Certificate Course On Piping Engg
Certificate Course On Piping Engg
-
.
May 11 -27,2005
May 25,2005
Dear Participant,
The thirty-sixth course is nearing completion and except for the few topics to be covered in the remaining
sessions, most core topics have been covered. Piping Engineering has a mind-boggling scope. When we started
off to design this course, there were quite a few who believed that such a course couldn't be designed'and
taught. We also had our doubts about the success that we would achieve when we set out to design what was
perhaps the first formal training programme in Piping Engineering, anywhere in the world. The rest is now
history. The course has not only been reasonably succtssful. it has led to a few other teaching institutions to
start similar programmes. Piping Engineering has become a 'teachable' subject. -
You people have come to this course with varied expectations. Your perceptions of what is central to piping
engineering and what is peripheral may have been diffaent fiom ours. It would be unreasonable on our part to
expect or claim that we have fulfilled all your expectations. But we made a sincere attempt. We would now like
you to spend some time this evening, although the test is staring you in your face, for the benefit of this course
and ponder over the last fifttca days. Please fill up the feedback form attached with this letta and return it
tomorrow, just before the commencement of the test You shall get your question papa in exchange of the filled
up feedback form. We attach a lot of importance to your opinion, constructive criticism and suggestions.
The consolidated opinion is conveyed to various speakers. If it is flattering, they feel encouraged. If it is not;
like good professionals; they would vow to do better given a chance next time. That is the way the course has
come to its present form and +at is the way it shall be.
So, considering it as your duty, give us your feedback. You need not mention your name on the form if you so
like. Names do not matter, opinions do.
.p.-Y*-. . . . . .
.
[ A. S. Moharir ] . .
.
Course Coordinator
Certificate Course
on
PIPING ENGINEERING
-
May 11 27,2005
. A
Organized by '
Friday,.20.05.2005"'
0730 : !OW
1030: 1300
1400 : 1630
1700 : 1930
.. ..
Practicals 1 Derxonmtjon
Flexibility .4nalysis (RIG)
Flexibility Andysis (Contd ...)
Practicals / Demonstntion
. :
. .
I All
1 ,411
I Ail
1
. .
CAW
Creativity Hall,ChE Dept
Creativity Hall, ChE
CADC
..
....
. . . ..
. .
-
. . . . .. . ..
'. . 1030':'I300 ' - : ':.PipeStrisses (ASM) All .: Creativity Hal\ Wt. ?:.;i:::.:. . . .
,:-' ' 1 4 0 0 f . 1 6 3 0 ' .. Nozzle Reinforcement (ASM) , . . . . . Creativity Hall, C ~ ~E ~ i -
:. ,;
:::i
i . . .
. . . .
. . . ' 1700 : 1930 . . ' . Practicals 7 Dems&ntion
. . . . ...
. . .
E . . CADC, cpc/R. NO..240, ChE-Dept. . . .
. . . . . ,. . . . . . . .
'
9
, '
..
'- '-07301'. 1000 \: -Practicals
.
. .:..
.-
. M . CADC, cpc/R. No;- 240, ChE. Dept.
All : Creativity-Hall, ChE Dcpt . .:..
k 1030 : 1300'::;;' Flexibility Analysis (Contd.:.)
-3. :
. 14m.,.. 1415'....: 'GroupPh&topPh.'
:. : ' : . . .
.:. . . . . . d l . . ... . .. .. . . . . . .. .
I
. . . .
..
. .
I . 1 . . . 1 . :.
.
. .. .. . . . . . . . .: . .
. . . . ....
- ..:
. : TUeSdOY, ;24,05.2'005
. . . . . . .. . . . .
' . '
. .
. . .
.
.,
. .
. . ...
.
.
. .. . . ..
.
.
.
.
. . .. . . . .. . .. . . . . ..
. . . . -
, . -
.
.. ...-
j . . : :.. .; . .
. . : . . . . . . \ .. .> . . .. .. . .
. . i
. . . . . . . *. ...... . . . . . . ...:.....
07.30 .
.. .. . . . .
.iooo :; meticals . : :
.. - - -.
. . . . .. . . . . . . . .
'M . . . CADC,
. .
N02240, &hE. Dept. . .
. .
. .. .
..
: . < : . - .
. .. .. .. ... ..... ...... . . :.. . ... ... . .. . . . . . .
:. >..
,
;
. . . . . .
i:.
. ... . . . .. . .. . . . . .. . .
.
- . . . . . . . . . .. . .. .
i . .
. . ,, ..... . . '
.. ..
....:. a - : .
. . . . .:..
:. i
.
' .
.073Q:looo::.. Case study .M . CFe&vityHd,.mDepi-. . . . . . . . . . . . . . . . . . . .
1030 : 1300' . ' . Cryogenic Systems V G h i All -: Dcpt .' . . '
'
Thursday, 26.05.2005 ., . . . . . .
. .- 1400
. . : 1615. . . .:
. .
. Quiz All Creativity.. Halt . ChE :;. Depl-118,
. . . . .
. . .
. Integrity Hall, ChE Dept-130, H d t y
Hall, ChE Dept-149- : - . .
' '
'
' 1700 : 1930 . Practicals, Journal Submission E ' .' . . CADC, cpc
. . . . . .
. . '... .
-
. .. .
. . . .
. . . . . . . . . . . .
. . . . .. .. . . .. . . . . . . . .
Friday, 2 27.05.2005~ . . . , . . . .......
. . . . . . . . . .
. . ;.: . . . . ..
. .. .
...
-
3 I
3 Certificate Course
I
9 on
1 PIPING ENGINEERING
9
0 I -
May 11 27,2005
INTRODUCTION
Prof. A. S. Moharir .
IlT Bombay
. -
Organized by
INTRODUCTION
About two decades . ago, in India, the In almost all chemical industries, the
design procedure for piping systems for installed capital cost of piping is a major
Refineries, Petrochemicals and Fertilizer factor in plant investment. Figs. 1 and
Plants, in magnitude, depth and 2 show a chart based on oil refineries,
complexities were not hlly evolved. Only chemical and petrochemical complexes.
in the recent past, we were exposed in Fig. 1 shows that, excluding major
detail to this field. Now we are self- equipment costs, piping is the largest plant
sufficient in the field of piping technology cost component. It exceeds the next
and design. largest component by a factor of two. It is
also observed h m Fig. 3 that piping
Piping systems in a chemical plant are exceeds all other field costs by a
comparable to the vanes and arteries substantial amount. Fig. 2 indicates &at
&ugh which fldds, vapors, slurries, design engineering utilizes approximately
solids, etc. flow under various conditions, 45% of engineering man-hours and 50%
as imposed by the process design 'of the of th'ese hours are used in piping design.
plant. Piping network is subjected to
almost all the sewerest conditions of the In addition to the above, the lost time in
plant such as high temperature, brissure, piping has au effect, which goes well.
flpw 'and combination of these. In beyond' its h t cast, as it involves
addition to the above, corrosion, erosion, financial loss in some pmportion to the
toxic conditions and radioactivity add to total plant inves.hnent. The delay in and
more problems and difficulties in piping during start up meam idle capital and
design. With the process conditions losses in plant earning capacity.
becoming more and more severe by the
advanccmcnt in process development, a
In the recent years, the &end is to develop
better techniques so as to save timt in
continuous e B r t is required to be carried
piping activities. Computer is being used
on simultaneously to cope .up with the
demands of process. This makes the job-of extensively to obtain rapid solutions to the
more complex problems of plant design
a piping engineer more complex and
and, in so for as piping is concerned, to
~ ~ i b l e .
. .
. . .. : . .
. . . . .. . .
.
.the solving of piioblems of pipe stressing.
,,Pip'& . , ; b h Cof .its m,rrq-
', '
Piping engineer requires not only wide sufficiently to discuss rationally, any
-
engheahg knowledge not necessarily particular subject with specialists
in depth, but certainly in understanding - concerned. More importantly, he must
but he must also have an understanding of have sufficient broad knowledge b h o w
engineering economics and costs, of that certain conditions can arise at the
metallurgy, of methods of pipe fabrication early stages of plant design, where lack of
and erection He must have some awareness can cause difficulties and even
knowledge of industrial chemistry and disasters.
chemical engineering in addition to a
sufficient knowledge of mechanical, civil, A fairly good knowledge of structural
electrical and instrument engineering so as engineering is a must. Piping in op&on
to discuss requirements and problems with is always in movement and subjected to
specialists in these fields. This will be pressure k d forces with consequent
more clear with the data piping reactions on mechanisms such as pumps,
department requires from other disciplines compressors and equipment ih general,
.-- as given in Annexure k He should be co- and on structures and related piping. .Lack
operative, able to communicate of knowledge can cause errors mflicient
effectively, lead or take part in teamwork, to cause machine or eqyiprnent
'
The size and scale of a company or design organization in a small office of say, ten
office do not change 'either the basic men, and a large company with hundreds .
piping design ~ ~ e n ort sthe of pipimg men, as indicated in Figs. 4 and
underlying design principles and practices. 5, but the job performed in both cases is
As the volume of piping design work and i d d d and has the same degree of
the number of projects executed relative importance to the whob project
increases, so also does the degree of design organization. The real
speciaIization increase. Functions such as diffz~encelies in rate of projects, passing
pip* layout, piping specifications, detail through the design office. In the small
drafting and material listing begin to ' office, the flow of projects is such that
emerge as separate departments within the each project is substantially completed
design office. There is little apparent before the succeeding project commences.
similarity between piping design This demands flexible organization of a
PIPING ENGINEERING CELL
small group, who have responsibility for In both cases, piping design is the most
all aspects of design: In the large lengthy and complex part of the whole
company, however, projects are much design procedure and almost always on
more Grequent. Thus the greater volume of the critical path of the project plan.
work handled by a large group makes a
high degree of specialization necessary for
economic and administrative reasons.
. 1
.
standardized methods of detailing and
&ta presentation.
3 Rapid data retrieval 1.
3 Standardization of engineering
Clarity
design methods for stressing,
material selection etc. .
i
b Much of the piping data is derived
fiom and used by other engineeting
3 Maxknum use of standards I
departments and must be clear, 3 Symbolic drawing procedures
consistent and reliable. I
I .
FIG. 1 . .
FIG. 2
PIPING ENGINEERING CELL
EII
Design Depts.
Piping layouts
Flow Sheet & Plant layout &
Piping Details
Process Data> E a ~ tlayout
.
Material List & Summary
Purchase Requisitions
v Fabrications
Utilities
Equipment
PIPING ENGINEERING CELL
PIPING SECTION
I 1
INPUTS TO PIPING
Data as per project design basis such as indicative
I
- 1.
OUTPUTS FROM PIPING
Overall plot plan showing location of various units,
I
Plot Plan, PFDs, P&XDs, FDS, Process Process tankfarms, offsite, package units, non-plant buildings, roads,
description, Equipment list, Line list, Site data, licensor culverts, piperacks, sleepers, etc.
etc. . . . .
. ,
. .
. ,
;.unitdoffsites , ,. . ., . . . . ..
. . .
.. . . . . .
3 Instr. cable tray size requirement on -- Instr.' 3. Equipment layouts (1 :200), (1:1OO), & (1 :50).
piperack/sleepers
4 Engineering data sheets of equipments like -- Mech. 4. TOG Elevations and loads with anchor bolt size, no., and
columns, vessels, tanks, etc. bolt locations for all equipment.
. . .
5 , . ~ n ~ data
. g . sheets, giving o v d dimensions, -- 5. GGeneralarrange&nt of piperack and equipment supports
. supporting m g e r n e n t with no. of anchor bolis. Process s,tructures
. .
including
.
loads.
. .
.. . :, ', . size, location and bolt circle dia.. All. nozzles
.
'
,
.
location, size, rating, etc.
. .
for hh'exchangers. .
. .
6 HVAC-ducting layouts preliminary and final. -- Utility 6. Piping general arrangement drgs. including platforms,
ladders, overhead cranes elevation, location, loads and
layout of monorail, cutouts, inserts and sleeves, required for
piping, etc.
.. 4
7 Layouts of various emuent & drain sewers and -- Civil 7. BOM & technical evaluation and technical bidding analysis.
location of manholes.
-- Civil
'
. . . . . .. . .
. .. . . . .
1 2 Overall f?undat'ion
.
layout.. . .
'.
. .
' .
.
. . ' ,
. -- Civil . ,12 Isometrics of piping including system ISOs
13 Platfixm drgs. and special pipe structure support -- Civil 13 Support drgs. of piping and special support details.
structure drgs.
i I
not necessarily be practical because for
fh MATORPHASES practicality, it is essential that the reaction
'i
'.
7 The major phases in the fife cycle of takes ,place at a suitable rate. Too fast
a c h d c a l process can be identified as: ,. .. reactions may lead to op&ation/control
I
4 1. Determination of Techno-aonomic problems while too slow reactions may
.> 's feasibility .
requke huge quipment to be able to process
2. . Design Phase commercial quantities. Means of
? '
.I,
ir - 3. Comtmc'iionPhase
, promoting/inhibiting reaction rates(catalysts)
>; ; . , .4. Commissionkig P k c srs ~ftcfirquircd. A major portion of
'-) 5. ~pmtibn/Produ~tion Phase . .. . ' . '
.li"EMIBILI[TY. . - --::
:
- .
. -.
. .
.- , .
-, . . .
. . .. . .
..
.
..
other units necessary to prepare feed for the
reactor or process output from the reactor.
.I,> ' . . ' Except perhaps hithe early days of., ' Once a chemical route which is
L
.
l . metallurgical industry, economic. gain has thermodynamically and kinetically feasible
)
. i
'
: been a.major .considerationin the choice and is chosen, a block flow diagram(BFD),
;i > ..
scale of .a production activity. Risk factor
and pollution considerations seem to be
'
.
'
which can be said to be the first engineering
diagram in the life cycle of a process, can be
d. :
,
)
.' i
gaining importa+e, but these are also due to prepared. It simply shows the operations that
CP economic considerations .
to. a large extent, are involved in the feed prepmtion section
1, ii
:..:+ . .
. .
1
1 -: . . . .
i I . ' . . . ,
PIPING ENGINEERING CELL 1
and product treatment section of a process total mass is obviously conserved in any
and the general sequence of events. The process including the chemical processes.
operations could be heat removal or addition, All operations in chemical processes wherein
. mixing or separation, purnpinglcompressing, the masses of individual components are also
etc. For a given scale of operation and conserved are termed as unit operations. This
estimated or expected performance levels of would necessitate that no chemical
the equipment to be later selected for these transformations take place during these
operations, one can put fust estimates of operations. Phase change, is however, not
stream characteristics such as flow rates, excluded. Pipe flow, pumping, compression,
composition, temperatures, pressure etc. on mixing, evaporation, distillation, extraction,
the BFD. With this, the process can be said etc. are unit operations in this sense.
to be born in two dimensions. The heart of any chemical process, a
The chemically feasible route is yet reactor, is however, an operation where the
to be tested for its technical and economic total mass is conserved but the species mass
viability. is not. Some or all the species undergo
,4t a broad level, a decision as to the chemical transformations. These are called
desirability of batch operation, continuous unit processes. For example, nitration,
operation or a combination has to be taken. oxidation, hydrogenation, chlorination,
Scale is an important issue here, but not the esterification are called unit processes.
only one. Some operations are inherently The. operations in a process as
batcwsemibatch in nature, e.g. adsorption. identified in the BFD may be carried out by
The poition of the flowsheet involving batch on< or more candidate unit operations. For
operation must operate in that mode. It can example, a component from a mixture may
suitably coexist with upstream/downstream be separated by distillation or crystallization
continuous operation through provision of or adsorption. Which choice is the best ( h m
suitably sized storage tanks which do the job economic point of view)? Is a parallel or
of isolating the batch operation section from series combination of alternatives a better
the continuous one. solution?
Some operations are feasible in batch Even after selecting the appropriate
as well as continuous mode but strict quality unit operation, one may have to converge on
control (absence of byproducts due to side the appropriate implementation strategies.
reactions etc.) or variations in feed/products For example, a four component mixture may
specifications etc. may tilt the scale in favour be separated by multiple distillation columns
of bztch operation. Foi !3c siuae scale oC iu several possibk ways. W'hichone of t h e
operation, batch process equipment result in options is the best for a given situation?
much larger process fluid inventory in the - . -... la -.case .of...reactors, choice. of -
plant at any time. If the fluids being handled equipment is equally important A fluid
are hazardous, it would mean that potential phase reaction, for example may be carried
hazards are higher in batch operation vis-A- out in a tubular reactor with or without
vis continuous operation. This aspect is recycle, a stirred pot or a combination. A
. assuming more and more importance in the reaction involving solid catalyst may be
emerging zero-risk scenario. carried out in a packet bed, moving bed,
Once tlic operations and the mode in basket type reactor, a flllidized bed reactor, a
which these are to be carried out are riser reactor, etc. Which one of these options
determined, the actual methods of achieving is the best for a given situation?
results of an operation are to be decided. The
i
PIPING ENGINEERING CELL
Plant cost and operating cost are two to carry out rigorous engineering
components to be considered in the choice of calculations for the chemical engineering
equipment. It is possible to pose the problem aspects as well as mechanical engineering
as an optimization problem (cost aspects and come out with rigorous
minimization), the solution of which gives documents (text, drawings) so that the
cost optimal flowsheet configuration. This implementation details can be passed on to -
phase of flowsheet development is called the subsequent phases in the life cycle.
Trocess Synthesis" and widely accepted It must be remembered that just as it
CAD tool in chemical engineering. is important to know what is happening
Mathematically, these are MILP (Mixed inside a particular piece of
Integer Linear Programming) or MINLP equipment(chernica1 engineering), it is
(Mixed Integer Non-Linear Programming) equally important to know whether the
problems. mechanical design and metallurgy of the
Selection of other pieces of confining vessel are adequate to allow this to
equipment such as pumps, reboilers, heat happen without risks to the other flowsheet
exchangers can be taken up at and components and to the external world. The -
considered as a part of process synthesis issues are inseparably involved and chemical
stage or postponed to a later stage. and mechanical engineering have to hand-
Chemical processes are generally in-hand. Unfortunately, that is normally not
energy intensive. With the rising energy cost, the case.
attention has recently turned to minimization The design phase has essentially two
of external energy requirement. These u e components; the process design and the
cooling water, steam, heating oil etc., the so mechanical design.
called utility steams. It is essential to Process is the detailed material and
minimize utility requirement by encouraging energy balance calculation across the process
as much process stream to process stream flowsheet. It would also establish the
heat transfer as possible within operational operating conditions, equipnents size(not
and layout constraints. These problems are necfessarily shape), utility requirements, ete.
also mathematically posed as MILP and With this idonnation appended to the BFD,
Ml.NL,P and are called as HEN (Heat one gets a Process Flow Diagrams(PFD).
Exchanger Network) Synthesis problem. For example, process design of a
With these process synthesis tasks distillation column would mean calculating
accomplished, conceptual design stage of the the number of trays, feed tray locations,
process is over. The equipxnt have been draw locati~ns,draw locations, condenser
selected and roughly their capacities are and reboiler duties, reflux ratio, etc. The heat
known. The capital cost and the operating exchanger process design would mean
,
equipment, high-low alarms and trips etc. To make sure that a batch or semi-
which may be required to be provided. batch operation can coexist with upstream -
. The PFD shows the flow rates, conditions may also call for intermediate
composition, temp-erature and pressure of all storage tanks.
feed, product and intermediate streams. The A PFD modified further to indicate
properties of these streams such as density stand-by equipment, storage tanks,
and velocity can therefore be calculated. instrumentation and control, pipe sizes,
Hydraulic calculations to decide the pressure valves, etc. becomes a P&ID. It may also -
drop due to flow fiom one unit to another show relative elevation of various
can be done at this stage. Pipe sizing which equipment, number of trays and feed tray
is a balance between operating cost (energy location in a distillation column, etc.
lost due to flow in pipes) and capital cost P & D is a very important schematic
(function of pipe diameter, thickness and during the design stage process. In fact this
pipe run) can be canied out. is what is stored and updated throughout the
The pressure drop correlation to be life of a process. It is considered as a
used depends on the nature of flowing cardinal drawing for various sections in a
medium: incompressible, compressible, design organization. It also is the basic
slurry, two-phase, three-phase, etc. drawing for subsequent equipment design,
Reasonably good correlation are plant layout, piping layout, bill of
available for calculating pressure drop for material(BOM), insulation calculations, etc.
single phase compressible or incompressible Project engineering literally begins with this
fluid flow. or t w ~ - ~ h &flow,
e correlations mother drawing in hand.
are available but their predictive power is Piping Engineer must be thoroughly
. doubhl. Possibility of various flow regimes, conversant with P&ID. Each organization
uncertainties regarding regime transition may have its own nomenclature and
boundaries and lack of datt make przdictian prxtices for making P&Ds. But the
flow hydraulics very difficult for two and differences are mostly in representation and
multiphase flow. All one can do is to use the *.
not in the Sonnation content.
best available correlation. U$ortunately, a P&ID also shows the other details of
large percentage of flow situations in the pipe lines such as material of
industry are atleast two-phase flows. construction, service, etc. The material of
The HAZOP findings, process construction can be decided based on the
requirement or the available reliability data fluid that a pipeline is supposed to carry and
may require a standby unit provision in the the temperature-pressure conditions. The
flowsheet. This is quite often the case with materials of construction for equipment
pumps. These call for appropriate piping similarly are service dependent.
also. Although a piping engineer begins
with P&ID, it would be desirable if he has
PIPING ENGINEERING CELL
some knowledge of the process background surface, which act as channels for leakage.
which led to P&ID. These channels need to be blocked by
At this stage, the capacity of each providing a softer material which is squeezed
equipment, the temperature- pressure that it between the two flanges so as to flow and
needs to withstand, the material of seal the irregularities on the flange surface.
construction, the inlet-outlet ports and their The gasket must flow but not be squeezed
sizes that need to be provided, the necessary out of flanges during bolting up conditions.
details of other intemals/externals(such as Also during operation, some of the bolt
trays in a distillation column, packing in an tension and pressure on gasket is reduced.
absorber, stirrer in a reactor, jacket around The gasket should still not leak.
kettle etc.) are available. The detailed The pressure vessel design would
mechanical design of each equipment involve calculating the shell wall thickness,
leading of fabrication drawing can be taken closure type selection and thickness
UP. calculations, selection of suitable gasket
The equipment design falls in the material with adequate yield stress and
area of pressure vessel design. The pressure gasket factor, choice of gasket location(mean
vessels are classified as fired and unired gasket diameter), gasket thichess, gasket
depending on whether they come in contact width, placement of bolts (bolt circle
with naked flame or not. Vessels subjected to diameter), bolt material selection, number of
inside pressure higher than the arnbient(eg. bolts, diameter of bolts etc. But this is not
vacuum service) are to be designed all.
'separately. There are separate design A vessel needs to have openings to
formulae for vessels subjected to internal and serve as inlet, outlet ports as well as for
external pressure. drainage, hand holes, man holes, etc. these
Typical vessel shapes ased in process could be on the shell or closures. The shell
industry are cylindrical and spherical. and closure wall thickness have been
Spherical shells are selficlosing while two designed to enswe that the stresses in the
ends of a cylindrical shell need to be closed walls even at the weakest ports (along
using closures of appropriate sbapes. welding, dong longitudinal seam or gizth
Depending on shell dimensions and service seam) do not cross the allowable stress value
conditions, the closures may be even aft61corrosion or inspite of nonudbrm
hemispherical, ellipsoidal, torrisperical, plate thickness (mill tolerance), etc. Whcb
conical or flat. openings are cut, stresses concentrate along
The ciosures need to be tightly fixed the edges of the opening and may exceed
to the shell, Flanges -are provided on the allowable stress value. Provision ef extra---
closure and the sheli for this purpose., thickness to counter this may be expensive.
Various .tyDes of flanges are possible and The theoretical finding that the stress
appropriate choice is important. Ingress of concentration is confined to a circle double
ambient air in the vessel or egress of inside the opening diameter is used to strengthen
fluid to the atmosphere must be avoided. the shell wall only in that region by welding
Apart from loss of material and/or off-spec a pad around the opening. The thickness
product, such a leakage could be hazardous. calculation of such a reinforcing pad is a part
If flange surfaces were pressed against each of pressure vessel calculation.
other, no matter how well they are machined, Not every opening need to be
the flanges would leak. This is so because of compensated. In the pressure vessels
the microscopic irregularities on the flange subjected to internal pressure, tensile stresses
are developed in the wall. In case of vessels thickness may have to amended to take care
subjected to external pressure, compressive of seismisity.
stresses are developed. The vessel wall It is assllmed that highest wind load
would have a tendency to buckle. To avoid and worst seismic effects do not occur
this, stiffening rings may be provided. simultaneously.
Spacing between stiffening rings and cross- The vibration period and deflection
section geometry of the stiffening ring are to of tall columns also need to be kept within
be designed using appropriate design tolerable limits. This can be done by
procedures. providing a suitably thick skirt.
Stiffening rings may be provided Eccentric loads on the column due to
externally or internally. Internal stiffening side connection also cause bending moment
rings may also be used as tray supports in at the skirt column connection and need to be
distillation columns, etc. considered.
Above design procedures may . After attention is paid to each and
normally be adequate for not so tall vessels. every aspect, a pressure vessel fabrication
For tall vessels which may most adequately drawing is issued for fabrication to begin at
be called towers, several other considerations an early stage. Equipment fabrication is time
come into picture. consuming. Also, in the field work,
Tougher distillations require lot of equipment need' to be in place quite early
trays in the column requiring to install very because only then the pipe routing job
tall columns. Tall column design is thus begins.
important. Pipe wall thickness design is
. ,- The wind velocities increase as one similarly carried out by treatin6 pipes as
goes away from ground level. A tall column cylindrical vessels. Flange calculations need
with its insulation, platforms and ladders not be done in the case of pipes as these are
.i provide obstruction to wind which i n turn provided by the codes in most cases. Once
.* -2 exerts force on the column. The column the nominal diameter and schedule of all
firmly supported at the skirt top bends as a pipes in a plant are known, a first bill of
result. This induces tensile stresses along the material for pipe length requirement can be
longitudinal seam on the leeward side. These prepared. This is even before the actual
additional stresses along with the stresses routing and isometrics are frozen. Additional
due to internal pressure should not cross the quantities can be procured once the 3-D
allowable value. This may have to be layout is finalized
ensured by provision of arlditiorlal shell wall In all the above calculations, design
thickness. The thickness requirement is pressure and design temperatun have to be
lowest at the top. To- minimize metal suitably chosen. For the equipment,
requirement, the tower may be divided into hydrostatic test pressures are .also to be
sections with the bottommost section having recommended.
highest thickness and the top just enough to With the completion of these
withstand internal pressure. calculations and the design documents: the
Tall tower design also needs to be design phase can be said to be over. The
checked for seismic effects which induce pipeline routing is however not yet decided.
additional stresses along longitudinal seam.
The seismic zone and the period of vibration' 3. CONSTRUCTION PHASE
decide the seismic coefficient. Wall Further analytical work needs to be
I
I
done before the final blue print of 3-D plant have to be laid out. It is not as simple as i
layout is finalized and construction begins. connecting the outlet of one equipment to the
Some of the activities given here may well inlet of the next in operational sequence by I
be considered as belonging to the design the shortest possible route. In fact, such I
phase itself. They are given here mainly direct connections are exceptional. And with
because,plant site details are a part of inputs reason! I
to the decision making. Most industrial hazards originate I
The choice of plant location, with failure of the piping system. The
if such a choice exists, is governed by I
equipment are fairly rigid and have strong
politico-socio-economic considerations. The foundation. During the cold assembly, all 1
basic approach is to assign weight factors to pieces are in place. When the operation
various considerations and to select a site
which scores maximum points.
begins, the high pressure temperature
conditions inside the equipment induce I
Knowing the site and its stresses and things literally move. Pipelines
neighborhood, a plant layout c a be worked I
being the most delicate elements in the plant,
out. Sites of the major equipment have to be bear the brunt of these operational loads, It is
decided on the site map. Apart firom the therefore essential that each pipeline routing,
I
equipment and offsites, other requirements especially the critical long ones, is properly
such as control room, fie station, hospital designed so that the pipe can sustain the
etc. are decided at this stage. The road map operational load. The load due to the weight I
of the site also emerges. Certain rules for of the fluid carrying pipe, vibrations in the
inter-unit distance which emerged fiom past equipment to which it is connected, thermal
experiences, certain guidelines for dusty, expansion etc. collectively and should not I
fire-prone, noisy, hazardous equipment lead to stresses in the pipe exceeding the
location are adhered to. allowable limitsoduringoperation.
A piping engineer is deeply . Weight analysis and stress analysis 1 :
involved in plant layout as it is one of the need to be carried out on pipeline. It may
most important factor which 'governs the lead to the requirement of rerouting the
piping layout and piping costs. pipeline, or provision of supports, hangars, I
influence on the piping layout, which is the details of the envisaged plant. It offers easy
next activity. visualization of Lbe plant structure. It allows
After the units have been located and checks on ergonomics. In conjunction with
r .
appropriately oriented on paper, the layout of stress analysis software, each pipeline can be
the veins and arteries of the plant, the pipes, checked for adequate flexibility and its route
I
PIPING ENGINEERING CELL
if called for. Details of civil structure can be Another reason why c~mrnissionin~
checked and corrected. Isometric drawings is tough is that the start-up conditions are
of each pipeline can' be derived from 3-D significantly different than steady state.
drawings with ease. Orthographic drawings conditions for which the plant has been
in different views can be created. designed.
The 3-D software model has all the Dynamic simulation is a good tool to
details of plant including actual pipe routing. evolve a good start-up policy. It is, however,
Bill of material for pipes and piping not used much of today. Start-up procedures
elements (pipe run,piping elements such a s for common unit operations such as
elbows, tees, specialties, flanges, valves etc.) distillation are fairly' well tested, though not
procured equipments (pumps etc.) can be necessarily optimal:
easily extracted. A piping engineer may be involved in
The progress of project star-up to take care of mechanical design
implementation can be monitored using 3-D problems that may crop up. Some process
drawings and field information. knowledge would be desirable.
Specification sheet for piping
elements can be prepared using a 3-D model. 5. NORMAL OPERATION PHASE
3-D model of the plant is complete The problems during the production
database and visual of the plant that would phase of plant are mostly operational if it
be. Its use would increase in coming years. has been designed well. The need to
The construction phase involves the debottleneck and optimize on throughput,
actual placement of equipment and routing however, calls for minor/major changes
pipelines. Welding and fabrication, painting involving installation of additional
for corrosion prevention, thermal insulation equipment or bypassing an existing
to prevent heat ingress or egress are the field equipment and related changes in pipe
activities that a piping engineer need to be routing. These changes may be trivial fiom
familiar with. process point of view but not necessarily
4. COMMISSIONING fiom the mechanical design implications
If the entire design has been done of view. A tritrially simple change may
scientifically, if design intentions are lead to stresses crossing failure limits and
reflected in various design documents causing disaster. A healthy operating
conectly, if fabrication, erecfion and practice would require a piping engineer to
assembly have been done as. per design be associated with any hardware change or
intai"Uons, then commis;ia&g which operaAhgpoint shift during productive piui
involves taking the cold-assembled plant to of the life cycle of a plant.
go on-stream and produce design capicity A piping engineer is also a
should be srnooth affair. This is normally not part of M O P team. He is also involved in
the case because lots of adhoc decisions need accident review.
to be taken on field during erection to take IN CONCLUSION.A PIPING
care of fabrication errors, iate or non- ENGMEER IS INYOLVED I A
delivery of items or design errors which are MAJOR PORTION OF THE LJFE
made at early stages of project engineering CYCLE OF A PROCESS. HIS
or even late second thoughts. The project is RESPOSIBILITIES AND SCOPE OF
normally on the critical path during field A CTNITIES MAKE THE
work and not all these decisions and their NOMENCLATURE "PIPING
implications are thoroughly probed. ENGINEER "A MISNOMER.
Certificate Course
PIPING ENGINEERING
-
May 11 27,2005
Consultant
Organized by
Practices are not always correctly understood. The following definitions are generally
accepted. .
CODE
A group of general rules or systematic procedures for design, fabrication,
installation and inspection prepared in such a manner that it can be adopted by legal
jurisdiction and made into law.
STANDARDS
Documents prepared by a professional group or committee who are believed to be
good and proper engineering practice and which contain mandatory requirements. The
users are responsible for the correct application of the same. CompIiance with a standard
does not itself confer immunity from legal obligation. .
RECOMMENDED PRACTICES
Documents prepared by professional group or committee indicating good
engineering practices but which are optional.
Each country has its own Codes and Standards. On global basis, American
National standards are undoubtedly the most widely used and compliance with those
requirements are accepted world over. In India, other than American standards, British
standards and Indian standards are also used for the design and selection of equipment
and piping systems. The major organizations for standards are;
The American Standards referred by Piping Engineers are mainly the standards by: I 4
i c:, 3
1.1 The American Petroleum Institute (API) 3
I '
(3
-
1:
I
1.3 The American National SLmdardsInstitute (ANSI) I ' 3
1.4 The American Society for Testing and Materials (ASTM).
. .
:-
\
2) MI6D - Pipe line Valves, End closures, Connectors and Swivels.
' I
3) API 6F - Recommended Practice for Fire Test for valves.
'r 4) API593 - Ductile Iron Plug Valves - flanged ends.
!
- . 'b&\dn%
API.609 - Butteffly valves
-
5) ASME B31.5 - Refrigeration Piping I '
Of the above, the most commonly used code is ASME B 3 1.3: Refineries and chemical
plants are designed based on the same. All power plants are designed as per ASME I ' --
B31.1.
*_.
SELECTION OF DESIGN CODE I .
.r
1
Unless agreement is specifically made between the contracting parties to use another I.
5
issue or the regulatory body having jurisdiction imposes the use of another issue, the < \'
. .
. 'j :
,
latest edition and addenda issued 6 monthsprior .to the original contract date,will h ~. l .d ., . .
.
, . .. . :. . .-
go&i for the first phase of the completion of work and h i t i d opirntion.
. . . . J ...-,
. :!
... $ .
. .
. . :.:. . . . . . . . ' ?
. .
1 .
f
It is the responsibility i f the user to seleci the code, Section,. which most nearl'yapplie3
.
.
. .. . to . .
. . :
. .
supplementary to those of the Code if necessary to assure safe piping for the proposed
I installation.
-1
9 When no section of the Code specifically covers proposed installation, the user has the
discretion to select any section determined to be'generally applicable. However, it i s
-3 / cautioned that supplementary requirements to the section chosen may be necessary t o
, x provide for safe piping system for the intended application.
/
The Code sets forth engineering requirements deemed necessary for the safe design and
construction of pressure piping. While safety is the basic consideration, this factor aione
will not necessarily govern the final specification for any piping installation.
The Code prohibits designs and practices h o r n to be unsafe and contains warnings
-%
, where caution, but not prohibition., is warranted. The designer is cautioned that the
. J I
Code is not a design handbook; it does not do away with the need for the engineer or
9 ) competent engineering judgement.
Other major ANSI I ASME dimensional standards referred for the piping elements are:
. .
Codes and Standards . . .
PIPING ENGINEERING CELL
14) ASME B 16.34 - Steel Valves, flanged and butt weldbg ends.
18) ASME B 18.2 1 & 2 - Square and hexagonal head Bolts and Nuts -
(in & mm)
In Part-II, the materials are listed in the Index based on the available forms such as plates,
castings, tubes, etc. and also on the numerical index.
The selection of S T M specification depends upon the type of manufacture, form
of material, its mechanic$ strength and the corrosion properties.
The specification number is given on Alphabetical prefix, 'Ai for Ferrous materials
and 'B' for Non-ferrous materials.
ASTM also specifies standard practice for numbering metal and all;$ as Unified
N-mb&g System.
A
1
Codes and Standards 6 I .
---
..
I '
PIPING ENGINEERING CELL
The UNS provides means of correlating many naturally used numbering systems
currently administered by Societies, trade associations, individual users and producers of
metals and alloys, thereby av&ding confusion caused by use of more than one
identification number for the same material and by the opposite situation of having the
same number assigned to two different materials.
UNS establishes 18 series numbers of metals and alloys. Each UNS number
consists of a single letter prefix followed by five digits. In most cases the alphabet is
suggestive of the family of the metal identified.
. . . .
1. ~ 0 0 0 0 1 A
- 99999 - ~ l k i n i u r nand ~lumi'niurnalloys
3. EOOOOl - E 99999 - Rare earth and rare earth like metals and
alloys
- Low melting metals and alloys
- Miscellaheous nonferrous metals and alloys
- Nickel and Nickel alloys
Stainless Steels
- Tool Steels
I
1.5 AWS STANDARDS
The American Welding Society (AWS) standards provide information on welding
hndamentals; weld design, welders' training qualification, testing and inspection of !
welds and guidance on the application and use of welds. Individual electrode
manufacturers have given their own brand names for the various electrodes and are sold
h d e r these names. I
4) C-507
. . - . . Ball valves 6'" - 48" . . 11
1) MSS-SP-6 - ~tandard~inishes
for Contact Surface for Flanges ,
. .
2) MSS-SP-25 - Standard Marking System for Valves, Fittings I
Flanges
a'
14) MSS-SP-78 Cast Iron Plug Valves
.
fB
4
I
15) MSS-SP-80 - Bronze Gate, Globe and heckv valves . .
: )
20) MSS-SP-89 - Pipe Hangers and Supports: Fabrication and
installation practices.
:I .
b'
3 21) MSS-SP-90 - Pipe Hangers and Supports: Guidelines on
," i terminology
- k I
i
2.0 BRITISH STANDPLRDS I
Accordingly lot of BS and DIN standards are getting replaced by CEN standards. I
\ -
There are certain British Standards referred by Indian Manufacturers for the
construction of piping elements such as valves. The most commonly referred British
I' *-.
. . i ,
I :
4) BS 970 - . Steel for forging, bars, rods, valve steel, etc.
1
f-
.z >
.
9) BS 1600 - Dimensions of Steel Pipes '
I ,' c. -.
,
1
- .-.
L < 4
- ,
-., i
11) BS 1868 - Steel Check Valves for Petroleum Industry I
-3
,-?
zL:
1
12) BS 1873 . . .
- . . . Steel Globe & Check Valves for Petroleum Industry . . I :
., i
<I
.
. .
.. . . ..
. . . .
. . -
13) BS 1965 . . - Butt welding pipe fittings ; .
. . . .
. .
. .
. . .
. .
.
. . ,'
. .
.
-;.,..;, 1
. -. 4.
. . .. .
. . . .. . . . . , . . . . . .
.' I -
14) BS2080 '.,.... .' - ' . .. F& t o .~ a c IeEnd t o ~ n d d i m k s i o n of
. s Valves. . . . '
, '. ' ..
: : -.:.
. . - - ,(obsolescent) . . - .. .
. .
, '
I
;
-1 ...,'
. . . . . . . '1 I
15) BS 2598 - Glass Pipelines and Fittings
i
16) BS 3059 - Boiler and Super Heater tubes i '
I
17) BS 3063 - Dimensions of Gaskets for pipe flanges
' (obsolescent)
. .
21) BS 3601 C.S. Pipes & Tubes for pressure purposes at room
temperature
:> ? \
J
! 31) BS5t51 -
Purposes
>:
i*
!
ii
33) BS 5153
34) BS5154
- CI Check valves for generalp-oses.
T=S
Copper alloy Gate, Globe, Check valves
)
I 35) BS 5156 Diaphragm valves for general purposes
l- L
Testing of valves
i
- Dimensions of Pipe Threads
- Plain Washers
i
27) ,IS 4038 Specification for Foot Valves
- I -.
39) IS 6630 Seamless Alloy Steel Pipes,for high temperature
services I ' -. -
% , r
40) IS 6913 - Stainless steel tubes for food and beverage industry
!
.
,
4
!
.J
There are certain other international standards also referred in the piping industry. They
are the DM standards of Gemany and the nSC standards of Japan. DIN standards are
more popular and equivalent British and Indian standards are also available for certain
piping elements.
Periodic review of the standards by the committee is held and these arc revised to
incorporate the modified features based on the results of research and feedback from the
industry. Although some technological lags are unavoidable, these are kept minimum by
those updations. Hence, it is necessary that the latest editions of the codes and standards
are referred for the design and year of publication also to be indicated along with.
f-
I
I..
i
T. N. Gopinath
Consultant
Organized by
PIPING ELEMENTS
T. N. GOPINATH
Piping Elements
PIPING ENGINEERING CELL
Piping Elmmu
PIPING ENGINEEFUNG CELL
recommendations from the Process lined piping systems, the thickness of pipe
Licensor to be followed. and/or lining are not covered under any of
the above standards. These are as per the
1.0 PIPES relevant ASTM standards. For certain
1.1 General plastic pipes, Indian Standards am also
available.
Pipe can be defmed as a pressure tight
cylindcr used to convey a fluid.
The word "pipe" is used as distinguished
from "tube" to apply to tubular products of
dimensions commonly used for piping
systems. Tht pipe dimensions of sizes 12
inch (300 mm) and smalkr have outside
diameter numerically larger than
corresponding sizes, In contrast, the
Piping Elements . . .
PIPING ENGINEERING CELL
114
318
8
10
0.540
0.675
13.7
17.1
j .
-
2 50 2.375 60.3
*2% 65 2.875 73.0 ,I .
3 80 3.500 88.9 I -
Y.)
steeI pipes. B.
mm) NB. This thickness is specified for pipe I ' -
Stainless steel pipes are available in
schedule 5s. 10s. 40s and 80s w h e m up to 12 inch (300 mrn) NB. For 12 inch - -3
(300 -1 hethichcJJ
- match*, to mat
carbon steel pipes are available in schedule ! P-
.J
P i p a Elements 4 I '
. -
. -
I
Ii -
PIPING ENGINEERING CELL
Fj i match except in the followings: to pipe andlor pipe to fittings joints are done
by threaded connections.
-. 10" SCH80lSCH80S Flanged ends are specified to
.3 1 12" SCH~OISCH~OS provide bolted connections between pipes
",i 12" SCH80lSCH80S and between pipes andlor fittings.
I 14" SCHlOISCHlOS Spigot/ Socket ends are specified when -
? i -1 16" SCHlOISCHlOS
lead caulked/cemented joints are provided
between pipes and between pipes and
3 I
18" SCHlOISCHlOS fittings.
,
J
%
; backing flanges.
' 1
1 In Indian Standard IS 1239s the 1.4.1 BUIT WELD PIPE JOINTS
3' thicknesses of pipes are specified as Light,
I Medium and Heavy. The medium and
f
':
: heavy pipes are only used for f l ~ handling.
d
In IS 3589, the thicknesses are specified in
)i
)
[ actual dimensions in rnm.
As regards the non-metallic and
lined piping systems, the thickness of pipe
7 1 and/or lining are not covered under any of
-9 f the above standards. These are as per fhe
1
.-
< ) r j relevant ASTM standards. For certain plastic
pipes, Indian Standards are also available. Advantages
)
3 The pipes are available in standard a) Most practical way of joining big bore
) - lengths of 20 feet (6 m). piping
=
-=,
;5
I
, - b) Reliable leak proof joint
c) Joint can be radiographed
-
I 1
9 1.4 Pipe Ends
-?, i
i
Based On the matel"kl of ~ 0 n ~ t r U ~ t and
i0n
the pipe to pipe joint, the ends of the pipes
Disadvantages
1 ' a) . Weld i n m i o n will affect flow
.
\ I
are specified as follows. b) End preparation is necessary
Beveled ends
Plain ends
Screwid ends
Flanged ends
Spigot/Socket ends
Piping Elements
PIPING ENGINEERING CELL
1.4.2 SOCKET WELD PIPE JOINTS e) Code specifies that seal welding shall
not be considered to contribute for
EXPANSIONJOINT strength of joint
TO PRNENT WELD
FROM CRACKING UNDER
THERMAL STRESS 1.4.4 FLANGED PIPE J O N I S
CH.160
Advantages
a) Easier Alignment than butt welding
b) No weld metal intrusion into bore
Disadvantages
a) The 1/16"(1.5 rnm) recess pockets Advantages
liquid a) Can be easily made at site
b) Use not permitted by code if Severe b) Can be used where welding is not
Erosion or Crevice Corrosion is permitted due to material properties or
anticipated. fire hazard.
*, r
c) Dismantling is very easy
1.4.3 SCREWED PIPE JOINTS
t
Disadvantages
THREAD ENGAGEMENT' a) It is a point of potential leakage
b) Cannot be used when piping is
subjected to high bending moment.
Advantages
a) Easily made at site
b) Can be used where welding is not
permitted due to fire hazard Advantages
. .
a) Can be easily made at site.
Disadvantages
b) Can accept misalignment upto 100 at
a) Joint may leak when not properly pipe joints.
sealed
b) Use not permitted by code if severe
erosion, crevice corrosion, shock or Disadvantages
vibration are anticipated. a) Suitable for low pressure application
c) Skength of pipe is reduced as b) Special configuration at pipe ends
reduce wall thickness
d) Seal welding may be required required.
Piping Elements 6
i
I PIPING ENGINEERING CELL
1
i 1.4.6 BUTTRESS END PIPE JOINTS e) Spiral Welded
Pipes having helical seam with
- -+;
either a butt, lap, lock-seam joint which is '
? 1 welded using either an electric resistance,
electric hsion or double submerged arc
-,
I
welding process.
1.5.2 Seamless
Pipes produced by piercing a billet
followed by rolling or drawing or both.
Used only for glass piping and not capable The most commonly used material
'-'
to hold high pressure. standards for the pipes are listed below:
1
1.5 Types Of Pipes
1.6 Pipe Materials
Based on the method of manufacture pipes
1. ASTM A 53 Welded and Seamless
could be classified as
Steel Pipe, Black and
'
1.5.1 Welded
Galvanized
a) Electric Resistance Welded (ERW)
2. ASTM A106 Seamless CS Pipe for
Pipes having longitudinal butt joint High Temp. Services
wherein coalescence is produced by the heat
3. ASTh4 A120 Black and Hot Dipped
'
obtained h m resistance of the pipe to flow
Zinc coated
of electric current in a circuit of which the (Galvanized) welded
pipe is a part, and by application of pressure.
and seamless pipe for
b) Furnace Butt Welded, Continuous ordinary use
Welded 4. ASTM A134 Electric h i o n welded
Pipes having longitudinal weld
steel plate pipe
joints forge welded by mechanical pressure
(Sizes 1 16"NB)
developed in passing the hot-formed and
5. ASTM A135 Electric resistance
edge-heated skelp through round pass weld
welded pipe
rolls.
6. ASTh4 A155 Electric fusion welded
c) Electric Fusion Welded (EFW)
s-1 pipe for high
Pipes having longitudinal butt joint
wherein coalescence is produced in the temperature service
preformed tube by manual or automatic
7. ASTM A312 Seamless and welded
gusfcnitic stainless sfeel
electric arc welding. Weld may be single or
double.
- pi?=
8. ASTM A333 Seamless and welded
d) Double Submerged-Arc Welded
steel pipe for low
Pipes having longitudinal butt joint
produced by at least two passes, one of temperature service
9. ASTM A335 Seamless ferritic alloy
which is on the inside of the pipe.
steel pipe for high
Coalescence is produced by heating with an
temperature service
electric arc or arcs between the bare metal
10. ASTM A358 Electric h i o n welded
electrode or electrodes and the pipe.
austenitic chrome-
Pressure is not used and filler material is
nickel steel pipe for
obtained fi-om electrode.
Piping Elements
PIPING ENGINEERING CELL I
high , temperature 22. ASTM A672 Electric fusion welded
service steel pipe for high
11. ASTM. A369 Carbon and fenitic pressure service at
.
alloy steel forged and moderate temperature
bored for high services
temperature service (Sizes 2 16" NB)
12. ASTM A376 Seamless austenitic 23. ASTM A691 Carbon and aIloy steel
steel pipe for high pipe, electric h i o n
temperature central welded for high
station service pressure service at high
A409 Welded large diameter temperatures
austenitic steel pipe for (Sizes 2 16" NB)
corrosive or high 24. ASTM A731 Seamless and welded
temperature service ferritic stainless steel
A426 Centrifugally cast pipe
ferritic alloy steel pipe 25. ASTM A790 Seamless and. welded
for high temperature ferritid austenitic
service stairrless steel pipe
15. ASTM A430 Austenitic steel forged 26. ASTM A813 Single or double welded
and bored pipe for high austenitic stainless steel
tempsrature service P~PC
16.' ASTM A45 1 Centrifugally cast 27. ASTM A8 14 . Cold worked welded
austenitic steel pipe for austenitic stainless steel
high temperature pipe
service 28. ASTM F1545 Plastic Lined Ferrous
17. ASTM A452 Centrifugally cast Pipe
austenitic steel cold 29. API 5L Line pipe
wrought pipe for high 30. IS 1239 Steel pipes for general
temperature service PWs=
(Sizes< 6" NB)
18. ASTM A524 Seamless carbon steel 31. IS 1536 C e n ~ g a l l ycast iron
pipe for atmosphen~ P~PC
and low temperature 32. IS 1537 Vertically cast iron pipe
services 33. IS 1978 Line pipe
19. ASTM A587 Electric welded low 34. -IS 1979 High test line pipe - -
carbon steel pipe for the 35. IS 3589 Steel pipe for general
chemical industry senrices
20. ASTM A660 Centrifugally cast 36. IS 4984 HDPE pipe for water
carbon steel pipe for service
high temperature 37. IS 4985 PVC pipe
senrice
21. ASTM A67 1 Electric fusion welded
steel pipe for
atmospheric and low
temperature service
(Sizes2 16" NB)
Piping Elements
I
PIPING ENGINEERING CELL
Piping Elements
PIPING ENGINEERING CELL
Consider, L
-= 50
Do.
since L is unspecified.
schedule. -
Refer ASME Section VIII Div. 1. UG 28 - ...=.
'~ll.owablePressure;.. .. .' . .
4x'550(- : . ' .
. .
Assume value of 't' and determine ratios Pa =
. . . .
= . 4 1 .9 p s i g : - . . , .
_
.
L Do 3x173 :
- and - .
',
Piping Elements
PIPING ENGINEERING CELL
Piping Elements
PIPING ENGINEERING CELL
Piping Elements 12
PIPING ENGINEERING CELL
Piping Elements
PIPING ENGINEERING CELL
2.1.3 FLANGED END FITTINGS or to branch off from main run of pipe. The
Fittings with both ends flanged are used special features of these are as below.
where welding is not possible or not
~ermitted. Normally these are made by 2.2.1 ELBOWS
casting. Classification of these fittings, Elbows are used to make 90 deg. or 45
based on the pressure temperature ratinzs, is deg. changes in the direction of run pipe.
same as that of flanges. There are two types of 90 deg. butt-welding
Flanged fittings fabricated from elbows available for use. These are the
standard butt-welded or socket welded long radius and short radius elbows. The
fittings are not covered under this standard. long radius elbows have a bend radius of
The material specification is the same as that 1.5D, where D is the nominal size, whereas
for castings. the short radius elbows have a bend radius
FLANGED END FITTING of ID. The 45 deg. elbows are of 1.5D
MATERIALS radius. Any bend with more than 1.5D
1. ASTM A 216 - Carbon Steel Castings bending radius has to be specially made as
2. ASTM A 351 - Stainless Steel Castings per requirements. For large diameter piping,
3. ASTM A 352 - Alloy Steel Castings bends are fabricated by profile cutting of
4. ASTM F 1545 - Plastic Lined Fittings pipes and are called mitre bends. Mitre
5.1s 1538 - C I Fittings bends with two piece, three piece or four
These fittings are covered under ASME B piece cocstruction can be made. These are
16.5 and BS 1650 for carbon and alloy steel normally not used in critical services. 22.5
piping and ASME B 16.1 for cast iron deg. elbows are also available in cast iron
fittings. B
construction. .\ 6 4
Piping Elements 14
, . PIPING ENGINEERING CELL
I
I
Fig. 2.4: Elbows - 45'
Piping Elements
PIPING ENGINEERING CELL
2.2.2 RETURNS
Returns change the direction through
180 deg. This is mainly used in heating
coils, heat exchangers, etc. Returns with
1.5Dradius and 1D radius are available.
... . . . . .
Piping Elements
PIPING ENGINEERING CELL
PP
1 ' J :
with slip-on flanges. Designer selects stub
d (longlshort) ensuring the weld of pipe to
.Ir,
%,-
-
, stub end not get covered by flange. When
Class A stub ends are used, the inner
)>.
.,, diameter of backing flange is chamfered for
). better seating.
,A I
The minimum lap thickness should Fig. 2.18: Half - Coupling
1 ' be the same as that of the pipe wall. When
<
1, i special facings such as tongue and groove, Full couplings are used to connect small
.- a male and female etc. are employed
bore pipes as projection of welding inside
) additional lap thickness shall be provided.
-, the pipe bore, when butt welding is used,
The gasket face finish shall be provided with
.
,-I I serrations as required. ASME B 16.9
reduce the flow area. Half couplings are
. used for branch connections and reducing
1 couplings for size reduction. Reducing
)
.-'
1
f Piping Eleraents
i
PIPING ENGINEERING CELL
couplings maintain the pipe centerlines same Unions can be with threaded end or with
and eccentric swage nipples are used to
' socket weld ends. There are three pieces in
maintain the outside surface same for such a union, two end pieces to attach to the run
systems. pipe and the third threaded piece to connect
these two. The ball type metal seating ensure
2.2.8 SWAGE NIPPLES sealing.
Swage Nippies are like reducers but are
used to connect butt welded pipe to smaller
screwed or socket welded pipe. There are
two types of swage nipples, tlre concentric
and the eccentric. Various conlbinations of
end connections are possible in swage
nipples. These are designated as
-
PBE Plain Both Ends
PLE - Plain Large End
-
PSE Plain Small End
-
BLE Beveled Large End
-
TSE Threaded Small End
'ig. 2.21: Union
These are covered under the regulatory Code . .
BS 3799.
2.2.10 SPECIAL FITTINGS
The items referred under special fittings are;
* Weldolet
* Sockolet
* Threadolet
* Elbolet
* Sweepolet
* Nipolet
* Latmlet
Fig, 2.19: Concentric Swage Nipple
I
-1
.
%>
$
I ..
Fig. 2.20: Eccentric Swage Nipple B
A I %
2.2.9 UNIONS
Unions are used in low pressure piping Fig. 2.24: Sockolet Fig. 2.25: Thredolet
where dismantling of the pipe is required
more often, as an alternative to flanges.
Piping Elements
1
PIPING ENGINEERING CELL
*.,
I
'->.
i Fig. 2.26: Latrolet Fig. 2.27: Elbolet
r* 1
5 ;
r ,
I ...
1
13 ' . ,
."\ I .
'Fig. 3.1 .: Slip-on Raised,Face Flange
I
?>.
'; i
-;
>
I
.
connection. Latrolet is used for branch
connection at an angle. .
3.0 FLANGES
123
3 : ) Flanges are used when the joint needs
dismantling. These are used mainly at
?
;3
I
4
equipmcnts, valves and specialties. In .
.
.
. . . . . .
'i
-.>
certain pipelines where maintenance is a
regular feature, breakout flanges are
Fig. 3.4: Lap Joint Flange with;-tub
. ..
.
End.
. .
.
. .
Piping Elements
I
PTPINC ENGINEER1 NG CELL
,I 3.2.6 1500 #
3.2.7 2500 #
i Pressure temperature rating charts, in
the standard ASME B 16.5, specify the non-
3 shock working gauge pressure to which the
i Fig. 39: Raised Face
-2
> flange can be subjected to at a particular
I temperature. The indicated pressure class of
B 15W,3 W , etc. are the basic ratings and the
'h flanges . can withstand higher pressures at
P I lower temperatures. ASME B 16.5 indicates
h
i
the allowable pressures for various materials
1
/"
I
-
. of construction vis a -vis the temperature.
\
1
Piping Elements 21
PIPIXG ENGINEERING CELL
Piping Elements
PIPING ENGINEERIISG CELL
For high temperature and high-pressure are used otherwise. Normally, the bolts are
applications, spiral wound metallic gaskets provided with hexagonal head, hexagonal
are used. The selection of material of nut and a round washer. Studs are provided
construction for winding depends upon the with two hexagonal nuts and two washers.
corrosive nature and concentration of the The length of boltdstuds required for the
fluid, the operating temperature and the flange joints of all pressure classes are
relative cost of alternate winding materials. specified in ASME B16.5.
The most commonly used are the Austenitic Flanged joints using low strength
stainless steel 304; 316 and 321 with carbon steel bolts shall not be used above
Asbestos filler. For very high temperatures, 200 OC or below -29 OC
graphite filler is also used. Alternate ASTM F-704 specifies the standard
winding materials also can be used practice of selecting bolt lengths for piping
depending upon the services. system-flanged joints.
ASME B 16.5 does not recommend
the use of 150# rating spiral wound 5.1 Material Of Construction For Bolting
gaskets on flanges other than welding Bolting materials normally used are:
neck and lapped joint type. 5.1.1 ASTM A 307 -Low Carbon Steel
Spiral wound gaskets are provided with Bolting Material
carbon steel external ring known as 5.1.2 ASTM A 320 -Alloy Steel Bolting
centering ring to position the gasket. When material
used in vacuum services, an internal ring is 5.1.3 ASTM A 563 - Carbon and alloy
also provided. The material of inner ring steel nuts
should be compatible with the fluid. The 5.1.4 ASTM A193 - Alloy Steel Bolting
spiral wound gasket will perform when the Material for high
flange face is 125-250 AARH finish. temperature service
5.1.5 ASTAMA 194 - Alloy Steel nut
4.4 Dimensional Standards material for high
Gasket dimensions are covered under temperature service
the following standards. 5.1.6 IS 1367 - Threaded steel
4.4.1 API 601 fasteners
- Metallic Gasket for Refinery Piping
4.4.2 BS 3381 5.2 D i m e n s i ~ n dStandards For Bolts
- Metallic Spiral Wound Gaskets The dimensional standards referred for
4.4.3 ANSI B 16.20 the studdbolts are:
- Metallic Gaskets for pipe flanges flanges
4.4.4 ANSI B 16.21 -
5.2.1 ANSI B 18.2.1 Square & HexagonaI
- Won-metallic Gaskets for pipe head bolts
flanges. -
5.2.2 ANSI B 18.2.2 Square & Hexagonal
. . nuts
5.0 BOLTING. . ' , 5.2.3 BS 916 - Black bolts & nuts
5.2.4 IS 1367 - Threaded steel
Depending upon the service, its fasteners.
prcssure/temperature and the type of gasket,
type of bolting is selected.
For low pressure, low temperature
services, machined bolts are used and studs
Piping Elements
PIPING ENGINEERING CELL
prefixed with the Alphabet 'B'. The use of gasket is not recomrncnded
Due to economic considerations either in piping Lined with resilient materials, but
carbon steel flanges with lininghonding of this can damage the lining restricting the
these materials or Lap joint backing flanges reuse.
wherever possible are used in this piping. .- The requirement of lined pipes has to be
studied case by case based on the service
7.0 NON-METALLIC AiiD LINED conditions.
PIPING The glass pipes & fittings have either
Non-metallic piping is used where the buttress end or beaded ends 'and are
problem of: corrosion is severe and it is connected with flange assembly.
difficult to get a suitable economical
metallic piping. Temperature limitations 8.0 PIPING SPECIFICATION 1
restrict the use of these non-metallic piping. PIPING CLASS
The commonly used materials are: A document indigiting the dimensional
ABS - Acrylonitrile-Butadiene-Styrene
and material specificatiok of pipes, fittings
-
CPVC Chlorinated Polyvinyl Chloride type is called a PIPING CLASS.
-
ETFE Ethylene Tetrafluoroethylene - - - - -& -~ valve
d
Each class represents &tinct features such
FEP - Fluoro Ethylene propylene
as p r e s s ~ e - t e m p e r a ~ e conditions,
-
FRP Fibreglass Reinforced Plastic corrosion resistance and strength abilities or
-
HDPE High Density Polyethylene a combination of these abilities. There
LDPE - Low Density Polyethylene
could be a number of them selected and used
PFA - Perfluoro Alkoxyalkane
for one project While selecting these, care
PP - Polypropylene should be taken to minimize the number to
-
PTFE Polytetrafluoroethylene rationalize the inventory. The designation
PVC - Poly Vinyl Chloride
of these Piping Classes varies with the
PVDF - Polyvinyliedel~eFluoride
company. While designing the piping
Glass
systepl for a project, the components, which
Cement
Ceramic are not mentioned in the piping class, should
be avoided.
J
Piping Elements 24 I
1
, i -
i PIPING ENGINEERLNG CELL
Piping Elements 25
PIPING ENGINEERING CELL
* Depending on pressure and temperature, * U s e Spiral wound gasket with inner ring
gasket shall be either CAF, spiral wound for Vacuum service
metallic for raised fice flanges or selected I * Low strength carbon steel bolting shall
based on the corrosive nature of the fluid. not be used above 200 O C and below -29 O C
* Use flat face flanges to mate with cast
iron valves and equipments.
Piping Elements
FACTOR A.
I
?'HE VALUES OF FACTOR A
USED I N FORMULAS F O ~ ~ V E S S E LUNDER
S EXTERNAL PRESSURE
Certificate Course
on
PIPING ENGINEERING
-
May II 27,2Q05
Prof. A. S. Moharir
IIT Bombay :
PIPE HYDRAULICS AND SIZING
-,
single phase flow. The paper attempts FLOW PRESSURE DROP
to build on this background.
+ A possible approach
1. ,I
PIPE SIZING
TYPES OF FLOW
+ Velocity considerations
+ Single' phase, Two phase, Multi- + Pressure drop considerations . '
f
c i- 1' is not strongly correlated with the everywhere along the flow path. This is true
-. pressure, the medium is termed as if there are no external inputs or withdrawals
-.p'
. /. incompressible and the flow as from the conduit Applied at the two points 1
<A . incompressible flow. Liquid flow and 2 of the inclined pipe shown (Fig.l), the
f (single, two or multiphase) would come Bernoulli's equation can be written a s
2
,
I
>
>
1% in this category naturally. However
when gasedvapors which are
follows:
1.,
compressible (that is their density is a P I/p+v, /2g+z, =P ,/p+v ,'/2g+z 2
: strong function of pressure) are
5 ! involved, but the pressure drop along the
flow path is not significant enough to
i 'r
.
'
S e c t the medium density, their flow
may also be treated as incompressible
'
)'
>
' flow. Oth&se, the flow of
jj> / gasedvapors is a compressible flow.
In some flow situations,
j
,I -
2;j !
- * especially two and multiphase flows, the
J inclination of the flow conduit from
.
2 s
horizontal is of great significance. Also
1 whether the flow in the inclined conduit
L4 I1 is upward or downw~d is also an-
:?
> important considera2icx In the case o f .
i'i single phase flow, the inclination is
i
important in the sense that it affects the
overall energy balance given for the flow
,
When the pipe is horizontal (2, = Z ) and
1
situation by the famous Bernoulli's ,
the conduit cross-section is uniform (v, =v )
-,
1 equation. But the flow type and
hydraulic pressure drop are not affected
, the pressures at the two points, 1 and 2,
should be equal, This is not the case because
by the pipe inclination. the flow is confined by the pipe and there is
i t a resistance to flow caused by fiiction
- -
i between the fluid and the wall, friction
-
between different layers of fluid flowing at
i l
different velocities and the small or big However, for other cross-section
swirls created in the liquid due to flow $rectangular, square, . annular, etc.), D is
turbulence. Flow against these defined in terms of the Hydraulic
resistances causes generation of heat radius@, ) as follows:
raising the temperature of the fluid as it
flows. This temperature rise is not D = 4 x Hydraulic radius.
enough to do any work an this energy
transformed into thermal energy is good
as lost energy. This expressed in The HYDRAULIC RADIUS is
pressure units or expressed in terms of defined as ratio of flow cross-sectional area
an equivalent column of the flowing to the wetted perimeter. For example, the
fluid is called fictional pressure drop or case of a rectangular cross-section with sides
head loss. a and b, the flow cross-section is ab while
the wetted perimeter is 2a+2b. Similarly, for
Incorporating this fact into the
Bernoulli's equation yields the following an annular region as shown (Fig.2), the
form which is generally used in hydraulic radius is as shown: .
calculating fictional pressure drop in
flow:
.
-
:.. r
.
= .I
It is a Dimensionless number if ..E
flow is termed laminar and for values transient and turbulent flows remain the I -
above 4000, it is a turbulent flow. The J
same as given earlier. The linear velocity 3 -
range 2000-4000 is termed as the used in the definition of Reynold's number ,
transition region. D in the definition of is obtained by dividing the volumetric flow I . ,
the Reynold's number is the actual rate by cross-sectional area for flow. 1
5
convert these correlations for other situations in process in industry would fall
friction factors. in the fully developed turbulent region and
Blazius equation (especially
the one with R, with exponent -0.2) given
LAMINAR REGION above is widely used.
The roughness factor E is dependent
on the pipe material and method of
fabrication and some representative values
TURBULENT REGION are given in the Table 1. Note the wide
variation in perceptiocs of the roughness by
Rough commercial pipes, Re less than different authors. In most plots, Moody's
50000: roughness values are used. Because of the
variation in friction factor definition and
roughness values, it is advisable to stick to
one plot with full knowledge of the fiiction
factor it pertains to and the roughness values
Smooth Pipe, Re less than 3400000
. .
it refers to.
The frictional pressure drop
calculated by any of the above methods
should be multiplied by the effective length
of the pipe segment to get the net frictional
drop across the segment. This is then used in
Blazius equation, filly developed the Bernoulli's equation to obtain the actual
turbulent, : pressure drop between pipe origin and
destination. The effective length is the
actual pipe length if the pipe line is straight
and long enough so that pressure drop due to
extra turbulence created at the entrance
Another Blazius equation when fluid enters the pipe from an
equipment or at the exit when the pipe fetds
f=0.046 R, "' into another equipment are relatively
insignificant as compared to overall
Smooth or rough pipe, R, less frictional pressure drop. In case, . the
.
pipe
-
has
fittings such as elbows, tees, valves,
- than 3400000, developing turbul&t expanders, reducers, etc., an hypothetical
flow: straight pipe length of same diameter as the
run pipe on which the fittings exits is added
in place of each of the fittings. The effective
length is the sum of the straight-mn pipe
length plus the total equivalent for all
fittings. Entrance and exit of fluid in and
h r n the pipe segment also adds to
Most f vs R e plots would mark turbulence and to extra pressure drop. This
effect is also incorporated by adding
transition between developing turbulent equivalent length of these. The actual
flows by a broken line. Most flow equivalent 'lengths for important fittings are
5 L
given in real terms (i.e. length of pipe to of segmenting the pipe line may be adopted.
) I be added) in Tables 2-5. (The tables are A good practice would be to
. I taken fiom the famous paper on practical calculate pressure drop over the pipe run
;
pressure drop calculations by Robert assuming fluid properties at inlet or average
,-, Kern) temperature/pressure conditions to begin
In another approach, equivalent with. If the pressure drop so calculated i s
length of fittings are mentioned in terms within 10% or less of the actual pressure
of diameters of the pipe. This number levels at which the fluid is flowing, one may
'j
should then be multiplied by the pipe ignore the effect of temperaturefpressure
t=.
B size to get the equivalent length of pipe change. If the pressure drop exceeds 10% of
to be added. The equivalent lengths for flow pressure, the above approach of
"1 valves and fittings in terns of diameters segmenting may be restored to.
I
:'6 are reported in several books and are not
given here. Analysis of the actual TWO PHASE PRESSURE DROP
I
3 I
1.
equivalent length for fittings of different
sizes as given in Tables 2-5 should show
CALCULATIONS
-f 1
r
.
. .
.
i
.J
folbwing could be useM to calculate - . ".
the cost of accessories per unit len& as
should be same as. ;that power cast). The '
. ' , .. -- 1
g .i 3
factor 0.0000542 comes ody b e ~ i u s eof . .. .i.9
. .
. . .
1, ..
.
.
'
. ,t
- (ft.lb.forceand-kwhr): :
-. : . .
' '
:
'
flanges, 2.1 tees, 32.6welds. So the total The. pressure drop, AP, can be . .' .u
.. . aJ3
t
[w
0.479
potT
0.027
1 0.0657YK
(A, + + F)
I
0.169
centigrade, and p in kg/cm.sec.
absence of such estimates and uses the and surface roughness (due to scaling,
expressions for , D h its erosion, corrosion etc.). Also, optimization -3
unsimplified form. ------- --- . exercises and capacity enhancements in '
* -
The values thus calculated may firture may require the same pipe to catry
not conform to the commercial sizes. larger amounts of process fluid. In view of 1
commercial size.
The adjacent commercial sizes procedures. .. !
on either side of the LAC diameter are I
(This paper has relied heavily on the article
identified Let these be L D, On by Robert Kmq published in Chem. En&. # -- 5
lower and higher sides respectively. An ,world I :
hypothetical size, called crossover A -
-
diameter is then defined as: a I t
-4
1 '
14 -3
I '
Distributive Flow
. ? 1) Bubble b) b1 is c
Intermittent Flow
Plug.
Segregated Flow
Stratifid 9 Annular
I
I
\
-
,( i
.-
I
1 L-
-
- >
9
I d'
I
.. C
-. I
I
Fi.4 i .
Bakerp~nmetcndctrrmined h e t)rpc oftwo pbuc Ikw and approprutr two phue llowcomhtion kusunit l a -&
I --
no-5
IBurmmetcnfur prcssurcdrop inliquid - Ilow through horiionral piw ' '
.
. .. .
.
':
. .
I ltnwd oil 1.1~liflan ..AS. J'I ( I Y . 1911
qnd ~t~rtiacUL.Chcm..Ea~~~Prop ... . . J
fig. 6
Lackbrrr ,H~rllrclliCorrtlrflo. r c l ~ l c rvrpoer amd liquid propenlcs to tstrbllrLcd t r a plant mw radmlcr.
FiL; 7 Fit J
Amortized trpitul costs lo8 ou reel aC plgc . Amflrrl cost d oprrmtlmg awe' C-I o f pipe.
Table 1
&
I Miller (32) K u t ~ t d a d z (19)
e !.
~n- 1 mm I m. 1 mm I ~n. I mm
CMUCle
Smaath
Rough 0.02
Wood
Birch vene~r
Pin0 vaeer
Rough
Gakan'd '
SmooChIhirh 0.W1 - 0.025
~ o r n ul%w~
l o.m .a.is
9 '
1 '
r '
-#
I
Resistances of E l b o w 8 , T ~ sand Bends -Table 3
! (Resistance in equivaIent ppe length. ft)
I
i
;iesist,nce o l Eccentric and C o n c e n t r i c R e c u c e r s .
And of Sudden Changes in
-
I
I
YWMU 3 w Yrrr -n 2 oc ess
I
l l o 10 10 lo ,a
Laud c LWW v*an ra u ~ , rvs -v hs ,I
w.rr I
pvrp S U S ~
i.
l to2 7 - 4
ho=bq8!W Zmf 105 4 - 7
c.uzUp.h.a~m~. 4 a a SIC 1 2 l a tr
ao4r -t 4 n J . SP'Z d o tr
Qlra
SLaa-r
-1
3a4 3-5
3 -4 5 4107 - L
(Isanurnrcaibes)
~ V r o o n 1 . w 2.2 2 14 4 106 1
rm? I
--
Ducnrrg.h.wkr!bg 2.5 to 3.5 3 IO5
bhbd bV13 5 M !2 8- IS
-
ONa 3 ~ 4 10s
v* oh
Rrrowabn ! i.
r ~ d b d p b
1.) lo 1
a4 D a7.S
2s to 5
9.3 O 1 .
[- 1ms roe !.J
On- 1 IS m 3
C~mprersarsuctrjn :I lo 204: ,
Clxnpramr d i s e h u ~ e tcO tu 3 0
Inlet. ~ C c a m4ur'Hne 1!t8 w ;I? I '
I d c t . zu ~wblnc I IO tu J!n
Wcl~cfr d v c i u c h u l e GSV.'
K:llcf -11bc t n e rc silcncc: '4-
.. .
TrroPham Flow brrrlrtknr
. T
'
Dkpr
m . Bubble I ' stratifid wm PI- kurulqr
bFb.3 9 - 142fi" 4- 1.l90f -"'4-16.4SOX Urn Fig, 6 #-27316~~"' # m e 9
b-033--94
d-IB.dpipe.in
Avoid Horiomol HorjzontJ Forp~12islwd
slug flow P~W: pipe ~ , l m d - ~ O .
. .
Courtesy: Mr. h i d B a b r and The Oil md Gas Joumd.
FIG. 1. Bakei parameten determine the type of tw+phase flow and the appmpshte two-
phas~flowcordation rett unit loss. ,
!-
.. .
-.
. .
I -.
Fluid FIOW, Two-Phase Design , .
t . -.-..-
. ' ..
. . .
. . .
. . . . . .
.
'. .
.
.
- ~ t y n o t d i n u mN~ ,
:'
. . . . .
. .
. . .
5 :
. . . .
. .
. .
'.
.
:-.
.
.
--
.
.
. . .
-
.
I.
.
.
.
1
.
.
. . .
.: . .
. .
. . . .
.
:
.
.
.
i .
FIQ. 2. F d h fktm
~ in new commcrdalatcd pipe fw vapor-pbast or liquid-pbc flaw.
I
L
,-
31sornw: BuPblc slog
T w Q ~ %vv
~ ~ Corrgtations
u
-.
an6 ZC. !31 (~/*;~+l
: W ~ A ; ~ - - ~ !r,p
!0-3 ant3 Ec. 19)
ana (1CI
(v,O.lt r*3.2-0.21%C
j2:1- 0..:2: @
3
1.2. IO I W .
$
-
9-
i
i
AVOW
lrug f:ow
Hcrrion~I HorizcntJ
pipe P~PC
Far olae f 2;n anc
ova-. use d 10. i
Caurterv: Atr. OWU-Iarker and The Oil and Cas-J~urnal.
I Q
Lockhart.Marrinelli modulus, X 2
-
. .
Organized by
VALVES
T. N. GOPINATH
Functions of Valves
I
Isolation
1
Regulation
I 1
Non-Return Special Purpose
The design of the valves are done in such 2.2 Needle Valves
a way as to perfom any of 'the above
hctions. The type of valves used can be 2.3 Butterfly Valves
classified in the following categpries.
2.4 Diaphragm Valves
. . 2.5 ,PistonValves
1.0 ISOUTION
2.6 Pinchvalves
1.1 Gate Valves
Valves 1
PIPING ENGINEERLSG CELL
3.0 Bronze
Valves
. .
i I
PIPING ENGINEERING CELL
h
normally contact the surface fluid. grade.
The table below indicates trim of
I
4. Wetted Parts
All parts, which come contact with the
-
7. Quarter Turn Vdves
This refers to the valve where the entire
service fluid, are called the wetted parts. operation of valve is achieved by 90
degrees turn ofthe closing element.
5. Wire Dmwiue
This t a m is 'used to indicate the 8. Pressure Drop
premature erosion of the valve seat Pressure drop is the loss of pressure
h u e d by excessive velocity b-een through resistance a m s s the valve while
seat and seat disc. An erosion pattern is flows and is expressed in terms of
left as if a wire had been drawn between ~ v a i mlength
t in pipe diameters
the scat surfaces. Excessive velocity can
occur when the valve is not closed Equivalent
tightly. A WOG (Water-oil-Gas, Type of Valve Parition length in pipe
relatively cool liquids) disc is the best dia (LA))
Gate Fully 13
defeasc against wiredrawing because its
resiliency makes it easier to close tightly. Globe
Discs of harder material are to be closed h g l e globe
Swing check
carefully to prevent wire drawing. In Plug -
LPG Service, the wire drawing effkct
causes a threat of anti-refrigeration. The Plug Port
Ball - Regular 40
ice formation on the wedge will obstruct Port
movement thereby increasing the leak Ball - Full port 8
through seat M e r .
-
6. Straight Through Flow 9. Upstream Pressure
This refers to the valve in which thc %s is h e prasurs of the fluid that
closing delnent is retracted entirely SO enters the valve. a s is sometimes
that there is no restriction of flow. referred to as'inlet or supply pressure.
. .
-
Valves 3
PIPING ENGINEERING CELL , .
i 1.70 . 11.. , .. .
6 4.06 . -. . ' 27. . . . i
6 .. .
6.35 45 . .
. .
.--
- 4 +
Valves
f
PIPING ENGINEERING CELL
2%!
ttt
I"" """
Valves. . .
. .
PIJ'ING ENGINEERLNG CELL I
i Steam H.P. W" -1 % " a) C.S. Body a) C.S. Body C.S. Body Pion
stellited trim stellited trim Stellited valves arc
800# Globe 800# Globe trim 800# costlier.
withSWends with W e n d s Liftcheck Fromthe
b) C.S. ~ o d y b) C.S. ~ o d y with SW point of
stellited trim stellitcd trim view of
800#Piston 800# Piston ' E=U
with SW ends with SW ends COIISCTVII-
:-
Valves
i
!
- PIPING ENGINEERING CELL
!
[
a) C.S. Body SS a) C.S. Body
ball PTFE 13% Cr.
scat 800# S W Trim 800#
Ball . SW Globe
b) C.S. Body
800#
13% Cr.
SWTrim valve
Globe
SAME AS LP STEAM
a) C.S.Body SS a) CS.Body a) C.S.
Ball PTFE 13% Cr. Body
Seat 800# Trim 8OO# 13% Cr.
S c d Ball SW Globe Trim
b) G.M.Body b) G.M. 8W Lift
Bronze him Body check
Scrd Gate to Brpnzc With S W
IS 778 Trim Scrd Ends
Globe to b) G.M.
IS 778 Body
Bronze
Trim
Scfd
check to
IS 778
a) CI Body 13% a) CI Body a). CS Body
Crdisc125# 13%Crdisc 13% Cr.
wafatype 125#wafcr trim
Butterfly type Butterfly water
Gear Gear Operator b'P=
above 6" NB check
above 6" NB
b) CIBody 13% b) CI Body b) CI Body
Cror 18%Cr 13% or 13% or
him 12% 18% Cr 18% Cr
Flgd Gate to trim 125# tri 125#
IS 14846 %d flgd
Globe swing
check to
Valves
PIPING ENGINEERING CELL
b) CSBody b) (3Body
13%Crtrim 13%Crtrim
Craphoil pkg Grapbo'i pkg
300# (Min) 300 #(?din) ,
6) Chlorine @ry) W' - 12" Ball valve with Globe Valve Check (Lift /
CS body M o d with CS Body Swing ) valve
HastalloyCball hfonelf CS Manel 1
&stem Hasfalloyc HastaEoyC
trim trim
7) Solvcntl Process %"- 12" a) C.S. Body SS a) C.S. Body a) CS. Body
(&.dm11 Steel) Ball I50 Flgd 13%Cr. 13%Cr. trim
full port Ball him ISO# Flgd Lift
valve with Flgd Globe cback 5P to 1
rn GFr Yin and Flgd
seats swing check
b) CSB* 2- a above
13% Cr plug
1sO#ngd
~~~ p h
seats
Valves
- s S:
1 -
PIPING ENGINEERMG CELL
Valves
i. ,
PIPING ENGINEERING CELL
1.1.2 Bonnet
1.1.18 Gasket
1.1.3 Wedge
Valves
PIPING ENGINEERING CELL
Valves
PIPING ENGINEERING CELL
,.
The stem connects the hand Normally, the packing is of -,
wheel and the wedge for operations. The braided asbestos with suitable corrosion
design can have rising stem and non- inhibitor. When special packing such as 1 3
rising stem. The stem is operated 'Graphoil' is used, the number of packing .:
rotating the stem nut by hand wheel rings required will be more. To I
mounted at the top of the yoke. accommodate more packing rings, the I -
P.
:L
I
In the rising st& design, the length of gland is also modified. This
stem moves up along with the wedge to design is called the 'Deep Gland' design. .,
?. h
open. This is called the OS & Y (Outside This is used for the high temperature I -j :
Screw and Yoke) type of design. In case services. But this cannot satisfy the 5
i '
of non-rising stem the wedge moves up EPA's fugitive emission standard of 1 ,.
.'-G
,
and down and the stem is stationary. 4 0 0 PPM threshold. Hence frequent ,
This is called the inside screw non rising LDAR will result in excessive I '
stem design. expenditure.
Normally, bar stock or forging
I
--. i
are used for the construction of stem. 1.1.6 Seat Rings ,. '-
-
There are two types of designs
T
1.15 Gland, Gland flange, Packing posslihle in seat rings. They are the -+
- ,
and Lantern integral and renewable. In case of I -
There are two types of gland renewable seat rings, it may be either
I
I
rj
designs possible, Single piece and Two tlmaded, rolled-in or welded-in. In case
piece. In two-piece design, there will be of integral seat rings, the seat material is .,'t
I
gland flange and a follower. The welddeposited directly on to the valve I r i
follower will have a spherical end, which body. The minimum hardness specified $
facilitates proper aligning of follower by the code for this material is 250 HB, ij
and loading on the packing. In Single with 50 HB minimum differential iI *
piece, the gland and follower will be between body .and gate seats, the body
$
integral. This design is used mostly in seat being harder. Deposition of harder I ' r
low-pressure valves. materials like "Stellite-6'* is also done *. I
I
K t
T:
3
of superior material than 'the gland The back seat m g e m e n t is
flange. Gland flanges are made of carbon
I 3
provided to repack the stufig box when ?:J
steel only. The glands are bolted to the
bonnet with gland eyebolts in low-
the gate is in fully open position. The
stem shall have an integral conical or -w
B
pressure valves. . . - spheaid backseat surface to Setit against ' , -
=133
The regulatory codes specify the bonnet backseat.
that the stuffing box should 9 .
..
J
accommodate minimum six packing 1.1.7 Yoke and Yoke Bush .
rings for class 150 valves. As regards Yoke may be integral with or =*
higher rating valves, it should have separate b m the bonnet. When the yoke . % 1
lantern ring with five packing rings is integral, the stem nut should be -<
above and two packing rings below removable without m o v i n g bonnet. ' -- 1
lantern. Lantern is not provided for class The yoke should have the same material
150 valves. Lantern is provided for
' 1
of construction as that of the shell. The
higher rating if required. When lantern is Yoke bush is normally a Ni-resist . 1
provided, the stuffing box shall be material. This is to prevent gauling of the
provided with two plugged holes. The stem, as stem will normally be of a I 1 -
Nickel alloy.
Valves
PIPING ENGLNEERING CELL
1' -
end. The port or the bore is the pasage
1.1.8 Hand wheel and Hand wheel Nut through the valve.
There are two types of port designs
The hand wheel is fixed to the stem possible in gate valves, full bore m d
by a threaded hand wheel nut. The arrow reduced bore. In case of full bore, the net
pointing the direction to open the valve area of the bore through the seat shall b e
will be marked with the word "open" or as nearly practicable equal to the
"close" or "shut", unless the size makes nominal pipe size. For reduced port
it impracticable. Valves shall be closed valves, the port diameter is normally one
by turning the hand wheel in clockwise size less than the size of the end.
direction. The compact design small bore (% -
The material of construction of hand 1 % inch) gate valves are as per API 602
wheel shall be malleable iton, Carbon or BS 5352. Unless the full bore design
steel, Nodular iron or Ductile iron. Cast is specifically asked for, manufacturers
iron is not preferred. The nut shall be of supply the reduced bore valves. The full
carbon steel or stainless steel. bore design gate valves are also c o v d
When the installed position of the in BS 5352 and is designated as 'std
valve is such that the hand wheel is not bore'. In full bo* design, the net area of
accessible, then the hand wheels are the bore through seat shall be equivalent
replaced by chain wheels and the valve to that of Sch 80 pipes for class 800
is operated with chains. For large valves and Sch 160 pipe for class 1500
diameter valve where the operating valves. In no case less than 90% of the
torque is high, gear arrangement is above figure is acceptable as per axle.
provided to facilitate operation. Mostly,
bevel gear equipment is adopted.
General recommendation for specifying 1.2 B ALL VALVES
Gear operator is:
I U I B LBIFII
n g -
Size.
Class 150 14" NB & above
Class 300 12" NI3 &above
Class 600& above 8-"NB & above
1.1.9 Bolting
Normally high tensile stud bolts are The ball valves are normally used as
used for bonnet bolts and low carbon positive shut off valves. The positive
bolts for gland and yoke bolting. Gland shut off is attained because of the soft
bolts are normally hinged bolts with seats. Special design is also available
hexagonal nuts. with ball having shaped port for
regulation Metal seated ball valves are
1.1.10 Valve Port also available' for high temperature
The valve size is specified by the service. The ball valves can be classified -
size of the end connection or the body based on:
. .
. .
Valves
PIPING ENGINEERING CELL
- 14
Valves
PIPING ENGINEERING CELL
are possible, viz., the fire safe design and same has been explained earlier. The ball
the non-fire safe design. In the fire safe at the bottom end of the body could b e
design, a secondary metal seat will be supported fully by the seat or it could be
provided so that when the soft seat is trunnion supported. The ball can be solid
l l l y burnt, the ball will shift its position ball or of hollow construction with
and seat against secondary metal seat cavity. The cavity is to be sealed when
and arrest full leakage. The modified the valves are used in volatile liquid.
design incorpoiates a double staged stem This design of the ball is called sealed
seat design and a seating system that cavity design.
adjusts to the line differential pressure. The gland shall be bolted type
At low differential pressures the floating or screwed. Internally screwed stuffing
ball seats against resilient tip seat. At box is not allowed by code. Bellow
higher differential pressures, the ball sealed bonnet is also provided in case o f
deflects to produce contact across the valves used in lethal services. Two basic
entire seating surface of the seat ring. bellow seal designs are available. The
In an actual fire, the heat same is explained under plug valves.
intensity of the fire could be so different The valves shall be operated b y
that it is impossible to ensure that wrench or by hand wheel with gear
elastomer seats are fully damaged during amgement. The wench shall be
fire. If the seats are only partially designed so that it is parallel to the flow
damaged, the ball cannot @Ice seating passage of the ball. The valve shall be
against the secondary metal seat and closed by turning the wrench or the hand
hence the valve would leak. Hence, in wheel in clockwise direction. The length
my opinion, none of the soft-seated ball of the wrench or the diameter of the hand
valves can be declared fire siafe since the wheel shall be such that minimum force
valves are bound to leak in case of is required to operate the valve under the
partially damaged seats. The maximum differential pressure.
manufacturers have come up with metal- When added emission control is
seated ball valves, which are l l l y fire required, additional packing and leak off
safe. Here the resilient seats are replaced port &e options that can be added.
by metal seats, which could even be Normally all the parts are metal
deposited with high temperatme resistant except the resilient seats in a ball valve. .
materials. The fire safe design should Plastic valves arc. also selected for
also ensure that any development of corrosive process fluids while they
static electricity should be Mly operate up to 150 psi and 100-150C and
discharged by proper design and also in food industry. To select the best
manufacture of valve. Such 'an plastic valve, process data such as
arrangement is called the 'Anti-static' number of cycles before failures is
design. This ensures to have a discharge critical.. Ball valves Lined with PTFE on
path h m ball to the spindle and h m the body and ceramic ball is used for
spindle to the valve body with an extreme corrosive fluids.
electrical resistance of not greater than
10 ohms when the valve is new. A 13 PLUG VALVES
typical method of achieving earthed The plug. valves, like ball
continuity is to provide stainless steel valves, are quarter turn positive shut off
spring-loaded plungers, one fitted valves. Two major types of plug valves
between the stem tongue and ball and are in use. They arc the lubricated metal-
second fitted between stem and body. seated plug vdves and Teflon sleeved
The ball could be of full bore or plug valves. These valves can have
a reduced bore. The design aspect of the flanged, butt-welded, screwed or socket
Valves
PIPING ENGINEERING CELL
weld ends. The pressure classification is with the tapered portiorl towards the top,
the same a s that specified for the gate it is called 'inverted plug'. Normally
valves. The range of pressure to which larger diameter (8"NB and above) have
these valves could be used depends upon this design.
the seat, seals and the lubricant. Plug Another design in use is the
valves with shaped port are used for flow Pressure Balanced Plug. The benefit of
control applications. the pressure-balanced design is the
elimination of the possibility of
13.1 Metal Seated Plug Valves unbalanced forces causing taper locking
In lubricated plug valves, the of the plug. This is achieved by using the
lubrication of the seating surfice is by live line presswe to replace the sealant
means of lubricant, which is fed into the pressure. The regular sealant injection is
operating surface of the valve either in not needed to keep the valve fiee to turn.
the form of mastic sticks or by grease The pressure balance system
gun. The selection of the lubricant consists of two holes in the plug
depends upon the service to which the wnnecting the chambers at each end of
valve is subjected to. In certain designs, the plug with the port, which contains
a low friction Poly Tetra Fluoro Ethylene line pressure.
(PTFE) is impregnated on the mrface The valve having pressure
structure of the valve plug. This is called balanced is called dynamically balanced
'LOMU' treatment. This reduces the plug. MIS Audw called these types of
frequency of valve lubrication. valves as 'Super-H' pressure balanced
The plug valve design refers to valves. The break away torque required
three patterns considering the shape or to operate these valves are lower than
port through the valve and the overall (almost half) that for the reduced port
length. They are the regular pattern, the ball valves.
short pattern and the venturi pattern.
The regular pattern valves have
plug ports generally rectangular in Comparison of Breakaway Torque
section and have area substantially equal Requirement of h v e s
to fill bore of the pipe. The transition
f?om the round body to nxbngular seat The following data has been published
ports is smooth without sudden alteration by a valve rnmufactum to indicate the
in section, which causes turbulence. easiness in operation of. the pressure
These are used where pipeline losses are balanced plug valve.
to be kept minimum. . . - . . a
..- ..: -.
The short pattern- valves baire
firce-to-face dimensions w m p d i n g
to wedge-gate valves. This is used as an
alternative to gate valves.
The Venturi Pattern Valves have
reduced port area. The change of section
through the body h a t is so graded as to
produce a venturi eff& to restore a large
percentage of velocity head ioss through
the valve and produce a resultant total
pressure drop of reiatively low order.
The plug could be installed with
the taper towards the bottom end of the
body or reverse. When the installation is
Valves
PIPING ENGINEERING CELL
- -
Valves
PIPING ENGINEERING CELL
plug valves are used in corrosive and surfaces of the sealing rings. This
abrasive service for on-off action. provides a large sealing surface I
i
Eccentric action plug moves into and compared to globe valves of ' 2
away fiom seat eliminating abrasive conventional design.
wear. These are covered under MSS-SP
standards.
Piston valves are of two types,
balanced and unbalanced. Balanced
I I:'
valves are used in high-pressure services I. r. I
'
and unbalanced one for low-pressure I . -
1.4 PISTON VALVES. services.
[ '? - *
The main parts of the valve can
be identified as -- -
.
~
1.4.1 Body
1.4.2 Bonnet
-
I---..,
,
-. i
I ' ',
I
1.4.3 Piston ! 2- .i
'
a
'
. .
1
~3
construction. Itcan have screwed.&,.. ;
' flanged ends or butt-welding ends. These - . . . ..
.
$. .. ..
.. . .:..J
.. t
valves foilow the regulatory codes' to :-
'
-
Valves
PIPING ENGINEERING CELL
The bonnet is also of the same The valve body can be lined or unlined.
material as that of the body and it is of
bolted construction. The piston along
with the two resilient seats provides
proper sealing. The upper valve ring seal
to atmosphere, the lower valve ring
provides seal across the ports. The
lantern ring serves as the distance piece
between the two rings.
There are two types of piston
designs available: Regulating type and
the normal. In regulating type the bottom
part of the piston is tapered to have
throttling effect. The sealing rings are
the heart of the piston valves. The
sealing rings are made h m specially
developed high quality elastomer
material or graphite. The materials are
selected depending upon the service
conditions viz. The fluid for which the ~
ini
ymaterial is selected to suit the
u
valve is used and its prassure comsive nature of the service fluid.
temperature conditions.
Spring washers are fitted under
the bonnet nuts to ensure that the Diaphragm valve with plastic body is
pressure of the bonnet on the valve ring also manufachued.
is kept constant This along with the There are two types of
resilient sealing rings produces a spring diaphragm valves available. They are the
action, which compemates for any Weir'type and 'Straight flow' type. The
differential expansion that can occur. .most commonly used one is the weir
There are two types of stem type and are popularly known as the
designs available, (ha inside sam rising 'Saunderst type. In this type' the body
stem and the 0' S and Y type with rising configuration is such that isolation as
stem. The haqd wheel is of &g design. well as control is possible.
1110'sandY type, a s t u 5 g b o x with a
bolted g l a d is provided. This design is . A typical diaphragm valve has
mainly wd for Thennic fluid/High the following major parts that could be
t e m ~semdces. t identified. They are:
The piston valves are prefemd
by maintenance people, as they need 1. Body
lesser attention. They call it as 'Fit and
Forget' type of valve. 2. Diaphragm
3. Bonnet
15 DIAPHRAGM VALVES
4. Stem
Diaphragm valves are mainly used for
low-pressure corrosive services as shut- 5. Stem bushing
off valves. These can also be used as
control valves. Here the diaphragm 6. Compressor
moves up and down to operate the valve.
-
Valves 1q
PIPING ENGINEERING CELL
I
7 . Hand wheel are covered by. British Standard md
MSS-SP Standards. I
I
8. Bonnet bolting. i 1
I '
the service for which it is used. The body parts of the butterfly valves are: I +--
Valves
I '
PIPING ENGINEERING CELL
Valves
PIPING ENGINEERING CELL
2.0 REGULATINGVALVES
The valves normally used in the
plant to regulate/control the flow are:
2.1 Globe Valves
Valves
- 23
PIPLNC ENGINEERING CELL
valves, disk can be provided with an 2.1.7 Yoke and Yoke bush
elastomer ring or facing which wiIl The construction of the Yoke is
ensure the same. The n d l e type disks the same as that of the gate valve. The
are used when finer flow control is to be Yoke sleeve of the gate valve is machine
achieved, These disks can be also of finished on all surfaces whereas that of
contoured design as used in flow control the globe valve shall be screwed or fitted .
valves. These are generally used for in the position and locked in case of
precise flow control applications. V port rising stern design.
type disc is used for k t t l i n g
application. 2.1.8 hand Wheel & Hand Wheel Nut
The disk shall be either loose or Unlike in gate valve the hand
integral with stem.The integral design is wheel also rises along with the stem for
used mainly for the needle type of disc. globe valve. When used as a control
The loose plug design allows the same to valve, actuators are fixed so that the
be renewable. When in the fully open stem movement is effected through tbe
position, the net area between the disk same. In case of bellow-sealed globe
and the seat shall be equal to the area valves, the non-tising hand wheel design
through the seat. is provided similar to that of gate valve.
Bellow seal is the only way to This is to ensure that the bellows art not
achieve emission control in this type of subjected to torsion.
valve.
The above are the major design
2.1.4 Stem aspects of the globe valves and
In case of globe valves, the comparison of'the same with that of the
stem is always of rising design along gate valves. As regards the material of
with the hand wheel. The stem is construction, end connection etc. are
provided with a disk nut at the lower concerned, the same shall be selected by
end. The upper end is provided with a the piping engineer based on the d c e
hand wheel screwed by stem nut. In case of the line to which the vdves are used.
of bellow sealed valves rising stem with Tbe environrnqnt in which the valve is
non-rising hand wheel is provided installed also will have to bt consided
similar to that in the case of gate valve. while selecting the material
2.15 Gland, Gland flange, Packing & There could be slight variation in
Lantern design. from mauufachmr to
Design, a d details same as that milllufbcturer, but the birsic design
of gate valves. features as specified are not a l t d ._
2.1.6 Seat rings 2.2 NEEDLE VALVES
In case of globe valves of The needle valves, like dobe
carbon steel, the hard faced seats can be valves, are used for flow control.
directly deposited on the body or the seat Normally needle valves are used in
rings shall be shoulder seated. smaller sizes and are provided with
either screwed or socket weld end Tbe
design of the needle valve can be c x d y
same as that of 'the globe valve except
for the disk. In globe valves, the disk is
Valves - 24-
PIPING ENGINEERING CELL
like a truncated pyramid whereas in the code covers this design, these are mostly
needle valves it will be full. This facility made as per Manufacturers'standard.
eures finer flow control. The disk could
also be integral with the stem, in which
case UIe bottom part of the stem will be 23 BUlTERFLY,DIAPHRA'GM,
machined .accordingly.
PISTONAND PMCB VALVES
The design and the construction
features of the same are alreadv
explained under the head '~solatio;
Valves'. These valves can perform the
dual duty of control as well as isolation.
-
3.0 NON RE'IWRN VALVES
As the name ipdicates, these '
Valves , - Crr
PIPING ENGINEERING CELL
3. Cover
-
Valves
PIPING ENGINEERING CELL
;
"
In these types of valves, the The body will be cast with a tapered
check mechanism is the disk, which is wedge seat and will be provided with
hinged. The pressure of the fluid l i b the renewable seat rings. The wall thickness
disk and allows the flow. The disk and end to endfface to face dimensions
of the body shall be as per the regulatory
code to which it is designed. The end
flanges shall be integrally cast or
attached by welding. The flanged
comection shall be to ANSI B 16.5 or
my other flange standard. The butt-
welding end comection shall be to ANSI
B 16.25.
The disk will be attached to the
,body through hinge and hinge pin and
swings against the same conttolling the
flow. The disk mataid shall be of
quality at least equal to that of the body.
The cover will be bolted on to
returns to the seat with its own weight. the body. The bolted c o ~ e c t i o nshall be
This allows the valve for mounting in raised face/ tongue and groove/male and
horizontal as well as vertical position femaleking type joint depending on the
with upward fluid flow. The main parts pressure rating of the valve. The gasket,
of the valves are - shall be selected to suit the type of
connection. It can be corrugated or flat
1. Body solid metal, corrugated or flat metal
jacketed, asbestos filled, metal ring joint,
2. Cover spiral wound asbestos filled. Rat ring
compressed,asbestos is used for low-
3. Hinge pressure application, Teflon or Teflon
filled for c o d v e applications.
4. Hinge Bracket Normally high W e bolts are uscd for
cover bolting. In cast iron check valves
low &n steel bolts arc used.
6. Cover Stud and Nut 3.2.2 Wafer check valves
The wafer check valves are the
7. Bracket Stud and Nut flangeless swing check valves. These are
covered under the regulatory code API
8. Disc 594. There are two types of wafer check
valve dkigns available.
9. Seat Ring
a) Single plate wafer check valve
10. Hinge Pin . Dual plate wafer check valve
b)
1 1. Disc Pin
Valves
- 22-
PIPRYG ENGINEERING CELL
4.0 SPECIAL-PURBOSE
VALVES
Valves, which perform duties
other than the two-way isolation, control
and check, are classified under the i .. -
category of special purpose valves. Few A most economical layout could be A
--
1
of such valves are selected from the study of above flow
patterns. r- . ,b
4.1 Multi-port Valves -'i
The 'typical applications of the three, way 1
4.2 Flush bttom Valves
.
. valves are-,
:
I ': :4
.
. .
. -Z .
J
.:..
.. .3
.
Valves . . .
PIPING ENGINEERING CELL
' : !
(1) alternate connection of the two (3) Simplification of piping layout and
supply lines to a common delivery, thus economy in fittings,
r3
(2) diversion of flow to either of two (4) Less risk of product mixing by
directions, incorrect valve operation,
(3) isolation of one of a pair of safety (5) The stops can be arranged to arrest
valves for maintenance purpose, the unrequired flow patterns and at
the same time make it impossible
' (4) division o f . flow with isolation
' for desired positions to be obtained.
facility. .
Two of the multi-port valves can
The flow gatterns of a four-way valve also be inter coupled to pennit fast
are- multiple operation in the simplest
possible way and with minimum
manpower.
It is essential for the designer to
specify the exact requirement of flow
pattems based on the piping
arrangement to the manufacturer. Lack
of proper coordination will result in a
totally different output tban what is
required.
The typical applications .of four way
valves are:
(1) Reversal of pump suction and 43 FLUSH BO'ITOM VALVES
delivery 'These are special type of
valves, which are used to drain out the
(2) B y pass of strainer or meter piping, reactors and vessels. These are
attached to the vessels on pad type
-3
y
, i
1 x,
(3) ~ e v & of flow through filter,
heat exchanger or dryer.
nozzle. The disks in closed position
match with the bottom of the vessel or
, piping leaving no room for hold up or
stagmlion.
The types of valves used
for this design arc the ball or the plug There ire two types of flush
valves. However, globe pattern valves boaom valves.
also can be designed with suitable disc a) Valves with disk opening into the -.
1 Valves - 2-9
I
PIPING ENGINEERING CELL
completely. In the second case, the disk depending upon the pressure holding
gets pulled down into the valve effecting capacity of the valve. I
II -
the discharge of material. The body lever and intemals
There are two types of disk are rnanufactured - out of gunmetal and I
design available, the plug type and the the float is of PVC or copper depending !
ram type. upon the temperature of the fluid. The
lever length could be adjusted to suit the
Normally, the inlet size of a
standard flush bottom valve is one size level in the reservoir. II
higher than that of the outlet size. There These valves have threaded
are special constructions possible with ends and are c o ~ e c t e dto the wall of the I
both sizes same. The outlet port is at an reservoir with hexagonal nut. The I
angle to the inlet port Normally 45 or 60 reservoir need not be provided with a
degrees deviation is provided. The end nozzle, only an opening is required. The
connections are normally flanged.
However, smaller size samplddrah
level of liquid will always be below inlet
connection.
1 J
..
valves have been developed with The maximum size of valve
1 ;
- -
welding end at inlet to withstand higher covered under the standard is 50 NB and I -
pressures. The maximum rating special design has to be done if higher 7 -
available at present for flanged valves is size valves are required. These are called II .< I
ANSI 300 lbs. equilibrium float valves. i -'>
service. The disk and seat also could be before stating. The suction strainer i1 -:-j1
machined to such accuracy to serve the helps to hold the solids while the pump
vacuum duty as well. is sucking the fluid f
c-9-
1
43 mom VALVES ~ h e s valves
e are covered under -
, .-,I
r
the reservoir. There'will be a float with similar to the Non-return valves. Valves I 1
lever, which contr~lsthe movement of are available with either flanged end
connection or screwed end connection. ' 1
the piston regulating the flow.
The material of construction of the body - 3
These valves are covered under is Cast lron or Gunmetal for the valves.
the Indian Standard IS 1703. There are 1
two types, the "HP" and the 'LP' !
- A ) -
Valves 30
PIPING ENGINEERIIVC CELL
!
4.5 LINE BLIND VALVES 4.6 KNIFE GATE VALVE
Line blind valves are used These are single seated valves
for positive shut off and replaces a used for slurry senices. They are
'spectacle blind'. Unlike blind plates covered under MSS-SP-Standards.
these are easier to operate and less Being single seated valve, it can be used
expensive than a standard valve. The for only unidirectional operations.
most common type of the line blind
valve is three-bolt/five bolt I-he blind In its simplest fonn, the sliding
valve. Another design is the single gate valves consist of two stationary steel
line blind valve or the 'pulp valve' plates each with large holes drilled
which can be power operated or with through it. A third plate slides between
hand wheel. There also exists a design of stationary plates to perfonn valve
visible-wedge line blind valve,, which operations. When open this design offers
provides a full bore opening or positive no resistance to flow. The ability of the
blinding inside a seat in a three quarter gate to slip through the plate effortlessly
enclosed body. No line residue c a spill
~ is the success of this design. The edge of
when wedges arc being changed and no the gate is shaped to shear the solids and
line movement is necessary when the elastomer seal is used to keep the
spectacles arc changed solids away from entering the space
between the plates when open and to
clean the sliding blade when it retracts.
The regulatory codes referred for these For valves used for vacuum
tests are either; service, a low-pressure air test on the
1. API - 598 - Valve inspection and seat shall also be canied out.
test.
Hydrostatic Test Pressures (in bar)
2. API - 607. - Fire safe testing of
soft-seated valves.
Pressure Tests
Pressure tests, unless otherwise
specified, shall be carried out on each
valve as follows;
balllplug,
or a rust inhibitor. - 3
3. Seat - Pneumatic Fire safe test is a destructive
test and carried out only in exceptional
All gate, globe, plug and ball cases when specified. The arrangement
valves are air seat tested at a minimum and test shall be as per API 607 or BS
of 80-psig/100 psig with liquid on the 6755.
side, which is not under pressure. This
test is not required for check valves.
Valves
1.0 ISOLATION VALVES
- I
1.1. ~ a t Valves
k
aa 3s
Piastic Industrial ball valves
CI and CS Ball valyes for general
Purposes
Stee1 Ball Valves for petroleum
Industries
Ball Valves for general purposes
Steel Ball Valves for Petroleum
Industries
. . . .
. :
. .
r .T
. . .. . ..
l .S.. Diaphragm Valves .. ,
I '
1
-
1 .
. .
'
I
'1
.
-..- .~.
-
Purposes ... ,.
1 ;
3 IS11791 : . - ~~DiaphragmValvesf~general.
. . . . I ~:.
<...I
-~l
. . . . . . . : . : . . . . . . .
-- . .
.
. . . . . . .
.,
:
. ,-
purposeg . . . . . . . . . . . . . .. . . - 1
. .
-!
. .. . .
. . . .
.
. .
. . . . .
. . . . . . . . .. .. .. .
. .
. . .
-. . . 1 . 1 . . ..-
. 1 . 6 , . ' ~ u t t e . ~ ~ ~ a .l v: e s . . , . " . . ' , . , .. . . : . . .. . . ,. . . . .
. .
.
. .. . . . . . .
.I
. . . .
. .
. - . i .
"
. '
'
7 3
: I !
. .
The Pipes and Tubes can be compared on the following lines: I
Tube pipe
1. Lower thickness and Lower ductility makes it
higher ductility permits unsuitable to coil. Duc to
rolling into coils without higher Moment of Inertia
high differential stress larger bending moment is
between h i & and required for the same radius.
outside of coil. This means larger residual
stress.
. . . ..
.. transfer. . .
. . . . ..
. . . . . . . ..
. . . . . . . .. . . :
. . . . .
. . . . . .. .
. .. . . . . . . . . . , . . .
. . . :
. .
Organized by
PIPING DRAWINGS
! T. N. GOPINATH
THE BASICS
The drawings are always considered as the which 3D representation of the pipelines can
language of engineers. The machine be prepared.
drawings and the geometrical drawings are 1.0 ' PLAN AND ISOMETRIC -
taught in the basic engineering curriculum. PRESENTATION OF A PIPING
Piping Engineers derive basics from these to SYSTEM
represent the pipeline routing on the
The purpose of drawing is to give detailed
drawing. There are two types of views used
information so that the pipelines could be
in the piping drawings: fabricated and erected to satisfy the process
requirements. Prior to making the piping
a) Orthographic- Plans and Elevations drawings the equipment layout drawings and
b) Pictorial - Isometric Views plot plan are prepared and these drawings
> Piping layout is developed in both plan view are used as the basis for developing the
II
and elevation view and section 1 details are piping drawing. Sometimes preliminary
f I
piping study is made to fix the equipment
added for clarity wherever necessary. These
co-ordinates. The other data required for the
I drawings are called the General
i Arrangement of Piping. To represent a three development of piping drawings are defined
J in the paper on "Equipment and Piping
plane piping in two dimensions of the paper,
certain symbols are followed. Most Layout".
1,
J
!
)
I
used are in !' For presentation of unit piping layout the
olthopphic s)mbals are ln
scale adopted usually are 1:25 or 1:33m and
I templates that are wed for spedins up the 1:100 for the pipe mk mas dilfasnf
1
:
drakg and 'lso the library sires of drawing sheets available for the
- , ,
for computer drafting.
In complex piping system, especially within -
preparation of the drawings. The Indian
Standard IS 10711 standardises the drawing
-- the unit/plant building where orthographic sheets as below:
views do not illustrate the details of design, OVERALL DIEAENSIONS
SIZE
pictorial view in isometric presentation is in rnrn (Untrimmed)
drawn for clarity. Specially printed isometric . 841x1189 . -
sheets are available with lines drawn 594 x 841
vertically and at 30' clockwise and 30' 420 x 594
counterclockwise respectively fiom the 297 x 420
horizontal axis of the paper by the use of 210 x 297
Piping Drawings
PIPING ENGINEERING CELL
TABLE- 1
I
PIPING SYMBOLS
Sr.
No.
DESCRIPTION j PLAN I END VIEW I I END VIEW 2
1.1 .1 BW elbow
'"71
1.1.2 1 SW elbow
-7 E
1.1.3 Scrd elbow
1-~-1
--I B
1 .I . 4 Flgd elbow
-
1.1 UPWARD BENDING
1.2.1
7
BW elbow
H 8-J 1
1.2.2 SW elbow
w .?L-JJ
1.2.3 Scrd elbow -II- T
t
(J
Piping Drawings
PIPING ENGINEERING CELL
-
Sr. DESCRIPTION PLAN END VIEW 1 END VIEW 2
-No
l.o CHANGE OF DIRECTION
AT 90'
1.2 1 UPWARD BENDING
CHANGE OF DIRECTION
AT OTHER ANGLES
1
3.1 DOWNWARD I
Piping Drawings
PIPlNG ENGINEERXRG CELL
Sr.
No. DESCRIPTION
I PLAN END VIEW 1 END VIEW 2
-
30 BRANCHING
3.1 DOWNWARD
I
J- S-
I
-r" B .
3.1.5 Stub connection ?+J
T H
'r' Y
3.1.6 Half Coupling ? ) >
3.2 UPWARD
3.2.1 BW Tee
3.2.2 SW Tee
.+a++ L. 1
- r
rC
,
,,A 0
3.2.3 Scrd Tee
i (d0-i-3
Piping Drawings
PIPING ENGINEENNG CELL
Sr.
DESCRIPTION PLAN END VIEW 1 END VIEW 2
No.
3.0 BRANCHING
3.2 1 UPWARD
Piping Drawings 5
PIPING ENGINEERING CELL
8.1 H a n d Wheel O p e r a t e d
F l g d Valve w i t h
v e r t i c a l h a n d wheel tik%H HWFI 6
8.2 'Lever o p e r a t e d
Valve
Hy- / .
wdi+ . 6
8.3 H a n d wheel operated
BW Valve w i t h
r o l l e d hand w h e e l $--&L, +&$+- . .
,..
.
10 ECCENTRIC REDUCER
. .
@.
FSU/ FSD
. .
. . . . . .
. . . . - .
. . .. . . . ..
. . . . .. . . . , . . .. . : . .
. .
.
.
. . . . .
. . . . .
. .
. .
. . . . .
.
.
.
. . .
.
. . . . . . . . . .
. .
. . . . . . . .
. . .
. .. . . .. . . . . . . . . . . . . . .. . . .. . . .
. . . ' . , , . .
. .
. . . . . . . . . . .
. . . .
. .
L A
Piping Drawings 6
I
PIPING ENGINEERING CELL
Piping General Arrangement is normally 2.4 Process equipment and piping have
drawn on A, size sheet. If the area to be priority on the Piping GA. The piping
i; covered is small then A, size sheet is also
used. Piping group produces a 'KEY PLAN',
drawings are started after fixing
positions of the equipments.
the plot plan on a small scale (1:500, 1:750 or
! 1:1OOO), which can be a c c b o d a t e d on. an 2.5 Equipment layout is reproduced on
i A,, size drawing sheet as per scale and dividing the Piping GA to its scale and drawn
the area of the site into smaller areas identified on the reverse side in case of manual
i by key letters or numbers. This is added to the drafting. In case of CAD separate
, i piping drawing for reference purposes. The layer is used.. The major primary
subject area of the particular drawing is beams and sec~ndarybeams are also
i hatched or shaded. shown if area covered is indoor.
The dimensional details of the title 2.6 Pertinent background details which
block are specified under the Indian Standard govern piping routing, such as floor
IS 11665. The drawing sheet is divided along drains, HVAC ducting, electrical and
the length and the breadth in equal spaces. The instrument cable trays, etc. are also
longitudinal blocks are identified by alphabets drawn in faint on the reverse.
and those along the breadth numerically.
These co-ordinates are used to locate the area 2.7 Utility stations are also established so
on the drawing. The direction of the north is that the most convenient utility header
taken either towards right or left on top of the routing can be carried out.
drawing sheet. This direction is kept constant
in all the areas covered in the plant, so also is 3.0 DEVELOPMENT OF PIPING
the scale of the drawing. GENERAL ARRANGEMENT
DRAWING
2.0 HOW TO START THE PIPING GA ?
3.1 Tbe piping drawings should be
2.1 Obtain the drawings numbers and fill in developed in such a way that all the
the title block, with the drawing number process requirements are met with.
and title at the bottom right hand comer
of the sheet. 3.2 It is not always possible for the piping
drawing to follow exactly the logical
2.2 Place the north arrow at the top lewright arrangement of the P & IDS.
hand corner of the sheet to indicate plant Sometimes lines must be routed with
north. different junction sequence and line
numbers and subsequently the list
2.3 Do not plan. drawing, in thc area above may be changed.
the title block of drawing, as this is
allotted for general notes, number and 3.3 Performance .and economics have to
title of reference drawings, brief be considered in parallel while
description of changes during revision deciding the routing.
and the bill of materials wherever
3.4 Piping is represented by single lines
applicable.
up to a size of l5ONB and double
lines for sizes 200NB and above. This
Piping Drawings 7
P I P I N G ENGINEEIUXG CELL
is to save die time of drafting and to 3.14 Each line should be ~dentifiedby line
avoid confusion. number and should also show the
insulation, tracing requirements, etc.
3.5 In single line representation only the
centre line of the pipeline is drawn using 3.15 Lines, if required, shall be broken to
solid line and in double line show the required details 05 hidden
representation the actual size to scale is lines without drawing other views.
drawn with centre line marked in chain-
dotted lines. 3.16 Do not draw details that can be
covered by a note.
3.6 Line numbers are shown against each
line exactly in the same way as 3.17 Draw plan to a larger scale for any
represented in the P&I diagrams. part needing more details and identify
it as "Detail 'A"', etc.
3.7 The change in specification should be
shown in line with P&I diagram. This 3.48 Draw part isometric sketches or part
change is -usually indicated inimediately elevations to clarify complex piping
to the downstream of the valve, flange or or piping hidden in the plan view.
equipment.
3.19 Full sections through the plant may be
3.8 Valves should be drawn to scale with avoided if isometric drawings are
identification number from the P&ID drawn for the lines. Part sections
marked thereon. where required shall be shown to
clear the hidden details in plan.
3.9 Draw valve hand wheels to scale with
stem fully extended. If it is lever 3.20 Sections in the plan views- are
operated, then the movement of handle identified by numbers say 1-1, 2-2,
position should be marked. etc. and details by alphabets, e-g.
"Detail 'A"'.
3.10 If a valve is chain operated, note the
distance of the chain fiom the operating
floor.
Piping Drawings
PIPING ENGINEERING CELL
I I r I I I I
GENERAL NOTES : H
- 0 -
G
- -
MATCHL!NE AREA - 1
F
- ,
: rJ REFERENCE DRAWINGS : -
: I
E
8 a : '
- : -
:
. F l '
<
-
i
;
W
1
$. ' D
- : a2 .
I
-
: x
.
- 4
MATCHLINE AREA'
.---.--------------------------------
J
KEY PAN . C
- U&M IR N
REV~S~NS
( MSCRlPTlCH 1 DATE 1 CHKD 1 4PPD
DRG.NO. REY. COUP4N.f M E e .
- By
PROJECT : -
CHKD BY TITLE : . C.A.DRAWING Of
PIPING Y(EI - YI A
@PO B?
SHEET: 1 OF I
8 I 7 ' 1 6 1 5 I 4 I 3. 1, 2. I . I
Piping Drawings
PIPING ENGINEERING CELL
I 0 LL w: a U m I <
'F
2
OIST. COLUMN
-
0
L~~
0
-
N
a3
- N1/350
I
350x300
5 EL. 1 13.650M Ln
-
-
0
m
C
0
In
N
$ EL. 1 0 1 . 5 5 0 M
rc)
,,?--.
:;I ;-
" 5 EL. 1 0 3 . 0 4 0 M
-
4b
0
0
-% EL. 100.448M rc)
c b m DR~(~YP)
- =
3 5 0 x 2 0 0 ECC-RED
-
- 0
In
In
* cn
C
B
q jut
- . 2000 - 2000
I A
BOTTOM PUMPS
ALL DIMENSIONS IN MM
L 4 I 3 I 2 I 1
Piping Drawings
!
) 1
FIG. 3 : TYPICAL PIPING ISOMETRIC DRAWING
r
)
Piping Drawings 11
I
PIPING ENGINEERING CELL i
following information:
4.4 Equipment location and equipment
4.1 Plant North -
The direction should be so identification.
selected as to facilitate easy checking of
GA with.Is0 4.5 _ Give nozzle identification on the
connected equipment.
:'
equipment if the specification is
different fiom the connecting piping.
I
. $1 3
<J
.*
Direction of operation. 1
;B
4.8 Size and number of control valve.
I .
;.
s -- 3
.,J
-
. .
- 1
,
. .
r
.
- =
$3
N
. __ . . to. take ; c. a. n of 'site variations, Ciin-- . 1'. g
. .
.. . . also be covered
. . .
with a . g e n dnote.
. . . .
.
,
. . :
. .
. :. . i..J
:)
.
'
.
. ..
.
:' '.
.
. ,
.
,
!
. .
'4
Piping Drawings 12 .
PIPING ENGINEERING CELL
As a general practice Carbon Steel 6.8 Centre lines of the equipment and .
piping 43NB and below are 'field fabricated'. pipelines shall be located with
All Alloy Steel and Carbon Steel spools 50 reference to the building columr~
NB and above are norma!ly 'shop fabricated'. centre lines or the co-ordinates which
Large diameter piping, being more difficult to can be considered 'as a reference base.
handle, more economically produced in
6.9 The distance between the lines shall
workshop.
be dimensioned centre line to centre
line.
Piping Drawings
I
YIPI3G ENGINEERING CELL I
6.10 The horizontal nozzles on the equipment 6.15 For foundation the Top of Grout
shall be located from centre to flange (TOG) elevation is shown.
face in plan. For vertical nozzles show
Face ofFlange elevation (FOF). 6.16 Show dimensions outside the drawn
view - do not cut pictures.
6.1 1 For valves, instruments and non -
standard equipments, show the 6.17 Draw dimension line uibroken with
dimensions from flange face to flange fine line. Write dimension just above
face. . the horizontal line. For vertical lines
write sideways.
6.12 Flanged valves are located with 6.18 The dimension lines can be
dimension to flange faces. Non-flanged teminated with arrow heads or
valves are dimensioned to their centres oblique dashes.
or stems.
6.19 If series of dimension is to be shown,
6.13 For flanged joints show a small gap string them together. Show overall
between dimension lines to indicate dimension .of the string of
gasket. Flanged joints can also be shown dimensions. Avoid one of the break-
without gasket but cover the same with a up dimensions to omit repetition and
general note and include gasket thickness crror during changes.
in the valve or equipment dimensions.
Piping Drawings
PIPING ENGINEERING CELL
6.20 Do not omit significant dimension other 7.1 Title of the drawing.
than fitting make up.
7.2 orientation - North arrow against plot
'V plan.
Piping Drawings IS
PIPING ENGINEERING CELL
7.17 Adequacy of clearance from civil 7.21 Details and section identification
structures, electrical apparatus and match.
instrument consoles,
7.22 "Matchline" provision and accuracy.
7.1.8 Floor and wall openings.
7.23 Presence of signatures and dates.
7.19 Accessibility of operation and
maintenance space and provision of drop 7-24 Accuracy of BOM in ~ s ~ m e t + s -
out and handling areas.
7.25 Number of issues and revision.
7.20 Foundation drawings and vendor
equipment requirements.
b
I '
i ---
Piping Drawings 16
I .
/ Certificate Course
PIPING ENGINEERING
-
May 1I 27,2005
. .
. .
PLOT PLAN
Consultant
: .
PLOT PLAN
T. N. GOPINATH
plant and that of the neighbour, fire hazards, 1.1.3. SOIL SURVEY
location o f ' . power and water supply, , , Soil survey is conducted to establish
expansion facilities,
. 'man-material
, .. . . . . the bearing capacity of the soil which will be
mvmmb eu.in a:balm& m m e ~
. .
.
required for the civil design. The nature of
the soil is also tested to determine the
Before the activity of development of the expansive nature, corrosion properties etc.
plot plan starts, there are a lot of data,
related to all disciplines of engineering, to
be collected and analysed andlor made use
of. Data to be collected before starting can
be classified as follows.
Plot Plan
PlPING ENGINEERING CELL
1.2 Electrical
1.3.10 Steel / Scrap Yard
The data related to electrical will
constitute the supply voltage levels, the 1.3.11 Fire Station
voltage levels required within the plant and
fault levels to establish the power 1.3.12 Weigh Bridge
distribution system, the location of supply
point to decide the location of the receiving 1.3.13 Staff Colony
station and the requirement of the state
electricity boards. 1.4 Meteorological Data
- ...
.
. . : wOrking Of the proces~plant is also required. . . . .c .,I
. .
1.3.7 Vehicle Parking . . .. :
.
. to develop a plot plm. These a&; . . .;I . 3
. .. ..- ., .. .. . .. ..
. . . .. . . . . .
. . .
. . .. . .. . . .&
..
... . . . . . . . . .
.
1.3.8 ~ e d i i aCentre.
l . .. .
. . . 13.1 Size / capacity of the p m e s s unit to . :4 v
. ..
the same.. . . . ' .
8' 1
i) Covered Area 1.5.2 Knowledge on the type of plant, \-- -3
ii) Open Area whether it is to be located indoors or s
Plot Plan
j
. ,
PIPING ENGINEERING CELL
Plot Plan 3
PIPING ENGINEERING CELL
B
23
Based on the data collected as listed above, 2.1.16 Administrative buildings, workshop,
tJ
the following details shall be worked out so cant- laboratories, pilot plant ctc.
that these can be used for the development
of plot plan 2.2 Tentative details of Pipe rack/Sleepcrs
c
* 1
b
. =d
2.1 Block dimensions of: 2.3 -Interunit distance based on the type
and nature of the process.
2.1.1 Process plants considering- the . .
e x p e o ~philosophy
' l ; . . . .. ,. ,2.4 Safety dist;m~afor #e mragfi:. :.:. - ,
'.. . .
: and' :
:. ' . . .
philosophy . . ,expansion. .
' ' . . . .. . . . . . . .. . . . .
requirements
... '
3.0.
. .
. ~ T E .:
iPOI~~TS-TO . .
. .
2.1.3 Electrical receiving station and sub- 3.1. Normally Construction is permitted
station maximum on 50% of the plot area with
total built up area equal to area of the
2.1.4 Uncovered storage spaces plot (i.e. F.S.I. .= 1 (Depending upon
the regulation governing the area and
2.1.5 Solid ware houses the type of industry)
Plot Plan
PIPING ENGINEERING CELL
3.2. Area reserved for tree plantation shall that material handling (solid,liquid) is
be 1/3 of the area occupied. minimum.
3.3. Parking space - 10% of the plot area 4.6 The blocks shall also be arranged
3.4. Water storage capacity - 24 hr. considering prevailing wind direction
minimum. so that flammable gases do not get
The following basics can be used to carried to sources of ignition.
.estimate the water requirement. 4.7 Storage . tanks shall be grouped
according to process classification.
3.4.1 Domestic water - 100 litres per person
Per day 4.8 Centralised control room shall be
located in safe area close to process
3.4.2 Water requirement for Boiler - Steam plant.
rating x Working factor
4.9 Two adjacent process units shall be
3.4.3 Cooling tower - 1114 % of capacity as located based on annual shut down
drift and blow down losses philosophy so that hot work shall not
affect the operation.
3.4.4 Washing - 10.15 litres per day per
sq.R of floor area of the plant 4.10 Process unit shal'l be located on higher
ground away h m the unwanted
-
3.4.5 Gardening 5 litres per day per sq.ft. traffic.
of garden area
4.11 Process units shall be s e ~ c e c iby
3.5. Height of Boiler Chimney H (in m) = peripheral roads for easy approach.
14 Q where-Qis the quantity of SO2
generated in kg/hr. 4.12 Utility block shall be kept at safe area
close to process plants.
Plot Plan 5
,. .
PIPING ENGINEERING CELL
4.18 Raw water storage shall be placed i) Class-A - Liquids, which have flash
closer to water source. Fire and raw point less than 23C
water tanks shall be located together.
4.19 Fire stations shall be away from .the ii) Class-B - Liquids which have flash-
hazardous area and nearer to main point 23C and above but
gate. below 65C
4.20 Effluent treatment plant shall be iii) Class-C - Liquids which have flash
located away &om the process and. point 65C and above but
utility area on the downwind direction. below 93C
4.22 Two gates are preferred, one for the 5.1.2 REGULATORY QUANTITY
material entry with weigh bridge and ABOVE WHICH LICENCE IS
the other one for man entry. NECESSARY
4.24 Process unit can be separated within a ii) Petroleum Class B 2,500 litres -
fencing providing additional gate. provided it is contain& in a receptacle not
exceeding 1,000 litres capacity
4.25 Consider recommendation from the
statutory authorities for inter unit iii) Petroleum Class C - 45,000 litres
distances.
5.1.3 LAYOW CONSIDERATIONS FOR -. - =
DEVELOPING 'MEE EXPLOSIVE . ' l. , '. . ' . .. '. ' ' . .. ' : . :'.
.
.
.
. . . I.t ... I
- ;
.,.
.
.
. , .
.
& mwf&& of
, ,
. ' .
"! .
...--I
.%.
5.1.1 CLASSIFICATIONOF
shdl be calculated after deducting the
volumt of the tanks (other than the
I,
"
- - >
1
PETROLEUM PRODUCTS largest tank) upto the height of -
enclosure. A h e b o d of 200 mm _4
I
. .
Plot Plan
PIPING ENGINEERING CELL
shall be considered in fixing the height bund to allow safe access/ escape in all
of the dyke. wind directions.
In case of excluded petroleum the !
capacity of the dyked enclosure could xi) Distances to be observed around
be based on spill containment and not facilities in an installation shall be a s
containment on tank ~u~ture. .
per the relevant chart fiunished in the
Petroleum Rules. (Refer Fig. 3 &
iii) The height of tank endosure dyke shall relevant Table in the Petroleum Rules)
be at least 1 M and shall not be more
lhan 2 M above average ground level
inside. However, for excluded 5.2 Layout Of Gas Storage
petroleum it can be 600 mm. 5.2.1 Storage Vessels are not allowed
below ground level.
iv) Class A andlor Class B petroleum can They are to be installed above ground
be stored in the same dyked enclosure. level.
When Class C is stored together, all
safety stipulations applicable to Class 5.2.2 Vessels shall be located in open.
A and Class B shall apply.
5.2.3 Vessels are not to be installed above
v) Excluded petroleum shall not be stored one another.
in the same dyke.
5.2.4 If vessels in the installation are more
vi) Tanks shall be arranged in two rows so than one, the longitudinal axis of
that each tank is appro~hableh m the vessels should be parallel to each
surround road. other.
vii) The tank height shall not exceed one 5.2.5 Top surfaces of vessels are requhd to
and a half times the diameter of tank or be made in one plane.
20 M whichever is less.
viii) hhhnurn distance between the tank 5.2.6 Vessels installed with their dished ends
I
shell and the inside of the dyke wall facing each other shall have screca
- dull not be less than one half the' . waIls in between them.
./ height of the tank. Height is
considered-fbmbottom to the top 5.2.7 The distances to be observed between
curb angle, two vessels in one installation and
distance from buildbig or group of
ix) It is better that the comer of the bund building or line of adjoining property
should be rounded and not at right are given in Table 1 & Table 2.
,
angle as it is difficult extinguish hre in
I a 90' angle comer because of the air 5.2.8 The area where vessels, pumping
compression effect. equipment, loading and unloading
i !. facilities and direct fired vaporizers are
, i There should be a a minimum of two
) x) . provided shall be enclosed by an
access points on opposite sides of the
, i
Plot Plan
PIPING ENGINEERING CELL
Industrial Type Fence at least 2 M high liquefied state shall be provided with
along the perimeter of Safety Zone. enclosure wall all around the ground.
The minimum distance between vessel
5.2:9 The minimum distances to be observed and enclosure wall shall be the
around installation shall be as per the. diameter of the vessel or five meters
guidelines in SMPV, which are whichever is less. Ground shall be
reproduced in able 1.& Table 2. graded to form a slope away 6.om
pumps, compressors or equipments.
5.2.10 Not withstanding anything contained The height of the enclosure shall be 30
in the sub rules above, the storage of cm. on the upper side and gradually
LPG can. be placed underground or increasing to 60 cm. On the lower side
covered by earth in such a manner and at the end of which a shallow sump for
subject to such conditions as may be collection of spilled liquid if any, shall
specified by the notifications by the be provided.
Central Government.
5.2.1 1 Above ground vessel for storage of
corrosive flammable or toxic gas in
- ,
:A
-.=,
=,
TABLE 1 I pi
F -
Minimum Safety distances for flammable, corrosive & toxic gases .<
. ,
,.-.
-
I .!
. /
Group of bldgdline
of adjoining property . -?. .
t
.+
, . . ..f
;j-
Not above 2000 . - # .<
, ;
.I
i/
....
I- <)
.<
',
1:.
. . . .
;,
, B
. . . . . .. ...
7 ?
above 40,000 .. . . A 3
- .
. . . , 1-" . b
v . Above 40,000 30 metres 2 metres ..
- - 1
. . 1 : --i
. . . . . . . : 8: --
. . . . J ..
. . . . . . . . .
. .
. .
. .
. . .
. . 1 ,'
. .
. .
i PIPING ENGINEERING CELL
!
TABLE 2
Minimum Safety distances for non-toxic gases
above 20,000
I t I
Y ote: The distances specified above may be reduced by the Chief Controller in cases 1
he is of the opinion that additional safety m&ures have been provided.,
PIPING ENGINEERING CELL
TABLE - 3
Minimum Clearances to be considered in a Process Unit
(As per OISD guidelines)
Plot PIan
!. .
- .
1 PIPING ENGINEERING CELL
ANOTHER PLOT
t
--.-.--
.-.-.-.-.-.-.---.-.-2c.---.-.-.---.-.-.--
3OM WIDE M.I.D.C. ROAD
Fig. 2
Plot Plan
PIPING ENGINEERING CELL
\/
\ /
/\
\/
/\
,
- .'\
\/
\/
0
\/
\/
FENCING
1
\/
\/
LL
+ +LOADING/UNLOADING
=+ PUMPS
++ -~ _ z * - u _ N c ~ . ~ ?PSIE
L
\/
\ / \/ \/ \/ \/
/\ /\ /\ A .".
?
-
Fig. 3: EQUIPMENT LAYOUT. EXPLOSEYE TANK FARM
Plot Plan
Certificate Course
-
May 11 27,2005
T. N. Gopinath
Consultant .
Organized by
Equipment and Piping arrangements During the planning stages, the Piping
cannot be segregated to have different Engineer could meet with simple ideas
approaches since the r&uirements of that can effect substantial cost savings. Let
equipment and piping layout design often us take a practical example to it.
overlap. In a chemical process industry, a waste
Equipment is arranged in the process heat boiler had to be installed at the
flow sequence in plan and elevation and exhaust of a diesel mgine to recover the
piping is laid to effect the pmcess flow. It waste heat. Thc .job was award4 to a
is v q . appropriate to say that the Consulting organization on a turnkey
Equipment and Piping layout design is an basis. The design activities took the
ART and not a SCIENCE.There is not a following sequence.
single formula available for the design of The process group worked out the
Equipment and Piping . layout. The required parameters did the process design
equipment layout design can be as rational of the heat exchanger and issued Process
as the matheamtics of fluid flow but with Data Sheet (PDS) to the Fabricated
the language of projective geometry. Equipment Group (FEG), who did the
Mathematics is abstract; geometry is mechanical design and issued the drawing
visual. All engineering courses have to the Piping Group. Piping Group located
mathematics; few have the subject of the h@ exchanger and designed the inlet
projective geometry but none has layout piping and also did the flixibiity analysis
design. HOWCVQ, systematic methods and of the same piping as it is subjected to
pmcedurts can be developed fiom high w . To save the upipment,
engineering principles, specifications, an anchor was placed near the inlet nozzle
practical engineering knowhow, and just with an expansion bellow. The data of the
SIMPLE COMMON SENSE. All this anchor loading was pascd on' thc
sbMlld be coupld with thC: capacity to Structural Group, who deigned a braced
vis;ualize the armsgcmmt of apipmcnt stmdum to take arc ofthis. The total cost
d pipig tbm dimcmsional~. The h e prohibitive. At this point, a
design must take comtmtibility; sumdon was ma& to tum the waste
economics, safety, quality and operation heat boiler q d d e down slnd thus
hito account. All these should be achieved clbhating the heavy shwture. The final
within the Saportest schedule and will design turned out to be simple, cost
demonstrate the technical capacity along effective and occupied less space. (Refa
with cnative taleat and common sense Fig. 1.1% 1.kb)
approach to problcm solving. Although the
tools to achieve thest goals h a v ~cHqngad
from pencil and papcr to computer
graphics, the responsibilities of the Piping
Engineer remains the same.
d) The area above title block to be kept e) All cquipmmts are marlcd with its !
free for general notes, legends, equipmdt no. as appearing in .a
reference drawings etc. equipment list 8t dimensions (diameter, -
i) One of the general notes s b d d heightncngth ttc.)
establish how to ascertain thc f ) All cquipments centerline art located in
1' :,
- .
datum level. plant building w.r.t. the column grid
ii) The legends normally adopted For layout of outdoor plant / ofkite I
.A f
ii)
Wind influence the location . of- The cross section of such units is
furnaces,cooling towers and stacks shown in the sketches 2.2.2 to 22.5. In
principle all these variations of the layout
shown therein are same. One or two lines
of process equipqg~tsare placed along the
a) Grade mounted Hoe2
..
oat4 pipe rack. Maintenance mads art provided
amnnement parallel to the pipe rack and process
equipments. Central pipe - rack is
In the grade-mounted horizontal in tht line economical as shown in Fig. 2.2.2 and
unit, the equiprnents are placed on either 2.2.3. Air coolers can be placed over the
side of the central pipe rack with auxiliary pipe rack while those at the ground will
roads. The main advantage of this increase the ground coverage. When .
arrangement is that the cquipments are pumps are lined up under the pipe rack
located at grade level, which makes' it with central access and air coolas placed
easier to constxuct, operate and maintain. above, the insuraacc requirement may ask
The disadvantage is that it talres a lot of for sprinklers above the pumps. Tbis type
ground area. The typical layout of a grade of layout is the most economical and
rnountcd outdoor petrochemical plant is thousands of petmchanical plants are built
illustrated in Fig. 22.1. all over the world &g this principle.
Fig. 2.2.2
TYPICAL CROSS SECTION OF AN OUTDOOR PROCESS PLANT
) Fig. 2.2.3
)
I r
i. tompressor r=->
houn II II
Fig. 2.2.4
Air coolers.
outside the ~ i ~ e r o c k'
When pumps are placed outside the rack b) Structure mounted Vertical
that will increase the distance between the &-ranetmtnt
pipe rack and process equipment resulting The structure mounted vertical
in additional pipe length. This arrangement bas equipment located at
arrangement is shown in Fig. 2.2.3. multilevels in steel or concrete structure,
The one sided arrangement as This could be indoor or outdoor. The
shown in Fig. 2.2.4 and 2.2.5 are more advantages of this are small amount of
expensive, since only one side of the area ground coverage and the ability to house
is used to locate the process equipments. the facility to suit process requirements
However, if only a narrow area is or climate conditions. The basic principle
available and or if expansion is to be taken of locating equipment in an indoor and
.up in future, these arrangements give outdoor plant remains same. The
optimum solution. applicable principle is economy. In a
The control room and fiunaces m multilevel layout, the vertical'rdationship
placed outside the main process area, of eqdpmmt also to be c o n s i d d The
keeping the required safe distaaces. confined building does not c h q e the
Auxiliary pipe rack is required to run philosophy of kuiPment layout and piping
cables to control room and piping tiom design. However, the requirements of
furnace to process area Safety distance operation and maintmance diffa.
and maximum ,allowable length of transfer in a building, mobile platforms can
line influence the h a c e location. be used extensively but it is m t practicable
Tlrie baric principle to be outdoors Hence permanent local
remembered while locating equipments in platfom are more common in outdoor
all these cases is to eliminate, combine plants Mobile cranes can be used in
and minimize structures to achieve cost . outdm for maintenance. In indoor, tube
savings. pulling area for exchangers is ta be built
in. Bdding will be costly if this facility is
to be included. Or else, the exchanger will
. . . . . .. .,
. .
. . . .
- .
.. . .
. .
. .
Equipment and Piping Layout . . I0
. . . . . .
- . PWpVG ENGINEERING CELL
I
'-3
I
I
have to be shifted to workshop for 2 3 Piping Layout
'B cleaning which again will need more time 23.1 PHILOSOPHY OF YARD
and hcnce cost. Removal of large vessels, PIPING
1 glass lined kettles etc., will need space The main artery of an outdoor process
I
above or below and also access aisle to plant is the pipe rack. Because the rack is
b outside with adequate clearance. Lifting located in the mid of an outdoor plant, the
beams with cranes located with negligible pipe rack must bc mted first. Hence the
* ! initial cast can make substafltial qvings in development of structural drawing
future maintenance cost. becomes one of d y requirements in a '
> r
is a schematic r e p k t a t i o n of all process
;
.
and utility-piping systems dnwn on a
copy of plot plan or it could be
plamrnetric r e p e o n of the utility
[ ? and proccss line diagrams. Although it
-3 dkGgads the txsct lmations, e l ~ ~ a t i o ~ ~
or inttrferenees, it locates the most
'j 1 congested -area.
The pipe rack splits the plant area into
-a convenient parts. The pi* rick takes
a I various shapes such as 'straight', 'L', 'T',
and 'C' or 'U*.This d p t i o n is based
on the o v d l m g c m e n t and site
.) 1 conditions. Based on the
2
incomingloutgoing lines and locations, the
pipe rack is laid.
? lYP1CA.L CROSS SECTION OF INDOOR
CHEMICAL PLANT
Fig. 2.3.1 to 2.3.7 shows the typical
pipc rack layout for various plant
1 Fig. 2.2.6b arrangements. Smaller plants have the
!
Quipment amj Piphg Layout 11
)
I
I
-5
PIPING ENGINEERING CELL
Fig. 2.3.3
Fig. 2 . 3 . ;
.----------------
Rood
I CONTROL !
i r.-.-- 1 1I
1-shaped yard. Lines can enter and
leove on three sides of the plot
Fig. 2.3..4
.
PROCESS EQUIPMENT : i. . . . .
.
. ..
1 . I-.-.,. I --.,. -.-._I .i . , -. ....:. . - -: .. . ,. . . -.
-'. .., . .. .
-
Strdight-' through: yard. Gnrs con enter. ond . '
leave both ends of the. plot '
. .
. .
.-. . . -
Fig... 2.3.2
' .. .
:
- . .-
. ...
.
.
.
.
. .
.
-
.
.
.
. .. .
.
.
.
..
.
.
.
.
.
.
.
. ' .... .
.
.
. .
.
. .
. .
,I..
i
i 1
\ i L.-.-.-.-., I!
.1
as proctss lines, dicf line headers and
utility lines. The rack should
),
J
I
-,
d
I ,
-Tl-[]:]:I:I:I:rr]
-I-
-
--[]:1:[~
~ ~ s F i ~ i % i iu&ci~-7
TJ I
accommodate the electrical and instrument
cable trays as well. The width of the pipe
! i - -- -- -- - LE0EPPuEN.!J I
rack is estimated as
1: I 528b I. . W=(fxnxs)+A+B
-.-
'>
. .
J
I
., . 1 I
@@@
L--------.---------.--J
S
1
@~sotsn '
i
When
f = ~dcty factor
= 1.5 if pipes arc counted from the PFD
)> Combination of L- and ~-sohped yard.. = 1.2 if pipcs art counted Erom P & ID.
)>
-
1 Fig. 2.3.6 n = Numk of lines in tht dcnstst area
up to the size of 450NB
>I
3 ; I
s = 300mm (estimated average spacing)
=225mm(if lines are smalla than
-4 350NB)
)
i shaped yard. Process and utility lines can
/
PPPmG ENGINEERING CELL !
. . . .
.
.
.. .
. . . .
, , ,
, , ,
. .
.
,
.
. .
. .
. . . .
. . ..
.
.
'
.
- -)
. 3
:;
1
normally -5 to 6 meters.. Wide. spacing -is-. . . . . . . . . . . . . . . . . .. ... . .
. .
.
1 ' -:
. . . . . . . .. . . .. . -
. .
necessary at road - - ,assings .
' ' w b e . . . . .' . . . . ' ' '
.
.- 1
loa&g accm s p e are-need& ni - . - . . .. . ' +.-
-
headroom clearance also dependsupon . . .
1 '
.I
.. -
the type of crossings. - .. ,
.
1
,'
.
-A
. . . .
. .
. .
. . . .
. .. .
. .
I .. .
I :
-<. .
.
-.. .+.
.
-.. .
b. ' i .
TURN I N PIPERACKS
(CHANCE IN ELEVATION WHEN
CHANCING DIRECTION)
Fig. 2.3.10
' p wui C
& STEAM TRAP
. .
GROUP OF LINES WITH EXPANSION LOOPS . .. 1 1
(HOTTEST AND LARGEST LINE OUTSIDE) f
. Fig. 2.3.1 2 . .
. . . .
' * - .
... . . . . . .
. .
J
(PRESENT FUTURE
Fig. 2.3.1 4
EXTENSION OF PIPERACK
The expansion of the rack &OM lJsP be Fig. 2.3.1 6
thought while planning. It is normal
practice to add additional tier on the top.
To accomplish the same, the space above The typical arrangement of hose
station along the rack is as shown in Fig.
the column should be kept free of piping
2.3.17.
or conduit. The preferred location of relief
header is as shown in Fig. 2.3.15.
. .
':
?' I
. ..
1.j i
.
i
I
- Fig. 2.3.15
. . .
(RefaFig;2.3.16).: '
1; . .
.
.
~. .
. .
.
. .
. . .
plans without major modifications.Heavy .- .
.
.-
.
. h i d $ping
~ may be, laidb l o w . '. . . .
233 VALVES-UXATKIN
Accessibility to valves and instrummts
should be the primary concern while
arrapging the same on the piping. Process
isolation valves should be M y
accessible, the valve-stem centdine W g -
at an elevation of 1200 - 1500 mm from rack is shown in Fig. 2.3.20. The valves
the operating level. If at elevated level, are staggered on eitha side of the catwalk
they can have chain operators. Valves When a pipe rack cnters a unit, the
located a t low or high locations can have elevation changes may be required The
extended stems to reach the access aisles. block valves could be installed on vextical
One thing must be ensured that the stem leg in this case as shown in Fig. 2.3.21.
will not be oriented below horizontal This allows relatively easy operation Fig.
level. (Fig. 23.18) 2.3.22 shows two level racks with
elevation charges above or below rack
level. High point vents and low point drain
valves are provided to avoid frustration
during testing. These shall be piped to
accessible spots.
Fig. 2.3.18
Fig 2.3.19
Fig 2.3,21b
Fig 2-3-20,
lJNy&[ RACK
I
. &~UNGEUENT OF R A ~ E R ILIMIT ' .
. . ISOL~Nl'VfOLMLRhCK- , . .
. - ELEVAT0.N C U G E . .
. .
.
. . .
.
Fig 2.3.22
.. .. .
.
.
. . .
.
.
.
. .
. . . . .
.
. . . .
TRAYS .
Fig 2.3.Z1a ' .
The Electrical and Instrument cable
J ' traylduct location is coordhted in the
design-planning phase itself and integrated
in thc o v w anangancnt.
Space for thew h y s is provided above
I the piping on the pipe rack. Future
)
-
-.-
TYPICAL PIPE RACK CROSS SECTION FOR PtPlNG ARRANGEMENT
Fig. 2.3.24
the edge of the yard, with orifice flanges (&ired) Rdes 1981.
I I - -,
near a rack column for access, with a d) The Gas Cylindk Rules 1981. I - I
portable ladder. Orifice runs after pumps e) The Indian Boiler Regulations 195I.
can be located near supporting column at f) I)evelopment'control rules by the State
2.5 rn level. Control valves are usually Industrial Development Corpo&tion. I
located near rack columns for convenient I
equipment and for connecting equipment Examination Technique where you ensure I
on opposite sides of rack The dimensions that all the following parametas are well L5
D and E at not more than the r e q u i d yard addrtssed
height will reduce the vertical pipe nms. a) It is p~ocessadequate? I
However, the distance E is kept 1 to 1.5 m b) It is opcrat~rfiricndly?
to have a proper erection and maintenance c)It is umstmctim clear? - ,I - 2
access and depends on the size of the pipe d)Has adequate maintenance -.
at the lower tier. provided?
., .
' 1
e)How to evacuate in case of emergency?
23.9 STATUTORYREQUIRE~MNTS OHas safe fire fighting access provided? I
- The layout designer should familiarize g)Starndad practices where-applicablehas 3
himself with the law of the l a d while been adqtd?
planning the equipment and piping h]is the piping arrangement aesthetic 9 I
j
mgement. The rcqUirement as per the i)Is supporting arrangement adequate and
,
followidg shall be adhered to: hetic?
a) The Factories Act 1948. j) Is p i p i i adequately flexible ? r - -9
b) The Petroleum Act 1934 & The
Petroleum rules 1976. - $
c) The Static and Mobile Pressure Vessels I ;
,
a;.
. Basically there are two types of pumps,
; :1: displacement and can deliver constant
.
j1 7:
.
.., . the; centrifugal type and the positive pulsatien fiee flow against higher head
. . disp,h==t type. than the centrifugal pumps. The layout and
The centrifugal type could be a single piping design do not differ h m that of
stage or a mdtistage The single stage catrifugal pumps.
pump has one impeller and multistage Reciprocating pumps are used where very
pump has two or more impellers in saies. high head is needed for a low flow. Here
The discharge of one impeller is the the discharge cannot be throttled to obtain
suction of the next one and the head capacity control as in the case of
developed in all the stages rn total& centrifugal pump. Imkd variable speed
Based on the suction and discharge drive or stroke -a&usheats is wed. The
ammgegsent the type of pumps availqble alternating action of reciprocating pumps
are produces pulsation flow. The extent and
(a) end suction top dis&arge firequency of pulsatian depends on the
(b) top suction top discharge number of cyl- in parallel and
(c) side suction side &charge. whether they are &glc or double acting.
Due to pulsating operations, these pumps
The end suction top discharge pump has are bulky, but are considered for very low
vertically split casing and the end suction flow applications. The pumps could be
end discharge pump has horizontally split single acting wit$ single piston plunger
casing. Vertically split casing has good with very high pulsating flow. The
maintenance access. They w normally the variation in cylieder arrangements gives
single, duplex, triplex and quadruplex arranged under the pipe rack in a refinery
pumps. The diaphragm pumps are or an outdoor process plant, keeping motor
compact and deliver precise quantities of end towards the access space and
fluid. suctioddischarge faces towards the
The positive displacements pumps are not process vessels (Refer Fig. 3.1.1). Siaglc
suitable for pumping slurry and are not pump should have access all around, a
suitable for abrasive services. minimum of 900mm. When space is
restricted, or the pumps are small, two
pumps can be placed on common
foundations with the orientation of the
The design of equipment and piping motor terminal modifled if required.
configuration affect the energy used and (Refer Fig. 3.1.2)
capital cost of pumps. Hence, economy of
piping and structures along with ease of
operation and maintenance . are the
principal aim while arranging the pumps.
I'umps arc placed close to process vessels.
Number of pumps should be lined up and
aesthetically well arrangd Pumps are
PYIODCIlYPYllUHQYCn
PUMP ARRANGEMENT
Fig. 3.1.2
OF PUMPS
RFFINERY / PETRO-LCU PI *NT
Fig. 3.1.la
-
I I
Fig. 3.1.3
Fig. 3.1.lb
ECC RE0
FSUl I A
FOOT V U K
I ' ) -
A
I'
IPWIP4G ENGINEERING CELL
R - 1.50
@ ; . .
----I-
. . . . .
. .
. . . . . . .
. . . . .
. .
.
. OPPOSING. . . JUNCTION - STAM. LINED. .
. '
. . .
. . ,. .
. . .
. .
. . . .
. .
- . . : : . . . . :.
.. . .
C L .
. .
. . ... :
... . . . . . . . . . . . . . . . . .
' _ . . . , . . . .
. . . .
. .
. .
FIG 3.1.6
i
3.2 Compressors discharge to avoid backpresswe. To avoid
Basically there are two types of vibration due to pulsating flow the
compressors used in the chemical pmess customary piping details are modified as
industry. They are the centrifugal type and follows.
the reciprocating type. a) Use bends instead of elbows
Layout and piping considerations for the b) Use angular inlets instead of laterals
centrifugal compressors do not differ in c) Use smoothjunction instead of head on
concepts from arrangement of centrifugal opposing flow.
pumps. However pipe sizes are much d) Use streamlined end-of-header
larger because of the large volume arrangement instead of dead end header
handled. These have horizontally split (Refer Fig 3.1.6). Components having
casing. Those having bottom connections large pressure drops should be avoided.
are elevated. Concrete columns and Types of valves should also be selected
tabletop arrangements are provided with accordingly. Support the piping at
surrounding access platform. directional changes and at valves. Support
C o m p m r foundations are kept should also h c t thc pipe movements.
indepcndcnt of building foundations. A High pressure and high-speed compressors
hand operated travelling rrane located at must have pulsation dampeners to
compressor centre line is to be provided eliminate pulsation in suction -md
overhead. Lay down space also has to be diiharge piping. If pulsating flow is
planned for. Knockout + and inter transmitted to piping, structures and
stage exchangers are so arranged as to process equipment, material fatigue can
have short and simple piping. Long radius occur. Dampeners' design is highly
elbows should be used immediately before specialized and manufacturers
the compressor suction. A straight length recommendation should be followad
of 5D at the suction is normally provided. N o d e velocities at inlet and outlet are
For air compressors, strainer has to be Limited to 15mfsec. While planning the
provided at the open-air inlet. layout, provision shall be made for thesc
Lubricating oil and seat oil consoles are dampeners.
atso to be located which occupy large area
near or under the compressors. 33 Heat Exchamgem
Manufacturer's mmmendation should be The information required for the
followed in this case. Equipment and Piping layout as applied to
The reciprocating c o q m s o r s are located h a t exchangers is the same as that
on concrete foundation at grade level and required for any other equipment and has
not on a concrete tabletop. The basis of lay beepl explained edier.
down area, foundation and the m f above
are identical to that of a centrifugal 33.1 EQUIPMENT LAYOUT
machine. The position of an exchanger in a
The piping interconnecting the pulsation Chemical or Peirochenaical plant depends
dampers, intercoolers, after coolers etc. on the location of the didlation
should be short and simple to reduce the vessels/columns. The relahvt position
vibration. It is advisable to provide a should be evaluated h m the process flow
vibration dampener (expansion bellow) at diagram PFD).
the outlet of the comprtssor. Sufficient The following general concepts apply for
straight length shall be provided after the locating the heat exchangers.
The basic types used in the\chernical facilitate channel, shell-cover and tube
process industry are bundle removal, as well as maintenance 1
a) Fixed tube-sheet Heat Exchangers: and cleaning. 1
Exchangers with complete enclosed tubes b) Excessive piping strains on the
are mainly used iu clean services.
Cleaning can be done by flushing through
exchanger nozzles h m the actual weight
of pipe and fittings and h n forces of
r I
the tube side and shell side. C l a out thennal expansion should be avoided.
connections are provided in the piping
between the exchanger nozzle and block
c) The piping shall be arranged in such a
way that no temporary support will be
i. -~
valve. The bolted cover and channel required for removing the channel and
facilitate inspection and physical cleaning tube bundle. . 1 -
of the tubes. When used in high d) Provide easily removable spool pieces,
temperature services, an expansion joint is flanged elbows, break flanges, or short t
built into the shell to take care of the pipe runs to provide adequate clearances
differential expansion between the shell for the operation of tube removal. i
and the tube. t ) The pipelines with valves and control -
a >,
b) 'U'tube Heat Exchangers: valves should run along with access aide
In this type, the tube bundle is hairpin
shaped and can f k l y expand. The bundle
closc to the exchanger.
f ) Pipe line connecting the exchanger
! -;L
-
is removable from the shell and provision with djaccnt process equipmmt can run I C I
in layout has to be made for the same this point to p i n t ' just above required I j
The following alterations can be suggested b) Angular n o d e can save one or two
in order to achieve an optimum piping bends in the pipeline. The maximum angle
arrangement. Consent from the process h m the vertical centre line can be about
0
group is requid to ensufle tha! these will 30 .(Refer Fig. 3.3.4)
not affect the thcnnal design of the
exchanger. The cost increase in
modification can be more than ofhet by
the cost effective piping. These factors
iduence the decision on piping routing as
well.
a) Elbow nozzle pennits lowering of heat
exchanger to grade to have better
accessibility to valves and instruments.
(ReferFig.3.3.3) . r;l
Angular connection for top ..nozzles
Fig. 3.3.4a
C) Horizontal a ~ h m g e r A be turned
vertical for comewing floor space.
Verticd exchangm can be changed to
horizontal when installation height is
restricted.
d) Exchanger saddle can also be relocated
to adjust to a iie-up or combined
Elbow n022li reduces he~ght of stocked exchanger
Fig. 3.3.3 fou11dation design. (Refer Fig. 3.3.2) ,
'jrF~-
.$=!!zL
-
Undcsiroblc
Slope
Out I
Roof
Slope
Out
o
f;
Vent 4.
ii) System hos loop and pocket ii) Gravity-flow suction line abtoined
by chonging direction of flow
through exchanger
. .
. . . ..
..
t-
. .
.
.
' I
I
'
,
. I
Pipe' Pies :
Rack 7 I Rack 7.
iii) Zig-zag flow p d t e r n iii) ser, piping ond better flaw pattern
1 productd by relocating nozzles.
etc. These could be horizontal or vertical. on welf-oricnted nozzles. The nozzle and . f
f
-2
support oricntation can be d u a t e d as
3.4.2 Drums are with internals, often below. (Refer Fig. 3.4.1) I- it -I -
required type or with cooling/h&g coils -oneen& Bottom inlet is also possible but . - . ..,.
! 3
or jacket. The material of construction can with d standpipe. Outlet is placed at the I .
v q h m carbon steel, stainless steel and bottom on the other end. The bottom inlet %
glass lined. These reactors are normally 1 '
is provided in cast of large diameter
vdcal. piping to save pipe and fittings. In some -
b-
These vessels are located in a process cases, the inlet and outlet are centrally 9
flow sequence. The area q u i d around 1 '
located. The vapor outlet in this case shall
reactors is much more compared to other be diametrically opposite to liquid inlet _%
process vessels.
The manual loading of thest, if b) Vents and Drains f . 1
required, also shall be facilitated. Hence Vent nozzles are located at the top and
these reactors will be located passing drain at the bottom of the other end.
' b
1
1 - .
A
. Fig. 3.4.;.
-
Vessels are sloped towards drain point. If g) Vessel saddles
the vtssel has a top manhole, the vent can Ideally, - saddlcs art located at 115 of
be located on the manhole cover. The the drum length from each tangent line.
drain valve can also be located at the low The vertical vessel can be supported on
' pomt of the outlet piping instead of vessel. skirt, on half skirt, on legs or on lugs as
c) Relief Valves/Rupture Disc the case may be. The analysis of the
Located anywhere on the top of the support attachment shall be done
1:-. dnxm, preferably at accessible location accordingly.
fmm the platform provided for valve Location of associated equipment mund
operation. the vessel also influences the nozzle
d) Level gauges orientation The liquid outlet should be
The gauge glass shall be located at the located towards the nearby pump suction.
least agitated liquid section. If the vessel is The elevation of the vessel should be such
horizontal, the location is best at the centre as to provide the required NPSH. In a
of inlA and outlet node. reactor, the manhole &odd be oriented
c) ~ueandTempccaturetap-offs. towards the access aisle to hilitate
Prasswe connection at the vapor space w u a l feed if mpmd. The utility
at the top of the vessels will make it manifold and t4c prscess inlet manifold
visible from the platform. The temperature should be placed at the operating level
connection shall be near the outlet hespective of the n o d e attached to the
pointing towards the platform. vessel.
f) Manboles The piping should run overhead as short
These can be positioned ~n the top, to and as simple as possible. Pipe rack shall
the side or at one end of the vessel. be arranged whieh will suppart electric
I)cpcading upon the vessel size, can and instrument trays along with pipelines.
be two manholes, one located on top and Piping should not transmit vibrations and
the other is located on the shell accessible should be isolated from vibrating
h m the grade. equipment with the help of apansion --
I
I
i Equipment and Piping Layout 35
t i
PIPING BENCIPJEEWBG CELL
bellows or hoses. Such equipment. are envisaged and detailed in the P & I
centrifbges, filters, dryers etc. In all these Diagrams.
cases, interaction with the manufacturers The structural arrangement for support
of equipment will always yield positive also contributes a considerable part in the
results. economy of installation. Certain
While detailing the layout and piping, it economical arrangement of support is
should always be borne in mind that this illustrated in Fig. 3.4.2 to 3.4.5, which are
should achieve the best performance as selfexplanatory.
r V a s s e l Lugs
f Less econornicol)
: kcass\
- (More econornicol)
reodor footimgs Verticol Drum
Fig. 3.4.3 . Fig. 3.4.5 . ,
Fig. 3.4.4
I '
PIWXNG ENGINEERING
. . . CELL .
t wd:Piping Layout
~qui~rneri
PIPING ENG1[TBdEEMNGCELL
******a**
:.
.. *
I
.
Certificate Course
f . on
r
.
PIPING ENGINEERING
. . .
May 11 1 27,2005
. i, . .
8. .
.
MECHANICAL DESIGN FUNDAMENTALS
-.,
I ...I ,
.'
:
'--II
:. 7
. .
-I.,,
1
.q
; Prof. A. S. Moharir . , , . ''
IIT Bombay.
i'
)I:.
.3.. :
-j . ,
>.:
- i'
...
? -:
Y;. , .
.'.;
. . . .
..).\*, . . .
J:-'...: . .
. . . . . .
.
.
.
.
. . .. - . . . . . .
. .
. . . .. . . . . . .
j . . . .
. . . .
.:
. .
I..: . . . . . . . . . . . . . . .
. .
.. . ..
. .
... O .r g a n i d b y : . . . . . . . . .
.
..
.
.
. .
.. . . . . . .. . .
. . . . . .
.
.
.
.
. . . . . . . . - . . .
.
--" .
>:. !
Piping.Engineering Cell
,
.
.
.
.
.
.
.
.
.
.
.. .
. . . . . . . .
. . . .
PIPING ENGINEERlNG CELL
1'
Mechanical Design Fundamental 2 -
BHPHNC ENGINEERING CELL
of a rod or wire during the course of which involved here and are briefly discussed to
its cross-section diminishes and the prepare the background for design.
stresses for an applied load increase is the Most materials of construction
simplest example. Specimen tests for used in the process industry are metallic in
determination of material properties such nature. Pure metals or alloys of v 'ous
as modulus of elasticity, ultimate tensile compositions are used for given s g c e .
stress or strength, fatipe behavior under While the first choice is dictated by the
cyclic load etc. tests the material behavior chemistry between the MoC and the
till such ultimate failure occurs. Some of process fluid, the ultimate choice from
these properties are crucial design inputs. among various options, which satisfy
chemistry considerations, is on the physics
SPECIMEN TEST AND IMPORTANT of the MoC. The important properties used
MATERIAL PROPERTIES FOR in design are temperature dependent and
DESIGN are experimentally determined using a
specimen test. The results of such tests in
Mechanical properties of any terns of properties of various Materials of
material of construction are dependent on Construction at different temperatures are
their chemical composition as well as then compiled as material standards. Each
method of manufacture. The choice of country has .its own standards institution
material of construction (MoC) for a given and may also follow several international
service (fluid to be handled, pressure, standards.
temperature etc.) depends on both the A schematic of a typical specimen
chemistry and physics of the MoC. test apparatus is as shown in Fig. 1.
The chemistry decides the
material's interaction with the fluid that it
is expected to handle. A suitable material
which would not be chemically reactive
with the fluid and hence will not be
corroded itself andfor contaminate the
contents with *corrosionproducts, which is
hard enough to withstand the erosive,
abrasive action of the fluidlsolid that is
being handled, etc. is important to choose.
Choice of material of construction from
this point of view requires expertise and
know led^^ -of metallurgy and chemistry. Fig. 1: Typical Specimen Test Apparatus
Broad guidelines for choice of MoC have Aspecimenpieceofah4cCisWfiun~
emerged. These are, however, outside the the jaws of the test machine and can be subjected
scope of the present topic. to t d e bad by pulling , h ejaws apatt with a
Another important aspect is that known fbrce or a cornhive load by
the material sb chosen be adequately ~themcloserwi~laYlwnfiRce.?be
strong so that any structure, which is made spimen can also be subjected to a cycle of
out of it, can withstand process conditions tmsileloadarad~eloadwithkmwn
for reasonable amount of time. Some basic ampIib.de and kcpmq. Mated Material can
concepts &om strength of material are be stdied under sllch applied loads arxl its
plqX&*ed
The two lmportarrt parameqers which situation arises when the specimen does
qum!@the behavior of a specimen are the strain not return to its original dimension. even
a n d t k ~ F o r t e n s i l e ~ i h e ~ i s when ~ l y the load is withdrawn. This is also
h e d o of inaease in length of the specimen the load level (or stress level) at which the
l m d e r ~ ~ l o a d t o h o r i @ l a g t h stress strain curve begins to deviate fiom
ofthe ~ k h e t h e l o a d i s a p p l i e d F o r the elastic straight-line behavior as shown
mmp&e load, it in simhiy the ratio of in Fig. 2. We say that the metal is
decrease in length to the original lengthunda undergoing plastic deformation in addition
sustained load Strain is thus an observable and to elastic deformation. When the load is
measurable quantity as the artensian or withdrawn, elastic deformation is
m ~ o of nthe specimen can. be c l k d y recovered but the plastic deformation
mea&red strain is also a dimensionlesscpntity- stays.
Stressisde~astheapplidloxlper Most metals exhibit an erratic and
unit d m of the qmimenUnlike strain,it uncertain stress-strain pattern as the load
is dimensional The common wits fix shs are increases fiuther. The circled region in
psi @ ' d scpm inch), kPa, MPa, kg per Fig. 2 shows this. The highest stress that
&an.etc. d q d i n g on the system of units the metal can withstand under sustained
used fbrfaceand lineard i m 6 load without continuing to elongate under
When tbere is rn k d , there are m same load is called the upper y&ld point.
skses and no drain When a snail tensile load is There is also a cluster of lower stress
applied, the strain can be measured and dms values at which there is accelerated strain.
derived. If h e load is ranowl, h specimen The lowest stress values among these are
returns to its original shape. That is rhere is no called a lower yield point (Fig. 2).
residual orpamanentstxaininthe specimen If the specimen test is carried out
s i t d o n &ues up to a cabinlevel of stress. A with different specimen cut out fiom, say,
stxsdmb curve in his region is also a shai&t the same piece of rod, each may show
Line(Fig 2),ie.~kts~is~rtionaltostrain different location of upper yield point. All
such specimen of same MoC would,
! however, exhibit same lower yield point.
Upper Yeld Points
The upper yield point depends upon the
chemistry of the MoC but also upon the
way the molten metal was frozen in a rod
or plate mill at manufacturing stage.
Stress During this sudden quenching of ,molten
L o w r Yeld Points
metal, crystals and crystal aggregates get
interlocked in awkward nosition and they
get to readjust themselves only during
stress tests and when plastic deformation
Slrain begins beyond the elastic deformation
range. This relaxation is reflected in the
Fig. 2: Typical Stress Strain Curve location of upper yield point. As d i f f m t
portions of the same rod or plate would
Most metals and alloys exhibit this have cooled down and frozen differently
behavior. This region of the curve is called under cold shower during m a n u f d g ,
the elastic region, as the MoC's behavior location of upper yield point cannot be
is elastic like a rubber band. As the tensile said to be a reliable property of MoC but is
load during the test is increased further, a
I
Mechanical Design Fundamental 4
7
PIPING ENGINEERING CELL
Strain .
can one have a stress value (corresponding applicable for the design temperature
to point C in Fig. 4), which is larger than should be obtained from the codes. Most
the yield stress? The structural element often, allowable stress value applicable at
should have disintegrated much before design temperature (also called design
reaching that level 'of stress. The conbion stress) is directly available from the
can b e avoided if one remembers that tJlis standards. If not, other available material
is only a convention followed while doing properties and recommended safety factors
stress calculations and gives, in a way, an should be used to arrive at allowable stress
hypothetical stress value. One must value. For example, if yield stress or 0.2%
remember that stresses, unlike strains, can proof stress value is available at design
neither be observed nor measured. They temperature, the same should be divided
are simply derived quantities. Such back by a safety factor of 1.5 to get
calculated stress values are often called allowable stress, if yield stress is not
'code stresses'. as they are calculated using available at design temperature but is
strain value and the modulus of elasticity available at room temperature, the same
reported in codes. '. should be divided by a safety factor of 3.0
to get allowable stress. If stress value for
Yield Stress & Ultimate Tensile rupture due to static fatigue or creep
Strength: failure is available at design temperature, a
UTS or Ultimate Tensile Strength safety factor of 1.5 may be used to get
or Ultimate Tensile Stress is that value of allowable stress. These safety factors are
stress beyond which plastic instability sets recommended for carbon steel and low
in as discussed earlier. Obviously, design alloy steels.
should be such that this level of stresses is Choice of design temperature is
not reached during the life of any crucial to get the allowable stress.
structural element. The lower Yield Point Knowledge of the process is very
discussed earlier is also called Yield important here. The howledge should be
Stress. not only about the normal operation, but
also about start up procedures. How the
Allowable Stress: structure part attains that temperature is
Yield Stress is used to decide the also important. Some of the commonly
allowable stress for any MoC at any used guidelines are as follows. For parts of
temperature by incorporating a suitable a structure, which are not heated directly
safety factor. Allowable stress is often but attain temperature because they are in
defined as the UTS divided by a safety contact with* the stored or contained
factor. The safety factor is obviously material, highest expected temperature of-
greater that 1. Designs which ensure that the stored material should be the design
the stress value anywhere in the structure temperature. For structilfal parts, which
is less than this allowable stress are are heated (say by steam, thermic fluid
considered safe designs as they do not etc.), highest expected temperature of the
allow the structural element to come heating media or highest expected body
anywhere close to the point where plastic part temperature plus 10C should be the
instability leading to disruption or design temperature. Here, 10C is the
disintegration of the element would set in. safety margin. For fired vessels, parts
Allowable stress decreases with which are shielded (say by r e h t o r y
temperature and an appropriate value lining), safety margin is 20C and for
carrying cross-section (cross-section of the The material seems to count only the total
specimen) diminished to compensate for time for which it was subjected to the load.
elongation (as volume c ' the metal in the
specimen remains the same), which led to Cyclic Fatigue:
higher stresses causing further elongation Here a specimen fails under a load
etc. Such failures are termed catastrophic cycle, which it has withstood for a
failures. These failures occur almost considerable number of times. The total
suddenly as soon as the load crosses a number of cycles for which the load was
threshold (ultimate tensile strength). These applied is important here. Whethex the
failures take place on the first occurrence cycle was frequent or infrequent io not
o f loads in excess of yield stress. Their is important. For example, if a material
another kind of failure, which is not undergoes cyclic fatigue failure under a
catastrophic in nature but occurs because load cycle of amplitude say X in say 1000
o f the damage done to the grain structure cycles, it would do so irrespective of
o f the specimen due to prolonged whether
application of sustained load and/or
tensile-compressive load cycles. The 1) the cyclic load was applied once every
history of applied load plays an important day for 1000 days, or
role here and the failure is said to have 2) the cyclic load was applied twice every
resulted due to Fatigue. day for 500 days, or
3) the cyclic load was applied with cycle
There are two kinds of fatigues: time of 1 minute and for 1OW minutes
Static Fatigue and Cyclic Fatigue. etc.
process plant are thus: sphere or coinciding with its minor axis would
hemisphere, cylinder, cone or a fnrstum of generate an ellipsoidal closure shape and
a cone, ellipsoid and torus. Design of such so on. These shapes of revolution are
body shapes implies decision regarding shown in Fig. 7.
their wall thickness for given inner or
outer overall dimensions which will ensure
that under the worst pressure and
temperature conditions, these shapes do
not develop stresses which would cross the
allowable stress limits. For each shape, the
codes give simple calculation formulae
which are often used without much
thought to the roots of such formulae.
These formulae are rooted in applied
mechanics, safety considerations,
fabrication considerations etc. It is
proposed to offer here a general applied
mechanics approach to the development of
relation between stress and applied load, Fig. 7: Shapes of Revolution . '
i
J
, -
I
1
Fig. 9: Differential Element
circumferencial radius of curvature may be
Let us define two-dimensional parameters larger than the conventionally d e h e d i ii
. of the arbitrary vessel shape. For known radius of a circle.
vessel shape, these parameters would The radius of curvature of the arc
automatically relate to conventionajlyused AB (and also CD) is called the meridianal ! .
dimensions such as radius of a cylinder radius of curvature.
etc. Let us now obtain the components
The pressure acts normal to the of the forces due to induced stresses acting I '
.surface of the tile ABCD. In view of the on the edges of the tiles, which oppose the
small dimension of the tile, it can be pressure forces. .
approximated to act at the center of the tile
t ' I
as shown in Fig. 9. As the tile is a part of Consider Fig. 10. Concentrate on the edge I
;
the vessel which is symmetrical about the AB. Let F be its focal point and r, the "
I '
pressure force if extended towards the AB subtend an angle de, at the focalpoint. .
. . . .
inside of the vessel would intersect the 4, i
- axis of rotation at,some point I- as shown in . .The
- ... induced ,.alo?g,@g= .AD% . . . : I, . . ... . . . .
BC are. obviously 'perpendicular t o the . , I .. .
Fig. 9. Also to be noted is the fact that AD
and BC are arcs of a circle. . .IiBes.
... . . . . FB respectively. Let these . . . .
FA and . . . . .. .
:s~essesbedenoted . . . . . . . . :.;..
by o,. ?hese'stresses . . . . .
. f
.
!
. 1.
If the circle of which AD (and &o . . .
:
...: .
BC) is an arc is to be drawn fiom point I, ha& a component. along the tion on
'
....1
its radius is called circumferencial radius hig. which pressure . force acts.. m s ' . . ' .
I'
,.,,
of curvature. It should be noted that it may direction bisects the angle. do, as shown. i
1
not be the same as the conventionally The~'strrn~es act along edge ck+,,The net: , . - -1
defined radius of a circle where we dr& force is thus &,.t and its component in a !- i
the circle fiom a point in the same plane as direction opposite to the direction of force i
1
that of the circle. Here, point I may not be is &,.t. sin (de,/2). As the situation on
in the plane of the circle and the I ' i
edge BD is similar, its component is also
d
3
Mechanical Design Fundamental
PIPING ENGINEERING CELL
Similar to the above treatment for stresses along edges AD and BC is the treatment for
stresses along edges AB and CD as shown in Fig. 11.
. . . . . .
. . . .
. - Fig. 11.:Force Componen& . . . - - . . .
. . ... . . . . . .
-
. . .
. . , . . . . . . . . : . . . .
2.a,.ds2.t.sin(deJ2) + 2.c~,.ds,.t.sin(de/2)
= P. ds, .ds,
The tile P C D had infinitesimally small
dimensions and therefore, fiom the Let the allowable stress be Sa. The
geometry (Fig. 10,ll) following identities thickness should be so chosen that a
should not exceed Sa. Or, from the above 1
hold.
ds, = r, .sin de, = r,.de, relationship,
PD PR 1 . -
ds, = r, .sin do, = r,.de2 tl- or t2- ! :i
sin(d042) = d6J2 1
Y
I '
t rl r2
his relationship between the
circumferential and- longitudinal stresses
and the geometry of any shape in ternis of
its two radii (r, and I,) with the wall
thickness and pressure can be used for any
shape.
IBe design (that is: thickness - 1) i .
. . .
-should be such that :everywhere in - the - . - . ..Fig.:1 ' 2 : F o ~~alance
. -.
.
e on a Section.
shape, the stresses-should. be within-the :
.
. .
. .
. , .:
.
.
:
Separate .ckdar
relationships for the two stresses 6,and < - section - downwards .must be
balanced by . the foice due the 'vertical '
..
For a simple shape such as sphere, bmponent of the longitudinal &, o,,
however, the above reIationship is acting'on the edge of this circle of,wida
sufficient in itself to find a suitable equal to the thickness t. If such a balance.
thickpess for a sphere of diameter D. is taken, one gets a relation for
The user should verify that for a longitudinal stress as
... . . .. , .
sphere, the rneridianal and circumferential . . .
. 2. Qa:. ,
.
, . . ' . ' S a .
,
-. correction in the denominator can be seen
... :
. .
to be more for cylinder than for the sphere.
where D and R are the diameter and radius This apparently has something to do with
of the cylinder respectively. For other the earlier discussed fact that for same
shapes, similar approach is to be followed. material, the spherical shape would fail at
Getting the two radii of curvature often stresses lower than the yield stresses for
reqwes more involved relationships iiom solid specimen and cylinder wotiC fail at
geometry for these and more complicated even lower stress values. This shape effect
shapes. is captured in the second term in the
denominator of the code design formulae.
w 4
5 -
Mechanical Design Fundamental 15
-=t
PIPING ErU'GIPJEERTIYG CELL
.?>
?, Code formulae have been under equ~pment or supports etc. that this
constant scrutiny. They represent a sum movement is prevented, compressive or
total of theory, safety considerations, tensile stresses would develop in the pipe
,I
i fabrication limitations, experience with wall. Sometimes, pipe sections are forced
behavior of designs carried out during the to change their route. These additional
past, acceptance of human limitations in loads on pipe have also to be taken into
understanding physics of solids and account while designing and routing a pipe
experimentally &asuring some of the section. Mechanical design of pipes need
important material and above to consider all such kinds of loads together
all, an overriding concern that the design and still offer safe operation. This
should be done to reduce (to extremely necessitates detailed analysis and a broad
low levels) the probability of d'lsastrous area of stress analysis has evolved for
failures causing damage to heaith of study of critical pipe sections.
concerned people and environment. Even for vessels, just designing the
Caution is the watchword of mechanical body is not sufficient. There have to be
designers, and rightly so. opeAgs on the body to provide for
several things such as inlet and outlet of
CONCLUSIONS process fluids, drainage, inspection,
instrumentation, maintenance etc. These
The paper attempted to discuss the openings would weaken the portion
important basics from physics of solids surrounding them and need to be specially
and applied mechanics, which form the considered for possible reinforcement. The
foundations on which practical design vessels have to have closures, which need
procedures rest. The actual designs are to be fastened in a leak proof manner to
subjected to several otler sources of the vessel body. The design of flanges,
stresses and strains such as compressive or gasket, nuts and bolts is a part of vessel
bending loads due to own weight, design. For pipe-to-pipe connection or
compressive and tensile load due to pipe to equipmeht connection, similar
vibrations in 1 structures due to design of flange, gasket, bolts etc. is an
seismicity, wind, eccentricity etc. In integral part of system design. Any.
additions to the above discussed loads due process industry has so much of piping,
to internal pressure, which lead to tensile that some of these designs have been
stresses, a structure may encounter standardized to a large extent and one
compressive stresses due to net pressure picks fiom available standard designs
acting h m outside. This gives rise to the 'rather than designiig -Eom-scriitcti every
possibility of failure due to buckling and t h e . Even then the basics of design
needs to be studid separately. A separate should not be overlooked.
set of design formulae for such special Designing structures that we see in any
cases is provided by the codes. chemical process plant is extremely
Structures, especially pipes also involved. These designs have to bear with
encounter thermal loads. Pipes are harsh process conditions inside and a more
installed at ambient temperature. During and &re safety conscious society outside.
operaticln, they cany fluids, which are at These m also d e s i p , which do not have
super-ambient or sub-ambient the luxury of full dress rehearsals. They
temperatures. The pipes would expand or must be right in the first attempt. Always
contract. If the pipes are so fastened to kzeping the theory in mind and
scrupulously following the codes and the least forgiving technology,' the
8
!
I standards whenever they are available is Chemical Process Technology.
the only way for designers dealing with
I
Table 1: SOME DESIGN FOIUMULAE
Shape Theory Code
Based on ID Based on OD
P. Ri P. R i P. Ro
Sphere t=-
2 Sa 2SaE-0.2P 2 SaE+0.8P
-
P. Ri P. Ri P. Ro
Cylinder t=
Sa S a E - 0.6 P Sa E + 0.4 P
I
I
'i - inner dimension . .
! o -outer dimension
-- . E - weld joint efficiency
j..
I -
May 11 27,2005 I
STRESS ANALYSIS
T. N. Gopinath
Consultant
STRESS ANALYSIS
T.N.GOPINATH
1.0 INTRODUCTION
1 . 3 . . Decide the allowable limits, the ii) Can readily be judged adequate by
system can withstand without comparison with previously analyzed
failure. systems.
1.3.5. After the system is designed, to iii) Satisfy equation specified in clause
ensure that the stresses are within 119.7.1(A3)/ 3 19.4.1 (c)
the safe limits. 1.5.2 Analyzing the layout by an
1.4 Types of loads approximate method.
All the American code for Pressure Approximate method shall be
Piping classify the loads mainly into three applied only if they are used for the range of
types. configuration for which adequate accuracy
has been demonstrated.
1.4.1. Sustained Loads: Those due to .5.3 Carrying cut a
forces present during normal
analysis.
operation
i) Analytical , . .
1.4.2. Occasional Loads: Those present
during rare intervals of operations ii) Model test,
1.4.3. Displacemefit Loads: Those due to iii) Chart method
displacement of pipe
These are dealt with in detail in the
chapter Pipe Under stress. Hence the 2.0 CODE COMPLIANCE
content of this chapter is limited to the Let us consider those aspects in the
details of analysis of piping system under code, which are mandatory requirements for
the sustained and diGlacement loads. This the expansion and flexibility of metallic
analysis is most commonly called as the piping. The Piping Specification nominates
Flexibility Analysis. Further those the code to be used for various aspects in the
conditions stipulated in,the regulatory code Piping System. Let us consider those, which
ASME B 3 1.1 and ASME B 3 1.3 only are are of importance to the Piping Engineer to
considered hereafter. carry out the flexibility analysis. Every such
code will contain recommendations and
1.5 Conditions of Acceptability of mandatory requirements on the followhg
Piping System
.. -. ' , -
.. ...~Minim.wrunrunflexibility
menu for thmdal ~xpansio.n'.
. . ,
nqw-. .. .. ..: . ..
. . .
. ;.
. .
. .
piping .layout.
. . . . . . . . . . . .
'. . . . .
. ..: . ii)
. .
~llowab~e.stresse~for
.
.,
.. .
various - -
.. . . .
. .
:
- - .. p. i p i i g m a t e r i a l s ' .. . ,
' .
,
. .- : .
1.5.1 Asper.clause.119..7.1/319.4.~ofthe'~ . . . .
Stress Analysis
PIPIKG ENGINEERING CELL
,
requirements and achieve the most i) Highly stressed small pipe run in
economical, safe and practical layout. series with large or relatively stiff
pipe runs. !
I Let us consider each of the above in turn
to see how they are dealt with by a Piping ii) Local reduction in size or wall
Engineer. thickness.
i Line configuration in a system of
iii)
uniform size in which the expansion
I
2.1 Installed And Operating or contraction must be absorbed
' Temperature
largely in short offset.
Pipe is erected at ambient
temperature and that depends on the climatic Unbalance must be avoided by
i conditions. 70F (21C) is the figure design and layout of piping system. If
commonly used for calculations. The same unbalance cannot be avoided the designer
piping when in operation in a Petrochemical shall use appropriate analytical methods as
I
- Plant could achieve a temperature in excess specified in the code to assure adequate
I
o f 500C if it were in a reactor piping flexibility.
' I
I system or it could be of the order of -120C, Each mdterial its om of
if it were associated with themal expmsion. These values are given
refrigeration system. in Appendix C of the code ASME B 31.3
j. 1 2.1.1 Displacement stresses. and Appendix B of the code ASME B 31.1.
B If the pipe is of carbon steel or of low alloy
A piping system undergo steel, it will expand at the rate of 6 to 7 mm
-
b i . dh~ensionalchanges with any change in every meter length as the temperature rises
temperature. If it is constrained B o Bee ~ to 5 0 0 0 ~ . hi^ me= that fie pipe -ng
b : . expansion or contraction, it will be displaced bemeen two equipments lom apad may
I
I &om it unrestrained position causing strain well want to expand by 60 to 70 or
1 r
v d stresses. The system could behave either more it heats up. The increased length
balanced Or unbalanced under such can be accommodated only by straining the
conditions. pipe as the ends are not ftee to move. This
) ' a) Balanced System straining, if not freely allowed, induces
stresses in the pipe as well as load at the
Displacement strains are well support points. However, when the line is
j!
distributed and not excessive at any point. cooled during shutdom to ambient
Layout of the system should aim at such temperature the expansion returns to zero,
I
) condition, which is assumed in flexibility the straining is no longer required and hence
acalysis methods provided in the code. the load and stress also disappears. This caii
) , be demonstrated as below.
1 b) Unbalanced System
2.2 Magnitude Of Thermal Load
In an unbalanced system, stress
A pipe line (Fig. 2.1), held between
cannot be considered proportional to
two anchors, when heated up, tries to
strains through Out a piping
expmd its resbaints resulting in
system in which an excessive amount of
forces, moments and stresses.
strain may occur in a localized portion of the
system. Unbalance may result from
Stress Analysis 3
)
I
I
I
PlPlivG IENGINEERIh'G CELL
C L
.I A L = a .AT. L .... (1)
Fig. 2.2 In the codes and many reported calculations,
however, a is used as inclusive of AT (i.e.
a.AT in above equation) and is called
If the pipe is allowed to expand fieely due to coefficient of thermal expansion fiom
rise in its temperature, it would expand by installedlarnbient to operating temperature.
AL as shown in Fig. 2.2. . Thg fiee
expansion will take place when one of the The expansion is then written as
anchors is released. AL would depend upon
the pipe length (L), temperature rise AL=a.L .... (2)
(difference between the temperature under This difference in meaning of a used in
hot condition and initial cold condition and equations 1 and 2 should be taken note of. A
also the length of the pipe). AL, can be typical Table C-1 of total thermal expansion
calcuIated if the coefficient of thermal fiom ASME 3 1.3 for a specific material is as
expansion, an important physical property of follows. It can be used to get a easily for the
any material, is known. The axial force applicable difference operating and
generated in the above configuration can be installed temperature.
estimated to be the axial force required to
compress the pipe back to its original
position fiom its expanded position.
. . -f
...
Table C-1ASME ~ 3 1 . 3 , ' I ' :.
TOTAL, THERMAL.
' EXPANSION,US UNITS, FOR METALS ,%
Total Linear Thermal Expasrion Bdween 70% and Indibatcd Temperature; in. J .l 00. ft .
. .
-k
,
,
. . . . .
. . . . . .
. .
. . . . . . . . . . - . .. . . . . . .
.
...... .I..:
. . . . . .
. . .
.. . . .
i . , . - . . . . .
. . .
. .
. -
. . . ..
Material . '
. .
. - J ;
'V
Temp., 'Carbon Steei;.. Wlisknitic Stainless Siwl.., - . . . . . .
.. -
. - - Copperand . .
. .
.
. L '
OF .. .
.
.
.
. . . . . .
.... .. . . . . . .
. . . .
. . . . .
. . . . Copper Alloys'. .
. . 1 . I
25 - ,-0.44, . . . . . : -- . -- . . I
+?-
100 0.23 0.34 -- -- 0.34
i
__ __
.
. . . I
Stress Analysis
PIPING ENGINEERING CELL
If the pipe is to be maintained in the original P = 18535.4 x 1.858 x 10' x 3.625 x 10"
position then there will be an axial force P to = 12,68,563 kg
compress the increase in pipe length of AL = 1269 tons !
(Fig. 2.3).
As per most of the design codes, there is no
stress in the above configuration, since no
bending moment is produced in the axial
I
t
C I run. However, the possibility of buckling
Fig. 2.3 due to the development of compressive
stresses must be considered. In no case,
The strain developed in the pipe, E, is then such a design could be accepted.
calculated as E = AL 1 L= a ~ltemative to this is the piping
system with no fixed points, allowing the
Lntemal stress developed due to this strain, pipe to expand. However, this is also not
f = EE (Hooke's Law) = E a feasible, as the equipment cannot float in
The force required to compress back is space. Equipment on wheels is one
1 P=Af=AEa possibility but seldom practiced. So every
time the plant is in operation and during
where A = Area of cross section of pipe, shutdown, the same cycle of events occurs.
In2(mrn2) The pipe starts from stress free condition
when cold, gets stressed wjth stress reaching
E = Modulus of elasticity of'material, psi maximum at operating condition and then
(KP~) the stresses get reduced to zero when
P = Compressive force on pipe, lbs CN) operation stops and system cools down.
f = Stress developed, psi (Kpa) This was an oversimplified .picture
AL = Axial compression of pipe, In (rnm) and this is not what exactly happens in
L = length of pipe, In (mm) practical situations. The piping system can
absorb large displacement without returning
exactly to previous configuration.
To evaluate the magnitude of such a Relaxation to the sustaining level of material
force, let us consider Carbon Steel pipe of will tend to establish a condition of stability
I
600 mrn outside diameter with 10 mrn in few cycles, each cycle lowering the upper
I
thickness, operating at a temperature of limit of hot stress until a state of equilibrium '
Stress Analysis
PIPISG ENGINEERING CELL
24000 psi
s y s t e m reloxed
s u s t a ~ n i n q level
/ ,
,/ \System self sprung
;y
II Fig. 2.4
!
Consider the piping system abc (as contraction through remaining 1" will result ,
installed) as shown in Fig. 2.4. As it is taken in a stress of 6000 psi in the opposite !
from installed condition to hot operating direction (tensile stress in this case). The I
condition, let us assume that the leg 'ab' system would now be in position ab3c as -
-
would expand by 2" and leg 'bc' by 2". shown in Fig. 2.4. The system, which was !
! .
This would happen if anchor at 'c' end of stressless at the start at cold condition, will
the pipe was movable. The pipe would then now have residual stresses under cold
f -
be in position ab'c' with the anchor c having condition and is said to cold spring. For I >
moved to c' as shown. If both the anchors example, if the pipe was cut anywhere along
(at a and c) are rigid, the pipe may still its route under this condition, it would I
expand and attain position abzc. It may then separate into two segments with violent
be compressed to bring bz back to position b. spring action.
Such free expansion is however not allowed The true magnitude of the stress , - >
and let us assume that the system absorbs either in hot or cold condition cannot be ,
this 4" expansion between anchors at a and c determined by simple calculations because '%
5
and the resultant calculated maximum stress the amount of relaxation is unknown and r --J
is 24,000 psi. Supposing the material at the cannot be judged reliably. It depends in a b
particular operating temperature can sustain complex way on the metallurgy, pipe mute, ._,
only 18,000 psi or 1/4 of this developed anchor locations an4 geometry etc. I
b*
stress, yielding will take place and the pipe However, service failures are related to
would be at its sustaining level indicated by cyclic rather than static conditions and it is %
? *
able. We would say that the pipe has therefoe permksible to assume that the -[ 1
absorbed stress of 6000 psi by yielding system will operate satis/actorily if sum of
somewhat. The stresses in the pipe at this hot a& -cold stresses is within a stress '1
stage are only 18000 psi. On cooling back to mnge, which is considered safe for an
ambient temperature the system must expected number of stress reversds. This
' # .
B
contract by 4". Contraction would relieve concept provides a logical basis to the B
the compressive stresses, which were design of a piping system because it takes r '
developed because the pipe wanted to into consideration all the stress levels to , ?
expand by 4" but was not allowed to do so which the system is subjected. The actual
f. $
completely. At % o f f s contraction, i.e., at stress intensity at a specific stage is of
a net contraction of 3", the system will academic interest only. * 1
become stressless. Completion of -
'-3
a
Stress Analysis 6
1 '
I
I
I
'
/
It could be seen that the code the pipe to crack. The cracking will start at
recognizes the fact that stresses in piping a point or points where the stress is
; I
system are not necessarily of constant maximum. This is what is meant by
1 intensity, that the expansion stress at "FatigueFailure".
elevated temperature may not be sustained
because of relaxation or creep and Average axial stress (over the pipe
consequently will drop to stress level the cross section) due to longitudinal forces
material can sustain. The phenomenon of caused by displacement strains are not
yielding in the elastic range or flow in the normally considered in the determination of
plastic stage presents a problem different displacement stress range since these
fiom that encountered in the analysis of stresses are not significant in typical piping
structure which operates at relatively low layouts. In special cases consideration of
temperatures and therefore in a state of average axial displacement stress is
steady stress. In this case, the elements are necessary. Example include buried lines
designed to meet the limiting stress or containing hot fluids, double wall pipes and
deformation within the elastic limit of the parallel lines with different operating
material. In contrast, with stresses from temperatures connected together at more
sustained loads such as internal pressure or than one point.
weight the displacement stresses can cross 2.3 Effect of Fatigue on Piping
the elastic limit with stress reversal fiom ARC Mark1 investigated the
cold to hot condition and still remain safe phenomenon of fatigue failure of piping
provided the number of stress reversals during 1940's and 1950's. He tested a
remains below the limit to exclude the number of configurations; straight pipe,
possibility of failure due to fatigue. various fittings such as elbow, miter bend,
Wle stresses resulting from welding tee, fabricated tee etc. mostly on
displacement strains diminish with time due 4" NB size by using cyclic displacements to
to yielding or creep, the algebraic difference apply alternate bending stress. Plotting the
between strains i n the extreme displacement cycles to failure for each applied
condition and as-installed condition remains displacement, he found that the results were
substantially constant during any one cycle on the expected lines and followed the shape
of operation. The difference in strain of fatigue curves.
produces a corresponding stress differential, Markyl observed that the fatigue
the diplacement stress range, which is failure occurred not in the middle of his test
used & the criteria for designing of piping spans, but in the vicinity of fittings and also
flexibility. at lower stress 1 cycle combinations than for
the straight pipes. This lead to what is called
The type of cy~;icstraining described the "Stress Intensification Factor" which
above, if repeated often enough, will cause covered under section 5.3.
Stress Analysis
PIPING ENGINEENNG CELL
iii)
Honge of imposed displacement to iv) '-
+I/P
h-- I
Fig, 2.6
\I( Ronge of outplone displacement
All
distir:--q
4 il- Range
-1- 4 p of inplone displocemen:
be reduced to elastic action in the piping strength of the material. Temperature and
system. This theory can be understood by pressure are the significant factors : 3
considering a pipe experiencing an imposed governing the stresses created in the piping )
--
displacement which is beyond it's yield systems. There are other factors that .-
strain. When cyclic displacement is influence the stress as well. They are The yield 3
removed, the piping component, which the valuk-.
exceeded the yield point, will retain the i) Wind load proportioi 1
residual distortion equal to imposed strain ii) Seismic load removed, '-;
; j
Stress Analb
Stress Analysis
->
-
PIPING ENGINEERING CELL
iii) Relief valve forces The ultimate tensile strength is the highest
iv) Fluid hammer stress which the specimen can accommodate
v) ' Settlement ! without failure.
vi) Equipment vibration The basic allowable material stress a t
vii) Weight of attachments the hot (operatingdesign) temperature (Sh)
viii) Weight of contents is defined by the code as minimum of
vi)
100h of the average stress for a
0.0 1% creep rate at 1000 hrs
67% of the average stress for
,+to, rupture after 1,00,000 hrs
piping Fig 2.9 vii) 80% of the minimum stress for
ks that rupture after 1,00,000 hrs.
-e The yield stress is the elastic limit and that is
X the value below which the stresses are
proportional to stqain and when the load is
removed, there is no permanent distortion.
Stress Analysis
PIPIYG ENGINEERING CELL
magnitude of the initial hot stresses and the deformation or bursting; plastic htability or
temperature, so that while fie hot stresses incremental collapse due to cycling in the
will gradually decrease with time, the sum plastic range and fatigue which may be
of hot and cold stresses will stay the same. developed in a system as its temperature is
This sum is called the EXPANSION raised fiom the lowest to the highest that it
STRESS RANGE. This leads us to the will experience in service or when it is shut
selection of an ALLOWABLE down. Each of this fiilure, modes is caused
EXPANSION STRESS RANGE. by a different type of stress and loading.
Self-springing occurs only when the However 'Fatigue failure' is recognized by
system is subjected to higher temperatures. the code as the most likely mode of failure
For the expected strain (expected expansion of the component and place the limit on the
per unit length), if the modulus of elasticity maximum stress which may be developed in
Stress Analysis 10
1
PIPING ENGINEERING CELL
!
a system as temperature is raised from would be subjected to, without the flow
lowest to highest that will experience in occurring in either hot or cold condition.
I service or when it is shut'down. Therefore,
This piping "Shakedown" is also S, = 1.6 Sc + 1.6 Sh = 1.6 (Sc + Sh)
known as self-springing and can be
represented as shown in the following sketch But the American design codes ASME
(Fig. 2.10). B 3 1,l and B 3 1.3 limit the stress range t o
78% of the yield stress, which gives a total
stress range of
The maximum stress range may be The above value does not consider the
set tq 2 times the yield stress, more excessive cyclic conditions. The code
accurately the run of hot and cold yield allows it by multiplying by a stress range
stresses, in order to ensure eventual elastic reduction factor. Accordingly, ASME
cycling within the bounds of allowable B 31.1 in clause 102.3.2(c) and ASME 31.3
stress. Incorporating a factor of safety, this in clause 302.3.5 specify the Allowable
can be represented by the following equation Expansion Stress Range as :
SE<= F (Syc + S n ) S, = f(1.25 S, + 0.25 S,)
where, SE - Expansion stress range
F - Factor of Safety where,
Syc - Yield stress at installed S, = Allowable Expansion Stress Range
temperature S, = Basic allowable - stress at minimum
SYh- Yield stress at operating
temperature . metal temperature
. . .
during the
. . .
.:> .
-. .
. ..
. - ,
. .
. . . . .
the allowable stresses are 62.5% of the yield . . . . . .
Stress Analysis
PIPING ENGIXEERING CELL 1;
I
'i
Stress range reduction factor for
f =
displacement cycle conditions for the
f = 6 . 0 ~ ) ' ~ <1.0
wherey I
total number of cycles over the
expected life N = equivalent number of
displacement cycles during the expected
i
full
service life of piping system [code cautions
1 :
I' c -
The factor has a value of 1.0 for I
sirnation where total nmber of cycles is the designer that the fatigue life of materials
I
7000 or less. This represents one cycle per Operated at temperature may be
day for nearly 20 years, which is a common reduced]
I
-
design parameter. Further, if we look at When the computed stress range varies,
endurance curve for and low whether fiom thermal expansion or other
alloy steel available in the ASME Section conditions, sE is defined as the greater
Vm Division 2, Pressure Vessel Code, it computed displacement stress range. The
can be seen thatat some point in the
of 7000 cycles, the Sc + Sh limitation
intersects the fatigue curve.
The code gives the value of 'f in the
table 302.3.5 (B 31.3) and 102.3.2 (c) (I3
value of N is such cases can be calculated by
the
N=N ,+E [f N, ] for i=l ,2.......n
where,
1 $ +
*,
I:
d
>
.
range smaller th an S, -1
N,=Number of cycles associated with + P
1 - 3
I
I ,
Stress Analysis 12
2
1, PIPING ENGINEERING CELL
. TmslL
SY
difference between them may be added to
the term 0.25 Sh in the equation for SA.
Stress Analysis
PIPING ENGINEERING CELL
Stress Analysis 14
- I
I
.- ,
<' .,
J I !
'9 1
r--> I'
.
t
I
,
>-
.
I6
I .
" i
,/ i'
..
I
I t ;
3 I '\,
'-)
.. !
2 .
-1 I
.'
'<
- \f
/ I
-7 .
;P ;
) -.
--' 19 . : API 610 specifies that the pump casing shouldbe designed to withrtmtddouble thefirca and moments as '
:
1
!
above. The piping configuration that produces load and moments outside the above range u a h acceptable
+ ! provided the conditions as specified in Appendix F of the above code are satified. For direction offorces and
.j ' moments see Fig.3.1 . '
_i I
-1i i
' . I I
i' :
-- J
'
.:31. . )
4
.2
'
,
. J
I
I
. .
. .
. .. .
1 . . . . . . . . ..
,$ i .. . .
1: i . .
. . .
Y
? i ji
I .
"bea
!t . (5..
1; . .
r 1
!
-
Z .
i. . .
. .
. .
. .
) ,I Stress ~nalisis IS
t
I '.
PIPING ENGINEERlNG CELL
I e
-
IS0 5199 - 2002(E) in Annex B gives the Fx = 75 D lbs Mx = 125 D ft.lbs .
allowable values of forces and moments on
the pump nozzle. The basic values given in
table B3 should be multiplied by
corresponding coefficient given in table B5 ! :
or B6. This is based on the study and tests where D is the nominal diameter of nozzle ..
>
-P
discharge pipe connections arr:
I
NFrnR: W d R-& I ?
j
&& AW. 4 -
3
Stress Analysis 16 I'
. .
\
PlPING ENGINEERING CELL
i I. The total resultant force and total resultant D, = Diameter (in inches) of a circular
moment imposed on the Compressor at any opening equal to the total area of inlet side
,-? connection must not exceed the following: and discharge opening upto a value of nine
(9)inches (230 rnm) in diameter. For values
beyond this use value of
927D - M cwtd3-
F' &9bpMS+_1 Dc = (18 + Equivalent Diameter) inches
3.
CQ%L> 't- 3
i I
F + 1.09 M <= 5.41 D in SI units = 460 + Equivalent Diameter in mrn.
'Ib F = Resultant force (IbsMewton) 3
' -j
M = Resultant Moment (ft.lbs/Newton
-3 meters) The components of these resultants shall
,
I
I . . not exceed
4 D = Pipe size of the connection (IPS) in
! inches/millimetersupto (8) inches in USCS
-x I
(200 mm) in diameter.
- f For sizes greate than this, use a value of D
I
--
-.
Z
I
equal to (16+IPS)/3 inches or (400+D)/3 in
mm.
1
2. The combined resultant of the forces and
i > i
moments of the inlet side and discharge
connections resolved at the centre line of
1 the discharge connection must not exceed
the followhg two conditions. where, . .
. r
.;
' n e s e resultants must not exceed Ey = Vertical component of E&
)3
F, = Horizontal components of Fc
- -J
462D,-M, at right angles to compressor shaft
), I 1 F,= in USCS
-.i
. . I
2 F, = Horizontal component of Fc
Parallel to compressor shaft
), Fc= 40.4Dc- 1.ah&in SI Units M, =, componat M, in a hoiantal :
~~~~~~~~r
. .
4 ft 1bdNewton meters
plane at right angles to the
. .
1 ! compressor shaft
1
- I
i
Stress Analysis
I
PLPlNG ENGINEERING CELL
+y Right angle to
compressor shaft
4
/
+ F*+ +x Paralklto
compressor shaft
+Mx
Fz
- DISCHARGE
PLAN
Fig. 3.3
. .
. . . . .
END VIEW . . ELEVATION " . . . . . . .
Fig. 3.4' . Fig.3.5 . . .
sucss Analysis
PIPING ENGINEERING CELL
+ Z +X
fig. 3.6
Fig. 3.7
3. These values of allowable forces and turbines due to the stean inlet, extraction,
moments pertain to the compressor stmcture and exhaust connections should be evaluated
only. They do not pertain to the forces and by simple set of force/moment calculation
moments in the connecting piping flanges similar to centrifugal compressors. These
and flange bolting which should not exceed computations shall be done as below.
the allowable stress as defined by applicable
codes and regulatory bodies. 1. The total resultant force and total
resultant moment imposed on the turbine at
Forces on inlet connections are to be any connection should not exceed the values
transferred along with moments to discharge calculated as per the following equation.
connection to analyze the compressor for
resultant forces and moments. Buh the
transfer of force will generate additional
500D M -
3F+M<500D orF<
transfer moments, which are added to the
, 3 .
total of moments to give resultant moments.
where,
1.
3.4 Reciprocating Compressors F = Resultant force (lbs) including pressure
API 618 "Reciprocating Compressor
for General Refinery Service" do not specify
the limit on the allowable forces and
forces where unrestrained expansion
joints are used at the connection except
on vertical exhausts. Full vacuum load
1:
is allowed on vertical down exhaust
moments in the code. The vendor shall
speeifL the forces and ~liomentsfor each
nozzle in the tabular form. However, the
.
flanges. 1.:
'\jc F? Fz2
values as per API 610 can be considered for
I.-I
+ +
guidance.
M = Resultant moment in foot-pounds,
3.5 Steam Turbines i
1-1
NEMA - SM 23 requires that the M = \]M/ + M,' + M,'
forces and moments acting on steam
L;
I '
I -
I
' PIPING ENGINEEIUNG CELL
i
i D = Nominal pipe size of the connection in
inches up to 8 inches in diameter. For values beyond this, use a value of D,(in
I
inches) equal to:
1 For sizes greater than this, use a value of
(18 + Equivalent diameter in inches)
(1 6 + IPS) Inches
1 D (in inches) =
3
3
Stress Analysis 21
I
/ /
PIPING ENGINEERING CELL i
I!
3.6.2 The design of each fixed or floating manufacturer. Restrictions are applied on
header, the design of fixed headers to side nozzle rotations also in this case to take care
frames, and the design of other support
members shall ensure that the simultaneous
of the clearances between the tube and
refractory lining. The thumb rule used is :
!'
application (sum)of all nozzle loadings on a Forces = 200 to 300 Ibtin. nominal ,I
single header will cause no damage. The bore of nozzle
components of the nozzle loadings on a -
Moments Equivalent to Sh/4
single header shall not exceed the following Nozzle ~otation- From 1/2 " to 1 i" fl
values. I :
3.9 Flat bottom Welded Storage Tanks
to API 650
Mx= 4500 ft Ib (6100 Nm)
My= 6000 ft lb (8130 Nm)
M, 3000 ft lb (4070 Nm)
The design of the piping system
connected to thin walled, large diameter
I j ,
. -:
-
Fy= 4500 lb (20020 Nm)
Fz 3750 1b (16680 Nm) interface between the piping system and the
tank nozzle. . The parameters to be ; 1.
-
-
-
F
a,
Note :-me application of the moments and considered.are the stifiess of the tank shell, i 'I.:
--
forces shown in table will cause movement the and the meridional -
-
that i l l tend to reduce the loads to the rotation of the shell opening at the nozzle 1
values given. connection resulting ftom the static head, . 7
Force . I -
\
Bending : Equivalent to bending 3s
. ,x '
Moment stress in standard schedule
Y-Y
pipe between 4000 to x" I
50001bs./in2 a
1 .
a t
+ -
1
x-
Z
3.8 Fired Heaters 2 t 1 -
i
The limiting values for forces and Fig.3.10: Storage Tank Nozzle Details -
moments should be laid down by the .$
( .
Stress Analysis 22
I
1 '
PIPING ENGINEERING CELL
a = Outside radius of the nozzle in rnrn(in) and (h/aYc)(Mc/F,~,
F R = Radial Thrust applied in N (lbf) e) plot point ( ~ J ~ Y F ) ( F R E P ),
Fp= Pressure head at the nozzle xaZp (UaYL)(ML/FP)on the nomogram with
L = Vertical distance fiom centre line of X axis and Y axis respectively.
nozzle to tank bottom in mm(in)
t = shell thickness at the nozzle connection f) Plot point (W~YF)(FREP) r
in rnm(in) (l./aYc)(MclFp) on the nomogram with
P = Pressure fiom liquid head in Mpa X axis and Y axis respectively.
(1bf7in2)
XA=L + a in rnm (in) g) Construct boundaries as lines at 45
XB= L - a in mm (in) depree angles between abscissa and
Xc=L inmm(in) ordinates passing through the calculated
Yc= Coefficient determined from Fig. P-4B value.
(API650)
YF,YL= Coefficient determined from h) The external piping loads FRr ML and
-
Fig. P 4A (API650) & are acceptable if both points
= a/(~t)'.' determined fiom b and c above lie
Mc= Circumferential moment at the nozzle within boundaries of the ncmogram
fkom the piping system in N-mm (in-lbf) constructed for that particular nozzle.
ML= Longitudinal moment at the nozzle
fkom the piping system in N-mm (in-lbf)
3.10 Static Equipment such as columns,
Appendix P of API 650 establishes reactors, tanks and vessels
minimum recommendations for the design
of storage tank opening subjected to external Each nozzle, 2" NB and larger, for columns,
piping loads. This is recommended only for drums and shell & tube heat exchangers
tanks larger than 36M (120 ft) in diameter constructed . out of steel or alloy is
and is considered as an accepted practise for recommended to be designed to withstand
the piping connection at the lower half of the forces and moments fiom the thermal
bottom shell course. expansion and sustained loading &om the
The following are the steps involved in the piping as per the following criteria These
determination of allowable loads. forces and moments shall be considered to
a) Determine the non dimensional be acting at the intersection of nozzle and
quantities xA/(Rt)Oo5 , X$(R~)''' and shell in he corroded condition. A total of
&/(~t)'.' for the nozzle connection 7000 fill temperature cycles shall be
under consideration. considered for the expected life of the
b) Layout two sets of orthogonal axes on equipment.
graph paper and label abscissas and
ordinates as specified in 'e' below.
c) Layout two sets of orthogonal axes on
graph paper and label abscissas and
ordinates as specified in 'f below.
d) Using the values of FR, ML and Mc
obtained fiom tbe piping analysis
determine the factors
. ('E./~YF>O;R@P)
('E./~YL)(M~FP)
Stress Analysis
PIPING ENGINEERING CELL
3.1 0.1 Nozzle to Shell or channels
a) Moments i
i) Longitudinal bending moment
NOZZLE .
I M L = P130D2Nm -
ii) Circumferential bending moment
M+ = p 100 D2Nm
iii) Resultant bending moment 1.'
Mb =(ML2 + ~ ~ ~ 1 %
= P 164~~~x11
iv) Torsional & moment
Mt = P 150 D2~m
I
I
I'
b) Forces
i) Axial force in plane of Flange
FL = P2000D N
Tangential force in plane of Flange
I.
'.
i
F+=p 1SOOD N
NOZZLE
/
/
/
iii) Resultant shear force
I
FR = + F~'1% I :
=. P 2500D N I
.
@
E
L FR = P2500D N where FA is the 1 : :
i.
, resultant of the components Fx and I : -L
Fz 3
Fig 3.12 Orientation of Forces and ii) Radial Tensile or compressive force I
Stress Analysis
PIPING ENGINEERING CELL
19. Allowable stress at flexibility DY
temperature (L-Ur iK1
20. Bend radius and type of bend where,
21. Branch connection type D.=the outside diameter oP pipe
22. Weight of attachments - In inch (or mm)
Valves and Specialties Y = Resultant of total displacement strains I -
23. Terminal movements with
directions In inch (or mm) to be absorbed by the
l a
-
Note: The Code states that the design
temperawe shall be assumed to be same a
Piping
, system. ! -
d :
-; 3
L = Developed length bet wee^ the anchors
the fluid temperature unless calculations or I '
!
-
1
test supports the use of other data In ft. or (m)
U = Anchor distulce, straight line between
.
anchors in R or (m)
K1= 30 SA& in USCS 1 . -
%j
i
Fig. 5.1
-
Pipe 6" (150 m m NB) Sch. 40 carbon Design Temperature - 400 O F (204%)
steel to ASTM A106 Gr. B
I
i
Stress Analysis 26
I '
PIPING ENGINEERING CELL
Step 1 Step 4
To establish the anchor to anchor distance
u
Total length in X direction = 35'
Fi. 5.2
-
Az = 2.7 =1.215"
Now further, suppose that everything is in
100 - -
carbon steel and- the vessel T1 has its
2
Y = J A x ' + A ~ '+AZ temperature raised to 200C. When the
= 40.945 ' + 0.810 + 1.215 z
valve is opened, there will be expansion in
the connecting pipeline, which c,m be
= 1.739" calculated as below.
Expansion of carbon steel fiorn 21c to .
2 0 0 ' ~= 2.2 mm.1 m
Sbess Analysis 27
PIPING ENGINEERING CELL
f+
the sides of the vessel as in Fig.
5.3
~wKll-&t
Fig.
fig. 5.3
&WF-+$-----------------
fiq. 5.1
owl----i1,-ii71 --------
Fig. 5.5
Stress Analysis
t'
I
e.
-I
!
M=PL/Z
6-
pi3
12EI
where,
kMovementin inches
-1
to a given value and this is the simplest
concept of all in the field of flexibility
analysis, namely "Minimum Length".
fig. 5.6
28
.
I
I
I
;
'
i
I
,.-I
I
,1. -
I
I
!*_
I'
I'
. ?;
'
'
'-1
1
b '
C
. 5-
it
d-; s
. "3
<Y
K.
-:
%>.
22
-7
24
z 3
555
w 7
I
-)
+
-
\3
33
*
Td
=
h3
:
J
:I
1
k'i
1
-,f
-J
- -
-.
%
-*
*$
1
1
.
.j
zt.
1.
-
PIPING ENGINEERING CELL
p =- El6 above
. t
144 L'
.b i
Miximum bending moment at B or C =fP L/2 =14.88 k(4.54 m)
.'i
7
[
:
=M ft.lbs. This indicates that the length BC should
not be less than 4.6 m.
Maximum bending stress f = lbs/ in '
I . We can also~calculatethe stress developed
-2 I, OD of pipe
Y= in such a system of known dimensions of
i 2 leg BC by the same mekod.
j
I f =-12MY
-ir ! I
i '
i ! El 6
.--\ i
Substituti ng P -4
7 5
144 L' 12EI6 . .
-
-\
f
12 EI& L D - Hence P ' , =
f =-x-x-x-
I 144L' 2 2 . . 13
Stress Analysis
I
PIPING ENGINEERING CELL I
Fig 5.8
I
If the same pipe is subjected to a constant .d
twisting moment, the rotation of one end 1
1
relative to the other end is given by : a
. .
. .
. . . . .
.
Fig 5.7 . ,
.
.
. '
.: . .
. . . . . . . .
. . . . .. .
. : . - . ' :
, c3
0 = Angle of twist in radians 1
T = Torsion moment in - Ibs (mm- N) ': 1
i -
Stress Analysis
PIPING ENGINEERING CELL
.
There are piping components other M .L
1 , :
, than straight pipe, which are required to g= -
make a complete piping system. These are EI
[ !
7 ...
.
..
.
..
. . elbows, tees, reducers, valves,. etc. The .
i., "
1 . . ' knowledge of individual effects on the
4
j
.
flexibility and the stresses in each .element .
i: . . is essential to analyze a piping system
- .
I close to its true nature of behavior.
1,
~. I
i
$-
: j i
.
j
.. ,
.
5.3.2 ELBOWS:
.
.
, ,
.. Early calculation on the flexibility.
t, - analysis containing elbows proved that the
. .I
) i
structural engineering- theory and : the . .
. ' .. , .
.?
. ;
3
. I
! .. than predicted and.the discrepancy w a s , . ' . . .. .
~ i510.
~ -. . - . . , .;. , .:
. . -
. .
1, t
i
-
. . due to the flexibility of elbows. . . . . .
The first theoretical analysis of the Let us consider how flattening of the cross
behavior of pipe bends when subjected to section occurs
a bending moment was made by Theodore
Von Karman, who showed that when a
curved pipe is subjected to a bending
moment in its own plane, the circular
section gets flattened and this results in
-3
!. =
i
I '
+%- i
!
.,
, ,
-
--
Fig. 5.14 Circumferential Stress in Pipe I' :
-
waU i
$3
If the element is analyzed in mom detail, it 1 ' 1
Fig. 5.12 is seen that the flattening produces -d
bending moments in the rings, which are -
J\
1
Let us consider a thin slice taken between
two radial planes " X X and "W".
maximum at the ends. These moments
p r o b e a stress which varies b r n tension
f
"1
(see Fig. 5.12). ,to compression through the t$ickne,ys of . -. i
pipe wall and which is ciicderentid in ;?.
The resultant effect of the tensile f T
i
load "T" in the -outer fibres is an inward direction. If we consider one half of the f
radial load on the element. Similarly the ring, the stress system gets .illustrated as .
>
A
3
-
9
the element. to bending moment M can be many times ' 3
If we view the slice as a cross the value of MY/I obtained by bending 3
-
,
section, and draw a loading diagram for theory of structural members. The factor 3
the ring, we anive at the situation shown by which the circumferential stresses / T
below. Under the applied loading the ring exceed the longitudinal stresses in the -
1
bend is called the "Stress Intensification
'i
I:
Stress Analysis 32
1' -'
I
I :
PIPING ENGINEERING CELL
Factor" called S.I.F. It can be defined as When any problem is analyzed, the
the ratio of the actual bending stress for a following considerations are made.
moment applied to nominal section.
The effect of the existence of these
'
a) The Flexibility actor applies to
bending in any plane. .
circumferential stresses is that when elbow b) The stress intensification factor i s
is subjected to repeated "in-plane" greater for "inplane" bending than for
bending, it ultimately develops a fatigue "outplane" bending. ASME B 31.3
crack along its sides. permits the use of inplane SIF for any
When we take additional benefit by plane whereas B 31. 1 does not-
Flexibility factor due to flattening of separate out these two. ,
elbows, consideration should' be given to Virtual Length
the induced circumferential stresses by
multiplying the stresses at the bends due to The product of length of arc centre line
overall bending moment by the and Flexibility factor is referred as
appropriate "Stress Intensification Factor". "Virtual length" of a bend and these are
considerable while analyzing thin walled
-3
-J
Appendix D of ASME B 3 1.1 & large diameter pipes.
1 31.3 tabulates the expressions to be used
-
1
7
for calculating the Flexibility Factor and Mitre Bends
L
3 ; Stress Intensification Factor. The In case of Mitre Bends qn equivalent bend
I-, parameter used for the calculation of these radius is used in the equation to calculate
factors is called the "Flexibility 'h'. The equivalent bend radius (Re) i s
1 Characteristic" denoted by letter "h" estimated by
; !
Re = r2(1 + 0.5s / r2cot 0)
for closely spaced
Re = r2(l+cot0).
mitres
for widely spaced mitres
where,
Stress Analysis
PIPING ENGINEEFUNG CELL
code ASME B3 1.1 I B3 1.3 and given in small the branch connection has little
Appendix D. These vary depending on the impact on the header and the calculated
type of branch connection. stress could be unreasonably large by
The unreinforced fabricated tee is using large SIF. It has been pointed out by
modelled using same formula for widely R W. Schneider of Bomey Forge that the
spaced miter bend with single miter i.e. highest stress intensification factor occurs
half angle of 45" This produces the when the ratio of branch to header is 0.7 at
flexibility characteristic of which the non-conservation is of the order
of two.
Secss Analysis 34
1 '
PIPING ENGINEERING CELL
the wire drawing effect on the mating should be applied on the values available
surface of the flange. Hence, additional
flexibility is to be considered where d
flange joint is located near a point of high
bending moment.
5.3.5 REDUCERS
fiom the table.
Divide 'kyby [I
+ (~)(~)i..[:r]
E 'T
. . . . . . . . .
1 , ~m B.3P.L
:
. :
. . ' . .
'. this clause,, the complete piping system ' ' , ' '
Where,
SE = Expansion stress range psi (KPa)
M, = Range of resultant moments due to
thermal expasion, in - lb
tmm-N)
in USCS units
in SI units
= V
+My+
M M: inuscs units.
Z = Section ~ o d u l u sin3
, (mm3)
t, = Nominal Thickness, in (mm)
Sh = Basic.allowable stress at the
operating temp., psi (KPa)
... ,.
The effects of thermal expansion must . .
. . . .
meet the requirements of the following .Where . . . . ,.. . .
equation. . -.
: K = 1.1$ for o'casional loadi'acting less ,' . . ,
.period. - -
K = 1.2 for occasional loa& @ting less
than 1% of any 24 hr. operating
In USCS units period.
MB = Resultant moment loading on cross
section due to occasional loads. If
calculation of moments due to earthquake
is required, use only one half of the
In SI unit
Stress Analysis
PIPING ENGINEERING CELL
I
earthquake moment range. Effect of Ma = Out-plane bending moment due to
- I anchor displacement due to earthquake sustained (primary) Loading, in-lb
may be excluded fiom the equation if they
are covered in Thermal Expansion stress
. . (mm-N)
li,l0 = In-plane and out-plane stress
;
I \
where
I Sh - in USCS S, =Resultant bending stress, psi ( m a )
. units S, =Torsional Stress = Mt/22, psi
1000Mt/ 22,KPa
M ,=Torsional moment, in - lb (nun N)-
' F, 1000 [ ( i i ~ i'+) (ia,)'I ' Z=Section
..
Modulus of Pipe, in' (mm')
SL -+ ..
=
Am . .. .
.
'. .
. ,
< ShinSFunits . , -
@) The resultant bending stress to be used
... . .
in the above equation for elbows and full
. . . .
s & h e d .loding,p i , m a ) .: ..
' '
Stress Analysis
PIPING ENGINEERING CELL
For Header
in USCS units.
where
In SI units.
. . . . .
. . ForBranch ' .
. .
in USCS units
. . . .
. .
or
. header
. . kxclusive 'of renf&cexne
. .. . . . . .
nt
. . . . . .
,
.
.
.
.Yo 3
For branch connection, the resultant - A
different. 1
r-- ;,
For Reducing outlet branch connections,
the equation shall be as follows. , - 3
)- I
! 6.2.3 STRESS DUE TO due to thermal expansion but it
OCCASIONAL LOADS affects the end reactions in direct
? 1 ratio. So overstress cannot be
I ASME B 31.3 do not specifically define
i i the equation for calculating the stresses
nullified by increasing the
thickness; on the contrary, this
due to occasional loads. The code, under makes the matter worse by
I clause 302.3.6 only states that the sum of
I
2 . longitudinal stresses due to sustained and increasing the end reactions. This
is demonstrated in .the following
occasional loads shall not exceed 1.33 example.
':1I times the basic allowable stress. The
method adopted is to calculate the
,
i
sustained and occasional stresses Let us consider two simple
* L 1 independently and to then add them
absolutelv.
cantilever arrangements having the same
deflection, pipe size and length but with
varying thickness.
6.3 COMPARISON OF CODES
Based on the above, we can identify L
i 6"(150mm) NB Sch. 80
ASME B 31.3 include Fax in the
-----_-- -- --
stress calculation due to sustained
load where as ASME B 31.1
-- - --
neglects all forces
Fig. 7.2
ASME'B 3 1.3 calculation methods 0
.
. . . . . .
.
. .
~ 3 1I .indudesit. .. . .
3EyI
ASME B3 I. 1 intensifies torsion.
. Hence P =
wh&e as ASME B 31.3 does not. L3
Z = 139cm3-
I' '
given time.
For 6" (150 rnm) NB Sch. 80 pipe
I = 1686 cm4 ASME B 31.3 gives the formula
Z = 200 cm3 for calculation of maximum reaction or
Therefore, moment when cold spring is applied to a
two anchor piping system in clause
319.5.1 as below.
Sch. 40 Sch. 80
Load P 1170 k 1686 k
Moment M 1170 k L 1686 k L
Stress = M/Z 8.4 k L 8.4 k L where
Form the above it can be seen that R = Estimated instantaneous maximum -=_-, =2
,
,.-
although the stress remains the same, the reaction force or moment at maximum or
forces and moments increase with the minimum metal temperature. f-i
=.
increase in thickness of the pipe. 3
E
R = Range of reaction force or moments BP
cl
Where the piping system
derived fiom flexibility analysis I 3
encounters large end reactions or
corresponding to the fblI displacement i r->
; ,
anchors shall be provided to resist the The factor 2/3 is based on experience, c-1
endforces. which shows that specified cold spring ! ' 6 j
cannot be fully assured even with r . -3
- . \.
8.0 COLD SPRING elaborate precautions. , 1
; - . ;$
i SE= computed displacement stress range The reaction thus computed shall
not exceed the limits, which the attached -
Sh= Maximum allowable stress at design quipment can safely sustain.
temperature
ASME B 3 1.1 deals with these factors
under the clause 119.9 and 119.10.
9.0 SELECTED CHART One of the shapes considered is the "Three
SOLUTIONS Dimensional 90" Turns" comprising of
three legs, each of which is at right angles
9.1 The book on Flexibility analysis to the other two.
"Piping Stress Calculations
Simplified", by S. W. Spielvogel
deals with a number of shapes
frequently encountered in practice.
This can be used for a quick check
on the terminal forces and
moments. This method neglects
the effect of flexibility of the bends
and to that extent the values are
over estimated.
- FY
Fig. 9.1
A.E4=Ll=25' Kb = 8.61 Kt - = 4.35
CD = L3= 5'
L l L 3 = m = 25/5 = 5
L2L3 = n = 10/5 = 2
By referring to chart, we get :
Stress Analysis
PIPING ENGIPU'EERING CELL
I
The stresses are evaluated from the Expansion Stress Range
equation, .
!
S = KC D/L32 lbs/ sq.. inch
The forces are evaluated from the equation, = 56 19 lbs./sq.inch
Allowable stress range = SA I
I
F = K C I / L ~I~~ S = f ( 1.25 Sc + 0.25 St,)
>
I
Moments are evaluated fiom the equation, = 1 (1.25 x 20,000 + 0.25 x 19,450) s
SE< SA. 1 6
i 3
D
Torsional Stress = K,C-
L*
- 4 . 3 5 5~ 1 0 ~ 4 . 5
5
= 19971bs./sq.inch
Stress Analysis
PIPING ENGINEERING CELL
I,
Moment M, = K,C -
L3
', i - 0.4x510x13.3
c
where,
f ,= Expansion Factor allowing for the
temperature and material of pipe
given in table.
E.ffmtivc~ l b Dimdef
a ~ :-
.
E.flative Elbow hg& . .
Length of Short:VerticalLeg
Length of Long.VerticdLeg.
Length of horizontal offset ...
l,,,~.. . . = 4/25 . =
' WW = 2515 =
) !
-, From Chart, shape factor f, = 1.66
1) Square comer length = h + H + W = l -35.0'
' ! Sum of elbow lengths = 2 Lr = 2 x 4.7 = 9.4'
)
Total effective length = 1 +2Lr=L=44.4'
Effective Diameter length = LDr = fl = 44.418.78 = 5.06
)- ,
7
, i Stress Analysis
I
PIPING EYGINEERING CELL I
Stress Analysis 44
PIPING ENGINEEIUNG CELL
When ihe tubes and the column If it so happens that the column
have different of shell will not permit the support of reboiler
construction, the piping leg 'cd' in on brackets attached to the shell just below
Anangement-l has the the vapor return nozzle, then the brackets
differential expansion. For are to be attached to the vessel skirt. This
Stress Analysis
PIPING ERGINEEFUNG CELL
will result in the support bracket at a larger 1 1.3 Arrangement-3 (See Fig. 113)
distance &om the level of the vapor return.
nozzle: When the reboiler is too heavy to support ,
Fig. 11.3
Fig. 11.2
Stress Analysis
benl-rlcarebourse
on
PIPING ENGINEERING
-
May 11 27,2005
Prof. A. S. Moharir
IIT Bombay.
efikct of dl a h loads and somd analytical against failure of the system as perceived by
&Is to,takc m g k x i n g decisions to mitigate one of tAt failme theories. If a'pipt B t s ' i
this effect. for a certain pmssurc experiences r much
higher pressure, the pipe would rupture e m if
'Stress analysis and safe design normally such load (pressure) is applied only once. The
require appreciation of several related failure or mphirc is sudden and complete.
concepts. An approximate list of the steps that Such a failure is called catastrophic failure. It
would be involved is as follows. takes place only when the load exceeds far
beyond the load for which design was bed
out Over the years, it has been rraliztd that
systems, especially piping systems can fail The design to guard against failw by primary
even when the loads arc always under the loads is bajed on one or more failure thcoriu
limits considered safe, but the load application such as the ones discked later in this paper.
is cyclic (t.g. high prcsmrc, low pressure, high
pressure,..). Such a failure is not guarded Secondary Loa& .
against by conventional pressure design
formula or compliance with failure theories. Just as thc primary loads have their origjn m
Once this was realized and it was seen than some force, secondary loads an caused by
systems may fail after prolonged use under the displacement of some kind. For example, the
load they could withstand till that time, it pipe connected to a storage tank may be uudcr
became clear that system design must comply load if the Eank nozzle to which it is connected
with at least two different types of loads moves down due to t d
csettlement Similarly,
causing two different types of failures. For pipe connected to a vessel is pulled upwards
piping system design, it is now well because the vessel nozzle moves up due to
established that one must treat these two types vessel expansion. Also, r pipe may n i t e due
of loads separately and together guard against to vibrations in the rotating equipment it is
catastrophic and ktigue failure. a t b c W to. .A pipe may cxpuitnce aqmsion
or &mtmctiou once it is.5ubjected to
Thc loads the piping systcm (or for that matter tcqaatws h i g h or'lower rapcctivcly as
, any structural part) faces arc broadly classified compated b tnnperPtrn at which it was
as primary loads and secondary loads. There tfssanbltd.
e i h p l a and charictcristics are given hcn in ,..
brief. ThtscccnldaryIojrdsareo~eqj.clicbutnot
.... .. always. -For example .load dtae to tauk
.
' .:
. Primary Loads ,' . settlement is not cyclic. 'Ihe load due to vessel
nozde movement dmbg o w on is cyclic
These are typically steady or sustained typcs bcwuse the displacement is withdrawn during
. of loads such as intmal fluid pmsurq shut-down and rsu+xs''agaiu aftcz fnsh
u r d pressure, gravitational forces acting gbrt-ip. A pipe subjectmitd a cycle of hot md
on the pipc such as weight of pipc and fluid, cold fluid sirnilarly.\mdcrgocscyclic loads and
forces due to relief or blow down, pmssm defolmatitra..
waves genesated due to wata hammer effects
Tht last two loads arc not n d y ~ ~ r m d a s u c h ~ ~ i s ~ f b e .a ~ t ~ & i g ~ ~
sustained loads. All these loads occur beaure mdnot -hit in nature.
of 'farces created and acting on the p*&: h
fact, primary loads have their ohgin in some Broadly speaking, cata&opbic failure is
force acting on the pipe causing tension, bacause individual crystah a'gnins were
compression, torsion ttc lead@ to n d ;lad subjected to dnsses, *&the chmdtry end
s~arsasscs;Tool8rgealoadofthistypt thep~csofthtsoUddd~withstand.
leads to -deformation, o b plastic. The. Fatigue f i i i i is ofk--hcause the gains
deformation is limited only if the material c o ~ ~ v e I y , ~because e d . their collective
shows strain hardcnimg cIua&&tics. Ifit has c l u w t d t i c s (far example with
no strain hardeningpmpnty or ifthe I d i s so caeh othn &.) chaaged dl& to cyclic load
excessive that the p h d c instability scts in,the Inmemental damage done by each cyck to
tystcm would continue t6 d e f m till mpfm. their collective texture accumulated to such
Ollt says, that primary loads are not self- ievds that 'thc system failed. In otber wards,
limiting. It means that the stresses cont'muc to dastmphic fkilurc is' more at m i w i c
exist as tong as the load persists and Icvcl, whatas fatigue failure is at mcsoscopic
defarmation does not stop because the system level if no! at macroscopic level.
has deformed mto a no-stress condition but
because strain harden'ig has come into play.
Tbis part of ..the papa - focuses more on orientation. which minimizes some ot4er
. primary loads .&d.catastrophic failure. A brief nonnal stress. 1 .
. . I . implication of cyclic loads and fatigue failure
j on desigi'is presented The subsequent
->
parts would deal more ~~mprehensively with
secondary loads including thermal loads and
i, . .
stress analysisconcepts. . .
tortured non-living being right fiom ik birth. minimizes some other nonnal .stress.
Leaving the furnace in the molten state, the Nonnal stresses fot such orientation
metal solidifies within seconds. It is a very
-
(maximum normal 'stress orientation) arc
hurried crystallization process. drystals called principal stresses, and arc designated S
could be of various lattice structurd pattans
such M BCC,FCC,HCP etc. depending on the ( h u r h . , sz and SI (minimum). Solid
material aud q e proccss. grains, crystals mechanics also states that tbe sum of the three
of the material hvc no time or chance to stmscs for all orientatim is dways the
orient thiPuel*in any particular fashion sameforaaygirmatternalload,ThatiS
'hey m thus from in d l rendam orientations
. in tb wld harmla pipe ~.+uiudes~rnemk sLi-s +sa 9 sI +sz +Sa
thatwescc. :
. .:. .'... . ...
n .
.. . ,. . ....<
-.
j -
1
stress in a
be
3-Dstate of stress can be shown to All failure theories state that these principle or
maximum shear stresses or some combination
I
of them should be within allowable limits for
the MoC under consideration To check for
compliance of the design would then involve
I-'
relating the applied load to get the net S ,S ,7 3
i.e. half of the difference between thc
maximum and minimum p ~ c i ~ stresses.al
n .L I
and then calculate S , S and 7 and some I g?
The maximum shear s t m s is. important to I 1 ra
.--
deemed 'to occur due to shear stress also. A
failure perception may stipulate that mrp5mu-n NORMAL AND SHEAR STRESSES 3
shear stress should not cross certain threshold
value. It is thmfore necessary to take the
FROM APPLIED LOAD
As said earlier, a pipe is subjected to all kinds
1: . '
worst case scenario for shear stresses also as e
above and ensure against failure. of loads. 'These need to be identified. Each I
'
.I .
L.
system such as axial-Hoopc's-did (LB-R) catdated fiom standard relations. The net ;
that we define for a pipe. Tbe load bearing
cross-section is then well defined and stress
n o d md shear stresses resulting firom dl
such actual and potentidloads an then arrived -1: A5
=
eil
<$5
components are calculated as ratio of load to at and principle 'idmaxbum shear stresses -2
catculatd Some potential' loads faced by a . j
load bearing cross-scctik Similarly, it is
possible to calculate shear stress in a @ d a t pipe and their relationships to stress rtn 53P
plane given the torsional. or bending load.
What an rtquked fix testing failure-safe
nature of design &, 'however, principal
stresses and maximum shear stress. These can ". . ...
. ..
. be calculated from the normal strcsscs and pig
A,p i g may ..&
a;;!
may .. face...,..~:#&,.:
.*;
&d force (Fi G). . a&
. .:t.- a$-+&
.: ..a-';=-
. shear stresses available in any convtnicnt .. :;.* . . & . .
;
T d\ --------.-.-.-.-.-- ,.-.-.\.
. ..
r .i.. :. .
.
Idad. dkction, A The stress can thcn be
I
. I -
-3
1
A-Lt f.' - J
S
L
=FL i Am
I
- i
1"
The third principle stress (minimum i.e. S ) is 3
1 The load-btaring cross-section IyLY be 1' ..
calculated rigorously or appraximtely - 3
follows. f *
A =~(d'-d3/4(rigorous)
(4 0 I
= z (do + d)VL(based on average diameter) Thc intemal:pnssun .also induces strrsses in
I the. circrrmfcrtntial direction . .as shown in
=zd t (based on Outer Dimeta) Fig. 3.
0
Fm t&l : w e d pip,
e t i m c a a k neglsotcd' Fmm manbra& . .
theory. SB may then be .approximated
. .
u
A pipe used for trrulrporting fluid would be fofi&&
! under in(rrml pressure load. A pipe swh as a
:-.
i '
jacketed p i p -or tuba in r Shell & Tube
exchanger etc. may be under net external
II pressure. Internal.or external presstat.induces
Radial stresses are &o induced due to m t d
stresses in the axial as well as circumfmcial
(Hoop's) directions. Ilu prrrans also press~reascanbesetn~mFig.4.
induces mnrcS m the radial direction, but as
I ?
. . argued earlier, thwe m often neglected. aE
9,
. .
''fle+& l.9/jdm: : a'
!
PIPE UNDER STRESS
i
PIPING ENGINEERING CELL
At inner radius, it is also com~ressive For fixed supports, the maximum bending
but equal to absolute fluidlprcsure (P ). In moment occurs at the ends and is given by
a
between, it varies. As mentioned earlier, the IXam theory as follows.
radial component is often neglected.
M = w '.I / 12 for fixed support
mr
Bending Load
Thc pipe configuration and support types used
A pipe c8n face sustained loads causing in process industry do not confirm to any of
bending. The bending moment can be related thest id* support types and can be best
.
to normal ahd shear stresses. ,.
'
considerid as somewhere in be- As a
result, a .common practice is to use the
Pipe bending is caused mainly due to two following average formula to calculate
reasons: Uniform weight load and bending moment for practical pipe
concentrated weight load' A pipe span configurations as follows.
supported at two ends would sag between
t h supports
~ due to its own weight and the
weight of insulation (if any) when not in
' opmtion. It may sag due to its weight and
Also, the m a h u m bending moment in thc I
wcight of hydrostatic test fluid it contains case of actual supports would - occur
during hydrostatic test. It may sag due to its
own weight, insulation weight and the weight of somewbae between the epds and the middle
the span. I-
of fluid it is canying during operation All
these weights are distributed miformly a m s s Another load that the pipe span wouId fact is
the unsupported span and lead to maximum . the concentrated load. A good example is a
' bending moment eitha at the center of the
' 1 '
ipan or at the end points of the span (support .
valve on a pipe run (see ~igure-6).
location) depending upon the tyge of the .. 7
Pdn LoadW
support used.
-b
. . . .
PlmdqW
.
I '
span be L (see Fig. 5).
t o b l bad
-
b-1 ~WWJmt I
-L-
I=
Fig*6: POW&Latd +. .
q. \ o n ~ t &s+-c
~
. .
. .
. . . -. . ,
i
), S =Mc/I Torsional Load
L b
> I
This load' (see Fig. 9) also causes shear
1 I is the moment inertia of the pipe cross- stresses. The shear stress caused due to torsion
I section. F0t a C ~ U ~~OSS-%tion
U pipe, I is
- at outa pipc rndiur ~~d is givsa
I . given as there in tenns of the torsional moment and
1 !
pipe dimensions as follows.
1
i
i
PIPE UNDER STRESS 7
)
!
i
PIPING ENGINEERING CELL
of specimen). . ..
THEORIES OF FAILURE . I . 2
. . .AP
strainsiarthc~orstruc~partcro~s . . , .
( 1
;id
_ . .__ ..... .. . ....
'.' . . . . . . .. -
- . . .. .
1
. ..
a. ocrtain threshold d u e . It is a n d . . .._._. _: . .. . . . ..- . .____.,< .. -;:.
,
specimen at the point of yield. That are it is intmsting to check the implication of this
various theories of faitwe that have btcn put theory on the case when a cylinder (or pipe) is
forth. These theories differ only in the way the subjected to internal pressure.
above-mentioned fimction is defined.
Important theories in common use arc As pcr the membrane theory for gnssure
considered hen. design'of cylinder, as long as the Haape's
stress is less that the yield stress of the MoC,
the design is safe. It is also known that
Hoopc's stress (S ) induced by internal
H
pressure is twice the axial stress (S ). The The maximum shear stress in the system
L
should be calculated as earlier.
.
principle stresses in the cylinder as. m the
&lit& given formula wouldbe
It should also bcintsssting to check the
implication of this theory on the case when a
cylinder (or pipe) is subjected to internal
pressure.
s = (SL + SHy2 - [{(SL - SH)n)l + rZ]"'
2 As the Hoope's stress induced by internal
pressure (S ) is 'twicethe axial stress (S ) and
L
thi shear stress is not induced directly (T = 0)
The nixximum principle stress in this case is the maximum shear stress in the.cylindcr as -
-
S (=S ). The Rankine theory and the design per the earlier given formula would be
2 H
criterion used in the membrane theory are thus
compatible.
sheer stress in a 'system Vmax) is greater than considq the design formula for sphere based
the maximum b a r .ukcss at yield .in a on membrane theory. .-
sptcimen subjected to uni-axial ,teasioa t e a " - . .,
Note that it is similar in wording to the Octahedral Shear Theory . ..
statement of the carlid. theory except that
mximumshcar~tnsgkusdascriterianfor 'Ibis is also called von Mists thcory.
co-on as against Illaimtrm @cip!e According to this theory' failure occurs when
s h s s used in the Rankine theory. the actah& shear st+s in a system (s ) is
d
In lmiaurial ttst, the maximum 'shear stress at greater 6thc octahedral shear stress at,yield
yield as per definition of maximum shear test in a specimkn subjected to uniaxial tension
given earlier is test Note that it is similar in wording to the
statement of the &hi% two theories stet
s = 0 5 [(S - S Y+4ra]*J that octahedral shear stress is used as criterion
.
p L iI for comparison as against maximuin principle
=SR=SR stress used in the Rankine theory or maximum
shear stress used in Tresca theory.
The Trescs theory thus just says that failure
occurs when the maximum shear stnss in a The octahedral shear stress is defined in terms
system (T .) is more than half the yield stress of the three principle stresses as follows.
II
of the material (S ).
Y
maximum tensile load of W, then the load is strain vertical. What the later gives is the
I
removed gradually till it passes through zero hypothetical stress that would have tieen
I
Certificate Course
PIPING ENGINEERING.
. -
May 11 27,2005.
Prof. A. S. Moharir-:'
. . . ..
. . .... .. .. ? .
......
. . .;
. .
..
Orgrrnriea by - . ' . .?
. .
. . . . .. . .
. . ..
. . . .. . ..<.
' Plping Engineering:Cell
'
. . ..;..
.
. . .
_
. ..c
.:...
. .. ..
Computer Aided ~ e s i g nCentre . .
.
..:.. . ..
.
.
Indian Institute of ~eehnolo'g~,Bombay
Powai, Mumbai -400 076
. . .
.. ' . li
I
' Piping system's importance in any process plant cannot be over emphasized. In
terms of cost, piping cost is estimated at approximately 25% of the total plant cost. This
is next only to the equipment cost (approximately 50%). In terms of engineering man-
hours, piping consumes almost half of the total man-hours. Same is the case for field
man-hours spent on fabrication, assembly and testing. The operating bill is alsa bloated
significantly by the energy consumed in transporting process or utility fluids through
pipes connecting equipment. In transport and distribution business such as cross-country
pipelines or gas networks etc, the entire capital and operating expenditure is in laying and
running the pipelines. Piping systems, wherever and for whatever these may be
employed, thus have a major footprint on overall project economics.
This module deals with fluid transients. The origin of fluid transience, i.e.
dynamic change in pressure and velocity profiles along a pipe route, otherwise designed
for steady state behaviour, impact of these transient values on pipe integrity and methods
to mitigate hannful fluid transients are discussed qualitatively as well as quantitatively.
1
PIPING ENGINEERING CELL
fluid. A fluid is defined as a substance which when in static equilibrium cannot sustain i
shear forces. The tenn 'fluid' encompasses 'liquids' and 'gases'. i
I
It is merely a statement of conservation of energy as applied to fluids in motion It ,
considers any fluid as having three types of energies, namely, potential energy, kinetic
energy and internal energy (by way of fluid pressure). While allowing exchange of I
energy amongst these forms, Bernoulli's equation states that the total energy remains -
I. i
constant. It is best understood by considering a conduit carrying .fluid between two points
f -
'1' and '2' as in figure I. If P, ,Z, and v,; i =I, 2 represents the fluid pressure, elevation 1 I-.
1
The equation is valid for any pair of points along a conduit. 1
7
-, ,.
A special case is worth considering. Let the conduit be horizontal ?
, ,
(Z, = 2,) and of unifom cross-section (v = v ).The above statement of conservation of 1 .
- f
3
energy would then imply that the pressure is same at the two ends of the pipe. This is I
L
contrary to expectations as one expects pressure at upstream point ('1') to be higher than -
4
the pressure at the downstream point ('2') and tbis pressure difference actually sustaining 2 z)
,
the fluid flow. A force (P, -P )# is then seen as acting on the fluid between points 1 and
. .
X?
-7
B
2 camkg itto move h h t i o n f -+2,.
.<
. .
,
. .
. '
. . . . . . <:>
.
..,-
. . . . . . . . . . . . . . . . ,.:,<..v,....
.
. . . . . ..,
.
. . . .. -I.,... : . . .
.?
* .
--- ..:
'1
This is incorporated in the 8 e r n o ~ l i wequati6n
s] by a 'loss? terms as follows: . .
. . .
h, is the head loss which accounts for the loss of energy due to fluid fiiction I. -
b
and/or turbulence. In fact, this energy gets converted into heat, marginally increasing the
fluid temperature which gets dissipated and is 'lost' for all practical purposes as it cannot
be employed to do any usehi work. Pumps and compressors are provided in the process
plant essentially to sustain this 'loss'. This 'loss' constitutes a significant portion of
operating cost. This constituent of the operating cost can be reduced by opting for a larger
bore pipe for a given service. This, however, increases the capital investment. Pipe sizing
is thus a balance between capital and operating costs. Reliable estimate of frictional
PIPING ENGINEEFUNG CELL
losses is thus important fiom process economics point of view. Some basic concepts and
calculations are covered here.
Frictional Losses
The fluid plug within the pipe between the points 1 and 2 experiences a differential
pressure at its two ends. This causes a forces acting on the plug which is equal to
(4 -p2 k
mi2 .
Where t$ is the pipe cross-sectional area (=-).
4
From above; this force is thus
PIPING ENGINEERING CELL
However, since the fluid plug is moving at a constant velocity (i.e. no acceleration), there
can be no net force acting on the plug. The above force due to pressure differential is seen
/I
as negated by an equal and opposite frictional force between the fluid and the pipe wall in I
contact with the fluid. If this shear force per unit contact area (shear stress) is denoted as I
I
.. 3
!
I ^"
I r
The shear stress depends on fluid velocity (v), fluid properties ( p, p ), and pipe properties
( d , ).~ E is a measure of pipe roughness and is expressed as an average height of f -.-,'
'roughness' mounds on the pipe surface. It is also called as 'equivalent sand roughness'. 1, / _
-
L .
. j
Thus
One can apply dimensional analysis to this qualitative hctionality and arrive at the i ,I>
b
1 :i
following relationship in dimensionless numbers.
dvp E
p d
For a given flow of a given fluid in a given pipe, one can thus write
--
' 1 - comtyt = x (say)
pvZ . . .. . .
,.
or T, =.xpy2 . . . . . .
.
. .
!
. ;$k2
- . . . . .
. . .. . ... . . .
. .
. . . .
. .
.+
. . 5.3
Using this in the force balance written earlier one gets
. .
. . .
. .
. . . . .
.
c . . . .
. .
. . . .
. .
, I ' .
,'
,
.V , 9
1
. . . . .
4XLvf. : * X L v 2 .
' - .'. :, . '. , ,
. . . .. . . .
.. .
- . .. . . . ... -
.
. . . .
-
'
. .. .
.
.
.
.. . . " I)
hf = ---
. .gd . 2gd :. . . . . . . . . -,>
. . . . . ,..A
. .
. -. .$
This in the hdamental relation used to calculate fictional head loss for flow through
pipes. X or its multiples are termed as fiiction factors (f). Three common definitions of
the friction factor are as follows:
I. Churchil
PIPING ENGINEERING CELL
f, =8X a h , =-f,Lv2
2gd
The use of three friction factors (without a subscript) is a source of confusion and often
calls for care on the part of the user. Over- or under - estimation of pressure drop can be
caused leading to erroneous pipe sizing or rating of pumps/compressors etc. if this point
is overlooked
The friction factor (f, ,f, or f,) is a function of two dimensionless numbers,
Reynold's number (dvp l p ) and roughness factor ( ~ / ).d The dependence is normally
presented graphically as friction factor vs Reynold's number plots with roughness factor
as a parameter. Familiarity with these f vs R e plots and a quick identification of which
fiiction factor a given plot refers to is very important for all hydraulic system rating and
design.
6
~lasikEquation
. . . . .
.
0.316:
.
.
.
. -
= 2 log (R&)
. .
. .. . . . . .. .
,
.. .
' .
.
. ..
.
.
.
. .
- 0.8
. . .
.
. .
. . .
.
.
.
.
.
.
.
.
.
.
.
. . ..
.
.
.
.
.
.
. .
. .
The above procedure is applicable only for straight pipelines. The actual pipe
routing would have several piping elements (elbows, tees, expanders, reducers, etc.)
PIPING ENGINEERING CELL
along its route as well as regulation, control valves etc. These cause extra turbulence and 1 -
energy loss. For simplicity of engineering calculations each element is assigned !
equivalent length. This is the straight pipe length which would cause same pressure drop ,- -
as the element for same flow rate. The piping elementlvalve can thus be replaced in 1 -
I
calculation by the equivalent (hypothetical) length. Total effective length of a pipe route
is thus calculated. Frictional pressure drop for a given route is thus calculable.
I TC'\.
I
Some Examples: a
+ Pressure drop in straight horizontal pipe
+ Pressure drop in pipe with fittings
I;
,'-I
The transient phase could take the system monotonically fiom one steady state to
another or take the system through over-,under-, or critically damped oscillations. Some
simplified situation could be analysed to appreciate the mathematics and behaviour of
fluid transients.
Ln the following examples, the fluid has been assumed to be incompressible. Also,
the changes in pressure are assumed not to cause change of phase. For example, consider
a liquid in the piping system well above its vapour pressure throughout.
Example 1 :
PIPING ENGINEERING CELL
I
I
'>
Consider a straight horizontal pipe as shown.
At steady state, a force balance over the pipe section between two points '1 ' and '2' was
written earlier as
i I
1
I
The term on the left hand side is force on the liquid plug due to pressure difference at its
two ends. The term on the right hand side is the shear force (fictional force) between the
.-, i moving fluid and the stationary pipe wall. '9' is the cross-sectional areeof the pipe. vo is
j ! --a\
If for some reason, say downstream pressure 'P, ' is suddenly changed at time
zero to P ,' and then held constant at P, 'subsequently, the velocity wiH change with time
and finally stabilize at the new steady state value v' given by
.>-
J,
,
.
'r
i
me
. . .
will change from vo to v' during the barnid phase and. one would
like to get a measure of that and also the governing mathematical model.
'
.- x3
~
velocity fkom vo to v'. There must, therefore, be a net force acting on the fluid. This is
the difference between the force due to pressure difference [= #(e- P,')]and shear force
at any time t when the velocity is v
i The net force must be ual to mass of the fluid plug between points '1' and '2'
J
j nultiplied by acceleratioJ= "/dj
at that instant
Expressed in an equation
....
h, -
- - ---
P, P * ' --. I
dr pL pL 2d
f;?
'
-
(Remember that the friction factor ' f ' itself is a function of v ) . This nonlinear first I
I
order ordinary differentical equation is subject to the initial condition.
-
V = V , at t = O
I
1 . '8
The solution gives a v vs time profile. Without solving the equation, one can
1
qualitatively say here that the velocity will monotonically change from v, to v' . The rate i
of change will be high initially and gradually taper. I . ',
One can extend this to a pipe which is not horizontal as well as a piping systems
with several piping elements as well as valves. For a simple case of laminar flow, one
I I
-..
$3
>
-~5
..-
could even attempt and get an analytical expression. Also the perturbation which sets up
fluid transients could be due to different causes and of different temporal nature. Some
such exercises can lead to a better appreciation of Bernoulli's equation extended to I <;
t
transient bchaviour. r g.i,'
. . . . . ; I ,-.i
!. ... . <.
...
Oscillating Transience '.>...
1 len*. of liquid.
r
.
colunrn= L
. ----------.-.-*-----.---.-------.-
.
,
- . feafflte l e d . .
- . .
2'. . . .
. . . .. . .
. . . . . . . . . . .. . . . . .
..
. .. . . . .
. . .
.... . .
. . . .. .
. : . . ., .. . . . . . . . .
. .
Let at time zero,.the column in the right limb be pushed down below the datum by
height h ,(thereby also raising the column in the left limb by h above the datum) and ,
PIPING ENGINEERING CELL
released. This perturbation sets up an interesting dynamics in the systems, which can be
modeled as follows:
- Let the fluid column be at position f h at time t as shown. Applying the Bernoulli's
1 equation modified for transient behaviour earlier, we get
f > I As 4 = P, and v, = v , = v
dh :
Also v = -
dv
, - - - -
- d2h
dt - dt dt2 , .
h (t) = c, cosc2t
1)
we get c, = h,
and cz =
w e thus observe the liquid column oscillating with an amplitude of h, and a frequency of
period of vibration is R
P%-
What happens if the fictional losses are not neglected ?
Can we make a statement as to when a perturbation can lead to this kind of oscillatory
response in a system ?
PIPING ENGINEERING CELL
-- -<. '+
Transient Discharge from a Tank
L
At any time 't' after the tube exit at point '2' is opened, Bernoulli's equation modified for
transient flow is :
2 2
-
4 + L + z ,- 4 v2
- -+-+Z, +h, +--L d v
Pg 2g Pg 2g g 'ft
Therefore,
Let the velocity at steady state be vo. Then, fiom steady state Bernoulli's quation. - 3-
i.,
Subtracting the steady state equation from the unsteady state equation, one gets
i
PIPING ENGDEERING CELL
i i
Rearranging ,md writing in integral form: . :.
. .
j.
-.- .
.-,
.F 'I, Integration using partial fractions gives
. .~
... ..
_$
i as c ,one can write
One can thus see that $e fluid velocity v reaches steady state velocity monotonically.
Time to reach a certain percentage of value of the steady state velocity can be found out
- - easily from above.
k; 1. What is ct for
v
- =- ?
1
>
4
vo 2
v
2. What is cf for - = 0.99,0.999?
"0
The mass of fluid plug in the horizontal pipe (length L, cross-sectional area .I$ ) is #Lp.
This has to be brought to a zero velocity h m a velocity -v, over a period of r seconds.
It thus needs to be imparted a deceleration (negative acceleration). Its magnitude can be
found by using the instantaneous velocity vs acceleration formula.
v = vo+at
Where v is velocity at time 't' and 'a' is acceleration. For v to be zero at t=r,
acceleration should be
=.
A mass (rn)of fluid in the horizontal pipe (m'= #Lp)can be impaxted this acceleration
(a) if a force F (= ma) acts on it in a direction opposite to the flow direction. ) . -* _
U
. . . . . . . . . . .. . . .
. .
. . . .
. . . . .. .. .
.
. . . .
: . . .
.$
F/# is the that would be gmerated i t t h e exitend of the pipe. %his p k u r e
L .. *._
.,.
which is generated due to sudden closure of a valve is called water hammer. Water
hammer effect can be severe if the length of the pipe upsbeam of the valve is larger, \ >
h
and/or the density of the liquid is large, andfor the velocity of the fluid prior to valve
h
closure is high, andlor the valve closuft time is small. Excessive pressure can lead to 1-
system failure. While L ,p , v,, are dependent on layout, service and pipe selection, the I A
PIPING ENGINEERING CELL
closure time( T ) can be suitably planned through valve selection, design and operation.
Valve choice is thus crucial from the point of view of mitigation of water hammer effects.
The above is a highly simplified picture of water hammer. It none the less
-
provides a quick conservative estimate of pressure levels that could be expected t o
develop due to sudden valve closure. The actual pressure developed will be somewhat
less than this estimate as the liquid is not totally incompressible nor is the pipe rigid.
Compression of the liquid and elastic expansion of pipe cross-section due to heightened
pressure help mitigate the water hammer effect to some extent.
Other complications are 3-Dlayout of piping systems in reality, to and fro travel
of pressure wave and possibility of its reflection, thermodynamic behaviour of the
flowing medium at different pressures which may cause phase change (evaporation,
condensation). Applied mechanics, fluid mechanics and wave mechanics all get together
to decide the pressure-velocity profiles with time and space in a piping system subject to
sudden closure (or opening) of a valve or a failure, restarting of a pump. The mathematics
is quite complicated and calls for numerical solutions of the governing partial differential
equations with numerous boundary conditions. Competent s/w tools are available which
expect the user to 'define' the system. Setting up of equations and boundary conditions as
well as solving these to generate pressure-time-space and velocity-time-space profiles in
the piping system is the job of the s/w. The user then analyzes the results and suggests
remedial measures (surge vessel, pressure relief valve, valve closure pattern., control
valves, etc.) to safeguard the piping system in the event of happenings leading to water
hammer effects.
The following sections deal with water hammer analysis with the aim to develop a
feel for physics so that educated use of such computer aided analysis is possible.
. . . . . . .. . .. ..
.
. . . .
. . . . . .
.9 .
'inthe medium. k'iirelatd to the fluid prop.&tiesas foliows. . .
j,
.i where E f is the bulk modulus of elasticity of the fluid.
PIPING ENGINEERING CELL -- I
time to close. Relation of the magnitude of this time to the time required for wave . I
reflect.\onis an important factor that decides the maximum pressure that gets generated.
I
Maximum pressure gets generated at the point of application of closure if the
valve closes in a time (T ) less than the time taken for the pressure wave to start fiom the
!I i I -
point of reflection, reach the point of application and return to the point of application.
The returning wave can negate some of the pressure and reduce pressure levels.
'
i'
i
I
r-
1
* Ii
If the distance between the point of closure and reflection is L, the above can be I .:.
.!,,
I
8
. 2 ;
,
''
. A reasonable correction for the maximum pressure surge given by Joukowski ,
8
,
I
+
$
;
V
formula for cases where valve closure spans over a period ( r ) more than 2L/c is given I J I -
27
by 1
i ..
' -.
'i
if
The reflected and the original waves can cause periods and locations of high and I
low prkssure. Periods of low pressure can cause degassing of liquids or even evaporation. I ..
I
-a1
2
Similarly, high pressures can cause re-condensation ctc. High and low pressures also can
cause periodicity of stresses in the pipe and eventual fatigue failure.
. .
. . ..
! $- x 1
Fluid transients -occur due to. r s ~ e d ~ t h sapart r v from &4?* yd~q.,
closure. ntc other .reasons could be suck& opening of '~alves, startirig -or stopping of
pumps, changing - elevation of reservoir, change . in- power. dqr=wd of .turbine,
. , '
.
. : . .
reciprocating pumps,
.
tuberupture
. . . in an heat exchanger, etc. . ..
. . .. . . . . . . . . . . . . . . .
.
. .
. . .. . . .
. . . . . . .
. . .- . . . . .
. . . :
. . . . .
Flow transience in ariy piping system or its section is captured in the following
--
two simult~eouspartial differential equations.
The two dependent variables are the pressure and the velocity of fluid. The two
independent variables are time and space.
=
..-
--) The equations can be solved with suitable initialhoundary conditions. These
,L would be situation specific. For a simple case of a straight pipe discharging fiom a large
19 resewior through a valve and the valve then closed over a period r as per some closing
;
i. curve, the conditions could be visualized as follows.
- \
3 P (x = 0, t)
3' = pgh
. P (x = L, t) = Pressure drop across valve
i P (x, t = 0) = Steady state pressure
v (x, t = 0) = Steady state velocity
j3 v (x = L, t) = Valve discharge rate/ pipe 9
,I
. .
For pipe routes with different . . and other valves e m u t e , sfiiu may
. .
. be required.over ea& s e c ~ o a,
..
That grid size which gives grid-size-independent .mlution is desired. Finer the grid,.more . . . .
. . . .
. . . .. . .. .. .. . . .
It is also useful to mull over the reasons for a product 44 appearing in one of the
equations. What physical statement is one making in this term?
. .
P I P N G ENGINEERWG CELL
P u m p and Valves
The occurrence of pressure surge has been discussed so far in relation to the
sudden shutting down of the valve. In general, pressure surges would occur as a
consequence of any event which causes rapid change in the velocity of the fluid. Rapid
closing or opening of the valve or start or shut down of a pump could cause such a
change in velocity and hence pressure surges. The role of pumps and valves in the piping
syste~ is discussed here further.
Comment on the possible happenings and pressure surges that 'could develop in the
system for a rapid and not so rapid valve closure. - . - - . , - - --.
+ Compile a list of data that you would collect to be ready for transient analysis.
Discuss qualitatively worst case scenario (very rapid closure)
+ Discuss instructions1measures to avoid abnormal pressures. i..
Control Valves
If there is a pressure/ flow control valve on the line experiencing surge, the
control valve dynamics would modify the surge characteristics. A knowledge of control
valve characteristics and control law is important. Some basic background of the types of
PIPING ENGINEERING CELL
, * ,
. .
I
I;
'-.,
(
k
j:
-?;>i . '. 4
, . .
,
. .
Vaibhav Pradham ' .
..-
: z Forbes Marshall, Mumbai
-j'
I):;
- .
1.
s;. i
:)..
. i
4
j
: :
. . . .
)I
i"'
,.
. . . .
. .
. . . . . . . . . . . . . . . .. .
,I.., $'
.
. . . . . . . .
. .
.
.
.
. '
.
. Organized by: . ...: :. . .. . ,
. .
I> . . . . .
. . . . . .
. .
. . .. . .
. .
. . . .
)\
i
. . piping Engineering Cell
. . ' 8 .
< . .
') I Computer Aided Design Centre
Indian Institute of Technologs Bombay.
. . . .
-
' ' '
)
Powai, Mumbai 4,00 076
) . .
i
)
. .
. .
. .
. . .
.
. . .
. . . .
) . .
i
%"Lw
arbes
Ty@cal Steam CI=uit
urn
. .
I
.. . . .
,
. ,,S - . Steam should. be 'avajlable i t the point of usag,e
I
i'
. . I 2
. . a ~ dtemperature and
El At the correct~~'.pressure
.
El At the des'iredtive. ..
eFa-;
7-.>
Feed Wa te s.
Temperature O C
.Fq
-15 bar
CAPITAL. COST
/ ELfCTRlCllY COST
-
.
-
fiery ton !(steam eeneruted per hour costs YOIJ
.
us. 60kkh$ .
Der anntjm
. .
. !..'
fJti!ity cost of 5 Ton boile; will be more
.. . .
- per arinum
-crc~re
Diit'&6~v
c ~ w iIS\ fws ?
dseful
2.The indir,~ctmethod. :
..
% q = I00 i'los~es
. . :. .
= 100 - stack loss L1
1 lossdue to watefand hydrogen in fuei L2
- radiation loss L3 - .
So, I % 11= .I
0'0 -'.(Lq-t: L2.+ ~ 3 1 1 C/.
.
/
_
This is far more .useful,
.... , because we are interested in I
increasing boiler e.ffici.6ncy
. ....:.. by r e d ~ c i n g ~ t h e
losses.
If each loss' is separately monitjred, thCy can be 1,
min&ized'e.g. damper tuning will reduce stack i?ss. I
!
-
. . efficiency
ize Boiler
2.,',I(1 I , ~ ~ - ~ ~ > ~ R - ~ ~ ~ ) / L L , % ~ ~ \ E ~ ~ Q . E ~ ~ J ~
-1 i(:now your boiler losses
- -
I J i b l ~ n ~ / - nS~~zCeI C ~10:;s
<
EXCESS AIR "/p J
Optirni=e blow down
STACK
TEMPERATI-IRE -'Trock your process itecnr co/lsunlb:,;an
STEAM '. 'J Keep continuous check on fhtd water
CONSUMFTIO~I
qlrolicy .
6011,ER
EFFICIEbICY , , -I Cfo~.v%s
eye on feed wocer t e m p e r o i i ~ r . :.
S:F R A T I O ' .. condensate I-ecol/ery
FEED WATER
TEMPERATURE ILI in imiz e elecrricity bills
,
.
. . . c .
. .:
.. .. :. .:.: .
. .
.';.:!:..:.. .-.I.<>
I
,.<.:::'..;-t><..
.I :.
.---.
,
. _
. .. . - - -* - - - .. - ...... . -
..I g percentitge. .
1. ~ x c. e. Air - .
-1 2. Stack ternocratt~re . .
J 3.- Conlbuslio~lair inla t tcxnpe~ali~l.tr
-1 1). Feed walrlr tompnri~ivro
-I 5. F t ~ vral(rt
d TI33
,I fi. W ~ O Wd O ~ l ~I'OC]IJ~JI'~C.\I
l
J 7. U t l - l ~ t ~ ~ l(>sse!i-
~tia . - - -
J 0. l.onclin!j g~iltterrio l troilrzr
J 9. t3oiIcfbi~i:;i.~l;~tiOfl ..
-1 if f\'flllli?iLy
10. R ~ ~ r r i f c~~f/ciff . .
J 11. ~ttnl;-~clunl/ly i :
-1 12. nurher nozzle ~ o l l i i l i t l ~ t ~ '
-J 13. Flar-fi(: profile ..
J ,114. F~leltenri~eraiure ..'j11
1. ill,,,.
-J 15. Fuel i~rassure
-J 16. f3urncr vil~ratiori , '
'OX~I~PI~
~-
I
.- ]A~i;llyser
! -Steam I
i Outlet I
.!
Flow 'Fneter I
.,-
., .i .
:
I '
I:
d\-. , :
i;
:1
!
- .
i :;.
Tzm erature
1 Bailer , i
.
.:
Flow
Rate
. 'I'
Pressure ibar g)
w~orbes The effect of too high
$ mrsw
TDS in the boiler..
HighTDSandlor . Contamination of Fouling of
..
suspended solids. Control Valves Exchangr
/ :sFi
7%-1.T
.Blockage
.
of Steam Traps .a2rz.
Control System - B C S I
.. . .. ..
. . .
. .
- : -: . ,
. .:
. . . ,
.
.
- -. . . . . . . . . . . . .
. .
. . . ,
. .
Barg ...
i-wh y . ~ e a sreu S t e m ?
i
Accuracy I I
i
c-
Turn Down . .
A
.
=.,
s
I
i I :
-7I
-2
i \ , -
n Densitycompensation I -"
-t!
:;;':!':I;--
. .,,:i:.: I I
9a $team Line Reducers
I
Condensate .
X incorrect
' . '
Cross-Section
4GGJKC; MAIN
. . .
+LA-. 11.
.... ... --- < - -
.-..__
. - .- -
: A-
-
--
-
--
. . .
' noi.ic
Vibration and t
k
c,auseclby
waierhammel
Slugofwaterfrom
. .? I i:d
Air Venting
j,
I ;I Application
4
.-r
-
1- 1 System pressure
); Back pressure
-
): Temperature
1 Differential pressure
-
)
Maximum load .
)
1
Minimum load
) Safety Factor
. i. l
Lift after trap
I rl
Temperature Control
Type of plant
Mate'rials IConnections
Condensate return
Freezing
Vibration
Air venting. . .
'
2
.
,i
.
.
. .
, . . 1 ' *
J
.-.
I,
1
.
&
7d
e*i- )
'j
:
.<
. . . . . . :
Q
.._ - . . .
a Ch:eelr-thefies,s~fe,;~a~fid'~~j,,~w
1. .) . .
.a' .
. . .
.
. . . .
. .
-,'..: 'I...' . . . .
........
1.i .
>_
xi-
.
. . . .
.
..
.
. . .
.
.
.
;.
. ... .
. . . . .
.
.
. .
..
.
. . . .
I
. .
.
ij
:)
. . . . .. . . .. . . . . . . . . .:
. . .
.
. . . . . .
. . . .
1 : -j
n Check the Instalation:
, ' , .
. - . . .
,
. .
73
.
- .
-.
.
7.
i:
.I
~.
..- .
\-. J
. . . .
. .
i
.a.
.-.
. . .
. -
.
. .
.
, .
.
. . ..
. . .
. .. ..
. .
, - .j
. . . . . . . ...
. . .
.. .
. .
.
. .
. .
. . . . I
.. 7:. .
.. --
Thermodynamic Traps
a Thermotatic Traps. . . .
.
-MeChanlcal Tra,,ps;.,l
.: ..
, ,
. .
:
. .
BaH:Frost:Traps1.' .;
C
. . . . . .. . .
. . . . . . . ' . . . . . . . .
. . . . . . . I : :
. .
. . . . . . .
.
.
.
.
'Inverted:BuAefTraps',: ,
. .
.
.
.
.
. . . . . . . .
. . . . .. . .
. . .
,
I
I .
On start-up, it:cominy
pressure raises the
disc
Cooled condensate,
plus air , is .
immediately
dischargeci.
..
dot condensate flowirlg
I . through the trap releases
flash steam.
High velocity creates lob\/
pressure under the disc
drawing it iowards t h swt.~
-
Simbltaneously. flash stearl
- - -- . - - - - ' .. - .
*- -F%; L
I
3
.d
Pressure in the
. . . . . . .
. . , Jhe ,cycle.'is. ~ h : ~ ~ : : . V.
. . . . .
. 'repeated and ..
. condensate moves -
freely throuy h the
trap. .
Condensate Removal From Steam Mains. . '. : c. I s&=+1
. .... ~
:., . -
+ J
i
I:
I I
c
b8 ::
1
'1 :27
. .?
! 2.:
.q3
I,j L
-.
A;r
$4i -
..
I. L
.-
%<
- .
\
. .. .
".->.
.
Jnivrrsily' ProieU Slic 8
LC -:
011start up, Condensate When steam
tliermostatic air reaches trap. Float arrives float clrops
i ) . vent allows air to raises and lever and rnaili valve
bypass main valve mechanism opens closes
I main valve. Hot
condensate closes
air vent
Bloat Trap
..
Appllcaaen: Jacketed Ves:se/s
Unit Heafe~sHeafef.
. . .$.
,.
. _
es and.
:I Driers
. .
Ti:. anc!csed Th? van: hole in th?
i:?Jl:l 1:011C'~llS2S ' buck?:.:rill kl~o.:!
arlc! stzani ercJ[;es air into tire top 1;f
. :r . ..
.- -..:, ..'
-
.,-
. , . . . .*
- . . : . . 8
.. .
~~p'a
. r .h e a ' t e
.,. Steam
d .
i Heat exchangers.
I
I
Mains
i Jackets .. drainage
.
8 ')
Air heaters a .
Thermodynamic Traps
Headcrs
Separators
. .
o Float Traps
--.
- .-
. .
,
Inverted Bucket Traps . .
. . .: . .
I
. .
. . . .
. . It
-3, .
f . . . .
. . . . ; '
! f.9
ii "r
I -
. . . Space ' i .
. . -tanks
heating db
.
-. . . .. :.. . . .-., . . . . . . . . .
. .
..- :
%3
. . . ,
. . ,:.
. . !
. .
f.2
.
'
. . . . .
i . . ,
.
.. . .
. .
..
. . - . ..
. . .
;
.
. . . . . . . .
.
. . .
. .
. .
.
. . .
.
.
. .. ..
' ..
.. ..
..
. .
.;
.
.
.
.
' 1 . .
.
. .
.
"
.
.
- -
.:
i
. . .
coils . .
coils I
1
i i . . . - .
. I . . i ! ..
. . heaters \
0 ujjlpw. :. Radiators !
. Instrument ~ a d i nat
.
1
. . . . :. i
heaters , ' . . . .
~alo;ifiers panels
j
. . . .
. . .
....
. .. .
.
.
. .
.
.
,.
. .
I:, ...
. ;: .,
. . . .. .
.
. .. . . . .. .
. a
. iI I
4 - .
J
. . . . . . . ....
.
...
I
FT . ~p TD. '
. .
.
.
~ p TD
FT'.:- ~. p . ~ ' ~pp FT: .
'.
. .
.
.
,
FT
- I~~+AVI (SM) . (BPI . . . . ( i ~ + ~ \ i )lrbl (SM) :. . (EP~ . ( ~ 1 )" . . . . ~. I B. + ~. V ). t ..
. . . . . .
(BP) . .
...
The ~onsequencesofSteam Leaks
,. :. , !.?
. . I
E For a year of. .. 8400
.. .
115,000 H~T,%
hourstm
. .. . . .
.
a
..
- . .
bf natural ggs.. -. ..._.
. .
repi&kntiia
. : -..' !.%:? . ,2:+<:<*i,$: .:;2-
. .1.. .: :
waste
;:>,:-
.
&
of
_ . f &&:!
.-,
i
r.. ..4-
....? -- -:y, ,: ..$,t .
-i;.x-
;pt. . . . .,
. :, : ,:;
... .....
.
..- ..'?.
. . ..
.
.
'
. . .. . . ,
Conden sate is an extremely valuable resource.
The high heatcont.e.nt.
f5edwaterosystem.
* justifies ~eturning
- -
Conden sate has a.lready been treated;and ., :.:
.
it...totl2.e:
thu.s.
.
.
.
..,.:
.
. ... 1-
!
1
I
I
I:'
I
is ~ 0 .continually
i being.--added-tqthe boiler. 1.
Result: up to 20% fuel ,savings.
- .. . -
A ....
. .-
Water supply
(15OC)
....
. .
. . . . . . . .
. I-. . . . .
.
. .
.
.
.
;. .
.
.
.
. .
.:,
.
. . .
. . .
. .
-valve..
.
.
.
.
.
. . .
. . . . . . . .
. .. . .
.
.
.
.
.
.
.
-
oiler
I---- Drain
Feed
a-lmple sream System with C~ndensate ,
2 s
i Return
90C Condensate return
I-1
. - -_ - _ _-
_-. 'I
'r ,
Inlet
Condensate Outlet
I 3
'I ' 3
0
Quantity of F-lash.Steam I1' a
U
8
-
I
!' - .
x-?
> 3
'[ ; 3
1' .
2 It c a n be operated with steam, col1lpressed
air or gas
,. 1" It can operate witk a mit~irnurn0.35 bar(g) to
I a maximum of 8.7 bar(g) without any
adjustment
2 Every 1 bir(g) inlet pressurecan lift the
condensate to a height of approximately 911; /
3 When the exhzust is vented to atmosphere,
. .. .,.:.......
..
...
.-1,
.. ......... ,..; .... :.. .. .
... ...
. ... .. . -.......
. ..; . .
.. .:
. ., ... .
....... i
....... .
. . . . .. .. . . . . . . ., . . .
. . .. . .
...
. . . .. . .
. . . . .. . . . . . . .. . . . . : .. : . . . *-
. . . . ... ... . . . . . :. . .:
....n..m
. . . J
,
. .
Flash
Stearn
-~orbes
Marshall
.rt'
Y
Approximate Amount of ~ n e r g yin Flash Stea1 .r -:i:
Flash
- -. - Steam
Certificate Course
PIPING ENGINEERING
-
May 11 27,2005
+
T. N. Gopinath
Consultant
-
Powai, Mumbai 400 076
PIPING ENGINEERING CELL
di
dal' 1b ,wkh:,
o f m&tibn, .h.a. .w *-,.
thiCksess of it hcludes " s q ~ which
,
h
i
I) " en d m are
delineated as those which carry weight ihm
insulation, opgating temperatures etc. below, wit4 supporting member being in
v) A copy of insulation specification with compression.
.densities. . . The code ASME B 3 1.3 specifies
vi) A copy of valve and 'specialty.tist under clause 321.1.1, the objective of the
indicatingweights. . .
support design as:
The layout and the design of the piping and effects induced by service pressure, wind,
its supporting elements shall be directed earthquake etc. Where the resonance with
towards preventing the following. imposed vibration and for shock occurs
1. Piping stresses in excess of those during operation, suitable dampners,
permitted in the code. nstraints, anchors etc shall be added to
2. Leakage at joints remove these effects.
3. Excessive thrust and moments on Anchors are provided to secure the
connected equipment (such as pumps desired points of piping whereas guides are
and turbines) provided to direct or absorb the same. They
4. Excessive stresses in the supporting (or shall permit the piping to expand a d
restraining) elements. conbad fhxly away from the fixed points.
5. Resonance with imposed fluid induced Sliding or Rest supports pamit free
Vibratiom. -anent of pipSag and shall be.designad to
6. E x d i v e interfkence with thermal include friction rcsktancc along wiih the
expansion and contraction in a piping d d weight of the piping. Resilient
system, which is otherwise adequately supports are those which support the dead
flexible. weight tbioughout the expansion /
7. Unintentional disengagement of piping cantraction of the piping.
from its supports The'primary sapport' is the
8. Excessive piping sag in systems supporting element, which is attached, or in
requiring drainage slope. contact with the piping and the 'secondmy
9. Excessive distortion or rag of piping support' is the supplementary steel
(e.g. thermo plastics) subject to creep provided to carry the load on to the
under conditions of repeated tl~ermal strum.
cycling.
10.Excessive heat flow, exposing 1.1 Anchors
suppMting elements to tern- At an anchor, a pipe is
'
anchored to it; this movement will then intervening pipe ABCD. We could then try
either add or subtract from the restrained anchoring the header on the piperack beam
thermal expansion of the piping as the case (2) as shown in Fig 1.2 and miking a check
may be. on the forces and moinents developed by thd
Anchors may be fitted at points other shape ABCD with only this section of the
than the terminations of a pipe in which case header included in the calculation.
they are known as "intermediate anchors"
and in this sense the great majority of On very long piperack runs, where
anchors used in piping installations are of more than one expansion loop is required to
this intermediate category. These anchors absorb the expansion between given
serve the purpose of defining fixed points in terminal points, intermediate anchors MUST
the system. be fitted between each pair of expansion
loops even though the line is of uniform size
As an example of this use of an anchor, and the loops are nominally identical, as in
consider the case where a 6"(150 mm) NB Fig. 1.3.
branch to the inlet of a Turbine taken h m a ~~i~ ~
12" (300 rnrn) NB header.
=&
11~~n=a
-nH
0
ra -I?-a B
I
+-
Fig.13
The reason for this requirement is that
pM
the pipe is subject to manufacturing
YP tolerances in wall thickness so that even
B
6 -0
8" C
though the loops have the same overall
dimensions they will have somewhat
,different flexibilities and in the absence of -
intermediate anchors which define the
Fig. 1.1
amount of expansion taken by each loop,
O , one or other of them would take more th& -
F' - 12-0
its calculated share of the total movement. .
I " 2
Anchor
1.2 Lint Stops
A line stop is a restraint, which
prevents any axial-movements of the pipe to
which it is fitted but at the same time allows
unrestricted travel in any direction at right
angles to the axis of the pipe. It also permits
B rotation, freely, in my plane.
Fig.l.7
In the Fig 1.4 we have a 6"(150 mm) NB.
branch ABCD from a 12" (300 mm) NB
header, and analysis shows that the forces
and moments at 'D' due to the deflection A,
.are excessive.
- a2
c
\/
"
In Fig. 1.5, we have added an anchor
at '2' which reduces the axial movement at
.,
-
.,
i
-
iu:
A
F j
II 'kto A2but a check analysis shows that the I . o
length of AB. ,
i z
.? 3
z
8 I _ _ _ _ _----
- - EXP a3 The remedy is shown in the Fig.l.6
- ,
above, where the anchor at 'E' has been
replaced with a 'line stop'. This allows the - j3
Fig.l.5 point 'A' to move over to the position 'A'
thereby relieving the forces and moments I , :)
due to the restraining of A3
..~. --
LINE STOP I n the situation shown in Fig.l.6
- 1
<J
'
A
above, there must be an axial compression . . ..' . .
. J
,along the leg "m' to move
. . ..
' . . fme
.' . . I ..,s ?, i
.:
. .
. . . .. . . . . .
. the 12" header sidewciys against the friction.
. . . . .
. . ... . . , .1
. . o l - .--for& exeirtcd a t its sup~orts, This.k c , :
. . .
.. .. I
. . . . .. ti
. . . . . . . . ' ,
. .. .
.. could, in some instance's. exceed that' which..
. .\.
. .
' - em be .taken on the nozzle .at 'D*.
. .'. The. . . . '
J
. . .
. problem can b&rewlvedby the ,@&tion of a : -!
.
E L lc L .. f
... .
fkther 'Stop' 'on the leg 'AB'as,shown at -
. .
. ..
,. . . ..
. .
, . .
due to the thermal expansion of the length to move axially and it offers no resistance to
'FB'. In practice, this ideal situation is rotation of the pipe in any direction.
3 difficult to realize but a suitable compromise !
,- i position can usually be found. This Guides are provided whenever it is
I
compromise solution could well entail necessary to maintain the position of the
additional structural steelwork. centerline of the pipe and some of the more
i common applications are as follows.
I
- ?
I
1.2 Guides 1.3.1 ALIGNMENT G U I ~ E SIN A PIPE
1
I
RACK
A guide is a restraint, which precludes The center to center spacing of the
-
.
f
i
1
9 I
i
!
'
lateral movement of the pipe in one or both
of the planes at right angles to the pipe
centerline. It leaves the pipe completely free
pipes in a rack is such that they must be
positively located at intervals along their
length.
L2
i I --I
Fig. 1.8
. .
)i
Suppose that we have a length of
pipe in a m k as shorn:i.n.Ei&.'.B.. There.
.'-Ti
-. . j force
will be an ~ . d "x*at due to the ,' ~t should be n o t d that thiE only occurs i n : . , , . .
. . .
,:
,
, .' tbrmil. &-ion of h c k n g t h ' M * pra.tiGe on mdl born pipwok. . .
.
.. . . ..: . .
this is balanced by the reaction at thekne .,.
... .. . .
. .
.
... .
- < . ' . '
stop at 'A'. The force 'X'.deflects. the.
. . .
' .. . pa :;=..n2 )3/L2 . .. .. . .
)..
' . length 'FG'to the position F'G,' d i t i ' .
. .
),
Selection of Pipe Supports 5
PIPING ENGINEERING CELL
. . . . 2 :..
. . . . . . .
'
. .
other &sing the pipe to behave as fixed- 2.5mm (0.1 inch) sag is permitted between
end beam. Therefore, the true case lies supports. The suggested maximum spacing
somewhere between the two beam models. between supports is for horizontal stmight
Hence, as a compromise case, the stress is runs of standard and heavier pipes at a
calculated as maximum operating temperature of
4 0 0 ' ~(750'~).
These do not apply where there are
concentrated loads between supports such
as flange, valve, specialties etc. and also
where change in direction occurs between
Hence, support spacing is decided by the supports.
formula
1 = JY The location of supports should consider
the following guidelines:
of pipe between the hangers is kept less those employed by Piping Engineer in the
than three fourth (314)of the suggested design of support. Although the individual
maximum span. The hanger H4 is located piping configurations and .strhcture layout
clearing the bend at point D and within the will vary practically in every instance; the
maximum suggested span from HS. general methods outlined above will apply
The method involved in locating for any critical piping system.
hangers for this problem are typical of
hangers involves the calculation of the movements fiom its cold to - 'operating. . .
I , i:
,! ..B
thermal movement of the pipe at each position. Those movements will include. .
$
hanger location. The simplified method the . supplied by equipment --
,.&
L . = ;
>
satisfactory approximation of piping connections. :_.I
3.
movements. However this approximation For the illustrated problem the
. .-
will always give positive error. The following vertical movements are known, u.. I
.
.- .x
I
i"
H3 - 0 mrn Cold to Hot -
Step I1
Make a simple sketch between two
adjacent points of lcnown movement
. . . .
. ._ . .. , _
.
. . . . . , . ..
1500 lb c l a s s ' ~ a t t . ~ a f v: e :
. .
. . .
. . .
. .
. .
. .
. . . .
. .
Draw a fiee body diagram of the piping is considered that the. weight o f 9OU bend ..
The load at the supporting point can be gravity of the bend can be calculated using ,
= 145.8-
Reaction at the point Hl & H2
-
= -
2
Distance of the CG form the center line of
the straight pipe = 229.0 - 145.8 = &3.2mm
. '
--
0 x 234.15 =, 0 ,.3-..
, Taking moments about H4 '
I . .>
. . i +
0.0832 x . . . ' 32.00
. = 2.66 .
m x. kg. = kg.m
, .'.. -?
%
,
2 s
.J
;
*-*3
161.10 - .
0.750 x 496.1 . = 372.08 . . 8 .J
Reaction at H2 = - . . -
.s
1 :. . . . . . . . .
. .
. . .. 572.1:
. . . ., . .. . . 404.88 .. ' *I
. .
.: .. .. .. .. .. . : . . .. . ..
, . . . . . .
.
.
. .
. . .
. . :
. . .
.. . .
-- . - ' .$I
*I.
. . I . . .
1 .;
. . .. . . .
=.82.62Q.. . .
:". . . . . . . . . . . . . .
. .
. .
.
. .
. . ' ' . 404.88
. . . .
. ..
.
. . .
. :)
. . . . . . . . . . . ! -<.J
. . . . . . . . . . . . . . . .
~eactionat ~3 : =
!
Reaction at H3 = 41 1.57 - 82.62.
. .
i.T
, '
. . . .
i ,
'.,
. . 0.750 . . . . . .
-. .I
= 328.95 kg.
= 539.84kg 1
572.1 - 539-84
--
Reaction at H4 =
. 1
= 32.26 kg.
1
I.,-
Selection of Pipe Suppotts
PIPING ENGINEERING CELL
.
I
f
i
422.5
I ~ e a c t i o nat the point H4 & H5 = -
i 2
= 211.25 kg:
399.8
Reaction at H5 =-
2.5
m x kg. -
>>
)\ 0.5 x 105.6 =
Reaction at H6 = 295.75 - 159.92
I 2.
Taking moment about H6 - As the nozzle B is relieved of load
.
.,
-'-4-.
2
.2
-
e
:
m x kg .= kg.m 5697.93 1 .,
Reaction at H7 = .,--:
;' 2
-
.;
.r I
: 'i.:
! . :
I ,
. SUMMARY OF LOAOING
-4
Y A'
i.e. - -
- -
X/Z Sin$
YZ A
The spring force."F" is equal to the spring. manufacturer specific and generally as
constant "K" times to the spring deflection below.
"E" a) sdring located horizontally with the
Thus F = K E supporting structure above and the
KE ( Y Z Sin+) supported pipeline below the spring called
Spring Moment = model "H" by the manufacturers.
A b) Spring located horizontally with the
supporting structure below and the
To O ~ ~ ~ ~ ~ P E Rconstant
F E C spring,
T supported pipeline also below the spring
the load moment must always equal to called model "E" by M/s Sarathy and model
spring moment. " M by M/s Myricks.
c) Spring located horizontally with the
KEYZ Sin+ supporting structure below and the
LWSinO= supported pipeline above the spring called
A model "F"by M/s Sarathy and model "S" by
By proper design 9 and 8 are made equal W s Myricks.
KMZ d) Spring located vertically with the
Therefore LW = supported structure above .and the supported
pipeline below the spring called "V" by the
manufacturers.
The spring and the rod are so e) Spring located vertically . with
designed that the spring deflection "E" supporting structure below and the
supported pipeline above the spring called
always equals the distance "A" between
model "P"by W s Myricks.
pivots "B"and " D
ThereforeLW. = KYZ
5.1.1 HOW TO SEIBCT A CONSTANT
SPRING SUPPORT
i) F a se1& fhd k i c model best suited for
'
KYZ
piping layout and the physical structure
or L - . available for mounting. .. . .
-
W. ii) Establish the total travel by giving a
This equation holds true. for all pos.it.ive dlo.wace of about,20%.to the
pos.ition of .within its, travel ranie. ealeulatd :actual.travel in no case
4 6 ~ * *P' "y",
. and "w* rem&..constant. It b : , 2 s . in ag&r to dl&r fm a '
. .
. . . . .. .
. . .. .. ..
: But due to spring hysteresis, bearing-' i.e. Totaltravel = Actual travel + Over
friction, sliding. fiction of moving .'par&and
,
the maximum and minimum loads piping systems and where constant supports
specified. are not required. The inherent characteristic
of a variable spring is such that its
v) If the total travel lies between the two supporting force varies with spring
indicated figures, the loads between the deflection and spring scale. The vertical
successive travels can be interpolated. expansion of piping causes a corresponding
compression or extension of spring and
'.
vi)The corresponding hanger size can be causes a change in the actual supporting
. read from the respective column. effect of the hanger The variation in
supporting force is equal to the product of
5.1.2 SPECIFICATION FOR ORDER the amount of vertical expansion and the
The following data is required to be spring scale. Since the pipe weight is the
specified while inquiring / ordering for a same during any condition, cold or
constant spring. operating, the variation in supporting force
results in additional stresses in the piping
i) The exact Hot or Operating load system. Accepted practice is to limit the
required to be supported during the amount of supporting force variation to
working condition. *25%.
The Spring hangers are specified by
ii) Hydrostatic test load. the Series, the Type and the Hanger size.
the piping systems into operation. In temperature piping at some location it may.
case of top mounted support, this develop elevated stress levels. Ln these cases
lock shall be freely removed by the snubbers are used. Snubbers resemble rigid '
hand after adjusting the distance struts, except that they contain a mechanism,
between the hangers and pipe by which movkent in presence of
rotating the turnbuckle. In case of static or slowly applied loads; but which
foot mounted supports the load locks up during rapidly applied loads.
flange is rotated till it touches Snubber will resist dynamic loads while
equipment / pipe being supported. permitting the natural and slower thermal
Then the threaded bush with growth of pipe a snubber will not act as a
hexagonal sides is rotated so that it. weight support. When both weight. and
moves up and the load is gradually vertical dynamic restraint are required at a
transferred on to the support. The point of large vertical movement, both
preset pin becomes loose when the spring and snubber are required. The spring
pipe load becomes the preset or will carry weight load while the s n u W will
factory calibrated load. The support restrain dynamic loads, with both supports
is then ready for use. permitting the required thennal movements.
There are two types of snubbers available,
v) Once the preset pin is removed the hydraulic and mechanical. The hydraulic
support allows movement up or snubber is made up of a piston and a double
down by the specified amount of chamber filled with viscous fluid. The
travel in accordance with the sealing of this fluid is the main problem
expected pipe movement. associated with it. The mechanical snubbers
operate purely on mechanical basis.
vi) When the line is in operation, Mechanical snubbers are also prone to
carefblly check the support for its inadvertent locking giving rise to additional
free movement. Generally no further pipe stresses.
adjustment is necessary. In case of
any adjustment, the same shall be 5.4 Sway Braces
achieved by turning the threaded Sway braces are used to limit the
bush with hexagonal sides in case of effect of pipe vibration. These art little more
foot-mounted support or the than variable springs acting in horizontal
turnbuckle in case of top mounted plane. When sway- brace is .insjdled,-'the -.
support. spring preload is adjusted to be zero when
pips- is in the operating position. Sway
5.3 Snubbers - braces, like~variablesprings, do add some
Rigid restraints are usually necessary expansion stresses in the pipe.
when the pipe is strong to s k i v e loads such
a s earthquake or high winds or other
dynamic loads such as fluid hammer. But
when these restraints are used in high
-
. . . .. - .
. . . . ..
. . - - - - -. cb
. -
!
I
!
-4
. . TYFE 'A'
'fu',wch-
C
TYPC '0'
5
)j
)' . Fig.S.l TYPE OF SPRING SUPPORTS
I
Selection of Pipe Supports
Certificate Course
on
PIPING ENGINEERING
-
May 11 27,2005
EXPANSION JOINTS.
T. N. Gopinath
Consultant