTarget
BCB1MEP2020 BC Basement1 InstallFireAlarmsandSpeakers 8 0.00% 0.00% 7Mar17 15Mar17 4Mar17 13Mar17 2 11 OnTarget
BCB1MEP2030 BC Basement1 InstallSprinklers 6 0.00% 0.00% 11Mar17 16Mar17 7Mar17 14Mar17 2 11 OnTarget
BCB1MEP2040 BC Basement1 InstallSwitchesandSockets 10 0.00% 0.00% 11Mar17 21Mar17 7Mar17 19Mar17 2 11 OnTarget
BCB1MEP2050 BC Basement1 InstallLowCurrentEquipments 10 0.00% 0.00% 12Mar17 22Mar17 8Mar17 20Mar17 2 11 OnTarget
BCB1MEP2060 BC Basement1 InstallGrillesandDiffussers 8 0.00% 0.00% 14Mar17 22Mar17 11Mar17 20Mar17 2 11 OnTarget
BCB1MEP2070 BC Basement1 InstallPlumpingFinalTittings(FloorDrains,Gratings,F 8 0.00% 0.00% 14Mar17 22Mar17 11Mar17 20Mar17 2 11 OnTarget
Groundfloor 123 0.00% 0.00% 27Nov16 18Apr17 27Nov16A 2May17 11 27 OnTarget
General 33 0.00% 0.00% 27Nov16 3Jan17 27Nov16A 17Jan17 11 117 OnTarget
MEPWorks 18 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BCGFMEP2000 BC GroundFloor InstallWallConduits 18 100.00% 94.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 Delayed
DryArea 69 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 58 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BCGFMEPD1000 BC GroundFloor FloorMEPconduitsforScreed 18 0.00% 15.00% 8Jan17 28Jan17 27Nov16A 11Feb17 11 7 OnTarget
BCGFMEPD1010 BC GroundFloor InstallElectricalWiring 18 61.11% 50.00% 18Dec16 7Jan17 27Nov16A 9Jan17 2 33 Delayed
BCGFMEPD1020 BC GroundFloor InstallLowCurrentWiring 18 44.44% 11.00% 21Dec16 10Jan17 19Dec16A 18Jan17 6 29 Delayed
BCGFMEPD1030 BC GroundFloor InstallHVACPipes 18 27.78% 60.00% 25Dec16 14Jan17 27Nov16A 22Jan17 6 29 OnTarget
BCGFMEPD1040 BC GroundFloor Firefightingpipes 18 27.78% 0.00% 25Dec16 14Jan17 1Jan17 22Jan17 6 29 Delayed
BCGFMEPD1050 BC GroundFloor InstallDuctsandHangers 18 11.11% 15.00% 28Dec16 17Jan17 27Nov16A 25Jan17 6 29 OnTarget
BCGFMEPD1060 BC GroundFloor DBInstallation 10 0.00% 0.00% 18Jan17 29Jan17 25Jan17 6Feb17 6 59 OnTarget
BCGFMEPD1070 BC GroundFloor InstallDroppers 12 0.00% 0.00% 9Feb17 22Feb17 15Mar17 28Mar17 29 22 OnTarget
BCGFMEPD1080 BC GroundFloor MeggeringTest 7 0.00% 0.00% 15Feb17 22Feb17 21Mar17 28Mar17 29 22 OnTarget
Wetarea 73 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 70 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BCGFMEPW1000 BC GroundFloor InstallElectricalWiring 18 11.11% 30.00% 28Dec16 17Jan17 23Dec16A 25Jan17 6 29 OnTarget
BCGFMEPW1010 BC GroundFloor InstallDrainagepipes 18 5.56% 75.00% 29Dec16 18Jan17 27Nov16A 26Jan17 6 29 OnTarget
BCGFMEPW1020 BC GroundFloor InstallHot&ColdWaterPiping 18 0.00% 0.00% 31Dec16 19Jan17 7Jan17 28Jan17 6 29 OnTarget
BCGFMEPW1030 BC GroundFloor InstallHVACPipes 18 0.00% 60.00% 3Jan17 23Jan17 27Nov16A 31Jan17 6 29 OnTarget
BCGFMEPW1040 BC GroundFloor Firefightingpipes 18 0.00% 95.00% 4Jan17 24Jan17 27Nov16A 1Feb17 6 30 OnTarget
BCGFMEPW1050 BC GroundFloor InstallDuctsandHangers 18 0.00% 15.00% 7Jan17 26Jan17 27Nov16A 4Feb17 6 29 OnTarget
BCGFMEPW1060 BC GroundFloor InstallDroppers 12 0.00% 0.00% 6Mar17 19Mar17 19Feb17 4Mar17 13 13 OnTarget
BCGFMEPW1070 BC GroundFloor MeggeringTest 7 0.00% 0.00% 12Mar17 19Mar17 25Feb17 4Mar17 13 13 OnTarget
Corridor/LiftLobby 74 0.00% 0.00% 22Dec16 18Mar17 27Nov16A 1Apr17 11 12 OnTarget
MEPWorks 54 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BCGFMEPCL1000 BC GroundFloor FloorMEPconduitsforScreed 10 0.00% 0.00% 12Feb17 22Feb17 25Feb17 8Mar17 11 12 OnTarget
BCGFMEPCL1010 BC GroundFloor InstallElectricalWiring 18 38.89% 39.00% 22Dec16 11Jan17 17Dec16A 11Jan17 0 13 OnTarget
BCGFMEPCL1030 BC GroundFloor InstallHot&ColdWaterPiping 18 22.22% 23.00% 26Dec16 15Jan17 15Dec16A 15Jan17 0 13 OnTarget
BCGFMEPCL1040 BC GroundFloor Firefightingpipes 18 22.22% 0.00% 26Dec16 15Jan17 31Dec16 19Jan17 4 9 Delayed
BCGFMEPCL1050 BC GroundFloor InstallHVACPipes 18 5.56% 60.00% 29Dec16 18Jan17 27Nov16A 23Jan17 4 9 OnTarget
BCGFMEPCL1060 BC GroundFloor InstallDuctsandHangers 18 0.00% 15.00% 2Jan17 22Jan17 27Nov16A 26Jan17 4 9 OnTarget
BCGFMEPCL1070 BC GroundFloor InstallCableTraysandTrunking 18 0.00% 10.00% 5Jan17 25Jan17 27Nov16A 30Jan17 4 9 OnTarget
BCGFMEPCL1075 BC GroundFloor InstallLowCurrentWiring 18 0.00% 0.00% 9Jan17 29Jan17 14Jan17 2Feb17 4 12 OnTarget
BCGFMEPCL1080 BC GroundFloor InstallLVCables 18 0.00% 0.00% 9Jan17 29Jan17 14Jan17 2Feb17 4 9 OnTarget
BCGFMEPCL1090 BC GroundFloor CorridorHLClearancebyARMAforgridfixing 18 0.00% 0.00% 12Jan17 1Feb17 17Jan17 6Feb17 4 12 OnTarget
BCGFMEPCL1100 BC GroundFloor InstallDroppers 18 0.00% 0.00% 30Jan17 19Feb17 4Feb17 23Feb17 4 9 OnTarget
BCGFMEPCL1110 BC GroundFloor MeggeringTest 18 0.00% 0.00% 30Jan17 19Feb17 4Feb17 23Feb17 4 9 OnTarget
BCGFMEPCL1120 BC GroundFloor CorridorMEPclearanceforBoardclosing 18 0.00% 0.00% 31Jan17 20Feb17 5Feb17 25Feb17 4 9 OnTarget
CommonFinalFinishes 54 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 36 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BCGFMEPF1000 BC GroundFloor InstallLightFittings 14 0.00% 0.00% 11Mar17 26Mar17 28Feb17 15Mar17 9 9 OnTarget
BCGFMEPF1010 BC GroundFloor InstallFireCabinets 14 0.00% 0.00% 12Mar17 27Mar17 1Mar17 16Mar17 9 9 OnTarget
BCGFMEPF1020 BC GroundFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 12Mar17 27Mar17 1Mar17 16Mar17 9 9 OnTarget
BCGFMEPF1030 BC GroundFloor InstallSprinklers 14 0.00% 0.00% 13Mar17 28Mar17 2Mar17 18Mar17 9 9 OnTarget
BCGFMEPF1040 BC GroundFloor InstallSwitchesandSockets 14 0.00% 0.00% 16Mar17 1Apr17 6Mar17 21Mar17 9 9 OnTarget
BCGFMEPF1050 BC GroundFloor InstallLowCurrentEquipments 14 0.00% 0.00% 18Mar17 2Apr17 7Mar17 22Mar17 9 9 OnTarget
BCGFMEPF1060 BC GroundFloor InstallGrillesandDiffussers 14 0.00% 0.00% 18Mar17 2Apr17 7Mar17 22Mar17 9 9 OnTarget
BCGFMEPF1070 BC GroundFloor InstallPlumpingFinalTittings(FloorDrains,Gratings,F 14 0.00% 0.00% 18Mar17 2Apr17 7Mar17 22Mar17 9 9 OnTarget
BCGFMEPF1080 BC GroundFloor InstallKitchenequipments 36 0.00% 0.00% 20Feb17 2Apr17 12Feb17 26Mar17 7 7 OnTarget
FirstFloor 96 0.00% 0.00% 27Nov16 18Mar17 27Nov16A 20Apr17 29 36 OnTarget
DryArea 22 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 7 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC1FMEPD1000 BC 1stFloor DBInstallation 7 100.00% 100.00% 27Nov16 4Dec16 27Nov16A 02Dec16A 2 0 OnTarget
WetArea 27 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 10 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC1FMEPW1000 BC 1stFloor MEPclearanceforBoardclosing 10 100.00% 100.00% 10Dec16 20Dec16 27Nov16A 29Nov16A 19 0 OnTarget
CommonFinalFinishes 61 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC1FMEPF1000 BC 1stFloor InstallLightFittings 14 71.43% 10.00% 19Dec16 3Jan17 25Dec16A 18Jan17 13 115 Delayed
BC1FMEPF1010 BC 1stFloor InstallFireCabinets 14 64.29% 100.00% 20Dec16 4Jan17 27Nov16A 01Dec16A 30 0 OnTarget
BC1FMEPF1020 BC 1stFloor InstallFireAlarmsandSpeakers 14 64.29% 0.00% 20Dec16 4Jan17 31Dec16 15Jan17 9 117 Delayed
BC1FMEPF1030 BC 1stFloor InstallSprinklers 14 57.14% 0.00% 21Dec16 5Jan17 1Jan17 16Jan17 9 117 Delayed
BC1FMEPF1040 BC 1stFloor InstallSwitchesandSockets 14 57.14% 20.00% 21Dec16 5Jan17 28Dec16A 12Jan17 5 68 Delayed
BC1FMEPF1050 BC 1stFloor InstallLowCurrentEquipments 14 50.00% 0.00% 22Dec16 7Jan17 31Dec16 15Jan17 7 66 Delayed
BC1FMEPF1060 BC 1stFloor InstallGrillesandDiffussers 14 50.00% 0.00% 22Dec16 7Jan17 31Dec16 15Jan17 7 66 Delayed
BC1FMEPF1070 BC 1stFloor InstallPlumpingFinalfittings(BathTub/Sanitaryware 14 50.00% 0.00% 22Dec16 7Jan17 31Dec16 15Jan17 7 66 Delayed
SecondFloor 79 0.00% 0.00% 10Dec16 11Mar17 27Nov16A 20Mar17 8 63 OnTarget
DryArea 19 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 7 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC2FMEPD1000 BC 2ndFloor DBInstallation 7 100.00% 50.00% 22Dec16 29Dec16 27Nov16A 3Jan17 4 98 Delayed
WetArea 42 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 36 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC2FMEPW1000 BC 2ndFloor WetAreaHLClearancebyARMAforgridfixing 10 100.00% 100.00% 10Dec16 20Dec16 27Nov16A 01Dec16A 17 0 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BC2FMEPW1010 BC 2ndFloor Droppers 12 8.33% 80.00% 29Dec16 11Jan17 27Nov16A 18Jan17 6 88 OnTarget
BC2FMEPW1020 BC 2ndFloor WetAreaMEPclearanceforBoardclosing 12 0.00% 80.00% 7Jan17 19Jan17 27Nov16A 26Jan17 6 88 OnTarget
Corridor/LiftLobby 34 0.00% 0.00% 22Dec16 18Mar17 27Nov16A 1Apr17 11 12 OnTarget
MEPWorks 18 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC2FMEPCL1000 BC 2ndFloor Droppers 12 0.00% 20.00% 1Jan17 14Jan17 27Nov16A 21Jan17 6 68 OnTarget
BC2FMEPCL1010 BC 2ndFloor CorridorMEPclearanceforBoardclosing 12 0.00% 20.00% 8Jan17 21Jan17 27Nov16A 28Jan17 6 68 OnTarget
CommonFinalFinishes 54 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC2FMEPF1000 BC 2ndFloor InstallLightFittings 14 0.00% 0.00% 31Jan17 15Feb17 7Feb17 22Feb17 6 85 OnTarget
BC2FMEPF1010 BC 2ndFloor InstallFireCabinets 14 0.00% 100.00% 1Feb17 16Feb17 27Nov16A 05Dec16A 64 0 OnTarget
BC2FMEPF1020 BC 2ndFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 1Feb17 16Feb17 31Dec16 15Jan17 28 64 OnTarget
BC2FMEPF1030 BC 2ndFloor InstallSprinklers 14 0.00% 0.00% 2Feb17 18Feb17 1Jan17 16Jan17 28 64 OnTarget
BC2FMEPF1040 BC 2ndFloor InstallSwitchesandSockets 14 0.00% 0.00% 2Feb17 18Feb17 1Jan17 16Jan17 28 64 OnTarget
BC2FMEPF1050 BC 2ndFloor InstallLowCurrentEquipments 14 0.00% 0.00% 4Feb17 19Feb17 2Jan17 17Jan17 28 64 OnTarget
BC2FMEPF1060 BC 2ndFloor InstallGrillesandDiffussers 14 0.00% 0.00% 4Feb17 19Feb17 2Jan17 17Jan17 28 64 OnTarget
BC2FMEPF1070 BC 2ndFloor InstallPlumpingFinalfittings(BathTub/Sanitaryware 14 0.00% 0.00% 4Feb17 19Feb17 2Jan17 17Jan17 28 64 OnTarget
ThirdFloor 93 0.00% 0.00% 27Nov16 14Mar17 26Nov16A 9Apr17 22 46 OnTarget
DryArea 51 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 40 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC3FMEPD1000 BC 3rdFloor InstallDuctsandHangers 14 100.00% 100.00% 27Nov16 12Dec16 27Nov16A 29Nov16A 12 0 OnTarget
BC3FMEPD1010 BC 3rdFloor DryAreaMEPHLClearancebyARMAforgridfixing 6 100.00% 100.00% 13Dec16 19Dec16 27Nov16A 19Dec16A 1 0 OnTarget
BC3FMEPD1020 BC 3rdFloor DBInstallation 10 90.00% 50.00% 20Dec16 31Dec16 27Nov16A 4Jan17 4 127 Delayed
BC3FMEPD1030 BC 3rdFloor InstallDropers 6 0.00% 55.00% 1Jan17 7Jan17 27Nov16A 2Jan17 4 90 OnTarget
BC3FMEPD1040 BC 3rdFloor DryAreaMEPclearanceforBoardclosing 6 0.00% 50.00% 5Jan17 11Jan17 27Nov16A 7Jan17 4 90 OnTarget
WetArea 42 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 36 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC3FMEPW1000 BC 3rdFloor InstallDuctsandHangers 7 100.00% 100.00% 13Dec16 20Dec16 27Nov16A 03Dec16A 16 0 OnTarget
BC3FMEPW1010 BC 3rdFloor WetAreaHLClearancebyARMAforgridfixing 6 100.00% 98.00% 21Dec16 27Dec16 27Nov16A 31Dec16 2 38 Delayed
BC3FMEPW1020 BC 3rdFloor InstallDroppers 12 0.00% 0.00% 31Dec16 12Jan17 31Dec16 12Jan17 0 48 OnTarget
BC3FMEPW1030 BC 3rdFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 12Jan17 23Jan17 8Jan17 19Jan17 4 47 OnTarget
Corridor/LiftLobby 49 0.00% 0.00% 22Dec16 18Mar17 27Nov16A 1Apr17 11 12 OnTarget
MEPWorks 35 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC3FMEPCL1000 BC 3rdFloor InstallDuctsandHangers 8 100.00% 100.00% 21Dec16 29Dec16 27Nov16A 29Nov16A 27 0 OnTarget
BC3FMEPCL1010 BC 3rdFloor CorridorHLClearancebyARMAforgridfixing 8 25.00% 0.00% 28Dec16 5Jan17 31Dec16 8Jan17 2 33 Delayed
BC3FMEPCL1020 BC 3rdFloor InstallDroppers 7 0.00% 0.00% 11Jan17 18Jan17 14Jan17 21Jan17 2 33 OnTarget
BC3FMEPCL1030 BC 3rdFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 19Jan17 30Jan17 22Jan17 1Feb17 2 33 OnTarget
CommonFinalFinishes 48 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 24 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC3FMEPF1000 BC 3rdFloor InstallLightFittings 14 0.00% 0.00% 1Feb17 16Feb17 4Feb17 19Feb17 2 88 OnTarget
BC3FMEPF1010 BC 3rdFloor InstallFireCabinets 14 0.00% 100.00% 2Feb17 18Feb17 27Nov16A 10Dec16A 61 0 OnTarget
BC3FMEPF1020 BC 3rdFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 2Feb17 18Feb17 31Dec16 15Jan17 29 64 OnTarget
BC3FMEPF1030 BC 3rdFloor InstallSprinklers 14 0.00% 0.00% 4Feb17 19Feb17 1Jan17 16Jan17 29 64 OnTarget
BC3FMEPF1040 BC 3rdFloor InstallSwitchesandSockets 14 0.00% 0.00% 4Feb17 19Feb17 1Jan17 16Jan17 29 64 OnTarget
BC3FMEPF1050 BC 3rdFloor InstallLowCurrentEquipments 14 0.00% 0.00% 5Feb17 20Feb17 2Jan17 17Jan17 29 64 OnTarget
BC3FMEPF1060 BC 3rdFloor InstallGrillesandDiffussers 14 0.00% 0.00% 5Feb17 20Feb17 2Jan17 17Jan17 29 64 OnTarget
BC3FMEPF1070 BC 3rdFloor InstallPlumpingFinalTittings(BathTub,FloorDrains, 14 0.00% 0.00% 5Feb17 20Feb17 2Jan17 17Jan17 29 64 OnTarget
BC3FMEPF1080 BC 3rdFloor MEPFinalFixes/Sanitarywares 18 0.00% 0.00% 24Jan17 13Feb17 26Jan17 15Feb17 2 33 OnTarget
ForthFloor 103 0.00% 0.00% 29Nov16 28Mar17 26Nov16A 9Apr17 10 46 OnTarget
DryArea 66 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 55 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC4FMEPD1000 BC 4thFloor InstallLowCurrentWiring 10 100.00% 100.00% 1Dec16 12Dec16 27Nov16A 27Nov16A 14 0 OnTarget
BC4FMEPD1010 BC 4thFloor DBInstallation 10 0.00% 20.00% 1Jan17 11Jan17 27Nov16A 8Jan17 3 124 OnTarget
BC4FMEPD1020 BC 4thFloor InstallDroppers 12 8.33% 30.00% 29Dec16 11Jan17 27Nov16A 9Jan17 3 78 OnTarget
BC4FMEPD1030 BC 4thFloor MeggeringTest 12 0.00% 60.00% 12Jan17 25Jan17 27Nov16A 12Jan17 12 78 OnTarget
BC4FMEPD1040 BC 4thFloor DryAreaMEPclearanceforBoardclosing 12 0.00% 30.00% 21Jan17 2Feb17 27Nov16A 21Jan17 12 78 OnTarget
WetArea 59 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 53 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC4FMEPW1000 BC 4thFloor InstallElectricalWiring 18 100.00% 100.00% 29Nov16 19Dec16 27Nov16A 03Dec16A 15 0 OnTarget
BC4FMEPW1010 BC 4thFloor Firefightingpipes 18 100.00% 100.00% 3Dec16 22Dec16 27Nov16A 17Dec16A 6 0 OnTarget
BC4FMEPW1020 BC 4thFloor InstallHVACPipes 18 100.00% 100.00% 6Dec16 26Dec16 27Nov16A 01Dec16A 22 0 OnTarget
BC4FMEPW1030 BC 4thFloor InstallDuctsandHangers 18 100.00% 100.00% 10Dec16 29Dec16 27Nov16A 28Dec16A 2 0 OnTarget
BC4FMEPW1040 BC 4thFloor WetAreaHLClearancebyARMAforgridfixing 8 62.50% 80.00% 25Dec16 2Jan17 27Nov16A 1Jan17 1 70 OnTarget
BC4FMEPW1050 BC 4thFloor InstallDroppers 12 0.00% 30.00% 9Jan17 22Jan17 27Nov16A 12Jan17 9 106 OnTarget
BC4FMEPW1060 BC 4thFloor MeggeringTest 7 0.00% 60.00% 15Jan17 22Jan17 27Nov16A 12Jan17 9 106 OnTarget
BC4FMEPW1070 BC 4thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 30.00% 18Jan17 29Jan17 27Nov16A 19Jan17 9 103 OnTarget
Corridor/LiftLobby 73 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 59 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC4FMEPCL1000 BC 4thFloor InstallElectricalWiring 18 100.00% 85.00% 6Dec16 26Dec16 27Nov16A 2Jan17 6 129 Delayed
BC4FMEPCL1010 BC 4thFloor InstallHot&ColdWaterPiping 18 100.00% 100.00% 10Dec16 29Dec16 27Nov16A 29Nov16A 27 0 OnTarget
BC4FMEPCL1020 BC 4thFloor Firefightingpipes 18 100.00% 100.00% 10Dec16 29Dec16 27Nov16A 03Dec16A 24 0 OnTarget
BC4FMEPCL1030 BC 4thFloor InstallHVACPipes 18 83.33% 100.00% 13Dec16 2Jan17 27Nov16A 29Nov16A 30 0 OnTarget
BC4FMEPCL1040 BC 4thFloor InstallDuctsandHangers 18 66.67% 97.00% 17Dec16 5Jan17 27Nov16A 31Dec16 5 131 OnTarget
BC4FMEPCL1050 BC 4thFloor InstallCableTraysandTrunking 18 50.00% 100.00% 20Dec16 9Jan17 27Nov16A 28Dec16A 11 0 OnTarget
BC4FMEPCL1060 BC 4thFloor InstallLowCurrentWiring 15 20.00% 100.00% 27Dec16 12Jan17 27Nov16A 17Dec16A 24 0 OnTarget
BC4FMEPCL1070 BC 4thFloor InstallLVCables 18 33.33% 100.00% 24Dec16 12Jan17 27Nov16A 28Dec16A 14 0 OnTarget
BC4FMEPCL1080 BC 4thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 50.00% 17Jan17 28Jan17 27Nov16A 4Jan17 20 75 OnTarget
BC4FMEPCL1090 BC 4thFloor InstallDroppers 18 0.00% 0.00% 19Jan17 8Feb17 31Dec16 19Jan17 17 72 OnTarget
BC4FMEPCL1100 BC 4thFloor MeggeringTest 18 0.00% 60.00% 19Jan17 8Feb17 27Nov16A 19Jan17 17 72 OnTarget
BC4FMEPCL1110 BC 4thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 1Feb17 12Feb17 12Jan17 23Jan17 17 72 OnTarget
CommonFinalFinishes 41 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC4FMEPF1000 BC 4thFloor InstallLightFittings 14 0.00% 0.00% 13Feb17 28Feb17 24Jan17 8Feb17 17 97 OnTarget
BC4FMEPF1010 BC 4thFloor InstallFireCabinets 14 0.00% 100.00% 14Feb17 1Mar17 27Nov16A 13Dec16A 68 0 OnTarget
BC4FMEPF1020 BC 4thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 14Feb17 1Mar17 31Dec16 15Jan17 39 64 OnTarget
BC4FMEPF1030 BC 4thFloor InstallSprinklers 14 0.00% 0.00% 15Feb17 2Mar17 1Jan17 16Jan17 39 64 OnTarget
BC4FMEPF1040 BC 4thFloor InstallSwitchesandSockets 14 0.00% 0.00% 15Feb17 2Mar17 1Jan17 16Jan17 39 64 OnTarget
BC4FMEPF1050 BC 4thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 16Feb17 4Mar17 2Jan17 17Jan17 39 64 OnTarget
BC4FMEPF1060 BC 4thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 16Feb17 4Mar17 2Jan17 17Jan17 39 64 OnTarget
BC4FMEPF1070 BC 4thFloor InstallPlumpingFinalTittings(Bathtub/Sanitaryware, 14 0.00% 0.00% 16Feb17 4Mar17 2Jan17 17Jan17 39 64 OnTarget
FifthFloor 99 0.00% 0.00% 8Dec16 2Apr17 26Nov16A 11Apr17 8 44 OnTarget
MEPWorks 38 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC5FMEPD1000 BC 5thFloor InstallLowCurrentWiring 10 100.00% 100.00% 8Dec16 19Dec16 27Nov16A 22Dec16A 2 0 OnTarget
BC5FMEPD1010 BC 5thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 100.00% 88.00% 15Dec16 26Dec16 27Nov16A 1Jan17 4 69 Delayed
BC5FMEPD1020 BC 5thFloor DBInstallation 10 90.00% 30.00% 20Dec16 31Dec16 27Nov16A 7Jan17 6 46 Delayed
BC5FMEPD1030 BC 5thFloor InstallDroppers 12 25.00% 0.00% 27Dec16 9Jan17 31Dec16 12Jan17 3 50 Delayed
BC5FMEPD1040 BC 5thFloor MeggeringTest 12 0.00% 0.00% 1Jan17 14Jan17 8Jan17 21Jan17 6 46 OnTarget
BC5FMEPD1050 BC 5thFloor DryAreaMEPclearanceforBoardclosing 14 0.00% 0.00% 5Jan17 21Jan17 12Jan17 28Jan17 6 46 OnTarget
WetArea 48 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 42 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC5FMEPW1000 BC 5thFloor InstallElectricalWiring 12 100.00% 100.00% 14Dec16 27Dec16 27Nov16A 17Dec16A 10 0 OnTarget
BC5FMEPW1010 BC 5thFloor InstallHVACPipes 10 100.00% 100.00% 18Dec16 28Dec16 27Nov16A 28Dec16A 1 0 OnTarget
BC5FMEPW1020 BC 5thFloor Firefightingpipes 10 100.00% 100.00% 19Dec16 29Dec16 27Nov16A 25Dec16A 5 0 OnTarget
BC5FMEPW1030 BC 5thFloor InstallDuctsandHangers 10 80.00% 98.00% 21Dec16 1Jan17 27Nov16A 31Dec16 1 69 OnTarget
BC5FMEPW1040 BC 5thFloor WetAreaHLClearancebyARMAforgridfixing 10 50.00% 70.00% 25Dec16 4Jan17 27Nov16A 4Jan17 1 69 OnTarget
BC5FMEPW1050 BC 5thFloor InstallDroppers 12 0.00% 0.00% 11Jan17 24Jan17 1Jan17 15Jan17 9 96 OnTarget
BC5FMEPW1060 BC 5thFloor MeggeringTest 7 0.00% 0.00% 17Jan17 24Jan17 7Jan17 15Jan17 9 96 OnTarget
BC5FMEPW1070 BC 5thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 21Jan17 31Jan17 10Jan17 22Jan17 9 93 OnTarget
Corridor/LiftLobby 68 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 54 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC5FMEPCL1000 BC 5thFloor InstallElectricalWiring 18 77.78% 100.00% 14Dec16 3Jan17 27Nov16A 17Dec16A 16 0 OnTarget
BC5FMEPCL1010 BC 5thFloor InstallHot&ColdWaterPiping 18 61.11% 100.00% 18Dec16 7Jan17 27Nov16A 29Nov16A 34 0 OnTarget
BC5FMEPCL1020 BC 5thFloor Firefightingpipes 18 61.11% 100.00% 18Dec16 7Jan17 27Nov16A 03Dec16A 31 0 OnTarget
BC5FMEPCL1030 BC 5thFloor InstallHVACPipes 18 44.44% 90.00% 21Dec16 10Jan17 27Nov16A 1Jan17 8 127 OnTarget
BC5FMEPCL1040 BC 5thFloor InstallDuctsandHangers 18 27.78% 98.00% 25Dec16 14Jan17 27Nov16A 4Jan17 8 127 OnTarget
BC5FMEPCL1050 BC 5thFloor InstallCableTraysandTrunking 18 11.11% 100.00% 28Dec16 17Jan17 27Nov16A 17Dec16A 28 0 OnTarget
BC5FMEPCL1060 BC 5thFloor InstallLowCurrentWiring 18 0.00% 100.00% 1Jan17 21Jan17 27Nov16A 17Dec16A 31 0 OnTarget
BC5FMEPCL1070 BC 5thFloor InstallLVCables 18 0.00% 90.00% 1Jan17 21Jan17 25Dec16A 1Jan17 17 70 OnTarget
BC5FMEPCL1080 BC 5thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 14Jan17 24Jan17 31Dec16 10Jan17 12 70 OnTarget
BC5FMEPCL1090 BC 5thFloor InstallDroppers 18 0.00% 0.00% 22Jan17 11Feb17 2Jan17 22Jan17 17 70 OnTarget
BC5FMEPCL1100 BC 5thFloor MeggeringTest 18 0.00% 0.00% 22Jan17 11Feb17 2Jan17 22Jan17 17 70 OnTarget
BC5FMEPCL1110 BC 5thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 4Feb17 14Feb17 15Jan17 25Jan17 17 70 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
CommonFinalFinishes 50 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC5FMEPF1000 BC 5thFloor InstallLightFittings 14 0.00% 0.00% 25Feb17 12Mar17 5Feb17 20Feb17 17 87 OnTarget
BC5FMEPF1010 BC 5thFloor InstallFireCabinets 14 0.00% 100.00% 26Feb17 13Mar17 27Nov16A 15Dec16A 76 0 OnTarget
BC5FMEPF1020 BC 5thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 26Feb17 13Mar17 31Dec16 15Jan17 49 64 OnTarget
BC5FMEPF1030 BC 5thFloor InstallSprinklers 14 0.00% 0.00% 27Feb17 14Mar17 1Jan17 16Jan17 49 64 OnTarget
BC5FMEPF1040 BC 5thFloor InstallSwitchesandSockets 14 0.00% 0.00% 27Feb17 14Mar17 1Jan17 16Jan17 49 64 OnTarget
BC5FMEPF1050 BC 5thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 28Feb17 15Mar17 2Jan17 17Jan17 49 64 OnTarget
BC5FMEPF1060 BC 5thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 28Feb17 15Mar17 2Jan17 17Jan17 49 64 OnTarget
BC5FMEPF1070 BC 5thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 28Feb17 15Mar17 2Jan17 17Jan17 49 64 OnTarget
SixthFloor 93 0.00% 0.00% 15Dec16 2Apr17 26Nov16A 11Apr17 8 44 OnTarget
DryArea 53 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPworks 42 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC6FMEPD1000 BC 6thFloor InstallElectricalWiring 10 100.00% 90.00% 15Dec16 26Dec16 27Nov16A 31Dec16 4 6 Delayed
BC6FMEPD1010 BC 6thFloor InstallLowCurrentWiring 10 70.00% 35.00% 22Dec16 2Jan17 27Nov16A 7Jan17 4 46 Delayed
BC6FMEPD1020 BC 6thFloor InstallHVACPipes 8 25.00% 85.00% 28Dec16 5Jan17 27Nov16A 10Jan17 4 46 OnTarget
BC6FMEPD1030 BC 6thFloor InstallDuctsandHangers 10 10.00% 95.00% 29Dec16 9Jan17 27Nov16A 14Jan17 4 46 OnTarget
BC6FMEPD1040 BC 6thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 60.00% 2Jan17 12Jan17 27Nov16A 17Jan17 4 46 OnTarget
BC6FMEPD1050 BC 6thFloor DBInstallation 10 0.00% 20.00% 10Jan17 21Jan17 27Nov16A 8Jan17 11 98 OnTarget
BC6FMEPD1060 BC 6thFloor FloorMEPconduitsforScreed 7 0.00% 0.00% 5Jan17 12Jan17 10Jan17 17Jan17 4 116 OnTarget
BC6FMEPD1070 BC 6thFloor InstallDroppers 12 0.00% 0.00% 14Jan17 26Jan17 18Jan17 31Jan17 4 85 OnTarget
BC6FMEPD1080 BC 6thFloor MeggeringTest 7 0.00% 0.00% 22Jan17 29Jan17 24Jan17 31Jan17 2 85 OnTarget
BC6FMEPD1090 BC 6thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 22Jan17 1Feb17 24Jan17 4Feb17 2 85 OnTarget
WetArea 49 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPworks 43 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC6FMEPW1000 BC 6thFloor InstallElectricalWiring 12 75.00% 79.00% 20Dec16 2Jan17 27Nov16A 7Jan17 4 4 OnTarget
BC6FMEPW1010 BC 6thFloor InstallHVACPipes 12 50.00% 85.00% 24Dec16 5Jan17 27Nov16A 10Jan17 4 49 OnTarget
BC6FMEPW1020 BC 6thFloor InstallDuctsandHangers 12 25.00% 95.00% 27Dec16 9Jan17 27Nov16A 14Jan17 4 49 OnTarget
BC6FMEPW1030 BC 6thFloor WetAreaHLClearancebyARMAforgridfixing 12 0.00% 50.00% 3Jan17 16Jan17 27Nov16A 21Jan17 4 46 OnTarget
BC6FMEPW1040 BC 6thFloor FloorMEPconduitsforScreed 10 0.00% 0.00% 9Jan17 19Jan17 14Jan17 24Jan17 4 57 OnTarget
BC6FMEPW1050 BC 6thFloor InstallDroppers 12 0.00% 0.00% 18Jan17 31Jan17 23Jan17 5Feb17 4 85 OnTarget
BC6FMEPW1060 BC 6thFloor MeggeringTest 10 0.00% 0.00% 21Jan17 31Jan17 25Jan17 5Feb17 4 85 OnTarget
BC6FMEPW1070 BC 6thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 28Jan17 7Feb17 1Feb17 12Feb17 4 82 OnTarget
CorridorLiftLobby 57 0.00% 0.00% 27Dec16 2Mar17 26Nov16A 25Feb17 5 83 OnTarget
MEPworks 43 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC6FMEPCL1000 BC 6thFloor InstallElectricalWiring 12 25.00% 40.00% 27Dec16 9Jan17 27Nov16A 14Jan17 4 4 OnTarget
BC6FMEPCL1010 BC 6thFloor InstallHot&ColdWaterPiping 10 0.00% 100.00% 2Jan17 12Jan17 27Nov16A 29Nov16A 39 0 OnTarget
BC6FMEPCL1020 BC 6thFloor InstallHVACPipes 12 0.00% 85.00% 3Jan17 16Jan17 27Nov16A 1Jan17 13 130 OnTarget
BC6FMEPCL1030 BC 6thFloor InstallDuctsandHangers 10 0.00% 100.00% 9Jan17 19Jan17 27Nov16A 10Dec16A 36 0 OnTarget
BC6FMEPCL1040 BC 6thFloor InstallCableTraysandTrunking 12 0.00% 40.00% 10Jan17 23Jan17 27Nov16A 8Jan17 14 55 OnTarget
BC6FMEPCL1050 BC 6thFloor InstallLowCurrentWiring 12 0.00% 32.00% 11Jan17 24Jan17 27Nov16A 9Jan17 14 59 OnTarget
BC6FMEPCL1060 BC 6thFloor InstallLVCables 7 0.00% 0.00% 19Jan17 26Jan17 3Jan17 11Jan17 14 55 OnTarget
BC6FMEPCL1070 BC 6thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 19Jan17 30Jan17 14Jan17 24Jan17 5 46 OnTarget
BC6FMEPCL1080 BC 6thFloor FloorMEPconduitsforScreed 6 0.00% 0.00% 28Jan17 2Feb17 22Jan17 28Jan17 5 57 OnTarget
BC6FMEPCL1090 BC 6thFloor InstallDroppers 10 0.00% 0.00% 31Jan17 11Feb17 25Jan17 5Feb17 5 46 OnTarget
BC6FMEPCL1100 BC 6thFloor MeggeringTest 12 0.00% 0.00% 29Jan17 11Feb17 23Jan17 5Feb17 5 46 OnTarget
BC6FMEPCL1110 BC 6thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 4Feb17 14Feb17 29Jan17 8Feb17 5 46 OnTarget
CommonfinalFinishes 44 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPworks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC6FMEPF1000 BC 6thFloor InstallLightFittings 14 0.00% 0.00% 15Feb17 2Mar17 11Feb17 26Feb17 4 82 OnTarget
BC6FMEPF1010 BC 6thFloor InstallFireCabinets 14 0.00% 100.00% 16Feb17 4Mar17 27Nov16A 18Dec16A 66 0 OnTarget
BC6FMEPF1020 BC 6thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 16Feb17 4Mar17 31Dec16 15Jan17 41 64 OnTarget
BC6FMEPF1030 BC 6thFloor InstallSprinklers 14 0.00% 0.00% 18Feb17 5Mar17 1Jan17 16Jan17 41 64 OnTarget
BC6FMEPF1040 BC 6thFloor InstallSwitchesandSockets 14 0.00% 0.00% 18Feb17 5Mar17 1Jan17 16Jan17 41 64 OnTarget
BC6FMEPF1050 BC 6thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 19Feb17 6Mar17 2Jan17 17Jan17 41 64 OnTarget
BC6FMEPF1060 BC 6thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 19Feb17 6Mar17 2Jan17 17Jan17 41 64 OnTarget
BC6FMEPF1070 BC 6thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 19Feb17 6Mar17 2Jan17 17Jan17 41 64 OnTarget
SeventhFloor 116 0.00% 0.00% 27Nov16 10Apr17 26Nov16A 11Apr17 1 44 OnTarget
DryArea 55 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPworks 38 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC7FMEPD1000 BC 7thFloor InstallElectricalWiring 10 100.00% 67.00% 19Dec16 29Dec16 27Nov16A 3Jan17 4 6 Delayed
BC7FMEPD1010 BC 7thFloor InstallLowCurrentWiring 7 57.14% 32.00% 26Dec16 2Jan17 27Nov16A 7Jan17 4 44 Delayed
BC7FMEPD1020 BC 7thFloor InstallHVACPipes 7 14.29% 85.00% 29Dec16 5Jan17 27Nov16A 10Jan17 4 44 OnTarget
BC7FMEPD1030 BC 7thFloor InstallDuctsandHangers 15 40.00% 41.00% 24Dec16 9Jan17 27Nov16A 14Jan17 4 44 OnTarget
BC7FMEPD1040 BC 7thFloor DryAreaMEPHLClearancebyARMAforgridfixing 18 33.33% 42.00% 24Dec16 12Jan17 27Nov16A 17Jan17 4 44 OnTarget
BC7FMEPD1050 BC 7thFloor FloorMEPconduitsforScreed 10 0.00% 0.00% 14Jan17 24Jan17 18Jan17 29Jan17 4 44 OnTarget
BC7FMEPD1060 BC 7thFloor DBInstallation 10 0.00% 20.00% 10Jan17 21Jan17 27Nov16A 8Jan17 11 68 OnTarget
BC7FMEPD1070 BC 7thFloor InstallDroppers 12 0.00% 0.00% 15Jan17 28Jan17 19Jan17 1Feb17 4 54 OnTarget
BC7FMEPD1080 BC 7thFloor MeggeringTest 7 0.00% 0.00% 22Jan17 29Jan17 25Jan17 1Feb17 3 54 OnTarget
BC7FMEPD1090 BC 7thFloor DryAreaMEPclearanceforBoardclosing 18 0.00% 0.00% 11Jan17 31Jan17 15Jan17 4Feb17 3 54 OnTarget
WetArea 68 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPworks 62 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC7FMEPW1000 BC 7thFloor FloorMEPconduitsforScreed 6 0.00% 0.00% 17Jan17 23Jan17 22Jan17 28Jan17 4 104 OnTarget
BC7FMEPW1010 BC 7thFloor WetAreaHLClearancebyARMAforgridfixing 10 0.00% 30.00% 24Jan17 4Feb17 27Nov16A 10Jan17 22 35 OnTarget
BC7FMEPW1020 BC 7thFloor WetAreaMEPclearanceforBoardclosing 12 0.00% 0.00% 22Feb17 7Mar17 14Jan17 28Jan17 34 37 OnTarget
BC7FMEPW1030 BC 7thFloor InstallElectricalWiring 10 40.00% 67.00% 26Dec16 5Jan17 27Nov16A 10Jan17 4 121 OnTarget
BC7FMEPW1040 BC 7thFloor InstallDrainagepipes 7 0.00% 98.00% 31Dec16 7Jan17 27Nov16A 11Jan17 4 121 OnTarget
BC7FMEPW1050 BC 7thFloor InstallHot&ColdWaterPiping 7 0.00% 100.00% 1Jan17 8Jan17 27Nov16A 17Dec16A 20 0 OnTarget
BC7FMEPW1060 BC 7thFloor InstallHVACPipes 7 0.00% 85.00% 4Jan17 11Jan17 27Nov16A 1Jan17 10 41 OnTarget
BC7FMEPW1070 BC 7thFloor InstallDuctsandHangers 16 12.50% 41.00% 28Dec16 15Jan17 27Nov16A 10Jan17 5 35 OnTarget
BC7FMEPW1080 BC 7thFloor InstallDroppers 12 0.00% 0.00% 30Jan17 12Feb17 4Jan17 18Jan17 22 45 OnTarget
BC7FMEPW1090 BC 7thFloor MeggeringTest 7 0.00% 0.00% 5Feb17 12Feb17 10Jan17 18Jan17 22 45 OnTarget
CorridorLiftLobby 69 0.00% 0.00% 27Dec16 2Mar17 26Nov16A 25Feb17 5 83 OnTarget
MEPworks 53 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC7FMEPCL1000 BC 7thFloor CorridorScreedMEpClearance(Apt) 6 0.00% 78.00% 17Jan17 23Jan17 26Nov16A 28Jan17 4 107 OnTarget
BC7FMEPCL1010 BC 7thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 4Feb17 14Feb17 8Feb17 19Feb17 4 4 OnTarget
BC7FMEPCL1020 BC 7thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 18Feb17 28Feb17 22Feb17 5Mar17 4 4 OnTarget
BC7FMEPCL1030 BC 7thFloor InstallElectricalWiring 12 0.00% 40.00% 2Jan17 15Jan17 27Nov16A 19Jan17 4 4 OnTarget
BC7FMEPCL1035 BC 7thFloor InstallHot&ColdWaterPiping 18 5.56% 98.00% 29Dec16 18Jan17 27Nov16A 23Jan17 4 4 OnTarget
BC7FMEPCL1060 BC 7thFloor InstallHVACPipes 7 0.00% 85.00% 15Jan17 22Jan17 27Nov16A 26Jan17 4 4 OnTarget
BC7FMEPCL1070 BC 7thFloor InstallDuctsandHangers 10 0.00% 85.00% 15Jan17 25Jan17 27Nov16A 30Jan17 4 4 OnTarget
BC7FMEPCL1080 BC 7thFloor InstallCableTraysandTrunking 18 0.00% 0.00% 9Jan17 29Jan17 14Jan17 2Feb17 4 4 OnTarget
BC7FMEPCL1085 BC 7thFloor InstallLowCurrentWiring 12 0.00% 29.00% 19Jan17 1Feb17 27Nov16A 6Feb17 4 4 OnTarget
BC7FMEPCL1090 BC 7thFloor InstallLVCables 7 0.00% 0.00% 25Jan17 1Feb17 30Jan17 6Feb17 4 9 OnTarget
BC7FMEPCL1100 BC 7thFloor InstallDroppers 18 0.00% 0.00% 2Feb17 22Feb17 7Feb17 27Feb17 4 9 OnTarget
BC7FMEPCL1110 BC 7thFloor MeggeringTest 7 0.00% 0.00% 15Feb17 22Feb17 20Feb17 27Feb17 4 9 OnTarget
CommonFinalFinishes 41 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPworks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC7FMEPF1010 BC 7thFloor InstallLightFittings 14 0.00% 0.00% 6Mar17 21Mar17 6Mar17 21Mar17 0 62 OnTarget
BC7FMEPF1020 BC 7thFloor InstallFireCabinets 14 0.00% 100.00% 7Mar17 22Mar17 27Nov16A 20Dec16A 80 0 OnTarget
BC7FMEPF1030 BC 7thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 7Mar17 22Mar17 31Dec16 15Jan17 57 64 OnTarget
BC7FMEPF1040 BC 7thFloor InstallSprinklers 14 0.00% 0.00% 8Mar17 23Mar17 1Jan17 16Jan17 57 64 OnTarget
BC7FMEPF1050 BC 7thFloor InstallSwitchesandSockets 14 0.00% 0.00% 8Mar17 23Mar17 1Jan17 16Jan17 57 64 OnTarget
BC7FMEPF1060 BC 7thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 9Mar17 25Mar17 2Jan17 17Jan17 57 64 OnTarget
BC7FMEPF1070 BC 7thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 9Mar17 25Mar17 2Jan17 17Jan17 57 64 OnTarget
BC7FMEPF1075 BC 7thFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 11Mar17 21Mar17 11Mar17 21Mar17 0 4 OnTarget
BC7FMEPF1080 BC 7thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 9Mar17 25Mar17 2Jan17 17Jan17 57 64 OnTarget
EightFloor 118 0.00% 0.00% 30Nov16 16Apr17 26Nov16A 25Apr17 8 32 OnTarget
DryArea 68 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPworks 51 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC8FMEPD1040 BC 8thFloor InstallElectricalWiring 12 75.00% 75.00% 20Dec16 2Jan17 27Nov16A 7Jan17 4 6 OnTarget
BC8FMEPD1050 BC 8thFloor InstallLowCurrentWiring 12 25.00% 27.00% 27Dec16 9Jan17 27Nov16A 14Jan17 4 119 OnTarget
BC8FMEPD1060 BC 8thFloor InstallHVACPipes 10 30.00% 84.00% 27Dec16 7Jan17 27Nov16A 1Jan17 5 65 OnTarget
BC8FMEPD1070 BC 8thFloor Firefightingpipes 18 44.44% 98.00% 21Dec16 10Jan17 27Nov16A 4Jan17 5 65 OnTarget
BC8FMEPD1080 BC 8thFloor InstallDuctsandHangers 10 0.00% 6.00% 3Jan17 14Jan17 27Nov16A 10Jan17 4 63 OnTarget
BC8FMEPD1085 BC 8thFloor DryAreaMEPHLClearancebyARMAforgridfixing 18 61.11% 50.00% 18Dec16 7Jan17 27Nov16A 9Jan17 2 54 Delayed
BC8FMEPD1086 BC 8thFloor FloorMEPconduitsforScreed 10 0.00% 0.00% 8Jan17 18Jan17 10Jan17 21Jan17 2 54 OnTarget
BC8FMEPD1090 BC 8thFloor DBInstallation 10 0.00% 20.00% 7Jan17 17Jan17 27Nov16A 14Jan17 4 63 OnTarget
BC8FMEPD1100 BC 8thFloor InstallDroppers 12 0.00% 0.00% 8Jan17 21Jan17 10Jan17 23Jan17 2 55 OnTarget
BC8FMEPD1110 BC 8thFloor MeggeringTest 10 0.00% 0.00% 10Jan17 21Jan17 12Jan17 23Jan17 2 55 OnTarget
BC8FMEPD1115 BC 8thFloor DryAreaMEPclearanceforBoardclosing 18 0.00% 0.00% 25Jan17 14Feb17 28Jan17 16Feb17 2 55 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
WetArea 64 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPworks 58 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC8FMEPW1000 BC 8thFloor WetAreaScreedMEpClearance 6 0.00% 98.00% 12Jan17 18Jan17 26Nov16A 23Jan17 4 108 OnTarget
BC8FMEPW1010 BC 8thFloor WetAreaHLClearancebyARMAforgridfixing 10 0.00% 20.00% 19Jan17 30Jan17 27Nov16A 19Jan17 9 31 OnTarget
BC8FMEPW1020 BC 8thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 20Feb17 2Mar17 26Jan17 6Feb17 21 31 OnTarget
BC8FMEPW1030 BC 8thFloor InstallElectricalWiring 10 40.00% 53.00% 26Dec16 5Jan17 27Nov16A 10Jan17 4 31 OnTarget
BC8FMEPW1040 BC 8thFloor InstallDrainagepipes 10 30.00% 97.00% 27Dec16 7Jan17 27Nov16A 11Jan17 4 31 OnTarget
BC8FMEPW1050 BC 8thFloor InstallHot&ColdWaterPiping 10 20.00% 90.00% 28Dec16 8Jan17 27Nov16A 12Jan17 4 31 OnTarget
BC8FMEPW1060 BC 8thFloor InstallHVACPipes 10 0.00% 84.00% 1Jan17 11Jan17 27Nov16A 16Jan17 4 31 OnTarget
BC8FMEPW1070 BC 8thFloor InstallDuctsandHangers 16 12.50% 13.00% 28Dec16 15Jan17 27Nov16A 19Jan17 4 31 OnTarget
BC8FMEPW1080 BC 8thFloor InstallDroppers 12 0.00% 0.00% 11Feb17 23Feb17 17Jan17 30Jan17 21 37 OnTarget
BC8FMEPW1090 BC 8thFloor MeggeringTest 10 0.00% 0.00% 13Feb17 23Feb17 19Jan17 30Jan17 21 37 OnTarget
CorridorLiftLobby 63 0.00% 0.00% 27Dec16 2Mar17 26Nov16A 25Feb17 5 83 OnTarget
MEPworks 47 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC8FMEPCL1000 BC 8thFloor CorridorScreedMEpClearance(Apt) 6 0.00% 60.00% 11Feb17 16Feb17 26Nov16A 2Jan17 40 130 OnTarget
BC8FMEPCL1010 BC 8thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 30Jan17 9Feb17 17Jan17 29Jan17 11 24 OnTarget
BC8FMEPCL1020 BC 8thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 19Feb17 1Mar17 6Feb17 18Feb17 11 20 OnTarget
BC8FMEPCL1030 BC 8thFloor InstallElectricalWiring 12 0.00% 40.00% 7Jan17 19Jan17 27Nov16A 8Jan17 11 20 OnTarget
BC8FMEPCL1050 BC 8thFloor InstallHot&ColdWaterPiping 10 0.00% 95.00% 12Jan17 23Jan17 27Nov16A 11Jan17 11 20 OnTarget
BC8FMEPCL1060 BC 8thFloor InstallHVACPipes 10 0.00% 85.00% 16Jan17 26Jan17 27Nov16A 15Jan17 11 20 OnTarget
BC8FMEPCL1070 BC 8thFloor InstallDuctsandHangers 10 0.00% 90.00% 19Jan17 30Jan17 27Nov16A 18Jan17 11 20 OnTarget
BC8FMEPCL1080 BC 8thFloor InstallCableTraysandTrunking 16 0.00% 0.00% 16Jan17 2Feb17 3Jan17 22Jan17 11 20 OnTarget
BC8FMEPCL1085 BC 8thFloor InstallLowCurrentWiring 10 0.00% 26.00% 26Jan17 6Feb17 27Nov16A 25Jan17 11 20 OnTarget
BC8FMEPCL1090 BC 8thFloor InstallLVCables 10 0.00% 0.00% 30Jan17 9Feb17 17Jan17 29Jan17 11 20 OnTarget
BC8FMEPCL1100 BC 8thFloor InstallDroppers 14 0.00% 0.00% 11Feb17 26Feb17 29Jan17 14Feb17 11 20 OnTarget
BC8FMEPCL1110 BC 8thFloor MeggeringTest 10 0.00% 0.00% 19Feb17 1Mar17 6Feb17 18Feb17 11 20 OnTarget
CommonFinalFinishes 41 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPworks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC8FMEPF1010 BC 8thFloor InstallLightFittings 14 0.00% 0.00% 2Mar17 18Mar17 20Feb17 7Mar17 9 74 OnTarget
BC8FMEPF1020 BC 8thFloor InstallFireCabinets 14 0.00% 100.00% 4Mar17 19Mar17 27Nov16A 22Dec16A 75 0 OnTarget
BC8FMEPF1030 BC 8thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 4Mar17 19Mar17 31Dec16 15Jan17 54 64 OnTarget
BC8FMEPF1040 BC 8thFloor InstallSprinklers 14 0.00% 0.00% 5Mar17 20Mar17 1Jan17 16Jan17 54 64 OnTarget
BC8FMEPF1050 BC 8thFloor InstallSwitchesandSockets 14 0.00% 0.00% 5Mar17 20Mar17 1Jan17 16Jan17 54 64 OnTarget
BC8FMEPF1060 BC 8thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 6Mar17 21Mar17 2Jan17 17Jan17 54 64 OnTarget
BC8FMEPF1070 BC 8thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 6Mar17 21Mar17 2Jan17 17Jan17 54 64 OnTarget
BC8FMEPF1075 BC 8thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 2Mar17 15Mar17 18Feb17 4Mar17 11 20 OnTarget
BC8FMEPF1080 BC 8thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 6Mar17 21Mar17 2Jan17 17Jan17 54 64 OnTarget
NinthFloor 123 0.00% 0.00% 4Dec16 25Apr17 26Nov16A 30Apr17 4 28 OnTarget
DryArea 58 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPworks 41 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC9FMEPD1000 BC 9thFloor DryAreaMEPScreedclearance 10 0.00% 97.00% 12Jan17 23Jan17 26Nov16A 23Jan17 0 38 OnTarget
BC9FMEPD1010 BC 9thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 74.00% 5Jan17 16Jan17 26Nov16A 16Jan17 0 30 OnTarget
BC9FMEPD1020 BC 9thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 29Jan17 8Feb17 18Jan17 30Jan17 8 31 OnTarget
BC9FMEPD1040 BC 9thFloor InstallElectricalWiring 12 50.00% 50.00% 24Dec16 5Jan17 27Nov16A 10Jan17 4 6 OnTarget
BC9FMEPD1050 BC 9thFloor InstallLowCurrentWiring 12 0.00% 16.00% 31Dec16 12Jan17 27Nov16A 17Jan17 4 116 OnTarget
BC9FMEPD1060 BC 9thFloor InstallHVACPipes 12 0.00% 81.00% 31Dec16 12Jan17 27Nov16A 2Jan17 10 39 OnTarget
BC9FMEPD1070 BC 9thFloor InstallDuctsandHangers 18 16.67% 17.00% 27Dec16 16Jan17 27Nov16A 16Jan17 0 30 OnTarget
BC9FMEPD1080 BC 9thFloor DBInstallation 10 0.00% 20.00% 17Jan17 28Jan17 27Nov16A 8Jan17 17 40 OnTarget
BC9FMEPD1090 BC 9thFloor InstallDroppers 12 0.00% 0.00% 17Jan17 30Jan17 16Jan17 30Jan17 0 31 OnTarget
BC9FMEPD1100 BC 9thFloor MeggeringTest 10 0.00% 0.00% 29Jan17 8Feb17 18Jan17 30Jan17 8 31 OnTarget
WetArea 67 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPworks 61 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC9FMEPW1000 BC 9thFloor WetAreaScreedMEpClearance 10 0.00% 100.00% 12Jan17 23Jan17 26Nov16A 22Dec16A 28 0 OnTarget
BC9FMEPW1010 BC 9thFloor WetAreaHLClearancebyARMAforgridfixing 10 0.00% 0.00% 24Jan17 4Feb17 12Jan17 23Jan17 10 24 OnTarget
BC9FMEPW1020 BC 9thFloor WetAreaMEPclearanceforBoardclosing 12 0.00% 0.00% 22Feb17 7Mar17 28Jan17 9Feb17 22 26 OnTarget
BC9FMEPW1030 BC 9thFloor InstallElectricalWiring 12 25.00% 47.00% 27Dec16 9Jan17 27Nov16A 14Jan17 4 24 OnTarget
BC9FMEPW1040 BC 9thFloor InstallDrainagepipes 10 0.00% 94.00% 31Dec16 10Jan17 27Nov16A 15Jan17 4 24 OnTarget
BC9FMEPW1050 BC 9thFloor InstallHot&ColdWaterPiping 10 0.00% 68.00% 1Jan17 11Jan17 27Nov16A 16Jan17 4 24 OnTarget
BC9FMEPW1060 BC 9thFloor InstallHVACPipes 12 0.00% 81.00% 2Jan17 15Jan17 27Nov16A 19Jan17 4 24 OnTarget
BC9FMEPW1070 BC 9thFloor InstallDuctsandHangers 18 5.56% 6.00% 29Dec16 18Jan17 27Nov16A 23Jan17 4 24 OnTarget
BC9FMEPW1080 BC 9thFloor InstallDroppers 12 0.00% 0.00% 22Feb17 7Mar17 28Jan17 9Feb17 22 26 OnTarget
BC9FMEPW1090 BC 9thFloor MeggeringTest 10 0.00% 0.00% 25Feb17 7Mar17 30Jan17 9Feb17 22 26 OnTarget
CorridorLiftLobby 65 0.00% 0.00% 27Dec16 2Mar17 26Nov16A 25Feb17 5 83 OnTarget
MEPworks 49 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC9FMEPCL1000 BC 9thFloor CorridorScreedMEpClearance 10 0.00% 60.00% 1Feb17 12Feb17 26Nov16A 28Jan17 13 107 OnTarget
BC9FMEPCL1010 BC 9thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 29Jan17 8Feb17 16Jan17 26Jan17 11 24 OnTarget
BC9FMEPCL1020 BC 9thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 13Feb17 23Feb17 30Jan17 9Feb17 12 24 OnTarget
BC9FMEPCL1030 BC 9thFloor InstallElectricalWiring 10 10.00% 20.00% 29Dec16 9Jan17 27Nov16A 14Jan17 4 119 OnTarget
BC9FMEPCL1050 BC 9thFloor InstallHot&ColdWaterPiping 10 0.00% 95.00% 14Jan17 24Jan17 27Nov16A 31Dec16 22 33 OnTarget
BC9FMEPCL1060 BC 9thFloor InstallHVACPipes 10 0.00% 80.00% 17Jan17 28Jan17 27Nov16A 3Jan17 22 33 OnTarget
BC9FMEPCL1070 BC 9thFloor InstallDuctsandHangers 16 0.00% 40.00% 14Jan17 31Jan17 27Nov16A 10Jan17 18 30 OnTarget
BC9FMEPCL1080 BC 9thFloor InstallCableTraysandTrunking 18 0.00% 0.00% 15Jan17 4Feb17 31Dec16 19Jan17 13 25 OnTarget
BC9FMEPCL1085 BC 9thFloor InstallLowCurrentWiring 10 0.00% 16.00% 28Jan17 7Feb17 27Nov16A 23Jan17 13 26 OnTarget
BC9FMEPCL1090 BC 9thFloor InstallLVCables 14 0.00% 0.00% 23Jan17 7Feb17 8Jan17 23Jan17 13 25 OnTarget
BC9FMEPCL1100 BC 9thFloor InstallDroppers 14 0.00% 0.00% 8Feb17 23Feb17 24Jan17 8Feb17 13 25 OnTarget
BC9FMEPCL1110 BC 9thFloor MeggeringTest 10 0.00% 0.00% 13Feb17 23Feb17 29Jan17 8Feb17 13 25 OnTarget
CommonFinalFinishes 54 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPworks 21 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC9FMEPF1010 BC 9thFloor InstallLightFittings 14 0.00% 0.00% 6Mar17 21Mar17 11Feb17 26Feb17 20 27 OnTarget
BC9FMEPF1020 BC 9thFloor InstallFireCabinets 14 0.00% 0.00% 7Mar17 22Mar17 12Feb17 27Feb17 20 27 OnTarget
BC9FMEPF1030 BC 9thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 7Mar17 22Mar17 12Feb17 27Feb17 20 27 OnTarget
BC9FMEPF1040 BC 9thFloor InstallSprinklers 14 0.00% 0.00% 8Mar17 23Mar17 13Feb17 28Feb17 20 27 OnTarget
BC9FMEPF1050 BC 9thFloor InstallSwitchesandSockets 14 0.00% 0.00% 8Mar17 23Mar17 13Feb17 28Feb17 20 27 OnTarget
BC9FMEPF1060 BC 9thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 9Mar17 25Mar17 14Feb17 1Mar17 20 27 OnTarget
BC9FMEPF1070 BC 9thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 9Mar17 25Mar17 14Feb17 1Mar17 20 27 OnTarget
BC9FMEPF1075 BC 9thFloor MEPFinalFixes/Sanitarywares 18 0.00% 0.00% 1Mar17 21Mar17 6Feb17 26Feb17 20 24 OnTarget
BC9FMEPF1080 BC 9thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 9Mar17 25Mar17 14Feb17 1Mar17 20 27 OnTarget
Tenthfloor 113 0.00% 0.00% 7Dec16 17Apr17 26Nov16A 11Apr17 5 44 OnTarget
DryArea 59 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPworks 42 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC10FMEPD1000 BC 10thFloor DryAreaMEPScreedclearance 10 0.00% 55.00% 12Jan17 23Jan17 26Nov16A 17Jan17 5 57 OnTarget
BC10FMEPD1010 BC 10thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 0.00% 12Jan17 23Jan17 12Jan17 24Jan17 0 27 OnTarget
BC10FMEPD1020 BC 10thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 5Feb17 15Feb17 30Jan17 11Feb17 5 27 OnTarget
BC10FMEPD1030 BC 10thFloor InstallElectricalWiring 10 10.00% 50.00% 29Dec16 9Jan17 27Nov16A 14Jan17 4 6 OnTarget
BC10FMEPD1040 BC 10thFloor InstallLowCurrentWiring 10 0.00% 13.00% 5Jan17 16Jan17 27Nov16A 21Jan17 4 113 OnTarget
BC10FMEPD1050 BC 10thFloor InstallHVACPipes 10 0.00% 72.00% 5Jan17 16Jan17 27Nov16A 2Jan17 12 39 OnTarget
BC10FMEPD1060 BC 10thFloor Firefightingpipes 10 0.00% 98.00% 9Jan17 19Jan17 27Nov16A 5Jan17 12 39 OnTarget
BC10FMEPD1070 BC 10thFloor InstallDuctsandHangers 16 0.00% 2.00% 5Jan17 23Jan17 27Nov16A 17Jan17 5 32 OnTarget
BC10FMEPD1080 BC 10thFloor DBInstallation 10 0.00% 20.00% 24Jan17 4Feb17 27Nov16A 8Jan17 23 45 OnTarget
BC10FMEPD1090 BC 10thFloor InstallDroppers 12 0.00% 0.00% 24Jan17 6Feb17 24Jan17 7Feb17 0 27 OnTarget
BC10FMEPD1100 BC 10thFloor MeggeringTest 10 0.00% 0.00% 5Feb17 15Feb17 30Jan17 11Feb17 5 27 OnTarget
WetArea 73 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPworks 67 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC10FMEPW1000 BC 10thFloor WetAreaScreedMEpClearance 10 0.00% 77.00% 16Jan17 26Jan17 26Nov16A 30Jan17 3 2 OnTarget
BC10FMEPW1010 BC 10thFloor WetAreaHLClearancebyARMAforgridfixing 10 0.00% 0.00% 28Jan17 7Feb17 16Jan17 26Jan17 10 13 OnTarget
BC10FMEPW1020 BC 10thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 28Feb17 11Mar17 16Feb17 27Feb17 10 13 OnTarget
BC10FMEPW1030 BC 10thFloor InstallElectricalWiring 18 33.33% 47.00% 24Dec16 12Jan17 27Nov16A 17Jan17 4 2 OnTarget
BC10FMEPW1040 BC 10thFloor InstallDrainagepipes 18 27.78% 83.00% 25Dec16 14Jan17 27Nov16A 18Jan17 4 2 OnTarget
BC10FMEPW1050 BC 10thFloor InstallHot&ColdWaterPiping 18 22.22% 57.00% 26Dec16 15Jan17 27Nov16A 19Jan17 4 2 OnTarget
BC10FMEPW1060 BC 10thFloor InstallHVACPipes 12 0.00% 72.00% 5Jan17 18Jan17 27Nov16A 23Jan17 4 2 OnTarget
BC10FMEPW1070 BC 10thFloor Firefightingpipes 10 0.00% 95.00% 9Jan17 19Jan17 27Nov16A 24Jan17 4 1 OnTarget
BC10FMEPW1080 BC 10thFloor InstallDuctsandHangers 16 0.00% 0.00% 4Jan17 22Jan17 9Jan17 26Jan17 4 2 OnTarget
BC10FMEPW1090 BC 10thFloor InstallDroppers 12 0.00% 0.00% 19Feb17 4Mar17 7Feb17 20Feb17 10 19 OnTarget
BC10FMEPW1100 BC 10thFloor MeggeringTest 10 0.00% 0.00% 21Feb17 4Mar17 9Feb17 20Feb17 10 19 OnTarget
CorridorLiftLobby 67 0.00% 0.00% 27Dec16 2Mar17 26Nov16A 25Feb17 5 83 OnTarget
MEPworks 51 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC10FMEPCL1000 BC 10thFloor CorridorScreedMEpClearance 6 0.00% 0.00% 18Feb17 23Feb17 22Jan17 28Jan17 23 64 OnTarget
BC10FMEPCL1010 BC 10thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 7Feb17 18Feb17 11Jan17 22Jan17 23 30 OnTarget
BC10FMEPCL1020 BC 10thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 22Feb17 5Mar17 26Jan17 6Feb17 23 29 OnTarget
BC10FMEPCL1030 BC 10thFloor InstallElectricalWiring 10 0.00% 0.00% 5Jan17 16Jan17 10Jan17 21Jan17 4 113 OnTarget
BC10FMEPCL1050 BC 10thFloor InstallHot&ColdWaterPiping 12 0.00% 54.00% 21Jan17 2Feb17 27Nov16A 5Jan17 24 30 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BC10FMEPCL1060 BC 10thFloor InstallHVACPipes 10 0.00% 80.00% 26Jan17 6Feb17 27Nov16A 9Jan17 24 30 OnTarget
BC10FMEPCL1070 BC 10thFloor InstallDuctsandHangers 12 0.00% 40.00% 28Jan17 9Feb17 27Nov16A 12Jan17 24 30 OnTarget
BC10FMEPCL1080 BC 10thFloor InstallCableTraysandTrunking 16 0.00% 0.00% 26Jan17 13Feb17 31Dec16 17Jan17 23 29 OnTarget
BC10FMEPCL1085 BC 10thFloor InstallLowCurrentWiring 10 0.00% 13.00% 6Feb17 16Feb17 27Nov16A 21Jan17 23 30 OnTarget
BC10FMEPCL1090 BC 10thFloor InstallLVCables 10 0.00% 0.00% 6Feb17 16Feb17 10Jan17 21Jan17 23 29 OnTarget
BC10FMEPCL1100 BC 10thFloor InstallDroppers 14 0.00% 0.00% 18Feb17 5Mar17 22Jan17 6Feb17 23 29 OnTarget
BC10FMEPCL1110 BC 10thFloor MeggeringTest 10 0.00% 0.00% 22Feb17 5Mar17 26Jan17 6Feb17 23 29 OnTarget
CommonFinalFinishes 41 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPworks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC10FMEPF1010 BC 10thFloor InstallLightFittings 14 0.00% 0.00% 7Mar17 22Mar17 23Feb17 11Mar17 10 16 OnTarget
BC10FMEPF1020 BC 10thFloor InstallFireCabinets 14 0.00% 0.00% 8Mar17 23Mar17 25Feb17 12Mar17 10 16 OnTarget
BC10FMEPF1030 BC 10thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 8Mar17 23Mar17 25Feb17 12Mar17 10 16 OnTarget
BC10FMEPF1040 BC 10thFloor InstallSprinklers 14 0.00% 0.00% 9Mar17 25Mar17 26Feb17 13Mar17 10 16 OnTarget
BC10FMEPF1050 BC 10thFloor InstallSwitchesandSockets 14 0.00% 0.00% 9Mar17 25Mar17 26Feb17 13Mar17 10 16 OnTarget
BC10FMEPF1060 BC 10thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 11Mar17 26Mar17 27Feb17 14Mar17 10 16 OnTarget
BC10FMEPF1070 BC 10thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 11Mar17 26Mar17 27Feb17 14Mar17 10 16 OnTarget
BC10FMEPF1075 BC 10thFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 12Mar17 22Mar17 28Feb17 11Mar17 10 13 OnTarget
BC10FMEPF1080 BC 10thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 11Mar17 26Mar17 27Feb17 14Mar17 10 16 OnTarget
11thFloor 120 0.00% 0.00% 5Dec16 23Apr17 26Nov16A 11Apr17 10 44 OnTarget
DryArea 63 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPworks 44 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC11FMEPD1000 BC 11thFloor DryAreaMEPScreedclearance 10 0.00% 100.00% 23Jan17 2Feb17 26Nov16A 26Nov16A 60 0 OnTarget
BC11FMEPD1010 BC 11thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 0.00% 16Jan17 26Jan17 7Jan17 18Jan17 8 36 OnTarget
BC11FMEPD1020 BC 11thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 8Feb17 19Feb17 21Jan17 1Feb17 16 36 OnTarget
BC11FMEPD1040 BC 11thFloor InstallElectricalWiring 12 0.00% 43.00% 31Dec16 12Jan17 27Nov16A 17Jan17 4 6 OnTarget
BC11FMEPD1050 BC 11thFloor InstallLowCurrentWiring 12 0.00% 10.00% 7Jan17 19Jan17 27Nov16A 24Jan17 4 110 OnTarget
BC11FMEPD1060 BC 11thFloor InstallHVACPipes 12 0.00% 38.00% 7Jan17 19Jan17 27Nov16A 8Jan17 11 38 OnTarget
BC11FMEPD1070 BC 11thFloor Firefightingpipes 10 0.00% 78.00% 12Jan17 23Jan17 27Nov16A 11Jan17 11 38 OnTarget
BC11FMEPD1080 BC 11thFloor InstallDuctsandHangers 16 0.00% 0.00% 9Jan17 26Jan17 31Dec16 17Jan17 8 36 OnTarget
BC11FMEPD1090 BC 11thFloor DBInstallation 10 0.00% 20.00% 28Jan17 7Feb17 27Nov16A 8Jan17 26 46 OnTarget
BC11FMEPD1100 BC 11thFloor InstallDroppers 12 0.00% 0.00% 28Jan17 9Feb17 18Jan17 1Feb17 8 36 OnTarget
BC11FMEPD1110 BC 11thFloor MeggeringTest 10 0.00% 0.00% 8Feb17 19Feb17 21Jan17 1Feb17 16 36 OnTarget
WetArea 62 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPworks 59 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC11FMEPW1000 BC 11thFloor WetAreaScreedMEpClearance 10 0.00% 70.00% 22Jan17 1Feb17 26Nov16A 6Feb17 4 1 OnTarget
BC11FMEPW1010 BC 11thFloor WetAreaHLClearancebyARMAforgridfixing 18 0.00% 0.00% 29Jan17 18Feb17 10Jan17 30Jan17 16 25 OnTarget
BC11FMEPW1020 BC 11thFloor WetAreaMEPclearanceforBoardclosing 18 0.00% 0.00% 20Feb17 12Mar17 1Feb17 21Feb17 16 25 OnTarget
BC11FMEPW1030 BC 11thFloor InstallElectricalWiring 12 0.00% 24.00% 3Jan17 16Jan17 27Nov16A 21Jan17 4 1 OnTarget
BC11FMEPW1040 BC 11thFloor InstallDrainagepipes 10 0.00% 25.00% 7Jan17 17Jan17 27Nov16A 22Jan17 4 1 OnTarget
BC11FMEPW1050 BC 11thFloor InstallHot&ColdWaterPiping 10 0.00% 55.00% 8Jan17 18Jan17 27Nov16A 23Jan17 4 1 OnTarget
BC11FMEPW1060 BC 11thFloor InstallHVACPipes 12 0.00% 38.00% 9Jan17 22Jan17 27Nov16A 26Jan17 4 1 OnTarget
BC11FMEPW1070 BC 11thFloor Firefightingpipes 7 0.00% 78.00% 16Jan17 23Jan17 27Nov16A 28Jan17 4 2 OnTarget
BC11FMEPW1080 BC 11thFloor InstallDuctsandHangers 16 0.00% 0.00% 8Jan17 25Jan17 12Jan17 30Jan17 4 1 OnTarget
BC11FMEPW1090 BC 11thFloor InstallDroppers 12 0.00% 0.00% 23Feb17 8Mar17 5Feb17 18Feb17 16 25 OnTarget
BC11FMEPW1100 BC 11thFloor MeggeringTest 7 0.00% 0.00% 5Mar17 12Mar17 14Feb17 21Feb17 16 25 OnTarget
CorridorLiftLobby 66 0.00% 0.00% 27Dec16 2Mar17 26Nov16A 25Feb17 5 83 OnTarget
MEPworks 44 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC11FMEPCL1000 BC 11thFloor CorridorScreedMEpClearance 12 0.00% 95.00% 31Jan17 13Feb17 26Nov16A 18Feb17 4 41 OnTarget
BC11FMEPCL1010 BC 11thFloor CorridorHLClearancebyARMAforgridfixing 21 0.00% 0.00% 17Jan17 9Feb17 22Jan17 14Feb17 4 12 OnTarget
BC11FMEPCL1020 BC 11thFloor CorridorMEPclearanceforBoardclosing 18 0.00% 0.00% 6Feb17 26Feb17 11Feb17 2Mar17 4 12 OnTarget
BC11FMEPCL1030 BC 11thFloor InstallElectricalWiring 12 0.00% 30.00% 7Jan17 19Jan17 27Nov16A 24Jan17 4 12 OnTarget
BC11FMEPCL1050 BC 11thFloor InstallHot&ColdWaterPiping 10 0.00% 52.00% 12Jan17 23Jan17 27Nov16A 28Jan17 4 12 OnTarget
BC11FMEPCL1060 BC 11thFloor InstallHVACPipes 10 0.00% 80.00% 16Jan17 26Jan17 27Nov16A 31Jan17 4 12 OnTarget
BC11FMEPCL1070 BC 11thFloor InstallDuctsandHangers 14 0.00% 5.00% 15Jan17 30Jan17 27Nov16A 4Feb17 4 12 OnTarget
BC11FMEPCL1080 BC 11thFloor InstallCableTraysandTrunking 16 0.00% 0.00% 16Jan17 2Feb17 21Jan17 7Feb17 4 12 OnTarget
BC11FMEPCL1085 BC 11thFloor InstallLowCurrentWiring 10 0.00% 10.00% 26Jan17 6Feb17 27Nov16A 11Feb17 4 12 OnTarget
BC11FMEPCL1090 BC 11thFloor InstallLVCables 7 0.00% 0.00% 30Jan17 6Feb17 4Feb17 11Feb17 4 15 OnTarget
BC11FMEPCL1100 BC 11thFloor InstallDroppers 14 0.00% 0.00% 7Feb17 22Feb17 12Feb17 27Feb17 4 15 OnTarget
BC11FMEPCL1110 BC 11thFloor MeggeringTest 7 0.00% 0.00% 15Feb17 22Feb17 20Feb17 27Feb17 4 15 OnTarget
CommonFinalFinishes 44 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPworks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC11FMEPF1010 BC 11thFloor InstallLightFittings 14 0.00% 0.00% 4Mar17 19Mar17 28Feb17 15Mar17 3 12 OnTarget
BC11FMEPF1020 BC 11thFloor InstallFireCabinets 14 0.00% 0.00% 5Mar17 20Mar17 1Mar17 16Mar17 3 12 OnTarget
BC11FMEPF1030 BC 11thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 5Mar17 20Mar17 1Mar17 16Mar17 3 12 OnTarget
BC11FMEPF1040 BC 11thFloor InstallSprinklers 14 0.00% 0.00% 6Mar17 21Mar17 2Mar17 18Mar17 3 12 OnTarget
BC11FMEPF1050 BC 11thFloor InstallSwitchesandSockets 14 0.00% 0.00% 6Mar17 21Mar17 2Mar17 18Mar17 3 12 OnTarget
BC11FMEPF1060 BC 11thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 7Mar17 22Mar17 4Mar17 19Mar17 3 12 OnTarget
BC11FMEPF1070 BC 11thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 7Mar17 22Mar17 4Mar17 19Mar17 3 12 OnTarget
BC11FMEPF1075 BC 11thFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 9Mar17 20Mar17 6Mar17 16Mar17 3 14 OnTarget
BC11FMEPF1080 BC 11thFloor InstallPlumpingFinalFittings(FloorDrains,Floortraps 14 0.00% 0.00% 7Mar17 22Mar17 4Mar17 19Mar17 3 12 OnTarget
12thFloor 115 0.00% 0.00% 7Dec16 19Apr17 26Nov16A 11Apr17 7 44 OnTarget
DryArea 62 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPworks 43 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC12FMEPD1000 BC 12thFloor DraAreaMEPScreedclearance 10 0.00% 70.00% 19Jan17 30Jan17 26Nov16A 26Jan17 4 49 OnTarget
BC12FMEPD1010 BC 12thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 0.00% 12Jan17 23Jan17 11Jan17 23Jan17 1 31 OnTarget
BC12FMEPD1020 BC 12thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 5Feb17 15Feb17 25Jan17 6Feb17 9 31 OnTarget
BC12FMEPD1040 BC 12thFloor InstallElectricalWiring 14 14.29% 18.00% 28Dec16 12Jan17 15Dec16A 17Jan17 4 6 OnTarget
BC12FMEPD1050 BC 12thFloor InstallLowCurrentWiring 14 0.00% 10.00% 1Jan17 16Jan17 27Nov16A 21Jan17 4 113 OnTarget
BC12FMEPD1060 BC 12thFloor InstallHVACPipes 14 0.00% 19.00% 1Jan17 16Jan17 27Nov16A 12Jan17 4 33 OnTarget
BC12FMEPD1070 BC 12thFloor Firefightingpipes 10 0.00% 0.00% 9Jan17 19Jan17 4Jan17 16Jan17 4 33 OnTarget
BC12FMEPD1080 BC 12thFloor InstallDuctsandHangers 16 0.00% 0.00% 5Jan17 23Jan17 1Jan17 19Jan17 4 33 OnTarget
BC12FMEPD1090 BC 12thFloor DBInstallation 10 0.00% 20.00% 24Jan17 4Feb17 27Nov16A 8Jan17 23 45 OnTarget
BC12FMEPD1100 BC 12thFloor InstallDroppers 12 0.00% 0.00% 24Jan17 6Feb17 23Jan17 6Feb17 1 31 OnTarget
BC12FMEPD1110 BC 12thFloor MeggeringTest 10 0.00% 0.00% 5Feb17 15Feb17 25Jan17 6Feb17 9 31 OnTarget
WetArea 57 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPworks 51 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC12FMEPW1000 BC 12thFloor WetAreaScreedMEpClearance 12 0.00% 62.00% 19Jan17 1Feb17 26Nov16A 2Feb17 1 3 OnTarget
BC12FMEPW1010 BC 12thFloor WetAreaHLClearancebyARMAforgridfixing 10 0.00% 0.00% 26Jan17 6Feb17 19Jan17 30Jan17 6 16 OnTarget
BC12FMEPW1020 BC 12thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 20Feb17 2Mar17 13Feb17 23Feb17 6 16 OnTarget
BC12FMEPW1030 BC 12thFloor InstallElectricalWiring 12 0.00% 0.00% 3Jan17 16Jan17 8Jan17 21Jan17 4 3 OnTarget
BC12FMEPW1040 BC 12thFloor InstallDrainagepipes 10 0.00% 30.00% 7Jan17 17Jan17 27Nov16A 22Jan17 4 3 OnTarget
BC12FMEPW1050 BC 12thFloor InstallHot&ColdWaterPiping 10 0.00% 27.00% 8Jan17 18Jan17 05Dec16A 23Jan17 4 3 OnTarget
BC12FMEPW1060 BC 12thFloor InstallHVACPipes 12 0.00% 18.00% 9Jan17 22Jan17 27Nov16A 26Jan17 4 3 OnTarget
BC12FMEPW1070 BC 12thFloor Firefightingpipes 10 0.00% 0.00% 12Jan17 23Jan17 17Jan17 28Jan17 4 2 OnTarget
BC12FMEPW1080 BC 12thFloor InstallDuctsandHangers 16 0.00% 0.00% 8Jan17 25Jan17 12Jan17 30Jan17 4 3 OnTarget
BC12FMEPW1090 BC 12thFloor InstallDroppers 12 0.00% 0.00% 11Feb17 23Feb17 4Feb17 16Feb17 6 22 OnTarget
BC12FMEPW1100 BC 12thFloor MeggeringTest 10 0.00% 0.00% 13Feb17 23Feb17 6Feb17 16Feb17 6 22 OnTarget
CorridorLiftLobby 61 0.00% 0.00% 27Dec16 2Mar17 26Nov16A 25Feb17 5 83 OnTarget
MEPworks 41 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC12FMEPCL1000 BC 12thFloor CorridorScreedMEpClearance 12 0.00% 50.00% 28Jan17 9Feb17 18Dec16A 14Feb17 4 92 OnTarget
BC12FMEPCL1010 BC 12thFloor CorridorHLClearancebyARMAforgridfixing 21 0.00% 0.00% 17Jan17 9Feb17 16Jan17 8Feb17 1 17 OnTarget
BC12FMEPCL1020 BC 12thFloor CorridorMEPclearanceforBoardclosing 12 0.00% 0.00% 8Feb17 21Feb17 8Feb17 21Feb17 0 16 OnTarget
BC12FMEPCL1030 BC 12thFloor InstallElectricalWiring 10 0.00% 0.00% 5Jan17 16Jan17 10Jan17 21Jan17 4 16 OnTarget
BC12FMEPCL1050 BC 12thFloor InstallHot&ColdWaterPiping 10 0.00% 0.00% 9Jan17 19Jan17 14Jan17 24Jan17 4 16 OnTarget
BC12FMEPCL1060 BC 12thFloor Firefightingpipes 7 0.00% 95.00% 12Jan17 19Jan17 27Nov16A 24Jan17 4 16 OnTarget
BC12FMEPCL1070 BC 12thFloor InstallHVACPipes 10 0.00% 80.00% 12Jan17 23Jan17 27Nov16A 28Jan17 4 16 OnTarget
BC12FMEPCL1080 BC 12thFloor InstallDuctsandHangers 16 0.00% 5.00% 9Jan17 26Jan17 27Nov16A 31Jan17 4 16 OnTarget
BC12FMEPCL1090 BC 12thFloor InstallCableTraysandTrunking 12 0.00% 0.00% 17Jan17 30Jan17 22Jan17 4Feb17 4 16 OnTarget
BC12FMEPCL1095 BC 12thFloor InstallLowCurrentWiring 10 0.00% 10.00% 23Jan17 2Feb17 27Nov16A 7Feb17 4 17 OnTarget
BC12FMEPCL1100 BC 12thFloor InstallLVCables 7 0.00% 0.00% 26Jan17 2Feb17 31Jan17 7Feb17 4 16 OnTarget
BC12FMEPCL1110 BC 12thFloor InstallDroppers 12 0.00% 0.00% 8Feb17 21Feb17 8Feb17 21Feb17 0 16 OnTarget
BC12FMEPCL1120 BC 12thFloor MeggeringTest 7 0.00% 0.00% 14Feb17 21Feb17 14Feb17 21Feb17 0 16 OnTarget
CommonFinalFinishes 45 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPworks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC12FMEPF1010 BC 12thFloor InstallLightFittings 14 0.00% 0.00% 27Feb17 14Mar17 20Feb17 7Mar17 6 19 OnTarget
BC12FMEPF1020 BC 12thFloor InstallFireCabinets 14 0.00% 0.00% 28Feb17 15Mar17 21Feb17 8Mar17 6 19 OnTarget
BC12FMEPF1030 BC 12thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 28Feb17 15Mar17 21Feb17 8Mar17 6 19 OnTarget
BC12FMEPF1040 BC 12thFloor InstallSprinklers 14 0.00% 0.00% 1Mar17 16Mar17 22Feb17 9Mar17 6 19 OnTarget
BC12FMEPF1050 BC 12thFloor InstallSwitchesandSockets 14 0.00% 0.00% 1Mar17 16Mar17 22Feb17 9Mar17 6 19 OnTarget
BC12FMEPF1060 BC 12thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 2Mar17 18Mar17 23Feb17 11Mar17 6 19 OnTarget
BC12FMEPF1070 BC 12thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 2Mar17 18Mar17 23Feb17 11Mar17 6 19 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BC12FMEPF1075 BC 12thFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 4Mar17 14Mar17 25Feb17 7Mar17 6 16 OnTarget
BC12FMEPF1080 BC 12thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 2Mar17 18Mar17 23Feb17 11Mar17 6 19 OnTarget
13thFloor 110 0.00% 0.00% 12Dec16 18Apr17 23Nov16A 11Apr17 6 44 OnTarget
General 22 0.00% 0.00% 27Nov16 3Jan17 27Nov16A 17Jan17 11 117 OnTarget
BC13F1000 BC 13thFloor PlasterMEpClearance(H0108,A0107) 14 100.00% 100.00% 12Dec16 27Dec16 11Dec16A 15Dec16A 11 0 OnTarget
DryArea 52 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPworks 33 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC13FMEPD1000 BC 13thFloor DraAreaMEPScreedclearance 10 0.00% 100.00% 25Jan17 5Feb17 26Nov16A 26Nov16A 62 0 OnTarget
BC13FMEPD1010 BC 13thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 0.00% 18Jan17 29Jan17 5Jan17 17Jan17 10 10 OnTarget
BC13FMEPD1020 BC 13thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 1Feb17 12Feb17 19Jan17 31Jan17 10 10 OnTarget
BC13FMEPD1040 BC 13thFloor InstallElectricalWiring 10 0.00% 5.00% 5Jan17 16Jan17 15Dec16A 21Jan17 4 6 OnTarget
BC13FMEPD1050 BC 13thFloor InstallLowCurrentWiring 10 0.00% 0.00% 9Jan17 19Jan17 14Jan17 24Jan17 4 110 OnTarget
BC13FMEPD1060 BC 13thFloor InstallHVACPipes 12 0.00% 20.00% 9Jan17 22Jan17 23Nov16A 10Jan17 10 10 OnTarget
BC13FMEPD1070 BC 13thFloor Firefightingpipes 10 0.00% 0.00% 15Jan17 25Jan17 2Jan17 14Jan17 10 10 OnTarget
BC13FMEPD1080 BC 13thFloor InstallDuctsandHangers 14 0.00% 0.00% 14Jan17 29Jan17 1Jan17 17Jan17 10 10 OnTarget
BC13FMEPD1090 BC 13thFloor DBInstallation 10 0.00% 0.00% 18Jan17 29Jan17 5Jan17 17Jan17 10 12 OnTarget
BC13FMEPD1100 BC 13thFloor InstallDroppers 12 0.00% 0.00% 30Jan17 12Feb17 17Jan17 31Jan17 10 10 OnTarget
BC13FMEPD1110 BC 13thFloor MeggeringTest 10 0.00% 0.00% 1Feb17 12Feb17 19Jan17 31Jan17 10 10 OnTarget
WetArea 63 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPworks 57 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC13FMEPW1000 BC 13thFloor WetAreaScreedMEpClearance 12 0.00% 58.00% 23Jan17 5Feb17 26Nov16A 9Feb17 4 6 OnTarget
BC13FMEPW1010 BC 13thFloor WetAreaHLClearancebyARMAforgridfixing 18 0.00% 0.00% 30Jan17 19Feb17 14Jan17 2Feb17 14 16 OnTarget
BC13FMEPW1020 BC 13thFloor WetAreaMEPclearanceforBoardclosing 18 0.00% 0.00% 23Feb17 15Mar17 7Feb17 27Feb17 14 16 OnTarget
BC13FMEPW1030 BC 13thFloor InstallElectricalWiring 10 0.00% 0.00% 9Jan17 19Jan17 14Jan17 24Jan17 4 6 OnTarget
BC13FMEPW1040 BC 13thFloor InstallDrainagepipes 10 0.00% 24.00% 10Jan17 21Jan17 23Dec16A 25Jan17 4 6 OnTarget
BC13FMEPW1050 BC 13thFloor InstallHot&ColdWaterPiping 10 0.00% 0.00% 11Jan17 22Jan17 16Jan17 26Jan17 4 6 OnTarget
BC13FMEPW1060 BC 13thFloor InstallHVACPipes 12 0.00% 20.00% 12Jan17 25Jan17 23Dec16A 30Jan17 4 6 OnTarget
BC13FMEPW1070 BC 13thFloor Firefightingpipes 7 0.00% 0.00% 19Jan17 26Jan17 24Jan17 31Jan17 4 5 OnTarget
BC13FMEPW1080 BC 13thFloor InstallDuctsandHangers 16 0.00% 0.00% 11Jan17 29Jan17 16Jan17 2Feb17 4 6 OnTarget
BC13FMEPW1090 BC 13thFloor InstallDroppers 12 0.00% 0.00% 23Feb17 8Mar17 7Feb17 20Feb17 14 22 OnTarget
BC13FMEPW1100 BC 13thFloor MeggeringTest 7 0.00% 0.00% 1Mar17 8Mar17 13Feb17 20Feb17 14 22 OnTarget
CorridorLiftLobby 71 0.00% 0.00% 27Dec16 2Mar17 26Nov16A 25Feb17 5 83 OnTarget
MEPworks 52 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC13FMEPCL1000 BC 13thFloor CorridorScreedMEpClearance 12 0.00% 100.00% 23Jan17 5Feb17 26Nov16A 19Dec16A 42 0 OnTarget
BC13FMEPCL1010 BC 13thFloor CorridorHLClearancebyARMAforgridfixing 21 0.00% 0.00% 30Jan17 22Feb17 14Jan17 6Feb17 14 16 OnTarget
BC13FMEPCL1020 BC 13thFloor CorridorMEPclearanceforBoardclosing 18 0.00% 0.00% 21Feb17 13Mar17 8Feb17 28Feb17 11 13 OnTarget
BC13FMEPCL1030 BC 13thFloor InstallElectricalWiring 10 0.00% 0.00% 12Jan17 23Jan17 17Jan17 28Jan17 4 13 OnTarget
BC13FMEPCL1050 BC 13thFloor InstallHot&ColdWaterPiping 10 0.00% 0.00% 16Jan17 26Jan17 21Jan17 31Jan17 4 13 OnTarget
BC13FMEPCL1060 BC 13thFloor Firefightingpipes 7 0.00% 0.00% 19Jan17 26Jan17 24Jan17 31Jan17 4 13 OnTarget
BC13FMEPCL1070 BC 13thFloor InstallHVACPipes 12 0.00% 60.00% 17Jan17 30Jan17 27Nov16A 4Feb17 4 13 OnTarget
BC13FMEPCL1080 BC 13thFloor InstallDuctsandHangers 14 0.00% 0.00% 18Jan17 2Feb17 23Jan17 7Feb17 4 13 OnTarget
BC13FMEPCL1090 BC 13thFloor InstallCableTraysandTrunking 14 0.00% 0.00% 22Jan17 6Feb17 26Jan17 11Feb17 4 13 OnTarget
BC13FMEPCL1095 BC 13thFloor InstallLowCurrentWiring 10 0.00% 10.00% 7Feb17 18Feb17 27Nov16A 9Jan17 34 37 OnTarget
BC13FMEPCL1100 BC 13thFloor InstallLVCables 7 0.00% 0.00% 2Feb17 9Feb17 7Feb17 14Feb17 4 13 OnTarget
BC13FMEPCL1110 BC 13thFloor InstallDroppers 12 0.00% 0.00% 11Feb17 23Feb17 15Feb17 28Feb17 4 13 OnTarget
BC13FMEPCL1120 BC 13thFloor MeggeringTest 7 0.00% 0.00% 16Feb17 23Feb17 21Feb17 28Feb17 4 13 OnTarget
CommonFinalFinishes 41 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPworks 24 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC13FMEPF1005 BC 13thFloor InstallGYMEquipment 24 0.00% 0.00% 7Mar17 3Apr17 22Feb17 22Mar17 10 10 OnTarget
BC13FMEPF1010 BC 13thFloor InstallLightFittings 14 0.00% 0.00% 12Mar17 27Mar17 27Feb17 14Mar17 11 13 OnTarget
BC13FMEPF1020 BC 13thFloor InstallFireCabinets 14 0.00% 0.00% 13Mar17 28Mar17 28Feb17 15Mar17 11 13 OnTarget
BC13FMEPF1030 BC 13thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 13Mar17 28Mar17 28Feb17 15Mar17 11 13 OnTarget
BC13FMEPF1040 BC 13thFloor InstallSprinklers 14 0.00% 0.00% 14Mar17 29Mar17 1Mar17 16Mar17 11 13 OnTarget
BC13FMEPF1050 BC 13thFloor InstallSwitchesandSockets 14 0.00% 0.00% 14Mar17 29Mar17 1Mar17 16Mar17 11 13 OnTarget
BC13FMEPF1060 BC 13thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 15Mar17 30Mar17 2Mar17 18Mar17 11 13 OnTarget
BC13FMEPF1070 BC 13thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 15Mar17 30Mar17 2Mar17 18Mar17 11 13 OnTarget
BC13FMEPF1075 BC 13thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 14Mar17 27Mar17 1Mar17 14Mar17 11 16 OnTarget
BC13FMEPF1080 BC 13thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 15Mar17 30Mar17 2Mar17 18Mar17 11 13 OnTarget
14thFloor 100 0.00% 0.00% 19Dec16 13Apr17 23Nov16A 16Apr17 2 40 OnTarget
DryArea 50 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPworks 33 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC14FMEPD1000 BC 14F DraAreaMEPScreedclearance 10 0.00% 100.00% 25Jan17 5Feb17 02Dec16A 19Dec16A 42 0 OnTarget
BC14FMEPD1010 BC 14F DryAreaMEPHLClearancebyARMAforgridfixing 12 0.00% 0.00% 16Jan17 29Jan17 10Jan17 23Jan17 5 26 OnTarget
BC14FMEPD1020 BC 14F DryAreaMEPclearanceforBoardclosing 12 0.00% 0.00% 30Jan17 12Feb17 24Jan17 6Feb17 5 26 OnTarget
BC14FMEPD1040 BC 14F InstallElectricalWiring 10 0.00% 0.00% 5Jan17 16Jan17 10Jan17 21Jan17 4 1 OnTarget
BC14FMEPD1050 BC 14F InstallLowCurrentWiring 10 0.00% 0.00% 9Jan17 19Jan17 14Jan17 24Jan17 4 110 OnTarget
BC14FMEPD1060 BC 14F InstallHVACPipes 12 0.00% 20.00% 9Jan17 22Jan17 23Nov16A 10Jan17 10 10 OnTarget
BC14FMEPD1070 BC 14F Firefightingpipes 10 0.00% 0.00% 15Jan17 25Jan17 2Jan17 14Jan17 10 10 OnTarget
BC14FMEPD1080 BC 14F InstallDuctsandHangers 14 0.00% 0.00% 14Jan17 29Jan17 1Jan17 17Jan17 10 10 OnTarget
BC14FMEPD1090 BC 14F DBInstallation 10 0.00% 0.00% 18Jan17 29Jan17 5Jan17 17Jan17 10 10 OnTarget
BC14FMEPD1100 BC 14F InstallDroppers 12 0.00% 0.00% 30Jan17 12Feb17 24Jan17 6Feb17 5 26 OnTarget
BC14FMEPD1110 BC 14F MeggeringTest 10 0.00% 0.00% 1Feb17 12Feb17 26Jan17 6Feb17 5 26 OnTarget
WetArea 56 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPworks 50 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC14FMEPW1000 BC 14F WetAreaScreedMEpClearance 6 0.00% 95.00% 2Feb17 8Feb17 25Dec16A 13Feb17 4 2 OnTarget
BC14FMEPW1010 BC 14F WetAreaHLClearancebyARMAforgridfixing 10 0.00% 0.00% 22Jan17 1Feb17 26Jan17 6Feb17 4 1 OnTarget
BC14FMEPW1020 BC 14F WetAreaMEPclearanceforBoardclosing 12 0.00% 0.00% 23Feb17 8Mar17 28Feb17 13Mar17 4 1 OnTarget
BC14FMEPW1030 BC 14F InstallElectricalWiring 12 0.00% 0.00% 10Jan17 23Jan17 15Jan17 28Jan17 4 1 OnTarget
BC14FMEPW1040 BC 14F InstallDrainagepipes 10 0.00% 0.00% 14Jan17 24Jan17 18Jan17 29Jan17 4 1 OnTarget
BC14FMEPW1050 BC 14F InstallHot&ColdWaterPiping 10 0.00% 0.00% 15Jan17 25Jan17 19Jan17 30Jan17 4 1 OnTarget
BC14FMEPW1060 BC 14F InstallHVACPipes 12 0.00% 20.00% 16Jan17 29Jan17 23Dec16A 2Feb17 4 1 OnTarget
BC14FMEPW1070 BC 14F Firefightingpipes 5 0.00% 0.00% 25Jan17 30Jan17 30Jan17 4Feb17 4 0 OnTarget
BC14FMEPW1080 BC 14F InstallDuctsandHangers 14 0.00% 0.00% 17Jan17 1Feb17 22Jan17 6Feb17 4 1 OnTarget
BC14FMEPW1090 BC 14F InstallDroppers 10 0.00% 0.00% 19Feb17 1Mar17 23Feb17 6Mar17 4 5 OnTarget
BC14FMEPW1100 BC 14F MeggeringTest 5 0.00% 0.00% 25Feb17 1Mar17 1Mar17 6Mar17 4 5 OnTarget
CorridorLiftLobby 54 0.00% 0.00% 27Dec16 2Mar17 26Nov16A 25Feb17 5 83 OnTarget
MEPworks 38 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC14FMEPCL1000 BC 14F CorridorScreedMEpClearance 6 0.00% 0.00% 11Feb17 16Feb17 15Feb17 21Feb17 4 43 OnTarget
BC14FMEPCL1010 BC 14F CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 31Jan17 11Feb17 5Feb17 15Feb17 4 8 OnTarget
BC14FMEPCL1020 BC 14F CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 14Feb17 25Feb17 19Feb17 1Mar17 4 8 OnTarget
BC14FMEPCL1030 BC 14F InstallElectricalWiring 10 0.00% 0.00% 12Jan17 23Jan17 17Jan17 28Jan17 4 8 OnTarget
BC14FMEPCL1050 BC 14F InstallHot&ColdWaterPiping 10 0.00% 0.00% 16Jan17 26Jan17 21Jan17 31Jan17 4 8 OnTarget
BC14FMEPCL1060 BC 14F Firefightingpipes 10 0.00% 0.00% 16Jan17 26Jan17 21Jan17 31Jan17 4 8 OnTarget
BC14FMEPCL1070 BC 14F InstallHVACPipes 10 0.00% 60.00% 19Jan17 30Jan17 27Nov16A 4Feb17 4 8 OnTarget
BC14FMEPCL1080 BC 14F InstallDuctsandHangers 12 0.00% 0.00% 21Jan17 2Feb17 25Jan17 7Feb17 4 8 OnTarget
BC14FMEPCL1090 BC 14F InstallCableTraysandTrunking 12 0.00% 0.00% 24Jan17 6Feb17 29Jan17 11Feb17 4 8 OnTarget
BC14FMEPCL1095 BC 14F InstallLowCurrentWiring 10 0.00% 0.00% 30Jan17 9Feb17 4Feb17 14Feb17 4 8 OnTarget
BC14FMEPCL1100 BC 14F InstallLVCables 10 0.00% 0.00% 30Jan17 9Feb17 4Feb17 14Feb17 4 9 OnTarget
BC14FMEPCL1110 BC 14F InstallDroppers 10 0.00% 0.00% 12Feb17 22Feb17 16Feb17 27Feb17 4 10 OnTarget
BC14FMEPCL1120 BC 14F MeggeringTest 10 0.00% 0.00% 12Feb17 22Feb17 16Feb17 27Feb17 4 10 OnTarget
CommonFinalFinishes 41 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPworks 21 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BC14FMEPF1010 BC 14F InstallLightFittings 14 0.00% 0.00% 5Mar17 20Mar17 9Mar17 25Mar17 4 0 OnTarget
BC14FMEPF1020 BC 14F InstallFireCabinets 14 0.00% 0.00% 7Mar17 22Mar17 12Mar17 27Mar17 4 0 OnTarget
BC14FMEPF1030 BC 14F InstallFireAlarmsandSpeakers 14 0.00% 0.00% 7Mar17 22Mar17 12Mar17 27Mar17 4 0 OnTarget
BC14FMEPF1040 BC 14F InstallSprinklers 14 0.00% 0.00% 9Mar17 25Mar17 14Mar17 29Mar17 4 0 OnTarget
BC14FMEPF1050 BC 14F InstallSwitchesandSockets 14 0.00% 0.00% 9Mar17 25Mar17 14Mar17 29Mar17 4 0 OnTarget
BC14FMEPF1060 BC 14F InstallLowCurrentEquipments 14 0.00% 0.00% 11Mar17 26Mar17 15Mar17 30Mar17 4 0 OnTarget
BC14FMEPF1070 BC 14F InstallGrillesandDiffussers 14 0.00% 0.00% 13Mar17 28Mar17 18Mar17 2Apr17 4 0 OnTarget
BC14FMEPF1075 BC 14F MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 9Mar17 22Mar17 14Mar17 27Mar17 4 1 OnTarget
BC14FMEPF1080 BC 14F InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 13Mar17 28Mar17 18Mar17 2Apr17 4 0 OnTarget
RoofFloor 97 0.00% 0.00% 27Nov16 19Mar17 26Nov16A 27Feb17 18 82 OnTarget
General 33 0.00% 0.00% 27Nov16 3Jan17 27Nov16A 17Jan17 11 117 OnTarget
BCRF1005 BC Roof FAHUinstalaltionandconenction 24 100.00% 70.00% 27Nov16 24Dec16 27Nov16A 8Jan17 12 61 Delayed
BCRF1015 BC Roof Chillersconnection/termination 24 100.00% 83.00% 30Nov16 27Dec16 27Nov16A 11Jan17 12 61 Delayed
BCRF1025 BC Roof HOtwatersolarpanelinstalaltionandconnections 24 95.83% 96.00% 4Dec16 31Dec16 27Nov16A 15Jan17 12 61 OnTarget
ChilledwaterpumpRoom/PumpRoom 72 0.00% 0.00% 27Nov16 18Feb17 26Nov16A 14Feb17 4 93 OnTarget
BCRF1000 BC Roof PlasterMEpClearance 10 100.00% 100.00% 27Nov16 7Dec16 27Nov16A 18Dec16A 8 0 OnTarget
BCRF1030 BC Roof MEPScreedclearance 10 100.00% 100.00% 19Dec16 29Dec16 26Nov16A 26Nov16A 30 0 OnTarget
BCRF1045 BC Roof MEPInstallations/Connections 36 8.33% 40.00% 27Dec16 6Feb17 27Nov16A 24Jan17 11 48 OnTarget
BCRF1050 BC Roof MEPHLClearancebyARMAforceilingpainting 12 83.33% 33.00% 19Dec16 1Jan17 27Nov16A 9Jan17 6 41 Delayed
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BCRF1190 BC Roof MEPFinalFixes 8 0.00% 0.00% 2Feb17 11Feb17 29Jan17 7Feb17 4 41 OnTarget
ElectricalRoom 54 0.00% 0.00% 20Dec16 20Feb17 19Dec16A 27Feb17 5 69 OnTarget
BCRF1480 BC Roof PlasterMEpClearance 6 83.33% 0.00% 25Dec16 31Dec16 31Dec16 7Jan17 5 27 Delayed
BCRF1510 BC Roof MEPScreedclearance 3 0.00% 0.00% 10Jan17 12Jan17 16Jan17 19Jan17 5 27 OnTarget
BCRF1530 BC Roof MEPInstallations/Connections 24 0.00% 0.00% 17Jan17 13Feb17 23Jan17 20Feb17 5 27 OnTarget
BCRF1540 BC Roof MEPHLClearancebyARMAforceilingpainting 10 0.00% 0.00% 10Jan17 21Jan17 16Jan17 28Jan17 5 34 OnTarget
BCRF1550 BC Roof Primer,Stucco,1stCoatPaintingforceiling&Wall 5 0.00% 0.00% 22Jan17 26Jan17 28Jan17 2Feb17 5 34 OnTarget
BCRF1580 BC Roof MEPFinalFixes 3 0.00% 0.00% 14Feb17 16Feb17 20Feb17 23Feb17 5 27 OnTarget
FAHU+SMokeFanRoom 42 0.00% 0.00% 24Dec16 9Feb17 27Nov16A 29Jan17 11 107 OnTarget
BCRF1600 BC Roof PlasterMEpClearance 10 60.00% 100.00% 24Dec16 3Jan17 27Nov16A 01Dec16A 29 0 OnTarget
BCRF1630 BC Roof MEPScreedclearance 10 0.00% 100.00% 1Jan17 11Jan17 27Nov16A 01Dec16A 36 0 OnTarget
BCRF1650 BC Roof MEPInstallations/Connections 24 0.00% 65.00% 7Jan17 2Feb17 27Nov16A 9Jan17 22 62 OnTarget
BCRF1660 BC Roof MEPHLClearancebyARMAforceilingpainting 12 0.00% 30.00% 1Jan17 14Jan17 07Dec16A 9Jan17 5 51 OnTarget
BCRF1700 BC Roof MEPFinalFixes 6 0.00% 0.00% 31Jan17 6Feb17 18Jan17 25Jan17 11 51 OnTarget
StaircaseFInishes 85 0.00% 0.00% 27Nov16 5Mar17 26Nov16A 8Mar17 3 3 OnTarget
BCSTS11020 BC PlasterMEPClearance 24 66.67% 70.00% 12Dec16 8Jan17 26Nov16A 11Jan17 2 2 OnTarget
Roofing 71 0.00% 0.00% 27Nov16 16Feb17 26Nov16A 7Feb17 8 83 OnTarget
BCRFS12070 BC Roof RoofEquipmentInstallation&Conncetion 48 12.50% 30.00% 24Dec16 16Feb17 27Nov16A 7Feb17 8 40 OnTarget
MEPServiceRoomworks 79 0.00% 0.00% 27Nov16 26Feb17 26Nov16A 27Feb17 0 82 OnTarget
BCSRS1SP1710 BC OtherServiceRoomsMEPworkcompletion 36 47.22% 48.00% 11Dec16 21Jan17 27Nov16A 21Jan17 0 39 OnTarget
LVRoom 33 0.00% 0.00% 27Nov16 3Jan17 27Nov16A 8Jan17 4 124 OnTarget
BCLVS11070 BC MEPInstalaltion&Conenctions 24 95.83% 80.00% 4Dec16 31Dec16 27Nov16A 4Jan17 4 21 Delayed
ElectricalRooms/Telephone/WaterMeterRoom 69 0.00% 0.00% 27Nov16 14Feb17 26Nov16A 27Feb17 10 82 OnTarget
BCELS11010 BC MEPClearanceforPlaster 21 100.00% 100.00% 27Nov16 20Dec16 26Nov16A 27Nov16A 21 0 OnTarget
BCELS11030 BC MEPClearanceforScreed(AsApplicable) 21 80.95% 81.00% 11Dec16 3Jan17 26Nov16A 16Jan17 10 5 OnTarget
BCELS11060 BC MEPworkCompletionbyARMA 30 56.67% 57.00% 11Dec16 14Jan17 27Nov16A 14Jan17 0 17 OnTarget
FanRoom 72 0.00% 0.00% 27Nov16 18Feb17 26Nov16A 4Feb17 12 88 OnTarget
BCFNS11030 BC MEPClearanceforScreed(AsApplicable) 12 66.67% 100.00% 21Dec16 3Jan17 26Nov16A 20Dec16A 13 0 OnTarget
BCFNS11070 BC MEPworkCompletionbyARMA 24 8.33% 60.00% 28Dec16 24Jan17 27Nov16A 10Jan17 12 64 OnTarget
GeneratorRoom 45 0.00% 0.00% 27Nov16 17Jan17 27Nov16A 11Jan17 5 102 OnTarget
BCGNS11000 BC GeneratorInstallation&connection 36 80.56% 95.00% 27Nov16 7Jan17 27Nov16A 1Jan17 5 72 OnTarget
Firewaterpump&IrrigationPumproom 45 0.00% 0.00% 11Dec16 31Jan17 27Nov16A 25Jan17 5 96 OnTarget
BCPUS11000 BC PumpInstallation&conenctions 36 47.22% 95.00% 11Dec16 21Jan17 27Nov16A 15Jan17 5 96 OnTarget
Garbageroom 79 0.00% 0.00% 27Nov16 26Feb17 26Nov16A 26Feb17 0 82 OnTarget
BCGRS11010 BC MEPClearanceforPlaster 10 100.00% 100.00% 27Nov16 7Dec16 26Nov16A 27Nov16A 10 0 OnTarget
BCGRS11030 BC MEPClearanceforScreed 6 33.33% 70.00% 28Dec16 3Jan17 26Nov16A 5Jan17 2 124 OnTarget
BCGRS11060 BC MEPworkCompletionbyARMA 21 61.90% 62.00% 15Dec16 8Jan17 27Nov16A 8Jan17 0 30 OnTarget
SwimmingPool&Pumprooms 54 0.00% 0.00% 27Nov16 28Jan17 26Nov16A 13Feb17 14 35 OnTarget
BCSPS11010 BC SwimmingPoolMEPWorksinctesting 42 40.48% 40.00% 11Dec16 28Jan17 27Nov16A 13Feb17 14 35 Delayed
ExternalElevation 78 0.00% 0.00% 27Nov16 25Feb17 26Nov16A 6Mar17 8 75 OnTarget
Pour01WestElevation 62 0.00% 0.00% 27Nov16 6Feb17 26Nov16A 16Feb17 9 90 OnTarget
BCEVS11045 BC MEPCutting&Chasingforconduits 6 100.00% 100.00% 27Nov16 3Dec16 26Nov16A 27Nov16A 6 0 OnTarget
BCEVS11330 BC MEPFittings 10 0.00% 0.00% 19Jan17 30Jan17 30Jan17 9Feb17 9 13 OnTarget
Pour01SouthElevation 61 0.00% 0.00% 4Dec16 12Feb17 26Nov16A 13Feb17 1 93 OnTarget
BCEVS11600 BC MEPCutting&Chasingforconduits 6 100.00% 100.00% 4Dec16 10Dec16 27Nov16A 27Nov16A 12 0 OnTarget
BCEVS11670 BC MEPFittings 10 0.00% 0.00% 25Jan17 5Feb17 26Jan17 6Feb17 1 16 OnTarget
CourtyardNorthElevation 54 0.00% 0.00% 29Nov16 30Jan17 26Nov16A 6Feb17 6 99 OnTarget
BCEVS11240 BC MEPCutting&Chasingforconduits 10 100.00% 100.00% 29Nov16 10Dec16 26Nov16A 27Nov16A 12 0 OnTarget
BCEVS11510 BC MEPFittings 10 0.00% 0.00% 12Jan17 23Jan17 26Jan17 6Feb17 12 99 OnTarget
CourtyardWestElevation 61 0.00% 0.00% 7Dec16 15Feb17 26Nov16A 13Feb17 2 93 OnTarget
BCEVS11700 BC MEPCutting&Chasingforconduits 6 100.00% 100.00% 7Dec16 13Dec16 26Nov16A 27Nov16A 15 0 OnTarget
BCEVS11770 BC MEPFittings 10 0.00% 0.00% 29Jan17 8Feb17 26Jan17 6Feb17 2 16 OnTarget
CourtyardSouthElevation 61 0.00% 0.00% 11Dec16 19Feb17 26Nov16A 13Feb17 5 93 OnTarget
BCEVS11800 BC MEPCutting&Chasingforconduits 6 100.00% 100.00% 11Dec16 17Dec16 26Nov16A 22Dec16A 4 0 OnTarget
BCEVS11870 BC MEPFittings 10 0.00% 0.00% 1Feb17 12Feb17 26Jan17 6Feb17 5 16 OnTarget
Pour02WestElevation 70 0.00% 0.00% 27Nov16 15Feb17 26Nov16A 16Feb17 1 90 OnTarget
BCEVS11070 BC MEPCutting&Chasingforconduits 10 100.00% 100.00% 4Dec16 14Dec16 26Nov16A 27Nov16A 16 0 OnTarget
BCEVS11340 BC MEPFittings 10 0.00% 0.00% 29Jan17 8Feb17 30Jan17 9Feb17 1 13 OnTarget
Pour02NorthElevation 76 0.00% 0.00% 29Nov16 25Feb17 26Nov16A 6Mar17 8 75 OnTarget
BCEVS11250 BC MEPCutting&Chasingforconduits 18 77.78% 25.00% 14Dec16 3Jan17 05Dec16A 15Jan17 10 2 Delayed
BCEVS11520 BC MEPFittings 14 0.00% 0.00% 2Feb17 18Feb17 12Feb17 27Feb17 8 2 OnTarget
EastElevation 69 0.00% 0.00% 6Dec16 23Feb17 26Nov16A 13Feb17 9 93 OnTarget
BCEVS11260 BC MEPCutting&Chasingforconduits 18 83.33% 95.00% 13Dec16 2Jan17 29Nov16A 31Dec16 2 131 OnTarget
BCEVS11530 BC MEPFittings 12 0.00% 0.00% 4Feb17 16Feb17 24Jan17 6Feb17 9 16 OnTarget
ExternalWork 50 0.00% 0.00% 6Feb17 4Apr17 15Feb17 6Apr17 2 2 OnTarget
BCEXS11020 BC ExternalMEPServices 30 0.00% 0.00% 13Feb17 19Mar17 15Feb17 21Mar17 2 2 OnTarget
Testing&Commissioning 54 0.00% 0.00% 27Feb17 30Apr17 1Mar17 2May17 2 25 OnTarget
BCTCS3ME1120 BC Testingandcommissioningforallsystem 48 0.00% 0.00% 27Feb17 23Apr17 1Mar17 25Apr17 2 2 OnTarget
Electrical 36 0.00% 0.00% 27Feb17 9Apr17 1Mar17 11Apr17 2 43 OnTarget
BCTC1070 BC TestingandCommissioningofLVPanels&System 28 0.00% 0.00% 27Feb17 30Mar17 1Mar17 2Apr17 2 43 OnTarget
BCTC1080 BC TestingandCommissioningofMCC's 28 0.00% 0.00% 27Feb17 30Mar17 1Mar17 2Apr17 2 43 OnTarget
BCTC1090 BC TestingandCommissioningofLightningProtectionSys 18 0.00% 0.00% 13Mar17 2Apr17 15Mar17 4Apr17 2 43 OnTarget
BCTC1100 BC TestingandCommissioningofEarthingSystem 18 0.00% 0.00% 20Mar17 9Apr17 22Mar17 11Apr17 2 43 OnTarget
BCTC1110 BC TestingandCommissioningofGenerator 12 0.00% 0.00% 27Mar17 9Apr17 29Mar17 11Apr17 2 43 OnTarget
LowCurrentSystems 28 0.00% 0.00% 27Feb17 30Mar17 1Mar17 2Apr17 2 2 OnTarget
BCTC1160 BC TestCentralBatterySystem 24 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 2 OnTarget
BCTC1170 BC TestStructuredCabling(data&telecom) 24 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 2 OnTarget
BCTC1180 BC TestLightingControlSystem 24 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 2 OnTarget
BCTC1190 BC TestSMATV 24 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 2 OnTarget
BCTC1200 BC TestVoiceEvacuationSystem 24 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 2 OnTarget
BCTC1210 BC TestCCTVandAccessControlSystem 18 0.00% 0.00% 27Feb17 19Mar17 1Mar17 21Mar17 2 2 OnTarget
BCTC1220 BC TestGRMSSystem 28 0.00% 0.00% 27Feb17 30Mar17 1Mar17 2Apr17 2 2 OnTarget
BCTC1230 BC TestUPS 12 0.00% 0.00% 18Mar17 30Mar17 20Mar17 2Apr17 2 2 OnTarget
BCTC1240 BC TestAudioVisualSystem 24 0.00% 0.00% 4Mar17 30Mar17 6Mar17 2Apr17 2 2 OnTarget
BCTC1250 BC TestFireAlarmSystem 24 0.00% 0.00% 4Mar17 30Mar17 6Mar17 2Apr17 2 2 OnTarget
FireFightingSystems 27 0.00% 0.00% 6Mar17 5Apr17 8Mar17 8Apr17 2 2 OnTarget
BCTC1300 BC Testing&CommissioningofFirePumps 12 0.00% 0.00% 6Mar17 19Mar17 8Mar17 21Mar17 2 2 OnTarget
BCTC1310 BC Testing&CommissioningofFireFHC's 12 0.00% 0.00% 9Mar17 22Mar17 12Mar17 25Mar17 2 2 OnTarget
BCTC1320 BC Testing&CommissioningofGasFireSuppressionSyste 18 0.00% 0.00% 16Mar17 5Apr17 19Mar17 8Apr17 2 2 OnTarget
DrainageSystems 12 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 2 OnTarget
BCTC1270 BC TestingandCommissioningofPumps 12 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 2 OnTarget
BCTC1280 BC TestingandCommissioningofDrainageSystem 12 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 2 OnTarget
WaterSupplySystem 24 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 8 OnTarget
BCTC1120 BC TestingandCommissioningofPumps 12 0.00% 0.00% 27Feb17 12Mar17 1Mar17 14Mar17 2 8 OnTarget
BCTC1130 BC TestingandCommissioningofWaterHeaters 24 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 8 OnTarget
BCTC1140 BC TestingandCommissioningofWaterTank 12 0.00% 0.00% 6Mar17 19Mar17 8Mar17 21Mar17 2 5 OnTarget
BCTC1150 BC WaterSupplyFlushingandChlorination 12 0.00% 0.00% 9Mar17 22Mar17 12Mar17 25Mar17 2 5 OnTarget
HVACSystem 54 0.00% 0.00% 27Feb17 30Apr17 1Mar17 2May17 2 0 OnTarget
BCTC1010 BC FlushingofChilledWaterSystem 24 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 24 OnTarget
BCTC1015 BC FAHU 18 0.00% 0.00% 6Mar17 26Mar17 8Mar17 28Mar17 2 24 OnTarget
BCTC1020 BC FCU 18 0.00% 0.00% 3Apr17 23Apr17 5Apr17 25Apr17 2 0 OnTarget
BCTC1030 BC WaterBalancing 24 0.00% 0.00% 3Apr17 30Apr17 5Apr17 2May17 2 0 OnTarget
BCTC1040 BC AirBalancing 24 0.00% 0.00% 3Apr17 30Apr17 5Apr17 2May17 2 0 OnTarget
BCTC1050 BC VentilationSystem 18 0.00% 0.00% 10Apr17 30Apr17 12Apr17 2May17 2 0 OnTarget
BMSSystem 24 0.00% 0.00% 27Mar17 23Apr17 29Mar17 25Apr17 2 5 OnTarget
BCTC1260 BC BMSSystemtTesting&Commissioning 24 0.00% 0.00% 27Mar17 23Apr17 29Mar17 25Apr17 2 5 OnTarget
LPGSystem 12 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 0 OnTarget
BCTC1290 BC Testing&CommissioningofLPGSystem 12 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 0 OnTarget
BoilerSystem 12 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 0 OnTarget
BCTC1330 BC Testing&CommissioningofBoilerSystem 12 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 0 OnTarget
AuthorityApproval 148 0.00% 0.00% 27Nov16 17May17 02Dec16A 18May17 1 1 OnTarget
Transformer&RMUworks(HVApprovals) 61 0.00% 0.00% 27Nov16 5Feb17 02Dec16A 23Jan17 11 37 OnTarget
BCAAMEP1000 BC Transformer/CableProcurement 12 100.00% 100.00% 27Nov16 10Dec16 02Dec16A 02Dec16A 7 0 OnTarget
BCAAMEP1010 BC Transformerinstallation&Connection 28 60.71% 100.00% 11Dec16 11Jan17 08Dec16A 08Dec16A 30 0 OnTarget
BCAAMEP1020 BC AuthorityApprovals 21 0.00% 0.00% 12Jan17 5Feb17 31Dec16 23Jan17 11 37 OnTarget
LVApproval 32 0.00% 0.00% 29Jan17 7Mar17 17Jan17 23Feb17 10 10 OnTarget
BCAAMEP1030 BC RequestforDEWAinspection 0 0.00% 0.00% 0Jan00 29Jan17 0Jan00 17Jan17 8 8 OnTarget
BCAAMEP1040 BC DEWA1stinspection 7 0.00% 0.00% 30Jan17 6Feb17 17Jan17 25Jan17 10 10 OnTarget
BCAAMEP1050 BC ClearDEWAsnag&applyforfinalinspection 6 0.00% 0.00% 7Feb17 13Feb17 25Jan17 1Feb17 10 10 OnTarget
BCAAMEP1060 BC Dewasecondinspection/Approval 7 0.00% 0.00% 14Feb17 21Feb17 1Feb17 9Feb17 10 10 OnTarget
BCAAMEP1070 BC Collection&installationofKWHmeters 12 0.00% 0.00% 22Feb17 7Mar17 9Feb17 23Feb17 10 10 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BCAAMEP1080 BC TemporaryPermenetPower 0 0.00% 0.00% 0Jan00 7Mar17 0Jan00 23Feb17 10 10 OnTarget
WaterSupplyApproval 146 0.00% 0.00% 27Nov16 15May17 31Dec16 17May17 2 0 OnTarget
BCAAMEP1090 BC PaymentforWaterMeters 30 93.33% 0.00% 27Nov16 1Jan17 31Dec16 2Feb17 28 11 Delayed
BCAAMEP1100 BC WaterMeterdelivery 48 0.00% 0.00% 2Jan17 26Feb17 4Feb17 30Mar17 28 11 OnTarget
BCAAMEP1110 BC DEWAInspection 10 0.00% 0.00% 9Mar17 22Mar17 12Mar17 23Mar17 1 5 OnTarget
BCAAMEP1120 BC DewaApproval 10 0.00% 0.00% 23Mar17 3Apr17 26Mar17 5Apr17 2 6 OnTarget
BCAAMEP1130 BC InstalWaterMeter 6 0.00% 0.00% 4Apr17 10Apr17 6Apr17 12Apr17 2 6 OnTarget
BCAAMEP1140 BC Testing&Commisioning 12 0.00% 0.00% 18Apr17 1May17 20Apr17 3May17 2 0 OnTarget
BCAAMEP1150 BC ObtainNOCfromDEWAforWater 12 0.00% 0.00% 2May17 15May17 4May17 17May17 2 0 OnTarget
TelecomApproval 64 0.00% 0.00% 14Feb17 30Apr17 27Feb17 11May17 9 5 OnTarget
BCAAMEP1160 BC CompletionofTelecomroom 0 0.00% 0.00% 0Jan00 14Feb17 0Jan00 27Feb17 10 5 OnTarget
BCAAMEP1170 BC SubmitApplication 3 0.00% 0.00% 15Feb17 19Feb17 27Feb17 2Mar17 8 4 OnTarget
BCAAMEP1180 BC EtisalatInspection 10 0.00% 0.00% 20Feb17 5Mar17 2Mar17 16Mar17 8 4 OnTarget
BCAAMEP1190 BC CoordinationwithEtisalatContractor 12 0.00% 0.00% 6Mar17 19Mar17 16Mar17 30Mar17 9 5 OnTarget
BCAAMEP1200 BC Testing&Commisioning 12 0.00% 0.00% 20Mar17 2Apr17 30Mar17 13Apr17 9 5 OnTarget
BCAAMEP1210 BC Inspection&ApprovalbyEtisalat 12 0.00% 0.00% 3Apr17 16Apr17 13Apr17 27Apr17 9 5 OnTarget
BCAAMEP1220 BC ObtainNOCfromEtisalat 10 0.00% 0.00% 17Apr17 30Apr17 27Apr17 11May17 8 4 OnTarget
GSMApproval(Etisalat) 52 0.00% 0.00% 15Feb17 16Apr17 27Feb17 27Apr17 9 17 OnTarget
BCAAMEP1230 BC RequestforSiteSurvey 3 0.00% 0.00% 15Feb17 19Feb17 27Feb17 2Mar17 8 16 OnTarget
BCAAMEP1240 BC SiteSurveybyEtisalat(AfterStrCompletion) 10 0.00% 0.00% 20Feb17 2Mar17 2Mar17 14Mar17 9 19 OnTarget
BCAAMEP1250 BC CoordinationwithEtisalatContractor 12 0.00% 0.00% 4Mar17 16Mar17 14Mar17 28Mar17 9 19 OnTarget
BCAAMEP1260 BC Testing&Commisioning 12 0.00% 0.00% 20Mar17 2Apr17 30Mar17 13Apr17 9 17 OnTarget
BCAAMEP1270 BC FinalApprovalbyAuthority 10 0.00% 0.00% 3Apr17 13Apr17 13Apr17 25Apr17 9 19 OnTarget
BCAAMEP1280 BC ObtainNOCfromEtisalat 10 0.00% 0.00% 3Apr17 16Apr17 13Apr17 27Apr17 8 14 OnTarget
CivilDefence 30 0.00% 0.00% 5Mar17 16Apr17 8Mar17 19Apr17 3 20 OnTarget
BCAAMEP1290 BC RequestforDCDinspection 0 0.00% 0.00% 0Jan00 5Mar17 0Jan00 8Mar17 3 3 OnTarget
BCAAMEP1300 BC DCDInspection 10 0.00% 0.00% 6Mar17 19Mar17 8Mar17 22Mar17 3 3 OnTarget
BCAAMEP1310 BC ClearDCDsnags&requestfor2ndinspection 6 0.00% 0.00% 20Mar17 27Mar17 22Mar17 30Mar17 3 20 OnTarget
BCAAMEP1320 BC DCDsecondinspection 7 0.00% 0.00% 28Mar17 5Apr17 30Mar17 10Apr17 3 20 OnTarget
BCAAMEP1330 BC IssuanceofCivilDefensecertificate 7 0.00% 0.00% 6Apr17 16Apr17 10Apr17 19Apr17 3 20 OnTarget
CivilDefenceExternalFireHydrant 30 0.00% 0.00% 5Mar17 16Apr17 8Mar17 19Apr17 3 20 OnTarget
BCAAMEP1340 BC RequestforDCDinspection 0 0.00% 0.00% 0Jan00 5Mar17 0Jan00 8Mar17 3 20 OnTarget
BCAAMEP1350 BC DCDInspection 10 0.00% 0.00% 6Mar17 19Mar17 8Mar17 22Mar17 3 20 OnTarget
BCAAMEP1360 BC ClearDCDsnags&requestfor2ndinspection 6 0.00% 0.00% 20Mar17 27Mar17 22Mar17 30Mar17 3 20 OnTarget
BCAAMEP1370 BC DCDsecondinspection 7 0.00% 0.00% 28Mar17 5Apr17 30Mar17 10Apr17 3 20 OnTarget
BCAAMEP1380 BC IssuanceofCivilDefensecertificate 7 0.00% 0.00% 6Apr17 16Apr17 10Apr17 19Apr17 3 20 OnTarget
24X7DirectAlaram 46 0.00% 0.00% 20Mar17 11May17 23Mar17 16May17 4 1 OnTarget
BCAAMEP1390 BC SubmitApplication 3 0.00% 0.00% 20Mar17 22Mar17 23Mar17 27Mar17 3 1 OnTarget
BCAAMEP1400 BC InspectionbyAuthority 6 0.00% 0.00% 23Mar17 30Mar17 28Mar17 4Apr17 3 1 OnTarget
BCAAMEP1410 BC Releaseofestimate 6 0.00% 0.00% 1Apr17 6Apr17 5Apr17 11Apr17 4 1 OnTarget
BCAAMEP1420 BC Payment 6 0.00% 0.00% 8Apr17 13Apr17 12Apr17 18Apr17 4 1 OnTarget
BCAAMEP1430 BC PanelInstallation 12 0.00% 0.00% 15Apr17 27Apr17 19Apr17 2May17 4 1 OnTarget
BCAAMEP1440 BC ObtainNOC 10 0.00% 0.00% 30Apr17 11May17 3May17 16May17 3 1 OnTarget
LPG 28 0.00% 0.00% 5Apr17 15May17 9Apr17 17May17 2 0 OnTarget
BCAAMEP1450 BC RequestforLPGinspection 0 0.00% 0.00% 0Jan00 5Apr17 0Jan00 9Apr17 1 2 OnTarget
BCAAMEP1460 BC LPGInspection 6 0.00% 0.00% 6Apr17 13Apr17 9Apr17 16Apr17 1 2 OnTarget
BCAAMEP1470 BC ClearLPGsnags&requestfor2ndinspection 5 0.00% 0.00% 16Apr17 20Apr17 17Apr17 23Apr17 1 2 OnTarget
BCAAMEP1480 BC LPGsecondinspection 6 0.00% 0.00% 24Apr17 1May17 26Apr17 3May17 2 0 OnTarget
BCAAMEP1490 BC NOCfromAuthority 10 0.00% 0.00% 2May17 15May17 4May17 17May17 2 0 OnTarget
DubaiPolice 44 0.00% 0.00% 28Mar17 17May17 29Mar17 18May17 1 1 OnTarget
BCAAMEP1500 BC SubmitApplication 3 0.00% 0.00% 28Mar17 30Mar17 29Mar17 2Apr17 1 1 OnTarget
BCAAMEP1510 BC 1stInspectionbyAuthority 10 0.00% 0.00% 2Apr17 13Apr17 3Apr17 16Apr17 1 1 OnTarget
BCAAMEP1520 BC Commets&Rectification 7 0.00% 0.00% 15Apr17 22Apr17 17Apr17 24Apr17 2 2 OnTarget
BCAAMEP1530 BC FinalInspection&Approval 10 0.00% 0.00% 23Apr17 3May17 25Apr17 6May17 2 2 OnTarget
BCAAMEP1540 BC ObtainNOCfromDubaiPolice 10 0.00% 0.00% 4May17 17May17 7May17 18May17 1 1 OnTarget
DMApproval 51 0.00% 0.00% 20Mar17 17May17 22Mar17 18May17 1 1 OnTarget
BCAAMEP1550 BC Requestforinspection 4 0.00% 0.00% 20Mar17 23Mar17 22Mar17 28Mar17 3 3 OnTarget
BCAAMEP1560 BC EHSInspection 12 0.00% 0.00% 20Mar17 2Apr17 22Mar17 5Apr17 3 36 OnTarget
BCAAMEP1570 BC DMfirstinspection 12 0.00% 0.00% 26Mar17 10Apr17 28Mar17 13Apr17 3 3 OnTarget
BCAAMEP1580 BC DMCommentrectification 10 0.00% 0.00% 11Apr17 20Apr17 13Apr17 23Apr17 3 3 OnTarget
BCAAMEP1590 BC DMfinalinspection&Approval 13 0.00% 0.00% 23Apr17 9May17 23Apr17 10May17 1 1 OnTarget
BCAAMEP1600 BC FICconnection 7 0.00% 0.00% 10May17 17May17 10May17 18May17 1 1 OnTarget
BCAAMEP1610 BC StromWaterConnection 7 0.00% 0.00% 10May17 17May17 10May17 18May17 1 1 OnTarget
BCAAMEP1620 BC ObtainBuildingCompletionCertificate 0 0.00% 0.00% 0Jan00 17May17 0Jan00 18May17 1 1 OnTarget
ProjectCloseOut 53 0.00% 0.00% 1Apr17 31May17 2Apr17 1Jun17 1 1 OnTarget
BCPC1000 BC O&MManualSubmission 12 0.00% 0.00% 4May17 17May17 6May17 18May17 1 4 OnTarget
BCPC1010 BC O&MTaining 12 0.00% 0.00% 13May17 25May17 14May17 27May17 1 4 OnTarget
BCPC1020 BC AsBuiltDrawings 48 0.00% 0.00% 1Apr17 25May17 2Apr17 27May17 1 4 OnTarget
BCPC1030 BC FinalSnag/Desnag&Handover 18 0.00% 0.00% 11May17 31May17 13May17 01Jun17* 1 1 OnTarget
BuildingBD BD 81 14.87% 0.00% 27Nov16 28Feb17 26Nov16A 20Mar17 16 64 Delayed
InsideWork(ApartmentsandOthers) 66 0.00% 0.00% 27Nov16 25Apr17 23Nov16A 2May17 5 27 OnTarget
Basement02 55 0.00% 0.00% 27Nov16 19Mar17 27Nov16A 28Mar17 8 56 OnTarget
MEPWorks 49 0.00% 0.00% 27Nov16 2Mar17 27Nov16A 12Mar17 8 70 OnTarget
MEP2ndFix 31 0.00% 0.00% 27Nov16 1Jan17 26Nov16A 23Jan17 19 111 OnTarget
BDB2MEP1100 BD Basement2 MEP2ndfixingcompletion 18 100.00% 90.00% 29Nov16 19Dec16 05Dec16A 10Jan17 19 11 Delayed
BDB2MEP1110 BD Basement2 MEPclearanceforboardclosing 10 80.00% 0.00% 21Dec16 1Jan17 11Jan17 23Jan17 19 11 Delayed
BDB2MEP1120 BD Basement2 InstallElectricalWiring 12 100.00% 85.00% 27Nov16 10Dec16 27Nov16A 1Jan17 19 5 Delayed
BDB2MEP1130 BD Basement2 InstallLowCurrentWiring 12 100.00% 70.00% 29Nov16 12Dec16 05Dec16A 3Jan17 19 128 Delayed
BDB2MEP1140 BD Basement2 InstallHot&ColdWaterPiping 12 100.00% 85.00% 29Nov16 12Dec16 27Nov16A 3Jan17 19 128 Delayed
BDB2MEP1150 BD Basement2 InstallHVACPipes 12 100.00% 100.00% 29Nov16 12Dec16 27Nov16A 28Dec16A 13 0 OnTarget
BDB2MEP1160 BD Basement2 InstallDuctsandHangers 12 100.00% 100.00% 3Dec16 15Dec16 27Nov16A 28Dec16A 10 0 OnTarget
BDB2MEP1170 BD Basement2 InstallCableTraysandTrunking 12 100.00% 100.00% 3Dec16 15Dec16 27Nov16A 28Dec16A 10 0 OnTarget
BDB2MEP1180 BD Basement2 InstallLVCables 12 100.00% 20.00% 6Dec16 19Dec16 26Nov16A 10Jan17 19 11 Delayed
BDB2MEP1190 BD Basement2 InstallDroppers 12 83.33% 0.00% 19Dec16 1Jan17 9Jan17 23Jan17 19 11 Delayed
BDB2MEP1200 BD Basement2 MeggeringTest 10 80.00% 0.00% 21Dec16 1Jan17 11Jan17 23Jan17 19 11 Delayed
BDB2MEP1210 BD Basement2 InstallEarthpit 18 100.00% 90.00% 27Nov16 17Dec16 27Nov16A 8Jan17 19 5 Delayed
MEPFinalFix 10 0.00% 0.00% 11Jan17 22Jan17 17Dec16A 13Feb17 19 11 OnTarget
BDB2MEP2110 BD Basement2 InstallLightFittings 10 0.00% 70.00% 11Jan17 22Jan17 17Dec16A 13Feb17 19 11 OnTarget
BDB2MEP2120 BD Basement2 InstallFireCabinets 10 0.00% 0.00% 11Jan17 22Jan17 1Feb17 13Feb17 19 11 OnTarget
BDB2MEP2130 BD Basement2 InstallFireAlarmsandSpeakers 10 0.00% 0.00% 11Jan17 22Jan17 1Feb17 13Feb17 19 11 OnTarget
BDB2MEP2140 BD Basement2 InstallSprinklers 10 0.00% 0.00% 11Jan17 22Jan17 1Feb17 13Feb17 19 11 OnTarget
BDB2MEP2150 BD Basement2 InstallSwitchesandSockets 10 0.00% 0.00% 11Jan17 22Jan17 1Feb17 13Feb17 19 11 OnTarget
BDB2MEP2160 BD Basement2 InstallLowCurrentEquipments 10 0.00% 0.00% 11Jan17 22Jan17 1Feb17 13Feb17 19 11 OnTarget
BDB2MEP2170 BD Basement2 InstallGrillesandDiffussers 6 0.00% 0.00% 16Jan17 22Jan17 6Feb17 13Feb17 19 11 OnTarget
BDB2MEP2175 BD Basement2 MEPFinalfittings 10 0.00% 0.00% 11Jan17 22Jan17 1Feb17 13Feb17 19 11 OnTarget
BDB2MEP2180 BD Basement2 InstallPlumpingFinalTittings(FloorDrains,Gratings,F 8 0.00% 0.00% 14Jan17 22Jan17 4Feb17 13Feb17 19 11 OnTarget
Basement01 66 0.00% 0.00% 29Dec16 25Apr17 27Nov16A 28Mar17 24 41 OnTarget
MEPWorks 47 0.00% 0.00% 27Nov16 2Mar17 27Nov16A 12Mar17 8 70 OnTarget
MEP2ndFix 29 0.00% 0.00% 27Nov16 1Jan17 26Nov16A 23Jan17 19 111 OnTarget
BDB1MEP1000 BD Basement1 MEP2ndfixingcompletion 18 100.00% 20.00% 29Nov16 19Dec16 26Nov16A 16Jan17 23 13 Delayed
BDB1MEP1010 BD Basement1 MEPclearanceforboardclosing 10 100.00% 0.00% 19Dec16 29Dec16 15Jan17 26Jan17 23 13 Delayed
BDB1MEP1020 BD Basement1 InstallElectricalWiring 12 100.00% 85.00% 27Nov16 10Dec16 27Nov16A 1Jan17 19 126 Delayed
BDB1MEP1030 BD Basement1 InstallLowCurrentWiring 10 100.00% 30.00% 30Nov16 11Dec16 27Nov16A 7Jan17 23 122 Delayed
BDB1MEP1040 BD Basement1 InstallDrainagepipes 10 100.00% 100.00% 1Dec16 12Dec16 27Nov16A 28Dec16A 13 0 OnTarget
BDB1MEP1050 BD Basement1 InstallHot&ColdWaterPiping 10 100.00% 85.00% 3Dec16 13Dec16 27Nov16A 8Jan17 22 122 Delayed
BDB1MEP1060 BD Basement1 InstallHVACPipes 10 100.00% 95.00% 4Dec16 14Dec16 27Nov16A 9Jan17 22 122 Delayed
BDB1MEP1070 BD Basement1 InstallDuctsandHangers 10 100.00% 95.00% 5Dec16 15Dec16 27Nov16A 10Jan17 22 122 Delayed
BDB1MEP1080 BD Basement1 InstallCableTraysandTrunking 10 100.00% 100.00% 5Dec16 15Dec16 27Nov16A 22Dec16A 5 0 OnTarget
BDB1MEP1090 BD Basement1 InstallLVCables 10 100.00% 60.00% 8Dec16 19Dec16 05Dec16A 3Jan17 13 3 Delayed
BDB1MEP1100 BD Basement1 InstallDroppers 12 100.00% 0.00% 17Dec16 29Dec16 12Jan17 26Jan17 23 13 Delayed
BDB1MEP1110 BD Basement1 MeggeringTest 10 100.00% 0.00% 19Dec16 29Dec16 15Jan17 26Jan17 23 13 Delayed
MEPFinalFix 11 0.00% 0.00% 11Jan17 22Jan17 17Dec16A 13Feb17 19 11 OnTarget
BDB1MEP2010 BD Basement1 InstallLightFittings 8 0.00% 70.00% 8Jan17 16Jan17 17Dec16A 13Feb17 23 13 OnTarget
BDB1MEP2020 BD Basement1 InstallFireCabinets 8 0.00% 0.00% 9Jan17 17Jan17 5Feb17 14Feb17 23 13 OnTarget
BDB1MEP2030 BD Basement1 InstallFireAlarmsandSpeakers 8 0.00% 0.00% 9Jan17 17Jan17 5Feb17 14Feb17 23 13 OnTarget
BDB1MEP2040 BD Basement1 InstallSprinklers 10 0.00% 0.00% 8Jan17 18Jan17 4Feb17 15Feb17 23 13 OnTarget
BDB1MEP2050 BD Basement1 InstallSwitchesandSockets 10 0.00% 0.00% 8Jan17 18Jan17 4Feb17 15Feb17 23 13 OnTarget
BDB1MEP2060 BD Basement1 InstallLowCurrentEquipments 10 0.00% 0.00% 9Jan17 19Jan17 5Feb17 16Feb17 23 13 OnTarget
BDB1MEP2070 BD Basement1 InstallGrillesandDiffussers 8 0.00% 0.00% 11Jan17 19Jan17 7Feb17 16Feb17 23 13 OnTarget
BDB1MEP2075 BD Basement1 MEPFinalfittings 8 0.00% 0.00% 8Jan17 16Jan17 4Feb17 13Feb17 23 10 OnTarget
BDB1MEP2080 BD Basement1 InstallPlumpingFinalTittings(FloorDrains,Gratings,F 8 0.00% 0.00% 11Jan17 19Jan17 7Feb17 16Feb17 23 13 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
GroundFloor 60 0.00% 0.00% 27Nov16 18Apr17 27Nov16A 2May17 11 27 OnTarget
MEPWorks 12 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BDGFMEP1000 BD GroundFloor InstallWallMEPConduitsforplasterclearance 12 100.00% 85.00% 7Dec16 20Dec16 27Nov16A 3Jan17 11 123 Delayed
RetailArea 36 0.00% 0.00% 30Nov16 10Jan17 27Nov16A 19Jan17 8 114 OnTarget
MEPWorks 36 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BDGFMEPD1030 BD GroundFloor InstallElectricalWiring 20 100.00% 80.00% 30Nov16 22Dec16 27Nov16A 3Jan17 10 12 Delayed
BDGFMEPD1040 BD GroundFloor InstallLowCurrentWiring 20 100.00% 30.00% 1Dec16 24Dec16 27Nov16A 15Jan17 19 118 Delayed
BDGFMEPD1050 BD GroundFloor InstallHVACPipes 20 100.00% 70.00% 1Dec16 24Dec16 27Nov16A 5Jan17 11 4 Delayed
BDGFMEPD1060 BD GroundFloor Firefightingpipes 18 100.00% 100.00% 7Dec16 27Dec16 27Nov16A 25Dec16A 3 0 OnTarget
BDGFMEPD1070 BD GroundFloor InstallDuctsandHangers 21 95.24% 97.00% 7Dec16 31Dec16 27Nov16A 9Jan17 8 4 OnTarget
BDGFMEPD1080 BD GroundFloor DBInstallation 18 77.78% 35.00% 14Dec16 3Jan17 05Dec16A 12Jan17 8 4 Delayed
BDGFMEPD1090 BD GroundFloor InstallDroppers 15 53.33% 0.00% 21Dec16 7Jan17 31Dec16 16Jan17 8 6 Delayed
BDGFMEPD1100 BD GroundFloor MeggeringTest 15 33.33% 0.00% 25Dec16 10Jan17 3Jan17 19Jan17 8 4 Delayed
BDGFMEPD1110 BD GroundFloor MEPclearance 10 0.00% 0.00% 31Dec16 10Jan17 9Jan17 19Jan17 8 4 OnTarget
WetArea 44 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 41 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BDGFMEPW1000 BD GroundFloor WetAreaHLClearancebyARMAforgridfixing 12 100.00% 0.00% 15Dec16 28Dec16 31Dec16 12Jan17 13 10 Delayed
BDGFMEPW1010 BD GroundFloor WetAreaMEPclearanceforBoardclosing 12 0.00% 0.00% 9Jan17 22Jan17 17Jan17 30Jan17 7 5 OnTarget
BDGFMEPW1020 BD GroundFloor InstallElectricalWiring 15 100.00% 70.00% 6Dec16 22Dec16 27Nov16A 4Jan17 11 13 Delayed
BDGFMEPW1030 BD GroundFloor InstallDrainagepipes 10 100.00% 100.00% 13Dec16 24Dec16 27Nov16A 25Dec16A 0 0 OnTarget
BDGFMEPW1040 BD GroundFloor InstallHot&ColdWaterPiping 10 100.00% 60.00% 14Dec16 25Dec16 27Nov16A 3Jan17 8 4 Delayed
BDGFMEPW1050 BD GroundFloor InstallHVACPipes 15 100.00% 80.00% 10Dec16 26Dec16 27Nov16A 4Jan17 8 4 Delayed
BDGFMEPW1060 BD GroundFloor Firefightingpipes 10 100.00% 100.00% 17Dec16 27Dec16 27Nov16A 25Dec16A 3 0 OnTarget
BDGFMEPW1070 BD GroundFloor InstallDuctsandHangers 14 100.00% 97.00% 13Dec16 28Dec16 27Nov16A 5Jan17 7 4 Delayed
BDGFMEPW1080 BD GroundFloor InstallDroppers 12 0.00% 0.00% 7Jan17 19Jan17 15Jan17 28Jan17 7 4 OnTarget
BDGFMEPW1090 BD GroundFloor MeggeringTest 10 0.00% 0.00% 10Jan17 21Jan17 18Jan17 29Jan17 7 4 OnTarget
Corridor/LiftLobby 43 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 37 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BDGFMEPCL1000 BD GroundFloor CorridorMEPClearanceforScreed 10 20.00% 60.00% 28Dec16 8Jan17 06Dec16A 19Jan17 10 13 OnTarget
BDGFMEPCL1010 BD GroundFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 31Dec16 10Jan17 4Jan17 16Jan17 5 5 OnTarget
BDGFMEPCL1020 BD GroundFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 10Jan17 21Jan17 15Jan17 26Jan17 5 5 OnTarget
BDGFMEPCL1030 BD GroundFloor InstallElectricalWiring 12 100.00% 60.00% 10Dec16 22Dec16 10Dec16A 4Jan17 11 13 Delayed
BDGFMEPCL1050 BD GroundFloor InstallHot&ColdWaterPiping 10 100.00% 60.00% 13Dec16 24Dec16 27Nov16A 5Jan17 11 13 Delayed
BDGFMEPCL1060 BD GroundFloor Firefightingpipes 10 100.00% 100.00% 14Dec16 25Dec16 27Nov16A 25Dec16A 1 0 OnTarget
BDGFMEPCL1070 BD GroundFloor InstallHVACPipes 12 100.00% 70.00% 15Dec16 28Dec16 27Nov16A 9Jan17 10 13 Delayed
BDGFMEPCL1080 BD GroundFloor InstallDuctsandHangers 16 100.00% 97.00% 12Dec16 29Dec16 27Nov16A 10Jan17 10 13 Delayed
BDGFMEPCL1090 BD GroundFloor InstallCableTraysandTrunking 16 93.75% 77.00% 13Dec16 31Dec16 27Nov16A 11Jan17 10 13 Delayed
BDGFMEPCL1095 BD GroundFloor InstallLowCurrentWiring 12 66.67% 0.00% 21Dec16 3Jan17 1Jan17 15Jan17 10 5 Delayed
BDGFMEPCL1100 BD GroundFloor InstallLVCables 10 60.00% 0.00% 24Dec16 3Jan17 3Jan17 15Jan17 10 13 Delayed
BDGFMEPCL1110 BD GroundFloor InstallDroppers 16 0.00% 0.00% 1Jan17 18Jan17 5Jan17 24Jan17 5 4 OnTarget
BDGFMEPCL1120 BD GroundFloor MeggeringTest 10 0.00% 0.00% 9Jan17 19Jan17 14Jan17 25Jan17 5 4 OnTarget
CommonFinalFinishes 26 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 14 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BDGFMEPF1010 BD GroundFloor InstallLightFittings 14 0.00% 0.00% 16Jan17 31Jan17 22Jan17 6Feb17 5 5 OnTarget
BDGFMEPF1020 BD GroundFloor InstallFireCabinets 14 0.00% 0.00% 16Jan17 31Jan17 22Jan17 6Feb17 5 5 OnTarget
BDGFMEPF1030 BD GroundFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 16Jan17 31Jan17 22Jan17 6Feb17 5 5 OnTarget
BDGFMEPF1040 BD GroundFloor InstallSprinklers 14 0.00% 0.00% 16Jan17 31Jan17 22Jan17 6Feb17 5 5 OnTarget
BDGFMEPF1050 BD GroundFloor InstallSwitchesandSockets 14 0.00% 0.00% 16Jan17 31Jan17 22Jan17 6Feb17 5 5 OnTarget
BDGFMEPF1060 BD GroundFloor InstallLowCurrentEquipments 14 0.00% 0.00% 16Jan17 31Jan17 22Jan17 6Feb17 5 5 OnTarget
BDGFMEPF1070 BD GroundFloor InstallGrillesandDiffussers 14 0.00% 0.00% 16Jan17 31Jan17 22Jan17 6Feb17 5 5 OnTarget
BDGFMEPF1075 BD GroundFloor MEPFinalFixes 12 0.00% 0.00% 18Jan17 31Jan17 24Jan17 6Feb17 5 5 OnTarget
BDGFMEPF1080 BD GroundFloor InstallPlumpingFinalTittings(FloorDrains,Gratings,F 14 0.00% 0.00% 16Jan17 31Jan17 22Jan17 6Feb17 5 5 OnTarget
FirstFloor 55 0.00% 0.00% 27Nov16 18Mar17 27Nov16A 20Apr17 29 36 OnTarget
WetArea 18 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 12 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD1F1100 BD 1stFloor WetAreaMEPclearanceforBoardclosing 10 100.00% 100.00% 6Dec16 17Dec16 27Nov16A 01Dec16A 14 0 OnTarget
BD1FMEPW1000 BD 1stFloor InstallDroppers 12 100.00% 100.00% 4Dec16 17Dec16 27Nov16A 29Nov16A 16 0 OnTarget
Corridor/LiftLobby 30 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 12 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD1F1150 BD 1stFloor CorridorMEPclearanceforBoardclosing 12 100.00% 100.00% 11Dec16 24Dec16 27Nov16A 28Dec16A 3 0 OnTarget
BD1FMEPCL1010 BD 1stFloor InstallDroppers 12 100.00% 100.00% 11Dec16 24Dec16 27Nov16A 28Dec16A 3 0 OnTarget
CommonFinalFinishes 24 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 16 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD1FMEPF1010 BD 1stFloor InstallLightFittings 10 0.00% 10.00% 31Dec16 10Jan17 25Dec16A 22Jan17 10 112 OnTarget
BD1FMEPF1020 BD 1stFloor InstallFireCabinets 14 21.43% 100.00% 27Dec16 11Jan17 27Nov16A 01Dec16A 36 0 OnTarget
BD1FMEPF1030 BD 1stFloor InstallFireAlarmsandSpeakers 14 21.43% 21.00% 27Dec16 11Jan17 21Dec16A 12Jan17 0 120 Delayed
BD1FMEPF1040 BD 1stFloor InstallSprinklers 14 14.29% 14.00% 28Dec16 12Jan17 21Dec16A 14Jan17 0 120 Delayed
BD1FMEPF1050 BD 1stFloor InstallSwitchesandSockets 14 14.29% 14.00% 28Dec16 12Jan17 15Dec16A 14Jan17 0 9 Delayed
BD1FMEPF1060 BD 1stFloor InstallLowCurrentEquipments 14 7.14% 7.00% 29Dec16 14Jan17 21Dec16A 15Jan17 0 9 Delayed
BD1FMEPF1070 BD 1stFloor InstallGrillesandDiffussers 14 7.14% 7.00% 29Dec16 14Jan17 21Dec16A 15Jan17 0 9 Delayed
BD1FMEPF1075 BD 1stFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 2Jan17 14Jan17 15Jan17 26Jan17 11 2 OnTarget
BD1FMEPF1080 BD 1stFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 7.14% 7.00% 29Dec16 14Jan17 21Dec16A 15Jan17 0 9 Delayed
DSide 46 0.00% 0.00% 27Nov16 18Jan17 26Nov16A 8Feb17 18 97 OnTarget
MEPWorks 46 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
D1FMEP1000 BD 1stFloor InstallWallMEPconduitsforplasterclearance 7 100.00% 100.00% 27Nov16 4Dec16 26Nov16A 01Dec16A 3 0 OnTarget
D1FMEP1010 BD 1stFloor InstallFloorMEPconduitsforScreedclearance 7 100.00% 100.00% 4Dec16 11Dec16 27Nov16A 01Dec16A 9 0 OnTarget
D1FMEP1020 BD 1stFloor InstallElectricalWiring 10 100.00% 0.00% 4Dec16 14Dec16 31Dec16 10Jan17 23 122 Delayed
D1FMEP1030 BD 1stFloor InstallDrainagepipes 10 100.00% 100.00% 6Dec16 17Dec16 27Dec16A 28Dec16A 9 0 OnTarget
D1FMEP1040 BD 1stFloor Firefightingpipes 10 100.00% 100.00% 10Dec16 20Dec16 27Nov16A 17Dec16A 4 0 OnTarget
D1FMEP1050 BD 1stFloor InstallHot&ColdWaterPiping 10 100.00% 0.00% 11Dec16 21Dec16 31Dec16 10Jan17 17 6 Delayed
D1FMEP1060 BD 1stFloor InstallDuctsandHangers 12 100.00% 0.00% 10Dec16 22Dec16 31Dec16 12Jan17 18 7 Delayed
D1FMEP1070 BD 1stFloor InstallHVACPipes 12 100.00% 0.00% 12Dec16 25Dec16 2Jan17 15Jan17 18 7 Delayed
D1FMEP1080 BD 1stFloor InstallCableTraysandTrunking 12 100.00% 0.00% 13Dec16 26Dec16 3Jan17 16Jan17 18 7 Delayed
D1FMEP1090 BD 1stFloor InstallLowCurrentWiring 10 100.00% 40.00% 19Dec16 29Dec16 27Nov16A 19Jan17 18 7 Delayed
D1FMEP1100 BD 1stFloor InstallLVCables 10 100.00% 20.00% 19Dec16 29Dec16 30Nov16A 19Jan17 18 7 Delayed
D1FMEP1110 BD 1stFloor InstallDroppers 12 41.67% 0.00% 25Dec16 7Jan17 15Jan17 28Jan17 18 7 Delayed
D1FMEP1120 BD 1stFloor MeggeringTest 10 20.00% 0.00% 28Dec16 8Jan17 18Jan17 29Jan17 18 7 Delayed
D1FMEP1130 BD 1stFloor MEPFinalFixing 10 0.00% 0.00% 8Jan17 18Jan17 29Jan17 8Feb17 18 7 OnTarget
SecondFloor 66 0.00% 0.00% 10Dec16 11Mar17 27Nov16A 20Mar17 8 63 OnTarget
DryArea 34 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 22 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD2FMEPD1000 BD 2ndFloor DryAreaHLClearancebyARMAforgridfixing(205) 3 100.00% 100.00% 5Dec16 7Dec16 27Nov16A 01Dec16A 6 0 OnTarget
BD2FMEPD1010 BD 2ndFloor DryAreaMEPclearanceforBoardclosing 3 100.00% 100.00% 19Dec16 21Dec16 27Nov16A 01Dec16A 18 0 OnTarget
BD2FMEPD1020 BD 2ndFloor InstallDuctsandHangers 10 100.00% 100.00% 27Nov16 7Dec16 27Nov16A 01Dec16A 6 0 OnTarget
BD2FMEPD1030 BD 2ndFloor DBInstallation 10 100.00% 100.00% 1Dec16 12Dec16 27Nov16A 10Dec16A 3 0 OnTarget
BD2FMEPD1040 BD 2ndFloor InstallDroppers 12 100.00% 100.00% 6Dec16 19Dec16 27Nov16A 22Dec16A 2 0 OnTarget
BD2FMEPD1050 BD 2ndFloor MeggeringTest 7 100.00% 100.00% 14Dec16 21Dec16 27Nov16A 28Nov16A 21 0 OnTarget
WetArea 37 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 31 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD2FMEPW1000 BD 2ndFloor WetAreaMEPclearanceforBoardclosing 14 85.71% 50.00% 17Dec16 1Jan17 27Nov16A 7Jan17 5 3 Delayed
BD2FMEPW1010 BD 2ndFloor InstallDrainagepipes 12 100.00% 100.00% 27Nov16 10Dec16 27Nov16A 01Dec16A 8 0 OnTarget
BD2FMEPW1020 BD 2ndFloor InstallHot&ColdWaterPiping 12 100.00% 100.00% 28Nov16 11Dec16 27Nov16A 29Nov16A 11 0 OnTarget
BD2FMEPW1030 BD 2ndFloor InstallHVACPipes 12 100.00% 100.00% 1Dec16 14Dec16 27Nov16A 03Dec16A 11 0 OnTarget
BD2FMEPW1040 BD 2ndFloor InstallDuctsandHangers 12 100.00% 100.00% 5Dec16 18Dec16 27Nov16A 01Dec16A 15 0 OnTarget
BD2FMEPW1050 BD 2ndFloor InstallDroppers 12 100.00% 70.00% 14Dec16 27Dec16 27Nov16A 3Jan17 6 6 Delayed
Corridors/LiftLobby 47 0.00% 0.00% 27Nov16 19Jan17 26Nov16A 6Feb17 15 99 OnTarget
MEPWorks 28 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD2FMEPCL1000 BD 2ndFloor CorridorHLClearancebyARMAforgridfixing 14 100.00% 100.00% 27Nov16 12Dec16 27Nov16A 27Nov16A 14 0 OnTarget
BD2FMEPCL1010 BD 2ndFloor CorridorMEPclearanceforBoardclosing 14 100.00% 0.00% 13Dec16 28Dec16 31Dec16 15Jan17 15 11 Delayed
BD2FMEPCL1020 BD 2ndFloor InstallDroppers 10 100.00% 30.00% 15Dec16 26Dec16 27Nov16A 14Jan17 15 120 Delayed
BD2FMEPCL1030 BD 2ndFloor MeggeringTest 5 100.00% 100.00% 21Dec16 26Dec16 27Nov16A 29Nov16A 24 0 OnTarget
CommonFinalFinishes 51 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD2FMEPF1010 BD 2ndFloor InstallLightFittings 14 0.00% 0.00% 1Jan17 16Jan17 18Jan17 2Feb17 15 11 OnTarget
BD2FMEPF1020 BD 2ndFloor InstallFireCabinets 14 0.00% 0.00% 2Jan17 17Jan17 19Jan17 4Feb17 15 11 OnTarget
BD2FMEPF1030 BD 2ndFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 2Jan17 17Jan17 19Jan17 4Feb17 15 11 OnTarget
BD2FMEPF1040 BD 2ndFloor InstallSprinklers 14 0.00% 0.00% 3Jan17 18Jan17 21Jan17 5Feb17 15 11 OnTarget
BD2FMEPF1050 BD 2ndFloor InstallSwitchesandSockets 14 0.00% 0.00% 3Jan17 18Jan17 21Jan17 5Feb17 15 11 OnTarget
BD2FMEPF1060 BD 2ndFloor InstallLowCurrentEquipments 14 0.00% 0.00% 4Jan17 19Jan17 22Jan17 6Feb17 15 11 OnTarget
BD2FMEPF1070 BD 2ndFloor InstallGrillesandDiffussers 14 0.00% 0.00% 4Jan17 19Jan17 22Jan17 6Feb17 15 11 OnTarget
BD2FMEPF1075 BD 2ndFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 4Jan17 17Jan17 22Jan17 4Feb17 15 9 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BD2FMEPF1080 BD 2ndFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 4Jan17 19Jan17 22Jan17 6Feb17 15 11 OnTarget
DSide 46 0.00% 0.00% 27Nov16 18Jan17 26Nov16A 8Feb17 18 97 OnTarget
MEPWorks 46 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
D2FCIV1100 BD 2ndFloor InstallWallMEPconduitsforplasterclearance 7 100.00% 100.00% 27Nov16 4Dec16 27Nov16A 01Dec16A 3 0 OnTarget
D2FCIV1110 BD 2ndFloor InstallFloorMEPconduitsforScreedclearance 7 100.00% 100.00% 4Dec16 11Dec16 27Nov16A 01Dec16A 9 0 OnTarget
D2FCIV1120 BD 2ndFloor InstallElectricalWiring 10 100.00% 100.00% 4Dec16 14Dec16 27Nov16A 03Dec16A 11 0 OnTarget
D2FCIV1130 BD 2ndFloor InstallDrainagepipes 10 100.00% 100.00% 6Dec16 17Dec16 27Nov16A 28Dec16A 9 0 OnTarget
D2FCIV1140 BD 2ndFloor Firefightingpipes 10 100.00% 100.00% 10Dec16 20Dec16 27Nov16A 17Dec16A 4 0 OnTarget
D2FCIV1150 BD 2ndFloor InstallHot&ColdWaterPiping 10 100.00% 100.00% 11Dec16 21Dec16 27Nov16A 28Dec16A 5 0 OnTarget
D2FCIV1160 BD 2ndFloor InstallDuctsandHangers 12 100.00% 100.00% 10Dec16 22Dec16 27Nov16A 28Dec16A 4 0 OnTarget
D2FCIV1170 BD 2ndFloor InstallHVACPipes 12 100.00% 90.00% 12Dec16 25Dec16 27Nov16A 1Jan17 5 6 Delayed
D2FCIV1180 BD 2ndFloor InstallCableTraysandTrunking 12 100.00% 0.00% 13Dec16 26Dec16 31Dec16 12Jan17 15 4 Delayed
D2FCIV1190 BD 2ndFloor InstallLowCurrentWiring 10 100.00% 30.00% 19Dec16 29Dec16 17Dec16A 16Jan17 15 4 Delayed
D2FCIV1200 BD 2ndFloor InstallLVCables 10 100.00% 20.00% 19Dec16 29Dec16 30Nov16A 16Jan17 15 4 Delayed
D2FCIV1210 BD 2ndFloor InstallDroppers 12 41.67% 0.00% 25Dec16 7Jan17 11Jan17 24Jan17 15 4 Delayed
D2FCIV1220 BD 2ndFloor MeggeringTest 10 20.00% 20.00% 28Dec16 8Jan17 21Dec16A 25Jan17 15 4 OnTarget
D2FCIV1230 BD 2ndFloor MEPFinalFixing 10 0.00% 0.00% 8Jan17 18Jan17 25Jan17 5Feb17 15 4 OnTarget
ThirdFloor 59 0.00% 0.00% 27Nov16 2Feb17 26Nov16A 5Feb17 2 100 OnTarget
DryArea 36 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 26 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD3FMEPD1000 BD 3rdFloor DryAreaHLClearancebyARMAforgridfixing 14 100.00% 100.00% 1Dec16 17Dec16 26Nov16A 22Dec16A 4 0 OnTarget
BD3FMEPD1010 BD 3rdFloor DryAreaMEPclearanceforBoardclosing 14 100.00% 65.00% 13Dec16 28Dec16 27Nov16A 7Jan17 7 8 Delayed
BD3FMEPD1020 BD 3rdFloor InstallElectricalWiring 8 100.00% 100.00% 29Nov16 7Dec16 27Nov16A 03Dec16A 5 0 OnTarget
BD3FMEPD1030 BD 3rdFloor InstallDuctsandHangers 7 100.00% 100.00% 5Dec16 12Dec16 27Nov16A 10Dec16A 3 0 OnTarget
BD3FMEPD1040 BD 3rdFloor DBInstallation 10 100.00% 100.00% 5Dec16 15Dec16 27Nov16A 22Dec16A 5 0 OnTarget
BD3FMEPD1050 BD 3rdFloor InstallDroppers 12 100.00% 5.00% 13Dec16 26Dec16 27Nov16A 12Jan17 14 121 Delayed
BD3FMEPD1060 BD 3rdFloor MeggeringTest 7 100.00% 100.00% 21Dec16 28Dec16 27Nov16A 27Nov16A 28 0 OnTarget
WetArea 38 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 32 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD3FMEPW1000 BD 3rdFloor WetAreaMEPclearanceforBoardclosing 10 40.00% 0.00% 26Dec16 5Jan17 3Jan17 15Jan17 8 4 Delayed
BD3FMEPW1010 BD 3rdFloor InstallElectricalWiring 7 100.00% 100.00% 30Nov16 7Dec16 27Nov16A 03Dec16A 5 0 OnTarget
BD3FMEPW1020 BD 3rdFloor InstallDuctsandHangers 10 100.00% 98.00% 30Nov16 11Dec16 27Nov16A 31Dec16 16 0 Delayed
BD3FMEPW1030 BD 3rdFloor InstallDroppers 12 83.33% 0.00% 19Dec16 1Jan17 31Dec16 12Jan17 10 2 Delayed
BD3FMEPW1040 BD 3rdFloor MeggeringTest 5 60.00% 0.00% 27Dec16 1Jan17 8Jan17 12Jan17 10 2 Delayed
Corridor/LiftLobby 37 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 29 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD3FMEPCL1000 BD 3rdFloor CorridorMEPclearanceforBoardclosing 14 57.14% 15.00% 21Dec16 5Jan17 27Nov16A 15Jan17 8 4 Delayed
BD3FMEPCL1010 BD 3rdFloor InstallLVCables 3 100.00% 100.00% 5Dec16 7Dec16 27Nov16A 27Nov16A 10 0 OnTarget
BD3FMEPCL1020 BD 3rdFloor InstallDroppers 10 100.00% 0.00% 4Dec16 14Dec16 31Dec16 10Jan17 23 122 Delayed
BD3FMEPCL1030 BD 3rdFloor MeggeringTest 5 100.00% 100.00% 10Dec16 14Dec16 27Nov16A 29Nov16A 14 0 OnTarget
CommonFinalFinishes 36 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 21 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD3FMEPF1000 BD 3rdFloor MEPFinalFixes/Sanitarywares 18 0.00% 0.00% 31Dec16 19Jan17 8Jan17 29Jan17 8 4 OnTarget
BD3FMEPF1010 BD 3rdFloor InstallLightFittings 14 0.00% 0.00% 4Jan17 19Jan17 12Jan17 29Jan17 8 1 OnTarget
BD3FMEPF1020 BD 3rdFloor InstallFireCabinets 14 0.00% 0.00% 5Jan17 21Jan17 14Jan17 30Jan17 8 1 OnTarget
BD3FMEPF1030 BD 3rdFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 5Jan17 21Jan17 14Jan17 30Jan17 8 1 OnTarget
BD3FMEPF1040 BD 3rdFloor InstallSprinklers 14 0.00% 0.00% 7Jan17 22Jan17 15Jan17 31Jan17 8 1 OnTarget
BD3FMEPF1050 BD 3rdFloor InstallSwitchesandSockets 14 0.00% 0.00% 7Jan17 22Jan17 15Jan17 31Jan17 8 1 OnTarget
BD3FMEPF1060 BD 3rdFloor InstallLowCurrentEquipments 14 0.00% 0.00% 8Jan17 23Jan17 16Jan17 1Feb17 8 1 OnTarget
BD3FMEPF1070 BD 3rdFloor InstallGrillesandDiffussers 14 0.00% 0.00% 8Jan17 23Jan17 16Jan17 1Feb17 8 1 OnTarget
BD3FMEPF1080 BD 3rdFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 8Jan17 23Jan17 16Jan17 1Feb17 8 1 OnTarget
DSide 46 0.00% 0.00% 27Nov16 18Jan17 26Nov16A 8Feb17 18 97 OnTarget
MEPWorks 46 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
D3FCIV1100 3rdFloor InstallWallMEPconduitsforplasterclearance 7 100.00% 100.00% 27Nov16 4Dec16 27Nov16A 10Dec16A 4 0 OnTarget
D3FCIV1110 3rdFloor InstallFloorMEPconduitsforScreedclearance 7 100.00% 100.00% 4Dec16 11Dec16 27Nov16A 10Dec16A 2 0 OnTarget
D3FCIV1120 3rdFloor InstallElectricalWiring 10 100.00% 100.00% 4Dec16 14Dec16 27Nov16A 03Dec16A 11 0 OnTarget
D3FCIV1130 3rdFloor InstallDrainagepipes 10 100.00% 100.00% 6Dec16 17Dec16 27Nov16A 28Dec16A 9 0 OnTarget
D3FCIV1140 3rdFloor Firefightingpipes 10 100.00% 100.00% 10Dec16 20Dec16 27Nov16A 17Dec16A 4 0 OnTarget
D3FCIV1150 3rdFloor InstallHot&ColdWaterPiping 10 100.00% 90.00% 11Dec16 21Dec16 27Nov16A 31Dec16 8 130 Delayed
D3FCIV1160 3rdFloor InstallDuctsandHangers 12 100.00% 60.00% 10Dec16 22Dec16 27Nov16A 4Jan17 11 127 Delayed
D3FCIV1170 3rdFloor InstallHVACPipes 12 100.00% 100.00% 12Dec16 25Dec16 27Nov16A 28Dec16A 2 0 OnTarget
D3FCIV1180 3rdFloor InstallCableTraysandTrunking 12 100.00% 0.00% 13Dec16 26Dec16 31Dec16 12Jan17 15 4 Delayed
D3FCIV1190 3rdFloor InstallLowCurrentWiring 10 100.00% 30.00% 19Dec16 29Dec16 17Dec16A 16Jan17 15 4 Delayed
D3FCIV1200 3rdFloor InstallLVCables 10 100.00% 20.00% 19Dec16 29Dec16 30Nov16A 16Jan17 15 4 Delayed
D3FCIV1210 3rdFloor InstallDroppers 12 41.67% 0.00% 25Dec16 7Jan17 11Jan17 24Jan17 15 4 Delayed
D3FCIV1220 3rdFloor MeggeringTest 10 20.00% 0.00% 28Dec16 8Jan17 15Jan17 25Jan17 15 4 Delayed
D3FCIV1230 3rdFloor MEPFinalFixing 10 0.00% 0.00% 8Jan17 18Jan17 25Jan17 5Feb17 15 4 OnTarget
ForthFloor 59 0.00% 0.00% 29Nov16 28Mar17 26Nov16A 9Apr17 10 46 OnTarget
DryArea 41 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 28 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD4FMEPD1000 BD 4thFloor DryareaPlasterMEPclearance(Hoistarea,Garbage,W 6 100.00% 99.00% 30Nov16 6Dec16 26Nov16A 31Dec16 20 132 Delayed
BD4FMEPD1010 BD 4thFloor DryAreaHLClearancebyARMAforgridfixing 10 100.00% 95.00% 10Dec16 20Dec16 26Nov16A 7Jan17 14 10 Delayed
BD4FMEPD1020 BD 4thFloor DryAreaMEPclearanceforBoardclosing 10 80.00% 0.00% 21Dec16 1Jan17 7Jan17 18Jan17 14 10 Delayed
BD4FMEPD1030 BD 4thFloor InstallDuctsandHangers 7 100.00% 100.00% 1Dec16 8Dec16 27Nov16A 28Dec16A 16 0 OnTarget
BD4FMEPD1040 BD 4thFloor DBInstallation 10 100.00% 100.00% 5Dec16 15Dec16 27Nov16A 22Dec16A 5 0 OnTarget
BD4FMEPD1050 BD 4thFloor InstallDroppers 12 83.33% 0.00% 19Dec16 1Jan17 4Jan17 18Jan17 14 10 Delayed
BD4FMEPD1060 BD 4thFloor MeggeringTest 5 60.00% 75.00% 27Dec16 1Jan17 27Nov16A 18Jan17 14 10 OnTarget
WetArea 36 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 24 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD4FMEPW1000 BD 4thFloor WetAreaMEPclearanceforBoardclosing 10 40.00% 0.00% 26Dec16 5Jan17 10Jan17 22Jan17 13 9 Delayed
BD4FMEPW1010 BD 4thFloor InstallDuctsandHangers 10 100.00% 100.00% 10Dec16 20Dec16 27Nov16A 17Dec16A 4 0 OnTarget
BD4FMEPW1020 BD 4thFloor InstallDroppers 12 75.00% 0.00% 20Dec16 2Jan17 4Jan17 18Jan17 13 6 Delayed
BD4FMEPW1030 BD 4thFloor MeggeringTest 5 40.00% 0.00% 28Dec16 2Jan17 12Jan17 18Jan17 13 6 Delayed
Corridor/LiftLobby 29 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 23 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD4FMEPCL1000 BD 4thFloor CorridorMEPclearanceforBoardclosing 14 57.14% 0.00% 21Dec16 5Jan17 5Jan17 22Jan17 13 9 Delayed
BD4FMEPCL1010 BD 4thFloor InstallHot&ColdWaterPiping 5 100.00% 100.00% 15Dec16 20Dec16 27Nov16A 27Nov16A 21 0 OnTarget
BD4FMEPCL1020 BD 4thFloor InstallDuctsandHangers 10 100.00% 100.00% 11Dec16 21Dec16 27Nov16A 29Nov16A 20 0 OnTarget
BD4FMEPCL1030 BD 4thFloor InstallLVCables 7 100.00% 100.00% 15Dec16 22Dec16 27Nov16A 22Dec16A 1 0 OnTarget
BD4FMEPCL1040 BD 4thFloor InstallDroppers 10 100.00% 0.00% 19Dec16 29Dec16 31Dec16 10Jan17 10 0 Delayed
BD4FMEPCL1050 BD 4thFloor MeggeringTest 5 100.00% 0.00% 25Dec16 29Dec16 5Jan17 10Jan17 10 0 Delayed
CommonFinalFinishes 36 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD4FMEPF1010 BD 4thFloor InstallLightFittings 14 0.00% 0.00% 1Jan17 16Jan17 17Jan17 2Feb17 14 10 OnTarget
BD4FMEPF1020 BD 4thFloor InstallFireCabinets 14 0.00% 0.00% 2Jan17 17Jan17 18Jan17 4Feb17 14 10 OnTarget
BD4FMEPF1030 BD 4thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 2Jan17 17Jan17 18Jan17 4Feb17 14 10 OnTarget
BD4FMEPF1040 BD 4thFloor InstallSprinklers 14 0.00% 0.00% 3Jan17 18Jan17 19Jan17 5Feb17 14 10 OnTarget
BD4FMEPF1050 BD 4thFloor InstallSwitchesandSockets 14 0.00% 0.00% 3Jan17 18Jan17 19Jan17 5Feb17 14 10 OnTarget
BD4FMEPF1060 BD 4thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 4Jan17 19Jan17 21Jan17 6Feb17 14 10 OnTarget
BD4FMEPF1070 BD 4thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 4Jan17 19Jan17 21Jan17 6Feb17 14 10 OnTarget
BD4FMEPF1075 BD 4thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 4Jan17 17Jan17 19Jan17 2Feb17 13 7 OnTarget
BD4FMEPF1080 BD 4thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 4Jan17 19Jan17 21Jan17 6Feb17 14 10 OnTarget
DSide 46 0.00% 0.00% 27Nov16 18Jan17 26Nov16A 8Feb17 18 97 OnTarget
MEPWorks 46 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
D4FCIV1100 BD 4thFloor InstallWallMEPconduitsforplasterclearance 7 100.00% 100.00% 30Nov16 7Dec16 26Nov16A 10Dec16A 1 0 OnTarget
D4FCIV1110 BD 4thFloor InstallFloorMEPconduitsforScreedclearance 7 100.00% 100.00% 7Dec16 14Dec16 03Dec16A 10Dec16A 5 0 OnTarget
D4FCIV1120 BD 4thFloor InstallElectricalWiring 10 100.00% 100.00% 7Dec16 18Dec16 27Nov16A 03Dec16A 14 0 OnTarget
D4FCIV1130 BD 4thFloor InstallDrainagepipes 10 100.00% 100.00% 10Dec16 20Dec16 27Nov16A 28Dec16A 6 0 OnTarget
D4FCIV1140 BD 4thFloor Firefightingpipes 10 100.00% 100.00% 13Dec16 24Dec16 27Nov16A 25Dec16A 0 0 OnTarget
D4FCIV1150 BD 4thFloor InstallHot&ColdWaterPiping 10 100.00% 80.00% 14Dec16 25Dec16 27Nov16A 1Jan17 6 129 Delayed
D4FCIV1160 BD 4thFloor InstallDuctsandHangers 12 100.00% 25.00% 13Dec16 26Dec16 27Nov16A 9Jan17 12 123 Delayed
D4FCIV1170 BD 4thFloor InstallHVACPipes 12 100.00% 100.00% 15Dec16 28Dec16 27Nov16A 28Dec16A 1 0 OnTarget
D4FCIV1180 BD 4thFloor InstallCableTraysandTrunking 12 100.00% 0.00% 17Dec16 29Dec16 31Dec16 12Jan17 12 4 Delayed
D4FCIV1190 BD 4thFloor InstallLowCurrentWiring 10 70.00% 30.00% 22Dec16 2Jan17 17Dec16A 16Jan17 12 4 Delayed
D4FCIV1200 BD 4thFloor InstallLVCables 10 70.00% 20.00% 22Dec16 2Jan17 30Nov16A 16Jan17 12 4 Delayed
D4FCIV1210 BD 4thFloor InstallDroppers 12 16.67% 0.00% 28Dec16 10Jan17 11Jan17 24Jan17 12 4 Delayed
D4FCIV1220 BD 4thFloor MeggeringTest 10 0.00% 0.00% 1Jan17 11Jan17 15Jan17 25Jan17 12 4 OnTarget
D4FCIV1230 BD 4thFloor MEPFinalFixing 10 0.00% 0.00% 11Jan17 22Jan17 25Jan17 5Feb17 12 4 OnTarget
FifthFloor 64 0.00% 0.00% 8Dec16 2Apr17 26Nov16A 11Apr17 8 44 OnTarget
DryArea 44 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 36 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BD5FMEPD1000 BD 5thFloor DryareaPlasterMEPclearance(Hoistarea,Garbage,W 7 100.00% 99.00% 6Dec16 13Dec16 26Nov16A 3Jan17 17 15 Delayed
BD5FMEPD1010 BD 5thFloor DryAreaHLClearancebyARMAforgridfixing 10 100.00% 45.00% 19Dec16 29Dec16 27Nov16A 19Jan17 17 15 Delayed
BD5FMEPD1020 BD 5thFloor DryAreaMEPclearanceforBoardclosing 10 10.00% 0.00% 29Dec16 9Jan17 18Jan17 30Jan17 17 15 Delayed
BD5FMEPD1030 BD 5thFloor InstallLowCurrentWiring 10 100.00% 100.00% 29Nov16 10Dec16 26Nov16A 27Nov16A 12 0 OnTarget
BD5FMEPD1040 BD 5thFloor InstallDuctsandHangers 10 100.00% 85.00% 3Dec16 13Dec16 27Nov16A 1Jan17 16 1 Delayed
BD5FMEPD1050 BD 5thFloor DBInstallation 10 100.00% 100.00% 10Dec16 20Dec16 27Nov16A 22Dec16A 1 0 OnTarget
BD5FMEPD1060 BD 5thFloor InstallDroppers 12 100.00% 0.00% 14Dec16 27Dec16 31Dec16 12Jan17 14 1 Delayed
BD5FMEPD1070 BD 5thFloor MeggeringTest 7 100.00% 45.00% 20Dec16 27Dec16 15Dec16A 12Jan17 14 1 Delayed
WetArea 41 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 35 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD5FMEPW1000 BD 5thFloor WetAreaMEPclearanceforBoardclosing 10 20.00% 0.00% 28Dec16 8Jan17 7Jan17 18Jan17 8 7 Delayed
BD5FMEPW1010 BD 5thFloor InstallElectricalWiring 4 100.00% 100.00% 6Dec16 10Dec16 27Nov16A 03Dec16A 7 0 OnTarget
BD5FMEPW1020 BD 5thFloor InstallHot&ColdWaterPiping 7 100.00% 100.00% 5Dec16 12Dec16 27Nov16A 01Dec16A 10 0 OnTarget
BD5FMEPW1030 BD 5thFloor InstallDuctsandHangers 14 100.00% 85.00% 29Nov16 14Dec16 27Nov16A 2Jan17 15 0 Delayed
BD5FMEPW1040 BD 5thFloor InstallDroppers 12 41.67% 0.00% 25Dec16 7Jan17 3Jan17 17Jan17 8 7 Delayed
BD5FMEPW1050 BD 5thFloor MeggeringTest 5 0.00% 0.00% 3Jan17 8Jan17 12Jan17 18Jan17 8 7 OnTarget
Corridor/liftLobby 31 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 25 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD5FMEPCL1000 BD 5thFloor CorridorMEPclearanceforBoardclosing 14 42.86% 0.00% 24Dec16 8Jan17 2Jan17 18Jan17 8 5 Delayed
BD5FMEPCL1020 BD 5thFloor InstallHot&ColdWaterPiping 10 100.00% 100.00% 11Dec16 21Dec16 27Nov16A 28Dec16A 5 0 OnTarget
BD5FMEPCL1030 BD 5thFloor InstallDuctsandHangers 12 100.00% 100.00% 11Dec16 24Dec16 27Nov16A 29Nov16A 22 0 OnTarget
BD5FMEPCL1040 BD 5thFloor InstallCableTraysandTrunking 7 100.00% 100.00% 18Dec16 25Dec16 07Dec16A 25Dec16A 1 0 OnTarget
BD5FMEPCL1045 BD 5thFloor InstallLowCurrentWiring 12 100.00% 100.00% 15Dec16 28Dec16 27Nov16A 17Dec16A 11 0 OnTarget
BD5FMEPCL1050 BD 5thFloor InstallLVCables 10 100.00% 90.00% 18Dec16 28Dec16 27Nov16A 31Dec16 2 9 Delayed
BD5FMEPCL1060 BD 5thFloor InstallDroppers 12 100.00% 0.00% 17Dec16 29Dec16 31Dec16 12Jan17 12 1 Delayed
BD5FMEPCL1070 BD 5thFloor MeggeringTest 5 100.00% 0.00% 25Dec16 29Dec16 8Jan17 12Jan17 12 1 Delayed
CommonFinalFinishes 36 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD5FMEPF1010 BD 5thFloor InstallLightFittings 14 0.00% 0.00% 4Jan17 19Jan17 24Jan17 9Feb17 17 15 OnTarget
BD5FMEPF1020 BD 5thFloor InstallFireCabinets 14 0.00% 0.00% 5Jan17 21Jan17 25Jan17 11Feb17 17 15 OnTarget
BD5FMEPF1030 BD 5thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 5Jan17 21Jan17 25Jan17 11Feb17 17 15 OnTarget
BD5FMEPF1040 BD 5thFloor InstallSprinklers 14 0.00% 0.00% 7Jan17 22Jan17 26Jan17 12Feb17 17 15 OnTarget
BD5FMEPF1050 BD 5thFloor InstallSwitchesandSockets 14 0.00% 0.00% 7Jan17 22Jan17 26Jan17 12Feb17 17 15 OnTarget
BD5FMEPF1060 BD 5thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 8Jan17 23Jan17 26Jan17 12Feb17 16 15 OnTarget
BD5FMEPF1070 BD 5thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 8Jan17 23Jan17 26Jan17 12Feb17 16 15 OnTarget
BD5FMEPF1075 BD 5thFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 12Jan17 23Jan17 22Jan17 2Feb17 8 7 OnTarget
BD5FMEPF1080 BD 5thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 10 0.00% 0.00% 12Jan17 23Jan17 31Jan17 12Feb17 16 15 OnTarget
SixthFloor 62 0.00% 0.00% 15Dec16 2Apr17 26Nov16A 11Apr17 8 44 OnTarget
DryArea 37 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 29 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD6FMEPD1000 BD 6thFloor DryareaPlasterMEPclearance(Hoistarea,Garbage,W 7 100.00% 99.00% 4Dec16 11Dec16 26Nov16A 3Jan17 19 14 Delayed
BD6FMEPD1010 BD 6thFloor DryAreaHLClearancebyARMAforgridfixing 10 100.00% 20.00% 11Dec16 21Dec16 27Nov16A 14Jan17 19 11 Delayed
BD6FMEPD1020 BD 6thFloor DryAreaMEPclearanceforBoardclosing 10 80.00% 0.00% 21Dec16 1Jan17 12Jan17 24Jan17 19 11 Delayed
BD6FMEPD1030 BD 6thFloor InstallLowCurrentWiring 10 100.00% 80.00% 29Nov16 10Dec16 27Nov16A 1Jan17 19 14 Delayed
BD6FMEPD1040 BD 6thFloor InstallDuctsandHangers 12 100.00% 72.00% 30Nov16 13Dec16 27Nov16A 4Jan17 19 4 Delayed
BD6FMEPD1050 BD 6thFloor DBInstallation 10 100.00% 40.00% 6Dec16 17Dec16 27Nov16A 5Jan17 17 14 Delayed
BD6FMEPD1060 BD 6thFloor InstallDroppers 12 100.00% 0.00% 7Dec16 20Dec16 31Dec16 12Jan17 20 2 Delayed
BD6FMEPD1070 BD 6thFloor MeggeringTest 7 100.00% 0.00% 13Dec16 20Dec16 5Jan17 12Jan17 20 2 Delayed
WetArea 33 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 29 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD6FMEPW1000 BD 6thFloor WetAreaMEPclearanceforBoardclosing 10 50.00% 0.00% 25Dec16 4Jan17 17Jan17 28Jan17 20 15 Delayed
BD6FMEPW1010 BD 6thFloor InstallElectricalWiring 10 100.00% 100.00% 3Dec16 13Dec16 27Nov16A 10Dec16A 4 0 OnTarget
BD6FMEPW1020 BD 6thFloor InstallDrainagepipes 10 100.00% 100.00% 4Dec16 14Dec16 27Nov16A 01Dec16A 12 0 OnTarget
BD6FMEPW1030 BD 6thFloor InstallHot&ColdWaterPiping 10 100.00% 100.00% 5Dec16 15Dec16 27Nov16A 25Dec16A 7 0 OnTarget
BD6FMEPW1040 BD 6thFloor InstallHVACPipes 10 100.00% 100.00% 8Dec16 19Dec16 27Nov16A 17Dec16A 3 0 OnTarget
BD6FMEPW1050 BD 6thFloor InstallDuctsandHangers 14 100.00% 72.00% 7Dec16 22Dec16 27Nov16A 3Jan17 10 0 Delayed
BD6FMEPW1060 BD 6thFloor InstallDroppers 12 58.33% 0.00% 22Dec16 4Jan17 15Jan17 28Jan17 20 15 Delayed
BD6FMEPW1070 BD 6thFloor MeggeringTest 7 28.57% 0.00% 28Dec16 4Jan17 21Jan17 28Jan17 20 15 Delayed
Corridor/LiftLobby 35 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 29 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD6FMEPCL1000 BD 6thFloor CorridorMEPclearanceforBoardclosing 14 64.29% 0.00% 20Dec16 4Jan17 12Jan17 28Jan17 20 15 Delayed
BD6FMEPCL1020 BD 6thFloor InstallHot&ColdWaterPiping 10 100.00% 85.00% 3Dec16 13Dec16 27Nov16A 1Jan17 16 131 Delayed
BD6FMEPCL1030 BD 6thFloor InstallHVACPipes 10 100.00% 100.00% 6Dec16 17Dec16 27Nov16A 01Dec16A 14 0 OnTarget
BD6FMEPCL1040 BD 6thFloor InstallDuctsandHangers 12 100.00% 90.00% 7Dec16 20Dec16 27Nov16A 1Jan17 9 3 Delayed
BD6FMEPCL1050 BD 6thFloor InstallCableTraysandTrunking 10 100.00% 90.00% 13Dec16 24Dec16 07Dec16A 4Jan17 9 3 Delayed
BD6FMEPCL1055 BD 6thFloor InstallLowCurrentWiring 12 100.00% 85.00% 14Dec16 27Dec16 27Nov16A 8Jan17 9 3 Delayed
BD6FMEPCL1060 BD 6thFloor InstallLVCables 10 100.00% 0.00% 17Dec16 27Dec16 31Dec16 10Jan17 12 6 Delayed
BD6FMEPCL1070 BD 6thFloor InstallDroppers 10 60.00% 0.00% 24Dec16 3Jan17 7Jan17 17Jan17 12 6 Delayed
BD6FMEPCL1080 BD 6thFloor MeggeringTest 7 42.86% 0.00% 27Dec16 3Jan17 10Jan17 17Jan17 12 6 Delayed
CommonFinalFinishes 36 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 24 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD6FMEPF1005 BD 6thFloor InstallGYMEquipment 24 4.17% 0.00% 29Dec16 25Jan17 18Jan17 15Feb17 17 15 Delayed
BD6FMEPF1010 BD 6thFloor InstallLightFittings 14 0.00% 0.00% 31Dec16 15Jan17 23Jan17 7Feb17 20 15 OnTarget
BD6FMEPF1020 BD 6thFloor InstallFireCabinets 14 0.00% 0.00% 1Jan17 16Jan17 24Jan17 8Feb17 20 15 OnTarget
BD6FMEPF1030 BD 6thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 1Jan17 16Jan17 24Jan17 8Feb17 20 15 OnTarget
BD6FMEPF1040 BD 6thFloor InstallSprinklers 14 0.00% 0.00% 2Jan17 17Jan17 25Jan17 9Feb17 20 15 OnTarget
BD6FMEPF1050 BD 6thFloor InstallSwitchesandSockets 14 0.00% 0.00% 2Jan17 17Jan17 25Jan17 9Feb17 20 15 OnTarget
BD6FMEPF1060 BD 6thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 3Jan17 18Jan17 26Jan17 11Feb17 20 15 OnTarget
BD6FMEPF1070 BD 6thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 3Jan17 18Jan17 26Jan17 11Feb17 20 15 OnTarget
BD6FMEPF1075 BD 6thFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 4Jan17 15Jan17 28Jan17 7Feb17 20 12 OnTarget
BD6FMEPF1080 BD 6thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 3Jan17 18Jan17 26Jan17 11Feb17 20 15 OnTarget
SeventhFloor 64 0.00% 0.00% 27Nov16 8Feb17 26Nov16A 2Mar17 18 79 OnTarget
DryArea 41 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 35 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD7FMEPD1000 BD 7thFloor DryareaPlasterMEPclearance(Hoistarea,Garbage,W 7 100.00% 99.00% 5Dec16 12Dec16 26Nov16A 4Jan17 19 15 Delayed
BD7FMEPD1010 BD 7thFloor DryAreaHLClearancebyARMAforgridfixing 14 100.00% 10.00% 12Dec16 27Dec16 27Nov16A 18Jan17 18 14 Delayed
BD7FMEPD1020 BD 7thFloor DryAreaMEPclearanceforBoardclosing 14 57.14% 0.00% 21Dec16 5Jan17 11Jan17 28Jan17 18 14 Delayed
BD7FMEPD1030 BD 7thFloor InstallLowCurrentWiring 10 100.00% 80.00% 29Nov16 10Dec16 27Nov16A 1Jan17 19 14 Delayed
BD7FMEPD1040 BD 7thFloor InstallDuctsandHangers 14 100.00% 75.00% 27Nov16 12Dec16 27Nov16A 3Jan17 19 14 Delayed
BD7FMEPD1050 BD 7thFloor DBInstallation 10 100.00% 40.00% 4Dec16 14Dec16 27Nov16A 5Jan17 19 14 Delayed
BD7FMEPD1060 BD 7thFloor InstallDroppers 12 100.00% 0.00% 4Dec16 17Dec16 31Dec16 12Jan17 23 2 Delayed
BD7FMEPD1070 BD 7thFloor MeggeringTest 7 100.00% 0.00% 10Dec16 17Dec16 5Jan17 12Jan17 23 2 Delayed
WetArea 40 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 34 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD7FMEPW1000 BD 7thFloor WetAreaMEPclearanceforBoardclosing 10 30.00% 0.00% 27Dec16 7Jan17 17Jan17 29Jan17 18 15 Delayed
BD7FMEPW1010 BD 7thFloor InstallElectricalWiring 12 100.00% 100.00% 29Nov16 12Dec16 27Nov16A 22Dec16A 8 0 OnTarget
BD7FMEPW1020 BD 7thFloor InstallDrainagepipes 12 100.00% 100.00% 30Nov16 13Dec16 27Nov16A 17Dec16A 2 0 OnTarget
BD7FMEPW1030 BD 7thFloor InstallHot&ColdWaterPiping 12 100.00% 89.00% 1Dec16 14Dec16 27Nov16A 1Jan17 14 4 Delayed
BD7FMEPW1040 BD 7thFloor InstallDuctsandHangers 16 100.00% 7.00% 30Nov16 18Dec16 27Nov16A 16Jan17 25 7 Delayed
BD7FMEPW1050 BD 7thFloor InstallDroppers 12 100.00% 0.00% 7Dec16 20Dec16 4Jan17 18Jan17 25 7 Delayed
BD7FMEPW1060 BD 7thFloor MeggeringTest 5 100.00% 0.00% 15Dec16 20Dec16 12Jan17 18Jan17 25 7 Delayed
Corridor/LiftLobby 38 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 32 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD7FMEPCL1000 BD 7thFloor CorridorMEPclearanceforBoardclosing 10 30.00% 0.00% 27Dec16 7Jan17 17Jan17 29Jan17 18 15 Delayed
BD7FMEPCL1020 BD 7thFloor InstallHot&ColdWaterPiping 12 100.00% 20.00% 3Dec16 15Dec16 27Nov16A 10Jan17 22 10 Delayed
BD7FMEPCL1030 BD 7thFloor InstallDuctsandHangers 14 100.00% 80.00% 1Dec16 17Dec16 27Nov16A 11Jan17 22 10 Delayed
BD7FMEPCL1040 BD 7thFloor InstallCableTraysandTrunking 10 100.00% 0.00% 10Dec16 20Dec16 3Jan17 15Jan17 22 10 Delayed
BD7FMEPCL1045 BD 7thFloor InstallLowCurrentWiring 12 100.00% 70.00% 11Dec16 24Dec16 27Nov16A 18Jan17 22 7 Delayed
BD7FMEPCL1050 BD 7thFloor InstallLVCables 10 100.00% 0.00% 13Dec16 24Dec16 7Jan17 18Jan17 22 10 Delayed
BD7FMEPCL1060 BD 7thFloor InstallDroppers 10 100.00% 0.00% 17Dec16 27Dec16 10Jan17 22Jan17 22 10 Delayed
BD7FMEPCL1070 BD 7thFloor MeggeringTest 7 100.00% 0.00% 20Dec16 27Dec16 14Jan17 22Jan17 22 10 Delayed
CommonFinalFinishes 36 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 18 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD7FMEPF1010 BD 7thFloor InstallLightFittings 14 0.00% 0.00% 2Jan17 17Jan17 23Jan17 8Feb17 18 15 OnTarget
BD7FMEPF1020 BD 7thFloor InstallFireCabinets 14 0.00% 0.00% 3Jan17 18Jan17 24Jan17 9Feb17 18 15 OnTarget
BD7FMEPF1030 BD 7thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 3Jan17 18Jan17 24Jan17 9Feb17 18 15 OnTarget
BD7FMEPF1040 BD 7thFloor InstallSprinklers 14 0.00% 0.00% 4Jan17 19Jan17 25Jan17 11Feb17 18 15 OnTarget
BD7FMEPF1050 BD 7thFloor InstallSwitchesandSockets 14 0.00% 0.00% 4Jan17 19Jan17 25Jan17 11Feb17 18 15 OnTarget
BD7FMEPF1060 BD 7thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 5Jan17 21Jan17 26Jan17 12Feb17 18 15 OnTarget
BD7FMEPF1070 BD 7thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 5Jan17 21Jan17 26Jan17 12Feb17 18 15 OnTarget
BD7FMEPF1075 BD 7thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 9Jan17 22Jan17 25Jan17 8Feb17 14 12 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BD7FMEPF1080 BD 7thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 5Jan17 21Jan17 26Jan17 12Feb17 18 15 OnTarget
EightFloor 59 0.00% 0.00% 30Nov16 16Apr17 26Nov16A 25Apr17 8 32 OnTarget
DryArea 41 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 32 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD8FMEPD1000 BD 8thFloor DryareaPlasterMEPclearance(Hoistarea,Garbage,W 7 100.00% 99.00% 30Nov16 7Dec16 26Nov16A 3Jan17 22 15 Delayed
BD8FMEPD1010 BD 8thFloor DryAreaHLClearancebyARMAforgridfixing 10 100.00% 15.00% 15Dec16 26Dec16 27Nov16A 18Jan17 19 15 Delayed
BD8FMEPD1020 BD 8thFloor DryAreaMEPclearanceforBoardclosing 10 40.00% 0.00% 26Dec16 5Jan17 14Jan17 25Jan17 16 15 Delayed
BD8FMEPD1030 BD 8thFloor InstallElectricalWiring 10 100.00% 100.00% 3Dec16 13Dec16 27Nov16A 10Dec16A 4 0 OnTarget
BD8FMEPD1040 BD 8thFloor InstallLowCurrentWiring 10 100.00% 63.00% 6Dec16 17Dec16 27Nov16A 3Jan17 15 6 Delayed
BD8FMEPD1050 BD 8thFloor InstallDuctsandHangers 12 100.00% 19.00% 7Dec16 20Dec16 27Nov16A 10Jan17 18 9 Delayed
BD8FMEPD1060 BD 8thFloor DBInstallation 10 100.00% 40.00% 7Dec16 18Dec16 27Nov16A 5Jan17 16 14 Delayed
BD8FMEPD1070 BD 8thFloor InstallDroppers 12 100.00% 0.00% 8Dec16 21Dec16 31Dec16 12Jan17 19 8 Delayed
BD8FMEPD1080 BD 8thFloor MeggeringTest 7 100.00% 0.00% 18Dec16 25Dec16 9Jan17 16Jan17 19 8 Delayed
WetArea 35 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 30 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD8FMEPW1000 BD 8thFloor WetAreaMEPclearanceforBoardclosing 10 10.00% 0.00% 29Dec16 9Jan17 17Jan17 29Jan17 16 15 Delayed
BD8FMEPW1010 BD 8thFloor InstallElectricalWiring 10 100.00% 100.00% 7Dec16 18Dec16 27Nov16A 22Dec16A 3 0 OnTarget
BD8FMEPW1020 BD 8thFloor InstallDrainagepipes 12 100.00% 90.00% 6Dec16 19Dec16 27Nov16A 1Jan17 10 130 Delayed
BD8FMEPW1030 BD 8thFloor InstallHot&ColdWaterPiping 12 100.00% 64.00% 7Dec16 20Dec16 27Nov16A 4Jan17 12 128 Delayed
BD8FMEPW1040 BD 8thFloor Firefightingpipes 10 100.00% 100.00% 13Dec16 24Dec16 27Nov16A 25Dec16A 0 0 OnTarget
BD8FMEPW1050 BD 8thFloor InstallDuctsandHangers 12 100.00% 19.00% 12Dec16 25Dec16 27Nov16A 10Jan17 14 3 Delayed
BD8FMEPW1060 BD 8thFloor InstallDroppers 12 100.00% 0.00% 15Dec16 28Dec16 31Dec16 14Jan17 14 3 Delayed
BD8FMEPW1070 BD 8thFloor MeggeringTest 10 100.00% 0.00% 18Dec16 28Dec16 2Jan17 14Jan17 14 3 Delayed
Corridor/LiftLobby 27 0.00% 0.00% 6Dec16 28Feb17 27Nov16A 8Feb17 17 97 OnTarget
MEPWorks 21 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD8FMEPCL1000 BD 8thFloor CorridorMEPclearanceforBoardclosing 12 83.33% 0.00% 19Dec16 1Jan17 3Jan17 16Jan17 13 8 Delayed
BD8FMEPCL1020 BD 8thFloor InstallHot&ColdWaterPiping 10 100.00% 0.00% 10Dec16 20Dec16 31Dec16 10Jan17 18 122 Delayed
BD8FMEPCL1030 BD 8thFloor Firefightingpipes 10 100.00% 100.00% 10Dec16 20Dec16 27Nov16A 17Dec16A 4 0 OnTarget
BD8FMEPCL1040 BD 8thFloor InstallDuctsandHangers 12 100.00% 80.00% 8Dec16 21Dec16 27Nov16A 2Jan17 9 4 Delayed
BD8FMEPCL1050 BD 8thFloor InstallCableTraysandTrunking 10 100.00% 10.00% 14Dec16 25Dec16 27Nov16A 9Jan17 13 8 Delayed
BD8FMEPCL1055 BD 8thFloor InstallLowCurrentWiring 12 100.00% 63.00% 15Dec16 28Dec16 27Nov16A 12Jan17 13 6 Delayed
BD8FMEPCL1060 BD 8thFloor InstallLVCables 10 100.00% 0.00% 18Dec16 28Dec16 2Jan17 12Jan17 13 8 Delayed
BD8FMEPCL1070 BD 8thFloor InstallDroppers 10 80.00% 0.00% 21Dec16 1Jan17 5Jan17 16Jan17 13 8 Delayed
BD8FMEPCL1080 BD 8thFloor MeggeringTest 5 60.00% 0.00% 27Dec16 1Jan17 11Jan17 16Jan17 13 8 Delayed
CommonFinalFinishes 36 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BD8FMEPF1010 BD 8thFloor InstallLightFittings 14 0.00% 0.00% 1Jan17 16Jan17 19Jan17 5Feb17 16 15 OnTarget
BD8FMEPF1020 BD 8thFloor InstallFireCabinets 14 0.00% 0.00% 2Jan17 17Jan17 21Jan17 6Feb17 16 12 OnTarget
BD8FMEPF1030 BD 8thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 2Jan17 17Jan17 21Jan17 6Feb17 16 12 OnTarget
BD8FMEPF1040 BD 8thFloor InstallSprinklers 14 0.00% 0.00% 3Jan17 18Jan17 22Jan17 7Feb17 16 12 OnTarget
BD8FMEPF1050 BD 8thFloor InstallSwitchesandSockets 14 0.00% 0.00% 3Jan17 18Jan17 22Jan17 7Feb17 16 12 OnTarget
BD8FMEPF1060 BD 8thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 4Jan17 19Jan17 23Jan17 8Feb17 16 12 OnTarget
BD8FMEPF1070 BD 8thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 4Jan17 19Jan17 23Jan17 8Feb17 16 12 OnTarget
BD8FMEPF1075 BD 8thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 4Jan17 17Jan17 23Jan17 6Feb17 16 10 OnTarget
BD8FMEPF1080 BD 8thFloor InstallPlumpingFinalTittings(FloorDrains,Floortraps 14 0.00% 0.00% 4Jan17 19Jan17 23Jan17 8Feb17 16 12 OnTarget
RoofFloor 58 0.00% 0.00% 27Nov16 19Mar17 26Nov16A 27Feb17 18 82 OnTarget
General 42 0.00% 0.00% 27Nov16 3Jan17 27Nov16A 17Jan17 11 117 OnTarget
BDRF1090 BD Roof FAHUinstallationandconenction 24 100.00% 100.00% 27Nov16 24Dec16 27Nov16A 05Dec16A 17 0 OnTarget
BDRF1100 BD Roof VRVunitsinstallation/connection/termination 36 80.56% 97.00% 27Nov16 7Jan17 26Nov16A 1Jan17 6 24 OnTarget
BDRF1110 BD Roof GRPWatertankinstallationandconnections 24 58.33% 97.00% 14Dec16 10Jan17 26Nov16A 4Jan17 6 24 OnTarget
FAHURoom 56 0.00% 0.00% 27Nov16 30Jan17 26Nov16A 28Jan17 2 107 OnTarget
BDRF1130 BD Roof PlasterMEpClearance 10 100.00% 100.00% 4Dec16 14Dec16 27Nov16A 10Dec16A 5 0 OnTarget
BDRF1160 BD Roof MEPScreedclearance 10 100.00% 100.00% 12Dec16 22Dec16 27Nov16A 10Dec16A 12 0 OnTarget
BDRF1180 BD Roof MEPInstallations/Connections 32 34.38% 90.00% 18Dec16 23Jan17 27Nov16A 3Jan17 18 22 OnTarget
BDRF1190 BD Roof MEPHLClearancebyARMAforceilingpainting 12 100.00% 50.00% 12Dec16 25Dec16 27Nov16A 5Jan17 10 8 Delayed
BDRF1230 BD Roof MEPFinalFixes 6 0.00% 0.00% 21Jan17 26Jan17 18Jan17 24Jan17 2 6 OnTarget
PumpRoom 56 0.00% 0.00% 27Nov16 30Jan17 26Nov16A 11Feb17 9 4 OnTarget
BDRF1260 BD Roof PlasterMEpClearance 6 100.00% 100.00% 4Dec16 10Dec16 27Nov16A 10Dec16A 1 0 OnTarget
BDRF1290 BD Roof MEPScreedclearance 3 100.00% 100.00% 20Dec16 22Dec16 27Nov16A 10Dec16A 12 0 OnTarget
BDRF1310 BD Roof MEPInstallations/Connections 24 12.50% 15.00% 27Dec16 23Jan17 26Nov16A 23Jan17 1 5 OnTarget
BDRF1320 BD Roof MEPHLClearancebyARMAforceilingpainting 10 90.00% 0.00% 20Dec16 31Dec16 8Jan17 19Jan17 16 5 Delayed
BDRF1360 BD Roof MEPFinalFixes 3 0.00% 0.00% 24Jan17 26Jan17 4Feb17 7Feb17 9 5 OnTarget
Electrical,LC,SMATV,GSMRooms 56 0.00% 0.00% 27Nov16 30Jan17 26Nov16A 5Feb17 5 8 OnTarget
BDRF1380 BD Roof PlasterMEpClearance 10 100.00% 95.00% 13Dec16 24Dec16 27Nov16A 31Dec16 6 5 Delayed
BDRF1410 BD Roof MEPScreedclearance 10 80.00% 20.00% 21Dec16 1Jan17 27Nov16A 14Jan17 11 1 Delayed
BDRF1430 BD Roof MEPInstallations/Connections 24 12.50% 90.00% 27Dec16 23Jan17 26Nov16A 2Jan17 19 23 OnTarget
BDRF1440 BD Roof MEPHLClearancebyARMAforceilingpainting 12 66.67% 0.00% 21Dec16 3Jan17 3Jan17 16Jan17 11 1 Delayed
BDRF1480 BD Roof MEPFinalFixes 6 0.00% 0.00% 21Jan17 26Jan17 26Jan17 1Feb17 5 1 OnTarget
CommonArea 49 0.00% 0.00% 27Nov16 22Jan17 26Nov16A 4Feb17 11 101 OnTarget
MEPservicesroomsandOthers 39 0.00% 0.00% 27Nov16 10Jan17 26Nov16A 4Feb17 21 101 OnTarget
LVRoomB 16 0.00% 0.00% 27Nov16 14Dec16 26Nov16A 5Jan17 19 126 OnTarget
BDSR11100 BD MEPworkCompletionbyARMA 14 100.00% 75.00% 27Nov16 12Dec16 26Nov16A 3Jan17 19 14 Delayed
LVRoomD 19 0.00% 0.00% 27Nov16 18Dec16 26Nov16A 5Jan17 15 127 OnTarget
BDL041050 BD MEPworkCompletionbyARMA 14 100.00% 85.00% 29Nov16 14Dec16 26Nov16A 2Jan17 15 13 Delayed
ElectricalRooms/Telephone/WaterMeterRooms 39 0.00% 0.00% 27Nov16 10Jan17 26Nov16A 22Jan17 9 113 OnTarget
BDEL1000 BD MEPClearanceforPlaster 14 100.00% 100.00% 27Nov16 12Dec16 27Nov16A 01Dec16A 10 0 OnTarget
BDEL1015 BD MEPClearanceforScreed(AsApplicable) 14 100.00% 100.00% 7Dec16 22Dec16 27Nov16A 01Dec16A 19 0 OnTarget
BDEL1060 BD MEPworkCompletionbyARMA 18 100.00% 60.00% 10Dec16 29Dec16 27Nov16A 8Jan17 7 3 Delayed
BDEL1085 BD MEPFinalfittings 4 0.00% 0.00% 3Jan17 7Jan17 14Jan17 18Jan17 9 9 OnTarget
FanRooms 24 0.00% 0.00% 27Nov16 24Dec16 26Nov16A 19Jan17 23 22 OnTarget
BDSR31170 BD MEPworkCompletionbyARMA 18 100.00% 80.00% 29Nov16 19Dec16 26Nov16A 3Jan17 13 24 Delayed
FireWater/IrrigationPump 22 0.00% 0.00% 27Nov16 21Dec16 26Nov16A 5Jan17 13 126 OnTarget
BDFP1020 BD MEPClearanceforScreed(AsApplicable) 3 100.00% 100.00% 4Dec16 6Dec16 27Nov16A 28Nov16A 8 0 OnTarget
BDFP1050 BD MEPworkCompletionbyARMA 18 100.00% 95.00% 28Nov16 18Dec16 27Nov16A 31Dec16 11 27 Delayed
GeneratorRooms 30 0.00% 0.00% 27Nov16 31Dec16 27Nov16A 5Jan17 5 126 OnTarget
BDGN1000 BD MEPClearanceforScreed(AsApplicable) 3 100.00% 100.00% 27Nov16 29Nov16 27Nov16A 27Nov16A 3 0 OnTarget
BDGN1030 BD MEPworkCompletionbyARMA 18 100.00% 85.00% 7Dec16 27Dec16 27Nov16A 2Jan17 5 25 Delayed
GarabageRooms 39 0.00% 0.00% 27Nov16 10Jan17 27Nov16A 16Jan17 5 117 OnTarget
BDGC1020 BD MEPClearanceforScreed(AsApplicable) 3 100.00% 100.00% 4Dec16 6Dec16 27Nov16A 27Nov16A 9 0 OnTarget
BDGC1050 BD MEPworkCompletionbyARMA 18 100.00% 88.00% 30Nov16 20Dec16 27Nov16A 12Jan17 20 16 Delayed
BDGC1070 BD Garbagechuteinstalaltion 24 58.33% 80.00% 14Dec16 10Jan17 27Nov16A 4Jan17 5 23 OnTarget
SwimingPoolandPumpRoom 28 0.00% 0.00% 6Dec16 7Jan17 27Nov16A 4Feb17 24 3 OnTarget
BDRFS2SU1080 BD Roof SwimmingPoolMEPWorks 18 61.11% 35.00% 18Dec16 7Jan17 27Nov16A 4Feb17 24 3 Delayed
StaircaseFinishes 45 0.00% 0.00% 27Nov16 17Jan17 26Nov16A 4Feb17 14 102 OnTarget
BDST1020 BD PlasterMEPClearance 18 100.00% 100.00% 27Nov16 17Dec16 26Nov16A 05Dec16A 11 0 OnTarget
OTS 41 0.00% 0.00% 27Nov16 12Jan17 26Nov16A 23Jan17 9 9 OnTarget
BDOTS1020 BD MEPCutting&Chasingforconduits 12 100.00% 100.00% 30Nov16 13Dec16 27Nov16A 29Nov16A 13 0 OnTarget
BDOTS1090 BD MEPWork 24 50.00% 50.00% 17Dec16 12Jan17 01Dec16A 23Jan17 9 9 OnTarget
Roofing 45 0.00% 0.00% 27Nov16 16Feb17 26Nov16A 7Feb17 8 83 OnTarget
BDRF1080 BD Roof RoofEquipmentInstallation&Conncetion 36 55.56% 97.00% 7Dec16 17Jan17 26Nov16A 1Jan17 15 27 OnTarget
ExternalElevation 51 0.00% 0.00% 27Nov16 25Feb17 26Nov16A 6Mar17 8 75 OnTarget
SouthSide 37 0.00% 0.00% 27Nov16 8Jan17 26Nov16A 8Jan17 1 125 OnTarget
BDELS2SU1090 BD MEPFittings 10 50.00% 100.00% 25Dec16 4Jan17 26Nov16A 26Nov16A 35 0 OnTarget
Westside 51 0.00% 0.00% 27Nov16 24Jan17 26Nov16A 29Jan17 4 1 OnTarget
BDELS1SU1130 BD MEPCutting&Chasingforconduits 10 100.00% 100.00% 4Dec16 14Dec16 26Nov16A 10Dec16A 5 0 OnTarget
BDELS2SU1200 BD MEPFittings 10 0.00% 0.00% 10Jan17 21Jan17 14Jan17 25Jan17 4 1 OnTarget
Northside 49 0.00% 0.00% 27Nov16 22Jan17 26Nov16A 1Feb17 9 2 OnTarget
BDELS1SU1240 BD MEPCutting&Chasingforconduits 12 100.00% 100.00% 1Dec16 14Dec16 27Nov16A 27Nov16A 16 0 OnTarget
BDELS2SU1310 BD MEPFittings 12 0.00% 0.00% 5Jan17 18Jan17 16Jan17 29Jan17 9 2 OnTarget
EastSide 48 0.00% 0.00% 27Nov16 21Jan17 26Nov16A 2Feb17 11 102 OnTarget
BDELS2SU1420 BD MEPFittings 10 0.00% 0.00% 5Jan17 16Jan17 18Jan17 29Jan17 11 3 OnTarget
Courtyardarea 41 0.00% 0.00% 27Nov16 12Jan17 26Nov16A 5Jan17 6 126 OnTarget
BDELS1SU1460 BD MEPCutting&Chasingforconduits 6 100.00% 100.00% 27Nov16 3Dec16 27Nov16A 01Dec16A 2 0 OnTarget
BDELS2SU1530 BD MEPFittings 10 10.00% 100.00% 29Dec16 9Jan17 03Dec16A 03Dec16A 33 0 OnTarget
ExternalWork 32 0.00% 0.00% 6Feb17 4Apr17 15Feb17 6Apr17 2 2 OnTarget
BDEXS1SU1250 BD ExternalMEPServices 18 0.00% 0.00% 18Jan17 7Feb17 28Jan17 16Feb17 8 90 OnTarget
BDEXS2SU1280 BD ExternalWaterFeatureMEPWorks 24 0.00% 0.00% 19Jan17 15Feb17 29Jan17 25Feb17 8 3 OnTarget
Testing&Commissioning 41 0.00% 0.00% 27Feb17 30Apr17 1Mar17 2May17 2 25 OnTarget
BDTCS3ME1100 BD Testing&CommissioningforAllSystem 36 0.00% 0.00% 11Jan17 21Feb17 29Jan17 12Mar17 15 15 OnTarget
Electrical 24 0.00% 0.00% 27Feb17 9Apr17 1Mar17 11Apr17 2 43 OnTarget
BDTC1110 BD TestingandCommissioningofLVPanels&System 24 0.00% 0.00% 11Jan17 7Feb17 29Jan17 26Feb17 15 83 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BDTC1120 BD TestingandCommissioningofMCC's 24 0.00% 0.00% 11Jan17 7Feb17 29Jan17 26Feb17 15 83 OnTarget
BDTC1130 BD TestingandCommissioningofLightningProtectionSys 18 0.00% 0.00% 18Jan17 7Feb17 5Feb17 26Feb17 15 83 OnTarget
BDTC1140 BD TestingandCommissioningofGenerator 10 0.00% 0.00% 28Jan17 7Feb17 14Feb17 26Feb17 15 83 OnTarget
BDTC1150 BD TestingandCommissioningofEarthingSystem 18 0.00% 0.00% 18Jan17 7Feb17 5Feb17 26Feb17 15 83 OnTarget
LowCurrentSystems 24 0.00% 0.00% 27Feb17 30Mar17 1Mar17 2Apr17 2 2 OnTarget
BDTC1200 BD TestAudioVisualSystem 18 0.00% 0.00% 15Jan17 4Feb17 1Feb17 22Feb17 15 15 OnTarget
BDTC1210 BD TestUPS 12 0.00% 0.00% 22Jan17 4Feb17 8Feb17 22Feb17 15 15 OnTarget
BDTC1220 BD TestFireAlarmSystem 24 0.00% 0.00% 8Jan17 4Feb17 25Jan17 22Feb17 15 15 OnTarget
BDTC1230 BD TestCentralBatterySystem 24 0.00% 0.00% 8Jan17 4Feb17 25Jan17 22Feb17 15 15 OnTarget
BDTC1240 BD TestStructuredCabling(data&telecom) 24 0.00% 0.00% 8Jan17 4Feb17 25Jan17 22Feb17 15 15 OnTarget
BDTC1250 BD TestLightingControlSystem 21 0.00% 0.00% 11Jan17 4Feb17 29Jan17 22Feb17 15 15 OnTarget
BDTC1260 BD TestSMATV 21 0.00% 0.00% 11Jan17 4Feb17 29Jan17 22Feb17 15 15 OnTarget
BDTC1270 BD TestVoiceEvacuationSystem 24 0.00% 0.00% 8Jan17 4Feb17 25Jan17 22Feb17 15 15 OnTarget
BDTC1280 BD TestCCTVandAccessControlSystem 18 0.00% 0.00% 15Jan17 4Feb17 1Feb17 22Feb17 15 15 OnTarget
BDTC1290 BD TestGRMSSystem 24 0.00% 0.00% 8Jan17 4Feb17 25Jan17 22Feb17 15 15 OnTarget
FireFightingSystems 15 0.00% 0.00% 6Mar17 5Apr17 8Mar17 8Apr17 2 2 OnTarget
BDTC1300 BD Testing&CommissioningofFireFHC's 10 0.00% 0.00% 11Jan17 22Jan17 29Jan17 9Feb17 15 14 OnTarget
BDTC1310 BD Testing&CommissioningofGasFireSuppressionSyste 15 0.00% 0.00% 5Jan17 22Jan17 23Jan17 9Feb17 15 14 OnTarget
BDTC1320 BD Testing&CommissioningofFirePumps 12 0.00% 0.00% 9Jan17 22Jan17 26Jan17 9Feb17 15 14 OnTarget
DrainageSystems 16 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 2 OnTarget
BDTC1170 BD TestingandCommissioningofPumps 10 0.00% 0.00% 25Jan17 5Feb17 12Feb17 23Feb17 15 11 OnTarget
BDTC1180 BD TestingandCommissioningofDrainageSystem 15 0.00% 0.00% 26Jan17 12Feb17 13Feb17 2Mar17 15 11 OnTarget
WaterSupplySystem 22 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 8 OnTarget
BDTC1020 BD TestingandCommissioningofWaterTank 10 0.00% 0.00% 11Jan17 22Jan17 29Jan17 9Feb17 15 14 OnTarget
BDTC1030 BD WaterSupplyFlushingandChlorination 10 0.00% 0.00% 15Jan17 25Jan17 1Feb17 13Feb17 15 14 OnTarget
BDTC1040 BD TestingandCommissioningofPumps 12 0.00% 0.00% 16Jan17 29Jan17 2Feb17 16Feb17 15 14 OnTarget
BDTC1050 BD TestingandCommissioningofWaterHeaters 18 0.00% 0.00% 16Jan17 5Feb17 2Feb17 23Feb17 15 14 OnTarget
HVACSystem 31 0.00% 0.00% 27Feb17 30Apr17 1Mar17 2May17 2 0 OnTarget
BDTC1070 BD Testing&CommissioningofVRFSystem 24 0.00% 0.00% 11Jan17 7Feb17 29Jan17 26Feb17 15 14 OnTarget
BDTC1080 BD DXUnitIndoor 10 0.00% 0.00% 31Jan17 11Feb17 18Feb17 1Mar17 15 14 OnTarget
BDTC1090 BD DXUnitOutdoor 10 0.00% 0.00% 4Feb17 14Feb17 21Feb17 5Mar17 15 14 OnTarget
BDTC1100 BD AirBalancing 24 0.00% 0.00% 19Jan17 15Feb17 6Feb17 6Mar17 15 14 OnTarget
BMSSystem 24 0.00% 0.00% 27Mar17 23Apr17 29Mar17 25Apr17 2 5 OnTarget
BDTC1160 BD BMSSystemtTesting&Commissioning 24 0.00% 0.00% 11Jan17 7Feb17 29Jan17 26Feb17 15 13 OnTarget
LPGSystem 20 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 0 OnTarget
BDTC1060 BD Testing&CommissioningofLPGSystem 20 0.00% 0.00% 11Jan17 2Feb17 29Jan17 21Feb17 15 15 OnTarget
BoilerSystem 10 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 0 OnTarget
BDTC1190 BD Testing&CommissioningofBoilerSystem 10 0.00% 0.00% 18Jan17 29Jan17 5Feb17 16Feb17 15 14 OnTarget
AuthorityApproval 74 0.00% 0.00% 27Nov16 17May17 02Dec16A 18May17 1 1 OnTarget
Transformer&RMUworks(HVApprovals) 36 0.00% 0.00% 27Nov16 5Feb17 02Dec16A 23Jan17 11 37 OnTarget
BDAAMEP1010 BD Transformerinstallation&Connection 24 100.00% 100.00% 27Nov16 24Dec16 26Nov16A 26Nov16A 25 0 OnTarget
BDAAMEP1020 BD AuthorityApproval 12 41.67% 0.00% 25Dec16 7Jan17 31Dec16 12Jan17 5 10 Delayed
LVApproval 33 0.00% 0.00% 29Jan17 7Mar17 17Jan17 23Feb17 10 10 OnTarget
BDAAMEP1030 BD RequestforDEWAinspection 4 100.00% 0.00% 19Dec16 22Dec16 8Jan17 11Jan17 14 12 Delayed
BDAAMEP1040 BD DEWA1stinspection 7 85.71% 0.00% 24Dec16 31Dec16 12Jan17 19Jan17 17 14 Delayed
BDAAMEP1050 BD ClearDEWAsnag&applyforfinalinspection 5 0.00% 0.00% 1Jan17 5Jan17 21Jan17 25Jan17 17 14 OnTarget
BDAAMEP1060 BD Dewasecondinspection/Approval 5 0.00% 0.00% 7Jan17 11Jan17 26Jan17 31Jan17 17 14 OnTarget
BDAAMEP1070 BD Collection&installationofKWHmeters 10 0.00% 0.00% 14Jan17 24Jan17 30Jan17 9Feb17 14 14 OnTarget
BDAAMEP1080 BD TemporarystablePoweron 0 0.00% 0.00% 0Jan00 24Jan17 0Jan00 9Feb17 14 14 OnTarget
BDAAMEP1220 BD Energize 1 0.00% 0.00% 25Jan17 25Jan17 11Feb17 11Feb17 14 14 OnTarget
WaterSupplyApproval 73 0.00% 0.00% 27Nov16 15May17 31Dec16 17May17 2 0 OnTarget
BDAAMEP1090 BD PaymentforWaterMeters 12 100.00% 0.00% 27Nov16 10Dec16 31Dec16 12Jan17 28 7 Delayed
BDAAMEP1100 BD WaterMeterdelivery 12 100.00% 0.00% 11Dec16 24Dec16 14Jan17 26Jan17 29 6 Delayed
BDAAMEP1110 BD DEWAInspection 6 0.00% 0.00% 3Jan17 10Jan17 15Jan17 22Jan17 8 6 OnTarget
BDAAMEP1120 BD DewaApproval 6 0.00% 0.00% 11Jan17 17Jan17 23Jan17 29Jan17 10 8 OnTarget
BDAAMEP1130 BD InstalWaterMeter 3 0.00% 0.00% 18Jan17 21Jan17 30Jan17 1Feb17 10 8 OnTarget
BDAAMEP1140 BD Testing&Commisioning 12 0.00% 0.00% 23Jan17 5Feb17 9Feb17 23Feb17 15 14 OnTarget
BDAAMEP1150 BD ObtainNOCfromDEWAforWater 12 0.00% 0.00% 6Feb17 19Feb17 23Feb17 9Mar17 15 14 OnTarget
TelecomApproval 34 0.00% 0.00% 14Feb17 30Apr17 27Feb17 11May17 9 5 OnTarget
BDAAMEP1160 BD CompletionofTelecomroom 0 0.00% 0.00% 0Jan00 10Jan17 0Jan00 22Jan17 9 9 OnTarget
BDAAMEP1170 BD SubmitApplication 1 0.00% 0.00% 10Jan17 10Jan17 19Jan17 22Jan17 7 6 OnTarget
BDAAMEP1180 BD EtisalatInspection 6 0.00% 0.00% 11Jan17 18Jan17 22Jan17 30Jan17 7 6 OnTarget
BDAAMEP1190 BD CoordinationwithEtisalatContractor 10 0.00% 0.00% 19Jan17 30Jan17 30Jan17 11Feb17 9 8 OnTarget
BDAAMEP1200 BD Testing&Commisioning 10 0.00% 0.00% 31Jan17 11Feb17 11Feb17 22Feb17 9 8 OnTarget
BDAAMEP1210 BD Inspection&ApprovalbyEtisalat 6 0.00% 0.00% 12Feb17 18Feb17 22Feb17 1Mar17 9 7 OnTarget
GSMApproval(Etisalat) 35 0.00% 0.00% 15Feb17 16Apr17 27Feb17 27Apr17 9 17 OnTarget
BDAAMEP1230 BD RequestforSiteSurvey 2 0.00% 0.00% 11Jan17 12Jan17 22Jan17 24Jan17 7 7 OnTarget
BDAAMEP1240 BD SiteSurveybyEtisalat(AfterStrCompletion) 6 0.00% 0.00% 14Jan17 19Jan17 24Jan17 31Jan17 9 9 OnTarget
BDAAMEP1250 BD CoordinationwithEtisalatContractor 10 0.00% 0.00% 21Jan17 31Jan17 31Jan17 12Feb17 9 9 OnTarget
BDAAMEP1260 BD Testing&Commisioning 10 0.00% 0.00% 1Feb17 12Feb17 12Feb17 23Feb17 9 9 OnTarget
BDAAMEP1270 BD FinalApprovalbyAuthority 7 0.00% 0.00% 13Feb17 20Feb17 23Feb17 4Mar17 9 9 OnTarget
BDAAMEP1280 BD ObtainNOCfromEtisalat 6 0.00% 0.00% 13Feb17 20Feb17 23Feb17 5Mar17 8 8 OnTarget
CivilDefence 22 0.00% 0.00% 5Mar17 16Apr17 8Mar17 19Apr17 3 20 OnTarget
BDAAMEP1290 BD RequestforDCDinspection 0 0.00% 0.00% 0Jan00 17Jan17 0Jan00 5Feb17 12 12 OnTarget
BDAAMEP1300 BD DCDInspection 6 0.00% 0.00% 10Jan17 17Jan17 26Jan17 5Feb17 12 12 OnTarget
BDAAMEP1310 BD ClearDCDsnags&requestfor2ndinspection 3 0.00% 0.00% 18Jan17 22Jan17 5Feb17 8Feb17 12 4 OnTarget
BDAAMEP1320 BD DCDsecondinspection 6 0.00% 0.00% 23Jan17 30Jan17 8Feb17 16Feb17 12 4 OnTarget
BDAAMEP1330 BD IssuanceofCivilDefensecertificate 7 0.00% 0.00% 31Jan17 8Feb17 16Feb17 27Feb17 12 4 OnTarget
CivilDefenceExternalFireHydrant 23 0.00% 0.00% 5Mar17 16Apr17 8Mar17 19Apr17 3 20 OnTarget
BDAAMEP1340 BD RequestforDCDinspection 0 0.00% 0.00% 0Jan00 17Jan17 0Jan00 5Feb17 12 11 OnTarget
BDAAMEP1350 BD DCDInspection 6 0.00% 0.00% 18Jan17 25Jan17 5Feb17 13Feb17 12 11 OnTarget
BDAAMEP1360 BD ClearDCDsnags&requestfor2ndinspection 3 0.00% 0.00% 26Jan17 30Jan17 13Feb17 16Feb17 12 11 OnTarget
BDAAMEP1370 BD DCDsecondinspection 7 0.00% 0.00% 31Jan17 8Feb17 16Feb17 27Feb17 12 11 OnTarget
BDAAMEP1380 BD IssuanceofCivilDefensecertificate 7 0.00% 0.00% 9Feb17 19Feb17 27Feb17 8Mar17 12 11 OnTarget
24X7DirectAlaram 49 0.00% 0.00% 20Mar17 11May17 23Mar17 16May17 4 1 OnTarget
BDAAMEP1390 BD SubmitApplication 1 100.00% 0.00% 20Dec16 20Dec16 1Jan17 1Jan17 8 5 Delayed
BDAAMEP1400 BD InspectionbyAuthority 6 100.00% 0.00% 21Dec16 28Dec16 2Jan17 9Jan17 8 5 Delayed
BDAAMEP1410 BD Releaseofestimate 6 16.67% 0.00% 29Dec16 4Jan17 10Jan17 16Jan17 10 6 Delayed
BDAAMEP1420 BD Payment 6 0.00% 0.00% 18Jan17 24Jan17 6Feb17 13Feb17 16 11 OnTarget
BDAAMEP1430 BD PanelInstallation 10 0.00% 0.00% 25Jan17 5Feb17 13Feb17 25Feb17 16 11 OnTarget
BDAAMEP1440 BD ObtainNOC 7 0.00% 0.00% 6Feb17 14Feb17 26Feb17 6Mar17 14 10 OnTarget
LPG 27 0.00% 0.00% 5Apr17 15May17 9Apr17 17May17 2 0 OnTarget
BDAAMEP1450 BD RequestforLPGinspection 0 0.00% 0.00% 0Jan00 12Jan17 0Jan00 23Jan17 7 7 OnTarget
BDAAMEP1460 BD LPGInspection 6 0.00% 0.00% 15Jan17 22Jan17 23Jan17 31Jan17 7 7 OnTarget
BDAAMEP1470 BD ClearLPGsnags&requestfor2ndinspection 5 0.00% 0.00% 23Jan17 29Jan17 31Jan17 7Feb17 7 7 OnTarget
BDAAMEP1480 BD LPGsecondinspection 6 0.00% 0.00% 30Jan17 6Feb17 16Feb17 23Feb17 13 13 OnTarget
BDAAMEP1490 BD NOCfromAuthority 10 0.00% 0.00% 7Feb17 20Feb17 26Feb17 9Mar17 13 13 OnTarget
DubaiPolice 46 0.00% 0.00% 28Mar17 17May17 29Mar17 18May17 1 1 OnTarget
BDAAMEP1500 BD SubmitApplication 3 33.33% 0.00% 29Dec16 2Jan17 15Jan17 17Jan17 11 1 Delayed
BDAAMEP1510 BD 1stInspectionbyAuthority 7 0.00% 0.00% 3Jan17 11Jan17 18Jan17 26Jan17 11 1 OnTarget
BDAAMEP1520 BD Commets&Rectification 7 0.00% 0.00% 12Jan17 19Jan17 28Jan17 4Feb17 13 1 OnTarget
BDAAMEP1530 BD FinalInspection&Approval 7 0.00% 0.00% 4Feb17 11Feb17 21Feb17 1Mar17 15 15 OnTarget
BDAAMEP1540 BD ObtainNOCfromDubaiPolice 7 0.00% 0.00% 12Feb17 20Feb17 1Mar17 12Mar17 13 13 OnTarget
DMApproval 36 0.00% 0.00% 20Mar17 17May17 22Mar17 18May17 1 1 OnTarget
BDAAMEP1550 BD Requestforinspection 3 0.00% 0.00% 15Jan17 17Jan17 31Jan17 5Feb17 12 12 OnTarget
BDAAMEP1560 BD EHSInspection 7 0.00% 0.00% 10Jan17 17Jan17 28Jan17 5Feb17 15 14 OnTarget
BDAAMEP1570 BD DMfirstinspection 7 0.00% 0.00% 18Jan17 26Jan17 5Feb17 14Feb17 12 12 OnTarget
BDAAMEP1580 BD DMCommentrectification 7 0.00% 0.00% 27Jan17 2Feb17 14Feb17 21Feb17 18 16 OnTarget
BDAAMEP1590 BD DMfinalinspection&Approval 7 0.00% 0.00% 5Feb17 13Feb17 21Feb17 2Mar17 12 12 OnTarget
BDAAMEP1600 BD FICconnection 6 0.00% 0.00% 14Feb17 20Feb17 2Mar17 9Mar17 14 14 OnTarget
BDAAMEP1610 BD StromWaterConnection 6 0.00% 0.00% 14Feb17 20Feb17 2Mar17 9Mar17 14 14 OnTarget
BDAAMEP1620 BD ObtainBuildingCompletionCertificate 0 0.00% 0.00% 0Jan00 20Feb17 0Jan00 12Mar17 16 16 OnTarget
ProjectCloseOut1 52 0.00% 0.00% 31Dec16 28Feb17 18Jan17 20Mar17 16 16 OnTarget
BAPC1000 BA O&MManualSubmission 18 0.00% 0.00% 4Feb17 23Feb17 22Feb17 15Mar17 16 12 OnTarget
BAPC1010 BA O&MTaining 15 0.00% 0.00% 7Feb17 23Feb17 26Feb17 15Mar17 16 12 OnTarget
BAPC1030 BA AsBuiltDrawings 48 0.00% 0.00% 31Dec16 23Feb17 18Jan17 15Mar17 16 12 OnTarget
BDTCS3ME1120 BD Snagandcleaning/HandingOver 18 0.00% 0.00% 8Feb17 28Feb17 27Feb17 20Mar17* 16 16 OnTarget
BuildingA BA 133 1.34% 0.00% 27Nov16 30Apr17 02Nov16A 9May17 8 20 Delayed
InsideWork(ApartmentsandOthers) 120 0.00% 0.00% 27Nov16 25Apr17 23Nov16A 2May17 5 27 OnTarget
Basement02 88 0.00% 0.00% 27Nov16 19Mar17 27Nov16A 28Mar17 8 56 OnTarget
MEPWorks 88 0.00% 0.00% 27Nov16 2Mar17 27Nov16A 12Mar17 8 70 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
MEP2ndFix 39 0.00% 0.00% 27Nov16 1Jan17 26Nov16A 23Jan17 19 111 OnTarget
BAB2MEP1000 BA Basement2 MEP2ndfixingcompletion 12 100.00% 40.00% 12Dec16 25Dec16 27Nov16A 17Jan17 20 8 Delayed
BAB2MEP1010 BA Basement2 MEPclearanceforboardclosing 10 0.00% 0.00% 31Dec16 10Jan17 23Jan17 2Feb17 20 8 OnTarget
BAB2MEP1020 BA Basement2 InstallElectricalWiring 10 100.00% 90.00% 27Nov16 7Dec16 27Nov16A 31Dec16 20 8 Delayed
BAB2MEP1040 BA Basement2 InstallHot&ColdWaterPiping 10 100.00% 75.00% 29Nov16 10Dec16 26Nov16A 2Jan17 20 8 Delayed
BAB2MEP1050 BA Basement2 InstallHVACPipes 10 100.00% 70.00% 30Nov16 11Dec16 27Nov16A 3Jan17 20 8 Delayed
BAB2MEP1060 BA Basement2 InstallDuctsandHangers 10 100.00% 92.00% 4Dec16 14Dec16 27Nov16A 7Jan17 20 8 Delayed
BAB2MEP1070 BA Basement2 InstallCableTraysandTrunking 12 100.00% 96.00% 5Dec16 18Dec16 27Nov16A 10Jan17 20 8 Delayed
BAB2MEP1075 BA Basement2 InstallLowCurrentWiring 12 100.00% 25.00% 12Dec16 25Dec16 27Nov16A 17Jan17 20 8 Delayed
BAB2MEP1080 BA Basement2 InstallLVCables 10 100.00% 0.00% 14Dec16 25Dec16 7Jan17 17Jan17 20 8 Delayed
BAB2MEP1090 BA Basement2 InstallDroppers 12 25.00% 0.00% 27Dec16 9Jan17 19Jan17 1Feb17 20 7 Delayed
BAB2MEP1100 BA Basement2 MeggeringTest 7 0.00% 0.00% 2Jan17 9Jan17 25Jan17 1Feb17 20 7 OnTarget
BAB2MEP1110 BA Basement2 InstallEarthpit 18 83.33% 50.00% 13Dec16 2Jan17 27Nov16A 25Jan17 20 3 Delayed
MEPFinalFix 40 0.00% 0.00% 11Jan17 22Jan17 17Dec16A 13Feb17 19 11 OnTarget
BAB2MEP2010 BA Basement2 InstallLightFittings 10 0.00% 0.00% 22Jan17 1Feb17 14Feb17 25Feb17 20 2 OnTarget
BAB2MEP2020 BA Basement2 InstallFireCabinets 10 0.00% 0.00% 25Jan17 5Feb17 18Feb17 28Feb17 20 2 OnTarget
BAB2MEP2030 BA Basement2 InstallFireAlarmsandSpeakers 10 0.00% 0.00% 29Jan17 8Feb17 21Feb17 4Mar17 20 2 OnTarget
BAB2MEP2040 BA Basement2 InstallSprinklers 10 0.00% 0.00% 1Feb17 12Feb17 25Feb17 7Mar17 20 2 OnTarget
BAB2MEP2050 BA Basement2 InstallSwitchesandSockets 10 0.00% 0.00% 5Feb17 15Feb17 28Feb17 11Mar17 20 2 OnTarget
BAB2MEP2060 BA Basement2 InstallLowCurrentEquipments 10 0.00% 0.00% 8Feb17 19Feb17 4Mar17 14Mar17 20 2 OnTarget
BAB2MEP2070 BA Basement2 InstallGrillesandDiffussers 10 0.00% 0.00% 12Feb17 22Feb17 7Mar17 18Mar17 20 2 OnTarget
BAB2MEP2075 BA Basement2 MEPFinalfittings 12 0.00% 0.00% 23Feb17 8Mar17 15Mar17 28Mar17 17 8 OnTarget
BAB2MEP2080 BA Basement2 InstallPlumpingFinalTittings(FloorDrains,Gratings,F 10 0.00% 0.00% 15Feb17 26Feb17 11Mar17 21Mar17 20 2 OnTarget
Basement01 83 0.00% 0.00% 29Dec16 25Apr17 27Nov16A 28Mar17 24 41 OnTarget
MEPWorks 83 0.00% 0.00% 27Nov16 2Mar17 27Nov16A 12Mar17 8 70 OnTarget
MEP2ndFix 40 0.00% 0.00% 27Nov16 1Jan17 26Nov16A 23Jan17 19 111 OnTarget
BAB1MEP1020 BA Basement1 InstallElectricalWiring 10 100.00% 65.00% 4Dec16 14Dec16 27Nov16A 3Jan17 17 7 Delayed
BAB1MEP1040 BA Basement1 InstallHot&ColdWaterPiping 10 100.00% 72.00% 7Dec16 18Dec16 26Nov16A 7Jan17 17 7 Delayed
BAB1MEP1050 BA Basement1 InstallHVACPipes 12 100.00% 90.00% 8Dec16 21Dec16 27Nov16A 10Jan17 17 7 Delayed
BAB1MEP1060 BA Basement1 InstallDuctsandHangers 10 100.00% 92.00% 14Dec16 25Dec16 27Nov16A 14Jan17 17 7 Delayed
BAB1MEP1070 BA Basement1 InstallCableTraysandTrunking 12 100.00% 95.00% 15Dec16 28Dec16 27Nov16A 17Jan17 17 7 Delayed
BAB1MEP1075 BA Basement1 InstallLowCurrentWiring 12 83.33% 9.00% 19Dec16 1Jan17 27Nov16A 21Jan17 17 7 Delayed
BAB1MEP1080 BA Basement1 InstallLVCables 10 80.00% 0.00% 21Dec16 1Jan17 10Jan17 21Jan17 17 7 Delayed
BAB1MEP1085 BA Basement1 HLClearancebyARMAforgridfixing 10 80.00% 0.00% 21Dec16 1Jan17 10Jan17 21Jan17 17 7 Delayed
BAB1MEP1090 BA Basement1 InstallDroppers 10 50.00% 0.00% 25Dec16 4Jan17 14Jan17 24Jan17 17 5 Delayed
BAB1MEP1100 BA Basement1 MeggeringTest 10 50.00% 0.00% 25Dec16 4Jan17 14Jan17 24Jan17 17 5 Delayed
BAB1MEP1105 BA Basement1 MEPclearanceforboardclosing 10 0.00% 0.00% 8Jan17 18Jan17 28Jan17 7Feb17 17 7 OnTarget
MEPFinalFix 36 0.00% 0.00% 11Jan17 22Jan17 17Dec16A 13Feb17 19 11 OnTarget
BAB1MEP2010 BA Basement1 InstallLightFittings 10 0.00% 0.00% 28Jan17 7Feb17 16Feb17 27Feb17 17 4 OnTarget
BAB1MEP2020 BA Basement1 InstallFireCabinets 10 0.00% 0.00% 31Jan17 11Feb17 20Feb17 2Mar17 17 4 OnTarget
BAB1MEP2030 BA Basement1 InstallFireAlarmsandSpeakers 10 0.00% 0.00% 4Feb17 14Feb17 23Feb17 6Mar17 17 4 OnTarget
BAB1MEP2040 BA Basement1 InstallSprinklers 10 0.00% 0.00% 7Feb17 18Feb17 27Feb17 9Mar17 17 4 OnTarget
BAB1MEP2050 BA Basement1 InstallSwitchesandSockets 10 0.00% 0.00% 11Feb17 21Feb17 2Mar17 13Mar17 17 4 OnTarget
BAB1MEP2060 BA Basement1 InstallLowCurrentEquipments 10 0.00% 0.00% 14Feb17 25Feb17 6Mar17 16Mar17 17 4 OnTarget
BAB1MEP2070 BA Basement1 InstallGrillesandDiffussers 10 0.00% 0.00% 18Feb17 28Feb17 9Mar17 20Mar17 17 4 OnTarget
BAB1MEP2075 BA Basement1 MEPFinalfittings 12 0.00% 0.00% 25Feb17 9Mar17 14Mar17 27Mar17 15 7 OnTarget
BAB1MEP2080 BA Basement1 InstallPlumpingFinalTittings(FloorDrains,Gratings,F 10 0.00% 0.00% 21Feb17 4Mar17 13Mar17 23Mar17 17 4 OnTarget
GroundFloor 94 0.00% 0.00% 27Nov16 18Apr17 27Nov16A 2May17 11 27 OnTarget
General 39 0.00% 0.00% 27Nov16 3Jan17 27Nov16A 17Jan17 11 117 OnTarget
MEPWorks 18 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BAGFMEP1000 BA GroundFloor MEPClearanceforPlaster 18 94.44% 66.00% 11Dec16 31Dec16 07Dec16A 9Jan17 7 10 Delayed
BAGFMEP1010 BA GroundFloor InstallWallConduits 18 94.44% 60.00% 11Dec16 31Dec16 26Nov16A 9Jan17 7 10 Delayed
DryArea 70 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 57 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BAGFMEPD1000 BA GroundFloor DryareaMEPClearanceforScreed 18 55.56% 0.00% 19Dec16 8Jan17 31Dec16 21Jan17 11 16 Delayed
BAGFMEPD1010 BA GroundFloor DryAreaHLClearancebyARMAforgridfixing 24 20.83% 0.00% 25Dec16 21Jan17 3Jan17 30Jan17 8 2 Delayed
BAGFMEPD1020 BA GroundFloor DryAreaMEPclearanceforBoardclosing 24 0.00% 0.00% 12Jan17 8Feb17 22Jan17 18Feb17 8 2 OnTarget
BAGFMEPD1030 BA GroundFloor InstallElectricalWiring 15 100.00% 48.00% 5Dec16 21Dec16 27Nov16A 10Jan17 17 6 Delayed
BAGFMEPD1040 BA GroundFloor InstallLowCurrentWiring 14 100.00% 10.00% 13Dec16 28Dec16 27Nov16A 17Jan17 17 116 Delayed
BAGFMEPD1050 BA GroundFloor InstallHVACPipes 14 100.00% 30.00% 13Dec16 28Dec16 27Nov16A 10Jan17 11 12 Delayed
BAGFMEPD1060 BA GroundFloor InstallDuctsandHangers 14 85.71% 96.00% 17Dec16 1Jan17 27Nov16A 14Jan17 11 12 OnTarget
BAGFMEPD1070 BA GroundFloor InstallDroppers 12 33.33% 0.00% 26Dec16 8Jan17 7Jan17 21Jan17 11 22 Delayed
BAGFMEPD1080 BA GroundFloor MeggeringTest 7 0.00% 0.00% 1Jan17 8Jan17 12Jan17 21Jan17 11 22 OnTarget
WetArea 64 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 59 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BAGFMEPW1000 BA GroundFloor WetAreaHLClearancebyARMAforgridfixing 24 100.00% 20.00% 27Nov16 24Dec16 31Dec16A 22Jan17 24 5 Delayed
BAGFMEPW1010 BA GroundFloor WetAreaMEPclearanceforBoardclosing 24 0.00% 0.00% 7Jan17 2Feb17 4Feb17 4Mar17 24 5 OnTarget
BAGFMEPW1020 BA GroundFloor InstallElectricalWiring 12 100.00% 48.00% 12Dec16 25Dec16 27Nov16A 14Jan17 17 6 Delayed
BAGFMEPW1030 BA GroundFloor InstallHot&ColdWaterPiping 12 33.33% 34.00% 26Dec16 8Jan17 27Nov16A 8Jan17 0 38 OnTarget
BAGFMEPW1040 BA GroundFloor InstallHVACPipes 12 8.33% 30.00% 29Dec16 11Jan17 27Nov16A 11Jan17 0 38 OnTarget
BAGFMEPW1050 BA GroundFloor InstallDroppers 12 8.33% 0.00% 29Dec16 11Jan17 31Dec16 12Jan17 1 37 Delayed
BAGFMEPW1060 BA GroundFloor MeggeringTest 10 0.00% 0.00% 1Jan17 11Jan17 2Jan17 12Jan17 1 37 OnTarget
Corridor 56 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 43 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BAGFMEPCL1000 BA GroundFloor CorridorMEPClearanceforScreed 10 0.00% 0.00% 14Jan17 24Jan17 23Jan17 4Feb17 9 16 OnTarget
BAGFMEPCL1010 BA GroundFloor CorridorHLClearancebyARMAforgridfixing 14 0.00% 0.00% 1Jan17 16Jan17 21Jan17 5Feb17 17 6 OnTarget
BAGFMEPCL1020 BA GroundFloor CorridorMEPclearanceforBoardclosing 14 0.00% 0.00% 18Jan17 2Feb17 7Feb17 22Feb17 17 6 OnTarget
BAGFMEPCL1030 BA GroundFloor InstallElectricalWiring 12 100.00% 48.00% 15Dec16 28Dec16 27Nov16A 17Jan17 17 6 Delayed
BAGFMEPCL1050 BA GroundFloor InstallHot&ColdWaterPiping 12 83.33% 34.00% 19Dec16 1Jan17 27Nov16A 21Jan17 17 6 Delayed
BAGFMEPCL1060 BA GroundFloor InstallHVACPipes 12 58.33% 30.00% 22Dec16 4Jan17 27Nov16A 24Jan17 17 6 Delayed
BAGFMEPCL1070 BA GroundFloor InstallDuctsandHangers 14 42.86% 96.00% 24Dec16 8Jan17 27Nov16A 28Jan17 17 6 OnTarget
BAGFMEPCL1080 BA GroundFloor InstallCableTraysandTrunking 14 21.43% 85.00% 27Dec16 11Jan17 27Nov16A 31Jan17 17 6 OnTarget
BAGFMEPCL1085 BA GroundFloor InstallLowCurrentWiring 10 0.00% 10.00% 4Jan17 15Jan17 27Nov16A 4Feb17 17 6 OnTarget
BAGFMEPCL1090 BA GroundFloor InstallLVCables 10 0.00% 0.00% 4Jan17 15Jan17 24Jan17 4Feb17 17 5 OnTarget
BAGFMEPCL1100 BA GroundFloor InstallDroppers 14 0.00% 0.00% 15Jan17 30Jan17 4Feb17 19Feb17 17 6 OnTarget
BAGFMEPCL1110 BA GroundFloor MeggeringTest 14 0.00% 0.00% 18Jan17 2Feb17 7Feb17 22Feb17 17 6 OnTarget
CommonFinalFinishes 69 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 23 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BAGFMEPF1010 BA GroundFloor InstallLightFittings 12 0.00% 0.00% 18Feb17 2Mar17 4Mar17 16Mar17 12 6 OnTarget
BAGFMEPF1020 BA GroundFloor InstallFireCabinets 14 0.00% 0.00% 19Feb17 6Mar17 1Mar17 16Mar17 9 6 OnTarget
BAGFMEPF1030 BA GroundFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 21Feb17 8Mar17 4Mar17 19Mar17 9 6 OnTarget
BAGFMEPF1040 BA GroundFloor InstallSprinklers 14 0.00% 0.00% 23Feb17 11Mar17 6Mar17 21Mar17 9 6 OnTarget
BAGFMEPF1050 BA GroundFloor InstallSwitchesandSockets 12 0.00% 0.00% 26Feb17 11Mar17 8Mar17 21Mar17 9 6 OnTarget
BAGFMEPF1060 BA GroundFloor InstallLowCurrentEquipments 12 0.00% 0.00% 28Feb17 13Mar17 11Mar17 23Mar17 9 6 OnTarget
BAGFMEPF1070 BA GroundFloor InstallGrillesandDiffussers 14 0.00% 0.00% 28Feb17 15Mar17 11Mar17 26Mar17 9 6 OnTarget
BAGFMEPF1075 BA GroundFloor MEPFinalFixes 12 0.00% 0.00% 19Feb17 4Mar17 5Mar17 18Mar17 12 5 OnTarget
BAGFMEPF1080 BA GroundFloor InstallPlumpingFinalTittings(FloorDrains,Gratings,F 14 0.00% 0.00% 28Feb17 15Mar17 11Mar17 26Mar17 9 6 OnTarget
FirstFloor 94 0.00% 0.00% 27Nov16 18Mar17 27Nov16A 20Apr17 29 36 OnTarget
DryArea 33 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 16 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA1FMEPD1010 BA 1stFloor DBInstallation 10 100.00% 65.00% 27Nov16 7Dec16 27Nov16A 3Jan17 23 40 Delayed
BA1FMEPD1020 BA 1stFloor InstallDroppers 10 100.00% 80.00% 4Dec16 14Dec16 27Nov16A 10Jan17 23 40 Delayed
BA1FMEPD1030 BA 1stFloor MeggeringTest 7 100.00% 90.00% 7Dec16 14Dec16 27Nov16A 10Jan17 23 40 Delayed
BA1FMEPD1035 BA 1stFloor DryAreaMEPclearanceforBoardclosing 10 100.00% 0.00% 4Dec16 14Dec16 31Dec16 10Jan17 23 39 Delayed
WetArea 27 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 18 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA1FMEPW1010 BA 1stFloor InstallDroppers 12 83.33% 10.00% 19Dec16 1Jan17 27Nov16A 11Jan17 9 41 Delayed
BA1FMEPW1020 BA 1stFloor MeggeringTest 10 80.00% 95.00% 21Dec16 1Jan17 27Nov16A 11Jan17 9 41 OnTarget
BA1FMEPW1025 BA 1stFloor WetAreaMEPclearanceforBoardclosing 14 42.86% 0.00% 24Dec16 8Jan17 31Dec16 15Jan17 6 38 Delayed
Corridor 40 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 30 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA1FMEPCL1000 BA 1stFloor CorridorHLClearancebyARMAforgridfixing 12 33.33% 35.00% 26Dec16 8Jan17 02Dec16A 8Jan17 0 24 OnTarget
BA1FMEPCL1020 BA 1stFloor InstallDroppers 10 0.00% 0.00% 9Jan17 19Jan17 8Jan17 19Jan17 0 24 OnTarget
BA1FMEPCL1030 BA 1stFloor MeggeringTest 5 0.00% 0.00% 17Jan17 22Jan17 16Jan17 22Jan17 0 24 OnTarget
BA1FMEPCL1035 BA 1stFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 18Jan17 29Jan17 17Jan17 29Jan17 0 24 OnTarget
CommonFinalFinishes 45 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA1FMEPF1010 BA 1stFloor InstallLightFittings 14 0.00% 0.00% 30Jan17 14Feb17 29Jan17 14Feb17 0 25 OnTarget
BA1FMEPF1020 BA 1stFloor InstallFireCabinets 14 0.00% 0.00% 31Jan17 15Feb17 30Jan17 15Feb17 0 25 OnTarget
BA1FMEPF1030 BA 1stFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 31Jan17 15Feb17 30Jan17 15Feb17 0 25 OnTarget
BA1FMEPF1040 BA 1stFloor InstallSprinklers 14 0.00% 0.00% 1Feb17 16Feb17 31Jan17 16Feb17 0 25 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BA1FMEPF1050 BA 1stFloor InstallSwitchesandSockets 14 0.00% 0.00% 1Feb17 16Feb17 31Jan17 16Feb17 0 25 OnTarget
BA1FMEPF1060 BA 1stFloor InstallLowCurrentEquipments 14 0.00% 0.00% 2Feb17 18Feb17 1Feb17 18Feb17 0 25 OnTarget
BA1FMEPF1070 BA 1stFloor InstallGrillesandDiffussers 14 0.00% 0.00% 2Feb17 18Feb17 1Feb17 18Feb17 0 25 OnTarget
BA1FMEPF1075 BA 1stFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 1Feb17 12Feb17 31Jan17 12Feb17 0 24 OnTarget
BA1FMEPF1080 BA 1stFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 2Feb17 18Feb17 1Feb17 18Feb17 0 25 OnTarget
SecondFloor 95 0.00% 0.00% 10Dec16 11Mar17 27Nov16A 20Mar17 8 63 OnTarget
DryArea 39 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 20 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA2FMEPD1010 BA 2ndFloor DBInstallation 10 100.00% 20.00% 8Dec16 19Dec16 27Nov16A 8Jan17 17 8 Delayed
BA2FMEPD1020 BA 2ndFloor InstallDroppers 12 100.00% 0.00% 13Dec16 26Dec16 2Jan17 15Jan17 17 8 Delayed
BA2FMEPD1030 BA 2ndFloor MeggeringTest 10 90.00% 0.00% 20Dec16 31Dec16 9Jan17 19Jan17 17 8 Delayed
BA2FMEPD1035 BA 2ndFloor DryAreaMEPclearanceforBoardclosing 10 90.00% 0.00% 20Dec16 31Dec16 9Jan17 19Jan17 17 8 Delayed
WetArea 31 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 18 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA2FMEPW1010 BA 2ndFloor InstallDroppers 12 100.00% 0.00% 10Dec16 22Dec16 31Dec16 12Jan17 18 20 Delayed
BA2FMEPW1020 BA 2ndFloor MeggeringTest 10 100.00% 100.00% 12Dec16 22Dec16 11Dec16A 25Dec16A 1 0 OnTarget
BA2FMEPW1025 BA 2ndFloor WetAreaMEPclearanceforBoardclosing 10 100.00% 0.00% 19Dec16 29Dec16 31Dec16 10Jan17 10 36 Delayed
Corridor 44 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 25 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA2FMEPCL1000 BA 2ndFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 1Jan17 11Jan17 21Jan17 31Jan17 17 8 OnTarget
BA2FMEPCL1020 BA 2ndFloor InstallDroppers 12 50.00% 0.00% 24Dec16 5Jan17 14Jan17 26Jan17 18 20 Delayed
BA2FMEPCL1030 BA 2ndFloor MeggeringTest 10 40.00% 50.00% 26Dec16 5Jan17 01Dec16A 26Jan17 18 20 OnTarget
BA2FMEPCL1035 BA 2ndFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 10Jan17 21Jan17 30Jan17 9Feb17 17 8 OnTarget
CommonFinalFinishes 34 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 26 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA2FMEPF1010 BA 2ndFloor InstallLightFittings 14 0.00% 0.00% 19Jan17 4Feb17 8Feb17 23Feb17 17 8 OnTarget
BA2FMEPF1020 BA 2ndFloor InstallFireCabinets 14 0.00% 0.00% 23Jan17 7Feb17 12Feb17 27Feb17 17 8 OnTarget
BA2FMEPF1030 BA 2ndFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 25Jan17 9Feb17 14Feb17 1Mar17 17 8 OnTarget
BA2FMEPF1040 BA 2ndFloor InstallSprinklers 14 0.00% 0.00% 26Jan17 11Feb17 15Feb17 2Mar17 17 8 OnTarget
BA2FMEPF1050 BA 2ndFloor InstallSwitchesandSockets 14 0.00% 0.00% 30Jan17 14Feb17 19Feb17 6Mar17 17 8 OnTarget
BA2FMEPF1060 BA 2ndFloor InstallLowCurrentEquipments 14 0.00% 0.00% 2Feb17 18Feb17 22Feb17 9Mar17 17 8 OnTarget
BA2FMEPF1070 BA 2ndFloor InstallGrillesandDiffussers 14 0.00% 0.00% 2Feb17 18Feb17 22Feb17 9Mar17 17 8 OnTarget
BA2FMEPF1075 BA 2ndFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 24Jan17 4Feb17 13Feb17 23Feb17 17 14 OnTarget
BA2FMEPF1080 BA 2ndFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 2Feb17 18Feb17 22Feb17 9Mar17 17 8 OnTarget
ThirdFloor 86 0.00% 0.00% 27Nov16 2Feb17 26Nov16A 5Feb17 2 100 OnTarget
DryArea 50 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 39 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA3FMEPD1000 BA 3rdFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 100.00% 95.00% 12Dec16 22Dec16 27Nov16A 7Jan17 13 9 Delayed
BA3FMEPD1020 BA 3rdFloor InstallLowCurrentWiring 10 90.00% 94.00% 20Dec16 31Dec16 27Nov16A 31Dec16 0 5 OnTarget
BA3FMEPD1030 BA 3rdFloor DBInstallation 10 0.00% 20.00% 1Jan17 11Jan17 27Nov16A 8Jan17 3 10 OnTarget
BA3FMEPD1040 BA 3rdFloor InstallDroppers 12 0.00% 0.00% 12Jan17 25Jan17 9Jan17 22Jan17 3 26 OnTarget
BA3FMEPD1050 BA 3rdFloor MeggeringTest 10 0.00% 0.00% 15Jan17 25Jan17 11Jan17 22Jan17 3 29 OnTarget
BA3FMEPD1055 BA 3rdFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 15Jan17 25Jan17 11Jan17 22Jan17 3 29 OnTarget
WetArea 45 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 39 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA3FMEPW1000 BA 3rdFloor WetAreaHLClearancebyARMAforgridfixing 10 100.00% 95.00% 19Dec16 29Dec16 27Nov16A 14Jan17 13 23 Delayed
BA3FMEPW1020 BA 3rdFloor InstallDroppers 12 0.00% 0.00% 19Jan17 1Feb17 16Jan17 29Jan17 3 26 OnTarget
BA3FMEPW1030 BA 3rdFloor MeggeringTest 10 0.00% 0.00% 22Jan17 1Feb17 18Jan17 29Jan17 3 26 OnTarget
BA3FMEPW1035 BA 3rdFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 22Jan17 1Feb17 21Jan17 1Feb17 0 23 OnTarget
Corridor 43 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 24 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA3FMEPCL1000 BA 3rdFloor CorridorScreedMEpClearance 12 0.00% 100.00% 1Jan17 14Jan17 07Dec16A 07Dec16A 33 0 OnTarget
BA3FMEPCL1010 BA 3rdFloor CorridorHLClearancebyARMAforgridfixing 10 30.00% 0.00% 27Dec16 7Jan17 5Jan17 17Jan17 9 26 Delayed
BA3FMEPCL1030 BA 3rdFloor InstallElectricalWiring 10 90.00% 100.00% 20Dec16 31Dec16 27Nov16A 01Dec16A 26 0 OnTarget
BA3FMEPCL1050 BA 3rdFloor InstallCableTraysandTrunking 10 60.00% 80.00% 24Dec16 3Jan17 27Nov16A 1Jan17 2 37 OnTarget
BA3FMEPCL1055 BA 3rdFloor InstallLowCurrentWiring 10 30.00% 94.00% 27Dec16 7Jan17 27Nov16A 4Jan17 2 37 OnTarget
BA3FMEPCL1060 BA 3rdFloor InstallLVCables 10 30.00% 0.00% 27Dec16 7Jan17 31Dec16 10Jan17 3 32 Delayed
BA3FMEPCL1070 BA 3rdFloor InstallDroppers 10 0.00% 0.00% 3Jan17 14Jan17 7Jan17 17Jan17 3 34 OnTarget
BA3FMEPCL1080 BA 3rdFloor MeggeringTest 12 0.00% 0.00% 1Jan17 14Jan17 4Jan17 17Jan17 3 34 OnTarget
BA3FMEPCL1085 BA 3rdFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 5Jan17 16Jan17 15Jan17 26Jan17 9 26 OnTarget
CommonFinalFinishes 25 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 22 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA3FMEPF1010 BA 3rdFloor InstallLightFittings 14 0.00% 0.00% 31Jan17 15Feb17 30Jan17 15Feb17 0 24 OnTarget
BA3FMEPF1020 BA 3rdFloor InstallFireCabinets 14 0.00% 0.00% 1Feb17 16Feb17 31Jan17 16Feb17 0 24 OnTarget
BA3FMEPF1030 BA 3rdFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 1Feb17 16Feb17 31Jan17 16Feb17 0 24 OnTarget
BA3FMEPF1040 BA 3rdFloor InstallSprinklers 14 0.00% 0.00% 2Feb17 18Feb17 1Feb17 18Feb17 0 24 OnTarget
BA3FMEPF1050 BA 3rdFloor InstallSwitchesandSockets 14 0.00% 0.00% 2Feb17 18Feb17 1Feb17 18Feb17 0 24 OnTarget
BA3FMEPF1060 BA 3rdFloor InstallLowCurrentEquipments 14 0.00% 0.00% 4Feb17 19Feb17 2Feb17 19Feb17 0 24 OnTarget
BA3FMEPF1070 BA 3rdFloor InstallGrillesandDiffussers 14 0.00% 0.00% 4Feb17 19Feb17 2Feb17 19Feb17 0 24 OnTarget
BA3FMEPF1075 BA 3rdFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 13Feb17 25Feb17 1Feb17 13Feb17 10 23 OnTarget
BA3FMEPF1080 BA 3rdFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 4Feb17 19Feb17 2Feb17 19Feb17 0 24 OnTarget
ForthFloor 83 0.00% 0.00% 29Nov16 28Mar17 26Nov16A 9Apr17 10 46 OnTarget
DryArea 40 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 23 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA4FMEPD1000 BA 4thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 100.00% 50.00% 15Dec16 26Dec16 27Nov16A 10Jan17 13 9 Delayed
BA4FMEPD1020 BA 4thFloor InstallHVACPipes 10 90.00% 90.00% 20Dec16 31Dec16 27Nov16A 31Dec16 0 5 OnTarget
BA4FMEPD1030 BA 4thFloor InstallDuctsandHangers 12 66.67% 67.00% 21Dec16 3Jan17 27Nov16A 3Jan17 0 11 OnTarget
BA4FMEPD1040 BA 4thFloor DBInstallation 10 30.00% 20.00% 27Dec16 7Jan17 27Nov16A 8Jan17 1 10 Delayed
BA4FMEPD1050 BA 4thFloor InstallDroppers 12 33.33% 0.00% 26Dec16 8Jan17 9Jan17 23Jan17 13 33 Delayed
BA4FMEPD1060 BA 4thFloor MeggeringTest 10 0.00% 0.00% 31Dec16 10Jan17 14Jan17 25Jan17 13 33 OnTarget
BA4FMEPD1070 BA 4thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 31Dec16 10Jan17 14Jan17 25Jan17 13 33 OnTarget
WetArea 51 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 45 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA4FMEPW1000 BA 4thFloor WetAreaScreedMEpClearance 12 100.00% 100.00% 17Dec16 29Dec16 08Dec16A 20Dec16A 9 0 OnTarget
BA4FMEPW1010 BA 4thFloor WetAreaHLClearancebyARMAforgridfixing 10 60.00% 50.00% 24Dec16 3Jan17 27Nov16A 4Jan17 1 32 Delayed
BA4FMEPW1030 BA 4thFloor InstallHVACPipes 10 60.00% 74.00% 24Dec16 3Jan17 27Nov16A 3Jan17 0 15 OnTarget
BA4FMEPW1040 BA 4thFloor InstallDuctsandHangers 10 30.00% 63.00% 27Dec16 7Jan17 27Nov16A 7Jan17 0 40 OnTarget
BA4FMEPW1050 BA 4thFloor InstallDroppers 12 16.67% 0.00% 28Dec16 10Jan17 31Dec16 12Jan17 2 38 Delayed
BA4FMEPW1060 BA 4thFloor MeggeringTest 7 0.00% 0.00% 5Jan17 12Jan17 8Jan17 15Jan17 2 38 OnTarget
BA4FMEPW1065 BA 4thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 26Jan17 6Feb17 16Jan17 26Jan17 9 28 OnTarget
Corridor 53 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 41 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA4FMEPCL1000 BA 4thFloor CorridorScreedMEPClearance 10 0.00% 0.00% 14Jan17 24Jan17 14Jan17 24Jan17 0 31 OnTarget
BA4FMEPCL1010 BA 4thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 19Jan17 30Jan17 19Jan17 30Jan17 0 15 OnTarget
BA4FMEPCL1020 BA 4thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 29Jan17 8Feb17 29Jan17 8Feb17 0 15 OnTarget
BA4FMEPCL1030 BA 4thFloor InstallElectricalWiring 10 60.00% 60.00% 24Dec16 3Jan17 27Nov16A 3Jan17 0 15 OnTarget
BA4FMEPCL1050 BA 4thFloor InstallHVACPipes 10 30.00% 30.00% 27Dec16 7Jan17 27Nov16A 7Jan17 0 15 OnTarget
BA4FMEPCL1060 BA 4thFloor InstallDuctsandHangers 10 0.00% 90.00% 31Dec16 10Jan17 27Nov16A 10Jan17 0 15 OnTarget
BA4FMEPCL1070 BA 4thFloor InstallCableTraysandTrunking 14 7.14% 35.00% 29Dec16 14Jan17 27Nov16A 14Jan17 0 15 OnTarget
BA4FMEPCL1075 BA 4thFloor InstallLowCurrentWiring 12 0.00% 69.00% 4Jan17 17Jan17 27Nov16A 17Jan17 0 15 OnTarget
BA4FMEPCL1080 BA 4thFloor InstallLVCables 10 0.00% 0.00% 7Jan17 17Jan17 7Jan17 17Jan17 0 26 OnTarget
BA4FMEPCL1090 BA 4thFloor InstallDroppers 10 0.00% 0.00% 14Jan17 24Jan17 14Jan17 24Jan17 0 28 OnTarget
BA4FMEPCL1100 BA 4thFloor MeggeringTest 10 0.00% 0.00% 14Jan17 24Jan17 14Jan17 24Jan17 0 28 OnTarget
CommonFinalFinishes 32 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA4FMEPF1000 BA 4thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 9Feb17 22Feb17 9Feb17 22Feb17 0 15 OnTarget
BA4FMEPF1010 BA 4thFloor InstallLightFittings 10 0.00% 0.00% 11Feb17 21Feb17 11Feb17 21Feb17 0 23 OnTarget
BA4FMEPF1020 BA 4thFloor InstallFireCabinets 14 0.00% 0.00% 7Feb17 22Feb17 7Feb17 22Feb17 0 23 OnTarget
BA4FMEPF1030 BA 4thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 7Feb17 22Feb17 7Feb17 22Feb17 0 23 OnTarget
BA4FMEPF1040 BA 4thFloor InstallSprinklers 14 0.00% 0.00% 8Feb17 23Feb17 8Feb17 23Feb17 0 23 OnTarget
BA4FMEPF1050 BA 4thFloor InstallSwitchesandSockets 10 0.00% 0.00% 8Feb17 19Feb17 8Feb17 19Feb17 0 23 OnTarget
BA4FMEPF1060 BA 4thFloor InstallLowCurrentEquipments 10 0.00% 0.00% 9Feb17 20Feb17 9Feb17 20Feb17 0 23 OnTarget
BA4FMEPF1070 BA 4thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 5Feb17 20Feb17 5Feb17 20Feb17 0 23 OnTarget
BA4FMEPF1080 BA 4thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 5Feb17 20Feb17 5Feb17 20Feb17 0 23 OnTarget
FifthFloor 79 0.00% 0.00% 8Dec16 2Apr17 26Nov16A 11Apr17 8 44 OnTarget
DryArea 42 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 31 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA5FMEPD1000 BA 5thFloor DryAreaMEPHLClearancebyARMAforgridfixing 12 66.67% 0.00% 21Dec16 3Jan17 3Jan17 17Jan17 12 9 Delayed
BA5FMEPD1020 BA 5thFloor InstallLowCurrentWiring 10 90.00% 69.00% 20Dec16 31Dec16 27Nov16A 3Jan17 2 7 Delayed
BA5FMEPD1030 BA 5thFloor InstallHVACPipes 10 90.00% 78.00% 20Dec16 31Dec16 27Nov16A 2Jan17 1 10 Delayed
BA5FMEPD1040 BA 5thFloor InstallDuctsandHangers 12 66.67% 0.00% 21Dec16 3Jan17 31Dec16 12Jan17 8 3 Delayed
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BA5FMEPD1050 BA 5thFloor DBInstallation 10 30.00% 20.00% 27Dec16 7Jan17 27Nov16A 16Jan17 8 3 Delayed
BA5FMEPD1060 BA 5thFloor InstallDroppers 12 0.00% 0.00% 4Jan17 17Jan17 17Jan17 31Jan17 12 9 OnTarget
BA5FMEPD1070 BA 5thFloor MeggeringTest 10 0.00% 0.00% 14Jan17 24Jan17 26Jan17 7Feb17 12 9 OnTarget
BA5FMEPD1075 BA 5thFloor DryAreaMEPclearanceforBoardclosing 12 0.00% 0.00% 11Jan17 24Jan17 24Jan17 7Feb17 12 9 OnTarget
WetArea 49 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 43 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA5FMEPW1000 BA 5thFloor WetAreaHLClearancebyARMAforgridfixing 18 0.00% 0.00% 4Jan17 24Jan17 31Dec16 19Jan17 4 8 OnTarget
BA5FMEPW1020 BA 5thFloor InstallDrainagepipes 8 0.00% 100.00% 1Jan17 9Jan17 27Nov16A 17Dec16A 21 0 OnTarget
BA5FMEPW1030 BA 5thFloor InstallHVACPipes 10 0.00% 78.00% 10Jan17 21Jan17 27Nov16A 2Jan17 17 21 OnTarget
BA5FMEPW1040 BA 5thFloor InstallDuctsandHangers 14 0.00% 0.00% 9Jan17 24Jan17 31Dec16 15Jan17 8 12 OnTarget
BA5FMEPW1050 BA 5thFloor InstallDroppers 12 0.00% 0.00% 15Jan17 28Jan17 5Jan17 18Jan17 8 30 OnTarget
BA5FMEPW1060 BA 5thFloor MeggeringTest 10 0.00% 0.00% 17Jan17 28Jan17 8Jan17 18Jan17 8 30 OnTarget
BA5FMEPW1065 BA 5thFloor WetAreaMEPclearanceforBoardclosing 18 0.00% 0.00% 30Jan17 19Feb17 17Jan17 6Feb17 11 14 OnTarget
Corridor 61 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 42 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA5FMEPCL1000 BA 5thFloor CorridorScreedMEpClearance 12 0.00% 0.00% 18Jan17 31Jan17 18Jan17 31Jan17 0 31 OnTarget
BA5FMEPCL1010 BA 5thFloor CorridorHLClearancebyARMAforgridfixing 21 0.00% 0.00% 4Jan17 28Jan17 3Jan17 26Jan17 1 5 OnTarget
BA5FMEPCL1020 BA 5thFloor CorridorMEPclearanceforBoardclosing 18 0.00% 0.00% 26Jan17 15Feb17 25Jan17 14Feb17 1 5 OnTarget
BA5FMEPCL1040 BA 5thFloor InstallHot&ColdWaterPiping 10 10.00% 50.00% 29Dec16 9Jan17 27Nov16A 4Jan17 4 9 OnTarget
BA5FMEPCL1050 BA 5thFloor InstallHVACPipes 12 0.00% 0.00% 31Dec16 12Jan17 31Dec16 12Jan17 0 5 OnTarget
BA5FMEPCL1060 BA 5thFloor InstallDuctsandHangers 12 0.00% 90.00% 3Jan17 16Jan17 27Nov16A 16Jan17 0 5 OnTarget
BA5FMEPCL1070 BA 5thFloor InstallCableTraysandTrunking 12 0.00% 0.00% 7Jan17 19Jan17 7Jan17 19Jan17 0 5 OnTarget
BA5FMEPCL1075 BA 5thFloor InstallLowCurrentWiring 12 0.00% 69.00% 10Jan17 23Jan17 27Nov16A 23Jan17 0 5 OnTarget
BA5FMEPCL1080 BA 5thFloor InstallLVCables 12 0.00% 0.00% 10Jan17 23Jan17 10Jan17 23Jan17 0 8 OnTarget
BA5FMEPCL1090 BA 5thFloor InstallDroppers 10 0.00% 0.00% 29Jan17 8Feb17 28Jan17 7Feb17 1 11 OnTarget
BA5FMEPCL1100 BA 5thFloor MeggeringTest 12 0.00% 0.00% 26Jan17 8Feb17 25Jan17 7Feb17 1 11 OnTarget
CommonFinalFinishes 34 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 25 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA5FMEPF1010 BA 5thFloor InstallLightFittings 14 0.00% 0.00% 15Feb17 2Mar17 13Feb17 28Feb17 2 5 OnTarget
BA5FMEPF1020 BA 5thFloor InstallFireCabinets 14 0.00% 0.00% 19Feb17 6Mar17 16Feb17 4Mar17 2 5 OnTarget
BA5FMEPF1030 BA 5thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 22Feb17 9Mar17 20Feb17 7Mar17 2 5 OnTarget
BA5FMEPF1040 BA 5thFloor InstallSprinklers 14 0.00% 0.00% 23Feb17 11Mar17 21Feb17 8Mar17 2 5 OnTarget
BA5FMEPF1050 BA 5thFloor InstallSwitchesandSockets 14 0.00% 0.00% 27Feb17 14Mar17 25Feb17 12Mar17 2 5 OnTarget
BA5FMEPF1060 BA 5thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 28Feb17 15Mar17 26Feb17 13Mar17 2 5 OnTarget
BA5FMEPF1070 BA 5thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 28Feb17 15Mar17 26Feb17 13Mar17 2 5 OnTarget
BA5FMEPF1075 BA 5thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 18Feb17 2Mar17 15Feb17 28Feb17 2 10 OnTarget
BA5FMEPF1080 BA 5thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 28Feb17 15Mar17 26Feb17 13Mar17 2 5 OnTarget
SixthFloor 76 0.00% 0.00% 15Dec16 2Apr17 26Nov16A 11Apr17 8 44 OnTarget
DryArea 44 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 25 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA6FMEPD1000 BA 6thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 30.00% 30.00% 27Dec16 7Jan17 25Dec16A 21Jan17 12 13 OnTarget
BA6FMEPD1020 BA 6thFloor InstallLowCurrentWiring 10 60.00% 70.00% 24Dec16 3Jan17 27Nov16A 7Jan17 2 7 OnTarget
BA6FMEPD1030 BA 6thFloor InstallHVACPipes 10 60.00% 48.00% 24Dec16 3Jan17 27Nov16A 5Jan17 1 7 Delayed
BA6FMEPD1040 BA 6thFloor InstallDuctsandHangers 12 41.67% 0.00% 25Dec16 7Jan17 31Dec16 12Jan17 5 3 Delayed
BA6FMEPD1050 BA 6thFloor DBInstallation 10 0.00% 20.00% 31Dec16 10Jan17 27Nov16A 16Jan17 5 3 OnTarget
BA6FMEPD1060 BA 6thFloor InstallDroppers 12 0.00% 0.00% 8Jan17 21Jan17 21Jan17 4Feb17 12 13 OnTarget
BA6FMEPD1070 BA 6thFloor MeggeringTest 10 0.00% 0.00% 10Jan17 21Jan17 23Jan17 4Feb17 12 13 OnTarget
BA6FMEPD1080 BA 6thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 10Jan17 21Jan17 23Jan17 4Feb17 12 13 OnTarget
WetArea 54 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 48 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA6FMEPW1000 BA 6thFloor WetAreaScreedMEpClearance 3 0.00% 100.00% 4Jan17 7Jan17 26Nov16A 19Dec16A 17 0 OnTarget
BA6FMEPW1010 BA 6thFloor WetAreaHLClearancebyARMAforgridfixing 12 0.00% 0.00% 10Jan17 23Jan17 31Dec16 14Jan17 9 15 OnTarget
BA6FMEPW1020 BA 6thFloor WetAreaMEPclearanceforBoardclosing 18 0.00% 0.00% 28Jan17 16Feb17 17Jan17 7Feb17 9 15 OnTarget
BA6FMEPW1030 BA 6thFloor InstallDrainagepipes 10 60.00% 98.00% 24Dec16 3Jan17 27Nov16A 5Jan17 1 12 OnTarget
BA6FMEPW1040 BA 6thFloor InstallHot&ColdWaterPiping 10 50.00% 90.00% 25Dec16 4Jan17 27Nov16A 7Jan17 1 12 OnTarget
BA6FMEPW1050 BA 6thFloor InstallHVACPipes 10 20.00% 48.00% 28Dec16 8Jan17 27Nov16A 10Jan17 1 15 OnTarget
BA6FMEPW1060 BA 6thFloor InstallDuctsandHangers 16 31.25% 65.00% 25Dec16 11Jan17 27Nov16A 14Jan17 1 15 OnTarget
BA6FMEPW1070 BA 6thFloor InstallDroppers 12 0.00% 0.00% 28Jan17 9Feb17 17Jan17 31Jan17 9 21 OnTarget
BA6FMEPW1080 BA 6thFloor MeggeringTest 10 0.00% 0.00% 30Jan17 9Feb17 19Jan17 31Jan17 9 21 OnTarget
Corridor 54 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 35 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA6FMEPCL1040 BA 6thFloor InstallHot&ColdWaterPiping 8 0.00% 50.00% 31Dec16 8Jan17 27Nov16A 10Jan17 1 12 OnTarget
BA6FMEPCL1050 BA 6thFloor InstallHVACPipes 12 8.33% 0.00% 29Dec16 11Jan17 31Dec16 14Jan17 1 12 Delayed
BA6FMEPCL1060 BA 6thFloor InstallDuctsandHangers 12 0.00% 85.00% 2Jan17 15Jan17 27Nov16A 17Jan17 1 12 OnTarget
BA6FMEPCL1070 BA 6thFloor InstallCableTraysandTrunking 12 0.00% 0.00% 5Jan17 18Jan17 7Jan17 21Jan17 1 12 OnTarget
BA6FMEPCL1075 BA 6thFloor InstallLowCurrentWiring 7 0.00% 70.00% 15Jan17 22Jan17 27Nov16A 24Jan17 1 12 OnTarget
BA6FMEPCL1080 BA 6thFloor InstallLVCables 12 0.00% 0.00% 9Jan17 22Jan17 10Jan17 24Jan17 1 15 OnTarget
BA6FMEPCL1085 BA 6thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 16Jan17 26Jan17 16Jan17 28Jan17 0 12 OnTarget
BA6FMEPCL1090 BA 6thFloor InstallDroppers 10 0.00% 0.00% 18Jan17 29Jan17 19Jan17 31Jan17 1 19 OnTarget
BA6FMEPCL1100 BA 6thFloor MeggeringTest 5 0.00% 0.00% 24Jan17 29Jan17 25Jan17 31Jan17 1 19 OnTarget
BA6FMEPCL1110 BA 6thFloor CorridorMEPclearanceforBoardclosing 12 0.00% 0.00% 25Jan17 7Feb17 25Jan17 8Feb17 0 12 OnTarget
CommonFinalFinishes 30 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 22 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA6FMEPF1010 BA 6thFloor InstallLightFittings 14 0.00% 0.00% 15Feb17 2Mar17 8Feb17 25Feb17 6 12 OnTarget
BA6FMEPF1020 BA 6thFloor InstallFireCabinets 14 0.00% 0.00% 19Feb17 6Mar17 12Feb17 28Feb17 6 12 OnTarget
BA6FMEPF1030 BA 6thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 20Feb17 7Mar17 13Feb17 1Mar17 6 12 OnTarget
BA6FMEPF1040 BA 6thFloor InstallSprinklers 14 0.00% 0.00% 21Feb17 8Mar17 14Feb17 2Mar17 6 12 OnTarget
BA6FMEPF1050 BA 6thFloor InstallSwitchesandSockets 14 0.00% 0.00% 22Feb17 9Mar17 15Feb17 4Mar17 6 12 OnTarget
BA6FMEPF1060 BA 6thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 23Feb17 11Mar17 16Feb17 5Mar17 6 12 OnTarget
BA6FMEPF1070 BA 6thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 25Feb17 12Mar17 18Feb17 6Mar17 6 12 OnTarget
BA6FMEPF1075 BA 6thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 15Feb17 1Mar17 8Feb17 22Feb17 6 16 OnTarget
BA6FMEPF1080 BA 6thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 25Feb17 12Mar17 18Feb17 6Mar17 6 12 OnTarget
SeventhFloor 99 0.00% 0.00% 27Nov16 8Feb17 26Nov16A 2Mar17 18 79 OnTarget
DryArea 44 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 31 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA7FMEPD1000 BA 7thFloor DryAreaMEPHLClearancebyARMAforgridfixing 12 16.67% 20.00% 28Dec16 10Jan17 21Dec16A 24Jan17 12 25 OnTarget
BA7FMEPD1010 BA 7thFloor DryAreaMEPclearanceforBoardclosing 12 0.00% 0.00% 14Jan17 26Jan17 24Jan17 7Feb17 10 25 OnTarget
BA7FMEPD1020 BA 7thFloor InstallLowCurrentWiring 10 60.00% 70.00% 24Dec16 3Jan17 27Nov16A 7Jan17 2 7 OnTarget
BA7FMEPD1030 BA 7thFloor InstallHVACPipes 10 60.00% 48.00% 24Dec16 3Jan17 27Nov16A 5Jan17 1 6 Delayed
BA7FMEPD1040 BA 7thFloor InstallDuctsandHangers 14 50.00% 0.00% 22Dec16 7Jan17 31Dec16 15Jan17 7 118 Delayed
BA7FMEPD1050 BA 7thFloor DBInstallation 10 0.00% 20.00% 8Jan17 18Jan17 27Nov16A 8Jan17 9 10 OnTarget
BA7FMEPD1060 BA 7thFloor InstallDroppers 12 0.00% 0.00% 11Jan17 24Jan17 24Jan17 7Feb17 12 25 OnTarget
BA7FMEPD1070 BA 7thFloor MeggeringTest 7 0.00% 0.00% 19Jan17 26Jan17 30Jan17 7Feb17 10 25 OnTarget
WetArea 79 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 50 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA7FMEPW1000 BA 7thFloor WetAreaScreedMEpClearance 12 0.00% 0.00% 5Jan17 18Jan17 9Jan17 22Jan17 3 4 OnTarget
BA7FMEPW1010 BA 7thFloor WetAreaHLClearancebyARMAforgridfixing 12 0.00% 0.00% 16Jan17 29Jan17 19Jan17 1Feb17 3 4 OnTarget
BA7FMEPW1020 BA 7thFloor WetAreaMEPclearanceforBoardclosing 12 0.00% 0.00% 6Feb17 19Feb17 9Feb17 22Feb17 3 5 OnTarget
BA7FMEPW1030 BA 7thFloor InstallDrainagepipes 10 60.00% 96.00% 24Dec16 3Jan17 27Nov16A 5Jan17 1 6 OnTarget
BA7FMEPW1040 BA 7thFloor InstallHot&ColdWaterPiping 10 50.00% 90.00% 25Dec16 4Jan17 27Nov16A 7Jan17 1 6 OnTarget
BA7FMEPW1050 BA 7thFloor InstallHVACPipes 12 33.33% 48.00% 26Dec16 8Jan17 27Nov16A 10Jan17 1 6 OnTarget
BA7FMEPW1060 BA 7thFloor InstallDuctsandHangers 14 21.43% 0.00% 27Dec16 11Jan17 31Dec16 15Jan17 3 4 Delayed
BA7FMEPW1070 BA 7thFloor InstallDroppers 12 0.00% 0.00% 1Feb17 14Feb17 5Feb17 18Feb17 3 9 OnTarget
BA7FMEPW1080 BA 7thFloor MeggeringTest 7 0.00% 0.00% 7Feb17 14Feb17 11Feb17 18Feb17 3 9 OnTarget
Corridor 64 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 45 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA7FMEPCL1000 BA 7thFloor CorridorScreedMEpClearance 12 0.00% 0.00% 15Jan17 28Jan17 17Jan17 30Jan17 2 32 OnTarget
BA7FMEPCL1010 BA 7thFloor CorridorHLClearancebyARMAforgridfixing 12 0.00% 0.00% 19Jan17 1Feb17 23Jan17 5Feb17 3 8 OnTarget
BA7FMEPCL1020 BA 7thFloor CorridorMEPclearanceforBoardclosing 12 0.00% 0.00% 31Jan17 13Feb17 4Feb17 16Feb17 3 8 OnTarget
BA7FMEPCL1030 BA 7thFloor InstallElectricalWiring 10 60.00% 100.00% 24Dec16 3Jan17 27Nov16A 05Dec16A 26 0 OnTarget
BA7FMEPCL1050 BA 7thFloor InstallHot&ColdWaterPiping 10 30.00% 50.00% 27Dec16 7Jan17 27Nov16A 4Jan17 2 20 OnTarget
BA7FMEPCL1060 BA 7thFloor InstallHVACPipes 12 16.67% 0.00% 28Dec16 10Jan17 31Dec16 12Jan17 2 16 Delayed
BA7FMEPCL1070 BA 7thFloor InstallDuctsandHangers 12 0.00% 75.00% 1Jan17 14Jan17 27Nov16A 16Jan17 2 16 OnTarget
BA7FMEPCL1080 BA 7thFloor InstallCableTraysandTrunking 12 0.00% 0.00% 4Jan17 17Jan17 7Jan17 19Jan17 2 16 OnTarget
BA7FMEPCL1085 BA 7thFloor InstallLowCurrentWiring 7 0.00% 70.00% 14Jan17 21Jan17 27Nov16A 23Jan17 2 16 OnTarget
BA7FMEPCL1090 BA 7thFloor InstallLVCables 12 0.00% 0.00% 8Jan17 21Jan17 10Jan17 23Jan17 2 19 OnTarget
BA7FMEPCL1100 BA 7thFloor InstallDroppers 10 0.00% 0.00% 2Feb17 13Feb17 6Feb17 16Feb17 3 8 OnTarget
BA7FMEPCL1110 BA 7thFloor MeggeringTest 5 0.00% 0.00% 8Feb17 13Feb17 12Feb17 16Feb17 3 8 OnTarget
CommonFinalFinishes 30 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 20 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA7FMEPF1010 BA 7thFloor InstallLightFittings 10 0.00% 0.00% 15Feb17 26Feb17 19Feb17 1Mar17 3 16 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BA7FMEPF1020 BA 7thFloor InstallFireCabinets 14 0.00% 0.00% 12Feb17 27Feb17 15Feb17 2Mar17 3 16 OnTarget
BA7FMEPF1030 BA 7thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 12Feb17 27Feb17 15Feb17 2Mar17 3 16 OnTarget
BA7FMEPF1040 BA 7thFloor InstallSprinklers 14 0.00% 0.00% 13Feb17 28Feb17 16Feb17 4Mar17 3 16 OnTarget
BA7FMEPF1050 BA 7thFloor InstallSwitchesandSockets 10 0.00% 0.00% 13Feb17 23Feb17 16Feb17 27Feb17 3 16 OnTarget
BA7FMEPF1060 BA 7thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 9Feb17 25Feb17 13Feb17 28Feb17 3 16 OnTarget
BA7FMEPF1070 BA 7thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 9Feb17 25Feb17 13Feb17 28Feb17 3 16 OnTarget
BA7FMEPF1075 BA 7thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 19Feb17 4Mar17 22Feb17 7Mar17 3 4 OnTarget
BA7FMEPF1080 BA 7thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 9Feb17 25Feb17 13Feb17 28Feb17 3 16 OnTarget
EightFloor 87 0.00% 0.00% 30Nov16 16Apr17 26Nov16A 25Apr17 8 32 OnTarget
DryArea 44 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 25 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA8FMEPD1000 BA 8thFloor DryAreaMEPHLClearancebyARMAforgridfixing 12 8.33% 8.00% 29Dec16 11Jan17 27Dec16A 12Jan17 0 13 Delayed
BA8FMEPD1010 BA 8thFloor DryAreaMEPclearanceforBoardclosing 12 0.00% 0.00% 12Jan17 25Jan17 12Jan17 26Jan17 0 33 OnTarget
BA8FMEPD1020 BA 8thFloor InstallLowCurrentWiring 10 20.00% 70.00% 28Dec16 8Jan17 27Nov16A 11Jan17 2 7 OnTarget
BA8FMEPD1030 BA 8thFloor InstallHVACPipes 10 20.00% 20.00% 28Dec16 8Jan17 21Dec16A 8Jan17 0 4 OnTarget
BA8FMEPD1040 BA 8thFloor InstallDuctsandHangers 10 0.00% 0.00% 1Jan17 11Jan17 1Jan17 11Jan17 0 4 OnTarget
BA8FMEPD1050 BA 8thFloor DBInstallation 10 0.00% 20.00% 4Jan17 15Jan17 27Nov16A 15Jan17 0 4 OnTarget
BA8FMEPD1060 BA 8thFloor InstallDroppers 12 0.00% 0.00% 12Jan17 25Jan17 12Jan17 26Jan17 0 33 OnTarget
BA8FMEPD1070 BA 8thFloor MeggeringTest 7 0.00% 0.00% 18Jan17 25Jan17 18Jan17 26Jan17 0 33 OnTarget
WetArea 70 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 47 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA8FMEPW1000 BA 8thFloor WetAreaScreedMEpClearance 10 0.00% 0.00% 14Jan17 24Jan17 9Jan17 19Jan17 4 9 OnTarget
BA8FMEPW1010 BA 8thFloor WetAreaHLClearancebyARMAforgridfixing 10 0.00% 0.00% 18Jan17 29Jan17 14Jan17 24Jan17 4 9 OnTarget
BA8FMEPW1020 BA 8thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 12Feb17 22Feb17 7Feb17 18Feb17 4 9 OnTarget
BA8FMEPW1030 BA 8thFloor InstallElectricalWiring 10 0.00% 100.00% 1Jan17 11Jan17 27Nov16A 03Dec16A 35 0 OnTarget
BA8FMEPW1040 BA 8thFloor InstallDrainagepipes 12 0.00% 100.00% 31Dec16 12Jan17 27Nov16A 13Dec16A 27 0 OnTarget
BA8FMEPW1050 BA 8thFloor InstallHot&ColdWaterPiping 8 0.00% 90.00% 5Jan17 14Jan17 27Nov16A 31Dec16 12 17 OnTarget
BA8FMEPW1060 BA 8thFloor InstallHVACPipes 12 0.00% 0.00% 4Jan17 17Jan17 31Dec16 12Jan17 4 9 OnTarget
BA8FMEPW1070 BA 8thFloor InstallDuctsandHangers 12 0.00% 0.00% 8Jan17 21Jan17 3Jan17 16Jan17 4 9 OnTarget
BA8FMEPW1080 BA 8thFloor InstallDroppers 12 0.00% 0.00% 2Feb17 15Feb17 29Jan17 11Feb17 4 15 OnTarget
BA8FMEPW1090 BA 8thFloor MeggeringTest 7 0.00% 0.00% 8Feb17 15Feb17 4Feb17 11Feb17 4 15 OnTarget
Corridor 46 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 35 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA8FMEPCL1000 BA 8thFloor CorridorHLClearancebyARMAforgridfixing 12 0.00% 0.00% 19Jan17 1Feb17 15Jan17 28Jan17 4 15 OnTarget
BA8FMEPCL1010 BA 8thFloor CorridorMEPclearanceforBoardclosing 12 0.00% 0.00% 31Jan17 13Feb17 26Jan17 8Feb17 4 15 OnTarget
BA8FMEPCL1030 BA 8thFloor InstallHot&ColdWaterPiping 10 0.00% 50.00% 4Jan17 15Jan17 27Nov16A 4Jan17 9 20 OnTarget
BA8FMEPCL1040 BA 8thFloor InstallHVACPipes 12 0.00% 0.00% 5Jan17 18Jan17 31Dec16 12Jan17 5 16 OnTarget
BA8FMEPCL1050 BA 8thFloor InstallDuctsandHangers 10 0.00% 0.00% 11Jan17 22Jan17 5Jan17 16Jan17 5 16 OnTarget
BA8FMEPCL1060 BA 8thFloor InstallCableTraysandTrunking 12 0.00% 0.00% 12Jan17 25Jan17 7Jan17 19Jan17 5 16 OnTarget
BA8FMEPCL1065 BA 8thFloor InstallLowCurrentWiring 10 0.00% 70.00% 18Jan17 29Jan17 27Nov16A 23Jan17 5 16 OnTarget
BA8FMEPCL1070 BA 8thFloor InstallLVCables 10 0.00% 0.00% 18Jan17 29Jan17 12Jan17 23Jan17 5 23 OnTarget
BA8FMEPCL1080 BA 8thFloor InstallDroppers 10 0.00% 0.00% 25Jan17 5Feb17 19Jan17 30Jan17 5 23 OnTarget
BA8FMEPCL1090 BA 8thFloor MeggeringTest 7 0.00% 0.00% 29Jan17 5Feb17 23Jan17 30Jan17 5 23 OnTarget
CommonFinalFinishes 30 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 25 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA8FMEPF0995 BA 8thFloor InstallGYMEquipment 24 0.00% 0.00% 18Feb17 16Mar17 31Dec16 26Jan17 42 44 OnTarget
BA8FMEPF1010 BA 8thFloor InstallLightFittings 10 0.00% 0.00% 22Feb17 5Mar17 18Feb17 28Feb17 4 17 OnTarget
BA8FMEPF1020 BA 8thFloor InstallFireCabinets 14 0.00% 0.00% 19Feb17 6Mar17 14Feb17 1Mar17 4 17 OnTarget
BA8FMEPF1030 BA 8thFloor InstallFireAlarmsandSpeakers 10 0.00% 0.00% 23Feb17 6Mar17 19Feb17 1Mar17 4 17 OnTarget
BA8FMEPF1040 BA 8thFloor InstallSprinklers 14 0.00% 0.00% 20Feb17 7Mar17 15Feb17 2Mar17 4 17 OnTarget
BA8FMEPF1050 BA 8thFloor InstallSwitchesandSockets 10 0.00% 0.00% 20Feb17 2Mar17 15Feb17 26Feb17 4 17 OnTarget
BA8FMEPF1060 BA 8thFloor InstallLowCurrentEquipments 10 0.00% 0.00% 21Feb17 4Mar17 16Feb17 27Feb17 4 17 OnTarget
BA8FMEPF1070 BA 8thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 16Feb17 4Mar17 12Feb17 27Feb17 4 17 OnTarget
BA8FMEPF1075 BA 8thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 21Feb17 6Mar17 16Feb17 1Mar17 4 9 OnTarget
BA8FMEPF1080 BA 8thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 16Feb17 4Mar17 12Feb17 27Feb17 4 17 OnTarget
NinthFloor 85 0.00% 0.00% 4Dec16 25Apr17 26Nov16A 30Apr17 4 28 OnTarget
DryArea 44 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 25 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA9FMEPD1000 BA 9thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 0.00% 4Jan17 15Jan17 3Jan17 14Jan17 1 25 OnTarget
BA9FMEPD1010 BA 9thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 15Jan17 25Jan17 14Jan17 24Jan17 1 25 OnTarget
BA9FMEPD1020 BA 9thFloor InstallElectricalWiring 10 20.00% 27.00% 28Dec16 8Jan17 27Nov16A 11Jan17 2 7 OnTarget
BA9FMEPD1030 BA 9thFloor InstallLowCurrentWiring 10 0.00% 61.00% 1Jan17 11Jan17 27Nov16A 15Jan17 2 7 OnTarget
BA9FMEPD1040 BA 9thFloor InstallHVACPipes 10 0.00% 0.00% 1Jan17 11Jan17 31Dec16 10Jan17 1 2 OnTarget
BA9FMEPD1050 BA 9thFloor InstallDuctsandHangers 10 0.00% 0.00% 4Jan17 15Jan17 3Jan17 14Jan17 1 2 OnTarget
BA9FMEPD1060 BA 9thFloor DBInstallation 10 0.00% 20.00% 8Jan17 18Jan17 27Nov16A 17Jan17 1 2 OnTarget
BA9FMEPD1070 BA 9thFloor InstallDroppers 12 0.00% 0.00% 12Jan17 25Jan17 11Jan17 24Jan17 1 25 OnTarget
BA9FMEPD1080 BA 9thFloor MeggeringTest 7 0.00% 0.00% 18Jan17 25Jan17 17Jan17 24Jan17 1 25 OnTarget
WetArea 65 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 47 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA9FMEPW1000 BA 9thFloor WetAreaScreedMEpClearance 10 0.00% 0.00% 11Jan17 22Jan17 14Jan17 25Jan17 2 4 OnTarget
BA9FMEPW1010 BA 9thFloor WetAreaHLClearancebyARMAforgridfixing 10 0.00% 0.00% 16Jan17 26Jan17 18Jan17 30Jan17 2 4 OnTarget
BA9FMEPW1020 BA 9thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 8Feb17 19Feb17 11Feb17 22Feb17 2 5 OnTarget
BA9FMEPW1030 BA 9thFloor InstallElectricalWiring 10 20.00% 27.00% 28Dec16 8Jan17 27Nov16A 11Jan17 2 4 OnTarget
BA9FMEPW1040 BA 9thFloor InstallDrainagepipes 12 25.00% 93.00% 27Dec16 9Jan17 27Nov16A 12Jan17 2 4 OnTarget
BA9FMEPW1050 BA 9thFloor InstallHot&ColdWaterPiping 10 0.00% 90.00% 31Dec16 10Jan17 27Nov16A 14Jan17 2 4 OnTarget
BA9FMEPW1060 BA 9thFloor InstallHVACPipes 12 0.00% 0.00% 1Jan17 14Jan17 3Jan17 17Jan17 2 4 OnTarget
BA9FMEPW1070 BA 9thFloor InstallDuctsandHangers 12 0.00% 0.00% 4Jan17 17Jan17 7Jan17 21Jan17 2 4 OnTarget
BA9FMEPW1080 BA 9thFloor InstallDroppers 12 0.00% 0.00% 26Jan17 8Feb17 29Jan17 12Feb17 2 14 OnTarget
BA9FMEPW1090 BA 9thFloor MeggeringTest 5 0.00% 0.00% 4Feb17 8Feb17 6Feb17 12Feb17 2 14 OnTarget
Corridor 62 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 43 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA9FMEPCL1000 BA 9thFloor CorridorScreedMEpClearance 12 0.00% 0.00% 9Jan17 22Jan17 11Jan17 25Jan17 2 37 OnTarget
BA9FMEPCL1010 BA 9thFloor CorridorHLClearancebyARMAforgridfixing 21 0.00% 0.00% 7Jan17 30Jan17 9Jan17 2Feb17 2 4 OnTarget
BA9FMEPCL1020 BA 9thFloor CorridorMEPclearanceforBoardclosing 18 0.00% 0.00% 29Jan17 18Feb17 31Jan17 21Feb17 2 4 OnTarget
BA9FMEPCL1030 BA 9thFloor InstallElectricalWiring 8 0.00% 40.00% 31Dec16 8Jan17 27Nov16A 11Jan17 2 5 OnTarget
BA9FMEPCL1050 BA 9thFloor InstallHot&ColdWaterPiping 10 0.00% 50.00% 1Jan17 11Jan17 27Nov16A 15Jan17 2 5 OnTarget
BA9FMEPCL1060 BA 9thFloor InstallHVACPipes 12 0.00% 0.00% 2Jan17 15Jan17 4Jan17 18Jan17 2 5 OnTarget
BA9FMEPCL1070 BA 9thFloor InstallDuctsandHangers 10 0.00% 0.00% 8Jan17 18Jan17 10Jan17 22Jan17 2 5 OnTarget
BA9FMEPCL1080 BA 9thFloor InstallCableTraysandTrunking 12 0.00% 0.00% 9Jan17 22Jan17 11Jan17 25Jan17 2 5 OnTarget
BA9FMEPCL1085 BA 9thFloor InstallLowCurrentWiring 10 0.00% 61.00% 15Jan17 25Jan17 27Nov16A 29Jan17 2 5 OnTarget
BA9FMEPCL1090 BA 9thFloor InstallLVCables 10 0.00% 0.00% 15Jan17 25Jan17 17Jan17 29Jan17 2 18 OnTarget
BA9FMEPCL1100 BA 9thFloor InstallDroppers 10 0.00% 0.00% 22Jan17 1Feb17 24Jan17 5Feb17 2 18 OnTarget
BA9FMEPCL1110 BA 9thFloor MeggeringTest 7 0.00% 0.00% 25Jan17 1Feb17 28Jan17 5Feb17 2 18 OnTarget
CommonFinalFinishes 32 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 20 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA9FMEPF1010 BA 9thFloor InstallLightFittings 10 0.00% 0.00% 21Feb17 4Mar17 23Feb17 7Mar17 2 4 OnTarget
BA9FMEPF1020 BA 9thFloor InstallFireCabinets 14 0.00% 0.00% 18Feb17 5Mar17 20Feb17 8Mar17 2 4 OnTarget
BA9FMEPF1030 BA 9thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 18Feb17 5Mar17 20Feb17 8Mar17 2 4 OnTarget
BA9FMEPF1040 BA 9thFloor InstallSprinklers 10 0.00% 0.00% 23Feb17 6Mar17 26Feb17 9Mar17 2 4 OnTarget
BA9FMEPF1050 BA 9thFloor InstallSwitchesandSockets 14 0.00% 0.00% 23Feb17 11Mar17 26Feb17 14Mar17 2 4 OnTarget
BA9FMEPF1060 BA 9thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 25Feb17 12Mar17 27Feb17 15Mar17 2 4 OnTarget
BA9FMEPF1070 BA 9thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 25Feb17 12Mar17 27Feb17 15Mar17 2 4 OnTarget
BA9FMEPF1075 BA 9thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 20Feb17 6Mar17 21Feb17 7Mar17 1 5 OnTarget
BA9FMEPF1080 BA 9thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 25Feb17 12Mar17 27Feb17 15Mar17 2 4 OnTarget
TenthFloor 105 0.00% 0.00% 7Dec16 17Apr17 26Nov16A 11Apr17 5 44 OnTarget
DryArea 48 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 29 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA10FMEPD1000 BA 10thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 0.00% 8Jan17 18Jan17 3Jan17 14Jan17 4 10 OnTarget
BA10FMEPD1010 BA 10thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 19Jan17 30Jan17 15Jan17 25Jan17 4 28 OnTarget
BA10FMEPD1020 BA 10thFloor InstallElectricalWiring 10 20.00% 20.00% 28Dec16 8Jan17 23Dec16A 11Jan17 2 7 OnTarget
BA10FMEPD1030 BA 10thFloor InstallLowCurrentWiring 10 0.00% 55.00% 4Jan17 15Jan17 27Nov16A 18Jan17 2 7 OnTarget
BA10FMEPD1040 BA 10thFloor InstallHVACPipes 10 0.00% 0.00% 4Jan17 15Jan17 31Dec16 10Jan17 4 5 OnTarget
BA10FMEPD1050 BA 10thFloor InstallDuctsandHangers 10 0.00% 0.00% 8Jan17 18Jan17 3Jan17 14Jan17 4 5 OnTarget
BA10FMEPD1060 BA 10thFloor DBInstallation 10 0.00% 20.00% 8Jan17 18Jan17 27Nov16A 14Jan17 4 5 OnTarget
BA10FMEPD1070 BA 10thFloor InstallDroppers 12 0.00% 0.00% 17Jan17 30Jan17 12Jan17 25Jan17 4 28 OnTarget
BA10FMEPD1080 BA 10thFloor MeggeringTest 7 0.00% 0.00% 23Jan17 30Jan17 18Jan17 25Jan17 4 28 OnTarget
WetArea 66 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 55 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA10FMEPW1000 BA 10thFloor WetAreaScreedMEpClearance 10 90.00% 90.00% 20Dec16 31Dec16 21Dec16A 19Jan17 17 1 OnTarget
BA10FMEPW1010 BA 10thFloor WetAreaHLClearancebyARMAforgridfixing 10 0.00% 0.00% 8Jan17 18Jan17 12Jan17 24Jan17 5 1 OnTarget
BA10FMEPW1030 BA 10thFloor InstallElectricalWiring 10 20.00% 20.00% 28Dec16 8Jan17 28Dec16A 11Jan17 2 5 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BA10FMEPW1040 BA 10thFloor InstallDrainagepipes 12 25.00% 80.00% 27Dec16 9Jan17 27Nov16A 12Jan17 2 5 OnTarget
BA10FMEPW1050 BA 10thFloor InstallHot&ColdWaterPiping 10 0.00% 85.00% 31Dec16 10Jan17 27Nov16A 14Jan17 2 5 OnTarget
BA10FMEPW1060 BA 10thFloor InstallHVACPipes 12 0.00% 0.00% 1Jan17 14Jan17 3Jan17 17Jan17 2 5 OnTarget
BA10FMEPW1070 BA 10thFloor Firefightingpipes 5 0.00% 98.00% 10Jan17 15Jan17 27Nov16A 18Jan17 2 6 OnTarget
BA10FMEPW1080 BA 10thFloor InstallDuctsandHangers 12 0.00% 0.00% 4Jan17 17Jan17 7Jan17 21Jan17 2 5 OnTarget
BA10FMEPW1090 BA 10thFloor InstallDroppers 12 0.00% 0.00% 30Jan17 12Feb17 4Feb17 18Feb17 5 9 OnTarget
BA10FMEPW1100 BA 10thFloor MeggeringTest 5 0.00% 0.00% 7Feb17 12Feb17 12Feb17 18Feb17 5 9 OnTarget
BA10FMEPW1105 BA 10thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 11Feb17 21Feb17 15Feb17 27Feb17 5 1 OnTarget
Corridor 66 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 47 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA10FMEPCL1000 BA 10thFloor CorridorScreedMEpClearance 12 91.67% 92.00% 18Dec16 31Dec16 21Dec16A 19Jan17 17 29 OnTarget
BA10FMEPCL1010 BA 10thFloor CorridorHLClearancebyARMAforgridfixing 12 0.00% 0.00% 16Jan17 29Jan17 14Jan17 28Jan17 1 15 OnTarget
BA10FMEPCL1020 BA 10thFloor CorridorMEPclearanceforBoardclosing 12 0.00% 0.00% 28Jan17 9Feb17 25Jan17 8Feb17 1 15 OnTarget
BA10FMEPCL1030 BA 10thFloor InstallElectricalWiring 10 20.00% 100.00% 28Dec16 8Jan17 27Nov16A 27Nov16A 37 0 OnTarget
BA10FMEPCL1050 BA 10thFloor InstallHot&ColdWaterPiping 12 8.33% 50.00% 29Dec16 11Jan17 27Nov16A 5Jan17 5 19 OnTarget
BA10FMEPCL1060 BA 10thFloor Firefightingpipes 5 0.00% 98.00% 7Jan17 11Jan17 27Nov16A 5Jan17 5 19 OnTarget
BA10FMEPCL1070 BA 10thFloor InstallHVACPipes 12 0.00% 0.00% 2Jan17 15Jan17 31Dec16 12Jan17 2 16 OnTarget
BA10FMEPCL1080 BA 10thFloor InstallDuctsandHangers 10 0.00% 0.00% 8Jan17 18Jan17 5Jan17 16Jan17 2 16 OnTarget
BA10FMEPCL1090 BA 10thFloor InstallCableTraysandTrunking 12 0.00% 0.00% 9Jan17 22Jan17 7Jan17 19Jan17 2 16 OnTarget
BA10FMEPCL1095 BA 10thFloor InstallLowCurrentWiring 12 0.00% 55.00% 12Jan17 25Jan17 27Nov16A 23Jan17 2 16 OnTarget
BA10FMEPCL1100 BA 10thFloor InstallLVCables 4 0.00% 0.00% 22Jan17 25Jan17 19Jan17 23Jan17 2 23 OnTarget
BA10FMEPCL1110 BA 10thFloor InstallDroppers 10 0.00% 0.00% 22Jan17 1Feb17 19Jan17 30Jan17 2 23 OnTarget
BA10FMEPCL1120 BA 10thFloor MeggeringTest 5 0.00% 0.00% 28Jan17 1Feb17 25Jan17 30Jan17 2 23 OnTarget
CommonFinalFinishes 33 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA10FMEPF1010 BA 10thFloor InstallLightFittings 14 0.00% 0.00% 18Feb17 5Mar17 22Feb17 11Mar17 5 4 OnTarget
BA10FMEPF1020 BA 10thFloor InstallFireCabinets 14 0.00% 0.00% 19Feb17 6Mar17 23Feb17 12Mar17 5 4 OnTarget
BA10FMEPF1030 BA 10thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 19Feb17 6Mar17 23Feb17 12Mar17 5 4 OnTarget
BA10FMEPF1040 BA 10thFloor InstallSprinklers 14 0.00% 0.00% 20Feb17 7Mar17 25Feb17 13Mar17 5 4 OnTarget
BA10FMEPF1050 BA 10thFloor InstallSwitchesandSockets 14 0.00% 0.00% 20Feb17 7Mar17 25Feb17 13Mar17 5 4 OnTarget
BA10FMEPF1060 BA 10thFloor InstallLowCurrentEquipments 14 0.00% 0.00% 21Feb17 8Mar17 26Feb17 14Mar17 5 4 OnTarget
BA10FMEPF1070 BA 10thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 21Feb17 8Mar17 26Feb17 14Mar17 5 4 OnTarget
BA10FMEPF1075 BA 10thFloor MEPFinalFixes/Sanitarywares 12 0.00% 0.00% 20Feb17 5Mar17 25Feb17 11Mar17 5 1 OnTarget
BA10FMEPF1080 BA 10thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 21Feb17 8Mar17 26Feb17 14Mar17 5 4 OnTarget
EleventhFloor 81 0.00% 0.00% 18Dec16 21Mar17 26Nov16A 19Mar17 2 24 OnTarget
DryArea 44 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 25 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA11FMEPD1000 BA 11thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 0.00% 8Jan17 18Jan17 3Jan17 14Jan17 4 31 OnTarget
BA11FMEPD1010 BA 11thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 18Jan17 29Jan17 14Jan17 24Jan17 4 31 OnTarget
BA11FMEPD1020 BA 11thFloor InstallElectricalWiring 10 0.00% 0.00% 1Jan17 11Jan17 3Jan17 15Jan17 2 4 OnTarget
BA11FMEPD1030 BA 11thFloor InstallLowCurrentWiring 10 0.00% 30.00% 4Jan17 15Jan17 27Nov16A 18Jan17 2 4 OnTarget
BA11FMEPD1040 BA 11thFloor InstallHVACPipes 10 0.00% 0.00% 4Jan17 15Jan17 31Dec16 10Jan17 4 5 OnTarget
BA11FMEPD1050 BA 11thFloor InstallDuctsandHangers 10 0.00% 0.00% 8Jan17 18Jan17 3Jan17 14Jan17 4 5 OnTarget
BA11FMEPD1060 BA 11thFloor DBInstallation 10 0.00% 20.00% 8Jan17 18Jan17 27Nov16A 14Jan17 4 5 OnTarget
BA11FMEPD1070 BA 11thFloor InstallDroppers 12 0.00% 0.00% 16Jan17 29Jan17 11Jan17 24Jan17 4 31 OnTarget
BA11FMEPD1080 BA 11thFloor MeggeringTest 7 0.00% 0.00% 22Jan17 29Jan17 17Jan17 24Jan17 4 31 OnTarget
WetArea 65 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
MEPWorks 56 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA11FMEPW1000 BA 11thFloor WetAreaScreedMEpClearance 12 66.67% 67.00% 21Dec16 3Jan17 21Dec16A 23Jan17 17 2 OnTarget
BA11FMEPW1010 BA 11thFloor WetAreaHLClearancebyARMAforgridfixing 10 0.00% 0.00% 10Jan17 21Jan17 16Jan17 28Jan17 6 2 OnTarget
BA11FMEPW1020 BA 11thFloor WetAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 13Feb17 23Feb17 19Feb17 2Mar17 6 2 OnTarget
BA11FMEPW1030 BA 11thFloor InstallElectricalWiring 10 0.00% 0.00% 1Jan17 11Jan17 3Jan17 15Jan17 2 2 OnTarget
BA11FMEPW1040 BA 11thFloor InstallDrainagepipes 12 0.00% 80.00% 31Dec16 12Jan17 27Nov16A 16Jan17 2 2 OnTarget
BA11FMEPW1050 BA 11thFloor InstallHot&ColdWaterPiping 12 0.00% 85.00% 1Jan17 14Jan17 27Nov16A 17Jan17 2 2 OnTarget
BA11FMEPW1060 BA 11thFloor InstallHVACPipes 12 0.00% 0.00% 4Jan17 17Jan17 7Jan17 21Jan17 2 2 OnTarget
BA11FMEPW1070 BA 11thFloor Firefightingpipes 10 0.00% 15.00% 8Jan17 18Jan17 27Nov16A 22Jan17 2 3 OnTarget
BA11FMEPW1080 BA 11thFloor InstallDuctsandHangers 12 0.00% 0.00% 8Jan17 21Jan17 10Jan17 24Jan17 2 2 OnTarget
BA11FMEPW1090 BA 11thFloor InstallDroppers 12 0.00% 0.00% 2Feb17 15Feb17 8Feb17 22Feb17 6 5 OnTarget
BA11FMEPW1100 BA 11thFloor MeggeringTest 7 0.00% 0.00% 8Feb17 15Feb17 14Feb17 22Feb17 6 5 OnTarget
Corridor 64 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 45 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA11FMEPCL1000 BA 11thFloor CorridorScreedMEpClearance 12 66.67% 67.00% 21Dec16 3Jan17 21Dec16A 23Jan17 17 38 OnTarget
BA11FMEPCL1010 BA 11thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 22Jan17 1Feb17 24Jan17 5Feb17 2 11 OnTarget
BA11FMEPCL1020 BA 11thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 31Jan17 11Feb17 2Feb17 14Feb17 2 11 OnTarget
BA11FMEPCL1030 BA 11thFloor InstallElectricalWiring 10 0.00% 0.00% 1Jan17 11Jan17 3Jan17 15Jan17 2 11 OnTarget
BA11FMEPCL1050 BA 11thFloor InstallHot&ColdWaterPiping 10 0.00% 50.00% 4Jan17 15Jan17 27Nov16A 18Jan17 2 11 OnTarget
BA11FMEPCL1060 BA 11thFloor Firefightingpipes 10 0.00% 98.00% 4Jan17 15Jan17 27Nov16A 18Jan17 2 11 OnTarget
BA11FMEPCL1070 BA 11thFloor InstallHVACPipes 12 0.00% 0.00% 5Jan17 18Jan17 8Jan17 22Jan17 2 11 OnTarget
BA11FMEPCL1080 BA 11thFloor InstallDuctsandHangers 10 0.00% 0.00% 11Jan17 22Jan17 14Jan17 25Jan17 2 11 OnTarget
BA11FMEPCL1090 BA 11thFloor InstallCableTraysandTrunking 12 0.00% 0.00% 12Jan17 25Jan17 15Jan17 29Jan17 2 11 OnTarget
BA11FMEPCL1095 BA 11thFloor InstallLowCurrentWiring 10 0.00% 30.00% 18Jan17 29Jan17 27Nov16A 1Feb17 2 11 OnTarget
BA11FMEPCL1100 BA 11thFloor InstallLVCables 10 0.00% 0.00% 18Jan17 29Jan17 21Jan17 1Feb17 2 14 OnTarget
BA11FMEPCL1110 BA 11thFloor InstallDroppers 10 0.00% 0.00% 25Jan17 5Feb17 28Jan17 8Feb17 2 16 OnTarget
BA11FMEPCL1120 BA 11thFloor MeggeringTest 7 0.00% 0.00% 29Jan17 5Feb17 31Jan17 8Feb17 2 16 OnTarget
CommonFinalFinishes 24 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 17 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA11FMEPF1010 BA 11thFloor InstallLightFittings 10 0.00% 0.00% 27Feb17 9Mar17 5Mar17 16Mar17 6 3 OnTarget
BA11FMEPF1020 BA 11thFloor InstallFireCabinets 14 0.00% 0.00% 23Feb17 11Mar17 1Mar17 18Mar17 6 3 OnTarget
BA11FMEPF1030 BA 11thFloor InstallFireAlarmsandSpeakers 14 0.00% 0.00% 23Feb17 11Mar17 1Mar17 18Mar17 6 3 OnTarget
BA11FMEPF1040 BA 11thFloor InstallSprinklers 14 0.00% 0.00% 25Feb17 12Mar17 2Mar17 19Mar17 6 3 OnTarget
BA11FMEPF1050 BA 11thFloor InstallSwitchesandSockets 10 0.00% 0.00% 25Feb17 7Mar17 2Mar17 14Mar17 6 3 OnTarget
BA11FMEPF1060 BA 11thFloor InstallLowCurrentEquipments 10 0.00% 0.00% 26Feb17 8Mar17 4Mar17 15Mar17 6 3 OnTarget
BA11FMEPF1070 BA 11thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 21Feb17 8Mar17 27Feb17 15Mar17 6 3 OnTarget
BA11FMEPF1075 BA 11thFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 26Feb17 9Mar17 2Mar17 14Mar17 4 2 OnTarget
BA11FMEPF1080 BA 11thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 21Feb17 8Mar17 27Feb17 15Mar17 6 3 OnTarget
TwelthFloor 99 0.00% 0.00% 27Nov16 21Mar17 26Nov16A 25Mar17 3 19 OnTarget
General 13 0.00% 0.00% 27Nov16 3Jan17 27Nov16A 17Jan17 11 117 OnTarget
BA12F1000 BA 12thFloor PlasterMEpClearance(H0108,A0107) 8 100.00% 100.00% 27Nov16 5Dec16 26Nov16A 26Nov16A 9 0 OnTarget
DryArea 40 0.00% 0.00% 18Dec16 7Mar17 27Nov16A 10Apr17 29 22 OnTarget
MEPWorks 28 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA12FMEPD1000 BA 12thFloor DraAreaMEPScreedclearance 12 0.00% 97.00% 19Jan17 1Feb17 29Nov16A 31Dec16 29 35 OnTarget
BA12FMEPD1010 BA 12thFloor DryAreaMEPHLClearancebyARMAforgridfixing 10 0.00% 0.00% 8Jan17 18Jan17 10Jan17 22Jan17 2 9 OnTarget
BA12FMEPD1020 BA 12thFloor DryAreaMEPclearanceforBoardclosing 10 0.00% 0.00% 18Jan17 29Jan17 21Jan17 1Feb17 2 9 OnTarget
BA12FMEPD1030 BA 12thFloor InstallElectricalWiring 10 0.00% 0.00% 1Jan17 11Jan17 3Jan17 15Jan17 2 1 OnTarget
BA12FMEPD1040 BA 12thFloor InstallLowCurrentWiring 10 0.00% 22.00% 2Jan17 12Jan17 27Nov16A 16Jan17 2 1 OnTarget
BA12FMEPD1050 BA 12thFloor InstallHVACPipes 10 0.00% 0.00% 5Jan17 16Jan17 8Jan17 19Jan17 2 1 OnTarget
BA12FMEPD1060 BA 12thFloor InstallDuctsandHangers 10 0.00% 0.00% 8Jan17 18Jan17 10Jan17 22Jan17 2 1 OnTarget
BA12FMEPD1070 BA 12thFloor DBInstallation 10 0.00% 20.00% 8Jan17 18Jan17 27Nov16A 22Jan17 2 1 OnTarget
BA12FMEPD1080 BA 12thFloor InstallDroppers 12 0.00% 0.00% 16Jan17 29Jan17 18Jan17 1Feb17 2 9 OnTarget
BA12FMEPD1090 BA 12thFloor MeggeringTest 7 0.00% 0.00% 22Jan17 29Jan17 24Jan17 1Feb17 2 9 OnTarget
WetArea 59 0.00% 0.00% 28Dec16 22Mar17 27Nov16A 7Mar17 13 74 OnTarget
BA12FMEPW1000 BA 12thFloor WetAreaScreedMEpClearance 12 41.67% 42.00% 25Dec16 7Jan17 21Dec16A 26Jan17 17 7 OnTarget
BA12FMEPW1010 BA 12thFloor WetAreaHLClearancebyARMAforgridfixing 18 0.00% 0.00% 4Jan17 24Jan17 19Jan17 9Feb17 14 7 OnTarget
BA12FMEPW1020 BA 12thFloor WetAreaMEPclearanceforBoardclosing 18 0.00% 0.00% 31Jan17 20Feb17 15Feb17 8Mar17 14 7 OnTarget
BA12FMEPW1030 BA 12thFloor InstallElectricalWiring 10 0.00% 0.00% 1Jan17 11Jan17 3Jan17 15Jan17 2 4 OnTarget
BA12FMEPW1040 BA 12thFloor InstallDrainagepipes 12 0.00% 0.00% 31Dec16 12Jan17 2Jan17 16Jan17 2 5 OnTarget
BA12FMEPW1050 BA 12thFloor InstallHot&ColdWaterPiping 12 0.00% 46.00% 3Jan17 16Jan17 27Nov16A 19Jan17 2 5 OnTarget
BA12FMEPW1060 BA 12thFloor InstallHVACPipes 12 0.00% 0.00% 7Jan17 19Jan17 9Jan17 23Jan17 2 5 OnTarget
BA12FMEPW1070 BA 12thFloor Firefightingpipes 10 0.00% 0.00% 12Jan17 23Jan17 15Jan17 26Jan17 2 5 OnTarget
BA12FMEPW1080 BA 12thFloor InstallDuctsandHangers 12 0.00% 0.00% 11Jan17 24Jan17 14Jan17 28Jan17 2 5 OnTarget
BA12FMEPW1090 BA 12thFloor InstallDroppers 12 0.00% 0.00% 29Jan17 11Feb17 13Feb17 27Feb17 14 1 OnTarget
BA12FMEPW1100 BA 12thFloor MeggeringTest 5 0.00% 0.00% 6Feb17 11Feb17 21Feb17 27Feb17 14 1 OnTarget
Corridor 58 0.00% 0.00% 15Dec16 18Feb17 27Nov16A 9Mar17 17 7 OnTarget
MEPWorks 39 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA12FMEPCL1000 BA 12thFloor CorridorScreedMEpClearance 12 41.67% 42.00% 25Dec16 7Jan17 21Dec16A 26Jan17 17 35 OnTarget
BA12FMEPCL1010 BA 12thFloor CorridorHLClearancebyARMAforgridfixing 10 0.00% 0.00% 18Jan17 29Jan17 1Feb17 13Feb17 13 3 OnTarget
BA12FMEPCL1020 BA 12thFloor CorridorMEPclearanceforBoardclosing 10 0.00% 0.00% 28Jan17 7Feb17 11Feb17 22Feb17 13 3 OnTarget
BA12FMEPCL1030 BA 12thFloor InstallElectricalWiring 10 0.00% 0.00% 1Jan17 11Jan17 3Jan17 15Jan17 2 4 OnTarget
BA12FMEPCL1050 BA 12thFloor InstallHot&ColdWaterPiping 10 0.00% 50.00% 3Jan17 14Jan17 27Nov16A 17Jan17 2 4 OnTarget
BA12FMEPCL1060 BA 12thFloor Firefightingpipes 10 0.00% 98.00% 3Jan17 14Jan17 27Nov16A 17Jan17 2 4 OnTarget
BA12FMEPCL1070 BA 12thFloor InstallHVACPipes 12 0.00% 0.00% 3Jan17 16Jan17 5Jan17 19Jan17 2 4 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BA12FMEPCL1080 BA 12thFloor InstallDuctsandHangers 14 0.00% 0.00% 3Jan17 18Jan17 5Jan17 22Jan17 2 4 OnTarget
BA12FMEPCL1090 BA 12thFloor InstallCableTraysandTrunking 12 0.00% 0.00% 9Jan17 22Jan17 11Jan17 25Jan17 2 4 OnTarget
BA12FMEPCL1095 BA 12thFloor InstallLowCurrentWiring 10 0.00% 22.00% 15Jan17 25Jan17 27Nov16A 29Jan17 2 4 OnTarget
BA12FMEPCL1100 BA 12thFloor InstallLVCables 12 0.00% 0.00% 12Jan17 25Jan17 15Jan17 29Jan17 2 19 OnTarget
BA12FMEPCL1110 BA 12thFloor InstallDroppers 10 0.00% 0.00% 22Jan17 1Feb17 24Jan17 5Feb17 2 19 OnTarget
BA12FMEPCL1120 BA 12thFloor MeggeringTest 5 0.00% 0.00% 28Jan17 1Feb17 30Jan17 5Feb17 2 19 OnTarget
CommonFinalFinishes 24 0.00% 0.00% 11Feb17 19Mar17 20Feb17 28Mar17 8 41 OnTarget
MEPWorks 16 0.00% 0.00% 4Dec16 24Dec16 27Nov16A 7Jan17 11 7 OnTarget
BA12FMEPF1010 BA 12thFloor InstallLightFittings 10 0.00% 0.00% 22Feb17 5Mar17 9Mar17 21Mar17 14 5 OnTarget
BA12FMEPF1020 BA 12thFloor InstallFireCabinets 14 0.00% 0.00% 19Feb17 6Mar17 6Mar17 22Mar17 14 5 OnTarget
BA12FMEPF1030 BA 12thFloor InstallFireAlarmsandSpeakers 10 0.00% 0.00% 23Feb17 6Mar17 11Mar17 22Mar17 14 5 OnTarget
BA12FMEPF1040 BA 12thFloor InstallSprinklers 14 0.00% 0.00% 20Feb17 7Mar17 7Mar17 23Mar17 14 5 OnTarget
BA12FMEPF1050 BA 12thFloor InstallSwitchesandSockets 14 0.00% 0.00% 20Feb17 7Mar17 7Mar17 23Mar17 14 5 OnTarget
BA12FMEPF1060 BA 12thFloor InstallLowCurrentEquipments 10 0.00% 0.00% 26Feb17 8Mar17 13Mar17 25Mar17 14 5 OnTarget
BA12FMEPF1070 BA 12thFloor InstallGrillesandDiffussers 14 0.00% 0.00% 21Feb17 8Mar17 8Mar17 25Mar17 14 5 OnTarget
BA12FMEPF1075 BA 12thFloor MEPFinalFixes/Sanitarywares 10 0.00% 0.00% 21Feb17 5Mar17 8Mar17 20Mar17 13 7 OnTarget
BA12FMEPF1080 BA 12thFloor InstallPlumpingFinalTittings(Sanitaryware,FloorDra 14 0.00% 0.00% 21Feb17 8Mar17 8Mar17 25Mar17 14 5 OnTarget
RoofFloor 71 0.00% 0.00% 27Nov16 19Mar17 26Nov16A 27Feb17 18 82 OnTarget
General 42 0.00% 0.00% 27Nov16 3Jan17 27Nov16A 17Jan17 11 117 OnTarget
BARF1050 BA Roof FAHUinstallationandconenction 24 100.00% 100.00% 27Nov16 24Dec16 26Nov16A 28Dec16A 3 0 OnTarget
BARF1060 BA Roof VRVunitsinstallation/connection/termination 36 80.56% 81.00% 27Nov16 7Jan17 27Nov16A 7Jan17 0 73 OnTarget
BARF1070 BA Roof GRPWatertankinstallationandconnections 24 58.33% 75.00% 14Dec16 10Jan17 27Nov16A 10Jan17 0 73 OnTarget
PumpRoom 42 0.00% 0.00% 27Nov16 30Jan17 26Nov16A 11Feb17 9 4 OnTarget
BARF1100 BA Roof PlasterMEpClearance 6 100.00% 100.00% 27Nov16 3Dec16 27Nov16A 10Dec16A 5 0 OnTarget
BARF1130 BA Roof MEPScreedclearance 6 100.00% 100.00% 5Dec16 11Dec16 27Nov16A 10Dec16A 2 0 OnTarget
BARF1150 BA Roof MEPInstallations/Connections 24 70.83% 71.00% 11Dec16 7Jan17 01Dec16A 7Jan17 0 52 OnTarget
BARF1160 BA Roof MEPHLClearancebyARMAforceilingpainting 6 100.00% 0.00% 5Dec16 11Dec16 31Dec16 5Jan17 22 42 Delayed
BARF1200 BA Roof MEPFinalFixes 6 0.00% 0.00% 4Jan17 10Jan17 16Jan17 22Jan17 10 42 OnTarget
ElectricalRoom 62 0.00% 0.00% 20Dec16 20Feb17 19Dec16A 27Feb17 5 69 OnTarget
BARF1230 BA Roof PlasterMEpClearance 6 100.00% 100.00% 21Dec16 27Dec16 19Dec16A 22Dec16A 5 0 OnTarget
BARF1260 BA Roof MEPScreedclearance 3 0.00% 0.00% 7Jan17 9Jan17 2Jan17 4Jan17 4 27 OnTarget
BARF1280 BA Roof MEPInstallations/Connections 24 0.00% 0.00% 14Jan17 9Feb17 9Jan17 5Feb17 4 27 OnTarget
BARF1290 BA Roof MEPHLClearancebyARMAforceilingpainting 10 0.00% 0.00% 7Jan17 17Jan17 2Jan17 12Jan17 4 34 OnTarget
BARF1330 BA Roof MEPFinalFixes 3 0.00% 0.00% 11Feb17 13Feb17 6Feb17 8Feb17 4 27 OnTarget
FAHURoom 50 0.00% 0.00% 27Nov16 30Jan17 26Nov16A 28Jan17 2 107 OnTarget
BARF1360 BA Roof PlasterMEpClearance 10 60.00% 100.00% 24Dec16 3Jan17 19Dec16A 20Dec16A 13 0 OnTarget
BARF1390 BA Roof MEPScreedclearance 10 0.00% 100.00% 1Jan17 11Jan17 26Nov16A 26Nov16A 41 0 OnTarget
BARF1410 BA Roof MEPInstallations/Connections 24 0.00% 0.00% 7Jan17 2Feb17 31Dec16 26Jan17 6 35 OnTarget
BARF1420 BA Roof MEPHLClearancebyARMAforceilingpainting 12 0.00% 0.00% 1Jan17 14Jan17 1Jan17 14Jan17 0 35 OnTarget
BARF1460 BA Roof MEPFinalFixes 6 0.00% 0.00% 31Jan17 6Feb17 24Jan17 30Jan17 6 35 OnTarget
RoofFinishes 48 0.00% 0.00% 25Jan17 2Apr17 4Feb17 11Apr17 8 31 OnTarget
BARF1530 BA Roof RoofFloortiling 18 100.00% 98.00% 27Nov16 17Dec16 26Nov16A 31Dec16 11 86 Delayed
BARF1540 BA Roof RoofSoftLandscaping 24 20.83% 0.00% 25Dec16 21Jan17 31Dec16 26Jan17 5 68 Delayed
CommonArea 96 0.00% 0.00% 27Nov16 22Jan17 26Nov16A 4Feb17 11 101 OnTarget
MEPservicesroomsandOthers 42 0.00% 0.00% 27Nov16 10Jan17 26Nov16A 4Feb17 21 101 OnTarget
LVRoomD 30 0.00% 0.00% 27Nov16 18Dec16 26Nov16A 5Jan17 15 127 OnTarget
BAL041050 BA MEPworkCompletionbyARMA 21 100.00% 65.00% 4Dec16 27Dec16 26Nov16A 8Jan17 9 8 Delayed
LVRoomB 30 0.00% 0.00% 27Nov16 14Dec16 26Nov16A 5Jan17 19 126 OnTarget
BASR11100 BA MEPworkCompletionbyARMA 21 95.24% 67.00% 7Dec16 31Dec16 26Nov16A 7Jan17 6 8 Delayed
ElectricalRooms/Telephone/WaterMeterRooms 40 0.00% 0.00% 27Nov16 10Jan17 26Nov16A 22Jan17 9 113 OnTarget
BAEL1000 BA MEPClearanceforPlaster 18 100.00% 92.00% 27Nov16 17Dec16 26Nov16A 1Jan17 12 9 Delayed
BAEL1020 BA MEPClearanceforScreed(AsApplicable) 18 100.00% 60.00% 8Dec16 28Dec16 26Nov16A 12Jan17 12 9 Delayed
BAEL1035 BA MEPworkCompletionbyARMA 30 63.33% 43.00% 8Dec16 11Jan17 27Nov16A 19Jan17 6 45 Delayed
FanRooms 36 0.00% 0.00% 27Nov16 24Dec16 26Nov16A 19Jan17 23 22 OnTarget
BAFA1020 BA MEPworkCompletionbyARMA 21 100.00% 53.00% 3Dec16 26Dec16 26Nov16A 10Jan17 13 52 Delayed
FireWater/IrrigationPump 34 0.00% 0.00% 27Nov16 21Dec16 26Nov16A 5Jan17 13 126 OnTarget
BAFP1010 BA MEPClearanceforScreed(AsApplicable) 14 100.00% 100.00% 29Nov16 14Dec16 27Nov16A 10Dec16A 5 0 OnTarget
BAFP1030 BA MEPworkCompletionbyARMA 24 100.00% 65.00% 28Nov16 25Dec16 27Nov16A 9Jan17 12 54 Delayed
GeneratorRooms 42 0.00% 0.00% 27Nov16 31Dec16 27Nov16A 5Jan17 5 126 OnTarget
BAGN1010 BA MEPClearanceforPlaster 6 100.00% 100.00% 1Dec16 7Dec16 05Dec16A 05Dec16A 3 0 OnTarget
BAGN1030 BA MEPClearanceforScreed(AsApplicable) 7 100.00% 100.00% 8Dec16 15Dec16 27Nov16A 10Dec16A 6 0 OnTarget
BAGN1060 BA MEPworkCompletionbyARMA 21 80.95% 81.00% 11Dec16 3Jan17 27Nov16A 3Jan17 0 58 OnTarget
GarabageRooms 33 0.00% 0.00% 27Nov16 10Jan17 27Nov16A 16Jan17 5 117 OnTarget
BAGR1000 BA MEPClearanceforPlaster 10 100.00% 100.00% 27Nov16 7Dec16 26Nov16A 10Dec16A 1 0 OnTarget
BAGR1020 BA MEPClearanceforScreed(AsApplicable) 10 100.00% 100.00% 7Dec16 18Dec16 27Nov16A 10Dec16A 8 0 OnTarget
BAGR1060 BA MEPworkCompletionbyARMA 18 100.00% 40.00% 7Dec16 27Dec16 27Nov16A 11Jan17 13 51 Delayed
SwimingPoolandPumpRoom 30 0.00% 0.00% 6Dec16 7Jan17 27Nov16A 4Feb17 24 3 OnTarget
BARFS2SU1080 BA Roof SwimmingPoolMEPWorks 24 62.50% 15.00% 13Dec16 9Jan17 27Nov16A 6Feb17 24 29 Delayed
StaircaseFinishes 76 0.00% 0.00% 27Nov16 17Jan17 26Nov16A 4Feb17 14 102 OnTarget
BAST1020 BA PlasterMEPClearance 18 83.33% 65.00% 13Dec16 2Jan17 27Nov16A 22Jan17 16 69 Delayed
OTS 69 0.00% 0.00% 27Nov16 12Jan17 26Nov16A 23Jan17 9 9 OnTarget
BAOTS1020 BA MEPCutting&Chasingforconduits 14 100.00% 91.00% 27Nov16 12Dec16 26Nov16A 1Jan17 16 131 Delayed
BAOTS1090 BA MEPWork 30 0.00% 0.00% 11Jan17 14Feb17 31Dec16 2Feb17 10 17 OnTarget
Roofing 47 0.00% 0.00% 27Nov16 16Feb17 26Nov16A 7Feb17 8 83 OnTarget
BARF1040 BA Roof RoofEquipmentInstallation&Conncetion 32 43.75% 58.00% 14Dec16 19Jan17 26Nov16A 15Jan17 5 49 OnTarget
ExternalElevation 86 0.00% 0.00% 27Nov16 25Feb17 26Nov16A 6Mar17 8 75 OnTarget
SouthSide 50 0.00% 0.00% 27Nov16 8Jan17 26Nov16A 8Jan17 1 125 OnTarget
BAEV1180 BA MEPFittings 12 0.00% 100.00% 3Jan17 16Jan17 26Nov16A 26Nov16A 45 0 OnTarget
Westside 42 0.00% 0.00% 27Nov16 24Jan17 26Nov16A 29Jan17 4 1 OnTarget
BAEV1230 BA MEPFittings 10 30.00% 0.00% 27Dec16 7Jan17 23Jan17 4Feb17 23 21 Delayed
Northside 86 0.00% 0.00% 27Nov16 22Jan17 26Nov16A 1Feb17 9 2 OnTarget
BAEV1040 BA MEPCutting&Chasingforconduits 14 50.00% 70.00% 22Dec16 7Jan17 26Nov16A 16Jan17 7 98 OnTarget
BAEV1280 BA MEPFittings 10 0.00% 0.00% 16Feb17 27Feb17 23Jan17 2Feb17 21 21 OnTarget
EastSide 72 0.00% 0.00% 27Nov16 21Jan17 26Nov16A 2Feb17 11 102 OnTarget
BAEV1110 BA MEPCutting&Chasingforconduits 14 35.71% 72.00% 25Dec16 9Jan17 02Dec16A 3Jan17 5 128 OnTarget
BAEV1330 BA MEPFittings 6 0.00% 0.00% 19Feb17 25Feb17 28Jan17 2Feb17 19 21 OnTarget
ExternalWork 46 0.00% 0.00% 6Feb17 4Apr17 15Feb17 6Apr17 2 2 OnTarget
BAEX1010 BA ExternalMEPServices 28 0.00% 0.00% 9Mar17 10Apr17 13Feb17 18Mar17 21 50 OnTarget
BAEX1060 BA ExternalWaterFeatureMEPWorks 28 0.00% 0.00% 23Mar17 24Apr17 27Feb17 1Apr17 21 21 OnTarget
Testing&Commissioning 56 0.00% 0.00% 27Feb17 30Apr17 1Mar17 2May17 2 25 OnTarget
BATCS3ME1100 BA Testing&CommissioningforAllSystem 48 0.00% 0.00% 12Feb17 8Apr17 22Feb17 18Apr17 9 8 OnTarget
Electrical 24 0.00% 0.00% 27Feb17 9Apr17 1Mar17 11Apr17 2 43 OnTarget
BATC1030 BA TestingandCommissioningofLVPanels&System 24 0.00% 0.00% 21Feb17 20Mar17 4Mar17 30Mar17 9 7 OnTarget
BATC1040 BA TestingandCommissioningofLightningProtectionSys 18 0.00% 0.00% 28Feb17 20Mar17 11Mar17 30Mar17 9 7 OnTarget
BATC1050 BA TestingandCommissioningofGenerator 10 0.00% 0.00% 9Mar17 20Mar17 20Mar17 30Mar17 9 7 OnTarget
BATC1060 BA TestingandCommissioningofEarthingSystem 18 0.00% 0.00% 28Feb17 20Mar17 11Mar17 30Mar17 9 7 OnTarget
BATC1070 BA TestingandCommissioningofMCC's 24 0.00% 0.00% 21Feb17 20Mar17 4Mar17 30Mar17 9 7 OnTarget
LowCurrentSystems 24 0.00% 0.00% 27Feb17 30Mar17 1Mar17 2Apr17 2 2 OnTarget
BATC1180 BA TestFireAlarmSystem 24 0.00% 0.00% 12Feb17 11Mar17 22Feb17 21Mar17 9 8 OnTarget
BATC1190 BA TestCentralBatterySystem 18 0.00% 0.00% 19Feb17 11Mar17 1Mar17 21Mar17 9 8 OnTarget
BATC1200 BA TestStructuredCabling(data&telecom) 24 0.00% 0.00% 12Feb17 11Mar17 22Feb17 21Mar17 9 8 OnTarget
BATC1210 BA TestSMATV 18 0.00% 0.00% 19Feb17 11Mar17 1Mar17 21Mar17 9 8 OnTarget
BATC1220 BA TestVoiceEvacuationSystem 24 0.00% 0.00% 12Feb17 11Mar17 22Feb17 21Mar17 9 8 OnTarget
BATC1230 BA TestCCTVandAccessControlSystem 18 0.00% 0.00% 19Feb17 11Mar17 1Mar17 21Mar17 9 8 OnTarget
BATC1240 BA TestAudioVisualSystem 18 0.00% 0.00% 19Feb17 11Mar17 1Mar17 21Mar17 9 8 OnTarget
BATC1250 BA TestUPS 10 0.00% 0.00% 28Feb17 11Mar17 11Mar17 21Mar17 9 8 OnTarget
BATC1260 BA TestLightingControlSystem 18 0.00% 0.00% 19Feb17 11Mar17 1Mar17 21Mar17 9 8 OnTarget
BATC1270 BA TestGRMSSystem 24 0.00% 0.00% 12Feb17 11Mar17 22Feb17 21Mar17 9 8 OnTarget
FireFightingSystems 15 0.00% 0.00% 6Mar17 5Apr17 8Mar17 8Apr17 2 2 OnTarget
BATC1300 BA Testing&CommissioningofGasFireSuppressionSyste 15 0.00% 0.00% 21Feb17 9Mar17 4Mar17 20Mar17 9 6 OnTarget
BATC1310 BA Testing&CommissioningofFirePumps 10 0.00% 0.00% 27Feb17 9Mar17 9Mar17 20Mar17 9 6 OnTarget
BATC1320 BA Testing&CommissioningofFireFHC's 10 0.00% 0.00% 27Feb17 9Mar17 9Mar17 20Mar17 9 6 OnTarget
DrainageSystems 15 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 2 OnTarget
BATC1080 BA TestingandCommissioningofPumps 12 0.00% 0.00% 26Feb17 11Mar17 8Mar17 21Mar17 9 4 OnTarget
BATC1090 BA TestingandCommissioningofDrainageSystem 15 0.00% 0.00% 22Feb17 11Mar17 5Mar17 21Mar17 9 4 OnTarget
WaterSupplySystem 24 0.00% 0.00% 27Feb17 26Mar17 1Mar17 28Mar17 2 8 OnTarget
BATC1140 BA TestingandCommissioningofWaterTank 10 0.00% 0.00% 19Feb17 1Mar17 1Mar17 12Mar17 9 6 OnTarget
BATC1150 BA WaterSupplyFlushingandChlorination 10 0.00% 0.00% 19Feb17 1Mar17 1Mar17 12Mar17 9 6 OnTarget
BATC1160 BA TestingandCommissioningofPumps 12 0.00% 0.00% 16Feb17 1Mar17 27Feb17 12Mar17 9 6 OnTarget
BATC1170 BA TestingandCommissioningofWaterHeaters 24 0.00% 0.00% 2Feb17 1Mar17 13Feb17 12Mar17 9 6 OnTarget
HVACSystem 20 0.00% 0.00% 27Feb17 30Apr17 1Mar17 2May17 2 0 OnTarget
DelayAnalysisReportBasedonTargetProgram *DelayedActivitiesareHiglightedInRed DataDate: 29Dec16
VarianceBL
Original Schedule% Activity% BLProject BLProject Actual/Forecas Actual/Forecas Delayed/O
ActivityID Building Floor ActivityName ProjectFinish TotalFloat
Duration Complete Complete Start Finish tedStart tedFinish nTrack
Date
BATC1100 BA Testing&CommissioningofVRFSystem 20 0.00% 0.00% 21Feb17 15Mar17 4Mar17 26Mar17 9 6 OnTarget
BATC1110 BA DXUnitIndoor 10 0.00% 0.00% 5Mar17 15Mar17 15Mar17 26Mar17 9 6 OnTarget
BATC1120 BA DXUnitOutdoor 10 0.00% 0.00% 5Mar17 15Mar17 15Mar17 26Mar17 9 6 OnTarget
BATC1130 BA AirBalancing 20 0.00% 0.00% 21Feb17 15Mar17 4Mar17 26Mar17 9 6 OnTarget
BMSSystem 24 0.00% 0.00% 27Mar17 23Apr17 29Mar17 25Apr17 2 5 OnTarget
BATC1280 BA BMSSystemtTesting&Commissioning 24 0.00% 0.00% 23Feb17 22Mar17 6Mar17 2Apr17 9 6 OnTarget
LPGSystem 20 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 0 OnTarget
BATC1020 BA Testing&CommissioningofLPGSystem 20 0.00% 0.00% 12Feb17 6Mar17 22Feb17 16Mar17 9 5 OnTarget
BoilerSystem 10 0.00% 0.00% 10Apr17 23Apr17 12Apr17 25Apr17 2 0 OnTarget
BATC1290 BA Testing&CommissioningofBoilerSystem 10 0.00% 0.00% 19Feb17 1Mar17 1Mar17 12Mar17 9 6 OnTarget
AuthorityApproval 107 0.00% 0.00% 27Nov16 17May17 02Dec16A 18May17 1 1 OnTarget
Transformer&RMUworks(HVApprovals) 61 0.00% 0.00% 27Nov16 5Feb17 02Dec16A 23Jan17 11 37 OnTarget
BAAAMEP1640 BA Transformer/CableProcurement 12 100.00% 100.00% 27Nov16 10Dec16 26Nov16A 27Nov16A 12 0 OnTarget
BAAAMEP1650 BA Transformerinstallation&Connection 28 60.71% 100.00% 11Dec16 11Jan17 30Nov16A 30Nov16A 37 0 OnTarget
BAAAMEP1660 BA AuthorityApprovals 21 0.00% 0.00% 12Jan17 5Feb17 31Dec16 23Jan17 11 17 OnTarget
LVApproval 32 0.00% 0.00% 29Jan17 7Mar17 17Jan17 23Feb17 10 10 OnTarget
BAAAMEP1670 BA RequestforDEWAinspection 0 0.00% 0.00% 0Jan00 18Jan17 0Jan00 22Jan17 1 0 OnTarget
BAAAMEP1680 BA DEWA1stinspection 7 0.00% 0.00% 19Jan17 26Jan17 22Jan17 30Jan17 2 1 OnTarget
BAAAMEP1690 BA ClearDEWAsnag&applyforfinalinspection 6 0.00% 0.00% 28Jan17 2Feb17 30Jan17 6Feb17 2 1 OnTarget
BAAAMEP1700 BA Dewasecondinspection/Approval 7 0.00% 0.00% 4Feb17 11Feb17 6Feb17 14Feb17 2 1 OnTarget
BAAAMEP1710 BA Collection&installationofKWHmeters 12 0.00% 0.00% 12Feb17 25Feb17 14Feb17 28Feb17 2 1 OnTarget
BAAAMEP1720 BA TemporaryPermenetPower 0 0.00% 0.00% 0Jan00 25Feb17 0Jan00 28Feb17 2 1 OnTarget
WaterSupplyApproval 106 0.00% 0.00% 27Nov16 15May17 31Dec16 17May17 2 0 OnTarget
BAAAMEP1730 BA PaymentforWaterMeters 24 100.00% 10.00% 27Nov16 25Dec16 25Dec16A 24Jan17 26 8 Delayed
BAAAMEP1740 BA WaterMeterdelivery 36 11.11% 0.00% 26Dec16 5Feb17 24Jan17 7Mar17 26 8 Delayed
BAAAMEP1750 BA DEWAInspection 10 0.00% 0.00% 12Jan17 25Jan17 29Jan17 9Feb17 11 3 OnTarget
BAAAMEP1760 BA DewaApproval 10 0.00% 0.00% 26Jan17 6Feb17 11Feb17 21Feb17 13 4 OnTarget
BAAAMEP1770 BA InstalWaterMeter 6 0.00% 0.00% 7Feb17 13Feb17 7Mar17 14Mar17 25 8 OnTarget
BAAAMEP1780 BA Testing&Commisioning 12 0.00% 0.00% 2Mar17 15Mar17 14Mar17 28Mar17 11 8 OnTarget
BAAAMEP1790 BA ObtainNOCfromDEWAforWater 12 0.00% 0.00% 16Mar17 29Mar17 28Mar17 11Apr17 11 8 OnTarget
TelecomApproval 60 0.00% 0.00% 14Feb17 30Apr17 27Feb17 11May17 9 5 OnTarget
BAAAMEP1800 BA CompletionofTelecomroom 0 0.00% 0.00% 0Jan00 11Jan17 0Jan00 26Jan17 13 4 OnTarget
BAAAMEP1810 BA SubmitApplication 3 0.00% 0.00% 12Jan17 16Jan17 29Jan17 31Jan17 11 4 OnTarget
BAAAMEP1820 BA EtisalatInspection 10 0.00% 0.00% 17Jan17 30Jan17 1Feb17 14Feb17 11 4 OnTarget
BAAAMEP1830 BA CoordinationwithEtisalatContractor 12 0.00% 0.00% 31Jan17 13Feb17 15Feb17 28Feb17 13 5 OnTarget
BAAAMEP1840 BA Testing&Commisioning 12 0.00% 0.00% 14Feb17 27Feb17 1Mar17 14Mar17 13 5 OnTarget
BAAAMEP1850 BA Inspection&ApprovalbyEtisalat 12 0.00% 0.00% 28Feb17 13Mar17 15Mar17 28Mar17 13 5 OnTarget
BAAAMEP1860 BA ObtainNOCfromEtisalat 7 0.00% 0.00% 14Mar17 22Mar17 29Mar17 6Apr17 11 4 OnTarget
GSMApproval(Etisalat) 52 0.00% 0.00% 15Feb17 16Apr17 27Feb17 27Apr17 9 17 OnTarget
BAAAMEP1870 BA RequestforSiteSurvey 3 0.00% 0.00% 12Jan17 16Jan17 29Jan17 31Jan17 11 5 OnTarget
BAAAMEP1880 BA SiteSurveybyEtisalat(AfterStrCompletion) 10 0.00% 0.00% 17Jan17 28Jan17 1Feb17 12Feb17 13 6 OnTarget
BAAAMEP1890 BA CoordinationwithEtisalatContractor 12 0.00% 0.00% 29Jan17 11Feb17 13Feb17 26Feb17 13 6 OnTarget
BAAAMEP1900 BA Testing&Commisioning 12 0.00% 0.00% 14Feb17 27Feb17 1Mar17 14Mar17 13 4 OnTarget
BAAAMEP1910 BA FinalApprovalbyAuthority 10 0.00% 0.00% 28Feb17 11Mar17 15Mar17 26Mar17 13 6 OnTarget
BAAAMEP1920 BA ObtainNOCfromEtisalat 10 0.00% 0.00% 28Feb17 13Mar17 15Mar17 28Mar17 11 3 OnTarget
CivilDefence 45 0.00% 0.00% 5Mar17 16Apr17 8Mar17 19Apr17 3 20 OnTarget
BAAAMEP1930 BA RequestforDCDinspection 0 0.00% 0.00% 0Jan00 25Jan17 0Jan00 29Jan17 1 4 OnTarget
BAAAMEP1940 BA DCDInspection 10 0.00% 0.00% 26Jan17 8Feb17 29Jan17 12Feb17 1 4 OnTarget
BAAAMEP1950 BA ClearDCDsnags&requestfor2ndinspection 6 0.00% 0.00% 9Feb17 16Feb17 12Feb17 20Feb17 1 16 OnTarget
BAAAMEP1960 BA DCDsecondinspection 7 0.00% 0.00% 12Mar17 20Mar17 21Mar17 29Mar17 7 5 OnTarget
BAAAMEP1970 BA IssuanceofCivilDefensecertificate 7 0.00% 0.00% 21Mar17 29Mar17 30Mar17 9Apr17 7 5 OnTarget
CivilDefenceExternalFireHydrant 30 0.00% 0.00% 5Mar17 16Apr17 8Mar17 19Apr17 3 20 OnTarget
BAAAMEP1980 BA RequestforDCDinspection 0 0.00% 0.00% 0Jan00 25Jan17 0Jan00 29Jan17 1 16 OnTarget
BAAAMEP1990 BA DCDInspection 10 0.00% 0.00% 26Jan17 8Feb17 29Jan17 12Feb17 1 16 OnTarget
BAAAMEP2000 BA ClearDCDsnags&requestfor2ndinspection 6 0.00% 0.00% 9Feb17 16Feb17 12Feb17 20Feb17 1 16 OnTarget
BAAAMEP2010 BA DCDsecondinspection 7 0.00% 0.00% 19Feb17 27Feb17 20Feb17 1Mar17 1 16 OnTarget
BAAAMEP2020 BA IssuanceofCivilDefensecertificate 7 0.00% 0.00% 28Feb17 8Mar17 1Mar17 12Mar17 1 16 OnTarget
24X7DirectAlaram 46 0.00% 0.00% 20Mar17 11May17 23Mar17 16May17 4 1 OnTarget
BAAAMEP2030 BA SubmitApplication 3 0.00% 0.00% 15Jan17 17Jan17 17Jan17 22Jan17 2 15 OnTarget
BAAAMEP2040 BA InspectionbyAuthority 6 0.00% 0.00% 18Jan17 25Jan17 22Jan17 30Jan17 2 15 OnTarget
BAAAMEP2050 BA Releaseofestimate 6 0.00% 0.00% 26Jan17 1Feb17 30Jan17 6Feb17 3 18 OnTarget
BAAAMEP2060 BA Payment 6 0.00% 0.00% 2Feb17 8Feb17 6Feb17 13Feb17 3 18 OnTarget
BAAAMEP2070 BA PanelInstallation 12 0.00% 0.00% 9Feb17 22Feb17 13Feb17 27Feb17 3 18 OnTarget
BAAAMEP2080 BA ObtainNOC 10 0.00% 0.00% 23Feb17 8Mar17 27Feb17 13Mar17 2 15 OnTarget
LPG 30 0.00% 0.00% 5Apr17 15May17 9Apr17 17May17 2 0 OnTarget
BAAAMEP2090 BA RequestforLPGinspection 0 0.00% 0.00% 0Jan00 14Feb17 0Jan00 2Feb17 8 14 OnTarget
BAAAMEP2100 BA LPGInspection 6 0.00% 0.00% 15Feb17 22Feb17 5Feb17 12Feb17 8 14 OnTarget
BAAAMEP2110 BA ClearLPGsnags&requestfor2ndinspection 5 0.00% 0.00% 23Feb17 1Mar17 13Feb17 19Feb17 8 14 OnTarget
BAAAMEP2120 BA LPGsecondinspection 6 0.00% 0.00% 7Mar17 14Mar17 19Mar17 26Mar17 8 5 OnTarget
BAAAMEP2130 BA NOCfromAuthority 10 0.00% 0.00% 15Mar17 28Mar17 27Mar17 9Apr17 8 5 OnTarget
DubaiPolice 55 0.00% 0.00% 28Mar17 17May17 29Mar17 18May17 1 1 OnTarget
BAAAMEP2140 BA SubmitApplication 3 0.00% 0.00% 26Jan17 30Jan17 29Jan17 1Feb17 1 9 OnTarget
BAAAMEP2150 BA 1stInspectionbyAuthority 10 0.00% 0.00% 31Jan17 13Feb17 1Feb17 15Feb17 1 9 OnTarget
BAAAMEP2160 BA Commets&Rectification 7 0.00% 0.00% 14Feb17 21Feb17 15Feb17 23Feb17 1 11 OnTarget
BAAAMEP2170 BA FinalInspection&Approval 10 0.00% 0.00% 7Mar17 18Mar17 18Mar17 28Mar17 9 8 OnTarget
BAAAMEP2180 BA ObtainNOCfromDubaiPolice 10 0.00% 0.00% 19Mar17 30Mar17 29Mar17 11Apr17 8 7 OnTarget
DMApproval 43 0.00% 0.00% 20Mar17 17May17 22Mar17 18May17 1 1 OnTarget
BAAAMEP2190 BA Requestforinspection 3 0.00% 0.00% 9Feb17 13Feb17 12Feb17 15Feb17 1 4 OnTarget
BAAAMEP2200 BA EHSInspection 10 0.00% 0.00% 9Feb17 20Feb17 12Feb17 23Feb17 2 33 OnTarget
BAAAMEP2210 BA DMfirstinspection 10 0.00% 0.00% 14Feb17 27Feb17 15Feb17 1Mar17 1 4 OnTarget
BAAAMEP2220 BA DMCommentrectification 6 0.00% 0.00% 28Feb17 5Mar17 1Mar17 7Mar17 1 6 OnTarget
BAAAMEP2230 BA DMfinalinspection&Approval 10 0.00% 0.00% 12Mar17 23Mar17 21Mar17 3Apr17 7 6 OnTarget
BAAAMEP2240 BA FICconnection 6 0.00% 0.00% 25Mar17 30Mar17 4Apr17 10Apr17 9 7 OnTarget
BAAAMEP2250 BA StromWaterConnection 6 0.00% 0.00% 25Mar17 30Mar17 4Apr17 10Apr17 9 7 OnTarget
BAAAMEP2260 BA ObtainBuildingCompletionCertificate 0 0.00% 0.00% 0Jan00 30Mar17 0Jan00 11Apr17 10 8 OnTarget
ProjectCloseOut 68 0.00% 0.00% 1Apr17 31May17 2Apr17 1Jun17 1 1 OnTarget
BDPC1000 BD O&MManualSubmission 18 0.00% 0.00% 18Mar17 6Apr17 29Mar17 18Apr17 10 8 OnTarget
BDPC1010 BD O&MTaining 15 0.00% 0.00% 21Mar17 6Apr17 2Apr17 18Apr17 10 8 OnTarget
BDPC1030 BD AsBuiltDrawings 48 0.00% 0.00% 11Feb17 6Apr17 22Feb17 18Apr17 10 8 OnTarget
BDPC1040 BD Snagandcleaning/HandingOver 18 0.00% 0.00% 10Apr17 30Apr17 19Apr17 09May17* 8 8 OnTarget